Sunteți pe pagina 1din 7

INTERNATIONAL JOURNAL OF BUILT ENVIRONMENT AND SUSTAINABILITY

Published by Faculty of Built Environment and Surveying, Universiti Teknologi Malaysia


Website: http://www.ijbes.utm.my
IJBES 6(1)/2019, 44-50

Application of direct payment clause 30A.0 of the Asian International Arbitration Centre (AIAC)
Standard Form of Contract (With Quantities)
Nur Emma Mustaffa, Hamizah Liyana Tajul Ariffin, Norazam Othman, Shahida Shaima Shamsudin
Department of Quantity Surveying, Faculty of Built Environment and Surveying, Universiti Teknologi Malaysia, 81310 UTM Johor Bahru, Johor, Malaysia
Email: b-nuremma@utm.my

History: ABSTRACT
Received: 14 November 2018
Accepted: 1 January 2019 Conditional payment such as “pay when paid” or “pay if paid” can create negative chain effect on
Available Online: 30 January 2019 the parties in construction projects, resulting in delay on the completion of a project,
Keywords: adversarialism and may affect a contractor’s reputation. Asian International Arbitration Centre
(AIAC) has launched a standard form of contract which is Construction Industry Payment
Payment Dispute, Direct Payment, Standard form of Adjudication Act (CIPAA) compliance with the aim to reduce payment issues. The aim of the
contract, Asian International Arbitration Centre,
research is to identify whether the clause for “direct payment under CIPAA 2012” of the new
CIPAA.
AIAC standard form of contract can facilitate problems in direct payment . In achieving the aim
Corresponding Author Contact: of the research, five legal cases were analysed and thirty questionnaires forms were distributed.
b-nuremma@utm.my
Legal cases analysis findings highlighted that the major reasons of the direct payment issue being
referred to court is due to the validity of the direct payment agreement between the disputant’s
DOI: parties. Based on the cases heard before CIPAA enactment, the findings show that out of the
three cases, the disputants went to litigation because of the legality of direct payment
10.11113/ijbes.v6.n1.329
agreements. Most of the agreements were made orally. For cases analysed after CIPAA was
enacted, the findings show that the disputant parties do not opt for adjudication and that the
main contractors try to mitigate their responsibilities to the employer. The results from the
questionnaires distributed established that, the direct payment clause could be successfully
adopted for future use of the industry. Eventhough the AIAC standard form of contract has
been formally introduced to the industry, but it is not widely used. From the findings of the
questionnaire, it shows that with encouragement and support from the industry, direct
payment clause of AIAC standard form of contract have the potential in reducing payment
issues in the future. With the remodeling of standard form of contracts that are available in
construction industry to be CIPAA compliance, it is hoped that this move may scale down the
prevalent payment issues in Malaysian construction industry.

1. Introduction great initiatives in avoiding these problems. The introduction of Asian


Institute of Arbitration Centre (AIAC) standard form of contract which
1.1 Background of study is CIPAA compliance may help in reducing payment issues.
For decades, the construction industry has been plagued by various 1.2 Statement of problem
constraints encompassing issues such as cost and time overrun, poor
quality and lack of sustainability (Bruno et al, 2017). Many factors Before CIPAA was enacted, the construction industry has been using
contribute to the success and failure of a construction project and it has PAM and PWD standard form of contract. In PAM standard form of
become an interesting arena for research (Yong and Mustaffa, 2017). contract, Clause 27.6 provides that the employer may deduct the
One of the common area for research is on payment, as it has been the amount paid to the subcontractor from the amount payable to the
root of every dispute in the construction industry. Sometimes, main contractor. The same provision can also be found in PWD standard
contractor feel they have an upper hand and power over the form of contract, under Clause 61.2(a). The two clauses in PAM and
subcontractors. The reason behind this is possibly caused by the PWD standard forms of contract require parties in dispute to go
tendency of the contractors to ignore their obligations to pay the through mediation and arbitration proceedings if any dispute pertaining
subcontractors in consideration of their poor financial cash flow to them cannot be solved. There is a provision in PAM form which
condition. Subcontractors are entitled to be informed about their gives the option for it to be solved by adjudication. However, there are
payment especially in recovering them. There are many dispute no specific provisions in PAM and PWD that directly relate the matter
resolutions in solving this particular problem such as litigation, to CIPAA. Since the existing standard forms of contract were issued
arbitration and adjudication. On the same wavelength, many institutions prior to this Act, the Asian International Arbitration Centre (AIAC) or
such as PAM, PWD and CIDB standard forms of contract have taken formally known as Kuala Lumpur Regional Arbitration Centre
(KLRCA) has taken the initiative to introduce a new standard form of
44
contract. This form which has been formally launched is to address the for the employer to pay the contractor accordingly for the completed
prevalent issue of payment in a more explicit manner. These new works. According to Tony (2018), in the event of valuation of work
standard forms of contract are claimed to be more user friendly and completed, the regular basis of timely valuation commonly has been
CIPAA compliance. This could feasibly be the ultimate solution for stated in advance. The main purpose of the contract is for the
direct payment problem. Since the form is relatively new in the contractor to deliver the output (buildings) and for the employer to pay
industry, the players may be reluctant to use the new form. upon completion of work done. It is essential for the paymasters to the
subcontractors to know that every rights of their nominated and
1.3 Research objectives
domestic subcontractor should be paid accordingly for the works that
The aim of this research is to identify whether the clause for “direct they have done. Generally, all parties’ cash flow interest must be
payment under CIPAA 2012” of the new AIAC standard form of protected.
contract can eradicate the problems arising in direct payment. In order
2.3 Payment issues
to accomplish the aim, these objectives need to be pursued; firstly is to
determine the common reason(s) that leads to problems in direct Payment problems are not new in construction industry. Not only
payment from legal perspective and secondly to investigate the nationally but globally, payment is considered as one of the main issues
awareness of construction industry players of the new direct payment that have significant influences no matter what industry a person is in.
Clause 30A.0 in AIAC standard form of contract (with quantities). According to European Payment Report (2013), payment is an issue of
concern in any industry.
1.4 Significant of study
2.3.1 Factors contributing to payment issues
This research is important in order to help the clients, contractor and
subcontractor to know of their rights and obligations arising in the According to Azhari (2014), there are ten factors that contribute to
context of direct payment under the new standard form of contract payment issues. The factors are as below
AIAC. In addition, it would shed some light guiding the construction
a. Paymaster’s Poor Financial Management
players in solving and protecting their rights to attain healthy cash flow.
b. Paymaster’s withholding of payment
It is hoped that the findings of the research would encourage the
c. Conflict among the parties involve
authorities to review their standard form of contracts and include the
d. The use of pay when paid clause in subcontractor contract
new provisions that might effectively help in remedying the problems
e. Contractual Provisions
concerning direct payment.
f. Disagreement on the valuation of work done
1.5 Scope of study g. Late in certification
h. Duration of project
The main drive of this research is on discovering the perception of the
i. Local Culture or Attitude
construction industry players on the direct payment provisions with
j. Technical Problems
regards to the new standard form of contract released by the AIAC.
Court cases have been referred to in identifying the direct payment 2.3.2 Impact of payment issues
problems occurred and the solutions to it. This research have been
There are a lot of impacts that can be caused by payment issues.
limited to construction cases in Lexis Malaysia under PAM 2006, PWD
According to a report by CIDB (2006), the most common effects of
2010 and CIPAA 2012, problems on direct payment that occurs among
non-payment and late payments are the stress created on the
the construction players and perception on the new AIAC standard form
contractors, financial hardship and cash flow problems. According to
of contract towards the direct payment clause.
Mohd Khairul (2016), contractors’ cash flows are going to be affected
2. Payment in Construction Project and Related due to retention fund, payment term to supplier and subcontractor,
Issues advance payment, delay payment and frequency of payment.
Sambasivan and Soon (2007) stated that any disruption within
2.1 Definition of payment the flow of cash will cause monetary hardship and even causing failure
Payment is the amount of money that is going to be paid to the lower down the contracting chain. Title of the goods will usually be
contractor as in the regular interim payments which are progressively transferred upon payment and late or non-payment would lead to
paid throughout the duration of the contract (Jane, 2018). Certain shortage in material (Sambasivan and Soon, 2007). According to Azhari
procedures enable the parties to calculate the amount, the due date and (2014) the impacts are as below:
the final date for payment of any payments falling due under the a. Creates negative chain effect on other parties
contract. b. Results in delay on completion of project
2.1.1 Payment clauses in contract documents c. Leads to bankruptcy
d. Project Delay
In PWD 203A Version 2010, payment clause which is stated in the e. Affect the contractor’s reputation
provision of this contract falls under Clause 28, “payment to contractor f. Profitability of the project
and interim certificate”. Likewise, in PAM 2006 standard form of
contract, the clause falls under Clause 30, “certificates and payment”. In It can be highlighted that the payment issues that comprise of retention
both of these standard forms of contract, each of the clauses explain of title, delay in payment, failure of payment, late and non-payment
when the employer’s representative needs to do valuation and the have persisted in the Malaysia construction industry for quite some time
clauses lay out the procedures of payment that binds the parties to the now, but have yet to be fully resolved.
contract respectively. 2.4 Clauses in standard form of contract for remedies of
2.2 Obligation of paymasters payment issues

Payment does not require submission of claim because it is an obligation

45
In Clause 27.6 PAM 2006, the Architect may ask the contractor to 2.7 Worldwide perspectives on direct payment
supply him with reasonable proof of the contractor’s claim that he had
discharged the previous certificate to the Nominated Subcontractor’s In another part of the globe, the United Kingdom’s Housing Grants,
payment. If the Contractor fails to do so, the Architect may certify and Construction and Regeneration Act 1996 finds that the provision of
the Employer may pay such amounts directly to the Nominated conditional payment is considered unsuccessful with the exception
Subcontractor and deduct the same amount from the Contractor when there is bankruptcy in the contractual chain. According to Sushani
(2005), even though these initiatives have been taken, payment
Similarly in PWD 2010 form, the normal procedure of payment from problems may still exist. The same occurrence and reports can be seen
client to the contractor falls under Clause 28.3. Regarding the direct in the literature in UK (Reilly, 2008), Australia (Barry, 2010) and New
payment to the subcontractor, the provision falls under Clause 61.1, Zealand (The Dominion Post, 2008) that pointed to the fact of
which cover the amount that being paid by the Government directly to liquidation could have effect the delayed payment.
the Nominated Subcontractor shall be deemed as payment to the
Contractor by the Government under the virtue of the contract. 2.8 Construction Industry Payment Adjudication Act 2012
(CIPAA 2012)
2.5 Direct payment
According to Loshini (2017), Construction Industry Payment and
Emmanuel (2015) stated that problem in late and unfair payment could Adjudication Act (“CIPAA 2012”) were enacted by the Malaysian
be influenced by the main contractor and subcontractor’s relationships. Parliament and came into action on 15 April 2014. The introduction of
Based on Supardi (2015), there are three principle methods in paying a statutory adjudication process was made with a declared intention to
subcontractors comprising of: improve payment problems in the construction industry. Small
contractors and subcontractors may be facing with cash flow problems
2.5.1 Payment upon certification
and they would be financially weak if they are not paid by employers or
Under the payment system, the main contractor receives payment in some cases the payment could be unfair or untruthful. In another
through interim payment certificates and it is a conditional precedent for example, the main contractor could possibly have the upper hand and
the main contractor to pay the subcontractors. It is not appropriate for refuse to pay their subcontractors. The Act identifies this issue and
the main contractor to default the payment to the subcontractor after made provisions to address this disputes.
the honoring period of certificate has lapsed.
2.9 Adjudication
2.5.2 Direct payment from the employer
Adjudication is a form of dispute resolution that was developed back in
Other than the payment upon presentation of the certificate, direct mid 2000 as an alternative to arbitration in the construction industry.
payment is another form of payment in which the payment is being paid Most of the standard form of contract adapts adjudication as its primary
directly to the subcontractor by the employer. As far as the employer is alternative dispute resolution (Dancaster, 2008; Seifert, 2005; Teo,
concerned, the subcontractor’s payment may be apportioned from the 2008).
Interim or Final Certificate received by the main contractor.
Under CIPAA 2012, the clause for direct payment is provided under
2.5.3 Contingent payment or conditional payment Section 30A. Even though in PAM 2006 and PWD 2010 have
provisions for adjudications and direct payment, but it does not have
The last principal method of payment is the contingent payment or also
specific provisions for direct payment clause that refers to CIPAA. For
known as under various terms such as “pay if paid” or “pay when pay”
example, in PAM (Rev. 2006), Adjudication and Arbitration are put
and “back to back” provisions in paying the subcontractors. According to
under the same Clause 34. There is no mention on adjudication in any
May and Siddiqi (2006), the main contractor may transfer the risk of
of the clauses in PWD 2010, only arbitration was mentioned in the
non-payment by the employer to the subcontractor in order to protect
standard form of contract. The same can be seen in CIDB 2000 form.
their interests. There are a few cases of direct payment that have
The exclusion of adjudication could be because these two forms have
highlighted contingent payment:
been in used before CIPAA 2012 takes its operative effect. However, in
a. Asiapools (M) Sdn Bhd v IJM Construction Sdn Bhd [2010] 3 MLJ 7 KLRCA newly launched form, specific provisions in CIPAA 2012 were
b. Seloga Sdn Bhd v UEM Gynisys Sdn Bhd[2007] 7 MLJ 385 mentioned. The provisions for extension of time (clause 23A), loss and
c. Antah Schindler SdnBhd v SsangyongEngrng& Const. Co Ltd [2008] 3 MLJ expense (clause 24A) and direct payment (clause 30A) of CIPAA 2012
204 were included in this form.
2.6 Direct payment under PAM and PWD All of the procedures under CIPAA may help in solving all the payment
disputes between the construction players. Maybe this is the reason
Under PAM 2006, Clause 27.6, where in case that the Contractor does why AIAC has made their initiative to do a new standard form of
not pay the Subcontractor; the contractor must provide proof within 14
contract as one of the solutions.
days upon Architect’s request. In the event of the Contractor failed to
provide such proof, the Architect may certify for the employer (obliged 2.10 Introduction to AIAC
or not to obliged) to pay such amount directly to the Nominated
Kuala Lumpur Regional Centre for Arbitration has been established in
Subcontractor and deduct the amount directly from the Contractor.
1978. Growing strong to 40 years later in 2018, the ideas of
Similarly under PWD 2010, under Clause 61, after the issuance of
Alternative Dispute Resolutions are no longer alien. KLRCA has strived
Interim Certificate under Clause 28 or Final Certificate under Clause
through 40 years with great effort in introducing ADR and educated
31, if the contract states the amount to be paid directly to the
users with the help of Bar Council and Construction Industry
Nominated Subcontractors or Supplier, the amount shall be deducted
Development Board (CIDB). The initiatives include the amendments to
from the payment due to the Contractor. It gives security to
the Arbitration Act 2005 as well as upgrading the role of the KLRCA
Government’s interest where the contractor will not render the
(Lim, 2009). At present, the Malaysian government has undertaken
Government in any way liable to Nominated Subcontractor or Supplier
several reform measures to improve the alternative dispute resolution.
(PWD 2010, Clause 62).
46
In celebrating the 40th anniversary of KLRCA recently, Datuk Sundra
Rajoo has launched a new KLRCA new standard form in accordance
3.2.2 Quantitative research
with CIPAA compliance and also changed the name of KLRCA to Asian
International Arbitration Centre (AIAC) to attract more international A set of questionnaire was distributed to achieve the second objective of
parties to arbitrate with them. This move is with clear hope that the current research. The questionnaire responses are then used to
Malaysia would be acknowledged as the number one arbitration centre investigate the perception of inclusion of the direct payment clause
worldwide. under CIPAA 2012 of AIAC standard form of contract. Questionnaires
were sent to all participants throughout Malaysia using the online
2.11 Background of the AIAC standard form of contract
custom form and were distributed to the industry players. The target
The AIAC standard form of contract is perceived to offers a better way sampling is and not limited to thirty targeted respondents.
to address the problems and close the gaps by giving solutions that
3.3 Data analysis
complies with CIPAA. Pursuant to that, AIAC would be expected to
ensure that the standard form of contract is up to date and align the The first objective has been concluded through the legal cases analysis.
updates with the latest laws and construction court judgment in the The selected cases have been organized in chronological order,
Malaysian’s construction industry. In such cases, it would enable the according to the years, from the previous years to most recent. The
disputants’ parties to easily resolve dispute while the works are still in cases have been studied from the point of view of the facts of cases,
progress. AIAC is also anticipated to ensure that the new standard form judgments passed by the courts and the findings of the cases. The cases
of contract will give benefit to both the employer and contractor and have been further scrutinized to investigate their relevancy in the
similarly perceived to be a user friendly form. It claims that there are introduction of AIAC standard form of contract. Data that addressed
over 60 expressions and words that provide clarity to the contract such the second objective was analysed using the descriptive analysis. After
as “Clause 33.0 Fossils, Clause 8.30 Weather Conditions and Clause the data has been obtained through questionnaires, they are then coded,
23.8(c) (viii) Antiquities”. There are some key features that are claimed edited and entered into a database.
by AIAC (2017) including clarity, integrity, accountability,
transparency, continuity and certainty. 3.4 Research limitation

To summarise the discussion, the academic community has extensively There are several limitations of the research. First, the industry chosen
explored the payment issues and usage adjudication statutory in their is only the construction industry and the respondents are from the
research. However, little research has been conducted to show the related companies in the industry in Malaysia (as this research focuses
significance to include the clause of direct payment under the CIPAA on the CIPAA 2012 that came into force to govern Malaysia). Thus,
2012 in standard form of construction contract. To address this gap, this the results from this research may not be generalized to other countries
research has been designed to investigate the level of perception of the which have different political, cultural and economic factors. Second,
industrial player on the inclusion of the clause of direct payment under this research only examines the documents involved in the contract
CIPAA in the new AIAC standard form of contract and the other documentation and the focuses directly on documents and records that
standard forms. are related to payment issues or within the application of direct
payment clause in CIPAA 2012.
3. Methodology
In order to carry out this research, the theoretical and technical
3.1 Introduction assumptions underlying the research methodology in the direct
payment concept field were review. In addition, a discussion of the
This part of the discussion will primarily be based on research process, research design for this study was made. On the research strategy, legal
tools, data collection and analysis of data. It is based on two modes of case studies have been adopted. This is then further combined with
research strategies centering around legal research based on analysis of research techniques where the respondents responds were observe
the legal cases and survey conducted on the industry’s players to gather through questionnaires and documentation analysis.
information on their views regarding the new AIAC standard form.
4. Data analysis, results and discussion of findings
3.2 Data collection
4.1 Introduction
This research adopts the descriptive study approach to describe the
variables and investigative enquiries of various sorts. The descriptive This part of the paper will be discussing the emerging role of the new
statistics would furnish the frequencies, the mean and the standard AIAC standard form of contract in the context of direct payment as the
deviation of the set of data. Facts or information that are already method in solving payment issues. The legal case analysis will be
available would be analysed further to create a crucial analysis of the discussing on the common reasons for direct payment under PAM
content. In this research, legal and quantitative approaches have been 2006, PWD 2010 and CIPAA. This is in order to achieve the first
used to achieve the objectives. objective of the research. The data for the research have been obtained
from cases extracted from Lexis Malaysia database. The cases selected
3.2.1 Legal research
were from the year 2010 to 2017. The cases described and analysed
The facts were then filtered through by limiting the selection to cases have been selected based on the common reasons of direct payment
that are more recent which have been reported from the year of 2010 to occurrence. The descriptive statistical analysis will discuss on the data
2017. The cases were derived from search conducted through Lexis collected from the questionnaire distributed to 30 respondents. The
Malaysia using keywords “direct payment and building contract”. The interpretations of the said data will be thoroughly discussed
cases were then further filtered into the cases that adopts building accordingly.
contract set out under professional bodies such as Jabatan Kerja Raya
4.2 Legal case analysis
(JKR), Pertubuhan Arkitek Malaysia (PAM) and Construction Industry
Payment Adjudication Act (CIPAA). It can be observed from the legal cases presented in Table 1 that they

47
Table 1 List of Cases
No Cases Reference Number
1 Westform Far East Sdn Bhd v Connaught Heights (2010) 3 MLJ 459
Sdn Bhd & Ors
2 Rira Bina Sdn Bhd v GBC Construction Sdn Bhd (2011) 2 MLJ 378
3 Desa Samudra Sdn Bhd v Bandar Teknik Sdn Bhd (2012) 1 MLJ 729
& Ors
4 Pembinaan Juta Mekar Sdn Bhd v Sap Holdings (2014) 11 MLJ 821
Bhd & Ors
5 Sigma Elevator (M) Sdn Bhd v Isyoda (M) Sdn (2016) 10 MLJ 635
Bhd & Anor

have several similarities pertaining to direct payment issues. The findings


also reveal that there are few limitations to direct payment clause in
AIAC standard form of contract. In general, it can be highlighted that Figure 1Awareness of AIAC standard form of contract
the cases were arguing on the existence of contractual agreement of the
direct payment. From the cases, direct payment agreement was in
existence regardless if it is expressly written or orally agreed. In
Pembinaan Juta Mekar Sdn Bhd v Sap Holdings Bhd & Ors (2014) 11 MLJ
821, with consistent action of the employer in paying the subcontractor
directly for 2 years, court held that there were contractual relationship
exists. In addition, even though the agreement was made orally, with
enough evidence, subcontractor may exercise their rights to get the
payment.
There were some limitations that can be observed from the cases above.
Contractor tends to mitigate their responsibility to third party regardless
towards the employer or subcontractors. The possible explanation for
this is the contractor may not understand the full concept of direct
payment. There were possibilities that the contractors are aware of the
concept however they try to manipulate and take advantage on the Figure 2 Usage of AIAC standard form in future project.
provisions.
respondents to use the AIAC standard form of contract in the future.
4.3 Descriptive statistical analysis
Only four respondents confidently answered positively, while another
A set of questionnaires were completed by thirty respondents. The data five respondents indicated that they would not expected to be using the
have been collected to investigate the level of awareness among the form. Two third responded that they may be using the form in their
construction industrial players on the introduction of AIAC standard future projects.
form of contract. More importantly, data collected are also for the
On a positive remark, the positive response promises that the future
purpose of observing the perspective of the construction players towards
use of this form looks bright. On the other hand, majority of the
the direct payment clause under the AIAC standard form of contract
responses give different indication to the future use of the form. They
(with quantities).
are either indecisive because they have not been fully exposed to the
4.3.1 Awareness on the AIAC standard form of contract form, or that they could be skeptical on the practicality of the form.
Another reason contributing to the “uncertain” responses given by the
The question asked on whether the respondents were aware of the new respondents could also be expressed by the smaller numbers of direct
AIAC 2018 standard form of contract. Less than a third of the payment cases that are resolved with the provisions provided in the
respondents (24%) indicated that they were aware of the existence of form. Similarly, the negative response indicates that the respondents
AIAC standard form of contract. Unfortunately, despite its objective to did not have trust in the new form and there are possibilities that they
resolve the prevalent payment disputes, more than two third of the are complacent with the forms that have been established in the
respondents (23 people) indicated that they were not aware of AIAC industry. Relatively, the reasons behind these responses are further
standard form of contract. discussed in the analysis under section C of the questionnaire.
The result may indicate that the AIAC standard form of contract is yet 4.3.3 Direct Payment (Clause 30A.0) AIAC 2018 standard form of contract
fully embraced by the construction industry. The initiatives taken by can help in reducing “non-payment” or “paid when paid” issues
AIAC to organize road shows to promote the standard forms of contract
are inadequate to increase the awareness of the forms’ presence in the Following the previous question, the next question was to examine the
industry. This could possibly be due to lack of communication channel respondents’ agreement on whether the direct payment clause would
that may not reach out to much smaller players of the industry. be able to assist in eliminating or reducing the payment issues. This
Subcontractors are the critical parties that are expected to face higher response would give an indication on the potential success of the direct
disadvantages when payment disputes arise. As the data have indicated payment clause on its full implementation. The RII is calculated at an
that there are a lack of awareness in the adoption of AIAC standard form index of 0.77 for this statement. The result reveals that the
of contract, more promotional activities need to be made in order for respondents, though they agree that the direct payment clause can help
the subcontractors to be aware of the existence of the new form. in reducing the “non-payment” or “paid when paid” issues, there is a
possibility of some reservation on their part on its success. This could
4.3.2 AIAC 2018 standard form of contract in future project be due to the fact that the AIAC standard form of contract is still
The following question asked was to assess the potential of the considered new in the industry and has not been used widely.

48
4.3.4 Direct payment clause of the standard form contract will change the 5.1 Issues pertaining direct payment
construction industry payment culture in future
Based on the legal case analysis findings, the major reasons of the direct
The subsequent question is to gauge on the respondents’ level of payment issue being referred to court is the validity of the direct
agreement on the statement that direct payment may have an effect in payment agreement between the disputant’s parties and the fact that
changing the payment culture that has been inculcated in the industry. other dispute resolutions methods apart from litigation have not been
The response that inclines positively towards the statement would give chosen. Without express agreement on direct payment clause, these
an indication that the direct payment clause would have a chance in can jeapordise subcontractors’ to express their rights to be paid by the
setting a new culture of payment in the construction industry. The RII main contractors. In addition, from the findings, the even though some
reveals an index of 0.72 which is interpreted as “Agree”. This result of the cases were held after CIPAA enactment, the disputants does not
indicates that the direct payment clause has the potential to change the opt for adjudication as the payment dispute resolution method.
payment culture in the industry On the contrary, there is a small chance
Meanwhile, the research has managed to achieve the objective in
that the change in culture would lead to a bigger problem in the
investigating the perception on the inclusion of the direct payment
construction industry. One of the possibilities is the mitigation of
clause 30A.0 in AIAC standard form of contract. The research has
obligation to pay the subcontractors by the contractors. This potential
identified that the clause could be successly adopted for future use of
problem could be due to the fact the direct payment clause is rather
the industry. Even though with the lack of awareness such form existed
vague on the types of payment that are covered under the clause.
and the understanding direct payment concept, the AIAC standard form
4.3.5 For future improvement of the payment and claim system, all standard of contract were not fully utilize. Nonetheless, the findings may
form of contract should be CIPAA compliance highlight that there is a reluctant on the part of the industry players to
change from what they are comfortable with to something new.
The final question in the questionnaire was targeted to assess the
probability that all standard forms of contracts should be improved and 5.2 Possible steps in promoting direct payment clause in AIAC
be CIPAA compliance. The response would indicate if the AIAC standard form of contract
standard form of contract would be successful as a model form that
To enhance and elevate the usage of AIAC standard form of contract,
complies with CIPAA and can be benchmarked as payment solution in
AIAC could have a wider and extensive promotion on the forms. Since
direct payment issues. From the RII analysis, the index for this question
AIAC is now recognised internationally, it is only appropriate to spread
was recorded at 0.79. This shows that most of the respondents agree
the exposure internationally. AIAC may also be a bench mark for local
with the idea of remodeling standard forms of contracts that are
standard form of contract to emulate. In addition to that, it is
available in construction industry to be CIPAA compliance. It is likely
recommended that for the parties concern to have more trainings and
that the respondents could identify the importance of CIPAA in solving
conferences to educate them on this latest standard form. From the data
payment related issue especially for Subcontractors who are directly at
obtained, the respondents are from younger generations who are open
the disadvantage of payment issues. All regulatory bodies such as CIDB,
to challenges and willing to accept changes. This contributes to
PAM and PWD should take the initiative to upgrade their standard form
probable success of the AIAC standard form of contract.
of contracts and adopt CIPAA into their contracts. They should imitate
AIAC’s move immediately since their current forms are yet to adopt The more educated construction players on the AIAC standard form of
CIPAA. The extra effort in improving the standard form of contract may contract, the more successful it would be in the future. It is hoped that
give a break through to the construction industry players who are the findings can be an eye opener for the related construction industry
reluctant of changes. players on the awareness of direct payment in scaling down the
prevalent payment issue in the Malaysian construction industry.
On the legal research, out of the five cases, only two cases were heard
after CIPAA were enacted. However, both cases do not opt for References
adjudication as the mode for their payment dispute resolution method.
Ang Su Sin, Tony (2006) Payment Issue – the recent dilemma in Malaysian
Most of the cases were heard in High Court, a couple of cases went construction, Unpublished Thesis, University Teknologi Malaysia
through Court of Appeal and one of the cases went to Federal Court. It
is time consuming and costly process to go have a case being heard at the Azizan Supardi & Hamimah Adnan (2015) Security of Payment in Malaysian
court. Instead of a long-awaited process in litigation, AIAC has made Construction Industry: Eradication of Sub-contract’s Contingent Payment, Recent
ready the solution to direct payment problems by producing standard Researches in Energy, Environment, Enterpreneurship, Innovation, p 116 – 12
form of contract with CIPAA compliance. The standard form Bruno L. Tanko, Fadhlin Abdullah and Zuhaili Mohamad Ramly (2017)
synchronously compliments CIPAA’s purpose in solving and avoiding Stakeholders assessment of constraints to project delivery in the Nigerian Construction
short-term cash-flow problems during project delivery. On the Company, International Journal of Built Environment and Sustainability, Vol 4
contrary, it is also observed that the cases showed certain limitations in (1) p 56 -62
the AIAC direct payment clause. Emmanuel Manu , Nii Ankrah A, Ezekiel Chinyio and, David Proverb, (2015)
Trust influencing factors in main contractor and subcontractor relationships during
One of the set back is that the direct payment clause does not clearly
projects, University of Wolverhampton, UK
define the terms of “any payment”. The term “any payment” in clause
30A.1 in AIAC could lead to misuse and abuse of the clause. From the Janet Chai Pei Ying, (2016) Construction Industry Payment and Adjudication Act
responds of the questionnaire distributed, all thirty respondents have 2012,International Journal of Mechanical and Industrial Engineering.
given a very good cooperation in assisting this research process. Most of KLRCA (2017) The Standard Form of Building Contract
the respondents are also well qualified in terms of their education level
and experience in working. Based on the findings, the direct payment Loshini Ramarmurty (2017) CIPAA: Forward or Backward? Retrieved from
www.skrine.com
Clause 30A.0 in AIAC standard form of contract has a very bright future
and gives big impact in the construction industry payment system. Mohamad Mohamed Nor Azhari Azman, Natasha Dzulkalnine, Zuhairi Abd
Hamid, and Khuan Wai Bing (2014) Payment Issue in Malaysian Construction
5. Conclusion and recommendations
49
Industry: Contractors’ Perspective, Jurnal Teknologi (Sciences and Engineering)
70:1, p 57-63
Mohd Khairul Anas Mohd Badroldin, Abdul Rahim Abdul Hamid, Syazwani
Abdul Raman, Rozana Zakaria & Saeed Reza Mohandes (2016), Late payment
practices in the Malaysian construction industry. Department of Structures and
Materials, University Teknologi Malaysia, , Malaysia.
Murali Sambasivan & Yau Wen Soon, (2007), Causes and effects of delays in
Malaysian construction industry, International Journal of Project Management
Yong Yee Cheong and Nur Emma Mustaffa (2017) Critical Success Factors for
Malaysian Construction Projects: An Investigative Review; International Journal
of Built Environment and Sustainability, Vol 4(2) p 93 - 104

50

S-ar putea să vă placă și