Documente Academic
Documente Profesional
Documente Cultură
Abstract - This paper discusses the increasing and hundreds into one black box that only had the
interest in performing End to End testing on base required Inputs and Outputs. Segregation of
modern protection systems. There are many the protection functions for the purpose of testing
and varied approaches to this test method, from
was not the primary design requirement; the
simplistic to overly complex. What is really
economy for creating the overall protection
required and what really makes this test
method valuable? What are the technical scheme through mUltiplexing internal functions
challenges and how to resolve them? These and and leveraging programmable logic was however.
other questions are answered. Using the legacy testing method of static
secondary injections proved laborious for a multi
This paper makes a comparison of the test
function protection relay that had become the
tools/approaches that are commonly used. It
complete protection system.
discusses the payback levels of investing in
proper preperation and the information
Back in the late 1980's, some utilities began to
required for each type of test method. It
explore using a system testing method on their
presents real case studies of various techniques
used on Step Distance / POTT / Current transmission line applications that potentially
Differential and issues associated with time could reduce the overall testing workload. This
sync that can make or break the test. method was dubbed panel injection testing since it
required a 3-phase injection of voltage and current
Index Terms- Protection system, and was the prelude to End-to-End Testing (E2E).
maintenance, testing, reliability, NERC, FERC, Mastering this method required more preparation
IEC 61850 time and extra equipment over typical I-phase
injection methods, but the successful execution in
grid. So it makes sense to carry this testing method • a bad or failing relay output contact,
over to all testing requirements. • a failed 52B contact (52A contact too),
• failing wire insulation or loose connection,
� Fault Clearing sy7t e";;; -
--- - - - - -
-
-------
� • bad turns of an interposing CT,
• inadvertent change of settings,
• an event log or report fails to generate,
• proper interlocking with another device,
• correct operation of a remote device,
• or measurement inaccuracies.
DOD
system application can never be verified with a
single function test. Both positive and negative
"system" test cases are therefore required.
126
End to End Testing - What Should You Know?
engineering preparation or is too difficult to critical part is that each protection terminal can
execute successfully. Well, not really. It involves properly identify the fault location of each test
three basic things; understanding the problem case. Using a little discretion, we can allow a
domain, access to information, and using the proper margin based on the worst case phase error
proper tools. accuracy.
5
I
ubstation 8 :
proper fault detection. By definition, we should : ;
F1
__ _ _ ____ _ ___ ____ ____ _ :
F2 F3
.
. . u . . .'
construct the test cases and for this application the F3 90 Z2+PTT-Recv <SOmS 10 Zl+PTT-Send <30mS
simulation can even be quite basic. For instance, F5 ·20 Z3+No PIT Notrip 120 Z2+No PIT NoTrip
F5·No Blk
are 2, 3, or 5 cycle depending on make and system ·20 23T <630mS 120 22T <330mS
127
End to End Testing - What Should You Know?
Hint: Some relay algorithms may be sensitive to a We would probably need new test tool capabilities
phase and magnitude step change in the currents, too that can generate the required test cases for
to avoid this keep the current's phase unchanged each location based on the system parameters.
between PrefauItlFauIt states only changing the
magnitude. Instead change the voltage phase For testing a Line Differential scheme using E2E
reference for the specific fault impedance phase test methods; the test sync start accuracy now must
angle. be improved over the POTT or DA scheme. As
noted, the 10 degree phase error was fine for the
POTT and even the DA scheme, but for the Line
4 Better Testing Tools
Diff it would likely need to be much more
For our POTT example it should be explained that accurate. With a sync start of +/- O.l mS we get a
in order to get the most out of the test cases phase error of 2. 18 degrees @ 60Hz. So if we
described, we need to be able to monitor more intend on testing the load swing limits of our Line
than just the General Trip from the protection Diff we would definitely need at least this
system. In this application we should also monitor accuracy, better if possible. Verifying a sensitive
at the same time, the PTT send/receive status, the blocking zone on a short line for this scheme could
52a1b status (even if simulated), and if possible require even higher sync accuracy. With an order
each Zone 1, 2, 3, Pickup and Timed operations. of magnitude better accuracy (O.Ol mS or l OuS) we
There are others as well, CB Close, Breaker could realize a phase error of +/- 0.2 18 degrees.
Failure Initiate, Reclose Enable just name a few. Most would consider this really good, but today
we have many schemes and applications that
Obviously, this requires access to both dry require accuracies of +/- IuS. (PMU's, PDC's, SV
contacts; control voltage wetted signals, and of IEC 6 1850-9-2)
maybe LED status implying optical pickups.
Based on these requirements, we would need a The facts are a really good GPS receiver can be +/-
minimum of eight (8) status inputs to possibly 12 15 nanoseconds accurate when locked on 6+
inputs for our test set. What if you are now testing satellites and implementing some good
a distributed protection scheme with independent compensation algorithms. A common commercial
pole operation, covering six protection systems at GPS receiver is 1- 10uS accurate. From that point,
different physical locations like Fig. 4? We every node, transition, or translation will add to
definitely need GPS sync, and even more status the delay and uncertainty. Using a time code based
monitoring capability. clock distribution (i.e. IRIG-BI22) we can realize
a native +/- l OOuS accuracy. (Ius if a PLL is used
to sync to the carrier) Even so, a modem test set
can introduce 400-1200 microseconds delay on a
start trigger due to its DAC initialization, edge
detection, and its reconstruction filter. So to
achieve +/- 1 uS accuracy we need a new
technology, we need to be 4-5 times better. IEEE
1588-2008 and IEEE C37.238-20 1 1 provide this
capability. Both are currently in revision again, but
Fig. 4 - Distribution Automation Loop Test already products using these standards are
achieving the desired results.
128
End to End Testing - What Should You Know?
Hint: It is always best practice to use matched test location allows for greater test flexibility,
set hardware when executing any synchronized especially for troubleshooting. Last, the ability to
test method. Each technology employed has add S2a/b or other contact simulations or alter
them in the file is a big plus to get good results.
different limitations and benefits. It is possible to
use mixed hardware and even mixed test set When using a Network Simulation tool the output
manufacturers, but it is always advised to make a is typically a sample stream similar to the
bench test, configured exactly as they will be used, COMTRADE file. But the main difference is that
to document the start delays and phase offsets in the simulation will alter its outputs based on the
parameters used and what the relay does, like CT
order to properly compensate for them in the test
saturation, DC offset, or stops the currents and
software and test cases used.
voltages when the relay calls for trip and react
with a proper or improper breaker operation based
5 Test Simulation Requirements on the test case used. This allows the relay to react
as it is programmed. So the test results are more in
Of course it takes more than the hardware line with the real world situation. Of course this
specifications to achieve the testing acumen we requires more detailed system study information
need. This falls on the software tools we use to and power system parameters, but if the goal is to
both configure and control the test set hardware. If obtain confidence in the given protection system
we concede that the hardware is not an issue, then as installed, then it can prove invaluable.
using the best simulation tools should make the
testing process simple. (With one small caveat.)
129
End to End Testing - What Should You Know?
application. This eliminates the need for further requirements for intrusive functional testing and
functional testing unless it is E/M. covers not only the protection devices themselves,
but also most components of the FCS. Both test
Requirement #3: Use the same system test cases
equipment and the software tools that run them
regularly on new or existing relays of the same
can provide these advantages for most protection
application for both commissioning and routine
applications.
testing.
This process will more quickly verify any new
firmware update, setting changes or a substitute 8 References
manufacturer's relay to be used in that same
application. [ 1] A. Apostolov, B. Vandiver III: "Maintenance
Testing of Multifunctional Distance Protection
Requirement #4: verify the health and availability
IEDs", IEEE T&D Conference, New Orleans, LA,
of the digital protection relay/system in situ
without violating its commissioned status or April 20 10
performing excessive testing.
[2] A. Apostolov, B. Vandiver III: "The Primary
This can only be accomplished by understanding Reason for Adopting System Testing Methods",
the device's design, algorithm's, and performance. PAC World Conference, Dublin, Ireland, June
This is directly related to how it is to be used in 20 1 1.
the designed protection application
[3] A. Apostolov, B. Vandiver III: "How Will PTP
Requirement #5: when possible, use matched test
equipment and the best accuracy clocks available, Impact Protection Automation & Control
and match the equipment capabilities to the Testing?", Power Energy & Automation
protection application requirements. Know your Conference, Spokane, WA, 2014.
gear.
7 Conclusions
130
End to End Testing - What Should You Know?
Biographies
131