Sunteți pe pagina 1din 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/275463636

Design of Earthing Scheme in Off-shore Utility Plant

Article · September 2014

CITATIONS READS

0 1,525

4 authors, including:

Pankaj Kumar Pankaj Rai


Electricity & Water Authority Bahrain Poornima Group of Colleges
3 PUBLICATIONS   0 CITATIONS    18 PUBLICATIONS   50 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Physicochemical Characterization of Ayurvedic Formulation View project

Speed control of a DC motor- a matlab approach View project

All content following this page was uploaded by Pankaj Kumar on 26 April 2015.

The user has requested enhancement of the downloaded file.


International Journal of Electronics, Electrical and Mechanical Fundamentals, (Vol. 16, Issue 01), August 2014
www.ijeemf.com (An Indexed, Referred and Impact Factor Journal) ISSN: 2278-3989

Design of Earthing Scheme in Off-


Off-Shore Utility
Plant

Pankaj Kumar1, Pankaj Rai2, Niranjan Kumar3


1
Electrical Engineering Deptt.
BIT Sindri, VBU, Hazaribag, India
pankaj_kumar97@rediffmail.com
2
Associate Professor, Electrical Engineering Deptt.
BIT Sindri, VBU, Hazaribag, India,
pr_bit2001@yahoo.com India
3
Associate Professor, Electrical Engineering Deptt.
NIT Jamshedpur, Jharkhand, India
nknitjsr@gmail.com

Abstract relay are not shown for the sake of simplicity,


The power system in offshore installation consists of a although applicable to other generators.
large electrical distribution network, with multiple gas It is imperative for System design engineer to
turbine-generators directly connected to 11kV pay particular attention to applications of
switchgear. Such a configuration introduces high multiple generators connected directly to 11kV
capacitive charging current (Ico); more than the
bus-bar without generator transformer (fig-1).
preferred high resistance grounding of generator
neutral from 10A, 10sec rating resistor, to safeguard Such a configuration introduces high capacitive
the generator iron core lamination from damage charging current (Ico), more than the preferred
during an earth fault. Hence, some utility selects low high resistance grounding of generator neutral
resistance grounding to limit the fault current above through 10A, 10sec NER, to safeguard the
Ico, however it does not protect the core. This paper generator core from damage during an earth
is an attempt to share the experience learned in fault. Therefore, some utility prefers to select
designing neutral earthing scheme for off-shore utility low resistance grounding to limit the fault
in view of high capacitive charging current and current above Ico and attempt to mitigate the risk
outlines impact on stator core damage, its mitigation
of core damage by reducing earth fault protection
and conclusion.
Keywords: GCB (Generator Circuit Breaker), clearing time.
GTG (Gas Turbine Generator), HRG (High
Resistance Grounding), LRG (Low Resistance 2. Capacitive Charging Current
Grounding), NER (Neutral Earthing Resistor),
NET (Neutral Earthing Transformer) Generator transformer (GT), approximately
equal to generator rating in MVA, requires
substantial space & weight on utility plate form.
1. Introduction For a compact Utility plate form design, GT is
generally not considered, unless defined as
Synchronous Generators are installed at Utility specification requirement. This result into a
Plate form. They are driven by aero-derivative power system where multiple generators feed
gas turbine and/or industrial gas turbine & diesel directly to 11kV Switchgear, refer a typical
engines to supply un-interrupted reliable power single line diagram in Fig-1. Such a
to different plate forms to meet process configuration however, increases the capacitive
requirement. A typical single line diagram is charging current (Ico), which needs to be
shown in Fig-1. NER with Breaker-C and 67N mitigated through equipment design and

IJEEMF
www.ijeemf.com

1
International Journal of Electronics, Electrical and Mechanical Fundamentals, (Vol. 16, Issue 01), August 2014
www.ijeemf.com (An Indexed, Referred and Impact Factor Journal) ISSN: 2278-3989

protection. At 11kV voltage level, there are magnitude of generated third harmonic voltage
equipment like generators, motors, transformers [2] is
and feeders along with a large network of 11kV U3=1.44+4.22 (Ia/In) – 2.72 (If/Ifn)
cable length, spread to different plate forms, Where U3 (%) – is the measured third
introducing significant capacitive charging harmonic voltage,
current, which could be of the order of 20A to Ia (Amp)-Armature current
200A [1]. Thus, low resistance grounding is an In (Amp) – Rated armature current,
option, considered for further analysis. If – is calculated field current
Ifn – is the calculated field current at rated output
2.1 Winding Pitch of Generator power
In off-shore installation, space and weight of
The winding pitch of generator could be 2/3rd or equipment are important for plate form design,
5/6th; however both contribute to 3rd harmonic unlike the onshore plant where horizontal
voltage, displaced by 3600 (electrical placement of sub-system is not a concern.
degrees). Industry always prefers a proven designed
generator. Reducing the winding pitch to 2/3rd
reduces 3rd harmonic, however rotor pole surface
loss is increased by 6 times approx. and
generator output reduced by 15%. Therefore for
same output, generator size needs to be
increased, which requires more space & weight
at plate form, having impact on the overall plate
form design. For a typical 32MVA generator
with 5/6th winding pitch, the 3rd harmonic
content is as follows:-
Phase to neutral Voltage is 2.97% and
Phase to phase voltage is 0.06%.
Hence, for proven standard generator, the
manufacturer offers an optimum designed
generator with 5/6th winding pitch.

2.2 Generator Core Lamination Damage


Curve

Manufacturer’s damage curve of generator stator


Fig-1 – Typical Single line diagram should always be referred for the magnitude and
duration of allowable earth fault current, so that
Multiple generators may operate with unequal laminated iron core is prevented from damage
loading during parallel operation; also contribute during fault.
to increase in harmonics, when connected with
low resistance grounding at generator neutral.
The third harmonic & fundamental phase
voltages are co-phasal, however their effect is
felt in the zero sequence circuit, in the form of a
circulating current at the third harmonic
frequency. The magnitude of this current is
determined by the third harmonic driving voltage
and the third harmonic impedance of the zero
sequence circuit. The third harmonic current can
circulate only if a closed zero sequence path is
available for the generator third harmonic
voltage to drive it, refer fig-4 for example. The

IJEEMF
www.ijeemf.com

2
International Journal of Electronics, Electrical and Mechanical Fundamentals, (Vol. 16, Issue 01), August 2014
www.ijeemf.com (An Indexed, Referred and Impact Factor Journal) ISSN: 2278-3989

10sec. with temperature rise of 7600C [5]. In


view of high temperature, it is essential to place
NER in safe area, not in hazardous area.
For Industrial generator, NER can be placed in
Main terminal box of generator. However, in
case of ExnA generator, NER cannot be placed
in Main terminal box or Line side cubicle of
generator, otherwise Exn certification cannot
achieved due to temperature class limit – T4 i.e.,
2000C. Thus, it is imperative to judiciously select
both continuous & short-time rating and degree
of protection of NER.

3. Selection of Grounding Methods


The selection of grounding method should
provide safety, reliability, and continuity of
service desired for the oil & gas distribution
system. IEEE Standard [7] lists several reasons
for limiting the ground fault current by resistance
grounding:

1. To reduce burning and melting effects in


Fig-2 – Generator iron core damage curve faulted electrical equipment, such as
Core damage is considered more severe than switchgear, transformers, cables, and
winding damage [7]. Fig. 2 is a typical set of rotating machines.
damage curves for generator, showing three 2. To reduce mechanical stresses in circuits
regions where there are negligible, little, and and apparatus carrying fault currents.
serious core burning area. 3. To reduce electrical-shock hazard to
12A, 10sec – Negligible/ damage to generator personnel caused by stray ground fault
iron core currents in the ground return path.
65A-200A for time duration selected according 4. To reduce the arc blast or flash hazard to
to the curve for little / slight damage to generator personnel who may have accidentally
iron core caused or who happen to be in close
Thus, earth fault current could be limited to proximity to the ground fault.
200A, subject to earth fault protection clearance 5. To reduce the momentary line voltage dip
time is reduced to 150ms, to enable core to occasioned by the occurrence and clearing
withstand higher fault current, in little burning of a ground fault.
area. For 75A fault current, the earth fault 6. To secure control of transient over-voltages
protection clearance time could be set for while at the same time avoiding the
1000ms (1sec). shutdown of a faulty circuit on the
occurrence of the first ground fault (high
2.3 Neutral Earthing Resistor resistance grounding).
For directly connected parallel operating
Due to high capacitive charging current and generators, the system neutral grounding scheme
stringent specification requirement for 11kV should be selected carefully because of high
NER like IP54 protection, the size of NER capacitive charging current of 60A at 11kV.
becomes quite large. Higher the degree of Selection of system grounding scheme should
protection, higher is the size of NER for ensure that no circulating 3rd harmonic current
maintaining balance between heat generation and be allowed in the neutral circuits of the
dissipation. Thus NERs needs more space, hence generators when they are operated in parallel.
difficult to accommodate in compact utility plate Generally, high resistance grounding (HRG) is
form design. Usually, short time rating of NER is preferred for generators to minimize generator

IJEEMF
www.ijeemf.com

3
International Journal of Electronics, Electrical and Mechanical Fundamentals, (Vol. 16, Issue 01), August 2014
www.ijeemf.com (An Indexed, Referred and Impact Factor Journal) ISSN: 2278-3989

core damage by using NER of 10A, 10sec cannot be achieved due to temperature class
however, low resistance grounding (LRG) is also limitation (T4=2000C), while NER temperature
used in off-shore installation where Ico is high. can be up to 7600C [6]. In that scenario, 3 no
Due to 60A capacitive charging current, HRG is NER along with 2 no NET are to be placed in
not recommended. safe area. Generator neutral is earthed through
Low resistance grounding (LRG) through NER - 10A, 10sec NER with breaker for NER switch-
Higher fault current is good for sensitive & in/off (fig-3). During normal operation, only one
selective relaying, limiting transient over- NET with loading resistor has to be kept in
voltages to moderate values, and a potential cost service while Generator NERs are kept switched-
savings over other grounding methods. However, off.
the main drawback is the possibility of
significant burning of the generator stator core
(Refer Fig-2). In addition, because of IP54 and
generator core guarantee for 60A fault current,
this scheme is found not suitable as illustrated
above (Refer 2.2). There are a certain issues,
which needs a particular attention-
1. While using low resistance grounding it is
recommended to have single NET/NER in
service at a time, to reduce 3rd harmonic
circulating current flow. So, with bus-
coupler in closed condition (refer fig-1),
only one NET should be in service and Fig-3 – Earthing scheme with LRG & HRG
others in switch-off condition. When bus-
coupler is off, then both NET should be in
service. In addition, there should not be
parallel grounding of generators. Parallel
grounding means generators shown in fig-1
are having their NERs in service.
2. Even though there is no parallel grounding,
there will still be capacitive leakage currents
at 11kV voltage level due to generators and
large network of 11kV cable length to
motors, service transformers and feeders,
spread to various plate forms. This current Fig-4 Earthing scheme with NET & loading
will flow through the generator neutral resistor at 11kV
earthing resistor. Thus, for a ground fault in
the stator winding occurring together with Under bus-coupler closed condition, second NET
low resistance grounding, the stator core should be off (fig-1 & fig-4). Prior to
will be severely damaged (fig-2). synchronization or under complete load throw
In view of above, Hybrid grounding is a better scenario of a generator, the corresponding NER
option, combining best features of both low should be put into service (refer fig-3) as GCB is
resistance and high resistance grounding opened to check the over-voltage condition due
methods [2]. This requires 3 no NER (HRG) to fault.
with degree of protection defined to IP23 & 2 no Neutral earthing transformer is connected in
Neutral Earthing Transformer (LRG), which star/broken delta (fig-4). The primary winding is
means more space & weight, however is solidly earthed and secondary in broken delta
insignificant and can be accommodated at Utility having loading resistor with Over-Voltage relay
plate form. For Industrial generator, NER can be (59N) [8]. The loading resistor is designed to
installed within main terminal box of the limit the zero-sequence current in secondary to
generator. For ExnA generator [9], NER cannot limit the earth fault current to 75A. Earthing
be placed within Main terminal box or Line side transformer/loading resistor is designed to
cubicle of generator otherwise Exn certification

IJEEMF
www.ijeemf.com

4
International Journal of Electronics, Electrical and Mechanical Fundamentals, (Vol. 16, Issue 01), August 2014
www.ijeemf.com (An Indexed, Referred and Impact Factor Journal) ISSN: 2278-3989

withstanding the earth fault current for 10 sec 4. Conclusions


(min).
Capacitive leakage current should be judiciously
Fault Scenario-1 & Mitigation calculated during basic engineering design. Earth
Fault Protection clearing time should always be
During an earth fault in 11kV switchgear or any derived from generator manufacturer supplied
of the outgoing feeders (fig-1), the loading core damage curve. It is essential to carefully
resistor across the NET broken delta restricts the select both continuous & short-time rating and
fault current to 75A and allows over-voltage degree of protection of NER; otherwise has
protection 59N to detect the over-voltage to trip impact on NER size, which can lead to a layout
the faulty circuit. In addition, the loading resistor problem on plate form. Therefore, while
provides damping to over-voltage due to Ferro- selecting earthing scheme, layout of the utility
resonance condition [3] [4] [5]. plant in which generator & electrical system
including NER and NET with loading resistor
Fault Scenario-2 & Mitigation are placed, must be considered. NER and NET
with loading resistor should always be installed
During an earth fault in generator or evacuation in Safe area (Non-hazardous area). During
system, Generator Relay Panel (having normal operation, one NET at 11kV bus is in
directional Earth Fault relay operation (67N) & service with bus-coupler closed and all generator
Instantaneous ground overcurrent protection NERs are isolated. To avoid coordination
(50G), Generator Differential Protection (87G) problems, it may be imperative to remove
and Over-voltage Protection (59N) - Part of supplementary protection and NER (HRG),
numerical Generator Protection-GRP) initiates when the generator is operated in connection
tripping of GCB and Excitation & Field with 11kV switchgear (i.e., normal mode) with
Breaker, closing of GTG shut-off valve to cut- LRG in service. Such a hybrid arrangement
off gas supply to gas turbine and simultaneous offers the best features of both high resistance
closing of generator NER within 150ms through grounding and low resistance grounding into the
lock out relay (86), so as to avoid build-up of power system.
stress on insulation of generator and associated
system. Under the above fault scenario, there References
are over voltages due to following-
1. Sudden load throw [1] Handbook of Electrical Engineering: For
2. Ferro-resonance conditions during fault [3] Practitioners in the Oil, Gas and
[4] [5]. Petrochemical Industry - by Alan L.
Thus, fault is mitigated through employing Sheldrake
Hybrid earthing scheme. Grounding scheme in [2] Earth fault protection for synchronous
offshore installation should be finalized Machines, International Application Treaty
judiciously during basic engineering design or under PCT, published on 13 May 2004
Front End Engineering Design (FEED). [3] Grounding and ground fault protection of
Capacitive leakage current needs to be calculated multiple generator installations on medium
[10] based on layout and similar off-shore plant voltage industrial and commercial power
database, to be validated later during detailed systems Part 1-4, An IEEE/IAS WG Report
engineering. Earth Fault protection clearing time [4] System Grounding and Ground-Fault
should always be derived from generator core Protection in the Petrochemical Industry: A
damage curve. Degree of protection should be need for a Better Understanding, John P.
correctly defined; otherwise NER size would be Nelson, Fellow, IEEE Transaction on
large, which requires more space at Utility plate Industry on Industry Applications, Vol. 38,
form. No. 6, November / December 2002
[5] State-of-the Art Medium Voltage Generator
Grounding and Ground Fault Protection of
Multiple Generator Installations, David
Shipp, Eaton Electrical, Warrendale,
Pennsylvania

IJEEMF
www.ijeemf.com

5
International Journal of Electronics, Electrical and Mechanical Fundamentals, (Vol. 16, Issue 01), August 2014
www.ijeemf.com (An Indexed, Referred and Impact Factor Journal) ISSN: 2278-3989

[6] IEEE 32- IEEE Standard Requirements,


Terminology, and Test Procedures for
Neutral Grounding Devices
[7] IEEE 142 - IEEE Recommended Practice for
Grounding of Industrial and Commercial
Power Systems
[8] IEEE 242-IEEE Recommended Practice for
Protection and Coordination of Industrial and
Commercial Power Systems
[9] IEC60079:15:2010 - Explosive atmospheres -
Part 15: Equipment protection by type of
protection "n"
[10] Industrial Power System, By Shoaib Khan,
CRC Press, Taylor & Francis Group

IJEEMF
www.ijeemf.com

View publication stats

S-ar putea să vă placă și