G-20016/45/2016-TF-II
Government of India
Ministry of Road Transport and Highways
****
Transport Bhawan, Sansad Marg,
New Delhi
Office Memorandum
2. All Wings/Zones of MoRT&H are requested to place on file duly filled statements
while sending RCE proposal to be sent to IFD for concurrence.
(A.K. Dey)
Assistant Financial Advisor
Tel. 23710214
Encls: As above
To,
1. DG (RD) & SS, MoRTH
2. JS (EIC), MoRT&H
3. JS (T), MoRT&H
4. JS (H), MoRT&H
5. All ADGs/CEs, MoRT&H
Copy to:
1. PPS to AS&FA
2. PA to DFA
Check List to be filled up by concerned Agency/office to take up Revised Estimates
(RCE) of Public funded Schemes/projects.
1.Basic Information
Particulars
Name of Project Revised cost estimate for
construction/improvement of road Roing-
Kornu-Paya stretch of NH-52 from Km
632.45 to Km 650.615 to NHDL Specn
(incl three bridges- 30.20 mtr MCBC
Sita-I at Km 634.82, 140.40 mtr long
Injupani/Sita-II Bridge (InjupaniNallah)
at Km 649.15 and 235.80 mtr long
Chimari Bridge over Chimari River at
Km 643.85 in Arunachal Pradesh under
Arunachal Pradesh package of Ministry
of Road Transport and Highways of
SARDP-NE.
Mode of execution of project Govt Department (BRO)
(BOT/EPC/TPC/Hybrid
SOR adopted for the year
Whether latest SOR is adopted for the Yes/No
project?
Whether additional scope of works included No
in the revised cost of project?
Whether administrative approval of NA
additional scope of work has been taken from
Competent Authority?
Total additional cost to incurred due to No
additional scope of work
Whether revised cost increased due to No
extraneous reasons including militancy/other
factors?
Whether centages cost namely Contingencies, Yes
interest, escalation, supervision, quality
control, maintenance charges are as per
norms prescribed by MoRTH?
Whether statuory compliance of land Yes
acquisition. Environmental clearance and
other completed?
In case of no in respect to above column,
please provide the details of factual position
of pending compliances.
2. Costing Information:
Original Land Additional cost Increase in Cost due to Total cost Total
cost proposed due to non execution of (1+2+3) Additional
procurement of project on cost of land in
additional land time/Escalation/Higher revised
due to change compensation payable Estimates
in scope (Rs.) (4-1)
(1) (2) (3) (4) (5)
4.14 - -+ 4.14 -
2C. Additional cost
Statement indicating variation under different categories during the approved time
cycle and beyond approved time cycle
(Rs.In Crore)
IDC & FC 0 0 0 0 0 0
Change in scope 0 0 0 0 0 0
Under-estimation 0 0 0 0 0 0
Addition/deletion 0 0 0 0 0 0
Others (change in 0 0 17.85 13.84 0 13.84
SSR)
Others (Contract, 18.04 13.99 20.21 15.67 13.99 15.67
Difference in
Cost of CRMB
and
VG10,Royality
charges for stone
and sand and cost
of road side
accommodation)
Total: 41.26 32.00 64.77 50.23 32.00(%) 50.23(%)