Sunteți pe pagina 1din 14

MASTER CONSTRUCTION PROGRAMME - 11 Oct'16 IKEA JB MASTER CONSTRUCTION PROGRAMME - SUMMARY 11-Oct-16 14:31

Activity ID Activity Name Original Start Finish Total Float 2016 2017
Duration Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
437 15-Apr-16 09-Oct-17 0 09-Oct-17, MASTER CONSTRUCTI
MASTER CONSTRUCTION PROGRAMME - 11 Oct'16
437 15-Apr-16 09-Oct-17 0 09-Oct-17, Key Milestones / Key Dat
Key Milestones / Key Dates
Contract Milestones 374 01-Jul-16 09-Oct-17 0 09-Oct-17, Contract Milestones

5147847_MIL_100190 Completion of Employer's Project Office 0 01-Jul-16* 0 01-Jul-16*

5147847_MIL_100180 IKEA instruction to proceed with SC connection 0 04-Jul-16* 0 04-Jul-16*

5147847_MIL_100210 TNB Substation Power on 0 06-May-17* 0 06-May-17*

5147847_MIL_100220 Sectional completion of IKEA Retail fit out 0 01-Jul-17* 0 01-Jul-17*

5147847_MIL_100230 Completion of Remaining Areas + Car park + SC Connection 0 26-Jul-17* 0 26-Jul-17*

5147847_MIL_100240 Overall Project Completion / Obtain CCC/ Hand over 0 09-Oct-17* 0 09-Oct-17*

Project Milestones 374 01-Jul-16 09-Oct-17 0 09-Oct-17, Project Milestones

5147847_MIL_100110 Completion of Employer's Project Office 0 01-Jul-16 35 01-Jul-16

5147847_MIL_100120 IKEA instruction to proceed with SC connection 0 04-Jul-16* 31 04-Jul-16*

5147847_MIL_100140 TNB Substation Power on 0 06-May-17 0 06-May-17

5147847_MIL_100150 Sectional completion of IKEA Retail fit out 0 01-Jul-17 18 01-Jul-17

5147847_MIL_100160 Completion of Remaining Areas + Car park + SC Connection 0 26-Jul-17 9 26-Jul-17

5147847_MIL_100170 Overall Project Completion / Obtain CCC/ Hand over 0 09-Oct-17 0 09-Oct-17

Project Key Dates 38 15-Apr-16 01-Jun-16 0 01-Jun-16, Project Key Dates

5147847_MIL_100100 Aw ar d of D &B C ontract 0 15-Apr-16 0

5147847_MIL_100080 Issuance of LOI 7 15-Apr-16 22-Apr-16 0 Issuance of LOI

5147847_PRO_100090 Issuance of LOA 28 23-Apr-16 27-May-16 0 Issuance of LOA

5147847_MIL_100070 PEW Packages commencement 0 01-Jun-16 0

237 15-Apr-16 31-Mar-17 94 31-Mar-17, Design Phase


Design Phase
Design by Nakano's Technical Team 203 15-Apr-16 09-Feb-17 128 09-Feb-17, Design by Nakano's Technica l Team

Developed Design (DD) 168 15-Apr-16 20-Dec-16 153 20-Dec-16, Developed Design (DD)

Architectural 107 14-Jun-16 18-Nov-16 43 18-Nov-16, Architectural

Vertical Elements / Floor Plans - Tunnel, B1 & GF 22 14-Jun-16 15-Jul-16 7 15-Jul-16, Vertical Elements / Floor Plans - Tunnel , B1 & GF

Vertical Elements / Floor Plans - 1F & 2F 20 30-Jun-16 29-Jul-16 0 29-Jul-16, Vertical Elements / Floor Plans - 1F & 2F

Roof Plans 23 13-Jul-16 12-Aug-16 18 12-Aug-16, Roof Plans

Car Park, Staircases & MEP Utilities Rooms 29 18-Jul-16 25-Aug-16 10 25-Aug-16, Car Park, Staircases & MEP Utiliti es Rooms

Wall, Floor & Ceiling Finishes 30 27-Jul-16 07-Sep-16 9 07-Sep-16, Wal l, Floor & Ceiling Finis hes

Doors & Windows 30 27-Jul-16 07-Sep-16 43 07-Sep-16, Doors & Windows

Toilet/Babycare Room, Showroom, Self-serve Area & Check-out Area 36 01-Aug-16 22-Sep-16 0 22-Sep-16, Toilet/Babycar e Room, Showr oom, Self- serve Area & Check-out Area

Smaland, Restaurant/Kitchen, Co-workers Area 34 17-Aug-16 07-Oct-16 20 07-Oct-16, Smaland, Restaurant/Kitchen, Co-workers Area

IKEA Office & Warehouse 33 02-Sep-16 21-Oct-16 0 21-Oct-16, IKEA Office & Warehouse

Prayer Room & Signages 22 05-Oct-16 03-Nov-16 7 03-Nov-16, Prayer Room & Signages

External Wall Cladding 25 27-Jul-16 30-Aug-16 0 30-Aug-16, External Wall Cladding

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Milestone Page 1 of 14
11-Oct-16 IKEA JB MC Programme - Rev 03
Actual Work Critical Remaining Work Summary
MASTER CONSTRUCTION PROGRAMME - 11 Oct'16 IKEA JB MASTER CONSTRUCTION PROGRAMME - SUMMARY 11-Oct-16 14:31

Activity ID Activity Name Original Start Finish Total Float 2016 2017
Duration Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Railing, Balustrades, Edge Guards & Misc. 23 18-Oct-16 18-Nov-16 43 18-Nov-16, Railing, Balustrades, Edge Guards & Misc.

Civil / Structural 118 15-Apr-16 07-Oct-16 91 07-Oct-16, Civil / Structural

Piling Design 36 15-Apr-16 07-Jun-16 0 07-Jun-16, Piling Design

Pilecap / Stump Design 25 09-May-16 13-Jun-16 0 13-Jun-16, Pilecap / Stump Design

Vertical Elements / Floor Plans - Tunnel, B1 & GF 22 14-Jun-16 15-Jul-16 24 15-Jul-16, Vertical Elements / Floor Plans - Tunnel, B1 & GF

Vertical Elements / Floor Plans - 1F & 2F 20 30-Jun-16 29-Jul-16 32 29-Jul-16, Vertical Elements / Floor Plans - 1F & 2F

Roof Layout 23 13-Jul-16 12-Aug-16 57 12-Aug-16, Roof Layout

MEP Uttility Rooms 29 18-Jul-16 25-Aug-16 118 25-Aug-16, MEP Uttility Rooms

Cast-in Situ RC Works 42 27-Jun-16 25-Aug-16 17 25-Aug-16, Cast-in Situ RC Works

Pre-cast Elements (Beams/Hollow Core Slab) 29 18-Jul-16 25-Aug-16 7 25-Aug-16, Pre-cast Elements (Beams/Hollow Core Slab)

Flat Flooring 29 18-Jul-16 25-Aug-16 67 25-Aug-16, Flat Flooring

Roof Truss 27 01-Aug-16 07-Sep-16 2 07-Sep-16, Roof Truss

Roof Cladding 25 27-Jul-16 30-Aug-16 0 30-Aug-16, Roof Cladding

Canopies & Shelter 37 12-Aug-16 07-Oct-16 36 07-Oct-16, Canopies & Shelter

MEP 116 30-Jun-16 20-Dec-16 57 20-Dec-16, MEP

Floor Layout - Tunnel, B1 & GF 20 30-Jun-16 29-Jul-16 27 29-Jul-16, Floor Layout - Tunnel, B1 & GF

Floor Layout - 1F & 2F 23 13-Jul-16 12-Aug-16 34 12-Aug-16, Floor Layout - 1F & 2F

Roof Layout 20 22-Jul-16 18-Aug-16 0 18-Aug-16, Roof Layout

HVAC Works 35 19-Aug-16 12-Oct-16 21 12-Oct-16, HVAC Works

Fire Protection Works 35 19-Aug-16 12-Oct-16 0 12-Oct-16, Fire Protection Works

Plumbing / Drainage Works 35 02-Aug-16 22-Sep-16 117 22-Sep-16, Plumbing / Drainage Works

Electrical Works 37 12-Aug-16 07-Oct-16 24 07-Oct-16, Electrical Works

ICT Works 32 20-Sep-16 03-Nov-16 76 03-Nov-16, ICT Works

BMS 44 18-Oct-16 20-Dec-16 23 20-Dec-16, BMS

Solar PV system 32 05-Sep-16 21-Oct-16 26 21-Oct-16, Solar PV system

Elevator, Escalator and Travelator Details and Plans 27 13-Jul-16 18-Aug-16 37 18-Aug-16, Elevator, Escalator and Travelator Details and Plans

SC Link 31 05-Jul-16 18-Aug-16 134 18-Aug-16, SC Link

Architectural 27 05-Jul-16 12-Aug-16 41 12-Aug-16, Architectural

Civil / Structural 27 05-Jul-16 12-Aug-16 41 12-Aug-16, Civil / Structural

MEP 23 19-Jul-16 18-Aug-16 134 18-Aug-16, MEP

Infrastructure Works 113 30-Jun-16 15-Dec-16 156 15-Dec-16, Infrastructure Works

External Works within Site Boundary 95 30-Jun-16 18-Nov-16 174 18-Nov-16, External Works within Site Boundary

External Works outside Site Boundary 45 12-Oct-16 15-Dec-16 138 15-Dec-16, External Wor ks outside Sit e Boundary

Techinical Design (TD) 113 18-Jul-16 30-Dec-16 156 30-Dec-16, Techinical Design (T D)

Architectural Works 95 18-Jul-16 02-Dec-16 62 02-Dec-16, Architectural Works

Vertical elements / Floor Plans - Tunnel, B1 & GF 10 18-Jul-16 29-Jul-16 31 29-Jul-16, Vertical elements / Floor Plans - Tunnel, B1 & GF
29-Jul-16

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Milestone Page 2 of 14
11-Oct-16 IKEA JB MC Programme - Rev 03
Actual Work Critical Remaining Work Summary
MASTER CONSTRUCTION PROGRAMME - 11 Oct'16 IKEA JB MASTER CONSTRUCTION PROGRAMME - SUMMARY 11-Oct-16 14:31

Activity ID Activity Name Original Start Finish Total Float 2016 2017
Duration Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Vertical elements / Floor Plans - 1F & 2F 10 01-Aug-16 12-Aug-16 21 12-Aug-16, Vertical elements / Floor Plans - 1F & 2F
12-Aug-16

Roof Plans 10 15-Aug-16 26-Aug-16 18 26-Aug-16, Roof Plans


26-Aug-16

Car Park, Staircases & MEP Utilities Rooms 10 26-Aug-16 09-Sep-16 10 09-Sep-16, Car Park, Staircases & MEP Utiliti es Rooms
09-Sep-16

External Wall Cladding 10 01-Sep-16 15-Sep-16 0 15-Sep-16, External Wall Cladding


15-Sep-16

Wall, Floor & Ceiling Finishes 10 08-Sep-16 23-Sep-16 9 23-Sep-16, Wal l, Floor & Ceiling Finis hes
23-Sep-16

Doors / Windows 10 08-Sep-16 23-Sep-16 43 23-Sep-16, Doors / Windows


23-Sep-16

Toilet/Babycare Room, Showroom, Self-serve Area & Check-out Area 10 23-Sep-16 07-Oct-16 0 07-Oct-16, Toilet/Babyc are Room, Showroom, Self-se rve Area & Check-out Area
07-Oct-16

Smaland, Restaurant/Kitchen, Co-workers Area 10 10-Oct-16 21-Oct-16 20 21-Oct-16, Smaland, Restaurant/Kitchen, Co-workers Area
21-Oct-16

IKEA Office & Warehouse 10 24-Oct-16 04-Nov-16 19 04-Nov-16, IKEA Office & War ehous e
04-Nov-16

Prayer Room & Signages 10 04-Nov-16 18-Nov-16 7 18-Nov-16, Prayer Room & Signages
18-Nov-16

Railing, Balustrades, Edge Guards & Misc. 10 21-Nov-16 02-Dec-16 62 02-Dec-16, Railing, Balustrades, Edge Guards & Misc.
02-Dec-16

Civil / Structural 66 18-Jul-16 21-Oct-16 91 21-Oct-16, Civil / Structural

Vertical elements / Floor Plans - Tunnel, B1 & GF 10 18-Jul-16 29-Jul-16 24 29-Jul-16, Vertical elements / Floor Plans - Tunnel, B1 & GF
29-Jul-16

Vertical elements / Floor Plans - 1F & 2F 10 01-Aug-16 12-Aug-16 32 12-Aug-16, Vertical elements / Floor Plans - 1F & 2F
12-Aug-16

Roof Layout 10 15-Aug-16 26-Aug-16 57 26-Aug-16, Roof Layout


26-Aug-16

MEP Utility Rooms 10 26-Aug-16 09-Sep-16 118 09-Sep-16, MEP Utility Rooms
09-Sep-16

Cast-in Situ RC Works 10 26-Aug-16 09-Sep-16 17 09-Sep-16, Cast-in Situ RC Works


09-Sep-16

Pre-cast Elements (Beams & Hollow Core Slabs) 10 26-Aug-16 09-Sep-16 7 09-Sep-16, Pre-cast Elements (Beams & Hollow Core Slabs)
09-Sep-16

Flat Flooring 10 26-Aug-16 09-Sep-16 67 09-Sep-16, Flat Flooring


09-Sep-16

Roof Truss 10 08-Sep-16 23-Sep-16 2 23-Sep-16, Roof Truss


23-Sep-16

Roof Cladding / Membarane 10 01-Sep-16 15-Sep-16 0 15-Sep-16, Roof Cladding / Membarane


15-Sep-16

Canopies & Shelter 10 10-Oct-16 21-Oct-16 36 21-Oct-16, Canopies & Shelter


21-Oct-16

MEP 103 01-Aug-16 30-Dec-16 60 30-Dec-16, MEP

Floor Layout - Tunnel, B1 & GF 10 01-Aug-16 12-Aug-16 27 12-Aug-16, Floor Layout - Tunnel, B1 & GF
12-Aug-16

Floor Layout - 1F & 2F 10 15-Aug-16 26-Aug-16 34 26-Aug-16, Floor Layout - 1F & 2F


26-Aug-16

Roof Layout 10 19-Aug-16 02-Sep-16 53 02-Sep-16, Roof Layout


02-Sep-16

HVAC Works 10 13-Oct-16 26-Oct-16 21 26-Oct-16, HVAC Works


26-Oct-16

Fire Protection System 10 13-Oct-16 26-Oct-16 0 26-Oct-16, Fire Protection System


26-Oct-16

Plumbing / Drainage Works 24 01-Sep-16 07-Oct-16 117 15-Sep-16


07-Oct-16, Plumbing / Drainage Works
07-Oct-16

Electrical Works 10 10-Oct-16 21-Oct-16 24 21-Oct-16, Electrical Works


21-Oct-16

ICT Works 10 04-Nov-16 18-Nov-16 76 18-Nov-16, ICT Works


18-Nov-16

BMS 7 21-Dec-16 30-Dec-16 23 30-Dec-16, BMS


30-Dec-16

Solar PV system 10 24-Oct-16 04-Nov-16 26 04-Nov-16, Solar PV system


04-Nov-16

Elevator, Escalator & Travelator Details and Plans 10 19-Aug-16 02-Sep-16 37 02-Sep-16, Elevator, Escalator & Travelator Details and Plans
02-Sep-16

Shopping Mall Connection 14 15-Aug-16 02-Sep-16 134 02-Sep-16, Shopping Mall Connection

Architectural 10 15-Aug-16 26-Aug-16 41 26-Aug-16, Architectural


26-Aug-16

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Milestone Page 3 of 14
11-Oct-16 IKEA JB MC Programme - Rev 03
Actual Work Critical Remaining Work Summary
MASTER CONSTRUCTION PROGRAMME - 11 Oct'16 IKEA JB MASTER CONSTRUCTION PROGRAMME - SUMMARY 11-Oct-16 14:31

Activity ID Activity Name Original Start Finish Total Float 2016 2017
Duration Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Civil / Structural 10 15-Aug-16 26-Aug-16 41 26-Aug-16, Civil / Structural
26-Aug-16

MEP 10 19-Aug-16 02-Sep-16 134 02-Sep-16, MEP


02-Sep-16

Infrastructure Works 107 26-Jul-16 30-Dec-16 156 30-Dec-16, Infrastructure Works

External Works within Site Boundary 89 26-Jul-16 02-Dec-16 174 08-Aug-16


10-Aug-16
12-Aug-16
15-Aug-16
22-Aug-16
29-Aug-16
06-Sep-16
26-Sep-16
29-Sep-16
07-Oct-16
12-Oct-16
21-Oct-16
25-Oct-16
04-Nov-16
18-Nov-16
02-Dec-16, External Wor ks within Site Boundary
02-Dec-16

External Works outside Site Boundary 28 21-Nov-16 30-Dec-16 138 02-Dec-16


16-Dec-16
30-Dec-16, External Wor ks outside Site Boundary
30-Dec-16

Shop Drawings Submissions / Approvals 118 18-Aug-16 09-Feb-17 103 09-Feb-17, Shop Drawings Submissions / Approvals

Architectural 118 18-Aug-16 09-Feb-17 60 09-Feb-17, Architectural

Building Plan / Elevation / Section 28 18-Aug-16 29-Sep-16 18 29-Sep-16, Building Plan / Elevation / Section

External Wall Cladding (Facade) 28 19-Sep-16 27-Oct-16 0 27-Oct-16, External Wall Cladding (Facade)

Window Schedule / Details 28 08-Nov-16 16-Dec-16 43 16-Dec-16, Window Schedule / Details

Skirting 28 26-Oct-16 05-Dec-16 37 05-Dec-16, Skirting

Door Schedule / Details 28 08-Nov-16 16-Dec-16 71 16-Dec-16, Door Schedule / Details

Glass Lift 28 18-Oct-16 25-Nov-16 48 25-Nov-16, Glass Lift

Handrail 28 02-Jan-17 09-Feb-17 44 09-Feb-17, Handrail

Partition Wall / finishes 28 05-Dec-16 13-Jan-17 0 13-Jan-17, Partition Wall / fi nishes

Car Park Line Marking 28 13-Sep-16 24-Oct-16 134 24-Oct-16, Car Park Line Marking

Ceiling 28 08-Nov-16 16-Dec-16 56 16-Dec-16, Ceiling

Bollard 28 05-Dec-16 13-Jan-17 78 13-Jan-17, Bollard

Office Interior 28 08-Nov-16 16-Dec-16 63 16-Dec-16, Office Interior

Toilet Layout & Details 28 08-Nov-16 16-Dec-16 0 16-Dec-16, Toilet Layout & Details

Window Sill Counter 28 19-Dec-16 26-Jan-17 43 26-Jan-17, Window Sill Counter

Wall Protection 28 05-Dec-16 13-Jan-17 21 13-Jan-17, Wall Prot ection

Kitchen 28 24-Oct-16 01-Dec-16 20 01-Dec-16, Kitchen

Evacuation Signage 28 21-Dec-16 31-Jan-17 67 31-Jan-17, Evacuation Signage

Floor Finishes 28 26-Oct-16 05-Dec-16 27 05-Dec-16, Floor Finishes

Iron mongery 28 17-Nov-16 28-Dec-16 64 28-Dec-16, Iron mongery

Civil / Structural 84 13-Sep-16 13-Jan-17 88 13-Jan-17, Civil / Structural

Block work 28 08-Nov-16 16-Dec-16 10 16-Dec-16, Block work

Waterproofing 28 21-Nov-16 30-Dec-16 7 30-Dec-16, Waterproofing

RC Staircase 28 13-Sep-16 24-Oct-16 10 24-Oct-16, RC Staircase

Steel Staircase 28 13-Sep-16 24-Oct-16 49 24-Oct-16, Steel Staircase

Roof Truss / Cladding 28 19-Sep-16 27-Oct-16 0 27-Oct-16, Roof Truss / Cladding

Roof Parapet Wall 28 28-Sep-16 08-Nov-16 62 08-Nov-16, Roof Parapet Wall

Wall Opening 28 05-Dec-16 13-Jan-17 22 13-Jan-17, Wall O pening

Roller Shutter Schedule / Details 28 21-Nov-16 30-Dec-16 62 30-Dec-16, Roller Shutter Schedule / Details

Server Room 28 13-Sep-16 24-Oct-16 118 24-Oct-16, Server Room

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Milestone Page 4 of 14
11-Oct-16 IKEA JB MC Programme - Rev 03
Actual Work Critical Remaining Work Summary
MASTER CONSTRUCTION PROGRAMME - 11 Oct'16 IKEA JB MASTER CONSTRUCTION PROGRAMME - SUMMARY 11-Oct-16 14:31

Activity ID Activity Name Original Start Finish Total Float 2016 2017
Duration Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Skylight 28 26-Sep-16 03-Nov-16 28 03-Nov-16, Skylight

Canopy 28 24-Oct-16 01-Dec-16 36 01-Dec-16, Canopy

Ticket Booth 28 28-Sep-16 08-Nov-16 134 08-Nov-16, Ticket Booth

MEP 63 05-Sep-16 06-Dec-16 76 06-Dec-16, MEP

Elevator, Escalator & Travelator 28 05-Sep-16 17-Oct-16 48 17-Oct-16, Elevator, Escalator & Tr avelator

Ventilation Grating 28 27-Oct-16 06-Dec-16 59 06-Dec-16, Ventilation Grating

Siphonage System 28 10-Oct-16 17-Nov-16 89 17-Nov-16, Siphonage System

External Works 38 21-Nov-16 13-Jan-17 121 13-Jan-17, External Works

Sign Tower 28 21-Nov-16 30-Dec-16 19 30-Dec-16, Sign Tow er

Fencing 28 05-Dec-16 13-Jan-17 121 13-Jan-17, Fencing

RETAIL FIT-OUT DESIGN BY IKEA 129 23-Sep-16 31-Mar-17 61 31-Mar-17, RETAIL FIT-OUT DESIGN BY IKEA

322 23-Apr-16 27-May-17 45 27-May-17, Procurement Phase


Procurement Phase
Sub Contract Work Packages 203 23-Apr-16 31-Dec-16 164 31-Dec-16, Sub Contract Work Packages

Architectural 152 27-Jun-16 31-Dec-16 86 31-Dec-16, Architectural

External Cladding 39 27-Jun-16 12-Aug-16 28 12-Aug-16, External Cladding


12-Aug-16

Wet Area Finishes 19 17-Sep-16 10-Oct-16 93 10-Oct-16, Wet Area Finishes


10-Oct-16

Wall Finishes 24 08-Sep-16 08-Oct-16 46 08-Oct-16, Wall F inishes


08-Oct-16

Floor Finishes 26 24-Sep-16 25-Oct-16 32 25-Oct-16, Floor Finishes


25-Oct-16

False Ceiling 35 23-Sep-16 04-Nov-16 68 04-Nov-16, False Ceiling


04-Nov-16

Partition Walls 35 22-Oct-16 03-Dec-16 0 03-Dec-16, Partition Walls


03-Dec-16

Toilet Partition 35 23-Sep-16 04-Nov-16 1 04-Nov-16, Toilet Partition


04-Nov-16

Doors / Windows / Iron Mongery 35 24-Sep-16 05-Nov-16 52 05-Nov-16, Doors / Windows / Iron Mongery
05-Nov-16

Aluminium / Glazing Works 37 24-Sep-16 09-Nov-16 129 09-Nov-16, Aluminium / Glazing Works
09-Nov-16

Railling, Balustrades, Edge Guards & Misc. 35 19-Nov-16 31-Dec-16 52 31-Dec-16, Railling, Balustrades, Edge Guards & Misc.
31-Dec-16

Signages 26 19-Nov-16 20-Dec-16 80 20-Dec-16, Signages


20-Dec-16

Civil / Structural 168 23-Apr-16 18-Nov-16 199 18-Nov-16, Civil / Structural

Piling Works 28 29-Apr-16 02-Jun-16 8 02-Jun-16, Piling Works


02-Jun-16

Cast in situ RC Works 74 14-Jun-16 10-Sep-16 227 04-Aug-16


13-Aug-16
10-Sep-16, Cast in situ RC Works
10-Sep-16

Pre-cast Elements (Columns / Beams / Slabs / Retaining Walls) 27 23-Apr-16 26-May-16 90 26-May-16, Pre-cast Elements (Columns / Beams / Slabs / Retaining Walls)
26-May-16

Waterproofing Works 58 27-Jun-16 05-Sep-16 68 12-Aug-16


05-Sep-16, Waterpr oofing Works
05-Sep-16

Flat Flooring 39 27-Jun-16 12-Aug-16 104 12-Aug-16, Flat Flooring


12-Aug-16

Roof Truss 25 04-May-16 02-Jun-16 85 02-Jun-16, Roof Truss


02-Jun-16

Roof Cladding 39 27-Jun-16 12-Aug-16 28 12-Aug-16, Roof Cladding


12-Aug-16

Block works 35 24-Sep-16 05-Nov-16 12 05-Nov-16, Block works


05-Nov-16

Rolling Shutters 39 01-Oct-16 18-Nov-16 75 18-Nov-16, Rolling Shutters


18-Nov-16

Navigation Tower Steel Works 39 09-May-16 25-Jun-16 316 25-Jun-16, Navigation Tower Steel Works
25-Jun-16

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Milestone Page 5 of 14
11-Oct-16 IKEA JB MC Programme - Rev 03
Actual Work Critical Remaining Work Summary
MASTER CONSTRUCTION PROGRAMME - 11 Oct'16 IKEA JB MASTER CONSTRUCTION PROGRAMME - SUMMARY 11-Oct-16 14:31

Activity ID Activity Name Original Start Finish Total Float 2016 2017
Duration Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
MEP 130 07-May-16 15-Oct-16 118 15-Oct-16, MEP

HVAC Works 28 07-May-16 11-Jun-16 136 11-Jun-16, HVAC Works


11-Jun-16

Fire Protection System 35 13-May-16 25-Jun-16 99 25-Jun-16, Fire Protection System


25-Jun-16

Plumbing / Drainage Works 23 25-Jun-16 23-Jul-16 137 23-Jul-16, Plumbing / Drainage Works
23-Jul-16

Electrical Works 34 13-Jul-16 20-Aug-16 78 20-Aug-16, Electrical Wor ks


20-Aug-16

ICT Works 28 13-Aug-16 17-Sep-16 141 17-Sep-16, ICT Works


17-Sep-16

BMS 46 19-Aug-16 15-Oct-16 88 15-Oct-16, BMS


15-Oct-16

Solar PV system 30 30-Jul-16 03-Sep-16 112 03-Sep-16, Solar PV system


03-Sep-16

Elevator, Escalator & Travelator 39 13-Jul-16 26-Aug-16 50 26-Aug-16, Elevator, Escalator & Travelator
26-Aug-16

External Works 82 25-Aug-16 05-Dec-16 129 05-Dec-16, External Wor ks

Road / Drainage Works 30 25-Aug-16 01-Oct-16 120 01-Oct-16, Road / Drainage Works
01-Oct-16

Hardscaping / SoftScaping 26 04-Nov-16 05-Dec-16 129 05-Dec-16, Hardscaping / SoftScaping


05-Dec-16

Procurement / Delivery of Long Lead Items 313 16-Jul-16 25-May-17 0 25-May-17, Procurement / Delivery of Long Lead Items

Architectural 100 28-Oct-16 05-Feb-17 0 05-Feb-17, Architectural

Civil / Structural 204 16-Jul-16 05-Feb-17 12 05-Feb-17, Civil / Structural

MEP 264 03-Sep-16 25-May-17 0 25-May-17, MEP

Client supply Items 259 10-Sep-16 27-May-17 26 27-May-17, Client supply Items

101 15-Sep-16 17-Jan-17 141 17-Jan-17, Material Submittals / Approvals


Material Submittals / Approvals
Architectural 87 21-Sep-16 05-Jan-17 70 05-Jan-17, Architectural

External Wall Cladding 26 21-Sep-16 21-Oct-16 31 21-Oct-16, External Wall Cladding

Windows 26 08-Nov-16 07-Dec-16 93 07-Dec-16, Windows

Doors 26 08-Nov-16 07-Dec-16 93 07-Dec-16, Doors

Glass Lift 26 21-Oct-16 22-Nov-16 61 22-Nov-16, Glass Lift

Dry Wall Partitions 26 05-Dec-16 05-Jan-17 7 05-Jan-17, Dry Wall Partitions

Ceiling Finishes 26 05-Nov-16 06-Dec-16 75 06-Dec-16, Ceiling Finishes

Office Interior 26 10-Nov-16 09-Dec-16 81 09-Dec-16, Office Interior

Toilet 26 05-Nov-16 06-Dec-16 40 06-Dec-16, Toilet

Kitchen 26 27-Oct-16 28-Nov-16 28 28-Nov-16, Kitchen

Floor Finishes 26 27-Oct-16 28-Nov-16 38 28-Nov-16, Floor Finishes

Skirting 26 01-Nov-16 01-Dec-16 47 01-Dec-16, Skirting

Iron mongery 26 19-Nov-16 20-Dec-16 83 20-Dec-16, Iron mongery

Civil / Structural 81 15-Sep-16 23-Dec-16 123 23-Dec-16, Civil / Structural

Block work 20 17-Nov-16 09-Dec-16 18 09-Dec-16, Block work

RC Staircase 20 23-Sep-16 17-Oct-16 17 17-Oct-16, RC Staircase

Steel Staircase 26 15-Sep-16 17-Oct-16 64 17-Oct-16, Steel Staircase

Waterproofing 26 23-Nov-16 23-Dec-16 14 23-Dec-16, Waterproof ing

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Milestone Page 6 of 14
11-Oct-16 IKEA JB MC Programme - Rev 03
Actual Work Critical Remaining Work Summary
MASTER CONSTRUCTION PROGRAMME - 11 Oct'16 IKEA JB MASTER CONSTRUCTION PROGRAMME - SUMMARY 11-Oct-16 14:31

Activity ID Activity Name Original Start Finish Total Float 2016 2017
Duration Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Ticket Booth 26 30-Sep-16 01-Nov-16 166 01-Nov-16, Ticket Booth

MEP 26 17-Dec-16 17-Jan-17 0 17-Jan-17, MEP

Sanitary Fittings 26 17-Dec-16 17-Jan-17 0 17-Jan-17, Sanitary Fittings

External Works 38 23-Nov-16 07-Jan-17 149 07-Jan-17, External Works

Sign Tower 26 23-Nov-16 23-Dec-16 131 23-Dec-16, Sign Tow er

Fencing 26 07-Dec-16 07-Jan-17 149 07-Jan-17, Fencing

99 25-Oct-16 24-Feb-17 73 24-Feb-17, Mock-Ups / Approvals


Mock-Ups / Approvals
Architectural Works 99 25-Oct-16 24-Feb-17 73 24-Feb-17, Architectural Works

External Wall Cladding 12 28-Oct-16 12-Nov-16 26 12-Nov-16, External Wall Cladding

Windows 12 17-Dec-16 31-Dec-16 86 31-Dec-16, Windows

Doors 12 17-Dec-16 31-Dec-16 86 31-Dec-16, Doors

Handrail 12 11-Feb-17 24-Feb-17 54 24-Feb-17, Handrail

Dry Wall Partitions 12 14-Jan-17 27-Jan-17 0 27-Jan-17, Dry Wall Partitions

Car Park Line Marking 12 25-Oct-16 09-Nov-16 160 09-Nov-16, Car Park Line Marking

Bollard 12 14-Jan-17 27-Jan-17 94 27-Jan-17, Bollard

Window Sill Counter 12 27-Jan-17 13-Feb-17 52 13-Feb-17, Window Sill Counter

Toilet 12 17-Dec-16 31-Dec-16 32 31-Dec-16, Toilet

Wall Protection 12 14-Jan-17 27-Jan-17 25 27-Jan-17, Wall Prot ection

Evacuation Signage 12 01-Feb-17 15-Feb-17 81 15-Feb-17, Evacuation Signage

Floor Finishes 12 06-Dec-16 20-Dec-16 32 20-Dec-16, Floor Finishes

Iron Mongery 12 29-Dec-16 11-Jan-17 77 11-Jan-17, Iron Mongery

Civil / Structural 78 25-Oct-16 27-Jan-17 63 27-Jan-17, Civil / Structural

Waterproofing 12 31-Dec-16 13-Jan-17 9 13-Jan-17, Water proofing

Skylight 12 04-Nov-16 18-Nov-16 34 18-Nov-16, Skylight

Roller Shutter 12 31-Dec-16 13-Jan-17 75 13-Jan-17, Roller Shutter

RC Staircase 12 25-Oct-16 09-Nov-16 11 09-Nov-16, RC Staircase

Steel Staircase 12 25-Oct-16 09-Nov-16 58 09-Nov-16, Steel Staircase

Roof Truss / Roof Cladding 12 28-Oct-16 12-Nov-16 8 12-Nov-16, Roof Truss / Roof Cladding

Roof Parapet Wall 12 09-Nov-16 22-Nov-16 74 22-Nov-16, Roof Parapet Wall

Wall Opening 12 14-Jan-17 27-Jan-17 26 27-Jan-17, Wall O pening

MEP 12 07-Dec-16 21-Dec-16 70 21-Dec-16, MEP

Ventilation Gratings 12 07-Dec-16 21-Dec-16 70 21-Dec-16, Ventilation Gratings

424 29-Apr-16 09-Oct-17 0 09-Oct-17, Authority Submissions / A


Authority Submissions / Approvals
Development Order (DO) 0 29-Apr-16 29-Apr-16 0 29-Apr-16, Development Order (DO)
29-Apr-16

Building Plan - Project Office 16 29-Apr-16 19-May-16 1 29-Apr-16


19-May-16, Building Plan - Project Office

Building Plan 75 03-May-16 18-Aug-16 22 18-Aug-16, Building Plan

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Milestone Page 7 of 14
11-Oct-16 IKEA JB MC Programme - Rev 03
Actual Work Critical Remaining Work Summary
MASTER CONSTRUCTION PROGRAMME - 11 Oct'16 IKEA JB MASTER CONSTRUCTION PROGRAMME - SUMMARY 11-Oct-16 14:31

Activity ID Activity Name Original Start Finish Total Float 2016 2017
Duration Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
ADO 75 03-May-16 18-Aug-16 22 18-Aug-16, ADO

ADO1 42 13-Dec-16 13-Feb-17 33 13-Dec-16* 13-Feb-17, ADO1

ABP 61 13-Feb-17 12-May-17 33 13-Feb-17 12-May-17, ABP

RSA Stage 1 & 2 62 29-Jun-16 30-Sep-16 70 29-Jun-16 30-Sep-16, RSA Stage 1 & 2

RSA Stage 3 - Detailed Engineering 65 26-Jul-16 31-Oct-16 64 26-Jul-16 31-Oct-16, RSA Stage 3 - Detailed Engineering

R&D 43 28-Jul-16 30-Sep-16 118 28-Jul-16 30-Sep-16, R & D

Lifts 65 20-Apr-17 26-Jul-17 0 20-Apr-17 26-Jul-17, Lifts

CCC 23 05-Sep-17 09-Oct-17 0 05-Sep-17


09-Oct-17, CCC

72 15-Apr-16 14-Jul-16 0 14-Jul-16, Site Preliminaries


Site Preliminaries
General 72 15-Apr-16 14-Jul-16 0 14-Jul-16, General

372 01-Jun-16 05-Sep-17 27 05-Sep-17, Construction Phase


Construction Phase
Site Early Works 187 01-Jun-16 18-Jan-17 0 18-Jan-17, Site Early Works

PEW Works 187 01-Jun-16 18-Jan-17 0 18-Jan-17, PEW Works

Earthworks (Cut & Fill) 187 01-Jun-16 18-Jan-17 0 18-Jan-17, Earthworks (Cut & Fill)

Piling 99 09-Jun-16 08-Oct-16 23 08-Oct-16, Piling

Sub-structure Works 121 15-Aug-16 11-Jan-17 12 11-Jan-17, Sub-structure Works

Evacuation Tunnel - Elevation 32.10 69 03-Sep-16 28-Nov-16 0 28-Nov-16, Evacuation Tunnel - Elevation 32.10

EE Tunnel 1 66 03-Sep-16 24-Nov-16 0 24-Nov-16, EE Tunnel 1

Tunnel (Gridline Q-I) 46 03-Sep-16 31-Oct-16 20 31-Oct-16, Tunnel (Gridline Q-I)

Tunnel (Gridline I-D) 47 17-Sep-16 14-Nov-16 9 14-Nov-16, Tunnel (Gridline I-D)

Tunnel (Gridline 12-17) 34 14-Oct-16 24-Nov-16 0 24-Nov-16, Tunnel (Gridline 12-17)

EE Tunnel 2 45 05-Oct-16 28-Nov-16 0 28-Nov-16, EE Tunnel 2

Tunnel (Gridline P-M) 36 05-Oct-16 17-Nov-16 9 17-Nov-16, Tunnel (Gridline P-M)

Tunnel (Gridline M-G) 39 12-Oct-16 28-Nov-16 0 28-Nov-16, Tunnel (Gridline M-G)

Basement B1(P2) - Elevation 36.50 93 15-Aug-16 07-Dec-16 40 07-Dec-16, Basement B1(P2) - Elevation 36.50

Zone A (Gridline 26-23/O-A) 31 15-Aug-16 22-Sep-16 0 22-Sep-16, Zone A (Gr idline 26-23/O-A)

Pile Caps 21 15-Aug-16 08-Sep-16 0 08-Sep-16, Pile Caps

Cut / Fill / Compaction around Pile Caps 16 02-Sep-16 22-Sep-16 0 22-Sep-16, Cut / Fill / Compaction around Pile Caps

Stump 11 08-Sep-16 22-Sep-16 0 22-Sep-16, Stump

Zone B (Gridline 23-19/Q-A) 19 09-Sep-16 04-Oct-16 19 04-Oct-16, Zone B (Gridline 23-19/Q-A)

Pile Caps 13 09-Sep-16 26-Sep-16 18 26-Sep-16, Pile Caps

Cut / Fill / Compaction around Pile Caps 10 22-Sep-16 04-Oct-16 18 04-Oct-16, Cut / Fill / Compaction around Pile Caps

Stump 8 22-Sep-16 30-Sep-16 21 30-Sep-16, Stump

Zone C (Gridline 19-17/Q-A) 15 27-Sep-16 14-Oct-16 33 14-Oct-16, Zone C (Gridline 19-17/Q-A)

Pile Caps 11 27-Sep-16 10-Oct-16 33 10-Oct-16, Pile Caps

Cut / Fill / Compaction around Pile Caps 10 04-Oct-16 14-Oct-16 33 14-Oct-16, Cut / Fill / Compaction around Pile Caps

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Milestone Page 8 of 14
11-Oct-16 IKEA JB MC Programme - Rev 03
Actual Work Critical Remaining Work Summary
MASTER CONSTRUCTION PROGRAMME - 11 Oct'16 IKEA JB MASTER CONSTRUCTION PROGRAMME - SUMMARY 11-Oct-16 14:32

Activity ID Activity Name Original Start Finish Total Float 2016 2017
Duration Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Stump 8 06-Oct-16 14-Oct-16 33 14-Oct-16, Stump

Zone D (Gridline 17-11/Q-A) 31 21-Sep-16 27-Oct-16 7 27-Oct-16, Zone D (Gridline 17-11/Q-A)

Pile Caps 21 21-Sep-16 15-Oct-16 0 15-Oct-16, Pile Caps

Cut / Fill / Compaction around Pile Caps 15 11-Oct-16 27-Oct-16 7 27-Oct-16, Cut / Fill / Compaction around Pile Caps

Stump 14 10-Oct-16 25-Oct-16 9 25-Oct-16, Stump

Zone E (Gridline 11-5/Q-A) 23 17-Oct-16 14-Nov-16 12 14-Nov-16, Zone E (Gridline 11-5/Q-A)

Pile Caps 17 17-Oct-16 05-Nov-16 0 05-Nov-16, Pile Caps

Cut / Fill / Compaction around Pile Caps 10 02-Nov-16 14-Nov-16 12 14-Nov-16, Cut / Fill / Compaction around Pile Caps

Stump 10 31-Oct-16 11-Nov-16 14 11-Nov-16, Stump

Zone F (Gridline 5-1/Q-A) 21 08-Nov-16 01-Dec-16 0 01-Dec-16, Zone F (Gridline 5-1/Q-A)

Pile Caps 15 08-Nov-16 24-Nov-16 0 24-Nov-16, Pile Caps

Cut / Fill / Compaction around Pile Caps 10 19-Nov-16 30-Nov-16 1 30-Nov-16, Cut / Fill / Compaction around Pile Caps

Stump 10 21-Nov-16 01-Dec-16 0 01-Dec-16, Stump

Excavation / UG Services 33 28-Oct-16 07-Dec-16 40 07-Dec-16, Excavation / UG Services

Ground Floor (P1)- Elevation 41.00 90 23-Sep-16 11-Jan-17 0 11-Jan-17, Ground Floor (P1)- Elevation 41.00

Retaining Walls 77 10-Oct-16 11-Jan-17 0 11-Jan-17, Retaining Walls

TNB Sub-Station - SW Side 24 10-Oct-16 08-Nov-16 0 08-Nov-16, T NB Sub-Stati on - SW Side

South Side 42 25-Oct-16 15-Dec-16 10 15-Dec-16, South Side

West side - Gridline 5-17 37 25-Oct-16 08-Dec-16 21 08-Dec-16, West side - G ridline 5-17

West Side - Gridline 17-26 37 18-Nov-16 02-Jan-17 2 02-Jan-17, West Side - Gridline 17-26

North Side - Gridline O-A 42 22-Nov-16 11-Jan-17 0 11-Jan-17, North Side - Gridline O-A

Pre-cast Installation 72 23-Sep-16 20-Dec-16 0 20-Dec-16, Pre-cast Installation

Zone A (Gridline 26-23/O-A) 25 23-Sep-16 22-Oct-16 0 22-Oct-16, Zone A ( Gri dline 26-23/O -A)

Zone B (Gridline 23-19/U-A) 16 06-Oct-16 24-Oct-16 18 24-Oct-16, Zone B (Gridline 23-19/U-A)

Zone C (Gridline 19-17/U-A) 12 15-Nov-16 28-Nov-16 9 28-Nov-16, Zone C (Gridline 19-17/U-A)

Zone D (Gridline 17-11/U-A) 27 28-Oct-16 30-Nov-16 0 30-Nov-16, Zone D (Gridline 17-11/U-A)

Zone E (Gridline 11-5/U-A) 18 29-Nov-16 20-Dec-16 0 20-Dec-16, Zone E (Gridline 11-5/U-A)

Zone F (Gridline 5-1/Q-A) 15 02-Dec-16 20-Dec-16 0 20-Dec-16, Zone F (Gridline 5-1/Q-A)

Super-structure 138 23-Sep-16 11-Mar-17 0 11-Mar-17, Super-structure

First Floor - Elevation 46.50 91 23-Sep-16 12-Jan-17 13 12-Jan-17, First Floor - Elevation 46.50

Pre-cast Installation 91 23-Sep-16 12-Jan-17 13 12-Jan-17, Pre-cast Installation

Zone A (Gridline 26-23/O-A) 36 23-Sep-16 05-Nov-16 2 05-Nov-16, Zone A (Gr idline 26-23/O-A)

Zone B (Gridline 23-19/U-A) 30 06-Oct-16 11-Nov-16 18 11-Nov-16, Zone B (Gridline 23-19/U-A)

Zone C (Gridline 19-17/U-A) 19 15-Nov-16 06-Dec-16 9 06-Dec-16, Zone C (Gridline 19-17/U-A)

Zone D (Gridline 17-11/u-A) 43 28-Oct-16 20-Dec-16 0 20-Dec-16, Zone D (Gridline 17-11/u-A)

Zone E (Gridline 11-5/U-A) 37 29-Nov-16 12-Jan-17 8 12-Jan-17, Zone E (Gridline 11-5/U-A)

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Milestone Page 9 of 14
11-Oct-16 IKEA JB MC Programme - Rev 03
Actual Work Critical Remaining Work Summary
MASTER CONSTRUCTION PROGRAMME - 11 Oct'16 IKEA JB MASTER CONSTRUCTION PROGRAMME - SUMMARY 11-Oct-16 14:32

Activity ID Activity Name Original Start Finish Total Float 2016 2017
Duration Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Zone F (Gridline 5-1/Q-A) 28 02-Dec-16 05-Jan-17 19 05-Jan-17, Zone F (Gridline 5-1/Q-A)

Second Floor - Elevation 52.00 67 03-Nov-16 23-Jan-17 12 23-Jan-17, Second Floor - Elevation 52.00

Pre-cast Installation 67 03-Nov-16 23-Jan-17 12 23-Jan-17, Pre-cast Installation

Zone A (Gridline 26-23/O-A) 16 03-Nov-16 22-Nov-16 0 22-Nov-16, Zone A (Gr idline 26-23/O-A)

Zone B (Gridline 23-19/Q-A) 17 09-Nov-16 28-Nov-16 18 28-Nov-16, Zone B (Gridline 23-19/Q-A)

Zone C (Gridline 19-17/Q-A) 9 05-Dec-16 15-Dec-16 9 15-Dec-16, Zone C (Gridline 19-17/Q-A)

Zone D (Gridline 17-11/Q-A) 13 17-Dec-16 02-Jan-17 15 02-Jan-17, Zone D (Gridline 17-11/Q-A)

Zone E (Gridline 11-5/Q-A) 12 10-Jan-17 23-Jan-17 7 23-Jan-17, Zone E (Gridline 11-5/Q-A)

Zone F (Gridline 5-1/Q-A) 8 03-Jan-17 11-Jan-17 22 11-Jan-17, Zone F (Gridline 5-1/Q-A)

Roof - Elevation 56.69 84 11-Nov-16 22-Feb-17 0 22-Feb-17, Roof - Elevation 56.69

Zone A (Gridline 26-23/O-A) 28 11-Nov-16 14-Dec-16 0 14-Dec-16, Zone A (G ridli ne 26- 23/O- A)

Zone B (Gridline 23-19/Q-A) 33 15-Nov-16 23-Dec-16 48 23-Dec-16, Zone B (Gridline 23-19/Q-A)

Zone C (Gridline 19-17/Q-A) 19 07-Dec-16 30-Dec-16 43 30-Dec-16, Zone C (Gridline 19-17/Q-A)

Zone D (Gridline 17-11/Q-A) 34 23-Dec-16 03-Feb-17 15 03-Feb-17, Zone D (Gridline 17-11/Q-A)

Zone E (Gridline 11-5/Q-A) 30 16-Jan-17 22-Feb-17 0 22-Feb-17, Zone E (Gridline 11-5/Q-A)

Zone F (Gridline 5-1/Q-A) 24 07-Jan-17 06-Feb-17 0 06-Feb-17, Zone F (Gridline 5-1/Q-A)

Roof Parapet 15 23-Feb-17 11-Mar-17 0 11-Mar-17, Roof Parapet

Flat Flooring 119 08-Nov-16 01-Apr-17 9 01-Apr-17, Flat Flooring

Basement B1(P2) - Elevation 36.50 70 19-Nov-16 14-Feb-17 48 14-Feb-17, Basement B1(P2) - Elevation 36.50

Zone A (Gridline 26-23/O-A) 10 19-Nov-16 30-Nov-16 36 30-Nov-16, Zone A (Gr idline 26-23/O-A)

Zone B (Gridline 23-19/Q-A) 10 24-Nov-16 05-Dec-16 32 05-Dec-16, Zone B (Gridline 23-19/Q-A)

Zone C (Gridline 19-17/Q-A) 5 14-Dec-16 19-Dec-16 21 19-Dec-16, Zone C (Gridline 19-17/Q-A)

Zone D (Gridline 17-11/Q-A) 15 09-Jan-17 25-Jan-17 31 25-Jan-17, Zone D (Gridline 17-11/Q-A)

Zone E (Gridline 11-5/Q-A) 10 02-Feb-17 14-Feb-17 48 14-Feb-17, Zone E (Gridline 11-5/Q-A)

Zone F (Gridline 5-1/Q-A) 10 18-Jan-17 31-Jan-17 53 31-Jan-17, Zone F (Gridline 5-1/Q-A)

Ground Floor (P1)- Elevation 41.00 70 08-Nov-16 01-Feb-17 8 01-Feb-17, Ground Floor (P1)- Elevation 41.00

Zone A (Gridline 26-23/O-A) 10 08-Nov-16 18-Nov-16 36 18-Nov-16, Zone A (Gr idline 26-23/O-A)

Zone B (Gridline 23-19/U-A) 10 12-Nov-16 23-Nov-16 32 23-Nov-16, Zone B (Gridline 23-19/U-A)

Zone C (Gridline 19-17/U-A) 5 07-Dec-16 13-Dec-16 11 13-Dec-16, Zone C (Gridline 19-17/U-A)

Zone D (Gridline 17-11/U-A) 15 21-Dec-16 07-Jan-17 0 07-Jan-17, Zone D (Gridline 17-11/U-A)

Zone E (Gridline 11-5/U-A) 15 13-Jan-17 01-Feb-17 8 01-Feb-17, Zone E (Gridline 11-5/U-A)

Zone F (Gridline 5-1/Q-A) 10 06-Jan-17 17-Jan-17 19 17-Jan-17, Zone F (Gridline 5-1/Q-A)

First Floor - Elevation 46.50 66 23-Nov-16 13-Feb-17 7 13-Feb-17, First Floor - Elevation 46.50

Zone A (Gridline 26-23/O-A) 10 23-Nov-16 03-Dec-16 23 03-Dec-16, Zone A (G ridli ne 26- 23/O- A)

Zone B (Gridline 23-19/U-A) 10 29-Nov-16 09-Dec-16 18 09-Dec-16, Zone B (Gridline 23-19/U-A)

Zone C (Gridline 19-17/U-A) 5 16-Dec-16 21-Dec-16 9 21-Dec-16, Zone C (Gridline 19-17/U-A)

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Milestone Page 10 of 14
11-Oct-16 IKEA JB MC Programme - Rev 03
Actual Work Critical Remaining Work Summary
MASTER CONSTRUCTION PROGRAMME - 11 Oct'16 IKEA JB MASTER CONSTRUCTION PROGRAMME - SUMMARY 11-Oct-16 14:32

Activity ID Activity Name Original Start Finish Total Float 2016 2017
Duration Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Zone D (Gridline 17-11/U-A) 15 03-Jan-17 19-Jan-17 25 19-Jan-17, Zone D (Gridline 17-11/U-A)

Zone E (Gridline 11-5/U-A) 15 24-Jan-17 13-Feb-17 7 13-Feb-17, Zone E (Gridline 11-5/U-A)

Zone F (Gridline 5-1/Q-A) 10 12-Jan-17 23-Jan-17 22 23-Jan-17, Zone F (Gridline 5-1/Q-A)

Second Floor - Elevation 52.00 44 08-Feb-17 01-Apr-17 0 01-Apr-17, Second Floor - Elevation 52.00

Zone A (Gridline 26-23/O-A) 10 08-Feb-17 20-Feb-17 24 20-Feb-17, Zone A (Gr idline 26-23/O-A)

Zone B (Gridline 23-19/Q-A) 10 08-Feb-17 20-Feb-17 24 20-Feb-17, Zone B (Gridline 23-19/Q-A)

Zone C (Gridline 19-17/Q-A) 5 08-Feb-17 14-Feb-17 29 14-Feb-17, Zone C (Gridline 19-17/Q-A)

Zone D (Gridline 17-11/Q-A) 5 28-Mar-17 01-Apr-17 0 01-Apr-17, Zone D (Gridline 17-11/Q-A)

Zone E (Gridline 11-5/Q-A) 5 28-Mar-17 01-Apr-17 0 01-Apr-17, Zone E (Gridline 11-5/Q-A)

Zone F (Gridline 5-1/Q-A) 5 28-Mar-17 01-Apr-17 0 01-Apr-17, Zone F (Gridline 5-1/Q-A)

Closing of Crane Access 55 29-Nov-16 04-Feb-17 19 04-Feb-17, Closing of Crane Access

Hollow Core Slab 49 29-Nov-16 26-Jan-17 20 26-Jan-17, Hollow Core Slab

Flat Flooring 50 05-Dec-16 04-Feb-17 19 04-Feb-17, Flat Flooring

MEP Works 124 02-Jan-17 02-Jun-17 0 02-Jun-17, MEP Works

Evacuation Tunnels 43 04-Jan-17 25-Feb-17 59 25-Feb-17, Evacuation Tunnels

Basement B1(P2) 124 02-Jan-17 02-Jun-17 0 02-Jun-17, Basement B1(P2)

Ground Floor (P1) 101 20-Jan-17 24-May-17 4 24-May-17, Ground Floor (P1)

1st Floor 70 14-Jan-17 10-Apr-17 38 10-Apr-17, 1st Floor

2nd Floor 47 03-Apr-17 30-May-17 0 30-May-17, 2nd Floor

Roof 46 13-Mar-17 06-May-17 14 06-May-17, Roof

Architectural Finishes 150 15-Dec-16 17-Jun-17 0 17-Jun-17, Architectural Finishes

Evacuation Tunnels 89 16-Dec-16 04-Apr-17 32 04-Apr-17, Evacuation Tunnels

Basement B1(P2) 146 20-Dec-16 17-Jun-17 0 17-Jun-17, Basement B1(P2)

Ground Floor (P1) 123 09-Jan-17 09-Jun-17 0 09-Jun-17, Ground Floor (P1)

1st Floor 117 03-Jan-17 25-May-17 0 25-May-17, 1st Floor

2nd Floor 62 21-Mar-17 06-Jun-17 0 06-Jun-17, 2nd Floor

Roof 95 15-Dec-16 10-Apr-17 45 10-Apr-17, Roof

SC Connection 173 28-Oct-16 30-May-17 1 30-May-17, SC Connection

Civil / Structural 117 28-Oct-16 21-Mar-17 1 21-Mar-17, Civil / Structural

Sub-structure 52 28-Oct-16 31-Dec-16 1 31-Dec-16, Sub-structure

Basement B1 (P2) 32 28-Oct-16 06-Dec-16 1 06-Dec-16, Basement B1 (P2)

Ground Floor (P1) 20 07-Dec-16 31-Dec-16 1 31-Dec-16, Ground Floor (P1)

Super-structure 65 02-Jan-17 21-Mar-17 1 21-Mar-17, Super-structure

First Floor 20 02-Jan-17 24-Jan-17 1 24-Jan-17, First Floor

Second Floor 20 24-Jan-17 20-Feb-17 1 20-Feb-17, Second Floor

Roof 25 20-Feb-17 21-Mar-17 1 21-Mar-17, Roof

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Milestone Page 11 of 14
11-Oct-16 IKEA JB MC Programme - Rev 03
Actual Work Critical Remaining Work Summary
MASTER CONSTRUCTION PROGRAMME - 11 Oct'16 IKEA JB MASTER CONSTRUCTION PROGRAMME - SUMMARY 11-Oct-16 14:32

Activity ID Activity Name Original Start Finish Total Float 2016 2017
Duration Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
MEP Works 50 21-Mar-17 22-May-17 1 22-May-17, MEP Works

Architectural Finishes 52 27-Mar-17 30-May-17 1 30-May-17, Architectural Finishes

External Wall Cladding Works 135 15-Dec-16 30-May-17 0 30-May-17, External Wall Cl adding Works

Lifts / Escalators / Travelators 123 07-Feb-17 08-Jul-17 0 08-Jul-17, Lifts / Escalators / Travelators

Lifts 123 07-Feb-17 08-Jul-17 0 08-Jul-17, Lifts

Escalators 70 17-Mar-17 12-Jun-17 0 12-Jun-17, Escalators

Travelators 50 11-Apr-17 12-Jun-17 0 12-Jun-17, Travelators

External Works 295 05-Sep-16 05-Sep-17 27 05-Sep-17, External Works

External Retaining Walls 71 05-Sep-16 01-Dec-16 27 01-Dec-16, External Retaining Wall s

Foundations 30 05-Sep-16 12-Oct-16 43 12-Oct-16, Foundations

Walls 40 13-Sep-16 01-Nov-16 27 01-Nov-16, Wal ls

Backfilling and Compaction 57 23-Sep-16 01-Dec-16 27 01-Dec-16, Backfilling and Compaction

Sub station 147 09-Nov-16 06-May-17 0 06-May-17, Sub station

Civil / Structural 39 09-Nov-16 24-Dec-16 0 24-Dec-16, Civil / Structural

Earth Works 12 09-Nov-16 22-Nov-16 0 22-Nov-16, Earth Works

Foundations 8 15-Nov-16 23-Nov-16 0 23-Nov-16, Foundations

Cable Trench with Inspection by TNB 7 23-Nov-16 30-Nov-16 0 30-Nov-16, Cable Trench with Inspection by TNB

Ground Slab 6 01-Dec-16 07-Dec-16 0 07-Dec-16, Ground Slab

Column 7 08-Dec-16 16-Dec-16 0 16-Dec-16, Column

Beams / Slabs 7 17-Dec-16 24-Dec-16 0 24-Dec-16, Beams / Slabs

MEP Works 13 02-Jan-17 16-Jan-17 2 16-Jan-17, MEP Works

Architectural Finishes 20 27-Dec-16 18-Jan-17 0 18-Jan-17, Architectural Finishes

TNB Inspection and Handover 2 19-Jan-17 20-Jan-17 0 20-Jan-17, TNB Inspection and Handover
20-Jan-17

TNB Sub Contractor 86 21-Jan-17 06-May-17 0 06-May-17, TNB Sub Contractor

IKEA HT Room 62 27-Dec-16 11-Mar-17 0 11-Mar-17, IKEA HT Room

Civil / Structural 24 27-Dec-16 23-Jan-17 0 23-Jan-17, Civil / Structural

Architectural Finishes 15 16-Jan-17 03-Feb-17 0 03-Feb-17, Architectural Finishes

MEP Works 30 04-Feb-17 11-Mar-17 0 11-Mar-17, MEP Wor ks

OSD Tank 41 20-Jun-17 08-Aug-17 22 08-Aug-17, OSD Tank

Civil / Structural 26 20-Jun-17 21-Jul-17 1 21-Jul-17, Civil / Structural

MEP Works 15 22-Jul-17 08-Aug-17 22 08-Aug-17, MEP Works

Generator Room 42 13-Mar-17 02-May-17 18 02-May-17, Generator Room

Civil / Structural 18 13-Mar-17 03-Apr-17 18 03-Apr-17, Civil / Structural

MEP Works 14 15-Apr-17 02-May-17 18 02-May-17, MEP Works

Architectural Finishes 10 04-Apr-17 14-Apr-17 18 14-Apr-17, Architectural Finishes

Cooling Towers 26 04-Apr-17 04-May-17 18 04-May-17, Cooling Towers

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Milestone Page 12 of 14
11-Oct-16 IKEA JB MC Programme - Rev 03
Actual Work Critical Remaining Work Summary
MASTER CONSTRUCTION PROGRAMME - 11 Oct'16 IKEA JB MASTER CONSTRUCTION PROGRAMME - SUMMARY 11-Oct-16 14:32

Activity ID Activity Name Original Start Finish Total Float 2016 2017
Duration Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Civil / Structural 14 04-Apr-17 19-Apr-17 18 19-Apr-17, Civil / Structural

MEP Works 12 20-Apr-17 04-May-17 18 04-May-17, MEP Works

Sign Tower 30 26-May-17 04-Jul-17 7 04-Jul-17, Sign Tower

Civil / Structural 15 26-May-17 14-Jun-17 7 14-Jun-17, Civil / Structural

MEP Works 12 19-Jun-17 04-Jul-17 7 04-Jul-17, MEP Works

Architectural Finishes 10 15-Jun-17 28-Jun-17 7 28-Jun-17, Architectural Finishes

Navigation Tower 36 22-Jul-17 04-Sep-17 1 04-Sep-17, Navigation Tower

Civil / Structural 18 22-Jul-17 11-Aug-17 1 11-Aug-17, Civil / Structural

MEP Works 15 02-Aug-17 18-Aug-17 1 18-Aug-17, MEP Works

Architectural Finishes 12 19-Aug-17 04-Sep-17 1 04-Sep-17, Architectural Finishes

Infrastructure Works Within Site Boundary 167 13-Feb-17 05-Sep-17 27 05-Sep-17, Infrastructure Wor ks Within Site B

Civil / Structural 150 13-Feb-17 14-Aug-17 0 14-Aug-17, Civil / Structural

MEP Works 153 01-Mar-17 05-Sep-17 0 05-Sep-17, MEP Works

Landscaping Works 60 13-May-17 26-Jul-17 60 26-Jul-17, Landscaping Works

Infrastructure Works Outside Site Boundary 157 24-Feb-17 05-Sep-17 0 05-Sep-17, Infrastructure Wor ks Outsi de Si te

Civil / Structural 111 24-Feb-17 11-Jul-17 0 11-Jul-17, Civil / Structural

MEP Works 101 20-Mar-17 22-Jul-17 0 22-Jul-17, MEP Works

Lancsaping Works 36 24-Jul-17 05-Sep-17 0 05-Sep-17, Lancsaping Works

64 08-May-17 26-Jul-17 0 26-Jul-17, Testi ng / Commissioni ng Phase


Testing / Commissioning Phase
5147847_CON_123620 Lifts / Escalators / Travelators ( 01 July) 43 08-May-17 01-Jul-17 0 Lifts / Escalators / Travelators ( 01 July)

5147847_CON_123680 Lifts / Escalators / Travelators ( 26 July) 55 19-May-17 26-Jul-17 0 Lifts / Escalators / Travelators ( 26 July)

5147847_CON_123560 Electrical Works 50 25-May-17 26-Jul-17 0 Electrical Works

5147847_CON_123580 Plumbing / Drainage Works 50 25-May-17 26-Jul-17 0 Plumbing / Drainage Works

5147847_CON_123590 ICT w or ks 50 25-May-17 26-Jul-17 0 ICT wor ks

5147847_CON_123610 Fire Fighting Works 50 25-May-17 26-Jul-17 0 Fire Fighting Works

5147847_CON_123570 HVAC Works 48 29-May-17 26-Jul-17 0 HVAC Works

5147847_CON_123600 BMS 46 31-May-17 26-Jul-17 0 BMS

119 15-May-17 09-Oct-17 0 09-Oct-17, Project Close out


Project Close out
Snagging / De Snagging / Hand Over 119 15-May-17 09-Oct-17 0 09-Oct-17, Snagging / De Snagging

Snagging / De Snagging 92 15-May-17 05-Sep-17 27 05-Sep-17, Snagging / De Snagging

5147847_CON_123700 Evacuation Tunnels 38 15-May-17 01-Jul-17 0 Evacuation Tunnels

5147847_CON_123650 1st Floor 28 26-May-17 01-Jul-17 0 1st Floor

5147847_CON_123710 SC Connection 46 30-May-17 26-Jul-17 1 SC Connection

5147847_CON_123660 2nd Floor 20 07-Jun-17 01-Jul-17 0 2nd Floor

5147847_CON_123640 Ground Floor 38 10-Jun-17 26-Jul-17 0 Ground Floor

5147847_CON_123630 B1 Floor 31 19-Jun-17 26-Jul-17 0 B1 Floor

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Milestone Page 13 of 14
11-Oct-16 IKEA JB MC Programme - Rev 03
Actual Work Critical Remaining Work Summary
MASTER CONSTRUCTION PROGRAMME - 11 Oct'16 IKEA JB MASTER CONSTRUCTION PROGRAMME - SUMMARY 11-Oct-16 14:32

Activity ID Activity Name Original Start Finish Total Float 2016 2017
Duration Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
5147847_CON_123720 External Wor ks 38 21-Jul-17 05-Sep-17 27 External Wor ks

Hand Over 0 09-Oct-17 09-Oct-17 0 09-Oct-17, Hand Over

5147847_CON_123670 CCC issuance / Handing Over 0 09-Oct-17 0 09-Oct-17

Date Revision Checked Approved


Remaining Level of Effort Remaining Work Milestone Page 14 of 14
11-Oct-16 IKEA JB MC Programme - Rev 03
Actual Work Critical Remaining Work Summary

S-ar putea să vă placă și