Documente Academic
Documente Profesional
Documente Cultură
PRODUCTION SYSTEM
The methods, procedure or arrangement which includes
all functions required to accumulate (gather) the inputs,
process or reprocess the inputs, and deliver the marketable
output (goods).
Limitations
1. Material handling is complex because of irregular and longer
flows.
2. Production planning and control is complex.
3. Work in process inventory is higher compared to continuous
production.
4. Higher set up costs due to frequent changes in set up.
Job Order type Production
In this type of production the products are manufactured directly to
customer’s orders and the quantity produced is also small, in many
cases it may be one piece only. The work is started only when the
organization has orders on hand.
Limitations
1. Higher cost due to frequent set up changes.
2. Higher level of inventory at all levels and hence higher inventory
cost.
3. Production planning is complicated.
4. Larger space requirements.
Continuous Production:
It is the specialised manufacture of identical articles.
The machinery and equipment's are fully engaged.
The products which are in high demand are produced
in large quantities in this production.
It is further classified into two types.
Mass Production
Flow Production
Mass Production
Mass production means the production of items in large quantity using
very specialised machines and processes. Items like metal screws,
nuts and bolts and plastic products are made in mass production. In
this type of production there is a continuous and steady flow of
materials.
Limitations
1. Breakdown of one machine will stop an entire production line.
2. Line layout needs major change with the changes in the product design.
3. High investment in production facilities.
4. The cycle time is determined by the slowest operation.
Continuous Production
Production facilities are arranged as per the sequence of production
Limitations
PRODUCTION DESIGN
production design is concerned with determination of manufacturing
tolerance, selection of material, achievement of max interchangeability of
man power, machines, manufacturing with utilizing those processes that
make a low cost production.
Design Machine
Tool
Process
Planning
13 - 21
Analyze
Part requirements
(drawing interpretation
Determine
Operation sequence
(Material evaluation and process selection)
Select
Equipment
(selection of machines, tooling and work holding devices)
Calculate
Processing times
(setting process parameters)
Select
QA/inspection methods
(selecting quality assurance methods)
Estimate
Manufacturing cost
(cost estimating)
Document
Process plan
(preparing the process planning documentation)
Communicate
Mfg.engr shoop floor
PROCESS PLANNING ACTIVITIES
STEP 1: Drawing interpretation- Analysis of the finished part
requirements as specified in the engineering design.
SETP 2: Material evaluation and process selection- Evaluating the
materials specified and determining the appropriate manufacturing
processes`
STEP 3: Selection of machines, tooling and work holding devices-
Selecting the proper equipment to accomplish the required operations.
STEP 4: Setting process parameters- Establishing specific parameters
for each operation for each machine.
STEP 5: Selection of QA methods- specifying the inspection criteria for
all critical processing factors.
STEP 6: Cost estimating- Estimating the manufacturing costs of
producing a component/product.
STEP 7: Preparing the process planning documentation- Preparing
routing sheets and operations list.
STEP 8: Communicating the manufacturing knowledge to the shop floor.
Process Selection
Process selection determines how the product (or service) will be
produced. It determines the most economical method of performing an
activity. It involves
1. Technological choice.
(a) Major technological choice.
(b) Minor technological choice.
2. Specific component choice.
3. Process flow choice.
1. Technological choice
(a) Major technological choice
While considering major technological choice, the following questions
should be analysed:
• Does technology exist to make the product?
• Are there competing technologies among which we should choose?
• Should innovations be licensed from foreign countries?
(b)Minor technological choice
Once the major technological choice is made, there may be a number
of minor technological process alternatives available. The operations
manager should be involved in evaluating alternatives for costs and for
consistency with the desired product and capacity plans.
Should the process be continuous, which is carried out for 24 hours a
day in order to avoid expensive start ups and shut downs as used by
steel and chemical industries.
The steps mentioned in the previous section are essentially same for
manual process planning. Following difficulties are associated with manual
experienced based process planning method :
It is time consuming and over a period of time, plan developed are not
consistent.
Feasibility of process planning is dependent on many upstream factors (design
and availability of machine tools). Downstream manufacturing activities such
as scheduling and machine tool allocation are also influenced by such process
plan.
Therefore, in order to generate a proper process plan, the process planner
must have sufficient knowledge and experience. Hence, it is very difficult to
develop the skill of the successful process planner and also a time
consuming issue.
2. Computer Aided Process Planning (CAPP)
Process planning involves the preparation and documentation of the
plans for manufacturing the products. Computer-Aided Process Planning
(CAPP) is a means of implementing this planning function by the use of
computers.
where,
FA = Fixed cost of machine A, Rs.
FB = Fixed cost of machine B, Rs.
VA = Variable cost of machine A, Rs.
VB = Variable cost of machine B, Rs.
Q = Required Quantity.
This would give a positive value when fixed cost of a process is greater
and variable cost less than those of the other process. If both fixed cost and
variable cost are lower than the other process, then the latter process is
always uneconomical whatever may be the production quantity. This can
also be done by graphical method.