Sunteți pe pagina 1din 11

BOQ FOR PROPOSED RETAINING WALL CONSTRUCTION WORK AT

PALAWATHTHA

ITEM DESCRIPTION UNIT QTY RATE


PRELIMINARY WORKS

Allow for construction, furnishing and


maintaining of temporary site office and sanitary
facilities for the Engineer, Contractor and sub Item 1.00 45,000.00
1.1 contractors.

Allow for construction, maintain and removal at


end of contract temporary building for protection Item 1.00 25,000.00
1.2 and storage of materials and plant.

Employer's staff at site and visiting. (Actual cost


for obtaining insurance cover shall be reimbursed
to the Contractor subject to the maximum quoted Item 1.00 100,000.00
for this item on submission of documentary
1.3 evidence)

Workmen's compensation insurance including all


Item 1.00 40,000.00
1.4 sub Contractor's workers

1.5 site cleaning item 1.00 25,000.00

Allow for construction, maintain and removal at


end of contract temporary building for protection Item 1.00 35,000.00
1.6 and storage of materials and plant.

2 Dry Earth Filling

Well compacted approved imported earth filling


free from any organic materials, in 300 mm
layers (up to a average depth of 1' 6") on existing
ground to makeup levels as per the specification m3 65.00 1,500.00
and to the Engineers approval soil supply by
client
2.1

2.2 Hard earth filling


Imported hard earth filling, well rammed and
consolidated using suitable roller to achieve 95%
maximum dry density, in make up levels under m3 293.00 1,500.00
floors 0'-6" thick layers soil supply by client

3.00 CONCRETE WORK

Concrete

All concrete shall be made dense with a vibrator


and finished to receive respective finishes. The
type and stability shall be agreed with the Note
consultant prior to commencement of concreting
of each item

Rates shall include for plant for mixing,


handling, hoisting, depositing, compacting,
vibrating, curing, making good after removal of Note
formwork and for any tests as necessary

Work up to FFL

3.10 Grade 25 reinforced concrete 1:11/2:3 mix

3 In wall shaft m3 81.36 21,908.00

lean concrete with G 15Nmm-2 m2 172.96 1,506.00

3.3.1 Form work

Rate shall include for all necessary boarding,


supporting, application of mould oil as necessary
erecting, framing, cutting angles, cleaning,
Note
wetting and treatment before placing concrete
and striking or removal etc. construction joints

3.3.1 Sides of wall shaft and beam m2 400.87 1,936.00

3.40 Reinforcement

The size of reinforcement rods described in the


drawing or elsewhere shall be minimum size and
the rolling margin and any other tolerance shall Note
be wholly above this size. Hooks and laps have
been measured with the quantities
Rate shall include for cutting, bending,
fabricating, placing in position, holding and
supporting including temporary fixing supports, Note
hangers and binding wire, cover blocks, ties,
spaces, chairs

Characteristic strength of High Tor steel should


Note
be 460 N/mm2

Characteristic strength of Mild steel should be


Note
250 N/mm2

Reinforcement as per drawings and specifications


in to the followings

3 In column shaft beam

3.4.1 In T10 Kg 2,766.44 275.00

3.4.2 InT12 kg 2,428.80 275.00

3.4.3 In T16 kg 1,497.84 275.00

4 chemical anchoring and extaing footing item 1.00 150,000.00

Scaffolding and Gi pipe ,clamp, etc rate to


item 1.00 270,000.00
5 be inclding transport

6 pump car costing item 1.00 240,000.00

7 JCB machine hours 50.00 2,800.00

Total cost
ON WORK AT

AMOUNT

45,000.00

25,000.00

100,000.00

40,000.00

25,000.00

35,000.00

97,500.00
439,500.00

1,782,431.59

260,478.96

776,074.64
760,771.00

667,920.00

411,906.00

150,000.00

270,000.00

240,000.00

140,000.00

6,266,582.20
ITEM DESCRIPTION T T L W H TOTAL

CONCRETE
Wall up to 3.6 2.991 0.250 3.600 2.692
12.230 0.250 3.600 11.007
7.537 0.250 3.600 6.783

1st 2000mm 2.991 2.000 0.200 1.196


12.230 2.000 0.200 4.892
7.537 2.000 0.200 3.015

Beam 3000 2.991 3.000 0.300 2.692


12.230 3.000 0.300 11.007
7.537 3.000 0.300 6.783

Beam 3000 2.991 0.300 0.450 0.404


12.230 0.300 0.450 1.651
7.537 0.300 0.450 1.017

up to 7.6 from 3.6 2.991 0.200 4.000 2.393


12.230 0.200 4.000 9.784
7.537 0.200 4.000 6.030

footing 2.991 0.600 0.400 0.718


12.230 0.600 0.400 2.935
7.537 0.600 0.400 1.809

foot parth 2.991 2.000 0.100 0.598


12.230 2.000 0.100 2.446
7.537 2.000 0.100 1.507

81.360

Lean concrete 2.991 2.000 5.982


12.230 2.000 24.460
7.537 2.000 15.074

2.991 3.000 8.973


12.230 3.000 36.690
7.537 3.000 22.611

2.991 2.000 5.982


12.230 2.000 24.460
7.537 2.000 15.074
2.991 0.600 1.795
12.230 0.600 7.338
7.537 0.600 4.522

172.961

Form work 2.00 2.991 3.600 21.535


2.00 12.230 3.600 88.056
2.00 7.537 3.600 54.266

2.00 2.991 0.200 1.196


2.00 12.230 0.200 4.892
2.00 7.537 0.200 3.015
2.00 2.000 0.200 0.800

2.00 2.991 0.300 1.795


2.00 12.230 0.300 7.338
2.00 7.537 0.300 4.522
2.00 3.000 0.300 1.800

2.00 2.991 0.450 2.692


2.00 12.230 0.450 11.007
2.00 7.537 0.450 6.783

2.00 2.991 4.000 23.928


2.00 12.230 4.000 97.840
2.00 7.537 4.000 60.296

footing 1.00 2.991 0.400 1.196


1.00 12.230 0.400 4.892
1.00 7.537 0.400 3.015

400.865

Reinforcement work

T12 shaft unto 3.6 2.00 120.00 4.500 1,080.000


3000 beam 1.00 140.00 4.500 630.000
3000 beam 1.00 140.00 4.000 560.000
1.00 140.00 3.500 490.000
2,760.000 0.880
2,428.800

T10 shaft up to 3.6 2.00 20.00 25.000 1,000.000


Beam 2000 2.00 140.00 2.600 728.000
Beam 2000 2.00 11.00 25.000 550.000
3000 beam 2.00 15.00 24.000 720.000
Shaft 3000 2.00 20.00 24.000 960.000
floor concrete 1.00 11.00 24.000 264.000
1.00 120.00 2.000 240.000
4,462.000 0.620
2,766.440
T16 shaft column 6.00 4.00 4.500 108.000
3000 beam shaft 1.00 140.00 6.000 840.000
948.000 1.580
1,497.840

soil 8.200 2.800 4.200 96.432


5.000 6.000 4.200 126.000
6.500 1.800 4.200 49.140
3.500 1.500 4.200 22.050

293.622

day Nos Rs Total


scarfolding 45.00 5.00 14.000 50.000 3,150.000 157,500.000

pipe 45.00 50.000 30.000 2,250.000 67,500.000

clamp 45.00 100.000 10.000 4,500.000 45,000.000


270,000.000

pump car 8.00 ### 240,000.000


m2
PROPOSED BOUNDARY WALL ON THE CONCRETE WALL (Length 25m height -3.6m)

ITEM DESCRIPTION UNIT QTY RATE AMOUNT

150mm Tk hollow block work with 1:5


1 m2 91.46 3,120.00 285,355.20
cement sand mortar

2 RRM work for foundation m3 7.00 10,714.00 74,998.00

150mm x225mm size RCC beam for


middle and top rate to be including 4T10
3 m 50.00 4,723.00 236,150.00
and R6 strap 150mm c/c and concrete
,form work

150mm x225mm size RCC column for


middle and top rate to be including 4T10
4 m 33.00 4,526.00 149,358.00
and R6 strap 150mm c/c and concrete
,form work

Wall finishes

Rates for plastering shall include for


providing expanded joints, plastering the
reveals, moldings, door window reveals,
etc. as per the detailed drawings.

External plaster in 1:5 cement, , sand


5 plastered to a thickness not less than m2 182.92 1,076.00 196,821.92
5/8" finished semi rough

6 Shoe drain work according to drawing m 43.00 4,200.00 180,600.00

Total cost 1,123,283.12

S-ar putea să vă placă și