Documente Academic
Documente Profesional
Documente Cultură
REV 06
Oct’ 2013
CONTENTS - SECTION- 765 KV SHUNT REACTOR, NEUTRAL GROUNDING
REACTOR AND SURGE ARRESTER
1. General
2. Type of Reactor
2.1. The shunt reactor shall be of either gapped core type or magnetically shielded air core
type (shell type) construction. The impedance ratio (X0/X1) specified shall be
achieved by any one of the following methods:
3. Transportation
3.1. The Contractor shall be responsible to select and verify the route, mode of
transportation and make all necessary arrangement with the appropriate authorities for
the transportation of the equipment. The dimension of the equipment shall be such that
when packed for transportation, it will comply with the requirements of loading and
clearance restrictions for the selected route. It shall be the responsibility of the
contractor to coordinate the arrangement for transportation of the Reactor for all the
stages from the manufacturer’s work to site.
3.2. The contractor shall carry out the route survey along with the transporter and finalise
the detail methodology for transportation of reactor and based on route survey; any
modification/ extension/ improvement to existing road, bridges, culverts etc. if
required, shall be in the scope of the bidder.
3.3. The main tank of the reactor shall be inland transported on Hydraulic trailers equipped
with GPS system for tracking the location of Reactor at all times during transportation
from manufacturer works to designated site. The contractor shall intimate to Employer
about the details of transporter engaged for transportation of the Reactor. The requisite
details for tracking the Reactor during transit shall be provided to Employer.
3.4. All metal blanking plates and covers which are specifically required to transport the
reactor shall be considered part of the reactor and handed over to the Purchaser after
completion of the erection. Bill of quantity of these items shall be included in the
relevant drawing/document.
3.5. The Contractor shall despatch the reactor filled with dry air at positive pressure. The
necessary arrangement shall be ensured by the contractor to take care of pressure drop
In case, turret having insulation assembly, is transported separately, then the above dry
air arrangement shall be provided for turret also.
3.6. Reactor shall also be fitted with sufficient number of Electronic impact recorders (on
returnable basis) during transportation to measure the magnitude and duration of the
impact in all three directions. The acceptance criteria and limits of impact, which can
be withstood by the equipment during transportation and handling in all three
directions, shall not exceed“3g” for 50mSec (20Hz) as per POWERGRID pre-
commissioning document mentioned at Annexure-D or as per contractor standard,
whichever is higher.
4. Performance
4.1. Shunt Reactors will be connected to the 800 kV transmission system for reactive load
compensation and shall be capable of controlling the dynamic over voltage occurring
in the system due to load rejection. Typical line parameters of 800 kV and & 400kV
Transmission Lines are given below:
4.2. Shunt Reactors shall be capable of operating continuously at a voltage 5% higher than
their rated voltage and thermal and cooling system shall be designed accordingly.
4.3. The neutral grounding reactors are required for grounding of the neutral point of shunt
reactors to limit the secondary arc current and the recovery voltage to a minimum
value.
4.4. The reactors shall be designed for switching surge overvoltage of 1.9 p.u. and
temporary over voltage of the order of 1.4 p.u. for about 10 cycles followed by power
frequency overvoltage upto 830 kVrms for about five minutes. The reactor shall
withstand the stress due to above transient dynamic conditions which may cause
additional current flow as a result of changed saturation characteristics/slope beyond
1.25 p.u. voltage.
4.5. The reactor shall be designed to withstand the following over-voltages repeatedly
without risk of failure:
4.6. The magnetic circuit will be designed such that the reactor is linear upto 125%
maximum operating voltage.
4.7.1. The reactor shall be designed with particular attention to the suppression of harmonic
voltage, especially the third and fifth so as to minimise interference with
communication circuit.
4.7.2. The noise level of reactor, when energised at maximum continuous operating voltage
and frequency shall not exceed the values specified at Annexure-A measured under
standard conditions as defined in IEC.
Manufacturer shall provide additional warrantee of five years (in addition to the
warrantee specified in the bidding documents) for the Reactor in case any of the
followings is observed within specified warrantee period:
a) Repair, inside the Reactor either at site or at factory is carried out after
commissioning.
c) The winding Tan delta goes beyond 0.005 or increase more than 0.001 within
a year w.r.t. pre-commissioning values. No temperature correction factor
shall be applicable.
5. Design review
5.1. The reactor shall be designed, manufactured and tested in accordance with the best
international engineering practices under strict quality control to meet the requirement
stipulated in the technical specification. Adequate safety margin w.r.to thermal,
mechanical, dielectric and electrical stress etc. shall be maintained during design,
selection of raw material, manufacturing process etc. in order to achieve long life of
reactor with least maintenance.
5.2. Raw material and sub-vendors used by reactor manufacturer shall be declared before
commencement of manufacturing. The validity of Type tests of Reactor shall be 5
years as on the originally scheduled date of bid opening, provided that offered
reactor design is identical to the type tested Reactor and same active materials
5.3. Design reviews shall be conducted by Purchaser or an appointed consultant during the
procurement process for Reactors; however the entire responsibility of design shall be
with the manufacturer. Purchaser may also visit the manufacturers works to inspect
design, manufacturing and test facilities.
5.4. The design review will commence after placement of award with the successful bidder
and shall be finalised before commencement of manufacturing activity. These design
reviews shall be carried out in detail to the specific design with reference of the
reactor under the scope of this specification. It shall be conducted generally following
the “Guidelines for conducting design reviews for Reactors -100 MVA and 123 kV
and above” prepared by CIGRE SC 12 Working Group 12.22.
5.5. The manufacturer shall provide all necessary information and calculations to
demonstrate that the reactor meets the requirements for mechanical strength and
durability due to inrush current. The latest recommendations of IEC and Cigre SC 12
shall be applied for short circuit withstand evaluation.
5.6. The manufacturer will be required to demonstrate the use of adequate safety margins
for thermal, mechanical, dielectric and vibration etc. in design to take into account the
uncertainties of his design and manufacturing processes. The scope of such design
review shall include but not limited to the requirement as mentioned at Annexure – E.
6. Construction Details
The construction details and features of each Shunt Reactor shall be in accordance
with the requirement stated hereunder. The components and fitting associated with
Reactors are subject to Purchaser’s approval and design review.
6.1. Tank
6.1.1. Tank shall be of welded construction and fabricated from tested quality low carbon
steel of adequate thickness. Unless otherwise approved, metal plate, bar and sections
for fabrication shall comply with BS-4360 / IS 2062. Material Samples, technical
literature, drawings, test reports and list of the names of the principal users with
experience gained shall be supplied on request.
6.1.2. All seams and those joints not required to be opened at site, shall be factory welded,
and wherever possible they shall be double welded. Welding shall conform to BS-
5135/IS 9595. After fabrication of tank and before painting, dye penetration test shall
be carried out on welded parts of jacking bosses, lifting lugs and all load bearing
members. The requirement of post weld heat treatment of tank/stress relieving shall be
based on recommendation of BS-5500 table 4.4.3.1/IS 10801.
6.1.3. Tank stiffeners shall be provided for general rigidity and these shall be designed to
prevent retention of water.
6.1.4. The tank shall be of proven design either bell type with bolted /welded joint or
conventional type with welded / bolted top cover. Bell type tank shall be provided
a. Lifting lugs: Four symmetrically placed lifting lugs shall be provided so that it will
be possible to lift the complete Reactor when filled with oil without structural
damage to any part of the Reactor. The factor of safety at any one point shall not
be less than 2.
c. Each jacking pad shall be designed to support with an adequate factor of safety at
least half of the total mass of the Reactor filled with oil allowing in addition for
maximum possible misalignment of the jacking force to the centre of the working
surface.
d. Suitable haulage holes shall be provided.
f. Suitable provisions of pockets for OTI, WTI & RTDs including two spare pockets.
6.1.6. The tank shall be designed in such a way that it can be mounted on the plinth directly.
6.1.7. The base of each tank shall be so designed that it shall be possible to move the
complete Reactor unit by skidding in any direction without damage when using plates
or rails. Unless otherwise approved, Reactor base shall have minimum thickness as
specified below:
Tank hotspot-under extreme conditions, the maximum temperature on any metal part
shall not exceed 130 Deg. Celsius.
6.2.1. The tank cover shall be designed to prevent retention of water and shall not distort
when lifted. The internal surface of the top cover shall be shaped to ensure efficient
collection and direction of free gas to the buchholz relay.
6.2.2. At least two adequately sized inspection openings one at each end of the tank, shall be
provided for easy access to bushings and earth connections. The inspection covers
shall not weigh more than 25 kg. Handles shall be provided on the inspection cover to
facilitate lifting.
6.2.4. Bushing turrets, covers of inspection openings, thermometer pockets etc. shall be
designed to prevent ingress of water into or leakage of oil from the tank.
6.2.5. All bolted connections shall be fitted with weather proof, hot oil resistant, resilient
gasket in between for complete oil tightness. If gasket is compressible, metallic
stops/other suitable means shall be provided to prevent over-compression.
6.2.6. Currents flowing in tank cover and bushing turrets - To allow for the effect of
possible induced and capacitive surge current, the tank cover and bushing turret shall
be fixed to the Reactor in such a way that good electrical contact is maintained around
the perimeter of the tank and turrets.
6.2.7. The Reactor shall be provided with a 150 mm nominal diameter butterfly valve and
bolted blanking plate, gasket and shall be fitted at the highest point of the Reactor for
maintaining vacuum in the tank.
6.2.8. Gas venting - The reactor cover, and generally the internal spaces of the reactor and
all pipe connections shall be designed so as to provide efficient venting of any gas in
any part of the reactor to the Buchholz relay. The space created under inspection
/manhole covers shall be filled with suitable material to avoid inadvertent gas pockets.
The Covers shall be vented at least at both longitudinal ends. The design for gas
venting shall take into accounts the slopes of the plinth (if any) on which the Reactor
is being mounted.
All gasketed joints shall be designed, manufactured and assembled to ensure long-
term leak and maintenance free operation. All gasketed joints unless otherwise
approved shall be of the O-ring and groove type. The Gaskets / O-Ring in contact with
oil shall be Nitrile rubber or any better approved quality.
The properties of all the above gaskets / O-Rings shall comply with the requirements
of IS-11149. Gaskets and O-rings shall be replaced every time whenever the joints are
opened.
The Reactor shall be placed directly on concrete plinth foundation. To facilitate the
movement of reactor to its foundation over rail track, bi-directional flanged rollers
shall be provided. It shall be suitable for fixing to the under carriage of Reactor. The
rail track gauge shall be 1676 mm. Two rails shall be provided as per the drawing
mentioned at Annexure-D
Scope shall include supply of complete two sets of rollers assembly for movement of
reactors over rail track for each substation in case scope covers more than one reactor
per sub-station under the package Otherwise, atleast one set shall be supplied.
6.6. Conservator
6.6.1. Conservator shall have air cell type constant oil pressure system to prevent oxidation
and contamination of oil due to contact with moisture. Conservator shall be fitted with
magnetic oil level gauge with potential free high and low oil level alarm contacts and
prismatic oil level gauge.
6.6.2. Conservator tank shall have adequate capacity with highest and lowest visible-levels
to meet the requirements of expansion of total cold oil volume in the reactor and
cooling equipment from minimum ambient temperature to top oil temperature of 110
deg C. The capacity of the conservator tank shall be such that the reactor shall be able
to carry the specified overload without overflowing of oil.
6.6.3. The conservator shall be fitted with lifting lugs in such a position so that it can be
removed for cleaning purposes. Suitable provision shall be kept to replace air cell and
cleaning of the conservator as applicable.
6.6.5. The connection of air cell to the top of the conservator is by air proof seal preventing
entrance of air into the conservator. The main conservator tank shall be stencilled on
its underside with the words “Caution: Air cell fitted”. Lettering of at least 150 mm
size shall be used in such a way to ensure clear legibility from ground level when the
Reactor is fully installed. To prevent oil filling into the air cell, the oil filling aperture
shall be clearly marked. The Reactor rating and diagram plate shall bear a warning
statement that the “Conservator is fitted with an air cell”.
6.6.6. Contact of the oil with atmosphere is prohibited by using a flexible air cell of nitrile
rubber reinforced with nylon cloth. The temperature of oil in the conservator is likely
to raise up to 110OC during operation. As such air cell used shall be suitable for
operating continuously at this temperature.
6.6.7. The reactor manual shall give full and clear instructions on the operation,
maintenance, testing and replacement of the air cell. It shall also indicate shelf life, life
expectancy in operation, and the recommended replacement intervals.
6.6.8. The conservator tank and piping shall be designed for complete vacuum / filling of the
main tank and conservator tank. Provision must be made for equalising the pressure in
the conservator tank and the air cell during vacuum / filling operations to prevent
rupturing of the air cell.
6.6.9. The contractor shall furnish the leakage rates of the rubber bag/ air cell for oxygen and
moisture. It is preferred that the leakage rate for oxygen from the air cell into the oil
will be low enough that the oil will not generally become saturated with oxygen
before 10 years. Air cells with well proven long life characteristics shall be preferred.
6.7.2. The feed pipe to the Reactor tank shall enter the reactor cover plate at its highest point
and shall be straight for a distance not less than five times its internal diameter on the
reactor side of the Buchholz relay, and straight for not less than three times that
diameter on the conservator side of the relay. This pipe shall rise towards the oil
conservator, through the Buchholz relay, at an angle of not less than 5 degrees. The
feed pipe diameter for the main conservator shall be not less than 80 mm. Gas-venting
pipes shall be connected to the final rising pipe between the reactor and Buchholz
relay as near as possible in axial direction and preferably not less than five times pipe
diameters from the Buchholz relay.
6.7.3. A double flange valve of preferably 50 mm and 25 mm size shall be provided to fully
drain the oil from the main tank conservator.
6.7.4. Pipe work shall neither obstruct the removal of the opening of inspection or manhole
covers.
Adequate number of pressure relief devices but at least 2 numbers shall be provided at
suitable locations preferably close to bushing turret/ cover. These shall have opening
diameter of at least 100 mm for rapid release of any pressure that may be generated in
the tank and which may result in damage to equipment. The device shall maintain its
oil tightness under static oil pressure equal to the static operating head of oil plus 20
kPa. The device shall operate and attain its full opening in not more than 2.5 ms when
subject to an internal pressure impulse equal to static operating head of oil plus 50
kPa. It shall be capable of withstanding full internal vacuum at mean sea level. It shall
be mounted directly on the tank. One set of potential free contacts (with plug &
Adequate number of Sudden Pressure relay with alarm/trip contacts (Plug & socket
type arrangement suitable for 2.5sq.mm control cable) shall be provided on tank of
Reactor. Operating features, size and quantity shall be reviewed during design review.
Pressurised water ingress test for Terminal Box (routine tests) shall be conducted on
Sudden Pressure Relay.
Two numbers double float, reed type Buchholz relay shall be provided in series of the
connecting pipe between the oil conservator and the Reactor tank with minimum
distance of five times pipe diameters between them. Any gas evolved in the Reactor
shall be collected in this relay. The relay shall be provided with a test cock suitable
for a flexible pipe connection for checking its operation and taking gas sample. A
copper tube shall be connected from the gas collector to a valve located about 1200
mm above ground level to facilitate sampling while the Reactor in service. Each
device shall be provided with two potential free contacts (Plug & socket type
arrangement suitable for 2.5sq.mm control cable), one for alarm / trip on gas
accumulation and the other for tripping on sudden rise of pressure.
The Buchholz relay shall not operate during starting/ stopping of the Reactor oil
circulation pumps under any oil temperature conditions. The pipe or relay aperture
baffles shall not be used to decrease the sensitivity of the relay. The relay shall not
mal-operate for through fault conditions or be influenced by the magnetic fields
around the Reactor during the external fault conditions. Pressurised water ingress test
for Terminal Box (routine tests) shall be conducted on Buchholz relay.
All Reactors shall be provided with a dial type thermometer of around 150 mm
diameter for top oil temperature indication. It shall have adjustable, potential free
alarm and trip contacts (Plug & socket type arrangement suitable for 2.5sq.mm
control cable) besides that required for control of cooling equipment if any. A
temperature sensing element suitably located in a pocket on top oil shall be provided.
This shall be connected to the OTI by means of capillary tubing. Temperature
indicator dials shall have linear gradations to clearly read at least every 2 deg C.
Accuracy of OTI shall be ± 3.0 deg C or better or better for a temperature of 100 deg
C.
The setting of alarm and tripping contacts shall be adjustable at site. For alarm & trip
settings refer POWERGRID Pre-Commissioning Procedures and formats for
switchyard equipments (enclosed at Annexure-D).
RTD shall be provided with Pt100 temperature sensor having nominal resistance
of 100 ohms at zero degree centigrade. The Pt100 temperature sensor shall have
three wire ungrounded system. The calibration shall be as per IEC 60751-2 or
equivalent. The Pt100 sensor may be placed in the pocket containing temperature
sensing element. RTD shall include image coil, for OTI system and shall provide
dual output 4-20mA for remote OTI and SCADA system individually. The
transducer shall be installed in the Individual Marshalling Box. Any special cable
required for shielding purpose, for connection between Pt100 temperature sensor
and transducer, shall be in the scope of Contractor.
It shall be suitable for flush mounting on Employer's control panel and shall
operate on 4-20mA input available from the above transducer. Any special cable
required for shielding purpose, for connection among Individual Marshalling Box,
Common Marshalling Box/Cooler control cabinet and remote OTI control circuit,
shall be in the scope of Contractor.
A device for measuring the hot spot temperature of each winding (HV, IV and LV)
shall be provided. All Reactors shall be provided with 150 mm dial type thermometer
for winding temperature indication and shall have adjustable potential free alarm and
trip contacts (Plug & socket type arrangement suitable for 2.5sq.mm control
cable) besides that required for control of cooling equipment if any. WTI shall have
Temperature sensing element, Image coil and Auxiliary CTs, if required to match the
image coil, shall be mounted in the cooler control cabinet. Temperature indicator dials
shall have linear gradations to clearly read at least every 2 deg C. Accuracy of OTI
shall be ± 3.0 deg C or better for a temperature of 100 deg C.
The setting of alarm and tripping contacts shall be adjustable at site. For alarm & trip
settings refer POWERGRID Pre-Commissioning Procedures and formats for
switchyard equipments (enclosed at Annexure-D).
In addition to the above, the following accessories shall be provided for remote
indication of oil temperature:
It shall be suitable for flush mounting on Employer's control panel and shall
operate on 4-20mA input available from the above transducer. Any special
cable required for shielding purpose, for connection among Individual
Marshalling Box / Cooler control cabinet, Common Marshalling Box and
remote WTI control circuit, shall be in the scope of Contractor.
Only one RWTI with suitable selector switches or separate individual RWTI
shall be provided for display of temperature of winding.
8 numbers optical temperature sensors shall be fitted on each unit. The optical sensors
measuring system shall be of direct measurement non calibrating type. All the sensors
shall be brought out to separate optical sensor box mounted on Reactor tank to
facilitate measurement of temperature during service life on each unit.
Location of optical temperature sensors inside the Reactor shall be decided during
design review.
6.15.1. Two (2) earthing pads (each complete with two (2) nos. holes, M16 bolts, plain and
spring washers) suitable for connection to 75 x 12 mm galvanised steel grounding flat
shall be provided each at position close to earth of the two (2) diagonally opposite
bottom corners of the tank.
6.15.2. Two earthing terminals suitable for connection to 75 x 12 mm galvanised steel flat
shall also be provided on each individual/common marshalling box and any other
equipment mounted separately. For the tank-mounted equipment like online drying/
Online DGA/Optical sensor etc. double earthing shall be provided through the tank for
which provision shall be made on the tank and connected through two flexible
insulated copper links.
6.15.3. Equi-potential flexible copper link of suitable size at least 4 Nos. for Tank mounted
turret with tank and tank with cover and or Bell shall be provided. For other
6.16. Core
6.16.1. The core shall be constructed from high grade, non-ageing, cold rolled, super grain
oriented silicon steel laminations (HI-B or better grade).
6.16.2. The leg magnetic packets (cheeses) shall be made from state of the art low loss
electrical steel. The “Cheeses” shall be designed to minimize losses and equalize the
distribution of flux in the legs.
6.16.3. The “cheeses” shall be bonded using high temperature epoxy resins to assure that they
will remain bonded in service at the maximum temperatures that will occur in the
magnetic circuit and for the full expected life. Vacuum impregnation is preferred. The
contractor shall present data on the characteristics of the packets at the time of design
review.
6.16.4. Material with high temperature withstand capability such as ceramic/ slate spacers
shall be used to separate the packets. High temperature, mechanically stable material
shall be used between the end packets and the top and bottom yokes. Special care shall
be taken not to impede the cooling in these areas.
6.16.5. Means shall be provided to distribute the flux from the “cheeses” and the windings to
the top and bottom yokes to prevent concentrations of flux with resulting high
temperatures in the yokes.
6.16.6. The yokes shall be designed such that high temperatures resulting from unequal
distribution of the flux in the yokes will not occur.
6.16.7. The spaces between “cheeses” will be designed so that high temperatures will not
result due to fringing of flux at the oil gaps between them. The designer shall calculate
the temperatures resulting from fringing.
6.16.8. The design of the magnetic circuit shall be such as to avoid static discharges,
development of short circuit paths within itself or to the earthed clamping structure
and production of flux component at right angles to the plane of laminations which
may cause local heating.
6.17.1. The structural design shall be made so that pressure will be maintained to prevent
loosening resulting from thermal expansion and contraction during all loading cycles.
6.17.2. The design shall be made in such a way that excessive vibration does not occur in the
windings, structural supports of the windings and magnetic circuit and this will be
subjected to design review.
6.17.3. The structure shall be designed to withstand the clamping and magnetic forces. The
calculated magnetic forces will be furnished at the time of design review.
6.18.1. The winding hot spots shall be calculated using the maximum localized losses,
insulation thickness at the maximum loss positions, and the oil flow patterns in the
winding. The oil temperature rise in the windings shall be used to determine hot spots
rather than the bulk top oil temperature.
6.18.2. The hot spot temperatures and surface temperatures in the magnetic circuit shall be
calculated. The maximum allowed hot spot temperature will be 125 deg C. The
maximum allowed tank surface temperature will be 120 deg C.
6.18.3. The hot spot for all leads shall be calculated and it shall not exceed the calculated hot
spot of the windings.
6.18.4. The hot spot in the windings and magnetic circuit shall be calculated for the over
voltage conditions specified.
6.19.1. Under normal operation, the temperature of any part of the core or its support structure
in contact with oil shall not exceed 120 deg C. The temperature of these parts shall not
exceed 130 deg C under the most extreme operating circumstances.
6.19.2. Also, the most onerous temperature of any part of the core and its supporting structure
in contact with insulation or non-metal material shall not exceed the safe operating
temperature of that material. Adequate temperature margins shall be provided to
maintain long life expectancy of these materials.
6.20.1. If grounding of the core cheeses are required a separate strap shall be brought to a
terminal located in a waterproof enclosure on the tank. Separate ground leads will be
routed from the top and bottom yokes to separate terminals in the enclosure.
6.20.2. The core shall be earthed to the core clamping structure at one point only, through a
removable external link suitably located and protected to facilitate testing after
installation of the reactor. The removable links shall have adequate section to carry
ground fault current. Separate identification name plate/labels shall be provided for
the ‘Core’ and ‘Core clamp’ on the tank cover.
6.20.3. Unless otherwise approved, no core earthing connection shall be of minimum size of
80 sq.mm copper with exception of the connections inserted between laminations
which may be reduced to a cross-sectional area of 20 sq. mm tinned copper where
they are clamped between the laminations.
6.20.4. Where the core laminations are divided into sections by insulating barriers or cooling
ducts parallel to the plane of the laminations, tinned copper bridging strips shall be
inserted to maintain electrical continuity between sections.
6.21. Windings
6.21.1. The Contractor shall ensure that windings of all Reactors are made in dust proof and
conditioned atmosphere.
6.21.2. The conductors shall be of electrolytic grade copper free from scales and burrs.
6.21.3. The insulation of Reactor windings and connections shall be free from insulating
compounds which are liable to soften, ooze out, shrink or collapse and shall be non-
catalytic and chemically inactive in Reactor oil during service.
6.21.4. Coil assembly and insulating spacers shall be so arranged as to ensure free circulation
of oil and to reduce the hot spot of the winding.
6.21.5. The coils would be made up, shaped and braced to provide for expansion and
contraction due to temperature changes.
6.21.6. The conductor shall be transposed at sufficient intervals in order to minimize eddy
currents and to equalise the distribution of currents and temperature along the
winding.
6.21.7. The windings shall be designed to withstand the dielectric tests specified. The type of
winding used shall be of time tested. An analysis shall be made of the transient
voltage distribution in the windings, and the clearances used to withstand the various
voltages. Margins shall be used in recognition of manufacturing tolerances and the
fact that the system will not always be in the new factory condition.
6.21.8. The barrier insulation including spacers shall be made from high- density pre-
compressed pressboard (1.1 gm/cc minimum for load bearing and 1 to 1.3 gm/cc
minimum for non-load bearing) to minimize dimensional changes.
6.21.9. All spacers shall have rounded edges. Radially stepped spacers between winding disks
will not be accepted.
6.21.10. The conductor insulation shall be made from high-density (at least 0.75 gm/cc) paper
having high mechanical strength. The characteristics for the paper will be reviewed at
the time of design review.
6.21.11. An electrostatic shield, made from material that will withstand the mechanical forces,
will be used to shield the high voltage windings from the magnetic circuit unless
otherwise approved.
All winding insulation shall be processed to ensure that there will be no detrimental
shrinkage after assembly. All windings shall be pre-sized before being clamped.
Windings shall be provided with clamping arrangements which will distribute the
clamping forces evenly over the ends of the winding.
Full details of the winding clamping arrangements, and their adjustment in or out of
the tank together with relevant drawings and values, shall be submitted during design
review.
The mating faces of bolted connections shall be appropriately finished and prepared
for achieving good long lasting, electrically stable and effective contacts. All lugs for
crimping shall be of the correct size for the conductors. Connections shall be carefully
designed to limit hot spots due to circulating eddy currents.
6.23.1. Winding termination interfaces with bushings shall be designed to allow for repeatable
and safe connection under site conditions to ensure the integrity of the Reactor in
service.
6.23.2. The winding–end termination, insulation system and transport fixings shall be so
designed that the integrity of the insulation system generally remains intact during
repeated work in this area.
6.23.3. Allowances shall be made on the winding ends for accommodating tolerances on the
axial dimensions of the set of bushings and also for the fact that bushings may have to
be rotated to get oil level inspection gauges to face in a direction for ease of inspection
from ground level.
6.23.4. In particular, rotation or straining of insulated connections shall be avoided during the
fastening of conductor pads (or other methods) on the winding ends onto the
termination surfaces of the bushing.
6.23.5. Suitable inspection and access facilities into the tank in the bushing oil-end area shall
be provided to minimize the possibility of creating faults during the installation of
bushings.
The typical painting details for reactor main tank, pipes, conservator tank, radiator,
control cabinet/ marshalling box / oil storage tank etc. shall be as given in Annexure –
F. The proposed paint system shall generally be similar or better than this. The
quality of paint should be such that its colour does not fade during drying process and
shall be able to withstand temperature up to 120 deg C. The detailed painting
procedure shall be finalized during award of the contract.
The insulating oil shall be virgin high grade inhibited, conforming to IEC-60296 & all
parameters specified at Annexure – G, while tested at supplier's premises. The
contractor shall furnish test certificates from the supplier against the acceptance norms
Sufficient quantity of oil necessary for maintaining required oil level in case of
leakage in tank, radiators, conservator etc. till the completion of warranty period
shall be supplied.
Inhibited oil used for first filling, testing and impregnation of active parts at
manufacturer's works shall be of same type of oil (in line with IEC 60076-3) which
shall be supplied at site and shall meet parameters as per specification.
The particle analysis shall be carried out in an oil sample taken after completion of the
oil filtration at site. The procedure and interpretation shall be in accordance with the
recommendation of CIGRE report WG-12.17 - “Effect of particles on transformer
dielectric strength”.
Dummy insulation test block shall be inserted in the active part of Reactor at factory
and same shall be used to detect the volume moisture content. Before application of
vacuum and oil filling in the Reactor, it will be ensured that moisture content in the
dummy insulation test block is less than 0.5%. Measurement shall be carried out as
per IEC.
8.3.1. Procedures for site drying, oil purification, oil filling etc shall be done as per Field
Quality Plan (FQP).
8.3.2. The duration of the vacuum treatment shall be demonstrated as adequate by means of
water measurement with a cold trap or other suitable method but shall generally not be
less than 72 hours. The vacuum shall be measured on the top of the Reactor tank and
should be less than 1mbar.
8.3.3. Oil filling under vacuum at site shall be done with reactor oil at a temperature not
exceeding 65°C. Vacuum shall not be broken until the Reactor is oil filled up to the
Buchholz relay.
8.3.4. The minimum safe level of oil filling (if different from the Buchholz level) to which
the Reactor shall be oil filled under vacuum, shall be indicated in the manual.
8.3.5. The Ultra High Vacuum type oil treatment plant of suitable capacity (minimum 6000
litres per hour) suitable for treatment of oil in EHV class Reactor shall be used in
order to achieve properties of treated oil. The plant shall be capable of treatment of
new oil (as per IEC 60296 and reconditioning of used oil (as per IS: 1866/IEC: 60422
for oil in service) at rated capacity on single pass basis as follow:
The insulating oil for the Reactor shall be delivered at site generally not before 90
days from the date of commissioning, with prior information to the Employer.
Insulating oil shall be delivered to the site in returnable oil drums / flexi bag / tanker.
The oil drums / flexi bag / tanker shall be taken back without any extra cost to
Employer within generally 45 days after utilisation of oil but in any case before
contract closing. However, the spare oil shall be delivered in non-returnable drums.
The spare reactor shall be completely erected, oil filled and commissioned similar to
the other reactors and kept on the foundation after completing all necessary activities
for long term storage. Any special maintenance procedure required during long term
storage shall be clearly brought out in the instruction manual. All pre commissioning
tests on the spare Reactor similar to the unit kept in service shall be carried out by the
contractor.
Purchaser intends to replace any of the reactor unit by the completely assembled oil
filled spare reactor fitted with bushings, cooler etc by isolator switching arrangement
and without physically shifting the reactor.
In case, due to space limitation, Isolator based switching arrangement is not possible,
the completely assembled oil filled Reactor is to be shifted by manual pulling through
rail track/road from its foundation to the other location within the substation. As any
unit may be designated as the spare, all units must be prepared accordingly.
10. Bushings
10.1. Bushings shall be robust and designed for adequate cantilever strength to meet the
requirement of seismic condition, substation layout and movement along with the
spare Reactor with bushing erected and provided with proper support from one
foundation to another foundation within the substation area. The electrical and
mechanical characteristics of bushings shall be in accordance with IEC: 60137/DIN
42530. All details of the bushing shall be submitted for approval and design review.
10.2. Bushing for voltage of 800 kV shall be of porcelain / composite type and hermetically
sealed Oil filled condenser type. Neutral Bushing for voltage of 145 kV shall be of
RIP type bushing with porcelain or composite insulator. 145kV BPI/support insulator
shall be solid porcelain type.
10.4. Where current transformers are specified, the bushings shall be removable without
disturbing the current transformers.
10.6. Porcelain used in bushing manufacture shall be homogenous, free from lamination,
cavities and other flaws or imperfections that might affect the mechanical or dielectric
quality and shall be thoroughly vitrified, tough and impervious to moisture.
10.7. Polymer / composite insulator shall be seamless sheath of a silicone rubber compound.
The housing & weather sheds should have silicon content of minimum 30% by
weight. It should protect the bushing against environmental influences, external
pollution and humidity. It shall be extruded or directly moulded on the core. The
interface between the housing and the core must be uniform and without voids. The
strength of the bond shall be greater than the tearing strength of the polymer. The
manufacturer shall follow non-destructive technique (N.D.T.) to check the quality of
jointing of the housing interface with the core. The technique being followed with
detailed procedure and sampling shall be decided during finalization of MQP.
The weather sheds of the insulators shall be of alternate shed profile as per IEC 60815-
3. The weather sheds shall be vulcanized to the sheath (extrusion process) or moulded
as part of the sheath (injection moulding process) and free from imperfections. The
vulcanization for extrusion process shall be at high temperature and for injection
moulding shall be at high temperature & high pressure. Any seams / burrs protruding
axially along the insulator, resulting from the injection moulding process shall be
removed completely without causing any damage to the housing. The track resistance
of housing and shed material shall be class 1A4.5 according to IEC60587. The
strength of the weather shed to sheath interface shall be greater than the tearing
strength of the polymer. The composite insulator shall be capable of high pressure
washing.
End fittings shall be free from cracks, seams, shrinks, air holes and rough edges. End
fittings should be effectively, sealed to prevent moisture ingress, effectiveness of
sealing system must be supported by test documents. All surfaces of the metal parts
shall be perfectly smooth with the projecting points or irregularities which may cause
corona. All load bearing surfaces shall be smooth and uniform so as to distribute the
loading stresses uniformly.
The hollow silicone composite insulators shall comply with the requirements of the
IEC publications IEC 61462 and the relevant parts of IEC 62217. The design of the
composite insulators shall be tested and verified according to IEC 61462 (Type &
Routine test).
10.11. Corona shield shall be provided at 765kV Bushing terminal (Air end) to minimise
corona.
10.12. Spare Bushing shall be specially packed suitable for long storage with non-returnable
packing, the details of which shall be provided to the purchaser
10.13. The terminal marking and their physical position shall be as per IEC: 60076.
The contractor shall connect the neutrals of three (3) 1-phase shunt reactor by
overhead connection to operate in three phase banks. The neutral terminals of winding
of the three (3) single phase shunt reactors shall be connected to an overhead common
3" IPS Al tube. The neutral formation shall be such that neutral winding of single-
phase spare shunt reactors can be disconnected or connected to either of the three
phase banks unless approved otherwise. All material like Bus post insulator,
Aluminium tube, conductor, clamps & connectors, earthing materials, support
structure, hardware etc required for neutral formation and connection with neutral CT
and earthing of neutral shall be provided by contractor.
Connection arrangement of spare unit of reactor with other units shall be made by
isolator switching. Neutral formation for spare unit of reactor shall be done by manual
connection. Necessary conductors and clamps & connectors for this purpose shall be
provided by the contractor.
The contractor shall make connection arrangement as well as control scheme in such a
way that spare unit of reactor can be connected in place of faulty unit without
physically shifting it from its location. For this purpose, 765kV, and Neutral
Connections of spare unit are to be extended upto the other unit by forming auxiliary
buses and shall be supported by structure mounted bus post insulators at suitable
intervals to enable spare unit connection through flexible/rigid conductor and suitable
connector in place of existing unit to be replaced. A typical sketch of connection
arrangement is shown in the drawing enclosed at Annexure-D. However, the detail
configuration and actual sizes of various items shall be finalised during detailed
engineering and shall be subject to Employer’s approval.
All associated materials like Bus post insulators, Aluminium tube, clamps &
connectors, insulator strings, hardware, cables, support structures, required for the
above mentioned arrangement shall be provided by the contractor.
13.1. The reactor shall be designed for Oil immersed with natural cooling (ONAN)
13.2.1. Design of cooling system shall satisfy the performance requirements. The radiator
shall be of sheet steel in accordance with IS 513 and minimum thickness 1 mm. Each
radiator bank shall be provided with the following accessories:
13.3. Each radiator bank shall be detachable and shall be provided with flanged inlet and
outlet branches. Expansion joint shall be provided on top and bottom cooler pipe
connection.
13.4. The cooler pipes, support structure including radiators and its accessories shall be hot
dip galvanised or corrosion resistant paint should be applied to external surface of it.
14. Cabling
All interconnecting control and power cables between various parts of Reactor like
turret CT, MBs, Buchholz, PRD etc. shall be routed through covered cable tray or GI
conduit and shall be properly dressed. All cables shall be armoured type. Un-armoured
cables (if provided) in any circuitry, shall be through GI conduit and no part shall be
exposed. Cable terminations shall be through stud type TB and ring type lugs. Typical
Technical specification for cables is attached at Annexure-J. Contractor shall provide
type tested cables from approved sources. No type testing for cables is envisaged.
15. Valves
15.1. All valves upto and including 100 mm shall be of gun metal or of cast steel/cast iron.
Larger valves may be of gun metal or may have cast iron bodies with gun metal
fittings. They shall be of full way type with internal screw and shall open when turned
counter clock wise when facing the hand wheel.
15.2. Suitable means shall be provided for locking the valves in the open and close
positions. Provision is not required for locking individual radiator valves.
15.3. Each valve shall be provided with the indicator to show clearly the position of the
valve.
15.5. All valves in oil line shall be suitable for continuous operation with Reactor oil at 115
deg C.
15.7. Valves or other suitable means shall be provided to fix the on line DGA monitoring
system to facilitate continuous monitoring. The location & size of the same shall be
finalised during detail design review.
a) In order to restrict the supply of oil in case of a fire in Reactor, flow sensitive
valve shall be provided to isolate the conservator oil from the main tank.
b) A valve which shall be flow sensitive and shut off when the flow in the pipe is
more than the flow expected in the permissible normal operating conditions. This
valve shall be located in the piping between the conservator and the buchholz relay
and shall not affect the flow of oil from and to the conservator in normal
conditions.
c) When the flow from conservator to main tank is more than the normal operating
conditions, the valve shall shut off by itself and will have to be reset manually. It
shall be provided with valve open/close position indicator along with alarm
contact indication in control room during closing operation of valve. This valve
shall be provided with locking arrangement for normal position and oil filling /
filtration position.
d) A suitable platform / ladder shall be provided to approach the valve for manual
reset.
15.9. All valves shall be painted with a shade (preferably red or yellow distinct and different
from of main tank surface and as per the painting system and procedure specified.
15.10. All hardware used shall be hot dip galvanised / stainless steel.
16.1. Each single phase reactor unit shall be provided with Individual Marshalling Box and
Common Marshalling (for a bank of three single phase unit) Box shall be provided.
The all control cabinets shall be made of stainless steel sheet of at least 1.6 mm thick.
The degree of protection shall be at least IP: 55 for outdoor and IP: 43 for indoor in
accordance with IS: 13947/IEC: 60947.
All doors, removable covers and plates shall be gasketed all around with suitably
profiled. All gasketed surfaces shall be smooth straight and reinforced if necessary to
minimize distortion to make a tight seal. For Control cubicle / Marshalling Boxes etc.
which are outdoor type, all the sealing gaskets shall be of EPDM rubber or any better
approved quality, whereas for all indoor control cabinets, the sealing gaskets shall be
of neoprene rubber or any better approved quality. The gaskets shall be tested in
accordance with approved quality plan, IS: 1149 and IS: 3400. Ventilating Louvers, if
provided, shall have screen and filters. The screen shall be fine wire mesh of brass. All
the separately mounted cabinets and panels shall be free standing floor mounted type
16.1.1. All the contacts of various protective devices mounted on the reactor and all the
secondary terminals of the bushing CTs shall also be wired upto the terminal board in
the Individual Marshalling box. All the CT secondary terminals in the Individual
Marshalling box shall have provision for shorting to avoid CT open circuit while it is
not in use. All the necessary terminations for remote connection to Purchaser's panel
shall be wired upto the Common Marshalling box.
16.2. A space heater and cubicle lighting with ON-OFF switch shall be provided in each
panel.
16.2.1. Control and power supplies are to be given after suitable selection at Common
Marshalling Box. Necessary isolating switches and protective devices shall be
provided at suitable points as per Purchaser's approved scheme.
16.2.2. The temperature indicators shall be so mounted that the dials are about 1200 mm from
ground level. Glazed door of suitable size shall be provided for convenience of
reading.
16.2.3. All the control circuit connections from individual marshalling box and of three single
phase units of a bank including spare reactor unit to Purchasers Control panels shall be
routed through common marshalling box. Common marshalling box shall be floor
mounted and of size not less than 1600mm (front) X 650mm (depth) X 1800mm
(height).
16.2.4. Connection arrangement for spare unit shall be in such a way that spare unit of reactor
can be connected in place of faulty unit without physically shifting, and all the control,
protection, indication signals of spare unit shall also be brought in common
marshalling box of all the banks. Necessary arrangement in schematic of Common
marshalling box is required to facilitate changeover of all the signals of faulty units to
spare unit of reactor, to ensure flow of control, protection and indication signals
between Purchasers Control panels and individual units under operation (i.e. any
designated unit for bank or spare unit, if it replace any designated unit). The control
and monitoring terminations of a spare Reactor unit shall be brought to CMB. The
necessary switching arrangement through male-female plug-in TB assembly shall be
provided for replacing spare unit with any one of the faulty phase unit for monitoring
& control from CMB.
16.2.5. Common marshalling box shall have following arrangement in addition to schematic
arrangement. Details of stationed auxiliary power supply are mentioned in GTR
specification.
16.2.6. Two auxiliary power supplies, 415 volt, three phase four (4) wire shall be provided by
the Purchaser at common marshalling box. Power supply to Spare unit shall be
extended from nearest CMB only through MCCB by contractor. Suitably rated power
contractors, MCBs/MCCBs as required for entire auxiliary power supply system
including distribution to individual marshalling boxes, Online Moisture & Hydrogen
monitoring system, Online drying system and Fibre optic sensor Box etc., shall be
provided by contractor. In case auxiliary power supply requirement for is different
than station auxiliary AC supply, then all necessary converters shall be provided by
the Contractor. For each circuit separate MCBs / MCCBs shall be provided in the
16.2.7. All loads shall be fed by one of the two feeders through an electrically interlocked
automatic transfer switch housed in the common marshalling box.
16.2.8. Design features of the transfer switch shall include the following:
a) Provision for the selection of one of the feeder as normal source and other as
standby.
b) Upon failure of the normal source, the loads shall be automatically
transferred after an adjustable time delay to standby sources.
c) Indication to be provided at cooler control cabinet for failure of normal
source and for transfer to standby source and also for failure to transfer.
d) Automatic re-transfer to normal source without any intentional time delay
following re-energization of the normal source.
e) Both the transfer and the re-transfers shall be dead transfers and AC feeders
shall not be paralleled at any time.
17.1.2. It shall be possible to remove the turret mounted current transformers from the
Reactor tank without removing the tank cover. Necessary precautions shall be taken to
minimize eddy currents and local heat generated in the turret.
17.1.3. Current transformer secondary leads shall be brought out to a weatherproof terminal
box near each bushing. These terminals shall be wired out to common marshalling
box using separate cables for each core.
17.1.4. Bushing Current transformer parameters indicated in this specification are tentative
and liable to change within reasonable limits. The Contractor shall obtain Purchaser's
approval before proceeding with the design of bushing current transformers.
17.2. Technical Parameters of Bushing CTs and Neutral CTs (outdoor type) are enclosed at
Annexure – H. The CT’s used for REF protection must have the identical parameters
in order to limit the circulating current under normal condition for stability of
protection.
17.2.1. Secondary resistance and magnetising current characteristics of TPS class (protection)
(as per IEC) CT of same rating shall be identical. This is applicable for Neutral CT
(outdoor) also and shall be reviewed during detail engineering.
17.2.2. One number single phase current transformer for earth fault protection shall be
provided for each bank of reactor and shall be located in the neutral conductor
connecting common neutral point with earth.
The surge arresters shall conform in general to IEC-60099-4 except to the extent
explicitly modified in the specification.
The bidder shall offer surge arresters of gapless type without any series or shunt gap.
The surge arresters shall be of heavy duty station class type. It shall be physically
located between the neutral of 765kV shunt reactor (brought out at 145kV class
bushing) and neutral grounding reactor and shall be electrically in parallel with the
latter.
The surge arresters shall be capable of discharging over voltage occurring during
switching of unloaded transformers and reactors.
The features and constructional details of surge arresters shall be in accordance with
requirement stipulated hereunder:
18.3.1. The non linear blocks shall be of sintered metal oxide material. These shall be
provided in such a way as to obtain robust construction, with excellent electrical and
mechanical properties even after repeated operations.
18.3.2. The reference current of the arrester shall be high enough to eliminate the influence of
grading and stray capacitance on the measured reference voltage.
18.3.3. The surge arresters shall be fitted with pressure relief devices and arc diverting parts
suitable for preventing rupture of polymer housing and providing path for flow of
rated fault currents in the event of arrester failure.
18.3.4. The arresters shall incorporate anti-contamination feature to prevent arrester failure
consequent to uneven voltage gradient across the stack in the event of contamination
of the arrester housing.
18.3.5. Seals shall be provided in such a way that these are always effectively maintained
even when discharging rated lightning current.
18.3.6. Outer insulator shall be polymer / composite insulator housing. Details specification
of polymer/composite insulators are given in clause 10.7
18.3.7. The end fittings shall be made of non-magnetic and corrosion proof material.
18.3.8. The name plate shall conform to the requirement of IEC incorporating the year of
manufacture.
18.3.10. The heat treatment cycle details along with necessary quality checks used for
individual blocks along with insulation layer formed across each block to be
furnished. Metallised coating thickness for reduced resistance between adjacent discs
to be furnished along-with procedure for checking the same.
18.4.1. Each arrester shall be complete with insulating base, support structure and terminal
connector. The height of the support structure shall not be less than 2500 mm. The
structure would be made of galvanized steel generally conforming to IS: 802. The
surge arrester can also be mounted on the neutral grounding reactor in lieu of separate
support structure.
18.4.2. Self contained discharge counter, suitably enclosed for outdoor use and requiring no
auxiliary or battery supply for operation along with necessary connection, shall be
provided for each unit. The counter shall be visible through an inspection window
from ground level. The counter terminals shall be robust and of adequate size and
shall be so located that incoming and outgoing connections are made with minimum
possible bends. One no. potential free change over type contacts (rated for 220V DC)
shall be provided for monitoring of surge counter operation in substation automation
system.
18.4.3. Suitable milliammeter on each arrester with appropriate connections shall be supplied
to measure the resistor grading leakage current. The push buttons shall be mounted
such that it can be operated from ground level.
18.4.4. Discharge counter and milliammeter shall be suitable for mounting on support
structure of the arrester with minimum protection class IP 55.
18.4.5. Grading/Corona rings shall be provided on each complete arrester unit as required for
proper stress distribution.
18.5. Tests
18.5.1. The surge arresters shall conform to type tests and shall be subjected to routine tests as
per IEC-60099-4.
19. Fittings
19.1. The following fittings shall be provided with each shunt reactor and for neutral
grounding reactor (whichever are applicable) covered under this specification.
19.5. Buchholz relay double float, reed type with isolating valves on both sides, bleeding
pipe with pet cock at the end to collect gases and alarm / trip contacts.
19.8. Bushing with metal parts and gaskets to suit the termination arrangement with lead if
applicable
19.9. Winding & Oil temperature indicators for local and remote mounting.
19.10. Cover lifting eyes, reactor lifting lugs, jacking pads, towing holes and core and
winding lifting lugs.
19.12. Bottom and top filter valves with threaded male adaptors, bottom sampling valve and
drain valve.
19.15. Individual marshalling box, Common Marshalling Box, Fibre optic sensor box.
19.18. Drain valves/plugs shall be provided in order that each section of pipe work can be
drained independently
19.25. Shut off valves on both sides of Buchholz relay at accessible height.
19.30. Ladder to climb up to the Reactor tank cover with suitable locking arrangement to
prevent climbing during charged condition
19.32. Bushing CT
19.33. Ladder to climb up to the reactor tank cover with suitable locking arrangement to
prevent climbing during charged condition.
19.35. On line dissolved gases and moisture monitor (if specified in BPS)
19.38. Two earthing terminals each on shunt reactor tank, radiators & marshalling box, SA
structures etc.
19.40. All hardware used shall be hot dip galvanised / stainless steel.
19.41. The fittings listed above are only indicative and any other fittings which generally are
required for satisfactory operation of the reactors are deemed to be included.
20.1. Online Dissolved Gas (Multi-gas) and Moisture Analyser (if specified in BPS) along
with all required accessories shall be provided with each Reactor for measurement &
analysis of dissolved gases and moisture in the oil. Interpretations shall be as per IEC
60599-1999.
20.2. The equipment shall detect, measure and analyse the following gases:
20.3. The analyser should measure (not calculate) all above gases and should have 100%
sensitivity. The equipment shall be capable of transferring data to sub-station
automation system confirming to IEC 61850. Necessary interface arrangement shall
be provided by the contractor for integration with automation system. The necessary
type test report for such confirmation shall be submitted during detailed engineering.
20.4. Equipment shall have facility to give SMS alert to at least three users whenever any
fault gas violates the predefined limit.
20.5. Equipment should work on station auxiliary supply. In case other supply is required
for the equipment then suitable converter shall be included. All the necessary power
and control cables, communication cables, cable accessories as required shall be
provided by the supplier.
20.6. Online DGA shall be installed out door on Reactor in harsh ambient and noisy
condition (Electromagnetic induction, Corona, and capacitive coupling). Suitable
arrangement shall be provided to take care of vibration for tank mounting. The
equipment shall be suitable for proper operation in EHV substation (800kV)
environment where switching takes place in the EHV/HV System. The suitable
indications for power On, Alarm, Caution, normal operation etc. shall be provided on
the front panel of the equipment. The equipment shall have IP55 Stainless Steel
enclosure, suitable for 55 0C ambient temperature and EMI and EMC compatibility.
The Equipment must carry a minimum of two (2) years manufacturer’s Warranty.
20.7. The equipment shall connect to the Reactor's main body in two locations. One
Connection is for the supply of oil from the Reactor. Second connection is for the
return of the oil to the Reactor.The connecting oil lines must be of Stainless Steel rigid
pipes or flexible hoses.
20.8. The equipment shall be able to measure gas concentration and when downloaded
should immediately compare it with user selected alarm & caution level for immediate
display. The sampling rate shall be selectable as 2 or 4 or 6 or 12 hours etc. The
equipment shall have inbuilt memory to store these results for complete one year even
if sampling is done at the lowest interval.
20.9. The Equipment must have an automatic Calibration facility at fixed intervals. For
calibration if anything required including cylinder must be mounted with the
Equipment.
Accuracy + 10%
Repeatability +3% to 10% depending upon gases
Oil temperature range - 200 C to + 1200 C
External Temp. Range - 200 C to + 550 C
20.11. Software for fault indication and fault diagnostics shall include following:
Fault indication:
Fault Diagnosis:
i) Key gases
ii) Ratios (Rogers, IEC. etc)
iii) Duval’s Triangle
20.12. The equipment shall be supplied with all necessary accessories required for carrying
out DGA of oil sample complete in all respect as per the technical specification. The
following shall be also form a part of supply.
i) Software
ii) Operation Manual (2 set for every unit),
iii) Software Manual and
iv) Compact disc giving operation procedures of Maintenance Manual &
Trouble shooting instructions.
In addition to provision of air cell in conservators for sealing of the oil system against
the atmosphere, each shunt reactor shall be provided with an on line insulating oil
drying system of adequate rating with proven field performance. This system shall be
tank/cooler bank mounted and no separate foundation shall be provided. This on line
insulating oil drying system shall be
i. Designed for very slow removal of moisture that may enter the oil system
or generated during cellulose decomposition. Oil flow to the equipment
shall be controlled through pump of suitable capacity.
ii. The equipment shall display the moisture content in oil (PPM) of the inlet
and outlet oil from the drying system.
The equipment shall be supplied with Operation Manual (2 set for every unit),
Software (if any), and Compact disc giving operation procedures of Maintenance
Manual & Trouble shooting instructions.
Oil sampling bottles shall be made of stainless steel having a capacity of 1litre. Oil
Sampling bottles shall be capable of being sealed gas-tight and shall be fitted with
cocks on both ends.
The design of bottle & seal shall be such that loss of hydrogen shall not exceed 5% per
week.
The glass syringe and three way stop cock valve shall meet the following specification
(if specified in BPS):
The cylinder-Plunger fit is leak proof and shall meet the requirement of IEC-
60567.Plunger shall be individually ground and fitted to barrel for smooth movement
with no back flow. Barrel rim should be flat on both sides tom prevent rolling and
should be wide enough for convenient finger tip grip. The syringe shall be custom fit
and uniquely numbered for matching. The syringe shall be clearly marked with
graduations of 2.0 ml and 10.0 ml and shall be permanently fused for life time
legibility.
24.1. Oil storage tank shall be of minimum 20 cubic meter capacity along with complete
accessories (if specified in BPS).The oil storage tank shall be designed and fabricated
as per relevant Indian Standards e.g. IS: 803 or other internationally acceptable
standards. Reactor oil storage tanks shall be towable on pneumatic tyres and rested on
manual screw jacks of adequate quantity & size. The tank shall be cylindrical in shape
and mounted horizontally and made of mild steel plate of adequate thickness.
Diameter of the tank shall be 2.0 meter approximately. The tank shall be designed for
storage of oil at a temperature of 100°C.
Technical Specification, 765kV Shunt Reactor Page 32 of 66
C/ENGG/MODEL-SPEC/765kV SR Rev. 06
24.2. The maximum height of any part of the complete assembly of the storage tank shall
not exceed 4.0 metres above road top.
24.3. The tank shall have adequate number of jacking pad so that it can be kept on jack
while completely filled with oil. The tank shall be provided with suitable saddles so
that tank can be rested on ground after removing the pneumatic tyres.
24.4. The tank shall also be fitted with manhole, outside & inside access ladder, silica gel
breather assembly, inlet & outlet valve, oil sampling valve with suitable adopter, oil
drainage valve, air vent etc. Pulling hook on both ends of the tank shall be provided so
that the tank can be pulled from either end while completely filled with oil. The
engine capacity in horse power to pull one tank completely fitted with oil shall be
indicated. Oil level indicator shall be provided with calibration in terms of litre so that
at any time operator can have an idea of oil in the tank. Solenoid valve (Electro-
mechanically operated) with Centrifugal pump shall be provided at bottom inlet so
that pump shall be utilised both ways during oil fill up and draining. Suitable
arrangement shall also be provided to prevent overflow and drain form the tank.
24.5. The following accessories shall also form part of supply along with each Oil storage
tank.
i) Four numbers of 50NB suitable rubber hoses for Reactor oil application up to
temperature of 100°C, full vacuum and pressure up to 2.5 Kg/ cm2 with
couplers and unions each not less than 10 metre long shall be provided.
ii) Two numbers of 100NB suitable for full vacuum without collapsing and
kinking vacuum hoses with couplers and unions each not less than 10 metre
long shall also be provided.
iii) One number of digital vacuum gauge with sensor capable of reading up to
0.001 torr, operating on 240V 50Hz AC supply shall be supplied. Couplers
and unions for sensor should block oil flow in the sensor. Sensor shall be
provided with at-least 8 meter cable so as to suitably place the Vacuum gauge
at ground level.
24.6. The painting of oil storage tank and its control panel shall be as per technical
specification.
24.7. The tank shall contain a self mounted centrifugal oil pump with inlet and outlet valves,
with couplers -suitable for flexible rubber hoses and necessary switchgear for its
control. There shall be no rigid connection to the pump. The pump shall be electric
motor driven, and shall have a discharge of not less than 6.0 kl/hr. with a discharge
head of 8.0m. The pump motor and the control cabinet shall be enclosed in a cubicle
with IP-55 enclosure.
One set of hand tools of reputed make packed in a carry bag/box broadly comprising
of double ended spanners (open jaws, cranked ring, tubular with Tommy bar each of
sizes 9mm to 24mm, one set each), adjustable wrenches (8 &12 inch one set), gasket
punches (of different sizes used- one set), pliers (flat nose, round nose & side cutting
one of each type), hammer with handle (one ), files with handle (two), knife with
27.1. Inspection
27.1.2. Core
a. Sample testing of core materials for checking specific loss, bend properties,
magnetisation characteristics and thickness
b. Check on the quality of varnish if used on the stampings:
i) Measurement of thickness and hardness of varnish on stampings
ii) Solvent resistance test to check that varnish does not react in hot oil
iii) Check overall quality of varnish by sampling to ensure uniform shining
colour, no bare spots, no over burnt varnish layer and no bubbles on
varnished surface
c. Check on the amount of burrs
d. Bow check on stampings
e. Check for the overlapping of stampings. Corners of the sheet are to be part.
f. Visual and dimensional check during assembly stage
g. Check for inter-laminar insulation between core sectors before and after
pressing
27.1.4. Winding
a. Check completed reactor against approved outline drawings, provision for all
fittings, finish level etc
b. Jacking test with oil on all the assembled reactors
c. Dye penetration test shall be carried out after the jacking test
The make of all major bought out items shall be subject to Purchaser's approval. The
Contractor shall also prepare a comprehensive inspection and testing programme for
all bought out/sub-contracted items and shall submit the same to the Purchaser for
approval. Such programme shall include the following components:
a) Buchholz Relay
b) Axles and wheels
c) Winding temperature indicators for local and remote mounting
d) Oil temperature indicators
e) Bushings
f) Bushing current transformers
g) Individual Marshalling box and common marshalling box for a bank of three
1-Phase units
h) Radiators
i) Pressure relief device
The above list is not exhaustive and the Contractor shall also include other bought-out
items in his programme.
The manufacturer shall be fully equipped to perform all the required tests as specified.
Bidder shall confirm the capabilities of the proposed manufacturing plant in this
regard when submitting the bid. Any limitations shall be clearly stated in.
The contractor shall bear all additional costs related to tests which are not possible to
carry out at his own works.
The contractor shall submit an Inspection and test plan (ITP) for approval. A typical
test plan is indicated in “Annexure-B”.
All tests shall be done in line with IEC: 60076 and the test procedures as mentioned
in “Annexure-B”. Complete test report shall be submitted to purchaser after proper
scrutiny and signing on each page by the test engineer of the contractor.
1) Bushing (Type Test as per IEC:60137 including Snap back/Seismic test for
400 kV and above voltage class bushing)
2) Bus post insulators
3) Buchholz relay
4) Marshalling & common marshalling box (IP-55 test)
5) Pressure Relief device Test
6) Sudden Pressure Relay Test
7) Magnetic Oil Level gauge & Terminal Box for IP-55 degree of protection.
8) Air Cell (Flexible air separator) - Oil side coating, Air side under Coating,
Air side outer coating and coated fabric as per IS: 3400/ BS: 903/ IS: 7016
9) OTI & WTI
27.4.2. Check for proper packing and preservation of accessories like radiators, bushings,
dehydrating breather, rollers, buchholz relay, fans, control cubicle, connecting pipes,
conservator etc.
27.4.3. Check for proper provision for bracing to arrest the movement of core and winding
assembly inside the tank.
27.4.4. Gas tightness test to confirm tightness and record of dew point of gas inside the tank.
Derivation of leakage rate and ensure the adequate reserve gas capacity.
The Contractor shall carry out a detailed inspection and testing programme for field
activities covering areas right from the receipt of material stage up to commissioning
stage. An indicative programme of inspection as envisaged by the Purchaser is given
below. However, it is contractor's responsibility to draw up and carry out such a
programme duly approved by the Purchaser. Testing of oil sample at site shall be
carried out as per specification. Contractor shall follow POWERGRID Field Quality
Plan (FQP).
27.6.1. Check and record condition of each package, visible parts of the reactor etc. for any
damage.
27.6.2. Check and record the gas pressure in the reactor tank as well as in the gas cylinder.
27.6.3. Visual check for wedging of core and coils before filling up with oil and also check
conditions of core and winding in general.
27.8.5. Check for the adequate protection on the electric circuit supplying the accessories.
27.8.6. Check resistance of all windings on all steps of the tap changer. Insulation resistance
measurement for the following:
i) Control wiring
ii) Main windings
iii) Bushing current transformer
1.3. Frequency Hz 50
1.4. No of Phases 1 (SINGLE)
1.5. Service Outdoor
1.6. Duty Continuous at 800/√3kV
1.7. Permissible current unbalance among ±1%
different phases
1.8. Harmonic content in phase current The crest value of the third harmonic
component in phase current not to
exceed 3% of the crest value of
fundamental when reactor is
energised at rated voltage with
sinusoidal wave form
1.9. Range of constant current Up to 1.25 p.u. voltage (the bidder
shall furnish complete saturation
characteristics of the Reactors up to
1.5 p.u. Voltage)
1.10. Tolerance on current (i) 0 to +5% for a single phase unit
(ii) ±1% for between units
1.11. Ratio of zero sequence reactance to Between 0.9 & 1.0.
positive reactance (X0/X1)
1.12. Temperature rise over 50 deg C
Ambient Temp
O
i) Top oil measured by thermometer C 40
O
ii) Average winding measured by C 45
resistance method
O
iii) Winding hot spot C 59
O
1.13. Max. design Ambient temp C 50
1.14. Windings
i) Lightning Impulse withstand Voltage
HV kVp 1950
Neutral kVp 550
ii) Switching Impulse withstand Voltage
Clause
Description Unit Parameters
No.
2. Technical Parameters
Rated voltage from insulation kV 145
2.1. Connection Between neutral of reactor and ground
2.2. Cooling System ONAN
2.3. Frequency Hz 50
2.4. No of Phases 1 (SINGLE)
2.5. Service Outdoor
2.6. Type Dry type air core for outdoor application
2.7. Insulation Graded /uniform
2.8. Max. continuous current (rms) 20 A
240A (however the NGR shall be
designed for a current rating of 600 Amp
Rated short time current (rms)
2.9. rms short time current to ensure
(60secs.)
mechanical robustness which will be
verified during design review.
Rated impedance at rated short
2.10. As specified in section project
time and continuous current
2.11. Insulation level for winding
Lightning Impulse withstand
i)
Voltage
Line side kVp 550
Ground side kVp 550
One Minute Power Frequency
ii)
withstand Voltage
Line side kVrms 275
Ground side kVrms 275
Solidly connected between neutral of
2.12. Method of grounding
shunt reactor and earth.
Whether neutral is to be brought
2.13. Yes (through 145kV class bushing
out
2.14. Mounting of NGR Pedestal insulator
i) Type Porcelain/ Silicon rubber
ii) Minimum creepage mm 3625
1 Min. power frequency withstand kV
iii) 305
voltage rms
Lightning Impulse withstand
iv) kVp 650
Voltage
2.15. Mounting structure Non magnetic material
Note:
The reactor shall be mounted high above ground level (2.55 mtr) to allow free and safe access at
ground level for personnel.
Technical Specification, 765kV Shunt Reactor Page 42 of 66
C/ENGG/MODEL-SPEC/765kV SR Rev. 06
Annexure -B
Test Plan
• The type tested unit shall be measured in the cold and hot state.
• In other units, measurement shall be carried out in the cold state and corrected as per
factors derived from the type test.
• Measurement shall also be carried out during 2-hour excitation test.
The following details shall be recorded under the heading of losses on the test
certificate:
The insulation of the magnetic circuit and between the magnetic circuit and the core
clamping structure, including core-bolts, bands and / or buckles shall withstand the
application of a test voltage of either 2 kV ac or 3 kV dc for 60 seconds.
The insulation of core to tank, core to yoke clamp (frame) and yoke clamp (frame) to
tank shall be able to withstand a voltage of 2 kV (rms) for 1 minute. Insulation resistance
shall be minimum 2 GΩ for all cases mentioned above.
The continuity of the single-point earthing shall be verified before despatch. The results
of the works tests shall be recorded on the test certificate, and shall include the resistance
reading obtained from a measurement made between the core and core clamping
structure by means of at least 1.5 kV ac or 2 kV dc.
The test shall be done before tanking prior to dispatch. During erection, the contractor
shall repeat this measurement on arrival at site. The records of these tests shall also be
included in the manual.
The heat run type test results shall serve as a “finger print” for the other units to be
routine tested.
The temperature rises recorded by infra red shall not be more than 10°C above top oil
temperature or 15°C above the local oil temperature.
The tests shall be done for a minimum of 24 hours with saturated temperature for at least
4 hours.
Full details of the test arrangements, procedures and conditions shall be provided with the
test certificates and the following shall at least be included.
• time
• Voltage
• Current
• Total power
• Ambient temperature measured on not less than three thermometers
• Top oil temperature: and
• Cooler inlet and outlet oil temperatures.
• Infra red pictures during the heating up phases
• Record the weight of conductor in each winding, and the losses in watts per
kilogram, the ‘cold’ resistance of each winding and the simultaneous top oil
and ambient air temperatures, together with the time required for the effect to
disappear.
• Record the thermal time constant of the winding.
• Log the half–hourly readings of the parameters as for the top oil temperature
rise test.
• Provide a table of readings, after shut-down of power, giving the following
information ;
All shunt reactor tanks shall be subjected to the specified vacuum. The tank designed for
full vacuum shall be tested at an internal pressure of 3.33 KN/sq.m absolute (25 torr) for
one hour. The permanent deflection of flat plates after the vacuum has been released
shall not exceed the values specified below:
---------------------------------------------------------------------
Horizontal length of Permanent deflection
flat plate (in mm) (in mm)
---------------------------------------------------------------------
Upto and including 750 5.0
751 to 1250 6.5
1251 to 1750 8.0
1751 to 2000 9.5
2001 to 2250 11.0
2251 to 2500 12.5
2501 to 3000 16.0
above 3000 19.0
--------------------------------------------------------------------
All shunt reactor tanks of each size ,its radiator, conservator vessel and other fittings
together or separately shall be subjected to a pressure corresponding to twice the normal
head of oil or normal oil head pressure plus 35 KN/sq.m whichever is lower, measured
at the base of the tank and maintained for one hour. The permanent deflection of the flat
plate after the excess pressure has been released shall not exceed the figures specified
above for vacuum test.
All tanks and oil filled compartments shall be completely filled with air or oil of a
viscosity not greater than that of insulating oil conforming to IEC 60296 at the ambient
temperature and subjected to a pressure equal to normal head of oil plus 35 kN/sq.m (5
psi) measured at the base of the tank. This pressure shall be maintained for a period of
not less than 12 hours for oil and 1 hour for air during which no leakage shall occur.
Note: (*) indicates Sa 2 ½ as per Swedish Standard SIS 055900 of ISO 8501 Part-1.
Note:
a. The secondary excitation current of class TPS shall not be more than 4 % of rated secondary
current at 25% of knee point voltage.
b. The CT used for REF protection must have the identical parameters in order to limit the
circulating current under normal condition for stability of protection.
e. Installation Outdoor
u. Partial discharge at 1.05 continuous over voltage Not more than 50pC
1.3 At least one (1) core shall be kept as spare in each copper control cable of 4C, 5C or 7C size
whereas minimum no. of spare cores shall be two (2) for control cables of 10 core or higher
size.
1.4 The Aluminium/Copper wires used for manufacturing the cables shall be true circular in
shape before stranding and shall be uniformly good quality, free from defects. All
aluminium used in the cables shall be of H2 grade.
1.5 The fillers and inner sheath shall be of non-hygroscopic, fire retardant material, shall be
softer than insulation and outer sheath shall be suitable for the operating temperature of the
cable.
1.6 Progressive sequential marking of the length of cable in metres at every one metre shall be
provided on the outer sheath of all cables.
1.7 Strip wire armouring method (a) mentioned in Table 5, Page-6 of IS: 1554 (Part 1) – 1988
shall not be accepted for any of the cables. For control cables only round wire armouring
shall be used.
1.8 The cables shall have outer sheath of a material with an oxygen index of not less than 29
and a temperature index of not less than 250°C.
1.9 All the cables shall conform to fire resistance test as per IS: 1554 (Part - I).
1.10 The normal current rating of all PVC insulated cables shall be as per IS: 3961.
1.12 Allowable tolerance on the overall diameter of the cables shall be plus or minus 2 mm.
1.13.1 The PVC (70°C) insulated 1100V grade power cables shall be of FR type, C1 category,
conforming to IS: 1554 (Part-I) and its amendments read along with this specification and
shall be suitable for a steady conductor temperature of 70°C. The conductor shall be
stranded aluminium. The Insulation shall be extruded PVC to type-A of IS: 5831. A distinct
inner sheath shall be provided in all multi core cables. For multi core armoured cables, the
inner sheath shall be of extruded PVC. The outer sheath shall be extruded PVC to Type ST-
1 of IS: 5831 for all cables.
1.14.1 The 1100V grade control cables shall be of FR type C1 category conforming to IS: 1554
1.14.2 Cores shall be identified as per IS: 1554 (Part-1) for the cables up to five (5) cores and for
cables with more than five (5) cores the identification of cores shall be done by printing
legible Hindu Arabic Numerals on all cores as per clause 10.3 of IS : 1554 (Part - 1).
a Type and material of armour Al wire [H4 grade] Gal. Steel wire
b Direction of armouring Left hand
c Calculated diameter of cable over inner sheath 33.9 53.2
(under armour), mm
d Nominal diameter of round armour wire (minimum) 2 2.5
e Guaranteed Short circuit capacity of the armour for 45kA 45kA
0.12 sec at room temperature.
o
f DC resistance at 20 C (Ω/Km) $ 0.577
14 Outer Sheath ST-2 & FR ST-2 & FR
SN Description Parameters
1a Cable Sizes 1 c x 150 3.5 cx 3.5 cx 4 c x 16 4c x 6 2cx6
70 35
1b Manufacturer's type designation AYWaY AYFY AYFY AYFY AYWY AYWY
2 Applicable standard IS: 1554/PT-I/1988 & its referred standards
3 Rated Voltage(volts) 1100 V grade
4 Type & Category FR & FR & FR & FR & FR & FR &
C1 C1 C1 C1 C1 C1
5 Suitable for earthed or unearthed for both
system
6 Continuous current rating when 202 105 70 41 24 28
laid in air in a ambient temp. of
50oC and for maximum conductor
temp. of 70 oC of PVC Cables[
For information only]
7 Rating factors applicable to the As per IS-3961-Pt-II-67
current ratings for various
conditions of installation:
8 Short circuit Capacity
a) Short Circuit Amp. (rms)KA for 1 11.2 5.22 2.61 1.19 0.448 0.448
sec duration
b) Conductor temp. allowed for the 1600C
short circuit duty (deg C.)
9 Conductor
a) Material STRANDED ALUMINIUM
b) Grade H 2 (Electrolytic grade)
c) Cross Section area (Sq.mm.) 150 M-70 M-35 16 6 6
N-35 N-16
d) Number of wires(No.) as per Table 2 of IS 8130
e) Form of Conductor Non- shaped shaped shaped Non- Non-
compacted conductor conductor conductor compacted compacted
Stranded Stranded Stranded
circular circular circular
f) Direction of lay of stranded layers Outermost layer shall be R.H lay & opposite in successive
layer
10 Conductor resistance (DC) at 20 0.206 0.443/0 0.868/ 1.91 4.61 4.61
oC per km-maximum .868 1.91
11 Insulation
a) Composition of insulation Extruded PVC type A as per IS-5831-84
b) Nominal thickness of 2.1 1.4/1.2 1.2/1.0 1.0 1.0 1.0
insulation(mm)
c) Minimum thickness of insulation 1.79 1.16/0.9 0.98/0. 0.8 0.8 0.8
8 8
12 Inner Sheath
a) Material Extruded PVC type ST-I as per IS-5831-84
b) Calculated diameter over the laid N.A 27.6 20.4 15.7 11.6 9.6
up cores,(mm)
c) Thickness of Sheath (minimum) N.A 0.4 0.3 0.3 0.3 0.3
mm
13 Armour as per IS 3975/88
a) a) Type and material of armour Al. Wire[H4 Gal.steel Gal.steel Gal.steel Gal.steel Gal.steel
grade] strip strip strip wire wire
Item Specification
Functional 1. The instrument should be suitable for Automatic Measurement of
Requirement Electrical Breakdown Strength of Reactor oil as per relevant standards.
2. The test results should have repeatability, consistency in laboratory
condition.
Test Output 0-100 kV (Rate of rise: 0.5 to 5KV/Sec)
Accuracy ± 1 kV
Resolution 0.1 KV
Switch off Time ≤ 1ms
Display/Control LCD/Keypads.
Printer Inbuilt/External
Measurement Fully Automatic Pre-programmed/User programmed Test Sequences including
Programmes as per latest IEC & other national/international standards.
Test Lead/ One complete set of electrodes, gauge etc. compatible with the instruments
Accessories should be provided for successfully carrying out the test in POWERGRID S/S.
Additionally all the required accessories, tools, drawing, documents should be
provided for the smooth functioning of kit. Further hard carrying case (which
should be robust/ rugged enough) for ensuring proper safety of the kit during
transportation shall have to be provided.
Design/Engg. The complete equipment along with complete accessories must be
designed/engineered by Original Equipment Manufacturer.
Power Supply It shall work on input supply variations, V: 230 ±10 %, f: 50 Hz ±5 % on
standard sockets.
Operating 0 to +50 deg C
Temperature
Relative humidity Max. 90% non-condensing.
Protection/ Against short circuit, over load, transient surges etc. Also the instrument should
Control have facility of stopping automatically on power failure. Also the kit should have
facility of HV chamber interlocking as well as zero start interlocking.
Display/Control LCD/keypads.
Environment The test kit shall be compatible for EMI/EMC/Safety environment requirement
as per IEC.
Guarantee Warranty/Guarantee Period: Min 01 year from the date of successful & complete
commissioning at Powergrid sub-station.
All the materials, including accessories, cables, laptops etc. are to be covered
under warranty/guaranty period. If the kit needs to be shifted to supplier’s works
for repairs within warranty/guaranty period, suppliers will have to bear the cost
of spares, software, transportation of kit for repair at test lab/ works.
Calibration Unit shall be duly calibrated before supply and the date of calibration shall not be
Certificate older than two month from the date of supply of Kit.
Training Supplier shall have to ensure that the instrument is made user friendly. Apart
from the detailed demonstration at site, the supplier shall also have to arrange
necessary training to POWERGRID engineers.
Commissioning, Successful bidder will have to commission the instrument to the satisfaction of
handing over the POWERGRID. The instrument failed during the demonstration shall be rejected
Instrument and no repairs are allowed.
After sales service Bidder will have to submit the documentary evidence of having established
mechanism in India for prompt services.
2ZI
m 0
cp 5000
idoddnsSelOIVGV2=1
H
Coo 1400
CA 3=-
0
2J
3 cr)
3 cr)
O
m -0 O
-u
O
r— 4200
C-)
CC
2875
;11
- 1040
1040
A OHNORHO
900
900
0 O O
O
CD
ra CD
Z O
4-)
4
U)
1530 2330
(ENGG -CIVIL)
_L 1670
GM
re-0
*
APPROVED BY
(ENGG-S/S
GM
rn
--U
:ON ONIMVe=10
C/0
0
I 21
NOLVON110JOdVONVIS
z
H
STD/BR /76 5/FDN/P OWERGRID/80/110
1-10
m z
C) O
m
U)
CD
O
CD
1 1 I I I I I I 1
PREPAREDCHECKEDAPPROVED
L2
BY [
CA ---. z
0
011 0
BY
,- , --„, , 4
440
o
4,
D> U) K
BY
r– —— ,
71
FrI •Z m
.<. U) L6
—
„, 0 0
6 Z
0 (f)
---.1 Cr) • >
0") --D1 *
,5 KV TRANSFORMERS& REACTORS
DIMN.FORCONDTNSERBUSHINGS
r n 17
03
CURRENT RATING(A)(Min.)
— c) pi __
(FOR DIFF.VALUES OF
L2+5
VOLTAGE RATINGKV
-p, F
,o
(LOWER PORTION)
I.)+ a ---
-
TYPE
< "71 7:1 z ,
M F K X + 2
N) K -x--
C) ri K _,
--. ._.,, 0x .....
, 15
K .... ..-•
TITLE
)
(I) (n
-7
o
-1::)
rTi o
32x12
20000
0)
2500
2550
o
LL
528
780
800
6 (0
48
0 o u,
u, '15
P1 -9 -p.
..,, m o
CD
10500
cn
2500
o
1425
18
430
480
(A
420
77 0 x (A o _
48
0
PI Z 4=. co 0 0 u,
>
000 -T -E-A -002
0 0
—I o _o— —
24x6
3625
1250
xi
220
350
400
500
650
0
34
0 z
Fri o
o
DRG NO
77 0 -p.
0 o ni r\,)
3150
1300
cr)
300
350
300
250
Z --I o m 01
48
O Nj co
1— 0 .4=.
x
cr)
,
-"' cri Ti N)
-‹ n I
2:1
0
0
i i i I I I I i I
-----,-
PREPARE
ID
CHECKEDBY
tml
D> •-.9
Cn 0
1-3
0 ,_3
1-11
'PROVEDBY
Z \
i-1 td
tml
Z
0
'0
1-3
n
0 c-)
0 Cn ›-
-o 0
0 o ed ed r
—1 z
F) n ••
ALFIBER SENSOR
EPTUAL DRG. FOR
—I
------1 0
n 'Ci
En -,-. 1-3 't 4
0 0 0 tzi
Do
Z >.
1--, Ill cn
tml 0
it
Cl) cn •-3 .--1
CD
1-4 -
t.-, Z
— q41
)-3 0>
cn 0> ti
0 CZ
01 l't C
,-4 tt
1-C trj 1-1
17:1 tii
4
FIBERSENSOR/AT-SR 0
0 z tli
C/ENGG/STD/OPICAL
DRG NO
k cn R°
tt
1-3 Z
t'll cn 72
0 •-0
t-1
0 Cn
0-C
■
-3
G) Co
0) CABLE FOR
-o
IEC 61850 LAN (OPTICAL)
m
m co
G)
m
z
9
C)
OWNER'S SCOPE(HOWEVER, ALL SPECIALCABLE ARE IN BIDDER'S SCOPE)
(3do0s m3acile) 318V0 1:13MOd(d)
(C) CONTROL CABLE&SPACAL CABLE AS APPLICABLE(BIDDER'S SCOPE)
co
a
SOURCE-1
SOURCE-2
EGINI11M1 3?:PicIS1:10J
0
co
0 co
CABLE FOR
IEC 61850 LAN (OPTICAL)
_L r 1
CD
C)
SOURCE-1
SOURCE-2 )
0
30VAI3IN
Co
CABLE FOR
-13
IEC 61850 LAN (OPTICAL)
'SW
co
CABLE CONNECTION FOR OPERATION WITH SPARE UNIT
CONCEPTUAL DRG. FOR SHOWING POWER AND CONTROL
03
Hd—T A3100tVAN594
r 7
KING HSOdHfld HRINHIHOd
AB C1A021(10
a
C)
C) SOURCE-1
m g >g
c
•••. SOURCE-2 c
amovau
4
t.
a
C m
fa
6i IIIR
O
O
a 0,4