Documente Academic
Documente Profesional
Documente Cultură
Ground
dAAnchors
h anddAAnchored
h d
Structures
Presentation to:
Precision Alignment
Adjustable connections allow alignment to be adjusted independent of pile alignment.
Interlocking panel joints maintain alignment.
Superior Appearance
Plant manufactured.
Panel geometry easily accommodates form liners for a variety of finishes.
Other Precast Facing Architectural Finishes
Construction Sequence
Excavation Support Construction Sequence
1. Install soldier piles (by drilling or driving).
2. Excavate in safe lifts not to exceed five feet each and install lagging to 2
f t below
feet b l tieback
ti b k grade. d
3. Install tiebacks. Allow 72 hour minimum grout cure time prior to testing.
4. Test tiebacks in accordance with PTI – Recommendations for Prestressed
Rock and Soil Anchors. Lock off tiebacks at specified load.
5. Continue excavation and lagging in accordance with Step 2 above to either
2 feet below tieback g
grade or construction subgrade,
g whichever comes first.
Excavation Support Construction Sequence
Soldier Pile Installation
• Drilled and Set HP Section
• Driven HP Section
• Drilled Pipe
Lagging Installation
• Install Piles and Excavate in Safe Lifts not to Exceed 5’ in Soil.
• Install Lagging Boards on Exposed Soil Face.
• Repeat Excavation Lift and Board Installation as Required.
Tieback Installation
• Position Drill and Drill Hole for Ground Anchor.
• Insert Anchor in Drilled Hole and Tremie Grout.
• Post Grout as Required to Increase Bond Capacity.
Permanent Wall Construction Sequence (Precast)
1. Install soldier piles (drilling generally used for permanent walls).
2. Excavate in safe lifts not to exceed five feet each and install lagging to 2
f t below
feet b l tieback
ti b k grade. d
3. Install tiebacks. Allow 72 hour minimum grout cure time prior to testing.
4. Test tiebacks in accordance with PTI – Recommendations for Prestressed
Rock and Soil Anchors. Lock off tiebacks at specified load.
5. Continue excavation and lagging in accordance with Step 2 above to either
2 feet below tieback g
grade or construction subgrade,
g whichever comes first.
6. Place filter fabric over timber lagging and install concrete leveling pad.
7. Layout and attach panel connections to soldier piles.
8. Set bottom course of precast facing panels, install drain pipe, and place
drainage stone to top of precast course.
9. Install remaining precast facing panels and place drainage stone with each
corresponding lift.
Permanent Wall Construction Sequence (Precast)
Design Background
Movement
M Load Elastic Material
AL AL
0.25DL 0.25DL
AL 0.50DL
0.25DL 0.75DL
0.50DL 1.00DL
AL 1.20DL
0.25DL AL
0.50DL 0.25DL
0.75DL 0.50DL
AL 0.75DL
0.25DL 1.00DL
0.50DL 1.20DL
0.75DL 1.33DL Max Test Load (10 min hold)
1.00DL AL
Adjust to lock-off load
Acceptance Criteria
• Creep
· Shall not exceed 00.040
040 inches at the maximum Test Load during
the load hold period of 1 to 10 minutes.
· If that value is exceeded, then the load hold period shall be
extended
d d to 60 minutes
i andd the
h totall creep movement bbetween 6
and 60 minutes shall not exceed 0.080 inches.
• Movement
· Residual movement – no absolute criteria
· Minimum Apparent Free Tendon Length >= 0.80 (Lu + Lj)
· Maximum Apparent Free Tendon Length <= Lu + Lj + 0.5Lb
• Lock-Off Load
· Within 5% of designated Lock-off load as verified by lift-off.
Proof Testing
• Determines whether the anchor has sufficient load capacity.
• That the apparent
pp free tendon length
g has been satisfactorily
y
established.
• That the creep rate stabilizes within specified limits.
Performance Testing
• Determines whether the anchor has sufficient load capacity.
• That the apparent free tendon length has been satisfactorily
established.
• The magnitude of residual movement at each load increment.
• That the creep rate stabilizes within specified limits.
SR 56 Section 021 Cambria County ~ Landslide Stabilization
Johnstown, PA
SOIL NAILING
• Definitions
• Applications
pp
• Components
• Types and Facing Options
• Construction Procedures / Sequence
• Design
• N il T
Nail Testing
ti
• Case History
• Soil Nailing g uses an arrayy of grouted
g g
ground anchors or “Soil Nails” to
improve the strength characteristics of a soil mass. This improvement in
strength properties causes the soil to be self supporting and stable against
lateral movement.
• Sh t t is
Shotcrete i typically
t i ll used d as a facing
f i ini order
d tto contain
t i the
th retained
t i d soil.
il
• Like Tieback Wall construction, Soil Nailing is generally performed from the
top down and as such offers many of the advantages that Tieback Wall
construction does in addition to others
others.
• Soil nailing does not require the installation of vertical pile elements nor
does it require toe embedment. Because of this, it can be more economical
than Tieback Walls in situations where it is appropriate.
• Because of the way in which Soil Nailing is installed, it is more sensitive to
site soil conditions than Tieback Walls and may not be appropriate under
certain circumstances.
Applications
• Permanent Earth Retention
p
• Temporary y Excavation Support
pp
• Slope Stabilization
• Repair or Rehabilitation of Existing Retaining Walls
Components
p
1. Shotcrete Facing System
2. Soil Nails
3. Permanent Facing System (if required)
Types
• Temporary
p y Excavation Support
pp
• Permanent Earth Retention w/ CIP or Shotcrete
• Permanent Earth retention w/ Segmental Precast Facing
Design Considerations
Because Soil Nailing is primarily a form of ground improvement, it is generally looked at in
terms of soil-structure interaction as opposed to being designed strictly as a force resisting
structure. Therefore,
Th f the
h d design
i off a soilil nailing
ili system iis approached
h d as a slope
l or soilil
mass stability problem.
There are a number of methodologies used for the analysis and design of Soil Nailing
systems.
- Two part wedge limit equilibrium analysis – The Krantz Method
- University of California Davis limit equilibrium model – The Davis Method
- Modified Davis Method
- Log-spiral
L i l surface
f iincluding
l di b bending
di stiffness
tiff – The
Th Ki
Kinematical
ti l M
Method
th d
- Methods outlined in FHWA Research Projects – Slope Stability / Soil-Structure Interaction
SOFTWARE
- GoldNAIL by Golder Associates (Circular Slip Circles)
- SNAIL by Caltrans (Bi-Linear Wedge Analysis)
- General Slope Stability Programs modified to consider the effects of Soil Nails
Similar results are obtained from all of these methods for normal design conditions that are
vertical walls without slope surcharge. Some of the software on the market (i.e. GoldNAIL)
tends to be quite conservative in terms of nail lengths and nail bond stresses required.
Design Guidelines and Specifications
The FHWA took the lead in the 1990’s in developing design guidelines for Soil Nail Walls
through a number of Demonstration Projects.
In 1996, FHWA produced the Manual for Design and Construction Monitoring of Soil Nail
Walls with Golder Associates based on Demonstration Project 103. This document
introduced the program GoldNAIL for the design of soil nail walls. GoldNAIL remains one of
two dominant computer programs for soil nail wall design.
In 2003, FHWA superseded the previous manual with Geotechnical Engineering Circular 7
– Soil Nail Walls. This document was developed by GeoSyntec Consultants and included
CalTrans SNAIL in the software lineup. There is considerable debate in the industry
regarding
di theth nailil testing
t ti procedures
d included
i l d d iin GEC
GEC-77 and
d requests
t hhave bbeen maded tto
change those requirements. It is recommended to use the testing rpocedures included in
the 1996 manual.
Later in 2008, it is expected that the Deep Foundations Institute will publish its Guide
Specification for Temporary and Permanent Soil Nail Walls that will include provisions for
using hollow bar (self drilling) soil nails. This specification was developed by the DFI
Tiebacks and Soil Nailing Committee with input from consultants and design-builders
throughout the United States. It is more of an industry consensus document than the
previous specifications included in the FHWA publications.
Soil Nail Testing
=
Equipment
Use essentially the same or similar equipment used for installation of
drilled and grouted ground anchors.
Typical Capacity Ranges
• Over 500 Tons in rock
• 20 to 200 Tons in soil ((settlement more significant)
g )
• In rock, structural capacity often governs
• Most micropile lengths are less than 100 feet
• Buckling is typically not an issue
• Cost range from $50 to $200 / LF
Applications
• Foundation Piles
pp through
• Foundation Support g Sinkholes or Difficult Soils
• Foundation Underpinning
• Slope Stabilization
• Earth Retention (A-Frame & Reticulated Structures)
Design and Construction Specifications
• 1997 FHWA Micropile Guidelines
p Guide Specification
• 2003 DFI Micropile p
• 2005 FHWA / NHI Micropile Reference Manual
• 2006 International Building Code
• 2007 AASHTO LRFD Design Specification
• Forthcoming AASHTO Construction Specification
• Imposed Limitations
– FHWA Compression: Fy = 87 ksi max (strain compatibility /)
– DFI Compression: Fy = 87 ksi max (strain compatibility /)
– IBC Compression: Fy = 80 ksi max
– IBC Compression: 0.40FyAb >= 0.40Pa
Testing
• Generally based on ASTM D1143 Quick Test
• The older FHWA specifications prescribed testing to 2.5 X Service
Design Load
• Newer publications recommend 2.0 X DL. Terratech recommends
2.0 DL in most cases.
• T
Tension
i ttesting
ti is
i generally
ll considered
id d tto bbe conservative
ti
compared to compression testing because it neglects any end
bearing and is often more economical for checking capacity.
However tension test results will not give representative movement
results for compression case.
• Compression testing requires anchors to hold down testing
apparatus adding to cost but gives representative results for
compression loading.
• Some proposed testing procedures incorporate anchor testing
procedures (cycles) but AASHTO is leaning toward testing just like
other foundation piles.
Testing
• 1000k Maximum Test Load, Berryville, VA (0.5” total movement)
General Q & A
THANK YOU
for Your Time and Attention