WHITE NILE PETROLEUM OPERATING DOCUMENT NO:

COMPANY LTD QA-PL-002

OGP TECHNICAL SERVICES SDN BHD


SUDAPET LTD
Sudapet Ltd.

THAR JATH DEVELOPMENT PROJECT

PROJECT EXECUTION & QUALITY PLAN

REVISION RECORD

REV NO. REVISION DESCRIPTION DATE OF ISSUE

00 ISSUED FOR PMC IMPLEMENTATION 5/1/2004

Review Approval
REV
NO Origin.
Engineer- Procure- Construc- Commiss-
Contract QA HSE
Project PROJECT
ing ment tion ioning Control MANAGER
CONSULTANT

00

CHECKED BY APPROVED BY
OWNER

DATE: DATE:
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 2 of 34

RECORD OF CHANGE
DATE OF PAGE PAGE
REVISION
AMENDMENT NUMBER NUMBER REASON FOR CHANGE
NO.
OR RE-ISSUE ISSUED REPLACED
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 3 of 34

TABLE OF CONTENT

1.0PURPOSE AND SCOPE................................................................... ..........................5


2.0OBJECTIVE............................................................................................................ .....5
3.0DEFINITIONS.................................................................................................. ............5
4.0REFERENCE............................................................................... ...............................5
5.0PROJECT DESCRIPTION....................................................................................... ....6
6.0SCOPE OF WORK ..................................................................................... ................6
7.0PROJECT ORGANISATION.......................................................................... ..............6
8.0EXECUTION STAGES............................................................................................... ..6
8.1ENGINEERING..........................................................................................................7
8.1.1General.................................................................................................................7
8.1.2Functional Objectives...........................................................................................7
8.1.3Engineering Practices ..........................................................................................7
8.1.4Resources.............................................................................................................9
8.1.5Sequence Of Activities.........................................................................................9
8.2PROCUREMENT AND MATERIALS MANAGEMENT......................................10
8.2.1General...............................................................................................................10
8.2.2Functional Objectives.........................................................................................10
8.2.3Management Practices........................................................................................11
8.2.4Resources ..........................................................................................................12
8.2.5Sequence Of Activities.......................................................................................12
8.3CONSTRUCTION....................................................................................................14
8.3.1General ..............................................................................................................14
8.3.2Functional Objectives ........................................................................................14
8.3.3Construction Management Practices .................................................................14
8.3.4Resources ..........................................................................................................16
8.3.5Sequence Of Activities ......................................................................................17
8.4COMMISSIONING..................................................................................................17
8.4.1General...............................................................................................................17
8.4.2Functional Objectives ........................................................................................17
8.4.3Commissioning Management Practices ............................................................18
8.4.4Resources ..........................................................................................................19
8.4.5Sequence Of Activities ......................................................................................19
8.5PROJECT PLANNING & CONTROL.....................................................................19
8.5.1General ..............................................................................................................19
8.5.2Functional Objectives ........................................................................................19
8.5.3Work Scope Definition ......................................................................................20
8.5.4Work Breakdown Structure (WBS)....................................................................20
8.5.5Time, Planning And Scheduling ........................................................................20
8.6COST ESTIMATING AND BUDGETTING............................................................23
8.6.1Project Capital Cost Estimation.........................................................................23
8.6.2CONSULTANT’s Project Operating Budget.....................................................23
8.7QUALITY MANAGEMENT ..................................................................................24
8.7.1General ..............................................................................................................24
8.7.2The Process Approach........................................................................................24
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 4 of 34

TABLE OF CONTENT

8.7.3QMS Program....................................................................................................24
8.8HEALTH, SAFETY & ENVIRONMENT (HSE).....................................................27
8.8.1General...............................................................................................................27
8.8.2HSE Objectives..................................................................................................27
8.8.3HSE Culture.......................................................................................................27
8.8.4Organisation.......................................................................................................28
8.8.5HSE Committee Organisation............................................................................29
8.8.6Implementation Strategy....................................................................................29
8.9DOCUMENT MANAGEMENT..............................................................................30
8.9.1Hierarchy of Document......................................................................................31
8.9.2Responsibility for Document and Records control ...........................................31
8.9.3Project Final Documentation .............................................................................32
8.10PROJECT COMPLETION MANAGEMENT.......................................................32
8.10.1Mechanical Completion...................................................................................32
8.10.2Initial Acceptance.............................................................................................33
8.10.3Final Acceptance..............................................................................................33
8.11CONSULTANT - OWNER INTERFACE..............................................................33
8.11.1Project Progress Meetings................................................................................33
8.11.2Meetings with OWNER...................................................................................33
8.11.3Meetings with CONTRACTOR.......................................................................33
8.11.4Monthly Status Report......................................................................................33
8.11.5Official Correspondences.................................................................................34
8.11.6Unofficial Daily Communication.....................................................................34
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 5 of 34

1.0 PURPOSE AND SCOPE

This Project Execution and Quality Plan shall generally detail the plan and
strategies that CONSULTANT shall undertake in performing CONSULTANT’s
scope of works as Project management CONSULTANT for Thar Jath
Development Project.

2.0 OBJECTIVE

The main objective of this plan is to inform the OWNER on PMC’s execution plan
as well as to create awareness among PMC staff on project execution strategies
and implementation.

3.0 DEFINITIONS

PMC Project Management CONSULTANT – OGP and Sudapet

OWNER White Nile Petroleum Operating Company

EPCC Engineering, Procurement, Construction and Commissioning

PCC Procurement, Construction and Commissioning

PIM Project Implementation Manual

Monitoring To keep track systematically with a target to collecting information.

Verification To confirm by examination and objective evidence

Materials For this project the term materials includes any material
processed, unprocessed, assembled or fabricated into the
equipment or other various devices that may be purchased for the
project. The term does not include services purchased in support
of the project.

WBS Work Breakdown Structure

Critical Path A series of activities, which are the longest path in the Project or
with the minimum float.

4.0 REFERENCE

Project Management Consultancy Services Proposal Document with WNPOC


DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 6 of 34

5.0 PROJECT DESCRIPTION

Block 5A is located onshore in southern Sudan approximately 950 km south of


Khartoum. Block 5A is within the Muglad Basin which has a number of both
existing and planned new developments and covers an area of approximately 7.4
million acres. Contract area for Block 5A is 20,917 sq.km.

Raw crude oil from Thar Jath and Mala fields will be collected by buried flowlines
and manifold systems leading to the Central Processing Facilities (CPF), where
crude oil will be treated for water removal and stabilization and exported through
a 173 km pipeline to the existing Heglig Pump Station # 1 for onward export of
the crude oil to Port Sudan.

In general, Block 5A Oil Development Project comprises the following facilities:

Package 1A – Accommodation Complex

Package 1B - Rubkona Bridge

Package 2 – Central Processing Facilities (CPF)

Package 3 – Field Surface Facilities (FSF)

Package 4 – Export Pipeline

Package 5 – Central Power Plant

6.0 SCOPE OF WORK

Details of scope of work for PMC shall be referred to PMC Proposal Document.

7.0 PROJECT ORGANISATION

The description of the roles, responsibilities and qualifications required of certain


key individuals is given in Attachment 1.

8.0 EXECUTION STAGES

As per the scope of work stated in the proposal agreement, the execution plan is
broken down into the following disciplines:

.a Engineering

.b Procurement

.c Construction & Pre-commissioning

.d Commissioning
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 7 of 34

.e Project Planning and Control

.f Quality Management

.g Health, Safety, and Environment

.h Document Management

.i Final Handover

8.1 ENGINEERING

8.1.1 General

This plan describes and establishes OGP’s engineering practices,


resources, and sequence of activities needed to meet project
management consulting requirements as described in the
CONSULTANT’s PMC contract.

8.1.2 Functional Objectives

To ensure successful delivery of CONSULTANT’s engineering services


that meet project needs, established requirements and OWNER
expectations in terms of time, cost, and quality for the scope of works
where engineering services conducted by PMC.

To assure OWNER that the CONTRACTORs engineering related work


and products are in compliance with the requirement stated in
respective contracts in terms of time, cost, and quality.

To closely work with other groups within the PMC organization to meet
project targets i.e. prompt feedback to procurement, construction and
commissioning groups on technical queries, prompt reaction against
quality assurance non-compliance and potential non-compliance.

8.1.2.i) Quality Indicator and Standards

Time - Engineering deliverables completed as per planned


schedule.

Cost - Rework cost not exceeding 1% of the contract value.

NCR – No recurrence of NCR’s of the same nature.

8.1.3 Engineering Practices

The following practices are appropriate to OGP engineering activities


during the project executions.
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 8 of 34

Organization

This project shall be staffed by qualified engineers as needed for


effective monitoring, assessment, and verification of engineering
requirement.

Responsibility and Authority

The engineering manager is responsible to ensure this plan is carried


out. Specific engineering responsibility, authority and interrelation of
those who monitor, assess or verify performance or results are defined
in appropriate procedures or instructions.

Resources

The engineering manager shall identify the required resources and


assign trained personnel to monitor and verify CONTRACTOR
performance of engineering works.

Monitoring and Verification

Monitoring and verification activities to be undertaken are addressed in


the procedure Monitoring and Verification of Engineering by OTHERS,
EN-PR-001.

Design Management Plan

For design that is under CONSULTANT’s responsibility, Package 1A and


Package 1B, CONSULTANT shall monitor and verify the changes
required and updates the document as appropriate. CONSULTANT’s
field engineering services shall be deployed to manage the interface
between engineering and procurement/construction/commissioning
CONTRACTOR. The engineering manager shall ensure that the design
management plan meeting requirement stated in the Quality Control of
Design Activities EN-PR-002.

For design which is under CONTRACTOR’s responsibility, Package 2,


Package 3, Package 4, and Package 5, the CONSULTANT’s
Engineering Group shall monitor and verify the CONTRACTOR’s design
WORKS are developed and implemented meeting the contract
requirement. Thereafter, the CONSULTANT’s Engineering Group shall
monitor and verify that CONTRACTOR’s performance and results
remained compliance with the approved plan.

Design Control

The CONSULTANT’s Engineering Group shall monitor and verify that


design control is established and practiced by both CONSULTANT’s
engineers and EPCC CONTRACTORs’ engineers.

Document and Data Control

The CONSULTANT’s Engineering Group shall achieve and maintain


document and data control as required by procedure Document Control,
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 9 of 34

QA-PR-001. The group shall also monitor and verify that the required
control in managing document and data are achieved and maintained
by CONTRACTORs.

Procurement

The CONSULTANT engineering group shall monitor and verify EPCC


CONTRACTOR’s procurement activities including reviewing and
recommending approval of evaluation process prior to CONTRACTOR
placing a purchase order or requisition.

8.1.4 Resources

The resources needed to manage the engineering group during this


project are for the most part related to monitoring and verification of
CONTRACTOR activities. To accomplish this task requires:

)a Trained technical staff with appropriate skills.

)b Organizational Freedom and Authority of all verification personnel is


established.

)c Time (man-hours) to accomplish the work

OGP has estimated the skills and man-hours needed and included
these factors in PMC contract agreement. Skills are described in
appropriate job descriptions and assignment addressed in this
document. Man-hours are constrained by the terms expressed in PMC
contract. Should substantial changes in the scope of work occur the
man-hour requirements might require adjustment and such must be
included in any proposed change adjusting the scope of work.

8.1.5 Sequence Of Activities

Activities to be performed by the engineering functions shall be


integrated into project schedules. The event/activities listed below shall
be scheduled and accomplished during the project phase indicated.

PHASE 1 - Bid Evaluation

a) Technical evaluation criteria

b) Commercial evaluation criteria

c) Preparation of Tender Estimates

d) Clarification of Issues raised by bidders

e) Technical evaluation of PCC and EPCC bids

f) Support of commercial bid evaluation


DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 10 of 34

PHASE 2 - Detailed Engineering and Procurement

a) Monitor and verify EPCC CONTRACTOR’s engineering


activities/performance

b) Review and approve PCC CONTRACTOR’s shop drawings

c) Review and recommend actions regarding technical document


submitted by EPCC CONTRACTOR.

d) Review and recommend actions regarding proposed technical


changes.

e) Provide technical information to other functional groups.

f) Ensure execution of HAZOP studies by EPCC CONTRACTOR

g) Monitor and report engineering related construction matters and


schedule status or progress

8.2 PROCUREMENT AND MATERIALS MANAGEMENT

8.2.1 General

This plan describes the Management Practices, Resources, and


Sequence of Activities to be accomplished by CONSULTANT’s
procurement and materials management functions as per the
requirement of PMC contract. Those activities of the overall project
management plan that determine the objectives and responsibilities
appropriate to the functions of specifying, purchasing, handling, storage,
packaging, preservation and delivery of materials to be included into the
completed work

8.2.2 Functional Objectives

To assure OWNER that procurement and materials related activities are


in compliance with the stated requirement and the materials procured by
the CONTRACTOR to meet established requirement for time, cost, and
quality.

8.2.2.i) Quality Indicator and Standards

Time – Procured materials delivered at site as per planned


schedule.

Cost - Rework cost not exceeding 1% of the contract value.

NCR – No recurrence of NCR’s of the same nature.


DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 11 of 34

8.2.3 Management Practices

These practices are appropriate to CONSULTANT’s procurement and


materials management activities during this project.

Organization

This project shall be staffed by qualified procurement and materials


management specialist as needed for effective monitoring and
verification of the CONTRACTOR’s procurement and material activities,
including monitoring and verification of SUPPLIER’s quality.

Responsibility and Authority

The Procurement & Materials Function Manager is responsible to


ensure this plan is carried out. Specific responsibilities, authority and
interrelation of those who monitor, assess or verify performance or
results are defined in appropriate Project Procedures. Overall Project
responsibility and relationships are addressed in Project Execution Plan
and authority in individual job descriptions.

Resources

The Procurement & Materials Functions Manager shall identify resource


requirements, provide needed resources and assign trained personnel
to monitor and verify CONTRACTOR’s performance including the
quality of materials procured by the CONTRACTOR.

Monitoring and Verification

Monitoring and verification activities to be undertaken are addressed in


the procedure Monitoring and Verification of Procurement by OTHERS,
PO-PR-001.

The Procurement & Materials Functions verification activities shall be


defined and documented in appropriate Project Procedure and Work
Instruction.

Procurement Plan

The Procurement & Materials Functions shall monitor and verify the
CONTRACTOR has developed and implemented a Procurement Plan,
which conforms to appropriate contract requirements. Thereafter, the
Procurement & Materials Functions shall monitor and verify the
CONTRACTOR performance complies with the approved plan. The
procurement plan shall address procedures for purchase specifications
and purchasing. The plan shall also provide appropriate
procedures/instructions for handling, storage, preservation and delivery
of materials.

Document and Data Control

The Procurement & Materials Functions shall achieve and maintain


document and data control as required by Project Procedures and Work
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 12 of 34

Instructions. The function shall also monitor and verify that the required
VENDOR and SUB-CONTRACTOR provided document and data
control is achieved and maintained in compliance with the
CONTRACTOR’s procedures as approved by OWNER.

8.2.4 Resources

The resources needed to manage the Procurement & Materials


Function during this project are for the most part related to monitoring
and verification of CONTRACTOR’s activities. To accomplish these
tasks effectively requires:

a) Trained Technical Staff with skills appropriate to the specific


activities.

b) Organizational Freedom and Authority of all verification personnel


must be clearly established.

c) Time (man-hour) to accomplish the work.

CONSULTANT has estimated the skills and man-hour needed and


included these factors in the PMC contract agreement. Skills are
described in appropriate job descriptions and assignment address in
Project Plans, Procedures, Work Instructions, etc. Man-hours are
constrained by the term expressed in the PMC contract. Should
substantial changes in the scope of work occur the man hour
requirements may require adjustment and such must be included in any
proposed change adjusting the scope of work.

8.2.5 Sequence Of Activities

Activities to be performed by the Procurement & Materials Functions


shall be integrated into the project schedule. The procurement and
materials management activities listed below shall be scheduled and
carried out during Detailed Engineering and Procurement.

a) Monitor and verify equipment and major purchases.

b) Coordinate Engineering review of Comprehensive Technical


Evaluations submitted by the CONTRACTOR.

c) Coordinate with and assist the Quality Assurance Function to carry


out;

• Review and recommend approval of procedures for inspection,


expediting, and quality assurance of material at VENDORs
shop.

• Engage third party inspection and expediting agencies.

• Review or Audit of VENDOR quality assurance activities are


carried out as approved by CONSULTANT.
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 13 of 34

• Monitor and verify that CONTRACTOR’s SUPPLIERs quality is


adequate to meet stated requirements.

d) Ensure that Comprehensive Technical Evaluations are approved


prior to CONTRACTOR placing orders.

e) Monitor and advise OWNER on the CONTRACTOR;

• maximum use of Malaysian resources and SUPPLIERs of


materials and equipment.

• appointment of VENDORs and SUB-CONTRACTOR.

)f Perform the following tasks and advise OWNER on the


CONTRACTOR compliance with approved standards, specifications,
and schedules.

• Monitor and verify procurement activities.

• Review proposed changes in VENDORs and recommended to


OWNER.

• Ensure CONTRACTOR is carrying out expediting when


necessary.

• Report and recommend actions to correct ANY change that will


affect schedule or quality.

• Assist OWNER’s Operations with spare parts management.

• Provide assistance with import tax exemptions and customs


clearance.

• If required assist OWNER with direct procurement of items


operation.

• Monitor and verify that the CONTRACTOR adheres to all


requirements imposed by authorities.

• Ensure that ownership and title of purchased items is vested in


OWNER no later than their arrival to site.

• Report to OWNER monthly on procurement schedule and


quality

)g Coordinate with the Project Controls Function to carry out

• Review of Procurement Schedule compatibility with Project


Schedule.
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 14 of 34

• Analyses of quoted delivery dates for compatibility, schedule


adherence, and ability to meet the construction schedule.

)h Coordinate with the Engineering Function to carry out

• Review of comprehensive technical evaluations and


recommend to OWNER.

• Witness shop test of equipment.

• Identifying long-term spares, consumable spares, lubricants


and lab equipment.

)i Coordinate and assist Construction and Commissioning to

• Monitor and verify that goods received at site are inspected,


identified and catalogued, properly stored and maintained by
the CONTRACTOR.

• Ensure adequacy of spare parts and process consumable


items are purchased for commissioning.

8.3 CONSTRUCTION

8.3.1 General

This section describes and establishes CONSULTANT’s Construction


Management practises, resources and sequence of activities needed to
meet project management consulting requirements as described in the
PMC Contract.

8.3.2 Functional Objectives

To monitor and verify that the project is built in accordance to the


schedule project standards, specifications, and other requirements in
EPCC contract agreement and advise OWNER on the performance of
EPCC CONTRACTOR.

8.3.2.i) Quality Indicator and Standards

Time – Construction progressed as per planned schedule.

Cost - Rework cost not exceeding 1% of the contract value.

NCR – No recurrence of NCR’s of the same nature.

8.3.3 Construction Management Practices

These practices are appropriate to CONSULTANT’s construction


management activities during this project.
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 15 of 34

Organization

Qualified personnel as needed for effective monitoring, assessment,


and advising OWNER on matters related to project management should
staff this project. Functional organization charts for project phases are to
be issued by Project Manager initially and thereafter when changes are
made.
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 16 of 34

Responsibility and Authority

The Project Manager is to ensure this Plan is carried out.

Resources

The Project Manager shall identify resources requirements, provide


needed resources as agreed by OWNER and assigned trained
personnel to monitor and verify CONTRACTOR’s performance of
construction work.

Monitoring and Verification

Monitoring and verification activities to be undertaken are addressed in


the procedure Monitoring and Verification of Construction by OTHERS,
CO-PR-001.

Verification by qualified and trained engineers is the primary means, by


which CONSULTANT measures and assesses performance and results.
Construction verification activities shall be documented in appropriate
project surveillance format.

Quality Plan

CONTRACTOR shall submit a detail Quality Plan for the construction


phase for approval by OWNER or OWNER’s Representatives. This Plan
shall address inspections, tests and other quality related activities to be
carried out by the CONTRACTOR. After OWNER approval of the
Quality Plan, CONSULTANT shall monitor and verify the
CONTRACTOR’s compliance to the approved Quality Plan.

Document and Data Control

The Construction Function shall achieve and maintained document and


data control as required by project procedures. The function shall also
monitor and verify that required documents and data control is achieved
and maintained by CONTRACTOR.

8.3.4 Resources

The resources needed to monitor and advise OWNER on construction


matters during this project are related to monitoring and verification of
CONTRACTOR activities. To accomplish these tasks effectively
requires:

a) Trained technical staff with skills appropriate to specific activities.

b) Organization freedom and authority of all verification personnel must


be clearly established.

c) Time (man-hour) to accomplish the work.

CONSULTANT has estimated the skills and man-hours needed and


included these factors in the PMC contract agreement. Skills are
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 17 of 34

described in appropriate job description and assignment addressed in


Project Plan, Procedures, Work Instruction, etc.

For site staff a fixed daily charge rate shall be applied. Estimate duration
of each site staff will be provided.

Man-hours are constrained by the term expressed in the PMC


CONTRACT. Should substantial changes in the scope of work occur, the
man hour requirement may require adjustment and such must be
included in any proposed change adjusting the scope of work.

8.3.5 Sequence Of Activities

Activities to be carried out by the Construction function and appropriate


phases of the WORK i.e. Base Work and Optional Work are describe in
the PMC scope of work and include the following areas of activity in
Engineering, Procurement, Construction and Commissioning.

a) Monitor and verify CONTRACTORs’ construction and quality


activities as described in the PMC contract.

b) Review and recommend action regarding plans and procedures


submitted by the EPCC CONTRACTOR. When approved, monitor
and verify CONTRACTOR compliance with these documents.

c) Review and recommend actions regarding proposed changes.

d) Monitor and report construction related cost and schedule


status/progress.

e) Support the Commissioning and Operation Functions as needed.

f) Prepare a construction closeout report.

8.4 COMMISSIONING

8.4.1 General

This section describes and establishes CONSULTANT’s commissioning


management practices; resources and sequence of activities need to
meet project management consulting as described in the PMC contract.

8.4.2 Functional Objectives

To monitor and verify CONTRACTOR’s commissioning activities in order


to advise OWNER that these activities are being implemented
incompliance with safety and environmental requirements, schedules,
approved procedures and other requirements of the contract
agreement.

8.4.2.i) Quality Indicator and Standards

Time – Commissioning progressed as per planned schedule.


DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 18 of 34

Cost - Rework cost not exceeding 1% of the contract value.

NCR – No recurrence of NCR’s of the same nature.

8.4.3 Commissioning Management Practices


These practices are appropriate to CONSULTANT commissioning
management activities during this project.

Organization

This project shall be staffed qualified specialists as needed for effective


monitoring, assessment and advising OWNER on matters related to
project Commissioning Manager initially and thereafter when changes
are made.

Responsibility and Authority

The Commissioning Function Manager is responsible to ensure this plan


is carried out. Specific responsibilities, authority and interrelation of
those who monitor, assess or verify performance or results are defined
in appropriate Project Procedures or Work Instructions. Overall Project
responsibility and relationships including the authority of each individual
i.e. job descriptions are addressed in Attachment 1.

Monitoring and Verification

Monitoring and verification activities to be undertaken are addressed in


the procedure Monitoring and Verification of Commissioning by
OTHERS, CM-PR-001.

Verification by qualified and trained specialist and Engineer is the


primary means by which CONSULTANT measures and assesses,
performance and results. Commissioning verification activities shall be
defined and documented in appropriate project procedure and work
instruction.

Commissioning Plan and Procedures

The Commissioning Function shall monitor and verify that the


CONTRACTOR has developed comprehensive written and schematic
procedures, which include start-up and shutdown procedures,
performance test and turnover procedures. These documents require
OWNER comment and approval. The commissioning function shall
monitor and verify that the CONTRACTOR’s performance and results
remain in compliance with these documents.

Document and Data Control

The commissioning functions shall achieve and maintain document and


data control as required by Project Procedures and Work Instructions.
The function shall also monitor and verify that required document and
data control is achieved and maintained by the CONTRACTOR. The
requirements, activities, and responsibilities appropriate to document
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 19 of 34

and data control are address in procedure Document Control QA-PR-


01.

8.4.4 Resources

The Commissioning Manager shall identify resource requirements,


provide needed resources and assign trained personnel to monitor and
verify CONTRACTOR’s performance of the commissioning work. The
resources needed to monitor and advise OWNER on commissioning
matters during the commissioning phase of this project are for the most
part related to monitoring and verification of CONTRACTOR’s activities.
To accomplish these tasks effectively requires trained technical staff
with skills appropriate to the specific activities.

Time (man-hour) to accomplish the work. CONSULTANT has estimated


the skills and man-hour needed and included these factors in the PMC
contract agreement. Skills are described in appropriate job descriptions
and assignment address in project plans, procedures, work instructions,
etc. Man-hours are constrained by the term expressed in the PMC
contract. Should substantial changes in the scope of work occur the
man hour requirements may require adjustment and such must be
included in any proposed change adjusting the scope of work.

8.4.5 Sequence Of Activities

The CONTRACTOR shall prepare a detailed schedule for the


commissioning time frame together with a VENDOR support schedule.
Both of these documents are too reviewed and approved by OWNER.

8.5 PROJECT PLANNING & CONTROL

8.5.1 General

This section shall provide the plan and strategies in Planning and
Scheduling of works in this project. This procedure covers the initial
activities during the Planning phase of the Project.

8.5.2 Functional Objectives

Project Planning and Control activities is aimed at monitoring and


verifying overall project progress in terms of time and cost to ensure
compliance to master schedule and budgeted cost.

8.5.2.i) Quality Indicator and Standards

Time – Project progress meets the planned completion dates


for phases in engineering, procurement, construction and
commissioning.

Cost - Overall cost not exceeding 1% of the contract value.


DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 20 of 34

8.5.3 Work Scope Definition

A Work Strategy shall be formulated by CONSULTANT to outline the


implementation strategy that would be the best for the Project.

The main output during this phase are:

a) Work Breakdown Structure

b) This Project Execution Plan

c) PMC Services Proposal

8.5.4 Work Breakdown Structure (WBS)

CONSULTANT shall develop the first and second level WBS that shall
hierarchically breakdown the Project into smaller, more manageable and
well-defined components to enhance the planning, organization, and
controls of the implementation and reporting of the Project activities.
The detail WBS shall be developed by PCC/EPCC CONTRACTOR and
will be approved by OWNER.

The First and second level WBS shall be approved by the


CONSULTANT’s Project Director and the OWNER’s Project Manager
within 1 month after the Project Start Date.

The approved WBS shall then be compiled in the Project


Implementation Manual for reference and guideline for all Project
activities.

8.5.5 Time, Planning And Scheduling

Time scheduling of the Project shall be addressed by the following


deliverables will be developed:

a) Master Project Schedule

b) Engineering Work Schedule (Level-2)

c) Procurement Work Schedule (Level-2)

d) Construction Work Schedule (Level-2)

e) Commissioning Work Schedule (Level-2)

A Project Schedule Report that provides narrative explanations to the


implementation strategy and sufficient details to describe the scheduling
basis and assumptions made may also accompany the above
schedules. The development of these schedules is more precisely
detailed in the following paragraphs
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 21 of 34

8.5.5.i) Master Project Schedule

CONSULTANT shall develop the Master Project Schedule with


thorough considerations to the following Project parameters:

a) Scope of Work as defined in the Contract

b) Scheduling objectives and constraints

c) Financial objectives

d) Quality objectives

The Master Project Schedule shall document sufficient level of


scheduling details to reflect the overall implementation and
strategy in undertaking the Project from the start until
completion.

The Schedule shall reflect the expected Critical Path of the


Project and shall be accompanied by an analysis of the
criticality.

A method statement to address on the foreseeable challenges


facing the critical activities that will potentially affect the whole
Project execution shall also be provided.

The Master Project Schedule shall be approved within 1 month


after the Project Start Date by the following authorities unless
otherwise agreed in the project requirements:

a) OGP Project Manager,

b) OGP Project Director and,

c) The OWNER’s Project Manager;

The approved Master Project Schedule shall then be compiled


in the Project Implementation Manual to serve as the Baseline
Schedule for all Project activities.

A sample of Schedule Basis Memorandum with Master Project


Schedule is attached at the end of this procedure (Attachment
1).

8.5.5.ii) Engineering Work Schedule

The EPCC CONTRACTOR is responsible to develop the


Level-2 Engineering Work Schedule shall be developed to plan
the available resources to accomplish the required Scope of
Work as normally outlined in the Contract as the List of
Engineering Deliverables.

For Package 1A and 1B, where CONSULTANT has executed


the engineering, no Engineering Work Schedule is required.
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 22 of 34

In Level 2 Engineering Work Schedule, a method statement to


address on the foreseeable challenges facing the critical
activities during this phase should also be provided.
CONSULTANT shall review and approve the work schedule.

8.5.5.iii) Procurement Work Schedule

The PCC/EPCC CONTRACTOR is responsible to develop the


Level-2 Procurement Work Schedule shall be developed to
plan the Procurement activities to accomplish the required
Scope of Work i.e. to procure the designated list of equipment
and materials within the allocated time frame as dictated by the
Master Project Schedule.

This Schedule shall highlight on major Procurement packages


and the critical Procurement milestones. Correct timing
references with Engineering, Construction and other Project
activities shall also be reflected in this schedule.

A method statement to address on the foreseeable challenges


facing the critical activities during this phase should also be
provided.

CONSULTANT shall review and approve the work schedule


submitted by PCC/EPCC CONTRACTOR.

8.5.5.iv) Construction Work Schedule

The PCC/EPCC CONTRACTOR is responsible to develop the


Level-2 Construction Work Schedule to plan the available
resources to accomplish the required Scope of Work i.e. to
construct the facilities and install the designated list of
equipment and materials.

The Construction Work Schedule shall then be further


developed to document sufficient level of details down to Level
4 to reflect the implementation plan to meet the Project
objectives and constraints.

The Schedule shall highlight on the critical activities during this


phase. A method statement to address on the foreseeable
challenges facing the critical activities during this phase that
will potentially affect the other aspects of the Project shall also
be provided. CONSULTANT shall review and approve the work
schedule.

8.5.5.v) Commissioning Work Schedule

The PCC/EPCC CONTRACTOR is responsible to develop the


Level 2 Commissioning Work Schedule to plan the available
resources to commissioning the facilities.
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 23 of 34

The Commissioning Work Schedule shall document sufficient


details to reflect the overall implementation strategy to meet
the Project objectives and constraints

The Schedule shall highlight on the critical activities and


milestones during this phase.

CONSULTANT shall review and approve the work schedule.

8.6 COST ESTIMATING AND BUDGETTING

This section of the procedure addresses on the Cost Estimating and Budgeting
for the Project where by the main deliverables are:

a. OWNER’s Capital Cost Estimation

b. CONSULTANT’s Project Operating Budget

8.6.1 Project Capital Cost Estimation

CONSULTANT shall develop the Cost Estimates for the Project Capital
Cost to the accuracy as required by the OWNER and submitted to
OWNER.

A Project Costing Report that provides narrative explanations to the


basis and assumptions made shall accompany the above Cost
Estimate.

The approved Project Capital Cost Estimation shall then be submitted


for OWNER’s review and records.

8.6.2 CONSULTANT’s Project Operating Budget

The CONSULTANT’s Operating Budget shall document sufficient level


of breakdown to reflect the financing plan in undertaking the Project
from the start until completion.

The following authorities shall approves the Project Overall Budget


within four weeks after the Project Award Date unless otherwise agreed
in the project requirements:

a) OGP Project Manager,

b) OGP Project Director and

c) The OWNER’s Project Manager.

The approved budget shall serve as the Baseline Cost Plan throughout
the Project duration.
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 24 of 34

8.7 QUALITY MANAGEMENT

8.7.1 General

CONSULTANT is committed to establish, document, implement, and


maintain the project quality management system (QMS) and continually
improve its effectiveness in accordance with ISO 9001:2000 standards.

CONSULTANT shall undertake the following efforts:

• To identify and map all product and functional core business


processes and critical supporting work processes. This shall include
determining the sequence and interaction of these processes. This
is shown in Figure 1

• To determine criteria and methods needed to ensure that both the


operation and control of these processes are effective.

• To ensure the resources availability and the necessity of information


in supporting the operation, as well as, monitoring these processes.

• To monitor, measure and analyze the processes.

• To implement actions necessary to achieve planned results and


continual improvement of these processes.

CONSULTANT shall identify appropriate individuals, appoint special task


forces, and obtain necessary external assistance or other suitable
means to help CONSULTANT undertaking the above efforts.

8.7.2 The Process Approach

CONSULTANT’s QMS is based on the management of its core


processes and system, which have a direct impact to the product and
service offered.

This is achieved by defining the processes and measurement system


and how the organization personnel, equipment and technical expertise
shall be managed to ensure that the customers and interested parties
agreed expectations and requirements are met. The CONSULTANT
Business Process shall conform to process approach of the ISO9001:
2000 QMS.

8.7.3 QMS Program

In essence, CONSULTANT QMS program shall cover all phases of the


project namely: basic engineering, detail engineering, ITB preparation,
procurement, construction and commissioning. The program is divided
into 3 categories:

Quality Planning
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 25 of 34

Quality Planning is a process to identify which quality standards or


requirement are relevant to the project and determining ways and
methods to satisfy them. The quality planning shall include the following
activities:

• Establish Project Quality Policy

• Establish a specific Project Quality Manual, QA-PL-001 that will


show how the requirement of ISO9001: 2000 is met by the project
QMS.

• Establish Project Execution Plan

• Support functional groups to establish each group’s objectives.

Quality Assurance

Quality Assurance is a process to establish and to reinforce project


quality standards or requirement and to measure and analyze the
effectiveness of the project execution in satisfying the established
quality standards or requirement. The process shall also identify
opportunities for continual improvement in the project. The activities
shall include:

• Establish Quality Assurance Procedures

• Establish Quality Assurance Specifications

• Support other project functional group to establish procedures

• Conduct QA/QC audits on internal CONSULTANT’s organization


(Refer to QA-PR-005, Project Audits).

• Conduct QA/QC audits on SUPPLIERs and PCC CONTRACTORs


(Refer to QA-PR-005, Project Audits).

• Manage issuance / maintenance of audit reports for all project


audits (Refer to QA-PR-005, Project Audits).

• Manage issuance / maintenance of non-conformance reports


(Refer to QA-PR-006, Control of CONSULTANT’s Non-
conformance and QA-PR-007, Control of CONTRACTOR’s Non-
conformance, QA-PR-008).

• Manage issuance / maintenance of preventive action reports


(Refer to QA-PR-004, Control of Potential Non-conformance)

• Manage customer complaint reports.

• Conduct Contract Compliance Verification on CONSULTANT’s


organization.
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 26 of 34

• Establish specific Quality Assurance Procedures for engineering,


procurement, construction and commissioning activities.

• Support other construction and commissioning group to establish


construction and commissioning procedures

• Review SUPPLIERs’ and PCC/EPCC CONTRACTORs’


procedures

• Coordinate Technical Audits

Quality Control

Quality Control is a process to measure and analyze project results from


specific operational activities using specialized operational monitoring
and verification tools and techniques to determine if the results in
compliance to established quality standards or requirement. This
process shall also include identification and elimination of non-
conforming products and identifying ways to eliminate the causes of
non-conformances. The quality control activities shall include the
following:

• Conduct general surveillance on engineering deliverables

• Conduct required inspection at SUPPLIERs’


manufacturing/fabrication facilities

• Lead specific data analysis works for quality improvement

• Conduct third party inspection verification

• Conduct general surveillance on construction and commissioning


activities

• Witness and approve Welding Procedure / Welder qualification

• Witness and approve validation other special construction and


commissioning work processes

• Monitor construction process traceability

• Monitor punch list program

• Conduct verification on mechanical completion and commissioning


completion readiness

• Lead specific data analysis works for quality improvement

• Final Documentation
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 27 of 34

8.8 HEALTH, SAFETY & ENVIRONMENT (HSE)

8.8.1 General

CONSULTANT is committed to implement a systematic HSE


management system (HSEMS) that shall ensure a safe and secured
project execution. HSEMS shall be established in order to achieve and
accomplish safe and secured project execution throughout the
CONSULTANT’s scope of works.

The HSEMS is defined as the policies, objectives, organizational


structure, responsibilities, standards, practices, procedures, processes,
controls and resources for implementing HSE management within the
business activities.

8.8.2 HSE Objectives

The objectives of the HSEMS are to ensure that:

a) The health, safety and environmental hazards and effects inherent


in the business operations have been systematically identified,

b) Arrangements are in place to control those hazards and effects and


to deal with the consequences should the need arise,

c) The necessary information, training, auditing and improvement


processes are in place to achieve these objectives.

In other words, the HSEMS is to ensure the reduction of risks within the
business operations and management through the effective
implementation of the contents of the system and thus providing a safe
work environment for all employees either they are direct employees or
CONTRACTORs’/SUB-CONTRACTORs’ employees.

8.8.2.i) Quality Indicator and Standards

Time - Engineering deliverables completed as per planned


schedule.

Cost - Rework cost not exceeding 5% of the contract value.

NCR – No recurrence of NCR’s of the same nature.

In order to emphasize the implementation of HSEMS in the project a


specific HSE Plan, SF-PL-001, shall be developed to specify
requirements of HSEMS to be adhered by the project community.

8.8.3 HSE Culture

8.8.3.i) This section addresses the management and company’s


commitment to sustain a culture that ensures the success of
the HSEMS.
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 28 of 34

8.8.3.ii) These requirements apply to all leading personnel who provide


the leadership, commitment and guidance for the successful
implementation of HSEMS.

8.8.3.iii) Management shall provide visible leadership and commitment


to the HSEMS.

8.8.3.iv) Management shall provide the necessary resources and


support to facilitate adherence of the HSE Policy and the
implementation of strategic objective requirements.

8.8.3.v) A company culture that supports the HSEMS shall be


characterised by:

• Belief in the company’s intention to improve and maintain its HSE


performance at a required level for effective HSEMS
implementation.

• Motivation to improve personal HSE performance based on positive


recognition, desirable attitudes and acceptance of individual
responsibility.

• Participation of staff at all levels by encouraging their involvement


and incorporating their input in HSEMS development, and
continually seeking and supporting their suggestions for
improvement.

• Commitment of staff at all levels is essential to have a successful,


effective consistent implementation and maintenance of the
HSEMS.

8.8.3.vi) The HSEMS Engineer shall monitor any inconsistencies or


lack of management leadership within the company, and
provide improvement measures as necessary.

8.8.4 Organisation

Implementation of HSEMS by CONSULTANT in the project involves


three areas of the organisation: The Project Overall organisation, the
project site organisation and the HSE Committee organisation.

8.8.4.i) Central Management Organisation

The organization structure shown in Attachment 1 depicts the


CONSULTANT’s Project Overall organization, including
functional areas and management roles. The Project Overall
organization has overall responsibility and accountability for
managing HSE in CONSULTANT’s activities. Inherent in each
of the roles in the business structure is the responsibility and
accountability for implementing the HSEMS within their area of
authority. These responsibilities are further described in this
section.
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 29 of 34

Within the Project Overall structure is the Quality and HSE


department. This department reports directly to the Project
Manager to ensure autonomy and a direct communication path
to senior management for quality and HSE related matters.
The Quality and HSE department is facilitator and a resource
for the organisation in implementing the HSEMS.

8.8.4.ii) Project Site Organisation

The project site organization has the responsibility and


accountability for managing HSE at project site. Similar to the
Project Overall structure, each of the roles in the project
organization has the responsibility and accountability for
implementing the HSEMS within their area of authority, and
these are described in this section. The respective Site
Managers shall be responsible for defining the HSE roles and
responsibilities of positions at construction sites that are not
provided in the HSEMS Plan.

8.8.5 HSE Committee Organisation

The Project HSE Committee shall have the mixture of all parties
involved in the project i.e. the OWNER, the CONSULTANT, and Sub-
CONTRACTORs. The objectives of the HSE Committee are as follows:

• Provide a safe and healthy workplace

• Foster co-operation and consultation between management and


workers in identifying, evaluating and controlling hazards

• Provide a channel of communication to exchange ideas, problem


solving and feedback

• All levels of management and supervision personnel shall commit


fully to their HSE responsibilities to ensure the success of HSEMS.

• Principal accountabilities shall include the general HSE strategic


objectives and others developed for individual positions in the
organisation charts to meet agreed HSE targets.

• All employees of CONSULTANT need to understand that they have


a duty and responsibility to stop work that is being attempted in an
unsafe manner, and to advise the senior manager immediately
where and why this has been done.

8.8.6 Implementation Strategy

CONSULTANT’s Strategic Objectives associated with Implementation


are:

8.8.6.i) Roles and Responsibilities of each individual in Projects.


Management shall ensure that all employees are provided with
a written description of their roles and responsibilities with
respect to the HSE management system and have the
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 30 of 34

necessary knowledge and skills to perform their current jobs


safely.

8.8.6.ii) Monitoring and Verification of HSE performance by


CONSULTANT and EPCC CONTRACTOR. Safety
performance will be monitored in a consistent manner across
project teams to track HSE performance within the
organisation. This requirement shall be extended to EPCC
CONTRACTORs where CONSULTANT’s role shall be to
continuously monitor the performance and make periodic
verifications to ensure the HSEMS requirement is met.

8.8.6.iii) Communication and Training of Safety. The Management


from CONSULTANT’s side or EPCC CONTRACTOR shall
ensure all employees are aware of the standards of the
HSEMS to be used, through communication and training at all
levels and all locations of works. Apart from CONSULTANT’s
HSE Plan, EPCC CONTRACTOR shall be required to provide
their own HSE Plans to define strategies, rules and
requirement in the implementation of HSE in each package.

8.8.6.iv) All CONTRACTORs will be subject to assessment and pre-


qualification prior to contract award. CONTRACTORs shall
demonstrate compliance and commitment to the
CONSULTANT’s HSEMS, as a minimum.

8.8.6.v) Management shall ensure that open and effective


communication channels are maintained between the
employees, the OWNER, the local community, and
CONTRACTORs to ensure that HSE concerns of all parties
are responsibly addressed.

8.8.6.vi) CONSULTANT shall continuously improve its HSE


performance through adoption of audit recommendations,
management review comments and feedback from the
workforce, OWNER and CONTRACTORs via well-established
communication channels.

8.8.6.vii) Outstanding HSE performance by OWNERs, employees and


CONTRACTORs shall be recognised.

8.8.6.viii)Incidents that result in actual losses, including potentially


serious near misses, will be reported investigated and
analysed in a consistent manner. Corrective actions arising
from investigations will be reviewed by Management and
recommendations for implementation issued.

8.9 DOCUMENT MANAGEMENT

Document Controller (DC) shall control all project documents and records. A
dedicated document room shall be furnished to ensure effective document and
records management of the project. CONSULTANT has established the
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 31 of 34

mandatory QMS procedures Document Control, QA-PR-001 and Control of


Project Records, QA-PR-003 to specify the management requirement for the
Document and Records control of project. For detail methods on filing of
document and records, procedure Project Document Filing System, PM-PR-001
is established. All document and records shall be established and identified by
unique numbering. The procedure Document Numbering System PM-PR-002 is
established to define rules to number a document or record.

8.9.1 Hierarchy of Document

In case of conflict between the requirements of any of the above


documents, the following order of precedence will apply:

a) The requirements of contract between WNPOC and OGP for the


supply of Consultancy services.

b) The requirements of the Project Implementation Manual.

c) The requirements of the Functional area plans, guidelines and


procedures.

Responsibility for the resolution of all conflicts between project quality


system documents rests with the Project Manager.

8.9.2 Responsibility for Document and Records control

Document Controller

• Maintaining master list of control document.

• Distributing controlled document whether in-process or approved


ones.

• Receive and distribute correspondence and maintaining the


database of correspondence.

• Maintain all original project records and distribute copies.

Functional Department

• Document & records content

• Document & records numbering

• Maintaining of database(s) of documents including; completion,


milestones (planned and forecast/actual)

• Reports from database(s) showing only the responsibility of the


functional group

Quality Assurance

• Monitoring the process of producing documents


DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 32 of 34

• Specifying format of document and records

• Monitoring effectiveness of document reviews and approvals


whether it is CONSULTANT’s or CONTRACTORs’

• Conducting audits and surveillances

Project Control

• Development of project control databases

• Identification of trends and variances against the planned dates

• Ensure variances are resolved or accepted and planned dates are


amended if required and re-approved.

8.9.3 Project Final Documentation

The Project Manager shall have overall responsibility to ensure that final
project documentation and quality records are fully monitored by
CONSULTANT's project team, to ensure the documentation shall fully
describe and demonstrate the quality of work performed in engineering,
procurement, construction and commissioning.

Responsibility rests with functional managers to ensure project


documentation and quality records in their individual functional area are
compiled in an organized manner, and ensure all documentation
demonstrates compliance with applicable standards.

8.10 PROJECT COMPLETION MANAGEMENT

8.10.1 Mechanical Completion

CONSULTANT shall form a specialized monitoring team to verify


CONTRACTOR’s Mechanical Completion. This team, which normally
led by Construction/Commissioning Manager, shall conduct the
following activities:

• Coordinating documentation of punch list

• Coordinating punch list clearance

• Identifying actions to resolve any punch list issues

• Reviewing Mechanical Completion checklist

• Updating Mechanical Completion checklist

• Reviewing Submission of Mechanical Completion Dossiers

• Recommend to OWNER the Approval of Mechanical Completion for


CONTRACTORs
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 33 of 34

Project QA/QC Engineer shall play his inspection and surveillance role
in making sure the correctness and completeness of the
CONSULTANT’s produced document and CONTRACTORs’ submitted
document.

8.10.2 Initial Acceptance

CONSULTANT’s commissioning team shall conduct monitoring and


verification of start-up activities until the stable operation of the plant.
The Initial Acceptance Dossiers shall be prepared by CONTRACTOR
and submitted to OWNER for review and approval. Upon approval of the
dossiers and completion of physical works, the team shall recommend
Initial Acceptance of the project and the handover of the plant from
CONTRACTOR to OWNER.

8.10.3 Final Acceptance

CONSULTANT shall monitor the clearance of all punch lists from Initial
Acceptance stage and ensure the completion of Project Handover
Dossiers prior to recommending Final Acceptance of the project to
OWNER.

8.11 CONSULTANT - OWNER INTERFACE

8.11.1 Project Progress Meetings

The Project Manager will chair weekly Project Progress Meetings. The
purpose of these meetings is to review the status/progress of all project
activities including activities, identify any major problems or concerns,
assign action items and set a schedule for resolving such problems or
concerns.

All the respective managers as well as Lead Discipline Engineers shall


attend these meetings.

8.11.2 Meetings with OWNER

The Project Manager will schedule and chair monthly meetings with the
OWNER as necessary. The Engineering Manager, Project Control
Manager, Procurement Manager and all Lead Discipline Engineers
attend these meetings. They are held to provide the OWNER with a
general status of the Project and to obtain his feedback.

8.11.3 Meetings with CONTRACTOR

CONTRACTOR’s Project Manager shall chair the meetings with


OWNER. CONSULTANT shall represent OWNER during discussion or
negotiation with CONTRACTOR and also the decision-making in the
meeting. OWNER may also be present in the meeting.

8.11.4 Monthly Status Report

The Engineering Manager is responsible for preparing the engineering


section of the Monthly Report. He is also responsible for assembling
DOC. NO. : QA-PL–002 REV. NO. : 00

DOC. TITLE : PROJECT EXECUTION & QUALITY PLAN Page 34 of 34

the supporting documents and supplying necessary information using


the Engineering Management System.

8.11.5 Official Correspondences

The procedure Communication & Correspondence Control, PM-PR-004


specifies the procedure for official written communication between
CONSULTANT and Contractor.

8.11.6 Unofficial Daily Communication

Any informal discussion, negotiation, decision-making with OWNER or


CONTRACTOR will not be valid unless written documentation is
generated to record such communication has occurred between
CONSULTANT - OWNER or CONSULTANT - CONTRACTOR.