Sunteți pe pagina 1din 45

Environmental Aspects & Impacts Register

Disposition Statement

This generic Register of Environmental Aspects and Impacts should be read in conjunction with McLaren Construction Ltd Aspects and Impacts Procedure, the
individual Site Environmental Risk Assessments and Environmental and Emergency Plans. These detail how the generic environmental aspects apply and how any
site-specific risks or actual impacts are identified and prevented, controlled or mitigated.

This statement explains the process by which environmental aspects have been identified and evaluated for significance. The aspects have been grouped into the
following topics:

1. Resource efficiency (non-renewable resources, energy and water)


2. Traffic and transport
3. Ground contamination
4. Water and effluent discharge
5. Noise, vibration and other nuisances
6. Air emissions (dusts, odours, greenhouse gases, ozone depleting substances, solvents etc.)
7. Toxic and hazardous substances (including oils and fuels)
8. Deleterious materials (asbestos, PCBs, etc.)
9. Wastes
10. Visual impact / townscape / landscape (including site lighting)
11. Cultural heritage and archaeology
12. Wildlife and natural features
13. Environmental emergencies and external occurrences (impact/collision, flood, etc.)
14. Indirect Environmental impacts

An example of the process by which aspects and impacts were identified is as follows: one aspect identified in the register is wastes and their disposal to landfill.
This aspect was considered significant because of the variety and importance of the potential impacts consequent to the degradation of the wastes after tipping
(leachates, methane / greenhouse gases, odours, visual impact, health concerns, etc.).

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


All wastes are automatically considered “significant” due to the specific commitment in the policy statement identifying them for particular attention, as well as the
detailed legal requirements that govern their day-to-day management (policy commitment to comply).

Aspects arising from normal, abnormal and emergency situations have also been identified, including project start-up (demolition and clearance), normal
operations (building and site management) and finishing phases of the project. Examples of abnormal or even emergency wastes would be the need to dispose of
asbestos, or contaminated soil following a spill.

The significant environmental aspects associated with wastes from various activities at operating sites are dealt with in Section 9 below and include:

• Emissions to air / landfill gases


• Releases to water / leachates
• Contamination of land
• Inefficient use of raw materials and natural resources
• Localised nuisance and health impacts close to landfill sites

Consideration has also been given to past, current and future activities, products and services - for example, the requirement for an increasing proportion of
construction materials to be derived from recycled sources.

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


ASPECT GROUPING: RESOURCE EFFICIENCY

Key To Significance
Ref Source(s) Impact Description Mitigation & Control
Impacts Status
All activities Depletion of mineral resources that are mined, Procurement Objective
using quarried or otherwise extracted from the natural Policy on FSC-certified timber
minerals, environment will deprive future generations of the Environmental Project Design / EGN1
metals, ability to enjoy a similar lifestyle to that enjoyed
cements, today.
timber, etc.
1.1 1,2,3,4,5
Key is to maximise resource efficiency, avoid waste Significant
and seek alternative “renewable” resources. Avoid
the use of certain metals and toxic materials where
possible. Design component can influence full life
cycle of building – e.g. through the specification of
control devices.
All activities Depletion of fossil fuel resources that are mined, Energy efficiency objectives at office
using energy quarried or otherwise extracted from the natural premises
environment will deprive future generations of the Environmental Plan
ability to enjoy a similar lifestyle to that enjoyed Environmental Project Design / EGN1
today. EGN13 Energy Conservation
1.2 1,2,3,4,5
Significant
Key is to maximise fuel efficiency, avoid waste and
seek alternative “renewable” fuels. Need to
maximise energy efficiency throughout full building
life cycle. See also Air emissions and greenhouse gas
/ climate change impacts.

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


1.3 All activities Excessive consumption can deplete national 1,2,3,4 Significant EGN3 Permits and consents (abstraction
using water reserves and /or place an additional burden on and dewatering)
existing water supplies. Environmental Plan
Environmental Project Design / EGN1
In the case of abstraction from underground
sources, water consumption also affects the water
table and can have a negative impact on aquatic
ecosystems. The use of suitable control devices can
help to reduce consumption.
1.4 All activities Environmental damage from the extraction, 1,2,3,4,5 Significant Procurement Objective
wherein processing and distribution processes of natural Policy on FSC-certified timber
resources are resources, whether renewable or not.
consumed

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


ASPECT GROUPING: TRAFFIC & TRANSPORT

Ref Source(s) Impact Description Key To Significance Mitigation & Control


Impacts Status
2.1 Pre-tender / Location of the site may generate increases in traffic 1, 2, 3 Significant Environmental Plan – traffic management
Tender / volume, resulting in localised congestion, parking plan
Design problems and potential nuisance to site neighbours EGN4 Traffic Management
during both construction and operation.
2.2 Vehicular Increased localised traffic movements and possible 1, 2, 3 Significant Environmental Plan – traffic management
Movement & congestion of access routes. plan
Access EGN5 Traffic Management
Additional impacts include mud on roads from site
vehicles and potential contamination of land and
water adjacent to routes through dispersal of
polluted run-off from road surfaces.

See also emissions to air, wastes, nuisance, etc.


(Note that Group Environmental Policy identifies
vehicle emissions as key issue).
2.3 Office Increased localised traffic movements and possible 1, 2, 3 Significant EGN5 Traffic Management
Operation congestion of access routes and parking in
surrounding area.

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


ASPECT GROUPING: GROUND CONTAMINATION

Ref Source(s) Impact Description Key To Significance Mitigation & Control


Impacts Status
3.1 Pre-tender / The impacts to ground quality resulting from the 1,2,3,4 Significant Environmental Plan
Tender / design, its construction and operation as well as Procedure EP09 Contaminated land
Design previous land-uses generating risks to the design EGN8 Land Contamination
itself.

The MCL Environmental Policy identifies land


contamination as a key issue for prioritisation.
3.2 Demolition Demolition of existing structures may necessitate 1, 2, 3, 4 Significant Environmental Plan
removal or decommissioning of possible sources of Procedure EP09 Contaminated land
contamination (e.g. on site dumping grounds, EGN9 Land Contamination
asbestos, old storage tanks above and below
ground, machine bases, sumps etc). These may
have created historical contamination as well as
present an on-going contamination risk.
3.3 Concrete ‘Aggressive’ contaminants may attack building, its 1, 2, 3 Significant Environmental Plan
Structures foundations and services. Procedure EP09 Contaminated land
EGN9 Land Contamination
3.4 Earthworks / Excavation and stockpiling of contaminated spoil 1, 2, 3, 4 Significant Environmental Plan
Excavation may expose potentially harmful contaminants within Procedure EP09 Contaminated land
the spoil to site workers or site neighbours (e.g. EGN9 Land Contamination
during dry conditions).

Contaminants may be mobilised to surface waters or


even groundwater.

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


3.5 Dewatering Waters pumped from contaminated site may 1, 2, 3, 4 Significant Environmental Plan
contain excessive levels of pollutants and require Procedure EP09 Contaminated land
specialist handing and disposal arrangements. Risk EGN9 Land Contamination
of polluting watercourses.
3.6 Piling Mobilisation of existing contamination vertically or 1, 2, 3, 4 Significant Environmental Plan
horizontally through the strata, contaminating Procedure EP09 Contaminated land
deeper groundwater resources. EGN9 Land Contamination

3.7 Storage & Improper storage and spillages of chemicals/oils to 1, 2, 3, 4 Significant Environmental Plan
Use of the ground may cause or contribute to existing Procedure EP09 Contaminated land
Chemicals & contamination of soil and groundwater. EGN9 Land Contamination
Oils EGN10 Oil and chemical storage
3.8 Waste Leachates from waste storage areas can cause or 1, 2, 3 Significant Environmental Plan
Storage contribute to ground contamination. Procedure EP09 Contaminated land
EGN9 Land Contamination
In addition to a negative visual impact, litter
accumulation can also be considered a form of land
contamination.

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


ASPECT GROUPING: WATER AND EFFLUENT DISCHARGE

Ref Source(s) Impact Description Key To Significance Mitigation & Control


Impacts Status
4.1 Pre-tender / Design may pollute water resources during 1,2,3,4 Significant Environmental Plan
Tender / construction and operation. Potential contamination EGN3 Permits and Consents
Design of groundwater, controlled waters or drainage EGN8 Water and Effluent Discharges
systems can result through spillage, run-off, abuse,
vandalism, pumping, de-watering or other
operations.

4.2 May involve decommissioning of structures that 1,2,3,4 Significant Environmental Plan
contain pollutants (e.g. fuel tanks, chemical stores, EGN3 Permits and Consents
machine bases etc). If not handled properly, these EGN8 Water and Effluent Discharges
pollutants may enter surface water/drainage
systems causing pollution.
4.3 Earthworks / Pollution of drainage system and/or watercourses 1,2,3,4 Significant Environmental Plan
Excavation with contaminated particulate matter from spoil EGN3 Permits and Consents
heaps/haul roads. EGN8 Water and Effluent Discharges
Sediment run-off to surface waters, affecting aquatic
biota.
4.4 De-watering Disposal of abstracted groundwater from 1,2,3,4 Significant Environmental Plan
contaminated sites or silty water may pollute EGN3 Permits and Consents
watercourses with impacts upon water quality, EGN8 Water and Effluent Discharges
habitats and amenity.

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


4.5 Concrete Cement powders/fines have potential to cause 1,2,3,4 Significant Environmental Plan
Pours / pollution of watercourses if not contained. EGN3 Permits and Consents
Batching Cementitious wastes can damage aquatic life and EGN8 Water and Effluent Discharges
contribute to loss of amenity.
4.6 Piling Piling can create a pathway through which 1,2,3,4 Significant Environmental Plan
contaminants in the upper soil layers may pass to EGN3 Permits and Consents
deeper sensitive groundwater resources (e.g. EGN8 Water and Effluent Discharges
aquifers).
4.7 Vehicular Pollution of drainage systems and water courses 1,2,3,4 Significant Environmental Plan
Movement & with oils (hydrocarbons) from vehicles, particulates EGN3 Permits and Consents
Access and other chemicals. Vehicle / wheel wash effluents. EGN8 Water and Effluent Discharge

4.8 Use of Plant Potential for losses of oils (fuel, hydraulic oil etc) 1,2,3,4 Significant Environmental Plan
& Machinery from items of plant to surface waters. EGN8 Water and Effluent Discharges
4.9 Storage / Use Spillage of oils and chemicals from storage failure 1,2,3,4 Significant Environmental Plan
of Chemicals and poor handling. EGN10 Oil and chemical storage
/ Oils EGN8 Water and Effluent Discharges
Emergency response plan
4.10 Waste Leachates from waste storage areas causing 1,2,3,4 Significant Environmental Plan
Storage pollution of surface waters. EGN8 Water and Effluent Discharges
EGN4 Waste management
4.11 Site A number of effluents can be generated on site 1,2,3,4 Significant Environmental Plan
effluents: including waste hygiene waters / sewage, silty EGN3 Permits and Consents
waters from excavations, oils, contaminated wash EGN4 Waste management …
waters, etc. EGN8 Water and Effluent Discharges

Effluents may contain contaminants and alter the


background characteristic of waters into which they
are discharged – BOD / COD, suspended solids, pH,
oil sheen, chemical content etc.

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


ASPECT GROUPING: NOISE, VIBRATION & OTHER NUISANCES

Ref Source(s) Impact Description Key To Significance Mitigation & Control


Impacts Status
5.1 Pre-tender / Potential for works to present a nuisance both 1, 2, 3 Significant Environmental Plan
Tender / during construction and operation. Nuisances are EGN6 Noise and Vibration
Design varied but include noise, vibration, dust, odour and
lighting. Group policy has noise from plant and
equipment as a priority.

The MCL Environmental Policy identifies localised


nuisances as a key issue for prioritisation.
5.2 Demolition Dust, noise and vibration may annoy site 1, 2, 3 Significant Environmental Plan
of existing neighbours. When it settles, dusts can also damage EGN6 Noise and Vibration
structure crops and contribute to silt pollution in surface
waters.

Lighting may also cause annoyance if not managed


correctly.
5.3 Earthworks / Dust from excavations may annoy site neighbours 1, 2, 3 Significant Environmental Plan
Excavation and potentially pose a health risk if contaminated. EGN6 Noise and Vibration

Lighting may also cause annoyance if not managed


correctly.

Odours from contaminated sites may cause


annoyance and/or adverse health effects.

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


5.4 Concrete Dust, noise & vibration may annoy site neighbours. 1, 2, 3 Significant Environmental Plan
Batching EGN6 Noise and Vibration
Lighting may also cause annoyance if not managed
correctly.
5.5 Piling Noise & vibration from piling may disturb site 1, 2, 3 Significant Environmental Plan
neighbours and cause a nuisance. EGN6 Noise and Vibration
Lighting may also cause annoyance if not managed
correctly.

5.6 Construction Dusts may be generated by cutting materials 1,2,3 Significant Environmental Plan
activities (drainage, masonry and paving flags). Vibration may EGN6 Noise and Vibration
result from drilling and breaking operations.
5.7 Use of Plant Excessive noise can present hazard to workers. 1, 2, 3 Significant Environmental Plan
& Machinery EGN6 Noise and Vibration
Excessive noise levels may cause nuisance to site
neighbours/residents (e.g. consider siting of air
conditioning / lift equipment). Extreme cases may
lead to prosecution by the Local Authority or even
civil actions.

Smoke, exhaust gases and particulate matter from


plant and equipment have nuisance potential.

Lighting from vehicles may also cause annoyance if


not managed correctly.

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


5.8 Vehicle Dust from unsurfaced roads may cause nuisance. 1, 2, 3 Significant Environmental Plan
Movement & EGN7 Dust and Air pollution
Access Dust may damage or cause equipment to
malfunction.

Engine noise may cause nuisance when close to


sensitive receptors – when in motion or idling.
Audible vehicle alarms and horns/klaxons can also
generate noise.
5.9 Waste Wastes may be transported both on and off-site 1, 2, 3 Significant Environmental Plan
Handling & causing litter problems. EGN4 Waste management…
Storage EGN7 Dust and Air pollution
Storage of contaminated or odorous wastes causing
nuisance to site neighbours.

Certain wastes may attract vermin that can spread


to adjacent sites.

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


ASPECT GROUPING: AIR EMISSIONS

Ref Source(s) Impact Description Key To Significance Mitigation & Control


Impacts Status
6.1 Pre-tender / Impacts resulting from the construction and 1,2,3,4 Significant Environmental Plan
Tender / operation of the design as detailed in the following
Design rows.
6.2 Vehicular Vehicle exhaust emissions (NOX SOX CO CO2 PM etc) 1, 2, 3, 4, Significant Environmental Plan
Movements contribute to global warming, acid rain and 5 EGN7 Dust and Air Pollution
& Access respiratory health problems.

Dust emissions from unsurfaced roads and dirty


vehicles, uncovered loads, etc. Exceeding relevant
guide limits for key pollutants, especially where in
the vicinity of sensitive receptors.
6.3 Use of Plant Exhaust emissions (NOX SOX CO CO2 PM etc), welding 1, 2, 3, 4, Significant Environmental Plan
& Equipment fumes emissions etc. Potential explosion from 5 EGN7 Dust and Air Pollution
emissions of gases or chemicals.

Exceeding relevant guide limits for key pollutants,


especially where in the vicinity of sensitive
receptors.
6.4 Demolition Dust from building/structure demolition. 1, 2, 3, 4 Significant Environmental Plan
Construction EGN7 Dust and Air Pollution
Fibrous materials from deleterious materials (e.g.
asbestos) that have potentially adverse human
health effects. Blown polystyrene and similar
materials may also use ozone-depleting chemicals as
their propellant.

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


6.5 Unauthorised Smoke fumes and particulates released from 1,2,3,4 Significant Environmental Plan
fires burning vegetation or other waste materials. Dark EGN7 Dust and Air Pollution
smoke is unsightly and bonfires can be considered a
“nuisance” under the legislation (e.g. when smoke
obscures roads).
6.5 Painting / Use of chemicals and solvents, especially Volatile 1, 2, 3, 4, Significant Environmental Plan
Coating Organic Compounds (VOCs) from paints & varnishes, 5 EGN7 Dust and Air Pollution
contribute to ozone depletion.
6.6 Heating Exhaust gases NOX, CO CO2 etc) from the 1, 2, 3, 4, Significant Environmental Plan
Systems combustion of fuels (typically gas and oil) for heating 5 EGN7 Dust and Air Pollution
Installation of water that contribute to global warming and acid
rain.
6.7 Cooling Use of refrigerants that have global warming and 1, 2, 3, 4, Significant Environmental Plan
Systems ozone depleting potential (e.g. CFCs, HCFCs, HFCs 5 EGN7 Dust and Air Pollution
Installation etc).

Potential release of bacteria (legionella) to the air


from water treatment systems (e.g. cooling towers
and evaporative condensers).
6.8 Ventilation Potential release of bacteria to air via humidification 1, 2, 3, 4 Significant Environmental Plan
systems
6.9 Office Use of electricity indirectly contributes to global 1,2,3,4,5 Significant Environmental Plan
Operation warming and acid rain (NOX, SOX, CO2 etc) EGN7 Dust and Air Pollution

Potential release of bacteria (legionella) to air from


cooling and ventilation systems in building.

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


ASPECT GROUPING: TOXIC AND HAZARDOUS SUBSTANCES

Ref Source(s) Impact Description Key To Significance Mitigation & Control


Impacts Status
7.1 All activities A wide range of hazardous, irritant, toxic, corrosive, 1,2,3,4,5 Significant – Environmental Plan
using poisonous and inflammable materials may be comply with legal COSHH assessments
hazardous present on site at any time. requirements
materials
Accordingly a variety of controls may need to be
used to ensure their safe storage, handling, use and
disposal – see Health and Safety procedures (ref.
COSHH etc.) – depending upon the type and
quantity of substances involved.
7.2 Fuels and oils These materials need careful storage in order to 1,2,3,4,5 Significant Environmental Plan
prevent accidental release to the environment. EGN10 Oil and chemical storage
Bowsers should have spill trays and, where possible,
be fitted with double skins to contain leaks. All oils
and fuels should be stored on sealed surfaces with
some secondary containment or spill kit.
7.3 Radioactive Not normally present on MCL sites (but may be ref. 1,2,3,4,5 Significant where Subcontractor selection
materials? hospitals etc.??) present
7.4 Sharps / First Sharp objects such as broken knife blades present a 1,2,3,4,5 Significant where Environmental Plan
Aid waste safety hazard and may need special waste storage present EGN4 Waste management…
containers. Similarly, any bandages or other First Aid
waste

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


ASPECT GROUPING: DELETERIOUS MATERIALS

Ref Source(s) Impact Description Key To Significance Mitigation & Control


Impacts Status
8.1 Pre-tender / Design / works may incorporate deleterious materials 1,2,3,4,5 Significant Environmental Plan
Tender / where alternatives exist (e.g. Ozone Depleting
Design Substances, etc)
8.2 Demolition Possible presence of deleterious materials within the 1, 2, 3 Significant Environmental Plan
fabric of existing buildings or structures (e.g. asbestos SHE003 procedure
in ceiling tiles, roof linings, chimney/stack linings etc).
Asbestos fibres become airborne once disturbed and
can cause serious respiratory diseases.
8.3 Excavation / Possible presence of deleterious materials in the 1, 2, 3 Significant Environmental Plan
Earthworks ground from previous land-uses presenting EGN9 Land Contamination
environmental and health and safety risks. EP09 Contaminated Land

8.4 Office Potential asbestos containing materials within the 1, 2, 3 Significant Environmental Plan
Operation fabric of the building that present a risk to employees SHE003 procedure
(e.g. fire doors, boiler rooms, etc)

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


ASPECT GROUPING: WASTE

Ref Source(s) Impact Description Key To Significance Mitigation & Control


Impacts Status
9.1 Pre-tender / Design / works may involve the generation of 1,2,3,4,5 All wastes are Objectives on wastes
Tender / significant waste materials that require disposal to significant - Environmental Plan
Design landfill and miss potential for re-use, recycling. MCL comply with legal EGN4 waste management and minimisation
suppliers and subcontractors will generate “active, and Group policy
inert and special” wastes. Waste management and commitments
minimisation are key McLaren Policy issues.

‘Special wastes’ present an additional threat to the


environment and/or human health. Possible cross
contamination of wastes (i.e. poor segregation) may
prohibit recycling or reprocessing of the materials.
Poor waste management may also result in litter,
pollution of land and water, and there is an
additional fire risk where wastes accumulate.
Wastes attract vermin.
9.2 Vegetation Generation of green wastes, possibly some ‘difficult’ 1,2,3,4,5 All wastes are Environmental Plan – (local composting
Clearance green wastes (e.g. invasive plants – Giant Hogweed, significant - plans?)
Japanese Knotweed, etc – that require special comply with legal EGN4 waste management and minimisation
treatment) to landfill or mulching centres. and policy
requirements
Disposal in landfill has associated impacts from
landfill gases and leachates.

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


9.3 Demolition Generation of aggregate, timber, metal, plastic, 1,2,3,4,5 All wastes are Environmental Plan
spoil, tiles, deleterious materials to landfill. significant - EGN4 waste management and minimisation
comply with legal
Disposal in landfill and possible associated landfill and policy
gases and leachates. Unnecessary disposal of requirements
materials that may be recycled or re-used.

Some wastes may be ‘special wastes’ (i.e. toxic or


hazardous to human health), thus requiring
specialist treatment/disposal.
9.4 Earthworks / Generation of spoil, contaminated spoil to landfill. 1,2,3,4,5 All wastes are Environmental Plan
Excavation significant - EGN4 waste management and minimisation
Disposal in landfill and possible associated landfill comply with legal
gases and leachates. Unnecessary disposal of fill that and policy
may be recycled or re-used. requirements
Spoil from contaminated sites may be ‘special
waste’ presenting risks to worker health and safety
and requiring specialist treatment/disposal.
9.5 De-watering Discharge of water, contaminated water to 1,2,3,4,5 All wastes are Environmental Plan
controlled/foul waters. significant - EGN4 waste management and minimisation
comply with legal EGN8 Water and effluent discharges
Pollution of ‘controlled’ waters from discharge of and policy
liquid wastewaters to surface waters, soakaways etc requirements
(where discharged to controlled waters).

Pollution of foul sewers from discharge of liquid


wastewaters (where discharged to sewer).

Possible programme delays and costs due to


regulatory involvement (e.g. consents/permits
determinations, negotiations with Environment

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


Agency/Water Service Company etc).
Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

9.6 Grouting Generation of spoil, contaminated spoil, bentonite 1,2,3,4,5 All wastes are Environmental Plan
Piling slurry. significant - EGN4 waste management and minimisation
comply with legal
Disposal in landfill and possible associated landfill and policy
gases and leachates. Unnecessary disposal of fill that requirements
may be recycled or reused.

Spoil from contaminated sites may be ‘special


waste’ presenting risks to worker health and safety
and requiring specialist treatment/disposal.
9.7 Brickwork / Generation of bricks/blocks and cement 1,2,3,4,5 All wastes are Environmental Plan
Blockwork significant - EGN4 waste management and minimisation
Disposal in landfill. Unnecessary disposal of comply with legal
materials that may be re-used / recycled. and policy
requirements
9.8 Welding Generation of empty gas bottles and welding rods. 1,2,3,4,5 All wastes are Environmental Plan
significant - EGN4 waste management and minimisation
Disposal in landfill. comply with legal
and policy
requirements
9.9 Carpentry Generation of timber. 1,2,3,4,5 All wastes are Environmental Plan
significant - EGN4 waste management and minimisation
Disposal in landfill and possible associated landfill comply with legal
gases and leachates. and policy
requirements
Unnecessary disposal of timber that may be re-used
/ recycled.

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


9.10 Painting / Generation of paints, solvents, containers. 1,2,3,4,5 All wastes are Environmental Plan
Coating / significant - EGN4 waste management and minimisation
Decorating Disposal in landfill and possible associated landfill comply with legal
gases and leachates. and policy
requirements
Paints, solvents and containers may be ‘special
waste’ presenting risks to worker health and safety
and requiring specialist treatment/disposal.

9.11 Plumbing Generation of plastic/metal piping sections, lagging, 1,2,3,4,5 All wastes are Environmental Plan
solder, packaging significant - EGN4 waste management and minimisation
comply with legal
Disposal in landfill and possible associated landfill and policy
gases and leachates. requirements

Unnecessary disposal of items that may be re-


used/recycled.
9.12 Plastering Generation of plaster, plaster board, timbers, 1,2,3,4,5 All wastes are Environmental Plan
packaging significant - EGN4 waste management and minimisation
comply with legal
Disposal in landfill and possible associated landfill and policy
gases and leachates. requirements

Unnecessary disposal of items that may be re-


used/recycled.

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


9.13 Furnishings Generation of wood, metal, wire/cabling, 1,2,3,4,5 All wastes are Environmental Plan
ceramics/tiles, glues, paints, epoxies, sealants, significant - EGN4 waste management and minimisation
containers, packaging comply with legal
and policy
Disposal in landfill and possible associated landfill requirements
gases and leachates.

Unnecessary disposal of items that may be re-


used/recycled.

Some items may be ‘special waste’ presenting risks


to worker health and safety and requiring specialist
treatment/disposal.
9.14 Roofing Generation of metals, felt, tar/bitumen, insulation, 1,2,3,4,5 All wastes are Environmental Plan
pvc sheeting significant - EGN4 waste management and minimisation
comply with legal
Disposal in landfill and possible associated landfill and policy
gases and leachates. requirements

Unnecessary disposal of items that may be re-


used/recycled.

Some items may be ‘special waste’ presenting risks


to worker health and safety and requiring specialist
treatment/disposal.

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


9.15 Vehicle and Generation of oils/greases, refrigerants, aggregates, 1,2,3,4,5 All wastes are Environmental Plan
plant repair glues, paints, sealants, containers, packaging significant - EGN4 waste management and minimisation
& comply with legal
maintenance Disposal in landfill and possible associated landfill and policy
gases and leachates. requirements

Unnecessary disposal of items that may be re-


used/recycled.

Some items may be ‘special waste’ presenting risks


to worker health and safety and requiring specialist
treatment/disposal.
9.16 Storage & Generation of waste chemicals and oils; used 1,2,3,4,5 All wastes are Environmental Plan
Use of chemical and oil containers. NB - Also need to significant - EGN4 waste management and minimisation
Chemicals consider any contaminated materials used to clean comply with legal
/Oils up after a spill, fire or other environmental incident. and policy
requirements
9.17 Office Generation of paper, cardboard, toner cartridges, 1,2,3,4,5 All wastes are Environmental Plan
Operations food wastes, furniture, electronic hardware, significant - EGN4 waste management and minimisation
packaging comply with legal
and policy
requirements
9.18 Purchasing of Generation of variety of unnecessary wastes 1,2,3,4,5 All wastes are Environmental Plan
Materials through over-ordering. significant - EGN4 waste management and minimisation
comply with legal
and policy
requirements
9.19 Waste Potential for abusive / fly tipping or incorrect 2,3,4,5 All wastes are Environmental Plan – subcontractor
transport disposal and treatment if the transport / disposal significant - controls / waste plans
and disposal process is not managed properly. comply with legal EGN4 waste management and minimisation
and policy

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ASPECT GROUPING: LANDSCAPE & VISUAL

Ref Source(s) Impact Description Key To Significance Mitigation & Control


Impacts Status
10.1 Pre- Design may be incompatible with surrounding 1, 2, 3, 4 Significant Environmental Plan
tender/Tend landscape. Adverse effects on designated sites EGN12 Ecology and Wildlife
er/Design (World Heritage Site, Area of Outstanding Natural EGN1 Environmental design
Beauty, National Park, Country Park, Special
Landscape Area, Registered Parks or Gardens, etc).

10.2 Vegetation Reduction in visual amenity due to the 1, 2, 3, 4 Significant Environmental Plan
Clearance removal/loss/displacement of natural landscape EGN12 Ecology and Wildlife
features (e.g. mature trees, woodland, hedgerows EGN1 Environmental design
etc).

10.3 Demolition Reduction in visual amenity due to the 1, 2, 3, 4 Significant Environmental Plan
of Existing removal/loss/displacement of structures (e.g. listed EGN1 Environmental design
Structures buildings, scheduled monument/structures etc). EGN11 Archaeology and built heritage

10.4 All under The construction of building/structure that is 1, 3, 3, 4 Significant Environmental Plan
‘Erection of incompatible with the landscape character. EGN1 Environmental design
Structure’

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


ASPECT GROUPING: HERITAGE & ARCHAEOLOGY

Ref Source(s) Impact Description Key To Significance Status Mitigation & Control
Impacts
11.1 Pre-tender / Damage/disturbance/destruction of features of 1, 2, 3 Significant Environmental Plan
Tender / cultural, historical or archaeological importance EGN11 Archaeology and built heritage
Design as detailed below.
11.2 Vegetation Destruction/damage to ‘important’ hedgerow, 1, 2, 3 Significant Environmental Plan
Clearance protected on the grounds of its archaeological EGN11 Archaeology and built heritage
and ecological importance.

Project delays due to regulatory involvement (e.g.


hedgerow retention notices, determination
periods, consents/approvals etc).
11.3 Excavation & Discovery of expected / unexpected 1, 2, 3 Significant Environmental Plan
Earthworks archaeological finds (e.g. burnt or blackened EGN11 Archaeology and built heritage
materials, brick or tile fragments, coins, pottery
or bone fragments, skeletons, timber joints or
post holes, brick or stone foundations, infilled
ditches or middens).

Project delays due to regulatory involvement (e.g.


physical investigation, damage assessments,
consents/approvals for protected structures).

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


11.4 Building Damage/destruction of protected buildings or 1, 2, 3 Significant Environmental Plan
Demolition structures (e.g. Listed Buildings, Scheduled EGN11 Archaeology and built heritage
Ancient Monuments).

Project delays due to regulatory involvement (e.g.


physical investigation, damage assessments,
consents/approvals for protected structures).
11.5 Piling Possible damage to heritage features through 1, 2, 3 Significant Environmental Plan
transmitted vibrations. EGN11 Archaeology and built heritage

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


ASPECT GROUPING: WILDLIFE & NATURAL FEATURES

Ref Source(s) Impact Description Key To Significance Mitigation & Control


Impacts Status
12.1 Pre-tender / Works may temporarily or irreversibly impact on 1, 2, 3,4,5 Significant Environmental Plan
Tender / ecology during siting, construction, operation and EGN12 Ecology and wildlife
Design demolition (impacts are detailed below).
12.2 Site / Temporary and potentially irreversible loss of 1, 2, 3,4,5 Significant Environmental Plan
Vegetation habitat through change in land-use, destruction of EGN3 Permits and Consents
Clearance ecosystem and occupation of land for structure or EGN12 Ecology and wildlife
construction site compound.

Damage/destruction and disturbance to adjacent or


nearby statutory sites (e.g.Sites of Special Scientific
Interest, Areas of Outstanding Natural Beauty,
National Nature Reserves etc).

Damage/destruction and/or disturbance to


protected flora and fauna as a result of the above.

Damage/destruction to protected trees or their


roots.
12.3 Demolition Noise and dust emitted from demolition activities 1, 2, 3, 4 Significant Environmental Plan
may annoy site neighbours as well as impact upon EGN12 Ecology and wildlife

sensitive ecological receptors.


12.4 De-watering De-watering may impact adjacent ecology by 1, 2, 3 Significant Environmental Plan
causing alterations to groundwater levels and EGN12 Ecology and wildlife
stream/river flows.

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


12.5 Use of Plant Noise emitted from plant may cause 1, 2, 3 Significant Environmental Plan
& Machinery nuisance/disturbance to protected species (e.g. EGN12 Ecology and wildlife
nesting birds, bats etc)

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

12.6 Storage/Use Potential for spillage of chemicals and oils to 1, 2, 3 Significant Environmental Plan
of Chemicals ground/water may impact adjacent ecological EGN12 Ecology and wildlife
& Oil receptors by following the flow of surface or
groundwater off-site.

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


ASPECT GROUPING: ENVIRONMENTAL EMERGENCIES AND EXTERNAL OCCURRENCES

Ref Source(s) Impact Description Key To Significance Mitigation & Control


Impacts Status
13.1 Collision Collision / impact from road/site vehicle, train, plane 1,2,3,4 Significant Environmental Plan
accident may result in fire, explosion, material Emergency Plan
damage, spillage or other occurrences that generate EGN2 Site set up
environmental impacts. Careful consideration should EGN16 material storage
therefore be given to locating stores etc. when EGN20 Spillage response
setting up site in order to avoid such risks.
13.2 Fire Fire causes material loss but also has adverse 1,2,3,4 Significant Environmental Plan
impacts on the environment: Emergency Plan
EGN8 Water and Effluent discharge
• emissions of toxic fumes, smoke, dusts
• contaminated run-off fire-fighting waters
• generation of wastes (fire-damaged materials)

Prevention must be the priority, but it may also be


necessary to consider mitigation techniques to
minimise environmental damage (containment of
contaminated run-off or its diversion into a
sacrificial area rather than down drains).
13.2 Weather Adverse weather conditions such as high winds and 1,2,3,4 Significant Environmental Plan /
flooding can damage the product (building and Emergency Plan
contents) and/or plant, equipment and materials.
Check whether site is situated on floodplain and
take suitable actions in the event of any flood alerts
in order to minimise damage. Consider other
weather extremes (snow, ice, etc.) and their
potential effects on the works and the environment.

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

13.3 External External release of pollutants (gas, dusts, liquids,..) 1,2,3,4 Significant Environmental Plan
releases may have an impact upon the health and safety of Emergency Plan
employees, and possibly upon materials or building EGN7 Dust and Air pollution
fabric depending upon their nature.

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


ASPECT GROUPING: INDIRECT ENVIRONMENTAL ASPECTS

Ref Source(s) Impact Description Key To Significance Mitigation & Control


Impacts Status
14.1 Product / Once the building is handed over, it will continue to 1,2,3,4,5 Significant Project Design
Building have most if not all of the aforementioned impacts Handover procedure (copies of project EMS
operation on the environment through periodic decoration documents
and use and repairs/refurbishment, grounds maintenance, EGN1 Environmental design
energy consumption etc.

McLaren is able to influence the full life cycle,


particularly when contracts are of a design and build
nature. Accordingly, full consideration should be
given in the design stage to the full life cycle effects
14.2 Product / Upon decommissioning, there will be opportunities 1,2,3,4,5 Significant Project Design
Building to re-use or recycle building materials and
demolition components.

Material selection and construction techniques can


influence the demolition process and
14.3 Interfaces Ability to influence or be influenced by other parts 1,2,3,4,5 Significant SHE meetings and steering groups
with Group/ of group (e.g. personnel policies on recruitment, EGN13 Energy conservation
other Jarvis home working, car provision, etc.)
companies

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |


SHEQ / DM/ R1C9/REV02 JAN 12

PROJECT ENVIRONMENTAL PLAN


Omega South Zone 7 Phase 1

AUTHORISATION AND ISSUE RECORD

The following Project Environmental Plan has been prepared in accordance with the
Environmental Management System (EMS) Procedure C9 – Operational Control. I authorise the
use of this plan as the main control element of the EMS on the above contract. This should be
read with the ‘Electronic’ access to the Documented Environment Management System and
Manual.

Name Adam Onyett


Signature
Date 29.08.13
Job Title SHEQ Coordinator

The Project Environmental Plan is to be issued to the Project Team, listed below, who shall
agree to comply with its contents at site level and maintain the necessary documentation listed
within it. The working copy of the plan is to be held on site and updated when applicable.

Name of Recipient Job Title Signature Date

The Site Manager, supported by the Contracts Manager and SHEQ Coordinator, is the key
person within this system and shall be responsible for the following;

Method of work undertaken on the project matches the client and regulatory authorities’
requirements and minimises the effect of our works on the environment.
Verification that approved working procedures and regular inspections are implemented
and all personnel are compliant.
Ensuring that all personnel on the project are aware of their responsibilities within the
EMS, arranging training where necessary (via the SHEQ Coordinator).
Holding the current version of the EMS and advising the project team of the relevant
procedures and records to be kept.

New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 2 of 11
SHEQ / DM/ R1C9/REV02 JAN 12

PROJECT ENVIRONMENTAL PLAN


Omega South Zone 7 Phase 1

1. DESCRIPTION OF PROJECT

The project is described in the Tender Information Pack issued by WSP and
summarised in this Health & Safety Plan. This includes, but is not limited to, the following
activities;

Mobilisation and Set up


Trial Holes
Unexploded Ordnance Survey
Breaking up of Concrete Slabs if req
Earthworks
Installation of Sub Station
Installation of Utility Services
Installation of Drainage
Construction of Site Access Road
Traffic & Materials Management

Risk Assessments with an associated Method Statement will be produced for each of
these activities prior to the commencement of any element of the works.
The Works is estimated to be a 40 week project to commence 19th August 2013.

2. RESPONSIBILITES WITHIN PROJECT TEAM

Specific environmental site responsibilities on this project are outlined in documents P4.R1.1
(for Contracts Manager) and P4.R1.2 (for Site Manager) of the OHSMS. These documents will
be included in Section 1 of the Health & Safety ‘As Built’ File.
Please read with the site staff structure and the roles and responsibilities for your position as
designated or agreed. Agree your specific role on this project with the Contracts Manager (see
Appendix C of the ‘C22 - Health and Safety Plan’).
Site notice boards must be established as the company standard for the site office and welfare
unit, with all emergency details clearly displayed.
Specific Procedures and Responsibilities
Procedure Description of Task Documents Generated Who

C9 Operational Control R1.C9 - Project Environmental Plan SC/CM


C1 Legal & Other Requirements R1.C1 – Legal Requirements SC/CM
C7 Communication R1.C7 – External Communication CM/SM
C11 Emergency Planning R1.C11 – Emergency Plan CM/SM
R2.C11 – Emergency Contacts
C14 Legal Compliance R1.C1 – Legal Requirements SC/CM
C15 Non Conformance Control R1.C15 – Non Conformance & SC/CM/
Corrective Action Record SM/G
C16 Control of Records R1.C16 – Control of Documents SM/E
C17 Internal Audits R2.C17 – Internal Audit Record SC
R3.C17 – Site Review/Inspection SM
E1 Environment Aspects and R1.E1 – Significant Aspects and SC/CM/
Risk Assessment Impacts Summary SM
R2.E1 – Aspect Significance
Assessment (Pollution)
R3.E1 – Aspect Significance
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 3 of 11
SHEQ / DM/ R1C9/REV02 JAN 12

PROJECT ENVIRONMENTAL PLAN


Omega South Zone 7 Phase 1

Assessment (Resources)
R4.E1 – Significant Aspects Impact
Control Sheet
H&S Site Specific Environmental Method Statements & Induction SM
Standard Information for Site
Workers/Visitors
SC - SHEQ COORDINATOR CM - CONTRACTS MANAGER SM - SITE MANAGER G – GANGER

3. MONITORING AND AWARENESS

3.1 The Site Management Team is required to carry out regular monitoring of the system
and will complete a detailed checklist as part of an Environmental Site Review (detailed
above). It is important that all established procedures are followed and that any
problems are reported immediately. The site will also be subjected to a formal internal
audit to assess the operation of the EMS.

3.2 Environmental awareness will be continually promoted and further improvements


discussed by carrying out Toolbox Talks on a regular basis to ensure that all operations
are carried out to minimise the risk of pollution and reduce the volume of waste
produced on site. All site personnel and sub-contractors will be required to sign the
attendance record for these talks.

3.3 Environmental considerations will form part of the initial site induction, where the
contents of this management plan will be disseminated to all personnel to ensure the
awareness of its contents to all persons on site.

3.4 Noise will be monitored weekly using a handheld noise meter and logged on document
‘Noise Monitoring Record’.

3.5 Dust will be visually monitored daily and records kept within the ‘Dust Monitoring
Record’.

3.6 Vibration will not be monitored as the level of vibration from the infrastructure works will
be limited to compaction and tracking of plant, so is therefore deemed unnecessary.

3.7 There is a requirement to carry out water sampling on 4 watercourses around site.

4. CONTROL OF WORKS

4.1 All incidents, no matter how minor, are to be reported to D. Morgan Site Manager and
Client team (see organisational chart Appendix A). External parties will be contacted if
required by D Morgan Site Management.

4.2 Fuel will be stored on site in limited quantities in a COSHH store which will be bunded,
with a collection tray for spill prevention and control. Refuelling operations will be
undertaken by daily visits from a mobile bowser and will take place in designated areas
where drip trays will be utilised to catch any potential spillages.

4.3 To further mitigate any potential contamination to ground or watercourses, the bowser is
equipped with a quick release fuel nozzle and all operated plant will be equipped with
spill kits to tackle any spillages which may occur (no matter how minor).

New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 4 of 11
SHEQ / DM/ R1C9/REV02 JAN 12

PROJECT ENVIRONMENTAL PLAN


Omega South Zone 7 Phase 1

4.4 All site fitters will be inducted to site rules. Any waste arising from maintenance / fitting
work shall be removed from site by the fitter and disposed of via either the D Morgan
main office fitting service waste agreements (i.e. waste oils, grease cartridges, rags) or
by our sub-contractor’s waste streams.

4.5 Plant, particularly articulated dump trucks, will have designated haul routes and
permitted areas for parking. These vehicles are to avoid causing any undue damage to
flora and fauna which is not to be cleared in this phase of the works. Every effort will be
made to reduce the impact of these works on the local ecology onsite.

4.6 Wherever possible materials will be reused locally not only to reduce waste, but also to
reduce emissions with localised rather than long haul movement of materials. It is also
intended to maximise ‘dig once, place once’ options, minimising double handling of
materials (saving both noise and emissions pollution).

4.7 Any hydraulic breaking operations will be kept to a minimum and within the agreed site
working hours. These operations, wherever possible, will be undertaken away from the
site boundary and local residences.

4.8 Water management will be a high priority on this project. Localised bunding and lagoons
may be required to prevent surface water adversely affecting the works. It may also be
necessary to excavate ‘grips’ or ‘v’ ditches to capture water and channel towards a
holding area (lagoon), preferably the permanent works swales.

4.9 Where water has collected in excavations or sump holes and is required to be pumped
clear, the water will be recharged to adjacent grassed areas of site in order to prevent its
release into any watercourse. If any is suspected to be contaminated (it has oily residues
apparent, odour or discolouration) then it must not be pumped until verified.

4.10 Wherever possible all breakable materials on site will be processed to engineering
materials and used within the works. This will reduce the number of vehicular
movements on the local roads and limit nuisance to the local community.

4.11 During the works all personnel shall remain vigilant to the potential of contaminated
materials. If any materials are suspected to contain contamination (oily residues, odour
or discolouration), then works will stop and samples will be taken to determine whether
or not the materials are contaminated.

4.12 It is believed that asbestos containing materials may be found on site. During the
clearance works all personnel shall be briefed as to the likely presence and on finding
such materials they will be fenced off and a plan for dealing with them put in place. This
will be to confirm that the materials contain asbestos; if notifiable then a specialist sub-
contractor will be procured (if not, then trained D Morgan personnel will undertake the
works); the materials will be double bagged in asbestos bags and placed in an enclosed
skip for offsite disposal to a licensed site to accept asbestos waste.

4.13 There are no trees within this project that require specific protective measures and only
those trees identified in the planning area for clearance will be removed.

4.14 During excavation works it is not anticipated that any archaeological findings will be
made. However, all personnel will observe a watching brief and stop work immediately if
any suspected archaeological findings are made.

4.15 Noise is a particular concern on all construction sites and as such every effort will be
made to limit and control noisy operations. No plant will be left idling when not in use and
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 5 of 11
SHEQ / DM/ R1C9/REV02 JAN 12

PROJECT ENVIRONMENTAL PLAN


Omega South Zone 7 Phase 1

all plant will be suitably silenced in line with its manufacture. Noisy operations will not be
permitted to continue for prolonged periods and not undertaken outside of normal
working hours.

4.16 Background noise monitoring will be undertaken prior to the commencement of the
works. During the construction phase, periodic noise monitoring will be undertaken. This
will be using a handheld device weekly over a 15 minute period at specific locations,
observed at random times during the week.

4.17 Dust control, mitigation and monitoring measures will be put in place for the duration of
remediation and earthworks on site. D Morgan will be employing dust suppression and
sweeping of selected roads on and around site during the works, as and when
considered necessary. The generation of dust on site will be minimised, particularly
during drier weather and controlled by the use of dampening down techniques using
water bowsers. A tractor and bowser will be used to damp down all haul routes and any
other areas with the potential to generate dust. The site supervisory team will monitor
dust generation closely.

4.18 All plant used on site will be modern and well maintained such that any emissions are
within acceptable limits for the plant being used. This also ensures optimum fuel
consumption.

4.19 As the works are scheduled to progress through winter months, there will be a
requirement for temporary lighting. This will be set up with task lighting towers at specific
work areas. All lighting will be set up such that it is focussed on work areas and
consideration will be made to avoid such lighting being directed near to sightings on live
roads.

4.20 In order to maintain a high standard of good practice, Omega Warrington Limited has
requested that the works are registered to the Considerate Constructors Scheme (CCS)
and adhere to the scheme’s code of practice. In accordance with BREEAM
requirements, a CCS score between 32 and 40 will be achieved and all sections within
the scheme will achieve a score more than or equal to 3. The scheme will be
implemented through each sub-contractor.

4.21 Additionally, all office staff must ensure they adopt the D Morgan ‘print both sides policy’
wherever possible and reduce the use of paper and printer ink as far as practicable. All
personnel will be required to follow the ‘switch me off’ policy when leaving a room and
switch off any electrical appliances which do not need to be consuming electricity.

4.22 Every effort must be made to segregate office, canteen and packaging waste and place
in the relevant receptacles for recycling. There will be separate bins for paper,
cardboard, plastics, cans and general waste.

5. EMERGENCY PROCEDURES

5.1 Fuel/Oil (or other potentially damaging substance) Spillage

In the event of a spillage incident the following procedure must be followed;

Eliminate sources of ignition and cordon off area.


Attempt to contain the spillage without risk to personal health and safety.
Inform a member of the Site Supervisory Team of the approximate volume of the
spillage, location and measures taken at present.
New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 6 of 11
SHEQ / DM/ R1C9/REV02 JAN 12

PROJECT ENVIRONMENTAL PLAN


Omega South Zone 7 Phase 1

Where necessary, use plant from the locality to form bunds, excavate to Dump
Trucks or any other action which may contain/mitigate the spillage.
Use spill kits from the plant to clean up or if necessary use adjacent soils.
Do not allow the spillage to enter a watercourse.
Site Manager to inform WSP staff and, if necessary, contact the following;
o Fire 999
o Environment Agency 0800 807060
o United Utilities 0845 746 2200
Site Manager to liaise with the above and agree measures to remediate area.
Site Manager to complete an ‘Incident Report Form’ or NCR.

5.2 Surface Water Release

In the event of surface water release the following procedure must be followed;

Attempt to contain the release without risk to personal health and safety.
Inform a member of the Site Supervisory Team of the approximate volume of
water released, location and measures taken at present.
Where necessary/possible, use plant from the locality to form bunds or excavate
a sump (remembering to check Permit to Dig prior to breaking ground).
Site Supervisory Team to call in bowser or pumps to ensure that the release is
contained in the bund/sump and does not overflow.
Site Manager to inform WSP staff and, if necessary, contact the following;
o Environment Agency 0800 807060
o United Utilities 0845 746 2200
Site Manager to liaise with the above and agree further/improved mitigation
measures.
Site Manager to complete an ‘Incident Report Form’ or NCR.

5.3 Emergency Preparedness

These emergency procedures should be brought to the attention of all site personnel
and, at a suitable time during the works, drills should be carried out to ensure that the
emergency arrangements are effective and understood by all personnel.

New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 7 of 11
SHEQ / DM/ R1C9/REV02 JAN 12

PROJECT ENVIRONMENTAL PLAN


Omega South Zone 7 Phase 1

SITE WASTE MANAGEMENT PLAN

6. SITE WASTE MANAGEMENT PLAN:

In line with the CL:AIRE Development Industry Code of Practice (2008) and under the
objectives of the Site Waste Management Plan Regulations (England) 2008, the client
and contractor shall provide a Site Waste Management Plan.

All materials will be separated/segregated as far as reasonably practicable in order to


minimise the quantities of mixed materials. The waste hierarchy will be considered at all
times.

The site arising materials are detailed in the tender documents and site method
statements. The materials have been identified as soils, brick & concrete, vegetation,
trees & hedges and general waste.

The fate of all materials will be tracked and recorded within the tables on the following
pages of this Plan.

Typically;

Soils
Suitable engineering materials will be used for cut to fill operations. Unsuitable inert materials
will be used within the landform.

Brick and/or Concrete


Any brick and/or concrete arising from the works will be processed (crushed) to produce
engineering materials. Concrete will be crushed to 6F2 specification and brick will be used for
hardcore purposes. Any tarmac arising from the works will be incorporated into the processed
materials in quantities not exceeding those from the ‘Specification for Highway Works’, Series
600, Table 6/1 for the type of aggregate being produced.

Vegetation, Trees & Hedges


All vegetation, trees and hedges will be dealt with in the Site Clearance; chipped and cut up as
necessary. Chippings will remain on site, with cuts and stumps being removed from site.

General Waste
All general waste will be separated into the following categories and recycled as far as possible;
paper, cardboard, plastics, cans and general waste. The estimated quantities of these wastes is
very low, but will be tracked throughout the works.

New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 8 of 11
SHEQ / DM/ R1C9/REV02 JAN 12

PROJECT ENVIRONMENTAL PLAN


Omega South Zone 7 Phase 1

WASTE RECORDS

Date Quantity Waste type Waste Carrier Waste Confirmation of Waste management route Transfer records
3
removed (m ) Management delivery (reused on/off site, recycled received and filed
Facility taken to on/off site, recovery, landfill,
otherwise disposed)

New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 9 of 11
SHEQ / DM/ R1C9/REV02 JAN 12

PROJECT ENVIRONMENTAL PLAN


Omega South Zone 7 Phase 1

ACTUAL QUANTITIES m3 / tonnes (delete as required)

Waste Waste Materials EWC Waste minimisation Volume re-used Volume recycled Volume Volume sent
Type methods used recovered in to landfill
on-site off-site on-site off-site other ways

Concrete 17-01-01
Brick 17-01-02
Inert

Tiles / ceramics 17-01-03


Rubble (mix of 17-01-07
concrete, brick, tiles
etc)
Soils 17-05-04
Metal 17-04-07
Timber 17-02-01
Plasterboard
Non-hazardous

Cable & wiring 17-04-11


Office/canteen 20-01-01
(paper)
20-01-08
(canteen)
Glass 17-02-02
Plastic 17-02-03
Mixed waste
Asbestos 17-06-05
Hazardous

Contaminated soil 17-05-03

Other

New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 10 of 11
SHEQ / DM/ R1C9/REV02 JAN 12

PROJECT ENVIRONMENTAL PLAN


Omega South Zone 7 Phase 1

WASTE QUANTITY COMPARISON

Waste Waste Materials EWC Estimated Quantity Actual Quantity Difference (+/-) Reason for variance
type 3 3
(m / tonnes) – (m / tonnes) - delete
delete as appropriate as appropriate
Concrete 17-01-01
Brick 17-01-02
Inert

Tiles / ceramics 17-01-03


Rubble (mix of 17-01-07
concrete, brick, tiles
etc)
Soils 17-05-04
Metal 17-04-07
Timber 17-02-01
Non-hazardous

Cable & wiring 17-04-11


Office/canteen 20-01-01
(paper)
20-01-08
(canteen)
Glass 17-02-02
Plastic 17-02-03
Mixed waste
Asbestos 17-06-05
Hazardous

Contaminated soil 17-05-03

Other

New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 11 of 11
Along with any client objectives issued and to assist the project team and contractors the following objectives have
been agreed with the project team

• Minimize dust during the project to surrounding environment


• Minimise waste and maximise recycling with a target of 2% waste to landfill
• Environmental awareness tool box talks to operatives on refuelling, house keeping, recycling etc
• Monitor aspects and impacts register

PRINCIPAL ENVIRONMENTAL LEGISLATION RELATING TO THE PROJECT

Refer to McLaren Legislation Register QMS 005 on McLaren Portal.

14.2 Liaison with Site Neighbours

Undertake leaflet or letter drops to all close neighbours to the site to inform them of the likely start date(s) for
construction and for any operations that may be particularly noisy or carried out an unsociable hours. This practice is
considered good practice as informed neighbours are less likely to complain.

14.3 Establishment of Site Accommodation

Wherever possible, the location for accommodation will be reviewed to avoid visual impact to adjoining neighbours
and for wastewater discharge to a suitable approved sewer. Alternative arrangements shall be made for disposal of
sewage via specialist contractor should this not be possible. If possible the accommodation will be sited on an area of
proposed hardstanding for incorporation into the contract works as this will avoid disruption of the existing
environment.

14.4 Environmental Impact & Aspect Control Measures

The following key control measures will assist in minimising the environmental impact. See also Pre-Commencement
Health Safety and Environmental Planning Meeting Record SAF01 for site specific environmental aspects and impacts
identification. ENF001 05/13 Environmental Aspects & Impacts Register found at Appendix 8.

14.5 Earthworks Arisings

Arisings from earthworks and piling shall be stored on agreed areas for the placement of excavated materials on site.
Use arisings as much as practicable on site to minimise off-site disposal.
The objective is to ensure that the least impact is generated and ecologically sensitive areas of the site are not
damaged by indiscriminate dumping or storage.

14.6 Vehicles and Plant

If at all possible, designate specific times for deliveries outside normal peak hours and to avoid unsociable hours and
consequential disruption to neighbours.
Plant shall be positioned so that exhaust emissions do not cause damage or nuisance, and kept to a minimum by
regular maintenance.

14.7 Diesel Storage and Refuelling

Ensure that all diesel stored on site is in a secure tank and properly bunded. As far as practicable, ensure that all
refuelling is undertaken in a safe, appropriately designated area. Bunds should be of adequate capacity to contain
110% of the capacity, leakproof and kept empty of rainwater and other materials. This will avoid pollution of the
ground, and to avoid prosecution for pollution or nuisance.

MMS 046 | 02/13 rev i 35 SHEQ MANAGEMENT PLAN |


14.8 Site Roads/Access routes

Ensure that site access roads are kept as clean as possible to prevent excessive contamination to the public highway.
Speed restrictions may also be imposed to prevent spread of dust.

14.9 Plant and Wheel Washing

No plant or equipment shall be washed out where there is the possibility of contamination to any natural
watercourse, particularly regarding concrete. When necessary, special washing facilities / locations shall be
established.

14.10 Storage of materials, fuels, oils and chemicals

All fuel, oil and chemicals shall be stored in containers specifically manufactured for the purpose, and/or
bunded/double skinned to prevent contamination in the event of spillage, damage. Tank capacity shall be checked
before delivery to prevent overfilling. Special care shall be taken when receiving and storing items such as oil,
chemicals, cement, lime, and paint to prevent spillage and contamination.

The contents of storage containers shall be clearly marked, to prevent accidental cross contamination.

‘Drums’ shall also be stored with lids uppermost to prevent leaking and contamination.

A licensed waste disposal contractor or the original supplier shall remove leaking or empty containers from site.

All valves and nozzles shall be protected from vandalism and unauthorised use by means of a padlock. Where this is
not possible, tanks/bowsers shall be stored in secure compound areas.

14.11 Noise

Choose plant and machinery to minimise noise emissions consistent with the technical requirements of the works. Use
noise suppression equipment if practicable. Adhere to any working hour restrictions that have been placed on the
project. Be vigilant at avoiding inadvertent excessive noise during night-time operations.

14.12 Dust

Provide damping down methods of any operations that may generate dust, these may include such activities as
earthworks, cutting, planning and sanding or by utilising plant and equipment with dust extraction and collection
facilities. Speed restrictions may assist on site access roads to mitigate this.

14.13 Lighting

The use of lighting for the works and temporary accommodation shall be carefully selected to ensure it is efficient and
effective, and positioned to ensure that light spillage is kept to a minimum.

14.14 Visual appearance

Care should be taken to ensure an overall positive attitude to housekeeping of the site, such as fencing, storage or
equipment and materials, avoidance of litter and windblown waste etc. This will provide all parties concerned with a
good impression of environmental controls leading to an enhanced perception

MMS 046 | 02/13 rev i 36 SHEQ MANAGEMENT PLAN |


15. WASTE MANAGEMENT

15.1 Waste Storage

Take active steps to ensure that MCL responsibilities under the Environmental Permitting Regulations 2010 and the
Waste (England and Wales) Regulations 2011 are properly discharged, particularly in the accurate completion, and
secure retention, of waste transfer notes. Consider possibilities for segregation of waste into different mainstream
material types (wood, metals, etc) for possible recycling.

Waste shall be stored appropriately depending on type and classification, i.e. Controlled waste, Hazardous waste and
General wastes. In any event, waste storage shall be kept to a minimum and in suitable containers or locations for
disposal. Whenever possible segregation shall be implemented to allow for recycling.

Where Hazardous waste is identified, it shall only be segregated and stored following approved methods from the
Environment Agency.

MCL will maintain a Site Waste Management Plan (SWMP) in accordance with The Site Waste Management Plan
Regulations 2008 this can be found at in the master filing system located in the site office. The SWMP will be kept for
two years after the completion of the project and archived accordingly.

15.2 Waste Disposal

Duty of care shall be applied to all waste, and it shall be ensured that all waste disposals are carried out by registered
contractors and records of disposal controlled by waste transfer notes. Waste disposal containers/vehicles shall be
covered during transport to prevent contents escaping.

Hazardous waste shall be controlled and disposed of following the Environment Agency approved procedures, and by
implementing their consignment note system.

Hazardous Waste producer licence is to be applied prior to the commencement of the project

16. QUALITY PLAN

16.1 Project Description

A brief description of the works is detailed in the SHEQ Plan.

16.2 Management Responsibility

It is the Site Managers responsibility to ensure that the requirements of MCL’s Quality Management Policy Manual
and this Project Specific Quality Plan are implemented. The Site Manager will delegate responsibilities for quality
activities to members of the site management team.

Details of the site management structure are given in the SHEQ Plan.

16.3 Quality Plan & Quality System

16.4 Quality Policy

A copy of the Company’s Integrated Health Safety Quality and Environmental Policy is detailed in MMP which can be
found in all location.

MMS 046 | 02/13 rev i 37 SHEQ MANAGEMENT PLAN |


16.5 Quality Manual & Project Quality Plan

To meet the requirements of the client, MCL applies a quality system in conjunction with other management controls.
MCL’s Management Procedures Manual (MMP) describes the system in detail. Specific contract Quality Management
requirements are detailed within this Quality Plan, or can be found in other sections of the SHEQ Plan and the
Company MMP procedures.

17. CONTRACT REVIEW

17.1 Contract Review Procedures

Contract Review Procedures are detailed within the Company MMP manual specifically by the Customer Focus and
Customer Related Processes (Tenders) process flow chart, which includes but is not limited to:-

• Tender Review
• Tender Adjudication
• Contract Award and Mobilisation
• Employer Pre – Contract Start Meeting
• Internal Pre – Contract Start Meeting
• Progress meetings

Reviews take place at award of contract, prior to commencing works and at regular intervals during the course of the
contract (usually monthly).

18. DESIGN CONTROL

18.1 Designer

The designer(s) where applicable, are detailed in the SHEQ Plan Directory

The designers will be accredited to a recognised professional body ie RIBA, ICE etc. and a copy of the certification will
be held on the designers file.

18.2 Design Control Procedures

Design will be controlled in accordance with Company MMP Manual specifically the Design and Development Process
Description flow chart which includes but is not limited to:-

• Identification of Design Requirements


• Risk Assessments
• Design Approval
• Appointing and Control of Design Authority
• Design Review Meeting Minutes

18.3 Design Review / Liaison with Client

Design meetings between the respective organisations will take place to review the design process. Calculations and
drawings will be forwarded to the client or their representative for comment / approval prior to related construction
works taking place. MMS033 – Design Approval Tracking Schedule refers.

MMS 046 | 02/13 rev i 38 SHEQ MANAGEMENT PLAN |

S-ar putea să vă placă și