Sunteți pe pagina 1din 444

This softawre is based on Standard Data book for analysis of Rates for Road and Bridge

Works

This Software runs on Microsoft Excel

INPUT- Input the usage rates of Plant & Machinery, labour and material as applicable

SUMMARY - In this sheet summary of all the rates analysized is presented

ANALYSIS- The analysis has been presented in 16 nos. of spread sheets

Worksheet- 1 : CHAPTER-1 CARRIAGE OF MATERIALS

Worksheet- 2 : CHAPTER-2 SITE CLEARANCE

Worksheet- 3 : CHAPTER-3 EARTH WORK, EROSION CONTROL AND DRAINAGE

Worksheet- 4 : CHAPTER-4 SUB-BASES, BASES (NON- BITUMINOUS) AND


SHOULDERS

Worksheet- 5 : CHAPTER-5 BASES AND SURFACE COURSES (BITUMINOUS)

Worksheet- 6 : CHAPTER-6 CEMENT CONCRETE PAVEMENTS

Worksheet- 7 : CHAPTER-7 GEOSYNTHETICS AND REINFORCED EARTH

Worksheet- 8 : CHAPTER-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD


APPURTENANCES

Worksheet- 9 : CHAPTER-9 PIPE CULVERTS

Worksheet- 10 : CHAPTER-10 MAINTENANCE OF ROADS

Worksheet- 11 : CHAPTER-11 HORTICULTURE

Worksheet- 12 : CHAPTER-12 FOUNDATIONS

Worksheet- 13 : CHAPTER-13 SUB-STRUCTURE

Worksheet- 14 : CHAPTER-14 SUPER-STRUCTURE

Worksheet- 15 : CHAPTER-15 RIVER TRAINING AND PROTECTION WORKS

Worksheet- 16 : CHAPTER-16 REPAIR AND REHABILITATION


INPUT
(A) Usage Rates of Plant and Machinery
Output of
Sl. No. Description of Machine Activity Output Unit Rate
Machine

P&M-001 Air Compressor General Purpose capacity in cfm 170/250 hour 293.76

P&M-002 Batching and Mixing Plant (a) 30 cum capacity Concrete Mixing cum/hour 20 hour 2457

P&M-003 Batching and Mixing Plant (b) 15 - 20 cum capacity Concrete Mixing cum/hour 13 hour 1704.24
P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour 986.04
P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 182.52
P&M-006 Concrete Paver Finisher with 40 HP Motor Paving of concrete surface cum / hour 20 hour 2637.36
P&M-007 Concrete Pump of 45 & 30 cum capacity Pumping of concrete cum / hour 33 / 22 hour 234.36
P&M-008 Concrete Bucket For Pouring concrete capacity in cum 1 hour 14.472
P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour 211.68
P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 199
P&M-011 Crane (a) 80 tonnes Lifting Purpose hour 1176.12
P&M-012 Cranes b) 35 tonnes Lifting Purpose hour 784.62
P&M-013 Cranes c) 3 tonnes Lifting Purpose hour 525
P&M-014 Dozer D - 80 - A 12 Spreading /Cutting / Clearing cum/hour 300/ 150/250 hour 3135.24
P&M-015 Dozer D - 50 - A 15 Spreading /Cutting / Clearing cum/hour 200/ 120/150 hour 2028.78
P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour 735.48

P&M-017 Front End loader 1 cum bucket capacity Soil loading / Aggregate loading cum/hour 60 /25 hour 1148

P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour 2211
P&M-019 Generator( b) 63 KVA Genration of electric Energy KVA 50 hour 361.8
P&M-020 GSB Plant 50 cum Producing GSB cum/hour 40 hour 872.64
P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix cum/hour 40 hour 42304
P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour 32155
P&M-023 Hotmix Plant - 60 to 90 TPH capacity DBM/BM/SDC/ Premix cum/hour 25 hour 27082
P&M-024 Hotmix Plant - 40 to 60 TPH capacity DBM/BM/SDC/ Premix cum/hour 17 hour 18918
P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour 2423.52
Soil Ordinary/Soil Marshy / Soil
P&M-026 Hydraulic Excavator of 1 cum bucket
Unsuitable
cum/hour 60 /60 /60 hour 1516.32
P&M-027 Integrated Stone Crusher 100THP Crushing of Spalls TPH 100 hour 7967.16
P&M-028 Integrated Stone Crusher 200 HP Crushing of Spalls TPH 200 hour 16760.52
P&M-029 Kerb Casting Machine Kerb Making Rm/hour 80 hour 279.72
P&M-030 Mastic Cooker Mastic Wearing coat capacity in tonne 1 hour 54.81
P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 456

P&M-032 Motor Grader 3.35 mtr blade Clearing /Spreading /GSB /WBM cum/hour 200/200/50/50 hour 2450

P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal sqm/hour 2700 hour 926.64
Paver Finisher Hydrostatic with sensor control 100
P&M-034
TPH
Paving of DBM/ BM/SDC/ Premix cum/hour 40 hour 3046

P&M-035 Paver Finisher Mechanical 100 TPH Paving of WMM /Paving of DLC cum/hour 40/30 hour 1382
0.75 m dia to 1.2 m dia Boring
P&M-036 Piling Rig with Bantonite Pump
attachment
Rm/hour 2 to 3 hour 5023.08
P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface cum/hour 25 hour 1143.72
P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour 1.5 to 2.00 hour 3834
P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 827.28

P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands hour 116.1

P&M-041 Ripper Scarifying cum/hour 60 hour 25.704


P&M-042 Rotavator Scarifying cum/hour 25 hour 15.66
P&M-043 Road marking machine Road marking Sqm/hour 100 hour 85.86

P&M-044 Smooth Wheeled Roller 8 tonne Soil Compaction /BM Compaction cum/hour 70/25 hour 649

P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 1051.92
Transportation of soil, GSB, WMM,
P&M-046 Tipper - 5 cum
Hotmix etc.
Capacity in cum 5.5 km 22.356
Transportation of soil, GSB, WMM,
P&M-047 Tipper - 5 cum
Hotmix etc.
Capacity in cum 5.5 tonne.km 2.6784
Transportation of soil, GSB, WMM,
P&M-048 Tipper - 5 cum
Hotmix etc.
Capacity in cum 5.5 hour 846

P&M-049 Transit Mixer 4.0/4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 hour 854.55

P&M-050 Transit Mixer 4/4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 tonne.km 4.32

P&M-051 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 hour 784.62

P&M-052 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 tonne.km 5.886
P&M-053 Tractor Pulling capacity in HP 50 hour 171.018
P&M-054 Tractor with Rotovator Rate of Tractor + Rotevator hour 227.88
P&M-055 Tractor with Ripper Rate of Tractor 6+ Ripper hour 285.12
P&M-056 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km 20.088
P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 752
P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 tonne.km 2.268
P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM cum/hour 100/60/60 hour 1720
P&M-060 Water Tanker Water Transport capacity in KL 6 hour 111.24
P&M-061 Water Tanker Water Transport capacity in KL 6 km 22.356
P&M-062 Wet Mix Plant 60 TPH Wet Mix cum/hour 25 hour 1107
Sl. No. Description of Machine Unit
P&M-063 Air compressor with pneumatic chisel attachment for cutting hard clay. hour 513
P&M-064 Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour hour 2279.88
P&M-065 Belt conveyor system hour Value
P&M-066 Boat to carry atleast 20 persons hour 142.56
P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output) hour 4787.64
P&M-068 Cement concrete batch mix plant @ 75 cum per hour hour 2052
P&M-069 Cold milling machine @ 20 cum per hour hour 855.36
P&M-070 Crane 5 tonne capacity hour 599.4
P&M-071 Crane 10 tonne capacity hour 627.48
P&M-072 Crane 15 tonne capacity hour 770.04
P&M-073 Crane 20 tonne capacity hour 785.16
P&M-074 Crane 40 T capacity hour 1166.4
P&M-075 Crane with grab 0.75 cum capacity hour 1176.12
P&M-076 Compressor with guniting equipment along with accessories hour Value
P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. hour 1107
P&M-078 Epoxy Injection gun hour Value
P&M-079 Generator 33 KVA hour 342.36
P&M-080 Generator 100 KVA hour 1635
P&M-081 Generator 250 KVA hour 3101
Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method of well
P&M-082
sinking.
hour Value
P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement) hour 214.92
P&M-084 Jack for Lifting 40 tonne lifting capacity. day 758.16
P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig) hrs 5023.08

P&M-086 Plate compactor hour 142.992


P&M-087 Snow blower equipment 140 HP @ 600 cum per hour hour Value

P&M-088 Texturing machine (for rigid pavement) hour 71.496

P&M-089 Truck Trailor 30 tonne capacity hour 1864.08

P&M-090 Truck Trailor 30 tonne capacity t.km 2.268

P&M-091 Tunnel Boring machine hour Value

P&M-092 Vibrating Pile driving hammer complete with power unit and accessories. hour Value

P&M-093 Wet Mix Plant 100 TPH hour 1128.6

P&M-094 Wet Mix Plant 75 TPH hour 2419

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k


lfefr
lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k
lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k lfefr &lg&eq[; vfHk;ark] rduhdh ijh{k.k
lfefr&lg&eq[; vfHk;ark
eq[; vfHk;ark] ÅtkZ foHkkx] >kj[k.M] jk¡ph dks"kkax
xzkeh.k fodkl foHkkx] >kj[k.M] jk¡ph
eaf=keaMy ¼fuxjkuh½ foHkkx]
>kj[k.M] jk¡ph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k
lfefr&lg&vfHk;ark izeq[k lfefr&lg&vfHk;ark izeq[k lfefr&lg&vfHk;ark izeq[k]
ty lalk/ku foHkkx] >kj[k.M] jk¡ph is;ty ,oa LoPNrk foHkkx] >kj[k.M] jk¡ph xzkeh.k dk;Z foHkkx] >kj[k.M] jk¡ph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k la;kstd] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&vfHk;ark izeq[k] lfefr&lg&vfHk;ark izeq[k
Hkou fuekZ.k foHkkx] >kj[k.M] jk¡ph iFk fuekZ.k foHkkx] >kj[k.M] jk¡ph
(B) Labour

Sl. No. Description of Labour Basic Rate D.A. Unit Rate

L-01 Blacksmith (IInd class) 153.00 67.57 day 220.57

L-02 Blacksmith (Ist class)/ Welder/ Plumber/ Electrician 172.00 75.19 day 247.19

L-03 Blaster (Stone cutter) 214.00 90.89 day 304.89

L-04 Carpenter I Class 172.00 75.19 day 247.19

L-05 Chiseller (Head Mazdoor) 135.00 60.43 day 195.43

L-06 Driller (Jumper) 151.00 67.57 day 218.57

L-07 Diver 151.00 67.57 day 218.57

L-08 Fitter 176.00 75.19 day 251.19

L-09 Mali 151.00 67.57 day 218.57

L-10 Mason (IInd class) 153.00 67.57 day 220.57

L-11 Mason (Ist class) 172.00 75.19 day 247.19

L-12 Mate / Supervisor 135.00 60.43 day 195.43

L-13 Mazdoor 127.00 60.43 day 187.43

L-14 Mazdoor/Dresser (Semi Skilled) 130.00 60.43 day 190.43

L-15 Mazdoor/Dresser/Sinker (Skilled) 151.00 67.57 day 218.57

L-16 Medical Officer day

L-17 Operator(grouting) 143.00 67.57 day 210.57

L-18 Painter I class 161.00 75.19 day 236.19

L-19 Para medical personnel day

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k


lfefr
lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k
lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k lfefr &lg&eq[; vfHk;ark] rduhdh ijh{k.k
lfefr&lg&eq[; vfHk;ark
eq[; vfHk;ark] ÅtkZ foHkkx] >kj[k.M] jk¡ph dks"kkax
xzkeh.k fodkl foHkkx] >kj[k.M] jk¡ph
eaf=keaMy ¼fuxjkuh½ foHkkx]
>kj[k.M] jk¡ph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k
lfefr&lg&vfHk;ark izeq[k lfefr&lg&vfHk;ark izeq[k lfefr&lg&vfHk;ark izeq[k]
ty lalk/ku foHkkx] >kj[k.M] jk¡ph is;ty ,oa LoPNrk foHkkx] >kj[k.M] jk¡ph xzkeh.k dk;Z foHkkx] >kj[k.M] jk¡ph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k la;kstd] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&vfHk;ark izeq[k] lfefr&lg&vfHk;ark izeq[k
Hkou fuekZ.k foHkkx] >kj[k.M] jk¡ph iFk fuekZ.k foHkkx] >kj[k.M] jk¡ph
(C) Materials

Sl. No. Description Unit Rate

M-001 Stone Boulder of size 150 mm and below at Quarry cum 525.85

M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at Quarry cum 550.80

M-003 Boulder with minimum size of 300 mm for Pitching at Quarry cum 352.58

M-004 Coarse sand at Quarry (Equivalent to Koliwar sand) cum 209.13

M-005 Coarse sand at Quarry (Equivalent to Koliwar sand) cum 209.13

M-006 Fine sand at Quarry cum 111.50

M-007 Moorum at Quarry cum 122.64

M-008 Gravel/Quarry spall at Quarry Cum 325.05

M-009 Granular Material or hard murrum for GSB works at Quarry Cum 156.79

M-010 Granular Material or hard murrum for GSB works at Quarry Cum 156.79

M-011 Fly ash conforming to IS: 3812 ( Part II & I) at source - 0.00

M-012 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) at Quarry Cum 630.22
Rate at
Rate at
Description Unit Plant (HMP /
Quarry Site
Batching)
M-013 Close graded Granular sub-base Material 53 mm to 9.5 mm at Quarry cum 766.35 766.35

M-014 Close graded Granular sub-base Material 37.5 mm to 9.5 mm at Quarry cum 838.84 838.84

M-015 Close graded Granular sub-base Material 26.5 mm to 9.5 mm at Quarry cum 823.07 823.07

M-016 Close graded Granular sub-base Material 9.5 mm to 4.75 mm at Quarry cum 724.27 724.27

M-017 Close graded Granular sub-base Material 9.5 mm to 2.36 mm at Quarry cum 648.35 648.35

M-018 Close graded Granular sub-base Material 4.75mm to 2.36 mm at Quarry cum 494.08 494.08

M-019 Close graded Granular sub-base Material 4.75mm to 75 micron mm at Quarry cum 471.39 471.39

M-020 Close graded Granular sub-base Material 2.36 mm at Quarry cum 403.33 403.33

M-021 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve at Quarry cum 215.86 215.86

M-022 Coarse graded Granular sub-base Material 2.36 mm & below at Quarry cum 244.51 244.51

M-023 Coarse graded Granular sub-base Material 4.75mm to 75 micron mm at Quarry cum 267.20 267.20

M-024 Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm at Quarry cum 267.20 267.20

M-025 Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm at Quarry cum 764.37 764.37

M-026 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm at Quarry cum 731.42 731.42

M-027 Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm at Quarry cum 805.88 805.88

M-028 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm at Quarry cum 731.42 731.42

M-029 Coarse graded Granular sub-base Material 53 mm to 26 .5 mm at Quarry cum 681.31 681.31

M-030 Aggregates below 5.6 mm at Quarry cum 221.82 221.82


M-031 Aggregates 22.4 mm to 2.36 mm at Quarry cum 817.35 817.35
M-032 Aggregates 22.4 mm to 5.6 mm at Quarry cum 788.72 788.72
M-033 Aggregates 45 mm to 2.8 mm at Quarry cum 647.13 647.13
M-034 Aggregates 45 mm to 22.4 mm at Quarry cum 743.66 743.66
M-035 Aggregates 53 mm to 2.8 mm at Quarry cum 644.08 644.08
M-036 Aggregates 53 mm to 22.4 mm at Quarry cum 567.52 567.52
M-037 Aggregates 63 mm to 2.8 mm at Quarry cum 734.30 734.30
M-038 Aggregates 63 mm to 45 mm at Quarry cum 547.62 547.62
M-039 Aggregates 90 mm to 45 mm at Quarry cum 477.96 477.96
M-040 Aggregates 10 mm to 5 mm at Quarry cum 720.97 720.97
M-041 Aggregates 11.2 mm to 0.09 mm at Quarry cum 516.77 516.77
M-042 Aggregates 13.2 mm to 0.09 mm at Quarry cum 641.56 641.56
M-043 Aggregates 13.2 mm to 5.6 mm at Quarry cum 652.90 652.90
M-044 Aggregates 13.2 mm to 10 mm at Quarry cum 936.51 936.51
M-045 Aggregates 20 mm to 10 mm at Quarry cum 1119.81 1119.81
M-046 Aggregates 25 mm to 10 mm at Quarry cum 937.63 937.63
M-047 Aggregates 19 mm to 6 mm at Quarry cum 871.76 871.76
M-048 Aggregates 37.5 mm to 19 mm at Quarry cum 853.15 853.15
M-049 Aggregates 37.5 mm to 25 mm at Quarry cum 772.96 772.96
M-050 Aggregates 6 mm nominal size at Quarry cum 497.86 497.86
M-051 Aggregates 10 mm nominal size at Quarry cum 674.15 674.15
M-052 Aggregates 13.2/12.5 mm nominal size at Quarry cum 777.69 777.69
M-053 Aggregates 20 mm nominal size at Quarry cum 887.53 887.53
M-054 Aggregates 25 mm nominal size at Quarry cum 887.53 887.53
M-055 Aggregates 40 mm nominal size at Quarry cum 780.12 780.12

Sl. No. Description Unit Rate

M-056 AC pipe 100 mm dia metre 50.28

M-057 Acrylic polymer bonding coat litre 129.48

M-058 Alluminium Paint litre 193.17

M-059 Aluminium alloy plate 2mm Thick sqm 1580.88

M-060 Aluminium alloy/galvanised steel tonne 46239.26


Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards lettering, cost of angle iron, cost of
M-061 sqm 7902.33
drilling holes, nuts, bolts etc.and signs as applicable
M-062 Road studs/RPM 100 x 100 mm fitted with lense reflectors vide cl. 804.2 of MORTH (5th Revision) nos 167.01

M-063 Barbed wire kg 58.68

M-064 Bearing (Cost of parts) nos #VALUE!

M-065 Bearing (Cast steel rocker bearing assembly of 250 tonne ) nos 55883.28
Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel
M-066 nos 0.50
laminates by the process of vulcanisation,)
M-067 Bearing (Forged steel roller bearing of 250 tonne nos 37256.21

Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against
M-068 nos 31752.36
stainless steel mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all components

M-069 Bearing (PTFE sliding plate bearing assembly of 80 tonnes ) nos #VALUE!

M-070 Bearing (Supply of sliding plate bearing of 80 tonne) nos 22579.27

M-071 Bentonite kg 2.24

M-072 Binding wire kg 62.52

M-073 Bitumen ( Cationic Emulsion ) Ex- Bokaro (M.S) Packed tonne 38918.67

M-074 Bitumen (VG-30 Grade) Ex- Bokaroi Packed tonne 39879.31

M-075 Bitumen (VG-10 Grade) Ex- Bokaro Packed tonne 38958.19

M-076 Bitumen (Cutback ) Ex- Bokaro Packed tonne 40973.30

M-077 Bitumen (emulsion) Ex- Bokaro (M.S) Packed tonne 40114.31

M-078 Bitumen (modified graded) Ex - Bokaro (CRMB - 55) Packed tonne 42274.22

M-079 Brick - 75A each 4.72

M-080 C.I.shoes for the pile kg 56.39

M-081 Cement (PSC / PPC) tonne 5982.46

M-082 Cold twisted bars (HYSD Bars) as per IS:1786-2008 average rate tonne 44187.50

M-083 Coller for joints 300 mm dia nos #VALUE!

M-084 Compressible Fibre Board(20mm thick) sqm 603.53

M-085 Connectors/ Staples each #VALUE!

M-086 Copper Plate(12m long x 250mmwide) kg 481.39


M-087 Corrosion resistant Structural steel tonne 48095.30

M-088 Corrugated sheet, 3 mm thick, "Thrie" beam section railing kg 37.59

M-089 Credit for excavated rock found suitable for use cum 102.33

M-090 Curing compound litre 91.13

M-091 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 451.08

M-092 Earth Cost or compensation for earth taken from private land cum 25.10
Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit
M-093 metre 19422.70
conforming to clause 915.1 of IRC: 83 (part II),
M-094 Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each 100 nos 1426.61

M-095 Epoxy compound with accessories for preparing epoxy mortar kg 282.81

M-096 Epoxy mortar kg 169.69

M-097 Epoxy primer kg 9.01

M-098 Epoxy resin-hardner mix for prime coat kg 481.82

M-099 Flag of red color cloth 600 x 600 mm each 34.46

M-100 Flowering Plants each 23.94

M-101 Galvanised MS flat clamp nos 11.07

M-102 Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size. sqm 73.09

M-103 Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long kg 38.63

M-104 Gelatin 80% kg 112.77

M-105 Geo grids sqm 77.51

M-106 Geomembrane sqm 77.51

M-107 Geonets sqm 77.51

M-108 Geotextile sqm 60.75

M-109 Geotextile filter fabric sqm 60.75

M-110 GI bolt 10 mm Dia nos 11.07

M-111 Grouting pump with agitator hour 112.77

M-112 Grass (Doob) kg 3.04

M-113 Grass (Fine) kg 3.04

M-114 HDPE pipes 75mm dia metre 152.45

M-115 HDPE pipes 90mm dia metre 152.45

M-116 Hedge plants each 22.80

M-117 Helical pipes 600mm diameter metre #VALUE!

M-118 Hot applied thermoplastic compound (Sp. Gravity - 2.10) litre 127.55

M-119 HTS strand tonne 62418.78

M-120 Joint Sealant Compound kg 17.81

M-121 Jute netting, open weave, 2.5 cm square opening for seeding and Mulching sqm 28.71

M-122 LDO for steam curing litre #VALUE!

M-123 M.S. Clamps nos 24.33

M-124 M.S. Clamps kg 66.31

M-125 M.S.shoes @ 35 Kg per pile of 15 m kg 42.08

M-126 Mild Steel bars tonne 49279.84

Modular strip/box seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm
M-127 assembly comprising of edge beams, central beam,2 modules chloroprene seal, anchorage elements, support and control system, metre 21404.46
all steel sections protected against corrosion and installed by the manufacturer or his authorised representative
Modular strip/box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm box/box seal joint
assembly containing 3 modules/cells and comprising of edge beams, two central beams, chloroprene seal, anchorage elements,
M-128 metre #VALUE!
support and control system, all steel sections protected against corrosion and installed by the manufacturer or his authorised
representative

M-129 Nipples 12mm nos 5.64

M-130 Nuts and bolts kg 45.42

M-131 Paint litre 138.35

M-132 Pavement Marking Paint litre 138.35

M-133 Paving Fabric sqm 60.75

M-134 Perforated geosynthetic pipe 150 mm dia metre 65.26

M-135 Perforated pipe of cement concrete, internal dia 100 mm metre 107.89

M-136 Pesticide kg 56.39

M-137 Pipes 200 mm dia, 2.5 m long for drainage metre 124.65

M-138 Plastic sheath, 1.25 mm thick for dowel bars sqm 10.96

M-139 Plastic tubes 50 cm dia, 1.2 m high nos #VALUE!

M-140 Polymer braids metre #VALUE!

M-141 Pre moulded Joint filler,25 mm thick for expansion joint. sqm 708.07

M-142 Pre-coated stone chips of 13.2 mm nominal size cum #VALUE!

Preformed continuous chloroprene elastomer or closed cell foam sealing element with high tear strength, vulcanised in a single
M-143 metre #VALUE!
operation for the full length of a joint to ensure water tightness.

M-144 Pre-moulded asphalt filler board sqm 708.07

M-145 Pre-packed cement based polymer concrete of strength 45 Mpa at 28 days kg #VALUE!

M-146 Primer kg 90.84

M-147 Quick setting compound kg 99.20

M-148 Random Rubble Stone cum 359.72

M-149 RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia metre 4395.60

M-150 RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia metre 5319.60

M-151 RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia metre 924.00

M-152 Reflectorising glass beads kg 70.68

M-153 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips) metre 480.32

M-154 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips) metre 480.32
Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced polymer/polymeric
M-155 metre 480.32
strips)
M-156 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips) metre 237.03

M-157 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips) metre 237.03

M-158 Rivets each 5.64

M-159 Sand bags (Cost of sand and Empty cement bag) nos 1.73

M-160 Sapling 2 m high 25 mm dia each 17.54

M-161 Scrap tyres of size 900 x 20 nos 59.20

M-162 Seeds kg 21.93

M-163 Selected earth (Including royality @ Rs. 24.0 per cum & compensation @ Rs. 1.10 per cum) cum 25.10

M-164 Separation Membrane of impermeable plastic sheeting 125 micron thick sqm 11.00

M-165 Sheathing duct metre 61.80

M-166 Shrubs each 11.40

M-167 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing cum 528.65

M-168 Sodium vapour lamp each 679.79

M-169 Square Rubble Coursed Stone cum 360.24

M-170 Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level each #VALUE!
M-171 Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level each #VALUE!

M-172 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos 90.84

M-173 Steel helmet and cushion block on top of pile head during driving. kg 51.16

M-174 Steel pipe 25 mm external dia as per IS:1239 metre 97.11

M-175 Steel pipe 50 mm external dia as per IS:1239 metre 172.29

M-176 Steel wire rope 20 mm kg 29.76

M-177 Steel wire rope 40 mm kg 29.76

M-178 Strip seal expansion join metre 6043.69

M-179 Structural Steel average rate tonne 48095.30

M-180 Super plastisizer admixture IS marked as per 9103-1999 kg 112.77

M-181 Synthetic Geogrids as per clause 3102.8 and approved design and specifications. sqm 85.89

M-182 Through and bond stone each 6.06

M-183 Tie rods 20mm diameter nos 47.51

M-184 Tiles size 300 x 300 mm and 25 mm thick each 23.18

M-185 Timber cum 31666.24

M-186 Traffic cones with 150 mm reflective sleeve nos 394.70

M-187 Tube anchorage set complete with bearing plate, permanent wedges etc nos 34.35

M-188 Unstaked lime tonne 4427.31

M-189 Water KL 167.07

M-190 Water based cement paint litre 75.18

M-191 Welded steel wire fabric Kg. #VALUE!

M-192 Wire mesh 50mm x 50mm size of 3mm wire kg 30.28

M-193 Wooden ballies 2" Dia for bracing each 17.81

M-194 Wooden ballies 8" Dia and 9 m long (9 m @ Rs. 43.00/m) each 49.23

M-195 Wooden packing cum #VALUE!

M-196 Wooden staff for fastening of flag 25 mm dia, 1.0 m long each 22.52

M-074 B VG-30 Grade Bulk Bitumen (Ex-Haldia) MT 35167.20

Overheads for Road Works 0.1

Contractors profit for Road Works 0.1


for input of Overheads or Contractors profit please type in column C as
Overheads for Bridge Works 0.25
like below
Type symble of apostrope(') then input value then one space then
Overheads for Bridge Works (Rehabilitation) 0.3
symble of percentage (%) for example '08 %
Contractors profit for Bridge Works 0.1

Lead from Mixing Plant to working site 1 km

Lead for E/W borow area to site 1 km

Lead for fly ash from source to site 1 km


Items No. Summary of Rates calculated and used for analysis of rates of other items Unit Rate

per cm height
Item 8.3 Printing new letter and figures of any shade (ii) English Roman
per letter
0.40

Item 8.8 Painting Two Coats on New Concrete Surfaces sqm 46.00
Item 8.9 Painting angle iron post two coats sqm 40.00

Item 12.6 (B) Cement mortor 1:2 (Excluding OH & CP) cum 4392.00

Item 12.6 (A) Cement mortor 1:3 (Excluding OH & CP) cum 3447.00

Item 12.6 (D) Cement mortor 1:6 (Excluding OH & CP) cum 2179.00

Item 12.7 (A ) Course Rubble masonary in cement mortor 1:3 (including OH & CP) cum 3034.00

Item 12.7 ( B) Random Rubble masonary in cement mortor 1:6 (including OH & CP) cum 2977.00

Item 12.8 (A) PCC Grade M15 including OH & CP for Open Foundation by Mixer cum 4259.00

Item 12.8 (A) PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 2979.00

Item 12.8 (B)


PCC
PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3382.00

Item 12.8 (C) RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3402.00
Item 12.8 (C)
RCC
RCC Grade M20 including OH & CP for Open Foundation by Batching Plant cum 4746.00
RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (C)
Batching Plant
cum 3319.00

Item 12.8 (D) PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3713.00

Item 12.8 (D) PCC Grade M25 including OH & CP for Open Foundation by Batching Plant cum 5181.00

PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (D)
Batching Plant
cum 3632.00

Item 12.8 (E) RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3737.00
RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (E)
Batching Plant
cum 3655.00

Item 12.8 (F) PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3749.00
PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (F)
Batching Plant
cum 3665.00

Item 12.8 (G) RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3757.00
RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (G)
Batching Plant
cum 3676.00
Item 12.8 (H)
Case I
RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3849.00
Item 12.8 (H)
Case II
RCC Grade M35 including OH & CP for Open Foundation by Batching Plant cum 5336.00

Item 12.8 (H) RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant cum 4077.00

RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.8 (H)
Batching Plant
cum 3959.00
PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Item 12.11 (C) i
Mechinery by Mixer
cum 3888.00
PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Item 12.11 (C) i
Mechinery by Batching Plant
cum 3597.00
Item 12.11 (C) PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
ii Mechinery by Mixer
cum 4086.00
Item 12.11 (C) PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
ii Mechinery by Batching Plant
cum 3793.00
Item 12.11 (C) PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
iii Mechinery by Mixer
cum 4122.00
Item 12.11 (C) PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
iii Mechinery by Batching Plant
cum 3831.00
Item 12.11 (C) PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
iv Mechinery by Mixer
cum 4205.00
Item 12.11 (C)
iv
PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant cum 5621.00
Item 12.11 (C) PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
iv Mechinery by Batching Plant
cum 3913.00
Item 12.11 (F)
iv
PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant cum 5336.00

Item No. 3.13 Excavation for Structures (Manual Means) cum 189.00

Item No. 3.13 Excavation for Structures (Mechenical Meanse) cum 43.00

Item 14.1(A) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 5417.00
Item 14.1(B) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 5996.00
Item 14.1(E) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 6841.76
Item 14.1(C) RCC Grade M30 for super-structure including formwork and excluding OH & CP by Batching Plant cum 4414.00
Item 14.1(C) RCC Grade M30 for super-structure excluding formwork and excluding OH & CP by Batching Plant cum 3678.00
Item 14.2 A Supplying ,fitting and placing HYSD bar reinforcement in super-structure exncluding OH & CP tonne 49225.00
Item 13.6 Supplying, fitting and placing HYSD including OH & CP for sub-structure tonne 66758.00
Item 5.17 Fog Seal sqm 38.00
Item 5.21
Case-I
Crack Prevention courses. Case-I Stress Absorbing Membrane (SAM) crack width less than 6 mm sqm 56.00

Item 5.21
Case-II
Crack Prevention courses. Case-II Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm sqm 68.00
Item 5.21 Crack Prevention courses. Case-III Stress Absorbing Membrane (SAM) crack width above 9 mm and
Case-IV cracked area above 50 %
sqm 90.00

Item 5.21
Case-IV
Crack Prevention courses. Case-IV Bitumen Impregnated Geotextile sqm 134.00

Item 5.15
Case-I
Slurry Seal Case-I 5 mm thickness sqm 64.00

Item 5.15
Case-II
Slurry Seal Case-II 3 mm thickness sqm 45.00

Item 5.15
Case-III
Slurry Seal Case III 1.5 mm thickness sqm 28.00

Item 5.9 Case-I Surface Dressing Case-I 19 mm nominal chipping size sqm 80.00

Item 5.9 Case-


II
Surface Dressing Case-II 13 mm nominal size chipping sqm 64.00
draft copy Directly Used Items Annexure - I

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
1.1 Loading and unloading of stone boulder / stone
aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit : cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point 1 Min
ii) Loading by front end loader 1 cum bucket capacity 13 Min
@ 25 cum per hour
iii) Maneuvering, reversing, dumping and turning for 2 Min
return
iv) Waiting time, unforeseen contingencies etc 4 Min
Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 846.00 279.18 P&M-048
Front end-loader 1 cum bucket capacity @ 25 hour 0.330 1148.00 378.84 P&M-017
cum/hour
b) Overheads @ 0.1 on (a) 65.80
c) Contractors profit @ 0.1 on (a+b) 72.38
Cost for 5.5 cum = a+b+c 796.20
Rate per cum = (a+b+c)/ 5.5 144.76
Note Unloading will be by tipping. say 145.00
1.4 Cost of Haulage Excluding Loading and Unloading

Haulage of materials by tipper excluding cost of loading,


unloading and stacking.
Unit : t.km
Taking output 10 tonnes load and lead 10 km = 100
t.km
1.4(I) Case I Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery.
i) Tipper 10 tonne capacity
Time taken for onward haulage with load hour 0.400 846.00 338.40 P&M-048
Time taken for empty return trip. hour 0.290 846.00 245.34 P&M-048
b) Overheads @ 0.1 on (a) 58.37
c) Contractors profit @ 0.1 on (a+b) 64.21
cost for 100 t km = a+b+c 706.33
Rate per t.km = (a+b+c)/100 7.06
say 7.10

1.4(II) Case II Unsurfaced Gravelled Road


Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
a)Machinery
Tipper 10 tonnes capacity
Time taken for onward hanlage with load hour 0.500 846.00 423.00 P&M-048
Time taken for empty return trip hour 0.330 846.00 279.18 P&M-048
b) Overheads @ 0.1 on (a) 70.22
c) Contractors profit @ 0.1 on (a+b) 77.24
Cost for 100 t .km = a+b+c 849.64
Rate per t.Km = (a+b+c)/100 8.50
say 8.50

1.4(III) Case III Katcha Track and Track in river bed / nallah bed and
choe bed.
Speed with load : 10 km / hour

30
draft copy Directly Used Items Annexure - I

Speed while returning empty : 15 km / hour


a) Machinery
I) Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 846.00 846.00 P&M-048
Time taken for empty return trip hour 0.670 846.00 566.82 P&M-048
b) Overheads @ 0.1 on (a) 141.28
c) Contractors profit @ 0.1 on (a+b) 155.41
Cost for 100 t .km = a+b+c 1709.51
Rate per t.Km = (a+b+c)/100 17.10
say 17.10
1.5 Hand Broken Stone Aggregates 63 mm nominal size
Supply of quarried stone, hand breaking into coarse
aggregate 63 mm nominal size (passing 80 mm and retained
on 50 mm sieve) and stacking as directed
Unit : cum
Taking output = 1 cum
a) Labour
Mate day 0.060 195.43 11.73 L-12
Mazdoor day 1.500 187.43 281.15 L-13
b) Material
Supply of quarried stone 150 - 200 mm size cum 1.100 550.80 605.89 M-002
c) Overheads @ 0.1 on (a+b) 89.88
d) Contractors profit @ 0.1 on (a+b+c) 98.86
Rate per cum = a+b+c+d 1087.49
say 1087.00
1.6 Crushing of stone aggregates 13.2 mm nominal size.

Crushing of stone boulders of 150 mm size in an integrated


stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 13 mm nominal size.
Unit : cum
Taking Output = 600 cum at crusher location.
a) Labour
Mate day 0.760 195.43 148.53 L-12
Mazdoor Skilled day 2.000 190.43 380.86 L-14
Mazdoor including breaking of any oversize boulder. day 17.000 187.43 3186.31 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 525.85 420677.95 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 16760.52 100563.12 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 1148.00 22960.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 846.00 16920.00 P&M-048
d) Overheads @ 0.1 on (a+b+c) 56483.68
e) Contractors profit @ 0.1 on (a+b+c+d) 62132.04
Cost for 600 cum = a+b+c+d+e 683452.49
Rate per cum = (a+b+c+d+e)*0.95/600 1082.13
say 1082.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 95% of above cost will be attributed to the production of
600 cum of stone chips of 13.2 mm size and balance 5% to
the production of stone dust which comes out as a by-
product.
3. The integrated stone crusher includes primary and
secondary crushing units.

1.7 Crushing of stone aggregates 20 mm nominal size

31
draft copy Directly Used Items Annexure - I

Crushing of stone boulders of 150 mm size in an integrated


stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 20 mm nominal size.
Unit : cum
Taking Output = 670 cum at crusher location.
a) Labour
Mate day 0.760 195.43 148.53 L-12
Mazdoor Skilled day 2.000 190.43 380.86 L-14
Mazdoor including breaking of any size boulder. day 17.000 187.43 3186.31 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 525.85 420677.95 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 16760.52 100563.12 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 1148.00 22960.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 846.00 16920.00 P&M-048
d) Overheads @ 0.1 on (a+b+c) 56483.68
e) Contractors profit @ 0.1 on (a+b+c+d) 62132.04
Cost for 670 cum = a+b+c+d+e 683452.49
Rate per cum = (a+b+c+d+e)*0.90/670 918.07
say 918.00

Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 20 and 40 mm.
2. 90% of above cost will be attributed to the production of
670 cum of stone aggregates of 20mm size and balance
10% will be for smaller size aggregates and stone dust
which comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.

1.8 Crushing of stone aggregates 40 mm nominal size


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 40 mm nominal size.
Unit : cum
Taking Output = 750 cum at crusher location.
a) Labour
Mate day 0.760 195.43 148.53 L-12
Mazdoor Skilled day 2.000 190.43 380.86 L-14
Mazdoor day 17.000 187.43 3186.31 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 525.85 420677.95 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt Hour 6.000 16760.52 100563.12 P&M-028
conveyor and vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 1148.00 22960.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 846.00 16920.00 P&M-048
d) Overheads @ 0.1 on (a+b+c) 56483.68
e) Contractors profit @ 0.1 on (a+b+c+d) 62132.04
Cost for 750 cum = (a+b+c+d+e)x0.85 580934.62
Rate per cum = (a+b+c+d+e)x0.85/750 774.58
say 775.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 85% of above cost will be attributed to the production of
750 cum of stone aggregates of 40mm size and balance
15% will be for smaller size aggregates and stone dust
which comes out as a by-product.

32
draft copy Directly Used Items Annexure - I

3. The integrated stone crusher includes primary and


secondary crushing units.
5.9 510 Surface Dressing
Providing and laying surface dressing as wearing course in
single coat using crushed stone aggregates of specified size
on a layer of bituminous binder laid on prepared surface and
rolling with 8-10 tonne smooth wheeled steel roller

Unit = sqm
Taking output = 9000 sqm
Case -1:-19 mm nominal chipping size
a) Labour
Mate day 0.440 195.43 85.99 L-12
Mazdoor day 9.000 187.43 1686.87 L-13
Mazdoor skilled day 2.000 218.57 437.14 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 456.00 3283.20 P&M-031
Air compressor 250 cfm hour 7.200 293.76 2115.07 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 2423.52 14541.12 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 846.00 5076.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Bitumen pressure distributor hour 6.000 986.04 5916.24 P&M-004
Smooth wheeled roller 8-10 tonne weight hour 6.000 649.00 3894.00 P&M-044
c) Material
Bitumen@ 1.20 kg per sqm tonne 10.800 39879.31 430696.56 M-074
Crushed stone chipping,19 mm nominal size @ 0.015 cum 135.000 887.53 119816.07 M-053
cum per sqm
d) Overheads @ 0.1 on (a+b+c) 59443.63
e) Contractors profit @ 0.1 on (a+b+c+d) 65387.99
Cost for 9000 sqm= a+b+c+d+e 719267.87
Rate per sqm = (a+b+c+d+e)/9000 79.92
say 80.00
Case - II13 mm nominal size chipping
a) Labour
Mate day 0.440 195.43 85.99 L-12
Mazdoor day 9.000 187.43 1686.87 L-13
Mazdoor skilled day 2.000 218.57 437.14 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 7.200 456.00 3283.20 P&M-031
Air compressor 250 cfm hour 7.200 293.76 2115.07 P&M-001
Hydraulic self propelled chip spreader @ 1500 sqm per hour 6.000 2423.52 14541.12 P&M-025
hour
Tipper 10 tonne capacity for carriage of stone chips hour 6.000 846.00 5076.00 P&M-048
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 986.04 5916.24 P&M-004
Vibratory roller 8-10 tonne weight hour 6.000 1720.00 10320.00 P&M-059
c) Material
Bitumen@ 1.00 kg per sqm tonne 9.000 39879.31 358913.80 M-074
Crushed stone chipping,13 mm nominal size @ 0.01 cum 90.000 777.69 69992.18 M-052
cum per sqm
d) Overheads @ 0.1 on (a+b+c) 47925.56
e) Contractors profit @ 0.1 on (a+b+c+d) 52718.12

33
draft copy Directly Used Items Annexure - I

Cost for 9000 sqm= a+b+c+d+e 579899.29


Rate per sqm = (a+b+c+d+e)/9000 64.43
say 64.00
Note 1.Where the proposed aggregate fails to pass the stripping
test, an approved adhesion agent may be added to the
binder as per clause 510.2.4. Alternatively, chips may be
pre-coated as per clause 510.2.5
2.Input for the second coat, where required, will be the
same as per the Ist coat mentioned above
5.15 516 Slurry Seal
Providing andlaying slurry seal consisting of a mixture of fine
aggregates, portland cement filler, bituminous emulsion
and water on a road surface including cleaning of surface,
mixing of slurry seal in a suitable mobile plant, laying and
compacting to provide even riding surface
Case I 5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum, weight of mix =
264 tonnes
weight of mix = 176 tonnes
a) Labour
Mate day 0.240 195.43 46.90 L-12
Mazdoor day 6.000 187.43 1124.58 L-13
b) Machinery
Mechanical broom hour 6.000 456.00 2736.00 P&M-031
Air compressor 250 cfm hour 6.000 293.76 1762.56 P&M-001
Mobile slurry seal equipment hour 6.000 926.64 5559.84 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 846.00 5076.00 P&M-048
stockpile on road side to slurry equipment,bitumen
emulsion and filler.
Pneumatic tyred roller with individual wheel load not hour 6.000 1143.72 6862.32 P&M-037
exceeding 1.5 tonnes
Water tanker6 KL capacity hour 2.000 111.24 222.48 P&M-060
c) Material
Residual Binder @ 11 % of mix 80 x 2.2 x 0.11 tonne 19.360 40114.31 776613.12 M-077
Fine aggregate 4.75 mm and below 87 % of total cum 102.080 209.13 21348.02 M-005
mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking
density1.5,= 153.12/1.5 = 102.08 cum
Filler @ 2 % of total mix = 80 x 2.2 x 0.02 tonne 3.520 4427.31 15584.12 M-188
Cost of water KL 12.000 167.07 2004.82 M-189
d) Overheads @ 0.1 on (a+b+c) 84582.88
e) Contractors profit @ 0.1 on (a+b+c+d) 93041.16
Cost for 16000 sqm= a+b+c+d+e 1023452.81
Rate per sqm = (a+b+c+d+e)/16000 63.97
say 64.00
Case II 3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
Mate day 0.200 195.43 39.09 L-12
Mazdoor day 5.000 187.43 937.15 L-13
b) Machinery
Mechanical broom hour 6.000 456.00 2736.00 P&M-031

34
draft copy Directly Used Items Annexure - I

Air compressor 250 cfm hour 6.000 293.76 1762.56 P&M-001


Mobile slurry seal equipment hour 6.000 926.64 5559.84 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 846.00 5076.00 P&M-048
stockpile on road side to slurry equipment,bitumen
emulsion and filler
Water tanker6 KL capacity hour 2.000 111.24 222.48 P&M-060
c) Material
Residual Binder @ 13 % of mix = 60 x 2.2 x 0.13 tonne 17.160 40114.31 688361.63 M-077
Fine aggregate 3 mm and below 85 % of total mix, 60x cum 74.800 209.13 15642.95 M-005
2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,
Filler @ 2 % of total mix =60x 2.2 x 0.02 tonne 2.640 4427.31 11688.09 M-188
Cost of water KL 12.000 167.07 2004.82 M-189
d) Overheads @ 0.1 on (a+b+c) 74091.86
e) Contractors profit @ 0.1 on (a+b+c+d) 81501.05
Cost for 30000 sqm= a+b+c+d+e 896511.51
Rate per sqm = (a+b+c+d+e)/20000 44.83
say 45.00
Case III 1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
Mate day 0.200 195.43 39.09 L-12
Mazdoor day 5.000 187.43 937.15 L-13
b) Machinery
Mechanical broom hour 6.000 456.00 2736.00 P&M-031
Air compressor 250 cfm hour 6.000 293.76 1762.56 P&M-001
Mobile slurry seal equipment hour 6.000 926.64 5559.84 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 846.00 5076.00 P&M-048
stockpile on road side to slurry equipment,bitumen
emulsion and filler.
Water tanker6 KL capacity hour 2.000 111.24 222.48 P&M-060
c) Material
Residual Binder @ 16 % of mix, 36 x 2.2 x 0.16 tonne 12.670 40114.31 508248.36 M-077
Fine aggregate 2.36 mm and below,82 % of total cum 43.300 244.51 10587.23 M-022
mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density 1.5

Filler @ 2 % of total mix = 36x 2.2 x 0.02 tonne 1.580 4427.31 6995.15 M-188
Cost of water KL 12.000 167.07 2004.82 M-189
d) Overheads @ 0.1 on (a+b+c) 55105.67
e) Contractors profit @ 0.1 on (a+b+c+d) 60616.23
Cost for 24000 sqm= a+b+c+d+e 666778.58
Rate per sqm = (a+b+c+d+e)/24000 27.78
say 27.80
Note 1.Tack coat, if required to be provided, before laying slurry
seal may be measured and paid separately

5.17 518 Fog Spray


Providing and applying low viscosity bitumen emulsion for
sealing cracks less than 3 mm wide or incipient fretting or
disintegration in an existing bituminous surfacing.
Unit = sqm
Taking output = 10500 sqm

35
draft copy Directly Used Items Annexure - I

a) Labour
Mate day 0.120 195.43 23.45 L-12
Mazdoor day 3.000 187.43 562.29 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 456.00 2736.00 P&M-031
Air compressor 250 cfm hour 6.000 293.76 1762.56 P&M-001
Bitumen emulsion pressure distributor @ 1750 sqm per tonne 6.000 986.04 5916.24 P&M-004
hour
c) Material
Bitumenemulsion @ 0.75 kg per sqm tonne 7.880 40114.31 316100.80 M-077
d) Overheads @ 0.1 on (a+b+c) 32710.13
e) Contractors profit @ 0.1 on (a+b+c+d) 35981.15
Cost for 10500 sqm= a+b+c+d+e 395792.62
Rate per sqm = (a+b+c+d+e)/10500 37.69
say 38.00
1.In case it is decided by the engineer to blind the fog spray,
the following may be added
a) Labour
Mate day 0.160 195.43 31.27 L-12
Mazdoor for precoating of grit day 4.000 187.43 749.72 L-13
c) Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm cum 26.250 267.20 7013.93 M-024
Bitumenemulsion for precoating grit @ 2 % of tonne 0.790 40114.31 31690.31 M-077
grit,39.38 x 0.02
c) Overhead charges @ 0.1 on (a+b) 3948.52
d) Contractor's profit @ 0.1 on (a+b+c) 4343.38
Cost for 10500 sqm = a+b+c+d 47777.13
Rate per sqm = (a+b+c+d)/10500 4.55
say 4.60

5.21 522 Crack Prevention Courses


Case - I Stress Absorbing Membrane (SAM) crack width less
than 6 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width below 6 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 9 kg per
10 sqm and spreading 5.6 mm crushed stone aggregates @
0.11 cum per 10 sqm with hydraulic chip spreader,
sweeping the surface for uniform spread of aggregates and
surface finished to conform to clause 902.

Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 195.43 46.90 L-12
Mazdoor day 6.000 187.43 1124.58 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 456.00 2736.00 P&M-031
Air compressor 250 cfm hour 6.000 293.76 1762.56 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 986.04 5916.24 P&M-004
Hydraulic Chip spreader hour 6.000 2423.52 14541.12 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 649.00 3894.00 P&M-044
c) Material
Modified binder tonne 9.450 42274.22 399491.41 M-078

36
draft copy Directly Used Items Annexure - I

Crushed stone aggregates 5.6 mm size cum 105.000 497.86 52275.81 M-050
d) Overheads @ 0.1 on (a+b+c) 48178.86
e) Contractors profit @ 0.1 on (a+b+c+d) 52996.75
Cost for 10500 sqm= a+b+c+d+e 582964.23
Rate per sqm = (a+b+c+d+e)/10500 55.52
say 56.00

Case - II Stress Absorbing Membrane (SAM) with crack width 6


mm to 9 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width 6 to 9 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 11 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.

Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 195.43 46.90 L-12
Mazdoor day 6.000 187.43 1124.58 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 6.000 456.00 2736.00 P&M-031
Air compressor 250 cfem capacity hour 6.000 293.76 1762.56 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 986.04 5916.24 P&M-004
Hydraulic Chip spreader hour 6.000 2423.52 14541.12 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 649.00 3894.00 P&M-044
c) Material
Modified binder tonne 11.550 42274.22 488267.28 M-078
Crushed stone chipping 11.2 mm size cum 105.000 674.15 70785.90 M-051
d) Overheads @ 0.1 on (a+b+c) 58907.46
e) Contractors profit @ 0.1 on (a+b+c+d) 64798.20
Cost for 10500 sqm= a+b+c+d+e 712780.25
Rate per sqm = (a+b+c+d+e)/10500 67.88
say 68.00
Case III Stress Absorbing Membrane (SAM) crack width above
9 mm and cracked area above 50 %
Providing and laying a single coatn of a stress absorbing
membrane over a cracked road surface, with crack width
above 9 mm and cracked area above 50 % after cleaning
with a mechanical broom, using modified binder complying
with clause 521, sprayed at the rate of 15 kg per 10 sqm
and spreading 11.2 mm crushed stone aggregates @ 0.12
cum per 10 sqm, sweeping the surface for uniform spread
of aggregates and surface finished to conform to clause 902.

Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 195.43 46.90 L-12
Mazdoor day 6.000 187.43 1124.58 L-13
Mazdoor skilled day 2.000 218.57 437.14 L-15
b) Machinery

37
draft copy Directly Used Items Annexure - I

Mechanical broom @ 1250 sqm per hour hour 6.000 456.00 2736.00 P&M-031
Air compressor 250 cfem capacity hour 6.000 293.76 1762.56 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 986.04 5916.24 P&M-004
Hydraulic Chip spreader hour 6.000 2423.52 14541.12 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 649.00 3894.00 P&M-044
c) Material
Modified binder tonne 15.750 42274.22 665819.02 M-078
Crushed stone aggregates 11.2 mm size cum 126.000 674.15 84943.09 M-051
d) Overheads @ 0.1 on (a+b+c) 78122.06
e) Contractors profit @ 0.1 on (a+b+c+d) 85934.27
Cost for 10500 sqm= a+b+c+d+e 945276.98
Rate per sqm = (a+b+c+d+e)/10500 90.03
say 90.00
Case IV Case - IV : Bitumen Impregnated Geotextile
Providing and laying a bitumen impregnated geotextile layer
after cleaning the road surface, geotextile conforming to
requirements of clause 704.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration
and constructed to the requirement of clause 704.4.5

Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.560 195.43 109.44 L-12
Mazdoor day 12.000 187.43 2249.16 L-13
Mazdoor skilled day 2.000 218.57 437.14 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 456.00 1276.80 P&M-031
Air compressor 250 cfem capacity hour 2.800 293.76 822.53 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour tonne 2.000 986.04 1972.08 P&M-004
Pneumatic roller hour 2.000 1143.72 2287.44 P&M-037
c) Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 tonne 3.680 38958.19 143366.14 M-075
kg per sqm
Geotextile including 10 % for overlaps sqm 3850.000 60.75 233893.61 M-108
d) Overheads @ 0.1 on (a+b+c) 38641.43
e) Contractors profit @ 0.1 on (a+b+c+d) 42505.58
Cost for 10500 sqm= a+b+c+d+e 467561.35
Rate per sqm = (a+b+c+d+e)/3500 133.59
say 134.00
NOTE As bitumen overlay construction shallfollow closely the fabric
placement on the same day, an output of 3500 sqm only
has been considered for the analysis which will cover a
length of 500 m, of 7 m widecarriagway. This can be
conveniently overlaid by a bitumenious course in a day

8.3 801 Printing new letter and figures of any shade


Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade
ii) English and Roman
Hyphens and the like not to be measured and paid for
Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter

38
draft copy Directly Used Items Annexure - I

a) Labour
Mate day 0.07 195.43 13.68 L-12
Painter Ist class day 1.25 236.19 295.24 L-18
Mazdoor day 0.50 187.43 93.72 L-13
b) Material
Paint Litre 0.50 138.35 69.18 M-131
c) Overheads @ 0.1 on (a+b) 47.18
d) Contractors profit @ 0.1 on (a+b+c) 51.90
Cost for 1600 cm = a+b+c+d 570.89
Rate per cm height per letter = (a+b+c +d)/1600 0.36
say 0.40
8.8 803 Painting Two Coats on New Concrete Surfaces
Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.12 195 23.45 L-12
Painter day 2.00 236 472.38 L-18
Mazdoor day 1.00 187 187.43 L-13
b) Material
Paint conforming to requirement of clause 803.3. Litre 6.00 138 830.12 M-132

Add for scaffolding @ 1% of labour cost where required 8.30

c) Overheads @ 0.1 on (a+b) 152.17


d) Contractors profit @ 0.1 on (a+b+c) 167.39
Cost for 40 sqm = a+b+c+d 1841.24
Rate per sqm = (a+b+c+d)/40 46.03
say 46.00
8.9 803 Painting on Steel Surfaces
Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.03 195 5.86 L-12
Painter day 0.45 236 106.29 L-18
Mazdoor day 0.25 187 46.86 L-13
b) Material
Paint ready mixed approved brand. Litre 1.25 138 172.94 M-131
Add @ 1% on cost of material for scaffolding 1.73
c) Overheads @ 0.1 on (a+b) 33.37
d) Contractors profit @ 0.1 on (a+b+c) 36.70
Cost for 10 sqm = a+b+c+d 403.75
Rate per sqm = (a+b+c+d)/10 40.37
say 40.00
12.6 Sub- Cement mortar1:3 (1cement :3 sand)
analysis
(A)
Unit = 1 cum
Taking output = 1 cum
a) Materials

39
draft copy Directly Used Items Annexure - I

Cement MT 0.51 5982.46 3051.05 M-81


Sand cum 1.05 209.13 219.59 M-5
b) Labour
Mate day 0.04 195.43 7.82 L-12
Mazdoor day 0.90 187.43 168.69 L-13
Total Material and Labour = (a+b) 3447.00

Sub- Cement mortar1:2 (1cement :2 sand)


analysis
(B)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement MT 0.672 5982.46 4020.21 M-81
Sand cum 0.933 209.13 195.19 M-5
b) Labour
Mate day 0.04 195.43 7.82 L-12
Mazdoor day 0.90 187.43 168.69 L-13
Total Material and Labour = (a+b) 4392.00

Sub- Cement mortar1:6 (1cement :6 sand)


analysis
(D)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement MT 0.288 5982.46 1722.95 M-81
Sand cum 1.337 209.13 279.64 M-5
b) Labour
Mate day 0.04 195.43 7.82 L-12
Mazdoor day 0.90 187.43 168.69 L-13
Total Material and Labour = (a+b) 2179.00
12.7 1400 Stone masonry work in cement mortar 1:3 in
foundation complete as drawing and Technical
Specification
Unit = cum
Taking output = 5 cum
(A) Square Rubble Coursed Rubble Masonry (first sort)

a) Material
Stone cum 5.50 360.24 1981.32 M-169
Through and bond stone each 35.00 6.06 211.97 M-182
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 1.50 3447.00 5170.50 Item 12.6
analysis) (A)
b) Labour
Mate day 0.66 195.43 128.98 L-12
Mason day 7.50 247.19 1853.93 L-11
Mazdoor day 9.00 187.43 1686.87 L-13
c) Overhead charges @ 0.25 on (a+b) 2758.39
d) Contractor's profit @ 0.1 on (a+b+c) 1379.20
Cost for 5 cum = a+b+c+d 15171.16
Rate per cum (a+b+c+d)/5 3034.23
say 3034.00
1405.3 B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 359.72 1978.45 M-148
Through and bond stone Nos 35.00 6.06 211.97 M-182
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 12.6 A) cum 1.55 3447.00 5342.85

40
draft copy Directly Used Items Annexure - I

b) Labour
Mate day 0.62 195.43 121.17 L-12
Mason day 6.00 247.19 1483.14 L-11
Mazdoor day 9.00 187.43 1686.87 L-13
c) Overheads @ 0.25 on (a+b) 2706.11
d) Contractors profit @ 0.1 on (a+b+c) 1353.06
Cost for 5 cum = a+b+c+d 14883.62
Rate per cum (a+b+c+d)/5 2976.72
say 2977.00
@ The labour already considered in cement mortar has been
taken into account while proposing labour for masonry
works.
12.7 1400 Stone masonry work in cement mortar 1:6 in
(Add) foundation complete as drawing and Technical
Specification
Unit = cum
Taking output = 5 cum
1405.3 B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 359.72 1978.45 M-148
Through and bond stone Nos 35.00 6.06 211.97 M-182
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 13.6 D) cum 1.55 280.00 434.00
b) Labour
Mate day 0.62 195.43 121.17 L-12
Mason day 6.00 247.19 1483.14 L-11
Mazdoor day 9.00 187.43 1686.87 L-13
c) Overheads @ 0.25 on (a+b) 1478.90
d) Contractors profit @ 0.1 on (a+b+c) 739.45
Cost for 5 cum = a+b+c+d 8133.95
Rate per cum (a+b+c+d)/5 1626.79
say 1627.00
@ The labour already considered in cement mortar has been
taken into account while proposing labour for masonry
works.

12.8 1500, Plain/Reinforced cement concrete in open foundation


1700 & complete as per drawing and technical specifications
2100
A PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 4.13 5982.46 24707.54
Coarse sand cum 6.75 209.13 1411.63
40 mm Aggregate cum 8.10 780.12 6318.96
20 mm Aggregate cum 4.05 887.53 3594.48
10 mm Aggregate cum 1.35 674.15 910.10
b) Labour
Mate day 0.86 195.43 168.07
Mason day 1.50 247.19 370.79
Mazdoor day 20.00 187.43 3748.60
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08
Generator 63 KVA hour 6.00 361.80 2170.80
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 2,979.00
d) Formwork @ 4% on cost of concrete i.e.cost of material, 1786.84
labour and machinery
e) Overheads @ 0.25 on (a+b+c+d) 11614.47
f) Contractors profit @ 0.1 on (a+b+c+d+e) 5807.24

41
draft copy Directly Used Items Annexure - I

Cost for 15 cum = a+b+c+d+e+f 63879.61


Rate per cum (a+b+c+d+e+f)/15 4258.64
say 4259.00
Note Nedle Vibrator is an item of minor T & P which is already
included in overhead charges. Hence not added in rate
analysis of cement concrete works.
12.8 B PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement MT 5.16 5982.46 30869.47
Coarse sand cum 6.75 209.13 1411.63
40 mm Aggregate cum 5.40 780.12 4212.64
20 mm Aggregate cum 5.40 887.53 4792.64
10 mm Aggregate cum 2.70 674.15 1820.21
b) Labour
Mate day 0.86 195.43 168.07
Mason day 1.50 247.19 370.79
Mazdoor day 20.00 187.43 3748.60
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08
Generator 33 KVA hour 6.00 342.36 2054.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,382.00
12.8 C RCC Grade M20
Unit = cum
Case I Using concrete mixer
Taking output = 15 cum
a) Material
Cement MT 5.21 5982.46 31168.60
Coarse sand cum 6.75 209.13 1411.63
20 mm Aggregate cum 8.10 887.53 7188.96
10 mm Aggregate cum 5.40 674.15 3640.42
b) Labour
Mate day 0.86 195.43 168.07
Mason day 1.50 247.19 370.79
Mazdoor day 20.00 187.43 3748.60
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08
Generator 33 KVA hour 6.00 342.36 2054.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,402.00
Case II With Batching Plant, Transit Mixer and Conrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 41.66 5982.46 249229.12
Coarse Sand cum 54.00 209.13 11293.04
20 mm Aggregate cum 64.80 887.53 57511.71
10 mm Aggregate cum 43.20 674.15 29123.34
b) Labour
Mate day 0.84 195.43 164.16
Mason day 3.00 247.19 741.57
Mazdoor day 18.00 187.43 3373.74
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00
Generator 100 KVA hour 6.00 1635.00 9810.00
Loader 1 cum capacity hour 6.00 1148.00 6888.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25
Lead beyond 1 km, L-lead in km T-km 300L 4.32 1140.00 L= 1
Concrete Pump hour 6 234.36 1406.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,319.00
d) Formwork @ 4% on cost of concrete i.e.cost of material, 15929.64
labour and machinery

42
draft copy Directly Used Items Annexure - I

e) Overheads @ 0.25 on (a+b+c+d) 103542.68


f) Contractors profit @ 0.1 on (a+b+c+d+e) 51771.34
Cost for 120 cum = a+b+c+d+e+f 569484.77
Rate per cum = ( a+b+c+d+e+f )/120 4745.71
say 4746.00
12.8 D PCC Grade M25
Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 5.99 5982.46 35834.91
Coarse sand cum 6.75 209.13 1411.63
40 mm Aggregate cum 5.40 780.12 4212.64
20 mm Aggregate cum 5.40 887.53 4792.64
10 mm Aggregate cum 2.70 674.15 1820.21
b) Labour
Mate day 0.86 195.43 168.07
Mason day 1.50 247.19 370.79
Mazdoor day 20.00 187.43 3748.60
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08
Generator 33 KVA hour 6.00 342.36 2054.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,713.00
Case II With Batching Plant, Transit Mixer and Conrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 47.95 5982.46 286858.77
Coarse sand cum 54.00 209.13 11293.04
40 mm Aggregate cum 43.20 780.12 33701.12
20 mm Aggregate cum 43.20 887.53 38341.14
10 mm Aggregate cum 21.60 674.15 14561.67
b) Labour
Mate day 0.84 195.43 164.16
Mason day 3.00 247.19 741.57
Mazdoor day 18.00 187.43 3373.74
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00
Generator 100 KVA hour 6.00 1635.00 9810.00
Loader 1 cum capacity hour 6.00 1148.00 6888.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25
Transit Mixer 4 cum capacity lead beyond T-Km 300L 4.32 1140.00 L= 1
1 Km, L - lead in Kilometer
Concrete Pump hour 6 234.36 1406.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,632.00
d) Formwork @ 3.75% of cost of concrete i.e.cost of 16343.99
material, labour and machinery
e) Overheads @ 0.25 on (a+b+c+d) 113045.90
f) Contractors profit @ 0.1 on (a+b+c+d+e) 56522.95
cost of 120 cum = a+b+c+d+e+f 621752.46
Rate per cum (a+b+c+d+e+f)/120 5181.27
say 5181.00
12.8 E RCC Grade M25
Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 6.05 5982.46 36193.86
Coarse sand cum 6.75 209.13 1411.63
20 mm Aggregate cum 8.10 887.53 7188.96
10 mm Aggregate cum 5.40 674.15 3640.42
b) Labour

43
draft copy Directly Used Items Annexure - I

Mate day 0.86 195.43 168.07


Mason day 1.50 247.19 370.79
Mazdoor day 20.00 187.43 3748.60
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08
Generator 33 KVA hour 6.00 342.36 2054.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,737.00
Case II With Batching Plant, Transit Mixer and Conrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 48.38 5982.46 289431.23
Coarse sand cum 54.00 209.13 11293.04
20 mm Aggregate cum 64.80 887.53 57511.71
10 mm Aggregate cum 43.20 674.15 29123.34
Admixer Kg 193.52 112.77 21823.45
b) Labour
Mate day 0.84 195.43 164.16
Mason day 3.00 247.19 741.57
Mazdoor day 18.00 187.43 3373.74
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00
Generator 100 KVA hour 6.00 1635.00 9810.00
Loader 1 cum capacity 1 cum hour 6.00 1148.00 6888.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25
Transit Mixer 4 cum capacity lead beyond T-Km 300L 4.32 1140.00 L= 1
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 234.36 1406.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,836.00
12.8 F PCC Grade M30
Unit = cum
Case I Using Concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 6.08 5982.46 36373.33
Coarse sand cum 6.75 209.13 1411.63
40 mm Aggregate cum 5.40 780.12 4212.64
20 mm Aggregate cum 5.40 887.53 4792.64
10 mm Aggregate cum 2.70 674.15 1820.21
b) Labour
Mate day 0.86 195.43 168.07
Mason day 1.50 247.19 370.79
Mazdoor day 20.00 187.43 3748.60
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08
Generator 33 KVA hour 6.00 342.36 2054.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,749.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 48.60 5982.46 290747.37
Coarse sand cum 54.00 209.13 11293.04
40 mm Aggregate cum 43.20 780.12 33701.12
20 mm Aggregate cum 43.20 887.53 38341.14
10 mm Aggregate cum 21.60 674.15 14561.67
b) Labour
Mate day 0.84 195.43 164.16
Mason day 3.00 247.19 741.57
Mazdoor day 18.00 187.43 3373.74
c) Machinery

44
draft copy Directly Used Items Annexure - I

Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00


Generator 100 KVA hour 6.00 1635.00 9810.00
Loader 1 cum capacity hour 6.00 1148.00 6888.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25
Transit Mixer 4 cum capacity lead beyond T-Km 300L 4.32 1140.00 L= 1
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 234.36 1406.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,665.00
12.8 G RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 6.10 5982.46 36492.98
Coarse sand cum 6.75 209.13 1411.63
20 mm Aggregate cum 8.10 887.53 7188.96
10 mm Aggregate cum 5.40 674.15 3640.42
b) Labour
Mate day 0.86 195.43 168.07
Mason day 1.50 247.19 370.79
Mazdoor day 20.00 187.43 3748.60
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08
Generator 33 KVA hour 6.00 342.36 2054.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,757.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.80 5982.46 291943.86
Coarse sand cum 54.00 209.13 11293.04
20 mm Aggregate cum 64.80 887.53 57511.71
10 mm Aggregate cum 43.20 674.15 29123.34
b) Labour
Mate day 0.84 195.43 164.16
Mason day 3.00 247.19 741.57
Mazdoor day 18.00 187.43 3373.74
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00
Generator 100 KVA hour 6.00 1635.00 9810.00
Loader 1 cum capacity hour 6.00 1148.00 6888.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25
Transit Mixer 4 cum capacity lead beyond T-Km 300L 4.32 1296.00 L= 1
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 234.36 1406.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,676.00
12.8 H RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 6.33 5982.46 37868.95
Coarse sand cum 6.75 209.13 1411.63
20 mm Aggregate cum 8.10 887.53 7188.96
10 mm Aggregate cum 5.40 674.15 3640.42
b) Labour
Mate day 0.86 195.43 168.07
Mason day 1.50 247.19 370.79
Mazdoor day 20.00 187.43 3748.60
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08
Generator 33 KVA hour 6.00 342.36 2054.16

45
draft copy Directly Used Items Annexure - I

Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,849.00
Case II Using Batching Plant, Transit Mixer and Conrete Pump

Unit ; cum
Taking Output = 120 cum
a) Material
Cement MT 50.64 5982.46 302951.58
Coarse sand cum 54.00 209.13 11293.04
20 mm Aggregate cum 64.80 887.53 57511.71
10 mm Aggregate cum 43.20 674.15 29123.34
Admixer Kg 202.56 112.77 22842.90
b) Labour
Mate day 0.84 195.43 164.16
Mason day 3.00 247.19 741.57
Mazdoor day 18.00 187.43 3373.74
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00
Generator 100 KVA hour 6.00 1635.00 9810.00
Loader 1 cum capacity hour 6.00 1148.00 6888.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25
Transit Mixer 4 cum capacity lead beyond T-Km 300L 4.32 1296.00 L= 1
1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 234.36 1406.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3,959.00
d) Formwork @ 3% on cost of concrete i.e.cost of material, 14248.87
labour and machinery
e) Overheads @ 0.25 on (a+b+c+d) 122302.83
f) Contractors profit @ 0.1 on (a+b+c+d+e) 61151.42
cost of 120 cum = a+b+c+d+e+f 672665.58
Rate per cum (a+b+c+d+e+f)/120 5605.55
say 5606.00
Rate per cum (a+b+c+d)/120 Excluding OH & CP 4077.00
Note: Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers @ 0.4% of weight of
cement may be added for achieving desired slump of
concrete.

12.11 1200, Plain/Reinforced cement concrete, in well foundation


1500 & complete as per drawing and technical specification
1700

C Bottom Plug
Concrete to be placed using tremie pipe
Case I Using Concrete Mixer
(i) PCC Grade M20
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 5.55 5982.46 33202.63
Coarse sand cum 6.75 209.13 1411.63
40 mm Aggregate cum 5.40 780.12 4212.64
20 mm Aggregate cum 5.40 887.53 4792.64
10 mm Aggregate cum 2.70 674.15 1820.21
Admixer Kg 18.60 112.77 2097.54
b) Labour
Mate day 0.90 195.43 175.89
Mason day 1.50 247.19 370.79
Mazdoor day 20.00 187.43 3748.60
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08
Generator 33 KVA hour 6.00 342.36 2054.16
Light Crane 3 tonnes capacity for handling tremie pipe hour 6.00 525.00 3150.00

46
draft copy Directly Used Items Annexure - I

Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3888.00
Note 10% extra cement may be added where under water
concreting is involved.
Case II Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement MT 44.40 5982.46 265621.05
Coarse sand cum 54.00 209.13 11293.04
20 mm Aggregate cum 64.80 887.53 57511.71
10 mm Aggregate cum 43.20 674.15 29123.34
Admixer Kg 148.80 112.77 16780.33
b) Labour
Mate day 0.88 195.43 171.98
Mason day 3.00 247.19 741.57
Mazdoor day 18.00 187.43 3373.74
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00
Generator 100 KVA hour 6.00 1635.00 9810.00
Loader 1 cum capacity hour 6.00 1148.00 6888.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 4.32 1296.00 L= 1
lead in Kilometer
Concrete Pump hour 6.00 234.36 1406.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3597.00

(ii) PCC Grade M25

Case I Using Concrete Mixer


Unit = cum
Taking output = 15 cum
a) Material
Cement MT 5.99 5982.46 35834.91
Coarse sand cum 6.75 209.13 1411.63
40 mm Aggregate cum 5.40 780.12 4212.64
20 mm Aggregate cum 5.40 887.53 4792.64
10 mm Aggregate cum 2.70 674.15 1820.21
Admixer Kg 21.60 112.77 2435.85
b) Labour
Mate day 0.90 195.43 175.89
Mason day 1.50 247.19 370.79
Mazdoor day 20.00 187.43 3748.60
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08
Generator 33 KVA hour 6.00 342.36 2054.16
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 525.00 3150.00
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 4086.00
Case II Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 47.88 5982.46 286440.00
Coarse sand cum 54.00 209.13 11293.04
20 mm Aggregate cum 64.80 887.53 57511.71
10 mm Aggregate cum 43.20 674.15 29123.34
Admixer Kg 172.80 112.77 19486.84
b) Labour
Mate day 0.88 195.43 171.98
Mason day 3.00 247.19 741.57
Mazdoor day 18.00 187.43 3373.74

47
draft copy Directly Used Items Annexure - I

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00
Generator 100 KVA hour 6.00 1635.00 9810.00
Loader 1 cum capacity hour 6.00 1148.00 6888.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 4.32 1296.00 L= 1
lead in Kilometer
Concrete Pump hour 6.00 234.36 1406.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3793.00

(iii) PCC Grade M30


Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement MT 6.08 5982.46 36373.33
Coarse sand cum 6.75 209.13 1411.63
40 mm Aggregate cum 5.40 780.12 4212.64
20 mm Aggregate cum 5.40 887.53 4792.64
10 mm Aggregate cum 2.70 674.15 1820.21
Admixer Kg 21.60 112.77 2435.85
b) Labour
Mate day 0.90 195.43 175.89
Mason day 1.50 247.19 370.79
Mazdoor day 20.00 187.43 3748.60
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08
Generator 33 KVA hour 6.00 342.36 2054.16
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 525.00 3150.00
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 4122.00
Case II Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.64 5982.46 290986.67
Coarse sand cum 54.00 209.13 11293.04
20 mm Aggregate cum 64.80 887.53 57511.71
10 mm Aggregate cum 43.20 674.15 29123.34
Admixer Kg 172.80 112.77 19486.84
b) Labour
Mate day 0.88 195.43 171.98
Mason day 3.00 247.19 741.57
Mazdoor day 18.00 187.43 3373.74
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00
Generator 100 KVA hour 6.00 1635.00 9810.00
Loader 1 cum capacity hour 6.00 1148.00 6888.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 4.32 1296.00 L= 1
lead in Kilometer
Concrete Pump hour 6.00 234.36 1406.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3831.00
(iv) PCC Grade M35

Case I Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a) Material
Cement MT 6.29 5982.46 37629.65
Coarse sand cum 6.75 209.13 1411.63
40 mm Aggregate cum 5.40 780.12 4212.64

48
draft copy Directly Used Items Annexure - I

20 mm Aggregate cum 5.40 887.53 4792.64


10 mm Aggregate cum 2.70 674.15 1820.21
Admixer Kg 21.60 112.77 2435.85
b) Labour
Mate day 0.90 195.43 175.89
Mason day 1.50 247.19 370.79
Mazdoor day 20.00 187.43 3748.60
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08
Generator 33 KVA hour 6.00 342.36 2054.16
Light Crane of 3 tonnes capacity for handling tremie hour 6.00 525.00 3150.00
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 4205.00
Case II Using Batching Plant, Transit Mixer and
Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 50.28 5982.46 300797.89
Coarse sand cum 54.00 209.13 11293.04
20 mm Aggregate cum 64.80 887.53 57511.71
10 mm Aggregate cum 43.20 674.15 29123.34
Admixer Kg 172.80 112.77 19486.84
b) Labour
Mate day 0.88 195.43 171.98
Mason day 3.00 247.19 741.57
Mazdoor day 18.00 187.43 3373.74
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00
Generator 100 KVA hour 6.00 1635.00 9810.00
Loader 1 cum capacity hour 6.00 1148.00 6888.00
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - T-Km 300L 4.32 1296.00 L= 1
lead in Kilometer
Concrete Pump hour 6.00 234.36 1406.16
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 3913.00
Add 5% of cost of material and labour towards cost of 21125.01
forming sump, protective bunds, chiselling and making
arrangements for under water concreteing with tremie pipe..

d) Overheads @ 0.25 on (a+b+c) 122646.38


e) Contractors profit @ 0.1 on (a+b+c+d) 61323.19
cost of 120 cum = a+b+c+d+e 674555.10
Rate per cum (a+b+c+d+e)/120 5621.29
Say 5621.00
F Well cap
iv) RCC Grade M35
Case II Using Batching Plant, Transit Mixer and Conrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement MT 50.64 5982.46 302951.58
Coarse sand cum 54.00 209.13 11293.04
20 mm Aggregate cum 64.80 887.53 57511.71
10 mm Aggregate cum 43.20 674.15 29123.34
b) Labour
Mate day 0.84 195.43 164.16
Mason day 3.00 247.19 741.57
Mazdoor day 18.00 187.43 3373.74
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00
Generator 100 KVA hour 6.00 1635.00 9810.00

49
draft copy Directly Used Items Annexure - I

Loader(capacity 1 cum) hour 6.00 1148.00 6888.00


Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 4.32 1296.00 L= 1
Concrete Pump hour 6.00 234.36 1406.16
Formwork @ 3% of (a+b+c) 13563.59
d) Overheads @ 0.25 on (a+b+c) 116420.78
e) Contractors profit @ 0.1 on (a+b+c+d) 58210.39
cost of 120 cum = a+b+c+d+e 640314.31
Rate per cum (a+b+c+d+e)/120 5335.95
Say 5336.00
Note Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers @ 0.4% of weight of
cement may be added for achieving desired slump of
concrete.

3.13 304 Excavation for Structures


Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and
utilising the remaning earth locally for road work.
I) Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.320 195.43 62.54 L-12
Mazdoor day 8.000 187.43 1499.44 L-13
b) Overheads @ 0.1 on (a) 156.20
c) Contractors profit @ 0.1 on (a+b) 171.82
Cost for 10 cum = a+b+c 1889.99
Rate per cum = (a+b+c)/10 189.00
say 189.00
Note Cost of dewatering may be added where required upto 10 %
of labour cost Assessment for dewatering shall be made as
per site conditions..

B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.32 195 62.54
Mazdoor day 8.00 187 1499.44
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1516 9097.92
c) Overheads @ 0.1 on (a+b) 1065.99
d) Contractors profit @ 0.1 on (a+b+c) 1172.59
Cost for 300 cum = a+b+c+d 12898.48
Rate per cum = (a+b+c+d)/300 42.99
say 43.00
Note Cost of dewatering upto 5% of (a+b) may be added, where
required. Assessment for dewatering shall be made as per
site conditions..

50
draft copy Directly Used Items Annexure - I

13.6 Section Supplying, fitting and placing HYSD bar reinforcement


1600 & in sub-structure complete as per drawing and technical
2200 specifications
Output : MT
Taking output = 1 MT
a) Material
HYSD bars including 5% overlaps and wastage MT 1.05 44187.50 46396.88
Binding wire kg 6.00 63.00 378.00
b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.34 195.43 66.45
Blacksmith day 2.00 247.19 494.38
Mazdoor day 6.50 187.43 1218.30
c) Overheads @ 0.25 on (a+b) 12138.50
d) Contractors profit @ 0.1 on (a+b+c) 6069.25
Rate for per MT (a+b+c+d) 66761.74
say 66762.00
14.1 1500 Furnishing and Placing Reinforced/Prestressed
&1600 cement concrete in super-structure as per drawing and
1700 Technical Specification
A RCC Grade M20
Case II Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 40.92 5982.46 244802.11
Coarse sand cum 54.00 209.13 11293.04
20 mm Aggregate cum 64.80 887.53 57511.71
10 mm Aggregate cum 43.20 674.15 29123.34
b) Labour
Mate day 0.84 195.43 164.16
Mason day 3.00 247.19 741.57
Mazdoor day 18.00 187.43 3373.74
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00
Generator 100 KVA hour 6.00 1635.00 9810.00
Loader hour 6.00 1148.00 6888.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 854.55 12818.25
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 4.32 1296.00 L= 1
Concrete Pump hour 6.00 234.36 1406.16
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum ###

(i) For solid slab super-structure, 20-30% of (a+b+c)


(p) Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 393971.00
cum
d) Formwork and staging 20 % of (a+b+c) 20.00 78794.20
e) Overheads @ 0.25 on (a+b+c+d) 118191.30
f) Contractors profit @ 0.1 on (a+b+c+d+e) 59095.65
Cost for 15 cum = a+b+c+d+e+f 650052.15
Rate per cum (a+b+c+d+e+f)/120 5417.10
say 5417.00
B RCC Grade M25
Case II Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 47.95 5982.46 286858.77
Coarse sand cum 54.20 209.13 11334.86

51
draft copy Directly Used Items Annexure - I

20 mm Aggregate cum 64.80 887.53 57511.71


10 mm Aggregate cum 43.20 674.15 29123.34
b) Labour
Mate day 0.84 195.43 164.16
Mason day 3.00 247.19 741.57
Mazdoor day 18.00 187.43 3373.74
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00
Generator 100 KVA hour 6.00 1635.00 9810.00
Loader hour 6.00 1148.00 6888.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 854.55 12818.25
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 4.32 1296.00 L= 1
Concrete Pump hour 6.00 234.36 1406.16
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum ###
For formwork and staging add the following:
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 436069.00
120 cum
d) Formwork and staging 20 % of (a+b+c) 20.00 87213.80
e) Overheads @ 0.25 on (a+b+c+d) 130820.70
f) Contractors profit @ 0.1 on (a+b+c+d+e) 65410.35
Cost for 15 cum= a+b+c+d+e+f 719513.85
Rate per cum (a+b+c+d+e+f)/120 5995.95
say 5996.00

C RCC Grade M 30

Case II Using Batching Plant, Transit Mixer and Concrete


Pump.
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.79 5982.46 291884.04
Coarse sand cum 54.60 209.13 11418.51
20 mm Aggregate cum 64.80 887.53 57511.71
10 mm Aggregate cum 43.20 674.15 29123.34
b) Labour
Mate day 0.88 195.43 171.98
Mason day 3.00 247.19 741.57
Mazdoor day 19.00 187.43 3561.17
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00
Generator 100 KVA hour 6.00 1635.00 9810.00
Loader hour 6.00 1148.00 6888.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 854.55 12818.25
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 4.32 1296.00 L= 1
Concrete Pump hour 6.00 234.36 1406.16
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum ###
For formwork and staging add the following:

(i) For solid slab super-structure, 20-30% of (a+b+c)


(p) Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 441373.00
cum
d) Formwork and staging 20 % of (a+b+c) 20.00 88274.60
e) Overheads @ 0.25 on (a+b+c+d) 132411.90
f) Contractors profit @ 0.1 on (a+b+c+d+e) 66205.95
Cost for 120 cum = a+b+c+d+e+f 728265.45

52
draft copy Directly Used Items Annexure - I

Rate per cum (a+b+c+d+e+f)/120 6068.88


say 6069.00
Rate per cum (a+b+c+d)/120 ( including formwork and excluding OH & CP) 4414.00
Rate per cum (a+b+c+d)/120 ( excluding formwork and Excluding OH & CP) 3678.00

E PSC Grade M-40


Case 1 Using concret mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement MT 6.45 5982.46 38586.84
Coarse sand cum 6.75 209.13 1411.63
20 mm Aggregate cum 8.10 887.53 7188.96
10 mm Aggregate cum 5.40 674.15 3640.42
Admixture @ 0.4% of cement kg 25.80 112.77 2909.49
b) Labour
Mate day 0.96 195.43 187.61
Mason day 2.00 247.19 494.38
Mazdoor day 22.00 187.43 4123.46
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08
Generator 33 KVA hour 6.00 342.36 2054.16
Basic Cost of Labour, Material & Mechinery (a+b+c) for 15 cum 61868.00

Case II Using Batching Plant, Transit Mixer and Concrete


Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 51.60 5982.46 308694.74
Coarse sand cum 54.00 209.13 11293.04
20 mm Aggregate cum 64.80 887.53 57511.71
10 mm Aggregate cum 43.20 674.15 29123.34
Admixture @ 0.4% of cement kg 206.40 112.77 23275.94
Admixer Kg 216.00 112.77 24358.55
b) Labour
Mate day 0.94 195.43 183.70
Mason day 3.50 247.19 865.17
Mazdoor day 20.00 187.43 3748.60
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00
Generator 100 KVA hour 6.00 1635.00 9810.00
Loader hour 6.00 1148.00 6888.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km hour 15.00 854.55 12818.25
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 4.32 1296.00 L= 1
Concrete Pump hour 6.00 234.36 1406.16
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum ###
For formwork and staging add the following:
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 506016.00
120 cum
d) Formwork and staging 18 % of (a+b+c) 18.00 91082.88
e) Overheads @ 0.25 on (a+b+c+d) 149274.72
f) Contractors profit @ 0.1 on (a+b+c+d+e) 74637.36
Cost for 15 cum= a+b+c+d+e+f 821010.96
Rate per cum (a+b+c+d+e+f)/120 6841.76
say 6842.00

53
draft copy Directly Used Items Annexure - I

Note 1.Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, admixers conforming IS: 9103
@ 0.4% of weight of cement may be added for achieving
desired slump of concrete.
2. Cement provided for various components of the super
structure is for estimating purpose only. Actual quantity of
cement will be as per approved mix design. Similarly, the
provision for coarse and fine aggregates is for estimating
purpose and the exact quantity shall be as per the mix
design.
3. The items like needle and surface vibrators are part of
minor T & P which is already covered under the overhead
charges. As such these items have not been added
seperately in the rate analysis.
14.2 1600 A) Supplying ,fitting and placing HYSD bar
reinforcement in super-structure complete as per
drawing and technical specifications
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5% for laps and wastage MT 1.05 44187.50 46396.88
Binding wire Kg 8.00 62.52 500.16
b) Labour for cutting, bending, tying and placing in position

Mate day 0.44 195.43 85.99


Blacksmith day 3.00 247.19 741.57
Mazdoor day 8.00 187.43 1499.44
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) 49225.00

54
t
e
CHAPTER-1 w
CARRIAGE OF MATERIALS .
e
Item No. .
Descriptions Unit Rate (in Rs.) f

1.1 Loading and unloading of stone boulder / stone aggregates / sand / kanker /Earth/ 0
moorum. (Placing tipper at loading point, loading with front end loader, dumping, cum 145.00 5
###
turning for return trip, excluding time for haulage and return trip) .
1.2
1
Loading and Unloading of Boulders by Manual Means cum 175.00 ###
2
1.3 Loading and Unloading of Cement, Steel ,Bitumen,Hume Pipe (NP4) by Manual Means .
tonne 229.00 ###
0
and stacking.
1.4 6
Cost of Haulage Excluding Loading and Unloading
(i)
Surfaced Road tonne.km 7.10 ###
(ii)
Unsurfaced Gravelled Road tonne.km 8.50 ###
(iii)
Katcha Track and Track in river bed / nallah bed and choe bed. tonne.km 17.10 ###

25
CHAPTER-2
SITE CLEARANCE
Item No.
Descriptions Unit Rate (in Rs.)

2.1
Cutting of Trees, including Cutting of Trunks, Branches and Removal (Cutting of trees, including
cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with
all lifts and up to a lead of 1000 mtrs and earth filling in the depression/pit.)

(i) Girth from 300 mm to 600 mm each 161.00 ###


(ii) Girth from 600 mm to 900 mm each 276.00 ###
(iii) Girth from 900 mm to 1800 mm each 555.00 ###
(iv) Girth above 1800 mm each 1069.00 ###
2.2 Clearing Grass and Removal of Rubbish hectare 11812.00 ###
2.3 Clearing and Grubbing Road Land .(Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of
trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to
be used or auctioned up to a lead of 1000 metres including removal and disposal of top organic
soil not exceeding 150 mm in thickness.)
(i)
By Manual Means:-

A
In area of light jungle hectare 35644.00 ###
B
In area of thorny jungle hectare 47664.00 ###
(ii)
By Mechanical Means

A
In area of light jungle hectare 39088.00 ###
B
In area of thorny jungle hectare 47252.00 ###
2.4 Dismantling of Structures (Dismantling of existing structures like culverts, bridges, retaining
walls and other structure comprising of masonry, cement concrete, wood work, steel work,
including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable material with all lifts and lead of 1000
metres)
(i) Lime /Cement Concrete
I By Manual Means
A Lime Concrete, cement concrete grade M-10 and below cum 234.00 ###
B Cement Concrete Grade M-15 & M-20 cum 281.00 ###
C Prestressed / Reinforced cement concrete grade M-20 & above cum 768.00 ###
II By Mechanical Means for items No. 202( b) & ( c)
A Cement Concrete Grade M-15 & M-20 cum 330.00 ###
B Prestressed / Reinforced cement concrete grade M-20 & above cum 565.00 ###
(ii) Dismantling Brick / Tile work
A In lime mortar cum 139.00 ###
B In cement mortar cum 186.00 ###
C In mud mortar cum 120.00 ###
D Dry brick pitching or brick soling cum 111.00 ###
(iii) Dismantling Stone Masonry
A Rubble stone masonry in lime mortar cum 158.00 ###
B Rubble stone masonry in cement mortar. cum 186.00 ###
C Rubble Stone Masonry in mud mortar. cum 139.00 ###
D Dry rubble masonry cum 130.00 ###

26
E Dismantling stone pitching/ dry stone spalls. cum 120.00 ###
F Dismantling boulders laid in wire crates including opening of crates and stacking dismantled
materials.
cum 139.00 ###

27
(iv) Wood work wrought framed and fixed in frames of trusses upto a height of 5 m above plinth
level
cum 357.00 ###
(v) Steel work in all types of sections upto a height of 5 m above plinth level excluding cutting of
rivet.
A Including dismembering tonne 957.00 ###
B Excluding dismembering. tonne 707.00 ###
C Extra over item No( V ) A and( V ) B for cutting rivets. tonne 7.10 ###
(vi) Scraping of bricks dismantled from brick work including stacking.

A 1000
In lime/Cement mortar
numbers
827.00 ###
B 1000
In mud mortar
numbers
295.00 ###
(vii) Scraping of Stone from dismantled stone masonry
A In cement and lime mortar cum 332.00 ###
B In Mud mortar cum 70.00 ###
(viii) Scarping plaster in lime or cement mortar from brick/ stone masonry sqm 10.10 ###
(ix) Removing all type of hume pipes and stacking within a lead of 1000 metres including earthwork
and dismantling of masonry works.
A Up to 600 mm dia metre 123.00 ###
B Above 600 mm to 900 mm dia metre 166.00 ###
C Above 900 mm metre 284.00 ###
2.5 Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposal of
dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable
materials separately)
I By Manual Means
A Bituminous courses cum 433.00 ###
B Granular courses cum 305.00 ###
II By Mechanical Means
A Bituminous course cum 155.00 ###
2.6 Dismantling of Cement Concrete Pavement (Dismantling of cement concrete pavement by
mechanical means using pneumatic tools, breaking to pieces not exceeding 0.02 cum in volume
and stock piling at designated locations and disposal of dismantled materials up to a lead of
cum 934.00 ###
1000 metres, stacking serviceable and unserviceable materials separately)
2.7 Dismantling Guard Rails (Dismantling guard rails by manual means and disposal of dismantled
material with all lifts and up to a lead of 1000 metres, stacking serviceable materials and metre 46.00 ###
unserviceable materials separately.)
2.8 Dismantling Kerb Stone (Dismantling kerb stone by manual means and disposal of dismantled
material with all lifts and up to a lead of 1000 metre)
metre 8.00 ###
2.9 Dismantling Kerb Stone channel (Dismantling kerb stone channel by manual means and disposal
of dismantled material with all lifts and up to a lead of 1000 metre)
metre 12.00 ###
2.10 Dismantling Kilometre Stone (Dismantling of kilometre stone including cutting of earth,
foundation and disposal of dismantled material with all lifts and lead upto 1000 m and back
filling of pit.)
A 5th KM stone each 232.00 ###
B Ordinary KM Stone each 139.00 ###
C Hectometre Stone each 27.80 ###
2.11 Dismantling of Fencing (Dismantling of barbed wire fencing/ wire mesh fencing including posts,
foundation concrete, back filling of pit by manual means including disposal of dismantled
material with all lifts and up to a lead of 1000 metres, stacking serviceable material and
metre 32.40 ###
unserviceable material separately. )
2.12
Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line 600 mm dia including
disposal with all lifts and lead upto 1000 metres and stacking of serviceable material and metre 109.00 ###
unserviceable material separately under supervision of concerned department)

2.13
Removal of Cement Concrete Pipe of Sewer Gutter (Removal of cement concrete pipe of sewer
gutter 1500 mm dia under the supervision of concerned department including disposal with all
lifts and up to a lead of 1000 metres and stacking of serviceable and unserviceable material
metre 172.00 ###
separately but excluding earth excavation and dismantling of masonry works.)

2.14 Removal of Telephone / Electric Poles and Lines (Removal of telephone / Electric poles including
excavation and dismantling of foundation concrete and lines under the supervision of concerned
department, disposal with all lifts and up to a lead of 1000 metres and stacking the serviceable
each 110.00 ###
and unserviceable material separately)

28
29
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Item No.
Descriptions Unit Rate (in Rs.)

3.1 Excavation in Soil by Manual Means. (Excavation for roadway in soil using manual means
including loading in truck for carrying of cut earth to embankment site with all lifts and lead ###
upto1000 metres.)
(i) Including Royalty @ Rs. 24.0 per cum but excluding the cost of watering, rolling &
cum 188.00
compaction ###
(ii) Including Royalty @ Rs. 24.0 per cum , cost of watering, rolling & compaction cum 207.00

Note
In case there is a situation where the cross-section is of cut and fill and cut earth is required to
be used in embankment in the immediate vicinity, the item of carriage in the truck shall be cum 113.00
omitted. inclunding Royalty @ Rs. 24.00 per cum.

3.2 (i) Excavation in ordinary rock by manual means (Excavation in ordinary rock using manual means
including loading in a truck and carrying of excavated material to embankment site with in all
lifts and leads upto 1000 metres ) including Royalty @ Rs. 24.00 per cum but excluding cost of
cum 238.00 ###
watering , rolling & compaction
(ii)
Excavation in ordinary rock using manual means including loading in a truck and
carrying of excavated material to embankment site with in all lifts and leads upto 1000 cum 256.00
metres including Royalty @ Rs. 24.00 per cum, cost of watering , rolling & compaction

Note
In case there is a situation where the cross-section is of cut and fill and cut earth is
required to be used in embankment in the immediate vicinity, the item of carriage in the cum 162.00
truck shall be omitted - inclunding Royalty @ Rs. 24.00 per cum.
3.3 Excavation in Soil with Dozer with lead upto 100 metres (Excavation for road way in soil by
mechanical means including cutting and pushing the earth to site of embankment upto a
distance of 100 metres (average lead50 metres), including trimming bottom and side slopes in
cum 129.00 ###
accordance with requirements of lines, grades and cross sections.)
3.4
Excavation in Ordinary Rock with Dozer with lead upto 100 metres (Excavation for roadway in
ordinary rock by deploying a dozer, 80 HP including cutting and pushing the cut earth to site of
embankment upto a distance of 100 metres ( average lead 50 metres ), trimming bottom and
cum 217.00 ###
side slopes in accordance with the requirements of lines, grades and cross sections.)

3.5 Excavation in Hard Rock (requiring blasting) with disposal upto 1000 metres (Excavation for
roadway in hard rock (requiring blasting) by drilling, blasting and breaking, trimming of bottom
and side slopes in accordance with requirements of lines, grades and cross sections, loading and
cum 266.00 ###
disposal of cut road with in all lifts and leads upto 1000 metres )
3.6 Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto 1000 metres.
(Excavation for roadwork in soil with hydraulic excavator of0.9 cum bucket capacity including
cutting and loading in tippers, trimming bottom and side slopes, in accordance with ###
requirements of lines, grades and cross sections, and transporting to the embankment location
within all lifts and lead upto 1000m)
(i) Including Royalty @ Rs. 24.00 per cum but excluding the cost of watering, rolling &
cum 101.00
compaction.
(ii)
Including Royalty @ Rs. 24.00 per cum, cost of watering, rolling & compaction. cum 116.00

3.7 Excavation in Ordinary Rockusing Hydraulic ExcavatorCK-90 and Tippers with disposal upto
1000 metres. (Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum
bucket capacity including cutting and loading in tippers, transporting to embankment site within ###
all lifts and lead upto 1000 m, trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.)
(i) Including Royalty @ Rs. 24.00 per cum but excluding the cost of watering, rolling &
cum 119.00
compaction.
(ii)
Including Royalty @ Rs. 24.00 per cum, cost of watering, rolling & compaction. cum 138.00

3.8 Excavation in Hard Rock (blasting prohibited) (Excavation for roadway in hard rock (blasting
prohibited) with rock breakers including breaking rock, loading in tippers and disposal within
all lifts and lead upto 1000 metres, trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.)

30
A Mechanised cum 494.00 ###
B Manual Method cum 748.00 ###

31
3.9
Excavation in Hard Rock (controlled blasting) with disposal upto 1000 metres (Excavation for
roadway in hard rock with controlled blasting by drilling, blasting and breaking, trimming of
bottom and side slopes in accordance with requirements of lines, grades and cross sections,
cum 338.00 ###
loading and disposal of cut road with in all lifts and leads upto 1000 metres )

3.10 Excavation in Marshy Soil (Excavation for roadway in marshy soil with hydraulic excavator 0.9
cum bucket capacity including cutting and loading in tippers and disposal with in all lifts and
lead upto 1000 metres, trimming of bottom and side slopes in accordance with requirements of
###
lines, grades and cross sections.)
(i) Including Royalty @ Rs. 24.00 per cum but excluding the cost of watering, rolling &
cum 109.00
compaction.
(ii)
Including Royalty @ Rs. 24.00 per cum, cost of watering, rolling & compaction. cum 128.00
3.11 Removal of Unserviceable Soil with Disposal upto 1000 metres (Removal of unserviceable soil
including excavation, loading and disposal upto 1000 metres lead but excluding replacement by cum 78.00 ###
suitable soil which shall be paid separately as per clause 305.)
3.12 Pre-splitting of Rock Excavation Slopes (Carrying out excavation in hard rock to achieve a
specified slope of the rock face by controlled use of explosives and blasting accessories in
properly aligned and spaced drill holes, collection of the excavated rock by a 80 HP dozer, sqm 135.00 ###
loading in tipper by a front end loader and disposing of the material with all lifts and lead upto
1000 m, all as specified in clause No. 303)
3.13
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing
and technical specification, including setting out, construction of shoring and bracing, removal
of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation
earth to the extent required and utilising the remaining earth locally for road work.)

(i) Ordinary soil


A Manual Means (Depth upto 3 m) cum 189.00 ###
B Mechanical Means (Depth upto 3 m) cum 43.00 ###
(ii) Ordinary rock (not requiring blasting)
A Manual Means (Depth upto 3 m) cum 236.00 ###
B Mechanical Means cum 58.00 ###
(iii) Hard rock ( requiring blasting )
A Manual Means cum 417.00 ###
(iv) Hard rock ( blasting prohibited )
A Mechanical Means cum 474.00 ###
(v) Marshy soil
A Manual means ( upto 3 m depth) cum 307.00 ###
B Mechanical Means cum 140.00 ###
3.14 Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means (Scarifying the
existing granular road surface to a depth of 50 mm and disposal of scarified material within all sqm 15.30 ###
lifts and leads upto 1000 metres. )
3.15 Scarifying existing bituminous surface to a depth of 50 mm by mechanical means (Scarifying the
existing bituminous road surface to a depth of 50 mm and disposal of scarified material with in sqm 6.00 ###
all lifts and lead upto 1000 metres.)
3.16 Embankment Construction with Material Obtained from Borrow Pits (Construction of
embankment with approved material obtained from borrow pits with all lifts and leads,
transporting to site, spreading, grading to required slope and compacting to meet requirement
###
of table 300-2)
(i) Rolling with vibratory roller cum 192.00
(ii) Rolling with smooth wheeled roller cum 183.00
3.17 Construction of Embankment with Material Deposited from Roadway Cutting (Construction of
embankment with approved materials deposited at site from roadway cutting and excavation
from drain and foundation of other structures graded and compacted to meet requirement of
###
table 300-2)
(i) Rolling with vibratory roller cum 125.00
(ii) Rolling with smooth wheeled roller cum 115.00
3.18 Construction of Subgrade and Earthen Shoulders (Construction of subgrade and earthen
shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to
site, spreading, grading to required slope and compacted to meet requirement of table No. 300-
###
2)
(i) Rolling with vibratory roller cum 228.00
(ii) Rolling with smooth wheeled roller cum 216.00
3.19 Compacting Original Ground

32
Case-I Compacting original ground supporting subgrade (Loosening of the ground upto a level of500
mm below the subgrade level, watered, graded and compacted in layers to meet requirement of ###
table 300-2 for subgrade construction.)

33
(i) Rolling with vibratory roller cum 71.00
(ii) Rolling with smooth wheeled roller cum 59.00
Case-II Compacting original ground supporting embankment ###
(i) Rolling with vibratory roller cum 39.00
(ii) Rolling with smooth wheeled roller cum 27.00
3.20 Stripping and Storing Top Soil (Stripping, storing of top soil by road side at 15 m internal and
re-application on embankment slopes, cut slopes and other areas in localities where the cum 156.00 ###
available embankment material is not conducive to plant growth)
3.21 Stripping, storing and re-laying top soil from borrow areas in agriculture fields. (Stripping of top
soil from borrow areas located in agriculture fields, storing at a suitable place, spreading and re-
laying after taking the borrow earth to maintain fertility of the agricultural field, finishing it to
cum 77.00 ###
the required levels and satisfaction of the farmer.)
3.22 Turfing with Sods (Furnishing and laying of the live sods of perennial turf forming grass on
embankment slope, verges or other locations shown on the drawing or as directed by the sqm 37.00 ###
engineer including preparation of ground, fetching of rods and watering)
3.23 Seeding and Mulching (Preparation of seed bed on previously laid top soil, furnishing and
placing of seeds, fertilizer, mulching material, applying bituminous emulsion at the rate of0.23
litres per sqm and laying and fixing jute netting, including watering for 3 months all as per
sqm 141.00 ###
clause 308)
3.24 Surface Drains in Soil (Construction of unlined surface drains of average cross sectional area
0.40 sqm in soil to specified lines, grades, levels and dimensions to the requirement of clause
301 and 309. Excavated material to be used in embankment within a lead of50 metres (average
lead 25 metres))
A Mechanical means metre 66.00 ###
B Manual Means metre 47.00 ###
3.25 Surface Drains in Ordinary Rock (Construction of unlined surface drain of average cross
sectional area 0.4 sqm in ordinary rock to specified lines, grades, levels and dimensions as per
approved design and to the requirement of clause 301 to 309. Excavated material to be used in
embankment at site.)
A Mechanical Means metre 135.00 ###
B Manual Means metre 71.00 ###
3.26 Surface Drains in Hard Rock (Rate per metre may be worked out based on quantity of hard rock
metre VALUE
as per design.)
3.27
Sub Surface Drains with Perforated Pipe (Construction of subsurface drain with perforated pipe
of 100 mm internal diameter of metal/ asbestos cement/ cement concrete/PVC, closely jointed,
perforations ranging from 3 mm to 6 mm depending upon size of material surrounding the pipe, metre 360.00 ###
with 150 mm bedding below the pipe and 300 mm cushion above the pipe, cross section of
excavation 450 x 550 mm. Excavated material to be utilised in roadway at site )

3.28
Aggregate Sub- Surface Drains (Construction of aggregate sub surface drain 300 mm x 450 mm
with aggregates conforming to table 300-4, excavated material to be utilised in roadway )
metre 137.00 ###

3.29 Underground Drain at Edge of Pavement (Construction of an underground drain 1 m x 1 m


(inside dimensions) lined with RCC-20 cm thick and covered with RCC slab10 cm in thickness on metre 2414.00 ###
urban roads)
3.30 Preparation and Surface Treatment of formation. (Preparation and surface treatment of
formation by removing mud and slurry, watering to the extent needed to maintain the desired
moisture content, trimming to the required line, grade, profile and rolling with 8-10 tonne
sqm 2.00 ###
smooth wheeled roller, complete as per clause 310.)
3.31 Construction of Rock fill Embankment (Construction of rock fill embankment with broken hard
rock fragments of size not exceeding 300 mm laid in layers not exceeding 500 mm thick
including filling of surface voids with stone spalls, blinding top layer with granular material,
cum 70.00 ###
rolled with vibratory road roller, all complete as per clause 313)
3.32 Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area by
mechanical means including cutting and trimming of side slopes and disposing of excavated cum 172.00 ###
earth with all lifts and lead upto 1000 metres)
3.33 Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting.
(Excavation in hilly area in ordinary rock not requiring ballasting by mechanical means including
cutting and trimming of slopes and disposal of cut material with all lift and lead upto 1000
cum 244.00 ###
metres )
3.34 Excavation in Hilly Areas in Hard Rock Requiring Blasting (Excavation in hilly areas in hard rock
requiring blasting, by mechanical means including trimming of slopes and disposal of cut cum 304.00 ###
material with all lifts and lead upto 1000 metres.)
3.35 Work in Urban Roads (The cost of earth work in urban roads inhabited area will be
VALUE
comparatively higher due to following reasons:)

34
3.36 Embankment Construction with Fly ash/Pond ash available from coal or lignite burning Thermal
Plants as waste material. (Construction of embankment with fly ash conforming to table 1 of
IRC: SP: 58 - 2001 obtained from coal or lignite burning thermal power stations as waste cum 111.00 ###
material, spread and compacted in layer of 200mm thickness each at OMC, all as specified in
IRC: SP: 58-2001 and as per approved plans.)

35
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Item No.
Descriptions Unit Rate (in Rs.)

4.1 Granular Sub-base with Close Graded Material (Table:- 400-1)


A Plant Mix Method (Construction of granular sub-base by providing close graded
Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work
site, spreading in uniform layers with motor grader on prepared surface and
compacting with vibratory power roller to achieve the desired density, complete as per
clause 401 )
(i) for grading- I Material cum 1346.00 ###
(ii) for grading- II Material cum 1313.00 ###
(iii) for grading-III Material cum 1182.00 ###
B
By Mix in Place Method (Construction of granular sub-base by providing close graded
material, spreading in uniform layers with motor grader on prepared surface, mixing
by mix in place method with rotavator at OMC, and compacting with vibratory roller to
achieve the desired density, complete as per clause 401)

(i) for grading- I Material cum 1115.00 ###


(ii) for grading- II Material cum 1082.00 ###
(iii) for grading-III Material cum 951.00 ###
4.2
Granular Sub-Base with Coarse Graded Material ( Table:- 400- 2) (Construction of
granular sub-base by providing coarse graded material, spreading in uniform layers
with motor grader on prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the desired density, complete
as per clause 401)
(i) for grading- I Material cum 1077.00 ###
(ii) for grading- II Material cum 1067.00 ###
(iii) for grading-III Material cum 1036.00 ###
4.3
Lime Stabilisation for Improving Subgrade (Laying and spreading available soil in the
subgrade on a prepared surface, pulverising, mixing the spread soil in place with
rotavator with 3 % slaked lime having minimum content of 70% of CaO, grading with
motor grader and compacting with the road roller at OMC to the desired density to
form a layer of improved sub grade)
A By Mechanical Means cum 443.00 ###
B By Manual Means cum 431.00 ###
4.4 Lime Treated Soil for Sub- Base (Providing, laying and spreading soil on a prepared
sub grade, pulverising, mixing the spread soil in place with rotavator with 3 % slaked
lime with minimum content of 70% of CaO, grading with motor grader and cum 500.00 ###
compacting with the road roller at OMC to achieve at least 98%of the max dry density
to form a layer of sub base.)
4.5 Cement Treated Soil Sub Base/ Base (Providing, laying and spreading soil on a
prepared sub grade, pulverising, adding the designed quantity of cement to the spread
soil, mixing in place with rotavator, grading with the motor grader and compacting cum 725.00 ###
with the road roller at OMC to achieve the desired unconfined compressive strength
and to form a layer of sub-base/base.)
4.6 Cement Treated Crushed Rock or combination as per clause 403.2 and table 400.4 in
Sub base/ Base (Providing, laying and spreading Material on a prepared sub grade,
adding the designed quantity of cement to the spread Material, mixing in place with
rotavator, grading with the motor grader and compacting with the road roller at OMC
to achieve the desired unconfined compressive strength and to form a layer of sub-
base/base.)
(i) For Sub-Base course cum 1880.00 ###
(ii) For Base course cum 1432.00 ###
Making 50 mm x 50 mm Furrows (Making 50 mm x 50 mm furrows, 25mm deep, 450
4.7
to the center line of the road and at one metre interval in the existing thin bituminous
wearing coarse including sweeping and disposal of excavated material within 1000
metres lead)

36
i) 25 mm deep furrow cutting sqm 2.40 ###
ii) 50 mm deep furrow cutting sqm 4.90 ###

37
4.8 Inverted Choke (Construction of inverted choke by providing, laying, spreading and
compacting screening B type/ coarse sand of specified grade in uniform layer on a cum 404.00 ###
prepared surface with motor grader and compacting with power roller etc)
4.9 Water Bound Macadam (Providing, laying, spreading and compacting stone aggregates of
specific sizes to water bound macadam specification including spreading in uniform thickness,
hand packing, rolling with vibratory roller 8-10 tonnes / Smooth 3 wheeled Steel Roller in
stages to proper grade and camber, applying and brooming requisite type of screening/ binding
Materials to fill up the interstices of coarse aggregate, watering and compacting to the required
density.)
A By Manual Means
(i) Grading- I (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller) cum 1034.00 ###
With Smooth 3 wheeled Steel Roller cum 1026.00
(b) Using Screening Type-A (13.2mm Agg.) (with Vibratory Roller) cum 1211.00 ###
With Smooth 3 wheeled Steel Roller cum 1203.00
(ii) Grading- II (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller) cum 1135.00 ###
With Smooth 3 wheeled Steel Roller cum 1127.00
(b) Using Screening Type-A (13.2mm Agg.) (with Vibratory Roller) cum 1228.00 ###
With Smooth 3 wheeled Steel Roller cum 1219.00
(c) Using Screening Type-B (11.2mm Agg.) (with Vibratory Roller) cum 1271.00 ###
With Smooth 3 wheeled Steel Roller cum 1245.00
(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller) cum 1165.00 ###
With Smooth 3 wheeled Steel Roller cum 1156.00
(b) Using Screening Type-B (11.2mm Agg.) (with Vibratory Roller) cum 1283.00 ###
With Smooth 3 wheeled Steel Roller cum 1274.00
B By Mechanical Means:
(i) Grading- I (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller) cum 939.00 ###
With Smooth 3 wheeled Steel Roller cum 931.00
(b) Using Screening Type-A (13.2mm Agg.) (with Vibratory Roller) cum 1116.00 ###
With Smooth 3 wheeled Steel Roller cum 1108.00
(ii) Grading- II (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller) cum 1040.00 ###
With Smooth 3 wheeled Steel Roller cum 1032.00
(b) Using Screening Type-A (13.2mm Agg.) (with Vibratory Roller) cum 1133.00 ###
With Smooth 3 wheeled Steel Roller cum 1125.00
(c) Using Screening Type-B (11.2mm Agg.) (with Vibratory Roller) cum 1176.00 ###
With Smooth 3 wheeled Steel Roller cum 1150.00
(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller) cum 1070.00 ###
With Smooth 3 wheeled Steel Roller cum 1061.00
(b) Using Screening Type-B (11.2mm Agg.) (with Vibratory Roller) cum 1188.00 ###
With Smooth 3 wheeled Steel Roller cum 1180.00
4.10 Crushed Cement Concrete Sub-base / Base (Breaking and crushing of material obtained by
breaking damaged cement concrete slabs to size range not exceeding 75 mm as specified in
table 400.7 transporting the aggregates obtained from breaking of cement concrete slabs at a ###
lead of L km., laying and compacting the same as sub base/ base course, constructed as WBM
to clause 404 except the use of screening or binding Material.)
With Vibratory Roller cum 228.00
With Smooth 3 wheeled Steel Roller cum 219.00
4.11
Penetration Coat Over Top Layer of Crushed Cement Concrete Base (Spraying of bitumen over
cleaned dry surface of crushed cement concrete base at the rate of 25 kg per 10 sqm by a
bitumen pressure distributor, spreading of key aggregates at the rate of 0.13 cum per 10 sqm
sqm 19.10 ###
by a mechanical gritter and rolling the surface as per clause 506.3.8)

38
4.12 Wet Mix Macadam (Providing, laying, spreading and compacting graded stone aggregate to wet
mix macadam specification including premixing the Material with water at OMC in mechanical
mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- ###
base / base course on well prepared surface and compacting with vibratory roller to achieve the
desired density.)
With Vibratory Roller cum 1309.00
With Smooth 3 wheeled Steel Roller cum 1315.00
4.13 Construction of Median and Island with Soil Taken from Roadway Cutting (Construction of
Median and Island above road level with approved material deposited at site from roadway
cutting and excavation for drain and foundation of other structures, spread, graded and
cum 181.00 ###
compacted as per clause 407)
4.14 Construction of Median and Island with Soil Taken from Borrow Areas (Construction of median
and Island above road level with approved material brought from borrow pits, spread, sloped cum 211.00 ###
and compacted as per clause 407)
4.15 Construction of Shoulders (A. Earthen Shoulders)
B.) Hard Shoulders VALUE
C.) Paved Shoulders VALUE
4.16 Footpaths and Separators (Construction of footpath/separator by providing a 150 mm
compacted granular sub base as per clause 401 and 25 mm thick cement concrete grade M15,
over laid with precast concrete tiles in cement mortar 1:3 including provision of all drainage
sqm 631.00 ###
arrangements but excluding kerb channel.)
4.17 Crusher Run Macadam Base (Providing crushed stone aggregate, depositing on a prepared
surface by hauling vehicles, spreading and mixing with a motor grader, watering and
compacting with a vibratory roller to clause 410 to form a layer of sub-base/Base)
A By Mix in Place Method
(i) For 53 mm maximum size cum 938.00 ###
(ii) For 45 mm maximum size cum 973.00 ###
B By Mixing Plant :
(i) For 53 mm maximum size cum 1110.00 ###
(ii) For 45 mm maximum size cum 1161.00 ###
4.18
Lime, Fly ash stabalised soil sub-base (Construction of Sub-base using lime - fly ash admixture
with granular soil, free from organic matter/ deleterious material or clayey silts and low
plasticity clays having PI between 5 and 20 and liquid limit less than 25 and commercial dry
lime, slaked at site or pre-slaked with CaO content not less than 50%, fly ash to conform to cum 476.00 ###
gradation as per clause 4.3 of IRC: 88-1984, lime + fly ash content ranging between 10 to 30%,
the minimum un-confined compressive strength and CBR value after 28 days curing and 4 days
soaking to be 7.5 kg/sq, cm and 25% respectively, all as specified in IRC: 88-1984)

39
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Item No.
Descriptions Unit Rate (in Rs.)

5.1 Prime coat (Providing and applying primer coat with bitumen emulsion on prepared surface of
granular Base including clearing of road surface and spraying primer at the rate of 0.60 kg/sqm sqm 31.00 ###
using mechanical means.)
5.2 Tack coat
Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at
the rate of 0.20 kg per sqm on the prepared bituminous/granular surface cleaned with sqm 11.00 ###
mechanical broom.
5.3 Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH hot mix
plant producing an average output of 75 tonnes per hour using crushed aggregates of specified
grading premixed with bituminous binder, transported to site, laid over a previously prepared
surface with paver finisher to the required grade, level and alignment and rolled as per clauses
501.6 and 501.7 to achieve the desired compaction)
(i) for Grading I ( 40 mm nominal size ) cum 6301.00 ###
(ii) for GradingII(19 mm nominal size) cum 6226.00 ###
5.3 A
Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH hot mix
plant producing an average output of 75 tonnes per hour using crushed aggregates of specified
grading premixed with bituminous binder, transported to site, laid over a previously prepared
surface with paver finisher to the required grade, level and alignment and rolled as per clauses
501.6 and 501.7 to achieve the desired compaction)with modified graded bitumen.

(i) for Grading I ( 40 mm nominal size ) cum 6511.00


(ii) for GradingII(19 mm nominal size) cum 6436.00
5.3 B
Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH hot mix
plant producing an average output of 75 tonnes per hour using crushed aggregates of specified
grading premixed with bituminous binder, transported to site, laid over a previously prepared
surface with paver finisher to the required grade, level and alignment and rolled as per clauses
501.6 and 501.7 to achieve the desired compaction)with VG-30 Bulk bitumen.

(i) for Grading I ( 40 mm nominal size ) cum 5888.00


(ii) for GradingII(19 mm nominal size) cum 5813.00
5.4
Bituminous Penetration Macadam (Construction of penetration macadam over prepared Base by
providing a layer of compacted crushed coarse aggregate using chips spreader with alternate
applications of bituminous binder and key aggregates and rolling with a smooth wheeled steel
roller 8-10 tonne capacity to achieve the desired degree of compaction)

A 50 mm thick sqm 315.00 ###


B 75 mm thick sqm 436.00 ###
5.5 Built-Up-Spray Grout (Providing, laying and rolling of built-up-spray grout layer over prepared
base consisting of a two layer composite construction of compacted crushed coarse aggregates
using motor grader for aggregates. key stone chips spreader may be used with application of
bituminous binder after each layer, and with key aggregates placed on top of the second layer
sqm 254.00 ###
to serve as a Base conforming to the line, grades and cross-section specified, the compacted
layer thickness being 75 mm)
5.6 Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with
100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous binder @ 4.0 to 4.5% by weight of
total mix of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver
finisher with sensor control to the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH
specification clause No. 507 complete in all respects.)

(i) for Grading I ( 40 mm nominal size ) cum 7495.00 ###


(ii) for GradingII(19 mm nominal size) cum 7576.00 ###
5.6 A
Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with
100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous binder @ 4.0 to 4.5% by weight of
total mix of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver
finisher with sensor control to the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH
specification clause No. 507 complete in all respects.) with Modifed Graded Bitumen.

(i) for Grading I ( 40 mm nominal size ) cum 7780.00


(ii) for GradingII(19 mm nominal size) cum 7860.00

40
5.6 B
Dense Graded Bituminous Macadam (Providing and laying dense bituminous macadam with
100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous binder @ 4.0 to 4.5% by weight of
total mix of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver
finisher with sensor control to the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH
specification clause No. 507 complete in all respects.) with VG-30 Grade Bulk Bitumen.

(i) for Grading I ( 40 mm nominal size ) cum 6936.00


(ii) for GradingII(19 mm nominal size) cum 7017.00
5.7 Semi - Dense Bituminous Concrete (Providing and laying semi dense bituminous concrete with
100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5 % of mix and
filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor
control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and
tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 508
complete in all respects)
(i) for Grading I ( 13 mm nominal size ) cum 7812.00 ###
(ii) for GradingII(10 mm nominal size) cum 8278.00 ###
5.7 A
Semi - Dense Bituminous Concrete (Providing and laying semi dense bituminous concrete with
100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5 % of mix and
filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor
control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and
tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 508
complete in all respects) with Modified Graded Bitumen.

(i) for Grading I ( 13 mm nominal size ) cum 8113.00


(ii) for GradingII(10 mm nominal size) cum 8613.00
5.8 Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH batch type
hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of
specified grading, premixed with bituminous binder @ 5.4 to 5.6 % of mix and filler,
transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control
to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem
rollers to achieve the desired compaction as per MORTH specification clause No. 509 complete
in all respects)
(i) for Grading-I ( 13 mm nominal size ) cum 8713.00 ###
(ii) for Grading-II(10 mm nominal size) cum 8550.00 ###
5.9 Surface Dressing (Providing and laying surface dressing as wearing course in single coat using
crushed stone aggregates of specified size on a layer of bituminous binder laid on prepared
surface and rolling with 8-10 tonne smooth wheeled steel roller)
Case -1 19 mm nominal chipping size sqm 80.00 ###
Case - II 13 mm nominal size chipping sqm 64.00 ###

41
5.10
Open - Graded Premix Surfacing (Providing, laying and rolling of open - graded premix surfacing
of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade
bitumen or cut-back or emulsion to required line, grade and level to serve as wearing course on
a previously prepared base, including mixing in a suitable plant, laying and rolling with a smooth
wheeled roller 8-10 tonne capacity, finished to required level and grades.)

(i) Case - I: Mechanical method using Penetration grade Bitumen and HMP of appropriate capacity
not less than 75 tonnes/hour .
sqm 121.00 ###
(ii) Case - II: Open-Graded Premix Surfacing using cationic Bitumen Emulsion sqm 135.00 ###
5.11
Close Graded Premix Surfacing/Mixed Seal Surfacing (Mechanical means using HMP of
appropriate capacity not less than 75 tonnes/hour. Providing, laying and rolling of close-graded
premix surfacing material of 20 mm thickness composed of 11.2 mm to 0.09 mm (Type-a) or
13.2 mm to 0.09 mm (Type-b) aggregates using penetration grade bitumen to the required
line, grade and level to serve as wearing course on a previously prepared base, including mixing
in a suitable plant, laying and rolling with a Smooth wheeled roller 8-10 tonne capacity, and
finishing to required level and grade. )

i) For Type A sqm 152.00 ###


i) For Type B sqm 142.00 ###
5.12 Seal Coat (Providing and laying seal coat sealing the voids in a bituminous surface laid to the
specified levels, grade and cross fall using Type A and B seal coats)
(i) Case - I : Type A sqm 57.00 ###
(ii) Case - II : Type B (Providing and laying of premix sand seal coat with HMP of appropriate
capacity not less than 75 tonnes/ hours using crushed stone chipping 6.7 mm size and sqm 49.00 ###
penetration bitumen of suitable grade.)
5.13
Supply of Stone Aggregates for Pavement Courses (Supply of stone aggregates from approved
sources confirming to the physical requirement, specified in the respective specified clauses,
including royalties, fees rents, collection, transportation, stacking and testing and measured in
cum as per clause 514.5 Competitive market rates to be ascertained. Alternatively, rates for cum VALUE
stone crushing given in chapter 1may be adopted, if found economical. In case for supply of
aggregates at site are not available, nearest crusher site may be ascertained. Loading and un-
loading charges and cost of carriage may be added to these rates to arrive at the cost at site.)

5.14
Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt wearing course with paving
grade bitumen meeting the requirements given in table 500-29, prepared by using mastic
cooker and laid to required level and slope after cleaning the surface, including providing
antiskid surface with bitumen precoated fine-grained hard stone chipping of 13.2 mm nominal sqm #VALUE! ###
size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to
center in both directions, pressed into surface when the temperature of surfaces not less than
1000C, protruding 1 mm to 4 mm over mastic surface, all complete as per clause 515.)

5.15 Slurry Seal Providing and laying slurry seal consisting of a mixture of fine aggregates, portland
cement filler, bituminous emulsion and water on a road surface including cleaning of surface,
sqm
mixing of slurry seal in a suitable mobile plant, laying and compacting to provide even riding
surface)
(i) 5 mm thickness sqm 64.00 ###
(ii) 3 mm thickness sqm 45.00 ###
(iii) 1.5 mm thickness sqm 28.00 ###
5.16 Recycling of Bituminous Pavement with Central Recycling Plant (Recycling pavement by cold
milling of exiting bituminous layers, planning the surface after cold milling, reclaiming excavated
material to the extent of 30 % of the required quantity, hauling and stock piling the reclaimed
material near the central recycling plant after carrying out necessary checks and evaluation, cum 6651.00 ###
adding fresh material including rejuvenators as required, mixing in a hot mix plant, transporting
and laying at site and compacting to the required grade, level and thickness, all as specified in
clause 517.)
5.17 Fog Spray sqm ###
added
1.In case it is decided by the engineer to blind the fog spray, the following may be added sqm 4.60 ###
5.18 Bituminous Cold Mix ( Including Gravel Emulsion) (Providing, laying and rolling of bituminous
cold mix on prepared base consisting of a mixture of unheated mineral aggregate and
emulsified or cutback bitumen, including mixing in a plant of suitable type and capacity,
transporting, laying, compacting and finishing to specified grades and levels.)
(i) Using bitumen emulsion and 9.5 mm or 13.2 mm nominal size aggregate cum 10116.00 ###
(ii) Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate cum 10087.00 ###
(iii) Using cutback bitumen and 9.5 mm or 13.2 mm nominal size aggregate cum 7079.00 ###
(iv) Using cutback bitumen and 19 mm or 26.5 mm nominal size aggregate cum 7016.00 ###

42
5.19 Sand Asphalt Base Course (Providing, laying and rolling sand-asphalt base course composed of
sand, mineral filler and bituminous binder on a prepared sub-grade or sub-base to the lines,
cum 7217.00 ###
levels, grades and cross sections as per the drawings including mixing in a plant of suitable type
and capacity, transporting, laying, compacting and finishing.)
5.20
Modified Binder (Supply of modified binder produced by mixing bitumen with modifier
such as natural rubber or crumb rubber or any other polymer found compatible with
bitumen and which allows properties given in clause 521.3 and IRC: SP: 53 blending
tonne VALUE
of modifier with bitumen to be done either at the refinery or at the site plant capable
of producing the modified binder to be delivered in drums which shall be agitated in
melted condition using suitable device before use to ensure uniform dispersion.)

5.21 Crack Prevention Courses


(i)
Stress Absorbing Membrane (SAM) crack width less than 6 mm (Providing and laying
of a stress absorbing membrane over a cracked road surface, with crack width below 6
mm after cleaning with a mechanical broom, using modified binder complying with
clause 521, sprayed at the rate of 9 kg per 10 sqm and spreading 5.6 mm crushed sqm 56.00 ###
stone aggregates @ 0.11 cum per 10 sqm with hydraulic chip spreader, sweeping the
surface for uniform spread of aggregates and surface finished to conform to clause
902.)

(ii)
Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm (Providing and
laying of a stress absorbing membrane over a cracked road surface, with crack width 6
to 9 mm after cleaning with a mechanical broom, using modified binder complying
sqm 68.00 ###
with clause 521, sprayed at the rate of 11 kg per 10 sqm and spreading 11.2 mm
crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to clause 902.)

(iii)
Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above
50 % (Providing and laying a single coat of a stress absorbing membrane over a
cracked road surface, with crack width above 9 mm and cracked area above 50 %
after cleaning with a mechanical broom, using modified binder complying with clause sqm 90.00 ###
521, sprayed at the rate of 15 kg per 10 sqm and spreading 11.2 mm crushed stone
aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of
aggregates and surface finished to conform to clause 902.)

(iv) Case - IV : Bitumen Impregnated Geotextile (Providing and laying a bitumen


impregnated geotextile layer after cleaning the road surface, geotextile conforming to
requirements of clause 704.3, laid over a tack coat with 1.05 kg per sqm of paving sqm 134.00 ###
grade bitumen 80 - 100 penetration and constructed to the requirement of clause
704.4.5)
5.22
Recipe Cold Mix (Providing and laying of premix of crushed stone aggregates and
emulsion binder, mixed in a batch type cold mixing plant, laid over prepared surface,
by paver finisher, rolled with a pneumatic tyred roller initially and finished with a
smooth steel wheel roller, all as per clause 519.3)

(i) 75 mm thickness cum 6546.00 ###


(ii) 40 mm thickness cum 9160.00 ###
(iii) 25 mm thickness cum 10234.00 ###
5.8 A Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH batch type hot mix
plant producing an average output of 75 tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 5.4 to 5.6 % of mix and filler, transporting the hot mix
to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level
and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired
9054.00
compaction as per MORTH specification clause No. 509 complete in all respects) with Modifed Graded
Bitumen.
(i) for Grading-I ( 13 mm nominal size )
(ii) for Grading-II(10 mm nominal size) 8892.00
5.8 B Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH batch type hot mix
plant producing an average output of 75 tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 5.4 to 5.6 % of mix and filler, transporting the hot mix
to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level
and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired
cum 8041.00
compaction as per MORTH specification clause No. 509 complete in all respects) with Bulk VG30
Bitumen.
(i) for Grading-I ( 13 mm nominal size )

(ii) for Grading-II(10 mm nominal size) cum 7879.00

43
44
CHAPTER-6
CEMENT CONCRETE PAVEMENTS
Item No. Descriptions Unit Rate (in Rs.)

6.1
Dry Lean Cement Concrete Sub- base (Construction of dry lean cement concrete Sub-
base over a prepared sub-grade with coarse and fine aggregate conforming to IS:
383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not
to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement
cum 2318.00 ###
content not to be less than 150 kg/ cum, optimum moisture content to be determined
during trial length construction, concrete strength not to be less than 10 Mpa at 7
days, mixed in a batching plant, transported to site, laid with a paver with electronic
sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing.)

6.2
Cement Concrete Pavement (Construction of un-reinforced, dowel jointed, plain
cement concrete pavement over a prepared sub base with 43 grade cement @ 400 kg
per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse
aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per
approved mix design, transported to site, laid with a fixed form or slip form paver,
cum 5238.00 ###
spread, compacted and finished in a continuous operation including provision of
contraction, expansion, construction and longitudinal joints, joint filler, separation
membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod,
admixtures as approved, curing compound, finishing to lines and grades as per
drawing )

6.3
Rolled Cement Concrete Base (Construction of rolled cement concrete base course
with coarse and fine aggregate conforming to IS:383, the size of coarse aggregate not
exceeding 25 mm with minimum, aggregate cement ratio15:1 and minimum cement
content of 200 kg/cum, aggregate gradation to be as per table 600-4 after blending, cum 2681.00 ###
mixing in batching plant at optimum moisture content, transporting to site, laying with
a paver with electronic sensor, compacting with 8-10 tonnes smooth wheeled
vibratory roller to achieve, the designed flexural strength, finishing and curing.)

6.4 Transition section between rigid and flexible pavement (Due to change in the
properties of materials and type of construction, a gradual changeover from rigid
pavement to flexible pavement is desirable to avoid any damage at the butting joint.
After provision of an expansion joint in the cement concrete slab, the thickness of slab Value
should be tapered to 10 cm over a length of 3 m towards the flexible pavement. The
deficiency of thickness caused due to tapering of the slab should be made up by the
asphaltic layers.)
6.5 Construction of Base/Sub-base of pavement with lean concrete - fly ash. (Construction
of Base/sub-base using cement, sand, fly ash and coarse aggregates proportioned as
per table 4 of IRC: 74/1979 and with water content ratio, slump and compressive
strength as defined in the said table, mix prepared in a batching and mixing plant and
cum 2187.00 ###
compacted with a vibratory roller 8-10 tonnes capacity within the time limit laid down
vide clause 7.6.3 of IRC: 74-1979, construction joints properly formed at the end of
day's work, cured for 14 days, all as specified in IRC: 74-1979 and as per approved
plans.)
6.6
Cement - Fly ash concrete pavement. (Construction reinforced-reinforced, dowel
jointed, plain cement concrete pavement over a prepared sub base with 43 grade
cement, coarse and fine aggregate conforming to IS 383, maximum size of coarse
aggregate not exceeding 25 mm, replacing cement by fly ash to the extent of 15%
and sand by 10%, mixed in a batching and mixing plant as per approved mix design,
cum 4830.00 ###
transported to site, laid with a fixed form or slip form paver, spread, compacted and
finished in a continuous operation including provision of contraction, expansion,
construction and longitudinal joints, joint filler, separation membrane, sealant primer,
joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing
compound, finishing to lines and grades as per drawing )

45
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Item No.
Descriptions Unit Rate (in Rs.)

7.1 Sub- Surface Drain with Geotextiles (Construction of sub surface drain 200 mm dia using
geotextiles treated with carbon black with physical properties as given in clause 702.2.3 formed
in to a stable network and a planar geocomposite structure, joints wrapped with geotextile to metre 530.00 ###
prevent ingress of soil, all as per clause 702 and approved drawings including excavation and
backfilling)
7.2 Narrow Filter Sub- Surface Drain (Construction of a narrow filter sub- surface drain consisting of
porous or perforated pipe laid in narrow trench surrounded by a geotextile filter fabric, with a
minimum of 450 mm overlap of fabric and installed as per clause 702.3 and 309.3.5 including
metre 363.00 ###
excavation and backfilling)
7.3 Laying Paving Fabric Beneath a Pavement Overlay (Providing and laying paving fabric with
physical requirements as per table 704-2 over a tack coat of paving grade Bitumen 80-100
penetration, laid at the rate of 1 kg per sqm over thoroughly cleaned and repaired surface to
sqm 128.00 ###
provide a water resistant membrane and crack retarding layer. Paving fabric to be free of
wrinkling and folding and to be laid before cooling of tack coat, brooming and rolling of surface
with pneumatic roller to maximise paving fabric contact with pavement surface)

7.4
Laying Boulder Apron in Crates of Synthetic Geogrids (Providing, preparing and laying of
geogrid crated apron 1 m x 5 m, 600 mm thick including excavation and backfilling with baffles
at 1 metre interval, made with geogrids having characteristics as per clause 704.2, joining sides
with connectors/ring staples, top corners to be tie tensioned, placing of suitable cross interval
ties in layers of 300 mm connecting opposite side with lateral braces and tied with polymer cum #VALUE! ###
braids to avoid bulging, constructed as per clause 704.3. filled with stone with minimum size of
200 mm and specific gravity not less than 2.65, packed with stone spalls, keyed to the
foundation recess in case of sloping ground and laid over a layer of geotextile to prevent
migration of fines, all as per clause 704 and laid as per clause 2503.3 and approved design.)

7.5 Reinforced Earth Retaining Wall (Reinforced earth retaining walls have four main components as
under: a) Excavation for foundation, foundation concrete and cement concrete grooved
seating in the foundation for facing elements (facia material). b) Facia material and its
placement. c) Assembling, joining with facing elements and laying of the reinforcing elements.
d) Earthfill with granular material which is to be retained by the wall.)

(i) Assembling, joining and laying of reinforcing elements.


A With reinforcing element of steel / Aluminium strips / polymeric strips.
Type 1 1.Galvanised carbon steel strips metre 639.00 ###
Type 2 2.Copper Strips metre 639.00 ###
Type 3 3.Aluminium Strips metre 318.00 ###
Type 4 4.Stainless steel strips metre 318.00 ###
Type 5 5.Glass reinforced polymer/fibre reinforced polymer/polymeric strips metre 639.00 ###
B With reinforcing elements of synthetic geogrids sqm 122.00 ###
(ii) Facing elements of RCC sqm 1117.00 ###

46
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Item No.
Descriptions Unit Rate (in Rs.)

8.1 Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with top and
bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M-10 grade
foundation 150 mm thick, foundation having 50 mm projection beyond kerb stone, kerb stone
laid with kerb laying machine, foundation concrete laid manually, all complete as per clause
408)
A Using Concrete Mixer metre 232.00 ###
B Using Concrete Batching and Mixing Plant metre 240.00 ###
8.2 Cast in Situ Cement Concrete M 20 Kerb with Channel (Construction of cement concrete kerb
with channel with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20
grade PCC on M10 grade foundation 150 mm thick, kerb channel 300 mm wide, 50 mm thick in
PCC M20 grade, sloped towards the kerb, kerb stone with channel laid with kerb laying
machine, foundation concrete laid manually, all complete as per clause 408)

A Using Concrete Mixer metre 426.00 ###


B Using Concrete Batching and Mixing Plant metre 439.00 ###
8.3 Printing new letter and figures of any shade (Printing new letter and figures of any shade with
synthetic enamel paint black or any other approved colour to give an even shade)
(i)
Hindi ( Matras commas and the like not to be measured and paid for Half letter shall be cm height
counted as half ) per letter
0.60 ###

(ii) cm height
English and Roman
per letter
0.40 ###
8.4 Retro- reflectorised Traffic signs (Providing and fixing of retro- reflectorised cautionary,
mandatory and informatory sign as per IRC :67 made of encapsulated lens type reflective
sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5 mm thick supported on a mild
steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below
ground level as per approved drawing)
(i) 90 cm equilateral triangle each 5105.00 ###
( ii ) 60 cm equilateral triangle each 3250.00 ###
( iii ) 60 cm circular each 4464.00 ###
( iv ) 80 mm x 60 mm rectangular each 6348.00 ###
(v) 60 cm x 45 cm rectangular each 4340.00 ###
(vi ) 60 cm x 60 cm square each 5200.00 ###
( vii ) 90 cm high octagon each 8184.00 ###
8.5
Direction and Place Identification signs upto 0.9 sqm size board. (Providing and erecting
direction and place identification retro-reflectorised sign asper IRC:67 made of encapsulated
lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm thick with
sqm 11696.00 ###
area not exceeding 0.9 sqm supported on a mild steel single angle iron post 75 x 75 x 6 mm
firmly fixed to the ground by means of properly designed foundation with M15 grade cement
concrete 45 x 45 x 60 cm, 60 cm below ground level as per approved drawing)

8.6 Direction and Place Identification signs with size more than 0.9 sqm size board. (Providing and
erecting direction and place identification retro- reflectorised sign asper IRC :67 made of
encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 2
mm thick with area exceeding 0.9 sqm supported on a mild steel angle iron post 75 mm x 75 sqm 12065.00 ###
mm x 6 mm, 2 Nos. firmly fixed to the ground by means of properly designed foundation with M
15 grade cement concrete45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved
drawing)
8.7 Overhead Signs (Providing and erecting overhead signs with a corrosion resistant aluminium
alloy sheet reflectorised with high intensity retro-reflective sheeting of encapsulated lense type
with vertical and lateral clearance given in clause 802.2 and 802.3 and installed as per clause
802.7 over a designed support system of aluminium alloy or galvanised steel trestles and
trusses of sections and type as per structural design requirements and approved plans)
A Truss and Vertical Support tonne 72157.00 ###
B Aluminium alloy plate for over head sign tonne 1982.00 ###
8.8 Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the surface with
synthetic enamel paint in all shades on new plastered concrete surfaces)
sqm 46.00 ###
8.9 Painting on Steel Surfaces (Providing and applying two coats of ready mix paint of approved
brand on steel surface after through cleaning of surface to give an even shade)
sqm 40.00 ###

47
8.10 Painting on Wood Surfaces (Providing and applying two coats of ready mix paint of approved
brand on wood surface after through cleaning of surface to give an even shade)
sqm 45.00 ###
8.11 Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New Work (Painting lines,
dashes, arrows etc on roads in two coats on new work with ready mixed road marking paint
conforming to IS:164 on bituminous surface, including cleaning the surface of all dirt, dust and
other foreign matter, demarcation at site and traffic control )
(i) Over 10 cm in width sqm 78.00 ###
(ii) Up to 10 cm in width sqm 67.00 ###
8.12 Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old Work (Painting lines, dashes,
arrows etc on roads in two coats on old work with ready mixed road marking paint confirming
to IS: 164 on bituminous surface, including cleaning the surface of all dirt, dust and other
foreign matter, demarcation at site and traffic control )
(i) Over 10 cm in width sqm 53.00 ###
(ii) Up to 10 cm in width sqm 57.00 ###
8.13 Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on
Bituminous Surface (Providing and laying of hot applied thermoplastic compound 2.5 mm thick
including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive sqm 514.00 ###
of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free
from streaks and holes.)
8.14 Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of standard design as
per IRC:8-1980, fixing in position including painting and printing etc)
(i) 5th kilometre stone (precast) each 2636.00 ###
(ii) Ordinary Kilometer stone (Precast) each 1624.00 ###
(iii) Hectometer stone (Precast) each 460.00 ###
8.15
Road Delineators (Supplying and installation of delineators (road way indicators, hazard
markers, object markers), 80-100 cm high above ground level, painted black and white in 15 cm
wide stripes, fitted with 80 x 100 mm rectangular or 75 mm dia circular reflectorised panels at
each 608.00 ###
the top, buried or pressed into the ground and confirming toIRC-79 and the drawings.)

8.16 Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of standard design as
per IRC:25-1967, fixed in position including finishing and lettering but excluding painting)
each 402.00 ###

8.17 G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2 metres high GI barbed wire
fencing with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed every 3 metres center to
center founded in M15 grade cement concrete, 0.6 metre below ground level, every 15th post,
last but one end post and corner post shall be strutted on both sides and end post on one side
metre 256.00 ###
only and provided with 9 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed
with GI staples, turn buckles etc complete as per clause 807 )
8.18 G.I Barbed wire Fencing 1.8 metre high (Providing and fixing 1.8 metres high GI barbed wire
fencing with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed every 3 metres center to
center founded in M15 grade cement concrete, 0.6 metre below ground level, every 15th post,
last but one end post and corner post shall be strutted on both sides and end post on one side
metre 427.00 ###
only and provided with 12 horizontal lines and 2 diagonals interwoven with horizontal wires,
fixed with GI staples, turn buckles etc complete as per clause 807 )
8.19
Fencing with welded steel wire Fabric 75 mm x 50 mm (Suggestive) (Providing 1.20 metre high
fencing with angle iron posts 50 mm x 50 mm x 6 mm at 3 metre center to center with 0.40
metre embedded in M15 grade cement concrete, corner, end and every 10th post to be metre #VALUE! ###
strutted, provided with welded steel wire fabric of 75 mm x 50 mm mesh or 75 mm x 25 mm
mesh and fixed to iron posts by flat iron 50 x 5 mm and bolts etc. complete in all respects.)

8.20 Tubular Steel Railing on Medium Weight steel channel ( ISMC series) 100 mm x 50 mm
(Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly painted on medium
metre 1619.00 ###
weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 metres high above ground, 2 m
centre to centre, complete as per approved drawings)
8.21 Tubular Steel Railing on Precast RCC posts, 1.2 m high above ground level (Providing, fencing
and erecting 50 mm dia painted steel pipe railing in 3 rows on precast M20 grade RCC vertical
metre 1136.00 ###
posts1.8 metres high (1.2 m above GL) with 3 holes 50 mm dia for pipe, fixed 2 metres centre
to, complete as per approved drawing)
8.22
Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement concrete crash
barrier at the edges of the road, approaches to bridge structures and medians, constructed with
M-20 grade concrete with HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm
dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler board, keyed to the
structure on which it is built and installed as per design given in the enclosure to MOST circular
No. RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved
drawing and at locations directed by the Engineer, all as specified)

(i) M 20 grade concrete metre 2826.00 ###

48
8.23 Metal Beam Crash Barrier
A Type - A, "W" : Metal Beam Crash Barrier (Providing and erecting a "W" metal beam crash
barrier comprising of 3 mm thick corrugated sheet metal beam rail, 70 cm above road/ground
level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre,
1.8 m high, 1.1 m below ground/road level, all steel parts and fitments to be galvanised by hot metre 2757.00 ###
dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to be fixed on the
vertical post with a spacer of channel section 150 x 75 x 5 mm, 330 mm long complete as per
clause 810)
B Type - B, "THRIE" : Metal Beam Crash Barrier (Providing and erecting a "Thrie" metal beam
crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 85 cm above
road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m
centre to centre, 2 m high with 1.15 m below ground level, all steel parts and fitments to be metre 3223.00 ###
galvanised by hot dip process, all fittings to conform to IS:1367 and IS:1364, metal beam rail to
be fixed on the vertical post with a space of channel section 150 x 75 x 5 mm, 546 mm long
complete as per clause 810)
8.24 Road Traffic Signals electrically operated (Since it is a ready made item commercially produced
and erected by specialised firm in the electrical and electronic field, rate may be taken based on
Value
market enquiry from firms specialised in this field and ISI certified for the approved design and
drawing.)
8.25
Flexible Crash Barrier, Wire Rope Safety Barrier (Providing and erecting a wire rope safety
barrier with vertical posts of medium weight RS Joist (ISMB series) 100 mm x 75 mm (11.50
kg/m), 1.50 m long 0.85 m above ground and 0.65 m below ground level, split at the bottom
for better grip, embedded in M 15 grade cement concrete 450 x 450 x 450 mm, 1.50 m center
to center and with 4 horizontal steel wire rope 40 mm dia and anchored at terminal posts 15 m metre 1992.00 ###
apart. Terminal post to be embedded in M 15 gradecementconcretefoundation2400 x 450 x 900
mm (depth), strengthened by a strut of RS joist 100 x 75 mm, 2 m long at 450 inclination and a
tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in foundation concrete as per
approved design and drawing, rate excluding excavation and cement concrete.)

8.26 Anti - Glare Devices in Median


A Plantation (Plantation of shrubs and plants of approved species in the median. apart from
cutting off glare from vehicle coming from opposite direction, these plants provide a pleasant
envoirenment and are eco-friendly. The rate for this item is available in the chapter 11 on
Value
horticulture. )
B Anti - Glare Screen with 25 mm steel pipe framework fixed with circular and rectangular vans
(Providing and erecting an anti - glare screen with 25 mm dia vertical pipes fabricated and
framed in the form of panels of one metre length and 1.75 mtr height fixed with circular vane
250 mm dia at top and rectangular vane 600 x 300 mm at the middle, made out of steel sheet metre 2628.00 ###
of 3 mm thickness, end vertical pipes of the panel made larger for embedding in foundation
concrete, applying 2 coats of paint on all exposed surfaces, all as per approved design and
drawings.)
C
Anti - Glare Screen with Rectangular Vane of MS sheet (Providing and erecting anti - glare
screen with rectangular vanes of size 750 x 500 mm made from MS sheet, 3 mm thick and fixed
on MS angle 50 x 50 x 6 mm at an angle of 450 to the direction of flow of traffic, 1.5 m center
to center, top edge of the screen 1.75 m above ground level, vertical post firmly embedded in
metre 850.00 ###
cement concrete foundation 0.60 m below ground level, applying 2 coats of paint on exposed
faces, all complete as per approved design and drawings)

8.27 Street Lighting (Providing and erecting street light mounted on a steel circular hollow pole of
standard specifications for street lighting, 9 m high spaced 40 m apart, 1.8 m overhang on both
sides if fixed in the median and on one side if fixed on the footpath, fitted with sodium vapour
lamp and fixed firmly in concrete foundation.)
(i) For Fixing in Median each #VALUE! ###
(ii) For fixing in Footpath each #VALUE! ###
8.28 Lighting on Bridges (Providing and fixing lighting on bridges, mounted on steel hollow circular
poles of standard specifications, 5 m high fixed on parapets with cement concrete, 20 m apart each #VALUE! ###
and fitted with sodium vapour lamp)
8.29 Cable Duct Across the Road (Providing and laying of a reinforced cement concrete pipe duct,
300 mm dia, across the road (new construction), extending from drain to drain in cuts and toe
of slope to toe of slope in fills, constructing head walls at both ends, providing a minimum fill of
granular material over top and sides of RCC pipe as per IRC:98-1997, bedded on a 0.3 m thick
layer of granular material free of rock pieces, outer to outer distance of pipe at least half dia of
pipe subject to minimum 450 mm in case of double and triple row ducts, joints to be made leak
proof, invert level of duct to be above higher than ground level to prevent entry of water and
dirt, all as per IRC: 98 - 1997 and approved drawings.)
(i) Single Row for one utility service metre #VALUE! ###
(ii) Double Row for two utility services metre #VALUE! ###
(iii) Triple Row for three utility services metre #VALUE! ###

49
8.30
Highway Patrolling and Traffic Aid Post (It is proposed to locate one Traffic Aid Post every 50-60
km of the highway. )
VALUE

8.31
Items related to under pass/ subway/ overhead bridge/ overhead foot bridge (The items
involved for underpass/ subway/ overhead bridge/ overhead foot bridge are earthwork, plain
cement concrete, plastering, painting, information sign etc. The rates for these items are VALUE
available in respective chapters which can be adopted for the quantities derived from the
approved designs and drawings)

8.32 Traffic Control System and Communication system (Providing a traffic control centre and
communication system including telecommunication facilities and related accessories, CCTV,
radar, vehicle detection camera, central computer system These are specialised item of
telecommunication system and are the commercial products. The designer is required to contact VALUE
the manufacturers to ascertain market prices. In case of civil works required to be executed for
these installations, pricing may be done as per rates in relevant chapters for quantities derived
approved design and drawing.)
8.33 Gantry Mounted Variable Message Sign board (Providing and erecting gantry mounted variable
message sign board electronically operated capable of flashing the desired message over a
designed support system of aluminium alloy or galvanised steel, erected as per approved design
and drawings and with lateral clearance as per clause 802.3)
(i) Gantry Support System tonne 69837.00 ###
(ii) Message Display (Message display board 6 sqm electronically operated with complete electronic
VALUE
fitments for flashing the pre-determined messages.)
8.34 Traffic Impact Attenuators at Abutments and Piers
A
With Scrap Tyres (Provision and installation of traffic attenuators at abutment/pier of flyovers
bridges using scrap tyres of size 100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one sqm 612.00 ###
above the other and tied with 20 mm wire rope as per approved design and drawings.)

B
Using Plastic/Steel Barrel, Filled with Sand (Provision and installation of traffic impact attenuator
at abutment/pier of flyovers bridges using plastic/steel barrels 0.60 m dia and 1.0 m in height,
filled with sand in three rows and tied with20 mm steel wire rope as per approved design and
sqm 463.00 ###
drawings)

C With HI - DRO cell Sandwich (Patented) ((In this patented HI - DRO cell system, water gets
discharged from plastic tubes on impact over a pre-determined time, thus absorbing the sqm #VALUE! ###
energy))
8.35 Road Markers/Road Stud with Lense Reflector (Providing and fixing of road stud 100x 100 mm,
vide cl. 804.2 of MORTH (5th Revision), resistant to corrosive effect of salt and grit, fitted with
lense reflectors, installed in concrete or asphaltic surface by drilling hole 30 mm upto a depth of each 227.00 ###
60 mm and bedded in a suitable bituminous grout or epoxy mortar, all as per BS 873 part
4:1973)
8.36 Traffic Cone (Provision of red fluorescent with white reflective sleeve traffic cone made of low
density polyethylene (LDPE) material with a square base of 390 x 390 x 35 mm and a height of each 480.00 ###
770 mm, 4 kg in weight, placed at 1.5 m interval, all as per BS 873)
8.37 Roadside Amenities
A
Rest Areas (Providing plainly furnished accommodation for rest rooms, dormitories, restaurants,
stalls, shops, petrol pump, telephone booth, first aid room, traffic aid post, police assistance
booth, including electricity, toilet and sewerage system Pricing may be done based on current VALUE
plinth area rates approved by PWD/CPWD/MES for a particular zone. Area is required to be
assessed for specific location as per actual site conditions)

B Parking areas and Bus Laybyes for Trucks, Buses and Light vehicles (Pricing of parking areas
may be done for the quantities of various items based on the approved dimensions and
VALUE
pavement design for a particular terrain and soil. Rates for items may be from respective
chapters.)
C Lawn (Providing a lawn planted with grass and its maintenance ) VALUE
8.38 Rumble Strips (Provision of 15 nos rumble strips covered with premix bituminous carpet,
15-20 mm high at center, 250 mm wide placed at 1 m center to center at approved locations to sqm VALUE
control speed, marked with white strips of road marking paint.)
8.39
Policeman Umbrella (Provision of a 2 m high (floor to roof) umbrella for traffic policeman at
road crossings, where necessary, installed on a raised platform, built on a central support of a
each VALUE
steel pipe 100 mm dia, roof made of 25 mm dia steel pipe to provide covered area of 3 sqm,
roofed with CGI sheets, all steel parts to be given 2 coats of paint)

50
8.40 High Mast Pole Lighting at Interchanges and Flyovers (Providing and erecting a high mast pole
lighting with 30 m high hot dip galvanised mast designed to withstand forces exerted with wind
speeds of 180 km per hour with 3 seconds gust, as per IS:875 (Part 3) - 1978, fitted with a
base flange, door at the base of mast with heavy duty internal lock, lantern carriage, suitable
winching arrangement for safe working load of 750 kg and high powered electrically driven
power tools for raising and lowering of lantern carriage, flexible 8 core electric cable,
lightening conductor, earthing terminal, and fixing 2 nos aviation obstruction lights on top of VALUE
the mast, all complete as per approved design and drawings This is a specialised work and is
generally done by firms who specialise in such jobs. The detailed designs and estimates are
submitted by the firms alongwith their tender for checks by the Department. The cost of this
work is required to be worked out based on approved design, drawings and estimate of the
lowest tender. A separate contract for this work is concluded as the contractors for road and
bridge works generally donot undertake such jobs.)

8.41 Toll Plaza (The construction, operation and maintenance of Toll Plaza can be broken into
separate items of work as under based on the approved design and drawings:-)
8.42
Safety Devices and signs in Construction Zones (Provision and fixing of traffic signs for limited
period at suitable locations in construction zone comprising of warning zone, approach
transition zone, working zone and terminal transition zone with a minimum distance of 60 cm
from the edge of the kerb in case of kerbed roads and 2 to 3 m from the edge of the
VALUE
carriageway in case of un-kerbed roads, the bottom edge of the lowest sign plate to be not less
than 2 m above the road level, fixed on 60 mm x 60 mm x 6 mm angle iron post, founded and
installed as per approved design and drawings, removed and disposed of after completion of
construction work, all as per IRC:SP:55-2001)

8.43
Portable Barricade in Construction Zone (Installation of a steel portable barricade with horizontal
rail 300 mm wide, 2.5 m in length fitted on a 'A' frame made with 45 x 45 x 5 mm angle iron
section, 1.5 m in height, horizontal rail painted (2 coats) with yellow and white stripes, 150 each 2737.00 ###
mm in width at an angle of 450, 'A' frame painted with 2 coats of yellow paint, complete as
per IRC: SP : 55-2001 )

8.44 Permanent Type Barricade in Construction Zone


A
With Steel Components (Construction of a permanent type barricade made of steel components,
1.5 m high from road level, fitted with 3 horizontal rails 200 mm wide and 4 m long on 50 x 50
each 4329.00 ###
x 5 mm angle iron vertical support, painted with yellow and white strips, 150 mm in width at
an angle of450, complete as per IRC:SP:55-2001 )

B
With Wooden Components (Construction of a permanent type barricade made of wooden
components, 1.5 m high from road level, fitted with 3 horizontal planks 200 mm wide and 3.66
each 7397.00 ###
m long on 100 x 100mm wooden vertical post, painted with yellow and white striups, 150 mm
in width at an angle of450, complete as per IRC:SP:55-2001 )

C
With Bricks (Construction of a permanent type barricade made with brick work in mud mortar,
1.5 m high, 4 m long, 600 mm thick, plastered with cement mortar 1:6, painted with yellow each 12297.00 ###
and white strips)

8.45
Drum Delineator in Construction Zone (Provision of metal drum/empty bitumen drum delineator,
300 mm in diameter, 800 mm high, filled with earth for stability, painted in circumferential
strips of alternate black and white 100 mm wide fitted with reflectors 3 Nos of 7.5 cm dia, all
each 326.00 ###
as per IRC:SP:55-2001)

8.46
Flagman (Positioning of a smart flagman with a yellow vest and a yellow cap and a red flag 600
x 600 mm securely fastened to a staff 1 m in length for guiding the traffic)
each 305.00 ###

51
CHAPTER-9
PIPE CULVERTS
Item No.
Descriptions Unit Rate (in Rs.)

9.1 PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 mix with crushed stone aggregate 40 mm
nominal size mechanically mixed, placed in foundation and compacted by vibration including cum 3372.00 ###
curing for 14 days.)

9.2 Laying Reinforced Cement Concrete Pipe NP4/prestrssed concrete pipe on first class bedding in
single row . (Laying Reinforced cement concrete pipe NP4/prestrssed concrete pipe for culverts
on first class bedding of granular material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets . )

A 1000 mm dia metre 5505.00 ###


B
1200 mm dia metre 6693.00 ###
9.3 Laying Reinforced Cement Concrete Pipe NP 4 /prestrssed concrete pipe on first class bedding in
double row . (Laying Reinforced cement concrete pipe NP4 /prestrssed concrete pipe for
culverts on first class bedding of granular material in double row including fixing collar with
cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets . )

A
1000 mm dia metre 11064.00 ###
B
1200 mm dia metre 13443.00 ###

52
CHAPTER-10
MAINTENANCE OF ROADS
Item No.
Descriptions Unit Rate (in Rs.)

10.1 Restoration of Rain Cuts (Restoration of rain cuts with soil, moorum, gravel or a mixture of
these, clearing the loose soil, benching for 300 mm width, laying fresh material in layers not
exceeding 250 mm and compacting with plate compactor or power rammers to restore the
cum 83.00 ###
original alignment, levels and slopes)
10.2 Maintenance of Earthen Shoulder (filling with fresh soil) (Making up loss of material/
irregularities on shoulder to the design level by adding fresh approved soil and compacting it sqm 37.00 ###
with appropriate equipment.)
10.3 Maintenance of Earth Shoulder (stripping excess soil) (Stripping excess soil from the shoulder
surface to achieve the approved level and compacting with plate compactor)
sqm 13.00 ###
10.4
Filling Pot- holes and Patch Repairs with open - graded Premix surfacing, 20mm. (Removal of
all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of
surface, painting of tack coat on the sides and base of excavation as per clause 503, back sqm 135.00 ###
filling the pot holes with hot bituminous material as per clause 511, compacting, trimming and
finishing the surface to form a smooth continuous surface, all as per clause 3004.2)

10.5
Filling Pot- holes and Patch Repairs with - Bituminous concrete, 40mm. (Removal of all failed
material, trimming of completed excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot
holes with hot bituminous material as per clause 504, compacting, trimming and finishing the
surface to form a smooth continuous surface, all as per clause 3004.2)

(i) for grading I Material sqm 347.00 ###


(ii) for grading II Material sqm 341.00 ###
10.6 Crack Filling (Filling of crack using slow - curing bitumen emulsion and applying crusher dust in
case crack are wider than 3mm.)
metre 3.70 ###
10.7 Dusting (Applying crusher dust to areas of road where bleeding of excess bitumen has
occurred.)
sqm 0.60 ###
10.8 A Fog Seal (ref item 5.17) sqm 38.00 ###
B Crack Prevention courses. (ref item 5.21)
(i) Stress Absorbing Membrane (SAM) crack width less than 6 mm sqm 56.00 ###
(ii) Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm sqm 68.00 -
(iii)
Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above 50 % sqm 90.00 -
(iv) Bitumen Impregnated Geotextile sqm 134.00 -
C Slurry Seal (ref item 5.15)
(i) 5 mm thickness sqm 64.00 ###
(ii) 3 mm thickness sqm 45.00 ###
(iii) 1.5 mm thickness sqm 28.00 ###
D Surface Dressing for maintance works. (ref item 5.9)
(i) 19 mm nominal chipping size sqm 80.00 ###
(ii) 13 mm nominal size chipping sqm 64.00 ###
10.9 Repair of joint Grooves with Epoxy Mortar Repair of spalled joint grooves of contraction joints,
longitudinal joints and expansion joints in concrete pavements using epoxy mortar or epoxy metre 371.00 ###
concrete)
10.10 Repair of old Joints Sealant (Removal of existing sealant and re sealing of contraction,
longitudinal or expansion joints in concrete pavement with fresh sealant material)
metre 19.00 ###
10.11 Hill Side Drain Clearance (Removal of earth from the choked hill side drain and disposing it on
the valley side manually)
metre 24.60 ###
10.12 Land Slide Clearance in soil (Clearance of land slides in soil and ordinary rock by a bull-dozer D
80 A-12, 180 HP and disposal of the same on the valley side)
cum 66.00 ###
10.13 Land slide Clearance in Hard Rock Requiring Blasting (Clearing of land slide in hard rock
requiring blasting for 50% of the boulders and disposal of the same on the valley side.)
cum 114.00 ###
10.14 Snow Clearance on Roads with Dozer (Snow clearance from road surface by a bull- dozer 165
Hp and disposing it on the valley side)
cum 4.60 ###
10.15 Snow Clearance on Roads with Snow Blowers (Snow clearance from road surface by a snow
cum #VALUE! ###
blower and disposing on the valley side.)

53
CHAPTER-11
HORTICULTURE
Item No.
Descriptions Unit Rate (in Rs.)

11.1 Spreading of Sludge Farm Yard Manure or/and good Earth (Spreading of sludge farm yard
manure or/ and good earth in required thickness (cost of sludge, farm- yard manure or/and cum 15.70 ###
good earth to be paid for separately))
11.2 Grassing with ' Doobs' Grass (Grassing with 'Doobs' grass including watering and maintenance
of the lawn for 30 days or more till the grass forms a thick lawn free from weeds and fit for
moving including supplying good earth if needed)
(i) In rows 15 cm apart in either direction sqm 8.70 ###
(ii) In rows 7.5 cm apart in either direction sqm 14.00 ###
11.3 Making Lawns including Ploughing and Dragging with 'Swagha' Breaking of Clod (Making lawns
including ploughing and breaking of clod, removal of rubbish, dressing and supplying doobs
grass roots and planting at 15 cm apart, including supplying and spreading of farm yard
sqm 9.70 ###
manure at rate of 0.18 cum per 100 sqm)
11.4 Maintenance of Lawns or Turfing of Slopes (Maintenance of lawns or Turfing of slopes (rough
grassing) for a period of one year including watering etc)
sqm 229.00 ###
11.5 Turfing Lawns with Fine Grassing including Ploughing, Dressing (Turfing lawns with fine
grassing including ploughing, dressing including breaking of clods, removal of rubbish,
dressing and supplying doobs grass roots at 10 cm apart, including supplying and spreading of
sqm 15.00 ###
farm yard manure at rate of0.6 cum per 100 sqm)
11.6 Maintenance of Lawns with Fine Grassing for the First Year sqm 175.00 ###
11.7 a) Planting Permanent Hedges including Digging of Trenches (Planting permanent hedges
including digging of trenches, 60 cm wide and 45 cm deep, refilling the excavated earth mixed
with farmyard manure, supplied at the rate of 4.65 cum per 100 metres and supplying and
metre 259.00 ###
planting hedge plants at 30 cm apart)
(b) Maintenance of Hedge for one year metre 174.00 ###
11.8 a) Planting Flowering Plants and Shrubs in Central Verge km 68661.00 ###
(b) Maintenance of Flowering Plants and Shrubs in Central Verge for one Year km 147975.00 ###
11.9 Planting of Trees and their Maintenance for one Year (Planting of trees by the road side
(Avenue trees) in 0.60 m dia holes, 1 m deep dug in the ground, mixing the soil with decayed
farm yard/sludge mannure, planting the saplings, backfilling the trench, watering, fixing the
each 780.00 ###
tree guard and maintaining the plants for one year)
11.10
Renovation Lawns including, Weeding, Forking the Ground, Top Dressing with Forked Soil
(Renovation lawns including, weeding, forking the ground, top dressing with forked soil,
watering and maintenance the lawns, for 30 days or more, till the grass forms a thick lawn, sqm 13.80 ###
free from weeds, and fit for moving and disposal of rubbish as directed, including supplying
good earth, if needed but excluding the cost of well decayed farm yard manure)

11.11 Supply at Site Well Decayed Farm Yard Manure (Supply at site of work well decayed farm yard
manure, from any available source, approved by the engineer in charge including screening cum 640.00
and stacking) ###
11.12 Supply at Site of Work/ Store - Deoiled Neem Cake (Supply at site of work/ store- deoiled neem
quintal VALUE
cake duly packed in used gunny bags)
11.13 Supplying Sludge (Supplying sludge duly stacked at site/ store) cum VALUE
11.14 Half Brick Circular Tree Guard, in 2nd class Brick, internal diametre 1.25 metres, and height
1.2 metres, above ground and 0.20 metre below ground (Half brick circular tree guard, in 2nd
class brick, internal diametre 1.25 metres, and height 1.2 metres, above ground and 0.20
each 1523.00 ###
metre below ground, bottom two courses laid dry, and top three courses in cement mortar 1:6
( 1 cement 6 sand) and the intermediate courses being in dry honey comb masonry, as per
design complete)
11.15 Edging with 2nd class Bricks, laid dry lengthwise (Edging with 2nd class bricks, laid dry
lengthwise, including excavation, refilling, consolidation, with a hand packing and spreading metre 31.20 ###
nearly surplus earth within a lead of 50 metres)
11.16
Making Tree Guard 53 cm dia and 1.3 m high as per design from empty bitumen drum (Making
tree guard 53 cm dia and 1.3 m high as per design from empty bitumen drum, slit suitably to
permit sun and air, (supplied by the department at stock issue rate) including providing and
each 363.00 ###
fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets, complete in all respect)

54
11.17
Making Tree Guard 53 cm dia and 2 metres high as per design from empty bitumen drums
(Making tree guard 53 cm dia and 2 metres high as per design from empty bitumen drums, slit
suitably to permit sun and air, ( supplied by the department at stock issue rate) including each 734.00 ###
providing and fixing four legs 40 cm long of 30 x 3 mm MS riveted to tree guard and providing
and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets complete in all respects)

55
11.18 Wrought Iron and Mild Steel Welded Work (Wrought iron and mild steel welded work) (using
angles, square bars, tees and channel grills, grating frames, gates and tree guards of any
size and design etc. including cost of screens and welding rods or bolts and nuts complete fixed quintal 7586.00 ###
in position but without the cost of excavation and concrete for fixing which will be paid
separately)
11.19 Tree Guard with MS Iron (Providing and fixing MS iron tree guard 60 cm dia and 2 metre high
above ground level formed of 4 Nos (25 x 6 mm) and 8 Nos (25 x 3 mm) vertical MS riveted to
each tree
3 Nos (25 x 6 mm) iron rings in two halves, bolted together with 8 mm dia and 30 mm long 1898.00 ###
guard
bolts including painting two coats with paint of approved brand over a coat of priming,
complete in all respects.)
11.20
Tree Guard with MS Angle Iron and Steel Wire (Providing and fixing tree guard 0.60 metre
each tree
square, 2.00 metre high fabricated with MS angle iron 30 x 30 x 3 mm, MS iron 25 x 3 mm 2442.00 ###
guard
and steel wire3 mm dia welded and fabricated as per design in two halves bolted together)

11.21
Compensatory Afforestation (Planting trees as compensatory afforestation at the rate of 290
trees per hectare at a spacing of 6 m by grubbing and leveling the ground upto a depth of 150
hectare 97806.00 ###
mm, digging holes 0.9 m dia, 1 m deep, mixing farm yard/sludge manure with soil, planting
of sapling 2 m high with 25 cm dia stem, backfilling the hole and watering)

56
CHAPTER-12
FOUNDATIONS
Item No.
Descriptions Unit Rate (in Rs.)

12.1 Excavation for Structures (Earth work in excavation of foundation of structures as per drawing
and technical specification, including setting out, construction of shoring and bracing, removal
of stumps and other deleterious matter, dressing of sides and bottom and backfilling with
approved material.)
I Ordinary soil
A Manual Means
(i) upto 3 m depth cum 94.00 ###
(ii) 3 m to 6 m depth cum 121.00 ###
(iii) Above 6 m depth cum 161.00 ###
B Mechanical Means
(i) Depth upto 3 m cum 61.00 ###
(ii) Depth 3 m to 6 m cum 70.00 ###
(iii) Depth above 6m cum 84.00 ###
II Ordinary rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m cum 134.00 ###
B Mechanical Means cum 78.00 ###
III Hard rock ( requiring blasting )
A Manual Means cum 363.00 ###
IV Hard rock ( blasting prohibited )
A Mechanical Means cum 377.00 ###
V Marshy soil
(i) upto 3 m depth
A Manual means cum 331.00 ###
B Mechanical Means cum 141.00 ###
VI Back Filling in Marshy Foundation Pits cum 213.00 ###
12.2 Filling Annular Space Around Footing in Rock (Lean cement concrete 1:3:6 nominal mix. Rate
may be taken as per items 13.4.)
12.3 Sand Filling in Foundation Trenches as per Drawing & Technical Specification cum 264.00 ###
12.4 PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed
stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted cum 3879.00 ###
by vibration including curing for 14 days.)
12.5 Brick masonry work in cement mortar in foundation complete excluding pointing and plastering,
as per drawing and technical specifications
###
(i) Rate for Brick Work in C. M. 1:2 in foundation cum 5406.00
(ii) Rate for Brick Work in C. M. 1:3 in foundation cum 5094.00
(iii) Rate for Brick Work in C. M. 1:4 in foundation cum 4882.00
(iv) Rate for Brick Work in C. M. 1:6 in foundation cum 4676.00
12.6 A Cement mortar1:3 (1cement :3 sand) cum 3447.00 ###
B Cement mortar1:2 (1cement :2 sand) cum 4392.00 ###
C Cement mortar1:4 (1cement :4 sand) cum 2804.00 ###
D Cement mortar1:6 (1cement :6 sand) cum 2179.00 ###
12.7 Stone masonry work in cement mortar 1:3 in foundation complete as drawing and Technical
Specification
(a) Square Rubble Coursed rubble masonry( first sort ) cum 3034.00 ###
(b) Random Rubble Masonry cum 2977.00 ###
12.8 Plain/Reinforced cement concrete in open foundation complete as per drawing and technical
specifications
A PCC Grade M15 cum 4259.00 ###
B PCC Grade M20 cum 4835.00 ###
C RCC Grade M20
Case I Using concrete mixer cum 4864.00 ###

57
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 4748.00 ###
D PCC Grade M25
Case I Using concrete Mixer cum 5296.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5183.00 ###
E RCC Grade M25
Case I Using concrete Mixer cum 5330.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5214.00 ###
F PCC Grade M30
Case I Using Concrete Mixer cum 5334.00 ###
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5217.00 ###
G RCC Grade M30
Case I Using Concrete Mixer cum 5346.00 ###
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5231.00 ###
H RCC Grade M35
Case I Using Concrete Mixer cum 5450.00 ###
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5336.00 ###
12.9 Providing and constructing temporary island 16 m diameter for construction of well foundation
for 8m dia. Well.
A Assuming depth of water 1.0 m and height of island to be 1.25m including Royalty for earth @
each 36545.00 ###
Rs. 3768.00 for each Island.
B Assuming depth of water 4.0 m and height of island 4.5 m including Royalty for earth @ Rs.
each 151808.00 ###
13565.00 for each Island.
C
Providing and constructing one span service road to reach island location from one pier location
to another pier location including Royalty for earth @ Rs. 225.00 per m for service Road.
metre 3102.00 ###

12.10 Providing and laying cutting edge of mild steel weighing 40 kg per metre for well foundation
tonne 88001.00 ###
complete as per drawing and technical specification.
12.11 Plain/Reinforced cement concrete, in well foundation complete as per drawing and technical
specification
A Well curb
(i) RCC M20 Grade
Case I Using concrete mixer cum 5613.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5476.00 ###
(ii) RCC M25 Grade
Case I Using concrete mixer cum 6166.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6031.00 ###
(iii) RCC M35 Grade
Case I Using concrete mixer cum 6351.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6532.00 ###
B Well steining
(I) PCC M15 Grade cum 4506.00 ###
(ii) PCC M20 Grade cum 5115.00 ###
(iii) RCC M20 Grade
Case I Using concrete mixer cum 5146.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5020.00 ###
(iv) PCC M25 Grade
Case I Using concrete mixer cum 5616.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5493.00 ###
(v) RCC M25 Grade
Case I Using concrete mixer cum 5652.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5528.00 ###
(vi) PCC M30 Grade
Case I Using concrete mixer cum 5670.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5543.00 ###

58
(vii) RCC M30 Grade
Case I Using concrete mixer cum 5682.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5560.00 ###
(viii) RCC M35 Grade
Case I Using concrete mixer cum 5822.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5988.00 ###
(ix) RCC M40 Grade 6064.00 ###
C Bottom Plug
(i) PCC Grade M20
Case I Using Concrete Mixer cum 5582.00 ###
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5166.00 ###
(ii) PCC Grade M25
Case I Using Concrete Mixer cum 5868.00 ###
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5449.00 ###
(iii) PCC Grade M30
Case I Using Concrete Mixer cum 5920.00 ###
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5503.00 ###
(iv) PCC Grade M35
Case I Using Concrete Mixer cum 6041.00 ###
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5621.00 ###
D Intermediate plug
(I) Grade M20 PCC
Case I Using Concrete Mixer cum 5346.00 ###
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 4946.00 ###
(ii) Grade M25 PCC
Case I Using Concrete Mixer cum 5618.00 ###
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5215.00 ###
(iii) Grade M30 PCC
Case I Using Concrete Mixer cum 5668.00 ###
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5268.00 ###
E Top plug
(i) Grade M15 PCC
Case I Using Concrete Mixer cum 4096.00 ###
(ii) Grade M20 PCC
Case I Using Concrete Mixer cum 4650.00 ###
(iii) Grade M25 PCC
Case I Using Concrete Mixer cum 5105.00 ###
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 4994.00 ###
(iv) Grade M30 PCC
Case I Using Concrete Mixer cum 5155.00 ###
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 5039.00 ###
F Well cap
(i) RCC Grade M20
Case I Using concrete Mixer cum 4813.00 ###
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 4695.00 ###
(ii) RCC Grade M25
Case I Using concrete Mixer cum 5330.00 ###
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5215.00 ###
(iii) RCC Grade M30
Case I Using Concrete Mixer cum 5346.00 ###
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5231.00 ###
(iv) RCC Grade M35

59
Case I Using Concrete Mixer cum 5450.00 ###
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 5336.00 ###
(v) RCC M40 Grade cum 5720.00 ###
12.12
Sinking of 6 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

A Sandy soil
(i) Depth below bed level upto 3.0 M metre 4414.00 ###
(ii) Beyond 3m upto 10m depth metre 6407.00 ###
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 8461.00 ###
meter
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 15869.00 ###
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . 19043.00 ###
(v) Beyond 30m upto 40 m metre
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
37704.00 ###
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 45245.00 ###
B Clayey soil ( 6m dia. Well )
(i) Depth below bed level upto 3.0 M metre 6417.00 ###
(ii) Beyond 3m upto 10m depth metre 14386.00 ###
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 18999.00 ###
meter
b Add for dewatering @ 5% of cost, if required. metre 19949.00 ###
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 35636.00 ###
meter
b Add 5% of cost for dewatering of the cost, if required metre 46772.00 ###
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 44545.00 ###
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 84665.00 ###
meter
b Add 5% of cost for dewatering, if required metre 106678.00 ###
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 101598.00 ###
C Soft rock (6m dia well )
(i) Depth of soft rock strata upto 3m metre 17185.00 ###
D Hard rock (6m dia well )
(i) Depth of soft rock strata upto 3m metre 19445.00 ###
12.13
Sinking of 7 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

A Sandy soil
(i) Depth below bed level upto 3.0 M metre 6852.00 ###
(ii) Beyond 3m upto 10m depth metre 9290.00 ###
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 12270.00 ###
meter
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 23016.00 ###
meter

60
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour) . metre 27619.00 ###
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 54684.00 ###
meter
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 65620.00 ###
B Clayey soil ( 7m dia. Well )
(I) Depth below bed level upto 3.0 M metre 9290.00 ###
(ii) Beyond 3m upto 10m depth metre 14913.00 ###
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 19695.00 ###
meter
b Add for dewatering @ 5% of cost, if required. metre 20680.00 ###
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
metre 36944.00 ###
b Add 5% of cost for dewatering on the cost, if required metre 48489.00 ###
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 46180.00 ###
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 87773.00 ###
meter
b Add 5% of cost for dewatering, if required metre 110594.00 ###
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). 105328.00 ###
C Soft rock ( 7m dia well )
(i) Depth of soft rock strata upto 3m metre 15823.00 ###
D Hard rock ( 7m dia well )
(i) Depth upto 3 m metre 22029.00 ###
12.14
Sinking of 8 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

A Sandy soil
(i) Depth below bed level upto 3.0 M metre 8400.00 ###
(ii) Beyond 3m upto 10m depth metre 10404.00 ###
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 13740.00 ###
meter
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 25773.00 ###
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 30928.00 ###
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 61234.00 ###
meter
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 73481.00 ###
B Clayey soil ( 8m dia. Well )
(i) Depth upto 3.0 M metre 11360.00 ###
(ii) Beyond 3m upto 10m depth metre 15405.00 ###
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 20345.00 ###
meter
b Add for dewatering @ 5% of cost, if required. metre 21362.00 ###
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 38161.00 ###
meter
b Add 5% of cost for dewatering on the cost, if required metre 50087.00 ###

61
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 47702.00 ###
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 90666.00 ###
meter
b Add 5% of cost for dewatering, if required metre 114239.00 ###
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 108799.00 ###
C Soft rock ( 8m dia well )
(i) Depth in soft rock strata upto 3m metre 17463.00 ###
D Hard rock ( 8m dia well )
(i) Depth in hard rock strata upto 3 m metre 21996.00 ###
12.15
Sinking of 9 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

A Sandy soil
(i) Depth below bed level upto 3.0 M metre 8468.00 ###
(ii) Beyond 3m upto 10m depth metre 11430.00 ###
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 15095.00 ###
meter
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 28315.00 ###
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 33978.00 ###
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 67272.00 ###
meter
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 80726.00 ###
B Clayey soil ( 9m dia. Well )
(i) Depth below bed level upto 3.0 M metre 11951.00 ###
(ii) Beyond 3m upto 10m depth metre 16624.00 ###
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 21955.00 ###
meter
b Add for dewatering @ 5% of cost, if required. metre 23052.00 ###
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 41181.00 ###
meter
b Add 5% of cost for dewatering on the cost, if required metre 54050.00 ###
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 51476.00 ###
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 97840.00 ###
meter
b Add 5% of cost for dewatering, if required metre 123278.00 ###
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 117408.00 ###
C Soft rock ( 9m dia well )
(i) Depth upto 3m metre 22109.00 ###
D Hard rock ( 9m dia well )
(i) Depth of hard rock strata upto 3 m metre 25495.00 ###
12.16
Sinking of 10 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

A Sandy soil
(i) Depth below bed level upto 3.0 M metre 10315.00 ###

62
(ii) Beyond 3m upto 10m depth metre 12026.00 ###
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 15882.00 ###
meter
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 29789.00 ###
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 35747.00 ###
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 70775.00 ###
meter
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 84930.00 ###
B Clayey soil (10m dia. Well )
(i) Depth below bed level upto 3.0 M metre 12932.00 ###
(ii) Beyond 3m upto 10m depth metre 16226.00 ###
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 21429.00 ###
meter
b Add for dewatering @ 5% of cost, if required. metre 22500.00 ###
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 40195.00 ###
meter
'b Add 5% of cost for dewatering on the cost, if required metre 52757.00 ###
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 50244.00 ###
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
meter
metre 95496.00 ###
b Add 5% of cost for dewatering, if required metre 120325.00 ###
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). 114596.00 ###
C Soft rock (10m dia well )
(i) Depth of soft rock strata upto 3m metre 22581.00 ###
D Hard rock (10m dia well )
(i) Depth of hard rock strata upto 3 m metre 30167.00 ###
12.17
Sinking of 11 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

A Sandy soil
(i) Depth from bed level upto 3.0 M metre 24089.00 ###
(ii) Beyond 3m upto 10m depth metre 17962.00 ###
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 23722.00 ###
meter
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
metre 44497.00 ###
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 53397.00 ###
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 105719.00 ###
meter
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 126862.00 ###
B Clayey soil (11 m dia. Well )
(i) Depth from bed level upto 3.0 M metre 21526.00 ###
(ii) Beyond 3m upto 10m depth metre 33288.00 ###
(iii) Beyond 10 m upto 20 m

63
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 43963.00 ###
meter
b Add for dewatering @ 5% of cost, if required. metre 46161.00 ###
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 82463.00 ###
meter
b Add 5% of cost for dewatering on the cost, if required metre 108232.00 ###
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 103078.00 ###
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 195920.00 ###
meter
b Add 5% of cost for dewatering, if required metre 246859.00 ###
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 235104.00 ###
C Soft rock (11m dia well )
(i) Depth of soft rock strata upto 3m metre 50611.00 ###
D Hard rock (11m dia well )
(i) Depth of hard rock upto 3 m metre 68215.00 ###
12.18
Sinking of 12 m external diameter well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case, complete
as per drawing and technical specifications. Depth of sinking is reckoned from bed level.

A Sandy soil
(i) I) Depth below bed level upto 3.0 M metre 49223.00 ###
(ii) Beyond 3m upto 10m depth metre 54629.00 ###
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 72146.00 ###
meter
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 135327.00 ###
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 162392.00 ###
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 321518.00 ###
meter
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 385821.00 ###
B Clayey soil (12 m dia. Well )
(i) Depth below bed level upto 3.0 M metre 53114.00 ###
(ii) Beyond 3m upto 10m depth metre 84547.00 ###
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
metre 111659.00 ###
b Add for dewatering @ 5% of cost, if required. metre 117242.00 ###
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 209444.00 ###
meter
b Add 5% of cost for dewatering on the cost, if required metre 274895.00 ###
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 261805.00 ###
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 497608.00 ###
meter
b Add 5% of cost for dewatering, if required metre 626986.00 ###
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 597129.00 ###
C Soft rock (12m dia well )
(i) Depth of soft rock strata upto 3m metre 119792.00 ###
D Hard rock (12m dia well )
(i) Depth of hard rock strata upto 3 m metre 158149.00###

64
12.19
Sinking of Twin D Type well ( other than pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown against each case, complete as per
drawing and technical specifications. Depth of sinking is reckoned from bed level.

A Sandy soil
(i) Depth from bed level upto 3.0 M metre 11195.00 ###
(ii) Beyond 3m upto 10m depth metre 12039.00 ###
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 15900.00 ###
meter
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 29825.00 ###
meter
b Add 20% of cost for Kentledge including supports, loading arrangement and Labour . metre 35790.00 ###
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 70860.00 ###
meter
b Add 20% of cost for Kentledge including supports, loading arrangement, and Labour etc. metre 85033.00 ###
B Clayey soil (Twin D Type Well )
(i) Depth below bed level upto 3.0 M metre 12987.00 ###
(ii) Beyond 3m upto 10m depth metre 18025.00 ###
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking for the previous
meter
metre 23806.00 ###
b Add for dewatering @ 5% of cost, if required. metre 24996.00 ###
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking for the previous
metre 44654.00 ###
meter
b Add 5% of cost for dewatering on the cost, if required metre 58608.00 ###
c Add 25% of cost for Kentledge including supports, loading arrangement and Labour ). metre 55817.00 ###
(v) Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking for the previous
metre 106091.00 ###
meter
b Add 5% of cost for dewatering, if required metre 133675.00 ###
c Add 20% of cost for Kentledge including supports, loading arrangement and Labour). metre 127309.00 ###
C Soft rock (Twin D Type well )
(i) Depth of soft rock strata upto 3m metre 26409.00 ###
D Hard rock (Twin D Type well )
(i) Depth of hard rock strata upto 3 m metre 32727.00 ###
12.20
Pneumatic sinking of wells with equipment of approved design, drawing and specifications
worked by competent and trained personnel and comprising of compression and decompression
chambers, reducers, two air locks separately for men and plant & materials, arrangement for
supply of fresh air to working chambers, check valves, exhaust valves, shafts made from steel
plates of riveted construction not less than 6 mm thick to withstand an air pressure of 0.50 MPa, #VALUE!
controlled blasting of hard rock where required, staircases and 1 m wide landing plate forms
with railing, arrangement for compression and decompression, electric lighting of 50 V
maximum, proper rooms for rest and medical examinations and compliance with safety
precautions as per IS:4138, all as per clause1207.6 of MoRTH Specifications.

12.21 Sand filling in wells complete as per drawing and technical specifications cum 264.00 ###
12.22 Providing steel liner 10 mm thick for curbs and 6mm thick for steining of wells including
tonne 81108.00 ###
fabricating and setting out as per detailed drawing
12.23 Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and
technical specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile metre 5447.00 ###
diameter-750 mm)
12.24 Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and
technical specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile metre 8918.00 ###
diameter-1000 mm)

65
12.25 Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per drawing and
technical specifications and removal of excavated earth with all lifts and lead upto 1000 m. (Pile metre 11415.00 ###
diameter-1200 mm)
12.26 Driven cast-in-place vertical M35 grade R.C.C. pile excluding reinforcement complete as per
metre 4106.00 ###
drawing and & Technical Specification (Pile diameter - 750 mm)
12.27 Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per
metre 6599.00 ###
drawing and & Technical Specification (Pile diameter - 1000 mm)
12.28 Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement complete as per
drawing and & Technical Specification (Pile diameter - 1200 mm)
metre 9623.00 ###

12.29 Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
metre #VALUE! ###
and & Technical Specification (Pile Diameter=500 mm)
12.30 Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
metre #VALUE! ###
and & Technical Specification (Pile Diameter=750 mm)
12.31 Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
metre #VALUE! ###
and & Technical Specification (Pile Diameter=1000 mm)
12.32 Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
metre #VALUE! ###
and & Technical Specification (Size of pile - 300 mm x 300 mm)
12.33 Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
metre #VALUE! ###
and & Technical Specification (Size of pile - 500 mm x 500 mm)
12.34 Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as per drawing
and & Technical Specification (Size of pile - 750 mm x 750 mm)
metre #VALUE! ###

12.35 Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the
pile - H Section steel column 400 x 250 mm (ISHB Series) )
metre #VALUE! ###

12.36 Driven vertical steel piles complete as per drawing and & Technical Specification (Section of the
pile - H Section steel column 450 x 250 mm (ISHB Series) )
metre #VALUE! ###

12.37
Pile load test on single vertical pile in accordance with IS:2911(Part-IV) tonne 5300.00

12.38 Cement concrete for reinforced concrete in pile cap complete as per drawing and Technical
Specification
A RCC Grade M20
(i) Using Concrete Mixer cum 4828.00 ###
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 4730.00 ###
B RCC Grade M25
(i) Using concrete mixer. cum 5324.00 ###
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 5268.00 ###
C RCC Grade M30
(i) Using concrete mixer. cum 5386.00 ###
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 5289.00 ###
D RCC Grade M35
(i) Using concrete mixer. cum 5518.00 ###
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 5462.00 ###
12.39 Levelling course for Pile cap cum 4080.00 ###
12.40 Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation complete as per
tonne 66645.00 ###
drawing and technical specifications
12.41 Supplying, fitting and placing un-coated Mild steel reinforcement complete in foundation as per
tonne 74219.00 ###
drawing and technical specification

66
CHAPTER-13
SUB-STRUCTURE
Item No.
Descriptions Unit Rate (in Rs.)

13.1 Brick masonry work in 1:3 in sub-structure complete excluding pointing and plastering, as per
cum 5122.00 ###
drawing and technical specifications
13.2
Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical specifications 10 sqm 452.00 ###
13.3 Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical
specifications
10 sqm 992.00 ###
13.4 Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and
Technical Specifications
A Random Rubble Masonry cum 3004.00 ###
B Coursed rubble masonry (first sort ) cum 3101.00 ###
C Ashlar masonry ( first sort ) cum 3906.00 ###
13.5 Plain/Reinforced cement concrete in sub-structure complete as per drawing and technical
specifications
A PCC Grade M15
(p) Height upto 5m cum 4506.00 ###
B PCC Grade M20
(p) Height upto 5m cum 5115.00 ###
C PCC Grade M25
(p) Height upto 5m
Case I Using concrete Mixer cum 5616.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5493.00 ###
(q) Height 5m to 10m
Case I Using concrete Mixer cum 5820.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5693.00 ###
(r) Height above 10m
Case I Using concrete Mixer cum 6075.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5943.00 ###
D PCC Grade M30
(p) Height upto 5m
Case I Using concrete Mixer cum 5670.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5543.00 ###
(q) Height 5m to 10m
Case I Using concrete Mixer cum 5877.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5745.00 ###
(r) Height above 10m
Case I Using concrete Mixer cum 6134.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5997.00 ###
E RCC Grade M20
(p) Height upto 5m
Case I Using concrete Mixer cum 5146.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5020.00 ###
(q) Height 5m to 10m
Case I Using concrete Mixer cum 5333.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5203.00 ###
(r) Height above 10m
Case I Using concrete Mixer cum 5567.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5431.00 ###
F RCC Grade M25
(p) Height upto 5m
Case I Using concrete Mixer cum 5652.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5528.00 ###
(q) Height 5m to 10m
Case I Using concrete Mixer cum 5837.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5709.00 ###
(r) Height above 10m

67
Case I Using concrete Mixer cum 6115.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5980.00 ###
G RCC Grade M30
(p) Height upto 5m
Case I Using concrete Mixer cum 5682.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5560.00 ###
(q) Height 5m to 10m
Case I Using concrete Mixer cum 5843.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5717.00 ###
(r) Height above 10m
Case I Using concrete Mixer cum 6070.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5939.00 ###
H RCC Grade M35
(p) Height upto 5m
Case I Using concrete Mixer cum 5822.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 5988.00 ###
(q) Height 5m to 10m
Case I Using concrete Mixer cum 5949.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6119.00 ###
(r) Height above 10m
Case I Using concrete Mixer cum 6139.00 ###
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 6315.00 ###
13.6 Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing
and technical specifications
tonne 66758.00 ###

13.7 Supplying, fitting and placing Mild steel reinforcement complete in sub-structure as per
drawing and technical specification
tonne 73666.00 ###

13.8
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return
wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V each 124.00 ###
:20H towards drawing foce. Complete as per drawing and Technical specifications

13.9 Back filling behind abutment, wing wall and return wall complete as per drawing and Technical
specification
A Granular material cum 497.00 ###
B Sandy material cum 422.00 ###
13.10
Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying
the requirements laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not
less than 600 mm with smaller size towards the soil and bigger size towards the wall and cum 1260.00 ###
provided over the entire surface behind abutment, wing wall and return wall to the full height
compacted to a firm condition complete as per drawing and technical specification.

13.11
Supplying, fitting and fixing in position true to line and level cast steel rocker bearing
tonne
conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete
capacity
312.00 ###
including all accessories as per drawing and Technical Specifications.

13.12
Supplying, fitting and fixing in position true to line and level forged steel roller bearing
tonne
conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH specifications complete
capacity
209.00 ###
including all accessories as per drawing and Technical Specifications.

13.13 Supplying, fitting and fixing in position true to line and level sliding plate bearing with PTFE
surface sliding on stainless steel complete including all accessories as per drawing and Technical tonne
#VALUE! ###
Specifications and BS: 5400, section 9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH capacity
Specifications.
13.14
Supplying, fitting and fixing in position true to line and level elastomeric bearing conforming to
cubic
IRC: 83 (Part-II) section IX and clause 2005 of MoRTH specifications complete including all
centimetre
0.72 ###
accessories as per drawing and Technical Specifications.

13.15 Supplying, fitting and fixing in position true to line and level sliding plate bearing with stainless
tonne
steel plate sliding on stainless steel plate with mild steel matrix complete including all
capacity
396.00 ###
accessories as per drawing and Technical Specifications.

68
13.16
Supplying, fitting and fixing in position true to line and level POT-PTFE bearing consisting of a
metal piston supported by a disc or unreinforced elastomer confined within a metal cylinder,
sealing rings, dust seals, PTFE surface sliding against stainless steel mating surface,
tonne
completre assembly to be of cast steel/fabricated structural steel, metal and elastomer
capacity
179.00 ###
elements to be as per IRC: 83 part-I & II respectively and other parts conforming to BS: 5400,
section 9.1 & 9.2 and clause 2006 of MoRTH Specifications complete asper drawing and
approved technical specifications.

69
CHAPTER-14
SUPER-STRUCTURE
Item No.
Descriptions Unit Rate (in Rs.)

14.1 Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per


drawing and Technical Specification
A RCC Grade M20
Case I Using Concrete Mixer
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 5553.00 ###
(q) Height 5m to 10m cum 5785.00 ###
(r) Height above 10m cum 6016.00 ###
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 5785.00 ###
(q) Height 5m to 10m cum 6016.00 ###
(r) Height above 10m cum 6247.00 ###
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 5417.00 ###
(q) Height 5m to 10m cum 5643.00 ###
(r) Height above 10m cum 5869.00 ###
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 5643.00 ###
(q) Height 5m to 10m cum 5869.00 ###
(r) Height above 10m cum 6094.00 ###
B RCC Grade M25
Case I Using Concrete Mixer
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 6126.00 ###
(q) Height 5m to 10m cum 6381.00 ###
(r) Height above 10m cum 6636.00 ###
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 6381.00 ###
(q) Height 5m to 10m cum 6636.00 ###
(r) Height above 10m cum 6891.00 ###
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 5996.00 ###
(q) Height 5m to 10m cum 6246.00 ###
(r) Height above 10m cum 6496.00 ###
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 6246.00 ###
(q) Height 5m to 10m cum 6496.00 ###
(r) Height above 10m cum 6745.00 ###
C RCC Grade M 30
Case I Using Concrete Mixer
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 6220.00 ###
(q) Height 5m to 10m cum 6479.00 ###
(r) Height above 10m cum 6738.00 ###
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 6479.00 ###
(q) Height 5m to 10m cum 6738.00 ###
(r) Height above 10m cum 6997.00 ###
Case II Using Batching Plant, Transit Mixer and Concrete Pump.

70
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 6069.00 ###
(q) Height 5m to 10m cum 6322.00 ###
(r) Height above 10m cum 6575.00 ###
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 6322.00 ###
(q) Height 5m to 10m cum 6575.00 ###
(r) Height above 10m cum 6827.00 ###
D RCC/PSC Grade M35
Case 1 Using concrete mixer.
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 6265.00 ###
(q) Height 5m to 10m cum 6530.00 ###
(r) Height above 10m cum 6796.00 ###
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 6530.00 ###
(q) Height 5m to 10m cum 6796.00 ###
(r) Height above 10m cum 7061.00 ###
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 7327.00 ###
(q) Height 5m to 10m cum 7857.00 ###
(r) Height above 10m cum 8388.00 ###
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 6116.00 ###
(q) Height 5m to 10m cum 6375.00 ###
(r) Height above 10m cum 6634.00 ###
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 6375.00 ###
(q) Height 5m to 10m cum 6634.00 ###
(r) Height above 10m cum 6893.00 ###
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 7152.00 ###
(q) Height 5m to 10m cum 7671.00 ###
(r) Height above 10m cum 8189.00 ###
E PSC Grade M-40
Case 1 Using concrete mixer.
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 6805.00 ###
(q) Height 5m to 10m cum 7089.00 ###
(r) Height above 10m cum 7373.00 ###
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 7089.00 ###
(q) Height 5m to 10m cum 7373.00 ###
(r) Height above 10m cum 7656.00 ###
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 6512.00 ###
(q) Height 5m to 10m cum 6788.00 ###
(r) Height above 10m cum 7064.00 ###
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 6788.00 ###
(q) Height 5m to 10m cum 7064.00 ###
(r) Height above 10m cum 7340.00 ###
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 7616.00 ###
(q) Height 5m to 10m cum 8168.00 ###
(r) Height above 10m cum 8720.00 ###

71
F PSC Grade M-45
(i) For solid slab/voided slab super-structure, 16-26% of cost of concrete (a+b+c)
(p) Height upto 5m cum 6761.00 ###
(q) Height 5m to 10m cum 7053.00 ###
(r) Height above 10m cum 7344.00 ###
(ii) For I-beam & slab including launching of precast girders by launching truss upto 40 m span,
21-31% of cost of concrete.
(p) Height upto 5m cum 7053.00 ###
(q) Height 5m to 10m cum 7344.00 ###
(r) Height above 10m cum 7635.00 ###
(iii) For cast-in-situ box girder, segmental construction and balanced cantilever, 36-56% of cost of
concrete.
(p) Height upto 5m cum 7927.00 ###
(q) Height 5m to 10m cum 8510.00 ###
(r) Height above 10m cum 9093.00 ###
G PSC Grade M-50
(i) For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost of
concrete
(p) Height upto 5m cum 8167.00 ###
(q) Height 5m to 10m cum 8772.00 ###
(r) Height above 10m cum 9377.00 ###
H PSC Grade M- 55
(i) For cast-in-situ box girder, segmental construction and balanced cantilever, 35-55% of cost of
concrete
(p) Height upto 5m cum 8635.00 ###
(q) Height 5m to 10m cum 9275.00 ###
(r) Height above 10m cum 9914.00 ###
14.2 a) Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per
drawing and technical specifications
tonne 67683.00 ###
14.3 High tensile steel wires/strands including all accessories for stressing, stressing operations and
grouting complete as per drawing and Technical Specifications
tonne 111392.00 ###
14.4 Providing and laying Cement concrete wearing coat M-30 grade including reinforcement
cum 10172.00 ###
complete as per drawing and Technical Specifications
14.5 Mastic Asphalt (Providing and laying 12 mm thick mastic asphalt wearing course on top of deck
slab excluding prime coat with paving grade bitumen meeting the requirements given in table
500-29, prepared by using mastic cooker and laid to required level and slope after cleaning the
surface, including providing antiskid surface with bitumen precoated fine grained hard stone
sqm #VALUE! ###
chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and at an approximate
spacing of 10 cm center to center in both directions, pressed into surface when the
temperature of surfaces not less than 100 deg. C, protruding 1 mm to 4 mm over mastic
surface, all complete as per clause 515.)
14.6
Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm, true
to line and grade, tolurence of vertical RCC post not to exceed 1 in 500, centre to centre
metre 1756.00 ###
spacing between vertical post not to exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved drawings and technical specifications.

14.7
Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to
line and grade, tolurence of vertical RCC post not to exceed 1 in 500, centre to centre spacing
metre 1703.00 ###
between vertical post not to exceed 2000 mm, leaving adequate space between vertical post
for expansion, complete as per approved drawings and technical specifications.

14.8 Providing, fitting and fixing mild steel railing complete as per drawing and Technical
metre 3229.00 ###
Specification
14.9 Drainage Spouts complete as per drawing and Technical specification each 920.00 ###
14.10 PCC M15 Grade leveling course below approach slab complete as per drawing and Technical
cum 4096.00 ###
specification
14.11 Reinforced cement concrete approach slab including reinforcement and formwork complete as
cum 8540.00 ###
per drawing and Technical specification
14.12 Providing anti-corrosive treatment to HYSD reinforcement with Fusion Bonded Epoxy Coating
tonne VALUE
(FBEC) (To be taken as per the prevailing market rates.)
14.13 Precast - pretensioned Girders (Providing, precasting, transportation and placing in position
cum #VALUE! ###
precast pretensioned concrete girders as per drawing and technical specifications)
14.14 Providing and fixing Helical pipes in voided concrete slabs metre #VALUE! ###

72
14.15 Crash Barriers (The rate analysis for rigid crash barrier in reinforced cement concrete, semi-
rigid crash barrier with metal beam and flexible crash barrier with wire ropes have been made metre VALUE
and included in chapter-8 on Traffic and Transportation.)
14.16 Painting on concrete surface (Providing and applying 2 coats of water based cement paint to
unplastered concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence metre 68.00 ###
and applying paint @ of 1 litre for 2 Sq.m. )
14.17 Burried Joint (Providing and laying a burried expansion joint, expansion gap being 20 mm,
covered with 12 mm thick, 200 mm wide galvanised wieldable structural steel plate as per IS:
2062, placed symmetrical to centre line of the joint, resting freely over the top surface of the metre 1285.00 ###
deck concrete, welding of 8 mm dia. 100 mm long galvanised nails spaced 300 mm c/c along
the centre line of the plate, all as specified in clause 2604.)
14.18 Filler joint
(i) Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete as per
metre 3058.00 ###
drawing & Technical Specification.
(ii) Providing & fixing 20 mm thick compressible fibre board in expansion joint complete as per
drawing & Technical Specification.
metre 212.00 ###
(iii)
Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed
ends of simply supported spans not exceeding 10 m to cater for a horizontal movement upto 20 metre 299.00 ###
mm, covered with sealant complete as per drawing and technical specifications.

(iv) Providing and filling joint sealing compound as per drawings and technical specifications with
coarse sand and 6% bitumen by weight
metre 18.50 ###
14.19 Asphaltic Plug joint (Providing and laying of asphaltic plug joint to provide for horizontal
movement of 25 mm and vertical movement of 2 mm, depth of joint varying from 75 mm to
100 mm, width varying from 500 mm to 750 mm (in traffic direction), covered with a closure
plate of 200mm x 6mm of wieldable structural steel conforming to IS: 2062, asphaltic plug to metre 1026.00 ###
consist of polymer modified bitumen binder, carefully selected single size aggregate of 12.5
mm nominal size and a heat resistant foam caulking/backer rod, all as per approved drawings
and specifications.)
14.20 Elastomeric Slab Steel Expansion Joint (Providing and laying of an elastomeric slab steel
expansion joint, catering to right or skew (less than 20 deg., moderately curved with
maximum horizontal movement upto 50 mm, complete as per approved drawings and standard
metre 28077.00 ###
specifications to be installed by the manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for installation and clause 2606 of
MoRTH specifications for road & bridge works.)
14.21 Compression Seal Joint (Providing and laying of compression seal joint consisting of steel
armoured nosing at two edges of the joint gap suitably anchored to the deck concrete and a
preformed chloroprene elastomer or closed cell foam joint sealer compressed and fixed into the metre #VALUE! ###
joint gap with special adhesive binder to cater for a horizontal movement upto 40 mm and
vertical movement of 3 mm.)
14.22 Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint catering to
maximum horizontal movement upto 70 mm, complete as per approved drawings and standard
metre 8756.00 ###
specifications to be installed by the manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for installation.)
14.23 Modular Strip / Box Seal Joint (Providing and laying of a modular strip Box steel expansion joint
including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm,
complete as per approved drawings and standard specifications to be installed by the metre 29464.00 ###
manufacturer/supplier or their authorised representative ensuring compliance to the
manufacturer's instructions for installation.)
14.24 Modular Strip / Box Seal Joint (Providing and laying of a modular strip box seal expansion joint
catering to a horizontal movement beyond 140mm and upto 210mm, complete as per approved
drawings and standard specifications to be installed by the manufacturer/supplier or their metre #VALUE! ###
authorised representative ensuring compliance to the manufacturer's instructions for
installation.)

73
CHAPTER-15
RIVER TRAINING AND PROTECTION WORKS
Item No.
Descriptions Unit Rate (in Rs.)

15.1 Providing and laying boulders apron on river bed for protection against scour with stone
boulders weighing not less than 40 kg each complete as per drawing and Technical
specification.
A Boulder laid dry without wire crates. cum 897.00 ###
15.2 Boulder apron laid in wire crates (Providing and laying of boulder apron laid in wire crates
made with 4mm dia GI wire conforming to IS: 280 & IS:4826 in 100mm x 100mm mesh
cum 1193.00 ###
(weaved diagonally) including 10% extra for laps and joints laid with stone boulders weighing
not less than 40 kg each.)
15.3
Cement concrete blocks (size 0.5 x 0.5 x 0.5 m) (Providing and laying of apron with cement
concrete blocks of size 0.5x0.5x0.5 m cast in-situ and made with nominal mix of M-15 grade cum 4344.00 ###
cement concrete with a minimum cement content of 250 kg/cum as per IRC: 21-2000.)

15.4
Providing and laying Pitching on slopes laid over prepared filter media including boulder apron
laid dry in front of toe of embankment complete as per drawing and Technical specifications

A Stone/Boulder cum 897.00 ###


B
Cement Concrete blocks of size 0.3x0.3 x0.3 m cast in cement concrete of Grade M15 cum 4344.00 ###
15.5 Providing and laying Filter material underneath pitching in slopes complete as per drawing and
Technical specification
cum 1386.00 ###

15.6 Geotextile Filter (Laying of a geotextile filter between pitching and embankment slopes on which
pitching is laid to prevent escape of the embankment material through the voids of the stone
pitching/cement concrete blocks as well as to allow free movement of water without creating
sqm 141.00 ###
any uplift head on the pitching.)
15.7
Toe protection (A toe wall for toe protection can either be in dry rubble masonry in case of dry
rubble pitching or pitching with stones in wire crates or it can be in PCC M15 nominal mix if
cement concrete block have been used for pitching . Rates for toe wall can be adopted from
respective clauses depending upon approved design. The rate for excavation for foundation,
dry rubble masonry and PCC M15 have been analysed and given in respective chapters.)

15.8 Providing and laying Flooring complete as per drawing and Technical specifications laid over
cement concrete bedding.
A Rubble stone laid in cement mortar 1:3 cum 3721.00 ###
B Cement Concrete blocks Grade M15 cum 5721.00 ###
15.9 Dry rubble Flooring cum 1163.00 ###
15.10 Curtain wall complete as per drawing and Technical specification
A Stone masonry in cement mortar (1:3) cum 3034.00 ###
B Cement concrete Grade M15 cum 4259.00 ###
15.11 Flexible Apron :Construction of flexible apron 1 m thick comprising of loose stone boulders
weighing not less than 40 kg beyond curtain wall.
cum 940.00 ###
15.12 Gabian Structure for Retaining Earth (Providing and construction of a gabain structure for
retaining earth with segments of wire crates of size 7 m x 3 m x 0.6 m each divided into 1.5 m
compartments by cross netting, made from 4 mm galvanised steel wire @ 32 kg per 10 sqm
having minimum tensile strength of 300 Mpa conforming to IS:280 and galvanizing coating cum 1217.00 ###
conforming to IS:4826, woven into mesh with double twist, mesh size not exceeding 100 x
100 mm, filled with boulders with least dimension of 200 mm, all loose ends to be tied with 4
mm galvanised steel wire)
15.13
Gabian Structure for Erosion Control, River Training Works and Protection works (Providing and
constructing gabain structures for erosion control, river training works and protection works
with wire crates of size 2 m x 1 m x 0.3 m each divided into 1m compartments by cross netting,
made from 4 mm galvanised steel wire @ 32 kg per 10 sqm having minimum tensile strength cum 1827.00 ###
of 300 Mpa conforming to IS:280 and galvanizing coating conforming to IS:4826, woven into
mesh with double twist, mesh size not exceeding 100 mm x 100 mm, filled with boulders with
least dimension of 200 mm, all loose ends to be securely tied with 4 mm galvanised steel wire.)

74
CHAPTER-16
REPAIR AND REHABILITATION
Item No.
Descriptions Unit Rate (in Rs.)

16.1
Removal of existing cement concrete wearing coat including its disposal complete as per
Technical specification without causing any detrimental effect to any part of the bridge structure sqm 83.00 ###
and removal of dismantled material with all lifts and lead upto 1000m (Thickness 75 mm)

16.2
Removal of existing asphaltic wearing coat comprising of 50 mm thick asphaltic concrete laid
over 12 mm thick mastic asphalt including disposal with all lift and lead upto 1000m.
sqm 62.00 ###

16.3 Guniting concrete surface with cement mortar applied with compressor after cleaning surface
sqm #VALUE! ###
and spraying with epoxy complete as per Technical specification
16.4
Providing and inserting nipples with approved fixing compound after drilling holes for grouting
as per Technical specifications including subsequent cutting/removal and sealing of the hole as each 79.00 ###
necessary of nipples after completion of grouting with Cement/Epoxy

16.5 Sealing of cracks/porous concrete by injection process through nipples/Grouting complete as


per Technical specification.
A Cement Grout kg 108.00 ###
B Cement mortar (1:1) Grouting kg 102.00 ###
16.6 Patching of damaged concrete surface with polymer concrete and curing compounds, initiator
and promoter, available in present formulations, to be applied as per instructions of sqm #VALUE! ###
manufacturer and as approved by the Engineer.
16.7 Sealing of crack / porous concrete with Epoxy Grout by injection through nipples complete as
kg #VALUE! ###
per clause 2803.1.
16.8 Applying epoxy mortar over leached, honey combed and spalled concrete surface and exposed
steel reinforcement complete as per Technical specification
sqm 404.00 ###
16.9
Removal of defective concrete, cleaning the surface thoroughly, applying the shotcrete mixture
mechanically with compressed air under pressure, comprising of cement, sand, coarse
aggregates, water and quick setting compound in the proportion as per clause 2807.1., sand
sqm #VALUE! ###
and coarse aggregates conforming to IS: 383 and table 1 of IS: 9012 respectively, water
cement ratio ranging from 0.35 to 0.50, density of gunite not less than 2000 kg/cum, strength
not less than 25 Mpa and workmanship conforming to clause 2807.6.

16.10 Applying pre-packed cement based polymer mortar of strength 45 Mpa at 28 days for
sqm #VALUE! ###
replacement of spalled concrete
16.11 Eproxy bonding of new concrete to old concrete sqm 598.00 ###
16.12 Providing external prestressing with high tensile steel wires/strands including drilling for passage
of prestessing steel, all accessories for stressing and stressing operation and grouting complete tonne 330461.00 ###
as per drawing and Technical specification
16.13 Providing external prestressing with high tensile steel wires/strands including drilling for passage
of prestessing steel, all accessories for stressing and stressing operation and grouting complete tonne 323552.00 ###
as per drawing and Technical specification
16.14 Providing external prestressing with high tensile steel wires/strands including drilling for passage
of prestessing steel, all accessories for stressing and stressing operation and grouting complete tonne 313982.00 ###
as per drawing and Technical specification
16.15 Replacement of bearings complete as per Technical specification each #VALUE! ###
16.16 Rectification of bearings as per Technical specifications each #VALUE! ###
16.17 Replacement of Expansion Joints complete as per drawings metre 2370.00 ###
16.18 Replacement of damaged concrete railing. metre 164.00 ###
16.19 Replacement of crash barrier. metre 304.00 ###
16.20 Replacement of damaged mild steel railing metre 136.00 ###
16.21 Repair of crash barrier (Repair of concrete crash barrier with cement concrete of M-30 grade by
cutting and trimming the damaged portion to a regular shape, cleaning the area to be repaired metre 217.00 ###
thoroughly, applying cement concrete after erection of proper form work.)
16.22
Repair of RCC Railing (Carrying out repair of RCC M30 railing to bring it to the original shape.) metre 160.00 ###
16.23 Repair of steel Railing (Repair of steel railing to bring it to the original shape) metre 301.00 ###

75
CHAPTER - 1
CARRIAGE OF MATERIALS
Ref. to Remarks
Sr
MoRTH Description Unit Quantity Rate Rs Cost Rs / Input
No Spec. ref.
1.1 Loading and Unloading of Stone Boulder/ Stone cum
aggregates/Sand/ Kanker/Moorum
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage and
return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point 1 Min
ii) Loading by front end loader 1 cum bucket capacity @ 25 13 Min
cum per hour
iii) Maneuvering, reversing, dumping and turning for return 2 Min

iv) Waiting time, unforeseen contingencies etc 4 Min


Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 846.00 279.18 P&M-048
Front end-loader 1 cum bucket capacity @ 25 cum/hour hour 0.330 1148.00 378.84 P&M-017
b) Overhead charges @ 0.1 on (a) 65.80
c) Contractor's profit @ 0.1 on (a+b) 72.38
Cost for 5.5 cum = a+b+c 796.20
Rate per cum = (a+b+c)/ 5.5 144.76
Note Unloading will be by tipping. say 145.00
1.2 Loading and Unloading of Boulders by Manual Means

Unit = cum
Taking output = 5.5 cum
a) Labour
Mate day 0.110 195.43 21.50 L-12
Mazdoor for loading and unloading day 0.750 187.43 140.57 L-13
b) Machinery
Tipper 5.5 tonne capacity hour 0.750 846.00 634.50 P&M-048
c) Overhead charges @ 0.1 on (a+b) 79.66
d) Contractor's profit @ 0.1 on (a+b+c) 87.62
Cost for5.5 cum = a+b+c+d 963.85
Rate per cum = (a+b+c+d)/5.5 175.25
Note Unloading will be by tipping. say 175.00
1.3 Loading and Unloading of Cement or Steel by Manual
Means and Stacking.
Unit = tonne
Taking output = 10 tonnes
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor for loading and unloading day 2.000 187.43 374.86 L-13
b) Machinery
Truck 10 tonne capacity hour 2.000 752.00 1504.00 P&M-057
c) Overhead charges @ 0.1 on (a+b) 189.45
d) Contractor's profit @ 0.1 on (a+b+c) 208.39
Cost for10 tonnes = a+b+c+d 2292.34
Rate per tonnes = (a+b+c+d)/10 229.23
say 229.00

67
Ref. to Remarks
Sr
MoRTH Description Unit Quantity Rate Rs Cost Rs / Input
No Spec. ref.
1.4 Cost of Haulage Excluding Loading and Unloading
Haulage of materials by tipper excluding cost of loading, unloading and
stacking.
Unit = t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km

(i) Surfaced Road


Speed with load : 25 km / hour.
Speed while Returning empty :35 km / hour.
a) Machinery.
Tipper 10 tonne capacity
Time taken for onward haulage with load hour 0.400 846.00 338.40 P&M-048
Time taken for empty return trip. hour 0.290 846.00 245.34 P&M-048
b) Overhead charges @ 0.1 on (a) 58.37
c) Contractor's profit @ 0.1 on (a+b) 64.21
cost for 100 t km = a+b+c 706.33
Rate per t.km = (a+b+c)/100 7.06
say 7.10
1.4 (ii) Unsurfaced Graveled Road
Speed with load: 20 km / hour
Speed for empty return trip :30 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load hour 0.500 846.00 423.00 P&M-048
Time taken for empty return trip hour 0.330 846.00 279.18 P&M-048
b) Overhead charges @ 0.1 on (a) 70.22
c) Contractor's profit @ 0.1 on (a+b) 77.24
Cost for 100 t .km = a+b+c 849.64
Rate per t.Km = (a+b+c)/100 8.50
say 8.50
1.4 (iii) Katcha Track and Track in River Bed/Nallah Bed and
Choked Bed
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 846.00 846.00 P&M-048
Time taken for empty return trip hour 0.670 846.00 566.82 P&M-048
b) Overhead charges @ 0.1 on (a) 141.28
c) Contractor's profit @ 0.1 on (a+b) 155.41
Cost for 100 t .km = a+b+c 1709.51
Rate per t.Km = (a+b+c)/100 17.10
say 17.10

68
Ref. to Remarks
Sr
MoRTH Description Unit Quantity Rate Rs Cost Rs / Input
No Spec. ref.
1.5 Hand Broken Stone Aggregates 63 mm Nominal Size

Supply of quarried stone, hand breaking into coarse aggregate


63 mm nominal size (passing 80 mm and retained on 50 mm
sieve) and stacking as directed
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.060 195.43 11.73 L-12
Mazdoor day 1.500 187.43 281.15 L-13
b) Material
Supply of quarried stone 150 - 200 mm size cum 1.100 550.80 605.89 M-002
c) Overhead charges @ 0.1 on (a+b) 89.88
d) Contractor's profit @ 0.1 on (a+b+c) 98.86
Rate per cum = a+b+c+d 1087.49
say 1087.00
1.6 Crushing of Stone Aggregates 13.2 mm Nominal Size

Crushing of stone boulders of 150 mm size in an integrated


stone crushing unit of 200 tonnes per hour capacity comprising
of primary and secondary crushing units, belt conveyor and
vibrating screens to obtain stone aggregates of 13.2 mm
nominal size.
Unit = cum
Taking Output = 600 cum at crusher location.
a) Labour
Mate day 0.760 195.43 148.53 L-12
Mazdoor Skilled day 2.000 218.57 437.14 L-15
Mazdoor including breaking of any oversize boulder. day 17.000 187.43 3186.31 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 525.85 420677.95 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt conveyor and Hour 6.000 16760.52 100563.12 P&M-028
vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 1148.00 22960.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 846.00 16920.00 P&M-048
d) Overhead charges @ 0.1 on (a+b+c) 56489.30
e) Contractor's profit @ 0.1 on (a+b+c+d) 62138.24
Cost for 600 cum = (a+b+c+d+e)x0.95 649344.56
Rate per cum = (a+b+c+d+e) * 0.95 / 600 1082.24
say 1082.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of stone chips
of size 13.2 mm.
2. 95 per cent of above cost will be attributed to the production of 600
cum of stone chips of 13.2 mm size and balance 5 per cent to the
production of stone dust which comes out as a by-product.

3. The integrated stone crusher includes primary and secondary


crushing units.
1.7 Crushing of Stone Aggregates 20 mm Nominal Size

Crushing of stone boulders of 150 mm size in an integrated


stone crushing unit of 200 tonnes per hour capacity comprising
of primary and secondary crushing units, belt conveyor and
vibrating screens to obtain stone aggregates of 20 mm nominal
size.
Unit = cum
Taking Output = 670 cum at crusher location.
a) Labour
Mate day 0.760 195.43 148.53 L-12

69
Ref. to Remarks
Sr
MoRTH Description Unit Quantity Rate Rs Cost Rs / Input
No Spec. ref.
Mazdoor Skilled day 2.000 218.57 437.14 L-15
Mazdoor including breaking of any size boulder. day 17.000 187.43 3186.31 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 525.85 420677.95 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt conveyor and Hour 6.000 16760.52 100563.12 P&M-028
vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 1148.00 22960.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 846.00 16920.00 P&M-048
d) Overhead charges @ 0.1 on (a+b+c) 56489.30
e) Contractor's profit @ 0.1 on (a+b+c+d) 62138.24
Cost for 670 cum = (a+b+c+d+e)x0.90 615168.53
Rate per cum = (a+b+c+d+e) * 0.90 / 670 918.16
say 918.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of stone chips
of size 20 and 40 mm.
2. 90 per cent of above cost will be attributed to the production of 670
cum of stone aggregates of 20mm size and balance 10 per cent will be
for smaller size aggregates and stone dust which comes out as a by-
product.
3. The integrated stone crusher includes primary and secondary
crushing units.
1.8 Crushing of Stone Aggregates 40 mm Nominal Size

Crushing of stone boulders of 150 mm size in an integrated


stone crushing unit of 200 tonnes per hour capacity comprising
of primary and secondary crushing units, belt conveyor and
vibrating screens to obtain stone aggregates of 40 mm nominal
size.
Unit = cum
Taking Output = 750 cum at crusher location.
a) Labour
Mate day 0.760 195.43 148.53 L-12
Mazdoor Skilled day 2.000 218.57 437.14 L-15
Mazdoor day 17.000 187.43 3186.31 L-13
b) Material
Stone Boulder of size 150 mm and below cum 800.000 525.85 420677.95 M-001
c) Machinery
Integrated stone crusher of 200 TPH including belt conveyor and Hour 6.000 16760.52 100563.12 P&M-028
vibrating screens
Front end loader 1 cum bucket capacity Hour 20.000 1148.00 22960.00 P&M-017
Tipper 5.5 cum capacity Hour 20.000 846.00 16920.00 P&M-048
d) Overhead charges @ 0.1 on (a+b+c) 56489.30
e) Contractor's profit @ 0.1 on (a+b+c+d) 62138.24
Cost for 750 cum = (a+b+c+d+e)x0.85 580992.50
Rate per cum = (a+b+c+d+e)x0.85/750 774.66
say 775.00
Note 1. 800 cum of stone boulders are needed to get 600 cum of stone chips
of size 13.2 mm.
2. 85 per cent of above cost will be attributed to the production of 750
cum of stone aggregates of 40mm size and balance 15 per cent will be
for smaller size aggregates and stone dust which comes out as a by-
product.
3. The integrated stone crusher includes primary and secondary
crushing units.

70
CHAPTER - 2
SITE CLEARANCE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.1 201 Cutting of Trees, including cutting of Trunks, Branches and
Removal
Cutting of trees, including cutting of trunks, branches and removal of
stumps, roots, stacking of serviceable material with all lifts and up to a
lead of 1000 metres and earth filling in the depression / pit.
Unit = Each
(i) Girth from 300 mm to 600 mm
a) Labour
Mate day 0.020 195.43 3.91 L-12
Mazdoors for cutting trees including cutting, refilling, compaction day 0.600 187.43 112.46 L-13
of backfilling and stacking of serviceable materials within 1000
metres lead by manual means.
b) Machinery
Tractor-trolley hour 0.100 171.02 17.10 P&M-053
c) Overhead charges @ 0.1 on (a+b) 13.35
d) Contractor's profit @ 0.1 on (a+b+c) 14.68
Rate for each tree = a+b+c+d 161.50
say 161.00
2.1 (ii) Girth from 600 mm to 900 mm
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoors for cutting trees including cutting, refilling, compaction day 0.900 187.43 168.69 L-13
of backfilling, and stacking of serviceable materials within 1000
metres lead by manual means
b) Machinery
Tractor-trolley hour 0.300 171.02 51.31 P&M-053
c) Overhead charges @ 0.1 on (a+b) 22.78
d) Contractor's profit @ 0.1 on (a+b+c) 25.06
Rate for each tree = a+b+c+d 275.65
say 276.00
2.1 (iii) Girth from 900 mm to 1800 mm
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoors for cutting trees including cutting, refilling, compaction day 2.000 187.43 374.86 L-13
of backfilling and stacking of serviceable materials within 1000
metres
b) Machinery
Tractor-trolley hour 0.400 171.02 68.41 P&M-053
c) Overhead charges @ 0.1 on (a+b) 45.89
d) Contractor's profit @ 0.1 on (a+b+c) 50.48
Rate for each tree = a+b+c+d 555.27
say 555.00
2.1 (iv) Girth above 1800 mm
a) Labour
Mate day 0.160 195.43 31.27 L-12
Mazdoors for cutting trees including cutting, refilling, compaction day 4.000 187.43 749.72 L-13
of backfilling and stacking of serviceable materials within 1000
metres
b) Machinery
Tractor-trolley hour 0.600 171.02 102.61 P&M-053
c) Overhead charges @ 0.1 on (a+b) 88.36
d) Contractor's profit @ 0.1 on (a+b+c) 97.20
Rate for each tree = a+b+c+d 1069.16
say 1069.00

71
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.2 201 Clearing Grass and Removal of Rubbish
Clearing grass and removal of rubbish up to a distance of 50 metres
outside the periphery of the area .
By Manual Means
Unit = Hectare
Taking output = 1 Hectare
a) Labour
Mate day 2.000 195.43 390.86 L-12
Mazdoor day 50.000 187.43 9371.50 L-13
b) Overhead charges @ 0.1 on (a) 976.24
c) Contractor's profit @ 0.1 on (a+b) 1073.86
Rate per Hectare = a+b+c 11812.46
say 11812.00
2.3 201 Clearing and Grubbing Road Land .
Clearing and grubbing road land including uprooting rank vegetation,
grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal
of stumps of trees cut earlier and disposal of unserviceable materials
and stacking of serviceable material to be used or auctioned, up to a
lead of 1000 metres including removal and disposal of top organic soil
not exceeding 150 mm in thickness.

Unit = Hectare
Taking output = 1 Hectare
(i) By Manual Means:-
A In area of light jungle
a) Labour
Mate day 6.000 195.43 1172.58 L-12
Mazdoor day 150.000 187.43 28114.50 L-13
b) Machinery
Tractor-trolley hour 1.000 171.02 171.02 P&M-053
c) Overhead charges @ 0.1 on (a+b) 2945.81
d) Contractor's profit @ 0.1 on (a+b+c) 3240.39
Rate per Hectare = a+b+c+d 35644.30
say 35644.00
2.3 (i) B In area of thorny jungle
a) Labour
Mate day 8.000 195.43 1563.44 L-12
Mazdoor day 200.000 187.43 37486.00 L-13
b) Machinery
Tractor-trolley hour 2.000 171.02 342.04 P&M-053
c) Overhead charges @ 0.1 on (a+b) 3939.15
d) Contractor's profit @ 0.1 on (a+b+c) 4333.06
Rate per Hectare = a+b+c+d 47663.69
say 47664.00
2.3 (ii) By Mechanical Means
A In area of light jungle
a) Labour
Mate day 0.160 195.43 31.27 L-12
Mazdoor day 4.000 187.43 749.72 L-13
b) Machinery
Dozer 80 HP with attachment for removal of trees & stumps hour 10.000 3135.24 31352.40 P&M-014
Tractor-trolley hour 1.000 171.02 171.02 P&M-053
c) Overhead charges @ 0.1 on (a+b) 3230.44
d) Contractor's profit @ 0.1 on (a+b+c) 3553.48
Rate per Hectare = a+b+c+d 39088.33
say 39088.00

72
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.3 (ii) B In area of thorny jungle
a) Labour
Mate day 0.240 195.43 46.90 L-12
Mazdoor day 6.000 187.43 1124.58 L-13
b) Machinery
Dozer 80 HP with attachment for removal of trees & stumps hour 12.000 3135.24 37622.88 P&M-014
Tractor-trolley hour 1.500 171.02 256.53 P&M-053
c) Overhead charges @ 0.1 on (a+b) 3905.09
d) Contractor's profit @ 0.1 on (a+b+c) 4295.60
Rate per Hectare = a+b+c+d 47251.58
say 47252.00
2.4 202 Dismantling of Structures
Dismantling of existing structures like culverts, bridges, retaining walls
and other structure comprising of masonry, cement concrete, wood
work, steel work, including T&P and scaffolding wherever necessary,
sorting the dismantled material, disposal of unserviceable material and
stacking the serviceable material with all lifts and lead of 1000 metres

Unit = cum
Taking output = 1.25 cum
(i) Lime /Cement Concrete
I By Manual Means
A Lime Concrete, cement concrete grade M-10 and below
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor for dismantling and loading day 1.000 187.43 187.43 L-13
b) Machinery
Tractor-trolley hour 0.270 171.02 46.17 P&M-053
c) Overhead charges @ 0.1 on (a+b) 24.14
d) Contractor's profit @ 0.1 on (a+b+c) 26.56
Cost for 1.25 cum = a+b+c+d 292.12
Rate per cum = (a+b+c+d)/ 1.25 233.70
say 234.00
2.4 (i) B Cement Concrete Grade M-15 & M-20
a) Labour
Mate day 0.050 195.43 9.77 L-12
Mazdoor for dismantling and loading day 1.250 187.43 234.29 L-13
b) Machinery
Tractor-trolley hour 0.270 171.02 46.17 P&M-053
c) Overhead charges @ 0.1 on (a+b) 29.02
d) Contractor's profit @ 0.1 on (a+b+c) 31.93
Cost for 1.25 cum = a+b+c+d 351.18
Rate per cum = (a+b+c+d)/ 1.25 280.95
say 281.00
2.4 (i) C Prestressed / Reinforced cement concrete grade M-20 & above

a) Labour
Mate day 0.150 195.43 29.31 L-12
Blacksmith day 0.250 247.19 61.80 L-02
Mazdoor for dismantling, loading and unloading day 3.500 187.43 656.01 L-13
b) Machinery
Tractor-trolley hour 0.270 171.02 46.17 P&M-053
c) Overhead charges @ 0.1 on (a+b) 79.33

73
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Contractor's profit @ 0.1 on (a+b+c) 87.26
Cost for 1.25 cum = a+b+c+d 959.88
Rate per cum = (a+b+c+d)/ 1.25 767.91
say 768.00
2.4 II By Mechanical Means for items No. 202( B)& ( C)
A Cement Concrete Grade M-15 & M-20
a) Labour
Mate day 0.020 195.43 3.91 L-12
Mazdoor for loading and unloading day 0.250 187.43 46.86 L-13
Mazdoor with Pneumatic breaker day 0.250 190.43 47.61 L-14
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic breaker @ hour 0.670 293.76 196.82 P&M-001
1.5 cum per hour
Tractor-trolley hour 0.270 171.02 46.17 P&M-053
c) Overhead charges @ 0.1 on (a+b) 34.14
d) Contractor's profit @ 0.1 on (a+b+c) 37.55
Cost for 1.25 cum = a+b+c+d 413.05
Rate per cum = (a+b+c+d)/ 1.25 330.44
say 330.00
2.4 II B Prestressed / reinforced cement concrete grade M-20 & above

a) Labour
Mate day 0.050 195.43 9.77 L-12
Mazdoor with Pneumatic breaker day 0.660 190.43 125.68 L-14
Blacksmith day 0.250 247.19 61.80 L-02
Mazdoor for loading and unloading day 0.250 187.43 46.86 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic breaker @ hour 1.000 293.76 293.76 P&M-001
1.00 cum per hour
Tractor-trolley hour 0.270 171.02 46.17 P&M-053
c) Overhead charges @ 0.1 on (a+b) 58.40
d) Contractor's profit @ 0.1 on (a+b+c) 64.24
Cost for 1.25 cum = a+b+c+d 706.69
Rate per cum = (a+b+c+d)/ 1.25 565.36
say 565.00
2.4 (ii) Dismantling Brick / Tile work
A In lime mortar
a) Labour
Mate day 0.020 195.43 3.91 L-12
Mazdoor for dismantling, loading and unloading day 0.500 187.43 93.72 L-13
b) Machinery
Tractor-trolley hour 0.270 171.02 46.17 P&M-053
c) Overhead charges @ 0.1 on (a+b) 14.38
d) Contractor's profit @ 0.1 on (a+b+c) 15.82
Cost for 1.25 cum = a+b+c+d 174.00
Rate per cum = (a+b+c+d)/ 1.25 139.20
say 139.00
2.4 (ii) B In cement mortar
a) Labour
Mate day 0.030 195.43 5.86 L-12
Mazdoor for dismantling, loading and unloading day 0.750 187.43 140.57 L-13
b) Machinery
Tractor-trolley hour 0.270 171.02 46.17 P&M-053
c) Overhead charges @ 0.1 on (a+b) 19.26

74
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Contractor's profit @ 0.1 on (a+b+c) 21.19
Cost for 1.25 cum = a+b+c+d 233.06
Rate per cum = (a+b+c+d)/ 1.25 186.45
say 186.00
2.4 (ii) C In mud mortar
a) Labour
Mate day 0.016 195.43 3.13 L-12
Mazdoor for dismantling and loading day 0.400 187.43 74.97 L-13
b) Machinery
Tractor-trolley hour 0.270 171.02 46.17 P&M-053
c) Overhead charges @ 0.1 on (a+b) 12.43
d) Contractor's profit @ 0.1 on (a+b+c) 13.67
Cost for 1.25 cum = a+b+c+d 150.37
Rate per cum = (a+b+c+d)/ 1.25 120.30
say 120.00
2.4 (ii) D Dry brick pitching or brick soling
a) Labour
Mate day 0.014 195.43 2.74 L-12
Mazdoor for Dismantling, loading and unloading day 0.350 187.43 65.60 L-13
b) Machinery
Tractor-trolley hour 0.270 171.02 46.17 P&M-053
c) Overhead charges @ 0.1 on (a+b) 11.45
d) Contractor's profit @ 0.1 on (a+b+c) 12.60
Cost for 1.25 cum = a+b+c+d 138.56
Rate per cum = (a+b+c+d)/ 1.25 110.85
say 111.00
2.4 (iii) Dismantling Stone Masonry
A Rubble stone masonry in lime mortar
a) Labour
Mate day 0.024 195.43 4.69 L-12
Mazdoor for dismantling, loading and unloading. day 0.600 187.43 112.46 L-13
b) Machinery
Tractor-trolley hour 0.270 171.02 46.17 P&M-053
c) Overhead charges @ 0.1 on (a+b) 16.33
d) Contractor's profit @ 0.1 on (a+b+c) 17.97
Cost for 1.25 cum = a+b+c+d 197.62
Rate per cum = (a+b+c+d)/ 1.25 158.10
say 158.00
2.4 (iii) B Rubble stone masonry in cement mortar.
a) Labour
Mate day 0.030 195.43 5.86 L-12
Mazdoor for dismantling, loading and unloading. day 0.750 187.43 140.57 L-13
b) Machinery
Tractor-trolley hour 0.270 171.02 46.17 P&M-053
c) Overhead charges @ 0.1 on (a+b) 19.26
d) Contractor's profit @ 0.1 on (a+b+c) 21.19
Cost for 1.25 cum = a+b+c+d 233.06
Rate per cum = (a+b+c+d)/ 1.25 186.45
say 186.00
2.4 (iii) C Rubble Stone Masonry in mud mortar.
a) Labour
Mate day 0.020 195.43 3.91 L-12
Mazdoor for dismantling, loading and unloading. day 0.500 187.43 93.72 L-13

75
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Machinery
Tractor-trolley hour 0.270 171.02 46.17 P&M-053
c) Overhead charges @ 0.1 on (a+b) 14.38
d) Contractor's profit @ 0.1 on (a+b+c) 15.82
Cost for 1.25 cum = a+b+c+d 174.00
Rate per cum = (a+b+c+d)/ 1.25 139.20
say 139.00
2.4 (iii) D Dry rubble masonry
a) Labour
Mate day 0.018 195.43 3.52 L-12
Mazdoor for dismantling, loading and unloading. day 0.450 187.43 84.34 L-13
b) Machinery
Tractor-trolley hour 0.270 171.02 46.17 P&M-053
c) Overhead charges @ 0.1 on (a+b) 13.40
d) Contractor's profit @ 0.1 on (a+b+c) 14.74
Cost for 1.25 cum = a+b+c+d 162.18
Rate per cum = (a+b+c+d)/ 1.25 129.75
say 130.00
2.4 (iii) E Dismantling stone pitching/ dry stone spalls.
a) Labour
Mate day 0.016 195.43 3.13 L-12
Mazdoor for dismantling, loading and unloading. day 0.400 187.43 74.97 L-13
b) Machinery
Tractor-trolley hour 0.270 171.02 46.17 P&M-053
c) Overhead charges @ 0.1 on (a+b) 12.43
d) Contractor's profit @ 0.1 on (a+b+c) 13.67
Cost for 1.25 cum = a+b+c+d 150.37
Rate per cum = (a+b+c+d)/ 1.25 120.30
say 120.00
2.4 (iii) F Dismantling boulders laid in wire crates including opening of
crates and stacking dismantled materials.

a) Labour
Mate day 0.020 195.43 3.91 L-12
Mazdoor for dismantling, loading and unloading day 0.500 187.43 93.72 L-13
b) Machinery
Tractor-trolley hour 0.270 171.02 46.17 P&M-053
c) Overhead charges @ 0.1 on (a+b) 14.38
d) Contractor's profit @ 0.1 on (a+b+c) 15.82
Cost for 1.25 cum = a+b+c+d 174.00
Rate per cum = (a+b+c+d)/ 1.25 139.20
say 139.00
2.4 (iv) Wood Work wrought framed and fixed in frames of trusses upto
a height of 5 m above plinth level
a) Labour
Mate day 0.060 195.43 11.73 L-12
Carpenter day 0.500 247.19 123.60 L-04
Mazdoor for dismantling, loading and unloading. day 1.000 187.43 187.43 L-13
b) Machinery
Tractor-trolley hour 0.270 171.02 46.17 P&M-053
c) Overhead charges @ 0.1 on (a+b) 36.89
d) Contractor's profit @ 0.1 on (a+b+c) 40.58
Cost for 1.25 cum = a+b+c+d 446.40
Rate per cum = (a+b+c+d)/ 1.25 357.12
say 357.00

76
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.4 (v) Steel Work in all types of sections upto a height of 5 m above
plinth level excluding cutting of rivet.
Unit = tonne
Taking output = 1 tonne
A Including dismembering
a) Labour
Mate day 0.140 195.43 27.36 L-12
Blacksmith day 1.000 247.19 247.19 L-02
Mazdoor for dismantling, loading and unloading day 2.500 187.43 468.58 L-13
Add 2.5 per cent of cost of labour for gas cutting, ropes, pulleys etc. 18.58

b) Machinery
Tractor-trolley hour 0.170 171.02 29.07 P&M-053
c) Overhead charges @ 0.1 on (a+b) 79.08
d) Contractor's profit @ 0.1 on (a+b+c) 86.99
Rate per tonne = a+b+c+d 956.84
say 957.00
2.4 (v) B Excluding dismembering.
a) Labour
Mate day 0.220 195.43 42.99 L-12
Mazdoor for dismantling, loading and unloading day 2.000 187.43 374.86 L-13
Blacksmith day 0.500 247.19 123.60 L-02
Add 2.5 per cent of cost of labour for gas cutting, ropes, pulleys etc. 13.54

b) Machinery
Tractor-trolley hour 0.170 171.02 29.07 P&M-053
c) Overhead charges @ 0.1 on (a+b) 58.41
d) Contractor's profit @ 0.1 on (a+b+c) 64.25
Rate per tonne = a+b+c+d 706.71
say 707.00
2.4 (v) C Extra over item No( v ) A and( v ) B for cutting rivets.
Unit = each
Taking output = 10 rivets
a) Labour
Mate day 0.010 195.43 1.95 L-12
Blacksmith day 0.130 247.19 32.13 L-02
Mazdoor day 0.130 187.43 24.37 L-13
b) Overhead charges @ 0.1 on (a) 5.85
c) Contractor's profit @ 0.1 on (a+b) 6.43
Cost for 10 rivets = a+b+c 70.73
Rate for each rivet = ( a+b+c)/10 7.07
say 7.10
2.4 (vi) Scraping of Bricks Dismantled from Brick Work including
Stacking.
Unit = numbers
Taking output = 1000 numbers
A In lime/Cement mortar
a) Labour
Mate day 0.140 195.43 27.36 L-12
Mazdoor day 3.500 187.43 656.01 L-13
b) Overhead charges @ 0.1 on (a) 68.34
c) Contractor's profit @ 0.1 on (a+b) 75.17
Rate per1000 Nos = a+b+c 826.87
say 827.00
2.4 (iv) B In mud mortar

77
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Labour
Mate day 0.050 195.43 9.77 L-12
Mazdoor day 1.250 187.43 234.29 L-13
b) Overhead charges @ 0.1 on (a) 24.41
c) Contractor's profit @ 0.1 on (a+b) 26.85
Rate per1000 Nos = a+b+c 295.31
say 295.00
2.4 (vii) Scraping of Stone from Dismantled Stone Masonry
Unit = cum
Taking output = 1 cum
A In cement and lime mortar
a) Labour
Mate day 0.060 195.43 11.73 L-12
Mazdoor day 1.400 187.43 262.40 L-13
b) Overhead charges @ 0.1 on (a) 27.41
c) Contractor's profit @ 0.1 on (a+b) 30.15
Rate per cum = a+b+c 331.69
say 332.00
2.4 B In Mud mortar
(vii)
a) Labour
Mate day 0.010 195.43 1.95 L-12
Mazdoor day 0.300 187.43 56.23 L-13
b) Overhead charges @ 0.1 on (a) 5.82
c) Contractor's profit @ 0.1 on (a+b) 6.40
Rate per cum = a+b+c 70.40
say 70.00
2.4 (viii) Scarping Plaster in Lime or Cement Mortar from Brick/ Stone
Masonry
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.160 195.43 31.27 L-12
Mazdoor for scarping and loading day 4.000 187.43 749.72 L-13
b) Machinery
Tractor-trolley hour 0.320 171.02 54.73 P&M-053
c) Overhead charges @ 0.1 on (a+b) 83.57
d) Contractor's profit @ 0.1 on (a+b+c) 91.93
Cost for 100 sqm = a+b+c+d 1011.21
Rate per sqm = (a+b+c+d)/100 10.11
say 10.10
2.4 (ix) Removing all type of Hume Pipes and Stacking within a lead of
1000 metres including Earthwork and Dismantling of Masonry
Works.
Unit = metre
Taking output = 1 metre
A Up to 600 mm dia
a) Labour
Mate day 0.020 195.43 3.91 L-12
Mazdoor day 0.520 187.43 97.46 L-13
b) Overhead charges @ 0.1 on (a) 10.14
c) Contractor's profit @ 0.1 on (a+b) 11.15
Rate per metre = a+b+c 122.66
say 123.00
2.4 (ix) B Above 600 mm to 900 mm dia

78
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Labour
Mate day 0.030 195.43 5.86 L-12
Mazdoor day 0.700 187.43 131.20 L-13
b) Overhead charges @ 0.1 on (a) 13.71
c) Contractor's profit @ 0.1 on (a+b) 15.08
Rate per metre = a+b+c 165.85
say 166.00
2.4 (ix) C Above 900 mm
a) Labour
Mate day 0.050 195.43 9.77 L-12
Mazdoor day 1.200 187.43 224.92 L-13
b) Overhead charges @ 0.1 on (a) 23.47
c) Contractor's profit @ 0.1 on (a+b) 25.82
Rate per metre = a+b+c 283.97
say 284.00
Note 1. The excavation of earth, dismantling of stone masonry work in head
walls and protection works is not included which is to be measured
and paid separately.
2. Credit for retrieved stone from masonry work may be taken as per
actual availability.
2.5 202 Dismantling of Flexible Pavements
Dismantling of flexible pavements and disposal of dismantled
materials up to a lead of 1000 metres, stacking serviceable and
unserviceable materials separately
Unit = cum
Taking output = 1 cum
I By Manual Means
A Bituminous courses
a) Labour
Mate day 0.060 195.43 11.73 L-12
Mazdoor for dismantling, loading and unloading day 1.500 187.43 281.15 L-13
b) Machinery
Tractor-trolley hour 0.380 171.02 64.99 P&M-053
c) Overhead charges @ 0.1 on (a+b) 35.79
d) Contractor's profit @ 0.1 on (a+b+c) 39.36
Rate per cum = a+b+c+d 433.01
say 433.00
2.5 I B Granular courses
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor for dismantling, loading and unloading. day 1.000 187.43 187.43 L-13
b) Machinery
Tractor-trolley hour 0.330 171.02 56.44 P&M-053
c) Overhead charges @ 0.1 on (a+b) 25.17
d) Contractor's profit @ 0.1 on (a+b+c) 27.69
Rate per cum = a+b+c+d 304.54
say 305.00
2.5 II By Mechanical Means
A Bituminous course
a) Labour
Mate day 0.010 195.43 1.95 L-12
Mazdoor day 0.300 187.43 56.23 L-13
b) Machinery
Tractor-trolley hour 0.380 171.02 64.99 P&M-053
Farm tractor with ripper @ 60 cum per hour hour 0.017 285.12 4.85 P&M-055

79
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Overhead charges @ 0.1 on (a+b) 12.80
d) Contractor's profit @ 0.1 on (a+b+c) 14.08
Rate per cum = a+b+c+d 154.90
say 155.00
2.6 202 Dismantling of Cement Concrete Pavement
Dismantling of cement concrete pavement by mechanical means
using pneumatic tools, breaking to pieces not exceeding 0.02 cum in
volume and stock piling at designated locations and disposal of
dismantled materials up to a lead of 1000 metres, stacking serviceable
and unserviceable materials separately

Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.030 195.43 5.86 L-12
Semi skilled mazdoor for operating pneumatic tools day 0.500 190.43 95.22 L-14
Mazdoors as helpers including loading and unloading day 0.500 187.43 93.72 L-13
b) Machinery
Air compressor 250 cfm with two leads for pneumatic cutters/ hour 1.000 293.76 293.76 P&M-001
hammers @ 1 cum per hour
Tractor-trolley hour 0.400 171.02 68.41 P&M-053
Joint Cutting Machine with 2-3 blades hour 1.000 214.92 214.92 P&M-083
c) Overhead charges @ 0.1 on (a+b) 77.19
d) Contractor's profit @ 0.1 on (a+b+c) 84.91
Rate per cum = a+b+c+d 933.97
say 934.00
Note The above analysis is for removal of complete pavement. In case full
depth repair work is required to be done after dismantling, provision of
a concrete cutting and sawing machine may be added for 0.25 hours.

2.7 202 Dismantling of Guard Rails


Dismantling guard rails by manual means and disposal of dismantled
material with all lifts and up to a lead of 1000 metres, stacking
serviceable materials and unserviceable materials separately.

Unit = running metre


Taking output = 1 metre
a) Labour
Mate day 0.006 195.43 1.17 L-12
Mazdoor including loading and unloading day 0.150 187.43 28.11 L-13
b) Machinery
Tractor-trolley hour 0.050 171.02 8.55 P&M-053
c) Overhead charges @ 0.1 on (a+b) 3.78
d) Contractor's profit @ 0.1 on (a+b+c) 4.16
Rate per metre = a+b+c+d 45.78
say 46.00
2.8 202 Dismantling of Kerb Stone
Dismantling kerb stone by manual means and disposal of dismantled
material with all lifts and up to a lead of 1000 metre

Unit = running metre


Taking output = 10 metre
a) Labour
Mate day 0.010 195.43 1.95 L-12
Mazdoor including loading and unloading day 0.150 187.43 28.11 L-13

80
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Machinery
Tractor-trolley hour 0.200 171.02 34.20 P&M-053
c) Overhead charges @ 0.1 on (a+b) 6.43
d) Contractor's profit @ 0.1 on (a+b+c) 7.07
Cost for 10 m = a+b+c+d 77.77
Rate per metre = (a+b+c+d)/10 7.78
say 8.00
2.9 202 Dismantling of Kerb Stone Channel
Dismantling kerb stone channel by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000 metre

Unit = running metre


Taking output = 10 metre
a) Labour
Mate day 0.015 195.43 2.93 L-12
Mazdoor including loading and unloading day 0.225 187.43 42.17 L-13
b) Machinery
Tractor-trolley hour 0.300 171.02 51.31 P&M-053
c) Overhead charges @ 0.1 on (a+b) 9.64
d) Contractor's profit @ 0.1 on (a+b+c) 10.60
Cost for 10 m = a+b+c+d 116.65
Rate per metre = (a+b+c+d)/10 11.67
say 12.00
2.10 202 Dismantling of Kilometre Stone
Dismantling of kilometre stone including cutting of earth, foundation
and disposal of dismantled material with all lifts and lead upto 1000 m
and back filling of pit.
Unit = Each
Taking output = one KM stone
A 5th KM stone
Quantity of cement concrete = 0.392 cum
a) Labour
Mate day 0.130 195.43 25.41 L-12
Mazdoor day 0.750 187.43 140.57 L-13
b) Machinery
Tractor-trolley hour 0.150 171.02 25.65 P&M-053
c) Overhead charges @ 0.1 on (a+b) 19.16
d) Contractor's profit @ 0.1 on (a+b+c) 21.08
Rate for one 5th KM stone = a+b+c+d 231.87
say 232.00
B Ordinary KM Stone
Quantity of cement concrete = 0.269 cum
a) Labour
Mate day 0.020 195.43 3.91 L-12
Mazdoor day 0.500 187.43 93.72 L-13
b) Machinery
Tractor-trolley hour 0.100 171.02 17.10 P&M-053
c) Overhead charges @ 0.1 on (a+b) 11.47
d) Contractor's profit @ 0.1 on (a+b+c) 12.62
Rate for one ordinary KM stone = a+b+c+d 138.82
say 139.00
C Hectometre Stone
Quantity of cement concrete = 0.048 cum
a) Labour
Mate day 0.004 195.43 0.78 L-12

81
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor day 0.100 187.43 18.74 L-13
b) Machinery
Tractor-trolley hour 0.020 171.02 3.42 P&M-053
c) Overhead charges @ 0.1 on (a+b) 2.29
d) Contractor's profit @ 0.1 on (a+b+c) 2.52
Rate for one Hectometre stone = a+b+c+d 27.76
say 27.80
2.11 202 Dismantling of Fencing
Dismantling of barbed wire fencing/ wire mesh fencing including posts,
foundation concrete, back filling of pit by manual means including
disposal of dismantled material with all lifts and up to a lead of 1000
metres, stacking serviceable material and unserviceable material
separately.

Unit = running metre


Taking output = 30 metres
a) Labour
Mate day 0.150 195.43 29.31 L-12
Mazdoor including loading and unloading day 3.000 187.43 562.29 L-13
Blacksmith day 0.750 247.19 185.39 L-02
b) Machinery
Tractor-trolley hour 0.150 171.02 25.65 P&M-053
c) Overhead charges @ 0.1 on (a+b) 80.26
d) Contractor's profit @ 0.1 on (a+b+c) 88.29
Cost for 30 metres = a+b+c+d 971.21
Rate per metre = (a+b+c+d)/30 32.37
say 32.40
2.12 202 Dismantling of CI Water Pipe Line
Dismantling of CI water pipe line 600 mm dia including disposal with
all lifts and lead upto 1000 metres and stacking of serviceable material
and unserviceable material separately under supervision of concerned
department

Unit = running metre


Taking output = 10 metres
a) Labour
Mate day 0.090 195.43 17.59 L-12
Mazdoor day 2.000 187.43 374.86 L-13
Plumber day 0.250 247.19 61.80 L-02
b) Machinery
Truck 10 tonne capacity hour 0.250 752.00 188.00 P&M-057
Light Crane 3 tonne capacity hour 0.500 525.00 262.50 P&M-013
c) Overhead charges @ 0.1 on (a+b) 90.47
d) Contractor's profit @ 0.1 on (a+b+c) 99.52
Cost for 10 metres = a+b+c+d 1094.74
Rate per metre = (a+b+c+d)/10 109.47
say 109.00
Note The rate analysis does not include any excavation in earth or
dismantling of masonry works which are to be measured and paid
separately.
2.13 202 Removal of Cement Concrete Pipe of Sewer Gutter
Removal of cement concrete pipe of sewer gutter 1500 mm dia under
the supervision of concerned department including disposal with all
lifts and up to a lead of 1000 metres and stacking of serviceable and
unserviceable material separately but excluding earth excavation and
dismantling of masonry works.

Unit = running metre

82
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking output = 10 metres
a) Labour
Mate day 0.100 195.43 19.54 L-12
Mazdoor day 2.500 187.43 468.58 L-13
b) Machinery
Crane 5 tonne capacity hour 0.300 599.40 179.82 P&M-070
Truck flat body 10 tonne hour 1.000 752.00 752.00 P&M-057
c) Overhead charges @ 0.1 on (a+b) 141.99
d) Contractor's profit @ 0.1 on (a+b+c) 156.19
Cost for 10 metres = a+b+c+d 1718.12
Rate per metre = (a+b+c+d)/10 171.81
say 172.00
Note The rate analysis does not include any excavation in earth or
dismantling of masonry works which are to be measured and paid
separately.
2.14 202 Removal of Telephone / Electric Poles and Lines
Removal of telephone / Electric poles including excavation and
dismantling of foundation concrete and lines under the supervision of
concerned department, disposal with all lifts and up to a lead of 1000
metres and stacking the serviceable and unserviceable material
separately

Unit = each
Taking output = 30 Nos
a) Labour
Mate day 0.480 195.43 93.81 L-12
Mazdoor day 10.000 187.43 1874.30 L-13
Electrician/Lineman day 2.000 247.19 494.38 L-02
b) Machinery
Tractor-trolley hour 1.500 171.02 256.53 P&M-053
c) Overhead charges @ 0.1 on (a+b) 271.90
d) Contractor's profit @ 0.1 on (a+b+c) 299.09
Cost for 30 poles = a+b+c+d 3290.01
Rate per pole = (a+b+c+d)/30 109.67
say 110.00

83
Analysis of Rate RCD/SOR

CHAPTER - 3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.1 301 Excavation in Soil by Manual Means .
Excavation for roadway in soil using manual means
including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto1000 metres.

Unit = cum
Taking output = 120 cum
a) Labour
Mate day 1.800 195.43 351.77 L-12
Mazdoor day 45.000 187.43 8434.35 L-13
b) Machinery
Truck 5.5 cum capacity hour 10.000 752.00 7520.00 P&M-057
c) Overhead charges @ 0.1 on (a+b) 1630.61
d) Contractor's profit @ 0.1 on (a+b+c) 1793.67
Cost of 120 cum = a+b+c+d 19730.41
Rate per cum = (a+b+c+d)/120 164.42
Royalty @ Rs. 24.00 per Cum 24.00
Rate per cum say 188.00
(ii) Including Royalty @ Rs. 24.0 per cum, cost of watering,
rolling & compaction 207.00
Rate per cum say 207.00
Note In case there is a situation where the cross-section is of cut
and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck
shall be omitted. 113.00
Rate per cum say 113.00
3.2 301 Excavation in Ordinary Rock by Manual Means
(i) Excavation in ordinary rock using manual means including
loading in a truck and carrying of excavated material to
embankment site with in all lifts and leads upto 1000 metres
including Royalty but excluding rolling , copaction & watering

Unit = cum
Taking output = 120 cum
a) Labour
Mate day 2.800 195.43 547.20 L-12
Mazdoor day 70.000 187.43 13120.10 L-13
b) Machinery
Truck 5.5 cum capacity hour 10.000 752.00 7520.00 P&M-057
c) Overhead charges @ 0.1 on (a+b) 2118.73
d) Contractor's profit @ 0.1 on (a+b+c) 2330.60
Cost for 120 cum = a+b+c+d 25636.64
Rate per cum = (a+b+c+d)/120 213.64
Royalty @ Rs. 24.00 per Cum 24.00
Rate per cum 237.64
say 238.00
(ii) Including Royalty @ Rs. 24.00 per Cum , watering , rolling &
compaction. 256.00

Note In case there is a situation where the cross-section is of cut


and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck 162.00
shall be omitted. including Royalty @ Rs. 15.00 per cum

3.3 301 Excavation in Soil with Dozer with lead upto 100
metres
Excavation for road way in soil by mechanical means
including cutting and pushing the earth to site of
embankment upto a distance of 100 metres (average lead50
metres), including trimming bottom and side slopes in
accordance with requirements of lines, grades and cross
sections.
Unit = cum

84
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking output = 180 cum
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery
Dozer, 80 HP @ 30 cum per hour hour 6.000 3135.24 18811.44 P&M-014
c) Overhead charges @ 0.1 on (a+b) 1920.19
d) Contractor's profit @ 0.1 on (a+b+c) 2112.21
Cost for 180 cum = a+b+c+d 23234.34
Rate per cum = (a+b+c+d)/180 129.08
say 129.00
3.4 301 Excavation in Ordinary Rock with Dozer with lead upto
100 metres
Excavation for roadway in ordinary rock by deploying a
dozer, 80 HP including cutting and pushing the cut earth to
site of embankment upto a distance of 100 metres ( average
lead 50 metres ), trimming bottom and side slopes in
accordance with the requirements of lines, grades and cross
sections.

Unit = cum
Taking output = 108 cum
a) Labour
Mate day 0.120 195.43 23.45 L-12
Mazdoor day 3.000 187.43 562.29 L-13
b) Machinery
Dozer, 80 HP @ 20 cum per hour hour 6.000 3135.24 18811.44 P&M-014
c) Overhead charges @ 0.1 on (a+b) 1939.72
d) Contractor's profit @ 0.1 on (a+b+c) 2133.69
Cost for 108 cum = a+b+c+d 23470.59
Rate per cum = (a+b+c+d)/108 217.32
say 217.00
3.5 301 Excavation in Hard Rock (requiring blasting) with
disposal upto 1000 metres
Excavation for roadway in hard rock (requiring blasting)
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and leads upto 1000 metres

Unit = cum
Taking 0utput = 180 cum
a) Labour
Mate day 0.220 195.43 42.99 L-12
Mazdoor day 3.000 187.43 562.29 L-13
Driller day 2.000 218.57 437.14 L-06
Blaster day 0.250 304.89 76.22 L-03
b) Machinery
Dozer, 80 HP @ 30 cum per hour hour 6.000 3135.24 18811.44 P&M-014
Air compressor, 250 cfm with 2 jack hammer hour 6.000 293.76 1762.56 P&M-001
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Tipper10 tonne capacity hour 11.250 846.00 9517.50 P&M-048
c) Materials
Gelatin 80 per cent kg 63.000 112.77 7104.58 M-104
Electric Detonators @ 1 detonator for 2 gelatin sticks of each 252.000 14.27 3595.07 M-094 /100
125 gms each
Credit for excavated rock found suitable for use @ 50 cum 90.000 -102.33 (9209.64) M-089
per cent quantity blasted
d) Overhead charges @ 0.1 on (a+b+c) 3958.82
e) Contractor's profit @ 0.1 on (a+b+c+d) 4354.70
Cost for 180 cum = a+b+c+d+e 47901.67
Rate per cum = (a+b+c+d+e)/180 266.12
say 266.00

85
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
`
Note 1. The quality and availability of rock shall be checked
before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced/restricted to that extent.
3.6 301 Excavation in Soil using Hydraulic Excavator CK 90
and Tippers with Disposal upto 1000 metres.
Excavation for roadwork in soil with hydraulic excavator of
0.9 cum bucket capacity including cutting and loading in
tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts and
lead upto 1000m (including Royalty @ Rs. 24.00 per Cum
but excluding watering, rolling & compaction)

Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 60 hour 6.000 1516.32 9097.92 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 16.000 846.00 13536.00 P&M-048
c) Overhead charges @ 0.1 on (a+b) 2302.44
d) Contractor's profit @ 0.1 on (a+b+c) 2532.69
Cost for 360 cum = a+b+c+d 27859.54
Rate per cum = (a+b+c+d)/360 77.39
Royalty @ Rs. 24.00 per Cum 24.00
Rate per cum 101.39
say 101.00
3.7 301 Excavation in Ordinary Rock using Hydraulic
Excavator CK-90 and Tippers with Disposal upto 1000
metres.
Excavation for roadway in ordinary rock with hydraulic
excavator of 0.9 cum bucket capacity including cutting and
loading in tippers, transporting to embankment site within all
lifts and lead upto 1000 m, trimming bottom and side slopes
in accordance with requirements of lines, grades and cross
sections (including Royalty @ Rs. 24.00 per Cum but
excluding watering, rolling & compaction)

Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ 36 hour 6.000 1516.32 9097.92 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 11.000 846.00 9306.00 P&M-048
c) Overhead charges @ 0.1 on (a+b) 1879.44
d) Contractor's profit @ 0.1 on (a+b+c) 2067.39
Cost for 240 cum = a+b+c+d 22741.24
Rate per cum = (a+b+c+d)/240 94.76
Royalty @ Rs. 24.00 per Cum 24.00
Rate per cum 118.76
say 119.00
3.8 301 Excavation in Hard Rock (blasting prohibited)

86
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Excavation for roadway in hard rock (blasting prohibited)
with rock breakers including breaking rock, loading in tippers
and disposal within all lifts and lead upto 1000 metres,
trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.
A Mechanised
Unit = cum
Taking output = 36 cum
a) Labour
Mate day 0.400 195.43 78.17 L-12
Mazdoor for trimming slopes including mannul loading day 10.000 187.43 1874.30 L-13
in truck
b) Machinery
Hydraulic excavator with rock breaker attachment @ 6 hour 6.000 1516.32 9097.92 P&M-026
cum per hour
Tipper 5.5 cum capacity, 1 trip per hour. hour 6.500 846.00 5499.00 P&M-048
Credit for excavated rock found suitable for use @ 50 cum 18.000 -102.33 -1841.93 M-089
per cent of excavated quantity
c) Overhead charges @ 0.1 on (a+b) 1470.75
d) Contractor's profit @ 0.1 on (a+b+c) 1617.82
Cost for 36 cum = a+b+c+d 17796.03
Rate per cum = (a+b+c+d)/36 494.33
say 494.00
Note 1. The quality and availability of rock shall be checked
before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be restricted/reduced to that extent.
3.Being small quantity, manual loading will be economical in
this case and has been provided accordingly.
3.8 B Manual Method
Unit = cum
Taking output = 16 cum
a) Labour
Mate day 1.640 195.43 320.51 L-12
Mazdoor including loading in truck day 16.000 187.43 2998.88 L-13
Chiseller day 24.000 195.43 4690.32 L-05
Blacksmith day 1.000 247.19 247.19 L-02
b) Machinery
Tipper 5.5 cum capacity, 1 trip per hour. hour 2.900 846.00 2453.40 P&M-048
Credit for excavated rock found suitable for use @ 50 cum 8.000 -102.33 -818.63 M-089
per cent of excavated
c) Overhead charges @ 0.1 on (a+b) 989.17
d) Contractor's profit @ 0.1 on (a+b+c) 1088.08
Cost for 16 cum = a+b+c+d 11968.91
Rate per cum = (a+b+c+d)/16 748.06
say 748.00
Note 1. Credit is considered for 50 per cent of quantity of work.
2. Loading for disposal will be done manually, being small
quantity.
3. In case some rock is issued to contractor at site, the item
of carriage shall be omitted to the extent of quantity issued
to the contractor.
3.9 301 Excavation in Hard Rock (controlled blasting) with
disposal upto 1000 metres

87
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Excavation for roadway in hard rock with controlled blasting
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and leads upto 1000 metres
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.220 195.43 42.99 L-12
Mazdoor day 3.000 187.43 562.29 L-13
Driller day 2.000 218.57 437.14 L-06
Blaster day 0.500 304.89 152.45 L-03
b) Machinery
Dozer 80 HP @ 30 cum per hour hour 6.000 3135.24 18811.44 P&M-014
Air compressor, 250 cfm with 2 jack hammers hour 6.000 293.76 1762.56 P&M-001
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Tipper 5.5 cum capacity, 4 trips per hour. hour 8.200 846.00 6937.20 P&M-048
c) Materials
Gelatin 80 per cent kg 63.000 112.77 7104.58 M-104
Electric Detonators @ 1 detonator for1/2 gelatin stick each 1008.000 14.27 14380.28 M-094 /100
of 125 gms each
Credit for excavated rock found suitable for use @ 50 cum 90.000 -102.33 -9209.64 M-089
per cent quantity blasted
Add 5 per cent of cost of a+b+c towards muffling 2393.46
arrangements to guard against any rock fly off during
blasting
d) Overhead charges @ 0.1 on (a+b+c) 5026.28
e) Contractor's profit @ 0.1 on (a+b+c+d) 5528.90
Cost for 180 cum = a+b+c+d+e 60817.93
Rate per cum = (a+b+c+d+e)/180 337.88
say 338.00
#VALUE!
Note 1. Credit is considered for 50 per cent of quantity of
blastered rock, if found suitable for construction..
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced to that extent.
3.10 301 Excavation in Marshy Soil
Excavation for roadway in marshy soil with hydraulic
excavator 0.9 cum bucket capacity including cutting and
loading in tippers and disposal with in all lifts and lead upto
1000 metres, trimming of bottom and side slopes in
accordance with requirements of lines, grades and cross
sections (including Royalty @ Rs. 24.00 per Cum but
excluding watering, rolling & compaction)

Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery
Hydraulic excavator 0.90 cum bucket capacity @ 50 hour 6.000 1516.32 9097.92 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 13.640 846.00 11539.44 P&M-048
c) Overhead charges @ 0.1 on (a+b) 2102.79
d) Contractor's profit @ 0.1 on (a+b+c) 2313.06
Cost for 300 cum = a+b+c+d 25443.70
Rate per cum = (a+b+c+d)/300 84.81

88
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Royalty @ Rs. 24.00 per Cum 24.00
Rate per cum 108.81
say 109.00
3.11 301 Removal of Unserviceable Soil with Disposal upto
1000 metres
Removal of unserviceable soil including excavation, loading
and disposal upto 1000 metres lead but excluding
replacement by suitable soil which shall be paid separately
as per clause 305.

Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery
Excavator0.90 cum bucket capacity @ 60 cum per hour hour 6.000 1516.32 9097.92 P&M-026

Tipper 5.5 cum capacity, 4 trips per hour. hour 16.360 846.00 13840.56 P&M-048
c) Overhead charges @ 0.1 on (a+b) 2332.90
d) Contractor's profit @ 0.1 on (a+b+c) 2566.19
Cost for 360 cum = a+b+c+d 28228.06
Rate per cum = (a+b+c+d)/360 78.41
say 78.00
Note This item does not include replacement of unsuitable soil by
suitable soil. Replacement, where required, is to be provided
and paid separately under clause 305.
3.12 303 Presplitting of Rock Excavation Slopes
Carrying out excavation in hard rock to achieve a specified
slope of the rock face by controlled use of explosives and
blasting accessories in properly aligned and spaced drill
holes, collection of the excavated rock by a 80 HP dozer,
loading in tipper by a front end loader and disposing of the
material with all lifts and lead upto 1000 m, all as specified in
clause No. 303

Unit = sqm
Taking output = 400 sqm( 120 cum considering 300mm
average depth of excavation over the existing rock
face)
a) Labour
Mate day 0.600 195.43 117.26 L-12
Mazdoor day 15.000 187.43 2811.45 L-13
b) Machinery
Air compressor 250 cfm with 2 leads @ 20 cum per hour 6.000 293.76 1762.56 P&M-001
hour
Dozer, 80 HP hour 6.000 3135.24 18811.44 P&M-014
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
c) Materials
Gelatin 80 per cent kg 42.000 112.77 4736.38 M-104
Electric Detonators @ 1 detonator for 1/2 gelatin stick each 672.000 14.27 9586.85 M-094 /100
of 125 gms each
d) Overhead charges @ 0.1 on (a+b+c) 4471.39
e) Contractor's profit @ 0.1 on (a+b+c+d) 4918.53
Cost for 400 sqm = a+b+c+d+e 54103.87
Rate per sqm = (a+b+c+d+e)/400 135.26
say 135.00

89
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note In case blasted rock is used to the contractor against
payment for constructed work, the cost of carriage shall be
reduced to that extent.
Excavation for Structures
3.13 304 Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work.

(i) Ordinary soil


Unit = cum
Taking output = 10 cum
A Manual Means (Depth upto 3 m)
a) Labour
Mate day 0.320 195.43 62.54 L-12
Mazdoor day 8.000 187.43 1499.44 L-13
b) Overhead charges @ 0.1 on (a) 156.20
c) Contractor's profit @ 0.1 on (a+b) 171.82
Cost for 10 cum = a+b+c 1889.99
Rate per cum = (a+b+c)/10 189.00
say 189.00
Note Cost of dewatering may be added where required upto 10
per cent of labour cost Assessment for dewatering shall be
made as per site conditions..
3.13 (i) B Mechanical Means (Depth upto 3 m)
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.320 195.43 62.54 L-12
Mazdoor day 8.000 187.43 1499.44 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 1516.32 9097.92 P&M-026
c) Overhead charges @ 0.1 on (a+b) 1065.99
d) Contractor's profit @ 0.1 on (a+b+c) 1172.59
Cost for 300 cum = a+b+c+d 12898.48
Rate per cum = (a+b+c+d)/300 42.99
say 43.00
Note Cost of dewatering upto 5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
3.13 (ii) Ordinary Rock (not requiring blasting)
A Manual Means (Depth upto 3 m)
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.400 195.43 78.17 L-12
Mazdoor day 10.000 187.43 1874.30 L-13
b) Overhead charges @ 0.1 on (a) 195.25
c) Contractor's profit @ 0.1 on (a+b) 214.77
Cost for 10 cum = a+b+c 2362.49
Rate per cum = (a+b+c)/10 236.25
say 236.00
Note Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..

90
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.13 B Mechanical Means
(ii)
Unit = cum
Taking output = 216 cum
a) Labour
Mate day 0.240 195.43 46.90 L-12
Mazdoor day 6.000 187.43 1124.58 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.000 1516.32 9097.92 P&M-026
c) Overhead charges @ 0.1 on (a+b) 1026.94
d) Contractor's profit @ 0.1 on (a+b+c) 1129.63
Cost for 216 cum = a+b+c+d 12425.98
Rate per cum = (a+b+c+d)/216 57.53
say 58.00
Note 1.Cost of dewatering upto 5 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
3.13 (iii) Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
i) Mate day 0.530 195.43 103.58 L-12
ii) Driller day 0.840 218.57 183.60 L-06
iii) Blaster day 0.400 304.89 121.96 L-03
iv) Mazdoor day 12.000 187.43 2249.16 L-13
b) Machinery
Air Compressor 250 cfm with 2 jack hammer @ 15 cum hour 0.67 293.76 196.82 P&M-001
per hour
c) Material
Blasting Material kg 3.500 112.77 394.70 M-104
Detonator electric each 14.000 14.27 199.73 M-094 /100
d) Overhead charges @ 0.1 on (a+b+c) 344.95
e) Contractor's profit @ 0.1 on (a+b+c+d) 379.45
Cost for 10 cum = a+b+c+d+e 4173.94
Rate per cum = (a+b+c+d+e)/10 417.39
say 417.00

Note Cost of dewatering @ 10 per cent of labour cost may be


added, where required Assessment for dewatering shall be
made as per site conditions.
3.13 (iv) Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum
A Mechanical Means
a) Labour
Mate day 0.200 195.43 39.09 L-12
Mazdoor day 5.000 187.43 937.15 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 10.000 293.76 2937.60 P&M-001
breaker @ 1 cum per hour
c) Overhead charges @ 0.1 on (a+b) 391.38
d) Contractor's profit @ 0.1 on (a+b+c) 430.52
Cost for 10 cum = a+b+c+d 4735.74

91
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per cum = (a+b+c+d)/10 473.57
say 474.00
Note 1. Cost of dewatering upto 5 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond 3 m is not dug and
hence not included.
3.13 (v) Marshy soil
Unit = cum
Taking output = 10 cum
A Manual means ( upto 3 m depth)
a) Labour
Mate/Supervisor day 0.400 195.43 78.17 L-12
Mazdoor day 10.000 187.43 1874.30 L-13
b) Machinery
Tractor-trolley hour 2.670 171.02 456.62 P&M-053
c) Material
Selected earth for refilling cum 5.000 25.10 125.50 M-163
d) Overhead charges @ 0.1 on (a+b+c) 253.46
e) Contractor's profit @ 0.1 on (a+b+c+d) 278.80
Cost for 10 cum = a+b+c+d+e 3066.85
Rate per cum = ( a+b+c+d+e)/ 10 306.69
say 307.00
Note 1. Cost of dewatering @ 30 per cent of (a), may be added,
where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 20 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
3.13 B Mechanical Means
(v)
a) Labour
i) Mate day 0.080 195.43 15.63 L-12
ii) Mazdoor for dressing sides, bottom and backfilling day 2.000 187.43 374.86 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 hour 0.170 1516.32 257.77 P&M-026
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.450 846.00 380.70 P&M-048
c) Material
Selected earth for refilling cum 5.000 25.10 125.50 M-163
d) Overhead charges @ 0.1 on (a+b+c) 115.45
e) Contractor's profit @ 0.1 on (a+b+c+d) 126.99
Cost for 10 cum = a+b+c+d+e 1396.91
Rate per cum = (a+b+c+d+e)/10 139.69
say 140.00
Note 1. Cost of dewatering @ 20 per cent of (a+b) may be
added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil
3.14 305.4.3 Scarifying Existing Granular Surface to a Depth of 50
mm by Manual Means

92
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Scarifying the existing granular road surface to a depth of 50
mm and disposal of scarified material within all lifts and
leads upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.200 195.43 39.09 L-12
Mazdoor including loading and unloading day 5.000 187.43 937.15 L-13
b) Machinery
Tractor-trolley hour 1.670 171.02 285.60 P&M-053
c) Overhead charges @ 0.1 on (a+b) 126.18
d) Contractor's profit @ 0.1 on (a+b+c) 138.80
Cost for 100 sqm = a+b+c+d 1526.82
Rate per sqm = (a+b+c+d)/100 15.27
say 15.30
Note In case material is to be reused at site, transportation cost
catered above for disposal shall be deleted.
3.15 305.4.3 Scarifying Existing Bituminous Surface to a depth of
50 mm by Mechanical Means
Scarifying the existing bituminous road surface to a depth of
50 mm and disposal of scarified material with in all lifts and
lead upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.010 195.43 1.95 L-12
Mazdoor day 0.250 187.43 46.86 L-13
b) Machinery
Tractor with ripper attachment @ 60 cum per hour hour 0.080 285.12 22.81 P&M-055
Front end loader 1 cum bucket capacity @ 25 cum per hour 0.200 1148.00 229.60 P&M-017
hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.230 846.00 194.58 P&M-048
c) Overhead charges @ 0.1 on (a+b) 49.58
d) Contractor's profit @ 0.1 on (a+b+c) 54.54
Cost for 100 sqm = a+b+c+d 599.92
Rate per sqm = (a+b+c+d)/100 6.00
say 6.00
3.16 305 Construction of Embankment with Material obtained
from Borrowpits
Construction of embankment with approved material
obtained from borrow pits with all lifts and leads, transporting
to site, spreading, grading to required slope and compacting
to meet requirement of table 300-2.

Unit = cum

a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor day 1.000 187.43 187.43 L-13
b) Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum hour 1.670 1516.32 2532.25 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 160 x L 2.68 428.54 Lead =1 km
& P&M-047
Add 10 per cent of cost of carriage to cover cost of 42.85
loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3135.24 1567.62 P&M-014
Motor grader for grading @ 100 cum per hour hour 1.000 2450.00 2450.00 P&M-032

93
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Water tanker6 KL capacity hour 4.000 111.24 444.96 P&M-060
Vibratory roller 8 -10 tonnes @ 100 cum per hour hour 1.000 1720.00 1720.00 P&M-059
c) Material
Cost of water KL 24.000 167.07 4009.64 M-189
Compensation & Royalty for earth taken from private cum 100.000 25.10 2510.00 M-092
land
d) Overhead charges @ 0.1 on (a+b+c) 1590.11
e) Contractor's profit @ 0.1 on (a+b+c+d) 1749.12
Cost for 100 cum = a+b+c+d+e 19240.35
Rate per cum = (a+b+c+d+e)/100 192.40
say 192.00
Note Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
3.17 305 Construction of Embankment with Material Deposited
from Roadway Cutting
Construction of embankment with approved materials
deposited at site from roadway cutting and excavation from
drain and foundation of other structures graded and
compacted to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.020 195.43 3.91 L-12
Mazdoor day 0.500 187.43 93.72 L-13
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3135.24 1567.62 P&M-014
Motor grader for grading @ 100 cum per hour hour 1.000 2450.00 2450.00 P&M-032
Water tanker6 KL capacity hour 4.000 111.24 444.96 P&M-060
Vibratory roller 8-10 tonnes @ 100 cum per hour hour 1.000 1720.00 1720.00 P&M-059
c) Material
Cost of water KL 24.000 167.07 4009.64 M-189
d) Overhead charges @ 0.1 on (a+b+c) 1028.98
e) Contractor's profit @ 0.1 on (a+b+c+d) 1131.88
Rate for 100 cum = a+b+c+d+e 12450.71
Rate per cum = (a+b+c+d+e)/100 124.51

say 125.00
Note In case the earth cutting is done by dozer and pushed for
filling in the embankment, the input of dozer in the cost of
embankment shall be deleted as the same is already
provided in the cost of excavation. However, if the earth is
dumped by tippers from roadway cutting, the input of dozer
for spreading is required to be provided.

3.18 305 Construction of Subgrade and Earthen Shoulders


Construction of sub-grade and earthen shoulders with
approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No.
300-2
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor day 1.000 187.43 187.43 L-13

94
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum hour 1.670 1516.32 2532.25 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 175xL 2.68 468.72 Lead =1 km
& P&M-047
Add 10 per cent of cost of carriage to cover cost of 46.87
loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3135.24 1567.62 P&M-014
Motor grader for grading @ 50 cum per hour hour 2.000 2450.00 4900.00 P&M-032
Water tanker with 6 km lead hour 4.000 111.24 444.96 P&M-060
Vibratory roller 8-10 tonnes @ 80 cum per hour hour 1.250 1720.00 2150.00 P&M-059
c) Material
Cost of water KL 24.000 167.07 4009.64 M-189
Compensation & Royalty for earth taken from private land cum 100.000 25.10 2510.00 M-092
d) Overhead charges @ 0.1 on (a+b+c) 1882.53
e) Contractor's profit @ 0.1 on (a+b+c+d) 2070.78
Cost for 100 cum = a+b+c+d+e 22778.63
Rate per cum = (a+b+c+d+e)/100 227.79
say 228.00
3.19 305.3.4 Compacting Original Ground
Case-I Compacting original ground supporting sub-grade
Loosening of the ground upto a level of 500 mm below the
sub-grade level, watered, graded and compacted in layers to
meet requirement of table 300-2 for sub-grade construction.

Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.120 195.43 23.45 L-12
Mazdoor day 3.000 187.43 562.29 L-13
b) Machinery
Tractor with ripper attachment hour 9.000 285.12 2566.08 P&M-055
Motor grader for grading hour 6.000 2450.00 14700.00 P&M-032
Water tanker 6 KL capacity hour 4.000 111.24 444.96 P&M-060
Vibratory roller 8-10 tonne @ 80 cum/hour hour 7.500 1720.00 12900.00 P&M-059
c) Material
Cost of water KL 24.000 167.07 4009.64 M-189
d) Overhead charges @ 0.1 on (a+b+c) 3520.64
e) Contractor's profit @ 0.1 on (a+b+c+d) 3872.71
Cost for 600 cum = a+b+c+d+e 42599.77
Rate per cum = (a+b+c+d+e)/600 71.00
say 71.00
3.19 Case-II :Compacting original ground supporting embankment

Loosening, leveling and Compacting original ground


supporting embankment to facilitate placement of first layer
of embankment, scarified to a depth of 150 mm, mixed with
water at OMC and then compacted by rolling so as to
achieve minimum dry density as given in Table 300-2 for
embankment construction.

Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery

95
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Tractor with ripper attachment hour 6.000 285.12 1710.72 P&M-055
Vibratory road roller 8-10 tonne capacity hour 7.500 1720.00 12900.00 P&M-059
Water tanker6 KL capacity hour 4.000 111.24 444.96 P&M-060
c) Material
Cost of water KL 24.000 167.07 4009.64 M-189
d) Overhead charges @ 0.1 on (a+b+c) 1945.58
e) Contractor's profit @ 0.1 on (a+b+c+d) 2140.14
Cost for 600 cum = (a+b+c+d+e) 23541.53
Rate per sqm = (a+b+c+d+e)/600 39.24
say 39.00
3.20 305 Stripping and Storing Top Soil
Stripping, storing of top soil by road side at 15 m internal and
re-application on embankment slopes, cut slopes and other
areas in localities where the available embankment material
is not conducive to plant growth.
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.200 195.43 39.09 L-12
Mazdoor day 5.000 187.43 937.15 L-13
b) Machinery
Dozer 80 HP @ 100 cum per hour hour 0.100 3135.24 313.52 P&M-014
c) Overhead charges @ 0.1 on (a+b) 128.98
d) Contractor's profit @ 0.1 on (a+b+c) 141.87
Cost for 10 cum = (a+b+c+d) 1560.61
Rate per cum = (a+b+c+d)/10 156.06
say 156.00
3.21 Stripping, Storing and Re-laying Top Soil from Borrow
Areas in Agriculture Fields.
Stripping of top soil from borrow areas located in agriculture
fields, storing at a suitable place, spreading and re-laying
after taking the borrow earth to maintain fertility of the
agricultural field, finishing it to the required levels and
satisfaction of the farmer.

Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery
Dozer, 80 HP hour 6.000 3135.24 18811.44 P&M-014
c) Overhead charges @ 0.1 on (a+b) 1920.19
d) Contractor's profit @ 0.1 on (a+b+c) 2112.21
Cost for 300 cum = (a+b+c+d) 23234.34
Rate per cum = (a+b+c+d)/300 77.45
say 77.00
3.22 307 Turfing with Sods
Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of sods
and watering.

Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 195.43 23.45 L-12

96
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor for preparation of ground and fetching of sods day 3.000 187.43 562.29 L-13

b) Machinery
Water tanker including watering for 3 months hour 2.000 111.24 222.48 P&M-060
Tractor-trolley hour 1.000 171.02 171.02 P&M-053
c) Material
Farm yard manure @ 0.18 cum per 100 sqm at site of cum 0.180 528.65 95.16 M-167
work
Cost of water KL 12.000 167.07 2004.82 M-189
d) Overhead charges @ 0.1 on (a+b+c) 307.92
e) Contractor's profit @ 0.1 on (a+b+c+d) 338.71
Cost for 100 sqm = a+b+c+d+e 3725.85
Rate per 100 sqm = (a+b+c+d+e)/100 37.26
say 37.00
3.23 308 Seeding and Mulching
Preparation of seed bed on previously laid top soil,
furnishing and placing of seeds, fertilizer, mulching material,
applying bituminous emulsion at the rate of 0.23 litres per
sqm and laying and fixing jute netting, including watering for
3 months all as per clause 308.

Unit = sqm
Taking output = 240 sqm
a) Labour
Mate day 0.400 195.43 78.17 L-12
Mazdoor day 10.000 187.43 1874.30 L-13
b) Machinery
Water tanker 6 KL capacity including watering for 3 hour 14.000 111.24 1557.36 P&M-060
months
Tractor-trolley hour 2.400 171.02 410.44 P&M-053
c) Material
Seeds kg 3.600 21.93 78.94 M-162
Sludge/Farm yard manure @ 0.18 cum per 100 sqm cum 0.430 528.65 227.32 M-167
Bitumen Emulsion litre 55.200 40.114 2214.31 M-077
Jute netting, open weave, 2.5 cm square opening sqm 264.000 28.71 7580.72 M-121
Cost of water for 3 months KL 84.000 167.07 14033.73 M-189
d) Overhead charges @ 0.1 on (a+b+c) 2805.53
e) Contractor's profit @ 0.1 on (a+b+c+d) 3086.08
Cost for 240 sqm = a+b+c+d+e 33946.91
Rate per sqm = (a+b+c+d+e)/240 141.45
say 141.00

3.24 309 Surface Drains in Soil


Construction of unlined surface drains of average cross
sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions to the requirement of clause 301 and
309. Excavated material to be used in embankment within a
lead of 50 metres (average lead 25 metres)

Unit = metre
Taking output = 10 metres
A Mechanical means
a) Labour
Mate day 0.010 195.43 1.95 L-12
Mazdoor for dressing of bed and side of drain day 0.250 187.43 46.86 L-13
b) Machinery
Hydraulic Excavator 0.3 cum bucket capacity @ 30 hour 0.330 1516.32 500.39 P&M-026
metres per hour

97
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Overhead charges @ 0.1 on (a+b) 54.92
d) Contractor's profit @ 0.1 on (a+b+c) 60.41
Cost for 10 metres = a+b+c+d 664.53
Rate per metre = (a+b+c+d)/10 66.45
say 66.00
3.24 B Manual Means
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Overhead charges @ 0.1 on (a) 39.05
c) Contractor's profit @ 0.1 on (a+b) 42.95
Cost for 10 metres = a+b+c 472.50
Rate per metre = (a+b+c)/10 47.25
say 47.00
Note Where lining of drain is provided, quantity shall be worked
out based on approved design and drawing and priced on
rate of cement concrete of approved grade or stone/brick
masonry as the case may be.
3.25 309 Surface Drains in Ordinary Rock
Construction of unlined surface drain of average cross
sectional area 0.4 sqm in ordinary rock to specified lines,
grades, levels and dimensions as per approved design and
to the requirement of clause 301 to 309. Excavated material
to be used in embankment at site.

Unit = metre
Taking output = 10 metres
A Mechanical Means
a) Labour
Mate day 0.020 195.43 3.91 L-12
Mazdoor for dressing of bed and side of drain day 0.500 187.43 93.72 L-13
b) Machinery
Hydraulic Excavator 0.3 cum bucket capacity @ 15 hour 0.670 1516.32 1015.93 P&M-026
metres per hour
c) Overhead charges @ 0.1 on (a+b) 111.36
d) Contractor's profit @ 0.1 on (a+b+c) 122.49
Cost for 10 metres = a+b+c+d 1347.41
Rate per metre = (a+b+c+d)/10 134.74
say 135.00
3.25 B Manual Means
a) Labour
Mate day 0.120 195.43 23.45 L-12
Mazdoor day 3.000 187.43 562.29 L-13
b) Overhead charges @ 0.1 on (a) 58.57
c) Contractor's profit @ 0.1 on (a+b) 64.43
Cost for 10 metres = a+b+c 708.75
Rate per metre = (a+b+c)/10 70.87
say 71.00
3.26 309 Surface Drains in Hard Rock
Rate per metre may be worked out based on quantity of
hard rock as per design.
For rate of hard rock cutting, refer relevant item in this
chapter
3.27 309 Sub-Surface Drains with Perforated Pipe

98
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Construction of subsurface drain with perforated pipe of 100
mm internal diameter of metal/ asbestos cement/ cement
concrete/PVC, closely jointed, perforations ranging from 3
mm to 6 mm depending upon size of material surrounding
the pipe, with 150 mm bedding below the pipe and 300 mm
cushion above the pipe, cross section of excavation 450 x
550 mm. Excavated material to be utilised in roadway at site.

Unit = metre
Taking output = 10 metres
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor for excavation and back filling day 2.000 187.43 374.86 L-13
c) Material
Perforated pipe of cement concrete, internal dia 100 metre 10.000 107.89 1078.86 M-135
mm
Crushed stone as per table 300-3 cum 2.400 630.22 1512.52 M-012
d) Overhead charges @ 0.1 on (a+b+c) 297.41
e) Contractor's profit @ 0.1 on (a+b+c+d) 327.15
Cost for 10 metres = a+b+c+d+e 3598.61
Rate per metre = (a+b+c+d+e)/10 359.86
say 360.00

Note Type of pipe may be modified depending upon provision in


design.
3.28 309 Aggregate Sub-Surface Drains
Construction of aggregate sub surface drain 300 mm x 450
mm with aggregates conforming to table 300-4, excavated
material to be utilised in roadway.
Unit = metre
Taking output = 10 metres
a) Labour
Mate day 0.020 195.43 3.91 L-12
Mazdoor for excavation and back filling with aggregates day 1.500 187.43 281.15 L-13

b) Material
Crushed stone as per table 300-3 cum 1.350 630.22 850.79 M-012
c) Overhead charges @ 0.1 on (a+b) 113.58
d) Contractor's profit @ 0.1 on (a+b+c) 124.94
Cost for 10 metres = a+b+c+d 1374.37
Rate per metre = (a+b+c+d)/10 137.44
say 137.00

3.29 309 Underground Drain at Edge of Pavement


Construction of an underground drain 1 m x 1 m (inside
dimensions) lined with RCC-20 cm thick and covered with
RCC slab10 cm in thickness on urban roads.

Unit = Running metre


Taking output = one metre
a) Earthwork in soil cum 1.500 43.00 64.50 Item No.
3.13
b) RCC work M-20 cum 0.495 4746.00 2349.27 Item 12.8
(C) RCC
Rate per metre = (a+b) 2413.77
Rates for these items may be taken from chapters on earth say 2414.00
work and substructures respectively.

99
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.30 310 Preparation and Surface Treatment of Formation.
Preparation and surface treatment of formation by removing
mud and slurry, watering to the extent needed to maintain
the desired moisture content, trimming to the required line,
grade, profile and rolling with 8-10 tonne smooth wheeled
roller, complete as per clause 310.
Unit = sqm
Taking output = 3500sqm
a) Labour
Mate day 0.280 195.43 54.72 L-12
Mazdoor day 6.000 187.43 1124.58 L-13
Mazdoor skilled day 1.000 218.57 218.57 L-15
b) Machinery
Smooth 3 wheeled steel roller 8-10 tonnes hour 3.000 649.00 1947.00 P&M-044
Water tanker 6 KL, one trip per hour hour 3.000 111.24 333.72 P&M-060
c) Material
Cost of water KL 18.000 167.07 3007.23 M-189
d) Overhead charges @ 0.1 on (a+b+c) 668.58
e) Contractor's profit @ 0.1 on (a+b+c+d) 735.44
Cost for 3500 sqm = a+b+c+d+e 8089.84
Rate per sqm = (a+b+c+d+e)/3500 2.31
say 2.00

3.31 313 Construction of Rock fill Embankment


Construction of rock fill embankment with broken hard rock
fragments of size not exceeding 300 mm laid in layers not
exceeding 500 mm thick including filling of surface voids with
stone spalls, blinding top layer with granular material, rolled
with vibratory road roller, all complete as per clause 313.

Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor day 1.500 187.43 281.15 L-13
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3135.24 1567.62 P&M-014
Vibratory road roller 8-10 tonnes @ 100 cum per hour hour 1.000 1720.00 1720.00 P&M-059

Water tanker 6 KL, one trip per hour hour 2.000 111.24 222.48 P&M-060
c) Material
Cost of water KL 12.000 167.07 2004.82 M-189
d) Overhead charges @ 0.1 on (a+b+c) 580.39
e) Contractor's profit @ 0.1 on (a+b+c+d) 638.43
Cost for 100 cum = a+b+c+d+e 7022.70
Rate per cum = (a+b+c+d+e)/100 70.23
say 70.00

Note It is assumed that rock is available locally at site from


roadway cutting. In case, portion of the rock requires
breaking to acceptable size of 300 mm, breaking charges
will have to be added.
EARTH WORK ON HILL ROAD
3.32 301 Excavation in Hill Area in Soil by Mechanical Means
Excavation in soil in hilly area by mechanical means
including cutting and trimming of side slopes and disposing
of excavated earth with all lifts and lead upto 1000 metres.

100
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Unit = cum
Taking output = 260 cum
a) Labour
Mate day 0.240 195.43 46.90 L-12
Mazdoor for trimming slopes and helping in excavation day 6.000 187.43 1124.58 L-13
etc.
b) Machinery
Dozer 80 HP (D-80 A 12)@ 43.28 cum per hour hour 6.000 3135.24 18811.44 P&M-014
Front end loader hour 6.000 1148.00 6888.00 P&M-017
Tipper 5.5cum capacity, 4 trips per hour. hour 12.000 846.00 10152.00 P&M-048
c) Overhead charges @ 0.1 on (a+b) 3702.29
d) Contractor's profit @ 0.1 on (a+b+c) 4072.52
Cost for 260 cum = a+b+c+d 44797.74
Rate per cum = (a+b+c+d)/260 172.30
say 172.00

Note In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth shall be disposed off on the valley side.

3.33 301 Excavation in Hilly Area in Ordinary Rock by


Mechanical Means not Requiring Blasting.
Excavation in hilly area in ordinary rock not requiring blasting
by mechanical means including cutting and trimming of
slopes and disposal of cut material with all lift and lead upto
1000 metres.
Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.320 195.43 62.54 L-12
Mazdoor day 8.000 187.43 1499.44 L-13
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 6.000 3135.24 18811.44 P&M-014
Front end loader hour 7.000 1148.00 8036.00 P&M-017
Tipper 5.5cum capacity, 4 trips per hour. hour 7.000 846.00 5922.00 P&M-048
c) Overhead charges @ 0.1 on (a+b) 3433.14
d) Contractor's profit @ 0.1 on (a+b+c) 3776.46
Cost for 170 cum = a+b+c+d 41541.02
Rate per cum = (a+b+c+d)/170 244.36
say 244.00

Note In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.

3.34 301 Excavation in Hilly Areas in Hard Rock Requiring


Blasting
Excavation in hilly areas in hard rock requiring blasting, by
mechanical means including trimming of slopes and disposal
of cut material with all lifts and lead upto 1000 metres.

Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.490 195.43 95.76 L-12
Mazdoor day 10.000 187.43 1874.30 L-13

101
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Driller day 2.000 218.57 437.14 L-06
Blaster day 0.250 304.89 76.22 L-03
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour hour 6.000 3135.24 18811.44 P&M-014
Air compressor 250 cfm with two jack hammer @ 20 hour 5.000 293.76 1468.80 P&M-001
cum per hour
Front end loader hour 7.000 1148.00 8036.00 P&M-017
Tipper 5.5cum capacity, 4 trips per hour. hour 7.000 846.00 5922.00 P&M-048
c) Materials
Gelatine 80 per cent kg 35.000 112.77 3946.99 M-104
Electric Detonators @ 1 Detonator for 2 Gelatine sticks each 140.000 14.27 1997.26 M-094 /100
of 125 gms each
d) Overhead charges @ 0.1 on (a+b+c) 4266.59
e) Contractor's profit @ 0.1 on (a+b+c+d) 4693.25
Cost for 170 cum = a+b+c+d+e 51625.75
Rate per cum = (a+b+c+d+e)/170 303.68
say 304.00

Note In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.

In case of hill roads, the altitude effect comes into play. The
output of men and machines decreases progressively after
2100 m elevation leading to increase in cost . High altitude
effect has been explained in the basic approach.
3.35 Work in Urban Roads
The cost of earth work in urban roads inhabited area will be
comparatively higher due to following reasons:
a) There is mixed traffic on urban roads like slow moving
hand and animal driven carts, rickshaws, cycles, two/ three
wheeler apart from the usual vehicular traffic resulting into
traffic jams. This causes loss of working time which may be
in the range of 10 -15 per cent

b) There is considerable disruption of traffic adversely


affecting the efficiency of the working parties including
machines due to congestion caused by pedestrian traffic,
local road side venders, parking of vehicles by the road side,
encroachments by the shopkeepers and local shops who
make use of the berms of the road in front of these shops
and unauthorised conversion of road berms into mini local
market The output of manpower and machines is
substantially reduced due to factors mentioned above.

c) Cost of living in urban areas is comparatively more


resulting into higher wages.
d) At times, work is executed during night time due to
heavy traffic during day time. This involves extra expenditure
by way of making arrangement for lighting and special
transport for working parties due to odd hour

In the light of above, the authorities engaged in preparing


the cost estimates may exercise their judgment and cater for
the additional cost to the extent of 2 to 3 per cent, keeping in
view the severity of factors mentioned above. Supporting
details for the extra cost based on the actual conditions in
specific cases will have to give in justification.

3.36 Suggest Embankment Construction with Flyash/Pond ash


ive available from coal or lignite burning Thermal Plants
as waste material.

102
Analysis of Rate RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Construction of embankment with Flyash conforming to table
1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning
thermal power stations as waste material, spread and
compacted in layer of 200mm thickness each at OMC, all as
specified in IRC: SP: 58-2001 and as per approved plans.

Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.160 195.43 31.27 L-12
Mazdoor day 4.000 187.43 749.72 L-13
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 hour 6.000 1516.32 9097.92 P&M-026
cum/hour
Tipper 10Tcapacity flyash 360 x 1.2 = 432 tonnes tonne.km 432 x L 2.68 1157.07 Lead =1 km
& P&M-047
Add 10 per cent of cost of carriagefor loading and 115.71
unloading
Dozer 80 HP for spreading @ 200 cum/hour hour 1.800 3135.24 5643.43 P&M-014
Motor Grader for grading @ 100 cum/hour hour 3.600 2450.00 8820.00 P&M-032
Water tanker6 KL capacity hour 12.000 111.24 1334.88 P&M-060
Vibratory Roller 8-10 tonne @ 100 cum/hour hour 3.600 1720.00 6192.00 P&M-059
c) Overhead charges @ 0.1 on (a+b) 3314.20
d) Contractor's profit @ 0.1 on (a+b+c) 3645.62
Cost for 360 cum = a+b+c+d 40101.82
Rate per cum = (a+b+c+d)/360 111.39
say 111.00

Note 1.As flyash is available free of cost as waste material from


Thermal Plants, cost of material has not been added.
2.The earth cover on sides and intermediate layers of earth
sandwiching the flyash have not been included in this
analysis. The same are required to be provided as per
approved design and priced separately as embankment
construction.

103
Analysis of Rate RCD/SOR

CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.1 401 Granular Sub-Base with Close Graded Material (Table:-
400-1)
A Plant Mix Method
Construction of granular sub-base by providing close graded
Material, mixing in a mechanical mix plant at OMC, carriage of
mixed Material to work site, spreading in uniform layers with
motor grader on prepared surface and compacting with
vibratory power roller to achieve the desired density, complete
as per clause 401

Unit = cum
Taking output = 225 cum (450 tonne)
a) Labour
Mate day 0.400 195.43 78.17 L-12
Mazdoor skilled day 2.000 218.57 437.14 L-15
Mazdoor day 8.000 187.43 1499.44 L-13
b) Machinery
Wet mix plant @ 75 tonne capacity per hour hour 6.000 2419.00 14514.00 P&M-094
Electric generator 125 KVA hour 6.000 2211.00 13266.00 P&M-018
Water tanker 6 KL capacity 5 km lead with one tripper hour 4.500 111.24 500.58 P&M-060
hour
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Tipper 10 tonne tonne.km 450 x L 2.68 1205.28 Lead =1 km &
P&M-047
Add 10 per cent of cost of carriage to cover loading and 120.53
unloading
Motor Grader 110 HP hour 6.000 2450.00 14700.00 P&M-032
Vibratory roller 8-10 t hour 6.000 1720.00 10320.00 P&M-059
c) Material
Close graded Granular sub-base Material as per table 400-1

For Grading-I Material


53 mm to 9.5 mm @ 50 per cent cum 144.000 766.35 110353.91 M-013
9.5 mm to 2.36 mm @ 20 per cent cum 57.000 648.35 36956.21 M-017
2.36 mm below @ 30 per cent cum 86.400 403.33 34847.63 M-020
Cost of water KL 27.000 167.07 4510.84 M-189
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 100.800 823.07 82965.26 M-015
9.5 mm to 2.36 mm @ 25 per cent cum 72.000 648.35 46681.53 M-017
2.36 mm below @ 40 per cent cum 115.200 403.33 46463.50 M-020
Cost of water KL 27.000 167.07 4510.84 M-189
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 35 per cent cum 100.800 724.27 73006.48 M-016
4.75 mm to 2.36 mm @ 12.5 per cent cum 36.000 494.08 17787.00 M-018
2.36 mm below @ 52.5 per cent cum 151.200 403.33 60983.34 M-020
Cost of water KL 27.000 167.07 4510.84 M-189
4.1A (i) Rate per cum for grading-I Material
d) Overhead charges @ 0.1 on (a+b+c) 25019.77
e) Contractor's profit @ 0.1 on (a+b+c+d) 27521.75
Cost for 225 cum = a+b+c+d+e 302739.25
Rate per cum = (a+b+c+d+e)/225 1345.51
say 1346.00

4.1A (ii) Rate per cum for grading-II Material


d) Overhead charges @ 0.1 on (a+b+c) 24415.03
e) Contractor's profit @ 0.1 on (a+b+c+d) 26856.53
Cost for 225 cum = a+b+c+d+e 295421.83
Rate per cum = (a+b+c+d+e)/225 1312.99
say 1313.00
4.1A (iii) Rate per cum for grading-III Material
d) Overhead charges @ 0.1 on (a+b+c) 21981.68
e) Contractor's profit @ 0.1 on (a+b+c+d) 24179.85
Cost for 225 cum = a+b+c+d+e 265978.33
Rate per cum = (a+b+c+d+e)/225 1182.13
say 1182.00

103
Analysis of Rate RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note Any one of the grading for material may be adopted as per
design
4.1 B By Mix in Place Method
Construction of granular sub-base by providing close graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.480 195.43 93.81 L-12
Mazdoor skilled day 2.000 218.57 437.14 L-15
Mazdoor unskilled day 10.000 187.43 1874.30 L-13
b) Machinery
Motor Grader 110 HP @ 50 cum hour 6.000 2450.00 14700.00 P&M-032
Vibratory roller 8 -10 tonne hour 6.000 1720.00 10320.00 P&M-059
Tractor - Rotavator hour 12.000 227.88 2734.56 P&M-054
Water tanker 6 KL capacity hour 3.000 111.24 333.72 P&M-060
c) Material
Close graded Granular sub-base Material as per table 400-1

For Grading-I Material


53 mm to 9.5 mm @ 50 per cent cum 192.000 766.35 147138.55 M-013
9.5 mm to 2.36 mm @ 20 per cent cum 76.000 648.35 49274.94 M-017
2.36 mm below @ 30 per cent cum 115.200 403.33 46463.50 M-020
Cost of water KL 18.000 167.07 3007.23 M-189
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 134.400 823.07 110620.35 M-015
9.5 mm to 2.36 mm @ 25 per cent cum 96.000 648.35 62242.04 M-017
2.36 mm below @ 40 per cent cum 153.600 403.33 61951.33 M-020
Cost of water KL 18.000 167.07 3007.23 M-189
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 35 per cent cum 134.400 724.27 97341.97 M-016
4.75 mm to 2.36 mm @ 12.5 per cent cum 48.000 494.08 23716.00 M-018
2.36 mm below @ 52.5 per cent cum 201.600 403.33 81311.13 M-020
Cost of water KL 18.000 167.07 3007.23 M-189
4.1B (i) Rate per cum for grading-I Material
d) Overhead charges @ 0.1 on (a+b+c) 27637.77
e) Contractor's profit @ 0.1 on (a+b+c+d) 30401.55
Cost for 300 cum = a+b+c+d+e 334417.07
Rate per cum = (a+b+c+d+e)/300 1114.72
say 1115.00
4.1B (ii) Rate per cum for grading-II Material
d) Overhead charges @ 0.1 on (a+b+c) 26831.45
e) Contractor's profit @ 0.1 on (a+b+c+d) 29514.59
Cost for 300 cum = a+b+c+d+e 324660.52
Rate per cum = (a+b+c+d+e)/300 1082.20
say 1082.00
4.1B (iii) Rate per cum for grading-III Material
d) Overhead charges @ 0.1 on (a+b+c) 23586.99
e) Contractor's profit @ 0.1 on (a+b+c+d) 25945.68
Cost for 300 cum = a+b+c+d+e 285402.52
Rate per cum = (a+b+c+d+e)/300 951.34
say 951.00
Note Any one of the grading for material may be adopted as per
design
4.2 401 Granular Sub-Base with Coarse Graded Material (Table:-
400- 2)

104
Analysis of Rate RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Construction of granular sub-base by providing coarse graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401.

Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.400 195.43 78.17 L-12
Mazdoor skilled day 2.000 218.57 437.14 L-15
Mazdoor day 8.000 187.43 1499.44 L-13
b) Machinery
Mortar Grader 110 HP @ 50 cum per hour hour 6.000 2450.00 14700.00 P&M-032
Vibratory roller 8 -10 tonne hour 6.000 1720.00 10320.00 P&M-059
Water tanker 6 KL capacity hour 3.000 111.24 333.72 P&M-060
c) Material
For coarse graded Granular sub-base Materials per table 400-
2
For grading-I Material
53 mm to 26.5 mm @ 35 per cent cum 134.400 681.31 91568.03 M-029
26.5 mm to 4.75 mm @ 45 per cent cum 172.800 731.42 126388.94 M-026
2.36 mm below @ 20 per cent (Coarse Sand) cum 76.800 244.51 18778.28 M-022
Cost of water KL 18.000 167.07 3007.23 M-189
OR
For Grading-II Material
26.5 mm to 4.75 mm @ 75 per cent cum 288.000 731.42 210648.24 M-026
2.36 mm below @ 25 per cent cum 96.000 244.51 23472.84 M-022
Cost of water KL 18.000 167.07 3007.23 M-189
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 66 per cent cum 255.000 764.37 194915.04 M-025
2.36 mm below @ 34 per cent cum 129.000 244.51 31541.64 M-022
Cost of water KL 18.000 167.07 3007.23 M-189
4.2 (i) Rate per cum for grading-I Material
d) Overhead charges @ 0.1 on (a+b+c) 26711.09
e) Contractor's profit @ 0.1 on (a+b+c+d) 29382.20
Cost for 300 cum = a+b+c+d+e 323204.25
Rate per cum = (a+b+c+d+e)/300 1077.35
say 1077.00
4.2 (ii) Rate per cum for grading-II Material
d) Overhead charges @ 0.1 on (a+b+c) 26449.68
e) Contractor's profit @ 0.1 on (a+b+c+d) 29094.65
Cost for 300 cum = a+b+c+d+e 320041.11
Rate per cum = (a+b+c+d+e)/300 1066.80
say 1067.00
4.2 (iii) Rate per cum for grading-III Material
d) Overhead charges @ 0.1 on (a+b+c) 25683.24
e) Contractor's profit @ 0.1 on (a+b+c+d) 28251.56
Cost for 300 cum = a+b+c+d+e 310767.17
Rate per cum = (a+b+c+d+e)/300 1035.89
say 1036.00
Note Any one of the grading for material may be adopted as per
design
4.3 402 Lime Stabilisation for Improving Sub-grade
Laying and spreading available soil in the sub-grade on a
prepared surface, pulverising, mixing the spread soil in place
with rotavator with 3 per cent slaked lime having minimum
content of 70 per cent of CaO, grading with motor grader and
compacting with the road roller at OMC to the desired density
to form a layer of improved sub grade

Unit = cum
Taking output = 300 cum (525 tonne)

105
Analysis of Rate RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
A By Mechanical Means
a) Labour
Mate day 0.360 195.43 70.35 L-12
Skilled mazdoor for alignment and geometrics day 1.000 218.57 218.57 L-15
Mazdoor for spraying lime day 8.000 187.43 1499.44 L-13
b) Machinery
Tractor with ripper and rotavator attachments @ 60 cum hour 12.000 285.12 3421.44 P&M-055
per hour for ripping and 25 cum per hour for mixing

Motor Grader 110 HP @ 50 cum per hour hour 6.000 2450.00 14700.00 P&M-032
Vibratory roller 8 - 10 tonne capacity hour 6.00x0.65* 1720.00 6708.00 P&M-059
Water tanker 6 KL capacity hour 12.000 111.24 1334.88 P&M-060
c) Material
Lime at site tonne 15.750 4427.31 69730.10 M-188
Cost of water KL 72.000 167.07 12028.91 M-189
d) Overhead charges @ 0.1 on (a+b+c) 10971.17
e) Contractor's profit @ 0.1 on (a+b+c+d) 12068.29
Cost for 300 cum= a+b+c+d+e 132751.15
Rate per cum =( a+b+c+d+e)/300 442.50
say 443.00
Note * Though vibratory roller is required only for 3 hours as per
norms, but the same has to be available at site for 6 hours as
other machines for spreading and mixing will take 6 hours. The
usage rates of roller have been multiplied with a factor of 0.65.

4.3 B By Manual Means


Unit = cum
Taking output = 150 cum (263 tonnes)
a) Labour
Mate day 1.440 195.43 281.42 L-12
Mazdoor skilled day 1.000 218.57 218.57 L-15
Mazdoor day 35.000 187.43 6560.05 L-13
b) Machinery
Vibratory roller 8 - 10 tonne @ 60 cum per hour hour 2.500 1720.00 4300.00 P&M-059
Water tanker 6 KL capacity hour 6.000 111.24 667.44 P&M-060
c) Material
Lime at site tonne 8.000 4427.31 35418.46 M-188
Cost of water KL 36.000 167.07 6014.46 M-189
d) Overhead charges @ 0.1 on (a+b+c) 5346.04
e) Contractor's profit @ 0.1 on (a+b+c+d) 5880.64
Cost for 150 cum= a+b+c+d+e 64687.08
Rate per cum =( a+b+c+d+e)/150 431.25
say 431.00
4.4 402 Lime Treated Soil for Sub- Base
Providing, laying and spreading soil on a prepared sub grade,
pulverising, mixing the spread soil in place with rotavator with
3 per cent slaked lime with minimum content of 70 per cent
of CaO, grading with motor grader and compacting with the
road roller at OMC to achieve at least 98 per cent of the max
dry density to form a layer of sub base.

Unit = cum
Taking output = 300 cum (525 tonnes)
a) Labour
Mate day 0.480 195.43 93.81 L-12
Mazdoor skilled day 2.000 218.57 437.14 L-15
Mazdoor day 10.000 187.43 1874.30 L-13
b) Machinery
Excavator 0.90 cum bucket capacity hour 6.000 1516.32 9097.92 P&M-026
Tipper for carriage of soil tonne.km 525 x L 2.68 1406.16 Lead =1 km &
P&M-047
Add 10 per cent of cost of carriage to cover cost of 140.62
loading and unloading
Motor Grader 110 HP @ 50 cum per hour hour 6.000 2450.00 14700.00 P&M-032

106
Analysis of Rate RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Vibratory roller 8 - 10 tonne hour 6.000 1720.00 10320.00 P&M-059
Tractor with Rotavator and blade @ 25 cum per hour hour 12.000 227.88 2734.56 P&M-054
Water tanker 6 KL capacity hour 12.000 111.24 1334.88 P&M-060
c) Material
Lime at site tonne 15.750 4427.31 69730.10 M-188
Cost of water KL 72.000 167.07 12028.91 M-189
d) Overhead charges @ 0.1 on (a+b+c) 12389.84
e) Contractor's profit @ 0.1 on (a+b+c+d) 13628.82
Cost for 300 cum = a+b+c+d+e 149917.06
Rate per cum= (a+b+c+d+e)/300 499.72
say 500.00
4.5 403 Cement Treated Soil Sub Base/ Base
Providing, laying and spreading soil on a prepared sub grade,
pulverising, adding the designed quantity of cement to the
spread soil, mixing in place with rotavator, grading with the
motor grader and compacting with the road roller at OMC to
achieve the desired unconfined compressive strength and to
form a layer of sub-base/base.

Unit = cum
Taking output = 300 cum (525 tonnes)
For 4 per cent quantity of cement by weight of soil
a) Labour
Mate day 0.480 195.43 93.81 L-12
Mazdoor skilled day 2.000 218.57 437.14 L-15
Mazdoor day 10.000 187.43 1874.30 L-13
b) Machinery
Excavator 0.90 cum bucket capacity hour 6.000 1516.32 9097.92 P&M-026
Tipper for carriage of soil tonne.km 525 x L 2.68 1406.16 Lead =1 km &
P&M-047
Add 10 per cent of cost of carriage to cover cost of 140.62
loading and unloading
Motor Grader 110 HP @ 50 cum per hour hour 6.000 2450.00 14700.00 P&M-032
Vibratory roller 8 - 10 tonne hour 6.000 1720.00 10320.00 P&M-059
Tractor with Rotavator and blade @ 25 cum per hour hour 12.000 227.88 2734.56 P&M-054
Water tanker 6 KL capacity hour 12.000 111.24 1334.88 P&M-060
c) Material
Cement at site (@ 4 per cent of 525 tonne) tonne 21.000 5982.46 125631.58 M-081
Cost of water KL 72.000 167.07 12028.91 M-189
d) Overhead charges @ 0.1 on (a+b+c) 17979.99
e) Contractor's profit @ 0.1 on (a+b+c+d) 19777.99
Cost for 300 cum = a+b+c+d+e 217557.85
Rate per cum= (a+b+c+d+e)/300 725.19
say 725.00
4.6 403 Cement Treated Crushed Rock or combination as per
clause 403.2 and table 400.4in Sub base/ Base
Providing, laying and spreading Material on a prepared sub
grade, adding the designed quantity of cement to the spread
Material, mixing in place with rotavator, grading with the motor
grader and compacting with the road roller at OMC to achieve
the desired unconfined compressive strength and to form a
layer of sub-base/base.

Unit = cum
Taking output = 300 cum (600 tonnes)
Quantity of cement assumed as 4 per cent of quantity
of crushed rock by weight.
a) Labour
Mate day 0.480 195.43 93.81 L-12
Mazdoor skilled day 2.000 218.57 437.14 L-15
Mazdoor day 10.000 187.43 1874.30 L-13
b) Machinery
Motor Grader 110 HP @ 50 cum per hour hour 6.000 2450.00 14700.00 P&M-032
Vibratory roller 8 - 10 tonne hour 6.000 1720.00 10320.00 P&M-059
Tractor with Rotavator and blade @ 25 cum per hour hour 12.000 227.88 2734.56 P&M-054

107
Analysis of Rate RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Water tanker 6 KL capacity hour 10.000 111.24 1112.40 P&M-060
c) Material
Cement at site @ 4 per cent by weight of crushed tonne 24.000 5982.46 143578.95 M-081
aggregate (600 tonne)
Grading of material for sub-base course
37.5 mm to 9.5 mm @ 55 per cent cum 211.200 838.84 177162.31 M-014
9.5 mm to 4.75 mm @ 20 per cent cum 76.800 764.37 58703.82 M-025
4.75 mm to 75 micron @ 25 per cent cum 96.000 471.39 45253.90 M-019
Cost of water KL 60.000 167.07 10024.09 M-189
or
Grading of material for Base course
37.5 mm to 9.5 mm @ 32.5 per cent cum 124.800 731.42 91280.90 M-028
9.5 mm to 4.75 mm @ 5 per cent cum 19.200 764.37 14675.96 M-025
4.75 mm to 75 micron @ 62.5 per cent cum 240.000 267.20 64127.38 M-023
Cost of water KL 60.000 167.07 10024.09 M-189
4.6 (i) For Sub-Base course
d) Overhead charges @ 0.1 on (a+b+c) 46599.53
e) Contractor's profit @ 0.1 on (a+b+c+d) 51259.48
Cost for 300 cum = a+b+c+d+e 563854.28
Rate per cum = (a+b+c+d+e)/300 1879.51
say 1880.00
4.6 (ii) For Base course
d) Overhead charges @ 0.1 on (a+b+c) 35495.95
e) Contractor's profit @ 0.1 on (a+b+c+d) 39045.54
Cost for 300 cum = a+b+c+d+e 429500.97
Rate per cum = (a+b+c+d+e)/300 1431.67
say 1432.00
Note Quantities of aggregates provided under 'c' above are
uncompacted quantities.
4.7 404.3.1 Making 50 mm x 50 mm Furrows
Making 50 mm x 50 mm furrows, 25mm/ 50mm deep, 450 C to
the center line of the road and at one metre interval in the
existing thin bituminous wearing coarse including sweeping
and disposal of excavated material within 1000 metres lead
Unit = sqm
Taking output = 30 m x 7 m = 210 sqm
(i) 25mm deep furrow cutting
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery
Tractor-trolley hour 0.200 171.02 34.20 P&M-053
c) Overhead charges @ 0.1 on (a+b) 42.47
d) Contractor's profit @ 0.1 on (a+b+c) 46.72
Cost for 210 sqm= a+b+c+d 513.88
Rate per sqm =(a+b+c+d)/210 2.45
say 2.40
(ii) 50mm deep furrow cutting
a) Labour
Mate day 0.160 195.43 31.27 L-12
Mazdoor day 4.000 187.43 749.72 L-13
b) Machinery
Tractor-trolley hour 0.400 171.02 68.41 P&M-053
c) Overhead charges @ 0.1 on (a+b) 84.94
d) Contractor's profit @ 0.1 on (a+b+c) 93.43
Cost for 210 sqm= a+b+c+d 1027.77
Rate per sqm =(a+b+c+d)/210 4.89
say 4.90
4.8 404.3.2 Inverted Choke

108
Analysis of Rate RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Construction of inverted choke by providing, laying, spreading
and compacting screening B type/ coarse sand of specified
grade in uniform layer on a prepared surface with motor grader
and compacting with power roller etc

Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.920 195.43 179.80 L-12
Mazdoor skilled day 2.000 218.57 437.14 L-15
Mazdoor day 21.000 187.43 3936.03 L-13
b) Machinery
Motor Grader 110 HP hour 6.000 2450.00 14700.00 P&M-032
Vibratory roller 8-10 tonnes @ 60 cum per hour hour 6.000 1720.00 10320.00 P&M-059
Water tanker 6 KL capacity hour 18.000 111.24 2002.32 P&M-060
c) Material
Screening type 'B' or coarse sand cum 720.000 209.13 150573.81 M-004
Cost of water KL 108.000 167.07 18043.37 M-189
d) Overhead charges @ 0.1 on (a+b+c) 20019.25
e) Contractor's profit @ 0.1 on (a+b+c+d) 22021.17
Cost for 600 cum = a+b+c+d+e 242232.89
Rate per cum = ( a+b+c+d+e)/600 403.72
say 404.00
4.9 404 Water Bound Macadam
Providing, laying, spreading and compacting stone aggregates
of specific sizes to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling
with 3 wheeled steel/ vibratory roller 8-10 tonnes in stages to
proper grade and camber, applying and brooming requisite
type of screening/ binding Materials to fill up the interstices of
coarse aggregate, watering and compacting to the required
density.

A By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 10.080 195.43 1969.93 L-12
Mazdoor skilled day 2.000 218.57 437.14 L-15
Mazdoor day 250.000 187.43 46857.50 L-13
b) Machinery

Vibratory roller 8 - 10 tonne @ 60cum per hour hour 6.000 1720.00 10320.00 P&M-059
or
Smooth 3 wheeled steel roller @ 30cum/hour hour 12.000
Water tanker 6 KL capacity hour 24.000 111.24 2669.76 P&M-060
c) Material ( Refer table 400 - 7, 8 & 9 )
4.9A (i) Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for cum 435.600 477.96 208200.49 M-039
compacted thickness of 100 mm

Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm cum 97.200 641.56 62359.56 M-042

OR
Crushable type such as Moorum or Gravel for grading-I cum 108.000 122.64 13244.66 M-007
@ 0.30 cum per 10 sqm

Binding material
Binding Material @ 0.08cum per 10 sqm for grading I cum 28.800 122.64 3531.91 M-007
material
Cost of water KL 144.000 167.07 24057.82 M-189
4.9A (i) (a) Using Screening Crushable type such as Moorum or Gravel
d) Overhead charges @ 0.1 on (a+b+c) 30775.73

109
Analysis of Rate RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Contractor's profit @ 0.1 on (a+b+c+d) 33853.30
Cost for 360 cum = a+b+c+d+e 372386.34
Rate per cum = (a+b+c+d+e)/360 1034.41
say 1034.00
OR
4.9A (i) (b) Using Screening Type-A (13.2mm agg.) with binding material
d) Overhead charges @ 0.1 on (a+b+c) 36040.41
e) Contractor's profit @ 0.1 on (a+b+c+d) 39644.45
Cost for 360 cum = a+b+c+d+e 436088.98
Rate per cum = (a+b+c+d+e)/360 1211.36
say 1211.00
4.9A (ii) Grading-II
Aggregate
Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4 cum 435.600 547.62 238543.51 M-038 / M-036
mm@ 0.91 cum per 10 sqm for compacted thickness of
75 mm

Stone Screening
Type A 13.2 mm for grading-II @ 0.12 cum per 10 sqm cum 57.600 641.56 36953.82 M-042

OR
Crushable type such as Moorum or Gravel for grading II cum 105.590 122.64 12949.10 M-007
&III @ 0.22 cum per 10 sqm
OR
Type B11.2 mm for grading-III @ 0.20 cum per 10 sqm cum 96.010 516.77 49615.28 M-041

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 122.64 3531.91 M-007
material
Cost of water KL 144.000 167.07 24057.82 M-189
4.9A (ii) (a) Using Screening Crushable type such as Moorum or Gravel
d) Overhead charges @ 0.1 on (a+b+c) 33780.48
e) Contractor's profit @ 0.1 on (a+b+c+d) 37158.52
Cost for 360 cum = a+b+c+d+e 408743.77
Rate per cum = (a+b+c+d+e)/360 1135.40
say 1135.00
OR
4.9A (ii) (b) Using Screening Type-A (13.2mm agg.) with binding material
d) Overhead charges @ 0.1 on (a+b+c) 36534.14
e) Contractor's profit @ 0.1 on (a+b+c+d) 40187.55
Cost for 360 cum = a+b+c+d+e 442063.08
Rate per cum = (a+b+c+d+e)/360 1227.95
say 1228.00
4.9A (ii) (c) Using Screening Type-B (11.2mm agg.) with binding material
d) Overhead charges @ 0.1 on (a+b+c) 37800.29
e) Contractor's profit @ 0.1 on (a+b+c+d) 41580.31
Cost for 360 cum = a+b+c+d+e 457383.45
Rate per cum = (a+b+c+d+e)/360 1270.51
say 1271.00
4.9A (iii) Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm cum 435.600 567.52 247212.94 M-036
for compacted thickness of 75 mm

Stone Screening
Type B 11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.400 516.77 44649.10 M-041

OR
Crushable type such as Moorum or Gravel for grading II cum 105.590 122.64 12949.10 M-007
&III @ 0.22 cum per 10 sqm

Binding material

110
Analysis of Rate RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 122.64 3531.91 M-007
material
Cost of water KL 144.000 167.07 24057.82 M-189
4.9A (a) Using Screening Crushable type such as Moorum or Gravel
(iii)
d) Overhead charges @ 0.1 on (a+b+c) 34647.42
e) Contractor's profit @ 0.1 on (a+b+c+d) 38112.16
Cost for 360 cum = a+b+c+d+e 419233.78
Rate per cum = (a+b+c+d+e)/360 1164.54
say 1165.00
OR
4.9A (b) Using Screening Type-B (11.2mm agg.)
(iii)
d) Overhead charges @ 0.1 on (a+b+c) 38170.61
e) Contractor's profit @ 0.1 on (a+b+c+d) 41987.67
Cost for 360 cum = a+b+c+d+e 461864.39
Rate per cum = (a+b+c+d+e)/360 1282.96
say 1283.00
( Anyone of the aggregate grading, screening and binding
material may be used as per design)
4.9 B By Mechanical Means:
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.680 195.43 132.89 L-12
Mazdoor skilled day 2.000 218.57 437.14 L-15
Mazdoor day 15.000 187.43 2811.45 L-13
b) Machinery
Motor grader 110 HP @ 50cum/hr. for spreading hour 7.200 2450.00 17640.00 P&M-032
Vibratory roller 8-10 tonnes @ 60cum/hr. hour 6.000 1720.00 10320.00 P&M-059
or
Smooth 3 wheeled steel roller @ 30cum/hr. hour 12.000
Water tanker 6 KL capacity hour 24.000 111.24 2669.76 P&M-060
c) Material ( Refer table 400 - 7, 8 & 9 )
4.9B (i) Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for cum 435.600 477.96 208200.49 M-039
compacted thickness of 100 mm

Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm cum 97.200 641.56 62359.56 M-042

OR
Crushable type such as Moorum or Gravel for grading-I cum 108.000 122.64 13244.66 M-007
@ 0.30 cum per 10 sqm

Binding material
Binding Material @ 0.08cum per 10 sqm for grading I cum 28.800 122.64 3531.91 M-007
material
Cost of water KL 144.000 167.07 24057.82 M-189

111
Analysis of Rate RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.9B (i) (a) Using Screening Crushable type such as Moorum or Gravel
d) Overhead charges @ 0.1 on (a+b+c) 27951.42
e) Contractor's profit @ 0.1 on (a+b+c+d) 30746.56
Cost for 360 cum = a+b+c+d+e 338212.19
Rate per cum = (a+b+c+d+e)/360 939.48
say 939.00
OR
4.9B (i) (b) Using Screening Type-A (13.2mm agg.) with binding material
d) Overhead charges @ 0.1 on (a+b+c) 33216.10
e) Contractor's profit @ 0.1 on (a+b+c+d) 36537.71
Cost for 360 cum = a+b+c+d+e 401914.84
Rate per cum = (a+b+c+d+e)/360 1116.43
say 1116.00
4.9B (ii) Grading-II
Aggregate
Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4 cum 435.600 547.62 238543.51 M-038 / M-036
mm@ 0.91 cum per 10 sqm for compacted thickness of
75 mm

Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm cum 57.600 641.56 36953.82 M-042
OR
Crushable type such as Moorum or Gravel for grading II cum 105.590 122.64 12949.10 M-007
&III @ 0.22 cum per 10 sqm
OR
Type B 11.2 mm for grading-III @ 0.20 cum per 10 sqm cum 96.010 516.77 49615.28 M-041

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 122.64 3531.91 M-007
material
Cost of water KL 144.000 167.07 24057.82 M-189
4.9B (ii) (a) Using Screening Crushable type such as Moorum or Gravel
d) Overhead charges @ 0.1 on (a+b+c) 30956.17
e) Contractor's profit @ 0.1 on (a+b+c+d) 34051.78
Cost for 360 cum = a+b+c+d+e 374569.63
Rate per cum = (a+b+c+d+e)/360 1040.47
say 1040.00
OR
4.9B (ii) (b) Using Screening Type-A (13.2mm agg.) with binding material
d) Overhead charges @ 0.1 on (a+b+c) 33709.83
e) Contractor's profit @ 0.1 on (a+b+c+d) 37080.81
Cost for 360 cum = a+b+c+d+e 407888.94
Rate per cum = (a+b+c+d+e)/360 1133.02
say 1133.00
4.9B (ii) (c) Using Screening Type-B (11.2mm agg.) with binding material
d) Overhead charges @ 0.1 on (a+b+c) 34975.98
e) Contractor's profit @ 0.1 on (a+b+c+d) 38473.57
Cost for 360 cum = a+b+c+d+e 423209.31
Rate per cum = (a+b+c+d+e)/360 1175.58
say 1176.00
4.9B (iii) Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm cum 435.600 567.52 247212.94 M-036
for compacted thickness of 75 mm

Stone Screening
Type B 11.2 mm for grading-III @ 0.18 cum per 10 sqm cum 86.400 516.77 44649.10 M-041

OR
Crushable type such as Moorum or Gravel for grading II cum 105.590 122.64 12949.10 M-007
&III @ 0.22 cum per 10 sqm

112
Analysis of Rate RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II cum 28.800 122.64 3531.91 M-007
material
Cost of water KL 144.000 167.07 24057.82 M-189
4.9B (a) Using Screening Crushable type such as Moorum or Gravel
(iii)
d) Overhead charges @ 0.1 on (a+b+c) 31823.11
e) Contractor's profit @ 0.1 on (a+b+c+d) 35005.42
Cost for 360 cum = a+b+c+d+e 385059.64
Rate per cum = (a+b+c+d+e)/360 1069.61
say 1070.00
OR
4.9B (b) Using Screening Type-B (11.2mm agg.) with binding material
(iii)
d) Overhead charges @ 0.1 on (a+b+c) 35346.30
e) Contractor's profit @ 0.1 on (a+b+c+d) 38880.93
Cost for 360 cum = a+b+c+d+e 427690.25
Rate per cum = (a+b+c+d+e)/360 1188.03
say 1188.00
Note As three wheeled smooth rollers are also very commonly
used, the same has been provided as an alternative.
4.10 405 Crushed Cement Concrete Sub-base / Base
Breaking and crushing of material obtained by breaking
damaged cement concrete slabs to size range not exceeding
75 mm as specified in table 400.7 transporting the aggregates
obtained from breaking of cement concrete slabs at a lead of L
km., laying and compacting the same as sub base/ base
course, constructed as WBM to clause 404 except the use of
screening or binding Material.

Unit = cum
Taking output =360 cum
a) Labour
Mate day 4.160 195.43 812.99 L-12
Mazdoor skilled day 2.000 218.57 437.14 L-15
Mazdoor for crushing broken cement concrete day 102.000 187.43 19117.86 L-13
pavement/slabs into aggregate
b) Machinery
Motor Grader,110 HP @ 50 cum/hr. hour 6.000 2450.00 14700.00 P&M-032
Vibratory roller 8 - 10 tonne@ 60 cum per hour hour 6.000 1720.00 10320.00 P&M-059
or
Smooth 3 wheeled steel roller @ 30cum/hr. hour 12.000
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Tipper 10 tonne capacity tonne.km 720 x L 2.68 1928.45 Lead =1 km &
P&M-047
Add 10 per cent of cost of carriage to cover cost of 192.84
loading and unloading
Water tanker 6 KL capacity with 5 km lead @ 1 trip per hour 12.000 111.24 1334.88 P&M-060
hour
c) Material
Material available from dismantled concrete slab after crushing
/ breaking and only carriage is required to be provided

Cost of water KL 72.000 167.07 12028.91 M-189


d) Overhead charges @ 0.1 on (a+b+c) 6776.11
e) Contractor's profit @ 0.1 on (a+b+c+d) 7453.72
Cost for 360 cum = a+b+c+d+e 81990.90
Rate per cum = (a+b+c+d+e)/360 227.75
say 228.00
With Vibratory Roller 228.00
With Smooth 3 wheeled Steel Roller 219.00

113
Analysis of Rate RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note 1. It is assumed that dismantling of concrete slab/pavement
has been considered separately. Hence same is not added in
this analysis. Only labour for crushing the dismantled slab into
aggregate has been added. Carriage from stock pile to work
site has been provided with a lead of L km.

2. In case of breaking of slabs is done locally without


involvement of transportation, the provision of tipper, front end
loader and loading/unloading charges may be deleted.
3. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative.
4.11 405.2 Penetration Coat Over Top Layer of Crushed Cement
Concrete Base
Spraying of bitumen over cleaned dry surface of crushed
cement concrete base at the rate of 25 kg per 10 sqm by a
bitumen pressure distributor, spreading of key aggregates at
the rate of 0.13 cum per 10 sqm by a mechanical gritter and
rolling the surface as per clause 506.3.8

Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate day 0.560 195.43 109.44 L-12
Mazdoor skilled day 2.000 218.57 437.14 L-15
Mazdoor day 12.000 187.43 2249.16 L-13
b) Machinery
Mechanical broom hydraulic @ 1250 sqm per hour hour 6.000 456.00 2736.00 P&M-031
Hydraulic self propelled chips spreader hour 6.000 2423.52 14541.12 P&M-025
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Tipper 10 tonne capacity hour 6.000 846.00 5076.00 P&M-048
Vibratory roller 8 -10 tonnes @ 30 cum per hour hour 6.00x0.65* 1720.00 6708.00 P&M-059
Bitumen pressure distributor @ 1750 sqm per hour hour 4.280 986.04 4220.25 P&M-004
c) Material
Crushed stone aggregate 11.2 mm size cum 97.500 674.15 65729.77 M-051
Bitumen (60-70 grade) tonne 0.250 39879.31 9969.83 M-074
d) Overhead charges @ 0.1 on (a+b+c) 11866.47
e) Contractor's profit @ 0.1 on (a+b+c+d) 13053.12
Cost for 7500 sqm = a+b+c+d+e 143584.30
Rate per sqm = (a+b+c+d+e)/7500 19.14
say 19.10
Note Though vibratory roller is required only for 3 hours as per
norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65.

4.12 406 Wet Mix Macadam


Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix
plant carriage of mixed Material by tipper to site, laying in
uniform layers with paver in sub- base / base course on well
prepared surface and compacting with vibratory roller to
achieve the desired density.

Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate day 0.480 195.43 93.81 L-12
Mazdoor skilled day 2.000 218.57 437.14 L-15
Mazdoor day 10.000 187.43 1874.30 L-13
b) Machinery
Wet mix plant of 75 tonne hourly capacity hour 6.600 2419.00 15965.40 P&M-094
Electric generator 125 KVA hour 6.000 2211.00 13266.00 P&M-018
Front end loader 1 cum capacity hour 6.000 1148.00 6888.00 P&M-017
Paver finisher hour 6.000 1382.00 8292.00 P&M-035
Vibratory roller 8 - 10 tonne hour 6x0.65 1720.00 6708.00 P&M-059
or
Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 12.000

114
Analysis of Rate RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Water tanker 6 KL capacity hour 3.000 111.24 333.72 P&M-060
Tipper tonne.km 495 x L 2.68 1325.81 Lead =1 km &
P&M-047
Add 10 per cent of cost of carriage to cover cost of 132.58
loading and unloading
c) Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent cum 89.100 743.66 66259.93 M-034
22.4 mm to 2.36 mm @ 40 per cent cum 118.800 817.35 97101.25 M-031
2.36 mm to 75 micron@ 30 per cent cum 89.100 244.51 21785.73 M-022
Cost of water KL 18.000 167.07 3007.23 M-189
d) Overhead charges @ 0.1 on (a+b+c) 24347.09
e) Contractor's profit @ 0.1 on (a+b+c+d) 26781.80
Cost for 225 cum = a+b+c+d+e 294599.78
Rate per cum = (a+b+c+d+e)/225 1309.33
say 1309.00
Note 1. Though vibratory roller is required only for 3 hours as per
norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65
2. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative which can be
used if the thickness of individual layer does not exceed 100
mm.
4.13 407 Construction of Median and Island with Soil Taken from
Roadway Cutting
Construction of Median and Island above road level with
approved material deposited at site from roadway cutting and
excavation for drain and foundation of other structures,
spread, graded and compacted as per clause 407
Unit = cum
Taking output =21 cum
a) Labour
Mate day 0.240 195.43 46.90 L-12
Mazdoor day 6.000 187.43 1124.58 L-13
b) Machinery
Water tanker 6 KL with 5 km lead and 1 trip per hour hour 1.000 111.24 111.24 P&M-060
Plate compactor @ 3.5 cum per hour hour 6.000 142.99 857.95 P&M-086
c) Material
Cost of water KL 6.000 167.07 1002.41 M-189
d) Overhead charges @ 0.1 on (a+b+c) 314.31
e) Contractor's profit @ 0.1 on (a+b+c+d) 345.74
Cost for 21 cum = a+b+c+d+e 3803.13
Rate per cum = (a+b+c+d+e)/21 181.10
say 181.00
Note This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case granular
fill is required to be paved, quantities of paving are required to
be calculated as per approved design and paid separately.

4.14 407 Construction of Median and Island with Soil Taken from
Borrow Areas
Construction of median and Island above road level with
approved material brought from borrow pits, spread, sloped
and compacted as per clause 407
Unit = cum
Taking output = 21 cum
a) Labour
Mate day 0.160 195.43 31.27 L-12
Mazdoor day 4.000 187.43 749.72 L-13
b) Machinery
Water tanker with 5 km lead hour 1.000 111.24 111.24 P&M-060
Plate Compactor @ 3.5 cum per hour hour 6.000 142.99 857.95 P&M-086

115
Analysis of Rate RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Hydraulic Excavator1.0 cum bucket capacity @60 cum hour 0.500 1516.32 758.16 P&M-026
per hour
Tipper 10 tonne capacity tonne.km 52.5 x L 2.68 140.62 Lead =1 km &
P&M-047
Add 10 per cent of cost of transportation to cover cost 14.06
of loading and unloading
c) Material
Cost of water KL 6.000 167.07 1002.41 M-189
d) Overhead charges @ 0.1 on (a+b+c) 366.54
e) Contractor's profit @ 0.1 on (a+b+c+d) 403.20
Cost for 21 cum = a+b+c+d+e 4435.17
Rate per cum = (a+b+c+d+e)/ 21 211.20
say 211.00
Note This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case surface
finish is of hard type, the same may be provided separately as
per approved design.

4.15 Construction of Shoulders


A. Earthen Shoulders
The rate as applicable for sub-grade construction may be
adopted.
B. Hard Shoulders
Rate as applicable for sub-base and or base may be adopted
as per approved design.
C. Paved shoulders
The rate may be adopted as applicable for different layers of
pavement depending upon approved design of paved
shoulders.
4.16 409 Footpaths and Separators
Construction of footpath/separator by providing a 150 mm
compacted granular sub base as per clause 401 and 25 mm
thick cement concrete grade M15, over laid with pre-cast
concrete tiles in cement mortar 1:3 including provision of all
drainage arrangements but excluding kerb channel..

Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 1.360 195.43 265.78 L-12
Mason day 4.000 247.19 988.76 L-11
Mazdoor day 30.000 187.43 5622.90 L-13
b) Machinery
Vibratory road roller 8 -10 tonnes @60 cum per hour hour 0.750 1720.00 1290.00 P&M-059
Water tanker 6 KL capacity @ 1 trip per hour hour 2.000 111.24 222.48 P&M-060
Concrete mixer 0.4/0.28 cum per hour hour 6.000 211.68 1270.08 P&M-009
c) Material
i) For Granular sub base material
53 mm to 26.5 mm @ 35 per cent cum 20.790 681.31 14164.43 M-029
26.5 mm to 4.75 mm @ 45 per cent cum 26.730 731.42 19550.79 M-026
2.36 mm below @ 20 per cent cum 11.880 244.51 2904.76 M-022
ii) For cement concrete grade M157.5 cum
Aggregate 12 mm crushed @ 0.9 cum of concrete cum 6.750 777.69 5249.41 M-052
Sand @ 0.45 cum/cum of concrete cum 3.380 209.13 706.86 M-005
Cement tonne 1.880 5982.46 11247.02 M-081
iii) For cement plaster 1:3
Sand cum 3.840 209.13 803.06 M-005
Cement tonne 1.830 5982.46 10947.89 M-081
iv) Pre-cast cement concrete tiles
Tiles size 300 x 300 mm and 25 mm thick each 3300.000 23.18 76496.36 M-184
v) RCC pipes
Pipes 200 mm dia,2.5 m long for drainage metre 22.500 124.65 2804.52 M-137
vi) Cost of water KL 12.000 167.07 2004.82 M-189
d) Overhead charges @ 0.1 on (a+b+c) 15653.99

116
Analysis of Rate RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Contractor's profit @ 0.1 on (a+b+c+d) 17219.39
Cost for 300 sqm = a+b+c+d+e 189413.33
Rate per sqm = (a+b+c+d+e)/300 631.38
say 631.00
4.17 410 Crusher Run Macadam Base
Providing crushed stone aggregate, depositing on a prepared
surface by hauling vehicles, spreading and mixing with a motor
grader, watering and compacting with a vibratory roller to
clause 410 to form a layer of sub-base/Base

Unit = cum
Taking output = 360 cum
A By Mix in Place Method
a) Labour
Mate day 0.480 195.43 93.81 L-12
Mazdoor skilled day 2.000 218.57 437.14 L-15
Mazdoor day 10.000 187.43 1874.30 L-13
b) Machinery
Tractor attached with rotavator @ 25 cum per hour hour 12.000 227.88 2734.56 P&M-054
Motor grader 110 HP hour 6.000 2450.00 14700.00 P&M-032
Vibratory roller 8 -10 tonnes @ 60 cum per hour hour 6.000 1720.00 10320.00 P&M-059
Water tanker 6 KL capacity hour 6.000 111.24 667.44 P&M-060
c) Material
Aggregate at site
i) For 53 mm maximum size
63 mm to 45 mm @ 33 per cent cum 157.460 547.62 86228.33 M-038
22.5 mm to 5.6 mm@ 32 per cent cum 151.060 788.72 119143.67 M-032
Below 5.6 mm @ 35 per cent cum 166.680 221.82 36972.99 M-030
Cost of water KL 36.000 167.07 6014.46 M-189
Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent cum 24.120 743.66 17937.03 M-034
22.4 mm to 5.6 mm@ 50 per cent cum 237.600 788.72 187399.29 M-032
Below 5.6 mm@ 45 per cent cum 213.480 221.82 47354.18 M-030
Cost of water KL 36.000 167.07 6014.46 M-189
4.17A (i) For 53 mm maximum size
d) Overhead charges @ 0.1 on (a+b+c) 27918.67
e) Contractor's profit @ 0.1 on (a+b+c+d) 30710.54
Cost for 360.0cum = a+b+c+d+e 337815.90
Rate per cum = (a+b+c+d+e)/360 938.38
or say 938.00
4.17A (ii) For 45 mm maximum size
d) Overhead charges @ 0.1 on (a+b+c) 28953.22
e) Contractor's profit @ 0.1 on (a+b+c+d) 31848.54
Cost for 360.0cum = a+b+c+d+e 350333.96
Rate per cum = (a+b+c+d+e)/360 973.15
say 973.00
Note Any one of the aggregate grading may be adopted
4.17 B By Mixing Plant :
Unit = cum
Taking output = 225 cum (450 tonnes)
a) Labour
Mate day 0.280 195.43 54.72 L-12
Mazdoor skilled day 1.000 218.57 218.57 L-15
Mazdoor day 6.000 187.43 1124.58 L-13
b) Machinery
Wet mix plant @ 75 tonne per hour hour 6.000 1128.60 6771.60 P&M-093
Electric generator 125 KVA hour 6.000 2211.00 13266.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Motor grader 110 HP hour 6.000 2450.00 14700.00 P&M-032
Vibratory roller 8 - 10 tonne hour 6.000 1720.00 10320.00 P&M-059

117
Analysis of Rate RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Water tanker 6 KL capacity hour 3.000 111.24 333.72 P&M-060
Tipper 10 tonne capacity tonne.km 450 x L 2.68 1205.28 Lead =1 km &
P&M-047
Add 10 per cent of cost of carriage to cover cost of 120.53
loading and unloading
c) Material
Aggregate at site
i) For 53 mm maximum size
63 mm to 45 mm @ 33 per cent cum 98.400 547.62 53885.86 M-038
22.5 mm to 5.6 mm@ 32 per cent cum 94.410 788.72 74462.82 M-032
Below 5.6 mm @ 35 per cent cum 104.180 221.82 23109.23 M-030
Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent cum 15.060 743.66 11199.49 M-034
22.4 mm to 5.6 mm@ 50 per cent cum 148.500 788.72 117124.56 M-032
Below 5.6 mm@ 45 per cent cum 133.430 221.82 29597.47 M-030
Cost of water KL 18.000 167.07 3007.23 M-189
4.17 B (i) For 53 mm maximum size
d) Overhead charges @ 0.1 on (a+b+c) 20646.09
e) Contractor's profit @ 0.1 on (a+b+c+d) 22710.70
Cost for 225 cum = a+b+c+d+e 249817.70
Rate per cum = (a+b+c+d+e)/225 1110.30
say 1110.00
4.17 B (ii) For 45 mm maximum size
d) Overhead charges @ 0.1 on (a+b+c) 21593.17
e) Contractor's profit @ 0.1 on (a+b+c+d) 23752.49
Cost for 225 cum = a+b+c+d+e 261277.41
Rate per cum = (a+b+c+d+e)/225 1161.23
say 1161.00
4.18 Suggest Lime, Flyash Stabilised Soil Sub-Base
ive
Construction of Sub-base using lime - Flyash admixture with
granular soil, free from organic matter/ deleterious material or
clayey silts and low plasticity clays having PI between 5 and
20 and liquid limit less than 25 and commercial dry lime,
slaked at site or pre-slaked with CaO content not less than 50
per cent, Flyash to conform to gradation as per clause 4.3 of
IRC: 88-1984, lime + Flyash content ranging between 10 to 30
per cent, the minimum un-confined compressive strength and
CBR value after 28 days curing and 4 days soaking to be
7.5kg/sq, cm and 25 per cent respectively, all as specified in
IRC: 88-1984.

Unit = cum
Taking output = 480 cum (720 tonnes, density 1.50
t/cum)
Assumptions made
Total mass taken for analysis = 720 t
Lime + Flyash admixture @ 20 per cent = 0.2 x 720=144 t
Soil = 720 -144 = 576 t
576 /1.6 = 360 cum
Lime + Flyash = 144 t
Ratio Lime 4 : Flyash 16
Lime = 29 kg.
Flyash = 115 kg.
a) Labour
Mate day 0.240 195.43 46.90 L-12
Mazdoor day 6.000 187.43 1124.58 L-13
Mazdoor (Skilled) day 1.000 218.57 218.57 L-15
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ hour 6.000 1516.32 9097.92 P&M-026
60cum/hr. for 360 cum soil
Tipper 10T capacity for carriage of soil 576 tonnes tonne.km 578 x L 2.68 1548.12 Lead =1 km &
P&M-047

118
Analysis of Rate RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Tipper 10T capacity for carriage of 115 tonnes Flyash tonne.km 115 x L 2.68 308.02 Lead =1 km &
P&M-047
Tipper 10T capacity for carriage of 29 tonnes of lime from hour 3.000 846.00 2538.00 P&M-048
store to work site
Add 10 per cent of cost of carriage to cover cost of 253.80
loading and unloading
Tractor with disc harrows for pulverisation hour 6.000 171.02 1026.11 P&M-053
Motor Grader 110 HP @ 50 cum per hour for mixing in- hour 9.600 2450.00 23520.00 P&M-032
place and grading
Vibratory roller 8 - 10 tonne hour 6.000 1720.00 10320.00 P&M-059
Water tanker 6 KL capacity hour 12.000 111.24 1334.88 P&M-060
c) Material
Slaked Lime tonne 29.000 4427.31 128391.93 M-188
Compensation for earth taken from private source cum 360.000 25.10 9036.00 M-092
d) Overhead charges @ 0.1 on (a+b+c) 18876.48
e) Contractor's profit @ 0.1 on (a+b+c+d) 20764.13
Cost for 480 cum = a+b+c+d+e 228405.43
Rate per cum= (a+b+c+d+e)/480 475.84
say 476.00
Note 1.Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
2.Cost of Flyash has not been considered as same will be
available free of cost. Only carriage of Flyash has been
provided.
3.Lime + Flyash has been taken as 20 per cent of total mass
and ratio of lime and Flyash as 1:4 for estimating purposes.
Total quantities will be as per approved design.

119
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
5.15 516 Slurry Seal
Providing and laying slurry seal consisting of a mixture of fine
aggregates, portland cement filler, bituminous emulsion and
water on a road surface including cleaning of surface, mixing
of slurry seal in a suitable mobile plant, laying and compacting
to provide even riding surface.
Case (i) 5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum
weight of mix = 176 tonnes
a) Labour
Mate day 0.240 195.43 46.90 L-12
Mazdoor day 6.000 187.43 1124.58 L-13
b) Machinery
Mechanical broom hour 6.000 456.00 2736.00 P&M-031
Air compressor 250 cfm hour 6.000 293.76 1762.56 P&M-001
Mobile slurry seal equipment hour 6.000 926.64 5559.84 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 846.00 5076.00 P&M-048
stockpile on road side to slurry equipment, bitumen
emulsion and filler.
Pneumatic tyred roller with individual wheel load not hour 6.000 1143.72 6862.32 P&M-037
exceeding 1.5 tonnes
Water tanker6 KL capacity hour 2.000 111.24 222.48 P&M-060
c) Material
Residual Binder @ 11 per cent of mix 80 x 2.2 x 0.11 tonne 19.360 40114.31 776613.12 M-077

Fine aggregate 4.75 mm and below 87 per cent of total cum 102.080 221.82 22643.41 M-030
mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking density1.5,
= 153.12/1.5 = 102.08 cum
Filler @ 2 per cent of total mix = 80 x 2.2 x 0.02 tonne 3.520 4427.31 15584.12 M-188
Cost of water KL 12.000 167.07 2004.82 M-189
d) Overhead charges @ 0.1 on (a+b+c) 84712.42
e) Contractor's profit @ 0.1 on (a+b+c+d) 93183.66
Cost for 16000 sqm = a+b+c+d+e 1025020.23
Rate per sqm = (a+b+c+d+e)/16000 64.06
say 64.00
5.15 Case (ii) 3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
Mate day 0.200 195.43 39.09 L-12
Mazdoor day 5.000 187.43 937.15 L-13
b) Machinery
Mechanical broom hour 6.000 456.00 2736.00 P&M-031
Air compressor 250 cfm hour 6.000 293.76 1762.56 P&M-001
Mobile slurry seal equipment hour 6.000 926.64 5559.84 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 846.00 5076.00 P&M-048
stockpile on road side to slurry equipment, bitumen
emulsion and filler
Water tanker6 KL capacity hour 2.000 111.24 222.48 P&M-060
c) Material
Residual Binder @ 13 per cent of mix = 60 x 2.2 x 0.13 tonne 17.160 40114.31 688361.63 M-077

Fine aggregate 3 mm and below 85 per cent of total cum 74.800 244.51 18289.26 M-022
mix, 60x 2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,

119
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Filler @ 2 per cent of total mix = 60x 2.2 x 0.02 tonne 2.640 4427.31 11688.09 M-188
Cost of water KL 12.000 167.07 2004.82 M-189
d) Overhead charges @ 0.1 on (a+b+c) 74356.49
e) Contractor's profit @ 0.1 on (a+b+c+d) 81792.14
Cost for 20000 sqm = a+b+c+d+e 899713.55
Rate per sqm = (a+b+c+d+e)/20000 44.99
say 45.00
5.15 Case (iii) 1.5 mm thickness

Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
Mate day 0.200 195.43 39.09 L-12
Mazdoor day 5.000 187.43 937.15 L-13
b) Machinery
Mechanical broom hour 6.000 456.00 2736.00 P&M-031
Air compressor 250 cfm hour 6.000 293.76 1762.56 P&M-001
Mobile slurry seal equipment hour 6.000 926.64 5559.84 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from hour 6.000 846.00 5076.00 P&M-048
stockpile on road side to slurry equipment, bitumen
emulsion and filler.
Water tanker6 KL capacity hour 2.000 111.24 222.48 P&M-060
c) Material
Residual Binder @ 16 per cent of mix, 36 x 2.2 x 0.16 tonne 12.670 40114.31 508248.36 M-077

Fine aggregate 2.36 mm and below,82 per cent of total cum 43.300 244.51 10587.23 M-022
mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density 1.5

Filler @ 2 per cent of total mix = 36x 2.2 x 0.02 tonne 1.580 4427.31 6995.15 M-188
Cost of water KL 12.000 167.07 2004.82 M-189
d) Overhead charges @ 0.1 on (a+b+c) 55105.67
e) Contractor's profit @ 0.1 on (a+b+c+d) 60616.23
Cost for 24000 sqm = a+b+c+d+e 666778.58
Rate per sqm = (a+b+c+d+e)/24000 27.78
say 28.00
Note 1.Tack coat, if required to be provided, before laying slurry
seal may be measured and paid separately
5.16 517 Recycling of Bituminous Pavement with Central
Recycling Plant
Recycling pavement by cold milling of existing bituminous
layers, planning the surface after cold milling, reclaiming
excavated material to the extent of 30 per cent of the
required quantity, hauling and stockpiling the reclaimed
material near the central recycling plant after carrying out
necessary checks and evaluation, adding fresh material
including rejuvenators as required, mixing in a hot mix plant,
transporting and laying at site and compacting to the required
grade, level and thickness, all as specified in clause 517.

Unit = cum
Taking output = 120 cum (276 tonnes)
a) Labour
Mate day 0.480 195.43 93.81 L-12
Mazdoor day 10.000 187.43 1874.30 L-13
Mazdoor skilled day 2.000 218.57 437.14 L-15
b) Machinery
Cold milling machine @ 20 cum per hour hour 6.000 855.36 5132.16 P&M-069
Mechanical broom @ 1250 sqm per hour hour 1.280 456.00 583.68 P&M-031

120
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Air compressor 250 cfm hour 1.280 293.76 376.01 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 0.910 986.04 897.30 P&M-004
Hot mix plant 100-120 TPH producing an average of 75 hour 3.000 42304.00 126912.00 P&M-021
tonnes per hour
Electric generator set 250 KVA hour 3.000 3101.00 9303.00 P&M-081
Front end loader 1.00 cum bucket capacity hour 3.000 1148.00 3444.00 P&M-017
Tipper 5.5 cum capacity hour 18.000 846.00 15228.00 P&M-048
Smooth wheeled roller 8-10 tonnes hour 3.00x0.65* 649.00 1265.55 P&M-044
Vibratory roller 8 tonnes hour 3.00x0.65* 1720.00 3354.00 P&M-059
Smooth wheeled tandem roller 6-8 tonnes hour 3.00x0.65* 1051.92 2051.24 P&M-045
c) Material
i) Bitumen
A bitumen content is 4.5 per cent bitumen weight of mix. For
reclaimed material, fresh bitumen will be required to the
extent of 60 per cent of normal requirement.
In a mix of 276 tonnes, 82.8 tonne is reclaimed and balance
193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne @ 60 tonne 1.9872 39879.31 79248.17 M-074
per cent = 82.8 x 0.60 x0.04 = 1.99
Bitumen required for fresh mix of 193.2 tonnes = 193.2 x tonne 7.728 39879.31 308187.32 M-074
0.04 = 7.73
ii) Aggregates
Percentage of mix requiring fresh aggregates - 70 per cent
Weight of fresh mix = 276 x 0.70 = 193.2 tonne
Weight of fresh aggregate in the mix = 193.2 x 0.96 = 185.47
tonne
Taking average density of 1.5 tonnes/cum, total volume
of aggregate = 123.65 cum.
Size wise requirement of fresh aggregates
37.5 - 25 mm @ 23 per cent cum 28.440 772.96 21982.99 M-049
25 - 10 mm @ 15 per cent cum 18.550 937.63 17393.11 M-046
10- 5 mm @ 20 per cent cum 24.730 720.97 17829.57 M-040
Below 5 mm @40 per cent cum 49.460 221.82 10971.23 M-030
Filler (cement) @ 2 per cent = 5.52tonnes of 276 tonne tonne 5.520 5982.46 33023.16 M-081

d) Overhead charges @ 0.1 on (a+b+c) 65958.77


e) Contractor's profit @ 0.1 on (a+b+c+d) 72554.65
Cost for 120 cum of DBM = a+b+c+d+e 798101.16
Rate per cum = (a+b+c+d+e)/120 6650.84
say 6651.00
Note Although the total rolling time is only 4 hours as per norms, all
the three rollers have to be available at site for 3 hours each
to match with the output of re-cycling plant. To cater for their
idling time, these have been multiplied with a factor of 0.65.

121
RCD/SOR

CHAPTER- 6
CEMENT CONCRETE PAVEMENTS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
6.1 601 Dry Lean Cement Concrete Sub- base
Construction of dry lean cement concrete Sub- base over a
prepared sub-grade with coarse and fine aggregate
conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed
15:1, aggregate gradation after blending to be as per table
600-1, cement content not to be less than 150 kg/ cum,
optimum moisture content to be determined during trial
length construction, concrete strength not to be less than 10
Mpa at 7 days, mixed in a batching plant, transported to site,
laid with a paver with electronic sensor, compacting with 8-
10 tonnes vibratory roller, finishing and curing.

Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.120 195.43 218.88 L-12
Mazdoor skilled day 6.000 218.57 1311.42 L-15
Mazdoor day 22.000 187.43 4123.46 L-13
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Cement concrete batch mix plant @ 75 cum per hour hour 6.000 2052.00 12312.00 P&M-068
Electric generator 100 KVA hour 6.000 1635.00 9810.00 P&M-080
Paver with electronic sensor hour 6.000 3046.00 18276.00 P&M-034
Vibratory roller 8-10 t capacity hour 8.000 1720.00 13760.00 P&M-059
Water tanker6 KL capacity hour 8.000 111.24 889.92 P&M-060
Tipper tonne.km 990 x L 2.68 2651.62 Lead =1 km
& P&M-047
Add 10 per cent of cost of carriage to cover cost of loading 265.16
and unloading
c) Material
Crushed stone coarse aggregate of 25 mm and 12.5 cum 405.000 833.00 337365.00 M-052 and
mm nominal sizes graded as per table 600-1 @ 0.90 M-054
cum/cum of concrete conforming to clause 602.2.4.
Coarse Sand as per IS: 383 @ 0.45 cum/cum of cum 203.000 209.13 42453.45 M-004
concrete
Cement @ 150 kg/cum of concrete tonne 67.500 5982.46 403815.79 M-081
Cost of water KL 48.000 167.07 8019.27 M-189
d) Overhead charges @ 0.1 on (a+b+c) 86216.00
e) Contractor's profit @ 0.1 on (a+b+c+d) 94837.60
Cost for 450 cum = a+b+c+d+e 1043213.57
Rate per cum = (a+b+c+d+e)/450 2318.25
say 2318.00
Note Quantity provided for aggregate is for estimating purpose.
Exact quantity shall be as per mix design.
6.2 602 Cement Concrete Pavement
Construction of un-reinforced, dowel jointed, plain cement
concrete pavement over a prepared sub base with 43 grade
cement @ 400 kg per cum, coarse and fine aggregate
conforming to IS 383, maximum size of coarse aggregate
not exceeding 25 mm, mixed in a batching and mixing plant
as per approved mix design, transported to site, laid with a
fixed form or slip form paver, spread, compacted and
finished in a continuous operation including provision of
contraction, expansion, construction and longitudinal joints,
joint filler, separation membrane, sealant primer, joint
sealant, debonding strip, dowel bar, tie rod, admixtures as
approved, curing compound, finishing to lines and grades as
per drawing

Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.000 195.43 390.86 L-12

122
RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor skilled day 15.000 218.57 3278.55 L-15
Mazdoor day 35.000 187.43 6560.05 L-13
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 456.00 1276.80 P&M-031
Front end loader 1 cum bucket capacity hour 18.000 1148.00 20664.00 P&M-017
Cement concrete batch mix plant @ 175 cum per hour hour 6.000 4787.64 28725.84 P&M-067
(effective output)
Electric generator 250 KVA hour 6.000 3101.00 18606.00 P&M-081
Slip form paver with electronic sensor hour 6.000 2637.36 15824.16 P&M-006
Water tanker6 KL capacity hour 36.000 111.24 4004.64 P&M-060
Transit truck agitator 5 cum capacity. tonne.km 2415xL 4.32 10432.80 Lead =1 km
& P&M-050
Add 10 per cent of cost of carriage to cover cost of loading 1043.28
and unloading
Concrete joint cutting machine . hour 12.000 214.92 2579.04 P&M-083
Texturing machine . hour 12.000 71.50 857.95 P&M-088
c) Material
Crushed stone coarse aggregates of 25mm and cum 945.000 833.00 787185.00 M-052 and
12.5mm nominal size @ 0.90 cum/cum of concrete M-054
conforming to clause 602.2.4. .
Sand as per IS: 383 and conforming to clause 602.2.4 cum 473.000 209.13 98918.63 M-004
@ 0.45 cum/cum of concrete
Cement 43 grade @ 400 kg/cum of concrete tonne 414.000 5982.46 2476736.84 M-081
32 mm mild steel dowel bars of grade S 240 tonne 9.450 49279.84 465694.52 M-126
16 mm deformed steel tie bars of grade S 415 tonne 1.170 44187.50 51699.38 M-082
Separation Membrane of impermeable plastic sheeting sqm 3675.000 11.00 40418.14 M-164
125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion sqm 16.330 708.07 11562.79 M-141
joint.
Joint sealant kg 875.000 17.81 15580.69 M-120
Sealant primer kg 116.670 9.01 1050.96 M-097
Plastic sheath,1.25 mm thick for dowel bars sqm 46.670 10.96 511.68 M-138
Curing compound liter 1850.000 91.13 168585.65 M-090
Super plastisizer admixture IS marked as per 9103- kg 2070.000 112.77 233436.07 M-180
1999 @ 0.5 per cent by weight of cement
Cost of water KL 216.000 167.07 36086.74 M-189
Add 1 per cent of material for cost of miscellaneous 43874.67
materials like tarpauline, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work
bridges for men to approach concrete surface without
walking over it, cutting blades and bites, minor equipments
like scabbling machine, threads, ropes, guide wires and any
other unforeseen items.

d) Overhead charges @ 0.1 on (a+b+c) 454558.57


e) Contractor's profit @ 0.1 on (a+b+c+d) 500014.43
Cost for 1050cum = a+b+c+d+e 5500158.73
Rate per cum = (a+b+c+d+e)/1050 5238.25
say 5238.00
Note The quantities for cement, coarse aggregate and fine
aggregates are for estimating only .The exact quantities will
be as per mix design.
6.3 603 Rolled Cement Concrete Base
Construction of rolled cement concrete base course with
coarse and fine aggregate conforming to IS:383, the size of
coarse aggregate not exceeding 25 mm with minimum,
aggregate cement ratio15:1 and minimum cement content of
200 kg/cum, aggregate gradation to be as per table 600-4
after blending, mixing in batching plant at optimum moisture
content, transporting to site, laying with a paver with
electronic sensor, compacting with 8-10 tonnes smooth
wheeled vibratory roller to achieve, the designed flexural
strength, finishing and curing.

Unit = cum

123
RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.200 195.43 234.52 L-12
Mazdoor skilled day 7.000 218.57 1529.99 L-15
Mazdoor day 23.000 187.43 4310.89 L-13
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Cement concrete batch mix plant @ 75 cum per hour hour 6.000 2052.00 12312.00 P&M-068
Electric generator 100 KVA hour 6.000 1635.00 9810.00 P&M-080
Paver with electronic sensor @ 75 cum/hr. hour 6.000 3046.00 18276.00 P&M-034
Vibratory roller 8-10 t capacity hour 8.000 1720.00 13760.00 P&M-059
Water tanker with 5 km lead 6 KL capacity hour 8.000 111.24 889.92 P&M-060
Tipper tonne.km 990xL 2.68 2651.62 Lead =1 km
& P&M-047
Add 10 per cent of cost of carriage to cover cost of loading 265.16
and unloading
c) Material
Crushed stone coarse aggregates of 25mm and cum 405.000 833.00 337365.00 M-052 and
12.5mm nominal size @ 0.90 cum/cum of concrete M-054
conforming to clause 602.2.3.
Sand as per IS: 383 and conforming to clause 602.2.3 cum 203.000 209.13 42453.45 M-004
@ 0.45 cum/cum of concrete
Cement @ 200 kg/cum of concrete tonne 90.000 5982.46 538421.05 M-081
Cost of water KL 48.000 167.07 8019.27 M-189
d) Overhead charges @ 0.1 on (a+b+c) 99718.69
e) Contractor's profit @ 0.1 on (a+b+c+d) 109690.56
Cost for 450cum = a+b+c+d+e 1206596.11
Rate per cum = (a+b+c+d+e)/450 2681.32
say 2681.00
Note The quantities for cement, coarse aggregate and fine
aggregates are for estimating only .The exact quantities will
be as per mix design.
6.4 New Transition Section between Rigid and Flexible
Pavement
Due to change in the properties of materials and type of
construction, a gradual changeover from rigid pavement to
flexible pavement is desirable to avoid any damage at the
butting joint. After provision of an expansion joint in the
cement concrete slab, the thickness of slab should be
tapered to 10 cm over a length of 3 m towards the flexible
pavement. The deficiency of thickness caused due to
tapering of the slab should be made up by the asphaltic
layers.

The quantities of items should be worked out based on the


approved design and drawings and priced as per rates given
under respective clauses for cement concrete and asphaltic
work.
6.5 Suggestive Construction of Base/Sub-Base of Pavement with Lean
Concrete - Flyash.
Construction of Base/sub-base using cement, sand, fly ash
and coarse aggregates proportioned as per table 4 of IRC:
74/1979 and with water content ratio, slump and
compressive strength as defined in the said table, mix
prepared in a batching and mixing plant and compacted with
a vibratory roller 8-10 tonnes capacity within the time limit
laid down vide clause 7.6.3 of IRC: 74-1979, construction
joints properly formed at the end of day's work, cured for 14
days, all as specified in IRC: 74-1979 and as per approved
plans.

Unit = cum

124
RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.120 195.43 218.88 L-12
Mazdoor skilled day 6.000 218.57 1311.42 L-15
Mazdoor day 22.000 187.43 4123.46 L-13
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Cement concrete batch mix plant @ 75 cum per hour hour 6.000 2052.00 12312.00 P&M-068
Electric generator 100 KVA hour 6.000 1635.00 9810.00 P&M-080
Paver finisher with electronic sensor hour 6.000 3046.00 18276.00 P&M-034
Vibratory roller 8-10 t capacity hour 8.000 1720.00 13760.00 P&M-059
Water tanker6 KL capacity hour 8.000 111.24 889.92 P&M-060
Tipper 10 T Capacity tonne.km 990 x L 2.68 2651.62 Lead =1 km
& P&M-047
Add 10 per cent of cost of carriage to cover cost of loading 265.16
and unloading
c) Material
Crushed stone coarse aggregate of 40 mm nominal cum 405.000 780.12 315948.02 M-055
size @ 0.90 cum/cum of concrete conforming to table 2
of IRC: 74-1979.
Coarse Sand as per IS: 383 - 1970 cum 110.960 209.13 23205.10 M-004
Cement @ 150 kg/cum of concrete tonne 67.500 5982.46 403815.79 M-081
Fly ash conforming to IS: 3812 ( Part II ) cum 91.540 0.00 0.00 M-011
( Total fine aggregates = 450 x 0.45 = 202.50 cum To be
divided in ratio of 2 sand : 1.65 flyash. Refer table 4 of IRC:
74-1979).
d) Overhead charges @ 0.1 on (a+b+c) 81347.54
e) Contractor's profit @ 0.1 on (a+b+c+d) 89482.29
Cost for 450cum = a+b+c+d+e 984305.20
Rate per cum = (a+b+c+d+e)/450 2187.34
say 2187.00
Note 1.Depending upon approved designs, crushed stone
aggregates of nominal size 20mm can also be used as per
gradation given in table 2 of IRC: 74-1979.
2.The ratio of specific gravities of fly ash and sand has been
assumed to be 0.827.

3.The quantities of materials given in the analyses are for


estimating purposes. Actual quantities shall be as per job
mix formula.
4.Construction procedure as laid down in clause, of IRC: 74-
1979 shall be followed.
6.6 Suggestive Cement - Flyash Concrete Pavement.
Construction of un-reinforced, dowel jointed, plain cement
concrete pavement over a prepared sub base with 43 grade
cement, coarse and fine aggregate conforming to IS 383,
maximum size of coarse aggregate not exceeding 25 mm,
replacing cement by fly ash to the extent of 15 per cent and
sand by 10 per cent, mixed in a batching and mixing plant as
per approved mix design, transported to site, laid with a fixed
form or slip form paver, spread, compacted and finished in a
continuous operation including provision of contraction,
expansion, construction and longitudinal joints, joint filler,
separation membrane, sealant primer, joint sealant,
debonding strip, dowel bar, tie rod, admixtures as approved,
curing compound, finishing to lines and grades as per
drawing

Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour

125
RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 2.000 195.43 390.86 L-12
Mazdoor skilled day 15.000 218.57 3278.55 L-15
Mazdoor day 35.000 187.43 6560.05 L-13
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 456.00 1276.80 P&M-031
Front end loader 1 cum bucket capacity hour 18.000 1148.00 20664.00 P&M-017
Cement concrete batch mix plant @ 175 cum per hour hour 6.000 4787.64 28725.84 P&M-067
(effective output)
Electric generator 250 KVA hour 6.000 3101.00 18606.00 P&M-081
Slip form paver with electronic sensor hour 6.000 2637.36 15824.16 P&M-006
Water tanker6 KL capacity hour 36.000 111.24 4004.64 P&M-060
Transit truck agitator 5 cum capacity. tonne.km 2415xL 4.32 10432.80 P&M-050
Lead= 1 km
Add 10 per cent of cost of carriage to cover cost of loading 1043.28
and unloading
Concrete joint cutting machine . hour 12.000 214.92 2579.04 P&M-083
Texturing machine . hour 12.000 71.50 857.95 P&M-088
c) Material
Crushed stone coarse aggregates of 25mm and cum 945.000 833.00 787185.00 M-052 and
12.5mm nominal size @ 0.90 cum/cum of concrete M-054
conforming to clause 602.2.4.
Sand as per IS: 383 and conforming to clause 602.2.4 cum 425.000 209.13 88880.38 M-004
Cement 43 grade tonne 357.000 5982.46 2135736.84 M-081
Fly ash conforming to IS: 3812-1966 (Part-I) tonne 109.000 0.00 0.00 M-011
32 mm mild steel dowel bars of grade S 240 tonne 9.450 49279.84 465694.52 M-126
16 mm deformed steel tie bars of grade S 415 tonne 1.170 44187.50 51699.38 M-082
Separation Membrane of impermeable plastic sheeting sqm 3675.000 11.00 40418.14 M-164
125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion sqm 16.330 708.07 11562.79 M-141
joint.
Joint sealant kg 875.000 17.81 15580.69 M-120
Sealant primer kg 116.670 9.01 1050.96 M-097
Plastic sheath,1.25 mm thick for dowel bars sqm 46.670 10.96 511.68 M-138
Curing compound liter 1850.000 91.13 168585.65 M-090
Super plastisizer admixture IS marked as per 9103- kg 2070.000 112.77 233436.07 M-180
1999 @ 0.5 per cent by weight of cement
Cost of water KL 216.000 167.07 36086.74 M-189
Add 1 per cent of material for cost of miscellaneous 40364.29
materials like tarpauline, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work
bridges for men to approach concrete surface without
walking over it, cutting blades and bites, minor equipments
like scabbling machine, threads, ropes, guide wires and any
other unforeseen items.

d) Overhead charges @ 0.1 on (a+b+c) 419103.71


e) Contractor's profit @ 0.1 on (a+b+c+d) 461014.08
Cost for 1050cum = a+b+c+d+e 5071154.88
Rate per cum = (a+b+c+d+e)/1050 4829.67
say 4830.00
Note 1.The quantities for cement, coarse aggregate and fine
aggregates are for estimating only .The exact quantities will
be as per mix design.

2.IRC: 68-1976 may be referred for guidelines on the design


of cement-fly ash concrete for rigid pavement construction.

*Calculation of cement, sand and fly ash.

126
RCD/SOR

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cement @ 400 kg/cum = 1050 x 400 = 420 tonnes. 15 per
cent of cement to be replaced by fly ash = 63 tonnes.
Balance cement = 357 tonnes. Quantity of fly ash = 63 x
specific gravity of fly ash /specific gravity of cement = 63 x
2.25/3.15 = 45 tonnes.

Sand @ 0.45 cum / cum of concrete = 1050 x 0.45 = 472.50


x 1.6 = 756 tonnes.10 per cent to be replaced by flyash.
Balance sand = 756 x 0.9 = 680.4 tonnes = 680.4 / 1.6 =
425 cum. Quantity of flyash = (756-680.4) x specific gravity
of fly ash/specific gravity of sand = 76.4 x 2.25 / 2.687 =
63.97 tonnes (say 64 tonnes)

Fly ash Total fly ash = 45 + 64 = 109 tonnes.

127
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
7.1 702 Sub-Surface Drain with Geotextiles
Construction of sub surface drain 200 mm dia using geotextiles
treated with carbon black with physical properties as given in
clause 702.2.3 formed in to a stable network and a planar
geocomposite structure, joints wrapped with geotextile to prevent
ingress of soil, all as per clause 702 and approved drawings
including excavation and backfilling

Unit = Running metre


Taking output = one metre
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor skilled day 0.250 218.57 54.64 L-15
Mazdoor day 0.500 187.43 93.72 L-13
b) Material
Geonets, geomembrane and geotextile to make planar
geocomposite stable network for sub surface drain including
wrapping of joints with 160 mm over lapping with geotextile .
Geonets sqm 1.000 77.51 77.51 M-107
Geomembrane sqm 1.000 77.51 77.51 M-106
Geotextile sqm 2.000 60.75 121.50 M-108
Add 2 per cent cost of material for miscellaneous items like 5.53
synthetic cord
c) Overhead charges @ 0.1 on (a+b) 43.82
d) Contractor's profit @ 0.1 on (a+b+c) 48.21
Rate per metre = a+b+c+d 530.26
say 530.00
Note Surplus excavated material to be used at site. Hence seprate cost
for disposal not added.
7.2 702.4 Narrow Filter Sub-Surface Drain
Construction of a narrow filter sub- surface drain consisting of
porous or perforated pipe laid in narrow trench surrounded by a
geotextile filter fabric, with a minimum of 450 mm overlap of fabric
and installed as per clause 702.3 and 309.3.5 including excavation
and backfilling
Unit = Running metre length
Taking output = one metre
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor skilled day 0.250 218.57 54.64 L-15
Mazdoor day 0.500 187.43 93.72 L-13
b) Material
Perforated geosynthetic pipe 150 mm dia metre 1.000 65.26 65.26 M-134
Geotextile filter fabric sqm 1.250 60.75 75.94 M-109
Add 2 per cent cost of material for miscellaneous item like 2.82
synthetic cord
c) Overhead charges @ 0.1 on (a+b) 30.02
d) Contractor's profit @ 0.1 on (a+b+c) 33.02
Rate per metre = a+b+c+d 363.24
say 363.00
Note Surplus excavated material to be used at site. Hence Separate cost
for disposal not added.
7.3 703 Laying Paving Fabric Beneath a Pavement Overlay

Providing and laying paving fabric with physical requirements as


per table 704-2 over a tack coat of paving grade Bitumen 80-100
penetration, laid at the rate of 1 kg per sqm over thoroughly
cleaned and repaired surface to provide a water resistant
membrane and crack retarding layer. Paving fabric to be free of
wrinkling and folding and to be laid before cooling of tack coat,
brooming and rolling of surface with pneumatic roller to maximise
paving fabric contact with pavement surface

Unit = sqm

127
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking output = 2800 sqm
a) Labour
Mate day 0.800 195.43 156.34 L-12
Mazdoor day 20.000 187.43 3748.60 L-13
b) Machinery
Road sweeper 1250 sqm per hour hour 2.240 456.00 1021.44 P&M-031
Pneumatic roller 14 tonnes 2000 sqm per hour hour 1.400 1143.72 1601.21 P&M-037
Bitumen pressure distributor 1750 sqm per hour hour 1.680 986.04 1656.55 P&M-004
c) Material
Paving Fabric sqm 2940.000 60.75 178609.66 M-133
Paving Bitumen 80-100 tonne 2.800 38958.19 109082.94 M-075
c) Overhead charges @ 0.1 on (a+b) 29587.67
d) Contractor's profit @ 0.1 on (a+b+c) 32546.44
Cost for 2800 sqm = a+b+c+d+e 358010.85
Rate per sqm =(a+b+c+d+e)/2800 127.86
say 128.00
7.4 704 Laying Boulder Apron in Crates of Synthetic Geogrids

Providing, preparing and laying of geogrid crated apron 1 m x 5 m,


600 mm thick including excavation and backfilling with baffles at 1
metre interval, made with geogrids having characteristics as per
clause 704.2, joining sides with connectors/ring staples, top corners
to be tie tensioned, placing of suitable cross interval ties in layers of
300 mm connecting opposite side with lateral braces and tied with
polymer braids to avoid bulging, constructed as per clause 704.3.
filled with stone with minimum size of 200 mm and specific gravity
not less than 2.65, packed with stone spalls, keyed to the
foundation recess in case of sloping ground and laid over a layer of
geotextile to prevent migration of fines, all as per clause 704 and
laid as per clause 2503.3 and approved design.

Unit = cum
Taking output = 3.00 cum
a) Labour
Mate day 0.060 195.43 11.73 L-12
Mazdoor skilled day 0.500 218.57 109.29 L-15
Mazdoor day 1.500 187.43 281.15 L-13
b) Material
Geo grids sqm 21.000 77.51 1627.72 M-105
Connectors/ Staples each 50.000 #VALUE! #VALUE! M-085
Polymer braids metre 20.000 #VALUE! #VALUE! M-140
Stones with minimum size of 200 mm cum 3.450 352.58 1216.39 M-003
Stones spall for filling voids cum 0.450 325.05 146.27 M-008
c) Overhead charges @ 0.1 on (a+b) #VALUE!
d) Contractor's profit @ 0.1 on (a+b+c) #VALUE!
Cost for 3 cum = a+b+c+d #VALUE!
Rate per cum = (a+b+c+d)/ 3 #VALUE!
say #VALUE!
7.5 3100 Reinforced Earth Structures
Reinforced earth Structures have four main components as under:

a) Excavation for foundation, foundation concrete and cement


concrete grooved seating in the foundation for facing elements
(facia material).
b) Facia material and its placement.
c) Assembling, joining with facing elements and laying of the
reinforcing elements.
d) Earth fill with granular material which is to be retained by the
wall.
Each component is analysed separately as under:
considering Average height of wall = 8 m.

128
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
7.5 3102 (i) Assembling, joining and laying of reinforcing elements.

A With reinforcing element of steel / Aluminium strips /


polymeric strips.
Unit = Running Metre
Taking Output = 450 m
a) Labour
Mate day 0.360 195.43 70.35 L-12
Mazdoor day 6.000 187.43 1124.58 L-13
Mazdoor skilled day 3.000 218.57 655.71 L-15
b) Material
@ Reinforcement strips 60 mm wide 5 mm thick as per clause 3102.

1.Galvanised carbon steel strips metre 450*1.1 480.32 237758.96 M-154


or
2.Copper Strips metre 450*1.1 480.32 237758.96 M-153
or
3.Aluminium Strips metre 450*1.1 237.03 117328.88 M-157
or
4.Stainless steel strips metre 450*1.1 237.03 117328.88 M-156
or
5.Glass reinforced polymer/fibre reinforced polymer/polymeric metre 450*1.1 480.32 237758.96 M-155
strips
@ Any one of the above alternative may be adopted as per
approved design.
Add 10 per cent of the cost of reinforcing strip towards accessories
like tie-strips, nuts and bolts and loops/lugs for joining reinforcing
elements with the facia pannels, overlaps, heat bonding or
extension.

Type 1.Galvanised carbon steel strips


1
c) Overhead charges @ 0.1 on (a+b) 23960.96
d) Contractor's profit @ 0.1 on (a+b+c) 23960.96
Cost of 450 m = a+b+c+d 287531.53
Rate per metre =(a+b+c+d)/450 638.96
say 639.00
Type 2.Copper Strips
2
c) Overhead charges @ 0.1 on (a+b) 23960.96
d) Contractor's profit @ 0.1 on (a+b+c) 23960.96
Cost of 450 m = a+b+c+d 287531.53
Rate per metre =(a+b+c+d)/450 638.96
say 639.00
Type 3.Aluminium Strips
3
c) Overhead charges @ 0.1 on (a+b) 11917.95
d) Contractor's profit @ 0.1 on (a+b+c) 11917.95
Cost of 450 m = a+b+c+d 143015.43
Rate per metre =(a+b+c+d)/450 317.81
say 318.00
Type 4.Stainless steel strips
4
c) Overhead charges @ 0.1 on (a+b) 11917.95
d) Contractor's profit @ 0.1 on (a+b+c) 11917.95
Cost of 450 m = a+b+c+d 143015.43
Rate per metre =(a+b+c+d)/450 317.81
say 318.00

129
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Type 5.Glass reinforced polymer/fibre reinforced
5 polymer/polymeric strips
c) Overhead charges @ 0.1 on (a+b) 23960.96
d) Contractor's profit @ 0.1 on (a+b+c) 23960.96
Cost of 450 m = a+b+c+d 287531.53
Rate per metre =(a+b+c+d)/450 638.96
say 639.00
7.5(i) B With reinforcing elements of synthetic geogrids
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 0.360 195.43 70.35 L-12
Mazdoor day 6.000 187.43 1124.58 L-13
Mazdoor skilled day 3.000 218.57 655.71 L-15
b) Material
Synthetic Geogrids as per clause 3102.8 and approved sqm 300.000 85.89 25767.05 M-181
design and specifications.
Add 10 per cent of the cost of reinforcing elements (synthetic 2576.71
geogrids) for accessories like tie-strips, nuts and bolts and
loops/lugs for joining reinforcing elements with the facia
pannels, overlaps and other protective elements for synthetic
geogrids.

c) Overhead charges @ 0.1 on (a+b) 3019.44


d) Contractor's profit @ 0.1 on (a+b+c) 3321.38
Cost of 300 sqm of Synthetic geogrids = a+b+c+d 36535.23
Rate per sqm = (a+b+c+d)/ 300 121.78
say 122.00
7.5 3104 (ii) Facing elements of RCC
Unit = sqm
Taking output = 75 sqm
a) Labour
Mate day 0.180 195.43 35.18 L-12
Mazdoor day 3.000 187.43 562.29 L-13
Mazdoor skilled day 1.500 218.57 327.86 L-15
b) Machinery
Light crane with lifting capacity upto 3 tonne hour 6.000 525.00 3150.00 P&M-013
c) Material
Pre-cast RCC M-35 facing elements of size as per design and cu.m 13.500 3849.00 51961.50 Item 12.8 (H)
18 cm thick for 75 sqm. (Refer Item 12.8 (H)) Case I
HYSD steel @ 5 kg / sqm (Refer Item 12.6) tonnes 0.380 66758.00 25368.04 Item 13.6
Add 2 per cent of cost of facia pannels, for all necessary temporary 1546.59
form work, scaffolding and provision of loops/lugs for lifting of
pannels and joining the reinforcing elements.

d) Overhead charges @ 0.1 on (a+b) 407.53


e) Contractor's profit @ 0.1 on (a+b+d) 448.29
Cost for 75 sqm = a+b+c+d+e 83807.27
Rate per sqm = (a+b+c+d+e)/ 75 1117.43
say 1117.00
Note 1.The specification and construction details to be adopted shall be
as per section 3100 of MoRTH Specification.
2.Drainage arrangement shall be made as per approved design
and drawings.
3.The quantity of filler media shall be calculated as per approved
design and specifications and shall be priced separately.The rate
for same to be adopted from chapter 15.

130
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
4.Excavation for foundation including foundation concrete and
groove in the foundation for seating of bottom most facia panel and
capping beam to be calculated as per design and priced separately.
The rates for excavation and foundation concrete shall be taken
from the chapter 12 & 13 in bridge section.

5.The earth fill to be retained is not included in this analysis. The


same is to be worked out and provided separately complete as per
clause 305.
, 6.For compaction of Earthwork, attention is invited to clause 3105.5
of MoRTH Specification.
7.Length of reinforcing strips will vary with the height of wall and will
be as per approved design and drawings.
8.The type of reinforcing elements to be adopted shall be as per
approved design and specifications.
9.The market rate for supply of reinforcing elements and their
accessories are to be ascertained from reputed firms in the field of
earth reinforcement.
10.The earth fill material shall be clean, free draining, granular with
high friction and low cohesion, non-corrosive, coarse grained with
not 10 per cent of particles passing 75 micron sieve, free of any
deleterious matter, chlorides, salts, acids, alkalies, mineral oil,
fungus and microbes and shall be of specified PH value.

11.Capping beam is to be priced separately as per approved


design. The rate for cement concrete shall be taken from the
chapter of sub-structure in bridge section.
12.The cost of reinforced earth retaining wall shall include following:

(I) Excavation for foundation including backfilling.


(ii) Foundation concrete as per approved design.
(iii) Cost of facial pannels and their erection .
(iv) Cost of reinforcing elements including their fixing and joining
with the facial pannels.
(v) Drainage arrangement including filter media as per approved
design and drawings.
13. The compacted earth filling to be retained shall form part of
embankment.

131
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
8.1 408 Cast in Situ Cement Concrete M20 Kerb
Construction of cement concrete kerb with top and bottom
width 115 and 165 mm respectively, 250 mm high in M 20
grade PCC on M-10 grade foundation 150 mm thick,
foundation having 50 mm projection beyond kerb stone, kerb
stone laid with kerb laying machine, foundation concrete laid
manually, all complete as per clause 408
Unit = Running metre
Taking output = 360 metre
A. Using Concrete Mixer
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base= 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.720 195.43 140.71 L-12
Mason day 2.000 247.19 494.38 L-11
Mazdoor day 16.000 187.43 2998.88 L-13
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 279.72 1678.32 P&M-029
Concrete mixer 0.48/0.28 cum capacity hour 12.000 211.68 2540.16 P&M-009
Water tanker6 KL capacity hour 5.000 111.24 556.20 P&M-060
c) Material
Crushed stone aggregate 20 mm nominal size 59 per 887.53 19339.20 M-053
cum 21.790
cent
Coarse sand 30 per cent cum 10.900 209.13 2279.52 M-005
Cement 11 per cent tonne 5.700 5982.46 34100.00 M-081
Cost of water KL 30.000 167.07 5012.05 M-189
d) Overhead charges @ 0.1 on (a+b+c) 6913.94
e) Contractor's profit @ 0.1 on (a+b+c+d) 7605.34
Cost for 360 meter = a+b+c+d+e 83658.69
Rate per metre = (a+b+c+d+e)/360 232.39
say 232.00
B Using Concrete Batching and Mixing Plant
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base = 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.120 195.43 23.45 L-12
Mason day 1.000 247.19 247.19 L-11
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 279.72 1678.32 P&M-029
Concrete batching and mixing plant @ 15 cum/hr. hour 1.600 1704.24 2726.78 P&M-003
Water tanker6 KL capacity hour 5.000 111.24 556.20 P&M-060
Tipper 5.5 cum capacity hour 6.000 846.00 5076.00 P&M-048
c) Material
Crushed stone aggregate 20 mm nominal size 59 per 887.53 19339.20 M-053
cum 21.790
cent
Coarse sand 30 per cent cum 10.900 209.13 2279.52 M-004
Cement 11 per cent tonne 5.700 5982.46 34100.00 M-081
Cost of water KL 30.000 167.07 5012.05 M-189
d) Overhead charges @ 0.1 on (a+b+c) 7141.36
e) Contractor's profit @ 0.1 on (a+b+c+d) 7855.49
Cost for 360 meter = a+b+c+d+e 86410.42
Rate per metre = (a+b+c+d+e)/360 240.03
say 240.00
8.2 408 Cast in Situ Cement Concrete M 20 Kerb with Channel

132
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Construction of cement concrete kerb with channel with top
and bottom width 115 and 165 mm respectively, 250 mm
high in M 20 grade PCC on M10 grade foundation 150 mm
thick, kerb channel 300 mm wide, 50 mm thick in PCCM20
grade, sloped towards the kerb, kerb stone with channel laid
with kerb laying machine, foundation concrete laid manually,
all complete as per clause 408
A Using Concrete Mixer
Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a) Labour
Mate day 0.720 195.43 140.71 L-12
Mason day 2.000 247.19 494.38 L-11
Mazdoor day 16.000 187.43 2998.88 L-13
b) Machinery
Kerb casting machine @ 50 metres/hour for laying kerb 279.72 1678.32 P&M-029
hour 6.000
and channel
Concrete mixer 0.48/0.28 hour 16.000 211.68 3386.88 P&M-009
Water tanker6 KL capacity hour 6.000 111.24 667.44 P&M-060
c) Material
Crushed stone aggregate 20 mm nominal size 60 per 887.53 32474.59 M-053
cum 36.590
cent
Coarse sand 30 per cent cum 18.300 209.13 3827.08 M-005
Cement 10 per cent tonne 9.010 5982.46 53901.93 M-081
Cost of water KL 36.000 167.07 6014.46 M-189
d) Overhead charges @ 0.1 on (a+b+c) 10558.47
e) Contractor's profit @ 0.1 on (a+b+c+d) 11614.31
Cost for 300 metre = a+b+c+d+e 127757.45
Rate per metre = (a+b+c+d+e)/300 425.86
say 426.00
8.2 B Using Concrete Batching and Mixing Plant
Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a) Labour
Mate day 0.120 195.43 23.45 L-12
Mason day 1.000 247.19 247.19 L-11
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery
Kerb casting machine @ 50 metres/hour for laying kerb 279.72 1678.32 P&M-029
hour 6.000
and channel
Concrete batching and mixing plant @ 15 cum/hr. hour 2.700 1704.24 4601.45 P&M-003
Water tanker6 KL capacity hour 6.000 111.24 667.44 P&M-060
Tipper of 5.5 cum capacity hour 6.000 846.00 5076.00 P&M-048
c) Material
Crushed stone aggregate 20 mm nominal size 60 per 887.53 32474.59 M-053
cum 36.590
cent
Coarse sand 30 per cent cum 18.300 209.13 3827.08 M-004
Cement 10 per cent tonne 9.010 5982.46 53901.93 M-081
Cost of water KL 36.000 167.07 6014.46 M-189
d) Overhead charges @ 0.1 on (a+b+c) 10888.68

133
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
e) Contractor's profit @ 0.1 on (a+b+c+d) 11977.54
Cost for 300 meter = a+b+c+d+e 131752.99
Rate per metre = (a+b+c+d+e)/300 439.18
say 439.00
8.3 801 Printing New Letter and Figures of any Shade
Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade

(i)
Hindi ( Matras commas and the like not to be measured
and paid for Half letter shall be counted as half )
Details for 100 letters of 16 cm height i.e. 1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.120 195.43 23.45 L-12
Painter day 2.000 236.19 472.38 L-18
Mazdoor day 1.000 187.43 187.43 L-13
b) Material
Paint Litre 0.700 138.35 96.85 M-131
c) Overhead charges @ 0.1 on (a+b) 78.01
d) Contractor's profit @ 0.1 on (a+b+c) 85.81
Cost for 1600 cm = a+b+c+d 943.93
Rate per cm height per letter = (a+b+c+ d)/1600 0.59
say 0.60
8.3 (ii) English and Roman
Hyphens and the like not to be measured and paid for
Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.070 195.43 13.68 L-12
Painter Ist class day 1.250 236.19 295.24 L-18
Mazdoor day 0.500 187.43 93.72 L-13
b) Material
Paint Litre 0.500 138.35 69.18 M-131
c) Overhead charges @ 0.1 on (a+b) 47.18
d) Contractor's profit @ 0.1 on (a+b+c) 51.90
Cost for 1600 cm = a+b+c+d 570.89
Rate per cm height per letter = (a+b+c +d)/1600 0.36
say 0.40
8.4 801 Retro-Reflectorised Traffic Signs

Providing and fixing of retro- reflectorised cautionary,


mandatory and informatory sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 1.5 mm thick supported on a mild steel
angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the
ground by means of properly designed foundation with M15
grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm
below ground level as per approved drawing

Unit = Each
Taking output = one traffic sign
i) Excavation for foundation cum 0.216 189.00 40.82 item 3.13 (1) A
ii) Cement concrete M15 grade cum 0.120 4259.00 511.08 Item 12.8 (A)
iii) Painting angle iron post two coats sqm 0.430 40.00 17.20 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 195.43 1.95 L-12
Mazdoor day 0.250 187.43 46.86 L-13
b) Material
Mild steel angle iron 75 x 75 x 6 mm kg 19.000 48.095 913.811 M-179 /1000

134
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable
Add 2 per cent of cost of angle iron towards cost of drilling
18.28
holes, nuts, bolts etc.
(i) 90 cm equilateral triangle sqm 0.350 7902.33 2765.81 M-061
or
( ii ) 60 cm equilateral triangle sqm 0.156 7902.33 1232.76 M-061
or
( iii ) 60 cm circular sqm 0.283 7902.33 2236.36 M-061
or
( iv ) 80 mm x 60 mm rectangular sqm 0.480 7902.33 3793.12 M-061
or
(v) 60 cm x 45 cm rectangular sqm 0.270 7902.33 2133.63 M-061
or
(vi ) 60 cm x 60 cm square sqm 0.360 7902.33 2844.84 M-061
or
( vii ) 90 cm high octagon sqm 0.672 7902.33 5310.36 M-061
c) Machinery
Tractor-trolley hour 0.010 171.02 1.71 P&M-053
(i) 90 cm equilateral triangle
d) Overhead charges @ 0.1 on (a+b+c) 374.84
e) Contractor's profit @ 0.1 on (a+b+c+d) 412.33
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 5104.70
say 5105.00
( ii ) 60 cm equilateral triangle
d) Overhead charges @ 0.1 on (a+b+c) 221.54
e) Contractor's profit @ 0.1 on (a+b+c+d) 243.69
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 3249.71
say 3250.00
( iii ) 60 cm circular
d) Overhead charges @ 0.1 on (a+b+c) 321.90
e) Contractor's profit @ 0.1 on (a+b+c+d) 354.09
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4464.06
say 4464.00
( iv ) 80 mm x 60 mm rectangular
d) Overhead charges @ 0.1 on (a+b+c) 477.57
e) Contractor's profit @ 0.1 on (a+b+c+d) 525.33
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 6347.74
say 6348.00
(v) 60 cm x 45 cm rectangular
d) Overhead charges @ 0.1 on (a+b+c) 311.62
e) Contractor's profit @ 0.1 on (a+b+c+d) 342.79
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4339.76
say 4340.00
(vi ) 60 cm x 60 cm square
d) Overhead charges @ 0.1 on (a+b+c) 382.75
e) Contractor's profit @ 0.1 on (a+b+c+d) 421.02
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 5200.32
say 5200.00
( vii ) 90 cm high octagon
d) Overhead charges @ 0.1 on (a+b+c) 629.30
e) Contractor's profit @ 0.1 on (a+b+c+d) 692.23
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 8183.61
say 8184.00

135
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
1.Any one area of aluminium sheeting given at (i) to (vii) may
Note be adopted as per site requirement and in accordance with
IRC : 67
2.Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters

3. The depth of foundation and quantity of cement concrete


in the foundation are indicative. These may be increased for
areas having higher wind velocities like in coastal areas.
This is applicable to all road signs and directions boards.

Direction and Place Identification Signs upto 0.9 sqm


8.5 801
Size Board.

Providing and erecting direction and place identification


retro-reflectorised sign as per IRC:67 made of high intensity
grade sheeting vide clause 801.3, fixed over aluminium
sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on a mild steel single angle iron post 75 x 75 x 6
mm firmly fixed to the ground by means of properly designed
foundation with M15 grade cement concrete 45 x 45 x 60
cm, 60 cm below ground level as per approved drawing

Unit = sqm
Taking output = 0.9 sqm
i) Excavation for foundation cum 0.216 189.00 40.82 Item No. 3.13
ii) Cement concrete M15 grade cum 0.120 4259.00 511.08 Item 12.8 (A)
iii) Painting angle iron post two coats sqm 0.430 40.00 17.20 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 195.43 1.95 L-12
Mazdoor day 0.200 187.43 37.49 L-13
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85 48.095 913.81 M-179 /1000
kg 19.000
metres long
Aluminium sheeting fixed with encapsulated lens type 7902.33 7112.09 M-061
sqm 0.900
reflective sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for drilling holes, nuts,
160.52
bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 171.02 3.42 P&M-053
d) Overhead charges @ 0.1 on (a+b+c) 822.93
e) Contractor's profit @ 0.1 on (a+b+c+d) 905.22
Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e 10526.54
Rate per sqm (for sign having area upto 0.9 sqm) =
11696.16
(I+ii+iii+a+b+c+d+e)/0.90
say 11696.00
I) Lettering and arrow marks on sign board to be provided
Note separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
Direction and Place Identification Signs with size more
8.6 801
than 0.9 sqm size Board.

Providing and erecting direction and place identification


retro- reflectorised sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick with area exceeding 0.9
sqm supported on a mild steel angle iron post 75 mm x 75
mm x 6 mm, 2 Nos. firmly fixed to the ground by means of
properly designed foundation with M 15 grade cement
concrete45 cm x 45 cm x 60 cm, 60 cm below ground level
as per approved drawing

Unit = sqm
Taking output = 1.50 sqm

136
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
i) Excavation for foundation cum 0.430 189.00 81.27 Item No. 3.13
ii) Cement concrete M15 grade cum 0.240 4259.00 1022.16 Item 12.8 (A)
iii) Painting angle iron post 2 coats sqm 0.860 40.00 34.40 Item 8.9
a) Labour (For fixing at site)
Mate day 0.010 195.43 1.95 L-12
Mazdoor day 0.300 187.43 56.23 L-13
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85 48.095 1827.62 M-179 /1000
kg 38.000
metres long, 2 nos
Aluminium sheeting fixed with encapsulated lens type 7902.33 11853.49 M-061
sqm 1.500
reflective sheeting
Add 2 per cent of cost of materials for drilling holes, nuts,
273.62
bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 171.02 3.42 P&M-053
d) Overhead charges @ 0.1 on (a+b+c) 1401.63
e) Contractor's profit @ 0.1 on (a+b+c+d) 1541.80
Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e 18097.60
Rate per sqm ( for sign having area more than 0.9
12065.06
sqm) = ( i+ii+iii+a+b+c+d+e)/1.50
say 12065.00
i) Lettering and arrow marks on sign board to be provided
Note separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
8.7 802 Overhead Signs

Providing and erecting overhead signs with a corrosion


resistant 2mm thick aluminium alloy sheet reflectorised with
high intensity retro-reflective sheeting of encapsulated lense
type with vertical and lateral clearance given in clause 802.2
and 802.3 and installed as per clause 802.7 over a designed
support system of aluminium alloy or galvanised steel
trestles and trusses of sections and type as per structural
design requirements and approved plans

A Truss and Vertical Support


Unit = tonne
Taking output = 1 tonne
a) Labour
Mate day 0.240 195.43 46.90 L-12
Blacksmith day 2.000 247.19 494.38 L-02
Mazdoor including for handling & fixing at site. day 4.000 187.43 749.72 L-13
b) Material
Aluminium alloy/galvanised steel including 5 per cent 46239.26 48551.23 M-060
tonne 1.050
wastage
Add 1 per cent on cost of material for nuts, bolts and drilling
485.51
and welding consumables
Add 15 per cent on cost of material for fabrication of trusses
7355.51
as per approved design
c) Machinery
Crane 3 tonne capacity hour 3.000 525.00 1575.00 P&M-013
Truck hour 0.500 752.00 376.00 P&M-057
d) Overhead charges @ 0.1 on (a+b+c) 5963.43
e) Contractor's profit @ 0.1 on (a+b+c+d) 6559.77
Rate per tonne = (a+b+c+d+e) 72157.45
say 72157.00
8.7 B Aluminium Alloy Plate for Over Head Sign
Unit = sqm

137
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Taking output = 1 sqm
a) Labour
Mate day 0.020 195.43 3.91 L-12
Blacksmith day 0.100 247.19 24.72 L-02
Mazdoor day 0.150 187.43 28.11 L-13
b) Material
Aluminium alloy plate,2 mm thick, fixed with high 1580.88 1580.88 M-059
sqm 1.000
intensity grade sheeting vide clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement, like
0.57
ladders, pulleys, ropes etc
c) Overhead charges @ 0.1 on (a+b) 163.82
d) Contractor's profit @ 0.1 on (a+b+c) 180.20
Rate per sqm = (a+b+c+d) 1982.21
say 1982.00
1. The cost of excavation and foundation concrete for fixing
of vertical support system to be worked out separately as
Note
per the approved drawing/design and to be included in the
estimate.
2. Lettering and arrow marks on sign board to be provided
separately as per actual requirement. Rates for these items
have been included separately in this chapter.
8.8 803 Painting Two Coats on New Concrete Surfaces
Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.120 195.43 23.45 L-12
Painter day 2.000 236.19 472.38 L-18
Mazdoor day 1.000 187.43 187.43 L-13
b) Material
Paint conforming to requirement of clause 803.3. Litre 6.000 138.35 830.12 M-132
Add for scaffolding @ 1 per cent of labour cost where
6.83
required
c) Overhead charges @ 0.1 on (a+b) 152.02
d) Contractor's profit @ 0.1 on (a+b+c) 167.22
Cost for 40 sqm = a+b+c+d 1839.46
Rate per sqm = (a+b+c+d)/40 45.99
say 46.00
8.9 803 Painting on Steel Surfaces
Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.030 195.43 5.86 L-12
Painter day 0.450 236.19 106.29 L-18
Mazdoor day 0.250 187.43 46.86 L-13
b) Material
Paint ready mixed approved brand. Litre 1.250 138.35 172.94 M-131
Add @ 1 per cent on cost of material for scaffolding 1.73
c) Overhead charges @ 0.1 on (a+b) 33.37
d) Contractor's profit @ 0.1 on (a+b+c) 36.70
Cost for 10 sqm = a+b+c+d 403.75
Rate per sqm= (a+b+c+d)/10 40.37

138
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
say 40.00
8.10 803 Painting on Wood Surfaces
Providing and applying two coats of ready mix paint of
approved brand on wood surface after thorough cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.030 195.43 5.86 L-12
Painter day 0.500 236.19 118.10 L-18
Mazdoor day 0.200 187.43 37.49 L-13
b) Material
Paint ready mixed of approved brand. Litre 1.500 138.35 207.53 M-131
Add @ 1 per cent on cost of material for scaffolding 2.08
c) Overhead charges @ 0.1 on (a+b) 37.10
d) Contractor's profit @ 0.1 on (a+b+c) 40.82
Cost for 10 sqm = a+b+c+d 448.97
Rate per sqm = (a+b+c+d)/10 44.90
say 45.00
Painting Lines, Dashes, Arrows etc on Roads in Two
8.11 803
Coats on New Work
Painting lines, dashes, arrows etc on roads in two coats on
new work with ready mixed road marking paint conforming to
IS:164 on bituminous surface, including cleaning the surface
of all dirt, dust and other foreign matter, demarcation at site
and traffic control
(i) Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.090 195.43 17.59 L-12
Painter day 0.550 236.19 129.90 L-18
Mazdoor day 1.550 187.43 290.52 L-13
b) Material
Road marking Paint as per IS :164 Litre 1.480 138.35 204.76 M-132
c) Overhead charges @ 0.1 on (a+b) 64.28
d) Contractor's profit @ 0.1 on (a+b+c) 70.70
Cost for 10 sqm = a+b+c+d 777.75
Rate per sqm= (a+b+c+d)/10 77.78
say 78.00
8.11 (ii) Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.070 195.43 13.68 L-12
Painter day 0.350 236.19 82.67 L-18
Mazdoor day 1.350 187.43 253.03 L-13
b) Material
Road marking paint Litre 1.480 138.35 204.76 M-132
c) Overhead charges @ 0.1 on (a+b) 55.41
d) Contractor's profit @ 0.1 on (a+b+c) 60.96
Cost for 10 sqm = a+b+c+d 670.51
Rate per sqm = (a+b+c+d)/10 67.05
say 67.00
Painting Lines, Dashes, Arrows etc on Roads in Two
8.12 803
Coats on Old Work

139
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Painting lines, dashes, arrows etc on roads in two coats on
old work with ready mixed road marking paint conforming to
IS: 164 on bituminous surface, including cleaning the
surface of all dirt, dust and other foreign matter, demarcation
at site and traffic control
(i) Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.060 195.43 11.73 L-12
Painter Ist class day 0.300 236.19 70.86 L-18
Mazdoor day 1.250 187.43 234.29 L-13
b) Material
Road marking paint Litre 0.900 138.35 124.52 M-132
c) Overhead charges @ 0.1 on (a+b) 44.14
d) Contractor's profit @ 0.1 on (a+b+c) 48.55
Cost for 10 sqm = a+b+c+d 534.08
Rate per sqm = (a+b+c+d)/10 53.41
say 53.00
8.12 (ii) Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.070 195.43 13.68 L-12
Painter Ist class day 0.350 236.19 82.67 L-18
Mazdoor day 1.350 187.43 253.03 L-13
b) Material
Road marking Paint Litre 0.900 138.35 124.52 M-132
c) Overhead charges @ 0.1 on (a+b) 47.39
d) Contractor's profit @ 0.1 on (a+b+c) 52.13
Cost for 10 sqm= a+b+c+d 573.41
Rate per sqm = (a+b+c+d)/10 57.34
say 57.00
Road Marking with Hot Applied Thermoplastic
8.13 803 Compound with Reflectorising Glass Beads on
Bituminous Surface

Providing and laying of hot applied thermoplastic compound


2.5 mm thick including reflectorising glass beads @ 250 gms
per sqm area, thickness of 2.5 mm is exclusive of surface
applied glass beads as per IRC:35 .The finished surface to
be level, uniform and free from streaks and holes.

Unit = sqm
Taking output = 640 sqm
a) Labour
Mate day 0.500 195.43 97.72 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery
Road marking machine @ 80 sqm per hour hour 8.000 85.86 686.88 P&M-043
Tractor-trolley hour 8.000 171.02 1368.14 P&M-053
c) Material
Hot applied thermoplastic compound Litre 2000.000 127.55 255097.14 M-118
Reflectorising glass beads kg 200.000 70.68 14135.96 M-152
d) Overhead charges @ 0.1 on (a+b+c) 27176.07
e) Contractor's profit @ 0.1 on (a+b+c+d) 29893.68
Cost for 640 sqm = a+b+c+d+e 328830.46

140
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Rate per sqm = a+b+c+d+e)/640 513.80
say 514.00
1. A sealing primer may be applied in advance on cement
concrete pavement to ensure proper bonding. Any laitance
Note
and/or curing compound to be removed where paint is
required to be applied on concrete surface.
2.Cost of painter is already included in hire charges of road
marking machine.
8.14 804 Kilometre Stone
Reinforced cement concrete M15grade kilometre stone of
standard design as per IRC:8-1980, fixing in position
including painting and printing etc
(i) 5th kilometre stone (precast)
Unit = Nos.
Taking output = 6 Nos.
a) M-15 grade of concrete cum 2.350 4259.00 10008.65 Item 12.8 (A)

b) Steel reinforcement @ 5 kg per sqm kg 22.080 66.758 1474.02 Item 13.6 /1000
189.00 317.52 Item No. 3.13
c) Excavation in soil for foundation cum 1.680

d) Painting two coats on concrete surface sqm 9.850 46.00 453.10 Item 8.8
e) Lettering on km post (average 30 letters of per cm per 0.40 720.00 Item 8.3
1800.000
10 cm height each) letter
Transportation and fixing
f) Labour
Mate day 0.260 195.43 50.81 L-12
Mason day 0.600 247.19 148.31 L-11
Mazdoor including loading/unloading day 6.000 187.43 1124.58 L-13
g) Machinery
Tractor-trolley hour 6.000 171.02 1026.11 P&M-053
h) Overhead charges @ 0.1 on (f+g) 234.98
i) Contractor's profit @ 0.1 on (f+g+h) 258.48
Cost for 6 Nos. 5th km stone = a+b+c+ d+e +f+g+h +i 15816.56
Rate for each 5th km stone = (a+b+c+d+e+f+g+h+i)/ 6 2636.09
say 2636.00
8.14 (ii) Ordinary kilometer stone (precast)
Unit = Nos.
Taking output = 14 Nos.
a) M-15 grade of concrete cum 3.770 4259.00 16056.43 Item 12.8 (A)
b) Steel reinforcement @ 5 kg per sqm kg 26.320 66.758 1757.07 Item 13.6 /1000
189.00 523.53 Item No. 3.13
c) Excavation in soil for foundation cum 2.770

d) Painting two coats on concrete surface sqm 11.410 46.00 524.86 Item 8.8
e) Lettering on km post ( average 12 letters of per cm per 0.40 672.00 Item 8.3
1680.000
10 cm height each) letter
Transportation and fixing
f) Labour
Mate day 0.320 195.43 62.54 L-12
Mason day 1.000 247.19 247.19 L-11
Mazdoor day 7.000 187.43 1312.01 L-13
g) Machinery
Tractor-trolley hour 6.000 171.02 1026.11 P&M-053
h) Overhead charges @ 0.1 on (f+g) 264.78
i) Contractor's profit @ 0.1 on (f+g+h) 291.26
Cost for 14 Nos. ordinary km stone = (a+b+ c+d+e+f+g+h+i)
22737.78

141
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Rate for each ordinary km stone = (a+b+
1624.13
c+d+e+f+g+h+j) /14
say 1624.00
8.14 (iii) Hectometer stone (precast)
Unit = Nos.
Taking output = 33 Nos.
a) M-15 grade of concrete cum 1.580 4259.00 6729.22 Item 12.8 (A)

b) Steel reinforcement @ 5 kg per sqm kg 66.000 66.758 4406.03 Item 13.6 /1000
c) Excavation in soil for foundation cum 1.390 189.00 262.71 Item No. 3.13
d) Painting two coats on concrete surface sqm 6.270 46.00 288.42 Item 8.8
e) Lettering on km post (average 1 letter of 10 per cm per 0.40 132.00 Item 8.3
330.000
cm height each) letter
Transportation and fixing
f) Labour
Mate day 0.340 195.43 66.45 L-12
Mason day 1.500 247.19 370.79 L-11
Mazdoor day 7.000 187.43 1312.01 L-13
g) Machinery
Tractor-trolley hour 6.000 171.02 1026.11 P&M-053
h) Overhead charges @ 0.1 on (f+g) 277.53
i) Contractor's profit @ 0.1 on (f+g+h) 305.29
Cost for 33 Nos. Hectometer stone = (a+b+c+d+e+f+ g+h+i)
15176.55
Rate for each Hectometer stone = (a+b +c +d+e+f+
459.90
g+h+i) / 33
say 460.00
The rate for excavation, cement concrete, steel
Note reinforcement, painting and lettering may be taken from
respective chapters.
8.15 805 Road Delineators

Supplying and installation of delineators (road way


indicators, hazard markers, object markers), 80-100 cm high
above ground level, painted black and white in 15 cm wide
strips, fitted with 80 x 100 mm rectangular or 75 mm dia
circular reflectorised panels at the top, buried or pressed into
the ground and conforming toIRC-79 and the drawings.

Unit = Each
Taking output= 30 Nos.
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor for fixing day 1.000 187.43 187.43 L-13
b) Material
Cost of approved type of delineators from ISI certified 451.08 13532.53 M-091
each 30.000
firm as per the standard drawing given in IRC - 79
Add 10 per cent cost of material for installation 1353.25
c) Overhead charges @ 0.1 on (a+b) 1508.10
d) Contractor's profit @ 0.1 on (a+b+c) 1658.91
Cost for 30 Nos. delineators = (a+b+ c+d) 18248.04
Rate per delineators = (a+b+c+d) /30 608.27
say 608.00

In case of soft ground, a proper foundation may be provided


as per approved design. In case foundation is required to be
Note
provided, the items of excavation and foundation concrete
are required to be measured and paid separately.

8.16 806 Boundary pillar


Reinforced cement concrete M15 grade boundary pillars of
standard design as per IRC:25-1967, fixed in position
including finishing and lettering but excluding painting

142
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Unit = Each
Taking output = 57 Nos.
a) M-15 grade of the boundary stone cum 1.250 4259.00 5323.75 Item 12.8 (A)

b) Steel reinforcement kg 79.800 66.758 5327.29 Item 13.6 /1000


c) Excavation in soil cum 10.720 189.00 2026.08 Item No. 3.13

per letter 0.40 912.00 Item 8.3


d) Lettering, each 10 cm high 2280.000
per cm high
Transportation and fixing
e) Labour
Mate day 0.570 195.43 111.40 L-12
Mazdoor day 14.250 187.43 2670.88 L-13
f) Machinery
Tractor-trolley hour 6.000 171.02 1026.11 P&M-053
g) Material
Stone spall cum 11.970 325.05 3890.89 M-008
h) Overhead charges @ 0.1 on (e+f+g) 769.93
i) Contractor's profit @ 0.1 on (e+f+g+h) 846.92
Cost for 57 Nos. boundary pillar = (a+b +c+d +e+ f+g+h+i )
22905.23
Rate for each boundary pillar = (a+b+c+d+e+
401.85
f+g+h+i)/57
say 402.00

In case of soft ground, a proper foundation may be provided


as per approved design. In case foundation is required to be
Note
provided, the items of excavation and foundation concrete
are required to be measured and paid separately.

8.17 807 G.I Barbed Wire Fencing 1.2 Metre High

Providing and fixing 1.2 metres high GI barbed wire fencing


with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed
every 3 metres center to center founded in M15 grade
cement concrete, 0.6 metre below ground level, every 15th
post, last but one end post and corner post shall be strutted
on both sides and end post on one side only and provided
with 9 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc
complete as per clause 807

Unit = per running metre


Taking output = 30 metres
a) Labour
Mate day 0.090 195.43 17.59 L-12
Blacksmith day 0.250 247.19 61.80 L-02
Mazdoor day 2.000 187.43 374.86 L-13
b) Material
Barbed wire 335 metres length @ 9.38 kg per 100 58.68 1843.61 M-063
kg 31.420
metres
MS angle iron 40 mm x 40mm x 6 mm, 23 metres in 48.095 3871.67 M-179 /1000
kg 80.500
length @ 3.5 kg per metre
Add for GI staple binding wire, drilling holes etc. @ 2 per
114.31
cent of the cost of material
c) Painting
Applying two coats of painting on exposed surface of 40.00 84.40 Item 8.9
sqm 2.110
angle iron posts ( Rate as per item no. 8.9)
d) Overhead charges @ 0.1 on (a+b) 628.38
e) Contractor's profit @ 0.1 on (a+b+d) 691.22
Cost for 30 metres fencing = a+b+c+d+e 7687.83
Rate per metre = (a+b+c+d+e)/30 256.26
say 256.00

143
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Cost of excavation for foundation and foundation concrete to
be added separately in the cost estimate as per approved
Note
design. The rate for these items may be taken from
respective chapters.
8.18 807 G.I Barbed Wire Fencing 1.8 Metre High
Providing and fixing 1.8 metres high GI barbed wire fencing
with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed
every 3 metres center to center founded in M15 grade
cement concrete, 0.6 metre below ground level, every 15th
post, last but one end post and corner post shall be strutted
on both sides and end post on one side only and provided
with 12 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc
complete as per clause 807
Unit = per running metre
Taking output = 30 metres
a) Labour
Mate day 0.120 195.43 23.45 L-12
Blacksmith day 0.400 247.19 98.88 L-02
Mazdoor day 2.500 187.43 468.58 L-13
b) Material
Barbed wire 428 metres length @ 9.38 kg per 100 58.68 2355.85 M-063
kg 40.150
metres
MS angle iron 50 mm x 50 mm x 6 mm,33.8 metres in 48.095 7310.49 M-179 /1000
kg 152.000
length @ 4.5 kg per metre
Add for GI staple, binding wire, drilling holes etc. @ 2
193.33
per cent of the cost of material
c) Painting
Applying two coats of painting on exposed surface of 40.00 158.40 Item 8.9
sqm 3.960
angle iron posts
d) Overhead charges @ 0.1 on (a+b) 1045.06
e) Contractor's profit @ 0.1 on (a+b+d) 1149.56
Cost for 30 metres fencing = a+b+c+d+e 12803.58
Rate per metre fencing = (a+b+c +d+e)/30 426.79
say 427.00
Cost of excavation for foundation and foundation concrete to
be added separately in the cost estimate as per approved
Note
design. The rate for these items may be taken from
respective chapters.
Suggest Fencing With Welded Steel Wire Fabric 75 mm x 50
8.19
ive mm

Providing 1.20 metre high fencing with angle iron posts 50


mm x 50 mm x 6 mm at 3 metre center to center with 0.40
metre embedded in M15 grade cement concrete, corner, end
and every 10th post to be strutted, provided with welded
steel wire fabric of 75 mm x 50 mm mesh or 75 mm x 25 mm
mesh and fixed to iron posts by flat iron 50 x 5 mm and bolts
etc. complete in all respects.
Unit = Running metre
Taking output = 30 m
a) Labour
Mate day 0.120 195.43 23.45 L-12
Welder day 1.000 247.19 247.19 L-02
Mazdoor day 2.000 187.43 374.86 L-13
b) Material
i) Angle iron for posts 50 x 50 x 6 mm kg 106.000 48.095 5098.10 M-179 /1000
ii) Runner flat 50 x 5 mm kg 26.000 48.095 1250.48 M-179 /1000
iii) Welded steel wire fabric 75x50 mm mesh @ 4
kg 151.000 input #VALUE! M-191
kg/sqm,4 x 30 x 1.2 + 5 per cent wastage
OR
Welded steel wire fabric 75 x 25 mm mesh @ 7.75
kg 293.000
kg/sqm, 7.75 x 30 x 1.2 + 5 per cent wastage

144
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Add 2.5 per cent of cost of material for drilling holes in
angles, flats, splitting angle at bottom, nuts and bolts and #VALUE!
welded consumables
c) Machinery
Tractor-trolley hour 0.100 171.02 17.10 P&M-053
d) Painting
Painting two coats including priming sqm 8.000 40.00 320.00 Item 8.9
e) Overhead charges @ 0.1 on (a+b+c) #VALUE!
f) Contractor's profit @ 0.1 on (a+b+c+e) #VALUE!
Cost for 30 metre = a+b+c+d+e+f #VALUE!
Rate per metre = (a+b+c+d+e+f)/30 #VALUE!
say #VALUE!
i) Adopt any one type of welded steel wire fabric 75 x 50 mm
Note
or 75 x 25 mm as per approved design.
ii) The item of excavation and cement concrete in foundation
shall be measured and paid separately
Tubular Steel Railing on Medium Weight Steel Channel
8.20 808
( ISMC series) 100 mm x 50 mm

Providing, fixing and erecting 50 mm dia steel pipe railing in


3 rows duly painted on medium weight steel channels (ISMC
series) 100 mm x 50 mm, 1.2 metres high above ground, 2
m centre to centre, complete as per approved drawings

Unit = Running metre


Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 189.00 244.94 Item No. 3.13
cum 1.296
0.6
ii) Foundation concrete M-15 grade PCC 6 x 0.6 x 4259.00 2759.83 Item 12.8 (A)
cum 0.648
0.6 x 0.3
iii) Painting of pipe sqm 4.710 40.00 188.40 Item 8.9
iv) Painting of channel section 6 nos,1.8 metres 40.00 86.40 Item 8.9
sqm 2.160
each 0.2 x 1.8 x 6 = 2.16
a) Labour (For fixing at site)
Mate day 0.010 195.43 1.95 L-12
Mazdoor day 0.250 187.43 46.86 L-13
Plumber day 0.010 247.19 2.47 L-02
b) Material
Steel pipe 50 mm external dia as per IS:1239 metre 30.000 172.29 5168.67 M-175
Medium weight steel channel (ISMC series) 100 mm x 48.095 4778.75 M-179 /1000
kg 99.360
50 mm,10.8 metres length @ 9.2 kg per metre
Add for drilling holes @ 2 per cent of cost of channels 95.57
c) Machinery
Tractor-trolley hour 0.040 171.02 6.84 P&M-053
d) Overhead charges @ 0.1 on (a+b+c) 1338.07
e) Contractor's profit @ 0.1 on (a+b+c+d) 1471.88
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 16190.64
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 1619.06
say 1619.00
Tubular Steel Railing on Precast RCC Posts, 1.2 m
8.21 808
High Above Ground Level
Providing, fencing and erecting 50 mm dia painted steel pipe
railing in 3 rows on precast M20 grade RCC vertical posts1.8
metres high (1.2 m above GL) with 3 holes 50 mm dia for
pipe, fixed 2 metres centre to, complete as per approved
drawing
Unit = Running metre
Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 189.00 244.94 Item No. 3.13
cum 1.296
0.6
ii) Foundation concrete M - 15 grade PCC 6 x 0.6 4259.00 2759.83 Item 12.8 (A)
cum 0.648
x 0.6 x 0.3

145
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
iii) RCC M - 20 for pre cast posts 6 nos of 1.8 5553.00 1776.96 Item 14.1(A)
cum 0.320
metres each
iv) Painting of pipe sqm 4.710 40.00 188.40 Item 8.9
a) Labour
Mate day 0.014 195.43 2.74 L-12
Mazdoor day 0.350 187.43 65.60 L-13
Plumber day 0.010 247.19 2.47 L-02
b) Material
Steel pipe 50 mm dia as per IS:1239 metre 30.000 172.29 5168.67 M-175
c) Machinery
Tractor-trolley hour 0.250 171.02 42.75 P&M-053
d) Overhead charges @ 0.1 on (a+b+c) 528.22
e) Contractor's profit @ 0.1 on (a+b+c+d) 581.05
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 11361.64
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 1136.16
say 1136.00
8.22 809 Reinforced Cement Concrete Crash Barrier

Provision of an Reinforced cement concrete crash barrier at


the edges of the road, approaches to bridge structures and
medians, constructed with M-20 grade concrete with HYSD
reinforcement conforming to IRC:21 and dowel bars 25 mm
dia, 450 mm long at expansion joints filled with pre-moulded
asphalt filler board, keyed to the structure on which it is built
and installed as per design given in the enclosure to MOST
circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994
as per dimensions in the approved drawing and at locations
directed by the Engineer, all as specified

Unit = Linear metre


Taking output = 10 m
(i) a) M 20 grade concrete
M 20 grade concrete cum 3.000 4259.00 12777.00 Item 14.1(A)
b) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor day 1.000 187.43 187.43 L-13
c) Material
HYSD steel reinforcement including dowel bars tonne 0.280 44187.50 12372.50 M-082
Pre-moulded asphalt filler board sqm 0.320 708.07 226.58 M-144
d) Overhead charges @ 0.1 on (b+c) 1279.43
e) Contractor's profit @ 0.1 on (b+c+d) 1407.38
Cost for 10 metre = a+b+c+d+e 28258.14
Rate per metre = (a+b+c+d+e)/10 2825.81
say 2826.00
i) Excavation and backfilling are incidental to work and not to
Note
be measured separately.
ii) Rate for RCC M 20 may be taken from chapter on super
structure.
8.23 810 Metal Beam Crash Barrier
A Type - A, "W" : Metal Beam Crash Barrier

Providing and erecting a "W" metal beam crash barrier


comprising of 3 mm thick corrugated sheet metal beam rail,
70 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 1.8 m high, 1.1 m below ground/road level, all steel
parts and fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal beam rail to
be fixed on the vertical post with a spacer of channel section
150 x 75 x 5 mm, 330 mm long complete as per clause 810

146
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Unit = Running metre
Taking output = 4.5 metre length
a) Labour
Mate day 0.060 195.43 11.73 L-12
Blacksmith day 0.500 247.19 123.60 L-02
Mazdoor day 1.000 187.43 187.43 L-13
b) Machinery
Tractor-trolley hour 0.100 171.02 17.10 P&M-053
c) Material
Corrugated sheet,3 mm thick, "W" beam section 48.095 1982.01 M-179 /1000
kg 41.210
railing,4.5 m in length
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 48.095 4259.32 M-179 /1000
kg 88.560
16.4 kg per metre
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @ 48.095 781.07 M-179 /1000
kg 16.240
16.4 kg per metre
Nuts and bolts kg 20.000 45.42 908.43 M-130
Add 25 per cent of the cost of material for fabrication, nuts,
1982.71
bolts and washers etc.)
d) Overhead charges @ 0.1 on (a+b+c) 1025.34
e) Contractor's profit @ 0.1 on (a+b+c+d) 1127.87
Cost for 4.5 metre = a+b+c+d+e 12406.60
Rate per metre = (a+b+c+d+e)/4.5 2757.02
say 2757.00
8.23 B Type - B, "THRIE" : Metal Beam Crash Barrier

Providing and erecting a "Thrie" metal beam crash barrier


comprising of 3 mm thick corrugated sheet metal beam rail,
85 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 2 m high with 1.15 m below ground level, all steel
parts and fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal beam rail to
be fixed on the vertical post with a space of channel section
150 x 75 x 5 mm, 546 mm long complete as per clause 810

Unit = Running metre


Taking output = 4.5 metre length
a) Labour
Mate day 0.060 195.43 11.73 L-12
Blacksmith day 0.500 247.19 123.60 L-02
Mazdoor day 1.000 187.43 187.43 L-13
b) Machinery
Tractor-trolley hour 0.100 171.02 17.10 P&M-053
c) Material
Corrugated sheet,3 mm thick, "Thrie" beam section 37.59 2741.84 M-088
kg 72.940
railing,4.5 m in length
Channel post 150 x 75 x 5 mm, 2 m long,3 Nos @ 16.4 48.095 4732.58 M-179 /1000
kg 98.400
kg per metre
Spacer 150 x 75 x 5 mm channel 0.546 m long,3 Nos kg 26.860 48.095 1291.84 M-179 /1000

Nuts and bolts kg 30.000 45.42 1362.65 M-130


Add 15 per cent of the cost of material for fabrication, nuts,
1519.34
bolts and washers etc.)
d) Overhead charges @ 0.1 on (a+b+c) 1198.81
e) Contractor's profit @ 0.1 on (a+b+c+d) 1318.69
Cost for 4.5 metre = a+b+c+d+e 14505.60
Rate per metre= (a+b+c+d+e)/4.5 3223.47
say 3223.00

147
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
In the case of median crash barrier, 'W' metal beam or thrie
beam section should be provided on both sides of the
Note vertical posts fixed in the median. Extra provision for metal
beam railing and spacer is required to be made when fixed
in the median depending on approved design.
8.24 811 Road Traffic Signals electrically operated
Since it is a ready made item commercially produced and
erected by specialised firm in the electrical and electronic
Note field, rate may be taken based on market enquiry from firms
specialised in this field and ISI certified for the approved
design and drawing.
Suggest
8.25 Flexible Crash Barrier, Wire Rope Safety Barrier
ive

Providing and erecting a wire rope safety barrier with vertical


posts of medium weight RS Joist (ISMB series) 100 mm x 75
mm (11.50 kg/m), 1.50 m long 0.85 m above ground and
0.65 m below ground level, split at the bottom for better grip,
embedded in M 15 grade cement concrete 450 x 450 x 450
mm, 1.50 m center to center and with 4 horizontal steel wire
rope 40 mm dia and anchored at terminal posts 15 m apart.
Terminal post to be embedded in M 15 grade cement
concrete foundation 2400 x 450 x 900 mm (depth),
strengthened by a strut of RS joist 100 x 75 mm, 2 m long
at 450 C inclination and a tie 100 x 8 mm, 1.50 m long at the
bottom, all embedded in foundation concrete as per
approved design and drawing, rate excluding excavation and
cement concrete.

Unit = Running metre


Taking output = 15 metre
a) Labour
Mate day 0.120 195.43 23.45 L-12
Mazdoor day 2.000 187.43 374.86 L-13
Blacksmith day 1.000 247.19 247.19 L-02
b) Material

i) RS Joist 100 x 75 mm - 16.5 m @ 11.5 kg per metre kg 190.000 48.095 9138.11 M-179 /1000

ii) Struts - 2 Nos. for terminal posts,2 m long each 2 x 2 48.095 2212.38 M-179 /1000
kg 46.000
x 11.50
iii) Tie 2 Nos. of 8 mm steel plate,1.5 sqm each for 48.095 9061.16 M-179 /1000
kg 188.400
terminal posts @ 62.80 kg/sqm (2 x 1.5)
iv) Steel wire rope 40 mm, including 7.50 per cent 29.76 1934.34 M-177
kg 65.000
extra for fixing at ends 15 x 4 x 1.075 @ 1 kg per m
Add 5 per cent of cost of material for drilling, gripping, fixing,
1117.30
fabrication and welding consumables
c) Painting
Applying 2 coats of painting on exposed surface sqm 16.500 40.00 660.00 Item 8.9
d) Machinery
Tractor-trolley hour 0.250 171.02 42.75 P&M-053
e) Overhead charges @ 0.1 on (a+b+d) 2415.15
f) Contractor's profit @ 0.1 on (a+b+d+e) 2656.67
Cost for 15 m = a+b+c+d+e+f 29883.36
Rate per m = (a+b+c+d+e+f)/15 1992.22
say 1992.00
The items of excavations and cement concrete works will be
Note measured and included separately as per the approved
designs and drawings.
Suggest
8.26 Anti-Glare Devices in Median
ive
A Plantation

148
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Plantation of shrubs and plants of approved species in the
median. apart from cutting off glare from vehicle coming from
opposite direction, these plants provide a pleasant
envoirenment and are eco-friendly. The rate for this item is
available in the chapter 11 on horticulture.
Anti-glare screen with 25 mm steel pipe framework
B
fixed with circular and rectangular vanes

Providing and erecting an anti - glare screen with 25 mm dia


vertical pipes fabricated and framed in the form of panels of
one metre length and 1.75 metre height fixed with circular
vane 250 mm dia at top and rectangular vane 600 x 300 mm
at the middle, made out of steel sheet of 3 mm thickness,
end vertical pipes of the panel made larger for embedding in
foundation concrete, applying 2 coats of paint on all exposed
surfaces, all as per approved design and drawings.

Unit = Running metre


Taking output = one metre
a) Labour
Mate day 0.004 195.43 0.78 L-12
Mazdoor day 0.100 187.43 18.74 L-13
b) Material
i) 25 mm steel pipe metre 16.000 97.11 1553.73 M-174
ii) MS sheet for 600 x 300 x 3 mm rectangular vane, 48.095 207.77 M-179 /1000
kg 4.320
one number @ 24kg/sqm
iii) MS sheet for 250 mm dia circular vane 3 mm thick,4 48.095 230.86 M-179 /1000
kg 4.800
numbers @ 24 kg/sqm
Add 5 per cent cost of material for fabrication, welding,
99.62
bending, nuts, bolts etc
c) Painting
Applying 2 coats of painting on exposed surface sqm 1.830 40.00 73.20 Item 8.9
d) Overhead charges @ 0.1 on (a+b) 211.15
e) Contractor's profit @ 0.1 on (a+b+d) 232.27
Rate per metre = a+b+c+d+e 2628.12
say 2628.00
The items of excavation and cement concrete as per
Note
approved design to be measured and paid separately
8.26 C Anti-glare screen with rectangular vane of MS sheet

Providing and erecting anti - glare screen with rectangular


vanes of size 750 x 500 mm made from MS sheet, 3 mm
thick and fixed on MS angle 50 x 50 x 6 mm at an angle of
450 C to the direction of flow of traffic, 1.5 m center to
center, top edge of the screen 1.75 m above ground level,
vertical post firmly embedded in M-15 cement concrete
foundation 0.60 m below ground level, applying 2 coats of
paint on exposed faces, all complete as per approved design
and drawings

Unit = Running metre


Taking output = 1.50 metre
a) Labour
Mate day 0.004 195.43 0.78 L-12
Mazdoor day 0.100 187.43 18.74 L-13
b) Material
i) Angle iron post,50 x 50 x 6 mm, length 2.35 m kg 10.580 48.095 508.85 M-179 /1000

ii) MS sheet 3 mm thick @ 24 kg/sqm kg 9.000 48.095 432.86 M-179 /1000

Add 5 percent of cost of material for fabrication,nuts,bolts etc 47.09


c) Machinery
Tractor-trolley hour 0.100 171.02 17.10 P&M-053
d) Painting

149
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Applying 2 coats of painting sqm 0.850 40.00 34.00 Item 8.9
e) Overhead charges @ 0.1 on (a+b+c) 102.54
f) Contractor's profit @ 0.1 on (a+b+c+e) 112.80
Cost for 1.5 m = a+b+c+d+e+f 1274.76
Rate per metre = (a+b+c+d+e+f)/1.50 849.84
say 850.00

The items of excavation and cement concrete as per


Note approved design to be measured and paid separately. Rate
of painting has been analaysed separately in this chapter.

Suggest
8.27 Street Lighting
ive
Providing and erecting street light mounted on a steel
circular hollow pole of standard specifications for street
lighting, 9 m high spaced 40 m apart, 1.8 m overhang on
both sides if fixed in the median and on one side if fixed on
the footpath, fitted with sodium vapour lamp and fixed firmly
in concrete foundation.
Unit = Each
Taking output = one light
a) Labour
Mate day 0.030 195.43 5.86 L-12
Mazdoor day 0.500 187.43 93.72 L-13
Electrician day 0.250 247.19 61.80 L-02
b) Material
i) Steel circular hollow pole of standard specification for #VALUE! #VALUE! M-171
street lighting to mount light at 9 m height above road each 1.000
level
ii) Sodium vapour lamp each 1.000 679.79 679.79 M-168
Add 5 per cent of cost of material for holder, electric cable,
#VALUE!
insulation, ladder, scaffolding etc
c) Painting
For Fixing in Median
Providing two coats of alluminium paint over steel 40.00 230.00 Item 8.9
sqm 5.750
circular hollow pipe with overhang on both sides
For fixing in Footpath
Providing two coats of alluminium paint over steel 40.00 185.20 Item 8.9
sqm 4.630
circular hollow pipe with overhang on one side
(i) For Fixing in Median
d) Overhead charges @ 0.1 on (a+b) #VALUE!
e) Contractor's profit @ 0.1 on (a+b+d) #VALUE!
Rate per light for fixing in Median= a+b+c+d+e #VALUE!
say #VALUE!
(ii) For fixing in Footpath
Rate per light for Fixing in Footpath = a+b+c+d+e #VALUE!
say #VALUE!
The items of excavation and cement concrete foundation will
be measured and included separately in the estimate as per
Note
approved design and drawing. The rate for painting has
been analysed in this chapter.
Suggest
8.28 Lighting on Bridges
ive
Providing and fixing lighting on bridges, mounted on steel
hollow circular poles of standard specifications, 5 m high
fixed on parapets with cement concrete, 20 m apart and
fitted with sodium vapour lamp
Unit = Each
Taking output = one light
a) Labour
Mate day 0.020 195.43 3.91 L-12
Mazdoor day 0.400 187.43 74.97 L-13

150
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Electrician day 0.200 247.19 49.44 L-02
b) Material
i) Steel circular hollow pole of standard specification for #VALUE! #VALUE! M-170
each 1.000
street lighting to mount light at 5 m above deck level
ii) Sodium vapour lamp 70 watt each 1.000 679.79 679.79 M-168
Add 1 per cent of cost of material for holder, electric cable,
#VALUE!
insulation, ladder, scaffolding etc
c) Painting
Providing two coats of alluminium paint over steel 40.00 110.40 Item 8.9
sqm 2.760
circular hollow pipe
d) Overhead charges @ 0.1 on (a+b) #VALUE!
e) Contractor's profit @ 0.1 on (a+b+d) #VALUE!
Rate per light = a+b+c+d+e #VALUE!
say #VALUE!
The items of cement concrete to be measured and paid
Note separately as per approved design. The rate for painting has
already been analysed in this chapter.
Suggest
8.29 Cable Duct Across the Road
ive

Providing and laying of a reinforced cement concrete pipe


duct, 300 mm dia, across the road (new construction),
extending from drain to drain in cuts and toe of slope to toe
of slope in fills, constructing head walls at both ends,
providing a minimum fill of granular material over top and
sides of RCC pipe as per IRC:98-1997, bedded on a 0.3 m
thick layer of granular material free of rock pieces, outer to
outer distance of pipe at least half dia of pipe subject to
minimum 450 mm in case of double and triple row ducts,
joints to be made leak proof, invert level of duct to be above
higher than ground level to prevent entry of water and dirt,
all as per IRC: 98 - 1997 and approved drawings.

Case(i) Single row for one utility service


Unit = Running metre
Taking output = 20metres
a) Random Rubble masonry/Brick masonry in 2977.00 7025.72 Item 12.7 ( B)
cum 2.360
cement mortar 1:6 for head wall both side
b) Labour
Mate day 0.050 195.43 9.77 L-12
Mazdoor day 1.000 187.43 187.43 L-13
Mazdoor skilled day 0.250 218.57 54.64 L-15
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 20.000 924.00 18480.00 M-151
Granular soil with PI less than 6 for bedding and sides 156.79 1128.87 M-009
cum 7.200
of pipe (0.6 x 0.6 x 20 m)
Collar for joints 300 mm dia each 9.000 input #VALUE! M-083
Cement mortar 1:2 for joints cum 0.020 4392.00 87.84 Item 12.6 (B)
d) Machinery
Tractor-trolley hour 0.500 171.02 85.51 P&M-053
e) Overhead charges @ 0.1 on (b+c+d) #VALUE!
f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!
Cost for 20 metre = a+b+c+d+e+f #VALUE!
Rate per metre = (a+b+c+d+e+f)/20 #VALUE!
say #VALUE!
8.29 Case(ii) Double row for two utility services
Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement 2977.00 10032.49 Item 12.7 ( B)
cum 3.370
mortar 1:6 for head wall both sides.
b) Labour
Mate day 0.050 195.43 9.77 L-12

151
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Mazdoor day 2.000 187.43 374.86 L-13
Mazdoor skilled day 0.250 218.57 54.64 L-15
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 40.000 924.00 36960.00 M-151
Granular soil with PI less than 6 for bedding and sides 156.79 2257.74 M-009
cum 14.400
of pipe (0.6 x 0.6 x 40 m)
Collar for joints 300 mm dia each 18.000 input #VALUE! M-083
Cement mortar 1:2 for joints cum 0.040 4392.00 175.68 Item 12.6 (B)
d) Machinery
Tractor-trolley hour 1.000 171.02 171.02 P&M-053
e) Overhead charges @ 0.1 on (b+c+d) #VALUE!
f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!
Cost for 20 metre = a+b+c+d+e+f #VALUE!
Rate per metre = (a+b+c+d+e+f)/20 #VALUE!
say #VALUE!
8.29 Case(iii) Triple rRow for three utility services

Unit = Running metre


Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement 2977.00 13039.26 Item 12.7 ( B)
cum 4.380
mortar 1:6 for head wall both sides.
b) Labour
Mate day 0.160 195.43 31.27 L-12
Mazdoor day 3.000 187.43 562.29 L-13
Mazdoor skilled day 1.000 218.57 218.57 L-15
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 60.000 924.00 55440.00 M-151
Granular soil with PI less than 6 for bedding and sides 156.79 3386.61 M-009
cum 21.600
of pipe (0.6 x 0.6 x 60 m)
Collar for joints 300 mm dia each 27.000 input #VALUE! M-083
Cement mortar 1:2 for joints cum 0.060 4392.00 263.52 Item 12.6 (B)
d) Machinery
Tractor-trolley hour 1.500 171.02 256.53 P&M-053
e) Overhead charges @ 0.1 on (b+c+d) #VALUE!
f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!
Cost for 20 metre = a+b+c+d+e+f #VALUE!
Rate per metre = (a+b+c+d+e+f)/20 #VALUE!
say #VALUE!
1.Inspection chamber at both ends is the responsibility of the
Note
agency who is laying the duct. Hence not included.
2.The rates for stone masonry / brick masonry and cement
mortar to be adopted from respective clauses.
Suggest
8.30 Highway Patrolling and Traffic Aid Post
ive
It is proposed to locate one Traffic Aid Post every 50-60 km
of the highway.
The organisation and financial aspect are required to be
finalised in consultation with administrative and traffic
authorities .

152
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Suggest Items Related to Underpass/ Subway/ Overhead
8.31
ive Bridge/ Overhead Foot Bridge
The items involved for underpass/ subway/ overhead bridge/
overhead foot bridge are earthwork, plain cement concrete,
plastering, painting, information sign etc. The rates for these
items are available in respective chapters which can be
adopted for the quantities derived from the approved
designs and drawings
Suggest
8.32 Traffic Control System and Communication System
ive
Providing a traffic control centre and communication system
including telecommunication facilities and related
accessories, CCTV, radar, vehicle detection camera, central
computer system
These are specialised item of telecommunication system
and are the commercial products. The designer is required
to contact the manufacturers to ascertain market prices. In
case of civil works required to be executed for these
installations, pricing may be done as per rates in relevant
chapters for quantities derived as per approved design and
drawing.
As regards the locations where such devices are required to
be installed, the traffic control authority should be consulted
to finalise the location
Suggest
8.33 Gantry Mounted Variable Message Sign Board
ive
Providing and erecting gantry mounted variable message
sign board electronically operated capable of flashing the
desired message over a designed support system of
aluminium alloy or galvanised steel, erected as per approved
design and drawings and with lateral clearance as per
clause 802.3
(i) Gantry Support System
Unit = tonne
Taking output=1 tonne
a) Labour
Mate day 0.120 195.43 23.45 L-12
Mazdoor day 2.000 187.43 374.86 L-13
Blacksmith day 1.000 247.19 247.19 L-02
b) Material
Alluminium alloy/galvanised steel including 5 per cent 46239.26 48551.23 M-060
tonne 1.050
wastage
Add 15 per cent of cost of material for fabrication and
7282.68
erection.
Add 1 per cent of cost of material for nuts, bolts and
485.51
welding
c) Machinery
Truck 10 tonne hour 1.000 752.00 752.00 P&M-057
d) Overhead charges @ 0.1 on (a+b+c) 5771.69
e) Contractor's profit @ 0.1 on (a+b+c+d) 6348.86
Rate per tonne = a+b+c+d+e 69837.48
say 69837.00
8.33 (ii) Message Display
Message display board 6 sqm electronically operated with
complete electronic fitments for flashing the pre-determined
messages.
This is a specilised commercial product and the lumpsum
rate including erection at site is required to be as certained
from the market and including in the rate analysis. The size
of the board will vary depending upon specific location.

153
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
The rate for the gantry mounted variable sign would be the
addition of cost of gantry support system as per approved
design determined at (i) above and the cost of message
display board as certained from the market at (ii) above

154
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Suggest
8.34 Traffic Impact Attenuators at Abutments and Piers
ive
A With Scrap Tyres
Provision and installation of traffic attenuators at
abutment/pier of flyovers bridges using scrap tyres of size
100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one
above the other and tied with 20 mm wire rope as per
approved design and drawings.
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 1.500 187.43 281.15 L-13
Blacksmith day 0.250 247.19 61.80 L-02
b) Material
Scrap tyres of size 900 x 20 each 80.000 59.20 4736.38 M-161
20 mm steel wire rope kg 150.000 29.76 4463.85 M-176
Add 1 per cent of cost of wire rope for clamps etc. 44.64
c) Machinery
Tractor-trolley hour 3.000 171.02 513.05 P&M-053
d) Overhead charges @ 0.1 on (a+b+c) 1011.65
e) Contractor's profit @ 0.1 on (a+b+c+d) 1112.82
Cost for 20 sqm = a+b+c+d+e 12240.97
Rate per sqm = (a+b+c+d+e)/20 612.05
say 612.00
8.34 B Using Plastic/Steel Barrel, Filled with Sand
Provision and installation of traffic impact attenuator at
abutment/pier of flyovers bridges using plastic/steel barrels
0.60 m dia and 1.0 m in height, filled with sand in three rows
and tied with20 mm steel wire rope as per approved design
and drawings
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.130 195.43 25.41 L-12
Mazdoor day 3.000 187.43 562.29 L-13
Blacksmith day 0.250 247.19 61.80 L-02
b) Material
Plastic barrels each 50.000
or
Steel barrels each 50.000 90.84 4542.17 M-172
Sand cum 8.000 209.13 1673.04 M-004
20 mm steel wire rope kg 15.000 29.76 446.39 M-176
Add 1 per cent of cost of wire rope for clamps etc. 4.46
c) Machinery
Tractor-trolley hour 2.000 171.02 342.04 P&M-053
d) Overhead charges @ 0.1 on (a+b+c) 765.76
e) Contractor's profit @ 0.1 on (a+b+c+d) 842.33
Cost for 20 sqm = a+b+c+d+e 9265.68
Rate per sqm = (a+b+c+d+e)/20 463.28
say 463.00
8.34 C With HI - DRO cell Sandwich (Patented)
(In this patented HI - DRO cell system, water gets
discharged from plastic tubes on impact over a pre-
determined time, thus absorbing the energy)

155
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Providing and installing a patentend HI - DRO cell system as
a traffic impact attenuators, using plastic tubes 50 cm dia,
1.2 m in height, 25 mm opening at the top, placed in three
rows, filled with water and tied with a 20 mm steel wire rope
Unit = sqm
Taking output = 10sqm
a) Labour
Mate day 0.100 195.43 19.54 L-12
Mazdoor day 2.500 187.43 468.58 L-13
b) Material
Plastic tubes 50 cm dia,1.2 m high each 40.000 #VALUE! #VALUE! M-139
Cost of water KL 12.000 167.07 2004.82 M-189
20 mm steel wire rope kg 100.000 29.76 2975.90 M-176
Add 1 per cent of cost of wire rope for clamps etc. 29.76
c) Machinery
Tractor-trolley hour 2.000 171.02 342.04 P&M-053
Water tanker6 KL capacity hour 2.000 111.24 222.48 P&M-060
d) Overhead charges @ 0.1 on (a+b+c) #VALUE!
e) Contractor's profit @ 0.1 on (a+b+c+d) #VALUE!
Cost for 10 sqm = a+b+c+d+e #VALUE!
Rate per sqm = (a+b+c+d+e)/10 #VALUE!
say #VALUE!
Suggest
8.35 Road Markers/Road Stud with Lense Reflector
ive
Road Markers/Road Stud with Lense Reflector
(Providing and fixing of road stud 100x 100 mm, vide
cl. 804.2 of MORTH (5th Revision), resistant to
corrosive effect of salt and grit, fitted with lense
reflectors, installed in concrete or asphaltic surface by
drilling hole 30 mm upto a depth of 60 mm and bedded
in a suitable bituminous grout or epoxy mortar, all as
per BS 873 part 4:1973)

Unit = Nos
Taking output = 50Nos
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor day 1.000 187.43 187.43 L-13
b) Material
Road studs 100 x 100 mm fitted with lense reflectors each 50.000 167.01 8350.30 M-062
Add 10 per cent of cost of material for fixing and installation 835.03
c) Overhead charges @ 0.1 on (a+b) 938.06
d) Contractor's profit @ 0.1 on (a+b+c) 1031.86
Cost for 50 studs = a+b+c+d 11350.49
Rate per studs = (a+b+c+d)/50 227.01
say 227.00
Suggest
8.36 Traffic Cone
ive
Provision of red fluorescent with white reflective sleeve traffic
cone made of low density polyethylene (LDPE) material
with a square base of 390 x 390 x 35 mm and a height of
770 mm, 4 kg in weight, placed at 1.5 m interval, all as per
BS 873
Unit = Running metre
Taking output = 68 Nos.
a) Labour
Mate day 0.020 195.43 3.91 L-12
Mazdoor day 0.500 187.43 93.72 L-13
b) Material

156
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Traffic cones with 150 mm reflective sleeve each 68.000 394.70 26839.51 M-186

157
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
c) Machinery
Tractor-trolley hour 0.100 171.02 17.10 P&M-053
d) Overhead charges @ 0.1 on (a+b+c) 2695.42
e) Contractor's profit @ 0.1 on (a+b+c+d) 2964.97
Cost for 68 Nos. = a+b+c+d+e 32614.62
Rate per metre = (a+b+c+d+e)/68 479.63
say 480.00
Suggest
8.37 Roadside Amenities
ive
A Rest areas
Providing plainly furnished accommodation for rest rooms,
dormitories, restaurants, stalls, shops, petrol pump,
telephone booth, first aid room, traffic aid post, police
assistance booth, including electricity, toilet and sewerage
system
Pricing may be done based on current plinth area rates
approved by PWD/CPWD/MES for a particular zone. Area is
required to be assessed for specific location as per actual
site conditions
Parking areas and bus laybyes for trucks, buses and
B
light vehicles
Pricing of parking areas may be done for the quantities of
various items based on the approved dimensions and
pavement design for a particular terrain and soil. Rates for
items may be from respective chapters.
C Lawn
Providing a lawn planted with grass and its maintenance
Pricing of lawn may be done as per rates given in the
chapter on horticulture for the quantities as per approved
dimensions in the drawings
Suggest
8.38 Rumble Strips
ive
Provision of 15 nos rumble strips covered with premix
bituminous carpet, 15-20 mm high at center, 250 mm wide
placed at 1 m center to center at approved locations to
control speed, marked with white strips of road marking
paint.
Unit = sqm
Taking output = 100 sqm (including gaps)
The rate per sqm of premix carpet and road marking may be
adopted from chapter 5 & 8 respectively for the quantities
calculated from approved drawings
Suggest
8.39 Policeman Umbrella
ive
Provision of a 2 m high (floor to roof) umbrella for traffic
policeman at road crossings, where necessary, installed on a
raised platform, built on a central support of a steel pipe 100
mm dia, roof made of 25 mm dia steel pipe to provide
covered area of 3 sqm, roofed with CGI sheets, all steel
parts to be given 2 coats of paint
Unit = each
Taking output = one number
Earthwork Quantities of these items to be cum
Cement Concrete calculated as per approved design and cum
cost added as per rates of these items
brick masonry or given in chapter 3 and 13 cum
stone masonry cum
Painting sqm 2.500
a) Labour
Mate day 0.090
Mazdoor day 1.000
Blacksmith day 1.000
Welder day 0.250

158
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
b) Material
Steel pipe 100 mm dia metre 3.500
Steel pipe 25 mm dia metre 10.000
CGI sheets kg 8.000
Add 25 per cent of cost of material for fabrication
Add 2 per cent of cost of material for welding consumables,
J-hooks, washers etc.
c) Machinery
Tractor-trolley hour 0.500
d) Overheads @ per cent on (a+b+c)
e) Contractors Profit@ per cent on (a+b+c+d)
Rate per policeman umbrella = a+b+c+d+e
suggesti
8.40 High Mast Pole Lighting at Interchanges and Flyovers
ve

Providing and erecting a high mast pole lighting with 30 m


high hot dip galvanised mast designed to withstand forces
exerted with wind speeds of 180 km per hour with 3 seconds
gust, as per IS:875 (Part 3) - 1978, fitted with a base flange,
door at the base of mast with heavy duty internal lock,
lantern carriage, suitable winching arrangement for safe
working load of 750 kg and high powered electrically driven
power tools for raising and lowering of lantern carriage,
flexible 8 core electric cable, lightening conductor, earthing
terminal, and fixing 2 nos aviation obstruction lights on top of
the mast, all complete as per approved design and drawings

This is a specialised work and is generally done by firms


who specialise in such jobs. The detailed designs and
estimates are submitted by the firms along with their tender
for checks by the Department. The cost of this work is
required to be worked out based on approved design,
drawings and estimate of the lowest tender. A separate
contract for this work is concluded as the contractors for
road and bridge works generally donot undertake such jobs.

8.41 Toll Plaza


The construction, operation and maintenance of Toll Plaza
can be broken into separate items of work as under based
on the approved design and drawings:-
a) Provision of toll collection service lane to separate
different categories of vehicles for purpose of toll collection.
This involves considerable increase in carriage way width
b) Provision of 2.5 m wide separators for different toll
collection service lanes for safety
c) Toll booths with integrated roof cover
d) Barrier gates for individual lanes
e) Provision of building to provide facility to toll plaza
personnel
f) Toll plaza office equipment and furniture
g) Water supply, electricity, sanitation, septic-tank system
and drainage
h) Telephone, intercomes, wireless communication
system
i) High mast lighting
j) Pavement marking
k) Overhead signs
l) Fixed message signs (Advance)
m) Variable message signs
n) Traffic cones and pylons
o) First aid post
p) Traffic aid post and security

159
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
The quantities for the above mentioned items may be
calculated from the approved design and drawings and their
rates adopted from respective chapters of the Standard Data
Book
8.42 Safety Devices and Signs in Construction Zones

Provision and fixing of traffic signs for limited period at


suitable locations in construction zone comprising of warning
zone, approach transition zone, working zone and terminal
transition zone with a minimum distance of 60 cm from the
edge of the kerb in case of kerbed roads and 2 to 3 m from
the edge of the carriageway in case of un-kerbed roads, the
bottom edge of the lowest sign plate to be not less than 2 m
above the road level, fixed on 60 mm x 60 mm x 6 mm angle
iron post, founded and installed as per approved design and
drawings, removed and disposed of after completion of
construction work, all as per IRC:SP:55-2001

Unit = each
Taking output = one sign post
Following types of signs are required to be fixed in
construction zones for safety of traffic
a) Diversion one km ahead
b) Traffic sign ahead
c) Road ahead closed
d) Men at work
e) Road narrow
f) Single file traffic
g) Right lane diverted
h) Left lane diverted
i) Right lane closed
j) Left lane closed
k) Median closed
l) Diversion to other carriageway
m) Traffic signal ahead
n) Two way traffic
o) Un - even road
p) Slippery road
q) Loose chippings
r) Dual carriageway ends
s) Diversion
t) Do not enter
u) Road closed
v) Stop
w) Slow
x) One way
y) Give way
z) Overtaking prohibited
aa) Speed limit
bb) Weight limit
cc) Height and length limit
dd) No stopping or standing
ee) Any other warning or regulatory safety sign as per
site requirement and consistent with IRC:SP:55-2001 and
IRC:67
The rate for traffic signs are already worked out and given
elsewhere in this chapter. The same may be adopted.
suggesti
8.43 Portable Barricade in Construction Zone
ve

160
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.

Installation of a steel portable barricade with horizontal rail


300 mm wide, 2.5 m in length fitted on a 'A' frame made with
45 x 45 x 5 mm angle iron section, 1.5 m in height,
horizontal rail painted (2 coats) with yellow and white stripes,
150 mm in width at an angle of 450 C, 'A' frame painted with
2 coats of yellow paint, complete as per IRC:SP:55-2001

Unit = each
Taking output = one steel portable barricade
a) Labour
Mate day 0.020 195.43 3.91 L-12
Mazdoor day 0.250 187.43 46.86 L-13
Painter day 0.500 236.19 118.10 L-18
Welder day 0.250 247.19 61.80 L-02
b) Material
Angle iron 45 x 45 x 5 mm kg 25.000 48.095 1202.38 M-179 /1000
MS sheet 300 mm wide,2.5 m long and 2.6 mm thick kg 15.000 48.095 721.43 M-179 /1000
Paint litre 0.500 138.35 69.18 M-131
Add 2 per cent of cost of steel for welding consumables,
38.48
nuts & bolts and drilling holes
c) Overhead charges @ 0.1 on (a+b) 226.21
d) Contractor's profit @ 0.1 on (a+b+c) 248.83
Rate per barricade = a+b+c+d 2737.17
say 2737.00
suggesti
8.44 Permanent Type Barricade in Construction Zone
ve
A With steel components
Construction of a permanent type barricade made of steel
components, 1.5 m high from road level, fitted with 3
horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5
mm angle iron vertical support, painted with yellow and white
strips, 150 mm in width at an angle of 45 0 C, complete as
per IRC:SP:55-2001
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.050 195.43 9.77 L-12
Mazdoor day 0.300 187.43 56.23 L-13
Painter day 0.600 236.19 141.71 L-18
Welder day 0.300 247.19 74.16 L-02
b) Material
Angle iron 50 x 50 x 5 mm,2 m long,2 Nos. kg 15.000 48.095 721.43 M-179 /1000
MS sheet of 12 SWG,3 Nos of 200 mm width and 4 m 48.095 2404.77 M-179 /1000
kg 50.000
length
Paint litre 1.000 138.35 138.35 M-131
Add 1 per cent of cost of steel for welding consumables,
31.26
nuts & bolts and drilling holes
c) Overhead charges @ 0.1 on (a+b) 357.77
d) Contractor's profit @ 0.1 on (a+b+c) 393.54
Rate per barricade = a+b+c+d 4328.99
say 4329.00
8.44 B With wooden components
Construction of a permanent type barricade made of wooden
components, 1.5 m high from road level, fitted with 3
horizontal planks 200 mm wide and 3.66 m long on 100 x
100mm wooden vertical post, painted with yellow and white
strips, 150 mm in width at an angle of 45 0 C, complete as
per IRC:SP:55-2001
Unit = each

161
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Taking output = one barricade
a) Labour
Mate day 0.050 195.43 9.77 L-12
Mazdoor day 0.300 187.43 56.23 L-13
Painter day 0.600 236.19 141.71 L-18
Carpenter day 0.600 247.19 148.31 L-04
b) Material
Timber cum 0.180 31666.24 5699.92 M-185
Add 1 per cent of cost of timber for nuts & bolts, nails, etc. 57.00
c) Overhead charges @ 0.1 on (a+b) 611.30
d) Contractor's profit @ 0.1 on (a+b+c) 672.42
Rate per barricade = a+b+c+d 7396.67
say 7397.00
8.44 C With bricks
Construction of a permanent type barricade made with brick
work in mud mortar, 1.5 m high, 4 m long, 600 mm thick,
plastered with cement mortar 1:6, painted with yellow and
white strips
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.240 195.43 46.90 L-12
Mazdoor day 3.000 187.43 562.29 L-13
Painter day 1.000 236.19 236.19 L-18
Mason day 2.000 247.19 494.38 L-11
b) Material
Brick each 1800.000 4.72 8499.67 M-079
Cement kg 22.000 5.982 131.61 M-081 /1000
Sand cum 0.090 209.13 18.82 M-005
Paint litre 1.250 138.35 172.94 M-131
c) Overhead charges @ 0.1 on (a+b) 1016.28
d) Contractor's profit @ 0.1 on (a+b+c) 1117.91
Rate per barricade = a+b+c+d 12297.00
say 12297.00
suggesti
8.45 Drum Delineator in Construction Zone
ve
Provision of metal drum/empty bitumen drum delineator, 300
mm in diameter, 800 mm high, filled with earth for stability,
painted in circumferential strips of alternate black and white
100 mm wide fitted with reflectors 3 Nos of 7.5 cm dia, all as
per IRC:SP:55-2001
Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.020 195.43 3.91 L-12
Mazdoor day 0.250 187.43 46.86 L-13
Painter day 0.250 236.19 59.05 L-18
b) Material
Steel drum 300 mm dia 1.2 m high/empty bitumen 90.84 90.84 M-172
each 1.000
drum
Paint litre 0.500 138.35 69.18 M-131
c) Overhead charges @ 0.1 on (a+b) 26.98
d) Contractor's profit @ 0.1 on (a+b+c) 29.68
Rate per drum delineator = a+b+c+d 326.50
say 326.00
suggesti
8.46 Flagman
ve

162
Ref. to
Cost Remarks/ Input
Sr No MoRTH Description Unit Quantity Rate Rs
Rs ref.
Spec.
Positioning of a smart flagman with a yellow vest and a
yellow cap and a red flag 600 x 600 mm securely fastened to
a staff 1 m in length for guiding the traffic
Unit = each
Taking output = one flagman
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor day 1.000 187.43 187.43 L-13
b) Material
Flag of red color cloth 600 x 600 mm each 1.000 34.46 34.46 M-099
Wooden staff for fastening of flag 25 mm dia, one m 22.52 22.52 M-196
each 1.000
long
c) Overhead charges @ 0.1 on (a+b) 25.22
d) Contractor's profit @ 0.1 on (a+b+c) 27.74
Rate per flagman = a+b+c+d 305.19
say 305.00

163
CHAPTER-9
PIPE CULVERTS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
9.1 408 PCC 1:3:6 in Foundation
Plain cement concrete 1:3:6 mix with crushed stone
aggregate 40 mm nominal size mechanically mixed, placed
in foundation and compacted by vibration including curing for
14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.640 195.43 125.08 L-12
Mason day 1.000 247.19 247.19 L-11
Mazdoor day 15.000 187.43 2811.45 L-13
b) Material
40mm Aggregate at site cum 13.800 780.12 10765.64 M-055
Sand at site cum 6.900 209.13 1443.00 M-005
Cement at site tonne 3.300 5982.46 19742.11 M-081
Cost of water KL 18.000 167.07 3007.23 M-189
c) Machinery
Concrete mixer0.4/ 0.28 cum hour 6.000 211.68 1270.08 P&M-009
Generator set 33 KVA hour 6.000 342.36 2054.16 P&M-079
Water tanker6 KL capacity hour 3.000 111.24 333.72 P&M-060
d) Overhead charges @ 0.1 on (a+b+c) 4179.96
e) Contractor's profit @ 0.1 on (a+b+c+d) 4597.96
Cost for 15 cum = a+b+c+d+e 50577.57
Rate per cum = (a+b+c+d+e)/15 3371.84
say 3372.00
Note Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
9.2 2900 Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Single Row .
Laying Reinforced cement concrete pipe NP4/prestressed
concrete pipe for culverts on first class bedding of granular
material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .
Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length
each )
A 1000 mm dia
a) Labour
Mate day 0.180 195.43 35.18 L-12
Mason day 0.500 247.19 123.60 L-11
Mazdoor day 4.000 187.43 749.72 L-13
b) Material
Sand at site cum 0.070 209.13 14.64 M-005
Cement at site tonne 0.050 5982.46 299.12 M-081
RCC pipe NP-4 /prestressed concrete pipe including metre 12.500 4395.60 54945.00 M-149
collar at site
Granular material passing 5.6 mm sieve for bedding cum 4.500 156.79 705.54 M-009
c) Overhead charges @ 0.1 on (a+b) 5687.28
d) Contractor's profit @ 0.1 on (a+b+c) 6256.01
Cost for 12.5 metres = a+b+c+d 68816.08
Rate per metre = (a+b+c+d)/12.5 5505.29
say 5505.00
Note 1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

9.2 B 1200 mm dia


a) Labour

162
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 0.280 195.43 54.72 L-12
Mason day 1.000 247.19 247.19 L-11
Mazdoor day 6.000 187.43 1124.58 L-13
b) Material
Sand at site cum 0.090 209.13 18.82 M-005
Cement at site tonne 0.070 5982.46 418.77 M-081
RCC pipe NP-4/prestressed concrete pipe including metre 12.500 5319.60 66495.00 M-150
collar at site
Granular material passing 5-6 mm sieve for class cum 5.000 156.79 783.94 M-009
bedding
c) Overhead charges @ 0.1 on (a+b) 6914.30
d) Contractor's profit @ 0.1 on (a+b+c) 7605.73
Cost for 12.5 metres = a+b+c+d 83663.05
Rate per metre= (a+b+c+d)/12.5 6693.04
say 6693.00
Note 1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

9.3 2900 Laying Reinforced Cement Concrete Pipe NP4 /


Prestressed Concrete Pipe on First Class Bedding in
Double Row .
Laying Reinforced cement concrete pipe NP4 / prestressed
concrete pipe for culverts on first class bedding of granular
material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .

Unit = metre
Taking output = 12.5 metres ( 10 pipes of 2.5 m length
each in two rows.)
A 1000 mm dia
a) Labour
Mate day 0.360 195.43 70.35 L-12
Mason day 1.000 247.19 247.19 L-11
Mazdoor day 8.000 187.43 1499.44 L-13
b) Material
Sand at site cum 0.140 209.13 29.28 M-005
Cement at site tonne 0.100 5982.46 598.25 M-081
RCC pipe NP-4/prestressed concrete pipe including metre 25.000 4395.60 109890.00 M-149
collar at site
Granular material passing 5.6 mm sieve for bedding cum 12.500 156.79 1959.84 M-009
c) Overhead charges @ 0.1 on (a+b) 11429.43
d) Contractor's profit @ 0.1 on (a+b+c) 12572.38
Cost for 12.5 metres = a+b+c+d 138296.16
Rate per metre = (a+b+c+d)/12.5 11063.69
Note 1. In case of cement craddle bedding, quantity of PCC M15 say 11064.00
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

9.3 B 1200 mm dia


a) Labour
Mate day 0.560 195.43 109.44 L-12
Mason day 2.000 247.19 494.38 L-11
Mazdoor day 12.000 187.43 2249.16 L-13

163
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Material
Sand at site cum 0.180 209.13 37.64 M-005
Cement at site tonne 0.140 5982.46 837.54 M-081
RCC pipe NP-4 /prestressed concrete pipe including metre 25.000 5319.60 132990.00 M-150
collar at site
Granular material passing 5-6 mm sieve for class cum 13.750 156.79 2155.83 M-009
bedding
c) Overhead charges @ 0.1 on (a+b) 13887.40
d) Contractor's profit @ 0.1 on (a+b+c) 15276.14
Cost for 12.5 metres = a+b+c+d 168037.53
Rate per metre= (a+b+c+d)/12.5 13443.00
Note 1. In case of cement craddle bedding, quantity of PCC M15 say 13443.00
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

164
CHAPTER- 10
MAINTENANCE OF ROADS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
10.1 3002 Restoration of Rain Cuts
Restoration of rain cuts with soil, moorum, gravel or a
mixture of these, clearing the loose soil, benching for 300
mm width, laying fresh material in layers not exceeding 250
mm and compacting with plate compactor or power rammers
to restore the original alignment, levels and slopes

Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery
Excavator1.0 cum bucket capacity @ 60 cum per hour hour 0.130 1516.32 197.12 P&M-026
Tipper ( L is average lead in km for borrow earth) tonne.km 12 x L 2.27 27.22 Lead =1 km &
P&M-058
Add 10 per cent of cost of carriage towards loading and 2.72
unloading charges.
Plate compactor hour 0.500 142.99 71.50 P&M-086
c) Overhead charges @ 0.1 on (a+b) 68.90
d) Contractor's profit @ 0.1 on (a+b+c) 75.80
Cost for 10 cum = a+b+c+d 833.75
Rate per cum = (a+b+c+d)/10 83.38
say 83.00
Note Only 75 per cent of fresh material has been provided as 25
per cent can be retrieved at site from earth that is flown
down the slope in the form of slurry and deposited at the foot
of the rain cuts
10.2 3003 Maintenance of Earthen Shoulder (filling with fresh
soil)
Making up loss of material/ irregularities on shoulder to the
design level by adding fresh approved soil and compacting it
with appropriate equipment.
Unit = sqm
Taking output = 100 sqm
Assuming average thickness of filling to be 150 mm
Quantity of fresh material = 15 cum
a) Labour
Mate day 0.180 195.43 35.18 L-12
Mazdoor day 4.500 187.43 843.44 L-13
b) Machinery
Excavator1.0 cum bucket capacity @ 60 cum per hour hour 0.250 1516.32 379.08 P&M-026
Tipper ( L is average lead in km for borrow earth) tonne.km 24xL 2.27 54.43 Lead =1 km &
P&M-058
Add 10 per cent of cost of transportation to cover cost of 5.44
loading and unloading
Plate compactor @ 25 sqm per hour hour 12.000 142.99 1715.90 P&M-086
c) Overhead charges @ 0.1 on (a+b) 303.35
d) Contractor's profit @ 0.1 on (a+b+c) 333.68
Cost for 100 sqm = a+b+c+d 3670.50
Rate per sqm = (a+b+c+d)100 36.71
say 37.00
10.3 3003 Maintenance of Earth Shoulder (stripping excess soil)

Stripping excess soil from the shoulder surface to achieve


the approved level and compacting with plate compactor
Unit = sqm
Taking output = 100 sqm
Assuming average depth of stripping as 75 mm
Quantity of earth cutting involved = 7.5 cum
a) Labour
Mate day 0.100 195.43 19.54 L-12
Mazdoor day 2.500 187.43 468.58 L-13
b) Machinery

165
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Plate compactor @ 25 sqm per hour hour 4.000 142.99 571.97 P&M-086
c) Overhead charges @ 0.1 on (a+b) 106.01
d) Contractor's profit @ 0.1 on (a+b+c) 116.61
Cost for 100 sqm = a+b+c+d 1282.70
Rate per sqm on = (a+b+c+d)100 12.83
say 13.00
Note The earth stripped from earthen shoulders to be dumped on
the side slopes locally for disposal.
10.4 3004.2 Filling Pot-holes and Patch Repairs with open-Graded
Premix surfacing, 20mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as per clause 511, compacting, trimming and
finishing the surface to form a smooth continuous surface, all
as per clause 3004.2

Unit = Sqm
Taking out put = 10250 sqm (205 cum)(405 tonne)
a) Labour
Mate Day 3.760 195.43 734.82 L-12
Mazdoor Day 90.000 187.43 16868.70 L-13
Mazdoor skilled Day 4.000 218.57 874.28 L-15
b) Machinery
Air compressor 250 cfm hour 6.000 293.76 1762.56 P&M-001
HMP 100-110 TPH Capacity hour 6.000 32155.00 192930.00 P&M-022
Tipper 10 tonnes capacity hour 45.000 846.00 38070.00 P&M-048
Smooth wheeled roller 8-10 tonnes hour 12.000 649.00 7788.00 P&M-044
c) Material
Crushed stone aggregates nominal size 13.2mm @ cum 184.500 777.69 143483.97 M-052
0.18 cum per 10 sqm
Crushed stone aggregates nominal size 11.2mm @ cum 92.250 674.15 62190.47 M-051
0.09 cum/10 sqm
Bitumen 80/100 @ 14.6 kg per 10 sqm tonne 14.970 38958.19 583204.12 M-075
Bitumen emulsion for tack coat including vertical sides tonne 2.460 40114.31 98681.21 M-077
of pot hole.
d) Overhead charges @ 0.1 on (a+b+c) 114658.81
e) Contractor's profit @ 0.1 on (a+b+c+d) 126124.70
Cost for 10250 sqm = a+b+c+d+e 1387371.65
Rate per sqm = (a+b+c+d+e)/10250 135.35
say 135.00
10.5 3004.2 Filling Pot-holes and Patch Repairs with Bituminous
concrete, 40mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as per clause 504, compacting, trimming and
finishing the surface to form a smooth continuous surface, all
as per clause 3004.2

Unit = Sqm
Taking out put = 4900 sqm (196 cum)(450 Tonnes)
a) Labour
Mate Day 2.920 195.43 570.66 L-12
Mazdoor Day 70.000 187.43 13120.10 L-13
Mazdoor skilled Day 3.000 218.57 655.71 L-15
b) Machinery
Air compressor 250 cfm hour 6.000 293.76 1762.56 P&M-001
HMP 100-110 TPH Capacity hour 6.000 32155.00 192930.00 P&M-022
Tipper 10 tonnes capacity hour 45.000 846.00 38070.00 P&M-048

166
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Smooth wheeled roller 8-10 tonnes hour 12.000 649.00 7788.00 P&M-044
c) Material
I) Bitumen tonne 22.500 38958.19 876559.31 M-075
ii) Bitumen emulsion for tack coat . tonne 1.180 40114.31 47334.89 M-077
iii) Aggregates
Grading I - 19mm(Nominal size)
20-10mm 35 per cent cum 99.750 1119.81 111701.16 M-045

10-5 mm 23 per cent cum 65.550 764.37 50104.63 M-025,M-040


5mm and below 40 per cent cum 114.000 221.82 25287.50 M-030
Filler 2 per cent by weight of aggregate tonne 8.620 4427.31 38163.39 M-188
Add 5 per cent for wastage 1908.17
or
Grading-II 13mm (Nominal size)
13.2-10 mm 30 per cent cum 85.500 936.51 80071.70 M-044
10-5 mm 25 per cent cum 71.250 764.37 54461.55 M-025
5 mm and Below43 per cent cum 122.550 221.82 27184.07 M-030
Filler 2 per cent tonne 8.620 4427.31 38163.39 M-188
Add 5 per cent for wastage 1908.17
Any one of the above alternatives of aggregate i.e. 19mm or
13mm nominal size may be adopted as per approved
design.
10.5 (i) for grading I Material
d) Overhead charges @ 0.1 on (a+b+c) 140595.61
e) Contractor's profit @ 0.1 on (a+b+c+d) 154655.17
Cost for 4900 cum = a+b+c+d+e 1701206.85
Rate per cum = (a+b+c+d+e)/4900 347.19
say 347.00
#VALUE!
10.5 (ii) for grading II Material
d) Overhead charges @ 0.1 on (a+b+c) 138058.01
e) Contractor's profit @ 0.1 on (a+b+c+d) 151863.81
Cost for 4900 cum = a+b+c+d+e 1670501.93
Rate per cum = (a+b+c+d+e)/4900 340.92
say 341.00
#VALUE!
Note For detailed working of quantities of aggregates, refer item
5.8 of chapter 5
10.6 3004.3. Crack Filling
3
Filling of crack using slow - curing bitumen emulsion and
applying crusher dust in case crack are wider than 3mm.
Unit = Running Meter
Taking out put = 500m
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor day 1.000 187.43 187.43 L-13
b) Material
Slow-curing bitumen emulsion Kg 33.000 40.11 1323.77 M-077
Stone crusher dust cum 0.020 215.86 4.32 M-021
c) Overhead charges @ 0.1 on (a+b) 152.33
d) Contractor's profit @ 0.1 on (a+b+c) 167.57
Cost for 500sqm = a+b+c+d 1843.24
Rate per meter = (a+b+c+d+e)/500 3.69
say 3.70
10.7 3004.4 Dusting

167
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Applying crusher dust to areas of road where bleeding
of excess bitumen has occurred.
Unit = Sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Material
Stone crusher dust finer than 3mm with not more cum 6.250 215.86 1349.15 M-021
than 10 per cent passing 0.075 sieve.
c) Overhead charges @ 0.1 on (a+b) 173.96
d) Contractor's profit @ 0.1 on (a+b+c) 191.36
Cost for 3500sqm = a+b+c+d 2104.97
Rate per meter = (a+b+c+d)/3500 0.60
say 0.60

10.8 (A) Fog Seal sqm 38.00 Item 5.17


3004.3.
2
(B) Crack Prevention courses.
3004.3.
4 (i) Stress Absorbing Membrane (SAM) crack width less than 6 sqm 56.00 Item 5.21
mm Case-I
(ii) Stress Absorbing Membrane (SAM) with crack width 6 mm to sqm 68.00 Item 5.21
9 mm Case-II
(iii) Stress Absorbing Membrane (SAM) crack width above 9 mm sqm 90.00 Item 5.21
and cracked area above 50 per cent Case-IV
(iv) Bitumen Impregnated Geotextile sqm 134.00 Item 5.21
Case-IV
10.8 (C) Slurry Seal
3004.5
(i) 5 mm thickness sqm 64.00 Item 5.15
Case-I
(ii) 3 mm thickness sqm 45.00 Item 5.15
Case-II
(iii) 1.5 mm thickness sqm 28.00 Item 5.15
Case-III
10.8 (D) Surface Dressing for maintenance works.
3004.6
(i) 19 mm nominal chipping size sqm 80.00 Item 5.9
Case-I
(ii) 13 mm nominal size chipping sqm 64.00 Item 5.9
Case-II
The above mentioned items have already been included in
chapter 5.
10.9 3005.1 Repair of Joint Grooves with Epoxy Mortar
Repair of spalled joint grooves of contraction joints,
longitudinal joints and expansion joints in concrete
pavements using epoxy mortar or epoxy concrete
Unit = running metre
Taking output = 10 metres
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor day 0.500 187.43 93.72 L-13
Chiseller day 0.500 195.43 97.72 L-05
b) Material
Epoxy primer kg 2.500 9.01 22.52 M-097
Epoxy compound with accessories for preparing epoxy kg 10.000 282.81 2828.09 M-095
mortar
c) Machinery
Air compressor 250 cfm for cleaning hour 0.050 293.76 14.69 P&M-001

168
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Overhead charges @ 0.1 on (a+b+c) 306.45
e) Contractor's profit @ 0.1 on (a+b+c+d) 337.10
Cost for 10 metres = a+b+c+d+e 3708.10
Rate per metre = (a+b+c+d+e)/10 370.81
say 371.00
10.10 3005.2 Repair of old Joints Sealant
Removal of existing sealant and re sealing of contraction,
longitudinal or expansion joints in concrete pavement with
fresh sealant material
Unit = running metre
Taking output = 10 metres
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor day 0.500 187.43 93.72 L-13
b) Material
Primer kg 0.250 90.84 22.71 M-146
Sealant kg 1.000 17.81 17.81 M-120
c) Machinery
Air compressor 250 cfm for cleaning hour 0.050 293.76 14.69 P&M-001
d) Overhead charges @ 0.1 on (a+b+c) 15.67
e) Contractor's profit @ 0.1 on (a+b+c+d) 17.24
Cost for 10 metres = a+b+c+d+e 189.65
Rate per metre = (a+b+c+d+e)/10 18.97
say 19.00
10.11 3000 Hill Side Drain Clearance
Removal of earth from the choked hill side drain and
disposing it on the valley side manually
Unit = running metre
Taking output = 10 metres
Assuming muck causing choking of drain to be 0.2 cum per
metre, quantity of earth to be removed for 10 metres = 2
cum
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 1.000 187.43 187.43 L-13
b) Overhead charges @ 0.1 on (a+b) 20.31
c) Contractor's profit @ 0.1 on (a+b) 22.34
Cost for 10 metres = a+b+c 245.71
Rate per metre = (a+b+c)/10 24.57
say 24.60
10.12 3000 Land Slide Clearance in soil
Clearance of land slides in soil and ordinary rock by a bull-
dozer D 80 A-12, 180 HP and disposal of the same on the
valley side
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor day 1.000 187.43 187.43 L-13
b) Machinery
Dozer 80 HP @ 60 cum per hour hour 1.670 3135.24 5235.85 P&M-014
c) Overhead charges @ 0.1 on (a+b) 543.11
d) Contractor's profit @ 0.1 on (a+b+c) 597.42
Cost for 100 cum = a+b+c+d 6571.63
Rate per cum = (a+b+c+d)/100 65.72
say 66.00

169
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note Land Slide clearance involves pushing of loose earth slided
on the road surface from hill face on the valley side. Since
no cutting of original ground is involved, the output of dozer
has been taken as 60 cum per hour for soil, ordinary rock
and blasted hard rock. However, if there are objection to
disposing of earth on valley side, additional resources for its
disposal shall be considered as per site conditions.

10.13 3000 Landslide Clearance in Hard Rock Requiring Blasting

Clearing of land slide in hard rock requiring blasting for 50


per cent of the boulders and disposal of the same on the
valley side.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.090 195.43 17.59 L-12
Mazdoor day 1.500 187.43 281.15 L-13
Driller day 0.750 218.57 163.93 L-06
Blaster day 0.070 304.89 21.34 L-03
b) Machinery
Dozer D 80 A-12,180 HP @ 60 cum per hour hour 1.670 3135.24 5235.85 P&M-014
Air compressor 250 cfm with two jack hammer hour 2.500 293.76 734.40 P&M-001
c) Materials
Gelatine 80 per cent @ 35 kg per 100 cum kg 17.500 112.77 1973.49 M-104
Electric Detonators @ 1 Detonator for 2 Gelatine sticks each 70.000 14.27 998.63 M-094 /100
of 125 gms each
c) Overhead charges @ 0.1 on (a+b) 942.64
d) Contractor's profit @ 0.1 on (a+b+c) 1036.90
Cost for 100 cum = a+b+c+d+e 11405.92
Rate per cum = (a+b+c+d+e)/100 114.06
say 114.00
Note Credit for the rock if found acceptable as construction
material shall be afforded
10.14 3000 Snow Clearance on Roads with Dozer
Snow clearance from road surface by a bull- dozer 165 Hp
and disposing it on the valley side
Unit = cum
Taking output = 5000 cum
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery
Dozer D 80 A-12,180 HP @ 850 cum per hour hour 5.880 3135.24 18435.21 P&M-014
c) Overhead charges @ 0.1 on (a+b) 1882.57
d) Contractor's profit @ 0.1 on (a+b+c) 2070.83
Cost for 5000 cum = a+b+c+d 22779.10
Rate per cum = (a+b+c+d)/5000 4.56
say 4.60
Note i) Labour provided will not be cutting the snow. They will be
guiding the dozer operator on the alignment of the road as
entire surface gets covered with snow and the edges of the
road are not visible and for changing the blade angle. Also
they will keep a watch on the hill side for any eventuality of
avalanches, slide etc

10.15 3000 Snow Clearance on Roads with Snow Blowers


Snow clearance from road surface by a snow blower and
disposing on the valley side.
Unit = cum

170
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking output = 3600 cum
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery
Snow blower equipment 140 HP @ 600 cum per hour hour 6.000 Value #VALUE! P&M-087

c) Overhead charges @ 0.1 on (a+b) #VALUE!


d) Contractor's profit @ 0.1 on (a+b+c) #VALUE!
Cost for 3600 cum (a+b+c+d) #VALUE!
Rate per cum = (a+b+c+d)/3600 #VALUE!
say #VALUE!

171
CHAPTER-11
HORTICULTURE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
11.1 307 Spreading of Sludge Farm Yard Manure or/and good
Earth
Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor day 1.000 187.43 187.43 L-13
b) Overhead charges @ 0.1 on (a) 19.52
c) Contractor's profit @ 0.1 on (a+b) 21.48
Cost for 15 cum= a+b+c 236.25
Rate per cum = (a+b+c)/15 15.75
say 15.70
11.2 307 Grassing with ' Doobs' Grass
Grassing with 'Doobs' grass including watering and
maintenance of the lawn for 30 days or more till the grass
forms a thick lawn free from weeds and fit for moving
including supplying good earth if needed
Unit = sqm
Taking output = 100 sqm
(i) In rows 15 cm apart in either direction
a) Labour
Mate day 0.170 195.43 33.22 L-12
Mazdoor for grassing day 0.750 187.43 140.57 L-13
Mazdoor for maintenance for 30 days day 1.000 187.43 187.43 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 111.24 55.62 P&M-060
c) Material
Doob grass kg 100.000 3.04 304.00 M-112
d) Overhead charges @ 0.1 on (a+b+c) 72.08
e) Contractor's profit @ 0.1 on (a+b+c+d) 79.29
Cost for 100 sqm = a+b+c+d+e 872.22
Rate per sqm= (a+b+c+d+e)/100 8.72
say 8.70
11.2 (ii) In rows 7.5 cm apart in either direction
a) Labour
Mate day 0.220 195.43 42.99 L-12
Mazdoor for grassing. day 1.250 187.43 234.29 L-13
for maintenance for 30 days day 1.000 187.43 187.43 L-13
b) Machinery
Water tanker6 KL capacity hour 0.750 111.24 83.43 P&M-060
c) Material
Doob grass kg 200.000 3.04 608.00 M-112
d) Overhead charges @ 0.1 on (a+b+c) 115.61
e) Contractor's profit @ 0.1 on (a+b+c+d) 127.18
Cost for 100 sqm = a+b+c+d+e 1398.93
Rate per sqm = (a+b+c+d+e)/100 13.99
say 14.00
Note In the case of horticulture one mate has been provided for
every 10 mazdoors as maintenance of grass and plants
require more care.
11.3 307 Making Lawns including Ploughing and Dragging with
'Swagha' Breaking of Clod
Making lawns including ploughing and breaking of clod,
removal of rubbish, dressing and supplying doobs grass
roots and planting at 15 cm apart, including supplying and
spreading of farm yard manure at rate of 0.18 cum per 100
sqm

Unit = sqm
Taking output = 100 sqm

171
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Labour
Mate day 0.150 195.43 29.31 L-12
Mazdoor for preparation of ground day 0.500 187.43 93.72 L-13
Mali for fetching doobs grass roots and grassing at 15 day 1.000 218.57 218.57 L-09
cm apart
b) Machinery
Water tanker6 KL capacity hour 0.500 111.24 55.62 P&M-060
Tractor with filler hour 0.010 171.02 1.71 P&M-053
c) Material
Supply of farm yard manure at site of work cum 0.180 528.65 95.16 M-167
Fine grass kg 100.000 3.04 304.00 M-113
d) Overhead charges @ 0.1 on (a+b+c) 79.81
e) Contractor's profit @ 0.1 on (a+b+c+d) 87.79
Cost for 100 sqm = a+b+c+d+e 965.68
Rate per sqm = (a+b+c+d+e)/100 9.66
say 9.70
11.4 307 Maintenance of Lawns or Turfing of Slopes
Maintenance of lawns or Turfing of slopes (rough grassing)
for a period of one year including watering etc

Unit = sqm
Taking output = 100 sqm
a) Labour
Mali day 10.000 218.57 2185.70 L-09
b) Machinery
Water tanker6 KL capacity hour 15.000 111.24 1668.60 P&M-060
c) Material
Cost of water KL 90.000 167.07 15036.14 M-189
d) Overhead charges @ 0.1 on (a+b+c) 1889.04
e) Contractor's profit @ 0.1 on (a+b+c+d) 2077.95
Cost for 100 sqm = a+b+c+d+e 22857.43
Rate per sqm = (a+b+c+d+e)/100 228.57
say 229.00
11.5 307 Turfing Lawns with Fine Grassing including Ploughing,
Dressing
Turfing lawns with fine grassing including ploughing,
dressing including breaking of clods, removal of rubbish,
dressing and supplying doobs grass roots at 10 cm apart,
including supplying and spreading of farm yard manure at
rate of 0.6 cum per 100 sqm

Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.250 195.43 48.86 L-12
Mazdoor for preparation of ground day 1.000 187.43 187.43 L-13
Mali for fetching doobs grass roots hedges and day 1.500 218.57 327.86 L-09
grassing at 10 cm apart
b) Machinery
Water tanker6 KL capacity hour 0.500 111.24 55.62 P&M-060
Tractor with tiller hour 0.010 171.02 1.71 P&M-053
c) Material
Supply of farm yard manure at site of work @ 0.6 cum cum 0.600 528.65 317.19 M-167
per 100 sqm
Fine grass kg 100.000 3.04 304.00 M-113
d) Overhead charges @ 0.1 on (a+b+c) 124.27
e) Contractor's profit @ 0.1 on (a+b+c+d) 136.69
Cost for 100 sqm = a+b+c+d+e 1503.62
Rate per sqm = (a+b+c+d+e)/100 15.04

172
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 15.00
11.6 307 Maintenance of Lawns with Fine Grassing for the First
Year
Maintenance of lawns with fine grassing for the first year
including watering etc

Unit = sqm
Taking output = 100 sqm
a) Labour
Mali day 10.000 218.57 2185.70 L-09
b) Machinery
Water tanker6 KL capacity hour 20.000 111.24 2224.80 P&M-060
c) Material
Cost of water KL 60.000 167.07 10024.09 M-189
d) Overhead charges @ 0.1 on (a+b+c) 1443.46
e) Contractor's profit @ 0.1 on (a+b+c+d) 1587.81
Cost for 100 sqm = a+b+c+d+e 17465.86
Rate per sqm = (a+b+c+d+e)/100 174.66
say 175.00
11.7 307 Planting and Maintaining of Permanent Hedges
(a) Planting permanent hedges including digging of
trenches
Planting permanent hedges including digging of trenches, 60
cm wide and 45 cm deep, refilling the excavated earth mixed
with farmyard manure, supplied at the rate of 4.65 cum per
100 metres and supplying and planting hedge plants at 30
cm apart

Unit = Running metre


Taking output = 100metre
a) Labour
Mate day 1.400 195.43 273.60 L-12
Mazdoor for digging of trench 60 cm wide and 45 cm day 10.000 187.43 1874.30 L-13
deep
Mazdoor for refilling the excavated earth mixed with day 4.000 187.43 749.72 L-13
cow dung, preparation of ground and digging of plant,
from the nursery carriage to site and planting in
position
b) Machinery
Water tanker6 KL capacity hour 0.500 111.24 55.62 P&M-060
c) Material
Cost of hedge plants 2 rows at 30 cm apart each 2x340 22.80 15504.00 M-116
Supply of farm yard manure at site of work cum 4.670 528.65 2468.80 M-167
Pesticide kg 0.250 56.39 14.10 M-136
Cost of water KL 3.000 167.07 501.20 M-189
d) Overhead charges @ 0.1 on (a+b+c) 2144.13
e) Contractor's profit @ 0.1 on (a+b+c+d) 2358.55
Cost for 100 metres = a+b+c+d+e 25944.02
Rate per metre = a+b+c+d+e)/100 259.44
say 259.00
(b) Maintenance of hedge for one year
Unit = Running metre
Taking output = 100 m
a) Labour
Mate day 3.000 195.43 586.29 L-12
Mazdoor day 30.000 187.43 5622.90 L-13
b) Machinery
Water tanker6 KL capacity hour 5.000 111.24 556.20 P&M-060
c) Material

173
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Manure sludge/Farm yard manure cum 2.000 528.65 1057.30 M-167
Pesticide kg 0.500 56.39 28.19 M-136
Cost of water KL 30.000 167.07 5012.05 M-189
Cost of hedge plants @ 10 per cent casualty each 68.000 22.80 1550.40 M-116
d) Overhead charges @ 0.1 on (a+b+c) 1441.33
e) Contractor's profit @ 0.1 on (a+b+c+d) 1585.47
Cost for 100 metres = a+b+c+d+e 17440.13
Rate per metre = a+b+c+d+e)/100 174.40
say 174.00
11.8 307 Planting and Maintaining of Flowering Plants and
Shrubs
(a) Planting flowering plants and shrubs in central verge

Unit = Running metres 200 plants and 800 shrubs in


two rows in one km length of road where width of
verge is 3m and above.
Taking output = 1000 metres
a) Labour
Mate day 1.200 195.43 234.52 L-12
Mazdoor day 12.000 187.43 2249.16 L-13
b) Machinery
Water tanker6 KL capacity hour 6.000 111.24 667.44 P&M-060
c) Material
Plants each 200.000 23.94 4787.19 M-100
Shrubs each 800.000 11.40 9120.00 M-166
Manure sludge/Farm yard manure cum 63.640 528.65 33643.29 M-167
Pesticide kg 0.500 56.39 28.19 M-136
Cost of water KL 36.000 167.07 6014.46 M-189
d) Overhead charges @ 0.1 on (a+b+c) 5674.42
e) Contractor's profit @ 0.1 on (a+b+c+d) 6241.87
Rate per Km = (a+b+c+d+e) 68660.53
say 68661.00
11.8 (b) Maintenance of flowering plants and shrubs in central
verge for one year
Unit = km
Taking output = one km
a) Labour
Mate day 36.000 195.43 7035.48 L-12
Mazdoor day 365.000 187.43 68411.95 L-13
b) Machinery
Water tanker6 KL capacity hour 90.000 111.24 10011.60 P&M-060
c) Material
Manure Sludge / farm yard manure at site cum 10.000 528.65 5286.50 M-167
Cost of water KL 180.000 167.07 30072.28 M-189
Replacement of casualties @ 10 per cent
Plants each 20.000 23.94 478.72 M-100
Shrubs each 80.000 11.40 912.00 M-166
Pesticides kg 1.500 56.39 84.58 M-136
d) Overhead charges @ 0.1 on (a+b+c) 12229.31
e) Contractor's profit @ 0.1 on (a+b+c+d) 13452.24
Rate per Km for one year = (a+b+c+d+e) 147974.66
say 147975.00
11.9 307 Planting of Trees and their Maintenance for one Year

174
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Planting of trees by the road side (Avenue trees) in 0.60 m
dia holes, 1 m deep dug in the ground, mixing the soil with
decayed farm yard/sludge manure, planting the saplings,
backfilling the trench, watering, fixing the tree guard and
maintaining the plants for one year

Unit = Each
Taking output = 10 trees
a) Labour
Mate day 1.700 195.43 332.23 L-12
Mazdoor for planting day 2.000 187.43 374.86 L-13
Mazdoor for maintenance for one year day 15.000 187.43 2811.45 L-13
b) Machinery
Water tanker6 KL capacity hour 2.000 111.24 222.48 P&M-060
c) Material
Sapling 2 m high 25 mm dia each 10.000 17.54 175.42 M-160
Farm yard manure cum 0.940 528.65 496.93 M-167
Pesticide kg 0.500 56.39 28.19 M-136
Cost of water KL 12.000 167.07 2004.82 M-189
d) Overhead charges @ 0.1 on (a+b+c) 644.64
e) Contractor's profit @ 0.1 on (a+b+c+d) 709.10
Cost for 10 trees = a+b+c+d+e 7800.13
Rate per trees = (a+b+c+d+e)/10 780.01
say 780.00
11.10 308 Renovation Lawns including, Weeding, Forking the
Ground, Top Dressing with Forked Soil
Renovation lawns including, weeding, forking the ground,
top dressing with forked soil, watering and maintenance the
lawns, for 30 days or more, till the grass forms a thick lawn,
free from weeds, and fit for moving and disposal of rubbish
as directed, including supplying good earth, if needed but
excluding the cost of well decayed farm yard manure

Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 195.43 23.45 L-12
Mazdoor day 3.000 187.43 562.29 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 111.24 55.62 P&M-060
c) Material
Cost of water KL 3.000 167.07 501.20 M-189
d) Overhead charges @ 0.1 on (a+b+c) 114.26
e) Contractor's profit @ 0.1 on (a+b+c+d) 125.68
Cost for 100 sqm = a+b+c+d+e 1382.51
Rate per sqm = (a+b+c+d+e) / 100 13.83
say 13.80
11.11 308.2 Supply at Site Well Decayed Farm Yard Manure
Supply at site of work well decayed farm yard manure, from
any available source, approved by the engineer in charge
including screening and stacking
Unit = cum
Taking output = one cum
a) Material
a) Cost of well decayed farm yard manure duly cum 1.000 528.65 528.65 M-167
screened, loading, carriage, unloading and
stacking at site
b) Overhead charges @ 0.1 on (a) 52.87
c) Contractor's profit @ 0.1 on (a+b) 58.15

175
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per cum = (a+b+c) 639.67
640.00
11.12 308.20 Supply at Site of Work/ Store-Deoiled Neem Cake
Supply at site of work/ store-deoiled neem cake duly packed
in used gunny bags
Unit = quintal
Taking output = one quintal
a) Cost, carriage, loading, unloading and stacking in quintal 1.000
store/site
b) Overheads@ per cent on (a)
c) Contractors profit@ per cent on (a+b)
Rate per quintal = a+b+c VALUE
11.13 308.2 Supplying Sludge
Supplying sludge duly stacked at site/ store
Unit = cum
Taking output = one cum
a) Cost of sludge including carriage, loading, cum 1.000
unloading and stacking at site
b) Overheads@ per cent on (a)
c) Contractors profit@ per cent on (a+b)
Rate per cum = a+b+c VALUE
11.14 New Half Brick Circular Tree Guard, in 2nd Class Brick,
internal diametre 1.25 metres, and height 1.2 metres,
above ground and 0.20 metre below ground

Half brick circular tree guard, in 2nd class brick, internal


diametre 1.25 metres, and height 1.2 metres, above ground
and 0.20 metre below ground, bottom two courses laid dry,
and top three courses in cement mortar 1:6 (1 cement 6
sand) and the intermediate courses being in dry honey comb
masonry, as per design complete
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 195.43 9.77 L-12
Mason day 0.250 247.19 61.80 L-11
Mazdoor day 0.250 187.43 46.86 L-13
b) Material
Brick 2nd class including carriage each 230.000 4.72 1086.07 M-079
Cement mortar 1:6 cum 0.025 2179.00 54.48 Item 12.6
(D)
c) Overhead charges @ 0.1 on (a+b) 125.90
d) Contractor's profit @ 0.1 on (a+b+c) 138.49
Rate per tree Guard = a+b+c+d 1523.35
say 1523.00
#VALUE!
Edging with 2nd class bricks, laid dry lengthwise, including
excavation, refilling, consolidation, with a hand packing and
spreading nearly surplus earth within a lead of 50 metres

Unit = Metre
Taking output= 10 metres
a) Labour
Mate day 0.002 195.43 0.39 L-12
Mason day 0.050 247.19 12.36 L-11
Mazdoor day 0.050 187.43 9.37 L-13
b) Material
Brick 2nd class including carriage each 50.000 4.72 236.10 M-079

176
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Overhead charges @ 0.1 on (a+b) 25.82
d) Contractor's profit @ 0.1 on (a+b+c) 28.40
Cost for 10 metre = a+b+c+d 312.45
Rate per metre = (a+b+c+d)/10 31.25
say 31.20
11.16 New Making Tree Guard 53 cm dia and 1.3 m High as per
Design from Empty Bitumen Drums
Making tree guard 53 cm dia and 1.3 m high as per design
from empty bitumen drum, slit suitably to permit sun and air,
(supplied by the department at stock issue rate) including
providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with
rivets, complete in all respect

Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.020 195.43 3.91 L-12
Blacksmith day 0.150 247.19 37.08 L-02
Mazdoor day 0.070 187.43 13.12 L-13
b) Material
Empty bitumen drum each 1.000 90.84 90.84 M-172
MS sheet 50 x 0.5 mm kg 0.650 48.10 31.26 M-179 /
1000
Rivets 6 mm dia and 10 mm in length each 22.000 5.64 124.05 M-158
c) Overhead charges @ 0.1 on (a+b) 30.03
d) Contractor's profit @ 0.1 on (a+b+c) 33.03
Rate for each tree guard = a+b+c+d 363.32
say 363.00
11.17 New Making Tree Guard 53 cm dia and 2 Metre High as per
Design from Empty Bitumen Drums
Making tree guard 53 cm dia and 2 metres high as per
design from empty bitumen drums, slit suitably to permit sun
and air, ( supplied by the department at stock issue rate)
including providing and fixing four legs 40 cm long of 30 x 3
mm MS riveted to tree guard and providing and fixing 2 nos
MS sheet rings 50 x 0.5 mm with rivets complete in all
respects

Unit = Each
Taking output = one tree guard
a) Labour
Mate 0.040 195.43 7.82 L-12
Blacksmith day 0.200 247.19 49.44 L-02
Mazdoor 0.200 187.43 37.49 L-13
b) Material
Empty bitumen drum each 1.500 90.84 136.27 M-172
MS sheet50 x 0.5 mm kg 0.650 48.10 31.26 M-179 /
1000
Rivets 6 mm dia and 10 mm in length each 50.000 5.64 281.93 M-158
MSplate30 x 3 mm kg 1.300 48.10 62.52 M-179 /
1000
c) Overhead charges @ 0.1 on (a+b) 60.67
d) Contractor's profit @ 0.1 on (a+b+c) 66.74
Rate for each tree guard = a+b+c+d 734.13
say 734.00
11.18 New Wrought Iron and Mild Steel Welded Work

177
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Wrought iron and mild steel welded work (using angles,
square bars, tees and channel grills, grating frames, gates
and tree guards of any size and design etc. including cost of
screens and welding rods or bolts and nuts complete fixed in
position but without the cost of excavation and concrete for
fixing which will be paid separately
Unit = quintal
Taking output = one quintal
a) Labour
Mate day 0.450 195.43 87.94 L-12
Blacksmith/ welder for cutting to design and shape and day 2.000 247.19 494.38 L-02
jointing
Mazdoor for fixing and helper for Blacksmith/welder day 2.500 187.43 468.58 L-13
b) Material
Angle, tees, channels etc quintal 1.050 4809.53 5050.01 M-179 /10
Deduct the cost of scrap quintal 0.050 -1603.18 (80.16) M-179/10/3

Add 5 per cent of cost of material for welding rods and other 248.49
welding accessories
c) Overhead charges @ 0.1 on (a+b) 626.92
d) Contractor's profit @ 0.1 on (a+b+c) 689.62
Rate per quintal = a+b+c+d 7585.78
say 7586.00
11.19 New Tree Guard with MS Iron
Providing and fixing MS iron tree guard 60 cm dia and 2
metre high above ground level formed of 4 Nos (25 x 6 mm)
and 8 Nos (25 x 3 mm) vertical MS riveted to 3 Nos (25 x 6
mm) iron rings in two halves, bolted together with 8 mm dia
and 30 mm long bolts including painting two coats with paint
of approved brand over a coat of priming, complete in all
respects.

Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 195.43 9.77 L-12
Blacksmith day 0.250 247.19 61.80 L-02
Mazdoor day 0.250 187.43 46.86 L-13
b) Material
MS iron 25 x 6 mm kg 19.200 48.095 923.43 M-179 /
1000
MS iron 25 x 3 mm kg 9.600 48.095 461.71 M-179 /
1000
Add 5 per cent of cost of material for riveting, bolting
and welding accessories
c) Machinery
Tractor-trolley hour 0.040 171.02 6.84 P&M-053
d) Painting
Painting two coats including priming sqm 1.770 40.00 70.80 Item 8.9
e) Overhead charges @ 0.1 on (a+b+c) 151.04
f) Contractor's profit @ 0.1 on (a+b+c+e) 166.15
Rate per tree guard =a+b+c+d+e+f 1898.40
say 1898.00
Note 1 The items of excavation and concreting to be measured
and paid separately as per design .
2 . Rate of painting may be adopted from the chapter as
Traffic signs.
11.20 New Tree Guard with MS Angle Iron and Steel Wire

178
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Providing and fixing tree guard 0.60 metre square, 2.00
metre high fabricated with MS angle iron 30 x 30 x 3 mm,
MS iron 25 x 3 mm and steel wire3 mm dia welded and
fabricated as per design in two halves bolted together

Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 195.43 9.77 L-12
Blacksmith day 0.250 247.19 61.80 L-02
Welder day 0.250 247.19 61.80 L-02
Mazdoor day 0.250 187.43 46.86 L-13
b) Material
MS angle 30 x 30 x 3 mm kg 13.500 48.10 649.29 M-179 /
1000
MS iron 25 x 3 mm kg 18.000 48.10 865.72 M-179 /
1000
Steel wire 3 mm dia kg 6.000 30.28 181.69 M-192
Add 5 per cent of cost of material for riveting, bolting 84.83
and welding accessories
c) Machinery
Tractor-trolley hour 0.040 171.02 6.84 P&M-053
d) Painting
Painting two coats including priming sqm 1.500 40.00 60.00 Item 8.9
e) Overhead charges @ 0.1 on (a+b+c) 196.86
f) Contractor's profit @ 0.1 on (a+b+c+e) 216.54
Rate per tree guard = a+b+c+d+e+f 2441.99
say 2442.00
11.21 New Compensatory Afforestation
Planting trees as compensatory afforestation at the rate of
290 trees per hectare at a spacing of 6 m by grubbing and
leveling the ground upto a depth of 150 mm, digging holes
0.9 m dia, 1 m deep, mixing farm yard/sludge manure with
soil, planting of sapling 2 m high with 25 cm dia stem,
backfilling the hole and watering

Unit = Hectare
Taking output = one hectare
a) Labour
i) Planting
Mate day 2.500 195.43 488.58 L-12
Mazdoor day 25.000 187.43 4685.75 L-13
ii) For Maintenance for one year
Mate day 5.000 195.43 977.15 L-12
Mazdoor day 50.000 187.43 9371.50 L-13
b) Machinery
Dozer 80 HP @ 1000 sqm/hour hour 10.000 2028.78 20287.80 P&M-015
Water tanker6 KL capacity (for planting) hour 3.000 111.24 333.72 P&M-060
Water tanker6 KL capacity (for maintenance) hour 25.000 111.24 2781.00 P&M-060
c) Material
Sapling 1 to 1.5 m high 2 cm dia stem each 290.000 14.03 4069.78 M-160 x
0.8
Add 10 per cent of sapling each 29.000 14.03 406.98 M-160 x
0.8
Decayed farm yard/sludge manure (planting) cum 60.900 528.65 32194.79 M-167
Decayed farm yard/sludge manure (maintenance) cum 4.000 528.65 2114.60 M-167
Pesticides for planting kg 0.500 56.39 28.19 M-136
Pesticides for maintenance kg 1.500 56.39 84.58 M-136
Cost of water KL 18.000 167.07 3007.23 M-189
d) Overhead charges @ 0.1 on (a+b+c) 8083.16

179
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Contractor's profit @ 0.1 on (a+b+c+d) 8891.48
Rate per hectare = a+b+c+d+e 97806.28
say 97806.00
Note Cost of fencing to be provided as per size of plot and
approved design, measured and paid separately

180
CHAPTER-12
FOUNDATIONS
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.1 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with approved material.
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.14 195.43 27.36
Mazdoor day 3.50 187.43 656.01
b) Overhead charges @ 0.25 on (a) 170.84
c) Contractor's profit @ 0.1 on (a+b) 85.42
Cost for 10 cum = a+b+c 939.63
Rate per cum = (a+b+c)/10 93.96
say 94.00
Note 1. Cost of dewatering may be added where required upto, 10
percent of labour cost assessment for dewatering shall be
made as per site conditions.

2.The excavated earth can be used partially for backfilling of


foundation pit and partly for road work except for marshy soil.
Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding marshy soil.
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.
12.1 (I) A (ii) Depth 3 m to 6 m
a) Labour
Mate/Supervisor day 0.18 195.43 35.18
Mazdoor day 4.50 187.43 843.44
b) Overhead charges @ 0.25 on (a) 219.65
c) Contractor's profit @ 0.1 on (a+b) 109.83
Cost for 10 cum = a+b+c 1208.09
Rate per cum = (a+b+c)/10 120.81
say 121.00
Note Cost of dewatering may be added where required upto 15 per
cent of labour cost. Assessment for dewatering shall be done
as per actual ground conditions.
12.1 (I) A (iii) Depth above 6 m
a) Labour
Mate/Supervisor day 0.24 195.43 46.90
Mazdoor day 6.00 187.43 1124.58
b) Overhead charges @ 0.25 on (a) 292.87
c) Contractor's profit @ 0.1 on (a+b) 146.44
Cost for 10 cum = a+b+c 1610.79
Rate per cum = (a+b+c)/10 161.08
say 161.00

Note 1. Cost of dewatering may be added where required upto 20


per cent of labour cost. Assessment for dewatering shall be
made as per site conditions..
12.1 (I) B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.32 195.43 62.54
Mazdoor day 8.00 187.43 1499.44
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1516.32 9097.92

180
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c) Overhead charges @ 0.25 on (a+b) 2664.97
d) Contractor's profit @ 0.1 on (a+b+c) 1332.49
Cost for 240 cum = a+b+c+d 14657.36
Rate per cum = (a+b+c+d)/240 61.07
say 61.00
Note Cost of dewatering upto 5 per cent of (a+b) may be added,
where required. Assessment for dewatering shall be made as
per site conditions..
12.1 (I) B (ii) Depth 3 m to 6 m
Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.32 195.43 62.54
Mazdoor day 8.00 187.43 1499.44
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1516.32 9097.92

c) Overhead charges @ 0.25 on (a+b) 2664.97

d) Contractor's profit @ 0.1 on (a+b+c) 1332.49

Cost for 210 cum = a+b+c+d 14657.36

Rate per cum = (a+b+c+d)/210 69.80


say 70.00

Note Cost of dewatering upto 7.5 per cent of (a+b) may be


added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1 (I) B (iii) Depth above 6m
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 195.43 78.17

Mazdoor day 10.00 187.43 1874.30

b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1516.32 9097.92

c) Overhead charges @ 0.25 on (a+b) 2762.60

d) Contractor's profit @ 0.1 on (a+b+c) 1381.30

Cost for 180 cum = a+b+c+d 15194.29

Rate per cum = (a+b+c+d)/180 84.41


say 84.00

Note 1. Cost of dewatering upto 10 per cent of (a+b) may be


added, where required. Assessment for dewatering shall be
made as per site conditions.
2.Labour provided for excavation by mechanical means
includes that required for trimming of bottom and side slopes.
12.1 II Ordinary Rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.20 195.43 39.09

Mazdoor day 5.00 187.43 937.15

b) Overhead charges @ 0.25 on (a) 244.06

c) Contractor's profit @ 0.1 on (a+b) 122.03

Cost for 10 cum = a+b+c 1342.32

Rate per cum = (a+b+c)/10 134.23


say 134.00

Note Cost of dewatering upto 10 per cent of labour cost may be


added, where required. Assessment for dewatering shall be
made as per site conditions.
12.1(II) B Mechanical Means

181
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.24 195.43 46.90

Mazdoor day 6.00 187.43 1124.58

b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1516.32 9097.92

c) Overhead charges @ 0.25 on (a+b) 2567.35

d) Contractor's profit @ 0.1 on (a+b+c) 1283.68

Cost for 180 cum = a+b+c+d 14120.43

Rate per cum = (a+b+c+d)/180 78.45


say 78.00

Note 1.Cost of dewatering upto 10 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond 3 m is not dug and
hence not included.
12.1 III Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.35 195.43 68.40

Driller day 0.50 218.57 109.29

Blaster day 0.25 304.89 76.22

Mazdoor day 8.00 187.43 1499.44

b) Machinery
Air Compressor 250 cfm with 2 jack hammer for drilling. hour 1.00 293.76 293.76

c) Material
Blasting Material kg 3.50 112.77 394.70

Detonator electric each 14.00 14.27 199.73

d) Overhead charges @ 0.25 on (a+b+c) 660.38

e) Contractor's profit @ 0.1 on (a+b+c+d) 330.19

Cost for 10 cum = a+b+c+d+e 3632.11

Rate per cum = (a+b+c+d+e)/10 363.21


say 363.00

Note Cost of dewatering @ 10 percent of (a+b) may be added,


where required. Assessment for dewatering shall be made as
per site conditions.
12.1 IV Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum
A Mechanical Means
a) Labour
Mate day 0.20 195.43 39.09

Mazdoor day 5.00 187.43 937.15

b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 6.00 293.76 1762.56
breaker
c) Overhead charges @ 0.25 on (a+b) 684.70

d) Contractor's profit @ 0.1 on (a+b+c) 342.35

Cost for 10 cum = a+b+c+d 3765.84

Rate per cum = (a+b+c+d)/10 376.58


say 377.00

Note 1. Cost of dewatering upto10 per cent of (a+b), may be


added, where required. Assessment for dewatering shall be
made as per site conditions.

182
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.In case of rock, foundation beyond3 m is not dug and hence
not included.
12.1 V Marshy Soil
Unit = cum
Taking output = 10 cum
Depth upto 3 m
A Manual means
a) Labour
Mate/Supervisor day 0.40 195.43 78.17

Mazdoor day 10.00 187.43 1874.30

b) Machinery
Tractor-trolley for removal. hour 2.67 171.02 456.62

c) Overhead charges @ 0.25 on (a+b) 602.27

d) Contractor's profit @ 0.1 on (a+b+c) 301.14

Cost for 10 cum = a+b+c+d 3312.50

Rate per cum = ( a+b+c+d)/ 10 331.25


say 331.00

Note 1. Cost of dewatering @ 30 per cent of (a), may be added,


where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 15 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item12.1-IA (ii) to (iii) for ordinary soil

12.1 (V) B Mechanical Means


a) Labour
Mate day 0.08 195.43 15.63

Mazdoor for dressing sides, bottom and backfilling day 2.00 187.43 374.86

b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 cum hour 0.17 1516.32 257.77
per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.45 846.00 380.70

c) Overhead charges @ 0.25 on (a+b) 257.24

d) Contractor's profit @ 0.1 on (a+b+c) 128.62

Cost for 10 cum = a+b+c+d 1414.83

Rate per cum = (a+b+c+d)/10 141.48


say 141.00

Note 1. Cost of dewatering @ 20 percent of (a+b) may be added,


where required
2. Shoring & strutting @ 10 percent of (a+b), where required
may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item 12.1-IB (ii) to (iii) for ordinary soil
VI Back Filling in Marshy Foundation Pits
Unit : Cum
Taking Output : 6 cum
a) Labour
Mate day 0.12 195.43 23.45

Mazdoor for dressing sides, bottom and backfilling day 3.00 187.43 562.29

b) Machinery
Tractor-trolley for transportation hour 2.00 171.02 342.04

c) Overhead charges @ 0.25 on (a+b) 231.94

d) Contractor's profit @ 0.1 on (a+b+c) 115.97

Cost for 6 cum = a+b+c+d 1275.69

Rate per cum = (a+b+c+d)/6 212.62

183
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 213.00

12.2 304 Filling Annular Space Around Footing in Rock


Unit = cum
Taking out put = 1 cum
Lean cement concrete 1:3:6 nominal mix. Rate may be taken VALUE
as per item 12.4.
12.3 304 Sand Filling in Foundation Trenches as per Drawing &
Technical Specification
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.01 195.43 1.95

Mazdoor day 0.30 187.43 56.23

b) Material
Sand (assuming 20 per cent voids) cum 1.20 111.50 133.80

c) Overhead charges @ 0.25 on (a+b) 48.00

d) Contractor's profit @ 0.1 on (a+b+c) 24.00

Rate per cum = a+b+c+d 263.98


say 264.00

12.4 2100 PCC 1:3:6 in Foundation


Plain cement concrete 1:3:6 nominal mix in foundation with
crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration
including curing for 14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.64 195.43 125.08

Mason day 1.00 247.19 247.19

Mazdoor day 15.00 187.43 2811.45

b) Material
40 mm Aggregate cum 13.50 780.12 10531.60

coarse Sand cum 6.75 209.13 1411.63

cement tonne 3.45 5982.46 20639.47

Cost of water KL 18.00 167.07 3007.23

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator 33 KVA hour 6.00 342.36 2054.16

Water tanker 6 KL capacity hour 2.00 111.24 222.48

d) Overhead charges @ 0.25 on (a+b+c) 10580.09

e) Contractor's profit @ 0.1 on (a+b+c+d) 5290.05

Cost for 15 cum = a+b+c+d+e 58190.50

Rate per cum = (a+b+c+d+e)/15 3879.37


say 3879.00

Note Vibrator is a part of minor T & P which is already included in


overhead charges of the contractor.
12.5 1300 Brick Masonry Work in Cement Mortar 1:3 in
Foundation complete excluding Pointing and Plastering,
as per Drawing and Technical Specifications.

Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class each 2500.00 4.72 11805.10

Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) cum 1.20 3447.00 4136.40

b) Labour
Mate day 0.48 195.43 93.81

184
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mason day 4.00 247.19 988.76

Mazdoor day 8.00 187.43 1499.44

c) Overhead charges @ 0.25 on (a+b) 4630.88

d) Contractor's profit @ 0.1 on (a+b+c) 2315.44

Cost for 5 cum = a+b+c+d 25469.82

Rate per cum (a+b+c+d)/5 5093.96


say 5094.00

(i) Rate for Brick Work in C. M. 1:2 in foundation 5406.00

(ii) Rate for Brick Work in C. M. 1:3 in foundation 5094.00

(iii) Rate for Brick Work in C. M. 1:4 in foundation 4882.00

(iv) Rate for Brick Work in C. M. 1:6 in foundation 4676.00

12.6 Sub- (A) Cement Mortar 1:3 (1 cement : 3 sand)


analysis
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.51 5982.46 3051.05

Sand cum 1.05 209.13 219.59

b) Labour
Mate day 0.04 195.43 7.82

Mazdoor day 0.90 187.43 168.69

Total Material and Labour = (a+b) say 3447.00

Sub- (B) Cement Mortar1:2 (1cement :2 sand)


analysis
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.672 5982.46 4020.21

Sand cum 0.933 209.13 195.19

b) Labour
Mate day 0.04 195.43 7.82

Mazdoor day 0.90 187.43 168.69

Total Material and Labour = (a+b) say 4392.00

Sub- (C) Cement Mortar1:4 (1cement :4 sand)


analysis
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.40 5982.46 2392.98

Sand cum 1.12 209.13 234.23

b) Labour
Mate day 0.04 195.43 7.82

Mazdoor day 0.90 187.43 168.69

Total Material and Labour = (a+b) say 2804.00

Sub- (D) Cement Mortar1:6 (1cement :6 sand)


analysis
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.288 5982.46 1722.95

Sand cum 1.337 209.13 279.64

b) Labour
Mate day 0.04 195.43 7.82

Mazdoor day 0.90 187.43 168.69

185
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Total Material and Labour = (a+b) say 2179.00

12.7 1400 Stone Masonry Work in Cement Mortar 1:3 in


Foundation complete as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
1405.4 (A) Square Rubble Coursed Rubble Masonry (first sort)
a) Material
Stone cum 5.50 360.24 1981.32

Through and bond stone each 35.00 6.06 211.97

(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)


Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) cum 1.50 3447.00 5170.50

b) Labour
Mate day 0.66 195.43 128.98

Mason day 7.50 247.19 1853.93

Mazdoor day 9.00 187.43 1686.87

c) Overhead charges @ 0.25 on (a+b) 2758.39

d) Contractor's profit @ 0.1 on (a+b+c) 1379.20

Cost for 5 cum = a+b+c+d 15171.16

Rate per cum (a+b+c+d)/5 3034.23


say 3034.00

1405.3 (B) Random Rubble Masonry


( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 359.72 1978.45

Through and bond stone each 35.00 6.06 211.97

(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)


Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) cum 1.55 3447.00 5342.85

b) Labour
Mate day 0.62 195.43 121.17

Mason day 6.00 247.19 1483.14

Mazdoor day 9.00 187.43 1686.87

c) Overhead charges @ 0.25 on (a+b) 2706.11

d) Contractor's profit @ 0.1 on (a+b+c) 1353.06

Cost for 5 cum = a+b+c+d 14883.62

Rate per cum (a+b+c+d)/5 2976.72


say 2977.00

Note The labour already considered in cement mortar has been


taken into account while proposing labour for masonry works.

12.8 1500, Plain/Reinforced Cement Concrete in Open Foundation


1700 & complete as per Drawing and Technical Specifications.
2100
A PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 5982.46 24707.54

Coarse sand cum 6.75 209.13 1411.63

40 mm Aggregate cum 8.10 780.12 6318.96

20 mm Aggregate cum 4.05 887.53 3594.48

10 mm Aggregate cum 1.35 674.15 910.10

b) Labour
Mate day 0.86 195.43 168.07

186
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mason day 1.50 247.19 370.79

Mazdoor day 20.00 187.43 3748.60

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator 63 KVA hour 6.00 361.80 2170.80

Per Cum Basic Cost of Labour, Material & Machinery 2979.00


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 1786.84
of material, labour and machinery

e) Overhead charges @ 0.25 on (a+b+c+d) 11614.47

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 5807.24

Cost for 15 cum = a+b+c+d+e+f 63879.61

Rate per cum = (a+b+c+d+e+f)/15 4258.64


say 4259.00

Note Needle Vibrator is an item of minor T & P which is already


included in overhead charges. Hence not added in rate
analysis of cement concrete works.
12.8 B PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement tonne 5.16 5982.46 30869.47

Coarse sand cum 6.75 209.13 1411.63

40 mm Aggregate cum 5.40 780.12 4212.64

20 mm Aggregate cum 5.40 887.53 4792.64

10 mm Aggregate cum 2.70 674.15 1820.21

b) Labour
Mate day 0.86 195.43 168.07

Mason day 1.50 247.19 370.79

Mazdoor day 20.00 187.43 3748.60

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator 33 KVA hour 6.00 342.36 2054.16

Per Cum Basic Cost of Labour, Material & Machinery 3382.00


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 2028.73
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 13186.76

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 6593.38

Cost for 15 cum = a+b+c+d+e+f 72527.15

Rate per cum = (a+b+c+d+e+f)/15 4835.14


say 4835.00

12.8 C RCC Grade M20


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.21 5982.46 31168.60

Coarse sand cum 6.75 209.13 1411.63

20 mm Aggregate cum 8.10 887.53 7188.96

10 mm Aggregate cum 5.40 674.15 3640.42

b) Labour
Mate day 0.86 195.43 168.07

Mason day 1.50 247.19 370.79

Mazdoor day 20.00 187.43 3748.60

c) Machinery

187
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator 33 KVA hour 6.00 342.36 2054.16

Per Cum Basic Cost of Labour, Material & Machinery 3402.00


(a+b+c)
d) Formwork @ 4 per cent on (a+b+c) 2040.85

e) Overhead charges @ 0.25 on (a+b+c+d) 13265.54

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 6632.77

Cost for 15 cum = a+b+c+d+e+f 72960.46

Rate per cum = ( a+b+c+d+e+f )/15 4864.03


say 4864.00

12.8 C Case II With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 5982.46 249229.12

Coarse Sand cum 54.00 209.13 11293.04

20 mm Aggregate cum 64.80 887.53 57511.71

10 mm Aggregate cum 43.20 674.15 29123.34

b) Labour
Mate day 0.84 195.43 164.16

Mason day 3.00 247.19 741.57

Mazdoor day 18.00 187.43 3373.74

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00

Generator 100 KVA hour 6.00 1635.00 9810.00

Loader 1 cum capacity hour 6.00 1148.00 6888.00

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25

Lead beyond 1 km, L-lead in km tonne.km 300L 4.32 1296.00

Concrete Pump hour 6 234.36 1406.16

Per Cum Basic Cost of Labour, Material & Machinery 3320.00


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 15935.88
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 103583.24

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 51791.62

Cost for 120 cum = a+b+c+d+e+f 569707.85

Rate per cum = ( a+b+c+d+e+f )/120 4747.57


say 4748.00

12.8 D PCC Grade M25


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 5982.46 35834.91

Coarse sand cum 6.75 209.13 1411.63

40 mm Aggregate cum 5.40 780.12 4212.64

20 mm Aggregate cum 5.40 887.53 4792.64

10 mm Aggregate cum 2.70 674.15 1820.21

b) Labour
Mate day 0.86 195.43 168.07

Mason day 1.50 247.19 370.79

Mazdoor day 20.00 187.43 3748.60

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator 33 KVA hour 6.00 342.36 2054.16

188
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Per Cum Basic Cost of Labour, Material & Machinery 3713.00
(a+b+c)
d) Formwork @ 3.75 per cent of (a+b+c) 2088.14

e) Overhead charges @ 0.25 on (a+b+c+d) 14442.97

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7221.48

Cost for 15 cum = a+b+c+d+e+f 79436.32

Rate per cum = ( a+b+c+d+e+f )/15 5295.75


say 5296.00

12.8 D Case II With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 47.95 5982.46 286858.77

Coarse sand cum 54.00 209.13 11293.04

40 mm Aggregate cum 43.20 780.12 33701.12

20 mm Aggregate cum 43.20 887.53 38341.14

10 mm Aggregate cum 21.60 674.15 14561.67

b) Labour
Mate day 0.84 195.43 164.16

Mason day 3.00 247.19 741.57

Mazdoor day 18.00 187.43 3373.74

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00

Generator 100 KVA hour 6.00 1635.00 9810.00

Loader 1 cum capacity hour 6.00 1148.00 6888.00

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead tonne.km 300L 4.32 1296.00
in Kilometer

Concrete Pump hour 6 234.36 1406.16

Per Cum Basic Cost of Labour, Material & Machinery 3634.00


(a+b+c)
d) Formwork @ 3.75 per cent of cost of concrete i.e. 16349.84
cost of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 113086.37

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 56543.18

cost of 120 cum = a+b+c+d+e+f 621975.01

Rate per cum = (a+b+c+d+e+f)/120 5183.13


say 5183.00

12.8 E RCC Grade M25


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 5982.46 36193.86

Coarse sand cum 6.75 209.13 1411.63

20 mm Aggregate cum 8.10 887.53 7188.96

10 mm Aggregate cum 5.40 674.15 3640.42

b) Labour
Mate day 0.86 195.43 168.07

Mason day 1.50 247.19 370.79

Mazdoor day 20.00 187.43 3748.60

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator 33 KVA hour 6.00 342.36 2054.16

Per Cum Basic Cost of Labour, Material & Machinery 3737.00


(a+b+c)

189
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) Formwork @ 3.75 per cent of a+b+c. 2101.75

e) Overhead charges @ 0.25 on (a+b+c+d) 14537.08

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7268.54

cost of 15 cum = a+b+c+d+e+f 79953.93

Rate per cum (a+b+c+d+e+f )/15 5330.26


say 5330.00

12.8 E Case II With Batching Plant, Transit Mixer and Concrete Pump

Unit: cum
Taking Output = 120 cum
a) Material
Cement tonne 48.38 5982.46 289431.23

Coarse sand cum 54.00 209.13 11293.04

20 mm Aggregate cum 64.80 887.53 57511.71

10 mm Aggregate cum 43.20 674.15 29123.34

b) Labour
Mate day 0.84 195.43 164.16

Mason day 3.00 247.19 741.57

Mazdoor day 18.00 187.43 3373.74

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00

Generator 100 KVA hour 6.00 1635.00 9810.00

Loader 1 cum capacity 1 cum hour 6.00 1148.00 6888.00

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead tonne.km 300L 4.32 1296.00
in Kilometer

Concrete Pump hour 6.00 234.36 1406.16

Per Cum Basic Cost of Labour, Material & Machinery 3655.00


(a+b+c)
d) Formwork @ 3.75 per cent on cost of concrete i.e. 16447.47
cost of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 113761.67

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 56880.83

cost of 120 cum = a+b+c+d+e+f 625689.17

Rate per cum (a+b+c+d+e+f )/120 5214.08


say 5214.00

12.8 F PCC Grade M30


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 5982.46 36373.33

Coarse sand cum 6.75 209.13 1411.63

40 mm Aggregate cum 5.40 780.12 4212.64

20 mm Aggregate cum 5.40 887.53 4792.64

10 mm Aggregate cum 2.70 674.15 1820.21

b) Labour
Mate day 0.86 195.43 168.07

Mason day 1.50 247.19 370.79

Mazdoor day 20.00 187.43 3748.60

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator 33 KVA hour 6.00 342.36 2054.16

Per Cum Basic Cost of Labour, Material & Machinery 3749.00


(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 1967.78
cost of material, labour and machinery

190
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
e) Overhead charges @ 0.25 on (a+b+c+d) 14547.48

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7273.74

cost of 15 cum = a+b+c+d+e+f 80011.15

Rate per cum (a+b+c+d+e+f )/15 5334.08


say 5334.00

12.8 F Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 48.60 5982.46 290747.37

Coarse sand cum 54.00 209.13 11293.04

40 mm Aggregate cum 43.20 780.12 33701.12

20 mm Aggregate cum 43.20 887.53 38341.14

10 mm Aggregate cum 21.60 674.15 14561.67

b) Labour
Mate day 0.84 195.43 164.16

Mason day 3.00 247.19 741.57

Mazdoor day 18.00 187.43 3373.74

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00

Generator 100 KVA hour 6.00 1635.00 9810.00

Loader 1 cum capacity hour 6.00 1148.00 6888.00

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead tonne.km 300L 4.32 1296.00
in Kilometer

Concrete Pump hour 6.00 234.36 1406.16

Per Cum Basic Cost of Labour, Material & Machinery 3666.00


(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 15395.95
cost of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 113820.04

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 56910.02

cost of 120 cum = a+b+c+d+e+f 626010.23

Rate per cum (a+b+c+d+e+f )/120 5216.75


say 5217.00

12.8 G RCC Grade M30


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 5982.46 36492.98

Coarse sand cum 6.75 209.13 1411.63

20 mm Aggregate cum 8.10 887.53 7188.96

10 mm Aggregate cum 5.40 674.15 3640.42

b) Labour
Mate day 0.86 195.43 168.07

Mason day 1.50 247.19 370.79

Mazdoor day 20.00 187.43 3748.60

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator 33 KVA hour 6.00 342.36 2054.16

Per Cum Basic Cost of Labour, Material & Machinery 3757.00


(a+b+c)
d) Formwork @ 3.5 per cent on cost of concrete i.e. cost 1972.10
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 14579.45

191
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7289.72

cost of 15 cum = a+b+c+d+e+f 80186.96

Rate per cum = (a+b+c+d+e+f)/15 5345.80


say 5346.00

12.8 G Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 5982.46 291943.86

Coarse sand cum 54.00 209.13 11293.04

20 mm Aggregate cum 64.80 887.53 57511.71

10 mm Aggregate cum 43.20 674.15 29123.34

b) Labour
Mate day 0.84 195.43 164.16

Mason day 3.00 247.19 741.57

Mazdoor day 18.00 187.43 3373.74

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00

Generator 100 KVA hour 6.00 1635.00 9810.00

Loader 1 cum capacity hour 6.00 1148.00 6888.00

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead tonne.km 300L 4.32 1296.00
in Kilometer

Concrete Pump hour 6.00 234.36 1406.16

Per Cum Basic Cost of Labour, Material & Machinery 3676.00


(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. cost 15438.91
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 114137.69

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 57068.84

cost of 120 cum = a+b+c+d+e+f 627757.28

Rate per cum (a+b+c+d+e+f )/120 5231.31


say 5231.00

12.8 H RCC Grade M35


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 5982.46 37868.95

Coarse sand cum 6.75 209.13 1411.63

20 mm Aggregate cum 8.10 887.53 7188.96

10 mm Aggregate cum 5.40 674.15 3640.42

b) Labour
Mate day 0.86 195.43 168.07

Mason day 1.50 247.19 370.79

Mazdoor day 20.00 187.43 3748.60

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator 33 KVA hour 6.00 342.36 2054.16

Per Cum Basic Cost of Labour, Material & Machinery 3849.00


(a+b+c)
d) Formwork @ 3 per cent on a+b+c 1731.65

e) Overhead charges @ 0.25 on (a+b+c+d) 14863.33

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7431.66

cost of 15 cum = a+b+c+d+e+f 81748.29

Rate per cum = (a+b+c+d+e+f)/15 5449.89

192
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 5450.00

12.8 H Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 50.64 5982.46 302951.58

Coarse sand cum 54.00 209.13 11293.04

20 mm Aggregate cum 64.80 887.53 57511.71

10 mm Aggregate cum 43.20 674.15 29123.34

b) Labour
Mate day 0.84 195.43 164.16

Mason day 3.00 247.19 741.57

Mazdoor day 18.00 187.43 3373.74

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00

Generator 100 KVA hour 6.00 1635.00 9810.00

Loader1 cum capacity hour 6.00 1148.00 6888.00

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead tonne.km 300L 4.32 1296.00
in Kilometer

Concrete Pump hour 6.00 234.36 1406.16

Per Cum Basic Cost of Labour, Material & Machinery 3768.00


(a+b+c)
d) Formwork @ 3 per cent on cost of concrete i.e. cost 13563.59
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 116420.78

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 58210.39

cost of 120 cum = a+b+c+d+e+f 640314.31

Rate per cum = (a+b+c+d+e+f)/120 5335.95


say 5336.00

Note: Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
WELL FOUNDATION
12.9 1200 Providing and Constructing Temporary Island 16 m
diameter for Construction of Well Foundation for 8m
dia. Well.
A Assuming depth of water 1.0 m and height of island to
be 1.25 m including Royality for earth @ Rs. 3768.00
for each Island.
Unit = 1 No
Taking output = 1 No.
a) Material
Earth (compacted) cum 251.20 25.1 6305.12

Sand bags each 750.00 1.73 1298.57

b) Labour
Mate day 0.40 195.43 78.17

Mazdoor for filling sand bags, stitching and placing day 15.00 187.43 2811.45

c) Machinery
Crane with grab 1 cum capacity hour 20.00 784.62 15692.40

Consumables @ 2.5 per cent of (c) above 392.31

d) Overhead charges @ 0.25 on (a+b+c) 6644.51

e) Contractor's profit @ 0.1 on (a+b+c+d) 3322.25

Rate per No. (a+b+c+d+e) 36544.78


say 36545.00

Note It is assumed that earth will be available within the working


space of crane with grab bucket.

193
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.9 B Assuming depth of water 4.0 m and height of island 4.5
m including Royality for earth @ Rs. 13565.00 for each
Island.
Unit = 1No
Taking output = 1 No
a) Material
Earth (compacted) cum 904.32 25.10 22698.43

Sand bags each 6000.00 1.73 10388.57

Wooden ballies 8" Dia and 9 m long each 95.00 49.23 4676.82

Wooden ballies 2" Dia for bracing metre 190.00 17.81 3383.23

b) Labour
Mate day 5.60 195.43 1094.41

Mazdoor for piling 8" dia ballies for piling 8" dia ballies day 18.00 187.43 3373.74

Mazdoor for bracing with 2" dia ballies day 12.00 187.43 2249.16

Mazdoor for filling sand bags, stitching and placing day 110.00 187.43 20617.30

c) Machinery
Crane with grab 1 cum capacity hour 50.00 784.62 39231.00

Consumables and other arrangements for piling ballies @ 2.5 2692.82


per cent of (a+b+c).
d) Overhead charges @ 0.25 on (a+b+c) 27601.37

e) Contractor's profit @ 0.1 on (a+b+c+d) 13800.69

Rate per No. (a+b+c+d+e) 151807.55


say 151808.00

Note For other well diameters rate can be worked out on the basis
of cross-sectional area of well. The diameter of the island
shall be in the conformity with clause 1203.2 of MoRTH
specifications.
12.9 C Providing and constructing one span service road to
reach island location from one pier location to another
pier location including Royality for earth @ Rs. 225.00
per m for service Road.
Assuming span length 30 m, width of service road 10m and
depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a) Material
Earth cum 450.00 25.10 11295.00

Sand bags each 300.00 1.73 519.43

b) Labour
Mate day 0.24 195.43 46.90

Mazdoor for filling sand bags, stitching and placing day 6.00 187.43 1124.58

c) Machinery
Front end Loader 1 cum capacity hour 27.00 1148.00 30996.00

Tipper 5.5 cum capacity hour 28.00 846.00 23688.00

d) Overhead charges @ 0.25 on (a+b+c) 16917.48

e) Contractor's profit @ 0.1 on (a+b+c+d) 8458.74

Cost for 30 m (a+b+c+d+e) 93046.13

Rate per m (a+b+c+d+e)/30 3101.54


say 3102.00

12.10 1200 & Providing and Laying Cutting Edge of Mild Steel
1900 weighing 40 kg per metre for Well Foundation complete
as per Drawing and Technical Specification.

Unit = 1 MT
Taking output = 1 MT
a) Material
Structural steel in plates, angles, etc including 5 per tonne 1.05 48095.30 50500.07
cent wastage
Nuts & bolts Kg 20.00 45.42 908.43

194
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
b) Labour
(for cutting, bending, making holes, joining, welding and
erecting in position)
Mate day 1.32 195.43 257.97

Fitter day 5.50 251.19 1381.55

Blacksmith day 5.50 247.19 1359.55

Welder day 5.50 247.19 1359.55

Mazdoor day 16.50 187.43 3092.60

Electrodes, cutting gas and other consumables @ 10 per cent 5140.85


of cost of (a) above
c) Overhead charges @ 0.25 on (a+b) 16000.14

d) Contractor's profit @ 0.1 on (a+b+c) 8000.07

Rate per MT (a+b+c+d) 88000.76


say 88001.00

12.11 1200, Plain/Reinforced Cement Concrete, in Well Foundation


1500 & complete as per Drawing and Technical Specification.
1700
Unit = 1 cum
Taking output = 1 cum
A Well curb
(i) RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3402.00

d) formwork @ 20 per cent of the cost of concrete 680.40

e) Overhead charges @ 0.25 on (a+b+c+d) 1020.60

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 510.30

Rate perm (a+b+c+d+e+f) 5613.30


say 5613.00

12.11 A Case II With Batching Plant, Transit Mixer and Concrete Pump
(i)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3319.00

d) formwork @ 20 per cent of the cost of concrete 663.80

e) Overhead charges @ 0.25 on (a+b+c+d) 995.70

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 497.85

Rate perm (a+b+c+d+e+f) 5476.35


say 5476.00

12.11 A (ii) RCC M25 Grade


Same as for 12.8 (E) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 3.75 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3737.00

d) formwork @ 20 per cent of the cost of concrete 747.40

e) Overhead charges @ 0.25 on (a+b+c+d) 1121.10

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 560.55

Rate perm (a+b+c+d+e+f) 6166.05


say 6166.00

12.11 A Case II With Batching Plant, Transit Mixer and Concrete Pump
(ii)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3655.00

d) formwork @ 20 per cent of the cost of concrete 731.00

e) Overhead charges @ 0.25 on (a+b+c+d) 1096.50

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 548.25

Rate perm (a+b+c+d+e+f) 6030.75

195
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 6031.00

12.11 A (iii) RCC M35 Grade


Same as for 12.8 (H) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 3.0 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3849.00

d) formwork @ 20 per cent of the cost of concrete 769.80

e) Overhead charges @ 0.25 on (a+b+c+d) 1154.70

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 577.35

Rate perm (a+b+c+d+e+f) 6350.85


say 6351.00

12.11 A Case II With Batching Plant, Transit Mixer and Concrete Pump
(iii)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3959.00

d) formwork @ 20 per cent of the cost of concrete 791.80

e) Overhead charges @ 0.25 on (a+b+c+d) 1187.70

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 593.85

Rate perm (a+b+c+d+e+f) 6532.35


say 6532.00

Note. If curb concrete is carried out within steel liner, cost of


formwork shall be excluded.

12.11 B Well steining


(I) PCC M15 Grade
Same as for 12.8 (A) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 2979.00

d) formwork @ 10 per cent of the cost of concrete 297.90

e) Overhead charges @ 0.25 on (a+b+c+d) 819.23

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 409.61

Rate perm (a+b+c+d+e+f) 4505.74


say 4506.00

12.11 B (ii) PCC M20 Grade


Same as for 12.8 (B) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3382.00

d) formwork @ 10 per cent of the cost of concrete 338.20

e) Overhead charges @ 0.25 on (a+b+c+d) 930.05

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 465.03

Rate perm (a+b+c+d+e+f) 5115.28


say 5115.00

12.11 B (iii) RCC M20 Grade


Same as for 12.8 (C) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3402.00

d) formwork @ 10 per cent of the cost of concrete 340.20

e) Overhead charges @ 0.25 on (a+b+c+d) 935.55

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 467.78

Rate perm (a+b+c+d+e+f) 5145.53


say 5146.00

196
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(iii)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3319.00

d) formwork @ 10 per cent of the cost of concrete 331.90

e) Overhead charges @ 0.25 on (a+b+c+d) 912.73

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 456.36

Rate perm (a+b+c+d+e+f) 5019.99


say 5020.00

12.11 B (iv) PCC M25 Grade


Same as for 12.8 (D) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3713.00

d) formwork @ 10 per cent of the cost of concrete 371.30

e) Overhead charges @ 0.25 on (a+b+c+d) 1021.08

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 510.54

Rate perm (a+b+c+d+e+f) 5615.91


say 5616.00

12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(iv)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3632.00

d) formwork @ 10 per cent of the cost of concrete 363.20

e) Overhead charges @ 0.25 on (a+b+c+d) 998.80

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 499.40

Rate perm (a+b+c+d+e+f) 5493.40


say 5493.00

'12.11 B (v) RCC M25 Grade


Same as for 12.8 (E) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3737.00

d) formwork @ 10 per cent of the cost of concrete 373.70

e) Overhead charges @ 0.25 on (a+b+c+d) 1027.68

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 513.84

Rate perm (a+b+c+d+e+f) 5652.21


say 5652.00

12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(v)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3655.00

d) formwork @ 10 per cent of the cost of concrete 365.50

e) Overhead charges @ 0.25 on (a+b+c+d) 1005.13

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 502.56

Rate perm (a+b+c+d+e+f) 5528.19


say 5528.00

'12.11 B (vi) PCC M30 Grade


Same as for 12.8 (F) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3749.00

d) formwork @ 10 per cent of the cost of concrete 374.90

e) Overhead charges @ 0.25 on (a+b+c+d) 1030.98

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 515.49

Rate perm (a+b+c+d+e+f) 5670.36

197
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 5670.00

12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(vi)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3665.00

d) formwork @ 10 per cent of the cost of concrete 366.50

e) Overhead charges @ 0.25 on (a+b+c+d) 1007.88

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 503.94

Rate perm (a+b+c+d+e+f) 5543.31


say 5543.00

'12.11 B (vii) RCC M30 Grade


Same as for 12.8 (G) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3757.00

d) formwork @ 10 per cent of the cost of concrete 375.70

e) Overhead charges @ 0.25 on (a+b+c+d) 1033.18

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 516.59

Rate perm (a+b+c+d+e+f) 5682.46


say 5682.00

12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(vii)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3676.00

d) formwork @ 10 per cent of the cost of concrete 367.60

e) Overhead charges @ 0.25 on (a+b+c+d) 1010.90

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 505.45

Rate perm (a+b+c+d+e+f) 5559.95


say 5560.00

'12.11 B (viii) RCC M35 Grade


Same as for 12.8 (H) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3849.00

d) formwork @ 10 per cent of the cost of concrete 384.90

e) Overhead charges @ 0.25 on (a+b+c+d) 1058.48

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 529.24

Rate perm (a+b+c+d+e+f) 5821.61


say 5822.00

12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(viii)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3959.00

d) formwork @ 10 per cent of the cost of concrete 395.90

e) Overhead charges @ 0.25 on (a+b+c+d) 1088.73

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 544.36

Rate perm (a+b+c+d+e+f) 5987.99


say 5988.00

'12.11 B (ix) RCC M40 Grade


Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 5982.46 308694.74

Coarse Sand cum 54.00 209.13 11293.04

20 mm Aggregate cum 64.80 887.53 57511.71

198
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
10 mm Aggregate cum 43.20 674.15 29123.34

Admixture kg 206.00 112.77 23230.84

b) Labour
Mate day 0.84 195.43 164.16

Mason day 3.00 247.19 741.57

Mazdoor day 18.00 187.43 3373.74

c) Machinery
Batching Plant hour 6.00 2457.00 14742.00

Generator 100 KVA hour 6.00 1635.00 9810.00

Loader 1 cum capacity hour 6.00 1148.00 6888.00

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25

Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 300xL 4.32 1296.00

Concrete Pump hour 6.00 234.36 1406.16

Per Cum Basic Cost of Labour, Material & Machinery 4010.00


(a+b+c)
d) Formwork @ 10 per cent on cost of concrete i.e. cost 48109.35
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 132300.73

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 66150.36

cost of 120 cum = a+b+c+d+e+f 727653.99

Rate per cum = (a+b+c+d+e+f)/120 6063.78


say 6064.00

12.11 C C Bottom Plug


Concrete to be placed using tremie pipe
Note: 10% extra cement to be added where under water
concreting is involved
(i) PCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.55 5982.46 33202.63

Coarse sand cum 6.75 209.13 1411.63

40 mm Aggregate cum 5.40 780.12 4212.64

20 mm Aggregate cum 5.40 887.53 4792.64

10 mm Aggregate cum 2.70 674.15 1820.21

Admixture Kg 18.60 112.77 2097.54

b) Labour
Mate day 0.90 195.43 175.89

Mason day 1.50 247.19 370.79

Mazdoor day 20.00 187.43 3748.60

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator 33 KVA hour 6.00 342.36 2054.16

Light Crane 3 tonnes capacity for handling tremie pipe hour 6.00 525.00 3150.00

Per Cum Basic Cost of Labour, Material & Machinery 3888.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 2591.63
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 15224.61

e) Contractor's profit @ 0.1 on (a+b+c+d) 7612.30

cost of 15 cum = a+b+c+d+e 83735.35

Rate per cum = (a+b+c+d+e)/15 5582.36


say 5582.00

12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete


(i) pump

199
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 44.40 5982.46 265621.05

Coarse sand cum 54.00 209.13 11293.04

20 mm Aggregate cum 64.80 887.53 57511.71

10 mm Aggregate cum 43.20 674.15 29123.34

Admixture Kg 148.80 112.77 16780.33

b) Labour
Mate day 0.88 195.43 171.98

Mason day 3.00 247.19 741.57

Mazdoor day 18.00 187.43 3373.74

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00

Generator 100 KVA hour 6.00 1635.00 9810.00

Loader 1 cum capacity hour 6.00 1148.00 6888.00

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25

Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 300L 4.32 1296.00
lead in Kilometer

Concrete Pump hour 6.00 234.36 1406.16

Per Cum Basic Cost of Labour, Material & Machinery 3597.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 19230.84
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 112702.00

e) Contractor's profit @ 0.1 on (a+b+c+d) 56351.00

cost of 120 cum = a+b+c+d+e 619861.02

Rate per cum = (a+b+c+d+e)/120 5165.51


say 5166.00

'12.11 C (ii) PCC Grade M25


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 5982.46 35834.91

Coarse sand cum 6.75 209.13 1411.63

40 mm Aggregate cum 5.40 780.12 4212.64

20 mm Aggregate cum 5.40 887.53 4792.64

10 mm Aggregate cum 2.70 674.15 1820.21

Admixture Kg 21.60 112.77 2435.85

b) Labour
Mate day 0.90 195.43 175.89

Mason day 1.50 247.19 370.79

Mazdoor day 20.00 187.43 3748.60

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator 33 KVA hour 6.00 342.36 2054.16

Light Crane of 3 tonnes capacity for handling tremie pipe hour 6.00 525.00 3150.00

Per Cum Basic Cost of Labour, Material & Machinery 4086.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 2740.16
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 16004.39

e) Contractor's profit @ 0.1 on (a+b+c+d) 8002.19

200
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
cost of 15 cum = a+b+c+d+e 88024.14

Rate per cum = (a+b+c+d+e)/15 5868.28


say 5868.00

12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete


(ii) pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.88 5982.46 286440.00

Coarse sand cum 54.00 209.13 11293.04

20 mm Aggregate cum 64.80 887.53 57511.71

10 mm Aggregate cum 43.20 674.15 29123.34

Admixture Kg 172.80 112.77 19486.84

b) Labour
Mate day 0.88 195.43 171.98

Mason day 3.00 247.19 741.57

Mazdoor day 18.00 187.43 3373.74

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00

Generator 100 KVA hour 6.00 1635.00 9810.00

Loader 1 cum capacity hour 6.00 1148.00 6888.00

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25

Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 300L 4.32 1296.00
lead in Kilometer

Concrete Pump hour 6.00 234.36 1406.16

Per Cum Basic Cost of Labour, Material & Machinery 3793.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 20407.11
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 118877.43

e) Contractor's profit @ 0.1 on (a+b+c+d) 59438.72

cost of 120 cum = a+b+c+d+e 653825.89

Rate per cum = (a+b+c+d+e)/120 5448.55


say 5449.00

'12.11 C (iii) PCC Grade M30


Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 5982.46 36373.33

Coarse sand cum 6.75 209.13 1411.63

40 mm Aggregate cum 5.40 780.12 4212.64

20 mm Aggregate cum 5.40 887.53 4792.64

10 mm Aggregate cum 2.70 674.15 1820.21

Admixture Kg 21.60 112.77 2435.85

b) Labour
Mate day 0.90 195.43 175.89

Mason day 1.50 247.19 370.79

Mazdoor day 20.00 187.43 3748.60

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator 33 KVA hour 6.00 342.36 2054.16

Light Crane of 3 tonnes capacity for handling tremie pipe hour 6.00 525.00 3150.00

Per Cum Basic Cost of Labour, Material & Machinery 4122.00


(a+b+c)

201
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 5 per cent of cost of material and labour towards cost of 2767.08
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 16145.73

e) Contractor's profit @ 0.1 on (a+b+c+d) 8072.86

cost of 15 cum = a+b+c+d+e 88801.49

Rate per cum = (a+b+c+d+e)/15 5920.10


say 5920.00

12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete


(iii) pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.64 5982.46 290986.67

Coarse sand cum 54.00 209.13 11293.04

20 mm Aggregate cum 64.80 887.53 57511.71

10 mm Aggregate cum 43.20 674.15 29123.34

Admixture Kg 172.80 112.77 19486.84

b) Labour
Mate day 0.88 195.43 171.98

Mason day 3.00 247.19 741.57

Mazdoor day 18.00 187.43 3373.74

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00

Generator 100 KVA hour 6.00 1635.00 9810.00

Loader 1 cum capacity hour 6.00 1148.00 6888.00

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25

Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 300L 4.32 1296.00
lead in Kilometer

Concrete Pump hour 6.00 234.36 1406.16

Per Cum Basic Cost of Labour, Material & Machinery 3831.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 20634.44
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 120070.93

e) Contractor's profit @ 0.1 on (a+b+c+d) 60035.47

cost of 120 cum = a+b+c+d+e 660390.14

Rate per cum = (a+b+c+d+e)/120 5503.25


say 5503.00

'12.11 C (iv) PCC Grade M35


Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.29 5982.46 37629.65

Coarse sand cum 6.75 209.13 1411.63

40 mm Aggregate cum 5.40 780.12 4212.64

20 mm Aggregate cum 5.40 887.53 4792.64

10 mm Aggregate cum 2.70 674.15 1820.21

Admixture Kg 21.60 112.77 2435.85

b) Labour
Mate day 0.90 195.43 175.89

Mason day 1.50 247.19 370.79

Mazdoor day 20.00 187.43 3748.60

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

202
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Generator 33 KVA hour 6.00 342.36 2054.16

Light Crane of 3 tonnes capacity for handling tremie pipe hour 6.00 525.00 3150.00

Per Cum Basic Cost of Labour, Material & Machinery 4205.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 2829.89
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 16475.51

e) Contractor's profit @ 0.1 on (a+b+c+d) 8237.75

cost of 15 cum = a+b+c+d+e 90615.29

Rate per cum = (a+b+c+d+e)/15 6041.02


say 6041.00

12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete


(iv) pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.28 5982.46 300797.89

Coarse sand cum 54.00 209.13 11293.04

20 mm Aggregate cum 64.80 887.53 57511.71

10 mm Aggregate cum 43.20 674.15 29123.34

Admixture Kg 172.80 112.77 19486.84

b) Labour
Mate day 0.88 195.43 171.98

Mason day 3.00 247.19 741.57

Mazdoor day 18.00 187.43 3373.74

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00

Generator 100 KVA hour 6.00 1635.00 9810.00

Loader 1 cum capacity hour 6.00 1148.00 6888.00

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25

Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 300L 4.32 1296.00
lead in Kilometer

Concrete Pump hour 6.00 234.36 1406.16

Per Cum Basic Cost of Labour, Material & Machinery 3913.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 21125.01
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 122646.38

e) Contractor's profit @ 0.1 on (a+b+c+d) 61323.19

cost of 120 cum = a+b+c+d+e 674555.10

Rate per cum = (a+b+c+d+e)/120 5621.29


say 5621.00

12.11 D Intermediate plug


(i) Grade M20 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3888.00

d) Overhead charges @ 0.25 on (a+b+c) 972.00

e) Contractor's profit @ 0.1 on (a+b+c+d) 486.00

Rate per cum = (a+b+c+d+e) 5346.00


say 5346.00

12.11 D Case II Using Batching Plant, Transit Mixer and Crane/concrete


(i) pump

203
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3597.00

d) Overhead charges @ 0.25 on (a+b+c) 899.25

e) Contractor's profit @ 0.1 on (a+b+c+d) 449.63

Rate per cum = (a+b+c+d+e) 4945.88


say 4946.00

'12.11 D (ii) Grade M25 PCC


Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 4086.00

d) Overhead charges @ 0.25 on (a+b+c) 1021.50

e) Contractor's profit @ 0.1 on (a+b+c+d) 510.75

Rate per cum = (a+b+c+d+e) 5618.25


say 5618.00

12.11 D Case II Using Batching Plant, Transit Mixer and Crane/concrete


(ii) pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3793.00

d) Overhead charges @ 0.25 on (a+b+c) 948.25

e) Contractor's profit @ 0.1 on (a+b+c+d) 474.13

Rate per cum = (a+b+c+d+e) 5215.38


say 5215.00

'12.11 D (iii) Grade M30 PCC


Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 4122.00

d) Overhead charges @ 0.25 on (a+b+c) 1030.50

e) Contractor's profit @ 0.1 on (a+b+c+d) 515.25

Rate per cum = (a+b+c+d+e) 5667.75


say 5668.00

12.11 D Case II Using Batching Plant, Transit Mixer and Crane/concrete


(iii) pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3831.00

d) Overhead charges @ 0.25 on (a+b+c) 957.75

e) Contractor's profit @ 0.1 on (a+b+c+d) 478.88

Rate per cum = (a+b+c+d+e) 5267.63


say 5268.00

12.11 E Top plug


(i) Grade M15 PCC
Same as Item 12.8(a) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 2979.00

d) Overhead charges @ 0.25 on (a+b+c) 744.75

e) Contractor's profit @ 0.1 on (a+b+c+d) 372.38

Rate per cum = (a+b+c+d+e) 4096.13


say 4096.00

Same as Item 12.8(b) excluding formwork


Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3382.00

d) Overhead charges @ 0.25 on (a+b+c) 845.50

e) Contractor's profit @ 0.1 on (a+b+c+d) 422.75

Rate per cum = (a+b+c+d+e) 4650.25

204
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 4650.00

Same as Item 12.8 (d) excluding formwork


Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3713.00

d) Overhead charges @ 0.25 on (a+b+c) 928.25

e) Contractor's profit @ 0.1 on (a+b+c+d) 464.13

Rate per cum = (a+b+c+d+e) 5105.38


say 5105.00

12.11 E Case II Using Batching Plant, Transit Mixer and Crane/concrete


(iii) pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3632.00

d) Overhead charges @ 0.25 on (a+b+c) 908.00

e) Contractor's profit @ 0.1 on (a+b+c+d) 454.00

Rate per cum = (a+b+c+d+e) 4994.00


say 4994.00

'12.11 E (iv) Grade M30 PCC


Same as Item 12.8(f) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3749.00

d) Overhead charges @ 0.25 on (a+b+c) 937.25

e) Contractor's profit @ 0.1 on (a+b+c+d) 468.63

Rate per cum = (a+b+c+d+e) 5154.88


say 5155.00

12.11 E Case II Using Batching Plant, Transit Mixer and Crane/concrete


(iv) pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3665.00

d) Overhead charges @ 0.25 on (a+b+c) 916.25

e) Contractor's profit @ 0.1 on (a+b+c+d) 458.13

Rate per cum = (a+b+c+d+e) 5039.38


say 5039.00

12.11 F Well cap


(i) RCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 5982.46 30630.18

Coarse sand cum 6.75 209.13 1411.63

20 mm Aggregate cum 8.10 887.53 7188.96

10 mm Aggregate cum 5.40 674.15 3640.42

b) Labour
Mate day 0.86 195.43 168.07

Mason day 1.50 247.19 370.79

Mazdoor day 20.00 187.43 3748.60

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator 33 KVA hour 6.00 342.36 2054.16

Form Work @ 4 per cent of a+b+c 2019.32

d) Overhead charges @ 0.25 on (a+b+c) 13125.55

e) Contractor's profit @ 0.1 on (a+b+c+d) 6562.77

cost of 15 cum = a+b+c+d+e 72190.52

Rate per cum = (a+b+c+d+e)/15 4812.70


say 4813.00

205
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 5982.46 244802.11

Coarse sand cum 54.00 209.13 11293.04

20 mm Aggregate cum 64.80 887.53 57511.71

10 mm Aggregate cum 43.20 674.15 29123.34

b) Labour
Mate day 0.84 195.43 164.16

Mason day 3.00 247.19 741.57

Mazdoor day 18.00 187.43 3373.74

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00

Generator 100 KVA hour 6.00 1635.00 9810.00

Loader (capacity 1 cum) hour 6.00 1148.00 6888.00

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25

Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 4.32 1296.00

Concrete Pump hour 6.00 234.36 1406.16

Formwork @ 4 per cent of (a+b+c) 15758.80

d) Overhead charges @ 0.25 on (a+b+c) 102432.22

e) Contractor's profit @ 0.1 on (a+b+c+d) 51216.11

cost of 120 cum = a+b+c+d+e 563377.21

Rate per cum = (a+b+c+d+e)/120 4694.81


say 4695.00

12.11 F (ii) RCC Grade M25


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 5982.46 36193.86

Coarse sand cum 6.75 209.13 1411.63

20 mm Aggregate cum 8.10 887.53 7188.96

10 mm Aggregate cum 5.40 674.15 3640.42

b) Labour
Mate day 0.86 195.43 168.07

Mason day 1.50 247.19 370.79

Mazdoor day 20.00 187.43 3748.60

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator 33 KVA hour 6.00 342.36 2054.16

Form Work @ 3.75 per cent of a+b+c 2101.75

d) Overhead charges @ 0.25 on (a+b+c) 14537.08

e) Contractor's profit @ 0.1 on (a+b+c+d) 7268.54

cost of 15 cum = a+b+c+d+e 79953.93

Rate per cum = (a+b+c+d+e)/15 5330.26


say 5330.00

12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(ii)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.40 5982.46 289550.88

Coarse sand cum 54.00 209.13 11293.04

206
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
20 mm Aggregate cum 64.80 887.53 57511.71

10 mm Aggregate cum 43.20 674.15 29123.34

b) Labour
Mate day 0.84 195.43 164.16

Mason day 3.00 247.19 741.57

Mazdoor day 18.00 187.43 3373.74

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00

Generator 100 KVA hour 6.00 1635.00 9810.00

Loader (capacity 1 cum) hour 6.00 1148.00 6888.00

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25

Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 4.32 1296.00

Concrete Pump hour 6.00 234.36 1406.16

Formwork @ 3.75 per cent of ( a+b+c) 16451.96

d) Overhead charges @ 0.25 on (a+b+c) 113792.70

e) Contractor's profit @ 0.1 on (a+b+c+d) 56896.35

cost of 120 cum = a+b+c+d+e 625859.86

Rate per cum = (a+b+c+d+e)/120 5215.50


say 5215.00

12.11 F (iii) RCC Grade M30


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 5982.46 36492.98

Coarse sand cum 6.75 209.13 1411.63

20 mm Aggregate cum 8.10 887.53 7188.96

10 mm Aggregate cum 5.40 674.15 3640.42

b) Labour
Mate day 0.86 195.43 168.07

Mason day 1.50 247.19 370.79

Mazdoor day 20.00 187.43 3748.60

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator 33 KVA hour 6.00 342.36 2054.16

Formwork @ 3.5 per cent of (a+b+c) 1972.10

d) Overhead charges @ 0.25 on (a+b+c) 14579.45

e) Contractor's profit @ 0.1 on (a+b+c+d) 7289.72

cost of 15 cum = a+b+c+d+e 80186.96

Rate per cum = (a+b+c+d+e)/15 5345.80


say 5346.00

12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(iii)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 5982.46 291884.04

Coarse sand cum 54.00 209.13 11293.04

20 mm Aggregate cum 64.80 887.53 57511.71

10 mm Aggregate cum 43.20 674.15 29123.34

b) Labour
Mate day 0.84 195.43 164.16

Mason day 3.00 247.19 741.57

Mazdoor day 18.00 187.43 3373.74

207
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00

Generator 100 KVA hour 6.00 1635.00 9810.00

Loader (capacity 1 cum) hour 6.00 1148.00 6888.00

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25

Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 4.32 1296.00

Concrete Pump hour 6.00 234.36 1406.16

Formwork @ 3.5 per cent of (a+b+c) 15436.82

d) Overhead charges @ 0.25 on (a+b+c) 114122.21

e) Contractor's profit @ 0.1 on (a+b+c+d) 57061.10

cost of 120 cum = a+b+c+d+e 627672.14

Rate per cum = (a+b+c+d+e)/120 5230.60


say 5231.00

12.11 F (iv) RCC Grade M35


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 5982.46 37868.95

Coarse sand cum 6.75 209.13 1411.63

20 mm Aggregate cum 8.10 887.53 7188.96

10 mm Aggregate cum 5.40 674.15 3640.42

b) Labour
Mate day 0.86 195.43 168.07

Mason day 1.50 247.19 370.79

Mazdoor day 20.00 187.43 3748.60

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator 33 KVA hour 6.00 342.36 2054.16

Formwork @ 3 per cent of (a+b+c) 1731.65

d) Overhead charges @ 0.25 on (a+b+c) 14863.33

e) Contractor's profit @ 0.1 on (a+b+c+d) 7431.66

cost of 15 cum = a+b+c+d+e 81748.29

Rate per cum = (a+b+c+d+e)/15 5449.89


say 5450.00

12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(iv)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 5982.46 302951.58

Coarse sand cum 54.00 209.13 11293.04

20 mm Aggregate cum 64.80 887.53 57511.71

10 mm Aggregate cum 43.20 674.15 29123.34

b) Labour
Mate day 0.84 195.43 164.16

Mason day 3.00 247.19 741.57

Mazdoor day 18.00 187.43 3373.74

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00

Generator 100 KVA hour 6.00 1635.00 9810.00

Loader (capacity 1 cum) hour 6.00 1148.00 6888.00

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25

208
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 4.32 1296.00

Concrete Pump hour 6.00 234.36 1406.16

Formwork @ 3 per cent of (a+b+c) 13563.59

d) Overhead charges @ 0.25 on (a+b+c) 116420.78

e) Contractor's profit @ 0.1 on (a+b+c+d) 58210.39

cost of 120 cum = a+b+c+d+e 640314.31

Rate per cum = (a+b+c+d+e)/120 5335.95


say 5336.00

Note Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
'12.11 F (v) RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 52.20 5982.46 312284.21

Coarse Sand cum 54.00 209.13 11293.04

20 mm Aggregate cum 64.80 887.53 57511.71

10 mm Aggregate cum 43.20 674.15 29123.34

Admixture kg 206.00 112.77 23230.84

b) Labour
Mate day 0.84 195.43 164.16

Mason day 3.00 247.19 741.57

Mazdoor day 18.00 187.43 3373.74

c) Machinery
Batching Plant hour 6.00 2457.00 14742.00

Generator 100 KVA hour 6.00 1635.00 9810.00

Loader 1 cum capacity hour 6.00 1148.00 6888.00

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25

Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 300.L 4.32 1296.00

Concrete Pump hour 6.00 234.36 1406.16

Formwork @ 3 per cent on cost of concrete i.e. cost of 14540.49


material, labour and machinery
d) Overhead charges @ 0.25 on (a+b+c) 124805.88

e) Contractor's profit @ 0.1 on (a+b+c+d) 62402.94

cost of 120 cum = a+b+c+d+e 686432.33

Rate per cum = (a+b+c+d+e)/120 5720.27


say 5720.00

12.12 Section Sinking of 6 m external diameter well (other than


1200 pneumatic method of sinking) through all types of strata
namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 6 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.50 m per hour.
a) Labour
Mate day 0.12 195.43 23.45

Sinker ( skilled ) day 1.00 218.57 218.57

209
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Sinking helper ( semi-skilled ) day 2.00 190.43 380.86

b) Machinery
Hire & running charges of crane with grab bucket of hour 2.00 1176.12 2352.24
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 235.22

c) Overhead charges @ 0.25 on (a+b) 802.59

d) Contractor's profit @ 0.1 on (a+b+c) 401.29

Rate per metre = (a+b+c+d) 4414.23


say 4414.00

12.12 A (ii) Beyond 3m upto 10m depth


Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 195.43 29.31

Sinker day 1.25 218.57 273.21

Sinking helper ( semi-skilled ) day 2.50 190.43 476.08

b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 1176.12 3528.36
0.75 cum capacity and accessories
Consumables in sinking @10 per cent of (b) 352.84

c) Overhead charges @ 0.25 on (a+b) 1164.95

d) Contractor's profit @ 0.1 on (a+b+c) 582.47

Rate per metre = (a+b+c+d) 6407.22


say 6407.00

12.12 A (iii) Beyond 10m upto 20m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 6727.00

12th m 5% 7063.00

13th m 5% 7416.00

14th m 5% 7787.00

15th m 5% 8176.00

16th m 5% 8585.00

17th m 5% 9014.00

18th m 5% 9465.00

19th m 5% 9938.00

20th m 5% 10435.00

Total Cost from 10m upto 20m 84606.00

Avg Rate per metre 8461.00

12.12 A (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 11218.00 13462.00

22nd m 7.5% 12059.00 14471.00

23rd m 7.5% 12963.00 15556.00

24th m 7.5% 13935.00 16722.00

25th m 7.5% 14980.00 17976.00

26th m 7.5% 16104.00 19325.00

27th m 7.5% 17312.00 20774.00

28th m 7.5% 18610.00 22332.00

29th m 7.5% 20006.00 24007.00

30th m 7.5% 21506.00 25807.00

Total Cost from 20m upto 30m 158693.00 190432.00

Avg Rate per metre 15869.00 19043.00

12.12 A (v) Beyond 30m upto 40 m

210
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement and Labour. 20% for
Kentledge
31st m 10% 23657.00 28388.00

32nd 10% 26023.00 31228.00

33rd m 10% 28625.00 34350.00

34th m 10% 31488.00 37786.00

35th m 10% 34637.00 41564.00

36th m 10% 38101.00 45721.00

37th m 10% 41911.00 50293.00

38th m 10% 46102.00 55322.00

39th m 10% 50712.00 60854.00

40th m 10% 55783.00 66940.00

Total Cost from 30m upto 40m 377039.00 452446.00

Avg Rate per metre 37704.00 45245.00

12.12 B Clayey Soil ( 6m dia. Well )


Unit = Running Meter.
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 195.43 29.31

Sinker ( skilled ) day 1.50 218.57 327.86

Sinking helper ( semi-skilled ) day 2.25 190.43 428.47

b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 1176.12 3528.36
0.75 cum capacity and accessories
Consumables in sinking @ 10 per cent of (b) 352.84

c) Overhead charges @ 0.25 on (a+b) 1166.71

d) Contractor's profit @ 0.1 on (a+b+c) 583.35

Rate per metre = (a+b+c+d) 6416.90


say 6417.00

12.12 B (ii) Beyond 3m upto 10m depth


Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.30 195.43 58.63

Sinker day 3.00 218.57 655.71

Sinking helper ( semi-skilled ) day 4.50 190.43 856.94

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 2.00 513.00 1026.00
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 808.27

c) Overhead charges @ 0.25 on (a+b) 2615.57

d) Contractor's profit @ 0.1 on (a+b+c) 1307.78

Rate per metre = (a+b+c+d) 14385.62


say 14386.00

12.12 B (iii) Beyond 10 m upto 20 m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a) (b)Including for
dewatering @
5% of cost, if
required

11th m 5% 15105.00 15860.00

12th m 5% 15860.00 16653.00

211
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
13th m 5% 16653.00 17486.00

14th m 5% 17486.00 18360.00

15th m 5% 18360.00 19278.00

16th m 5% 19278.00 20242.00

17th m 5% 20242.00 21254.00

18th m 5% 21254.00 22317.00

19th m 5% 22317.00 23433.00

20th m 5% 23433.00 24605.00

Total Cost from 10m upto 20m 189988.00 199488.00

Avg Rate per metre 18999.00 19949.00

12.12 B (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering of the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) (c)Including 25% (b) Including
loading arrangement and Labour ). for Kentledge 5% for
dewatering, if
required
21st m 7.5% 25190.00 31488.00 33062.00

22nd m 7.5% 27079.00 33849.00 35541.00

23rd m 7.5% 29110.00 36388.00 38207.00

24th m 7.5% 31293.00 39116.00 41072.00

25th m 7.5% 33640.00 42050.00 44153.00

26th m 7.5% 36163.00 45204.00 47464.00

27th m 7.5% 38875.00 48594.00 51024.00

28th m 7.5% 41791.00 52239.00 54851.00

29th m 7.5% 44925.00 56156.00 58964.00

30th m 7.5% 48294.00 60368.00 63386.00

Total Cost from 20m upto 30m 356360.00 445452.00 467724.00

Avg Rate per metre 35636.00 44545.00 46772.00

12.12 B (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) (b) Including (b)Including
loading arrangement and Labour). 20% for 5% for
Kentledge dewatering, if
required
31st m 10% 53123.00 63748.00 66935.00

32nd 10% 58435.00 70122.00 73628.00

33rd m 10% 64279.00 77135.00 80992.00

34th m 10% 70707.00 84848.00 89090.00

35th m 10% 77778.00 93334.00 98001.00

36th m 10% 85556.00 102667.00 107800.00

37th m 10% 94112.00 112934.00 118581.00

38th m 10% 103523.00 124228.00 130439.00

39th m 10% 113875.00 136650.00 143483.00

40th m 10% 125263.00 150316.00 157832.00

Total Cost from 30m upto 40m 846651.00 1015982.00 1066781.00

Avg Rate per metre 84665.00 101598.00 106678.00

12.12 C Soft Rock (6m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.
a) Labour
Mate day 0.92 195.43 179.80

Sinker ( skilled ) day 3.00 218.57 655.71

212
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Sinking helper ( semi-skilled ) day 20.00 190.43 3808.60

Diver day 0.50 218.57 109.29

b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1176.12 4704.48
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.50 513.00 1795.50

Consumables in sinking @ 10 per cent of (b) 650.00

Add for dewatering @ of 5 per cent of (a+b), if required 595.17

c) Overhead charges @ 0.25 on (a+b) 3124.63

d) Contractor's profit @ 0.1 on (a+b+c) 1562.32

Rate per metre = (a+b+c+d) 17185.49


say 17185.00

12.12 D Hard Rock (6m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 4.00 112.77 451.08

Electric Detonators each 18.00 14.27 256.79

b) Labour
Mate day 1.56 195.43 304.87

Driller day 2.00 218.57 437.14

Blaster day 0.25 304.89 76.22

Mazdoor day 12.00 187.43 2249.16

Mazdoor (Skilled) day 4.00 218.57 874.28

c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 513.00 1026.00
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 601.22

Consumables in sinking @ 10 per cent of cost of (b). 808.27

d) Overhead charges @ 0.25 on (a+b+c) 3535.44

e) Contractor's profit @ 0.1 on (a+b+c+d) 1767.72

Rate per metre = (a+b+c+d+e) 19444.92


say 19445.00

12.13 Section Sinking of 7 m external diameter well ( other than


1200 pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 7 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.30 m per hour.
a) Labour
Mate day 0.15 195.43 29.31

Sinker ( skilled ) day 1.25 218.57 273.21

Sinking helper ( semi-skilled ) day 2.50 190.43 476.08

b) Machinery
Hire & running charges of crane with grab bucket of hour 3.25 1176.12 3822.39
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 382.24

213
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c) Overhead charges @ 0.25 on (a+b) 1245.81

d) Contractor's profit @ 0.1 on (a+b+c) 622.90

Rate per metre = (a+b+c+d) 6851.94


say 6852.00

12.13 A (ii) Beyond 3m upto 10m depth


Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 195.43 35.18

Sinker day 1.50 218.57 327.86

Sinking helper ( semi-skilled ) day 3.00 190.43 571.29

b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1176.12 5292.54
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 529.25

c) Overhead charges @ 0.25 on (a+b) 1689.03

d) Contractor's profit @ 0.1 on (a+b+c) 844.51

Rate per metre = (a+b+c+d) 9289.66


say 9290.00

12.13 A (iii) Beyond 10m upto 20m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 9754.00

12th m 5% 10242.00

13th m 5% 10754.00

14th m 5% 11292.00

15th m 5% 11857.00

16th m 5% 12450.00

17th m 5% 13073.00

18th m 5% 13727.00

19th m 5% 14413.00

20th m 5% 15134.00

Total Cost from 10m upto 20m 122696.00

Avg Rate per metre 12270.00

12.13 A (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement and Labour). 20% for
Kentledge
21st m 7.5% 16269.00 19523.00

22nd m 7.5% 17489.00 20987.00

23rd m 7.5% 18801.00 22561.00

24th m 7.5% 20211.00 24253.00

25th m 7.5% 21727.00 26072.00

26th m 7.5% 23357.00 28028.00

27th m 7.5% 25109.00 30131.00

28th m 7.5% 26992.00 32390.00

29th m 7.5% 29016.00 34819.00

30th m 7.5% 31192.00 37430.00

Total Cost from 20m upto 30m 230163.00 276194.00

Avg Rate per metre 23016.00 27619.00

12.13 A (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 34311.00 41173.00

32nd 10% 37742.00 45290.00

214
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
33rd m 10% 41516.00 49819.00

34th m 10% 45668.00 54802.00

35th m 10% 50235.00 60282.00

36th m 10% 55259.00 66311.00

37th m 10% 60785.00 72942.00

38th m 10% 66864.00 80237.00

39th m 10% 73550.00 88260.00

40th m 10% 80905.00 97086.00

Total Cost from 30m upto 40m 546835.00 656202.00

Avg Rate per metre 54684.00 65620.00

12.13 B Clayey Soil ( 7m dia. Well )


Unit = Running Meter.
Taking output = 1 cum
(I) Depth below bed level upto 3.0 M
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 195.43 35.18

Sinker ( skilled ) day 1.50 218.57 327.86

Sinking helper ( semi-skilled ) day 3.00 190.43 571.29

b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1176.12 5292.54
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 529.25

d) Overhead charges @ 0.25 on (a+b) 1689.03

e) Contractor's profit @ 0.1 on (a+b+c) 844.51

Rate per metre = (a+b+c+d) 9289.66


say 9290.00

12.13 B (ii) Beyond 3m upto 10m depth


Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.26 195.43 50.81

Sinker day 2.00 218.57 437.14

Sinking helper ( semi-skilled ) day 4.00 190.43 761.72

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.25 513.00 1667.25
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 872.40

c) Overhead charges @ 0.25 on (a+b) 2711.51

d) Contractor's profit @ 0.1 on (a+b+c) 1355.75

Rate per metre = (a+b+c+d) 14913.30


say 14913.00

12.13 B (iii) Beyond 10 m upto 20 m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a) (b) Including for
dewatering @
5% of cost, if
required

11th m 5% 15659.00 16442.00

12th m 5% 16442.00 17264.00

13th m 5% 17264.00 18127.00

14th m 5% 18127.00 19033.00

15th m 5% 19033.00 19985.00

16th m 5% 19985.00 20984.00

17th m 5% 20984.00 22033.00

18th m 5% 22033.00 23135.00

215
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
19th m 5% 23135.00 24292.00

20th m 5% 24292.00 25507.00

Total Cost from 10m upto 20m 196954.00 206802.00

Avg Rate per metre 19695.00 20680.00

12.13 B (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

c Add 25 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including
loading arrangement and Labour ). 25% for 5% for
Kentledge dewatering, if
required
31st m 7.5% 26114.00 32643.00 34275.00

32nd 7.5% 28073.00 35091.00 36846.00

33rd m 7.5% 30178.00 37723.00 39609.00

34th m 7.5% 32441.00 40551.00 42579.00

35th m 7.5% 34874.00 43593.00 45773.00

36th m 7.5% 37490.00 46863.00 49206.00

37th m 7.5% 40302.00 50378.00 52897.00

38th m 7.5% 43325.00 54156.00 56864.00

39th m 7.5% 46574.00 58218.00 61129.00

40th m 7.5% 50067.00 62584.00 65713.00

Total Cost from 30m upto 40m 369438.00 461800.00 484891.00

Avg Rate per metre 36944.00 46180.00 48489.00

12.13 B (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including
loading arrangement and Labour). 20% for 5% for
Kentledge dewatering, if
required
31st m 10% 55074.00 66089.00 69393.00

32nd 10% 60581.00 72697.00 76332.00

33rd m 10% 66639.00 79967.00 83965.00

34th m 10% 73303.00 87964.00 92362.00

35th m 10% 80633.00 96760.00 101598.00

36th m 10% 88696.00 106435.00 111757.00

37th m 10% 97566.00 117079.00 122933.00

38th m 10% 107323.00 128788.00 135227.00

39th m 10% 118055.00 141666.00 148749.00

40th m 10% 129861.00 155833.00 163625.00

Total Cost from 30m upto 40m 877731.00 1053278.00 1105941.00

Avg Rate per metre 87773.00 105328.00 110594.00

12.13 C Soft Rock ( 7m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.58 195.43 113.35

Sinker ( skilled ) day 4.00 218.57 874.28

Sinking helper ( semi-skilled ) day 10.00 190.43 1904.30

Diver day 0.75 218.57 163.93

b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1176.12 5292.54
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 513.00 1923.75

Consumables in sinking @ 10 per cent of (b) 721.63

216
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add for dewatering @ of 5 per cent of (a+b), if required 513.61

c) Overhead charges @ 0.25 on (a+b) 2876.85

d) Contractor's profit @ 0.1 on (a+b+c) 1438.42

Rate per metre = (a+b+c+d) 15822.65


say 15823.00

12.13 D Hard Rock ( 7m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 7.00 112.77 789.40

Electric Detonators each 30.00 14.27 427.98

b) Labour
Mate day 1.60 195.43 312.69

Driller day 2.00 218.57 437.14

Blaster day 0.25 304.89 76.22

Mazdoor day 18.00 187.43 3373.74

Mazdoor (Skilled) day 4.00 218.57 874.28

Diver day 0.50 218.57 109.29

c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 513.00 1026.00
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 663.30

Consumables in sinking @ 10 per cent of cost of (b). 874.60

d) Overhead charges @ 0.25 on (a+b+c) 4005.34

e) Contractor's profit @ 0.1 on (a+b+c+d) 2002.67

Rate per metre = (a+b+c+d+e) 22029.37


say 22029.00

12.14 Section Sinking of 8 m external diameter well ( other than


1200 pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 8 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.18 195.43 35.18

Sinker ( skilled ) day 1.50 218.57 327.86

Sinking helper ( semi-skilled ) day 3.00 190.43 571.29

b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1176.12 4704.48
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 470.45

c) Overhead charges @ 0.25 on (a+b) 1527.31

d) Contractor's profit @ 0.1 on (a+b+c) 763.66

Rate per metre = (a+b+c+d) 8400.22


say 8400.00

12.14 A (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.20 m/hour

217
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
a) Labour
Mate day 0.25 195.43 48.86

Sinker day 1.75 218.57 382.50

Sinking helper ( semi-skilled ) day 3.50 190.43 666.51

b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1176.12 5880.60
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 588.06

c) Overhead charges @ 0.25 on (a+b) 1891.63

d) Contractor's profit @ 0.1 on (a+b+c) 945.82

Rate per metre = (a+b+c+d) 10403.97


say 10404.00

12.14 A (iii) Beyond 10m upto 20m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 10924.00

12th m 5% 11470.00

13th m 5% 12044.00

14th m 5% 12646.00

15th m 5% 13278.00

16th m 5% 13942.00

17th m 5% 14639.00

18th m 5% 15371.00

19th m 5% 16140.00

20th m 5% 16947.00

Total Cost from 10m upto 20m 137401.00

Avg Rate per metre 13740.00

12.14 A (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 18218.00 21862.00

22nd m 7.5% 19584.00 23501.00

23rd m 7.5% 21053.00 25264.00

24th m 7.5% 22632.00 27158.00

25th m 7.5% 24329.00 29195.00

26th m 7.5% 26154.00 31385.00

27th m 7.5% 28116.00 33739.00

28th m 7.5% 30225.00 36270.00

29th m 7.5% 32492.00 38990.00

30th m 7.5% 34929.00 41915.00

Total Cost from 20m upto 30m 257732.00 309279.00

Avg Rate per metre 25773.00 30928.00

12.14 A (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 38422.00 46106.00

32nd 10% 42264.00 50717.00

33rd m 10% 46490.00 55788.00

34th m 10% 51139.00 61367.00

35th m 10% 56253.00 67504.00

36th m 10% 61878.00 74254.00

37th m 10% 68066.00 81679.00

38th m 10% 74873.00 89848.00

218
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
39th m 10% 82360.00 98832.00

40th m 10% 90596.00 108715.00

Total Cost from 30m upto 40m 612341.00 734809.00

Avg Rate per metre 61234.00 73481.00

12.14 B Clayey Soil ( 8m dia. Well )


Unit = Running Meter.
Taking output = 1 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.22 195.43 42.99

Sinker ( skilled ) day 2.00 218.57 437.14

Sinking helper ( semi-skilled ) hour 3.50 190.43 666.51

b) Machinery
Hire & running charges of crane with grab bucket of 5.50 1176.12 6468.66
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 646.87

c) Overhead charges @ 0.25 on (a+b) 2065.54

d) Contractor's profit @ 0.1 on (a+b+c) 1032.77

Rate per metre = (a+b+c+d) 11360.48


say 11360.00

12.14 B (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.32 195.43 62.54

Sinker day 2.50 218.57 546.43

Sinking helper ( semi-skilled ) day 4.50 190.43 856.94

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.50 513.00 1795.50
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 885.22

c) Overhead charges @ 0.25 on (a+b) 2800.83

d) Contractor's profit @ 0.1 on (a+b+c) 1400.42

Rate per metre = (a+b+c+d) 15404.59


say 15405.00

12.14 B (iii) Beyond 10 m upto 20 m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a) (b) Including for
dewatering @
5% of cost, if
required
11th m 5% 16175.00 16984.00

12th m 5% 16984.00 17833.00

13th m 5% 17833.00 18725.00

14th m 5% 18725.00 19661.00

15th m 5% 19661.00 20644.00

16th m 5% 20644.00 21676.00

17th m 5% 21676.00 22760.00

18th m 5% 22760.00 23898.00

19th m 5% 23898.00 25093.00

20th m 5% 25093.00 26348.00

Total Cost from 10m upto 20m 203449.00 213622.00

Avg Rate per metre 20345.00 21362.00

12.14 B (iv) Beyond 20m upto 30 m

219
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

c Add 25 per cent of cost for Kentledge including supports, (a) (c)Including 25% (b) Including
loading arrangement and Labour ). for Kentledge 5% for
dewatering, if
required

31st m 7.5% 26975.00 33719.00 35405.00

32nd 7.5% 28998.00 36248.00 38060.00

33rd m 7.5% 31173.00 38966.00 40914.00

34th m 7.5% 33511.00 41889.00 43983.00

35th m 7.5% 36024.00 45030.00 47282.00

36th m 7.5% 38726.00 48408.00 50828.00

37th m 7.5% 41630.00 52038.00 54640.00

38th m 7.5% 44752.00 55940.00 58737.00

39th m 7.5% 48108.00 60135.00 63142.00

40th m 7.5% 51716.00 64645.00 67877.00

Total Cost from 30m upto 40m 381613.00 477018.00 500868.00

Avg Rate per metre 38161.00 47702.00 50087.00

12.14 B (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) (c ) Including (b) Including
loading arrangement and Labour). 20% for 5% for
Kentledge dewatering, if
required
31st m 10% 56888.00 68266.00 71679.00

32nd 10% 62577.00 75092.00 78847.00

33rd m 10% 68835.00 82602.00 86732.00

34th m 10% 75719.00 90863.00 95406.00

35th m 10% 83291.00 99949.00 104946.00

36th m 10% 91620.00 109944.00 115441.00

37th m 10% 100782.00 120938.00 126985.00

38th m 10% 110860.00 133032.00 139684.00

39th m 10% 121946.00 146335.00 153652.00

40th m 10% 134141.00 160969.00 169017.00

Total Cost from 30m upto 40m 906659.00 1087990.00 1142389.00

Avg Rate per metre 90666.00 108799.00 114239.00

12.14 C Soft Rock ( 8m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.68 195.43 132.89

Sinker ( skilled ) day 4.00 218.57 874.28

Sinking helper ( semi-skilled ) day 12.00 190.43 2285.16

Diver day 1.00 218.57 218.57

b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1176.12 5880.60
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 513.00 1923.75

Consumables in sinking @ 10 per cent of (b) 780.44

Add for dewatering @ of 5 per cent of (a+b), if required 604.78

c) Overhead charges @ 0.25 on (a+b) 3175.12

d) Contractor's profit @ 0.1 on (a+b+c) 1587.56

Rate per metre = (a+b+c+d) 17463.15

220
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 17463.00

12.14 D Hard Rock ( 8m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour
a) Material
Gelatine 80 per cent Kg 8.00 112.77 902.17

Electric Detonators each 32.00 14.27 456.52

b) Labour
Mate day 1.09 195.43 213.02

Driller day 2.00 218.57 437.14

Blaster day 0.25 304.89 76.22

Mazdoor day 20.00 187.43 3748.60

Mazdoor (Skilled) day 4.00 218.57 874.28

c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 513.00 1026.00
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 671.60

Consumables in sinking @ 10 per cent of cost of (b). 534.93

d) Overhead charges @ 0.25 on (a+b+c) 3999.30

e) Contractor's profit @ 0.1 on (a+b+c+d) 1999.65

Rate per metre = (a+b+c+d+e) 21996.14


say 21996.00

12.15 Section Sinking of 9 m external diameter well ( other than


1200 pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 9 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.19 195.43 37.13

Sinker ( skilled ) day 1.50 218.57 327.86

Sinking helper ( semi-skilled ) day 3.25 190.43 618.90

b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1176.12 4704.48
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 470.45

c) Overhead charges @ 0.25 on (a+b) 1539.70

d) Contractor's profit @ 0.1 on (a+b+c) 769.85

Rate per metre = (a+b+c+d) 8468.37


say 8468.00

12.15 A (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.27 195.43 52.77

Sinker day 1.75 218.57 382.50

Sinking helper ( semi-skilled ) day 4.00 190.43 761.72

b) Machinery

221
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Hire & running charges of crane with grab bucket of hour 5.50 1176.12 6468.66
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 646.87

c) Overhead charges @ 0.25 on (a+b) 2078.13

d) Contractor's profit @ 0.1 on (a+b+c) 1039.06

Rate per metre = (a+b+c+d) 11429.70


say 11430.00

12.15 A (iii) Beyond 10m upto 20m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 12001.00

12th m 5% 12601.00

13th m 5% 13231.00

14th m 5% 13893.00

15th m 5% 14588.00

16th m 5% 15317.00

17th m 5% 16083.00

18th m 5% 16887.00

19th m 5% 17731.00

20th m 5% 18618.00

Total Cost from 10m upto 20m 150950.00

Avg Rate per metre 15095.00

12.15 A (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 20014.35 24017.00

22nd m 7.5% 21515.00 25818.00

23rd m 7.5% 23129.00 27755.00

24th m 7.5% 24864.00 29837.00

25th m 7.5% 26729.00 32075.00

26th m 7.5% 28734.00 34481.00

27th m 7.5% 30889.00 37067.00

28th m 7.5% 33206.00 39847.00

29th m 7.5% 35696.00 42835.00

30th m 7.5% 38373.00 46048.00

Total Cost from 20m upto 30m 283149.35 339780.00

Avg Rate per metre 28315.00 33978.00

12.15 A (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 42210.30 50652.00

32nd 10% 46431.00 55717.00

33rd m 10% 51074.00 61289.00

34th m 10% 56181.00 67417.00

35th m 10% 61799.00 74159.00

36th m 10% 67979.00 81575.00

37th m 10% 74777.00 89732.00

38th m 10% 82255.00 98706.00

39th m 10% 90481.00 108577.00

40th m 10% 99529.00 119435.00

Total Cost from 30m upto 40m 672716.30 807259.00

Avg Rate per metre 67272.00 80726.00

222
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.15 B Clayey Soil ( 9m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.24 195.43 46.90

Sinker ( skilled ) day 2.25 218.57 491.78

Sinking helper ( semi-skilled ) day 3.75 190.43 714.11

b) Machinery
Hire & running charges of crane with grab bucket of hour 5.75 1176.12 6762.69
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 676.27

c) Overhead charges @ 0.25 on (a+b) 2172.94

d) Contractor's profit @ 0.1 on (a+b+c) 1086.47

Rate per metre = (a+b+c+d) 11951.17


say 11951.00

12.15 B (ii) Beyond 3m upto 10m depth


Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.34 195.43 66.45

Sinker day 2.50 218.57 546.43

Sinking helper ( semi-skilled ) day 5.00 190.43 952.15

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1176.12 7644.78
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.75 513.00 1923.75
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 956.85

c) Overhead charges @ 0.25 on (a+b) 3022.60

d) Contractor's profit @ 0.1 on (a+b+c) 1511.30

Rate per metre = (a+b+c+d) 16624.31


say 16624.00

12.15 B (iii) Beyond 10 m upto 20 m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a) (b) Including for
dewatering @
5% of cost, if
required

11th m 5% 17455.00 18328.00

12th m 5% 18328.00 19244.00

13th m 5% 19244.00 20206.00

14th m 5% 20206.00 21216.00

15th m 5% 21216.00 22277.00

16th m 5% 22277.00 23391.00

17th m 5% 23391.00 24561.00

18th m 5% 24561.00 25789.00

19th m 5% 25789.00 27078.00

20th m 5% 27078.00 28432.00

Total Cost from 10m upto 20m 219545.00 230522.00

Avg Rate per metre 21955.00 23052.00

12.15 B (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

223
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c Add 25 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including
loading arrangement and Labour ). 25% for 5% for
Kentledge dewatering, if
required

31st m 7.5% 29109.00 36386.00 38205.00

32nd 7.5% 31292.00 39115.00 41071.00

33rd m 7.5% 33639.00 42049.00 44151.00

34th m 7.5% 36162.00 45203.00 47463.00

35th m 7.5% 38874.00 48593.00 51023.00

36th m 7.5% 41790.00 52238.00 54850.00

37th m 7.5% 44924.00 56155.00 58963.00

38th m 7.5% 48293.00 60366.00 63384.00

39th m 7.5% 51915.00 64894.00 68139.00

40th m 7.5% 55809.00 69761.00 73249.00

Total Cost from 30m upto 40m 411807.00 514760.00 540498.00

Avg Rate per metre 41181.00 51476.00 54050.00

12.15 B (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including
loading arrangement and Labour). 20% for 5% for
Kentledge dewatering, if
required
31st m 10% 61390.00 73668.00 77351.00

32nd 10% 67529.00 81035.00 85087.00

33rd m 10% 74282.00 89138.00 93595.00

34th m 10% 81710.00 98052.00 102955.00

35th m 10% 89881.00 107857.00 113250.00

36th m 10% 98869.00 118643.00 124575.00

37th m 10% 108756.00 130507.00 137032.00

38th m 10% 119632.00 143558.00 150736.00

39th m 10% 131595.00 157914.00 165810.00

40th m 10% 144755.00 173706.00 182391.00

Total Cost from 30m upto 40m 978399.00 1174078.00 1232782.00

Avg Rate per metre 97840.00 117408.00 123278.00

12.15 C Soft Rock ( 9m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.76 195.43 148.53

Sinker ( skilled ) day 4.00 218.57 874.28

Sinking helper ( semi-skilled ) day 14.00 190.43 2666.02

Diver day 1.20 218.57 262.28

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1176.12 7644.78
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.00 513.00 2052.00

Consumables in sinking @ 10 per cent of (b) 969.68

Add for dewatering @ of 5 per cent of (a+b), if required 1461.76

c) Overhead charges @ 0.25 on (a+b) 4019.83

d) Contractor's profit @ 0.1 on (a+b+c) 2009.92

Rate per metre = (a+b+c+d) 22109.07


say 22109.00

12.15 D Hard Rock ( 9m dia well )


Unit = Running Meter

224
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a) Material
Gelatine 80 per cent Kg 10.00 112.77 1127.71

Electric Detonators each 40.00 14.27 570.65

b) Labour
Mate day 1.17 195.43 228.65

Driller day 2.00 218.57 437.14

Blaster day 0.25 304.89 76.22

Mazdoor day 22.00 187.43 4123.46

Mazdoor (Skilled) day 4.00 218.57 874.28

Diver day 1.00 218.57 218.57

c) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 1176.12 8232.84
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.50 513.00 1282.50
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 773.68

Consumables in sinking @ 10 per cent of cost of (b). 595.83

d) Overhead charges @ 0.25 on (a+b+c) 4635.38

e) Contractor's profit @ 0.1 on (a+b+c+d) 2317.69

Rate per metre = (a+b+c+d+e) 25494.61


say 25495.00

12.16 1200 Sinking of 10 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter
Taking output = 1 m
Diameter of well - 10 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.20 m / hour
a) Labour
Mate day 0.20 195.43 39.09

Sinker ( skilled ) day 1.50 218.57 327.86

Sinking helper ( semi-skilled ) day 3.50 190.43 666.51

b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1176.12 5880.60
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 588.06

c) Overhead charges @ 0.25 on (a+b) 1875.53

d) Contractor's profit @ 0.1 on (a+b+c) 937.76

Rate per metre = (a+b+c+d) 10315.40


say 10315.00

12.16 A (ii) Beyond 3m upto 10m depth


Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.31 195.43 60.58

Sinker day 2.00 218.57 437.14

Sinking helper ( semi-skilled ) day 4.25 190.43 809.33

b) Machinery
Hire & running charges of crane with grab bucket of hour 5.75 1176.12 6762.69
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 676.27

225
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c) Overhead charges @ 0.25 on (a+b) 2186.50

d) Contractor's profit @ 0.1 on (a+b+c) 1093.25

Rate per metre = (a+b+c+d) 12025.76


say 12026.00

12.16 A (iii) Beyond 10m upto 20m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 12627.00

12th m 5% 13258.00

13th m 5% 13921.00

14th m 5% 14617.00

15th m 5% 15348.00

16th m 5% 16115.00

17th m 5% 16921.00

18th m 5% 17767.00

19th m 5% 18655.00

20th m 5% 19588.00

Total Cost from 10m upto 20m 158817.00

Avg Rate per metre 15882.00

12.16 A (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 21057.00 25268.00

22nd m 7.5% 22636.00 27163.00

23rd m 7.5% 24334.00 29201.00

24th m 7.5% 26159.00 31391.00

25th m 7.5% 28121.00 33745.00

26th m 7.5% 30230.00 36276.00

27th m 7.5% 32497.00 38996.00

28th m 7.5% 34934.00 41921.00

29th m 7.5% 37554.00 45065.00

30th m 7.5% 40371.00 48445.00

Total Cost from 20m upto 30m 297893.00 357471.00

Avg Rate per metre 29789.00 35747.00

12.16 A (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 44408.00 53290.00

32nd 10% 48849.00 58619.00

33rd m 10% 53734.00 64481.00

34th m 10% 59107.00 70928.00

35th m 10% 65018.00 78022.00

36th m 10% 71520.00 85824.00

37th m 10% 78672.00 94406.00

38th m 10% 86539.00 103847.00

39th m 10% 95193.00 114232.00

40th m 10% 104712.00 125654.00

Total Cost from 30m upto 40m 707752.00 849303.00

Avg Rate per metre 70775.00 84930.00

12.16 B Clayey Soil (10m dia. Well )


Unit = Running Meter
Taking output = 1 cum

226
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.18m/hour.
a) Labour
Mate day 0.25 195.43 48.86

Sinker ( skilled ) day 2.50 218.57 546.43

Sinking helper ( semi-skilled ) day 5.50 190.43 1047.37

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 705.67

c) Overhead charges @ 0.25 on (a+b) 2351.26

d) Contractor's profit @ 0.1 on (a+b+c) 1175.63

Rate per metre = (a+b+c+d) 12931.93


say 12932.00

12.16 B (ii) Beyond 3m upto 10m depth


Rate of sinking 0.15m/hour.
a) Labour
Mate day 0.40 195.43 78.17

Sinker day 3.00 218.57 655.71

Sinking helper ( semi-skilled ) day 5.50 190.43 1047.37

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.00 513.00 2052.00
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 910.87

c) Overhead charges @ 0.25 on (a+b) 2950.21

d) Contractor's profit @ 0.1 on (a+b+c) 1475.10

Rate per metre = (a+b+c+d) 16226.15


say 16226.00

12.16 B (iii) Beyond 10 m upto 20 m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a) (b) Including for
dewatering @
5% of cost, if
required

11th m 5% 17037.00 17889.00

12th m 5% 17889.00 18783.00

13th m 5% 18783.00 19722.00

14th m 5% 19722.00 20708.00

15th m 5% 20708.00 21743.00

16th m 5% 21743.00 22830.00

17th m 5% 22830.00 23972.00

18th m 5% 23972.00 25171.00

19th m 5% 25171.00 26430.00

20th m 5% 26430.00 27752.00

Total Cost from 10m upto 20m 214285.00 225000.00

Avg Rate per metre 21429.00 22500.00

12.16 B (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including
loading arrangement and Labour ). 25% for 5% for
Kentledge dewatering, if
required
31st m 7.5% 28412.00 35515.00 37291.00

32nd 7.5% 30543.00 38179.00 40088.00

227
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
33rd m 7.5% 32834.00 41043.00 43095.00

34th m 7.5% 35297.00 44121.00 46327.00

35th m 7.5% 37944.00 47430.00 49802.00

36th m 7.5% 40790.00 50988.00 53537.00

37th m 7.5% 43849.00 54811.00 57552.00

38th m 7.5% 47138.00 58923.00 61869.00

39th m 7.5% 50673.00 63341.00 66508.00

40th m 7.5% 54473.00 68091.00 71496.00

Total Cost from 30m upto 40m 401953.00 502442.00 527565.00

Avg Rate per metre 40195.00 50244.00 52757.00

12.16 B (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including
loading arrangement and Labour). 20% for 5% for
Kentledge dewatering, if
required
31st m 10% 59920.00 71904.00 75499.00

32nd 10% 65912.00 79094.00 83049.00

33rd m 10% 72503.00 87004.00 91354.20

34th m 10% 79753.00 95704.00 100489.20

35th m 10% 87728.00 105274.00 110537.70

36th m 10% 96501.00 115801.00 121591.05

37th m 10% 106151.00 127381.00 133750.05

38th m 10% 116766.00 140119.00 147124.95

39th m 10% 128443.00 154132.00 161838.60

40th m 10% 141287.00 169544.00 178021.20

Total Cost from 30m upto 40m 954964.00 1145957.00 1203254.95

Avg Rate per metre 95496.00 114596.00 120325.00

12.16 C Soft Rock (10m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a) Labour
Mate day 0.86 195.43 168.07

Sinker ( skilled ) day 4.00 218.57 874.28

Sinking helper ( semi-skilled ) day 16.00 190.43 3046.88

Diver day 1.40 218.57 306.00

b) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 1176.12 8232.84
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.25 513.00 2180.25

Consumables in sinking @ 10 per cent of (b) 1041.31

Add for dewatering @ 5 per cent of cost, if required 572.72

c) Overhead charges @ 0.25 on (a+b) 4105.59

d) Contractor's profit @ 0.1 on (a+b+c) 2052.79

Rate per metre = (a+b+c+d) 22580.73


say 22581.00

12.16 D Hard Rock (10m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a) Material
Gelatine 80 per cent Kg 11.00 112.77 1240.48

228
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Electric Detonators each. 44.00 14.27 627.71

b) Labour
Mate day 1.27 195.43 248.20

Driller day 2.00 218.57 437.14

Blaster day 0.25 304.89 76.22

Mazdoor day 24.00 187.43 4498.32

Mazdoor (Skilled) day 4.00 218.57 874.28

c) Machinery
Hire & running charges of crane with grab bucket of hour 8.50 1176.12 9997.02
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 513.00 1539.00
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 576.80

Consumables in sinking @ 10 per cent of cost of (b+c). 1824.70

d) Overhead charges @ 0.25 on (a+b+c) 5484.97

e) Contractor's profit @ 0.1 on (a+b+c+d) 2742.48

Rate per metre = (a+b+c+d+e) 30167.32


say 30167.00

12.17 1200 Sinking of 11 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter
Taking output = 0.50 m
Diameter of well - 11 m.
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.21 195.43 41.04

Sinker ( skilled ) day 1.50 218.57 327.86

Sinking helper (semi-skilled) day 3.30 190.43 628.42

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 705.67

d) Overhead charges @ 0.25 on (a+b+c) 2189.93

e) Contractor's profit @ 0.1 on (a+b+c+d) 1094.96

Cost for 0.5m = a+b+c+d 12044.60

Rate per metre = (a+b+c+d)/0.50 24089.19


say 24089.00

12.17 A (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.13 m/hour
a) Labour
Mate day 0.32 195.43 62.54

Sinker day 2.00 218.57 437.14

Sinking helper (semi-skilled) day 4.50 190.43 856.94

b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1176.12 4704.48
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 470.45

c) Overhead charges @ 0.25 on (a+b+c) 1632.89

d) Contractor's profit @ 0.1 on (a+b+c+d) 816.44

Cost for 0.5m = a+b+c+d 8980.87

Rate per metre = (a+b+c+d)/0.50 17961.74

229
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 17962.00

12.17 A (iii) Beyond 10m upto 20m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 18860.00

12th m 5% 19803.00

13th m 5% 20793.00

14th m 5% 21833.00

15th m 5% 22925.00

16th m 5% 24071.00

17th m 5% 25275.00

18th m 5% 26539.00

19th m 5% 27866.00

20th m 5% 29259.00

Total Cost from 10m upto 20m 237224.00

Avg Rate per metre 23722.00

12.17 A (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 31453.00 37744.00

22nd m 7.5% 33812.00 40574.00

23rd m 7.5% 36348.00 43618.00

24th m 7.5% 39074.00 46889.00

25th m 7.5% 42005.00 50406.00

26th m 7.5% 45155.00 54186.00

27th m 7.5% 48542.00 58250.00

28th m 7.5% 52183.00 62620.00

29th m 7.5% 56097.00 67316.00

30th m 7.5% 60304.00 72365.00

Total Cost from 20m upto 30m 444973.00 533968.00

Avg Rate per metre 44497.00 53397.00

12.17 A (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 66334.00 79601.00

32nd 10% 72967.00 87560.00

33rd m 10% 80264.00 96317.00

34th m 10% 88290.00 105948.00

35th m 10% 97119.00 116543.00

36th m 10% 106831.00 128197.00

37th m 10% 117514.00 141017.00

38th m 10% 129265.00 155118.00

39th m 10% 142192.00 170630.00

40th m 10% 156411.00 187693.00

Total Cost from 30m upto 40m 1057187.00 1268624.00

Avg Rate per metre 105719.00 126862.00

12.17 B Clayey Soil (11 m dia. Well )


Unit = Running Meter
Taking output = 0.50 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.10 m/hour
a) Labour

230
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mate day 0.26 195.43 50.81

Sinker ( skilled ) day 2.50 218.57 546.43

Sinking helper (semi-skilled) day 4.00 190.43 761.72

b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1176.12 5880.60
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 588.06

c) Overhead charges @ 0.25 on (a+b) 1956.90

d) Contractor's profit @ 0.1 on (a+b+c) 978.45

Cost for 0.5m = a+b+c+d 10762.97

Rate per metre = (a+b+c+d)/0.50 21525.95


say 21526.00

12.17 B (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.08 m/hour
a) Labour
Mate day 0.43 195.43 84.03

Sinker day 3.50 218.57 765.00

Sinking helper (semi-skilled) day 5.75 190.43 1094.97

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.25 513.00 2180.25
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 923.70

c) Overhead charges @ 0.25 on (a+b) 3026.17

d) Contractor's profit @ 0.1 on (a+b+c) 1513.08

Cost for 0.5m = a+b+c+d 16643.92

Rate per metre = (a+b+c+d)/0.50 33287.84


say 33288.00

12.17 B (iii) Beyond 10 m upto 20 m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a) (b)Including for
dewatering @
5% of cost, if
required
11th m 5% 34952.00 36700.00

12th m 5% 36700.00 38535.00

13th m 5% 38535.00 40462.00

14th m 5% 40462.00 42485.00

15th m 5% 42485.00 44609.00

16th m 5% 44609.00 46839.00

17th m 5% 46839.00 49181.00

18th m 5% 49181.00 51640.00

19th m 5% 51640.00 54222.00

20th m 5% 54222.00 56933.00

Total Cost from 10m upto 20m 439625.00 461606.00

Avg Rate per metre 43963.00 46161.00

12.17 B (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) (c)Including 25% (b)Including
loading arrangement and Labour ). for Kentledge 5% for
dewatering, if
required

21st m 7.5% 58289.00 72861.00 76504.00

22nd 7.5% 62661.00 78326.00 82242.00

23rd m 7.5% 67361.00 84201.00 88411.00

231
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
24th m 7.5% 72413.00 90516.00 95042.00

25th m 7.5% 77844.00 97305.00 102170.00

26th m 7.5% 83682.00 104603.00 109833.00

27th m 7.5% 89958.00 112448.00 118070.00

28th m 7.5% 96705.00 120881.00 126925.00

29th m 7.5% 103958.00 129948.00 136445.00

30th m 7.5% 111755.00 139694.00 146679.00

Total Cost from 20m upto 30m 824626.00 1030783.00 1082322.00

Avg Rate per metre 82463.00 103078.00 108232.00

12.17 B (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) (c ) Including (b)Including
loading arrangement and Labour). 20% for 5% for
Kentledge dewatering, if
required
31st m 10% 122931.00 147517.00 154893.00

32nd 10% 135224.00 162269.00 170382.00

33rd m 10% 148746.00 178495.00 187420.00

34th m 10% 163621.00 196345.00 206162.00

35th m 10% 179983.00 215980.00 226779.00

36th m 10% 197981.00 237577.00 249456.00

37th m 10% 217779.00 261335.00 274402.00

38th m 10% 239557.00 287468.00 301841.00

39th m 10% 263513.00 316216.00 332027.00

40th m 10% 289864.00 347837.00 365229.00

Total Cost from 30m upto 40m 1959199 2351039 2468591

Avg Rate per metre 195920.00 235104.00 246859.00

12.17 C Soft Rock (11m dia well )


Unit = Running Meter.
Taking output = 0.50 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.06 m/hour
a) Labour
Mate day 0.95 195.43 185.66

Sinker ( skilled ) day 4.25 218.57 928.92

Sinking helper (semi-skilled) day 18.00 190.43 3427.74

Diver day 1.50 218.57 327.86

b) Machinery
Hire & running charges of crane with grab bucket of hour 8.00 1176.12 9408.96
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.50 513.00 2308.50

Consumables in sinking @ 10 per cent of (b) 1171.75

Add for dewatering @ 5 per cent of cost of (b), if 644.46


required
c) Overhead charges @ 0.25 on (a+b) 4600.96

d) Contractor's profit @ 0.1 on (a+b+c) 2300.48

Cost for 0.5m = a+b+c+d 25305.28

Rate per metre = (a+b+c+d)/0.50 50610.57


say 50611.00

12.17 D Hard Rock (11m dia well )


Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a) Material
Gelatine 80 per cent Kg 12.00 112.77 1353.25

232
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Electric Detonators each. 48.00 14.27 684.78

b) Labour
Mate day 1.35 195.43 263.83

Driller day 2.00 218.57 437.14

Blaster day 0.25 304.89 76.22

Mazdoor day 26.00 187.43 4873.18

Mazdoor (Skilled) day 4.00 218.57 874.28

c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1176.12 11761.20
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.50 513.00 1795.50
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 677.84

Consumables in sinking @ 10 per cent of cost of (b+c). 2008.14

d) Overhead charges @ 0.25 on (a+b+c) 6201.34

e) Contractor's profit @ 0.1 on (a+b+c+d) 3100.67

Cost for 0.5m = a+b+c+d 34107.36

Rate per metre = (a+b+c+d)/0.50 68214.72


say 68215.00

12.18 1200 Sinking of 12 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter
Taking output = 0.25 m
Diameter of well - 12 m.
A Sandy Soil
(i) I) Depth below bed level upto 3.0 M
Rate of sinking @ 0.05 m/hour
a) Labour
Mate day 0.22 195.43 42.99

Sinker ( skilled ) day 1.75 218.57 382.50

Sinking helper (semi-skilled) day 4.00 190.43 761.72

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 705.67

c) Overhead charges @ 0.25 on (a+b) 2237.40

d) Contractor's profit @ 0.1 on (a+b+c) 1118.70

Cost for 0.25m = a+b+c+d 12305.71

Rate per metre = (a+b+c+d)/0.25 49222.82


say 49223.00

12.18 A (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.038 m/hour
a) Labour
Mate day 0.37 195.43 72.31

Sinker day 2.50 218.57 546.43

Sinking helper (semi-skilled) day 4.75 190.43 904.54

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1176.12 7644.78
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 764.48

c) Overhead charges @ 0.25 on (a+b) 2483.13

d) Contractor's profit @ 0.1 on (a+b+c) 1241.57

Cost for 0.25m = a+b+c+d 13657.24

233
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate per metre = (a+b+c+d)/0.25 54628.94
say 54629.00

12.18 A (iii) Beyond 10m upto 20m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 57360.00

12th m 5% 60228.00

13th m 5% 63239.00

14th m 5% 66401.00

15th m 5% 69721.00

16th m 5% 73207.00

17th m 5% 76867.00

18th m 5% 80710.00

19th m 5% 84746.00

20th m 5% 88983.00

Total Cost from 10m upto 20m 721462.00

Avg Rate per metre 72146.00

12.18 A (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement and Labour. 20% for
Kentledge

21st m 7.5% 95657.00 114788.00

22nd m 7.5% 102831.00 123397.00

23rd m 7.5% 110543.00 132652.00

24th m 7.5% 118834.00 142601.00

25th m 7.5% 127747.00 153296.00

26th m 7.5% 137328.00 164794.00

27th m 7.5% 147628.00 177154.00

28th m 7.5% 158700.00 190440.00

29th m 7.5% 170603.00 204724.00

30th m 7.5% 183398.00 220078.00

Total Cost from 20m upto 30m 1353269.00 1623924.00

Avg Rate per metre 135327.00 162392.00

12.18 A (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 201738.00 242086.00

32nd 10% 221912.00 266294.00

33rd m 10% 244103.00 292924.00

34th m 10% 268513.00 322216.00

35th m 10% 295364.00 354437.00

36th m 10% 324900.00 389880.00

37th m 10% 357390.00 428868.00

38th m 10% 393129.00 471755.00

39th m 10% 432442.00 518930.00

40th m 10% 475686.00 570823.00

Total Cost from 30m upto 40m 3215177 3858213

Avg Rate per metre 321518.00 385821.00

12.18 B Clayey Soil (12 m dia. Well )


Unit = Running Meter.
Taking output = 0.25 meter.
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.04 m/hour

234
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
a) Labour
Mate day 0.30 195.43 58.63

Sinker ( skilled ) day 3.00 218.57 655.71

Sinking helper (semi-skilled) day 4.50 190.43 856.94

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 1176.12 7350.75
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 735.08

c) Overhead charges @ 0.25 on (a+b) 2414.27

d) Contractor's profit @ 0.1 on (a+b+c) 1207.14

Cost for 0.25m = a+b+c+d 13278.51

Rate per metre = (a+b+c+d)/0.25 53114.04


say 53114.00

12.18 B (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.03 m/hour
a) Labour
Mate day 0.48 195.43 93.81

Sinker day 3.75 218.57 819.64

Sinking helper (semi-skilled) day 6.00 190.43 1142.58

b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 1176.12 9797.08
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.50 513.00 2308.50
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 1210.56

c) Overhead charges @ 0.25 on (a+b) 3843.04

d) Contractor's profit @ 0.1 on (a+b+c) 1921.52

Cost for 0.25m = a+b+c+d 21136.72

Rate per metre = (a+b+c+d)/0.25 84546.89


say 84547.00

12.18 B (iii) Beyond 10 m upto 20 m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a) (b)Including for
dewatering @
5% of cost, if
required

11th m 5% 88774.00 93213.00

12th m 5% 93213.00 97874.00

13th m 5% 97874.00 102768.00

14th m 5% 102768.00 107906.00

15th m 5% 107906.00 113301.00

16th m 5% 113301.00 118966.00

17th m 5% 118966.00 124914.00

18th m 5% 124914.00 131160.00

19th m 5% 131160.00 137718.00

20th m 5% 137718.00 144604.00

Total Cost from 10m upto 20m 1116594.00 1172424.00

Avg Rate per metre 111659.00 117242.00

12.18 B (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) (c)Including 25% (b)Including
loading arrangement and Labour ). for Kentledge 5% for
dewatering, if
required
21st m 7.5% 148047.00 185059.00 194312.00

22nd 7.5% 159151.00 198939.00 208886.00

235
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
23rd m 7.5% 171087.00 213859.00 224552.00

24th m 7.5% 183919.00 229899.00 241394.00

25th m 7.5% 197713.00 247141.00 259498.00

26th m 7.5% 212541.00 265676.00 278960.00

27th m 7.5% 228482.00 285603.00 299883.00

28th m 7.5% 245618.00 307023.00 322374.00

29th m 7.5% 264039.00 330049.00 346551.00

30th m 7.5% 283842.00 354803.00 372543.00

Total Cost from 20m upto 30m 2094439 2618051 2748953

Avg Rate per metre 209444.00 261805.00 274895.00

12.18 B (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) (c ) Including (b)Including
loading arrangement and Labour). 20% for 5% for
Kentledge dewatering, if
required

31st m 10% 312226.00 374671.00 393405.00

32nd 10% 343449.00 412139.00 432746.00

33rd m 10% 377794.00 453353.00 476021.00

34th m 10% 415573.00 498688.00 523622.00

35th m 10% 457130.00 548556.00 575984.00

36th m 10% 502843.00 603412.00 633583.00

37th m 10% 553127.00 663752.00 696940.00

38th m 10% 608440.00 730128.00 766634.00

39th m 10% 669284.00 803141.00 843298.00

40th m 10% 736212.00 883454.00 927627.00

Total Cost from 30m upto 40m 4976078 5971294 6269860

Avg Rate per metre 497608.00 597129.00 626986.00

12.18 C Soft Rock (12m dia well )


Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a) Labour
Mate day 1.06 195.43 207.16

Sinker ( skilled ) day 4.50 218.57 983.57

Sinking helper (semi-skilled) day 20.00 190.43 3808.60

Diver day 1.75 218.57 382.50

b) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1176.12 11761.20
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.75 513.00 2436.75
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 1419.80

Add for dewatering @ 5 per cent, if required 780.89

c) Overhead charges @ 0.25 on (a+b) 5445.11

d) Contractor's profit @ 0.1 on (a+b+c) 2722.56

Cost for 0.25m = a+b+c+d 29948.12

Rate per metre = (a+b+c+d)/0.25 119792.48


say 119792.00

12.18 D Hard Rock (12m dia well )


Unit = Running Meter
Taking output = 0.25 m
(i) Depth in hard rock strata upto 3 m
Rate of sinking @ 0.020 m/hour

236
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
a) Material
Gelatine80 per cent Kg 14.00 112.77 1578.79

Electric detonator each. 56.00 14.27 798.90

b) Labour
Mate day 1.44 195.43 281.42

Driller day 2.00 218.57 437.14

Blaster day 0.25 304.89 76.22

Mazdoor day 28.00 187.43 5248.04

Mazdoor (Skilled) day 4.50 218.57 983.57

c) Machinery
Hire & running charges of crane with grab bucket of hour 12.50 1176.12 14701.50
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 4.00 513.00 2052.00
breaker/Jack hammer or drill
Dewatering @ 5 per cent, if required. 837.68

Consumables in sinking @ 10 per cent of (c). 1759.12

d) Overhead charges @ 0.25 on (a+b+c) 7188.59

e) Contractor's profit @ 0.1 on (a+b+c+d) 3594.30

Cost for 0.25m = a+b+c+d+e 39537.27

Rate per metre = (a+b+c+d+e)/0.25 158149.08


say 158149.00

12.19 1200 Sinking of Twin D Type well (other than pneumatic


method of sinking) through all types of strata namely
sandy soil, clayey soil and rock as shown against each
case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter
Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.20 195.43 39.09

Sinker ( skilled ) day 1.25 218.57 273.21

Sinking helper (semi-skilled) day 3.75 190.43 714.11

b) Machinery
Hire & running charges of crane with grab bucket of hour 5.50 1176.12 6468.66
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 646.87

c) Overhead charges @ 0.25 on (a+b) 2035.48

d) Contractor's profit @ 0.1 on (a+b+c) 1017.74

Rate per metre = (a+b+c+d) 11195.16


say 11195.00

12.19 A (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.30 195.43 58.63

Sinker day 1.50 218.57 327.86

Sinking helper (semi-skilled) day 4.00 190.43 761.72

b) Machinery
Hire & running charges of crane with grab bucket of hour 5.88 1176.12 6915.59
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 691.56

c) Overhead charges @ 0.25 on (a+b) 2188.84

237
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) Contractor's profit @ 0.1 on (a+b+c) 1094.42

Rate per metre = (a+b+c+d) 12038.60


say 12039.00

12.19 A (iii) Beyond 10m upto 20m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 12641.00

12th m 5% 13273.00

13th m 5% 13937.00

14th m 5% 14634.00

15th m 5% 15366.00

16th m 5% 16134.00

17th m 5% 16941.00

18th m 5% 17788.00

19th m 5% 18677.00

20th m 5% 19611.00

Total Cost from 10m upto 20m 159002.00

Avg Rate per metre 15900.00

12.19 A (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 21082.00 25298.00

22nd m 7.5% 22663.00 27196.00

23rd m 7.5% 24363.00 29236.00

24th m 7.5% 26190.00 31428.00

25th m 7.5% 28154.00 33785.00

26th m 7.5% 30266.00 36319.00

27th m 7.5% 32536.00 39043.00

28th m 7.5% 34976.00 41971.00

29th m 7.5% 37599.00 45119.00

30th m 7.5% 40419.00 48503.00

Total Cost from 20m upto 30m 298248.00 357898.00

Avg Rate per metre 29825.00 35790.00

12.19 A (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 44461.00 53353.00

32nd 10% 48907.00 58688.00

33rd m 10% 53798.00 64558.00

34th m 10% 59178.00 71014.00

35th m 10% 65096.00 78115.00

36th m 10% 71606.00 85927.00

37th m 10% 78767.00 94520.00

38th m 10% 86644.00 103973.00

39th m 10% 95308.00 114370.00

40th m 10% 104839.00 125807.00

Total Cost from 30m upto 40m 708604.00 850325.00

Avg Rate per metre 70860.00 85033.00

12.19 B Clayey Soil (Twin D Type Well )


Unit = Running Meter
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M

238
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate of sinking @ 0.16 m/hour
a) Labour
Mate day 0.26 195.43 50.81

Sinker ( skilled ) day 2.50 218.57 546.43

Sinking helper (semi-skilled) day 4.00 190.43 761.72

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 1176.12 7350.75
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 735.08

c) Overhead charges @ 0.25 on (a+b) 2361.20

d) Contractor's profit @ 0.1 on (a+b+c) 1180.60

Rate per metre = (a+b+c+d) 12986.57


say 12987.00

12.19 B (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.45 195.43 87.94

Sinker day 3.25 218.57 710.35

Sinking helper (semi-skilled) day 6.00 190.43 1142.58

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.67 1176.12 7844.72
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.50 513.00 2308.50
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 1015.32

c) Overhead charges @ 0.25 on (a+b) 3277.35

d) Contractor's profit @ 0.1 on (a+b+c) 1638.68

Rate per metre = (a+b+c+d) 18025.45


say 18025.00

12.19 B (iii) Beyond 10 m upto 20 m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a) (b)Including for
dewatering @
5% of cost, if
required

11th m 5% 18927.00 19873.00

12th m 5% 19873.00 20867.00

13th m 5% 20867.00 21910.00

14th m 5% 21910.00 23006.00

15th m 5% 23006.00 24156.00

16th m 5% 24156.00 25364.00

17th m 5% 25364.00 26632.00

18th m 5% 26632.00 27964.00

19th m 5% 27964.00 29362.00

20th m 5% 29362.00 30830.00

Total Cost from 10m upto 20m 238061.00 249964.00

Avg Rate per metre 23806.00 24996.00

12.19 B (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) (c)Including 25% (b)Including
loading arrangement and Labour ). for Kentledge 5% for
dewatering, if
required

21st m 7.5% 31564.00 39455.00 41428.00

22nd 7.5% 33931.00 42414.00 44535.00

23rd m 7.5% 36476.00 45595.00 47875.00

239
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
24th m 7.5% 39212.00 49015.00 51466.00

25th m 7.5% 42153.00 52691.00 55326.00

26th m 7.5% 45314.00 56643.00 59475.00

27th m 7.5% 48713.00 60891.00 63936.00

28th m 7.5% 52366.00 65458.00 68731.00

29th m 7.5% 56293.00 70366.00 73884.00

30th m 7.5% 60515.00 75644.00 79426.00

Total Cost from 20m upto 30m 446537.00 558172.00 586082.00

Avg Rate per metre 44654.00 55817.00 58608.00

12.19 B (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) (c ) Including (b)Including
loading arrangement and Labour). 20% for 5% for
Kentledge dewatering, if
required

31st m 10% 66567.00 79880.00 83874.00

32nd 10% 73224.00 87869.00 92262.00

33rd m 10% 80546.00 96655.00 101488.00

34th m 10% 88601.00 106321.00 111637.00

35th m 10% 97461.00 116953.00 122801.00

36th m 10% 107207.00 128648.00 135080.00

37th m 10% 117928.00 141514.00 148590.00

38th m 10% 129721.00 155665.00 163448.00

39th m 10% 142693.00 171232.00 179794.00

40th m 10% 156962.00 188354.00 197772.00

Total Cost from 30m upto 40m 1060910.00 1273091.00 1336746.00

Avg Rate per metre 106091.00 127309.00 133675.00

12.19 C Soft Rock (Twin D Type Well )


Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a) Labour
Mate day 0.86 195.43 168.07

Sinker ( skilled ) day 4.50 218.57 983.57

Sinking helper (semi-skilled) day 15.00 190.43 2856.45

Diver day 1.50 218.57 327.86

b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 1176.12 9797.08
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 6.00 513.00 3078.00

Consumables in sinking @ 10 per cent of (b) 1287.51

Add for dewatering @ 5 per cent, if required 708.13

c) Overhead charges @ 0.25 on (a+b) 4801.66

d) Contractor's profit @ 0.1 on (a+b+c) 2400.83

Rate per metre = (a+b+c+d) 26409.15


say 26409.00

12.19 D Hard Rock (Twin D Type Well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a) Material
Geletine80 per cent Kg 10.00 112.77 1127.71

240
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Electric detonators each. 40.00 14.27 570.65

b) Labour
Mate day 1.34 195.43 261.88

Driller day 2.00 218.57 437.14

Blaster day 0.25 304.89 76.22

Mazdoor day 25.00 187.43 4685.75

Mazdoor (Skilled) day 4.25 218.57 928.92

c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1176.12 11761.20
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 513.00 1539.00
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if required. 984.51

Consumables in sinking @ 10 per cent of (b). 1428.47

d) Overhead charges @ 0.25 on (a+b+c) 5950.36

e) Contractor's profit @ 0.1 on (a+b+c+d) 2975.18

Rate per metre = (a+b+c+d+e) 32726.99


say 32727.00

12.20 1200 Pneumatic sinking of wells with equipment of approved


design, drawing and specifications worked by
competent and trained personnel and comprising of
compression and decompression chambers, reducers,
two air locks separately for men and plant & materials,
arrangement for supply of fresh air to working
chambers, check valves, exhaust valves, shafts made
from steel plates of riveted construction not less than 6
mm thick to withstand an air pressure of 0.50 MPa,
controlled blasting of hard rock where required,
staircases and 1 m wide landing plateforms with railing,
arrangement for compression and decompression,
electric lighting of 50 V maximum, proper rooms for rest
and medical examinations and compliance with safety
precautions as per IS:4138, all as per clause1207.6 of
MoRTH Specifications.

Unit - 1 cum
Taking output = 5 cum
a) Material
M35 grade RCC corbel provided for supporting of Cum 8.00 3768.00 30144.00
equipment (Dimensions as per ground conditions). Rate
may be adopted vide Item 12.8 (H)
HYSD bar reinforcement in corbel tonne 0.48 44187.50 21210.00

Blasting material
Gelatine 80 per cent Kg 1.50 112.77 169.16

Electric detonators each 6.00 14.27 85.60

b) Labour
Medical Officer day 0.50 0.00 0.00

Para medical personnel day 1.00 0.00 0.00

Mate day 1.86 195.43 363.50

Driller day 1.00 218.57 218.57

Blaster day 0.50 304.89 152.45

Mazdoor (for cutting, blasting, cleaning, removal of day 30.00 187.43 5622.90
Material etc.)
Mazdoor (Skilled) (for fixation and removal of adopter day 10.00 218.57 2185.70
for air lock, carrying out mechanical and electrical
operations and repairs and other skilled jobs.)
Diver day 4.00 218.57 874.28

c) Machinery

241
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
(i) Induction, deinduction and erection of plant and hour 6.00 Value #VALUE!
equipment including all components and
accessories for pneumatic method of well sinking.

Induction and deinduction L.S 100000.00

Erection at site and commissioning L.S 150000.00

Usage of plant and equipment for pneumatic method of hour 6.00 3834.00 23004.00
well sinking
Air compressor 250 cfm, 2 nos. hour 2x6 293.76 3525.12

Hire and running charges of crane of 15 tonne capacity hour 6.00 770.04 4620.24

Motorised barge of 20 tonne capacity hour 6.00 142.56 855.36

Boat to carry atleast 20 persons hour 6.00 142.56 855.36

Electric generating set 33 KVA hour 6.00 342.36 2054.16

Tipper 10 tonne capacity hour 6.00 846.00 5076.00

d) Overhead charges @ 0.25 on (a+b+c) #VALUE!

e) Contractor's profit @ 0.1 on (a+b+c+d) #VALUE!

Cost for 5 cum = a+b+c+d+e (see notes below) #VALUE!

Rate per cum = (a+b+c+d+e)/5 #VALUE!

Note 1.The cost of induction, deinduction and erection of


equipment shall be divided by the total quantity of pneumatic
sinking for all the wells of a particular bridge to arrive at the
per cum rate on account of this item.
2.Cost of pneumatic sinking per cum of individual wells will be
added to the cost indicated at (1) above to arrive at the final
rate of pneumatic sinking per cum.
3.The cost of induction and deinduction will depend upon the
distance involved for shifting of equipment which may be
assessed in individual cases as per actual ground conditions
at the time of making of cost estimates.
4.In case pneumatic sinking is involved on a dry bed, the
provision of barge and boat may be omitted.
5.The necessity and dimensions of the corbel will be as per
actual ground conditions.
6.Small equipments like welding sets, pumps, vibrators,
pneumatic tools, portable lamps, fire extinguishers, hose
pipes etc., have not been included as the same are covered
as items of minor T&P under overhead charges.
7.Depth of sinking shall be restricted to 30 m.
12.21 1207 Sand Filling in Wells complete as per Drawing and
Technical Specifications.
Unit = 1 cum
Taking output = 1 cum
a) Material
Sand (assuming 20 per cent voids ) cum 1.20 111.50 133.80

b) Labour
Mate day 0.01 195.43 1.95

Mazdoor day 0.30 187.43 56.23

c) Overhead charges @ 0.25 on (a+b) 48.00

d) Contractor's profit @ 0.1 on (a+b+c) 24.00

Rate per cum (a+b+c+d) 263.98


say 264.00

12.22 1200 & Providing Steel Liner 10 mm thick for Curbs and 6 mm
1900 thick for Steining of Wells including Fabricating and
Setting out as per Detailed Drawing.
Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage tonne 1.05 48095.30 50500.07

b) Labour

242
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mate day 1.24 195.43 242.33

Fitter day 6.00 251.19 1507.14

Blacksmith day 5.00 220.57 1102.85

Welder day 5.00 247.19 1235.95

Mazdoor day 10.00 187.43 1874.30

Electrodes, cutting gas and other consumables @ 5 per 2525.00


cent on cost a (a) above.
c) Overhead charges @ 0.25 on (a+b) 14746.91

d) Contractor's profit @ 0.1 on (a+b+c) 7373.46

Rate for per MT (a+b+c+d) 81108.01


say 81108.00

12.23 1100 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a) Materials
PCC Grade M35 cum 6.62 5621.00 37211.02

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 5023.08 30138.48
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 525.00 262.50
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included in
piling rig
Loader I cum bucket capacity. hour 0.30 1148.00 344.40

Tipper 5.5 cum capacity for disposal of muck from pile hour 0.30 846.00 253.80
bore hole
Bentonite kg 300.00 2.24 673.49

c) Labour
Mate/Supervisor day 0.14 195.43 27.36

Mazdoor day 3.50 187.43 656.01

d) Overhead charges @ 0.25 on (b+c) 8089.01

e) Contractor's profit @ 0.1 on (b+c+d) 4044.50

Cost for 15 m = a+b+c+d+d+e 81700.57

Rate per metre (a+b+c+d+e)/15 5446.70


say 5447.00

12.24 Bored cast-in-situ M35 grade R.C.C. Pile excluding


1100,16 Reinforcement complete as per Drawing and Technical
00 & Specifications and removal of excavated earth with all
1700 lifts and lead upto 1000 m.
Pile diameter-1000 mm
Unit = meter
Taking output = 10 m
a) Materials
PCC Grade M35 cum 7.85 5621.00 44124.85

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 5023.08 30138.48
power unit and complete accessories including shifting
from one bore location to another.

243
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Hire and running charges of light crane for lowering hour 0.50 525.00 262.50
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included in
piling rig
Loader I cum bucket capacity. hour 0.40 1148.00 459.20

Tipper 5.5 cum capacity for disposal of muck from pile hour 0.40 846.00 338.40
bore hole
Bentonite kg 350.00 2.24 785.74

c) Labour
Mate/Supervisor day 0.16 195.43 31.27

Mazdoor day 4.00 187.43 749.72

d) Overhead charges @ 0.25 on (b+c) 8191.33

e) Contractor's profit @ 0.1 on (b+c+d) 4095.66

Cost for 10 m = a+b+c+d+d+e 89177.15

Rate per metre (a+b+c+d+e)/10 8917.72


say 8918.00

12.25 1100 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a) Materials
PCC Grade M35 cum 10.17 5621.00 57165.57

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 5023.08 30138.48
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 525.00 262.50
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included in
piling rig
Loader I cum bucket capacity. hour 0.50 1148.00 574.00

Tipper 5.5 cum capacity for disposal of muck from pile hour 0.50 846.00 423.00
bore hole
Bentonite kg 385.00 2.24 864.32

c) Labour
Mate/Supervisor day 0.18 195.43 35.18

Mazdoor day 4.50 187.43 843.44

d) Overhead charges @ 0.25 on (b+c) 8285.23

e) Contractor's profit @ 0.1 on (b+c+d) 4142.61

Cost for 9 m = a+b+c+d+d+e 102734.32

Rate per metre (a+b+c+d+e)/9 11414.92


say 11415.00

12.26 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 750 mm
Unit = Running meter
Taking output = 40 metre
a) Materials
PCC Grade M35 cum 17.66 5621.00 99266.86

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
b) Materials Pile shoes

244
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
i) C.I. shoes for the pile Kg 160.00 56.39 9021.68

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 66.31 4641.36

iii) Steel helmet and cushion block on top of casing head Kg 50.00 51.16 2558.23
during driving
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 5023.08 30138.48
acting pile driving hammer complete with power unit and
accessories..
Hiring and running charges for light crane 5 tonnes hour 0.50 599.40 299.70
lifting capacity for lowering reinforcement and handling
steel casing.
d) Labour
Mate/Supervisor day 0.12 195.43 23.45

Mazdoor day 3.00 187.43 562.29

e) Overhead charges @ 0.25 on (b+c+d) 11811.30

f) Contractor's profit @ 0.1 on (b+c+d+e) 5905.65

Cost for 40 m = a+b+c+d+e 164229.01

Rate per metre (a+b+c+d+e)/40 4105.73


say 4106.00

Note 1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.

12.27 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
a) Materials
PCC Grade M35 cum 23.55 5621.00 132374.55

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 56.39 9021.68

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 66.31 4641.36

iii) Steel helmet and cushion block on top of casing head Kg 50.00 51.16 2558.23
during driving
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 5023.08 30138.48
acting pile driving hammer complete with power unit and
accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 599.40 299.70
lifting capacity for lowering reinforcement and handling
steel casing.
Hire and running charges for light crane for lowering hour 0.50 525.00 262.50
reinforcement cage.
d) Labour
Mate/Supervisor day 0.16 195.43 31.27

Mazdoor day 4.00 187.43 749.72

e) Overhead charges @ 0.25 on (b+c+d) 11925.74

f) Contractor's profit @ 0.1 on (b+c+d+e) 5962.87

Cost for 30 m = a+b+c+d+e 197966.10

Rate per metre (a+b+c+d+e)/30 6598.87


say 6599.00

245
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Note 1.The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
12.28 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 1200 mm
Unit = Running meter
Taking output = 20 metre
a) Materials
PCC Grade M35 cum 22.61 5621.00 127090.81

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 56.39 9021.68

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 66.31 4641.36

iii) Steel helmet on top of casing head during driving Kg 50.00 51.16 2558.23

c) Machinery
Hire and running charges of piling rig Including double hour 6.00 5023.08 30138.48
acting pile driving hammer complete with power unit and
accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 599.40 299.70
lifting capacity for lowering reinforcement and handling
steel casing.
d) Labour
Mate/Supervisor day 0.18 195.43 35.18

Mazdoor day 4.50 187.43 843.44

e) Overhead charges @ 0.25 on (b+c+d) 11884.52

f) Contractor's profit @ 0.1 on (b+c+d+e) 5942.26

Cost for 20 m = a+b+c+d+e 192455.66

Rate per metre (a+b+c+d+e)/20 9622.78


say 9623.00

Note 1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
12.29 1100 & Driven precast vertical M35 grade R.C.C. Piles
1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile Diameter = 500 mm
Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M35 cum 11.78 5336.00 62858.08

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I Shoes Kg 240.00 56.39 13532.53

b) M.S. shoes Kg 105.00 42.08 4418.43

246
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c) Steel helmet and cushion block on top of pile head Kg 30.00 51.16 1534.94
during driving.
c) Machinery
Crane20 t capacity hour 6.00 785.16 4710.96

Vibrating Pile driving hammer complete with power unit hour 6.00 Value #VALUE!
and accessories.
d) Labour
Mate/Supervisor day 0.12 195.43 23.45

Mazdoor day 3.00 187.43 562.29

Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) #VALUE!

f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!

Cost for 60 m = a+b+c+d+e+f #VALUE!

Rate per metre (a+b+c+d+e+f)/60 #VALUE!


say #VALUE!

Note The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
12.30 1100 & Driven precast vertical M35 grade R.C.C. Piles
1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile Diameter = 750 mm
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M35 cum 22.08 5336.00 117818.88

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I. shoes Kg 160.00 56.39 9021.68

b) M.S. shoes Kg 70.00 42.08 2945.62

c) Steel helmet and cushion block on top of pile head Kg 40.00 51.16 2046.59
during driving.
c) Machinery
Crane 40 T capacity hour 6.00 1166.40 6998.40

Vibrating Pile driving hammer complete with power unit hour 6.00 Value #VALUE!
and accessories.
d) Labour
Mate/Supervisor day 0.16 195.43 31.27

Mazdoor day 4.00 187.43 749.72

Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) #VALUE!

f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!

Cost for 50 m = a+b+c+d+e+f #VALUE!

Rate per metre (a+b+c+d+e+f)/50 #VALUE!


say #VALUE!

Note The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
12.31 1100 & Driven precast vertical M35 grade R.C.C. Piles
1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile Diameter = 1000 mm
Unit = Running Meter
Taking output = 40 m
a) Materials

247
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
RCC Grade M35 cum 31.40 5336.00 167550.40

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I. shoes for the pile Kg 160.00 56.39 9021.68

b) M.S. shoes @ 35 Kg per pile of 15 m Kg 70.00 42.08 2945.62

c) Steel helmet and cushion block on top of pile head Kg 50.00 51.16 2558.23
during driving.
c) Machinery
Crane 50 t capacity. hour 6.00 1176.12 7056.72

Vibrating Pile driving hammer complete with power unit hour 6.00 Value #VALUE!
and accessories.
d) Labour
Mate/Supervisor day 0.20 195.43 39.09

Mazdoor day 5.00 187.43 937.15

Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) #VALUE!

f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!

Cost for 40 m = a+b+c+d+e+f #VALUE!

Rate per metre (a+b+c+d+e+f)/40 #VALUE!


say #VALUE!

Note The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
12.32 1100&1 Driven precast vertical M35 grade R.C.C. Piles
700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Size of pile - 300 mm x 300 mm
Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 5.40 5336.00 28814.40
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C I shoes kg 240.00 56.39 13532.53

b) M. S shoes kg 105.00 42.08 4418.43

c) Steel helmet and cushion block on top of pile head Kg 30.00 51.16 1534.94
during driving.
c) Machinery
Crane 10 tonne capacity hour 6.00 627.48 3764.88

Vibrating Pile driving hammer complete with power unit hour 6.00 Value #VALUE!
and accessories.
d ) Labour
Mate/Supervisor day 0.12 195.43 23.45

Mazdoor day 3.00 187.43 562.29

Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) #VALUE!

f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!

Cost for 60 m = a+b+c+d+e+f #VALUE!

Rate per metre (a+b+c+d+e+f)/60 #VALUE!


say #VALUE!

Note The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.

248
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.33 1100 Driven precast vertical M35 grade R.C.C. Piles
&1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Size of pile - 500 mm x 500 mm
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 12.50 5336.00 66700.00
plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C I shoes kg 160.00 56.39 9021.68

b) M. S shoes kg 70.00 42.08 2945.62

c) Steel helmet and cushion block on top of pile head Kg 30.00 51.16 1534.94
during driving.
c) Machinery
Crane 20 tonne capacity hour 6.00 785.16 4710.96

Vibrating Pile driving hammer complete with power unit hour 6.00 Value #VALUE!
and accessories.
d ) Labour
Mate/Supervisor day 0.16 195.43 31.27

Mazdoor day 4.00 187.43 749.72

Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) #VALUE!

f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!

Cost for 50 m = a+b+c+d+e+f #VALUE!

Rate per metre (a+b+c+d+e+f)/50 #VALUE!


say #VALUE!

Note The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
12.34 1100 Driven precast vertical M35 grade R.C.C. Piles
&1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Size of pile - 750 mm x 750 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 22.50 5336.00 120060.00
plug vide item no. 13.11( F ) (IV)
b ) Material
Pile shoes
a) C I shoes kg 160.00 56.39 9021.68

b) M. S shoes kg 70.00 42.08 2945.62

c) Steel helmet and cushion block on top of pile head Kg 30.00 51.16 1534.94
during driving.
c) Machinery
Crane 20 tonne capacity hour 6.00 785.16 4710.96

Vibrating Pile driving hammer complete with power unit hour 6.00 Value #VALUE!
and accessories.
d ) Labour
Mate/Supervisor day 0.18 195.43 35.18

Mazdoor day 4.50 187.43 843.44

Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) #VALUE!

249
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!

Cost for 40 m = a+b+c+d+e+f #VALUE!

Rate per metre (a+b+c+d+e+f)/40 #VALUE!


say #VALUE!

Note The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
12.35 1100, Driven Vertical Steel Piles complete as per Drawing and
1900 & Technical Specification
Section of the pile - H Section steel column 400 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 70 m
a) Materials
Structural steel including 5 per cent wastage @ 82.20 tonnes 6.04 48095.30 290495.64
kg/m
b) Machinery
Crane 10 T capacity hour 6.00 627.48 3764.88

Vibrating Pile driving hammer complete with power unit hour 6.00 Value #VALUE!
and other accessories.
c) Labour
Mate/Supervisor day 0.12 195.43 23.45

Mazdoor day 3.00 187.43 562.29

Add 0.5 per cent of (a+b+c) for providing steel #VALUE!


helmet on top of pile head during driving, stacking of
piles at site, providing anti-corrosion treatment and other
imponderables during installation.
d) Overhead charges @ 0.25 on (a+b+c) #VALUE!

e) Contractor's profit @ 0.1 on (a+b+c+d) #VALUE!

Cost for 70 m = a+b+c+d+e #VALUE!

Rate per metre (a+b+c+d+e)/70 #VALUE!


say #VALUE!

12.36 1100 Driven Vertical Steel Piles complete as per Drawing and
&1900 & Technical Specification
Section of the pile - H Section steel column 450 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 60 m
a) Materials
Structural steel including 5 per cent wastage @92.50 tonnes 5.83 48095.30 280395.63
kg/m
b) Machinery
Crane 10 T capacity hour 6.00 627.48 3764.88

Vibrating Pile driving hammer complete with power unit hour 6.00 Value #VALUE!
and accessories.
c) Labour
Mate/Supervisor day 0.14 195.43 27.36

Mazdoor day 3.50 187.43 656.01

Add 0.5 per cent of (a+b+c) for providing steel #VALUE!


helmet and cushion block on top of pile head during
driving, stacking of piles at site, providing anti-corrosive
treatment and other imponderables during installation.

d) Overhead charges @ 0.25 on (a+b+c) #VALUE!

e) Contractor's profit @ 0.1 on (a+b+c+d) #VALUE!

Cost for 60 m = a+b+c+d+e #VALUE!

Rate per metre (a+b+c+d+e)/60 #VALUE!


say #VALUE!

12.37 1100 Pile Load Test on single Vertical Pile in accordance with
IS:2911(Part-IV)
Unit = 1 MT

250
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Taking output = 1 MT
a) Initial and routine load test tonne 1.00 300.00 300.00

b) Lateral load test tonne 1.00 5000.00 5000.00

Note Although, this item is incidental to work and is not required to 5300.00
be included in BOQ of contract, the same is required to be
added in the estimate to assess cost of work.

12.38 1100, Cement Concrete for Reinforced Concrete in Pile Cap


1500 complete as per Drawing and Technical Specification
&1700
A RCC Grade M20
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 5.12 5982.46 30630.18

Coarse sand cum 6.75 209.13 1411.63

20 mm Aggregate cum 8.10 887.53 7188.96

10 mm Aggregate cum 5.40 674.15 3640.42

b) Labour
Mate day 0.90 195.43 175.89

Mason day 1.50 220.57 330.86

Mazdoor for concreting day 20.00 187.43 3748.60

Mazdoor for breaking pile head, bending bars, cleaning day 1.00 187.43 187.43
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator (capacity 33 KVA) hour 6.00 342.36 2054.16

Formwork @ 4 per cent on cost of concrete i.e. cost of 2025.53


a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 13165.93

e) Contractor's profit @ 0.1 on (a+b+c+d) 6582.97

Cost for 15 cum = a+b+c+d+e 72412.62

Rate per metre (a+b+c+d+e)/15 4827.51


say 4828.00

12.38A (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 5.12 5982.46 30630.18

Coarse sand cum 6.75 209.13 1411.63

20 mm Aggregate cum 8.10 887.53 7188.96

10 mm Aggregate cum 5.40 674.15 3640.42

b) Labour
Mate day 0.16 195.43 31.27

Mason day 0.38 220.57 83.82

Mazdoor for concreting day 2.50 187.43 468.58

Mazdoor for breaking pile head, bending bars, cleaning day 1.00 187.43 187.43
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2457.00 1842.75

Generator 100 KVA hour 0.75 1635.00 1226.25

Loader (capacity 1 cum) hour 0.75 1148.00 861.00

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km hour 2.00 854.55 1709.10

Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 4.32 162.00

Concrete Pump hour 0.75 234.36 175.77

Formwork @ 4 per cent on cost of concrete i.e. cost of 1984.77


a) Material, b) Labour and c) Machinery

251
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) Overhead charges @ 0.25 on (a+b+c) 12900.98

e) Contractor's profit @ 0.1 on (a+b+c+d) 6450.49

Cost for 15 cum = a+b+c+d+e 70955.38

Rate per metre (a+b+c+d+e)/15 4730.36


say 4730.00

Note The value of a, b and c may be taken as applicable i.e. either


using concrete mixer or batching plant.
12.38 B RCC Grade M25
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 5.99 5982.46 35834.91

Coarse sand cum 6.75 209.13 1411.63

20 mm Aggregate cum 8.10 887.53 7188.96

10 mm Aggregate cum 5.40 674.15 3640.42

b) Labour
Mate day 0.90 195.43 175.89

Mason day 1.50 220.57 330.86

Mazdoor for concreting day 20.00 187.43 3748.60

Mazdoor for breaking pile head, bending bars, cleaning day 1.00 187.43 187.43
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator (capacity 33 KVA) hour 6.00 342.36 2054.16

Formwork @ 4 per cent on cost of concrete i.e. cost of 2233.72


a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 14519.16

e) Contractor's profit @ 0.1 on (a+b+c+d) 7259.58

Cost for 15 cum = a+b+c+d+e 79855.40

Rate per metre (a+b+c+d+e)/15 5323.69


say 5324.00

12.38B (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 5.99 5982.46 35834.91

Coarse sand cum 6.75 209.13 1411.63

20 mm Aggregate cum 8.10 887.53 7188.96

10 mm Aggregate cum 5.40 674.15 3640.42

b) Labour
Mate day 0.16 195.43 31.27

Mason day 0.38 220.57 83.82

Mazdoor for concreting day 2.50 187.43 468.58

Mazdoor for breaking pile head, bending bars, cleaning day 1.00 187.43 187.43
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2457.00 1842.75

Generator 125 KVA hour 0.75 2211.00 1658.25

Loader (capacity 1 cum) hour 0.75 1148.00 861.00

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km hour 2.00 854.55 1709.10

Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 4.32 162.00

Concrete Pump hour 0.75 234.36 175.77

Formwork @ 4 per cent on cost of concrete i.e. cost of 2210.24


a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 14366.53

e) Contractor's profit @ 0.1 on (a+b+c+d) 7183.26

252
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 15 cum = a+b+c+d+e 79015.91

Rate per metre (a+b+c+d+e)/15 5267.73


say 5268.00

Note The value of a, b and c may be taken as applicable i.e. either


using concrete mixer or batching plant.
12.38 C RCC Grade M30
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 6.10 5982.46 36492.98

Coarse sand cum 6.75 209.13 1411.63

20 mm Aggregate cum 8.10 887.53 7188.96

10 mm Aggregate cum 5.40 674.15 3640.42

b) Labour
Mate day 0.90 195.43 175.89

Mason day 1.50 220.57 330.86

Mazdoor for concreting day 20.00 187.43 3748.60

Mazdoor for breaking pile head, bending bars, cleaning day 1.00 187.43 187.43
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator (capacity 33 KVA) hour 6.00 342.36 2054.16

Formwork @ 4 per cent on cost of concrete i.e. cost of 2260.04


a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 14690.26

e) Contractor's profit @ 0.1 on (a+b+c+d) 7345.13

Cost for 15 cum = a+b+c+d+e 80796.44

Rate per metre (a+b+c+d+e)/15 5386.43


say 5386.00

'12.38C (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 6.10 5982.46 36492.98

Coarse sand cum 6.75 209.13 1411.63

20 mm Aggregate cum 8.10 887.53 7188.96

10 mm Aggregate cum 5.40 674.15 3640.42

b) Labour
Mate day 0.16 195.43 31.27

Mason day 0.38 220.57 83.82

Mazdoor for concreting day 2.50 187.43 468.58

Mazdoor for breaking pile head, bending bars, cleaning day 1.00 187.43 187.43
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2457.00 1842.75

Generator 100 KVA hour 0.75 1635.00 1226.25

Loader (capacity 1 cum) hour 0.75 1148.00 861.00

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km hour 2.00 854.55 1709.10

Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 4.32 162.00

Concrete Pump hour 0.75 234.36 175.77

Formwork @ 4 per cent on cost of concrete i.e. cost of 2219.28


a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 14425.31

e) Contractor's profit @ 0.1 on (a+b+c+d) 7212.65

Cost for 15 cum = a+b+c+d+e 79339.19

Rate per metre (a+b+c+d+e)/15 5289.28

253
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 5289.00

Note The value of a, b and c may be taken as applicable i.e. either


using concrete mixer or batching plant.
12.38 D RCC Grade M35
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 6.33 5982.46 37868.95

Coarse sand cum 6.75 209.13 1411.63

20 mm Aggregate cum 8.10 887.53 7188.96

10 mm Aggregate cum 5.40 674.15 3640.42

b) Labour
Mate day 0.90 195.43 175.89

Mason day 1.50 220.57 330.86

Mazdoor day 20.00 187.43 3748.60

Mazdoor for breaking pile head, bending bars, cleaning day 1.00 187.43 187.43
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator (capacity 33 KVA) hour 6.00 342.36 2054.16

Formwork @ 4 per cent on cost of concrete i.e. cost of 2315.08


a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 15048.01

e) Contractor's profit @ 0.1 on (a+b+c+d) 7524.01

Cost for 15 cum = a+b+c+d+e 82764.07

Rate per metre (a+b+c+d+e)/15 5517.60


say 5518.00

'12.38D (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 6.33 5982.46 37868.95

Coarse sand cum 6.75 209.13 1411.63

20 mm Aggregate cum 8.10 887.53 7188.96

10 mm Aggregate cum 5.40 674.15 3640.42

b) Labour
Mate day 0.16 195.43 31.27

Mason day 0.38 220.57 83.82

Mazdoor for concreting day 2.50 187.43 468.58

Mazdoor for breaking pile head, bending bars, cleaning day 1.00 187.43 187.43
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2457.00 1842.75

Generator 125 KVA hour 0.75 2211.00 1658.25

Loader (capacity 1 cum) hour 0.75 1148.00 861.00

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km hour 2.00 854.55 1709.10

Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 4.32 162.00

Concrete Pump hour 0.75 234.36 175.77

Formwork @ 4 per cent on cost of concrete i.e. cost of 2291.60


a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 14895.38

e) Contractor's profit @ 0.1 on (a+b+c+d) 7447.69

Cost for 15 cum = a+b+c+d+e 81924.58

Rate per metre (a+b+c+d+e)/15 5461.64


say 5462.00

254
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.39 1100&1 Levelling Course for Pile cap
700
Providing and laying of PCC M15 levelling course
100mm thick below the pile cap.
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 5982.46 24707.54

Coarse sand cum 6.75 209.13 1411.63

40 mm aggregate cum 8.10 780.12 6318.96

20 mm Aggregate cum 4.05 887.53 3594.48

10 mm Aggregate cum 1.35 674.15 910.10

b) Labour
Mate day 0.86 195.43 168.07

Mason day 1.50 220.57 330.86

Mazdoor day 20.00 187.43 3748.60

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08

Generator 33 KVA hour 6.00 342.36 2054.16

d) Overhead charges @ 0.25 on (a+b+c) 11128.62

e) Contractor's profit @ 0.1 on (a+b+c+d) 5564.31

Cost for 15 cum = a+b+c+d+e 61207.42

Rate per metre (a+b+c+d+e)/15 4080.49


say 4080.00

12.40 1600 Supplying, Fitting and Placing un-coated HYSD bar


Reinforcement in Foundation complete as per Drawing
and Technical Specifications.
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including5 per cent overlaps and wastage tonne 1.05 44187.50 46396.88

Binding wire Kg 6.00 62.52 375.14

b) Labour for cutting, bending, shifting to site, tying


and placing in position
Mate day 0.40 195.43 78.17

Blacksmith day 2.00 247.19 494.38

Mazdoor day 6.00 187.43 1124.58

c) Overhead charges @ 0.25 on (a+b) 12117.29

d) Contractor's profit @ 0.1 on (a+b+c) 6058.64

Rate per MT (a+b+c+d) 66645.08


say 66645.00

12.41 1600 Supplying, fitting and placing un-coated Mild steel


reinforcement complete in foundation as per drawing
and technical specification
Unit = 1 MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps and wastage tonne 1.05 49279.84 51743.84

Binding wire Kg 6.00 62.52 375.14

b) Labour for straightening, cutting, bending, shifting


to site, tying and placing in position
Mate day 0.43 195.43 84.03

Blacksmith day 2.25 247.19 556.18

Mazdoor day 6.50 187.43 1218.30

c) Overhead charges @ 0.25 on (a+b) 13494.37

d) Contractor's profit @ 0.1 on (a+b+c) 6747.19

Rate for per MT (a+b+c+d) 74219.04

255
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 74219.00

256
CHAPTER-12
FOUNDATIONS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.1 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with approved material.
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.14 195.43 27.36 L-12
Mazdoor day 3.50 187.43 656.01 L-13
b) Overhead charges @ 0.25 on (a) 170.84
c) Contractor's profit @ 0.1 on (a+b) 85.42
Cost for 10 cum = a+b+c 939.63
Rate per cum = (a+b+c)/10 93.96
say 94.00
Note 1. Cost of dewatering may be added where required upto, 10
percent of labour cost assessment for dewatering shall be
made as per site conditions.

2.The excavated earth can be used partially for backfilling of


foundation pit and partly for road work except for marshy soil.
Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding marshy soil.
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.
12.1 (I) A (ii) Depth 3 m to 6 m
a) Labour
Mate/Supervisor day 0.18 195.43 35.18 L-12
Mazdoor day 4.50 187.43 843.44 L-13
b) Overhead charges @ 0.25 on (a) 219.65
c) Contractor's profit @ 0.1 on (a+b) 109.83
Cost for 10 cum = a+b+c 1208.09
Rate per cum = (a+b+c)/10 120.81
say 121.00
Note Cost of dewatering may be added where required upto 15 per
cent of labour cost. Assessment for dewatering shall be done
as per actual ground conditions.
12.1 (I) A (iii) Depth above 6 m
a) Labour
Mate/Supervisor day 0.24 195.43 46.90 L-12
Mazdoor day 6.00 187.43 1124.58 L-13
b) Overhead charges @ 0.25 on (a) 292.87
c) Contractor's profit @ 0.1 on (a+b) 146.44
Cost for 10 cum = a+b+c 1610.79
Rate per cum = (a+b+c)/10 161.08
say 161.00

Note 1. Cost of dewatering may be added where required upto 20


per cent of labour cost. Assessment for dewatering shall be
made as per site conditions..
12.1 (I) B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.32 195.43 62.54 L-12
Mazdoor day 8.00 187.43 1499.44 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1516.32 9097.92 P&M-026

257
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Overhead charges @ 0.25 on (a+b) 2664.97
d) Contractor's profit @ 0.1 on (a+b+c) 1332.49
Cost for 240 cum = a+b+c+d 14657.36
Rate per cum = (a+b+c+d)/240 61.07
say 61.00
Note Cost of dewatering upto 5 per cent of (a+b) may be added,
where required. Assessment for dewatering shall be made as
per site conditions..
12.1 (I) B (ii) Depth 3 m to 6 m
Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.32 195.43 62.54 L-12
Mazdoor day 8.00 187.43 1499.44 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1516.32 9097.92 P&M-026

c) Overhead charges @ 0.25 on (a+b) 2664.97

d) Contractor's profit @ 0.1 on (a+b+c) 1332.49

Cost for 210 cum = a+b+c+d 14657.36

Rate per cum = (a+b+c+d)/210 69.80


say 70.00

Note Cost of dewatering upto 7.5 per cent of (a+b) may be


added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1 (I) B (iii) Depth above 6m
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 195.43 78.17 L-12

Mazdoor day 10.00 187.43 1874.30 L-13

b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1516.32 9097.92 P&M-026

c) Overhead charges @ 0.25 on (a+b) 2762.60

d) Contractor's profit @ 0.1 on (a+b+c) 1381.30

Cost for 180 cum = a+b+c+d 15194.29

Rate per cum = (a+b+c+d)/180 84.41


say 84.00

Note 1. Cost of dewatering upto 10 per cent of (a+b) may be


added, where required. Assessment for dewatering shall be
made as per site conditions.
2.Labour provided for excavation by mechanical means
includes that required for trimming of bottom and side slopes.
12.1 II Ordinary Rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.20 195.43 39.09 L-12

Mazdoor day 5.00 187.43 937.15 L-13

b) Overhead charges @ 0.25 on (a) 244.06

c) Contractor's profit @ 0.1 on (a+b) 122.03

Cost for 10 cum = a+b+c 1342.32

Rate per cum = (a+b+c)/10 134.23


say 134.00

Note Cost of dewatering upto 10 per cent of labour cost may be


added, where required. Assessment for dewatering shall be
made as per site conditions.
12.1(II) B Mechanical Means

258
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.24 195.43 46.90 L-12

Mazdoor day 6.00 187.43 1124.58 L-13

b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1516.32 9097.92 P&M-026

c) Overhead charges @ 0.25 on (a+b) 2567.35

d) Contractor's profit @ 0.1 on (a+b+c) 1283.68

Cost for 180 cum = a+b+c+d 14120.43

Rate per cum = (a+b+c+d)/180 78.45


say 78.00

Note 1.Cost of dewatering upto 10 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond 3 m is not dug and
hence not included.
12.1 III Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.35 195.43 68.40 L-12

Driller day 0.50 218.57 109.29 L-06

Blaster day 0.25 304.89 76.22 L-03

Mazdoor day 8.00 187.43 1499.44 L-13

b) Machinery
Air Compressor 250 cfm with 2 jack hammer for drilling. hour 1.00 293.76 293.76 P&M-001

c) Material
Blasting Material kg 3.50 112.77 394.70 M-104

Detonator electric each 14.00 14.27 199.73 M-094/100

d) Overhead charges @ 0.25 on (a+b+c) 660.38

e) Contractor's profit @ 0.1 on (a+b+c+d) 330.19

Cost for 10 cum = a+b+c+d+e 3632.11

Rate per cum = (a+b+c+d+e)/10 363.21


say 363.00

Note Cost of dewatering @ 10 percent of (a+b) may be added,


where required. Assessment for dewatering shall be made as
per site conditions.
12.1 IV Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum
A Mechanical Means
a) Labour
Mate day 0.20 195.43 39.09 L-12

Mazdoor day 5.00 187.43 937.15 L-13

b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 6.00 293.76 1762.56 P&M-001
breaker
c) Overhead charges @ 0.25 on (a+b) 684.70

d) Contractor's profit @ 0.1 on (a+b+c) 342.35

Cost for 10 cum = a+b+c+d 3765.84

Rate per cum = (a+b+c+d)/10 376.58


say 377.00

Note 1. Cost of dewatering upto10 per cent of (a+b), may be


added, where required. Assessment for dewatering shall be
made as per site conditions.

259
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
2.In case of rock, foundation beyond3 m is not dug and hence
not included.
12.1 V Marshy Soil
Unit = cum
Taking output = 10 cum
Depth upto 3 m
A Manual means
a) Labour
Mate/Supervisor day 0.40 195.43 78.17 L-12

Mazdoor day 10.00 187.43 1874.30 L-13

b) Machinery
Tractor-trolley for removal. hour 2.67 171.02 456.62 P&M-053

c) Overhead charges @ 0.25 on (a+b) 602.27

d) Contractor's profit @ 0.1 on (a+b+c) 301.14

Cost for 10 cum = a+b+c+d 3312.50

Rate per cum = ( a+b+c+d)/ 10 331.25


say 331.00

Note 1. Cost of dewatering @ 30 per cent of (a), may be added,


where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 15 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item12.1-IA (ii) to (iii) for ordinary soil

12.1 (V) B Mechanical Means


a) Labour
Mate day 0.08 195.43 15.63 L-12

Mazdoor for dressing sides, bottom and backfilling day 2.00 187.43 374.86 L-13

b) Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 cum hour 0.17 1516.32 257.77 P&M-026
per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.45 846.00 380.70 P&M-048

c) Overhead charges @ 0.25 on (a+b) 257.24

d) Contractor's profit @ 0.1 on (a+b+c) 128.62

Cost for 10 cum = a+b+c+d 1414.83

Rate per cum = (a+b+c+d)/10 141.48


say 141.00

Note 1. Cost of dewatering @ 20 percent of (a+b) may be added,


where required
2. Shoring & strutting @ 10 percent of (a+b), where required
may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item 12.1-IB (ii) to (iii) for ordinary soil
VI Back Filling in Marshy Foundation Pits
Unit : Cum
Taking Output : 6 cum
a) Labour
Mate day 0.12 195.43 23.45 L-12

Mazdoor for dressing sides, bottom and backfilling day 3.00 187.43 562.29 L-13

b) Machinery
Tractor-trolley for transportation hour 2.00 171.02 342.04 P&M-053

c) Overhead charges @ 0.25 on (a+b) 231.94

d) Contractor's profit @ 0.1 on (a+b+c) 115.97

Cost for 6 cum = a+b+c+d 1275.69

Rate per cum = (a+b+c+d)/6 212.62

260
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 213.00

12.2 304 Filling Annular Space Around Footing in Rock


Unit = cum
Taking out put = 1 cum
Lean cement concrete 1:3:6 nominal mix. Rate may be taken VALUE
as per item 12.4.
12.3 304 Sand Filling in Foundation Trenches as per Drawing &
Technical Specification
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.01 195.43 1.95 L-12

Mazdoor day 0.30 187.43 56.23 L-13

b) Material
Sand (assuming 20 per cent voids) cum 1.20 111.50 133.80 M-006

c) Overhead charges @ 0.25 on (a+b) 48.00

d) Contractor's profit @ 0.1 on (a+b+c) 24.00

Rate per cum = a+b+c+d 263.98


say 264.00

12.4 2100 PCC 1:3:6 in Foundation


Plain cement concrete 1:3:6 nominal mix in foundation with
crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration
including curing for 14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.64 195.43 125.08 L-12

Mason day 1.00 247.19 247.19 L-11

Mazdoor day 15.00 187.43 2811.45 L-13

b) Material
40 mm Aggregate cum 13.50 780.12 10531.60 M-055

coarse Sand cum 6.75 209.13 1411.63 M-005

cement tonne 3.45 5982.46 20639.47 M-081

Cost of water KL 18.00 167.07 3007.23 M-189

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079

Water tanker 6 KL capacity hour 2.00 111.24 222.48 P&M-060

d) Overhead charges @ 0.25 on (a+b+c) 10580.09

e) Contractor's profit @ 0.1 on (a+b+c+d) 5290.05

Cost for 15 cum = a+b+c+d+e 58190.50

Rate per cum = (a+b+c+d+e)/15 3879.37


say 3879.00

Note Vibrator is a part of minor T & P which is already included in


overhead charges of the contractor.
12.5 1300 Brick Masonry Work in Cement Mortar 1:3 in
Foundation complete excluding Pointing and Plastering,
as per Drawing and Technical Specifications.

Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class each 2500.00 4.72 11805.10 M-079

Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) cum 1.20 3447.00 4136.40 Item 12.6
(A)

b) Labour
Mate day 0.48 195.43 93.81 L-12

261
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mason day 4.00 247.19 988.76 L-11

Mazdoor day 8.00 187.43 1499.44 L-13

c) Overhead charges @ 0.25 on (a+b) 4630.88

d) Contractor's profit @ 0.1 on (a+b+c) 2315.44

Cost for 5 cum = a+b+c+d 25469.82

Rate per cum (a+b+c+d)/5 5093.96


say 5094.00

(i) Rate for Brick Work in C. M. 1:2 in foundation 5406.00

(ii) Rate for Brick Work in C. M. 1:3 in foundation 5094.00

(iii) Rate for Brick Work in C. M. 1:4 in foundation 4882.00

(iv) Rate for Brick Work in C. M. 1:6 in foundation 4676.00

12.6 Sub- (A) Cement Mortar 1:3 (1 cement : 3 sand)


analysis
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.51 5982.46 3051.05 M-081

Sand cum 1.05 209.13 219.59 M-005

b) Labour
Mate day 0.04 195.43 7.82 L-12

Mazdoor day 0.90 187.43 168.69 L-13

Total Material and Labour = (a+b) say 3447.00

Sub- (B) Cement Mortar1:2 (1cement :2 sand)


analysis
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.672 5982.46 4020.21 M-081

Sand cum 0.933 209.13 195.19 M-005

b) Labour
Mate day 0.04 195.43 7.82 L-12

Mazdoor day 0.90 187.43 168.69 L-13

Total Material and Labour = (a+b) say 4392.00

Sub- (C) Cement Mortar1:4 (1cement :4 sand)


analysis
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.40 5982.46 2392.98 M-081

Sand cum 1.12 209.13 234.23 M-005

b) Labour
Mate day 0.04 195.43 7.82 L-12

Mazdoor day 0.90 187.43 168.69 L-13

Total Material and Labour = (a+b) say 2804.00

Sub- (D) Cement Mortar1:6 (1cement :6 sand)


analysis
(Addl.)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.288 5982.46 1722.95 M-081

Sand cum 1.337 209.13 279.64 M-005

b) Labour
Mate day 0.04 195.43 7.82 L-12

Mazdoor day 0.90 187.43 168.69 L-13

262
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Total Material and Labour = (a+b) say 2179.00

12.7 1400 Stone Masonry Work in Cement Mortar 1:3 in


Foundation complete as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
1405.4 (A) Square Rubble Coursed Rubble Masonry (first sort)
a) Material
Stone cum 5.50 360.24 1981.32 M-169

Through and bond stone each 35.00 6.06 211.97 M-182

(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)


Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) cum 1.50 3447.00 5170.50 Item 12.6
(A)

b) Labour
Mate day 0.66 195.43 128.98 L-12

Mason day 7.50 247.19 1853.93 L-11

Mazdoor day 9.00 187.43 1686.87 L-13

c) Overhead charges @ 0.25 on (a+b) 2758.39

d) Contractor's profit @ 0.1 on (a+b+c) 1379.20

Cost for 5 cum = a+b+c+d 15171.16

Rate per cum (a+b+c+d)/5 3034.23


say 3034.00

1405.3 (B) Random Rubble Masonry


( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 359.72 1978.45 M-148

Through and bond stone each 35.00 6.06 211.97 M-182

(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)


Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis) cum 1.55 3447.00 5342.85 Item 12.6
(A)

b) Labour
Mate day 0.62 195.43 121.17 L-12

Mason day 6.00 247.19 1483.14 L-11

Mazdoor day 9.00 187.43 1686.87 L-13

c) Overhead charges @ 0.25 on (a+b) 2706.11

d) Contractor's profit @ 0.1 on (a+b+c) 1353.06

Cost for 5 cum = a+b+c+d 14883.62

Rate per cum (a+b+c+d)/5 2976.72


say 2977.00

Note The labour already considered in cement mortar has been


taken into account while proposing labour for masonry works.

12.8 1500, Plain/Reinforced Cement Concrete in Open Foundation


1700 & complete as per Drawing and Technical Specifications.
2100
A PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 5982.46 24707.54 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

40 mm Aggregate cum 8.10 780.12 6318.96 M-055

20 mm Aggregate cum 4.05 887.53 3594.48 M-053

10 mm Aggregate cum 1.35 674.15 910.10 M-051

b) Labour
Mate day 0.86 195.43 168.07 L-12

263
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mason day 1.50 247.19 370.79 L-11

Mazdoor day 20.00 187.43 3748.60 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator 63 KVA hour 6.00 361.80 2170.80 P&M-019

Per Cum Basic Cost of Labour, Material & Machinery 2979.00


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 1786.84
of material, labour and machinery

e) Overhead charges @ 0.25 on (a+b+c+d) 11614.47

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 5807.24

Cost for 15 cum = a+b+c+d+e+f 63879.61

Rate per cum = (a+b+c+d+e+f)/15 4258.64


say 4259.00

Note Needle Vibrator is an item of minor T & P which is already


included in overhead charges. Hence not added in rate
analysis of cement concrete works.
12.8 B PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement tonne 5.16 5982.46 30869.47 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

40 mm Aggregate cum 5.40 780.12 4212.64 M-055

20 mm Aggregate cum 5.40 887.53 4792.64 M-053

10 mm Aggregate cum 2.70 674.15 1820.21 M-051

b) Labour
Mate day 0.86 195.43 168.07 L-12

Mason day 1.50 247.19 370.79 L-11

Mazdoor day 20.00 187.43 3748.60 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079

Per Cum Basic Cost of Labour, Material & Machinery 3382.00


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 2028.73
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 13186.76

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 6593.38

Cost for 15 cum = a+b+c+d+e+f 72527.15

Rate per cum = (a+b+c+d+e+f)/15 4835.14


say 4835.00

12.8 C RCC Grade M20


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.21 5982.46 31168.60 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

20 mm Aggregate cum 8.10 887.53 7188.96 M-053

10 mm Aggregate cum 5.40 674.15 3640.42 M-051

b) Labour
Mate day 0.86 195.43 168.07 L-12

Mason day 1.50 247.19 370.79 L-11

Mazdoor day 20.00 187.43 3748.60 L-13

c) Machinery

264
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079

Per Cum Basic Cost of Labour, Material & Machinery 3402.00


(a+b+c)
d) Formwork @ 4 per cent on (a+b+c) 2040.85

e) Overhead charges @ 0.25 on (a+b+c+d) 13265.54

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 6632.77

Cost for 15 cum = a+b+c+d+e+f 72960.46

Rate per cum = ( a+b+c+d+e+f )/15 4864.03


say 4864.00

12.8 C Case II With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 5982.46 249229.12 M-081

Coarse Sand cum 54.00 209.13 11293.04 M-004

20 mm Aggregate cum 64.80 887.53 57511.71 M-053

10 mm Aggregate cum 43.20 674.15 29123.34 M-051

b) Labour
Mate day 0.84 195.43 164.16 L-12

Mason day 3.00 247.19 741.57 L-11

Mazdoor day 18.00 187.43 3373.74 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002

Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080

Loader 1 cum capacity hour 6.00 1148.00 6888.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25 P&M-049

Lead beyond 1 km, L-lead in km tonne.km 300L 4.32 1296.00 P&M-050


Lead= 1 km
Concrete Pump hour 6 234.36 1406.16 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 3320.00


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 15935.88
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 103583.24

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 51791.62

Cost for 120 cum = a+b+c+d+e+f 569707.85

Rate per cum = ( a+b+c+d+e+f )/120 4747.57


say 4748.00

12.8 D PCC Grade M25


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 5982.46 35834.91 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

40 mm Aggregate cum 5.40 780.12 4212.64 M-055

20 mm Aggregate cum 5.40 887.53 4792.64 M-053

10 mm Aggregate cum 2.70 674.15 1820.21 M-051

b) Labour
Mate day 0.86 195.43 168.07 L-12

Mason day 1.50 247.19 370.79 L-11

Mazdoor day 20.00 187.43 3748.60 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079

265
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Per Cum Basic Cost of Labour, Material & Machinery 3713.00
(a+b+c)
d) Formwork @ 3.75 per cent of (a+b+c) 2088.14

e) Overhead charges @ 0.25 on (a+b+c+d) 14442.97

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7221.48

Cost for 15 cum = a+b+c+d+e+f 79436.32

Rate per cum = ( a+b+c+d+e+f )/15 5295.75


say 5296.00

12.8 D Case II With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 47.95 5982.46 286858.77 M-081

Coarse sand cum 54.00 209.13 11293.04 M-004

40 mm Aggregate cum 43.20 780.12 33701.12 M-055

20 mm Aggregate cum 43.20 887.53 38341.14 M-053

10 mm Aggregate cum 21.60 674.15 14561.67 M-051

b) Labour
Mate day 0.84 195.43 164.16 L-12

Mason day 3.00 247.19 741.57 L-11

Mazdoor day 18.00 187.43 3373.74 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002

Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080

Loader 1 cum capacity hour 6.00 1148.00 6888.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25 P&M-049

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead tonne.km 300L 4.32 1296.00 P&M-050
in Kilometer Lead= 1 km

Concrete Pump hour 6 234.36 1406.16 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 3634.00


(a+b+c)
d) Formwork @ 3.75 per cent of cost of concrete i.e. 16349.84
cost of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 113086.37

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 56543.18

cost of 120 cum = a+b+c+d+e+f 621975.01

Rate per cum = (a+b+c+d+e+f)/120 5183.13


say 5183.00

12.8 E RCC Grade M25


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 5982.46 36193.86 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

20 mm Aggregate cum 8.10 887.53 7188.96 M-053

10 mm Aggregate cum 5.40 674.15 3640.42 M-051

b) Labour
Mate day 0.86 195.43 168.07 L-12

Mason day 1.50 247.19 370.79 L-11

Mazdoor day 20.00 187.43 3748.60 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079

Per Cum Basic Cost of Labour, Material & Machinery 3737.00


(a+b+c)

266
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Formwork @ 3.75 per cent of a+b+c. 2101.75

e) Overhead charges @ 0.25 on (a+b+c+d) 14537.08

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7268.54

cost of 15 cum = a+b+c+d+e+f 79953.93

Rate per cum (a+b+c+d+e+f )/15 5330.26


say 5330.00

12.8 E Case II With Batching Plant, Transit Mixer and Concrete Pump

Unit: cum
Taking Output = 120 cum
a) Material
Cement tonne 48.38 5982.46 289431.23 M-081

Coarse sand cum 54.00 209.13 11293.04 M-004

20 mm Aggregate cum 64.80 887.53 57511.71 M-053

10 mm Aggregate cum 43.20 674.15 29123.34 M-051

b) Labour
Mate day 0.84 195.43 164.16 L-12

Mason day 3.00 247.19 741.57 L-11

Mazdoor day 18.00 187.43 3373.74 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002

Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080

Loader 1 cum capacity 1 cum hour 6.00 1148.00 6888.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25 P&M-049

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead tonne.km 300L 4.32 1296.00 P&M-050
in Kilometer Lead= 1 km

Concrete Pump hour 6.00 234.36 1406.16 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 3655.00


(a+b+c)
d) Formwork @ 3.75 per cent on cost of concrete i.e. 16447.47
cost of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 113761.67

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 56880.83

cost of 120 cum = a+b+c+d+e+f 625689.17

Rate per cum (a+b+c+d+e+f )/120 5214.08


say 5214.00

12.8 F PCC Grade M30


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 5982.46 36373.33 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

40 mm Aggregate cum 5.40 780.12 4212.64 M-055

20 mm Aggregate cum 5.40 887.53 4792.64 M-053

10 mm Aggregate cum 2.70 674.15 1820.21 M-051

b) Labour
Mate day 0.86 195.43 168.07 L-12

Mason day 1.50 247.19 370.79 L-11

Mazdoor day 20.00 187.43 3748.60 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079

Per Cum Basic Cost of Labour, Material & Machinery 3749.00


(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 1967.78
cost of material, labour and machinery

267
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Overhead charges @ 0.25 on (a+b+c+d) 14547.48

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7273.74

cost of 15 cum = a+b+c+d+e+f 80011.15

Rate per cum (a+b+c+d+e+f )/15 5334.08


say 5334.00

12.8 F Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 48.60 5982.46 290747.37 M-081

Coarse sand cum 54.00 209.13 11293.04 M-004

40 mm Aggregate cum 43.20 780.12 33701.12 M-055

20 mm Aggregate cum 43.20 887.53 38341.14 M-053

10 mm Aggregate cum 21.60 674.15 14561.67 M-051

b) Labour
Mate day 0.84 195.43 164.16 L-12

Mason day 3.00 247.19 741.57 L-11

Mazdoor day 18.00 187.43 3373.74 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002

Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080

Loader 1 cum capacity hour 6.00 1148.00 6888.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25 P&M-049

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead tonne.km 300L 4.32 1296.00 P&M-050
in Kilometer Lead= 1 km

Concrete Pump hour 6.00 234.36 1406.16 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 3666.00


(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. 15395.95
cost of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 113820.04

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 56910.02

cost of 120 cum = a+b+c+d+e+f 626010.23

Rate per cum (a+b+c+d+e+f )/120 5216.75


say 5217.00

12.8 G RCC Grade M30


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 5982.46 36492.98 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

20 mm Aggregate cum 8.10 887.53 7188.96 M-053

10 mm Aggregate cum 5.40 674.15 3640.42 M-051

b) Labour
Mate day 0.86 195.43 168.07 L-12

Mason day 1.50 247.19 370.79 L-11

Mazdoor day 20.00 187.43 3748.60 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079

Per Cum Basic Cost of Labour, Material & Machinery 3757.00


(a+b+c)
d) Formwork @ 3.5 per cent on cost of concrete i.e. cost 1972.10
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 14579.45

268
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7289.72

cost of 15 cum = a+b+c+d+e+f 80186.96

Rate per cum = (a+b+c+d+e+f)/15 5345.80


say 5346.00

12.8 G Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 5982.46 291943.86 M-081

Coarse sand cum 54.00 209.13 11293.04 M-004

20 mm Aggregate cum 64.80 887.53 57511.71 M-053

10 mm Aggregate cum 43.20 674.15 29123.34 M-051

b) Labour
Mate day 0.84 195.43 164.16 L-12

Mason day 3.00 247.19 741.57 L-11

Mazdoor day 18.00 187.43 3373.74 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002

Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080

Loader 1 cum capacity hour 6.00 1148.00 6888.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25 P&M-049

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead tonne.km 300L 4.32 1296.00 P&M-050
in Kilometer Lead= 1 km

Concrete Pump hour 6.00 234.36 1406.16 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 3676.00


(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. cost 15438.91
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 114137.69

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 57068.84

cost of 120 cum = a+b+c+d+e+f 627757.28

Rate per cum (a+b+c+d+e+f )/120 5231.31


say 5231.00

12.8 H RCC Grade M35


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 5982.46 37868.95 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

20 mm Aggregate cum 8.10 887.53 7188.96 M-053

10 mm Aggregate cum 5.40 674.15 3640.42 M-051

b) Labour
Mate day 0.86 195.43 168.07 L-12

Mason day 1.50 247.19 370.79 L-11

Mazdoor day 20.00 187.43 3748.60 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079

Per Cum Basic Cost of Labour, Material & Machinery 3849.00


(a+b+c)
d) Formwork @ 3 per cent on a+b+c 1731.65

e) Overhead charges @ 0.25 on (a+b+c+d) 14863.33

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7431.66

cost of 15 cum = a+b+c+d+e+f 81748.29

Rate per cum = (a+b+c+d+e+f)/15 5449.89

269
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 5450.00

12.8 H Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 50.64 5982.46 302951.58 M-081

Coarse sand cum 54.00 209.13 11293.04 M-004

20 mm Aggregate cum 64.80 887.53 57511.71 M-053

10 mm Aggregate cum 43.20 674.15 29123.34 M-051

b) Labour
Mate day 0.84 195.43 164.16 L-12

Mason day 3.00 247.19 741.57 L-11

Mazdoor day 18.00 187.43 3373.74 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002

Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080

Loader1 cum capacity hour 6.00 1148.00 6888.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25 P&M-049

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead tonne.km 300L 4.32 1296.00 P&M-050
in Kilometer Lead= 1 km

Concrete Pump hour 6.00 234.36 1406.16 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 3768.00


(a+b+c)
d) Formwork @ 3 per cent on cost of concrete i.e. cost 13563.59
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 116420.78

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 58210.39

cost of 120 cum = a+b+c+d+e+f 640314.31

Rate per cum = (a+b+c+d+e+f)/120 5335.95


say 5336.00

Note: Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
WELL FOUNDATION
12.9 1200 Providing and Constructing Temporary Island 16 m
diameter for Construction of Well Foundation for 8m
dia. Well.
A Assuming depth of water 1.0 m and height of island to
be 1.25 m including Royality for earth @ Rs. 3768.00
for each Island.
Unit = 1 No
Taking output = 1 No.
a) Material
Earth (compacted) cum 251.20 25.1 6305.12 M-092

Sand bags each 750.00 1.73 1298.57 M-159

b) Labour
Mate day 0.40 195.43 78.17 L-12

Mazdoor for filling sand bags, stitching and placing day 15.00 187.43 2811.45 L-13

c) Machinery
Crane with grab 1 cum capacity hour 20.00 784.62 15692.40 P&M-012

Consumables @ 2.5 per cent of (c) above 392.31

d) Overhead charges @ 0.25 on (a+b+c) 6644.51

e) Contractor's profit @ 0.1 on (a+b+c+d) 3322.25

Rate per No. (a+b+c+d+e) 36544.78


say 36545.00

Note It is assumed that earth will be available within the working


space of crane with grab bucket.

270
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.9 B Assuming depth of water 4.0 m and height of island 4.5
m including Royality for earth @ Rs. 13565.00 for each
Island.
Unit = 1No
Taking output = 1 No
a) Material
Earth (compacted) cum 904.32 25.10 22698.43 M-092

Sand bags each 6000.00 1.73 10388.57 M-159

Wooden ballies 8" Dia and 9 m long each 95.00 49.23 4676.82 M-194

Wooden ballies 2" Dia for bracing metre 190.00 17.81 3383.23 M-193

b) Labour
Mate day 5.60 195.43 1094.41 L-12

Mazdoor for piling 8" dia ballies for piling 8" dia ballies day 18.00 187.43 3373.74 L-13

Mazdoor for bracing with 2" dia ballies day 12.00 187.43 2249.16 L-13

Mazdoor for filling sand bags, stitching and placing day 110.00 187.43 20617.30 L-13

c) Machinery
Crane with grab 1 cum capacity hour 50.00 784.62 39231.00 P&M-012

Consumables and other arrangements for piling ballies @ 2.5 2692.82


per cent of (a+b+c).
d) Overhead charges @ 0.25 on (a+b+c) 27601.37

e) Contractor's profit @ 0.1 on (a+b+c+d) 13800.69

Rate per No. (a+b+c+d+e) 151807.55


say 151808.00

Note For other well diameters rate can be worked out on the basis
of cross-sectional area of well. The diameter of the island
shall be in the conformity with clause 1203.2 of MoRTH
specifications.
12.9 C Providing and constructing one span service road to
reach island location from one pier location to another
pier location including Royality for earth @ Rs. 225.00
per m for service Road.
Assuming span length 30 m, width of service road 10m and
depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a) Material
Earth cum 450.00 25.10 11295.00 M-092

Sand bags each 300.00 1.73 519.43 M-159

b) Labour
Mate day 0.24 195.43 46.90 L-12

Mazdoor for filling sand bags, stitching and placing day 6.00 187.43 1124.58 L-13

c) Machinery
Front end Loader 1 cum capacity hour 27.00 1148.00 30996.00 P&M-017

Tipper 5.5 cum capacity hour 28.00 846.00 23688.00 P&M-048

d) Overhead charges @ 0.25 on (a+b+c) 16917.48

e) Contractor's profit @ 0.1 on (a+b+c+d) 8458.74

Cost for 30 m (a+b+c+d+e) 93046.13

Rate per m (a+b+c+d+e)/30 3101.54


say 3102.00

12.10 1200 & Providing and Laying Cutting Edge of Mild Steel
1900 weighing 40 kg per metre for Well Foundation complete
as per Drawing and Technical Specification.

Unit = 1 MT
Taking output = 1 MT
a) Material
Structural steel in plates, angles, etc including 5 per tonne 1.05 48095.30 50500.07 M-179
cent wastage
Nuts & bolts Kg 20.00 45.42 908.43 M-130

271
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Labour
(for cutting, bending, making holes, joining, welding and
erecting in position)
Mate day 1.32 195.43 257.97 L-12

Fitter day 5.50 251.19 1381.55 L-08

Blacksmith day 5.50 247.19 1359.55 L-02

Welder day 5.50 247.19 1359.55 L-02

Mazdoor day 16.50 187.43 3092.60 L-13

Electrodes, cutting gas and other consumables @ 10 per cent 5140.85


of cost of (a) above
c) Overhead charges @ 0.25 on (a+b) 16000.14

d) Contractor's profit @ 0.1 on (a+b+c) 8000.07

Rate per MT (a+b+c+d) 88000.76


say 88001.00

12.11 1200, Plain/Reinforced Cement Concrete, in Well Foundation


1500 & complete as per Drawing and Technical Specification.
1700
Unit = 1 cum
Taking output = 1 cum
A Well curb
(i) RCC M20 Grade
Same as for 12.8 (C) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3402.00 Item 12.8
(C)

d) formwork @ 20 per cent of the cost of concrete 680.40

e) Overhead charges @ 0.25 on (a+b+c+d) 1020.60

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 510.30

Rate perm (a+b+c+d+e+f) 5613.30


say 5613.00

12.11 A Case II With Batching Plant, Transit Mixer and Concrete Pump
(i)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3319.00 Item 12.8
(C)

d) formwork @ 20 per cent of the cost of concrete 663.80

e) Overhead charges @ 0.25 on (a+b+c+d) 995.70

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 497.85

Rate perm (a+b+c+d+e+f) 5476.35


say 5476.00

12.11 A (ii) RCC M25 Grade


Same as for 12.8 (E) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 3.75 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3737.00 Item 12.8
(E)

d) formwork @ 20 per cent of the cost of concrete 747.40

e) Overhead charges @ 0.25 on (a+b+c+d) 1121.10

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 560.55

Rate perm (a+b+c+d+e+f) 6166.05


say 6166.00

12.11 A Case II With Batching Plant, Transit Mixer and Concrete Pump
(ii)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3655.00 Item 12.8
(E)

d) formwork @ 20 per cent of the cost of concrete 731.00 DIR used


item
e) Overhead charges @ 0.25 on (a+b+c+d) 1096.50

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 548.25

Rate perm (a+b+c+d+e+f) 6030.75

272
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 6031.00

12.11 A (iii) RCC M35 Grade


Same as for 12.8 (H) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 3.0 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3849.00 Item 12.8
(H) Case I

d) formwork @ 20 per cent of the cost of concrete 769.80

e) Overhead charges @ 0.25 on (a+b+c+d) 1154.70

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 577.35

Rate perm (a+b+c+d+e+f) 6350.85


say 6351.00

12.11 A Case II With Batching Plant, Transit Mixer and Concrete Pump
(iii)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3959.00 Item 12.8
(H)

d) formwork @ 20 per cent of the cost of concrete 791.80 DIR used


item
e) Overhead charges @ 0.25 on (a+b+c+d) 1187.70

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 593.85

Rate perm (a+b+c+d+e+f) 6532.35


say 6532.00

Note. If curb concrete is carried out within steel liner, cost of


formwork shall be excluded.

12.11 B Well steining


(I) PCC M15 Grade
Same as for 12.8 (A) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 2979.00 Item 12.8
(A)

d) formwork @ 10 per cent of the cost of concrete 297.90

e) Overhead charges @ 0.25 on (a+b+c+d) 819.23

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 409.61

Rate perm (a+b+c+d+e+f) 4505.74


say 4506.00

12.11 B (ii) PCC M20 Grade


Same as for 12.8 (B) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3382.00 Item 12.8
(B) PCC

d) formwork @ 10 per cent of the cost of concrete 338.20

e) Overhead charges @ 0.25 on (a+b+c+d) 930.05

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 465.03

Rate perm (a+b+c+d+e+f) 5115.28


say 5115.00

12.11 B (iii) RCC M20 Grade


Same as for 12.8 (C) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3402.00 Item 12.8
(C)

d) formwork @ 10 per cent of the cost of concrete 340.20

e) Overhead charges @ 0.25 on (a+b+c+d) 935.55

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 467.78

Rate perm (a+b+c+d+e+f) 5145.53


say 5146.00

273
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(iii)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3319.00 Item 12.8
(C)

d) formwork @ 10 per cent of the cost of concrete 331.90

e) Overhead charges @ 0.25 on (a+b+c+d) 912.73

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 456.36

Rate perm (a+b+c+d+e+f) 5019.99


say 5020.00

12.11 B (iv) PCC M25 Grade


Same as for 12.8 (D) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3713.00 Item 12.8
(D)

d) formwork @ 10 per cent of the cost of concrete 371.30

e) Overhead charges @ 0.25 on (a+b+c+d) 1021.08

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 510.54

Rate perm (a+b+c+d+e+f) 5615.91


say 5616.00

12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(iv)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3632.00 Item 12.8
(D)

d) formwork @ 10 per cent of the cost of concrete 363.20

e) Overhead charges @ 0.25 on (a+b+c+d) 998.80

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 499.40

Rate perm (a+b+c+d+e+f) 5493.40


say 5493.00

'12.11 B (v) RCC M25 Grade


Same as for 12.8 (E) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3737.00 Item 12.8
(E)

d) formwork @ 10 per cent of the cost of concrete 373.70

e) Overhead charges @ 0.25 on (a+b+c+d) 1027.68

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 513.84

Rate perm (a+b+c+d+e+f) 5652.21


say 5652.00

12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(v)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3655.00 Item 12.8
(E)

d) formwork @ 10 per cent of the cost of concrete 365.50 DIR used


item
e) Overhead charges @ 0.25 on (a+b+c+d) 1005.13

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 502.56

Rate perm (a+b+c+d+e+f) 5528.19


say 5528.00

'12.11 B (vi) PCC M30 Grade


Same as for 12.8 (F) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3749.00 Item 12.8
(F)

d) formwork @ 10 per cent of the cost of concrete 374.90

e) Overhead charges @ 0.25 on (a+b+c+d) 1030.98

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 515.49

Rate perm (a+b+c+d+e+f) 5670.36

274
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 5670.00

12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(vi)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3665.00 Item 12.8
(F)

d) formwork @ 10 per cent of the cost of concrete 366.50

e) Overhead charges @ 0.25 on (a+b+c+d) 1007.88

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 503.94

Rate perm (a+b+c+d+e+f) 5543.31


say 5543.00

'12.11 B (vii) RCC M30 Grade


Same as for 12.8 (G) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3757.00 Item 12.8
(G)

d) formwork @ 10 per cent of the cost of concrete 375.70

e) Overhead charges @ 0.25 on (a+b+c+d) 1033.18

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 516.59

Rate perm (a+b+c+d+e+f) 5682.46


say 5682.00

12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(vii)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3676.00 Item 12.8
(G)

d) formwork @ 10 per cent of the cost of concrete 367.60

e) Overhead charges @ 0.25 on (a+b+c+d) 1010.90

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 505.45

Rate perm (a+b+c+d+e+f) 5559.95


say 5560.00

'12.11 B (viii) RCC M35 Grade


Same as for 12.8 (H) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3849.00 Item 12.8
(H) Case I

d) formwork @ 10 per cent of the cost of concrete 384.90

e) Overhead charges @ 0.25 on (a+b+c+d) 1058.48

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 529.24

Rate perm (a+b+c+d+e+f) 5821.61


say 5822.00

12.11 B Case II With Batching Plant, Transit Mixer and Concrete Pump
(viii)
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3959.00 Item 12.8
(H)

d) formwork @ 10 per cent of the cost of concrete 395.90 DIR used


item
e) Overhead charges @ 0.25 on (a+b+c+d) 1088.73

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 544.36

Rate perm (a+b+c+d+e+f) 5987.99


say 5988.00

'12.11 B (ix) RCC M40 Grade


Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 5982.46 308694.74 M-081

Coarse Sand cum 54.00 209.13 11293.04 M-004

20 mm Aggregate cum 64.80 887.53 57511.71 M-053

275
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
10 mm Aggregate cum 43.20 674.15 29123.34 M-051

Admixture kg 206.00 112.77 23230.84 M-180

b) Labour
Mate day 0.84 195.43 164.16 L-12

Mason day 3.00 247.19 741.57 L-11

Mazdoor day 18.00 187.43 3373.74 L-13

c) Machinery
Batching Plant hour 6.00 2457.00 14742.00 P&M-002

Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080

Loader 1 cum capacity hour 6.00 1148.00 6888.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25 P&M-049

Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 300xL 4.32 1296.00 Lead= 1 ,
P&M-050
Concrete Pump hour 6.00 234.36 1406.16 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 4010.00


(a+b+c)
d) Formwork @ 10 per cent on cost of concrete i.e. cost 48109.35
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d) 132300.73

f) Contractor's profit @ 0.1 on (a+b+c+d+e) 66150.36

cost of 120 cum = a+b+c+d+e+f 727653.99

Rate per cum = (a+b+c+d+e+f)/120 6063.78


say 6064.00

12.11 C C Bottom Plug


Concrete to be placed using tremie pipe
Note: 10% extra cement to be added where under water
concreting is involved
(i) PCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.55 5982.46 33202.63 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

40 mm Aggregate cum 5.40 780.12 4212.64 M-055

20 mm Aggregate cum 5.40 887.53 4792.64 M-053

10 mm Aggregate cum 2.70 674.15 1820.21 M-051

Admixture Kg 18.60 112.77 2097.54 M-180

b) Labour
Mate day 0.90 195.43 175.89 L-12

Mason day 1.50 247.19 370.79 L-11

Mazdoor day 20.00 187.43 3748.60 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079

Light Crane 3 tonnes capacity for handling tremie pipe hour 6.00 525.00 3150.00 P&M-013

Per Cum Basic Cost of Labour, Material & Machinery 3888.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 2591.63
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 15224.61

e) Contractor's profit @ 0.1 on (a+b+c+d) 7612.30

cost of 15 cum = a+b+c+d+e 83735.35

Rate per cum = (a+b+c+d+e)/15 5582.36


say 5582.00

12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete


(i) pump

276
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 44.40 5982.46 265621.05 M-081

Coarse sand cum 54.00 209.13 11293.04 M-004

20 mm Aggregate cum 64.80 887.53 57511.71 M-053

10 mm Aggregate cum 43.20 674.15 29123.34 M-051

Admixture Kg 148.80 112.77 16780.33 M-180

b) Labour
Mate day 0.88 195.43 171.98 L-12

Mason day 3.00 247.19 741.57 L-11

Mazdoor day 18.00 187.43 3373.74 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002

Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080

Loader 1 cum capacity hour 6.00 1148.00 6888.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25 P&M-049

Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 300L 4.32 1296.00 P&M-050
lead in Kilometer Lead= 1 km

Concrete Pump hour 6.00 234.36 1406.16 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 3597.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 19230.84
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 112702.00

e) Contractor's profit @ 0.1 on (a+b+c+d) 56351.00

cost of 120 cum = a+b+c+d+e 619861.02

Rate per cum = (a+b+c+d+e)/120 5165.51


say 5166.00

'12.11 C (ii) PCC Grade M25


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 5982.46 35834.91 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

40 mm Aggregate cum 5.40 780.12 4212.64 M-055

20 mm Aggregate cum 5.40 887.53 4792.64 M-053

10 mm Aggregate cum 2.70 674.15 1820.21 M-051

Admixture Kg 21.60 112.77 2435.85 M-180

b) Labour
Mate day 0.90 195.43 175.89 L-12

Mason day 1.50 247.19 370.79 L-11

Mazdoor day 20.00 187.43 3748.60 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079

Light Crane of 3 tonnes capacity for handling tremie pipe hour 6.00 525.00 3150.00 P&M-013

Per Cum Basic Cost of Labour, Material & Machinery 4086.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 2740.16
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 16004.39

e) Contractor's profit @ 0.1 on (a+b+c+d) 8002.19

277
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
cost of 15 cum = a+b+c+d+e 88024.14

Rate per cum = (a+b+c+d+e)/15 5868.28


say 5868.00

12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete


(ii) pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.88 5982.46 286440.00 M-081

Coarse sand cum 54.00 209.13 11293.04 M-004

20 mm Aggregate cum 64.80 887.53 57511.71 M-053

10 mm Aggregate cum 43.20 674.15 29123.34 M-051

Admixture Kg 172.80 112.77 19486.84 M-180

b) Labour
Mate day 0.88 195.43 171.98 L-12

Mason day 3.00 247.19 741.57 L-11

Mazdoor day 18.00 187.43 3373.74 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002

Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080

Loader 1 cum capacity hour 6.00 1148.00 6888.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25 P&M-049

Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 300L 4.32 1296.00 P&M-050
lead in Kilometer Lead= 1 km

Concrete Pump hour 6.00 234.36 1406.16 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 3793.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 20407.11
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 118877.43

e) Contractor's profit @ 0.1 on (a+b+c+d) 59438.72

cost of 120 cum = a+b+c+d+e 653825.89

Rate per cum = (a+b+c+d+e)/120 5448.55


say 5449.00

'12.11 C (iii) PCC Grade M30


Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 5982.46 36373.33 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

40 mm Aggregate cum 5.40 780.12 4212.64 M-055

20 mm Aggregate cum 5.40 887.53 4792.64 M-053

10 mm Aggregate cum 2.70 674.15 1820.21 M-051

Admixture Kg 21.60 112.77 2435.85 M-180

b) Labour
Mate day 0.90 195.43 175.89 L-12

Mason day 1.50 247.19 370.79 L-11

Mazdoor day 20.00 187.43 3748.60 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079

Light Crane of 3 tonnes capacity for handling tremie pipe hour 6.00 525.00 3150.00 P&M-013

Per Cum Basic Cost of Labour, Material & Machinery 4122.00


(a+b+c)

278
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Add 5 per cent of cost of material and labour towards cost of 2767.08
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 16145.73

e) Contractor's profit @ 0.1 on (a+b+c+d) 8072.86

cost of 15 cum = a+b+c+d+e 88801.49

Rate per cum = (a+b+c+d+e)/15 5920.10


say 5920.00

12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete


(iii) pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.64 5982.46 290986.67 M-081

Coarse sand cum 54.00 209.13 11293.04 M-004

20 mm Aggregate cum 64.80 887.53 57511.71 M-053

10 mm Aggregate cum 43.20 674.15 29123.34 M-051

Admixture Kg 172.80 112.77 19486.84 M-180

b) Labour
Mate day 0.88 195.43 171.98 L-12

Mason day 3.00 247.19 741.57 L-11

Mazdoor day 18.00 187.43 3373.74 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002

Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080

Loader 1 cum capacity hour 6.00 1148.00 6888.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25 P&M-049

Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 300L 4.32 1296.00 P&M-050
lead in Kilometer Lead= 1 km

Concrete Pump hour 6.00 234.36 1406.16 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 3831.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 20634.44
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 120070.93

e) Contractor's profit @ 0.1 on (a+b+c+d) 60035.47

cost of 120 cum = a+b+c+d+e 660390.14

Rate per cum = (a+b+c+d+e)/120 5503.25


say 5503.00

'12.11 C (iv) PCC Grade M35


Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.29 5982.46 37629.65 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

40 mm Aggregate cum 5.40 780.12 4212.64 M-055

20 mm Aggregate cum 5.40 887.53 4792.64 M-053

10 mm Aggregate cum 2.70 674.15 1820.21 M-051

Admixture Kg 21.60 112.77 2435.85 M-180

b) Labour
Mate day 0.90 195.43 175.89 L-12

Mason day 1.50 247.19 370.79 L-11

Mazdoor day 20.00 187.43 3748.60 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

279
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079

Light Crane of 3 tonnes capacity for handling tremie pipe hour 6.00 525.00 3150.00 P&M-013

Per Cum Basic Cost of Labour, Material & Machinery 4205.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 2829.89
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 16475.51

e) Contractor's profit @ 0.1 on (a+b+c+d) 8237.75

cost of 15 cum = a+b+c+d+e 90615.29

Rate per cum = (a+b+c+d+e)/15 6041.02


say 6041.00

12.11 C Case II Using Batching Plant, Transit Mixer and Crane/concrete


(iv) pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.28 5982.46 300797.89 M-081

Coarse sand cum 54.00 209.13 11293.04 M-004

20 mm Aggregate cum 64.80 887.53 57511.71 M-053

10 mm Aggregate cum 43.20 674.15 29123.34 M-051

Admixture Kg 172.80 112.77 19486.84 M-180

b) Labour
Mate day 0.88 195.43 171.98 L-12

Mason day 3.00 247.19 741.57 L-11

Mazdoor day 18.00 187.43 3373.74 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002

Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080

Loader 1 cum capacity hour 6.00 1148.00 6888.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25 P&M-049

Transit Mixer 4 cum capacity, lead beyond 1 Km, L - tonne.km 300L 4.32 1296.00 P&M-050
lead in Kilometer Lead= 1 km

Concrete Pump hour 6.00 234.36 1406.16 P&M-007

Per Cum Basic Cost of Labour, Material & Machinery 3913.00


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of 21125.01
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d) Overhead charges @ 0.25 on (a+b+c) 122646.38

e) Contractor's profit @ 0.1 on (a+b+c+d) 61323.19

cost of 120 cum = a+b+c+d+e 674555.10

Rate per cum = (a+b+c+d+e)/120 5621.29


say 5621.00

12.11 D Intermediate plug


(i) Grade M20 PCC
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3888.00

d) Overhead charges @ 0.25 on (a+b+c) 972.00

e) Contractor's profit @ 0.1 on (a+b+c+d) 486.00

Rate per cum = (a+b+c+d+e) 5346.00


say 5346.00

12.11 D Case II Using Batching Plant, Transit Mixer and Crane/concrete


(i) pump

280
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3597.00

d) Overhead charges @ 0.25 on (a+b+c) 899.25

e) Contractor's profit @ 0.1 on (a+b+c+d) 449.63

Rate per cum = (a+b+c+d+e) 4945.88


say 4946.00

'12.11 D (ii) Grade M25 PCC


Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 4086.00

d) Overhead charges @ 0.25 on (a+b+c) 1021.50

e) Contractor's profit @ 0.1 on (a+b+c+d) 510.75

Rate per cum = (a+b+c+d+e) 5618.25


say 5618.00

12.11 D Case II Using Batching Plant, Transit Mixer and Crane/concrete


(ii) pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3793.00

d) Overhead charges @ 0.25 on (a+b+c) 948.25

e) Contractor's profit @ 0.1 on (a+b+c+d) 474.13

Rate per cum = (a+b+c+d+e) 5215.38


say 5215.00

'12.11 D (iii) Grade M30 PCC


Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 4122.00

d) Overhead charges @ 0.25 on (a+b+c) 1030.50

e) Contractor's profit @ 0.1 on (a+b+c+d) 515.25

Rate per cum = (a+b+c+d+e) 5667.75


say 5668.00

12.11 D Case II Using Batching Plant, Transit Mixer and Crane/concrete


(iii) pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3831.00

d) Overhead charges @ 0.25 on (a+b+c) 957.75

e) Contractor's profit @ 0.1 on (a+b+c+d) 478.88

Rate per cum = (a+b+c+d+e) 5267.63


say 5268.00

12.11 E Top plug


(i) Grade M15 PCC
Same as Item 12.8(a) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 2979.00

d) Overhead charges @ 0.25 on (a+b+c) 744.75

e) Contractor's profit @ 0.1 on (a+b+c+d) 372.38

Rate per cum = (a+b+c+d+e) 4096.13


say 4096.00

Same as Item 12.8(b) excluding formwork


Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3382.00

d) Overhead charges @ 0.25 on (a+b+c) 845.50

e) Contractor's profit @ 0.1 on (a+b+c+d) 422.75

Rate per cum = (a+b+c+d+e) 4650.25

281
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 4650.00

Same as Item 12.8 (d) excluding formwork


Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3713.00

d) Overhead charges @ 0.25 on (a+b+c) 928.25

e) Contractor's profit @ 0.1 on (a+b+c+d) 464.13

Rate per cum = (a+b+c+d+e) 5105.38


say 5105.00

12.11 E Case II Using Batching Plant, Transit Mixer and Crane/concrete


(iii) pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3632.00

d) Overhead charges @ 0.25 on (a+b+c) 908.00

e) Contractor's profit @ 0.1 on (a+b+c+d) 454.00

Rate per cum = (a+b+c+d+e) 4994.00


say 4994.00

'12.11 E (iv) Grade M30 PCC


Same as Item 12.8(f) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3749.00

d) Overhead charges @ 0.25 on (a+b+c) 937.25

e) Contractor's profit @ 0.1 on (a+b+c+d) 468.63

Rate per cum = (a+b+c+d+e) 5154.88


say 5155.00

12.11 E Case II Using Batching Plant, Transit Mixer and Crane/concrete


(iv) pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 3665.00

d) Overhead charges @ 0.25 on (a+b+c) 916.25

e) Contractor's profit @ 0.1 on (a+b+c+d) 458.13

Rate per cum = (a+b+c+d+e) 5039.38


say 5039.00

12.11 F Well cap


(i) RCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 5982.46 30630.18 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

20 mm Aggregate cum 8.10 887.53 7188.96 M-053

10 mm Aggregate cum 5.40 674.15 3640.42 M-051

b) Labour
Mate day 0.86 195.43 168.07 L-12

Mason day 1.50 247.19 370.79 L-11

Mazdoor day 20.00 187.43 3748.60 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079

Form Work @ 4 per cent of a+b+c 2019.32

d) Overhead charges @ 0.25 on (a+b+c) 13125.55

e) Contractor's profit @ 0.1 on (a+b+c+d) 6562.77

cost of 15 cum = a+b+c+d+e 72190.52

Rate per cum = (a+b+c+d+e)/15 4812.70


say 4813.00

282
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 5982.46 244802.11 M-081

Coarse sand cum 54.00 209.13 11293.04 M-004

20 mm Aggregate cum 64.80 887.53 57511.71 M-053

10 mm Aggregate cum 43.20 674.15 29123.34 M-051

b) Labour
Mate day 0.84 195.43 164.16 L-12

Mason day 3.00 247.19 741.57 L-11

Mazdoor day 18.00 187.43 3373.74 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002

Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080

Loader (capacity 1 cum) hour 6.00 1148.00 6888.00 P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 4.32 1296.00 P&M-050
Lead= 1 km
Concrete Pump hour 6.00 234.36 1406.16 P&M-007

Formwork @ 4 per cent of (a+b+c) 15758.80

d) Overhead charges @ 0.25 on (a+b+c) 102432.22

e) Contractor's profit @ 0.1 on (a+b+c+d) 51216.11

cost of 120 cum = a+b+c+d+e 563377.21

Rate per cum = (a+b+c+d+e)/120 4694.81


say 4695.00

12.11 F (ii) RCC Grade M25


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 5982.46 36193.86 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

20 mm Aggregate cum 8.10 887.53 7188.96 M-053

10 mm Aggregate cum 5.40 674.15 3640.42 M-051

b) Labour
Mate day 0.86 195.43 168.07 L-12

Mason day 1.50 247.19 370.79 L-11

Mazdoor day 20.00 187.43 3748.60 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079

Form Work @ 3.75 per cent of a+b+c 2101.75

d) Overhead charges @ 0.25 on (a+b+c) 14537.08

e) Contractor's profit @ 0.1 on (a+b+c+d) 7268.54

cost of 15 cum = a+b+c+d+e 79953.93

Rate per cum = (a+b+c+d+e)/15 5330.26


say 5330.00

12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(ii)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.40 5982.46 289550.88 M-081

Coarse sand cum 54.00 209.13 11293.04 M-004

283
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
20 mm Aggregate cum 64.80 887.53 57511.71 M-053

10 mm Aggregate cum 43.20 674.15 29123.34 M-051

b) Labour
Mate day 0.84 195.43 164.16 L-12

Mason day 3.00 247.19 741.57 L-11

Mazdoor day 18.00 187.43 3373.74 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002

Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080

Loader (capacity 1 cum) hour 6.00 1148.00 6888.00 P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 4.32 1296.00 P&M-050
Lead= 1 km
Concrete Pump hour 6.00 234.36 1406.16 P&M-007

Formwork @ 3.75 per cent of ( a+b+c) 16451.96

d) Overhead charges @ 0.25 on (a+b+c) 113792.70

e) Contractor's profit @ 0.1 on (a+b+c+d) 56896.35

cost of 120 cum = a+b+c+d+e 625859.86

Rate per cum = (a+b+c+d+e)/120 5215.50


say 5215.00

12.11 F (iii) RCC Grade M30


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 5982.46 36492.98 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

20 mm Aggregate cum 8.10 887.53 7188.96 M-053

10 mm Aggregate cum 5.40 674.15 3640.42 M-051

b) Labour
Mate day 0.86 195.43 168.07 L-12

Mason day 1.50 247.19 370.79 L-11

Mazdoor day 20.00 187.43 3748.60 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079

Formwork @ 3.5 per cent of (a+b+c) 1972.10

d) Overhead charges @ 0.25 on (a+b+c) 14579.45

e) Contractor's profit @ 0.1 on (a+b+c+d) 7289.72

cost of 15 cum = a+b+c+d+e 80186.96

Rate per cum = (a+b+c+d+e)/15 5345.80


say 5346.00

12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(iii)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 5982.46 291884.04 M-081

Coarse sand cum 54.00 209.13 11293.04 M-004

20 mm Aggregate cum 64.80 887.53 57511.71 M-053

10 mm Aggregate cum 43.20 674.15 29123.34 M-051

b) Labour
Mate day 0.84 195.43 164.16 L-12

Mason day 3.00 247.19 741.57 L-11

Mazdoor day 18.00 187.43 3373.74 L-13

284
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002

Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080

Loader (capacity 1 cum) hour 6.00 1148.00 6888.00 P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 4.32 1296.00 P&M-050
Lead= 1 km
Concrete Pump hour 6.00 234.36 1406.16 P&M-007

Formwork @ 3.5 per cent of (a+b+c) 15436.82

d) Overhead charges @ 0.25 on (a+b+c) 114122.21

e) Contractor's profit @ 0.1 on (a+b+c+d) 57061.10

cost of 120 cum = a+b+c+d+e 627672.14

Rate per cum = (a+b+c+d+e)/120 5230.60


say 5231.00

12.11 F (iv) RCC Grade M35


Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 5982.46 37868.95 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

20 mm Aggregate cum 8.10 887.53 7188.96 M-053

10 mm Aggregate cum 5.40 674.15 3640.42 M-051

b) Labour
Mate day 0.86 195.43 168.07 L-12

Mason day 1.50 247.19 370.79 L-11

Mazdoor day 20.00 187.43 3748.60 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079

Formwork @ 3 per cent of (a+b+c) 1731.65

d) Overhead charges @ 0.25 on (a+b+c) 14863.33

e) Contractor's profit @ 0.1 on (a+b+c+d) 7431.66

cost of 15 cum = a+b+c+d+e 81748.29

Rate per cum = (a+b+c+d+e)/15 5449.89


say 5450.00

12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(iv)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 5982.46 302951.58 M-081

Coarse sand cum 54.00 209.13 11293.04 M-004

20 mm Aggregate cum 64.80 887.53 57511.71 M-053

10 mm Aggregate cum 43.20 674.15 29123.34 M-051

b) Labour
Mate day 0.84 195.43 164.16 L-12

Mason day 3.00 247.19 741.57 L-11

Mazdoor day 18.00 187.43 3373.74 L-13

c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002

Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080

Loader (capacity 1 cum) hour 6.00 1148.00 6888.00 P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25 P&M-049

285
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 4.32 1296.00 P&M-050
Lead= 1 km

Concrete Pump hour 6.00 234.36 1406.16 P&M-007

Formwork @ 3 per cent of (a+b+c) 13563.59

d) Overhead charges @ 0.25 on (a+b+c) 116420.78

e) Contractor's profit @ 0.1 on (a+b+c+d) 58210.39

cost of 120 cum = a+b+c+d+e 640314.31

Rate per cum = (a+b+c+d+e)/120 5335.95


say 5336.00

Note Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
'12.11 F (v) RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 52.20 5982.46 312284.21 M-081

Coarse Sand cum 54.00 209.13 11293.04 M-004

20 mm Aggregate cum 64.80 887.53 57511.71 M-053

10 mm Aggregate cum 43.20 674.15 29123.34 M-051

Admixture kg 206.00 112.77 23230.84 M-180

b) Labour
Mate day 0.84 195.43 164.16 L-12

Mason day 3.00 247.19 741.57 L-11

Mazdoor day 18.00 187.43 3373.74 L-13

c) Machinery
Batching Plant hour 6.00 2457.00 14742.00 P&M-002

Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080

Loader 1 cum capacity hour 6.00 1148.00 6888.00 P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 854.55 12818.25 P&M-049

Transit Mixer 4 cum capacity for lead beyond 1 km. tonne.km 300.L 4.32 1296.00 P&M-050
Lead= 1 km

Concrete Pump hour 6.00 234.36 1406.16 P&M-007

Formwork @ 3 per cent on cost of concrete i.e. cost of 14540.49


material, labour and machinery
d) Overhead charges @ 0.25 on (a+b+c) 124805.88

e) Contractor's profit @ 0.1 on (a+b+c+d) 62402.94

cost of 120 cum = a+b+c+d+e 686432.33

Rate per cum = (a+b+c+d+e)/120 5720.27


say 5720.00

12.12 Section Sinking of 6 m external diameter well (other than


1200 pneumatic method of sinking) through all types of strata
namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 6 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.50 m per hour.
a) Labour
Mate day 0.12 195.43 23.45 L-12

Sinker ( skilled ) day 1.00 218.57 218.57 L-15

286
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Sinking helper ( semi-skilled ) day 2.00 190.43 380.86 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 2.00 1176.12 2352.24 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 235.22

c) Overhead charges @ 0.25 on (a+b) 802.59

d) Contractor's profit @ 0.1 on (a+b+c) 401.29

Rate per metre = (a+b+c+d) 4414.23


say 4414.00

12.12 A (ii) Beyond 3m upto 10m depth


Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 195.43 29.31 L-12

Sinker day 1.25 218.57 273.21 L-15

Sinking helper ( semi-skilled ) day 2.50 190.43 476.08 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 1176.12 3528.36 P&M-075
0.75 cum capacity and accessories
Consumables in sinking @10 per cent of (b) 352.84

c) Overhead charges @ 0.25 on (a+b) 1164.95

d) Contractor's profit @ 0.1 on (a+b+c) 582.47

Rate per metre = (a+b+c+d) 6407.22


say 6407.00

12.12 A (iii) Beyond 10m upto 20m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 6727.00

12th m 5% 7063.00

13th m 5% 7416.00

14th m 5% 7787.00

15th m 5% 8176.00

16th m 5% 8585.00

17th m 5% 9014.00

18th m 5% 9465.00

19th m 5% 9938.00

20th m 5% 10435.00

Total Cost from 10m upto 20m 84606.00

Avg Rate per metre 8461.00

12.12 A (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 11218.00 13462.00

22nd m 7.5% 12059.00 14471.00

23rd m 7.5% 12963.00 15556.00

24th m 7.5% 13935.00 16722.00

25th m 7.5% 14980.00 17976.00

26th m 7.5% 16104.00 19325.00

27th m 7.5% 17312.00 20774.00

28th m 7.5% 18610.00 22332.00

29th m 7.5% 20006.00 24007.00

30th m 7.5% 21506.00 25807.00

Total Cost from 20m upto 30m 158693.00 190432.00

Avg Rate per metre 15869.00 19043.00

12.12 A (v) Beyond 30m upto 40 m

287
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement and Labour. 20% for
Kentledge
31st m 10% 23657.00 28388.00

32nd 10% 26023.00 31228.00

33rd m 10% 28625.00 34350.00

34th m 10% 31488.00 37786.00

35th m 10% 34637.00 41564.00

36th m 10% 38101.00 45721.00

37th m 10% 41911.00 50293.00

38th m 10% 46102.00 55322.00

39th m 10% 50712.00 60854.00

40th m 10% 55783.00 66940.00

Total Cost from 30m upto 40m 377039.00 452446.00

Avg Rate per metre 37704.00 45245.00

12.12 B Clayey Soil ( 6m dia. Well )


Unit = Running Meter.
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 195.43 29.31 L-12

Sinker ( skilled ) day 1.50 218.57 327.86 L-15

Sinking helper ( semi-skilled ) day 2.25 190.43 428.47 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 3.00 1176.12 3528.36 P&M-075
0.75 cum capacity and accessories
Consumables in sinking @ 10 per cent of (b) 352.84

c) Overhead charges @ 0.25 on (a+b) 1166.71

d) Contractor's profit @ 0.1 on (a+b+c) 583.35

Rate per metre = (a+b+c+d) 6416.90


say 6417.00

12.12 B (ii) Beyond 3m upto 10m depth


Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.30 195.43 58.63 L-12

Sinker day 3.00 218.57 655.71 L-15

Sinking helper ( semi-skilled ) day 4.50 190.43 856.94 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 2.00 513.00 1026.00 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 808.27

c) Overhead charges @ 0.25 on (a+b) 2615.57

d) Contractor's profit @ 0.1 on (a+b+c) 1307.78

Rate per metre = (a+b+c+d) 14385.62


say 14386.00

12.12 B (iii) Beyond 10 m upto 20 m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a) (b)Including for
dewatering @
5% of cost, if
required

11th m 5% 15105.00 15860.00

12th m 5% 15860.00 16653.00

288
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13th m 5% 16653.00 17486.00

14th m 5% 17486.00 18360.00

15th m 5% 18360.00 19278.00

16th m 5% 19278.00 20242.00

17th m 5% 20242.00 21254.00

18th m 5% 21254.00 22317.00

19th m 5% 22317.00 23433.00

20th m 5% 23433.00 24605.00

Total Cost from 10m upto 20m 189988.00 199488.00

Avg Rate per metre 18999.00 19949.00

12.12 B (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering of the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) (c)Including 25% (b) Including
loading arrangement and Labour ). for Kentledge 5% for
dewatering, if
required
21st m 7.5% 25190.00 31488.00 33062.00

22nd m 7.5% 27079.00 33849.00 35541.00

23rd m 7.5% 29110.00 36388.00 38207.00

24th m 7.5% 31293.00 39116.00 41072.00

25th m 7.5% 33640.00 42050.00 44153.00

26th m 7.5% 36163.00 45204.00 47464.00

27th m 7.5% 38875.00 48594.00 51024.00

28th m 7.5% 41791.00 52239.00 54851.00

29th m 7.5% 44925.00 56156.00 58964.00

30th m 7.5% 48294.00 60368.00 63386.00

Total Cost from 20m upto 30m 356360.00 445452.00 467724.00

Avg Rate per metre 35636.00 44545.00 46772.00

12.12 B (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) (b) Including (b)Including
loading arrangement and Labour). 20% for 5% for
Kentledge dewatering, if
required
31st m 10% 53123.00 63748.00 66935.00

32nd 10% 58435.00 70122.00 73628.00

33rd m 10% 64279.00 77135.00 80992.00

34th m 10% 70707.00 84848.00 89090.00

35th m 10% 77778.00 93334.00 98001.00

36th m 10% 85556.00 102667.00 107800.00

37th m 10% 94112.00 112934.00 118581.00

38th m 10% 103523.00 124228.00 130439.00

39th m 10% 113875.00 136650.00 143483.00

40th m 10% 125263.00 150316.00 157832.00

Total Cost from 30m upto 40m 846651.00 1015982.00 1066781.00

Avg Rate per metre 84665.00 101598.00 106678.00

12.12 C Soft Rock (6m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.
a) Labour
Mate day 0.92 195.43 179.80 L-12

Sinker ( skilled ) day 3.00 218.57 655.71 L-15

289
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Sinking helper ( semi-skilled ) day 20.00 190.43 3808.60 L-14

Diver day 0.50 218.57 109.29 L-07

b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1176.12 4704.48 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.50 513.00 1795.50 P&M-063

Consumables in sinking @ 10 per cent of (b) 650.00

Add for dewatering @ of 5 per cent of (a+b), if required 595.17

c) Overhead charges @ 0.25 on (a+b) 3124.63

d) Contractor's profit @ 0.1 on (a+b+c) 1562.32

Rate per metre = (a+b+c+d) 17185.49


say 17185.00

12.12 D Hard Rock (6m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 4.00 112.77 451.08 M-104

Electric Detonators each 18.00 14.27 256.79 M-094/100

b) Labour
Mate day 1.56 195.43 304.87 L-12

Driller day 2.00 218.57 437.14 L-06

Blaster day 0.25 304.89 76.22 L-03

Mazdoor day 12.00 187.43 2249.16 L-13

Mazdoor (Skilled) day 4.00 218.57 874.28 L-15

c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 513.00 1026.00 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 601.22

Consumables in sinking @ 10 per cent of cost of (b). 808.27

d) Overhead charges @ 0.25 on (a+b+c) 3535.44

e) Contractor's profit @ 0.1 on (a+b+c+d) 1767.72

Rate per metre = (a+b+c+d+e) 19444.92


say 19445.00

12.13 Section Sinking of 7 m external diameter well ( other than


1200 pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 7 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.30 m per hour.
a) Labour
Mate day 0.15 195.43 29.31 L-12

Sinker ( skilled ) day 1.25 218.57 273.21 L-15

Sinking helper ( semi-skilled ) day 2.50 190.43 476.08 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 3.25 1176.12 3822.39 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 382.24

290
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Overhead charges @ 0.25 on (a+b) 1245.81

d) Contractor's profit @ 0.1 on (a+b+c) 622.90

Rate per metre = (a+b+c+d) 6851.94


say 6852.00

12.13 A (ii) Beyond 3m upto 10m depth


Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 195.43 35.18 L-12

Sinker day 1.50 218.57 327.86 L-15

Sinking helper ( semi-skilled ) day 3.00 190.43 571.29 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1176.12 5292.54 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 529.25

c) Overhead charges @ 0.25 on (a+b) 1689.03

d) Contractor's profit @ 0.1 on (a+b+c) 844.51

Rate per metre = (a+b+c+d) 9289.66


say 9290.00

12.13 A (iii) Beyond 10m upto 20m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 9754.00

12th m 5% 10242.00

13th m 5% 10754.00

14th m 5% 11292.00

15th m 5% 11857.00

16th m 5% 12450.00

17th m 5% 13073.00

18th m 5% 13727.00

19th m 5% 14413.00

20th m 5% 15134.00

Total Cost from 10m upto 20m 122696.00

Avg Rate per metre 12270.00

12.13 A (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement and Labour). 20% for
Kentledge
21st m 7.5% 16269.00 19523.00

22nd m 7.5% 17489.00 20987.00

23rd m 7.5% 18801.00 22561.00

24th m 7.5% 20211.00 24253.00

25th m 7.5% 21727.00 26072.00

26th m 7.5% 23357.00 28028.00

27th m 7.5% 25109.00 30131.00

28th m 7.5% 26992.00 32390.00

29th m 7.5% 29016.00 34819.00

30th m 7.5% 31192.00 37430.00

Total Cost from 20m upto 30m 230163.00 276194.00

Avg Rate per metre 23016.00 27619.00

12.13 A (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 34311.00 41173.00

32nd 10% 37742.00 45290.00

291
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
33rd m 10% 41516.00 49819.00

34th m 10% 45668.00 54802.00

35th m 10% 50235.00 60282.00

36th m 10% 55259.00 66311.00

37th m 10% 60785.00 72942.00

38th m 10% 66864.00 80237.00

39th m 10% 73550.00 88260.00

40th m 10% 80905.00 97086.00

Total Cost from 30m upto 40m 546835.00 656202.00

Avg Rate per metre 54684.00 65620.00

12.13 B Clayey Soil ( 7m dia. Well )


Unit = Running Meter.
Taking output = 1 cum
(I) Depth below bed level upto 3.0 M
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 195.43 35.18 L-12

Sinker ( skilled ) day 1.50 218.57 327.86 L-15

Sinking helper ( semi-skilled ) day 3.00 190.43 571.29 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1176.12 5292.54 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 529.25

d) Overhead charges @ 0.25 on (a+b) 1689.03

e) Contractor's profit @ 0.1 on (a+b+c) 844.51

Rate per metre = (a+b+c+d) 9289.66


say 9290.00

12.13 B (ii) Beyond 3m upto 10m depth


Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.26 195.43 50.81 L-12

Sinker day 2.00 218.57 437.14 L-15

Sinking helper ( semi-skilled ) day 4.00 190.43 761.72 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.25 513.00 1667.25 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 872.40

c) Overhead charges @ 0.25 on (a+b) 2711.51

d) Contractor's profit @ 0.1 on (a+b+c) 1355.75

Rate per metre = (a+b+c+d) 14913.30


say 14913.00

12.13 B (iii) Beyond 10 m upto 20 m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a) (b) Including for
dewatering @
5% of cost, if
required

11th m 5% 15659.00 16442.00

12th m 5% 16442.00 17264.00

13th m 5% 17264.00 18127.00

14th m 5% 18127.00 19033.00

15th m 5% 19033.00 19985.00

16th m 5% 19985.00 20984.00

17th m 5% 20984.00 22033.00

18th m 5% 22033.00 23135.00

292
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
19th m 5% 23135.00 24292.00

20th m 5% 24292.00 25507.00

Total Cost from 10m upto 20m 196954.00 206802.00

Avg Rate per metre 19695.00 20680.00

12.13 B (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

c Add 25 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including
loading arrangement and Labour ). 25% for 5% for
Kentledge dewatering, if
required
31st m 7.5% 26114.00 32643.00 34275.00

32nd 7.5% 28073.00 35091.00 36846.00

33rd m 7.5% 30178.00 37723.00 39609.00

34th m 7.5% 32441.00 40551.00 42579.00

35th m 7.5% 34874.00 43593.00 45773.00

36th m 7.5% 37490.00 46863.00 49206.00

37th m 7.5% 40302.00 50378.00 52897.00

38th m 7.5% 43325.00 54156.00 56864.00

39th m 7.5% 46574.00 58218.00 61129.00

40th m 7.5% 50067.00 62584.00 65713.00

Total Cost from 30m upto 40m 369438.00 461800.00 484891.00

Avg Rate per metre 36944.00 46180.00 48489.00

12.13 B (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including
loading arrangement and Labour). 20% for 5% for
Kentledge dewatering, if
required
31st m 10% 55074.00 66089.00 69393.00

32nd 10% 60581.00 72697.00 76332.00

33rd m 10% 66639.00 79967.00 83965.00

34th m 10% 73303.00 87964.00 92362.00

35th m 10% 80633.00 96760.00 101598.00

36th m 10% 88696.00 106435.00 111757.00

37th m 10% 97566.00 117079.00 122933.00

38th m 10% 107323.00 128788.00 135227.00

39th m 10% 118055.00 141666.00 148749.00

40th m 10% 129861.00 155833.00 163625.00

Total Cost from 30m upto 40m 877731.00 1053278.00 1105941.00

Avg Rate per metre 87773.00 105328.00 110594.00

12.13 C Soft Rock ( 7m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.58 195.43 113.35 L-12

Sinker ( skilled ) day 4.00 218.57 874.28 L-15

Sinking helper ( semi-skilled ) day 10.00 190.43 1904.30 L-14

Diver day 0.75 218.57 163.93 L-07

b) Machinery
Hire & running charges of crane with grab bucket of hour 4.50 1176.12 5292.54 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 513.00 1923.75 P&M-063

Consumables in sinking @ 10 per cent of (b) 721.63

293
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Add for dewatering @ of 5 per cent of (a+b), if required 513.61

c) Overhead charges @ 0.25 on (a+b) 2876.85

d) Contractor's profit @ 0.1 on (a+b+c) 1438.42

Rate per metre = (a+b+c+d) 15822.65


say 15823.00

12.13 D Hard Rock ( 7m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 7.00 112.77 789.40 M-104

Electric Detonators each 30.00 14.27 427.98 M-094/100

b) Labour
Mate day 1.60 195.43 312.69 L-12

Driller day 2.00 218.57 437.14 L-06

Blaster day 0.25 304.89 76.22 L-03

Mazdoor day 18.00 187.43 3373.74 L-13

Mazdoor (Skilled) day 4.00 218.57 874.28 L-15

Diver day 0.50 218.57 109.29 L-07

c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 513.00 1026.00 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 663.30

Consumables in sinking @ 10 per cent of cost of (b). 874.60

d) Overhead charges @ 0.25 on (a+b+c) 4005.34

e) Contractor's profit @ 0.1 on (a+b+c+d) 2002.67

Rate per metre = (a+b+c+d+e) 22029.37


say 22029.00

12.14 Section Sinking of 8 m external diameter well ( other than


1200 pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 8 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.18 195.43 35.18 L-12

Sinker ( skilled ) day 1.50 218.57 327.86 L-15

Sinking helper ( semi-skilled ) day 3.00 190.43 571.29 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1176.12 4704.48 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 470.45

c) Overhead charges @ 0.25 on (a+b) 1527.31

d) Contractor's profit @ 0.1 on (a+b+c) 763.66

Rate per metre = (a+b+c+d) 8400.22


say 8400.00

12.14 A (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.20 m/hour

294
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Labour
Mate day 0.25 195.43 48.86 L-12

Sinker day 1.75 218.57 382.50 L-15

Sinking helper ( semi-skilled ) day 3.50 190.43 666.51 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1176.12 5880.60 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 588.06

c) Overhead charges @ 0.25 on (a+b) 1891.63

d) Contractor's profit @ 0.1 on (a+b+c) 945.82

Rate per metre = (a+b+c+d) 10403.97


say 10404.00

12.14 A (iii) Beyond 10m upto 20m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 10924.00

12th m 5% 11470.00

13th m 5% 12044.00

14th m 5% 12646.00

15th m 5% 13278.00

16th m 5% 13942.00

17th m 5% 14639.00

18th m 5% 15371.00

19th m 5% 16140.00

20th m 5% 16947.00

Total Cost from 10m upto 20m 137401.00

Avg Rate per metre 13740.00

12.14 A (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 18218.00 21862.00

22nd m 7.5% 19584.00 23501.00

23rd m 7.5% 21053.00 25264.00

24th m 7.5% 22632.00 27158.00

25th m 7.5% 24329.00 29195.00

26th m 7.5% 26154.00 31385.00

27th m 7.5% 28116.00 33739.00

28th m 7.5% 30225.00 36270.00

29th m 7.5% 32492.00 38990.00

30th m 7.5% 34929.00 41915.00

Total Cost from 20m upto 30m 257732.00 309279.00

Avg Rate per metre 25773.00 30928.00

12.14 A (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 38422.00 46106.00

32nd 10% 42264.00 50717.00

33rd m 10% 46490.00 55788.00

34th m 10% 51139.00 61367.00

35th m 10% 56253.00 67504.00

36th m 10% 61878.00 74254.00

37th m 10% 68066.00 81679.00

38th m 10% 74873.00 89848.00

295
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
39th m 10% 82360.00 98832.00

40th m 10% 90596.00 108715.00

Total Cost from 30m upto 40m 612341.00 734809.00

Avg Rate per metre 61234.00 73481.00

12.14 B Clayey Soil ( 8m dia. Well )


Unit = Running Meter.
Taking output = 1 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.22 195.43 42.99 L-12

Sinker ( skilled ) day 2.00 218.57 437.14 L-15

Sinking helper ( semi-skilled ) hour 3.50 190.43 666.51 L-14

b) Machinery
Hire & running charges of crane with grab bucket of 5.50 1176.12 6468.66 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 646.87

c) Overhead charges @ 0.25 on (a+b) 2065.54

d) Contractor's profit @ 0.1 on (a+b+c) 1032.77

Rate per metre = (a+b+c+d) 11360.48


say 11360.00

12.14 B (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.32 195.43 62.54 L-12

Sinker day 2.50 218.57 546.43 L-15

Sinking helper ( semi-skilled ) day 4.50 190.43 856.94 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.50 513.00 1795.50 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 885.22

c) Overhead charges @ 0.25 on (a+b) 2800.83

d) Contractor's profit @ 0.1 on (a+b+c) 1400.42

Rate per metre = (a+b+c+d) 15404.59


say 15405.00

12.14 B (iii) Beyond 10 m upto 20 m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a) (b) Including for
dewatering @
5% of cost, if
required
11th m 5% 16175.00 16984.00

12th m 5% 16984.00 17833.00

13th m 5% 17833.00 18725.00

14th m 5% 18725.00 19661.00

15th m 5% 19661.00 20644.00

16th m 5% 20644.00 21676.00

17th m 5% 21676.00 22760.00

18th m 5% 22760.00 23898.00

19th m 5% 23898.00 25093.00

20th m 5% 25093.00 26348.00

Total Cost from 10m upto 20m 203449.00 213622.00

Avg Rate per metre 20345.00 21362.00

12.14 B (iv) Beyond 20m upto 30 m

296
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

c Add 25 per cent of cost for Kentledge including supports, (a) (c)Including 25% (b) Including
loading arrangement and Labour ). for Kentledge 5% for
dewatering, if
required

31st m 7.5% 26975.00 33719.00 35405.00

32nd 7.5% 28998.00 36248.00 38060.00

33rd m 7.5% 31173.00 38966.00 40914.00

34th m 7.5% 33511.00 41889.00 43983.00

35th m 7.5% 36024.00 45030.00 47282.00

36th m 7.5% 38726.00 48408.00 50828.00

37th m 7.5% 41630.00 52038.00 54640.00

38th m 7.5% 44752.00 55940.00 58737.00

39th m 7.5% 48108.00 60135.00 63142.00

40th m 7.5% 51716.00 64645.00 67877.00

Total Cost from 30m upto 40m 381613.00 477018.00 500868.00

Avg Rate per metre 38161.00 47702.00 50087.00

12.14 B (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) (c ) Including (b) Including
loading arrangement and Labour). 20% for 5% for
Kentledge dewatering, if
required
31st m 10% 56888.00 68266.00 71679.00

32nd 10% 62577.00 75092.00 78847.00

33rd m 10% 68835.00 82602.00 86732.00

34th m 10% 75719.00 90863.00 95406.00

35th m 10% 83291.00 99949.00 104946.00

36th m 10% 91620.00 109944.00 115441.00

37th m 10% 100782.00 120938.00 126985.00

38th m 10% 110860.00 133032.00 139684.00

39th m 10% 121946.00 146335.00 153652.00

40th m 10% 134141.00 160969.00 169017.00

Total Cost from 30m upto 40m 906659.00 1087990.00 1142389.00

Avg Rate per metre 90666.00 108799.00 114239.00

12.14 C Soft Rock ( 8m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.68 195.43 132.89 L-12

Sinker ( skilled ) day 4.00 218.57 874.28 L-15

Sinking helper ( semi-skilled ) day 12.00 190.43 2285.16 L-14

Diver day 1.00 218.57 218.57 L-07

b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1176.12 5880.60 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 3.75 513.00 1923.75 P&M-063

Consumables in sinking @ 10 per cent of (b) 780.44

Add for dewatering @ of 5 per cent of (a+b), if required 604.78

c) Overhead charges @ 0.25 on (a+b) 3175.12

d) Contractor's profit @ 0.1 on (a+b+c) 1587.56

Rate per metre = (a+b+c+d) 17463.15

297
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 17463.00

12.14 D Hard Rock ( 8m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour
a) Material
Gelatine 80 per cent Kg 8.00 112.77 902.17 M-104

Electric Detonators each 32.00 14.27 456.52 M-094/100

b) Labour
Mate day 1.09 195.43 213.02 L-12

Driller day 2.00 218.57 437.14 L-06

Blaster day 0.25 304.89 76.22 L-03

Mazdoor day 20.00 187.43 3748.60 L-13

Mazdoor (Skilled) day 4.00 218.57 874.28 L-15

c) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.00 513.00 1026.00 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 671.60

Consumables in sinking @ 10 per cent of cost of (b). 534.93

d) Overhead charges @ 0.25 on (a+b+c) 3999.30

e) Contractor's profit @ 0.1 on (a+b+c+d) 1999.65

Rate per metre = (a+b+c+d+e) 21996.14


say 21996.00

12.15 Section Sinking of 9 m external diameter well ( other than


1200 pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 9 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.19 195.43 37.13 L-12

Sinker ( skilled ) day 1.50 218.57 327.86 L-15

Sinking helper ( semi-skilled ) day 3.25 190.43 618.90 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1176.12 4704.48 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 470.45

c) Overhead charges @ 0.25 on (a+b) 1539.70

d) Contractor's profit @ 0.1 on (a+b+c) 769.85

Rate per metre = (a+b+c+d) 8468.37


say 8468.00

12.15 A (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.27 195.43 52.77 L-12

Sinker day 1.75 218.57 382.50 L-15

Sinking helper ( semi-skilled ) day 4.00 190.43 761.72 L-14

b) Machinery

298
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Hire & running charges of crane with grab bucket of hour 5.50 1176.12 6468.66 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 646.87

c) Overhead charges @ 0.25 on (a+b) 2078.13

d) Contractor's profit @ 0.1 on (a+b+c) 1039.06

Rate per metre = (a+b+c+d) 11429.70


say 11430.00

12.15 A (iii) Beyond 10m upto 20m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 12001.00

12th m 5% 12601.00

13th m 5% 13231.00

14th m 5% 13893.00

15th m 5% 14588.00

16th m 5% 15317.00

17th m 5% 16083.00

18th m 5% 16887.00

19th m 5% 17731.00

20th m 5% 18618.00

Total Cost from 10m upto 20m 150950.00

Avg Rate per metre 15095.00

12.15 A (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 20014.35 24017.00

22nd m 7.5% 21515.00 25818.00

23rd m 7.5% 23129.00 27755.00

24th m 7.5% 24864.00 29837.00

25th m 7.5% 26729.00 32075.00

26th m 7.5% 28734.00 34481.00

27th m 7.5% 30889.00 37067.00

28th m 7.5% 33206.00 39847.00

29th m 7.5% 35696.00 42835.00

30th m 7.5% 38373.00 46048.00

Total Cost from 20m upto 30m 283149.35 339780.00

Avg Rate per metre 28315.00 33978.00

12.15 A (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 42210.30 50652.00

32nd 10% 46431.00 55717.00

33rd m 10% 51074.00 61289.00

34th m 10% 56181.00 67417.00

35th m 10% 61799.00 74159.00

36th m 10% 67979.00 81575.00

37th m 10% 74777.00 89732.00

38th m 10% 82255.00 98706.00

39th m 10% 90481.00 108577.00

40th m 10% 99529.00 119435.00

Total Cost from 30m upto 40m 672716.30 807259.00

Avg Rate per metre 67272.00 80726.00

299
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.15 B Clayey Soil ( 9m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.24 195.43 46.90 L-12

Sinker ( skilled ) day 2.25 218.57 491.78 L-15

Sinking helper ( semi-skilled ) day 3.75 190.43 714.11 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 5.75 1176.12 6762.69 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 676.27

c) Overhead charges @ 0.25 on (a+b) 2172.94

d) Contractor's profit @ 0.1 on (a+b+c) 1086.47

Rate per metre = (a+b+c+d) 11951.17


say 11951.00

12.15 B (ii) Beyond 3m upto 10m depth


Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.34 195.43 66.45 L-12

Sinker day 2.50 218.57 546.43 L-15

Sinking helper ( semi-skilled ) day 5.00 190.43 952.15 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1176.12 7644.78 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 3.75 513.00 1923.75 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 956.85

c) Overhead charges @ 0.25 on (a+b) 3022.60

d) Contractor's profit @ 0.1 on (a+b+c) 1511.30

Rate per metre = (a+b+c+d) 16624.31


say 16624.00

12.15 B (iii) Beyond 10 m upto 20 m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a) (b) Including for
dewatering @
5% of cost, if
required

11th m 5% 17455.00 18328.00

12th m 5% 18328.00 19244.00

13th m 5% 19244.00 20206.00

14th m 5% 20206.00 21216.00

15th m 5% 21216.00 22277.00

16th m 5% 22277.00 23391.00

17th m 5% 23391.00 24561.00

18th m 5% 24561.00 25789.00

19th m 5% 25789.00 27078.00

20th m 5% 27078.00 28432.00

Total Cost from 10m upto 20m 219545.00 230522.00

Avg Rate per metre 21955.00 23052.00

12.15 B (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required

300
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c Add 25 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including
loading arrangement and Labour ). 25% for 5% for
Kentledge dewatering, if
required

31st m 7.5% 29109.00 36386.00 38205.00

32nd 7.5% 31292.00 39115.00 41071.00

33rd m 7.5% 33639.00 42049.00 44151.00

34th m 7.5% 36162.00 45203.00 47463.00

35th m 7.5% 38874.00 48593.00 51023.00

36th m 7.5% 41790.00 52238.00 54850.00

37th m 7.5% 44924.00 56155.00 58963.00

38th m 7.5% 48293.00 60366.00 63384.00

39th m 7.5% 51915.00 64894.00 68139.00

40th m 7.5% 55809.00 69761.00 73249.00

Total Cost from 30m upto 40m 411807.00 514760.00 540498.00

Avg Rate per metre 41181.00 51476.00 54050.00

12.15 B (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including
loading arrangement and Labour). 20% for 5% for
Kentledge dewatering, if
required
31st m 10% 61390.00 73668.00 77351.00

32nd 10% 67529.00 81035.00 85087.00

33rd m 10% 74282.00 89138.00 93595.00

34th m 10% 81710.00 98052.00 102955.00

35th m 10% 89881.00 107857.00 113250.00

36th m 10% 98869.00 118643.00 124575.00

37th m 10% 108756.00 130507.00 137032.00

38th m 10% 119632.00 143558.00 150736.00

39th m 10% 131595.00 157914.00 165810.00

40th m 10% 144755.00 173706.00 182391.00

Total Cost from 30m upto 40m 978399.00 1174078.00 1232782.00

Avg Rate per metre 97840.00 117408.00 123278.00

12.15 C Soft Rock ( 9m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.76 195.43 148.53 L-12

Sinker ( skilled ) day 4.00 218.57 874.28 L-15

Sinking helper ( semi-skilled ) day 14.00 190.43 2666.02 L-14

Diver day 1.20 218.57 262.28 L-07

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1176.12 7644.78 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.00 513.00 2052.00 P&M-063

Consumables in sinking @ 10 per cent of (b) 969.68

Add for dewatering @ of 5 per cent of (a+b), if required 1461.76

c) Overhead charges @ 0.25 on (a+b) 4019.83

d) Contractor's profit @ 0.1 on (a+b+c) 2009.92

Rate per metre = (a+b+c+d) 22109.07


say 22109.00

12.15 D Hard Rock ( 9m dia well )


Unit = Running Meter

301
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a) Material
Gelatine 80 per cent Kg 10.00 112.77 1127.71 M-104

Electric Detonators each 40.00 14.27 570.65 M-094/100

b) Labour
Mate day 1.17 195.43 228.65 L-12

Driller day 2.00 218.57 437.14 L-06

Blaster day 0.25 304.89 76.22 L-03

Mazdoor day 22.00 187.43 4123.46 L-13

Mazdoor (Skilled) day 4.00 218.57 874.28 L-15

Diver day 1.00 218.57 218.57 L-07

c) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 1176.12 8232.84 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 2.50 513.00 1282.50 P&M-063
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required. 773.68

Consumables in sinking @ 10 per cent of cost of (b). 595.83

d) Overhead charges @ 0.25 on (a+b+c) 4635.38

e) Contractor's profit @ 0.1 on (a+b+c+d) 2317.69

Rate per metre = (a+b+c+d+e) 25494.61


say 25495.00

12.16 1200 Sinking of 10 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter
Taking output = 1 m
Diameter of well - 10 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.20 m / hour
a) Labour
Mate day 0.20 195.43 39.09 L-12

Sinker ( skilled ) day 1.50 218.57 327.86 L-15

Sinking helper ( semi-skilled ) day 3.50 190.43 666.51 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1176.12 5880.60 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 588.06

c) Overhead charges @ 0.25 on (a+b) 1875.53

d) Contractor's profit @ 0.1 on (a+b+c) 937.76

Rate per metre = (a+b+c+d) 10315.40


say 10315.00

12.16 A (ii) Beyond 3m upto 10m depth


Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.31 195.43 60.58 L-12

Sinker day 2.00 218.57 437.14 L-15

Sinking helper ( semi-skilled ) day 4.25 190.43 809.33 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 5.75 1176.12 6762.69 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 676.27

302
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Overhead charges @ 0.25 on (a+b) 2186.50

d) Contractor's profit @ 0.1 on (a+b+c) 1093.25

Rate per metre = (a+b+c+d) 12025.76


say 12026.00

12.16 A (iii) Beyond 10m upto 20m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 12627.00

12th m 5% 13258.00

13th m 5% 13921.00

14th m 5% 14617.00

15th m 5% 15348.00

16th m 5% 16115.00

17th m 5% 16921.00

18th m 5% 17767.00

19th m 5% 18655.00

20th m 5% 19588.00

Total Cost from 10m upto 20m 158817.00

Avg Rate per metre 15882.00

12.16 A (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 21057.00 25268.00

22nd m 7.5% 22636.00 27163.00

23rd m 7.5% 24334.00 29201.00

24th m 7.5% 26159.00 31391.00

25th m 7.5% 28121.00 33745.00

26th m 7.5% 30230.00 36276.00

27th m 7.5% 32497.00 38996.00

28th m 7.5% 34934.00 41921.00

29th m 7.5% 37554.00 45065.00

30th m 7.5% 40371.00 48445.00

Total Cost from 20m upto 30m 297893.00 357471.00

Avg Rate per metre 29789.00 35747.00

12.16 A (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 44408.00 53290.00

32nd 10% 48849.00 58619.00

33rd m 10% 53734.00 64481.00

34th m 10% 59107.00 70928.00

35th m 10% 65018.00 78022.00

36th m 10% 71520.00 85824.00

37th m 10% 78672.00 94406.00

38th m 10% 86539.00 103847.00

39th m 10% 95193.00 114232.00

40th m 10% 104712.00 125654.00

Total Cost from 30m upto 40m 707752.00 849303.00

Avg Rate per metre 70775.00 84930.00

12.16 B Clayey Soil (10m dia. Well )


Unit = Running Meter
Taking output = 1 cum

303
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.18m/hour.
a) Labour
Mate day 0.25 195.43 48.86 L-12

Sinker ( skilled ) day 2.50 218.57 546.43 L-15

Sinking helper ( semi-skilled ) day 5.50 190.43 1047.37 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 705.67

c) Overhead charges @ 0.25 on (a+b) 2351.26

d) Contractor's profit @ 0.1 on (a+b+c) 1175.63

Rate per metre = (a+b+c+d) 12931.93


say 12932.00

12.16 B (ii) Beyond 3m upto 10m depth


Rate of sinking 0.15m/hour.
a) Labour
Mate day 0.40 195.43 78.17 L-12

Sinker day 3.00 218.57 655.71 L-15

Sinking helper ( semi-skilled ) day 5.50 190.43 1047.37 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.00 513.00 2052.00 P&M-063
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 910.87

c) Overhead charges @ 0.25 on (a+b) 2950.21

d) Contractor's profit @ 0.1 on (a+b+c) 1475.10

Rate per metre = (a+b+c+d) 16226.15


say 16226.00

12.16 B (iii) Beyond 10 m upto 20 m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a) (b) Including for
dewatering @
5% of cost, if
required

11th m 5% 17037.00 17889.00

12th m 5% 17889.00 18783.00

13th m 5% 18783.00 19722.00

14th m 5% 19722.00 20708.00

15th m 5% 20708.00 21743.00

16th m 5% 21743.00 22830.00

17th m 5% 22830.00 23972.00

18th m 5% 23972.00 25171.00

19th m 5% 25171.00 26430.00

20th m 5% 26430.00 27752.00

Total Cost from 10m upto 20m 214285.00 225000.00

Avg Rate per metre 21429.00 22500.00

12.16 B (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including
loading arrangement and Labour ). 25% for 5% for
Kentledge dewatering, if
required
31st m 7.5% 28412.00 35515.00 37291.00

32nd 7.5% 30543.00 38179.00 40088.00

304
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
33rd m 7.5% 32834.00 41043.00 43095.00

34th m 7.5% 35297.00 44121.00 46327.00

35th m 7.5% 37944.00 47430.00 49802.00

36th m 7.5% 40790.00 50988.00 53537.00

37th m 7.5% 43849.00 54811.00 57552.00

38th m 7.5% 47138.00 58923.00 61869.00

39th m 7.5% 50673.00 63341.00 66508.00

40th m 7.5% 54473.00 68091.00 71496.00

Total Cost from 30m upto 40m 401953.00 502442.00 527565.00

Avg Rate per metre 40195.00 50244.00 52757.00

12.16 B (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) ( c) Including (b) Including
loading arrangement and Labour). 20% for 5% for
Kentledge dewatering, if
required
31st m 10% 59920.00 71904.00 75499.00

32nd 10% 65912.00 79094.00 83049.00

33rd m 10% 72503.00 87004.00 91354.20

34th m 10% 79753.00 95704.00 100489.20

35th m 10% 87728.00 105274.00 110537.70

36th m 10% 96501.00 115801.00 121591.05

37th m 10% 106151.00 127381.00 133750.05

38th m 10% 116766.00 140119.00 147124.95

39th m 10% 128443.00 154132.00 161838.60

40th m 10% 141287.00 169544.00 178021.20

Total Cost from 30m upto 40m 954964.00 1145957.00 1203254.95

Avg Rate per metre 95496.00 114596.00 120325.00

12.16 C Soft Rock (10m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a) Labour
Mate day 0.86 195.43 168.07 L-12

Sinker ( skilled ) day 4.00 218.57 874.28 L-15

Sinking helper ( semi-skilled ) day 16.00 190.43 3046.88 L-14

Diver day 1.40 218.57 306.00 L-07

b) Machinery
Hire & running charges of crane with grab bucket of hour 7.00 1176.12 8232.84 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.25 513.00 2180.25 P&M-063

Consumables in sinking @ 10 per cent of (b) 1041.31

Add for dewatering @ 5 per cent of cost, if required 572.72

c) Overhead charges @ 0.25 on (a+b) 4105.59

d) Contractor's profit @ 0.1 on (a+b+c) 2052.79

Rate per metre = (a+b+c+d) 22580.73


say 22581.00

12.16 D Hard Rock (10m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a) Material
Gelatine 80 per cent Kg 11.00 112.77 1240.48 M-104

305
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Electric Detonators each. 44.00 14.27 627.71 M-094/100

b) Labour
Mate day 1.27 195.43 248.20 L-12

Driller day 2.00 218.57 437.14 L-06

Blaster day 0.25 304.89 76.22 L-03

Mazdoor day 24.00 187.43 4498.32 L-13

Mazdoor (Skilled) day 4.00 218.57 874.28 L-15

c) Machinery
Hire & running charges of crane with grab bucket of hour 8.50 1176.12 9997.02 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 513.00 1539.00 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 576.80

Consumables in sinking @ 10 per cent of cost of (b+c). 1824.70

d) Overhead charges @ 0.25 on (a+b+c) 5484.97

e) Contractor's profit @ 0.1 on (a+b+c+d) 2742.48

Rate per metre = (a+b+c+d+e) 30167.32


say 30167.00

12.17 1200 Sinking of 11 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter
Taking output = 0.50 m
Diameter of well - 11 m.
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.21 195.43 41.04 L-12

Sinker ( skilled ) day 1.50 218.57 327.86 L-15

Sinking helper (semi-skilled) day 3.30 190.43 628.42 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 705.67

d) Overhead charges @ 0.25 on (a+b+c) 2189.93

e) Contractor's profit @ 0.1 on (a+b+c+d) 1094.96

Cost for 0.5m = a+b+c+d 12044.60

Rate per metre = (a+b+c+d)/0.50 24089.19


say 24089.00

12.17 A (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.13 m/hour
a) Labour
Mate day 0.32 195.43 62.54 L-12

Sinker day 2.00 218.57 437.14 L-15

Sinking helper (semi-skilled) day 4.50 190.43 856.94 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 4.00 1176.12 4704.48 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 470.45

c) Overhead charges @ 0.25 on (a+b+c) 1632.89

d) Contractor's profit @ 0.1 on (a+b+c+d) 816.44

Cost for 0.5m = a+b+c+d 8980.87

Rate per metre = (a+b+c+d)/0.50 17961.74

306
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 17962.00

12.17 A (iii) Beyond 10m upto 20m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 18860.00

12th m 5% 19803.00

13th m 5% 20793.00

14th m 5% 21833.00

15th m 5% 22925.00

16th m 5% 24071.00

17th m 5% 25275.00

18th m 5% 26539.00

19th m 5% 27866.00

20th m 5% 29259.00

Total Cost from 10m upto 20m 237224.00

Avg Rate per metre 23722.00

12.17 A (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 31453.00 37744.00

22nd m 7.5% 33812.00 40574.00

23rd m 7.5% 36348.00 43618.00

24th m 7.5% 39074.00 46889.00

25th m 7.5% 42005.00 50406.00

26th m 7.5% 45155.00 54186.00

27th m 7.5% 48542.00 58250.00

28th m 7.5% 52183.00 62620.00

29th m 7.5% 56097.00 67316.00

30th m 7.5% 60304.00 72365.00

Total Cost from 20m upto 30m 444973.00 533968.00

Avg Rate per metre 44497.00 53397.00

12.17 A (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b) Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 66334.00 79601.00

32nd 10% 72967.00 87560.00

33rd m 10% 80264.00 96317.00

34th m 10% 88290.00 105948.00

35th m 10% 97119.00 116543.00

36th m 10% 106831.00 128197.00

37th m 10% 117514.00 141017.00

38th m 10% 129265.00 155118.00

39th m 10% 142192.00 170630.00

40th m 10% 156411.00 187693.00

Total Cost from 30m upto 40m 1057187.00 1268624.00

Avg Rate per metre 105719.00 126862.00

12.17 B Clayey Soil (11 m dia. Well )


Unit = Running Meter
Taking output = 0.50 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.10 m/hour
a) Labour

307
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 0.26 195.43 50.81 L-12

Sinker ( skilled ) day 2.50 218.57 546.43 L-15

Sinking helper (semi-skilled) day 4.00 190.43 761.72 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 5.00 1176.12 5880.60 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 588.06

c) Overhead charges @ 0.25 on (a+b) 1956.90

d) Contractor's profit @ 0.1 on (a+b+c) 978.45

Cost for 0.5m = a+b+c+d 10762.97

Rate per metre = (a+b+c+d)/0.50 21525.95


say 21526.00

12.17 B (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.08 m/hour
a) Labour
Mate day 0.43 195.43 84.03 L-12

Sinker day 3.50 218.57 765.00 L-15

Sinking helper (semi-skilled) day 5.75 190.43 1094.97 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.25 513.00 2180.25 P&M-063
cutting hard clay
Consumables in sinking @ 10 per cent of (b) 923.70

c) Overhead charges @ 0.25 on (a+b) 3026.17

d) Contractor's profit @ 0.1 on (a+b+c) 1513.08

Cost for 0.5m = a+b+c+d 16643.92

Rate per metre = (a+b+c+d)/0.50 33287.84


say 33288.00

12.17 B (iii) Beyond 10 m upto 20 m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a) (b)Including for
dewatering @
5% of cost, if
required
11th m 5% 34952.00 36700.00

12th m 5% 36700.00 38535.00

13th m 5% 38535.00 40462.00

14th m 5% 40462.00 42485.00

15th m 5% 42485.00 44609.00

16th m 5% 44609.00 46839.00

17th m 5% 46839.00 49181.00

18th m 5% 49181.00 51640.00

19th m 5% 51640.00 54222.00

20th m 5% 54222.00 56933.00

Total Cost from 10m upto 20m 439625.00 461606.00

Avg Rate per metre 43963.00 46161.00

12.17 B (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) (c)Including 25% (b)Including
loading arrangement and Labour ). for Kentledge 5% for
dewatering, if
required

21st m 7.5% 58289.00 72861.00 76504.00

22nd 7.5% 62661.00 78326.00 82242.00

23rd m 7.5% 67361.00 84201.00 88411.00

308
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
24th m 7.5% 72413.00 90516.00 95042.00

25th m 7.5% 77844.00 97305.00 102170.00

26th m 7.5% 83682.00 104603.00 109833.00

27th m 7.5% 89958.00 112448.00 118070.00

28th m 7.5% 96705.00 120881.00 126925.00

29th m 7.5% 103958.00 129948.00 136445.00

30th m 7.5% 111755.00 139694.00 146679.00

Total Cost from 20m upto 30m 824626.00 1030783.00 1082322.00

Avg Rate per metre 82463.00 103078.00 108232.00

12.17 B (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) (c ) Including (b)Including
loading arrangement and Labour). 20% for 5% for
Kentledge dewatering, if
required
31st m 10% 122931.00 147517.00 154893.00

32nd 10% 135224.00 162269.00 170382.00

33rd m 10% 148746.00 178495.00 187420.00

34th m 10% 163621.00 196345.00 206162.00

35th m 10% 179983.00 215980.00 226779.00

36th m 10% 197981.00 237577.00 249456.00

37th m 10% 217779.00 261335.00 274402.00

38th m 10% 239557.00 287468.00 301841.00

39th m 10% 263513.00 316216.00 332027.00

40th m 10% 289864.00 347837.00 365229.00

Total Cost from 30m upto 40m 1959199 2351039 2468591

Avg Rate per metre 195920.00 235104.00 246859.00

12.17 C Soft Rock (11m dia well )


Unit = Running Meter.
Taking output = 0.50 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.06 m/hour
a) Labour
Mate day 0.95 195.43 185.66 L-12

Sinker ( skilled ) day 4.25 218.57 928.92 L-15

Sinking helper (semi-skilled) day 18.00 190.43 3427.74 L-14

Diver day 1.50 218.57 327.86 L-07

b) Machinery
Hire & running charges of crane with grab bucket of hour 8.00 1176.12 9408.96 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 4.50 513.00 2308.50 P&M-063

Consumables in sinking @ 10 per cent of (b) 1171.75

Add for dewatering @ 5 per cent of cost of (b), if 644.46


required
c) Overhead charges @ 0.25 on (a+b) 4600.96

d) Contractor's profit @ 0.1 on (a+b+c) 2300.48

Cost for 0.5m = a+b+c+d 25305.28

Rate per metre = (a+b+c+d)/0.50 50610.57


say 50611.00

12.17 D Hard Rock (11m dia well )


Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a) Material
Gelatine 80 per cent Kg 12.00 112.77 1353.25 M-104

309
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Electric Detonators each. 48.00 14.27 684.78 M-094/100

b) Labour
Mate day 1.35 195.43 263.83 L-12

Driller day 2.00 218.57 437.14 L-06

Blaster day 0.25 304.89 76.22 L-03

Mazdoor day 26.00 187.43 4873.18 L-13

Mazdoor (Skilled) day 4.00 218.57 874.28 L-15

c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1176.12 11761.20 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.50 513.00 1795.50 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required. 677.84

Consumables in sinking @ 10 per cent of cost of (b+c). 2008.14

d) Overhead charges @ 0.25 on (a+b+c) 6201.34

e) Contractor's profit @ 0.1 on (a+b+c+d) 3100.67

Cost for 0.5m = a+b+c+d 34107.36

Rate per metre = (a+b+c+d)/0.50 68214.72


say 68215.00

12.18 1200 Sinking of 12 m external diameter well ( other than


pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned
from bed level.
Unit = Running Meter
Taking output = 0.25 m
Diameter of well - 12 m.
A Sandy Soil
(i) I) Depth below bed level upto 3.0 M
Rate of sinking @ 0.05 m/hour
a) Labour
Mate day 0.22 195.43 42.99 L-12

Sinker ( skilled ) day 1.75 218.57 382.50 L-15

Sinking helper (semi-skilled) day 4.00 190.43 761.72 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.00 1176.12 7056.72 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 705.67

c) Overhead charges @ 0.25 on (a+b) 2237.40

d) Contractor's profit @ 0.1 on (a+b+c) 1118.70

Cost for 0.25m = a+b+c+d 12305.71

Rate per metre = (a+b+c+d)/0.25 49222.82


say 49223.00

12.18 A (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.038 m/hour
a) Labour
Mate day 0.37 195.43 72.31 L-12

Sinker day 2.50 218.57 546.43 L-15

Sinking helper (semi-skilled) day 4.75 190.43 904.54 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.50 1176.12 7644.78 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 764.48

c) Overhead charges @ 0.25 on (a+b) 2483.13

d) Contractor's profit @ 0.1 on (a+b+c) 1241.57

Cost for 0.25m = a+b+c+d 13657.24

310
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per metre = (a+b+c+d)/0.25 54628.94
say 54629.00

12.18 A (iii) Beyond 10m upto 20m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 57360.00

12th m 5% 60228.00

13th m 5% 63239.00

14th m 5% 66401.00

15th m 5% 69721.00

16th m 5% 73207.00

17th m 5% 76867.00

18th m 5% 80710.00

19th m 5% 84746.00

20th m 5% 88983.00

Total Cost from 10m upto 20m 721462.00

Avg Rate per metre 72146.00

12.18 A (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement and Labour. 20% for
Kentledge

21st m 7.5% 95657.00 114788.00

22nd m 7.5% 102831.00 123397.00

23rd m 7.5% 110543.00 132652.00

24th m 7.5% 118834.00 142601.00

25th m 7.5% 127747.00 153296.00

26th m 7.5% 137328.00 164794.00

27th m 7.5% 147628.00 177154.00

28th m 7.5% 158700.00 190440.00

29th m 7.5% 170603.00 204724.00

30th m 7.5% 183398.00 220078.00

Total Cost from 20m upto 30m 1353269.00 1623924.00

Avg Rate per metre 135327.00 162392.00

12.18 A (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 201738.00 242086.00

32nd 10% 221912.00 266294.00

33rd m 10% 244103.00 292924.00

34th m 10% 268513.00 322216.00

35th m 10% 295364.00 354437.00

36th m 10% 324900.00 389880.00

37th m 10% 357390.00 428868.00

38th m 10% 393129.00 471755.00

39th m 10% 432442.00 518930.00

40th m 10% 475686.00 570823.00

Total Cost from 30m upto 40m 3215177 3858213

Avg Rate per metre 321518.00 385821.00

12.18 B Clayey Soil (12 m dia. Well )


Unit = Running Meter.
Taking output = 0.25 meter.
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.04 m/hour

311
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Labour
Mate day 0.30 195.43 58.63 L-12

Sinker ( skilled ) day 3.00 218.57 655.71 L-15

Sinking helper (semi-skilled) day 4.50 190.43 856.94 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 1176.12 7350.75 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 735.08

c) Overhead charges @ 0.25 on (a+b) 2414.27

d) Contractor's profit @ 0.1 on (a+b+c) 1207.14

Cost for 0.25m = a+b+c+d 13278.51

Rate per metre = (a+b+c+d)/0.25 53114.04


say 53114.00

12.18 B (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.03 m/hour
a) Labour
Mate day 0.48 195.43 93.81 L-12

Sinker day 3.75 218.57 819.64 L-15

Sinking helper (semi-skilled) day 6.00 190.43 1142.58 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 1176.12 9797.08 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.50 513.00 2308.50 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 1210.56

c) Overhead charges @ 0.25 on (a+b) 3843.04

d) Contractor's profit @ 0.1 on (a+b+c) 1921.52

Cost for 0.25m = a+b+c+d 21136.72

Rate per metre = (a+b+c+d)/0.25 84546.89


say 84547.00

12.18 B (iii) Beyond 10 m upto 20 m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a) (b)Including for
dewatering @
5% of cost, if
required

11th m 5% 88774.00 93213.00

12th m 5% 93213.00 97874.00

13th m 5% 97874.00 102768.00

14th m 5% 102768.00 107906.00

15th m 5% 107906.00 113301.00

16th m 5% 113301.00 118966.00

17th m 5% 118966.00 124914.00

18th m 5% 124914.00 131160.00

19th m 5% 131160.00 137718.00

20th m 5% 137718.00 144604.00

Total Cost from 10m upto 20m 1116594.00 1172424.00

Avg Rate per metre 111659.00 117242.00

12.18 B (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) (c)Including 25% (b)Including
loading arrangement and Labour ). for Kentledge 5% for
dewatering, if
required
21st m 7.5% 148047.00 185059.00 194312.00

22nd 7.5% 159151.00 198939.00 208886.00

312
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
23rd m 7.5% 171087.00 213859.00 224552.00

24th m 7.5% 183919.00 229899.00 241394.00

25th m 7.5% 197713.00 247141.00 259498.00

26th m 7.5% 212541.00 265676.00 278960.00

27th m 7.5% 228482.00 285603.00 299883.00

28th m 7.5% 245618.00 307023.00 322374.00

29th m 7.5% 264039.00 330049.00 346551.00

30th m 7.5% 283842.00 354803.00 372543.00

Total Cost from 20m upto 30m 2094439 2618051 2748953

Avg Rate per metre 209444.00 261805.00 274895.00

12.18 B (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) (c ) Including (b)Including
loading arrangement and Labour). 20% for 5% for
Kentledge dewatering, if
required

31st m 10% 312226.00 374671.00 393405.00

32nd 10% 343449.00 412139.00 432746.00

33rd m 10% 377794.00 453353.00 476021.00

34th m 10% 415573.00 498688.00 523622.00

35th m 10% 457130.00 548556.00 575984.00

36th m 10% 502843.00 603412.00 633583.00

37th m 10% 553127.00 663752.00 696940.00

38th m 10% 608440.00 730128.00 766634.00

39th m 10% 669284.00 803141.00 843298.00

40th m 10% 736212.00 883454.00 927627.00

Total Cost from 30m upto 40m 4976078 5971294 6269860

Avg Rate per metre 497608.00 597129.00 626986.00

12.18 C Soft Rock (12m dia well )


Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a) Labour
Mate day 1.06 195.43 207.16 L-12

Sinker ( skilled ) day 4.50 218.57 983.57 L-15

Sinking helper (semi-skilled) day 20.00 190.43 3808.60 L-14

Diver day 1.75 218.57 382.50 L-07

b) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1176.12 11761.20 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.75 513.00 2436.75 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 1419.80

Add for dewatering @ 5 per cent, if required 780.89

c) Overhead charges @ 0.25 on (a+b) 5445.11

d) Contractor's profit @ 0.1 on (a+b+c) 2722.56

Cost for 0.25m = a+b+c+d 29948.12

Rate per metre = (a+b+c+d)/0.25 119792.48


say 119792.00

12.18 D Hard Rock (12m dia well )


Unit = Running Meter
Taking output = 0.25 m
(i) Depth in hard rock strata upto 3 m
Rate of sinking @ 0.020 m/hour

313
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Material
Gelatine80 per cent Kg 14.00 112.77 1578.79 M-104

Electric detonator each. 56.00 14.27 798.90 M-094/100

b) Labour
Mate day 1.44 195.43 281.42 L-12

Driller day 2.00 218.57 437.14 L-06

Blaster day 0.25 304.89 76.22 L-03

Mazdoor day 28.00 187.43 5248.04 L-13

Mazdoor (Skilled) day 4.50 218.57 983.57 L-15

c) Machinery
Hire & running charges of crane with grab bucket of hour 12.50 1176.12 14701.50 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 4.00 513.00 2052.00 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent, if required. 837.68

Consumables in sinking @ 10 per cent of (c). 1759.12

d) Overhead charges @ 0.25 on (a+b+c) 7188.59

e) Contractor's profit @ 0.1 on (a+b+c+d) 3594.30

Cost for 0.25m = a+b+c+d+e 39537.27

Rate per metre = (a+b+c+d+e)/0.25 158149.08


say 158149.00

12.19 1200 Sinking of Twin D Type well (other than pneumatic


method of sinking) through all types of strata namely
sandy soil, clayey soil and rock as shown against each
case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter
Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.20 195.43 39.09 L-12

Sinker ( skilled ) day 1.25 218.57 273.21 L-15

Sinking helper (semi-skilled) day 3.75 190.43 714.11 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 5.50 1176.12 6468.66 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 646.87

c) Overhead charges @ 0.25 on (a+b) 2035.48

d) Contractor's profit @ 0.1 on (a+b+c) 1017.74

Rate per metre = (a+b+c+d) 11195.16


say 11195.00

12.19 A (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.30 195.43 58.63 L-12

Sinker day 1.50 218.57 327.86 L-15

Sinking helper (semi-skilled) day 4.00 190.43 761.72 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 5.88 1176.12 6915.59 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b) 691.56

c) Overhead charges @ 0.25 on (a+b) 2188.84

314
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Contractor's profit @ 0.1 on (a+b+c) 1094.42

Rate per metre = (a+b+c+d) 12038.60


say 12039.00

12.19 A (iii) Beyond 10m upto 20m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m 5% 12641.00

12th m 5% 13273.00

13th m 5% 13937.00

14th m 5% 14634.00

15th m 5% 15366.00

16th m 5% 16134.00

17th m 5% 16941.00

18th m 5% 17788.00

19th m 5% 18677.00

20th m 5% 19611.00

Total Cost from 10m upto 20m 159002.00

Avg Rate per metre 15900.00

12.19 A (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement and Labour. 20% for
Kentledge
21st m 7.5% 21082.00 25298.00

22nd m 7.5% 22663.00 27196.00

23rd m 7.5% 24363.00 29236.00

24th m 7.5% 26190.00 31428.00

25th m 7.5% 28154.00 33785.00

26th m 7.5% 30266.00 36319.00

27th m 7.5% 32536.00 39043.00

28th m 7.5% 34976.00 41971.00

29th m 7.5% 37599.00 45119.00

30th m 7.5% 40419.00 48503.00

Total Cost from 20m upto 30m 298248.00 357898.00

Avg Rate per metre 29825.00 35790.00

12.19 A (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 20 per cent of cost for Kentledge including supports, (a) (b)Including
loading arrangement, and Labour etc. 20% for
Kentledge
31st m 10% 44461.00 53353.00

32nd 10% 48907.00 58688.00

33rd m 10% 53798.00 64558.00

34th m 10% 59178.00 71014.00

35th m 10% 65096.00 78115.00

36th m 10% 71606.00 85927.00

37th m 10% 78767.00 94520.00

38th m 10% 86644.00 103973.00

39th m 10% 95308.00 114370.00

40th m 10% 104839.00 125807.00

Total Cost from 30m upto 40m 708604.00 850325.00

Avg Rate per metre 70860.00 85033.00

12.19 B Clayey Soil (Twin D Type Well )


Unit = Running Meter
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M

315
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate of sinking @ 0.16 m/hour
a) Labour
Mate day 0.26 195.43 50.81 L-12

Sinker ( skilled ) day 2.50 218.57 546.43 L-15

Sinking helper (semi-skilled) day 4.00 190.43 761.72 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.25 1176.12 7350.75 P&M-075
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b) 735.08

c) Overhead charges @ 0.25 on (a+b) 2361.20

d) Contractor's profit @ 0.1 on (a+b+c) 1180.60

Rate per metre = (a+b+c+d) 12986.57


say 12987.00

12.19 B (ii) Beyond 3m upto 10m depth


Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.45 195.43 87.94 L-12

Sinker day 3.25 218.57 710.35 L-15

Sinking helper (semi-skilled) day 6.00 190.43 1142.58 L-14

b) Machinery
Hire & running charges of crane with grab bucket of hour 6.67 1176.12 7844.72 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for hour 4.50 513.00 2308.50 P&M-063
cutting hard clay.
Consumables in sinking @ 10 per cent of (b) 1015.32

c) Overhead charges @ 0.25 on (a+b) 3277.35

d) Contractor's profit @ 0.1 on (a+b+c) 1638.68

Rate per metre = (a+b+c+d) 18025.45


say 18025.00

12.19 B (iii) Beyond 10 m upto 20 m


a Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add for dewatering @ 5 per cent of cost, if required. (a) (b)Including for
dewatering @
5% of cost, if
required

11th m 5% 18927.00 19873.00

12th m 5% 19873.00 20867.00

13th m 5% 20867.00 21910.00

14th m 5% 21910.00 23006.00

15th m 5% 23006.00 24156.00

16th m 5% 24156.00 25364.00

17th m 5% 25364.00 26632.00

18th m 5% 26632.00 27964.00

19th m 5% 27964.00 29362.00

20th m 5% 29362.00 30830.00

Total Cost from 10m upto 20m 238061.00 249964.00

Avg Rate per metre 23806.00 24996.00

12.19 B (iv) Beyond 20m upto 30 m


a Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering on the cost, if required
c Add 25 per cent of cost for Kentledge including supports, (a) (c)Including 25% (b)Including
loading arrangement and Labour ). for Kentledge 5% for
dewatering, if
required

21st m 7.5% 31564.00 39455.00 41428.00

22nd 7.5% 33931.00 42414.00 44535.00

23rd m 7.5% 36476.00 45595.00 47875.00

316
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
24th m 7.5% 39212.00 49015.00 51466.00

25th m 7.5% 42153.00 52691.00 55326.00

26th m 7.5% 45314.00 56643.00 59475.00

27th m 7.5% 48713.00 60891.00 63936.00

28th m 7.5% 52366.00 65458.00 68731.00

29th m 7.5% 56293.00 70366.00 73884.00

30th m 7.5% 60515.00 75644.00 79426.00

Total Cost from 20m upto 30m 446537.00 558172.00 586082.00

Avg Rate per metre 44654.00 55817.00 58608.00

12.19 B (v) Beyond 30m upto 40 m


a Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b Add 5 per cent of cost for dewatering, if required
c Add 20 per cent of cost for Kentledge including supports, (a) (c ) Including (b)Including
loading arrangement and Labour). 20% for 5% for
Kentledge dewatering, if
required

31st m 10% 66567.00 79880.00 83874.00

32nd 10% 73224.00 87869.00 92262.00

33rd m 10% 80546.00 96655.00 101488.00

34th m 10% 88601.00 106321.00 111637.00

35th m 10% 97461.00 116953.00 122801.00

36th m 10% 107207.00 128648.00 135080.00

37th m 10% 117928.00 141514.00 148590.00

38th m 10% 129721.00 155665.00 163448.00

39th m 10% 142693.00 171232.00 179794.00

40th m 10% 156962.00 188354.00 197772.00

Total Cost from 30m upto 40m 1060910.00 1273091.00 1336746.00

Avg Rate per metre 106091.00 127309.00 133675.00

12.19 C Soft Rock (Twin D Type Well )


Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a) Labour
Mate day 0.86 195.43 168.07 L-12

Sinker ( skilled ) day 4.50 218.57 983.57 L-15

Sinking helper (semi-skilled) day 15.00 190.43 2856.45 L-14

Diver day 1.50 218.57 327.86 L-07

b) Machinery
Hire & running charges of crane with grab bucket of hour 8.33 1176.12 9797.08 P&M-075
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers hour 6.00 513.00 3078.00 P&M-063

Consumables in sinking @ 10 per cent of (b) 1287.51

Add for dewatering @ 5 per cent, if required 708.13

c) Overhead charges @ 0.25 on (a+b) 4801.66

d) Contractor's profit @ 0.1 on (a+b+c) 2400.83

Rate per metre = (a+b+c+d) 26409.15


say 26409.00

12.19 D Hard Rock (Twin D Type Well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a) Material
Geletine80 per cent Kg 10.00 112.77 1127.71 M-104

317
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Electric detonators each. 40.00 14.27 570.65 M-094/100

b) Labour
Mate day 1.34 195.43 261.88 L-12

Driller day 2.00 218.57 437.14 L-06

Blaster day 0.25 304.89 76.22 L-03

Mazdoor day 25.00 187.43 4685.75 L-13

Mazdoor (Skilled) day 4.25 218.57 928.92 L-15

c) Machinery
Hire & running charges of crane with grab bucket of hour 10.00 1176.12 11761.20 P&M-075
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic hour 3.00 513.00 1539.00 P&M-063
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if required. 984.51

Consumables in sinking @ 10 per cent of (b). 1428.47

d) Overhead charges @ 0.25 on (a+b+c) 5950.36

e) Contractor's profit @ 0.1 on (a+b+c+d) 2975.18

Rate per metre = (a+b+c+d+e) 32726.99


say 32727.00

12.20 1200 Pneumatic sinking of wells with equipment of approved


design, drawing and specifications worked by
competent and trained personnel and comprising of
compression and decompression chambers, reducers,
two air locks separately for men and plant & materials,
arrangement for supply of fresh air to working
chambers, check valves, exhaust valves, shafts made
from steel plates of riveted construction not less than 6
mm thick to withstand an air pressure of 0.50 MPa,
controlled blasting of hard rock where required,
staircases and 1 m wide landing plateforms with railing,
arrangement for compression and decompression,
electric lighting of 50 V maximum, proper rooms for rest
and medical examinations and compliance with safety
precautions as per IS:4138, all as per clause1207.6 of
MoRTH Specifications.

Unit - 1 cum
Taking output = 5 cum
a) Material
M35 grade RCC corbel provided for supporting of Cum 8.00 3768.00 30144.00 Item 12.8
equipment (Dimensions as per ground conditions). Rate (H)
may be adopted vide Item 12.8 (H)
HYSD bar reinforcement in corbel tonne 0.48 44187.50 21210.00 M-082

Blasting material
Gelatine 80 per cent Kg 1.50 112.77 169.16 M-104

Electric detonators each 6.00 14.27 85.60 M-094/100

b) Labour
Medical Officer day 0.50 0.00 0.00 L-16

Para medical personnel day 1.00 0.00 0.00 L-19

Mate day 1.86 195.43 363.50 L-12

Driller day 1.00 218.57 218.57 L-06

Blaster day 0.50 304.89 152.45 L-03

Mazdoor (for cutting, blasting, cleaning, removal of day 30.00 187.43 5622.90 L-13
Material etc.)
Mazdoor (Skilled) (for fixation and removal of adopter day 10.00 218.57 2185.70 L-15
for air lock, carrying out mechanical and electrical
operations and repairs and other skilled jobs.)
Diver day 4.00 218.57 874.28 L-07

c) Machinery

318
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
(i) Induction, deinduction and erection of plant and hour 6.00 Value #VALUE! P&M-082
equipment including all components and
accessories for pneumatic method of well sinking.

Induction and deinduction L.S 100000.00

Erection at site and commissioning L.S 150000.00

Usage of plant and equipment for pneumatic method of hour 6.00 3834.00 23004.00 P&M-038
well sinking
Air compressor 250 cfm, 2 nos. hour 2x6 293.76 3525.12 P&M-001

Hire and running charges of crane of 15 tonne capacity hour 6.00 770.04 4620.24 P&M-072

Motorised barge of 20 tonne capacity hour 6.00 142.56 855.36 P&M-066

Boat to carry atleast 20 persons hour 6.00 142.56 855.36 P&M-066

Electric generating set 33 KVA hour 6.00 342.36 2054.16 P&M-079

Tipper 10 tonne capacity hour 6.00 846.00 5076.00 P&M-048

d) Overhead charges @ 0.25 on (a+b+c) #VALUE!

e) Contractor's profit @ 0.1 on (a+b+c+d) #VALUE!

Cost for 5 cum = a+b+c+d+e (see notes below) #VALUE!

Rate per cum = (a+b+c+d+e)/5 #VALUE!

Note 1.The cost of induction, deinduction and erection of


equipment shall be divided by the total quantity of pneumatic
sinking for all the wells of a particular bridge to arrive at the
per cum rate on account of this item.
2.Cost of pneumatic sinking per cum of individual wells will be
added to the cost indicated at (1) above to arrive at the final
rate of pneumatic sinking per cum.
3.The cost of induction and deinduction will depend upon the
distance involved for shifting of equipment which may be
assessed in individual cases as per actual ground conditions
at the time of making of cost estimates.
4.In case pneumatic sinking is involved on a dry bed, the
provision of barge and boat may be omitted.
5.The necessity and dimensions of the corbel will be as per
actual ground conditions.
6.Small equipments like welding sets, pumps, vibrators,
pneumatic tools, portable lamps, fire extinguishers, hose
pipes etc., have not been included as the same are covered
as items of minor T&P under overhead charges.
7.Depth of sinking shall be restricted to 30 m.
12.21 1207 Sand Filling in Wells complete as per Drawing and
Technical Specifications.
Unit = 1 cum
Taking output = 1 cum
a) Material
Sand (assuming 20 per cent voids ) cum 1.20 111.50 133.80 M-006

b) Labour
Mate day 0.01 195.43 1.95 L-12

Mazdoor day 0.30 187.43 56.23 L-13

c) Overhead charges @ 0.25 on (a+b) 48.00

d) Contractor's profit @ 0.1 on (a+b+c) 24.00

Rate per cum (a+b+c+d) 263.98


say 264.00

12.22 1200 & Providing Steel Liner 10 mm thick for Curbs and 6 mm
1900 thick for Steining of Wells including Fabricating and
Setting out as per Detailed Drawing.
Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage tonne 1.05 48095.30 50500.07 M-179

b) Labour

319
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 1.24 195.43 242.33 L-12

Fitter day 6.00 251.19 1507.14 L-08

Blacksmith day 5.00 220.57 1102.85 L-01

Welder day 5.00 247.19 1235.95 L-02

Mazdoor day 10.00 187.43 1874.30 L-13

Electrodes, cutting gas and other consumables @ 5 per 2525.00


cent on cost a (a) above.
c) Overhead charges @ 0.25 on (a+b) 14746.91

d) Contractor's profit @ 0.1 on (a+b+c) 7373.46

Rate for per MT (a+b+c+d) 81108.01


say 81108.00

12.23 1100 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a) Materials
PCC Grade M35 cum 6.62 5621.00 37211.02 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 5023.08 30138.48 P&M-036
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 525.00 262.50 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included in
piling rig
Loader I cum bucket capacity. hour 0.30 1148.00 344.40 P&M-017

Tipper 5.5 cum capacity for disposal of muck from pile hour 0.30 846.00 253.80 P&M-048
bore hole
Bentonite kg 300.00 2.24 673.49 M-071

c) Labour
Mate/Supervisor day 0.14 195.43 27.36 L-12

Mazdoor day 3.50 187.43 656.01 L-13

d) Overhead charges @ 0.25 on (b+c) 8089.01

e) Contractor's profit @ 0.1 on (b+c+d) 4044.50

Cost for 15 m = a+b+c+d+d+e 81700.57

Rate per metre (a+b+c+d+e)/15 5446.70


say 5447.00

12.24 Bored cast-in-situ M35 grade R.C.C. Pile excluding


1100,16 Reinforcement complete as per Drawing and Technical
00 & Specifications and removal of excavated earth with all
1700 lifts and lead upto 1000 m.
Pile diameter-1000 mm
Unit = meter
Taking output = 10 m
a) Materials
PCC Grade M35 cum 7.85 5621.00 44124.85 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 5023.08 30138.48 P&M-036
power unit and complete accessories including shifting
from one bore location to another.

320
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Hire and running charges of light crane for lowering hour 0.50 525.00 262.50 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included in
piling rig
Loader I cum bucket capacity. hour 0.40 1148.00 459.20 P&M-017

Tipper 5.5 cum capacity for disposal of muck from pile hour 0.40 846.00 338.40 P&M-048
bore hole
Bentonite kg 350.00 2.24 785.74 M-071

c) Labour
Mate/Supervisor day 0.16 195.43 31.27 L-12

Mazdoor day 4.00 187.43 749.72 L-13

d) Overhead charges @ 0.25 on (b+c) 8191.33

e) Contractor's profit @ 0.1 on (b+c+d) 4095.66

Cost for 10 m = a+b+c+d+d+e 89177.15

Rate per metre (a+b+c+d+e)/10 8917.72


say 8918.00

12.25 1100 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a) Materials
PCC Grade M35 cum 10.17 5621.00 57165.57 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with hour 6.00 5023.08 30138.48 P&M-036
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 525.00 262.50 P&M-013
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included in
piling rig
Loader I cum bucket capacity. hour 0.50 1148.00 574.00 P&M-017

Tipper 5.5 cum capacity for disposal of muck from pile hour 0.50 846.00 423.00 P&M-048
bore hole
Bentonite kg 385.00 2.24 864.32 M-071

c) Labour
Mate/Supervisor day 0.18 195.43 35.18 L-12

Mazdoor day 4.50 187.43 843.44 L-13

d) Overhead charges @ 0.25 on (b+c) 8285.23

e) Contractor's profit @ 0.1 on (b+c+d) 4142.61

Cost for 9 m = a+b+c+d+d+e 102734.32

Rate per metre (a+b+c+d+e)/9 11414.92


say 11415.00

12.26 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 750 mm
Unit = Running meter
Taking output = 40 metre
a) Materials
PCC Grade M35 cum 17.66 5621.00 99266.86 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
b) Materials Pile shoes

321
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
i) C.I. shoes for the pile Kg 160.00 56.39 9021.68 M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 66.31 4641.36 M-124

iii) Steel helmet and cushion block on top of casing head Kg 50.00 51.16 2558.23 M-173
during driving
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 5023.08 30138.48 P&M-085
acting pile driving hammer complete with power unit and
accessories..
Hiring and running charges for light crane 5 tonnes hour 0.50 599.40 299.70 P&M-070
lifting capacity for lowering reinforcement and handling
steel casing.
d) Labour
Mate/Supervisor day 0.12 195.43 23.45 L-12

Mazdoor day 3.00 187.43 562.29 L-13

e) Overhead charges @ 0.25 on (b+c+d) 11811.30

f) Contractor's profit @ 0.1 on (b+c+d+e) 5905.65

Cost for 40 m = a+b+c+d+e 164229.01

Rate per metre (a+b+c+d+e)/40 4105.73


say 4106.00

Note 1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.

12.27 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
a) Materials
PCC Grade M35 cum 23.55 5621.00 132374.55 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 56.39 9021.68 M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 66.31 4641.36 M-124

iii) Steel helmet and cushion block on top of casing head Kg 50.00 51.16 2558.23 M-173
during driving
c) Machinery
Hire and running charges of piling rig Including double hour 6.00 5023.08 30138.48 P&M-085
acting pile driving hammer complete with power unit and
accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 599.40 299.70 P&M-070
lifting capacity for lowering reinforcement and handling
steel casing.
Hire and running charges for light crane for lowering hour 0.50 525.00 262.50 P&M-013
reinforcement cage.
d) Labour
Mate/Supervisor day 0.16 195.43 31.27 L-12

Mazdoor day 4.00 187.43 749.72 L-13

e) Overhead charges @ 0.25 on (b+c+d) 11925.74

f) Contractor's profit @ 0.1 on (b+c+d+e) 5962.87

Cost for 30 m = a+b+c+d+e 197966.10

Rate per metre (a+b+c+d+e)/30 6598.87


say 6599.00

322
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note 1.The quantity of concrete required to be removed above the
designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
12.28 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile diameter - 1200 mm
Unit = Running meter
Taking output = 20 metre
a) Materials
PCC Grade M35 cum 22.61 5621.00 127090.81 Item 12.11
(C) iv
Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 56.39 9021.68 M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m Kg 70.00 66.31 4641.36 M-124

iii) Steel helmet on top of casing head during driving Kg 50.00 51.16 2558.23 M-173

c) Machinery
Hire and running charges of piling rig Including double hour 6.00 5023.08 30138.48 P&M-085
acting pile driving hammer complete with power unit and
accessories.
Hiring and running charges for light crane 5 tonnes hour 0.50 599.40 299.70 P&M-070
lifting capacity for lowering reinforcement and handling
steel casing.
d) Labour
Mate/Supervisor day 0.18 195.43 35.18 L-12

Mazdoor day 4.50 187.43 843.44 L-13

e) Overhead charges @ 0.25 on (b+c+d) 11884.52

f) Contractor's profit @ 0.1 on (b+c+d+e) 5942.26

Cost for 20 m = a+b+c+d+e 192455.66

Rate per metre (a+b+c+d+e)/20 9622.78


say 9623.00

Note 1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven cast-
in-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
12.29 1100 & Driven precast vertical M35 grade R.C.C. Piles
1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile Diameter = 500 mm
Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M35 cum 11.78 5336.00 62858.08 Item 12.11
(F) iv

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I Shoes Kg 240.00 56.39 13532.53 M-080

b) M.S. shoes Kg 105.00 42.08 4418.43 M-125

323
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Steel helmet and cushion block on top of pile head Kg 30.00 51.16 1534.94 M-173
during driving.
c) Machinery
Crane20 t capacity hour 6.00 785.16 4710.96 P&M-073

Vibrating Pile driving hammer complete with power unit hour 6.00 Value #VALUE! P&M-092
and accessories.
d) Labour
Mate/Supervisor day 0.12 195.43 23.45 L-12

Mazdoor day 3.00 187.43 562.29 L-13

Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) #VALUE!

f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!

Cost for 60 m = a+b+c+d+e+f #VALUE!

Rate per metre (a+b+c+d+e+f)/60 #VALUE!


say #VALUE!

Note The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
12.30 1100 & Driven precast vertical M35 grade R.C.C. Piles
1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile Diameter = 750 mm
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M35 cum 22.08 5336.00 117818.88 Item 12.11
(F) iv

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I. shoes Kg 160.00 56.39 9021.68 M-080

b) M.S. shoes Kg 70.00 42.08 2945.62 M-125

c) Steel helmet and cushion block on top of pile head Kg 40.00 51.16 2046.59 M-173
during driving.
c) Machinery
Crane 40 T capacity hour 6.00 1166.40 6998.40 P&M-074

Vibrating Pile driving hammer complete with power unit hour 6.00 Value #VALUE! P&M-092
and accessories.
d) Labour
Mate/Supervisor day 0.16 195.43 31.27 L-12

Mazdoor day 4.00 187.43 749.72 L-13

Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) #VALUE!

f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!

Cost for 50 m = a+b+c+d+e+f #VALUE!

Rate per metre (a+b+c+d+e+f)/50 #VALUE!


say #VALUE!

Note The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
12.31 1100 & Driven precast vertical M35 grade R.C.C. Piles
1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Pile Diameter = 1000 mm
Unit = Running Meter
Taking output = 40 m
a) Materials

324
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
RCC Grade M35 cum 31.40 5336.00 167550.40 Item 12.11
(F) iv

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I. shoes for the pile Kg 160.00 56.39 9021.68 M-080

b) M.S. shoes @ 35 Kg per pile of 15 m Kg 70.00 42.08 2945.62 M-125

c) Steel helmet and cushion block on top of pile head Kg 50.00 51.16 2558.23 M-173
during driving.
c) Machinery
Crane 50 t capacity. hour 6.00 1176.12 7056.72 P&M-011

Vibrating Pile driving hammer complete with power unit hour 6.00 Value #VALUE! P&M-092
and accessories.
d) Labour
Mate/Supervisor day 0.20 195.43 39.09 L-12

Mazdoor day 5.00 187.43 937.15 L-13

Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) #VALUE!

f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!

Cost for 40 m = a+b+c+d+e+f #VALUE!

Rate per metre (a+b+c+d+e+f)/40 #VALUE!


say #VALUE!

Note The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
12.32 1100&1 Driven precast vertical M35 grade R.C.C. Piles
700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Size of pile - 300 mm x 300 mm
Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 5.40 5336.00 28814.40 Item 12.11
plug vide item no. 12.11( F ) (IV) (F) iv

b ) Material Pile shoes


a) C I shoes kg 240.00 56.39 13532.53 M-080

b) M. S shoes kg 105.00 42.08 4418.43 M-125

c) Steel helmet and cushion block on top of pile head Kg 30.00 51.16 1534.94 M-173
during driving.
c) Machinery
Crane 10 tonne capacity hour 6.00 627.48 3764.88 P&M-071

Vibrating Pile driving hammer complete with power unit hour 6.00 Value #VALUE! P&M-092
and accessories.
d ) Labour
Mate/Supervisor day 0.12 195.43 23.45 L-12

Mazdoor day 3.00 187.43 562.29 L-13

Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) #VALUE!

f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!

Cost for 60 m = a+b+c+d+e+f #VALUE!

Rate per metre (a+b+c+d+e+f)/60 #VALUE!


say #VALUE!

Note The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.

325
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.33 1100 Driven precast vertical M35 grade R.C.C. Piles
&1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Size of pile - 500 mm x 500 mm
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 12.50 5336.00 66700.00 Item 12.11
plug vide item no. 12.11( F ) (IV) (F) iv

b ) Material Pile shoes


a) C I shoes kg 160.00 56.39 9021.68 M-080

b) M. S shoes kg 70.00 42.08 2945.62 M-125

c) Steel helmet and cushion block on top of pile head Kg 30.00 51.16 1534.94 M-173
during driving.
c) Machinery
Crane 20 tonne capacity hour 6.00 785.16 4710.96 P&M-073

Vibrating Pile driving hammer complete with power unit hour 6.00 Value #VALUE! P&M-092
and accessories.
d ) Labour
Mate/Supervisor day 0.16 195.43 31.27 L-12

Mazdoor day 4.00 187.43 749.72 L-13

Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) #VALUE!

f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!

Cost for 50 m = a+b+c+d+e+f #VALUE!

Rate per metre (a+b+c+d+e+f)/50 #VALUE!


say #VALUE!

Note The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
12.34 1100 Driven precast vertical M35 grade R.C.C. Piles
&1700 excluding Reinforcement complete as per Drawing and
& Technical Specification
Size of pile - 750 mm x 750 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom cum 22.50 5336.00 120060.00 Item 12.11
plug vide item no. 13.11( F ) (IV) (F) iv

b ) Material
Pile shoes
a) C I shoes kg 160.00 56.39 9021.68 M-080

b) M. S shoes kg 70.00 42.08 2945.62 M-125

c) Steel helmet and cushion block on top of pile head Kg 30.00 51.16 1534.94 M-173
during driving.
c) Machinery
Crane 20 tonne capacity hour 6.00 785.16 4710.96 P&M-073

Vibrating Pile driving hammer complete with power unit hour 6.00 Value #VALUE! P&M-092
and accessories.
d ) Labour
Mate/Supervisor day 0.18 195.43 35.18 L-12

Mazdoor day 4.50 187.43 843.44 L-13

Add 1 per cent of (a+b+c) for carriage of piles from #VALUE!


casting yard to work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 0.25 on (b+c+d) #VALUE!

326
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
f) Contractor's profit @ 0.1 on (b+c+d+e) #VALUE!

Cost for 40 m = a+b+c+d+e+f #VALUE!

Rate per metre (a+b+c+d+e+f)/40 #VALUE!


say #VALUE!

Note The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
12.35 1100, Driven Vertical Steel Piles complete as per Drawing and
1900 & Technical Specification
Section of the pile - H Section steel column 400 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 70 m
a) Materials
Structural steel including 5 per cent wastage @ 82.20 tonnes 6.04 48095.30 290495.64 M-179
kg/m
b) Machinery
Crane 10 T capacity hour 6.00 627.48 3764.88 P&M-071

Vibrating Pile driving hammer complete with power unit hour 6.00 Value #VALUE! P&M-092
and other accessories.
c) Labour
Mate/Supervisor day 0.12 195.43 23.45 L-12

Mazdoor day 3.00 187.43 562.29 L-13

Add 0.5 per cent of (a+b+c) for providing steel #VALUE!


helmet on top of pile head during driving, stacking of
piles at site, providing anti-corrosion treatment and other
imponderables during installation.
d) Overhead charges @ 0.25 on (a+b+c) #VALUE!

e) Contractor's profit @ 0.1 on (a+b+c+d) #VALUE!

Cost for 70 m = a+b+c+d+e #VALUE!

Rate per metre (a+b+c+d+e)/70 #VALUE!


say #VALUE!

12.36 1100 Driven Vertical Steel Piles complete as per Drawing and
&1900 & Technical Specification
Section of the pile - H Section steel column 450 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 60 m
a) Materials
Structural steel including 5 per cent wastage @92.50 tonnes 5.83 48095.30 280395.63 M-179
kg/m
b) Machinery
Crane 10 T capacity hour 6.00 627.48 3764.88 P&M-071

Vibrating Pile driving hammer complete with power unit hour 6.00 Value #VALUE! P&M-092
and accessories.
c) Labour
Mate/Supervisor day 0.14 195.43 27.36 L-12

Mazdoor day 3.50 187.43 656.01 L-13

Add 0.5 per cent of (a+b+c) for providing steel #VALUE!


helmet and cushion block on top of pile head during
driving, stacking of piles at site, providing anti-corrosive
treatment and other imponderables during installation.

d) Overhead charges @ 0.25 on (a+b+c) #VALUE!

e) Contractor's profit @ 0.1 on (a+b+c+d) #VALUE!

Cost for 60 m = a+b+c+d+e #VALUE!

Rate per metre (a+b+c+d+e)/60 #VALUE!


say #VALUE!

12.37 1100 Pile Load Test on single Vertical Pile in accordance with
IS:2911(Part-IV)
Unit = 1 MT

327
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking output = 1 MT
a) Initial and routine load test tonne 1.00 300.00 300.00

b) Lateral load test tonne 1.00 5000.00 5000.00

Note Although, this item is incidental to work and is not required to 5300.00
be included in BOQ of contract, the same is required to be
added in the estimate to assess cost of work.

12.38 1100, Cement Concrete for Reinforced Concrete in Pile Cap


1500 complete as per Drawing and Technical Specification
&1700
A RCC Grade M20
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 5.12 5982.46 30630.18 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

20 mm Aggregate cum 8.10 887.53 7188.96 M-053

10 mm Aggregate cum 5.40 674.15 3640.42 M-051

b) Labour
Mate day 0.90 195.43 175.89 L-12

Mason day 1.50 220.57 330.86 L-10

Mazdoor for concreting day 20.00 187.43 3748.60 L-13

Mazdoor for breaking pile head, bending bars, cleaning day 1.00 187.43 187.43 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator (capacity 33 KVA) hour 6.00 342.36 2054.16 P&M-079

Formwork @ 4 per cent on cost of concrete i.e. cost of 2025.53


a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 13165.93

e) Contractor's profit @ 0.1 on (a+b+c+d) 6582.97

Cost for 15 cum = a+b+c+d+e 72412.62

Rate per metre (a+b+c+d+e)/15 4827.51


say 4828.00

12.38A (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 5.12 5982.46 30630.18 M-081

Coarse sand cum 6.75 209.13 1411.63 M-004

20 mm Aggregate cum 8.10 887.53 7188.96 M-053

10 mm Aggregate cum 5.40 674.15 3640.42 M-051

b) Labour
Mate day 0.16 195.43 31.27 L-12

Mason day 0.38 220.57 83.82 L-10

Mazdoor for concreting day 2.50 187.43 468.58 L-13

Mazdoor for breaking pile head, bending bars, cleaning day 1.00 187.43 187.43 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2457.00 1842.75 P&M-002

Generator 100 KVA hour 0.75 1635.00 1226.25 P&M-080

Loader (capacity 1 cum) hour 0.75 1148.00 861.00 P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km hour 2.00 854.55 1709.10 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 4.32 162.00 Lead =1 km
& P&M-050
Concrete Pump hour 0.75 234.36 175.77 P&M-007

Formwork @ 4 per cent on cost of concrete i.e. cost of 1984.77


a) Material, b) Labour and c) Machinery

328
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Overhead charges @ 0.25 on (a+b+c) 12900.98

e) Contractor's profit @ 0.1 on (a+b+c+d) 6450.49

Cost for 15 cum = a+b+c+d+e 70955.38

Rate per metre (a+b+c+d+e)/15 4730.36


say 4730.00

Note The value of a, b and c may be taken as applicable i.e. either


using concrete mixer or batching plant.
12.38 B RCC Grade M25
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 5.99 5982.46 35834.91 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

20 mm Aggregate cum 8.10 887.53 7188.96 M-053

10 mm Aggregate cum 5.40 674.15 3640.42 M-051

b) Labour
Mate day 0.90 195.43 175.89 L-12

Mason day 1.50 220.57 330.86 L-10

Mazdoor for concreting day 20.00 187.43 3748.60 L-13

Mazdoor for breaking pile head, bending bars, cleaning day 1.00 187.43 187.43 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator (capacity 33 KVA) hour 6.00 342.36 2054.16 P&M-079

Formwork @ 4 per cent on cost of concrete i.e. cost of 2233.72


a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 14519.16

e) Contractor's profit @ 0.1 on (a+b+c+d) 7259.58

Cost for 15 cum = a+b+c+d+e 79855.40

Rate per metre (a+b+c+d+e)/15 5323.69


say 5324.00

12.38B (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 5.99 5982.46 35834.91 M-081

Coarse sand cum 6.75 209.13 1411.63 M-004

20 mm Aggregate cum 8.10 887.53 7188.96 M-053

10 mm Aggregate cum 5.40 674.15 3640.42 M-051

b) Labour
Mate day 0.16 195.43 31.27 L-12

Mason day 0.38 220.57 83.82 L-10

Mazdoor for concreting day 2.50 187.43 468.58 L-13

Mazdoor for breaking pile head, bending bars, cleaning day 1.00 187.43 187.43 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2457.00 1842.75 P&M-002

Generator 125 KVA hour 0.75 2211.00 1658.25 P&M-018

Loader (capacity 1 cum) hour 0.75 1148.00 861.00 P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km hour 2.00 854.55 1709.10 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 4.32 162.00 Lead =1 km
& P&M-050
Concrete Pump hour 0.75 234.36 175.77 P&M-007

Formwork @ 4 per cent on cost of concrete i.e. cost of 2210.24


a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 14366.53

e) Contractor's profit @ 0.1 on (a+b+c+d) 7183.26

329
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cost for 15 cum = a+b+c+d+e 79015.91

Rate per metre (a+b+c+d+e)/15 5267.73


say 5268.00

Note The value of a, b and c may be taken as applicable i.e. either


using concrete mixer or batching plant.
12.38 C RCC Grade M30
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 6.10 5982.46 36492.98 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

20 mm Aggregate cum 8.10 887.53 7188.96 M-053

10 mm Aggregate cum 5.40 674.15 3640.42 M-051

b) Labour
Mate day 0.90 195.43 175.89 L-12

Mason day 1.50 220.57 330.86 L-10

Mazdoor for concreting day 20.00 187.43 3748.60 L-13

Mazdoor for breaking pile head, bending bars, cleaning day 1.00 187.43 187.43 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator (capacity 33 KVA) hour 6.00 342.36 2054.16 P&M-079

Formwork @ 4 per cent on cost of concrete i.e. cost of 2260.04


a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 14690.26

e) Contractor's profit @ 0.1 on (a+b+c+d) 7345.13

Cost for 15 cum = a+b+c+d+e 80796.44

Rate per metre (a+b+c+d+e)/15 5386.43


say 5386.00

'12.38C (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 6.10 5982.46 36492.98 M-081

Coarse sand cum 6.75 209.13 1411.63 M-004

20 mm Aggregate cum 8.10 887.53 7188.96 M-053

10 mm Aggregate cum 5.40 674.15 3640.42 M-051

b) Labour
Mate day 0.16 195.43 31.27 L-12

Mason day 0.38 220.57 83.82 L-10

Mazdoor for concreting day 2.50 187.43 468.58 L-13

Mazdoor for breaking pile head, bending bars, cleaning day 1.00 187.43 187.43 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2457.00 1842.75 P&M-002

Generator 100 KVA hour 0.75 1635.00 1226.25 P&M-080

Loader (capacity 1 cum) hour 0.75 1148.00 861.00 P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km hour 2.00 854.55 1709.10 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 4.32 162.00 Lead =1 km
& P&M-050
Concrete Pump hour 0.75 234.36 175.77 P&M-007

Formwork @ 4 per cent on cost of concrete i.e. cost of 2219.28


a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 14425.31

e) Contractor's profit @ 0.1 on (a+b+c+d) 7212.65

Cost for 15 cum = a+b+c+d+e 79339.19

Rate per metre (a+b+c+d+e)/15 5289.28

330
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 5289.00

Note The value of a, b and c may be taken as applicable i.e. either


using concrete mixer or batching plant.
12.38 D RCC Grade M35
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 6.33 5982.46 37868.95 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

20 mm Aggregate cum 8.10 887.53 7188.96 M-053

10 mm Aggregate cum 5.40 674.15 3640.42 M-051

b) Labour
Mate day 0.90 195.43 175.89 L-12

Mason day 1.50 220.57 330.86 L-10

Mazdoor day 20.00 187.43 3748.60 L-13

Mazdoor for breaking pile head, bending bars, cleaning day 1.00 187.43 187.43 L-13
etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator (capacity 33 KVA) hour 6.00 342.36 2054.16 P&M-079

Formwork @ 4 per cent on cost of concrete i.e. cost of 2315.08


a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 15048.01

e) Contractor's profit @ 0.1 on (a+b+c+d) 7524.01

Cost for 15 cum = a+b+c+d+e 82764.07

Rate per metre (a+b+c+d+e)/15 5517.60


say 5518.00

'12.38D (ii) Using Batching Plant, Transit Mixer and Concrete Pump

a) Material
Cement tonne 6.33 5982.46 37868.95 M-081

Coarse sand cum 6.75 209.13 1411.63 M-004

20 mm Aggregate cum 8.10 887.53 7188.96 M-053

10 mm Aggregate cum 5.40 674.15 3640.42 M-051

b) Labour
Mate day 0.16 195.43 31.27 L-12

Mason day 0.38 220.57 83.82 L-10

Mazdoor for concreting day 2.50 187.43 468.58 L-13

Mazdoor for breaking pile head, bending bars, cleaning day 1.00 187.43 187.43 L-13
etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 2457.00 1842.75 P&M-002

Generator 125 KVA hour 0.75 2211.00 1658.25 P&M-018

Loader (capacity 1 cum) hour 0.75 1148.00 861.00 P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km hour 2.00 854.55 1709.10 P&M-049

Lead beyond 1 Km, L - lead in Kilometer tonne.km 37.5L 4.32 162.00 Lead =1 km
& P&M-050
Concrete Pump hour 0.75 234.36 175.77 P&M-007

Formwork @ 4 per cent on cost of concrete i.e. cost of 2291.60


a) Material, b) Labour and c) Machinery
d) Overhead charges @ 0.25 on (a+b+c) 14895.38

e) Contractor's profit @ 0.1 on (a+b+c+d) 7447.69

Cost for 15 cum = a+b+c+d+e 81924.58

Rate per metre (a+b+c+d+e)/15 5461.64


say 5462.00

331
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.39 1100&1 Levelling Course for Pile cap
700
Providing and laying of PCC M15 levelling course
100mm thick below the pile cap.
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 5982.46 24707.54 M-081

Coarse sand cum 6.75 209.13 1411.63 M-005

40 mm aggregate cum 8.10 780.12 6318.96 M-055

20 mm Aggregate cum 4.05 887.53 3594.48 M-053

10 mm Aggregate cum 1.35 674.15 910.10 M-051

b) Labour
Mate day 0.86 195.43 168.07 L-12

Mason day 1.50 220.57 330.86 L-10

Mazdoor day 20.00 187.43 3748.60 L-13

c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009

Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079

d) Overhead charges @ 0.25 on (a+b+c) 11128.62

e) Contractor's profit @ 0.1 on (a+b+c+d) 5564.31

Cost for 15 cum = a+b+c+d+e 61207.42

Rate per metre (a+b+c+d+e)/15 4080.49


say 4080.00

12.40 1600 Supplying, Fitting and Placing un-coated HYSD bar


Reinforcement in Foundation complete as per Drawing
and Technical Specifications.
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including5 per cent overlaps and wastage tonne 1.05 44187.50 46396.88 M-082

Binding wire Kg 6.00 62.52 375.14 M-072

b) Labour for cutting, bending, shifting to site, tying


and placing in position
Mate day 0.40 195.43 78.17 L-12

Blacksmith day 2.00 247.19 494.38 L-02

Mazdoor day 6.00 187.43 1124.58 L-13

c) Overhead charges @ 0.25 on (a+b) 12117.29

d) Contractor's profit @ 0.1 on (a+b+c) 6058.64

Rate per MT (a+b+c+d) 66645.08


say 66645.00

12.41 1600 Supplying, fitting and placing un-coated Mild steel


reinforcement complete in foundation as per drawing
and technical specification
Unit = 1 MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps and wastage tonne 1.05 49279.84 51743.84 M-126

Binding wire Kg 6.00 62.52 375.14 M-072

b) Labour for straightening, cutting, bending, shifting


to site, tying and placing in position
Mate day 0.43 195.43 84.03 L-12

Blacksmith day 2.25 247.19 556.18 L-02

Mazdoor day 6.50 187.43 1218.30 L-13

c) Overhead charges @ 0.25 on (a+b) 13494.37

d) Contractor's profit @ 0.1 on (a+b+c) 6747.19

Rate for per MT (a+b+c+d) 74219.04

332
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
say 74219.00

333
RCD/SOR
CHAPTER-13
SUB-STRUCTURE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.1 1300 & Brick masonry work in 1:3 in sub-structure complete
2200 excluding pointing and plastering, as per drawing and
Technical Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class each 500.00 4.72 2361.02 M-079
Cement mortar 1:3 (Rate as in Item 12.6 A sub- cum 0.24 3447.00 827.28 Item 12.6 (A)
analysis)
b) Labour
Mate day 0.06 195.43 11.73 L-12
Mason day 0.80 247.19 197.75 L-11
Mazdoor day 0.80 187.43 149.94 L-13
Add for scaffolding @ 5 per cent of cost of material 177.39
and labour
c) Overhead charges @ 0.25 on (a+b) 931.28
d) Contractor's profit @ 0.1 on (a+b+c) 465.64
Rate per cum (a+b+c+d) 5122.02
say 5122.00
13.2 1300 & Pointing with cement mortar (1:3 ) on brick work in
2200 substructure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6 ) cum 0.03 3447.00 103.41 Item 12.6 (A)

b) Labour
Mate day 0.04 195.43 7.82 L-12
Mason day 0.50 247.19 123.60 L-11
Mazdoor day 0.50 187.43 93.72 L-13
c) Overhead charges @ 0.25 on (a+b) 82.13
d) Contractor's profit @ 0.1 on (a+b+c) 41.07
Rate per 10 sqm (a+b+c+d) 451.74
say 452.00
Note Scaffolding is already included in item 13.1
13.3 1300 & Plastering with cement mortar (1:3 ) on brick work in
2200 sub-structure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.144 3447.00 496.37 Item 12.6 (A)
b) Labour
Mate day 0.04 195.43 7.82 L-12
Mason day 0.50 247.19 123.60 L-11
Mazdoor day 0.50 187.43 93.72 L-13
c) Overhead charges @ 0.25 on (a+b) 180.37
d) Contractor's profit @ 0.1 on (a+b+c) 90.19
Rate per 10 sqm (a+b+c+d) 992.06
say 992.00
Note 1.Scaffolding is already included in item no. 13.1
2.The number of masons and Mazdoors already catered in
the cement mortar have been taken into account while
providing these categories in brick masonry, pointing and
plastering.
13.4 1400 & Stone masonry work in cement mortar 1:3 for
2200 substructure complete as per drawing and Technical
Specifications
A Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 359.72 359.72 M-148
Through and bond stone No 7.00 6.06 42.39 M-182
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.33 3447.00 1137.51 Item 12.6 (A)
b) Labour
Mate day 0.10 195.43 19.54 L-12
Mason day 1.20 247.19 296.63 L-11
Mazdoor day 1.20 187.43 224.92 L-13
Add for scaffolding @ 5 per cent of cost of a) 104.04
Material and b) Labour
c) Overhead charges @ 0.25 on (a+b) 546.19
d) Contractor's profit @ 0.1 on (a+b+c) 273.09
Rate per cum (a+b+c+d) 3004.02
say 3004.00

253
RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.4 B Coursed rubble masonry (first sort )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.10 359.72 395.69 M-148
Through and bond stone each 7.00 6.06 42.39 M-182
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.30 3447.00 1034.10 Item 12.6 (A)
b) Labour
Mate day 0.12 195.43 23.45 L-12
Mason day 1.50 247.19 370.79 L-11
Mazdoor day 1.50 187.43 281.15 L-13
Add for scaffolding @ 5 per cent of cost of material 107.38
and labour
c) Overhead charges @ 0.25 on (a+b) 563.74
d) Contractor's profit @ 0.1 on (a+b+c) 281.87
Rate per cum (a+b+c+d) 3100.55
say 3101.00
13.4 C Ashlar masonry ( first sort )
Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.11 360.24 399.87 M-169
Through and bond stone each 7.00 6.06 42.39 M-182
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.33 3447.00 1137.51 Item 12.6 (A)
b) Labour for masonry work
Mate day 0.20 195.43 39.09 L-12
Mason day 2.50 247.19 617.98 L-11
Mazdoor day 2.50 187.43 468.58 L-13
Add for scaffolding @ 5 per cent of cost of a) 135.27
Material and b) Labour
c) Overhead charges @ 0.25 on (a+b) 710.17
d) Contractor's profit @ 0.1 on (a+b+c) 355.08
Rate per cum (a+b+c+d) 3905.93
say 3906.00
Note The labour already considered in the cement mortar have
been taken into account while providing these categories in
the stone masonry works.
13.5 1500, Plain/Reinforced cement concrete in sub-structure
1700 & complete as per drawing and Technical Specifications
2200
Unit = cum
Taking output = 1 cum
A PCC Grade M15
(p) Height upto 5m
Same as Item 12.8 (A) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 2979.00 Item 12.8 (A)
(a+b+c) of Item 12.8 (A)
d) formwork
Add 10 per cent of cost of material, labour and 10.00 297.90
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 819.23
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 409.61
Rate per cum (a+b+c+d+e+f) 4505.74
say 4506.00
13.5 B PCC Grade M20
(p) Height upto 5m
Same as Item 12.8 (B) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery 3382.00 Item 12.8 (B)
(a+b+c) of Item 12.8 (B) PCC
d) formwork
Add 10 per cent of cost of material, labour and 10.00 338.20
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 930.05
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 465.03
Rate per cum (a+b+c+d+e+f) 5115.28
say 5115.00

254
RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.5 C PCC Grade M25
(p) Height upto 5m
Same as Item 12.8 (D) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.75 per cent of cost of material, labour and machinery.

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery 3713.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 371.30
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1021.08
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 510.54
Rate per cum (a+b+c+d+e+f) 5615.91
say 5616.00
13.5 C Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 3632.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 363.20
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 998.80
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 499.40
Rate per cum (a+b+c+d+e+f) 5493.40
say 5493.00
13.5 C (q) Height 5m to 10m
Same as Item 12.8 (D) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.75 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3713.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I
d) formwork
Add 12 per cent of cost of material, labour and 12.00 445.56
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 74.26
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1058.21
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 529.10
Rate per cum (a+b+c+d+e+f) 5820.13
say 5820.00
13.5 C Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3632.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 435.84
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 72.64
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1035.12
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 517.56
Rate per cum (a+b+c+d+e+f) 5693.16
say 5693.00
13.5 C (r) Height above 10m
Same as Item 12.8 (D) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.75 per cent of cost of
material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3713.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 556.95
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 148.52
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1104.62
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 552.31
Rate per cum (a+b+c+d+e+f) 6075.40
say 6075.00

255
RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.5 C Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 3632.00 Item 12.8 (D)
(a+b+c) of Item 12.8 (D) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 544.80
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 145.28
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1080.52
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 540.26
Rate per cum (a+b+c+d+e+f) 5942.86
say 5943.00
13.5 D PCC Grade M30
(p) Height upto 5m
Same as Item 12.8 (F) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.50 per cent of cost of material, labour and machinery.

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery 3749.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 374.90
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1030.98
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 515.49
Rate per cum (a+b+c+d+e+f) 5670.36
say 5670.00
13.5 D Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 3665.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 366.50
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1007.88
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 503.94
Rate per cum (a+b+c+d+e+f) 5543.31
say 5543.00
13.5 D (q) Height 5m to 10m
Same as Item 12.8 (F) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.50 per cent of
cost of material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3749.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case I
d) formwork
Add 12 per cent of cost of material, labour and 12.00 449.88
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 74.98
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1068.47
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 534.23
Rate per cum (a+b+c+d+e+f) 5876.56
say 5877.00
13.5 D Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3665.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 439.80
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 73.30
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1044.53
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 522.26
Rate per cum (a+b+c+d+e+f) 5744.89
say 5745.00
13.5 D (r) Height above 10m
Same as Item 12.8 (F) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.50 per cent of cost of
material, labour and machinery

256
RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3749.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 562.35
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 149.96
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1115.33
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 557.66
Rate per cum (a+b+c+d+e+f) 6134.30
say 6134.00
13.5 D Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 3665.00 Item 12.8 (F)
(a+b+c) of Item 12.8 (F) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 549.75
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 146.60
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1090.34
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 545.17
Rate per cum (a+b+c+d+e+f) 5996.86
say 5997.00
13.5 E RCC Grade M20
(p) Height upto 5m
Same as Item 12.8 (C) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3402.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 340.20
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 935.55
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 467.78
Rate per cum (a+b+c+d+e+f) 5145.53
say 5146.00
13.5 E Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 3319.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 331.90
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 912.73
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 456.36
Rate per cum (a+b+c+d+e+f) 5019.99
say 5020.00
13.5 E (q) Height 5m to 10m
For height, upto 10m, add 2 per cent of cost as above
excluding formwork. For cost of formwork add 12 per cent of
cost of material, labour and machinery instead of 4 per cent .

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery 3402.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case I
d) formwork
Add 12 per cent of cost of material, labour and 12.00 408.24
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 68.04
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 969.57
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 484.79
Rate per cum (a+b+c+d+e+f) 5332.64
say 5333.00
13.5 E Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3319.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 398.28
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 66.38
machinery excluding formwork to cater for extra lift

257
RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Overhead charges @ 0.25 on (a+b+c+d) 945.92
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 472.96
Rate per cum (a+b+c+d+e+f) 5202.53
say 5203.00
13.5 E (r) Height above 10m
Same as Item 12.8 (C) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 4 per cent of cost of
material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3402.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 510.30
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 136.08
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1012.10
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 506.05
Rate per cum (a+b+c+d+e+f) 5566.52
say 5567.00
13.5 E Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 3319.00 Item 12.8 (C)
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 497.85
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 132.76
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 987.40
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 493.70
Rate per cum (a+b+c+d+e+f) 5430.71
say 5431.00
13.5 F RCC Grade M25
(p) Height upto 5m
Same as Item 12.8 (E) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.75 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3737.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 373.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1027.68
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 513.84
Rate per cum (a+b+c+d+e+f) 5652.21
say 5652.00
13.5 F Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 3655.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case II
DIR used item
d) formwork
Add 10 per cent of cost of material, labour and 10.00 365.50
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1005.13
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 502.56
Rate per cum (a+b+c+d+e+f) 5528.19
say 5528.00
13.5 F (q) Height 5m to 10m
For height, upto 10m, add 1.8 per cent of cost as above
excluding formwork. For cost of formwork add 11.8 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3737.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case I
d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 440.97
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 67.27
machinery excluding formwork to cater for extra lift

258
RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Overhead charges @ 0.25 on (a+b+c+d) 1061.31
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 530.65
Rate per cum (a+b+c+d+e+f) 5837.19
say 5837.00
13.5 F Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3655.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case II
DIR used item
d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 431.29
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 65.79
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1038.02
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 519.01
Rate per cum (a+b+c+d+e+f) 5709.11
say 5709.00
13.5 F (r) Height above 10m
For height, above 10m, add 4 per cent of cost as above
excluding formwork. For cost of formwork add 15 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3737.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 560.55
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 149.48
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1111.76
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 555.88
Rate per cum (a+b+c+d+e+f) 6114.67
say 6115.00
13.5 F Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 3655.00 Item 12.8 (E)
(a+b+c) of Item 12.8 (E) Case II
DIR used item
d) formwork
Add 15 per cent of cost of material, labour and 15.00 548.25
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 146.20
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1087.36
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 543.68
Rate per cum (a+b+c+d+e+f) 5980.49
say 5980.00
13.5 G RCC Grade M30
(p) Height upto 5m
Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3757.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 375.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1033.18
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 516.59
Rate per cum (a+b+c+d+e+f) 5682.46
say 5682.00
13.5 G Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 3676.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 367.60
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1010.90
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 505.45
Rate per cum (a+b+c+d+e+f) 5559.95
say 5560.00

259
RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.5 G (q) Height 5m to 10m
For height, upto 10m, add 1.6 per cent of cost as above
excluding formwork. For cost of formwork add 11.5 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3757.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 432.06
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 60.11
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1062.29
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 531.15
Rate per cum (a+b+c+d+e+f) 5842.60
say 5843.00
13.5 G Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3676.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 422.74
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 58.82
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1039.39
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 519.69
Rate per cum (a+b+c+d+e+f) 5716.64
say 5717.00
13.5 G (r) Height above 10m
For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3757.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 14 per cent of cost of material, labour and 14.00 525.98
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 131.50
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1103.62
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 551.81
Rate per cum (a+b+c+d+e+f) 6069.90
say 6070.00
13.5 G Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 3676.00 Item 12.8 (G)
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 14 per cent of cost of material, labour and 14.00 514.64
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 128.66
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1079.83
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 539.91
Rate per cum (a+b+c+d+e+f) 5939.04
say 5939.00
13.5 H RCC Grade M35
(p) Height upto 5m
Same as Item 12.8 (H) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3849.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case I Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 384.90
machinery (a+b+c) for Formwork
e) Overhead charges @ 0.25 on (a+b+c+d) 1058.48
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 529.24
Rate per cum (a+b+c+d+e+f) 5821.61
say 5822.00
13.5 H Case With Batching Plant, Transit Mixer and Concrete Pump
(p) II
Per Cum Basic Cost of Labour, Material & Machinery 3959.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case II

260
RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
DIR used item
d) formwork
Add 10 per cent of cost of material, labour and 10.00 395.90
machinery (a+b+c) for Formwork

261
RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Overhead charges @ 0.25 on (a+b+c+d) 1088.73
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 544.36
Rate per cum (a+b+c+d+e+f) 5987.99
say 5988.00
13.5 H (q) Height 5m to 10m 5412.00
For height, upto 10m, add 1.4 per cent of cost as above
excluding formwork. For cost of formwork add 11 per cent of
cost of material, labour and machinery .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3849.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case I Case I
d) formwork
Add 11 per cent of cost of material, labour and 11.00 423.39
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 53.89
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1081.57
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 540.78
Rate per cum (a+b+c+d+e+f) 5948.63
say 5949.00
13.5 H Case With Batching Plant, Transit Mixer and Concrete Pump
(q) II
Per Cum Basic Cost of Labour, Material & Machinery 3959.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 11 per cent of cost of material, labour and 11.00 435.49
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 55.43
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1112.48
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 556.24
Rate per cum (a+b+c+d+e+f) 6118.63
say 6119.00
13.5 H (r) Height above 10m 5530.00
For height, above 10m, add 3 per cent of cost as above
excluding formwork. For cost of formwork add 13 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3849.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case I Case I
d) formwork
Add 13 per cent of cost of material, labour and 13.00 500.37
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 115.47
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1116.21
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 558.11
Rate per cum (a+b+c+d+e+f) 6139.16
say 6139.00
13.5 H Case With Batching Plant, Transit Mixer and Concrete Pump
(r) II
Per Cum Basic Cost of Labour, Material & Machinery 3959.00 Item 12.8 (H)
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 13 per cent of cost of material, labour and 13.00 514.67
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 118.77
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 0.25 on (a+b+c+d) 1148.11
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 574.06
Rate per cum (a+b+c+d+e+f) 6314.61
say 6315.00
5707.00
Note The basic components of this analysis are the same as
those of items 13.8 (A to H). The only changes are as under:

a) Ramps/Stairs: Extra expenditure on structures which


are more than 5 m high @ 2 per cent of cost for height upto
10 m and 4 per cent for heights above 10 m will be involved
for approaching the work spot by providing higher ramp/stair
case for use by the working parties.
b) The above mentioned percentages have been suitably
modified for different categories as cost for various
categories varies, whereas effort for access for same height
will be similar. As the cost of richer concrete is comparatively
more, the percentage to be added has been reduced to
maintain the same cost for extra efforts.

262
RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.6 Section Supplying, fitting and placing HYSD bar reinforcement
1600 & in sub-structure complete as per drawing and
2200 Technical Specifications

263
RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Output: MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent overlaps and wastage tonne 1.05 44187.50 46396.88 M-082

Binding wire kg 6.00 62.52 375.14 M-072


b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.34 195.43 66.45 L-12
Blacksmith day 2.00 247.19 494.38 L-02
Mazdoor day 6.50 187.43 1218.30 L-13
c) Overhead charges @ 0.25 on (a+b) 12137.78
d) Contractor's profit @ 0.1 on (a+b+c) 6068.89
Rate for per MT (a+b+c+d) 66757.82
say 66758.00
13.7 1600 & Supplying, fitting and placing Mild steel reinforcement
2200 complete in sub-structure as per drawing and
Technical Specification
Unit = MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps and wastage tonne 1.05 49279.84 51743.84 M-126
Binding wire kg 6.00 62.52 375.14 M-072
b) Labour for straightening, cutting, bending,
shifting to site, tying and placing in position
Mate day 0.28 195.43 54.72 L-12
Blacksmith day 1.50 247.19 370.79 L-02
Mazdoor day 5.50 187.43 1030.87 L-13
c) Overhead charges @ 0.25 on (a+b) 13393.84
d) Contractor's profit @ 0.1 on (a+b+c) 6696.92
Rate for per MT (a+b+c+d) 73666.10
say 73666.00
13.8 2706 & Providing weep holes in Brick masonry/Plain/
2200 Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full
width of the structure with slope of 1V :20H towards
drawing foce. Complete as per drawing and Technical
Specifications
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per cent ) metre 31.50 50.28 1583.73 M-056

Average length of weep hole is taken as one metre for the


purpose of estimating.
MS clamp each. 30.00 24.33 729.88 M-123
collar for AC pipe (average) taking 10% of above pipe each. 10.00 5.03 50.28 M-056/10
rate
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.05 3447.00 172.35 Item 12.6 (A)
b) Labour
Mate day 0.03 195.43 5.86 L-12
Mason day 0.50 247.19 123.60 L-11
Mazdoor day 0.25 187.43 46.86 L-13
c) Overhead charges @ 0.25 on (a+b) 678.14
d) Contractor's profit @ 0.1 on (a+b+c) 339.07
Cost for 30 m = a+b+c+d 3729.76
Rate per No. (a+b+c+d)/30 124.33
say 124.00
Note 1. In case of stone masonry, the size of the weep hole shall
be 150 mm x 80 mm or circular with 150 mm diameter.
2. For structure in stone masonry, the weep holes shall be
deemed to be included in the item of stone masonry work
and shall not be paid separately.
13.9 710.1.4. Back filling behind abutment, wing wall and return wall
of complete as per drawing and Technical Specification
IRC:78
& 2200
Unit = cum
Taking output = 10 cum
A Granular material
a) Labour
Mate day 0.28 195.43 54.72 L-12
Mazdoor day 7.00 187.43 1312.01 L-13
b) Material
Granular material cum 12.00 156.79 1881.45 M-009
c) Machinery
Plate compactor/power rammer hour 2.50 142.99 357.48 P&M-086

264
RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Water Tanker hour 0.05 111.24 5.56 P&M-060

265
RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
d) Overhead charges @ 0.25 on (a+b+c) 902.81
e) Contractor's profit @ 0.1 on (a+b+c+d) 451.40
Cost for 10 cum of granular backfill = a+b+c+d+e 4965.43
Rate per cum = (a+b+c+d+e)/10 496.54
say 497.00
13.9 B Sandy material
a) Labour
Mate day 0.28 195.43 54.72 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 187.43 1312.01 L-13
b) Material
Sand cum 12.00 111.50 1338.00 M-006
c) Machinery
Plate compactor/power rammer hour 2.50 142.99 357.48 P&M-086
Water Tanker hour 0.06 111.24 6.67 P&M-060
d) Overhead charges @ 0.25 on (a+b+c) 767.22
e) Contractor's profit @ 0.1 on (a+b+c+d) 383.61
Cost for 10 cum of sandy backfill = a+b+c+d+e 4219.71
Rate per cum = (a+b+c+d+e)/10 421.97
say 422.00
13.10 710.1.4. Providing and laying of Filter media with granular
of materials/stone crushed aggregates satisfying the
IRC:78 requirements laid down in clause 2504.2.2. of MoRTH
and specifications to a thickness of not less than 600 mm
2200 with smaller size towards the soil and bigger size
towards the wall and provided over the entire surface
behind abutment, wing wall and return wall to the full
height compacted to a firm condition complete as per
drawing and Technical Specification.

Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 195.43 62.54 L-12
Mazdoor for filling, watering, ramming etc. day 7.00 187.43 1312.01 L-13
Mazdoor (Skilled) day 1.00 218.57 218.57 L-15
b) Material
Filter media of stone aggregate conforming to clause cum 12.00 630.22 7562.58 M-012
2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 111.24 6.67 P&M-060
d) Overhead charges @ 0.25 on (a+b+c) 2290.59
e) Contractor's profit @ 0.1 on (a+b+c+d) 1145.30
cost for 10 cum of Fiter Media = a+b+c+d+e 12598.26
Rate per cum = (a+b+c+d+e)/10 1259.83
say 1260.00
13.11 2000, Supplying, fitting and fixing in position true to line and
1000 & level cast steel rocker bearing conforming to IRC:
2200 83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as
per drawing and Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 195.43 11.73 L-12
Mazdoor (Skilled) day 0.50 218.57 109.29 L-15
Mazdoor day 1.00 187.43 187.43 L-13
b) Material
Cast steel rocker bearing assembly of 250 tonne each. 1.00 55883.28 55883.28 M-065
design load capacity duly painted complete with all its
components as per drawing and specifications
Add 1 per cent of cost of bearing assembly for 558.83
foundation anchorage bolts, lifting arrangements,
grease and other consumables.
c) Overhead charges @ 0.25 on (a+b) 14187.64
d) Contractor's profit @ 0.1 on (a+b+c) 7093.82
cost for 250 tonnes capacity bearing = a+b+c+d 78032.01
Rate per tonne capacity = (a+b+c+d)/250 312.13
say 312.00

266
RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.12 2000 , Supplying, fitting and fixing in position true to line and
1000 & level forged steel roller bearing conforming to IRC:
2200 83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as
per drawing and Technical Specifications.

Unit: one tonne capacity


Considering a 250 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 195.43 11.73 L-12
Mazdoor day 1.00 187.43 187.43 L-13
Mazdoor (Skilled) day 0.50 218.57 109.29 L-15
b) Material
Forged steel roller bearing of 250 tonne design load each. 1.00 37256.21 37256.21 M-067
capacity duly painted complete with all its components
as per drawing and specifications
Add 1 per cent of cost of bearing assembly for 372.56
foundation anchorage bolts, lifting arrangements,
grease and other consumables.
c) Overhead charges @ 0.25 on (a+b) 9484.30
d) Contractor's profit @ 0.1 on (a+b+c) 4742.15
cost for 250 tonnes capacity bearing = a+b+c+d 52163.67
Rate per tonne capacity = (a+b+c+d)/250 208.65
say 209.00
13.13 2000 & Supplying, fitting and fixing in position true to line and
2200 level sliding plate bearing with PTFE surface sliding on
stainless steel complete including all accessories as
per drawing and Technical Specifications and BS:
5400, section 9.1 & 9.2 (for PTFE) and clause 2004
of MoRTH Specifications.

Unit: one tonne capacity


Considering a 80 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 195.43 11.73 L-12
Mazdoor day 1.00 187.43 187.43 L-13
Mazdoor (Skilled) day 0.50 218.57 109.29 L-15
b) Material
PTFE sliding plate bearing assembly of 80 tonnes each. 1.00 #VALUE! #VALUE! M-069
design load capacity duly painted complete with all its
components as per drawing and Technical
Specifications
Add 1 per cent for foundation anchorage bolts and #VALUE!
consumables.

267
RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
c) Overhead charges @ 0.25 on (a+b) #VALUE!
d) Contractor's profit @ 0.1 on (a+b+c) #VALUE!
cost for 80 tonnes capacity bearing = a+b+c+d #VALUE!
Rate per tonne capacity = (a+b+c+d)/80 #VALUE!
say #VALUE!
13.14 2000 & Supplying, fitting and fixing in position true to line and
2200 level elastomeric bearing conforming to IRC: 83 (Part-
II) section IX and clause 2005 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
Unit: one cubic centimetre
Considering an elastomeric bearing of size 500 x 400 x 96
mm for this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel
plates = 4545 cu.cm.
Hence volume of elastometer = 14655 cu.cm.
a) Labour
Mate day 0.06 195.43 11.73 L-12
Mazdoor day 1.00 187.43 187.43 L-13
Mazdoor (Skilled) day 0.50 218.57 109.29 L-15
b) Material
Elastomeric bearing assembly consisting of 7 layers of cucm 19200.00 0.50 9623.13 M-066
elastomer bonded to 6 nos. internal reinforcing steel
laminates by the process of vulcanisation, complete
with all components as per drawing and Technical
Specifications.
Add 1 per cent of cost of bearing assembly for 96.23
foundation anchorage bolts and consumables.
c) Overhead charges @ 0.25 on (a+b) 2506.95
d) Contractor's profit @ 0.1 on (a+b+c) 1253.48
cost for 19200cc of elastomeric bearing = a+b+c+d 13788.23
Rate per cc of elastomeric bearing = (a+b+c+d)/19200 0.72

say 0.72
13.15 2000 & Supplying, fitting and fixing in position true to line and
2200 level sliding plate bearing with stainless steel plate
sliding on stainless steel plate with mild steel matrix
complete including all accessories as per drawing and
Technical Specifications.
Unit: one tonne capacity
Considering the sliding bearing of 80 tonnes design capacity
for this analysis.
a) Labour
Mate day 0.04 195.43 7.82 L-12
Mazdoor day 0.75 187.43 140.57 L-13
Mazdoor (Skilled) day 0.35 218.57 76.50 L-15
b) Material
Supply of sliding plate bearing of 80 tonne design each. 1.00 22579.27 22579.27 M-070
capacity complete as per drawings and Technical
Specifications.
Add 1 per cent of cost of bearing assembly for 225.79
foundation anchorage bolts and consumables.
c) Overhead charges @ 0.25 on (a+b) 5757.49
d) Contractor's profit @ 0.1 on (a+b+c) 2878.74
cost for 80 tonnes of capacity bearing = a+b+c+d 31666.18
Rate per tonne Capacity =(a+b+c+d) / 80 395.83
say 396.00

268
RCD/SOR
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
13.16 2000 & Supplying, fitting and fixing in position true to line and level
2200 POT-PTFE bearing consisting of a metal piston supported by
a disc or unreinforced elastomer confined within a metal
cylinder, sealing rings, dust seals, PTFE surface sliding
against stainless steel mating surface, complete assembly to
be of cast steel/fabricated structural steel, metal and
elastomer elements to be as per IRC: 83 part-I & II
respectively and other parts conforming to BS: 5400, section
9.1 & 9.2 and clause 2006 of MoRTH Specifications
complete as per drawing and approved Technical
Specifications.

Unit: one tonne capacity 387.20


Considering a Pot bearing assembly of 250 tonne capacity
for this analysis.
a) Labour
Mate day 0.08 195.43 15.63 L-12
Mazdoor day 1.50 187.43 281.15 L-13
Mazdoor (Skilled) day 0.50 218.57 109.29 L-15
b) Material
Pot type bearing assembly consisting of a metal piston each. 1.00 31752.36 31752.36 M-068
supported by a disc, PTFE pads providing sliding
surfaces against stainless steel mating together with
cast steel assemblies/fabricated structural steel
assemblies duly painted with all components as per
clause 2006 and complete as per drawings and
Technical Specifications.

Add 1 per cent of cost of bearing assembly for 317.52


foundation anchorage bolts and consumables.
c) Overhead charges @ 0.25 on (a+b) 8118.99
d) Contractor's profit @ 0.1 on (a+b+c) 4059.49
cost for 250 tonnes capacity bearing = a+b+c+d 44654.43
Rate per tonne capacity = (a+b+c+d)/250 178.62
say 179.00

269
CHAPTER-14
SUPER-STRUCTURE
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1 1500 Furnishing and Placing Reinforced/ Prestressed cement
&1600 concrete in super-structure as per drawing and Technical
1700 Specification
A RCC Grade M20
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 5982.46 30630.18 M-081
Coarse sand cum 6.75 209.13 1411.63 M-005
20 mm Aggregate cum 8.10 887.53 7188.96 M-053
10 mm Aggregate cum 5.40 674.15 3640.42 M-051
b) Labour
Mate day 0.86 195.43 168.07 L-12
Mason day 1.50 247.19 370.79 L-11
Mazdoor day 20.00 187.43 3748.60 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009
Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) for 50483.00
15 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 50483.00
cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 10096.60
e) Overhead charges @ 0.25 on (a+b+c+d) 15144.90
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7572.45
Cost for 15 cum = a+b+c+d+e+f 83296.95
Rate per cum = (a+b+c+d+e+f)/15 5553.13
say 5553.00
14.1A (q) Height 5m to 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 50483.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 12620.75
e) Overhead charges @ 0.25 on (a+b+c+d) 15775.94
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7887.97
Cost for 15 cum = a+b+c+d+e+f 86767.66
Rate per cum = (a+b+c+d+e+f)/15 5784.51
say 5785.00
14.1A (r) Height above 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 50483.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 15144.90
e) Overhead charges @ 0.25 on (a+b+c+d) 16406.98
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 8203.49
Cost for 15 cum = a+b+c+d+e+f 90238.36
Rate per cum = (a+b+c+d+e+f)/15 6015.89
say 6016.00
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m

268
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 50483.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 12620.75
e) Overhead charges @ 0.25 on (a+b+c+d) 15775.94
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 7887.97
Cost for 15 cum = a+b+c+d+e+f 86767.66
Rate per cum = (a+b+c+d+e+f)/15 5784.51
say 5785.00
14.1A (q) Height 5m to 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 50483.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 15144.90
e) Overhead charges @ 0.25 on (a+b+c+d) 16406.98
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 8203.49
Cost for 15 cum = a+b+c+d+e+f 90238.36
Rate per cum = (a+b+c+d+e+f)/15 6015.89
say 6016.00
14.1A (r) Height above 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 50483.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 17669.05
e) Overhead charges @ 0.25 on (a+b+c+d) 17038.01
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 8519.01
Cost for 15 cum = a+b+c+d+e+f 93709.07
Rate per cum = (a+b+c+d+e+f)/15 6247.27
say 6247.00
14.1A Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 5982.46 244802.11 M-081
Coarse sand cum 54.00 209.13 11293.04 M-004
20 mm Aggregate cum 64.80 887.53 57511.71 M-053
10 mm Aggregate cum 43.20 674.15 29123.34 M-051
b) Labour
Mate day 0.84 195.43 164.16 L-12
Mason day 3.00 247.19 741.57 L-11
Mazdoor day 18.00 187.43 3373.74 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002
Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080
Loader hour 6.00 1148.00 6888.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 854.55 12818.25 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 4.32 1296.00 Lead =1 km
& P&M-050
Concrete Pump hour 6.00 234.36 1406.16 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for ###
120 cum
For formwork and staging add the following:
14.1A (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 393971.00
cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 78794.20

269
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
e) Overhead charges @ 0.25 on (a+b+c+d) 118191.30
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 59095.65
Cost for 120 cum = a+b+c+d+e+f 650052.15
Rate per cum = (a+b+c+d+e+f)/120 5417.10
say 5417.00
14.1A (q) Height 5m to 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 393971.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 98492.75
e) Overhead charges @ 0.25 on (a+b+c+d) 123115.94
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 61557.97
Cost for 120 cum = a+b+c+d+e+f 677137.66
Rate per cum = (a+b+c+d+e+f)/120 5642.81
say 5643.00
14.1A (r) Height above 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 393971.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 118191.30
e) Overhead charges @ 0.25 on (a+b+c+d) 128040.58
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 64020.29
Cost for 120 cum = a+b+c+d+e+f 704223.16
Rate per cum = (a+b+c+d+e+f)/120 5868.53
say 5869.00
14.1A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 393971.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 98492.75
e) Overhead charges @ 0.25 on (a+b+c+d) 123115.94
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 61557.97
Cost for 120 cum = a+b+c+d+e+f 677137.66
Rate per cum = (a+b+c+d+e+f)/120 5642.81
say 5643.00
14.1A (q) Height 5m to 10m
Case II (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 393971.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 118191.30
e) Overhead charges @ 0.25 on (a+b+c+d) 128040.58
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 64020.29
Cost for 120 cum = a+b+c+d+e+f 704223.16
Rate per cum = (a+b+c+d+e+f)/120 5868.53
say 5869.00
14.1A (r) Height above 10m
Case II (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 393971.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 137889.85
e) Overhead charges @ 0.25 on (a+b+c+d) 132965.21
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 66482.61
Cost for 120 cum = a+b+c+d+e+f 731308.67
Rate per cum = (a+b+c+d+e+f)/120 6094.24
say 6094.00
14.1 B RCC Grade M25
Case I Using Concrete Mixer
Unit = 1 cum

270
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Taking output = 15 cum
a) Material
Cement tonne 5.99 5982.46 35834.91 M-081
Coarse sand cum 6.75 209.13 1411.63 M-005
20 mm Aggregate cum 8.10 887.53 7188.96 M-053
10 mm Aggregate cum 5.40 674.15 3640.42 M-051
b) Labour
Mate day 0.86 195.43 168.07 L-12
Mason day 1.50 247.19 370.79 L-11
Mazdoor day 20.00 187.43 3748.60 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009
Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) for 55688.00
15 cum
For formwork and staging add the following:
14.1B (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 55688.00
cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 11137.60
e) Overhead charges @ 0.25 on (a+b+c+d) 16706.40
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 8353.20
Cost for 15 cum = a+b+c+d+e+f 91885.20
Rate per cum = (a+b+c+d+e+f)/15 6125.68
say 6126.00
14.1B (q) Height 5m to 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 55688.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 13922.00
e) Overhead charges @ 0.25 on (a+b+c+d) 17402.50
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 8701.25
Cost for 15 cum = a+b+c+d+e+f 95713.75
Rate per cum = (a+b+c+d+e+f)/15 6380.92
say 6381.00
14.1B (r) Height above 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 55688.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 16706.40
e) Overhead charges @ 0.25 on (a+b+c+d) 18098.60
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 9049.30
Cost for 15 cum = a+b+c+d+e+f 99542.30
Rate per cum = (a+b+c+d+e+f)/15 6636.15
say 6636.00
14.1B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 55688.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 13922.00
e) Overhead charges @ 0.25 on (a+b+c+d) 17402.50
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 8701.25
Cost for 15 cum = a+b+c+d+e+f 95713.75
Rate per cum = (a+b+c+d+e+f)/15 6380.92
say 6381.00

271
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1B (q) Height 5m to 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 55688.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 16706.40
e) Overhead charges @ 0.25 on (a+b+c+d) 18098.60
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 9049.30
Cost for 15 cum = a+b+c+d+e+f 99542.30
Rate per cum = (a+b+c+d+e+f)/15 6636.15
say 6636.00
14.1B (r) Height above 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 55688.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 19490.80
e) Overhead charges @ 0.25 on (a+b+c+d) 18794.70
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 9397.35
Cost for 15 cum = a+b+c+d+e+f 103370.85
Rate per cum = (a+b+c+d+e+f)/15 6891.39
say 6891.00
14.1B Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.95 5982.46 286858.77 M-081
Coarse sand cum 54.20 209.13 11334.86 M-004
20 mm Aggregate cum 64.80 887.53 57511.71 M-053
10 mm Aggregate cum 43.20 674.15 29123.34 M-051
b) Labour
Mate day 0.84 195.43 164.16 L-12
Mason day 3.00 247.19 741.57 L-11
Mazdoor day 18.00 187.43 3373.74 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002
Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080
Loader hour 6.00 1148.00 6888.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 854.55 12818.25 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 4.32 1296.00 Lead =1 km
& P&M-050
Concrete Pump hour 6.00 234.36 1406.16 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for ###
120 cum
For formwork and staging add the following:
14.1B (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 436069.00
cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 87213.80
e) Overhead charges @ 0.25 on (a+b+c+d) 130820.70
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 65410.35
Cost for 120 cum = a+b+c+d+e+f 719513.85
Rate per cum = (a+b+c+d+e+f)/120 5995.95
say 5996.00
14.1B (q) Height 5m to 10m
Case II (i)

272
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 436069.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 109017.25
e) Overhead charges @ 0.25 on (a+b+c+d) 136271.56
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 68135.78
Cost for 120 cum = a+b+c+d+e+f 749493.59
Rate per cum = (a+b+c+d+e+f)/120 6245.78
say 6246.00
14.1B (r) Height above 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum 436069.00

d) Formwork and staging 30 per cent of (a+b+c) 30.00 130820.70


e) Overhead charges @ 0.25 on (a+b+c+d) 141722.43
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 70861.21
Cost for 120 cum = a+b+c+d+e+f 779473.34
Rate per cum = (a+b+c+d+e+f)/120 6495.61
say 6496.00
14.1B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 436069.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 109017.25
e) Overhead charges @ 0.25 on (a+b+c+d) 136271.56
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 68135.78
Cost for 120 cum = a+b+c+d+e+f 749493.59
Rate per cum = (a+b+c+d+e+f)/120 6245.78
say 6246.00
14.1B (q) Height 5m to 10m
Case II (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 436069.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 130820.70
e) Overhead charges @ 0.25 on (a+b+c+d) 141722.43
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 70861.21
Cost for 120 cum = a+b+c+d+e+f 779473.34
Rate per cum = (a+b+c+d+e+f)/120 6495.61
say 6496.00
14.1B (r) Height above 10m
Case II (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 436069.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 152624.15
e) Overhead charges @ 0.25 on (a+b+c+d) 147173.29
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 73586.64
Cost for 120 cum = a+b+c+d+e+f 809453.08
Rate per cum = (a+b+c+d+e+f)/120 6745.44
say 6745.00
14.1 C RCC Grade M 30
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 5982.46 36492.98 M-081
Coarse sand cum 6.75 209.13 1411.63 M-005
20 mm Aggregate cum 8.10 887.53 7188.96 M-053
10 mm Aggregate cum 5.40 674.15 3640.42 M-051

273
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
b) Labour
Mate day 0.90 195.43 175.89 L-12
Mason day 1.50 247.19 370.79 L-11
Mazdoor day 21.00 187.43 3936.03 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009
Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) for 56541.00
15 cum
For formwork and staging add the following:
14.1C (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 56541.00
cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 11308.20
e) Overhead charges @ 0.25 on (a+b+c+d) 16962.30
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 8481.15
Cost for 15 cum = a+b+c+d+e+f 93292.65
Rate per cum = (a+b+c+d+e+f)/15 6219.51
say 6220.00
14.1C (q) Height 5m to 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 56541.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 14135.25
e) Overhead charges @ 0.25 on (a+b+c+d) 17669.06
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 8834.53
Cost for 15 cum = a+b+c+d+e+f 97179.84
Rate per cum = (a+b+c+d+e+f)/15 6478.66
say 6479.00
14.1C (r) Height above 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 56541.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 16962.30
e) Overhead charges @ 0.25 on (a+b+c+d) 18375.83
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 9187.91
Cost for 15 cum = a+b+c+d+e+f 101067.04
Rate per cum = (a+b+c+d+e+f)/15 6737.80
say 6738.00
14.1C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 56541.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 14135.25
e) Overhead charges @ 0.25 on (a+b+c+d) 17669.06
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 8834.53
Cost for 15 cum = a+b+c+d+e+f 97179.84
Rate per cum = (a+b+c+d+e+f)/15 6478.66
say 6479.00
14.1C (q) Height 5m to 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 56541.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 16962.30
e) Overhead charges @ 0.25 on (a+b+c+d) 18375.83
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 9187.91

274
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cost for 15 cum = a+b+c+d+e+f 101067.04
Rate per cum = (a+b+c+d+e+f)/15 6737.80
say 6738.00
14.1C (r) Height above 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 56541.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 19789.35
e) Overhead charges @ 0.25 on (a+b+c+d) 19082.59
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 9541.29
Cost for 15 cum = a+b+c+d+e+f 104954.23
Rate per cum = (a+b+c+d+e+f)/15 6996.95
say 6997.00
14.1C Case II Using Batching Plant, Transit Mixer and Concrete Pump.

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 5982.46 291884.04 M-081
Coarse sand cum 54.60 209.13 11418.51 M-004
20 mm Aggregate cum 64.80 887.53 57511.71 M-053
10 mm Aggregate cum 43.20 674.15 29123.34 M-051
b) Labour
Mate day 0.88 195.43 171.98 L-12
Mason day 3.00 247.19 741.57 L-11
Mazdoor day 19.00 187.43 3561.17 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002
Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080
Loader hour 6.00 1148.00 6888.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 854.55 12818.25 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 4.32 1296.00 Lead =1 km
& P&M-050
Concrete Pump hour 6.00 234.36 1406.16 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for ###
120 cum
For formwork and staging add the following:
14.1C (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 441373.00
cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 88274.60
e) Overhead charges @ 0.25 on (a+b+c+d) 132411.90
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 66205.95
Cost for 120 cum = a+b+c+d+e+f 728265.45
Rate per cum = (a+b+c+d+e+f)/120 6068.88
say 6069.00
14.1C (q) Height 5m to 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 441373.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 110343.25
e) Overhead charges @ 0.25 on (a+b+c+d) 137929.06
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 68964.53
Cost for 120 cum = a+b+c+d+e+f 758609.84
Rate per cum = (a+b+c+d+e+f)/120 6321.75
say 6322.00

275
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1C (r) Height above 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 441373.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 132411.90
e) Overhead charges @ 0.25 on (a+b+c+d) 143446.23
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 71723.11
Cost for 120 cum = a+b+c+d+e+f 788954.24
Rate per cum = (a+b+c+d+e+f)/120 6574.62
say 6575.00
14.1C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 441373.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 110343.25
e) Overhead charges @ 0.25 on (a+b+c+d) 137929.06
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 68964.53
Cost for 120 cum = a+b+c+d+e+f 758609.84
Rate per cum = (a+b+c+d+e+f)/120 6321.75
say 6322.00
14.1C (q) Height 5m to 10m
Case II (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 441373.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 132411.90
e) Overhead charges @ 0.25 on (a+b+c+d) 143446.23
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 71723.11
Cost for 120 cum = a+b+c+d+e+f 788954.24
Rate per cum = (a+b+c+d+e+f)/120 6574.62
say 6575.00
14.1C (r) Height above 10m
Case II (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 441373.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 154480.55
e) Overhead charges @ 0.25 on (a+b+c+d) 148963.39
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 74481.69
Cost for 120 cum = a+b+c+d+e+f 819298.63
Rate per cum = (a+b+c+d+e+f)/120 6827.49
say 6827.00
14.1 D RCC/PSC Grade M35
Case I Using Concrete Mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 5982.46 37868.95 M-081
Coarse sand cum 6.75 209.13 1411.63 M-005
20 mm Aggregate cum 8.10 887.53 7188.96 M-053
10 mm Aggregate cum 5.40 674.15 3640.42 M-051
b) Labour
Mate day 0.90 195.43 175.89 L-12
Mason day 1.50 247.19 370.79 L-11
Mazdoor day 21.00 187.43 3936.03 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009
Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) for 57917.00
15 cum

276
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 57917.00
cum
d) Formwork and staging 18 per cent of (a+b+c) 18.00 10425.06
e) Overhead charges @ 0.25 on (a+b+c+d) 17085.52
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 8542.76
Cost for 15 cum = a+b+c+d+e+f 93970.33
Rate per cum = (a+b+c+d+e+f)/15 6264.69
say 6265.00
14.1D (q) Height 5m to 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 57917.00
cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 13320.91
e) Overhead charges @ 0.25 on (a+b+c+d) 17809.48
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 8904.74
Cost for 15 cum = a+b+c+d+e+f 97952.13
Rate per cum = (a+b+c+d+e+f)/15 6530.14
say 6530.00
14.1D (r) Height above 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 57917.00
cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 16216.76
e) Overhead charges @ 0.25 on (a+b+c+d) 18533.44
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 9266.72
Cost for 15 cum = a+b+c+d+e+f 101933.92
Rate per cum = (a+b+c+d+e+f)/15 6795.59
say 6796.00
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 57917.00
cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 13320.91
e) Overhead charges @ 0.25 on (a+b+c+d) 17809.48
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 8904.74
Cost for 15 cum = a+b+c+d+e+f 97952.13
Rate per cum = (a+b+c+d+e+f)/15 6530.14
say 6530.00
14.1D (q) Height 5m to 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 57917.00
cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 16216.76
e) Overhead charges @ 0.25 on (a+b+c+d) 18533.44
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 9266.72
Cost for 15 cum = a+b+c+d+e+f 101933.92
Rate per cum = (a+b+c+d+e+f)/15 6795.59
say 6796.00
14.1D (r) Height above 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 57917.00
cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 19112.61
e) Overhead charges @ 0.25 on (a+b+c+d) 19257.40
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 9628.70

277
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cost for 15 cum = a+b+c+d+e+f 105915.71
Rate per cum = (a+b+c+d+e+f)/15 7061.05
say 7061.00
14.1D (iii) For box girder and balanced cantilever, 38-58 per cent of
Case I cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 57917.00
cum
d) Formwork and staging 38 per cent of (a+b+c) 38.00 22008.46
e) Overhead charges @ 0.25 on (a+b+c+d) 19981.37
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 9990.68
Cost for 15 cum = a+b+c+d+e+f 109897.51
Rate per cum = (a+b+c+d+e+f)/15 7326.50
say 7327.00
14.1D (q) Height 5m to 10m
Case I (iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 57917.00
cum
d) Formwork and staging 48 per cent of (a+b+c) 48.00 27800.16
e) Overhead charges @ 0.25 on (a+b+c+d) 21429.29
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 10714.65
Cost for 15 cum = a+b+c+d+e+f 117861.10
Rate per cum = (a+b+c+d+e+f)/15 7857.41
say 7857.00
14.1D (r) Height above 10m
Case I (iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 57917.00
cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 33591.86
e) Overhead charges @ 0.25 on (a+b+c+d) 22877.22
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 11438.61
Cost for 15 cum = a+b+c+d+e+f 125824.68
Rate per cum = (a+b+c+d+e+f)/15 8388.31
say 8388.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 5982.46 302951.58 M-081
Coarse sand cum 54.00 209.13 11293.04 M-004
20 mm Aggregate cum 64.80 887.53 57511.71 M-053
10 mm Aggregate cum 43.20 674.15 29123.34 M-051
b) Labour
Mate day 0.88 195.43 171.98 L-12
Mason day 3.00 247.19 741.57 L-11
Mazdoor day 19.00 187.43 3561.17 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002
Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080
Loader hour 6.00 1148.00 6888.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 854.55 12818.25 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 4.32 1296.00 Lead =1 km
& P&M-050
Concrete Pump hour 6.00 234.36 1406.16 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for ###
120 cum
For formwork and staging add the following:

278
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1D (i) For solid slab super-structure, 18-28 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 452315.00
cum
d) Formwork and staging 18 per cent of (a+b+c) 18.00 81416.70
e) Overhead charges @ 0.25 on (a+b+c+d) 133432.93
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 66716.46
Cost for 120 cum = a+b+c+d+e+f 733881.09
Rate per cum = (a+b+c+d+e+f)/120 6115.68
say 6116.00
14.1D (q) Height 5m to 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 452315.00
cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 104032.45
e) Overhead charges @ 0.25 on (a+b+c+d) 139086.86
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 69543.43
Cost for 120 cum = a+b+c+d+e+f 764977.74
Rate per cum = (a+b+c+d+e+f)/120 6374.81
say 6375.00
14.1D (r) Height above 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 452315.00
cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 126648.20
e) Overhead charges @ 0.25 on (a+b+c+d) 144740.80
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 72370.40
Cost for 120 cum = a+b+c+d+e+f 796074.40
Rate per cum = (a+b+c+d+e+f)/120 6633.95
say 6634.00
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 452315.00
cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 104032.45
e) Overhead charges @ 0.25 on (a+b+c+d) 139086.86
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 69543.43
Cost for 120 cum = a+b+c+d+e+f 764977.74
Rate per cum = (a+b+c+d+e+f)/120 6374.81
say 6375.00
14.1D (q) Height 5m to 10m
Case II (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 452315.00
cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 126648.20
e) Overhead charges @ 0.25 on (a+b+c+d) 144740.80
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 72370.40
Cost for 120 cum = a+b+c+d+e+f 796074.40
Rate per cum = (a+b+c+d+e+f)/120 6633.95
say 6634.00
14.1D (r) Height above 10m
Case II (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 452315.00
cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 149263.95
e) Overhead charges @ 0.25 on (a+b+c+d) 150394.74
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 75197.37
Cost for 120 cum = a+b+c+d+e+f 827171.06

279
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per cum = (a+b+c+d+e+f)/120 6893.09
say 6893.00
14.1D (iii) For box girder and balanced cantilever, 38-58 per cent of
Case II cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 452315.00
cum
d) Formwork and staging 38 per cent of (a+b+c) 38.00 171879.70
e) Overhead charges @ 0.25 on (a+b+c+d) 156048.68
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 78024.34
Cost for 120 cum = a+b+c+d+e+f 858267.71
Rate per cum = (a+b+c+d+e+f)/120 7152.23
say 7152.00
14.1D (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 452315.00
cum
d) Formwork and staging 48 per cent of (a+b+c) 48.00 217111.20
e) Overhead charges @ 0.25 on (a+b+c+d) 167356.55
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 83678.28
Cost for 120 cum = a+b+c+d+e+f 920461.03
Rate per cum = (a+b+c+d+e+f)/120 7670.51
say 7671.00
14.1D (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 452315.00
cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 262342.70
e) Overhead charges @ 0.25 on (a+b+c+d) 178664.43
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 89332.21
Cost for 120 cum = a+b+c+d+e+f 982654.34
Rate per cum = (a+b+c+d+e+f)/120 8188.79
say 8189.00
14.1 E PSC Grade M-40
Case 1 Using concrete mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.45 5982.46 38586.84 M-081
Coarse sand cum 6.75 209.13 1411.63 M-005
20 mm Aggregate cum 8.10 887.53 7188.96 M-053
10 mm Aggregate cum 5.40 674.15 3640.42 M-051
Admixture @ 0.4 per cent of cement kg 25.80 112.77 2909.49 M-180
b) Labour
Mate day 0.96 195.43 187.61 L-12
Mason day 2.00 247.19 494.38 L-11
Mazdoor day 22.00 187.43 4123.46 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 211.68 1270.08 P&M-009
Generator 33 KVA hour 6.00 342.36 2054.16 P&M-079
Basic Cost of Labour, Material & Machinery (a+b+c) for 61868.00
15 cum
For formwork and staging add the following:
14.1E (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m

280
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 61868.00
cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 12373.60
e) Overhead charges @ 0.25 on (a+b+c+d) 18560.40
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 9280.20
Cost for 15 cum = a+b+c+d+e+f 102082.20
Rate per cum = (a+b+c+d+e+f)/15 6805.48
say 6805.00
14.1E (q) Height 5m to 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 61868.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 15467.00
e) Overhead charges @ 0.25 on (a+b+c+d) 19333.75
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 9666.88
Cost for 15 cum = a+b+c+d+e+f 106335.63
Rate per cum = (a+b+c+d+e+f)/15 7089.04
say 7089.00
14.1E (r) Height above 10m
Case I (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 61868.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 18560.40
e) Overhead charges @ 0.25 on (a+b+c+d) 20107.10
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 10053.55
Cost for 15 cum = a+b+c+d+e+f 110589.05
Rate per cum = (a+b+c+d+e+f)/15 7372.60
say 7373.00
14.1E (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 61868.00
cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 15467.00
e) Overhead charges @ 0.25 on (a+b+c+d) 19333.75
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 9666.88
Cost for 15 cum = a+b+c+d+e+f 106335.63
Rate per cum = (a+b+c+d+e+f)/15 7089.04
say 7089.00
14.1E (q) Height 5m to 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 61868.00
cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 18560.40
e) Overhead charges @ 0.25 on (a+b+c+d) 20107.10
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 10053.55
Cost for 15 cum = a+b+c+d+e+f 110589.05
Rate per cum = (a+b+c+d+e+f)/15 7372.60
say 7373.00
14.1E (r) Height above 10m
Case I (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 15 61868.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 21653.80
e) Overhead charges @ 0.25 on (a+b+c+d) 20880.45
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 10440.23
Cost for 15 cum = a+b+c+d+e+f 114842.48
Rate per cum = (a+b+c+d+e+f)/15 7656.17
say 7656.00

281
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1E Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 5982.46 308694.74 M-081
Coarse sand cum 54.00 209.13 11293.04 M-004
20 mm Aggregate cum 64.80 887.53 57511.71 M-053
10 mm Aggregate cum 43.20 674.15 29123.34 M-051
Admixture @ 0.4 per cent of cement kg 206.40 112.77 23275.94 M-180
b) Labour
Mate day 0.94 195.43 183.70 L-12
Mason day 3.50 247.19 865.17 L-11
Mazdoor day 20.00 187.43 3748.60 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002
Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080
Loader hour 6.00 1148.00 6888.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 854.55 12818.25 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 4.32 1296.00 Lead =1 km
& P&M-050
Concrete Pump hour 6.00 234.36 1406.16 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for ###
120 cum
For formwork and staging add the following:
14.1E (i) For solid/voided slab super-structure, 18-28 per cent of
Case II (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum 481657.00

d) Formwork and staging 18 per cent of (a+b+c) 18.00 86698.26


e) Overhead charges @ 0.25 on (a+b+c+d) 142088.82
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 71044.41
Cost for 15 cum = a+b+c+d+e+f 781488.48
Rate per cum = (a+b+c+d+e+f)/120 6512.40
say 6512.00
14.1E (q) Height 5m to 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 481657.00
cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 110781.11
e) Overhead charges @ 0.25 on (a+b+c+d) 148109.53
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 74054.76
Cost for 120 cum = a+b+c+d+e+f 814602.40
Rate per cum = (a+b+c+d+e+f)/120 6788.35
say 6788.00
14.1E (r) Height above 10m
Case II (i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 481657.00
cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 134863.96
e) Overhead charges @ 0.25 on (a+b+c+d) 154130.24
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 77065.12
Cost for 120 cum = a+b+c+d+e+f 847716.32
Rate per cum = (a+b+c+d+e+f)/120 7064.30
say 7064.00
14.1E (ii) For T-beam & slab inclduing launching of precast girders
Case II by launching truss upto 40 m, 23-33 per cent of cost of
concrete (a+b+c)
282
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 481657.00
cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 110781.11
e) Overhead charges @ 0.25 on (a+b+c+d) 148109.53
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 74054.76
Cost for 120 cum = a+b+c+d+e+f 814602.40
Rate per cum = (a+b+c+d+e+f)/120 6788.35
say 6788.00
14.1E (q) Height 5m to 10m
Case II (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 481657.00
cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 134863.96
e) Overhead charges @ 0.25 on (a+b+c+d) 154130.24
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 77065.12
Cost for 120 cum = a+b+c+d+e+f 847716.32
Rate per cum = (a+b+c+d+e+f)/120 7064.30
say 7064.00
14.1E (r) Height above 10m
Case II (ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 481657.00
cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 158946.81
e) Overhead charges @ 0.25 on (a+b+c+d) 160150.95
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 80075.48
Cost for 120 cum = a+b+c+d+e+f 880830.24
Rate per cum = (a+b+c+d+e+f)/120 7340.25
say 7340.00
14.1E (iii) For cast-in-situ box girder, segment construction and
Case II balanced cantilever, 38-58 per cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 481657.00
cum
d) Formwork and staging 38 per cent of (a+b+c) 38.00 183029.66
e) Overhead charges @ 0.25 on (a+b+c+d) 166171.67
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 83085.83
Cost for 120 cum = a+b+c+d+e+f 913944.16
Rate per cum = (a+b+c+d+e+f)/120 7616.20
say 7616.00
14.1E (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 481657.00
cum
d) Formwork and staging 48 per cent of (a+b+c) 48.00 231195.36
e) Overhead charges @ 0.25 on (a+b+c+d) 178213.09
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 89106.55
Cost for 120 cum = a+b+c+d+e+f 980172.00
Rate per cum = (a+b+c+d+e+f)/120 8168.10
say 8168.00
14.1E (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 481657.00
cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 279361.06
e) Overhead charges @ 0.25 on (a+b+c+d) 190254.52
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 95127.26
Cost for 120 cum = a+b+c+d+e+f 1046399.83

283
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per cum = (a+b+c+d+e+f)/120 8720.00
say 8720.00
14.1F F PSC Grade M-45
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 55.80 5982.46 333821.05 M-081
Coarse sand cum 54.00 209.13 11293.04 M-004
20 mm Aggregate cum 64.80 887.53 57511.71 M-053
10 mm Aggregate cum 43.20 674.15 29123.34 M-051
Admixture @ 0.4 per cent of cement kg 223.20 112.77 25170.50 M-180
b) Labour
Mate day 0.94 195.43 183.70 L-12
Mason day 3.50 247.19 865.17 L-11
Mazdoor day 20.00 187.43 3748.60 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002
Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080
Loader hour 6.00 1148.00 6888.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 854.55 12818.25 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 4.32 1296.00 Lead =1 km
& P&M-050
Concrete Pump hour 6.00 234.36 1406.16 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for ###
120 cum
For formwork and staging add the following:
14.1F (i) For solid slab/voided slab super-structure, 16-26 per cent
of cost of concrete (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 508678.00
cum
d) Formwork and staging 16 per cent of (a+b+c) 16.00 81388.48
e) Overhead charges @ 0.25 on (a+b+c+d) 147516.62
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 73758.31
Cost for 120 cum = a+b+c+d+e+f 811341.41
Rate per cum = (a+b+c+d+e+f)/120 6761.18
say 6761.00
14.1F (i) (q) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 508678.00
cum
d) Formwork and staging 21 per cent of (a+b+c) 21.00 106822.38
e) Overhead charges @ 0.25 on (a+b+c+d) 153875.10
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 76937.55
Cost for 120 cum = a+b+c+d+e+f 846313.02
Rate per cum = (a+b+c+d+e+f)/120 7052.61
say 7053.00
14.1F (i) (r) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 508678.00
cum
d) Formwork and staging 26 per cent of (a+b+c) 26.00 132256.28
e) Overhead charges @ 0.25 on (a+b+c+d) 160233.57
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 80116.79
Cost for 120 cum = a+b+c+d+e+f 881284.64
Rate per cum = (a+b+c+d+e+f)/120 7344.04
say 7344.00

284
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1F (ii) For T-beam & slab including launching of precast girders
by launching truss upto 40 m span, 21-31 per cent of cost
of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 508678.00
cum
d) Formwork and staging 21 per cent of (a+b+c) 21.00 106822.38
e) Overhead charges @ 0.25 on (a+b+c+d) 153875.10
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 76937.55
Cost for 120 cum = a+b+c+d+e+f 846313.02
Rate per cum = (a+b+c+d+e+f)/120 7052.61
say 7053.00
14.1F (ii) (q) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 508678.00
cum
d) Formwork and staging 26 per cent of (a+b+c) 26.00 132256.28
e) Overhead charges @ 0.25 on (a+b+c+d) 160233.57
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 80116.79
Cost for 120 cum = a+b+c+d+e+f 881284.64
Rate per cum = (a+b+c+d+e+f)/120 7344.04
say 7344.00
14.1F (ii) (r) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 508678.00
cum
d) Formwork and staging 31 per cent of (a+b+c) 31.00 157690.18
e) Overhead charges @ 0.25 on (a+b+c+d) 166592.05
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 83296.02
Cost for 120 cum = a+b+c+d+e+f 916256.25
Rate per cum = (a+b+c+d+e+f)/120 7635.47
say 7635.00
14.1F (iii) For cast-in-situ box girder, segmental construction and
balanced cantilever, 36-56 per cent of cost of concrete.

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120 508678.00
cum
d) Formwork and staging 36 per cent of (a+b+c) 36.00 183124.08
e) Overhead charges @ 0.25 on (a+b+c+d) 172950.52
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 86475.26
Cost for 120 cum = a+b+c+d+e+f 951227.86
Rate per cum = (a+b+c+d+e+f)/120 7926.90
say 7927.00
14.1F (iii) (q) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 508678.00
cum
d) Formwork and staging 46 per cent of (a+b+c) 46.00 233991.88
e) Overhead charges @ 0.25 on (a+b+c+d) 185667.47
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 92833.74
Cost for 120 cum = a+b+c+d+e+f 1021171.09
Rate per cum = (a+b+c+d+e+f)/120 8509.76
say 8510.00
14.1F (iii) (r) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 508678.00
cum
d) Formwork and staging 56 per cent of (a+b+c) 56.00 284859.68
e) Overhead charges @ 0.25 on (a+b+c+d) 198384.42
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 99192.21
Cost for 120 cum = a+b+c+d+e+f 1091114.31

285
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per cum = (a+b+c+d+e+f)/120 9092.62
say 9093.00
14.1 G PSC Grade M-50
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 58.80 5982.46 351768.42 M-081
Coarse sand cum 54.00 209.13 11293.04 M-004
20 mm Aggregate cum 64.80 887.53 57511.71 M-053
10 mm Aggregate cum 43.20 674.15 29123.34 M-051
Admixture @ 0.4 per cent of cement kg 235.20 112.77 26523.75 M-180
b) Labour
Mate day 0.94 195.43 183.70 L-12
Mason day 3.50 247.19 865.17 L-11
Mazdoor day 20.00 187.43 3748.60 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002
Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080
Loader hour 6.00 1148.00 6888.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 854.55 12818.25 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 4.32 1296.00 Lead =1 km
& P&M-050
Concrete Pump hour 6.00 234.36 1406.16 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for ###
120 cum
For formwork and staging add the following:
14.1G (i) For cast-in-situ box girder, segmental construction and
balanced cantilever, 35-55 per cent of cost of concrete

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120 527979.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 184792.65
e) Overhead charges @ 0.25 on (a+b+c+d) 178192.91
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 89096.46
Cost for 120 cum = a+b+c+d+e+f 980061.02
Rate per cum = (a+b+c+d+e+f)/120 8167.18
say 8167.00
14.1G (i) (q) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 527979.00
cum
d) Formwork and staging 45 per cent of (a+b+c) 45.00 237590.55
e) Overhead charges @ 0.25 on (a+b+c+d) 191392.39
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 95696.19
Cost for 120 cum = a+b+c+d+e+f 1052658.13
Rate per cum = (a+b+c+d+e+f)/120 8772.15
say 8772.00
14.1G (i) (r) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 527979.00
cum
d) Formwork and staging 55 per cent of (a+b+c) 55.00 290388.45
e) Overhead charges @ 0.25 on (a+b+c+d) 204591.86
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 102295.93
Cost for 120 cum = a+b+c+d+e+f 1125255.24
Rate per cum = (a+b+c+d+e+f)/120 9377.13
say 9377.00

286
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.1 H PSC Grade M- 55
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 63.50 5982.46 379885.96 M-081
Coarse sand cum 54.00 209.13 11293.04 M-004
20 mm Aggregate cum 64.80 887.53 57511.71 M-053
10 mm Aggregate cum 43.20 674.15 29123.34 M-051
Admixture @ 0.4 per cent of cement kg 254.00 112.77 28643.85 M-180
b) Labour
Mate day 0.94 195.43 183.70 L-12
Mason day 3.50 247.19 865.17 L-11
Mazdoor day 20.00 187.43 3748.60 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2457.00 14742.00 P&M-002
Generator 100 KVA hour 6.00 1635.00 9810.00 P&M-080
Loader hour 6.00 1148.00 6888.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 854.55 12818.25 P&M-049
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 4.32 1296.00 Lead =1 km
& P&M-050
Concrete Pump hour 6.00 234.36 1406.16 P&M-007
Basic Cost of Labour, Material & Machinery (a+b+c) for ###
120 cum
For formwork and staging add the following:
14.1H (i) For cast-in-situ box girder, segmental construction and
balanced cantilever, 35-55 per cent of cost of concrete

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120 558216.00
cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 195375.60
e) Overhead charges @ 0.25 on (a+b+c+d) 188397.90
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 94198.95
Cost for 120 cum = a+b+c+d+e+f 1036188.45
Rate per cum = (a+b+c+d+e+f)/120 8634.90
say 8635.00
14.1H (i) (q) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 558216.00
cum
d) Formwork and staging 45 per cent of (a+b+c) 45.00 251197.20
e) Overhead charges @ 0.25 on (a+b+c+d) 202353.30
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 101176.65
Cost for 120 cum = a+b+c+d+e+f 1112943.15
Rate per cum = (a+b+c+d+e+f)/120 9274.53
say 9275.00
14.1H (i) (r) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c) for 120 558216.00
cum
d) Formwork and staging 55 per cent of (a+b+c) 55.00 307018.80
e) Overhead charges @ 0.25 on (a+b+c+d) 216308.70
f) Contractor's profit @ 0.1 on (a+b+c+d+e) 108154.35
Cost for 120 cum = a+b+c+d+e+f 1189697.85
Rate per cum = (a+b+c+d+e+f)/120 9914.15
say 9914.00

287
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note 1.Where ever concrete is carried out using batching plant, transit
mixer, concrete pump, admixers conforming IS: 9103 @ 0.4 per
cent of weight of cement may be added for achieving desired
slump of concrete.
2. Cement provided for various components of the super
structure is for estimating purpose only. Actual quantity of cement
will be as per approved mix design. Similarly, the provision for
coarse and fine aggregates is for estimating purpose and the
exact quantity shall be as per the mix design.
3. The items like needle and surface vibrators are part of minor T
& P which is already covered under the overhead charges. As
such these items have not been added separately in the rate
analysis.
14.2 1600 Supplying, fitting and placing HYSD bar reinforcement in
super-structure complete as per drawing and technical
specifications
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent for laps and wastage tonne 1.05 44187.50 46396.88 M-082
Binding wire Kg 8.00 62.52 500.19 M-072
b) Labour for cutting, bending, tying and placing in
position
Mate day 0.44 195.43 85.99 L-12
Blacksmith day 3.00 247.19 741.57 L-02
Mazdoor day 8.00 187.43 1499.44 L-13
Basic Cost of Labour & Material (a+b) 49225.00
c) Overhead charges @ 0.25 on (a+b) 12306.02
d) Contractor's profit @ 0.1 on (a+b+c) 6153.01
Rate per MT = a+b+c+d 67683.09
say 67683.00
14.3 1800 High tensile steel wires/strands including all accessories
for stressing, stressing operations and grouting complete
as per drawing and Technical Specifications

Unit = 1 MT
Taking output = 0.377 MT
Details of cost for 12T13 strand 40 m long cable (weight = 0.377
MT)
a) Material
H.T. Strand @ 9.42 kg/m including 2 per cent for wastage tonne 0.385 62418.78 24031.23 M-119
and extra length for jacking
Sheathing duct ID 66 mm along with 5 per cent extra metre 42.00 61.80 2595.56 M-165
length 40 x 1.05 = 42 m.
Tube anchorage set complete with bearing plate, each 2.00 34.35 68.71 M-187
permanent wedges etc
Cement for grouting including 3 per cent wastage @ 3.00 tonne 0.125 5982.46 747.81 M-081
kg/m = 3 x 1.03 x 40 = 123.60 kg (say, = 125 kg)
Add 0.50 per cent cost of material for Spacers, Insulation 137.22
tape and miscellaneous items
b) Labour
i) For making and fixing cables, anchorages
Mate day 0.16 195.43 31.27 L-12
Blacksmith day 1.00 247.19 247.19 L-02
Mazdoor day 3.00 187.43 562.29 L-13
ii) For prestressing
Mate/Supervisor day 0.05 195.43 9.77 L-12
Prestressing operator / Fitter day 0.25 251.19 62.80 L-08
Mazdoor day 1.00 187.43 187.43 L-13
iii) For grouting
Mate/Supervisor day 0.05 195.43 9.77 L-12
Mason day 0.25 247.19 61.80 L-11

288
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor day 1.00 187.43 187.43 L-13
c) Machinery
Stressing jack with pump hour 2.50 116.10 290.25 P&M-040
Grouting pump with agitator hour 1.00 112.77 112.77 M-111
Generator 33 KVA. hour 3.50 342.36 1198.26 P&M-079
d) Overhead charges @ 0.25 on (a+b+c) 7635.39
e) Contractor's profit @ 0.1 on (a+b+c+d) 3817.69
Cost for 0.377 MT (a+b+c+d+e) 41994.63
Rate per MT = (a+b+c+d+e)/0.377 111391.58
say 111392.00
Note Cost of HT steel has been taken for delivery at site. Hence
carriage has not been considered.
14.4 2702 Providing and laying Cement concrete wearing coat M-30
grade including reinforcement complete as per drawing
and Technical Specifications
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer relevant item of cum 1.00 3678.00 3678.00 Item 14.1(C)
concrete in Item 14.1 excluding formwork
HYSD bar reinforcement Rate as per item No tonne 0.075 49225.00 3691.88 Item 14.2 A
14.2(Excluding OH & CP)
DIR used item
b) Labour
Mazdoor for cleaning deck slab concrete surface. day 0.15 187.43 28.11 L-13
c) Overhead charges @ 0.25 on (a+b) 1849.50
d) Contractor's profit @ 0.1 on (a+b+c) 924.75
Rate per cum (a+b+c+d) 10172.24
say 10172.00
14.5 515 & Mastic Asphalt
2702
Providing and laying 12 mm thick mastic asphalt wearing
course on top of deck slab excluding prime coat with
paving grade bitumen meeting the requirements given in
table 500-29, prepared by using mastic cooker and laid to
required level and slope after cleaning the surface,
including providing antiskid surface with bitumen
precoated fine grained hard stone chipping of 9.5 mm
nominal size at the rate of 0.005cum per 10 sqm and at an
approximate spacing of 10 cm center to center in both
directions, pressed into surface when the temperature of
surfaces not less than 100 deg. C, protruding 1 mm to 4
mm over mastic surface, all complete as per clause 515.

Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum)
assuming a density of 2.3 tonnes/cum.
a) Labour
Mate day 0.49 195.43 95.76 L-12
Mazdoor day 11.00 187.43 2061.73 L-13
Mazdoor (Skilled) day 1.25 218.57 273.21 L-15
b) Machinery

289
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mechanical broom @ 1250 sqm per hour hour 0.06 456.00 27.36 P&M-031
Air compressor 250 cfm hour 0.06 293.76 17.63 P&M-001
Mastic cooker 1 tonne capacity hour 6.00 54.81 328.86 P&M-030
Bitumen boiler 1500 litres capacity hour 6.00 182.52 1095.12 P&M-005
Tractor for towing and positioning of mastic cooker and hour 1.00 171.02 171.02 P&M-053
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate(3.35mm to 9.5 mm size) = 40 per cent .
Proportion of material required for mastic asphalt with coarse
aggregates (based on mix design done by CRRI for a specific
case)
i) Bitumen 80/100 or 60/70 @ 10.2 per cent by weight of tonne 0.204 39879.31 8135.38 M-074
mix. 2 x 10.2/100 = 0.204
ii) Crusher stone dust @ 31.9 per cent by weight of mix = cum 0.39 215.86 84.19 M-021
2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium carbonate content not tonne 0.36 4427.31 1593.83 M-188
less than 80 per cent by weight @ 17.92 per cent by
weight of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40 per cum 0.55 674.15 370.78 M-051
cent by weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456 =
0.55
v) Pre-coated stone chips of 9.5 mm nominal size for skid cum 0.036 #VALUE! #VALUE! M-142
resistance = 72.46x0.005/10 = 0.036
vi) Bitumen for coating of chips @ 2 per cent by weight = kg 1.05 39.88 41.87 M-074/1000
0.036 x 1.456 x 2/100 = 0.001048MT = 1.05kg
d) Overhead charges @ 0.25 on (a+b+c) #VALUE!
e) Contractor's profit @ 0.1 on (a+b+c+d) #VALUE!
Cost for 72.46 sqm = a+b+c+d+e #VALUE!
Rate per sqm = (a+b+c+d+e)/72.46 #VALUE!
say #VALUE!
Note 1.The rates for 6 mm or any other thickness may be worked out
on pro-rata basis.
2. Where tack coat is required to be provided before laying
mastic asphalt, the same is required to be measured and paid
separately.
3.The quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per mix design.

4.This rate analysis is based on design made by CRRI for a


specific case and is meant for estimating purposes only. Actual
design is required to be done for each case.
5.The quantity of bitumen works out 17 per cent of the mastic
asphalt blocks without aggregates and falls within the standards
laid down by MoRTH Specifications.
14.6 2703, Construction of precast RCC railing of M30 Grade,
1500, aggregate size not exceeding 12 mm, true to line and
1600 & grade, tolerance of vertical RCC post not to exceed 1 in
1700 500, centre to centre spacing between vertical post not to
exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved
drawings and technical specifications.

Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a) Material
i) M30 Grade Reinforced Cement Concrete cum 4.092 3678.00 15050.38 Item 14.1(C)
No. of vertical posts = (12 + 2)2 = 28 Nos., External area of DIR used
vertical post 0.25x0.275 = 0.069sqm, Concrete in Vertical item
posts = 0.069 x 28 = 1.932 cum, Hand rail in 3 tiers = 3 x
24 = 72 m, External area = 0.170 x 0.175 = 0.03 sqm,
Concrete in hand rails = 0.03 x 72 = 2.16 cum, Total
Concrete = 1.932 + 2.16 = 4.092 cum. (Refer MoRTH SD /
202).

290
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Add 5 per cent of above cost for form work for casting in 752.52
casting yard.
ii) HYSD bar reinforcement Rate as per item No tonne 0.865 49225.00 42579.63 Item 14.2 A
14.2(Excluding OH & CP)
DIR used item
Refer MoRTH SD / 202.
Add 5 per cent of (a) for handling and fixing of precast 2919.13
panels in position
b) Overhead charges @ 0.25 on (a) 15325.41
c) Contractor's profit @ 0.1 on (a+b) 7662.71
Rate for 48 m (a+b+c) 84289.76
Rate per metre (a+b+c)/48 1756.04
say 1756.00
Note 1.Quantities of material have been adopted from standard plans
of MoRTH vide drawing no. SD/202.
2.48 m length is the total linear length adding both sides of 24 m
span.
14.7 2703, Construction of RCC railing of M30 Grade in-situ with 20
1500, mm nominal size aggregate, true to line and grade,
1600 & tolerance of vertical RCC post not to exceed 1 in 500,
1700 centre to centre spacing between vertical post not to
exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved
drawings and technical specifications.

Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a) Material
i) M30 Grade Reinforced Cement Concrete cum 4.092 3678.00 15050.38 Item 14.1(C)

No. of vertical posts = (12 + 2)2 = 28 Nos., External area of


vertical post 0.25x0.275 = 0.069sqm, Concrete in vehicle
posts = 0.069 x 28 = 1.932 cum, Hand rail in 3 tiers = 3 x
24 = 72 m, External area = 0.170 x 0.175 = 0.03 sqm,
Concrete in hand rails = 0.03 x 72 = 2.16 cum, Total
Concrete = 1.932 + 2.16 = 4.092 cum. (Refer MoRTH SD /
202).

Add 12 per cent of above cost for form work. 1806.05


ii) HYSD bar reinforcement Rate as per item No tonne 0.865 49225.00 42579.63 Item 14.2 A
14.2(Excluding OH & CP)
refer MoRTH SD / 202.
b) Overhead charges @ 0.25 on (a) 14859.01
c) Contractor's profit @ 0.1 on (a+b) 7429.51
Rate for 48 m (a+b+c) 81724.56
Rate per metre (a+b+c)/48 1702.60
say 1703.00
Note 1. Quantities of material have been adopted from standard plans
of MoRTH vide drawing no. SD/202.
2. 48 m length is the total linear length adding both sides of 24 m
span.
14.8 2703.2 Providing, fitting and fixing mild steel railing complete as
& 1900 per drawing and Technical Specification
Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a) Material:
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT tonne 2.946 48095.30 141688.77 M-179
2) MS Flat = 0.964 x 1.05 = 1.012 MT tonne 1.012 48095.30 48672.45 M-179
3) MS bars = 0.17 x 1.05 = 0.180 MT tonne 0.18 48095.30 8657.15 M-179
4) MS bolts, nuts and washers tonne 0.15 45421.67 6813.25 M-130*1000
Add @ 5 per cent of cost of material for painting one shop 10291.58
coat with red oxide primer and three coats of synthetic
enamel paint and consumables to safeguard against
weathering and corrosion.
Add for cost of concrete for fixing vertical posts in the 2058.32
performed recess @ 1 per cent of cost of material.

291
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Add for electricity charges, welding and drilling equipment, 2058.32
electrodes and other consumables @ 1 per cent of cost of
material.
b) Labour
Mate day 2.80 195.43 547.20 L-12
Mazdoor (Skilled) day 30.00 218.57 6557.10 L-15
Mazdoor day 40.00 187.43 7497.20 L-13
c) Overhead charges @ 0.25 on (a+b) 58710.33
d) Contractor's profit @ 0.1 on (a+b+c) 29355.17
Cost for 100 m steel railing = a+b+c+d 322906.84
Rate per metre (a+b+c+d)/100 3229.07
say 3229.00
14.9 2705 Drainage Spouts complete as per drawing and Technical
specification
Unit = 1 No.
Taking output = 1 No.
a) Material
Corrosion resistant Structural steel including 5 per cent Kg 4.00 48.10 192.38 M-087/1000
wastage
GI pipe 100mm dia metre 6.00 50.28 301.66 M-056
GI bolt 10 mm Dia each 6.00 11.07 66.41 M-110
Galvanised MS flat clamp each 2.00 11.07 22.14 M-101
b) Labour
For fabrication
Mate day 0.02 195.43 3.91 L-12
Skilled (Blacksmith, welder etc.) day 0.02 247.19 4.94 L-02
Mazdoor day 0.02 187.43 3.75 L-13
For fixing in position
Mate day 0.01 195.43 1.95 L-12
Mason day 0.01 247.19 2.47 L-11
Mazdoor day 0.20 187.43 37.49 L-13
Add @ 5 per cent of cost of material and labour for 31.86
electrodes, cutting gas, sealant, anti-corrosive bituminous
paint, mild steel grating etc.
c) Overhead charges @ 0.25 on (a+b) 167.24
d) Contractor's profit @ 0.1 on (a+b+c) 83.62
Rate per metre (a+b+c+d) 919.82
say 920.00
Note 1. In case of viaducts in urban areas, the drainage spouts should
be connected with suitably located pipelines to discharge the
surface run-off to drains provided at ground level.

2. In case of bridges, sufficient length of G.I Pipe shall be


provided to ensure that there is no splashing of water from the
drainage spout on the structure.
14.10 2700 PCC M15 Grade leveling course below approach slab
complete as per drawing and Technical specification
Unit = 1 cum
Taking output = 1 cum
Material
Concrete, Rate as per item No. 12.8 (A) excluding cum 1.00 4096.00 4096.00 Item 12.8 (A)
formworks
Rate per cum say 4096.00
14.11 1500,16 Reinforced cement concrete approach slab including
00,1700 reinforcement and formwork complete as per drawing and
& 2704 Technical specification
Unit = 1 cum
Taking output = 1 cum
a) Material

292
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Cement concreteM30 Grade Refer relevant item of cum 1.00 3676.00 3676.00 Item 12.8
concrete in item 12.8(G)by using batching plant, excluding (G)
formwork i.e. per cum basic cost (a+b+c) (Excluding OH &
CP)
( Refer relevant item of concrete in item No. 13.8 (G) 73.52
except that form work may be added at the rate of 2 per
cent of cost against 3.5 per cent provided in the
foundation concrete.
HYSD bar reinforcement Rate as per item No tonne 0.05 49225.00 2461.25 Item 14.2 A
14.2(Excluding OH & CP)
b) Overhead charges @ 0.25 on (a) 1552.69
c) Contractor's profit @ 0.1 on(a+b) 776.35
Rate per cum (a+b+c) 8539.81
say 8540.00
Note The grade of reinforced cement concrete may be adopted as
M30 for severe conditions and M25 for moderate conditions.
14.12 1600 Providing anti-corrosive treatment to HYSD reinforcement
with Fusion Bonded Epoxy Coating (FBEC)

Unit = 1 MT
Taking output = 1 MT
To be taken as per the prevailing market rates. VALUE
Note Contractors generally do not have expertise for this item . The
job is therefore, got done from specialised firms who have the
expertise in the field of construction chemicals. The prevailing
rate in the market is required to be ascertained from the market
and added in the cost estimate. Detailed guidelines in this regard
have been issued by MoRTH vide their circular no. RW/NH-
34041/44/91-S&R dated 21.3.2000.

14.13 1800 & Precast - pretensioned Girders


2300
Providing, precasting, transportation and placing in
position precast pretensioned concrete girders as per
drawing and technical specifications
Unit = 1 cum
Taking output = 1 cum
Grade of concrete - M40
a) Material
Cement tonne 0.47 5982.46 2811.75 M-081
Coarse sand cum 0.45 209.13 94.11 M-004
20 mm Aggregate cum 0.54 887.53 479.26 M-053
10 mm Aggregate cum 0.36 674.15 242.69 M-051
Admixture @ 0.4 per cent of cement Kg 1.88 112.77 212.01 M-180
HYSD steel . tonne 0.10 44187.50 4418.75 M-082
HT strand with 5 per cent as wastage and extra length for tonne 0.06 62418.78 3745.13 M-119
anchoring
LDO for steam curing Litre 37.00 #VALUE! #VALUE! M-122
Add consumables such as binding wire, foam, packing #VALUE!
tape, shuttering oil, HDPE pipe for unbonding of strand,
bolt & nuts etc @ 1 per cent of material cost
b) Labour
(i) Cutting, bending, making reinforcement cage, placing in
position, binding etc. complete
Taking quantity of steel 100 Kg/cum of concrete including
laps and wastage
Mate day 0.06 195.43 11.73 L-12
Mazdoor (Skilled) day 0.35 218.57 76.50 L-15
Mazdoor day 1.40 187.43 262.40 L-13
(ii) Cable cutting and threading in position including
binding by insulation tape with HDPE pipes etc.,
prestessing and cutting of extra length of HT strand after
de-stressing.
Taking quantity of HT strand 60 Kg/cum

293
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mate day 0.02 195.43 3.91 L-12
Mazdoor (Skilled) day 0.14 218.57 30.60 L-15
Mazdoor day 0.50 187.43 93.72 L-13
(iii) Erection and dismantling of shuttering
Taking shuttering area 10 sqm/cum of concrete
Mate day 0.12 195.43 23.45 L-12
Mazdoor (Skilled) day 1.00 218.57 218.57 L-15
Mazdoor day 2.00 187.43 374.86 L-13
(iv) Concreting by Batching plant and stationary concrete
pump
Mate day 0.03 195.43 5.86 L-12
Mazdoor (Skilled) day 0.05 218.57 10.93 L-15
Mazdoor day 0.60 187.43 112.46 L-13
(v) Steam curing and manual curing
Mate day 0.01 195.43 1.95 L-12
Mazdoor day 0.35 187.43 65.60 L-13
(vi) Handling of precast girder, stacking in stockyard and
again loading in trailor
Mate day 0.01 195.43 1.95 L-12
Mazdoor day 0.25 187.43 46.86 L-13
(vii) Placement of girders in position over pier caps
including placement of sand jacks, channel, levelling etc.

Mate day 0.01 195.43 1.95 L-12


Mazdoor (Skilled) day 0.06 218.57 13.11 L-15
Mazdoor day 0.24 187.43 44.98 L-13
c) Machinery
i) At casting yard
Generator 100 KVA hour 0.05 1635.00 81.75 P&M-080
Batching Plant @ 20 cum/hour hour 0.05 2457.00 122.85 P&M-002
Transit Mixer 4 cum capacity hour 0.10 854.55 85.46 P&M-049
Concrete Pump stationary hour 0.05 234.36 11.72 P&M-007
Crane 35 tonne capacity hour 0.10 784.62 78.46 P&M-012
Trailor 30 tonne capacity hour 0.10 1864.08 186.41 P&M-089
Loader hour 0.05 1148.00 57.40 P&M-017
ii) For transportation and placement at site
Crane 35 tonne capacity hour 0.15 784.62 117.69 P&M-012
Trailer 30 tonne capacity for transporting to site. tonne.km 2.5xL 2.27 5.67 Lead =1 km
& P&M-090
(L - Lead in Kilometer)
Trailor 30 tonne capacity during placement. hour 0.15 1864.08 279.61 P&M-089
Cost of formwork, steam curing arrangement, pretensioning #VALUE!
arrangement etc @ 5 per cent of cost material, labour and
machinery
d) Overhead charges @ 0.25 on (a+b+c) #VALUE!
e) Contractor's profit @ 0.1 on (a+b+c+d) #VALUE!
Rate per cum = (a+b+c+d+e) #VALUE!
say #VALUE!
14.14 1700 & Providing and fixing Helical pipes in voided concrete slabs
1800
Unit = 1 RM
Taking output = 1 RM
a) Material
Helical pipes 600mm diameter metre 1.00 #VALUE! #VALUE! M-117
Tie rods 20mm diameter each 1.00 47.51 47.51 M-183
Consumables for sealing joints etc.@ 5 per cent of cost of #VALUE!
material
b) Labour
Mate day 0.01 195.43 1.95 L-12

294
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Fitter day 0.05 251.19 12.56 L-08
Mazdoor day 0.20 187.43 37.49 L-13
c) Overhead charges @ 0.25 on (a+b) #VALUE!
d) Contractor's profit @ 0.1 on (a+b+c) #VALUE!
Rate per cum (a+b+c+d) #VALUE!
say #VALUE!
14.15 800 Crash Barriers
The rate analysis for rigid crash barrier in reinforced cement Per m VALUE
concrete, semi-rigid crash barrier with metal beam and flexible
crash barrier with wire ropes have been made and included in
chapter-8 on Traffic and Transportation.
14.16 800 Painting on concrete surface
Providing and applying 2 coats of water based cement
paint to unplastered concrete surface after cleaning the
surface of dirt, dust, oil, grease, efflorescence and
applying paint @ of 1 litre for 2 sqm.
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.01 195.43 1.95 L-12
Painter day 0.25 236.19 59.05 L-18
Mazdoor (Skilled) day 0.25 218.57 54.64 L-15
b) Material
Water based paint of approved quality for cement concrete Litres 5.00 75.18 375.90 M-190
surface
c) Overhead charges @ 0.25 on (a+b) 122.89
d) Contractor's profit @ 0.1 on (a+b+c) 61.44
Cost for 10 sqm (a+b+c+d) 675.88
Rate per sqm (a+b+c+d)/10 67.59
say 68.00
14.17 2604 Burried Joint
Providing and laying a burried expansion joint, expansion
gap being 20 mm, covered with 12 mm thick, 200 mm wide
galvanised weldable structural steel plate as per IS: 2062,
placed symmetrical to centre line of the joint, resting freely
over the top surface of the deck concrete, welding of 8 mm
dia. 100 mm long galvanised nails spaced 300 mm c/c
along the centre line of the plate, all as specified in clause
2604.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.02 195.43 3.91 L-12
Mazdoor day 0.40 187.43 74.97 L-13
Mazdoor (Skilled) day 0.20 218.57 43.71 L-15
b) Material
Galvanised M.S plate 200 mm wide,12 mm thick @ 94.20 kg 237.50 46.24 10981.82 M-060/1000
kg/sqm including 5 per cent wastage
Add 1 per cent of cost of steel plate cutting, welding 109.82
consumables and galvanised nails.
c) Overhead charges @ 0.25 on (a+b) 2803.56
d) Contractor's profit @ 0.1 on (a+b+c) 1401.78
Cost for 12 m = (a+b+c+d) 15419.58
Rate per m = (a+b+c+d)/12 1284.96
say 1285.00
Note Guidelines laid down vide the MoRTH circular No. RW/NH-
34059/1/96-S&R dated 30.11.2000 and subsequent corrigendum
dated 25.01.2001 may be reffered for expansion joints.

14.18 2605 Filler joint

295
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
(i) Providing & fixing 2 mm thick corrugated copper plate in
expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
Cutting, bending, carrying & fixing etc.
Mate day 0.04 195.43 7.82 L-12
Mazdoor day 0.50 187.43 93.72 L-13
Mazdoor (Skilled) day 0.50 218.57 109.29 L-15
b) Material
Copper plate - 12m long x 250 mm wide kg 55.00 481.39 26476.19 M-086
Area = 12 x 0.25 = 3 sqm
Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say = 55 kg.
c) Overhead charges @ 0.25 on (a+b) 6671.75
d) Contractor's profit @ 0.1 on (a+b+c) 3335.88
Cost for 12 m = (a+b+c+d) 36694.63
Rate per m = (a+b+c+d)/12 3057.89
say 3058.00
14.18 (ii) Providing & fixing 20 mm thick compressible fibre board in
expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
For carrying, placing & fixing.
Mate day 0.01 195.43 1.56 L-12
Mazdoor day 0.10 187.43 18.74 L-13
Mazdoor (Skilled) day 0.10 218.57 21.86 L-15
b) Material
20 mm thick compressible fibre board 12 m long x 25 cm sqm 3.00 603.53 1810.60 M-084
deep.
Area = 12 x 0.25 = 3 sqm
c) Overhead charges @ 0.25 on (a+b) 463.19
d) Contractor's profit @ 0.1 on (a+b+c) 231.60
Cost for 12 m = (a+b+c+d) 2547.55
Rate per m = (a+b+c+d)/12 212.30
say 212.00
14.18 (iii) Providing and fixing in position 20 mm thick premoulded
joint filler in expansion joint for fixed ends of simply
supported spans not exceeding 10 m to cater for a
horizontal movement upto 20 mm, covered with sealant
complete as per drawing and technical specifications.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.01 195.43 1.95 L-12
Mazdoor day 0.20 187.43 37.49 L-13
Mazdoor (Skilled) day 0.10 218.57 21.86 L-15
b) Material
Premoulded joint filler 12 m long,20 mm thick and 300 mm sqm 3.60 708.07 2549.05 M-141
deep.
c) Overhead charges @ 0.25 on (a+b) 652.59
d) Contractor's profit @ 0.1 on (a+b+c) 326.29
Cost for 12 m = (a+b+c+d) 3589.23
Rate per m = (a+b+c+d)/12 299.10
say 299.00

296
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
14.18 (iv) Providing and filling joint sealing compound as per
drawings and technical specifications with coarse sand
and 6 per cent bitumen by weight
Unit = Running meter
Taking output = 12 m
12m long x 100 mm wide x 10mm deep recess

297
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
a) Labour
Mate day 0.02 195.43 3.91 L-12
Mazdoor day 0.50 187.43 93.72 L-13
Mazdoor (Skilled) day 0.10 218.57 21.86 L-15
b) Material
Sand cum 0.012 209.13 2.51 M-005
Volume 12 x 0.1 x 0.01 = 0.012 cum
Weight 0.012 x 1400 = 16.8kg
Bitumen cum 0.001 39879.31 39.88 M-074
16.8 x 0.06 = 1 kg
c) Overhead charges @ 0.25 on (a+b) 40.47
d) Contractor's profit @ 0.1 on (a+b+c) 20.23
Cost for 12 m = (a+b+c+d) 222.57
Rate per m = (a+b+c+d)/12 18.55
say 18.50
Note For arriving at the final rate of filler joints per m
length and per cm depth of joint filling compound,
the rates at Sl. No. i), ii), iii) & iv) shall be added
14.19 2600 Asphaltic Plug joint
Providing and laying of asphaltic plug joint to provide for
horizontal movement of 25 mm and vertical movement of 2
mm, depth of joint varying from 75 mm to 100 mm, width
varying from 500 mm to 750 mm (in traffic direction),
covered with a closure plate of 200mm x 6mm of weldable
structural steel conforming to IS: 2062, asphaltic plug to
consist of polymer modified bitumen binder, carefully
selected single size aggregate of 12.5 mm nominal size
and a heat resistant foam caulking/backer rod, all as per
approved drawings and specifications.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.052 195.43 10.16 L-12
Mazdoor day 1.00 187.43 187.43 L-13
Mazdoor (Skilled) day 0.30 218.57 65.57 L-15
b) Material
Crushed stone aggregate 12.5 mm nominal size cum 0.75 777.69 583.27 M-052
Polymer modified bitumen kg 77.50 42.27 3276.25 M-078/ 1000

Galvanised structural steel plate 200 mm wide,6 mm thick, kg 113.00 38.63 4365.70 M-103
12 m long (2.4 sqm) @ 47.10 kg/sqm including 5 per cent
wastage
Add 1 per cent for welding and foam caulking/backer rod 84.88
and other incidentals.
c) Machinery
Mastic cooker 1 tonne capacity hour 1.00 54.81 54.81 P&M-030
Smooth 3-wheeled steel roller 8-10 capacity hour 0.50 649.00 324.50 P&M-044
d) Overhead charges @ 0.25 on (a+b+c) 2238.14
e) Contractor's profit @ 0.1 on (a+b+c+d) 1119.07
Cost for 12 m asphalt plug joint = (a+b+c+d+e) 12309.80
Rate per m = (a+b+c+d+e)/12 1025.82
say 1026.00
Note The nominal size of aggregates shall be 12.5 mm for depth of
joint upto 75 mm and 20 mm for joints of depth more than 75
mm.
14.20 2606 Elastomeric Slab Steel Expansion Joint

298
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Providing and laying of an elastomeric slab steel
expansion joint, catering to right or skew (less than 20
deg., moderately curved with maximum horizontal
movement upto 50 mm, complete as per approved
drawings and standard specifications to be installed by the
manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for
installation and clause 2606 of MoRTH specifications for
road & bridge works.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.06 195.43 11.73 L-12
Mazdoor day 1.00 187.43 187.43 L-13
Mazdoor (Skilled) day 0.50 218.57 109.29 L-15
b) Material
Supply of elastomeric slab seal expansion joint assembly metre 12.00 19422.70 233072.41 M-093
manufactured by using chloroprene, elastomer for
elastomeric slab unit conforming to clause 915.1 of IRC: 83
(part II), complete as per approved drawings and standard
specification conforming to clause 2606 of MoRT&H
Specification
Add 5 per cent of cost of material for anchorage 11653.62
reinforcement, welding and other incidentals.
c) Overhead charges @ 0.25 on (a+b) 61258.62
d) Contractor's profit @ 0.1 on (a+b+c) 30629.31
Cost for 12 m = (a+b+c+d) 336922.40
Rate per m = (a+b+c+d)/12 28076.87
say 28077.00
14.21 2600 Compression Seal Joint
Providing and laying of compression seal joint consisting
of steel armoured nosing at two edges of the joint gap
suitably anchored to the deck concrete and a preformed
chloroprene elastomer or closed cell foam joint sealer
compressed and fixed into the joint gap with special
adhesive binder to cater for a horizontal movement upto
40 mm and vertical movement of 3 mm.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.036 195.43 7.04 L-12
Mazdoor day 0.60 187.43 112.46 L-13
Mazdoor (Skilled) day 0.30 218.57 65.57 L-15
b) Material
1. Galvanised angle sections 100mm x 100mm of 12mm kg 446.00 38.63 17231.00 M-103
thickness weldable structural steel as per IS: 2062, 2 nos.
of 12 m length each @ 17.7 kg/m and 5 per cent wastage.

Add 5 per cent of cost of above for structural steel for 870.80
anchorage, welding and other incidentals.
Preformed continuous chloroprene elastomer or closed cell metre 12.00 #VALUE! #VALUE! M-143
foam sealing element with high tear strength, vulcanised in
a single operation for the full length of a joint to ensure
water tightness.
Add 1 per cent of cost of sealing element for lubricant- #VALUE!
cum-adhesive and other consumables.
c) Overhead charges @ 0.25 on (a+b) #VALUE!
d) Contractor's profit @ 0.1 on (a+b+c) #VALUE!
Cost for 12 m = (a+b+c+d) #VALUE!
Rate per m = (a+b+c+d)/12 #VALUE!
say #VALUE!

299
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Note 1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly with
the deck has not been included in this analysis as the same is
catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint assembly shall be
welded to the main reinforcement of the deck.
14.22 2607 Strip Seal Expansion Joint
Providing and laying of a strip seal expansion joint
catering to maximum horizontal movement upto 70 mm,
complete as per approved drawings and standard
specifications to be installed by the manufacturer/supplier
or their authorised representative ensuring compliance to
the manufacturer's instructions for installation.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.05 195.43 9.77 L-12
Mazdoor day 1.00 187.43 187.43 L-13
Mazdoor (Skilled) day 0.25 218.57 54.64 L-15
b) Material
Supply of complete assembly of strip seal expansion joint metre 12.00 6043.69 72524.32 M-178
comprising of edge beams, anchorage, strip seal element
and complete accessories as per approved specifications
and drawings.
Add 5 per cent of cost of material for anchorage 3638.81
reinforcement, welding and other incidentals.
c) Overhead charges @ 0.25 on (a+b) 19103.74
d) Contractor's profit @ 0.1 on (a+b+c) 9551.87
Cost for 12 m = (a+b+c+d) 105070.58
Rate per m = (a+b+c+d)/12 8755.88
say 8756.00
Note 1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly with
the deck has not been included in this analysis as the same is
catered in the quantities of RCC deck.
14.23 2600 Modular Strip / Box Seal Joint
Providing and laying of a modular strip Box seal expansion
joint including anchorage catering to a horizontal
movement beyond 70 mm and upto 140mm, complete as
per approved drawings and standard specifications to be
installed by the manufacturer/supplier or their authorised
representative ensuring compliance to the manufacturer's
instructions for installation.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.056 195.43 10.94 L-12
Mazdoor day 1.00 187.43 187.43 L-13
Mazdoor (Skilled) day 0.40 218.57 87.43 L-15
b) Material
Supply of a modular strip/box seal joint assembly metre 12.00 21404.46 256853.52 M-127
comprising of edge beams, central beam,2 modules
chloroprene seal, anchorage elements, support and control
system, all steel sections protected against corrosion and
installed by the manufacturer or his authorised
representative.
c) Overhead charges @ 0.25 on (a+b) 64284.83
d) Contractor's profit @ 0.1 on (a+b+c) 32142.41
Cost for 12 m Modular strip/box seal joint = (a+b+c+d) 353566.56

300
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Rate per m = (a+b+c+d)/12 29463.88
say 29464.00
Note 1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly with
the deck has not been included in this analysis as the same is
catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint assembly shall be
welded to the main reinforcement of the deck.
14.24 2600 Modular Strip / Box Seal Joint
Providing and laying of a modular strip box seal expansion
joint catering to a horizontal movement beyond 140mm
and upto 210mm, complete as per approved drawings and
standard specifications to be installed by the
manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for
installation.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.07 195.43 13.68 L-12
Mazdoor day 1.25 187.43 234.29 L-13
Mazdoor (Skilled) day 0.50 218.57 109.29 L-15
b) Material
Supply of a modular box/box seal joint assembly containing metre 12.00 #VALUE! #VALUE! M-128
3 modules/cells and comprising of edge beams, two central
beams, chloroprene seal, anchorage elements, support and
control system, all steel sections protected against
corrosion and installed by the manufacturer or his
authorised representative.
c) Overhead charges @ 0.25 on (a+b) #VALUE!
d) Contractor's profit @ 0.1 on (a+b+c) #VALUE!
Cost for 12 m Modular strip/box seal joint = (a+b+c+d) #VALUE!
Rate per m = (a+b+c+d)/12 #VALUE!
say #VALUE!
Note 1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly with
the deck has not been included in this analysis as the same is
catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint assembly shall be
welded to the main reinforcement of the deck.

301
CHAPTER - 15
RIVER TRAINING AND PROTECTION WORKS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
15.1 2503 Providing and laying boulders apron on river bed for
protection against scour with stone boulders weighing not
less than 40 kg each complete as per drawing and Technical
specification.
A Boulder Laid Dry Without Wire Crates.
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 352.58 352.58 M-003
Stone Spalls cum 0.20 325.05 65.01 M-008
b) Labour
Mate day 0.04 195.43 7.82 L-12
Mason day 0.35 247.19 86.52 L-11
Mazdoor * day 0.75 187.43 140.57 L-13
c) Overhead charges @ 0.25 on (a+b) 163.12
d) Contractor's profit @ 0.1 on (a+b+c) 81.56
Rate per cum = (a+b+c+d) 897.18
say 897.00
* Including excavation for trimming for preparation of bed.
Note Nominal excavation required for preparation of bed has been taken
into account while making provision for labour.
15.2 2503 Boulder Apron Laid in Wire Crates
Providing and laying of boulder apron laid in wire crates made with
4mm dia GI wire conforming to IS: 280 & IS:4826 in 100mm x
100mm mesh (weaved diagonally) including 10 per cent extra for
laps and joints laid with stone boulders weighing not less than 40
kg each.
Unit = cum
Taking output = 3 mx1.5mx1.25m = 5.63 cum
a) Material
4mm GI wire crates woven in mesh size of 100 mm x 100 mm. sqm 22.00 73.09 1608.03 M-102
Stone cum 5.63 352.58 1985.02 M-003
Stone Spalls cum 1.13 325.05 367.31 M-008
b) Labour
Mate day 0.18 195.43 35.18 L-12
Mazdoor (Skilled) day 1.50 218.57 327.86 L-15
Mazdoor day *3.00 187.43 562.3 L-13
c) Overhead charges @ 0.25 on (a+b) 1221.4
d) Contractor's profit @ 0.1 on (a+b+c) 610.71
Cost for 5.63 cum = a+b+c+d 6717.81
Rate per cum = (a+b+c+d)/5.63 1193.22
say 1193.00
* Including excavation for trimming for preparation of bed.
Note Readymade woven wire crate rolls have been considered in the
rate analysis. In case readymade rolls are not available, GI wire
4mm dia. @ 32 kg per 10 sqm may be provided. In that case 2 per
cent of the cost of GI wire may be added for weaving the wire
crates.
15.3 2503 Cement Concrete Blocks (size 0.5 x 0.5 x 0.5 m)
Providing and laying of apron with cement concrete blocks of size
0.5x0.5x0.5 m cast in-situ and made with nominal mix of M-15
grade cement concrete with a minimum cement content of 250
kg/cum as per IRC: 21-2000.
Unit = cum
Taking out put = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (A) including OH & cum 1.00 4259.00 4259.00 Item 12.8 (A)
CP
Add 2 per cent of cost to account for excavation for preparation of 85.18
bed, nominal surface reinforcement and filling of granular material
in recesses between blocks.
Rate per cum 4344.18
say 4344.00

300
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
15.4 2504 Providing and laying Pitching on slopes laid over prepared
filter media including boulder apron laid dry in front of toe of
embankment complete as per drawing and Technical
specifications
A Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg cum 1.00 352.58 352.58 M-003
Stone spalls of minimum 25 mm size cum 0.20 325.05 65.01 M-008
b) Labour
Mate day 0.04 195.43 7.82 L-12
Mason day 0.35 247.19 86.52 L-11
Mazdoor day 0.75 187.43 140.57 L-13
c) Overhead charges @ 0.25 on (a+b) 163.12
d) Contractor's profit @ 0.1 on (a+b+c) 81.56
Rate per cum = (a+b+c+d) 897.18
say 897.00
15.4 B Cement Concrete Blocks of size 0.3x0.3 x0.3 m cast in
cement concrete of Grade M15
Unit = cum
Taking output = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (A) cum 1.00 4259.00 4259.00 Item 12.8 (A)

Add 2 per cent of cost to account for nominal surface 85.18


reinforcement and filling of granular material in recesses between
blocks.
Rate per cum 4344.18
say 4344.00
15.5 2504
Providing and laying Filter material underneath pitching in
slopes complete as per drawing and Technical specification

Unit = cum
Taking output = 1 cum
a) Material
Graded stone aggregate of required size cum 1.20 630.22 756.26 M-012
b) Labour
Mate day 0.05 195.43 9.77 L-12
Mazdoor (Skilled) day 0.25 218.57 54.64 L-15
Mazdoor * day 1.00 187.43 187.43 L-13
c) Overhead charges @ 0.25 on (a+b) 252.03
d) Contractor's profit @ 0.1 on (a+b+c) 126.01
Rate per cum = (a+b+c+d) 1386.14
say 1386.00
Includes Mazdoor required for trimming of slope to proper profile
and preparation of bed.
15.6 700 & Geotextile Filter
2504

Laying of a geotextile filter between pitching and embankment


slopes on which pitching is laid to prevent escape of the
embankment material through the voids of the stone
pitching/cement concrete blocks as well as to allow free movement
of water without creating any uplift head on the pitching.

Unit = sqm
Taking output = 10 sqm.
a) Labour
Mate day 0.02 195.43 3.91 L-12
Mazdoor day 0.30 187.43 56.23 L-13
Mazdoor (Skilled) day 0.10 218.57 21.86 L-15
b) Material

301
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Permeable synthetic geotextile including 5 per cent for overlap sqm 11.00 85.89 944.79 M-181
and wastage
c) Overhead charges @ 0.25 on (a+b) 256.70
d) Contractor's profit @ 0.1 on (a+b+c) 128.35
Cost for 10 sqm = a+b+c+d 1411.83
Rate per sqm = (a+b+c+d)/10 141.18
say 141.00
15.7 2504.4 Toe protection

A toe wall for toe protection can either be in dry rubble masonry in
case of dry rubble pitching or pitching with stones in wire crates or
it can be in PCC M15 nominal mix if cement concert block have
been used for pitching . Rates for toe wall can be adopted from
respective clauses depending upon approved design. The rate for
excavation for foundation, dry rubble masonry and PCC M15 have
been analysed and given in respective chapters.

15.8 2505
Providing and laying Flooring complete as per drawing and
Technical specifications laid over cement concert bedding.

A Rubble stone laid in cement mortar 1:3


Unit = cum
Taking output = 1 cum
a) Cement mortor 1:3 (Rate as in Item 12.6 sub-analysis) cum 0.33 3447.00 1137.51 Item 12.6 (A)
excluding OH & CP
b) Add for cement concrete bedding (M15 Nominal mix) cum 0.33 2979.00 983.07 Item 12.8 (A)
vide Item 12.8 (A) excluding OH & CP . Quantity shall be
adopted as per design ( Assume Rubble stone Flooring
thickness 300mm and cement concrete bedding thickness
100mm)
Add 1 per cent of cost to account for excavation for preparation of 21.21
bed.
c) Material
Stone cum 1.00 352.58 352.58 M-003
Stone Spalls cum 0.20 325.05 65.01 M-008
d) Labour
Mate day 0.08 195.43 15.63 L-12
Mason day 0.50 247.19 123.60 L-11
Mazdoor (for laying stones, filling of quarry spalls) day 1.50 187.43 281.15 L-13
e) Overhead charges @ 0.25 on (a+c+d) 493.87
f) Contractor's profit @ 0.1 on (a+c+d+e) 246.93
Rate per cum = (a+b+c+d+e+f) 3720.55
say 3721.00
* Includes cement mortar for laying and filling of joints.
15.8 B Cement Concrete blocks Grade M15
Concrete Grade M15 block. (Rate as per item No. 12.8 (A) cum 1.00 4259.00 4259.00 Item 12.8 (A)
including OH & CP.
Add for cement concrete bedding (M15 Nominal mix) vide Item cum 0.33 4259.00 1405.47 Item 12.8 (A)
12.8 (A) including OH & CP. Quantity shall be adopted as per
design ( Assume Cement Concrete blocks thickness 300mm and
cement concrete bedding thickness 100mm)
Add 1 per cent of cost to account for excavation for preparation of 56.64
bed.
Rate per cum 5721.11
say 5721.00
15.9 2506 Dry Rubble Flooring
Construction of dry rubble flooring at cross drainage works for
relatively less important works.
Unit = cum
Taking output = 1 cum
a) Material

302
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Stone cum 1.00 352.58 352.58 M-003
Stone Spalls cum 0.20 325.05 65.01 M-008
b) Labour
Mate day 0.10 195.43 19.54 L-12
Mason day 0.50 247.19 123.60 L-11
mazdoor day 1.50 187.43 281.15 L-13
Add 1 per cent of (b) for trimming and preparation of base. 4.24
c) Overhead charges @ 0.25 on (a+b) 211.53
d) Contractor's profit @ 0.1 on (a+b+c) 105.76
Rate per cum = (a+b+c+d) 1163.41
say 1163.00
15.10 2507.2 Curtain wall complete as per drawing and Technical
specification
A Stone masonry in cement mortar (1:3)

Coursed rubble masonry (1st sort) cum 1.00 3034.00 3034.00 Item 12.7 (A )

Rate same as per item No. 12.7 (A) including OH & CP


Rate per cum say 3034.00

15.10 B Cement concrete Grade M15


Concrete Grade M15 Rate as per item No. 12.8 (A) including OH & cum 1.00 4259.00 4259.00 Item 12.8 (A)
CP
Rate per cum say 4259.00
Note Other items like excavation for foundation, filling behind wall, filter
media, weep holes etc. shall be added separately as per approved
design.
15.11 2507.2 Flexible Apron :Construction of flexible apron 1 m thick
comprising of loose stone boulders weighing not less than
40 kg beyond curtain wall.
Unit = cum
Taking Output = 1 cum
a) Material
Stone cum 1.00 352.58 352.58 M-003
Stone Spalls cum 0.20 325.05 65.01 M-008
b) Labour
Mate day 0.05 195.43 9.77 L-12
Mason day 0.25 247.19 61.80 L-11
Mazdoor day 1.00 187.43 187.43 L-13
Add 1 per cent of cost of (a+b) for trimming and preparation of 6.77
bed.
c) Overhead charges @ 0.25 on (a+b) 170.84
d) Contractor's profit @ 0.1 on (a+b+c) 85.42
Rate per cum = (a+b+c+d) 939.61
say 940.00
15.12 2503.3 Gabian Structure for Retaining Earth
Providing and construction of a gabian structure for retaining earth
with segments of wire crates of size 7 m x 3 m x 0.6 m each
divided into 1.5 m compartments by cross netting, made from 4
mm galvanised steel wire @ 32 kg per 10 sqm having minimum
tensile strength of 300 Mpa conforming to IS:280 and galvanizing
coating conforming to IS:4826, woven into mesh with double twist,
mesh size not exceeding 100 x 100 mm, filled with boulders with
least dimension of 200 mm, all loose ends to be tied with 4 mm
galvanised steel wire
Unit = cum
Taking output = 7 x 3 x 0.6 = 12.60 cum
a) Labour
Mate day 0.28 195.43 54.72 L-12
Mazdoor day 5.00 187.43 937.15 L-13

303
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
Mazdoor (Skilled) day 2.00 218.57 437.14 L-15
b) Material
Galvanised steel wire crates of mesh size 100 mm x 100 mm sqm 61.00 73.09 4458.63 M-102
woven with 4mm dia. GI wire in rolls of required size.
Stone boulders with least dimension of 200 mm cum 12.60 352.58 4442.49 M-003
Stone spalls of minimum size 25 mm cum 2.52 325.05 819.13 M-008
c) Overhead charges @ 0.25 on (a+b) 2787.32
d) Contractor's profit @ 0.1 on (a+b+c) 1393.66
Cost for 12.60 cum (a+b+c+d) 15330.24
Rate per cum (a+b+c+d)/12.60 1216.69
say 1217.00
Note Readymade woven wire crate rolls have been considered in the
rate analysis. In case readymade rolls are not available, GI wire
4mm dia. @ 32 kg per 10 sqm may be provided. In that case 2 per
cent of the cost of GI wire may be added for weaving the wire
crates.
15.13 2503.3 Gabian Structure for Erosion Control, River Training Works
and Protection works
Providing and constructing gabian structures for erosion control,
river training works and protection works with wire crates of size 2
m x 1 m x 0.3 m each divided into 1m compartments by cross
netting, made from 4 mm galvanised steel wire @ 32 kg per 10
sqm having minimum tensile strength of 300 Mpa conforming to
IS:280 and galvanizing coating conforming to IS:4826, woven into
mesh with double twist, mesh size not exceeding 100 mm x 100
mm, filled with boulders with least dimension of 200 mm, all loose
ends to be securely tied with 4 mm galvanised steel wire.
Unit = cum
Taking output = 2 x 1 x 0.3 x 10 Nos. = 6.00 cum
a) Labour
Mate day 0.14 195.43 27.36 L-12
Mazdoor day 2.50 187.43 468.58 L-13
Mazdoor (Skilled) day 1.00 218.57 218.57 L-15
b) Material
Galvanised steel wire crates of mesh size 100 mm x 100 mm sqm 65.00 73.09 4751.00 M-102
woven with 4mm dia. GI wire in rolls of required size to cover 6.00
cum.
Stone boulders with least dimension of 200 mm cum 6.00 352.58 2115.47 M-003
Stone spalls of minimum size 25 mm cum 1.20 325.05 390.06 M-008
c) Overhead charges @ 0.25 on (a+b) 1992.76
d) Contractor's profit @ 0.1 on (a+b+c) 996.38
Cost for 6.00 cum (a+b+c+d) 10960.18
Rate per cum (a+b+c+d)/6.00 1826.70
say 1827.00
Note Readymade woven wire crate rolls have been considered in the
rate analysis. In case readymade rolls are not available, GI wire
4mm dia. @ 32 kg per 10 sqm may be provided. In that case 2 per
cent of the cost of GI wire may be added for weaving the wire
crates.

304
CHAPTER-16
REPAIR AND REHABILITATION
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
16.1 2809 Removal of existing cement concrete wearing coat including its disposal
complete as per Technical Specification without causing any detrimental
effect to any part of the bridge structure and removal of dismantled material
with all lifts and lead upto 1000 m

Unit = Sq m ( Thickness 75 mm)


Taking output = 10 sqm
a) Labour
Mate day 0.06 195.43 11.73 L-12
Mazdoor day 1.00 187.43 187.43 L-13
b) Machinery
Air Compressor 250 cfm with pneumatic breaker/jack hammer along with hour 1.00 293.76 293.76 P&M-001
accessories.
Tractor-trolley. hour 0.50 171.02 85.51 P&M-053
c) Overhead charges @ 0.3 on (a+b) 173.53
d) Contractor's profit @ 0.1 on (a+b+c) 75.20
Cost for 10 sqm = (a+d+c+d) 827.15
Rate per sqm = (a+b+c+d)/10 82.71
say 83.00
16.2 2809 Removal of existing asphaltic wearing coat comprising of 50 mm thick
asphaltic concert laid over 12 mm thick mastic asphalt including disposal
with all lift and lead upto 1000 m.

Unit = Sq m
Taking output = 10 sqm
a) Labour
Mate day 0.03 195.43 5.86 L-12
Mazdoor day 0.75 187.43 140.57 L-13
b) Machinery
Air Compressor 250 cfm with pneumatic breaker. hour 0.75 293.76 220.32 P&M-001
Tractor-trolley. hour 0.40 171.02 68.41 P&M-053
c) Overhead charges @ 0.3 on (a+b) 130.55
d) Contractor's profit @ 0.1 on (a+b+c) 56.57
Cost for 10 sqm = (a+d+c+d) 622.28
Rate per sqm = (a+b+c+d)/10 62.23
say 62.00
16.3 2807 Guniting concrete surface with cement mortar applied with compressor after
cleaning surface and spraying with epoxy complete as per Technical
Specification
Unit = Sq m
Taking output = 1 sqm
Assuming thickness 25 mm
a) Material
Cement kg 16.00 5.982 95.72 M-081/1000
Graded sand cum 0.04 209.13 8.37 M-005
Wire mesh 50mm x 50mm size of 3mm wire kg 2.00 30.28 60.56 M-192
Epoxy kg 0.67 282.81 189.48 M-095
Accelerator compound for guniting @ 4 per cent of weight of cement kg 0.64 112.77 72.17 M-180

Add 2 per cent of cost of material for miscellaneous consumables like 8.53
nozzles, wire brush, cotton waste etc.
b) Labour
Mate day 0.01 195.43 1.95 L-12
Mason day 0.04 247.19 9.89 L-11
Mazdoor day 0.14 187.43 26.24 L-13
c) Machinery
Compressor with guniting equipment along with accessories hour 0.10 Value #VALUE! P&M-076

d) Overhead charges @ 0.3 on (a+b+c) #VALUE!


e) Contractor's profit @ 0.1 on (a+b+c+d) #VALUE!
Rate per sqm = (a+b+c+d+e) #VALUE!
say #VALUE!
16.4 2800 Providing and inserting nipples with approved fixing compound after drilling
holes for grouting as per Technical Specifications including subsequent
cutting/removal and sealing of the hole as necessary of nipples after
completion of grouting with Cement/Epoxy
Unit = Number
Taking output = 1 No.
a) Material
Nipples each 1.00 5.64 5.64 M-129

305
Cement, fixing compound and consumables @ 15 per cent of cost of nipple 0.85

b) Labour
Mate day 0.01 195.43 1.95 L-12
Mazdoor (Skilled) labour for drilling day 0.08 218.57 17.49 L-15
Mazdoor (Skilled) labour for fixing nipple and sealing inlets day 0.08 218.57 17.49 L-15

Mazdoor for cutting and removing of nipples day 0.04 187.43 7.50 L-13
Add 10 per cent of labour cost for drilling holes etc 4.44
c) Overhead charges @ 0.3 on (a+b) 16.60
d) Contractor's profit @ 0.1 on (a+b+c) 7.20
Rate per No. = (a+b+c+d) 79.15
say 79.00
16.5 2806 Sealing of cracks/porous concrete by injection process through
nipples/Grouting complete as per Technical Specification.

A Cement Grout
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage kg 1.10 5.98 6.58 M-081/1000
Admixtures (anti shrinkage compound) @ 20 per cent of cost of cement 1.32
b) Labour
Mate day 0.08 195.43 15.63 L-12
Mazdoor (Skilled) day 0.10 218.57 21.86 L-15
Mazdoor day 0.10 187.43 18.74 L-13
c) Machinery
Grout pump with agitator and accessories hour 0.10 112.77 11.28 M-111
d) Overhead charges @ 0.3 on (a+b+c) 22.62
e) Contractor's profit @ 0.1 on (a+b+c+d) 9.80
Rate per kg = (a+b+c+d+e) 107.83
say 108.00
B Cement Mortar (1:1) Grouting
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage kg 0.55 5.98 3.29 M-081/1000
Sand including 10 per cent wastage kg 0.55 0.14 0.08 M-005/1500
Admixtures (anti shrinkage compound) @ 20 per cent of cost of cement 0.66

b) Labour
Mate day 0.08 195.43 15.63 L-12
Mazdoor (Skilled) day 0.10 218.57 21.86 L-15
Mazdoor day 0.10 187.43 18.74 L-13
c) Machinery
Grout pump with agitator and accessories hour 0.10 112.77 11.28 M-111
d) Overhead charges @ 0.3 on (a+b+c) 21.46
e) Contractor's profit @ 0.1 on (a+b+c+d) 9.30
Rate per kg = (a+b+c+d+e) 102.30
say 102.00
16.6 2800 Patching of damaged concrete surface with polymer concrete and curing
compounds, initiator and promoter, available in present formulations, to be
applied as per instructions of manufacturer and as approved by the
Engineer.

Unit = sqm
Taking output = 10 sqm for an average thickness of 25mm.

a) Labour
Mate day 0.06 195.43 11.73 L-12
Mazdoor (Skilled) day 0.75 218.57 163.93 L-15
Mazdoor day 0.75 187.43 140.57 L-13
b) Material
Pre-packed polymer concrete based on epoxy system complete with curing kg 315.00 #VALUE! #VALUE! M-145
compound, intiator and promoter including 5 per cent wastage.

c) Machinery
Grout pump with agitator and accessories hour 2.00 112.77 225.54 M-111
d) Overhead charges @ 0.3 on (a+b+c) #VALUE!
e) Contractor's profit @ 0.1 on (a+b+c+d) #VALUE!
Cost for 10 sqm = a+b+c+d+e #VALUE!
Rate per sqm = (a+b+c+d+e)/10 #VALUE!
say #VALUE!

306
Note This item is a proprietory item available in market as pre-packed polymer concrete
and is required to be applied as per instructions of the manufacturer.

307
16.7 2803 Sealing of crack / porous concrete with Epoxy Grout by injection through
nipples complete as per clause 2803.1.

Unit = kg
Taking output = 1 kg
a) Material
Epoxy including 10 per cent wastage kg 1.10 282.81 311.09 M-095
b) Labour
Mate day 0.08 195.43 15.63 L-12
Mazdoor (Skilled) day 0.10 218.57 21.86 L-15
Mazdoor day 0.10 187.43 18.74 L-13
c) Machinery
Epoxy Injection gun hour 0.10 Value #VALUE! P&M-078
d) Overhead charges @ 0.3 on (a+b+c) #VALUE!
e) Contractor's profit @ 0.1 on (a+b+c+d) #VALUE!
Rate per kg = (a+b+c+d+e) #VALUE!
say #VALUE!
16.8 2804 Applying epoxy mortar over leached, honey combed and spalled concrete
surface and exposed steel reinforcement complete as per Technical
Specification

Unit = sqm
Taking output = 10 sqm
Assume average 10mm thickness of epoxy mortar
a) Material
Epoxy resin-hardener mix for prime coat kg 2.50 481.82 1204.56 M-098
Epoxy mortar kg 2.20 169.69 373.31 M-096
Epoxy resin -hardener mix for seal coat. kg 2.00 481.82 963.65 M-098
Add 3 per cent cost of material for other consumables like acetone etc and to 76.25
cover wastage.
b) Labour
Mate day 0.04 195.43 7.82 L-12
Mazdoor (Skilled) day 0.50 218.57 109.29 L-15
Mazdoor day 0.50 187.43 93.72 L-13
c) Overhead charges @ 0.3 on (a+b) 848.57
d) Contractor's profit @ 0.1 on (a+b+c) 367.71
Cost for 10 sqm = a+b+c+d 4044.86
Rate per sqm = (a+b+c+d)/10 404.49
say 404.00
16.9 2807 Removal of defective concrete, cleaning the surface thoroughly, applying the
shotcrete mixture mechanically with compressed air under pressure,
comprising of cement, sand, coarse aggregates, water and quick setting
compound in the proportion as per clause 2807.1., sand and coarse
aggregates conforming to IS: 383 and table 1 of IS: 9012 respectively, water
cement ratio ranging from 0.35 to 0.50, density of gunite not less than 2000
kg/cum, strength not less than 25 Mpa and workmanship conforming to
clause 2807.6.

unit: sqm
Taking output = 10 sqm, 40 mm average thickness.
a) Labour
Mate day 0.04 195.43 7.82 L-12
Mazdoor day 0.50 187.43 93.72 L-13
Mazdoor (Skilled) day 0.50 218.57 109.29 L-15
b) Machinery
Air compressor 250 cfm hour 1.00 293.76 293.76 P&M-001
Shotcreteing equipment hour 1.00 Value #VALUE! P&M-076
water tanker 6 KL capacity hour 0.02 111.24 2.22 P&M-060
c) Material
Cement kg 120.00 5.982 717.89 M-081/1000
Sand cum 0.15 209.13 31.37 M-005
Coarse aggregate of size 4.75mm cum 0.15 267.20 40.08 M-024
Quick setting compound kg 2.50 99.20 247.99 M-147
Water KL 0.10 167.07 16.71 M-189
d) Overhead charges @ 0.3 on (a+b+c) #VALUE!
e) Contractor's profit @ 0.1 on (a+b+c+d) #VALUE!
Cost for 10 sqm = a+b+c+d+e #VALUE!
Rate per sqm = (a+b+c+d+e)/10 #VALUE!
say #VALUE!
16.10 2800 Applying pre-packed cement based polymer mortar of strength 45 Mpa at 28
days for replacement of spalled concrete

Unit = sqm
Taking output = 10 sqm
Assumed thickness - 10 mm
a) Material
Acrylic polymer bonding coat Litre 1.40 129.48 181.27 M-057

308
pre-packed cement based polymer mortar of strength 45 Mpa at 28 days kg 12.00 #VALUE! #VALUE! M-145

Add 3 per cent of (a ) above for wastage. #VALUE!


b) Labour

309
Mate day 0.04 195.43 7.82 L-12
Mazdoor (Skilled) day 0.50 218.57 109.29 L-15
Mazdoor day 0.50 187.43 93.72 L-13
c) Overhead charges @ 0.3 on (a+b) #VALUE!
d) Contractor's profit @ 0.1 on (a+b+c) #VALUE!
Cost for 10 sqm = a+b+c+d #VALUE!
Rate per sqm = (a+b+c+d)/10 #VALUE!
say #VALUE!
16.11 2805 Eproxy bonding of new concrete to old concrete
Unit = sqm
Taking output = 10 sqm
a) Material
Epoxy resin with pot life not less than 60-90 minutes and satisfying testing as kg 8.00 481.82 3854.58 M-098
per clause 2803.9
Add 3 per cent of (a ) above for wastage. 115.64
b) Labour
Mate day 0.04 195.43 7.82 L-12
Mazdoor (Skilled) day 0.50 218.57 109.29 L-15
Mazdoor day 0.50 187.43 93.72 L-13
c) Overhead charges @ 0.3 on (a+b) 1254.31
d) Contractor's profit @ 0.1 on (a+b+c) 543.53
Cost for 10 sqm = a+b+c+d 5978.88
Rate per sqm = (a+b+c+d)/10 597.89
say 598.00
16.12 2810 Providing external prestressing with high tensile steel wires/strands
including drilling for passage of prestessing steel, all accessories for
stressing and stressing operation and grouting complete as per drawing and
Technical Specification

Span assumed: 25 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 1 MT
Assume 12.7mm dia. Strand in 12T13 system. Weight-9.42 kg/m of cable.

a) Material
HTS strand including 5 per cent wastage and extra length for jacking tonne 1.05 62418.78 65539.72 M-119

HDPE pipes 75mm dia including 5 per cent wastage metre 112.00 152.45 17074.37 M-114
Cement for grouting kg 400.00 5.982 2392.98 M-081/1000
Tube anchorage set complete with bearing plate, permanent wedges etc each 8.00 34.35 274.83 M-187

Epoxy kg 6.00 282.81 1696.85 M-095


MS plates for deviator (where deviator blocks are not provided) tonne 2.10 48095.30 101000.14 M-179

Add 20 per cent cost of material for other materials like lead sheet, sleeves, 37595.78
deviator fixtures etc.
b) Labour
i) For making holes in the structure .
Mate day 0.24 195.43 46.90 L-12
Mazdoor Semi-skilled) day 3.00 190.43 571.29 L-14
Mazdoor day 3.00 187.43 562.29 L-13
ii) For making and fixing anchorages for cables and placement of cables .

Mate day 0.44 195.43 85.99 L-12


Blacksmith day 3.00 247.19 741.57 L-02
Mazdoor day 8.00 187.43 1499.44 L-13
iii) For prestressing
Mate/Supervisor day 0.13 195.43 25.41 L-12
Fitter day 0.70 251.19 175.83 L-08
Mazdoor day 2.65 187.43 496.69 L-13
iv) For grouting
Mate/Supervisor day 0.13 195.43 25.41 L-12
Mason day 0.70 247.19 173.03 L-11
Mazdoor day 2.65 187.43 496.69 L-13
c) Machinery
Stressing jack with pump hour 4.00 116.10 464.40 P&M-040
Grouting pump with agitator hour 1.35 112.77 152.24 M-111
d) Overhead charges @ 0.3 on (a+b+c) 69327.55
e) Contractor's profit @ 0.1 on (a+b+c+d) 30041.94
Rate per MT = (a+b+c+d+e) 330461.34
say 330461.00

310
16.13 2810 Providing external prestressing with high tensile steel wires/strands
including drilling for passage of prestessing steel, all accessories for
stressing and stressing operation and grouting complete as per drawing and
Technical Specification

Span assumed: 50 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 3.10 MT
Assume 12.7mm dia. Strand in 19T13 system. Weight-14.73 kg/m of cable.

a) Material
HTS strand including 5 per cent wastage and extra length for jacking tonne 3.10 62418.78 193498.21 M-119

HDPE pipes 90mm dia including 5 per cent wastage metre 224.00 152.45 34148.74 M-115
Cement for grouting tonne 1.01 5982.46 6042.28 M-081
Tube anchorage set complete with bearing plate, permanent wedges etc each 8.00 34.35 274.83 M-187

Epoxy kg 10.00 282.81 2828.09 M-095


MS plates for deviator (where deviator blocks are not provided) tonne 7.00 48095.30 336667.13 M-179

Add 20 per cent cost of material for other materials like lead sheet, sleeves, 114691.86
deviator fixtures etc.
b) Labour
i) For making holes in the structure .
Mate day 0.08 195.43 15.63 L-12
Mazdoor Semi-skilled) day 8.00 190.43 1523.44 L-14
Mazdoor day 8.00 187.43 1499.44 L-13
ii) For making and fixing anchorages for cables and placement of cables .

Mate day 1.28 195.43 250.15 L-12


Blacksmith day 7.00 247.19 1730.33 L-02
Mazdoor day 25.00 187.43 4685.75 L-13
iii) For prestressing
Mate/Supervisor day 0.20 195.43 39.09 L-12
Fitter day 1.00 251.19 251.19 L-08
Mazdoor day 4.00 187.43 749.72 L-13
iv) For grouting
Mate/Supervisor day 0.26 195.43 50.81 L-12
Mason day 1.50 247.19 370.79 L-11
Mazdoor day 5.00 187.43 937.15 L-13
c) Machinery
Stressing jack with pump hour 7.00 116.10 812.70 P&M-040
Grouting pump with agitator hour 3.00 112.77 338.31 M-111
d) Overhead charges @ 0.3 on (a+b+c) 210421.69
e) Contractor's profit @ 0.1 on (a+b+c+d) 91182.73
Cost for 3.10 MT = a+b+c+d+e 1003010.06
Rate per MT = (a+b+c+d+e)/3.10 323551.63
say 323552.00
16.14 2810 Providing external prestressing with high tensile steel wires/strands
including drilling for passage of prestessing steel, all accessories for
stressing and stressing operation and grouting complete as per drawing and
Technical Specification

Span assumed: 100 m


No. of cables: 6 no.
No. of anchorages : 12 no.
Unit = MT
Taking output = 9.28 MT
Assume 12.7mm dia. Strand in 19T13 system. Weight-14.73 kg/m of cable.

a) Material
HTS strand including 5 per cent wastage and extra length for jacking tonne 9.28 62418.78 579246.24 M-119

HDPE pipes 90 mm dia including 5 per cent wastage metre 672.00 152.45 102446.23 M-115
Cement for grouting tonne 3.04 5982.46 18186.67 M-081
Tube anchorage set complete with bearing plate, permanent wedges etc each 12.00 34.35 412.24 M-187

Epoxy kg 14.00 282.81 3959.33 M-095


MS plates for deviator (where deviator blocks are not provided) tonne 20.00 48095.30 961906.09 M-179

Add 20 per cent cost of material for other materials like lead sheet, sleeves, 333231.36
deviator fixtures etc.

311
b) Labour
i) For making holes in the structure .
Mate day 1.72 195.43 336.14 L-12

312
Mazdoor Semi-skilled) day 18.00 190.43 3427.74 L-14
Mazdoor day 25.00 187.43 4685.75 L-13
ii) For making and fixing anchorages for cables and placement of cables .

Mate day 4.00 195.43 781.72 L-12


Blacksmith day 20.00 247.19 4943.80 L-02
Mazdoor day 80.00 187.43 14994.40 L-13
iii) For prestressing
Mate/Supervisor day 0.30 195.43 58.63 L-12
Fitter day 1.50 251.19 376.79 L-08
Mazdoor day 6.00 187.43 1124.58 L-13
iv) For grouting
Mate/Supervisor day 1.00 195.43 195.43 L-12
Mason day 5.00 247.19 1235.95 L-11
Mazdoor day 20.00 187.43 3748.60 L-13
c) Machinery
Stressing jack with pump hour 10.00 116.10 1161.00 P&M-040
Grouting pump with agitator hour 10.00 112.77 1127.71 M-111
d) Overhead charges @ 0.3 on (a+b+c) 611275.92
e) Contractor's profit @ 0.1 on (a+b+c+d) 264886.23
Cost for 9.28 MT = a+b+c+d+e 2913748.55
Rate per MT = (a+b+c+d+e)/9.28 313981.52
say 313982.00
16.15 2808 Replacement of Bearings complete as per Technical Specification
Unit = No
Taking output = 3 No.
Lifting of superstructure span by jacking up from below i.e. by placing the jacks on
pier/abutment caps for span length of 30m.

a) Lifting of span
i) Hire charges for jack of 40 tonne lifting capacity. each 3.00 758.16 2274.48 P&M-084
Mate day 0.64 195.43 125.08 L-12
Mazdoor (Skilled) day 4.00 218.57 874.28 L-15
Mazdoor day 12.00 187.43 2249.16 L-13
v) Wooden packing cum 0.15 #VALUE! #VALUE! M-195
b) Replacement of bearing
Cost of bearing. each 3.00 55883.28 167649.83 M-065
c) Overhead charges @ 0.3 on (a+b) #VALUE!
d) Contractor's profit @ 0.1 on (a+b+c) #VALUE!
Cost of repair of 3 bearings = a+b+c+d #VALUE!
Rate of repair per bearing = (a+b+c+d)/3 #VALUE!
say #VALUE!
Note The work entails replacement of all the bearings on one side of the span.

16.16 2808 Rectification of Bearings as per Technical Specifications

Unit = 1 No
Taking output = 3 No.
a) Lifting of superstructure span by jacking up from below i.e. by placing
the jacks on pier/abutment caps for span length of 30m.

i) Hire charges for jack of 40 tonne lifting capacity. each 3.00 758.16 2274.48 P&M-084
ii) Mate day 0.64 195.43 125.08 L-12
iii) Mazdoor (Skilled) day 4.00 218.57 874.28 L-15
iv) Mazdoor day 12.00 187.43 2249.16 L-13
v) Wooden packing cum 0.15 #VALUE! #VALUE! M-195
b) Cost of parts to be replaced for 3 bearings. each 3.00 #VALUE! #VALUE! M-064
c) Overhead charges @ 0.3 on (a+b) #VALUE!
d) Contractor's profit @ 0.1 on (a+b+c) #VALUE!
Cost of repair of 3 bearings = a+b+c+d #VALUE!
Rate of repair per bearing = (a+b+c+d)/3 #VALUE!
say #VALUE!
Note The rectification of 3 bearings included in this analysis are on the same side of the
span.
16.17 Replacement of Expansion Joints complete as per drawings

Unit -1 RM
Taking output = 12 RM
a) Material
Epoxy for bonding new concrete to old concrete @ 0.8 kg/sqm kg 9.60 282.81 2714.97 M-095
M-30 grade cement concrete excluding OH & CP (Rate as per items 14.1 C (i) cum 3.60 4414.00 15890.40 Item 14.1(C)

b) Labour

313
Removal of old expansion joint including breaking of concrete, cutting of lugs and
shifting of broken material etc.
Mate day 0.26 195.43 50.81 L-12
Mazdoor day 6.00 187.43 1124.58 L-13
Mazdoor (Skilled) day 0.50 218.57 109.29 L-15
c) Overhead charges @ 0.3 on (a+b) 5967.01
d) Contractor's profit @ 0.1 on (a+b+c) 2585.71
Cost for replacement of 12 RM = a+b+c+d 28442.76
Rate per RM = (a+b+c+d)/12 2370.23
say 2370.00
Note The rate for the installation of new expansion joints may be taken from the chapter
on superstructure. Broken concrete will have to be replaced which has been
included in this analysis.

16.18 Replacement of Damaged Concrete Railing.


Unit = RM
Taking output = 10 RM
a) Labour
Labour for dismantling old railing and disposal of dismantled material.

Mate day 0.20 195.43 39.09 L-12


Mazdoor day 5.00 187.43 937.15 L-13
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.00 171.02 171.02 P&M-053
c) Overhead charges @ 0.3 on (a+b) 344.18
d) Contractor's profit @ 0.1 on (a+b+c) 149.14
Cost for 10 m = a+b+c+d 1640.57
Rate per metre = (a+b+c+d)/10 164.06
say 164.00
Note The rate for the provision of new railing may be adopted from the chapter on
superstructure.
16.19 Replacement of Crash Barrier.
Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and disposal of dismantled material.

Mate day 0.40 195.43 78.17 L-12


Mazdoor day 10.00 187.43 1874.30 L-13
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.00 171.02 171.02 P&M-053
c) Overhead charges @ 0.3 on (a+b) 637.05
d) Contractor's profit @ 0.1 on (a+b+c) 276.05
Cost for 10 m = a+b+c+d 3036.59
Rate per metre = (a+b+c+d)/10 303.66
say 304.00
Note The rate for the construction of new crash barrier may be adopted from chapter 8 on
Traffic and Transportation.
16.20 Replacement of Damaged Mild Steel Railing
Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and disposal of dismantled material.

Mate day 0.16 195.43 31.27 L-12


Mazdoor day 4.00 187.43 749.72 L-13
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.00 171.02 171.02 P&M-053
c) Overhead charges @ 0.3 on (a+b) 285.60
d) Contractor's profit @ 0.1 on (a+b+c) 123.76
Cost for 10 m = a+b+c+d 1361.37
Rate per metre = (a+b+c+d)/10 136.14
say 136.00
16.21 Repair of Crash Barrier
Repair of concrete crash barrier with cement concert of M-30 grade by cutting and
trimming the damaged portion to a regular shape, cleaning the area to be repaired
thoroughly, applying cement concert after erection of proper form work.

Unit = Running meter.


Taking output = 10 M.
It is assumed that damage is to the extent of 10 per cent of the volume of
concrete .This will require 0.30 cum of concrete.

a) Manpower*
Mate day 0.04 195.43 7.82 L-12

314
Mazdoor day 1.00 187.43 187.43 L-13
* For dismantling and trimming the surface to a regular shape and removal of
damaged material.
b) Material
M-30 grade cement concrete excluding OH & CP (Rate as per items 14.1 C (i) cum 0.30 4414.00 1324.20 Item 14.1(C)

DIR used item


This may be priced based on the rate given the chapter of superstructure.

c) Overhead charges @ 0.3 on (a) 455.83


d) Contractor's profit @ 0.1 on (a+c) 197.53

Cost for 10 m = a+b+c+d 2172.81


Rate per m = (a+b+c+d)/10 217.28
say 217.00
16.22 Repair of RCC Railing

Carrying out repair of RCC M30 railing to bring it to the original shape.

Unit = Running meter.


Taking output = 10 M.
It is assumed that damage is to the extent of 10 per cent .
a) Material
M-30 grade cement concrete excluding OH & CP (Rate as per items 14.1 C (i) cum 0.10 4414.00 441.40 Item 14.1(C)

HYSD bar reinforcement Rate as per item No 14.2(Excluding OH & CP) tonne 0.013 49225.00 639.93 Item 14.2 A

DIR used item


b) Labour*
Mate day 0.016 195.43 3.13 L-12
mazdoor day 0.20 187.43 37.49 L-13
* For dismantling and trimming the surface to a regular shape and removal of
damaged material.
c) Overhead charges @ 0.3 on (b) 336.58
d) Contractor's profit @ 0.1 on (b+c) 145.85
Cost for 10 m = a+b+c+d 1604.37
Rate per m = (a+b+c+d)/10 160.44
say 160.00

16.23 Repair of Steel Railing


Repair of steel railing to bring it to the original shape
It is assumed that the damage to the steel railing is to the extent of 10 per cent .

Unit = Running meter.


Taking output = 10 M.
a) Material
Mild steel ISMC series kg 29.00 48.10 1394.76 M-179/1000
Flat iron kg 10.00 48.10 480.95 M-179/1000
MS Bolt and nuts kg 1.00 45.42 45.42 M-130
Add 5 per cent of cost of material for painting. 96.06
b) Labour
Mate day 0.016 195.43 3.13 L-12
Mazdoor (Skilled) day 0.20 218.57 43.71 L-15
Mazdoor day 0.20 187.43 37.49 L-13
c) Overhead charges @ 0.3 on (a+b) 630.46
d) Contractor's profit @ 0.1 on (a+b+c) 273.20
Cost of repair for10m = a+b+c+d 3005.18
Cost of meter = (a+b+c+d)/10 300.52
say 301.00

315
Sub - Analysis_B

Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
3.1 301 Excavation in Soil by Manual Means .
SUB Excavation for roadway in soil using manual means
ANA -B including loading in truck for carrying of cut earth to
(1) embankment site with all lifts and lead upto1000
metres.Including royality @ Rs. 24.00 per cum but
excluding the cost of watering , rolling & compaction

Note In case there is a situation where the cross-


section is of cut and fill and cut earth is
required to be used in embankment in the
immediate vicinity, the item of carriage in the
truck shall be omitted.

Unit = cum
Taking output = 120 cum
a) Labour
Mate day 1.800 195.43 351.77 L-12
Mazdoor day 45.000 187.43 8434.35 L-13
b) Machinery
Truck 5.5 cum capacity hour 10.000 0.00 0.00 P&M-057
c) Overhead charges @ 0.1 on (a+b) 878.61

d) Contractor's profit @ 0.1 on (a+b+c) 966.47


Cost of 120 cum = a+b+c+d 10631.21
Rate per cum = (a+b+c+d)/120 88.59
Royality @ Rs. 24.00 per Cum 24.00
Rate per cum say 113.00

3.1 301 Excavation in Soil by Manual Means .


SUB Excavation for roadway in soil using manual means
ANA -B including loading in truck for carrying of cut earth to
(2) embankment site with all lifts and lead upto1000
metres.
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 1.800 195.43 351.77 L-12
Mazdoor day 45.000 187.43 8434.35 L-13
b) Machinery
Truck 5.5 cum capacity hour 10.000 752.00 7520.00 P&M-057
Smooth wheel roller @ 70 cum per hour hour 1.500 649.00 973.50 P&M-044
Water Tanker @ 6.0 KL capicity hour 0.800 111.24 88.99 P&M-060
c) Materials
Cost of water KL 4.800 167.07 801.93 M-189
d) Overhead charges @ 0.1 on (a+b+c) 1817.05
e) Contractor's profit @ 0.1 on (a+b+c+d) 1998.76
Cost of 120 cum = a+b+c+d+e 21986.36
Rate per cum = (a+b+c+d+e)/120 183.22
Royality @ Rs. 24.00 per Cum 24.00
Rate per cum say 207.00

3.2 301 Excavation in Ordinary Rock by Manual Means

SUB Excavation in ordinary rock using manual means


ANA -B including loading in a truck and carrying of excavated
material to embankment site with in all lifts and leads
upto 1000 metres (including royality @ Rs. 24.00 per
cum but excluding watering, rolling & compaction)

Unit = cum
Taking output = 120 cum

RCD/SOR_2nd Edition
Sub - Analysis_B

a) Labour
Mate day 2.800 195.43 547.20 L-12
Mazdoor day 70.000 187.43 13120.10 L-13
b) Machinery
c) Overhead charges @ 0.1 on (a+b) 1366.73
d) Contractor's profit @ 0.1 on (a+b+c) 1503.40
Cost for 120 cum = a+b+c+d 16537.44
Rate per cum = (a+b+c+d)/120 137.81
Royality @ Rs. 24.00 per Cum 24.00
Rate per cum 161.81
say 162.00
Note In case there is a situation where the cross-section is
of cut and fill and cut earth is required to be used in
embankment in the immediate vicinity, the item of
carriage in the truck shall be omitted.
3.2 301 Excavation in Ordinary Rock by Manual Means

SUB Excavation in ordinary rock using manual means


ANA -B including loading in a truck and carrying of excavated
material to embankment site with in all lifts and leads
upto 1000 metres (including royality @ Rs. 30.00 per
cum, watering, rolling & compaction - from immediate
vicinity)

Unit = cum
Taking output = 120 cum
a) Labour
Mate day 2.800 195.43 547.20 L-12
Mazdoor day 70.000 187.43 13120.10 L-13
b) Machinery
Truck 5.5 cum capacity hour 10.000 752.00 7520.00 P&M-057
Smooth wheel roller @ 70 cum per hour hour 1.500 649.00 973.50 P&M-044
Water Tanker @ 6.0 KL capicity hour 0.800 111.24 88.99 P&M-060
c) Materials
Cost of water KL 4.800 167.07 801.93 M-189
d) Overhead charges @ 0.1 on (a+b+c) 2305.17
e) Contractor's profit @ 0.1 on (a+b+c+d) 2535.69
Cost for 120 cum = a+b+c+d 27892.59
Rate per cum = (a+b+c+d)/120 232.44
Royality @ Rs. 24.00 per Cum 24.00
Rate per cum 256.44
say 256.00
3.6 301 Excavation in Soil using Hydraulic Excavator
CK 90 and Tippers with Disposal upto 1000
metres.
SUB Excavation for roadwork in soil with hydraulic
ANA -B excavator of 0.9 cum bucket capacity including
cutting and loading in tippers, trimming bottom and
side slopes, in accordance with requirements of
lines, grades and cross sections, and transporting to
the embankment location within all lifts and lead upto
1000m (including royality @ Rs. 24.00 per cum,
watering, rolling & compaction)

Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @ hour 6.000 1516.32 9097.92 P&M-026
60 cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 16.000 846.00 13536.00 P&M-048
Smooth wheel roller @ 70 cum per hour hour 4.500 649.00 2920.50 P&M-044
Water Tanker @ 6.0 KL capicity hour 2.400 111.24 266.98 P&M-060
c) Materials
Cost of water KL 14.400 167.07 2405.78 M-189
d) Overhead charges @ 0.1 on (a+b+c) 2861.77
e) Contractor's profit @ 0.1 on (a+b+c+d) 3147.94

RCD/SOR_2nd Edition
Sub - Analysis_B

Cost for 360 cum = a+b+c+d 34627.38


Rate per cum = (a+b+c+d)/360 96.19
Royality @ Rs. 24.00 per Cum 24.00
Rate per cum 120.19
say 120.00
3.7 301 Excavation in Ordinary Rock using Hydraulic
Excavator CK-90 and Tippers with Disposal
upto 1000 metres.

SUB Excavation for roadway in ordinary rock with


ANA -B hydraulic excavator of 0.9 cum bucket capacity
including cutting and loading in tippers, transporting
to embankment site within all lifts and lead upto 1000
m, trimming bottom and side slopes in accordance
with requirements of lines, grades and cross sections
(including royality @ Rs. 24.00 per cum , watering,
rolling & compaction)

Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity hour 6.000 1516.32 9097.92 P&M-026
@ 36 cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 11.000 846.00 9306.00 P&M-048
Smooth wheel roller @ 70 cum per hour hour 3.000 649.00 1947.00 P&M-044
Water Tanker @ 6.0 KL capicity hour 1.600 111.24 177.98 P&M-060
c) Materials
Cost of water KL 9.600 167.07 1603.85 M-189
d) Overhead charges @ 0.1 on (a+b+c) 2252.33
e) Contractor's profit @ 0.1 on (a+b+c+d) 2477.56
Cost for 240 cum = a+b+c+d+e 27253.14
Rate per cum = (a+b+c+d+e)/240 113.55
Royality @ Rs. 24.00 per Cum 24.00
Rate per cum 137.55
say 138.00
3.10 301 Excavation in Marshy Soil
SUB Excavation for roadway in marshy soil with hydraulic
ANA -B excavator 0.9 cum bucket capacity including cutting
and loading in tippers and disposal with in all lifts and
lead upto 1000 metres, trimming of bottom and side
slopes in accordance with requirements of lines,
grades and cross sections (including royality @ Rs.
24.00 per cum , watering, rolling & compaction)

Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery
Hydraulic excavator 0.90 cum bucket capacity hour 6.000 1516.32 9097.92 P&M-026
@ 50 cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 13.640 846.00 11539.44 P&M-048
Smooth wheel roller @ 70 cum per hour hour 3.750 649.00 2433.75 P&M-044
Water Tanker @ 6.0 KL capicity hour 2.000 111.24 222.48 P&M-060
c) Materials
Cost of water KL 12.000 167.07 2004.82 M-189
d) Overhead charges @ 0.1 on (a+b+c) 2568.89
e) Contractor's profit @ 0.1 on (a+b+c+d) 2825.78
Cost for 300 cum = a+b+c+d+e 31083.57
Rate per cum = (a+b+c+d+e)/300 103.61
Royality @ Rs. 24.00 per Cum 24.00
Rate per cum 127.61
say 128.00
3.16 305 Construction of Embankment with Material
obtained from Borrowpits

RCD/SOR_2nd Edition
Sub - Analysis_B

SUB Construction of embankment with approved material


ANA -B obtained from borrow pits with all lifts and leads,
transporting to site, spreading, grading to required
slope and compacting to meet requirement of table
300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor day 1.000 187.43 187.43 L-13
b) Machinery
Hydraulic Excavator1 cum bucket capacity @ hour 1.670 1516.32 2532.25 P&M-026
60 cum per hour
Tipper 10 tonne capacity tonne.km 160 x L 2.68 428.54 P&M-047
Add 10 per cent of cost of carriage to cover 42.85
cost of loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3135.24 1567.62 P&M-014

Motor grader for grading @ 100 cum per hour hour 1.000 2450.00 2450.00 P&M-032

Water tanker6 KL capacity hour 4.000 111.24 444.96 P&M-060


Smooth wheel roller 8-10 tonnes @ 70 cum per hour 1.430 649.00 928.07 P&M-044
hour
c) Material
Cost of water KL 24.000 167.07 4009.64 M-189
Compensation & Royality for earth taken from cum 100.000 25.10 2510.00 M-092
private land
d) Overhead charges @ 0.1 on (a+b+c) 1510.92
e) Contractor's profit @ 0.1 on (a+b+c+d) 1662.01
Cost for 100 cum = a+b+c+d+e 18282.12
Rate per cum = (a+b+c+d+e)/100 182.82
say 183.00
Compensation for earth will vary from place to place
and will have to be assessed realistically as per
particular ground situation. In case earth is available
from Govt. land, compensation for earth will not be
required. The position is required to be clearly stated
in the cost estimate.

3.17 305 Construction of Embankment with Material


Deposited from Roadway Cutting
SUB Construction of embankment with approved
ANA -B materials deposited at site from roadway cutting and
excavation from drain and foundation of other
structures graded and compacted to meet
requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.020 195.43 3.91 L-12
Mazdoor day 0.500 187.43 93.72 L-13
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3135.24 1567.62 P&M-014

Motor grader for grading @ 100 cum per hour hour 1.000 2450.00 2450.00 P&M-032

Water tanker6 KL capacity hour 4.000 111.24 444.96 P&M-060


Smooth wheel roller 8-10 tonnes @ 56 cum per hour 1.430 649.00 928.07 P&M-044
hour
c) Material
Cost of water KL 24.000 167.07 4009.64 M-189
d) Overhead charges @ 0.1 on (a+b+c) 949.79
e) Contractor's profit @ 0.1 on (a+b+c+d) 1044.77 M-189
Rate for 100 cum = a+b+c+d+e 11492.47 M-092
Rate per cum = (a+b+c+d+e)/100 114.92

say 115.00

RCD/SOR_2nd Edition
Sub - Analysis_B

In case the earth cutting is done by dozer and


pushed for filling in the embankment, the input of
dozer in the cost of embankment shall be deleted as
the same is already provided in the cost of
excavation. However, if the earth is dumped by
tippers from roadway cutting, the input of dozer for
spreading is required to be provided.

3.18 305 Construction of Subgrade and Earthen


Shoulders
SUB Construction of sub-grade and earthen shoulders
ANA -B with approved material obtained from borrow pits
with all lifts & leads, transporting to site, spreading,
grading to required slope and compacted to meet
requirement of table No. 300-2

Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 195.43 7.82 L-12
Mazdoor day 1.000 187.43 187.43 L-13
b) Machinery
Hydraulic excavator1 cum bucket capacity @ hour 1.670 1516.32 2532.25 P&M-026
60 cum per hour
Tipper 10 tonne capacity tonne.km 175xL 2.68 468.72 P&M-047
Add 10 per cent of cost of carriage to cover 46.87
cost of loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 3135.24 1567.62 P&M-014

Motor grader for grading @ 50 cum per hour hour 2.000 2450.00 4900.00 P&M-032
Water tanker with 6 km lead hour 4.000 111.24 444.96 P&M-060
Smooth wheel roller 8-10 tonnes @ 56 cum per hour 1.790 649.00 1161.71 P&M-044
hour
c) Material
Cost of water KL 24.000 167.07 4009.64 M-189
Compensation & Royality for earth taken from private cum 100.000 25.10 2510.00 M-092
land
d) Overhead charges @ 0.1 on (a+b+c) 1783.70
e) Contractor's profit @ 0.1 on (a+b+c+d) 1962.07
Cost for 100 cum = a+b+c+d+e 21582.80
Rate per cum = (a+b+c+d+e)/100 215.83
say 216.00
3.19 305.3.4 Compacting Original Ground
Compacting original ground supporting sub-
grade
SUB Case-I Loosening of the ground upto a level of 500 mm
ANA -B below the sub-grade level, watered, graded and
compacted in layers to meet requirement of table
300-2 for sub-grade construction.
Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.120 195.43 23.45 L-12
Mazdoor day 3.000 187.43 562.29 L-13
b) Machinery
Tractor with ripper attachment hour 9.000 285.12 2566.08 P&M-055
Motor grader for grading hour 6.000 2450.00 14700.00 P&M-032
Water tanker 6 KL capacity hour 4.000 111.24 444.96 P&M-060
Smooth wheel roller 8-10 tonnes @ 56 cum per hour 10.710 649.00 6950.79 P&M-044
hour
c) Material
Cost of water KL 24.000 167.07 4009.64 M-189
d) Overhead charges @ 0.1 on (a+b+c) 2925.72
e) Contractor's profit @ 0.1 on (a+b+c+d) 3218.29
Cost for 600 cum = a+b+c+d+e 35401.22
Rate per cum = (a+b+c+d+e)/600 59.00
say 59.00

RCD/SOR_2nd Edition
Sub - Analysis_B

3.19 Compacting original ground supporting


embankment
SUB Case- Loosening, leveling and Compacting original ground
ANA -B II supporting embankment to facilitate placement of
first layer of embankment, scarified to a depth of 150
mm, mixed with water at OMC and then compacted
by rolling so as to achieve minimum dry density as
given in Table 300-2 for embankment construction.

Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor day 2.000 187.43 374.86 L-13
b) Machinery
Tractor with ripper attachment hour 6.000 285.12 1710.72 P&M-055
Smooth wheel roller 8-10 tonnes @ 56 cum per hour 10.710 649.00 6950.79 P&M-044
hour
Water tanker6 KL capacity hour 4.000 111.24 444.96 P&M-060
c) Material
Cost of water KL 24.000 167.07 4009.64 M-189
d) Overhead charges @ 0.1 on (a+b+c) 1350.66
e) Contractor's profit @ 0.1 on (a+b+c+d) 1485.73
Cost for 600 cum = (a+b+c+d+e) 16342.99
Rate per sqm = (a+b+c+d+e)/600 27.24
say 27.00
5.11 512 Close Graded Premix Surfacing/Mixed Seal
Surfacing
Mechanical means using HMP of appropriate
capacity not less than 75 tonnes/hour.
Sub - Case I Providing, laying and rolling of close-graded premix
Analysis surfacing material of 20 mm thickness composed of
for Type 11.2 mm to 0.09 mm (Type-a) or 13.2 mm to 0.09
'B" mm (Type-b) aggregates using penetration grade
bitumen to the required line, grade and level to serve
as wearing course on a previously prepared base,
including mixing in a suitable plant, laying and rolling
with a Smooth wheeled roller 8-10 tonne capacity,
and finishing to required level and grade.

Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour
Mate day 0.840 195.43 164.16 L-12
Mazdoor working with HMP, road sweeper, day 16.000 187.43 2998.88 L-13
paver and roller
Skilled mazdoor for checking line & levels day 5.000 218.57 1092.85 L-15
b) Machinery
i) HMP of appropicate capacity - 75 t per hour hour 6.000 32155.00 192930.00 P&M-022
ii) Electric Generator Set 250 KVA hour 6.000 3101.00 18606.00 P&M-081
iii) Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
iv) Tipper 10 tonne capacity tonne.km 450 x L 2.68 1205.28 Lead =1 km &
P&M-047
Add 10 per cent of cost of carriage to cover cost of 120.53
loading and unloading
v) Paver finisher hydrostatic with sensor hour 6.000 3046.00 18276.00 P&M-034
attachment
iv) Smooth wheeled8-10 tonnes weight hour 6.000 649.00 3894.00 P&M-044
c) Material
Type - B

RCD/SOR_2nd Edition
Sub - Analysis_B

Bitumen @ 19 kg per 10 sqm tonne 19.480 39879.31 776848.98 M-074


Stone crushed aggregates 13.2 mm to 0.09 cum 276.750 641.56 177551.54 M-042
mm @ 0.27 cum per 10 sqm
d) Overhead charges @ 0.1 on (a+b+c) 120057.62
e) Contractor's profit @ 0.1 on (a+b+c+d) 132063.38
Cost for 10250 sqm = a+b+c+d+e 1452697.23
Rate per sqm = (a+b+c+d+e)/10250 141.73
For Type 'B' say 142.00
With Smooth wheel Roller
4.9 404 Water Bound Macadam
SUB Providing, laying, spreading and compacting stone
ANA -B aggregates of specific sizes to water bound
macadam specification including spreading in
uniform thickness, hand packing, rolling with 3
wheeled steel/ vibratory roller 8-10 tonnes in stages
to proper grade and camber, applying and brooming
requisite type of screening/ binding Materials to fill up
the interstices of coarse aggregate, watering and
compacting to the required density.

By Manual Means
A Unit = cum
Taking output = 360 cum
a) Labour
Mate day 10.080 195.43 1969.93 L-12
Mazdoor skilled day 2.000 218.57 437.14 L-15
Mazdoor day 250.000 187.43 46857.50 L-13
b) Machinery
Smooth 3 wheeled steel roller @ 30cum/hour hour 12.000 649.00 7788.00 P&M-044
Water tanker 6 KL capacity hour 24.000 111.24 2669.76 P&M-060
c) Material ( Refer table 400 - 7, 8 & 9 )
4.9A Grading-I
(i) Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 cum 435.600 477.96 208200.49 M-039
sqm for compacted thickness of 100 mm

Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per cum 97.200 641.56 62359.56 M-042
10 sqm
OR
Crushable type such as Moorum or Gravel for cum 108.000 122.64 13244.66 M-007
grading-I @ 0.30 cum per 10 sqm

Binding material
Binding Material @ 0.08cum per 10 sqm for cum 28.800 122.64 3531.91 M-007
grading I material
Cost of water KL 144.000 167.07 24057.82 M-189
4.9A (i) Using Scrining Crushable type such as Moorum or Gravel
(a) d) Overhead charges @ 0.1 on (a+b+c) 30522.53
e) Contractor's profit @ 0.1 on (a+b+c+d) 33574.78
Cost for 360 cum = a+b+c+d+e 369322.62
Rate per cum = (a+b+c+d+e)/360 1025.90
say 1026.00
OR
4.9A (i) Using Scrining Type-A (13.2mm agg.)
(b) d) Overhead charges @ 0.1 on (a+b+c) 35787.21
e) Contractor's profit @ 0.1 on (a+b+c+d) 39365.93
Cost for 360 cum = a+b+c+d+e 433025.26

RCD/SOR_2nd Edition
Sub - Analysis_B

Rate per cum = (a+b+c+d+e)/360 1202.85


say 1203.00
4.9A Grading-II
(ii) Aggregate
Grading-II 63 mm to 45 mm /Grading-III 53 mm cum 435.600 547.62 238543.51 M-038
to 22.4 mm@ 0.91 cum per 10 sqm for
compacted thickness of 75 mm

Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per cum 57.600 641.56 36953.82 M-042
10 sqm
OR
Crushable type such as Moorum or Gravel for cum 105.590 122.64 12949.10 M-007
grading II &III @ 0.22 cum per 10 sqm
OR
Type B11.2 mm for grading-III @ 0.18 cum per cum 86.400 516.77 44649.10 M-041
10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for cum 28.800 122.64 3531.91 M-007
grading II material
Cost of water KL 144.000 167.07 24057.82 M-189
4.9A (ii) Using Scrining Crushable type such as Moorum or Gravel
(a) d) Overhead charges @ 0.1 on (a+b+c) 33527.28
e) Contractor's profit @ 0.1 on (a+b+c+d) 36880.00
Cost for 360 cum = a+b+c+d+e 405680.05
Rate per cum = (a+b+c+d+e)/360 1126.89
say 1127.00
OR
4.9A (ii) Using Scrining Type-A (13.2mm agg.)
(b) d) Overhead charges @ 0.1 on (a+b+c) 36280.94
e) Contractor's profit @ 0.1 on (a+b+c+d) 39909.03
Cost for 360 cum = a+b+c+d+e 438999.36
Rate per cum = (a+b+c+d+e)/360 1219.44
say 1219.00
4.9A (ii) Using Scrining Type-B (11.2mm agg.)
(c) d) Overhead charges @ 0.1 on (a+b+c) 37050.47
e) Contractor's profit @ 0.1 on (a+b+c+d) 40755.51
Cost for 360 cum = a+b+c+d+e 448310.65
Rate per cum = (a+b+c+d+e)/360 1245.31
say 1245.00
4.9A Grading-III
(iii) Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per cum 435.600 567.52 247212.94 M-036
10 sqm for compacted thickness of 75 mm

Stone Screening
Type B 11.2 mm for grading-III @ 0.18 cum per cum 86.400 516.77 44649.10 M-041
10 sqm
OR
Crushable type such as Moorum or Gravel for cum 105.590 122.64 12949.10 M-007
grading II &III @ 0.22 cum per 10 sqm

Binding material
Binding Material @ 0.06cum per 10 sqm for cum 28.800 122.64 3531.91 M-007
grading II material
Cost of water KL 144.000 167.07 24057.82 M-189
4.9A (iii) Using Scrining Crushable type such as Moorum or Gravel

RCD/SOR_2nd Edition
Sub - Analysis_B

(a) d) Overhead charges @ 0.1 on (a+b+c) 34394.22


e) Contractor's profit @ 0.1 on (a+b+c+d) 37833.64
Cost for 360 cum = a+b+c+d+e 416170.06
Rate per cum = (a+b+c+d+e)/360 1156.03
say 1156.00
OR
4.9A (iii) Using Scrining Type-B (11.2mm agg.)
(b) d) Overhead charges @ 0.1 on (a+b+c) 37917.41
e) Contractor's profit @ 0.1 on (a+b+c+d) 41709.15
Cost for 360 cum = a+b+c+d+e 458800.67
Rate per cum = (a+b+c+d+e)/360 1274.45
say 1274.00
( Anyone of the aggregate grading, screening and
binding material may be used as per design)
4.9 By Mechanical Means:
SUB B Unit = cum
ANA -B
Taking output = 360 cum
a) Labour
Mate day 0.680 195.43 132.89 L-12
Mazdoor skilled day 2.000 218.57 437.14 L-15
Mazdoor day 15.000 187.43 2811.45 L-13
b) Machinery
Motor grader 110 HP @ 50cum/hr. for spreading hour 7.200 2450.00 17640.00 P&M-032

Smooth 3 wheeled steel roller @ 30cum/hr. hour 12.000 649.00 7788.00 P&M-044
Water tanker 6 KL capacity hour 24.000 111.24 2669.76 P&M-060
c) Material ( Refer table 400 - 7, 8 & 9 )
4.9B Grading - I
(i) Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 cum 435.600 477.96 208200.49 M-039
sqm for compacted thickness of 100 mm

Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per cum 97.200 641.56 62359.56 M-042
10 sqm
OR
Crushable type such as Moorum or Gravel for cum 108.000 122.64 13244.66 M-007
grading-I @ 0.30 cum per 10 sqm
Binding material

Binding Material @ 0.08cum per 10 sqm for cum 28.800 122.64 3531.91 M-007
grading I material
Cost of water KL 144.000 167.07 24057.82 M-189
4.9B (i) Using Scrining Crushable type such as Moorum or Gravel
(a) d) Overhead charges @ 0.1 on (a+b+c) 27698.22

e) Contractor's profit @ 0.1 on (a+b+c+d) 30468.04

Cost for 360 cum = a+b+c+d+e 335148.47


Rate per cum = (a+b+c+d+e)/360 930.97
say 931.00
OR
4.9B (i) Using Scrining Type-A (13.2mm agg.)
(b) d) Overhead charges @ 0.1 on (a+b+c) 32962.90
e) Contractor's profit @ 0.1 on (a+b+c+d) 36259.19
Cost for 360 cum = a+b+c+d+e 398851.12

RCD/SOR_2nd Edition
Sub - Analysis_B

Rate per cum = (a+b+c+d+e)/360 1107.92


say 1108.00
4.9B Grading - II
(ii) Aggregate
Grading-II 63 mm to 45 mm /Grading-III 53 mm cum 435.600 547.62 238543.51 M-038
to 22.4 mm@ 0.91 cum per 10 sqm for
compacted thickness of 75 mm

Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per cum 57.600 641.56 36953.82 M-042
10 sqm
OR
Crushable type such as Moorum or Gravel for cum 105.590 122.64 12949.10 M-007
grading II &III @ 0.22 cum per 10 sqm
OR
Type B11.2 mm for grading-III @ 0.18 cum per cum 86.400 516.77 44649.10 M-041
10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for cum 28.800 122.64 3531.91 M-007
grading II material
Cost of water KL 144.000 167.07 24057.82 M-189
4.9B (ii) Using Scrining Crushable type such as Moorum or Gravel
(a) d) Overhead charges @ 0.1 on (a+b+c) 30702.97
e) Contractor's profit @ 0.1 on (a+b+c+d) 33773.26
Cost for 360 cum = a+b+c+d+e 371505.91
Rate per cum = (a+b+c+d+e)/360 1031.96
say 1032.00
OR
4.9B (ii) Using Scrining Type-A (13.2mm agg.)
(b) d) Overhead charges @ 0.1 on (a+b+c) 33456.63
e) Contractor's profit @ 0.1 on (a+b+c+d) 36802.29
Cost for 360 cum = a+b+c+d+e 404825.22
Rate per cum = (a+b+c+d+e)/360 1124.51
say 1125.00
4.9B (ii) Using Scrining Type-B (11.2mm agg.)
(c) d) Overhead charges @ 0.1 on (a+b+c) 34226.16
e) Contractor's profit @ 0.1 on (a+b+c+d) 37648.77
Cost for 360 cum = a+b+c+d+e 414136.51
Rate per cum = (a+b+c+d+e)/360 1150.38
say 1150.00
4.9B Grading - III
(iii) Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per cum 435.600 567.52 247212.94 M-036
10 sqm for compacted thickness of 75 mm

Stone Screening
Type B11.2 mm for grading-III @ 0.18 cum per cum 86.400 516.77 44649.10 M-041
10 sqm
OR
Crushable type such as Moorum or Gravel for cum 105.590 122.64 12949.10 M-007
grading II &III @ 0.22 cum per 10 sqm

Binding material
Binding Material @ 0.06cum per 10 sqm for cum 28.800 122.64 3531.91 M-007
grading II material
Cost of water KL 144.000 167.07 24057.82 M-189

RCD/SOR_2nd Edition
Sub - Analysis_B

4.9B (iii) Using Scrining Crushable type such as Moorum or Gravel


(a) d) Overhead charges @ 0.1 on (a+b+c) 31569.91
e) Contractor's profit @ 0.1 on (a+b+c+d) 34726.90
Cost for 360 cum = a+b+c+d+e 381995.92
Rate per cum = (a+b+c+d+e)/360 1061.10
say 1061.00
OR
4.9B (iii) Using Scrining Type-B (11.2mm agg.)
(b) d) Overhead charges @ 0.1 on (a+b+c) 35093.10
e) Contractor's profit @ 0.1 on (a+b+c+d) 38602.41
Cost for 360 cum = a+b+c+d+e 424626.53
Rate per cum = (a+b+c+d+e)/360 1179.52
say 1180.00
4.10 405 Crushed Cement Concrete Sub-base / Base

SUB Breaking and crushing of material obtained by


ANA -B breaking damaged cement concrete slabs to size
range not exceeding 75 mm as specified in table
400.7 transporting the aggregates obtained from
breaking of cement concrete slabs at a lead of L km.,
laying and compacting the same as sub base/ base
course, constructed as WBM to clause 404 except
the use of screening or binding Material.

Unit = cum
Taking output =360 cum
a) Labour
Mate day 4.160 195.43 812.99 L-12
Mazdoor skilled day 2.000 218.57 437.14 L-15
Mazdoor for crushing broken cement concrete day 102.000 187.43 19117.86 L-13
pavement/slabs into aggregate
b) Machinery
Motor Grader,110 HP @ 50 cum/hr. hour 6.000 2450.00 14700.00 P&M-032
Smooth 3 wheeled steel roller @ 30cum/hr. hour 12.000 649.00 7788.00 P&M-044
Front end loader 1 cum bucket capacity hour 6.000 1148.00 6888.00 P&M-017
Tipper 10 tonne capacity tonne.km 720 x L 2.68 1928.45 Lead =1 km &
P&M-047
Add 10 per cent of cost of carriage to cover 192.84
cost of loading and unloading
Water tanker 6 KL capacity with 5 km lead @ 1 hour 12.000 111.24 1334.88 P&M-060
trip per hour
c) Material
Material available from dismantled concrete slab
after crushing / breaking and only carriage is
required to be provided
Cost of water KL 72.000 167.07 12028.91 M-189
d) Overhead charges @ 0.1 on (a+b+c) 6522.91
e) Contractor's profit @ 0.1 on (a+b+c+d) 7175.20
Cost for 360 cum = a+b+c+d+e 78927.18
Rate per cum = (a+b+c+d+e)/360 219.24
With Smooth 3 wheeled Steel Roller say 219.00
1. It is assumed that dismantling of concrete
slab/pavement has been considered separately.
Hence same is not added in this analysis. Only
labour for crushing the dismantled slab into
aggregate has been added. Carriage from stock pile
to work site has been provided with a lead of L km.

Note 2. In case of breaking of slabs is done locally without


involvement of transportation, the provision of tipper,
front end loader and loading/unloading charges may
be deleted.
4.12 406 Wet Mix Macadam

RCD/SOR_2nd Edition
Sub - Analysis_B

SUB Providing, laying, spreading and compacting graded


ANA -B stone aggregate to wet mix macadam specification
including premixing the Material with water at OMC
in mechanical mix plant carriage of mixed Material by
tipper to site, laying in uniform layers with paver in
sub- base / base course on well prepared surface
and compacting with vibratory roller to achieve the
desired density.

Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate day 0.480 195.43 93.81 L-12
Mazdoor skilled day 2.000 218.57 437.14 L-15
Mazdoor day 10.000 187.43 1874.30 L-13
b) Machinery
Wet mix plant of 75 tonne hourly capacity hour 6.600 2419.00 15965.40 P&M-094
Electric generator 125 KVA hour 6.000 2211.00 13266.00 P&M-018
Front end loader 1 cum capacity hour 6.000 1148.00 6888.00 P&M-017
Paver finisher hour 6.000 1382.00 8292.00 P&M-035
Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 12.000 649.00 7788.00 P&M-044
Water tanker 6 KL capacity hour 3.000 111.24 333.72 P&M-060
Tipper tonne.km 495 x L 2.68 1325.81 Lead =1 km &
P&M-047
Add 10 per cent of cost of carriage to cover 132.58
cost of loading and unloading
c) Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent cum 89.100 743.66 66259.93 M-034
22.4 mm to 2.36 mm @ 40 per cent cum 118.800 817.35 97101.25 M-031
2.36 mm to 75 micron@ 30 per cent cum 89.100 244.51 21785.73 M-022
Cost of water KL 18.000 167.07 3007.23 M-189
d) Overhead charges @ 0.1 on (a+b+c) 24455.09
e) Contractor's profit @ 0.1 on (a+b+c+d) 26900.60
Cost for 225 cum = a+b+c+d+e 295906.58
Rate per cum = (a+b+c+d+e)/225 1315.14
say 1315.00
1. Though vibratory roller is required only for 3 hours
as per norms, the same is required to be available at
site for 6 hours to match with other machines. The
usage rates of vibratory roller may be multiplied with
a factor of 0.65.
Note 2. As three wheeled smooth steel rollers are
commonly in use, the same has been provided as an
alternative which can be used if the thickness of
individual layer does not exceed 100 mm.

12.5 1300 Brick Masonry Work in Cement Mortar 1:2 in


Foundation complete excluding Pointing and
Plastering, as per Drawing and Technical
Specifications.
SUB Unit = cum
ANA -B
Taking output = 5 cum
a) Material
Bricks Ist class each 2500.00 4.72 11805.10 M-079
Cement mortar 1:2 (Rate as in Item 12.6 B sub- cum 1.20 4392.00 5270.40 Item 12.6 (B)
analysis)
b) Labour
Mate day 0.48 195.43 93.81 L-12
Mason day 4.00 247.19 988.76 L-11
Mazdoor day 8.00 187.43 1499.44 L-13
c) Overhead charges @ 0.25 on (a+b) 4914.38
d) Contractor's profit @ 0.1 on (a+b+c) 2457.19
Cost for 5 cum = a+b+c+d 27029.07
Rate per cum (a+b+c+d)/5 5405.81
say 5406.00

RCD/SOR_2nd Edition
Sub - Analysis_B

12.5 1300 Brick Masonry Work in Cement Mortar 1:4 in


Foundation complete excluding Pointing and
Plastering, as per Drawing and Technical
Specifications.

SUB Unit = cum


ANA -B
Taking output = 5 cum
a) Material
Bricks Ist class each 2500.00 4.72 11805.10 M-079
Cement mortar 1:4 (Rate as in Item 12.6 C sub- cum 1.20 2804.00 3364.80 Item 12.6 (C)
analysis)
b) Labour
Mate day 0.48 195.43 93.81 L-12
Mason day 4.00 247.19 988.76 L-11
Mazdoor day 8.00 187.43 1499.44 L-13
c) Overhead charges @ 0.25 on (a+b) 4437.98
d) Contractor's profit @ 0.1 on (a+b+c) 2218.99
Cost for 5 cum = a+b+c+d 24408.87
Rate per cum (a+b+c+d)/5 4881.77
say 4882.00

12.5 1300 Brick Masonry Work in Cement Mortar 1:6 in


Foundation complete excluding Pointing and
Plastering, as per Drawing and Technical
Specifications.

SUB Unit = cum


ANA -B
Taking output = 5 cum
a) Material
Bricks Ist class each 2500.00 4.72 11805.10 M-079
Cement mortar 1:6 (Rate as in Item 12.6 D cum 1.20 2179.00 2614.80 Item 12.6 (D)
sub-analysis)
b) Labour
Mate day 0.48 195.43 93.81 L-12
Mason day 4.00 247.19 988.76 L-11
Mazdoor day 8.00 187.43 1499.44 L-13
c) Overhead charges @ 0.25 on (a+b) 4250.48
d) Contractor's profit @ 0.1 on (a+b+c) 2125.24
Cost for 5 cum = a+b+c+d 23377.62
Rate per cum (a+b+c+d)/5 4675.52
say 4676.00

RCD/SOR_2nd Edition
CHAPTER-1
CARRIAGE OF MATERIALS
Ref. to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec. Input ref.
1.1 Loading and Unloading of Stone cum
Boulder/ Stone aggregates/Sand/
Kanker/Moorum

Placing tipper at loading point, loading with


front end loader, dumping, turning for
return trip, excluding time for haulage and
return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point 1 Min
ii) Loading by front end loader 1 cum 13 Min
bucket capacity @ 25 cum per hour
iii) Maneuvering, reversing, dumping and 2 Min
turning for return
iv) Waiting time, unforeseen 4 Min
contingencies etc
Total 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 846.00 279.18 P&M-048
Front end-loader 1 cum bucket capacity @ hour 0.330 1148.00 378.84 P&M-017
25 cum/hour
b) Overhead charges @ 0.1 on (a) 65.80
c) Contractor's profit @ 0.1 on (a+b) 72.38

Cost for 5.5 cum = a+b+c 796.20


Rate per cum = (a+b+c)/ 5.5 144.76
Note Unloading will be by tipping. say 145.00
1.2 Loading and Unloading of Boulders by
Manual Means
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate day 0.110 195.43 21.50 L-12
Mazdoor for loading and unloading day 0.750 187.43 140.57 L-13
b) Machinery
Tipper 5.5 tonne capacity hour 0.750 846.00 634.50 P&M-048
c) Overhead charges @ 0.1 on (a+b) 79.66

d) Contractor's profit @ 0.1 on (a+b+c) 87.62

Cost for5.5 cum = a+b+c+d 963.85


Rate per cum = (a+b+c+d)/5.5 175.25
Note Unloading will be by tipping. say 175.00
1.3 Loading and Unloading of Cement or
Steel by Manual Means and Stacking.

Unit = tonne
Taking output = 10 tonnes
a) Labour
Mate day 0.080 195.43 15.63 L-12
Mazdoor for loading and unloading day 2.000 187.43 374.86 L-13
b) Machinery
Truck 10 tonne capacity hour 2.000 752.00 1504.00 P&M-057
c) Overhead charges @ 0.1 on (a+b) 189.45

d) Contractor's profit @ 0.1 on (a+b+c) 208.39

Cost for10 tonnes = a+b+c+d 2292.34


Rate per tonnes = (a+b+c+d)/10 229.23
say 229.00
1.4 Cost of Haulage Excluding Loading and
Unloading
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit = t.km
Taking output 10 tonnes load and lead 10
km = 100 t.km
(i) Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty :35 km / hour.
a) Machinery.
Tipper 10 tonne capacity
Time taken for onward haulage with load hour 0.400 846.00 338.40 P&M-048

Time taken for empty return trip. hour 0.290 846.00 245.34 P&M-048
b) Overhead charges @ 0.1 on (a) 58.37
c) Contractor's profit @ 0.1 on (a+b) 64.21

cost for 100 t km = a+b+c 706.33


Rate per t.km = (a+b+c)/100 7.06
say 7.10
1.4 (ii) Unsurfaced Graveled Road
Speed with load: 20 km / hour
Speed for empty return trip :30 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load hour 0.500 846.00 423.00 P&M-048

Time taken for empty return trip hour 0.330 846.00 279.18 P&M-048
b) Overhead charges @ 0.1 on (a) 70.22
c) Contractor's profit @ 0.1 on (a+b) 77.24

Cost for 100 t .km = a+b+c 849.64


Rate per t.Km = (a+b+c)/100 8.50
say 8.50
1.4 (iii) Katcha Track and Track in River
Bed/Nallah Bed and Choe Bed
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 846.00 846.00 P&M-048
Time taken for empty return trip hour 0.670 846.00 566.82 P&M-048
b) Overhead charges @ 0.1 on (a) 141.28
c) Contractor's profit @ 0.1 on (a+b) 155.41

Cost for 100 t .km = a+b+c 1709.51


Rate per t.Km = (a+b+c)/100 17.10
say 17.10

S-ar putea să vă placă și