Sunteți pe pagina 1din 361

This softawre is based on Standard Data book for analysis of Rates for Road and Bridge

Works
This Software runs on Microsoft Excel
INPUT- Input the usage rates of Plant & Machinery, labour and material as applicable
SUMMARY - In this sheet summary of all the rates analysized is presented
ANALYSIS- The analysis has been presented in 16 nos. of spread sheets
Worksheet- 1 : CHAPTER-1 CARRIAGE OF MATERIALS
Worksheet- 2 : CHAPTER-2 SITE CLEARANCE
Worksheet- 3 : CHAPTER-3 EARTH WORK, EROSION CONTROL AND DRAINAGE

Worksheet- 4 : CHAPTER-4 SUB-BASES, BASES (NON- BITUMINOUS) AND


SHOULDERS
Worksheet- 5 : CHAPTER-5 BASES AND SURFACE COURSES (BITUMINOUS)
Worksheet- 6 : CHAPTER-6 CEMENT CONCRETE PAVEMENTS
Worksheet- 7 : CHAPTER-7 GEOSYNTHETICS AND REINFORCED EARTH
Worksheet- 8 : CHAPTER-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD
APPURTENANCES
Worksheet- 9 : CHAPTER-9 PIPE CULVERTS
Worksheet- 10 : CHAPTER-10 MAINTENANCE OF ROADS
Worksheet- 11 : CHAPTER-11 HORTICULTURE
Worksheet- 12 : CHAPTER-12 FOUNDATIONS
Worksheet- 13 : CHAPTER-13 SUB-STRUCTURE
Worksheet- 14 : CHAPTER-14 SUPER-STRUCTURE
Worksheet- 15 : CHAPTER-15 RIVER TRAINING AND PROTECTION WORKS
Worksheet- 16 : CHAPTER-16 REPAIR AND REHABILITATION
GOVERNMENT OF RAJASTHAN
PUBLIC WORKS DEPARTMENT

RATE - ANALYSIS
OF
BASIC SCHEDULE OF RATES 2008

ROAD AND BRIDGE WORKS


FOR
NATIONAL HIGHWAYS

SUPERINTENDING ENGINEER
PUBLIC WORKS DEPARTMENT
NATIONAL HIGHWAY, CIRCLE JAIPUR
(A) Usage Rates of Plant and Machinery
Output of
Sl. No. Description of Machine Activity Output Unit Rate
Machine
P&M-001 Air Compressor General Purpose capacity in cfm 170/250 hour 150
Batching and Mixing Plant (a) 30 cum
P&M-002 Concrete Mixing cum/hour 20 hour 1500
capacity
Batching and Mixing Plant (b) 15 - 20
P&M-003 Concrete Mixing cum/hour 13 hour 1200
cum capacity
P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour 580

P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 150
Concrete Paver Finisher with 40 HP
P&M-006 Paving of concrete surface cum / hour 20 hour 1600
Motor
Concrete Pump of 45 & 30 cum
P&M-007 Pumping of concrete cum / hour 33 / 22 hour 500
capacity
P&M-008 Concrete Bucket For Pouring concrete capacity in cum 1 hour 100

P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour 100

P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 150

P&M-011 Crane (a) 80 tonnes Lifting Purpose hour 800

P&M-012 Cranes b) 35 tonnes Lifting Purpose hour 500

P&M-013 Cranes c) 3 tonnes Lifting Purpose hour 225

P&M-014 Dozer D - 80 - A 12 Spreading /Cutting / Clearing cum/hour 300/ 150/250 hour 2000

P&M-015 Dozer D - 50 - A 15 Spreading /Cutting / Clearing cum/hour 200/ 120/150 hour 1400

P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour 580
Front End loader 1 cum bucket Soil loading / Aggregate
P&M-017 cum/hour 60 /25 hour 700
capacity loading
P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour 650

P&M-019 Generator( b) 63 KVA Genration of electric Energy KVA 50 hour 525

P&M-020 GSB Plant 50 cum Producing GSB cum/hour 40 hour 650

P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix cum/hour 40 hour 6900

P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour 6700

P&M-023 Hotmix Plant - 60 to 90 TPH capacity DBM/BM/SDC/ Premix cum/hour 25 hour 6500

P&M-024 Hotmix Plant - 40 to 60 TPH capacity DBM/BM/SDC/ Premix cum/hour 17 hour 6300

P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour 1200
Soil Ordinary/Soil Marshy / Soil
P&M-026 Hydraulic Excavator of 1 cum bucket cum/hour 60 /60 /60 hour 700
Unsuitable
P&M-027 Integrated Stone Crusher 100THP Crushing of Spalls TPH 100 hour 5600

P&M-028 Integrated Stone Crusher 200 HP Crushing of Spalls TPH 200 hour 11000

P&M-029 Kerb Casting Machine Kerb Making Rm/hour 80 hour 200

P&M-030 Mastic Cooker Mastic Wearing coat capacity in tonne 1 hour 40

P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 150

P&M-032 Motor Grader 3.35 mtr blade Clearing /Spreading /GSB /WBM cum/hour 200/200/50/50 hour 1200

P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal sqm/hour 2700 hour 550
Paver Finisher Hydrostatic with Paving of DBM/ BM/SDC/
P&M-034 cum/hour 40 hour 1500
sensor control 100 TPH Premix
P&M-035 Paver Finisher Mechanical 100 TPH Paving of WMM /Paving of DLC cum/hour 40/30 hour 580
0.75 m dia to 1.2 m dia Boring
P&M-036 Piling Rig with Bantonite Pump Rm/hour 2 to 3 hour 3500
attachment
P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface cum/hour 25 hour 1000

P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour 1.5 to 2.00 hour 2500

P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 500

P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands hour 80

P&M-041 Ripper Scarifying cum/hour 60 hour 18

P&M-042 Rotavator Scarifying cum/hour 25 hour 11

P&M-043 Road marking machine Road marking Sqm/hour 100 hour 65


Soil Compaction /BM
P&M-044 Smooth Wheeled Roller 8 tonne cum/hour 70/25 hour 170
Compaction
P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 700
Transportation of soil, GSB,
P&M-046 Tipper - 5 cum Capacity in cum 5.5 km 185
WMM, Hotmix etc.
Transportation of soil, GSB,
P&M-047 Tipper - 5 cum Capacity in cum 5.5 tonne.km 1.85
WMM, Hotmix etc.
Transportation of soil, GSB,
P&M-048 Tipper - 5 cum Capacity in cum 5.5 hour 185
WMM, Hotmix etc.
Transportation of Concrete Mix
P&M-049 Transit Mixer 4.0/4.5 cum cum/hour 4.5 hour 600
to site

Page 1 of 361
Transportation of Concrete Mix
P&M-050 Transit Mixer 4/4.5 cum cum/hour 4.5 tonne.km 1.85
to site
Transportation of Concrete Mix
P&M-051 Transit Mixer 3.0 cum cum/hour 3 hour 550
to site
Transportation of Concrete Mix
P&M-052 Transit Mixer 3.0 cum cum/hour 3 tonne.km 1.85
to site
P&M-053 Tractor Pulling capacity in HP 50 hour 150

P&M-054 Tractor with Rotevator Rate of Tractor + Rotevator hour 150

P&M-055 Tractor with Ripper Rate of Tractor 6+ Ripper hour 175

P&M-056 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km 185

P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 185

P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 tonne.km 1.85

P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM cum/hour 100/60/60 hour 1000

P&M-060 Water Tanker Water Transport capacity in KL 6 hour 105

P&M-061 Water Tanker Water Transport capacity in KL 6 km 105

P&M-062 Wet Mix Plant 60 TPH Wet Mix cum/hour 25 hour 790

Sl. No. Description of Machine Unit Rate


P&M-063 Air compressor with pneumatic chisel attachment for cutting hard clay. hour 250

P&M-064 Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour hour 1200

P&M-065 Belt conveyor system hour 120

P&M-066 Boat to carry atleast 20 persons hour 1500

P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output) hour 6000

P&M-068 Cement concrete batch mix plant @ 75 cum per hour hour 1500

P&M-069 Cold milling machine @ 20 cum per hour hour 150

P&M-070 Crane 5 tonne capacity hour 250

P&M-071 Crane 10 tonne capacity hour 300

P&M-072 Crane 15 tonne capacity hour 400

P&M-073 Crane 20 tonne capacity hour 475

P&M-074 Crane 40 T capacity hour 525

P&M-075 Crane with grab 0.75 cum capacity hour 900

P&M-076 Compressor with guniting equipment along with accessories hour 250

P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. hour 4000

P&M-078 Epoxy Injection gun hour 200

P&M-079 Generator 33 KVA hour 400

P&M-080 Generator 100 KVA hour 600

P&M-081 Generator 250 KVA hour 750


Induction, deinduction and erection of plant and equipment including all components and accessories for
P&M-082 hour 5000
pneumatic method of well sinking.
P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement) hour 150

P&M-084 Jack for Lifting 40 tonne lifting capacity. day 3000

P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig) hrs 3000

P&M-086 Plate compactor hour 75

P&M-087 Snow blower equipment 140 HP @ 600 cum per hour hour 500

P&M-088 Texturing machine (for rigid pavement) hour 200

P&M-089 Truck Trailor 30 tonne capacity hour 300

P&M-090 Truck Trailor 30 tonne capacity t.km 300

P&M-091 Tunnel Boring machine hour 350

P&M-092 Vibrating Pile driving hammer complete with power unit and accessories. hour 550

P&M-093 Wet Mix Plant 100 TPH hour 1000

P&M-094 Wet Mix Plant 75 TPH 800

Page 2 of 361
(B) Labour

Sl. No. Description of Labour Unit Rate

L-01 Blacksmith (IInd class) day 130

L-02 Blacksmith (Ist class)/ Welder/ Plumber/ Electrician day 150

L-03 Blaster (Stone cutter) day 150

L-04 Carpenter I Class day 150

L-05 Chiseller (Head Mazdoor) day 150

L-06 Driller (Jumper) day 150

L-07 Diver day 150

L-08 Fitter day 150

L-09 Mali day 150

L-10 Mason (IInd class) day 175

L-11 Mason (Ist class) day 250

L-12 Mate / Supervisor day 150

L-13 Mazdoor day 100

L-14 Mazdoor/Dresser (Semi Skilled) day 120

L-15 Mazdoor/Dresser/Sinker (Skilled) day 125

L-16 Medical Officer day 500

L-17 Operator(grouting) day 250

L-18 Painter I class day 200

L-19 Para medical personnel day 250

(C) Materials

Sl. No. Description Unit Rate

M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum 200

M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum 210

M-003 Boulder with minimum size of 300 mm for Pitching at Site cum 265

M-004 Coarse sand at Mixing Plant (Crusher dust) cum 160

M-005 Coarse sand at Site cum 350

M-006 Fine sand at Site cum 300

M-007 Moorum at Site cum 130

M-008 Gravel/Quarry spall at Site Cum 160

M-009 Granular Material or hard murrum for GSB works at Site Cum 160

M-010 Granular Material or hard murrum for GSB works at Mixing Plant Cum 160

M-011 Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant Cum 150

M-012 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) Cum 160

Page 3 of 361 Rate at


Plant
Description Unit
(HMP/Batc
Rate at Site
hing)
M-013 Close graded Granular sub-base Material 53 mm to 9.5 mm cum 200 200
Ref. to Remark
Sr No MoRTH Description Unit QuantityRate Rs Cost Rs s/ Input
Spec. ref.
1.1 Loading and unloading of stone
boulder / stone aggregates / sand /
kanker / moorum.
Placing tipper at loading point, loading with
front end loader, dumping, turning for
return trip, excluding time for haulage and
return trip
Unit : cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point 1 Min
ii) Loading by front end loader 1 cum 13 Min
bucket capacity @ 25 cum per hour
iii) Maneuvering, reversing, dumping 2 Min
and turning for return
iv) Waiting time, unforeseen 4 Min
contingencies
Total etc 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 185.00 61.05 P&M-
Front end-loader 1 cum bucket capacity hour 0.330 700.00 231.00 048
P&M-
@ 25 cum/hour 017
b) Overheads @ 10 % on (a) 29.21
c) Contractors profit @ 10 % on (a+b) 32.13
Cost for 5.5 cum = a+b+c 353.38
Rate per cum = (a+b+c)/ 5.5 64.25
Note Unloading will be by tipping. say 64.00
1.4 Cost of Haulage Excluding Loading
and Unloading
Haulage of materials by tipper excluding
cost of loading, unloading and stacking.
Unit : t.km
Taking output 10 tonnes load and lead
10 km = 100 t.km
1.4(I) Case I Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km /
hour.
a) Machinery.
i) Tipper 10 tonne capacity
Time taken for onward haulage with hour 0.400 185.00 74.00 P&M-
load
Time taken for empty return trip. hour 0.290 185.00 53.65 048
P&M-
b) Overheads @ 10 % on (a) 12.77 048
c) Contractors profit @ 10 % on (a+b) 14.04
cost for 100 t km = a+b+c 154.46
Rate per t.km = (a+b+c)/100 1.54
say 1.50

1.4(II) Case II Unsurfaced Gravelled Road


Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
a)Machinery
Tipper 10 tonnes capacity

Page 4 of 361
Time taken for onward hanlage with hour 0.500 185.00 92.50 P&M-
load
Time taken for empty return trip hour 0.330 185.00 61.05 048
P&M-
b) Overheads @ 10 % on (a) 15.36 048
c) Contractors profit @ 10 % on (a+b) 16.89
Cost for 100 t .km = a+b+c 185.80
Rate per t.Km = (a+b+c)/100 1.86
say 1.90

1.4(III) Case III Katcha Track and Track in river bed /


nallah bed and choe bed.
Speed with load : 10 km / hour
Speed while returning empty : 15 km /
hour
a) Machinery
I) Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 185.00 185.00 P&M-
Time taken for empty return trip hour 0.670 185.00 123.95 048
P&M-
b) Overheads @ 10 % on (a) 30.90 048
c) Contractors profit @ 10 % on (a+b) 33.98
Cost for 100 t .km = a+b+c 373.83
Rate per t.Km = (a+b+c)/100 3.74
say 3.70
1.5 Hand Broken Stone Aggregates 63 mm
nominal size
Supply of quarried stone, hand breaking
into coarse aggregate 63 mm nominal size
(passing 80 mm and retained on 50 mm
sieve) and stacking as directed
Unit : cum
Taking output = 1 cum
a) Labour
Mate day 0.060 150.00 9.00 L-12
Mazdoor day 1.500 100.00 150.00 L-13
b) Material
Supply of quarried stone 150 - 200 mm cum 1.100 210.00 231.00 M-002
c) size
Overheads @ 10 % on (a+b) 39.00
d) Contractors profit @ 10 % on 42.90
(a+b+c)
Rate per cum = a+b+c+d 471.90
say 472.00
1.6 Crushing of stone aggregates 13.2 mm
nominal size.
Crushing of stone boulders of 150 mm size
in an integrated stone crushing unit of 200
tonnes per hour capacity comprising of
primary and secondary crushing units, belt
conveyor and vibrating screens to obtain
stone aggregates of 13 mm nominal size.
Unit : cum
Taking Output = 600 cum at crusher
location.
a) Labour
Mate day 0.760 150.00 114.00 L-12
Mazdoor Skilled day 2.000 120.00 240.00 L-14
Mazdoor including breaking of any day 17.000 100.00 1700.00 L-13
oversize boulder.

Page 5 of 361
b) Material
Stone Boulder of size 150 mm and cum 800.000 200.00 ### M-001
below
c) Machinery
Integrated stone crusher of 200 TPH Hour 6.000 ### 66000.00 P&M-
including belt conveyor and vibrating 028
screens
Front end loader 1 cum bucket capacity Hour 20.000 700.00 14000.00 P&M-
Tipper 5.5 cum capacity Hour 20.000 185.00 3700.00 017
P&M-
d) Overheads @ 10 % on (a+b+c) 24575.40 048
e) Contractors profit @ 10 % on 27032.94
(a+b+c+d)
Cost for 600 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)*0.95/600 470.82
say 471.00
Note 1. 800 cum of stone boulders are needed to
get 600 cum of stone chips of size 13.2
mm.
2. 95% of above cost will be attributed to
the production of 600 cum of stone chips of
13.2 mm size and balance 5% to the
production of stone dust which comes out
as a by-product.
3. The integrated stone crusher includes
primary and secondary crushing units.

1.7 Crushing of stone aggregates 20 mm


nominal
Crushing size
of stone boulders of 150 mm size
in an integrated stone crushing unit of 200
tonnes per hour capacity comprising of
primary and secondary crushing units, belt
conveyor and vibrating screens to obtain
stone aggregates of 20 mm nominal size.
Unit : cum
Taking Output = 670 cum at crusher
location.
a) Labour
Mate day 0.760 150.00 114.00 L-12
Mazdoor Skilled day 2.000 120.00 240.00 L-14
Mazdoor including breaking of any size day 17.000 100.00 1700.00 L-13
boulder.
b) Material
Stone Boulder of size 150 mm and cum 800.000 200.00 ### M-001
below
c) Machinery
Integrated stone crusher of 200 TPH Hour 6.000 ### 66000.00 P&M-
including belt conveyor and vibrating 028
screens
Front end loader 1 cum bucket capacity Hour 20.000 700.00 14000.00 P&M-
Tipper 5.5 cum capacity Hour 20.000 185.00 3700.00 017
P&M-
d) Overheads @ 10 % on (a+b+c) 24575.40 048
e) Contractors profit @ 10 % on 27032.94
(a+b+c+d)
Cost for 670 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)*0.90/670 399.44
say 399.00

Note 1. 800 cum of stone boulders are needed to


get 600 cum of stone chips of size 20 and
40 mm. of above cost will be attributed to
2. 90%
the production of 670 cum of stone
aggregates of 20mm size and balance 10%
will be for smaller size aggregates and
stone dust which comes out as a by-

Page 6 of 361
3. The integrated stone crusher includes
primary and secondary crushing units.

1.8 Crushing of stone aggregates 40 mm


nominal
Crushing size
of stone boulders of 150 mm size
in an integrated stone crushing unit of 200
tonnes per hour capacity comprising of
primary and secondary crushing units, belt
conveyor and vibrating screens to obtain
stone aggregates of 40 mm nominal size.
Unit : cum
Taking Output = 750 cum at crusher
location.
a) Labour
Mate day 0.760 150.00 114.00 L-12
Mazdoor Skilled day 2.000 120.00 240.00 L-14
Mazdoor day 17.000 100.00 1700.00 L-13
b) Material
Stone Boulder of size 150 mm and cum 800.000 200.00 ### M-001
below
c) Machinery
Integrated stone crusher of 200 TPH Hour 6.000 ### 66000.00 P&M-
including belt conveyor and vibrating 028
screens
Front end loader 1 cum bucket capacity Hour 20.000 700.00 14000.00 P&M-
Tipper 5.5 cum capacity Hour 20.000 185.00 3700.00 017
P&M-
d) Overheads @ 10 % on (a+b+c) 24575.40 048
e) Contractors profit @ 10 % on 27032.94
(a+b+c+d)
Cost for 750 cum = (a+b+c+d+e)x0.85 ###
Rate per cum = (a+b+c+d+e)x0.85/750 337.01
say 337.00
Note 1. 800 cum of stone boulders are needed to
get 600 cum of stone chips of size 13.2
mm.
2. 85% of above cost will be attributed to
the production of 750 cum of stone
aggregates of 40mm size and balance 15%
will be for smaller size aggregates and
stone dust which comes out as a by-
3. The integrated stone crusher includes
primary and secondary crushing units.
5.9 510 Surface Dressing
Providing and laying surface dressing as
wearing course in single coat using crushed
stone aggregates of specified size on a
layer of bituminous binder laid on prepared
surface and rolling with 8-10 tonne smooth
wheeled steel roller
Unit = sqm
Taking output = 9000 sqm
Case -1:-19 mm nominal chipping size
a) Labour
Mate day 0.440 150.00 66.00 L-12
Mazdoor day 9.000 100.00 900.00 L-13
Mazdoor skilled day 2.000 125.00 250.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour 7.200 150.00 1080.00 P&M-
hour
Air compressor 250 cfm hour 7.200 150.00 1080.00 031
P&M-
001

Page 7 of 361
Hydraulic self propelled chip spreader hour 6.000 1200.00 7200.00 P&M-
@ 1500 sqm per hour 025
Tipper 10 tonne capacity for carriage of hour 6.000 185.00 1110.00 P&M-
stone chips from stockpile on road side 048
to chipend
Front spreader
loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-
Bitumen pressure distributor hour 6.000 580.00 3480.00 017
P&M-
Smooth wheeled roller 8-10 tonne hour 6.000 170.00 1020.00 004
P&M-
c) weight
Material 044
Bitumen@ 1.20 kg per sqm tonne 10.800 ### ### M-074
Crushed stone chipping,19 mm nominal cum 135.000 410.00 55350.00 M-053
size @ 0.015 cum per sqm
d) Overheads @ 10 % on (a+b+c) 36766.00
e) Contractors profit @ 10 % on 40442.60
(a+b+c+d)
Cost for 9000 sqm= a+b+c+d+e ###
Rate per sqm = (a+b+c+d+e)/9000 49.43
say 49.00
Case - II13 mm nominal size chipping
a) Labour
Mate day 0.440 150.00 66.00 L-12
Mazdoor day 9.000 100.00 900.00 L-13
Mazdoor skilled day 2.000 125.00 250.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour 7.200 150.00 1080.00 P&M-
hour
Air compressor 250 cfm hour 7.200 150.00 1080.00 031
P&M-
Hydraulic self propelled chip spreader hour 6.000 1200.00 7200.00 001
P&M-
@ 1500 sqm per hour 025
Tipper 10 tonne capacity for carriage of hour 6.000 185.00 1110.00 P&M-
stone chips from stockpile on road side 048
to chipend
Front spreader
loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-
Bitumen pressure distributor @ 1750 hour 6.000 580.00 3480.00 017
P&M-
sqm per hour
Vibratory roller 8-10 tonne weight hour 6.000 1000.00 6000.00 004
P&M-
c) Material 059
Bitumen@ 1.00 kg per sqm tonne 9.000 ### ### M-074
Crushed stone chipping,13 mm nominal cum 90.000 410.00 36900.00 M-052
size @ 0.01 cum per sqm
d) Overheads @ 10 % on (a+b+c) 30553.60
e) Contractors profit @ 10 % on 33608.96
(a+b+c+d)
Cost for 9000 sqm= a+b+c+d+e ###
Rate per sqm = (a+b+c+d+e)/9000 41.08
say 41.00
Note 1.Where the proposed aggregate fails to
pass the stripping test, an approved
adhesion agent may be added to the binder
as per clause 510.2.4. Alternatively, chips
may be pre-coated as per clause 510.2.5
2.Input for the second coat, where
required, will be the same as per the Ist
5.15 516 coat mentioned
Slurry Seal above

Page 8 of 361
Providing andlaying slurry seal consisting of
a mixture of fine aggregates, portland
cement filler, bituminous emulsion and
water on a road surface including cleaning
of surface, mixing of slurry seal in a
suitable mobile plant, laying and
compacting to provide even riding surface
Case I 5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum,
weight of mix = 264 tonnes
weight of mix = 176 tonnes
a) Labour
Mate day 0.240 150.00 36.00 L-12
Mazdoor day 6.000 100.00 600.00 L-13
b) Machinery
Mechanical broom hour 6.000 150.00 900.00 P&M-
Air compressor 250 cfm hour 6.000 150.00 900.00 031
P&M-
Mobile slurry seal equipment hour 6.000 550.00 3300.00 001
P&M-
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 033
P&M-
Tipper 5.5 cum capacity for carriage of hour 6.000 185.00 1110.00 017
P&M-
aggregate from stockpile on road side 048
to slurry equipment,bitumen emulsion
and filler.
Pneumatic tyred roller with individual hour 6.000 1000.00 6000.00 P&M-
wheel load not exceeding 1.5 tonnes 037
Water tanker6 KL capacity hour 2.000 105.00 210.00 P&M-
c) Material 060
Residual Binder @ 11 % of mix 80 x 2.2 tonne 19.360 ### ### M-077
x 0.11
Fine aggregate 4.75 mm and below 87 cum 102.080 350.00 35728.00 M-005
% of total mix,80 x 2.2 x 0.87 = 153.12
tonnes. Taking density1.5,= 153.12/1.5
= 102.08 cum
Filler @ 2 % of total mix = 80 x 2.2 x tonne 3.520 2400.00 8448.00 M-188
0.02
Cost of water KL 12.000 50.00 600.00 M-189
d) Overheads @ 10 % on (a+b+c) 52667.20
e) Contractors profit @ 10 % on 57933.92
(a+b+c+d)
Cost for 16000 sqm= a+b+c+d+e ###
Rate per sqm = (a+b+c+d+e)/16000 39.83
say 40.00
Case II 3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
Mate day 0.200 150.00 30.00 L-12
Mazdoor day 5.000 100.00 500.00 L-13
b) Machinery
Mechanical broom hour 6.000 150.00 900.00 P&M-
Air compressor 250 cfm hour 6.000 150.00 900.00 031
P&M-
Mobile slurry seal equipment hour 6.000 550.00 3300.00 001
P&M-
033

Page 9 of 361
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-
Tipper 5.5 cum capacity for carriage of hour 6.000 185.00 1110.00 017
P&M-
aggregate from stockpile on road side 048
to slurry equipment,bitumen emulsion
and filler
Water tanker6 KL capacity hour 2.000 105.00 210.00 P&M-
c) Material 060
Residual Binder @ 13 % of mix = 60 x tonne 17.160 ### ### M-077
2.2
Finexaggregate
0.13 3 mm and below 85 % cum 74.800 350.00 26180.00 M-005
of total mix, 60x 2.2 x 0.85 = 112.2
tonnes.
Filler @ Taking density
2 % of total mix1.5,
=60x 2.2 x tonne 2.640 2400.00 6336.00 M-188
0.02
Cost of water KL 12.000 50.00 600.00 M-189
d) Overheads @ 10 % on (a+b+c) 45610.60
e) Contractors profit @ 10 % on 50171.66
(a+b+c+d)
Cost for 30000 sqm= a+b+c+d+e ###
Rate per sqm = (a+b+c+d+e)/20000 27.59
say 28.00
Case III 1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
Mate day 0.200 150.00 30.00 L-12
Mazdoor day 5.000 100.00 500.00 L-13
b) Machinery
Mechanical broom hour 6.000 150.00 900.00 P&M-
Air compressor 250 cfm hour 6.000 150.00 900.00 031
P&M-
Mobile slurry seal equipment hour 6.000 550.00 3300.00 001
P&M-
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 033
P&M-
Tipper 5.5 cum capacity for carriage of hour 6.000 185.00 1110.00 017
P&M-
aggregate from stockpile on road side 048
to slurry equipment,bitumen emulsion
and filler.
Water tanker6 KL capacity hour 2.000 105.00 210.00 P&M-
c) Material 060
Residual Binder @ 16 % of mix, 36 x 2.2 tonne 12.670 ### ### M-077
x 0.16
Fine aggregate 2.36 mm and below,82 cum 43.300 200.00 8660.00 M-022
% of total mix,36x 2.2 x 0.82 = 64.94
tonnes. Taking density 1.5
Filler @ 2 % of total mix = 36x 2.2 x tonne 1.580 2400.00 3792.00 M-188
0.02
Cost of water KL 12.000 50.00 600.00 M-189
d) Overheads @ 10 % on (a+b+c) 32828.20
e) Contractors profit @ 10 % on 36111.02
(a+b+c+d)
Cost for 24000 sqm= a+b+c+d+e ###
Rate per sqm = (a+b+c+d+e)/24000 16.55
say 17.00
Note 1.Tack coat, if required to be provided,
before laying slurry seal may be measured
and paid separately
5.17 518 Fog Spray

Page 10 of 361
Providing and applying low viscosity
bitumen emulsion for sealing cracks less
than 3 mm wide or incipient fretting or
disintegration in an existing bituminous
surfacing.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.120 150.00 18.00 L-12
Mazdoor day 3.000 100.00 300.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour 6.000 150.00 900.00 P&M-
hour
Air compressor 250 cfm hour 6.000 150.00 900.00 031
P&M-
Bitumen emulsion pressure distributor tonne 6.000 580.00 3480.00 001
P&M-
@ 1750 sqm per hour 004
c) Material
Bitumenemulsion @ 0.75 kg per sqm tonne 7.880 ### ### M-077
d) Overheads @ 10 % on (a+b+c) 19471.80
e) Contractors profit @ 10 % on 21418.98
(a+b+c+d)
Cost for 10500 sqm= a+b+c+d+e ###
Rate per sqm = (a+b+c+d+e)/10500 22.44
say 22.00
1.In case it is decided by the engineer to
blind the fog spray, the following may be
added
a) Labour
Mate day 0.160 150.00 24.00 L-12
Mazdoor for precoating of grit day 4.000 100.00 400.00 L-13
c) Material
Crushed stone grit 3 mm size @ 3.75 kg cum 26.250 200.00 5250.00 M-024
per sqm
Bitumenemulsion for precoating grit @ tonne 0.790 ### 18960.00 M-077
2 % of grit,39.38 x 0.02
24634.00
2.35
say 2.00

5.21 522 Crack Prevention Courses


Case - I Stress Absorbing Membrane (SAM)
crack width less than 6 mm
Providing and laying of a stress absorbing
membrane over a cracked road surface,
with crack width below 6 mm after cleaning
with a mechanical broom, using modified
binder complying with clause 521, sprayed
at the rate of 9 kg per 10 sqm and
spreading 5.6 mm crushed stone
aggregates @ 0.11 cum per 10 sqm with
hydraulic chip spreader, sweeping the
surface for uniform spread of aggregates
and surface finished to conform to clause
Unit = sqm
Taking output = 10500 sqm
a) Labour

Page 11 of 361
Mate day 0.240 150.00 36.00 L-12
Mazdoor day 6.000 100.00 600.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour 6.000 150.00 900.00 P&M-
hour
Air compressor 250 cfm hour 6.000 150.00 900.00 031
P&M-
Bitumen pressure distributor @ 1750 hour 6.000 580.00 3480.00 001
P&M-
sqm per hour
Hydraulic Chip spreader hour 6.000 1200.00 7200.00 004
P&M-
Smooth wheeled road roller 8-10 tonne hour 6.000 170.00 1020.00 025
P&M-
c) Material 044
Modified binder tonne 9.450 ### ### M-078
Crushed stone aggregates 5.6 mm size cum 105.000 350.00 36750.00 M-050
d) Overheads @ 10 % on (a+b+c) 32937.75
e) Contractors profit @ 10 % on 36231.53
(a+b+c+d)
Cost for 10500 sqm= a+b+c+d+e ###
Rate per sqm = (a+b+c+d+e)/10500 37.96
say 38.00

Case - Stress Absorbing Membrane (SAM)


II with crack width 6 mm to 9 mm
Providing and laying of a stress absorbing
membrane over a cracked road surface,
with crack width 6 to 9 mm after cleaning
with a mechanical broom, using modified
binder complying with clause 521, sprayed
at the rate of 11 kg per 10 sqm and
spreading 11.2 mm crushed stone
aggregates @ 0.12 cum per 10 sqm,
sweeping the surface for uniform spread of
aggregates
Unit = sqmand surface finished to conform
Taking output = 10500 sqm
a) Labour
Mate day 0.240 150.00 36.00 L-12
Mazdoor day 6.000 100.00 600.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour 6.000 150.00 900.00 P&M-
hour
Air compressor 250 cfem capacity hour 6.000 150.00 900.00 031
P&M-
Bitumen pressure distributor @ 1750 hour 6.000 580.00 3480.00 001
P&M-
sqm per hour
Hydraulic Chip spreader hour 6.000 1200.00 7200.00 004
P&M-
Smooth wheeled road roller 8-10 tonne hour 6.000 170.00 1020.00 025
P&M-
c) Material 044
Modified binder tonne 11.550 ### ### M-078
Crushed stone chipping 11.2 mm size cum 105.000 410.00 43050.00 M-051
d) Overheads @ 10 % on (a+b+c) 39756.45
e) Contractors profit @ 10 % on 43732.10
(a+b+c+d)
Cost for 10500 sqm= a+b+c+d+e ###
Rate per sqm = (a+b+c+d+e)/10500 45.81
say 46.00

Page 12 of 361
Case III Stress Absorbing Membrane (SAM)
crack width above 9 mm and cracked
area above
Providing and50laying
% a single coatn of a
stress absorbing membrane over a cracked
road surface, with crack width above 9 mm
and cracked area above 50 % after cleaning
with a mechanical broom, using modified
binder complying with clause 521, sprayed
at the rate of 15 kg per 10 sqm and
spreading 11.2 mm crushed stone
aggregates @ 0.12 cum per 10 sqm,
sweeping the surface for uniform spread of
aggregates and surface finished to conform
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 150.00 36.00 L-12
Mazdoor day 6.000 100.00 600.00 L-13
Mazdoor skilled day 2.000 125.00 250.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour 6.000 150.00 900.00 P&M-
hour
Air compressor 250 cfem capacity hour 6.000 150.00 900.00 031
P&M-
Bitumen pressure distributor @ 1750 hour 6.000 580.00 3480.00 001
P&M-
sqm per hour
Hydraulic Chip spreader hour 6.000 1200.00 7200.00 004
P&M-
Smooth wheeled road roller 8-10 tonne hour 6.000 170.00 1020.00 025
P&M-
c) Material 044
Modified binder tonne 15.750 ### ### M-078
Crushed stone aggregates 11.2 mm cum 126.000 410.00 51660.00 M-051
d) size
Overheads @ 10 % on (a+b+c) 53019.85
e) Contractors profit @ 10 % on 58321.84
(a+b+c+d)
Cost for 10500 sqm= a+b+c+d+e ###
Rate per sqm = (a+b+c+d+e)/10500 61.10
say 61.00
Case IV Case - IV : Bitumen Impregnated
Geotextile
Providing and laying a bitumen
impregnated geotextile layer after cleaning
the road surface, geotextile conforming to
requirements of clause 704.3, laid over a
tack coat with 1.05 kg per sqm of paving
grade bitumen 80 - 100 penetration and
constructed to the requirement of clause
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.560 150.00 84.00 L-12
Mazdoor day 12.000 100.00 1200.00 L-13
Mazdoor skilled day 2.000 125.00 250.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour 2.800 150.00 420.00 P&M-
hour
Air compressor 250 cfem capacity hour 2.800 150.00 420.00 031
P&M-
Bitumen pressure distributor @ 1750 tonne 2.000 580.00 1160.00 001
P&M-
sqm per hour 004

Page 13 of 361
Pneumatic roller hour 2.000 1000.00 2000.00 P&M-
c) Material 037
Paving grade bitumen of 80 - 100 tonne 3.680 ### 95790.40 M-075
penetration @ 1.05 kg per sqm
Geotextile including 10 % for overlaps sqm ### 300.00 ### M-108
d) Overheads @ 10 % on (a+b+c) ###
e) Contractors profit @ 10 % on ###
(a+b+c+d)
Cost for 10500 sqm= a+b+c+d+e ###
Rate per sqm = (a+b+c+d+e)/3500 434.33
say 434.00
NOTE As bitumen overlay construction shallfollow
closely the fabric placement on the same
day, an output of 3500 sqm only has been
considered for the analysis which will cover
a length of 500 m, of 7 m widecarriagway.
This can be conveniently overlaid by a
bitumenious course in a day
Printing new letter and figures of any
8.3 801
shade
Printing new letter and figures of any shade
with synthetic enamel paint black or any
other approved colour to give an even
shade
ii) English and Roman
Hyphens and the like not to be measured
and paid
Detail forfor100 letters of 16 cm height.
i.e.1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.07 150 10.50
Painter Ist class day 1.25 200 250.00
Mazdoor day 0.50 100 50.00
b) Material
Paint Litre 0.50 135 67.50
c) Overheads @ 10 % on (a+b) 37.80
d) Contractors profit @ 10 % on (a+b+c) 41.58
Cost for 1600 cm = a+b+c+d 457.38
Rate per cm height per letter =
0.29
(a+b+c +d)/1600
say 0.30
Painting Two Coats on New Concrete
8.8 803
Surfaces
Painting two coats after filling the surface
with synthetic enamel paint in all shades on
new plastered concrete surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.12 150 18.00
Painter day 2.00 200 400.00
Mazdoor day 1.00 100 100.00
b) Material
Paint conforming to requirement of
Litre 6.00 150 900.00
clause 803.3.

Page 14 of 361
Add for scaffolding @ 1% of labour cost
9.00
where required
c) Overheads @ 10 % on (a+b) 142.70
d) Contractors profit @ 10 % on (a+b+c) 156.97
Cost for 40 sqm = a+b+c+d 1726.67
Rate per sqm = (a+b+c+d)/40 43.17
say 43.00
8.9 803 Painting on Steel Surfaces
Providing and applying two coats of ready
mix paint of approved brand on steel
surface after through cleaning of surface to
give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.03 150 4.50
Painter day 0.45 200 90.00
Mazdoor day 0.25 100 25.00
b) Material
Paint ready mixed approved brand. Litre 1.25 135 168.75
Add @ 1% on cost of material for
1.69
scaffolding
c) Overheads @ 10 % on (a+b) 28.99
d) Contractors profit @ 10 % on (a+b+c) 31.89
Cost for 10 sqm = a+b+c+d 350.82
Rate per sqm = (a+b+c+d)/10 35.08
say 35.00
12.6 Sub- Cement mortar1:3 (1cement :3 sand)
analysi
s (A)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement MT 0.51 4180.00 2131.80
Sand cum 1.05 350.00 367.50
b) Labour
Mate day 0.04 150.00 6.00
Mazdoor day 0.90 100.00 90.00
Total Material and Labour = (a+b) 2595.00

Sub- Cement mortar1:2 (1cement :2 sand)


analysi
s (B)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement MT 0.67 4180.00 2808.96
Sand cum 0.93 350.00 326.67
b) Labour
Mate day 0.04 150.00 6.00
Mazdoor day 0.90 100.00 90.00

Page 15 of 361
Total Material and Labour = (a+b) 3232.00

Sub- Cement mortar1:6 (1cement :6 sand)


analysi
s (D)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement MT 0.29 4180.00 1203.84
Sand cum 1.20 350.00 420.00
b) Labour
Mate day 0.04 150.00 6.00
Mazdoor day 0.90 100.00 90.00
Total Material and Labour = (a+b) 1720.00
12.7 1400 Stone masonry work in cement mortar
1:3 in foundation complete as drawing
and Technical Specification
Unit = cum
Taking output = 5 cum
(A) Square Rubble Coursed Rubble
Masonry (first sort)
a) Material
Stone cum 5.50 4000.00 22000.00 M-169
Through and bond stone each 35.00 30.00 1050.00 M-182
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item cum 1.50 2595.00 3892.50 Item
12.6 A sub-analysis) 12.6 (A)
b) Labour
Mate day 0.66 150.00 99.00 L-12
Mason day 7.50 250.00 1875.00 L-11
Mazdoor day 9.00 100.00 900.00 L-13
c) Overhead charges @ 10 % on 2981.65
(a+b)
d) Contractor's profit @ 10 % on 3279.82
(a+b+c)
Cost for 5 cum = a+b+c+d 36077.97
Rate per cum (a+b+c+d)/5 7215.59
say 7216.00
1405.3 B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 300.00 1650.00
Through and bond stone Nos 35.00 30.00 1050.00
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 12.6 A)cum 1.55 2595.00 4022.25
b) Labour
Mate day 0.62 150.00 93.00
Mason day 6.00 250.00 1500.00
Mazdoor day 9.00 100.00 900.00
c) Overheads @ 10 % on (a+b) 921.53
d) Contractors profit @ 10 % on (a+b+c) 1013.68
Cost for 5 cum = a+b+c+d 11150.45

Page 16 of 361
Rate per cum (a+b+c+d)/5 2230.09
say 2230.00
@ The labour already considered in cement
mortar has been taken into account while
proposing labour for masonry works.
12.7 1400 Stone masonry work in cement mortar
(Add) 1:6 in foundation complete as drawing
and Technical Specification
Unit = cum
Taking output = 5 cum
1405.3 B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 300.00 1650.00
Through and bond stone Nos 35.00 30.00 1050.00
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 13.6 D)cum 1.55 1720.00 2666.00
b) Labour
Mate day 0.62 150.00 93.00
Mason day 6.00 250.00 1500.00
Mazdoor day 9.00 100.00 900.00
c) Overheads @ 10 % on (a+b) 785.90
d) Contractors profit @ 10 % on (a+b+c) 864.49
Cost for 5 cum = a+b+c+d 9509.39
Rate per cum (a+b+c+d)/5 1901.88
say 1902.00
@ The labour already considered in cement
mortar has been taken into account while
proposing labour for masonry works.

12.8 1500, Plain/Reinforced cement concrete in


1700 & open foundation complete as per
2100 drawing and technical specifications
A PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 4.13 4180.00 17263.40
Coarse sand cum 6.75 350.00 2362.50
40 mm Aggregate cum 8.10 350.00 2835.00
20 mm Aggregate cum 4.05 410.00 1660.50
10 mm Aggregate cum 1.35 410.00 553.50
b) Labour
Mate day 0.86 150.00 129.00
Mason day 1.50 250.00 375.00
Mazdoor day 20.00 100.00 2000.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00
Generator 63 KVA hour 6.00 525.00 3150.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###

Page 17 of 361
d) Formwork @ 4% on cost of concrete 1237.16
i.e.cost of material, labour and machinery
e) Overheads @ 10 % on (a+b+c+d) 3216.61
f) Contractors profit @ 10 % on (a+b+c+d+e) 3538.27
Cost for 15 cum = a+b+c+d+e+f 38920.93
Rate per cum (a+b+c+d+e+f)/15 2594.73
say 2595.00
Note Nedle Vibrator is an item of minor T & P
which is already included in overhead
charges. Hence not added in rate analysis
of cement concrete works.
12.8 B PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement MT 5.16 4180.00 21568.80
Coarse sand cum 6.75 350.00 2362.50
40 mm Aggregate cum 5.40 350.00 1890.00
20 mm Aggregate cum 5.40 410.00 2214.00
10 mm Aggregate cum 2.70 410.00 1107.00
b) Labour
Mate day 0.86 150.00 129.00
Mason day 1.50 250.00 375.00
Mazdoor day 20.00 100.00 2000.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00
Generator 33 KVA hour 6.00 400.00 2400.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
12.8 C RCC Grade M20
Unit = cum
Case I Using concrete mixer
Taking output = 15 cum
a) Material
Cement MT 5.21 4180.00 21777.80
Coarse sand cum 6.75 350.00 2362.50
20 mm Aggregate cum 8.10 410.00 3321.00
10 mm Aggregate cum 5.40 410.00 2214.00
b) Labour
Mate day 0.86 150.00 129.00
Mason day 1.50 250.00 375.00
Mazdoor day 20.00 100.00 2000.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00
Generator 33 KVA hour 6.00 400.00 2400.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Case II With Batching Plant, Transit Mixer and
Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 41.66 4180.00 ###
Coarse Sand cum 54.00 160.00 8640.00
20 mm Aggregate cum 64.80 410.00 26568.00

Page 18 of 361
10 mm Aggregate cum 43.20 410.00 17712.00
b) Labour
Mate day 0.84 150.00 126.00
Mason day 3.00 250.00 750.00
Mazdoor day 18.00 100.00 1800.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 600.00 3600.00
Loader 1 cum capacity hour 6.00 700.00 4200.00
Transit Mixer 4 cum capacity for lead upto 1
hour
km. 15.00 600.00 9000.00
Lead beyond 1 km, L-lead in km T-km 300L 1.85 11100.00 L= 20
Concrete Pump hour 6 500.00 3000.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
d) Formwork @ 4% on cost of concrete 10785.39
i.e.cost of material, labour and machinery
e) Overheads @ 10 % on (a+b+c+d) 28042.02
f) Contractors profit @ 10 % on (a+b+c+d+e) 30846.22
Cost for 120 cum = a+b+c+d+e+f ###
Rate per cum = ( a+b+c+d+e+f )/120 2827.57
say 2828.00
12.8 D PCC Grade M25
Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 5.99 4180.00 25038.20
Coarse sand cum 6.75 350.00 2362.50
40 mm Aggregate cum 5.40 350.00 1890.00
20 mm Aggregate cum 5.40 410.00 2214.00
10 mm Aggregate cum 2.70 410.00 1107.00
b) Labour
Mate day 0.86 150.00 129.00
Mason day 1.50 250.00 375.00
Mazdoor day 20.00 100.00 2000.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00
Generator 33 KVA hour 6.00 400.00 2400.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Case II With Batching Plant, Transit Mixer and
Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 47.95 4180.00 ###
Coarse sand cum 54.00 160.00 8640.00
40 mm Aggregate cum 43.20 350.00 15120.00
20 mm Aggregate cum 43.20 410.00 17712.00
10 mm Aggregate cum 21.60 410.00 8856.00
b) Labour
Mate day 0.84 150.00 126.00
Mason day 3.00 250.00 750.00
Mazdoor day 18.00 100.00 1800.00

Page 19 of 361
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 600.00 3600.00
Loader 1 cum capacity hour 6.00 700.00 4200.00
Transit Mixer 4 cum capacity for lead upto 1
hour
km. 15.00 600.00 9000.00
Transit Mixer 4 cum capacity lead T-Km 300L 1.85 11100.00 L= 20
beyond 1 Km, L - lead in
Kilometer
Concrete Pump hour 6 500.00 3000.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
d) Formwork @ 3.75% of cost of concrete 11000.06
i.e.cost of material, labour and machinery
e) Overheads @ 10 % on (a+b+c+d) 30433.51
f) Contractors profit @ 10 % on (a+b+c+d+e) 33476.86
cost of 120 cum = a+b+c+d+e+f ###
Rate per cum (a+b+c+d+e+f)/120 3068.71
say 3069.00
12.8 E RCC Grade M25
Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 6.05 4180.00 25289.00
Coarse sand cum 6.75 350.00 2362.50
20 mm Aggregate cum 8.10 410.00 3321.00
10 mm Aggregate cum 5.40 410.00 2214.00
b) Labour
Mate day 0.86 150.00 129.00
Mason day 1.50 250.00 375.00
Mazdoor day 20.00 100.00 2000.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00
Generator 33 KVA hour 6.00 400.00 2400.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Case II With Batching Plant, Transit Mixer and
Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 48.38 4180.00 ###
Coarse sand cum 54.00 160.00 8640.00
20 mm Aggregate cum 64.80 410.00 26568.00
10 mm Aggregate cum 43.20 410.00 17712.00
Admixer Kg 193.52 50.00 9676.00
b) Labour
Mate day 0.84 150.00 126.00
Mason day 3.00 250.00 750.00
Mazdoor day 18.00 100.00 1800.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 600.00 3600.00
Loader 1 cum capacity 1 cum hour 6.00 700.00 4200.00
Transit Mixer 4 cum capacity for lead upto 1
hour
km. 15.00 600.00 9000.00

Page 20 of 361
Transit Mixer 4 cum capacity lead T-Km 300L 1.85 11100.00 L= 20
beyond 1 Km, L - lead in
Kilometer
Concrete Pump hour 6.00 500.00 3000.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
12.8 F PCC Grade M30
Unit = cum
Case I Using Concrete Mixer
Taking output = 15 cum
a) Material
Cement MT 6.08 4180.00 25414.40
Coarse sand cum 6.75 350.00 2362.50
40 mm Aggregate cum 5.40 350.00 1890.00
20 mm Aggregate cum 5.40 410.00 2214.00
10 mm Aggregate cum 2.70 410.00 1107.00
b) Labour
Mate day 0.86 150.00 129.00
Mason day 1.50 250.00 375.00
Mazdoor day 20.00 100.00 2000.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00
Generator 33 KVA hour 6.00 400.00 2400.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Case II Using Batching Plant, Transit Mixer
and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement MT 48.60 4180.00 ###
Coarse sand cum 54.00 160.00 8640.00
40 mm Aggregate cum 43.20 350.00 15120.00
20 mm Aggregate cum 43.20 410.00 17712.00
10 mm Aggregate cum 21.60 410.00 8856.00
b) Labour
Mate day 0.84 150.00 126.00
Mason day 3.00 250.00 750.00
Mazdoor day 18.00 100.00 1800.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 600.00 3600.00
Loader 1 cum capacity hour 6.00 700.00 4200.00
Transit Mixer 4 cum capacity for lead upto 1
hour
km. 15.00 600.00 9000.00
Transit Mixer 4 cum capacity lead T-Km 300L 1.85 11100.00 L= 20
beyond 1 Km, L - lead in
Kilometer
Concrete Pump hour 6.00 500.00 3000.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
12.8 G RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 6.10 4180.00 25498.00
Coarse sand cum 6.75 350.00 2362.50

Page 21 of 361
20 mm Aggregate cum 8.10 410.00 3321.00
10 mm Aggregate cum 5.40 410.00 2214.00
b) Labour
Mate day 0.86 150.00 129.00
Mason day 1.50 250.00 375.00
Mazdoor day 20.00 100.00 2000.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00
Generator 33 KVA hour 6.00 400.00 2400.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Case II Using Batching Plant, Transit Mixer
and Conrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.80 4180.00 ###
Coarse sand cum 54.00 160.00 8640.00
20 mm Aggregate cum 64.80 410.00 26568.00
10 mm Aggregate cum 43.20 410.00 17712.00
b) Labour
Mate day 0.84 150.00 126.00
Mason day 3.00 250.00 750.00
Mazdoor day 18.00 100.00 1800.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 600.00 3600.00
Loader 1 cum capacity hour 6.00 700.00 4200.00
Transit Mixer 4 cum capacity for lead upto 1
hour
km. 15.00 600.00 9000.00
Transit Mixer 4 cum capacity lead T-Km 300L 1.85 11100.00 L= 20
beyond 1 Km, L - lead in
Kilometer
Concrete Pump hour 6.00 500.00 3000.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
12.8 H RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 6.33 4180.00 26459.40
Coarse sand cum 6.75 350.00 2362.50
20 mm Aggregate cum 8.10 410.00 3321.00
10 mm Aggregate cum 5.40 410.00 2214.00
b) Labour
Mate day 0.86 150.00 129.00
Mason day 1.50 250.00 375.00
Mazdoor day 20.00 100.00 2000.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00
Generator 33 KVA hour 6.00 400.00 2400.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Case II Using Batching Plant, Transit Mixer
and Conrete Pump
Unit ; cum

Page 22 of 361
Taking Output = 120 cum
a) Material
Cement MT 50.64 4180.00 ###
Coarse sand cum 54.00 160.00 8640.00
20 mm Aggregate cum 64.80 410.00 26568.00
10 mm Aggregate cum 43.20 410.00 17712.00
Admixer Kg 202.56 50.00 10128.00
b) Labour
Mate day 0.84 150.00 126.00
Mason day 3.00 250.00 750.00
Mazdoor day 18.00 100.00 1800.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 600.00 3600.00
Loader 1 cum capacity hour 6.00 700.00 4200.00
Transit Mixer 4 cum capacity for lead upto 1
hour
km. 15.00 600.00 9000.00
Transit Mixer 4 cum capacity lead T-Km 300L 1.85 11100.00 L= 20
beyond 1 Km, L - lead
in Kilometer
Concrete Pump hour 6.00 500.00 3000.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
d) Formwork @ 3% on cost of concrete 9518.98
i.e.cost of material, labour and machinery
e) Overheads @ 10 % on (a+b+c+d) 32681.82
f) Contractors profit @ 10 % on (a+b+c+d+e) 35950.00
cost of 120 cum = a+b+c+d+e+f ###
Rate per cum (a+b+c+d+e+f)/120 3295.42
say 3295.00
Rate per cum (a+b+c+d)/120 2723.00
Excluding
Note: Where everOH & CP is carried out using
concrete
batching plant, transit mixer, concrete
pump, admixers @ 0.4% of weight of
cement may be added for achieving desired
slump of concrete.

12.11 1200, Plain/Reinforced cement concrete, in


1500 & well foundation complete as per
1700 drawing and technical specification

C Bottom Plug
Concrete to be placed using tremie pipe
Case I Using Concrete Mixer
(i) PCC Grade M20
Unit = cum
Taking output = 15 cum
a) Material
Cement MT 5.55 4180.00 23199.00
Coarse sand cum 6.75 350.00 2362.50
40 mm Aggregate cum 5.40 350.00 1890.00
20 mm Aggregate cum 5.40 410.00 2214.00
10 mm Aggregate cum 2.70 410.00 1107.00
Admixer Kg 18.60 50.00 930.00
b) Labour
Mate day 0.90 150.00 135.00

Page 23 of 361
Mason day 1.50 250.00 375.00
Mazdoor day 20.00 100.00 2000.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00
Generator 33 KVA hour 6.00 400.00 2400.00
Light Crane 3 tonnes capacity for hour 6.00 225.00 1350.00
handling tremie pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Note 10% extra cement may be added where
under water concreting is involved.
Case II Using Batching Plant, Transit Mixer
and Crane/concrete pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement MT 44.40 4180.00 ###
Coarse sand cum 54.00 160.00 8640.00
20 mm Aggregate cum 64.80 410.00 26568.00
10 mm Aggregate cum 43.20 410.00 17712.00
Admixer Kg 148.80 50.00 7440.00
b) Labour
Mate day 0.88 150.00 132.00
Mason day 3.00 250.00 750.00
Mazdoor day 18.00 100.00 1800.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 600.00 3600.00
Loader 1 cum capacity hour 6.00 700.00 4200.00
Transit Mixer 4 cum capacity for lead upto 1
hour
km. 15.00 600.00 9000.00
Transit Mixer 4 cum capacity, lead T-Km 300L 1.85 11100.00 L= 20
beyond 1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 500.00 3000.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###

(ii) PCC Grade M25

Case I Using Concrete Mixer


Unit = cum
Taking output = 15 cum
a) Material
Cement MT 5.99 4180.00 25038.20
Coarse sand cum 6.75 350.00 2362.50
40 mm Aggregate cum 5.40 350.00 1890.00
20 mm Aggregate cum 5.40 410.00 2214.00
10 mm Aggregate cum 2.70 410.00 1107.00
Admixer Kg 21.60 50.00 1080.00
b) Labour
Mate day 0.90 150.00 135.00
Mason day 1.50 250.00 375.00
Mazdoor day 20.00 100.00 2000.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00

Page 24 of 361
Generator 33 KVA hour 6.00 400.00 2400.00
Light Crane of 3 tonnes capacity for hour 6.00 225.00 1350.00
handling tremie pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Case II Using Batching Plant, Transit Mixer
and Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 47.88 4180.00 ###
Coarse sand cum 54.00 160.00 8640.00
20 mm Aggregate cum 64.80 410.00 26568.00
10 mm Aggregate cum 43.20 410.00 17712.00
Admixer Kg 172.80 50.00 8640.00
b) Labour
Mate day 0.88 150.00 132.00
Mason day 3.00 250.00 750.00
Mazdoor day 18.00 100.00 1800.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 600.00 3600.00
Loader 1 cum capacity hour 6.00 700.00 4200.00
Transit Mixer 4 cum capacity for lead upto 1
hour
km. 15.00 600.00 9000.00
Transit Mixer 4 cum capacity, lead T-Km 300L 1.85 11100.00 L= 20
beyond 1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 500.00 3000.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###

(iii) PCC Grade M30


Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement MT 6.08 4180.00 25414.40
Coarse sand cum 6.75 350.00 2362.50
40 mm Aggregate cum 5.40 350.00 1890.00
20 mm Aggregate cum 5.40 410.00 2214.00
10 mm Aggregate cum 2.70 410.00 1107.00
Admixer Kg 21.60 50.00 1080.00
b) Labour
Mate day 0.90 150.00 135.00
Mason day 1.50 250.00 375.00
Mazdoor day 20.00 100.00 2000.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00
Generator 33 KVA hour 6.00 400.00 2400.00
Light Crane of 3 tonnes capacity for hour 6.00 225.00 1350.00
handling tremie pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Case II Using Batching Plant, Transit Mixer
and Crane/concrete pump
Unit = cum

Page 25 of 361
Taking output = 120 cum
a) Material
Cement MT 48.64 4180.00 ###
Coarse sand cum 54.00 160.00 8640.00
20 mm Aggregate cum 64.80 410.00 26568.00
10 mm Aggregate cum 43.20 410.00 17712.00
Admixer Kg 172.80 50.00 8640.00
b) Labour
Mate day 0.88 150.00 132.00
Mason day 3.00 250.00 750.00
Mazdoor day 18.00 100.00 1800.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 600.00 3600.00
Loader 1 cum capacity hour 6.00 700.00 4200.00
Transit Mixer 4 cum capacity for lead upto 1
hour
km. 15.00 600.00 9000.00
Transit Mixer 4 cum capacity, lead T-Km 300L 1.85 11100.00 L= 20
beyond 1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 500.00 3000.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
(iv) PCC Grade M35

Case I Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a) Material
Cement MT 6.29 4180.00 26292.20
Coarse sand cum 6.75 350.00 2362.50
40 mm Aggregate cum 5.40 350.00 1890.00
20 mm Aggregate cum 5.40 410.00 2214.00
10 mm Aggregate cum 2.70 410.00 1107.00
Admixer Kg 21.60 50.00 1080.00
b) Labour
Mate day 0.90 150.00 135.00
Mason day 1.50 250.00 375.00
Mazdoor day 20.00 100.00 2000.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00
Generator 33 KVA hour 6.00 400.00 2400.00
Light Crane of 3 tonnes capacity for hour 6.00 225.00 1350.00
handling tremie pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Case II Using Batching Plant, Transit Mixer
and Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 50.28 4180.00 ###
Coarse sand cum 54.00 160.00 8640.00
20 mm Aggregate cum 64.80 410.00 26568.00
10 mm Aggregate cum 43.20 410.00 17712.00
Admixer Kg 172.80 50.00 8640.00

Page 26 of 361
b) Labour
Mate day 0.88 150.00 132.00
Mason day 3.00 250.00 750.00
Mazdoor day 18.00 100.00 1800.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 600.00 3600.00
Loader 1 cum capacity hour 6.00 700.00 4200.00
Transit Mixer 4 cum capacity for lead upto 1
hour
km. 15.00 600.00 9000.00
Transit Mixer 4 cum capacity, lead T-Km 300L 1.85 11100.00 L= 20
beyond 1 Km, L - lead in Kilometer
Concrete Pump hour 6.00 500.00 3000.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###
Add 5% of cost of material and labour 13720.62
towards cost of forming sump, protective
bunds, chiselling and making arrangements
for under water concreteing with tremie
pipe..
d) Overheads @ 10 % on (a+b+c) 32803.30
e) Contractors profit @ 10 % on (a+b+c+d) 36083.63
cost of 120 cum = a+b+c+d+e ###
Rate per cum (a+b+c+d+e)/120 3307.67
Say 3308.00
F Well cap
iv) RCC Grade M35
Case II Using Batching Plant, Transit Mixer
and Conrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 50.64 4180.00 ###
Coarse sand cum 54.00 160.00 8640.00
20 mm Aggregate cum 64.80 410.00 26568.00
10 mm Aggregate cum 43.20 410.00 17712.00
b) Labour
Mate day 0.84 150.00 126.00
Mason day 3.00 250.00 750.00
Mazdoor day 18.00 100.00 1800.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 600.00 3600.00
Loader(capacity 1 cum) hour 6.00 700.00 4200.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1
hour
km. 15.00 600.00 9000.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 1.85 11100.00 L= 20
Concrete Pump hour 6.00 500.00 3000.00
Formwork @ 3% of (a+b+c) 9215.14
d) Overheads @ 10 % on (a+b+c) 31638.63
e) Contractors profit @ 10 % on (a+b+c+d) 34802.50
cost of 120 cum = a+b+c+d+e ###
Rate per cum (a+b+c+d+e)/120 3190.23
Say 3190.00

Page 27 of 361
Note Where ever concrete is carried out using
batching plant, transit mixer, concrete
pump, admixers @ 0.4% of weight of
cement may be added for achieving desired
slump of concrete.
3.13 304 Excavation for Structures
Earth work in excavation of foundation of
structures as per drawing and technical
specification, including setting out,
construction of shoring and bracing,
removal of stumps and other deleterious
matter, dressing of sides and bottom,
backfilling the excavation earth to the
extent required and utilising the remaning
earth locally for
I) Ordinary road work.
soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.320 150.00 48.00 L-12
Mazdoor day 8.000 100.00 800.00 L-13
b) Overheads @ 10 % on (a) 84.80
c) Contractors profit @ 10 % on (a+b) 93.28
Cost for 10 cum = a+b+c 1026.08
Rate per cum = (a+b+c)/10 102.61
say 103.00
Note Cost of dewatering may be added where
required upto 10 % of labour cost
Assessment for dewatering shall be made
as per site conditions..

B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.32 150 48.00
Mazdoor day 8.00 100 800.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacityhour 6.00 700 4200.00
c) Overheads @ 10 % on (a+b) 504.80
d) Contractors profit @ 10 % on (a+b+c) 555.28
Cost for 300 cum = a+b+c+d 6108.08
Rate per cum = (a+b+c+d)/300 20.36
say 20.00
Note Cost of dewatering upto 5% of (a+b) may
be added, where required. Assessment for
dewatering shall be made as per site
conditions..

Page 28 of 361
13.6 Section Supplying, fitting and placing HYSD
1600 & bar reinforcement in sub-structure
2200 complete as per drawing and technical
specifications
Output : MT
Taking output = 1 MT
a) Material
HYSD bars including 5% overlaps and MT 1.05 ### 36225.00
wastage
Binding wire kg 6.00 40.00 240.00
b) Labour for cutting, bending, shifting
to site, tying and placing in position
Mate day 0.34 150.00 51.00
Blacksmith day 2.00 150.00 300.00
Mazdoor day 6.50 100.00 650.00
c) Overheads @ 10 % on (a+b) 3746.60
d) Contractors profit @ 10 % on (a+b+c) 4121.26
Rate for per MT (a+b+c+d) 45333.86
say ###
14.1 1500 Furnishing and Placing
&1600 Reinforced/Prestressed cement
1700 concrete in super-structure as per
drawing and Technical Specification
A RCC Grade M20
Case II Using Batching Plant, Transit Mixer
and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 40.92 4180.00 ###
Coarse sand cum 54.00 160.00 8640.00
20 mm Aggregate cum 64.80 410.00 26568.00
10 mm Aggregate cum 43.20 410.00 17712.00
b) Labour
Mate day 0.84 150.00 126.00
Mason day 3.00 250.00 750.00
Mazdoor day 18.00 100.00 1800.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 600.00 3600.00
Loader hour 6.00 700.00 4200.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
hour 15.00 600.00 9000.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 1.85 11100.00 L= 20
Concrete Pump hour 6.00 500.00 3000.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum ###

(i) For solid slab super-structure, 20-30%


(p) of (a+b+c)
Height upto 5m
Basic Cost of Labour, Material & Mechinery ###
(a+b+c) for 120 cum
d) Formwork and staging 20 % of (a+b+c) 20.00 53308.40
e) Overheads @ 10 % on (a+b+c+d) 31985.04
f) Contractors profit @ 10 % on (a+b+c+d+e) 35183.54
Cost for 15 cum = a+b+c+d+e+f ###

Page 29 of 361
Rate per cum (a+b+c+d+e+f)/120 3225.16
say 3225.00
B RCC Grade M25

Case II Using Batching Plant, Transit Mixer


and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 47.95 4180.00 ###
Coarse sand cum 54.20 160.00 8672.00
20 mm Aggregate cum 64.80 410.00 26568.00
10 mm Aggregate cum 43.20 410.00 17712.00
b) Labour
Mate day 0.84 150.00 126.00
Mason day 3.00 250.00 750.00
Mazdoor day 18.00 100.00 1800.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 600.00 3600.00
Loader hour 6.00 700.00 4200.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
hour 15.00 600.00 9000.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 1.85 11100.00 L= 20
Concrete Pump hour 6.00 500.00 3000.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum ###
For formwork and staging add the
(i) following:
For solid slab super-structure, 20-30%
(p) of (a+b+c)
Height upto 5m
Basic Cost of Labour, Material & Mechinery ###
(a+b+c) for 120 cum
d) Formwork and staging 20 % of 20.00 59191.80
(a+b+c)
e) Overheads @ 10 % on (a+b+c+d) 35515.08
f) Contractors profit @ 10 % on 39066.59
(a+b+c+d+e)
Cost for 15 cum= a+b+c+d+e+f ###
Rate per cum (a+b+c+d+e+f)/120 3581.10
say 3581.00

C RCC Grade M 30

Case II Using Batching Plant, Transit Mixer


and Concrete Pump.
Unit = cum
Taking output = 120 cum
a) Material
Cement MT 48.79 4180.00 ###
Coarse sand cum 54.60 160.00 8736.00
20 mm Aggregate cum 64.80 410.00 26568.00
10 mm Aggregate cum 43.20 410.00 17712.00
b) Labour
Mate day 0.88 150.00 132.00

Page 30 of 361
Mason day 3.00 250.00 750.00
Mazdoor day 19.00 100.00 1900.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 600.00 3600.00
Loader hour 6.00 700.00 4200.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
hour 15.00 600.00 9000.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 1.85 11100.00 L= 20
Concrete Pump hour 6.00 500.00 3000.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum ###
For formwork and staging add the
following:
(i) For solid slab super-structure, 20-30%
(p) of (a+b+c)
Height upto 5m
Basic Cost of Labour, Material & Mechinery ###
(a+b+c) for 120 cum
d) Formwork and staging 20 % of (a+b+c) 20.00 59928.20
e) Overheads @ 10 % on (a+b+c+d) 35956.92
f) Contractors profit @ 10 % on (a+b+c+d+e) 39552.61
Cost for 15 cum = a+b+c+d+e+f ###
Rate per cum (a+b+c+d+e+f)/120 3625.66
say 3626.00
Rate per cum (a+b+c+d)/120 ( including formwork and excluding 2996.00
OH & CP)
Rate per cum (a+b+c+d)/120 ( excluding formwork and Excluding2497.00
OH & CP)

E PSC Grade M-40


Case 1 Using concret mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement MT 6.45 4180.00 26961.00
Coarse sand cum 6.75 350.00 2362.50
20 mm Aggregate cum 8.10 410.00 3321.00
10 mm Aggregate cum 5.40 410.00 2214.00
Admixture @ 0.4% of cement kg 25.80 50.00 1290.00
b) Labour
Mate day 0.96 150.00 144.00
Mason day 2.00 250.00 500.00
Mazdoor day 22.00 100.00 2200.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00
Generator 33 KVA hour 6.00 400.00 2400.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 15 cum ###

Case II Using Batching Plant, Transit Mixer


and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material

Page 31 of 361
Cement MT 51.60 4180.00 ###
Coarse sand cum 54.00 160.00 8640.00
20 mm Aggregate cum 64.80 410.00 26568.00
10 mm Aggregate cum 43.20 410.00 17712.00
Admixture @ 0.4% of cement kg 206.40 50.00 10320.00
Admixer Kg 216.00 50.00 10800.00
b) Labour
Mate day 0.94 150.00 141.00
Mason day 3.50 250.00 875.00
Mazdoor day 20.00 100.00 2000.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00
Generator 100 KVA hour 6.00 600.00 3600.00
Loader hour 6.00 700.00 4200.00
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
hour 15.00 600.00 9000.00
Lead beyond 1 Km, L - lead in Kilometer T-Km 300L 1.85 11100.00 L= 20
Concrete Pump hour 6.00 500.00 3000.00
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum ###
For formwork and staging add the
(i) following:
For solid slab super-structure, 18-28%
(p) of (a+b+c)
Height upto 5m
Basic Cost of Labour, Material & Mechinery ###
(a+b+c) for 120 cum
d) Formwork and staging 18 % of 18.00 59875.92
(a+b+c)
e) Overheads @ 10 % on (a+b+c+d) 39251.99
f) Contractors profit @ 10 % on 43177.19
(a+b+c+d+e)
Cost for 15 cum= a+b+c+d+e+f ###
Rate per cum (a+b+c+d+e+f)/120 3957.91
say 3958.00
Note 1.Where ever concrete is carried out using
batching plant, transit mixer, concrete
pump, admixers conforming IS: 9103 @
0.4% of weight of cement may be added for
achieving desired slump of concrete.
2. Cement provided for various components
of the super structure is for estimating
purpose only. Actual quantity of cement
will be as per approved mix design.
Similarly, the provision for coarse and fine
aggregates is for estimating purpose and
the exact quantity shall be as per the mix
3. The items like needle and surface
vibrators are part of minor T & P which is
already covered under the overhead
charges. As such these items have not
been added seperately in the rate analysis.
14.2 1600 A) Supplying ,fitting and placing HYSD
bar reinforcement in super-structure
complete as per drawing and technical
specifications
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5% for laps and wastage
MT 1.05 ### 36225.00

Page 32 of 361
Binding wire Kg 8.00 40.00 320.00
b) Labour for cutting, bending, tying and
placing in position
Mate day 0.44 150.00 66.00
Blacksmith day 3.00 150.00 450.00
Mazdoor day 8.00 100.00 800.00
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c) ###

Page 33 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-1
CARRIAGE OF MATERIALS
Loading and unloading of stone boulder / stone aggregates / sand / kanker /
1.1 moorum. (Placing tipper at loading point, loading with front end loader, dumping, cum 64.00
turning for return trip, excluding time for haulage and return trip)
1.2 Loading and Unloading of Boulders by Manual Means cum 51.00
1.3 Loading and Unloading of Cement or Steel by Manual Means and stacking. tonne 70.00
1.4 Cost of Haulage Excluding Loading and Unloading
(i) Surfaced Road tonne.km 1.50
(ii) Unsurfaced Gravelled Road tonne.km 1.90
(iii) Katcha Track and Track in river bed / nallah bed and choe bed. tonne.km 3.70
Hand Broken Stone Aggregates 63 mm nominal size (Supply of quarried stone,
1.5 hand breaking into coarse aggregate 63 mm nominal size (passing 80 mm and retained cum 472.00
on 50 mm sieve) and stacking as directed)
Crushing of stone aggregates 13.2 mm nominal size. (Crushing of stone boulders
1.6 of 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity cum 471.00
comprising of primary and secondary crushing units, belt conveyor and vibrating screens
to obtain stone aggregates of 13 mm nominal size.)
Crushing of stone aggregates 20 mm nominal size (Crushing of stone boulders of
1.7 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity cum 399.00
comprising of primary and secondary crushing units, belt conveyor and vibrating screens
to obtain stone aggregates of 20 mm nominal size.)
Crushing of stone aggregates 40 mm nominal size (Crushing of stone boulders of
1.8 150 mm size in an integrated stone crushing unit of 200 tonnes per hour capacity cum 337.00
comprising of primary and secondary crushing units, belt conveyor and vibrating screens
to obtain stone aggregates of 40 mm nominal size.)
CHAPTER-2
SITE CLEARANCE
Cutting of Trees, including Cutting of Trunks, Branches and Removal (Cutting of
2.1 trees, including cutting of trunks, branches and removal of stumps, roots, stacking of
serviceable material with all lifts and up to a lead of 1000 mtrs and earth filling in the
depression/pit.)
(i) Girth from 300 mm to 600 mm each 94.00
(ii) Girth from 600 mm to 900 mm each 171.00
(iii) Girth from 900 mm to 1800 mm each 329.00
(iv) Girth above 1800 mm each 622.00
2.2 Clearing Grass and Removal of Rubbish hectare 6413.00
Clearing and Grubbing Road Land .(Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm,
2.3 removal of stumps of trees cut earlier and disposal of unserviceable materials and
stacking of serviceable material to be used or auctioned up to a lead of 1000 metres
including removal and disposal of top organic soil not exceeding 150 mm in thickness.)
(i) By Manual Means:-
A In area of light jungle hectare 19421.00
B In area of thorny jungle hectare 26015.00
(ii) By Mechanical Means
A In area of light jungle hectare 24895.00
B In area of thorny jungle hectare 30082.00
Dismantling of Structures (Dismantling of existing structures like culverts, bridges,
retaining walls and other structure comprising of masonry, cement concrete, wood work,
2.4 steel work, including T&P and scaffolding wherever necessary, sorting the dismantled
material, disposal of unserviceable material and stacking the serviceable material with all
lifts and lead of 1000 metres)
(i) Lime /Cement Concrete
I By Manual Means
A Lime Concrete, cement concrete grade M-10 and below cum 142.00
B Cement Concrete Grade M-15 & M-20 cum 167.00
C Prestressed / Reinforced cement concrete grade M-20 & above cum 436.00
II By Mechanical Means for items No. 202( b) & ( c)
A Cement Concrete Grade M-15 & M-20 cum 193.00
B Prestressed / Reinforced cement concrete grade M-20 & above cum 329.00
(ii) Dismantling Brick / Tile work
A In lime mortar cum 91.00
B In cement mortar cum 116.00
C In mud mortar cum 80.00
D Dry brick pitching or brick soling cum 75.00
(iii) Dismantling Stone Masonry
A Rubble stone masonry in lime mortar cum 101.00
B Rubble stone masonry in cement mortar. cum 116.00

Page 34 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
C Rubble Stone Masonry in mud mortar. cum 91.00
D Dry rubble masonry cum 85.00
E Dismantling stone pitching/ dry stone spalls. cum 80.00
F Dismantling boulders laid in wire crates including opening of crates and cum 91.00
(iv) stacking
Wood workdismantled materials.
wrought framed and fixed in frames of trusses upto a height of 5 m cum 217.00
(v) abovework
Steel plinth
inlevel
all types of sections upto a height of 5 m above plinth level
A excluding
Includingcutting of rivet.
dismembering tonne 553.00
B Excluding dismembering. tonne 413.00
C Extra over item No( V ) A and( V ) B for cutting rivets. tonne 4.00
(vi) Scraping of bricks dismantled from brick work including stacking.
In lime/Cement mortar 1000
A 449.00
numbers
In mud mortar 1000
B 160.00
numbers
(vii) Scraping of Stone from dismantled stone masonry
A In cement and lime mortar cum 180.00
B In Mud mortar cum 38.00
(viii) Scarping plaster in lime or cement mortar from brick/ stone masonry sqm 6.00
Removing all type of hume pipes and stacking within a lead of 1000 metres
(ix) including earthwork and dismantling of masonry works.
A Up to 600 mm dia metre 67.00
B Above 600 mm to 900 mm dia metre 90.00
C Above 900 mm metre 154.00
Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposal
2.5 of dismantled materials up to a lead of 1000 metres, stacking serviceable and
unserviceable materials separately)
I By Manual Means
A Bituminous courses cum 261.00
B Granular courses cum 188.00
II By Mechanical Means
A Bituminous course cum 111.00
Dismantling of Cement Concrete Pavement (Dismantling of cement concrete
pavement by mechanical means using pneumatic tools, breaking to pieces not exceeding
2.6 0.02 cum in volume and stock piling at designated locations and disposal of dismantled cum 574.00
materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials
separately)
Dismantling Guard Rails (Dismantling guard rails by manual means and disposal of
2.7 dismantled material with all lifts and up to a lead of 1000 metres, stacking serviceable metre 28.00
materials and unserviceable materials separately.)
Dismantling Kerb Stone (Dismantling kerb stone by manual means and disposal of
2.8 dismantled material with all lifts and up to a lead of 1000 metre) metre 6.00

Dismantling Kerb Stone channel (Dismantling kerb stone channel by manual means
2.9 and disposal of dismantled material with all lifts and up to a lead of 1000 metre) metre 8.00

Dismantling Kilometre Stone (Dismantling of kilometre stone including cutting of


2.10 earth, foundation and disposal of dismantled material with all lifts and lead upto 1000 m
and back filling of pit.)
A 5th KM stone each 142.00
B Ordinary KM Stone each 82.00
C Hectometre Stone each 16.00
Dismantling of Fencing (Dismantling of barbed wire fencing/ wire mesh fencing
2.11 including posts, foundation concrete, back filling of pit by manual means including metre 18.00
disposal of dismantled material with all lifts and up to a lead of 1000 metres, stacking
serviceable material and unserviceable material separately. )
Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line 600 mm dia
2.12 including disposal with all lifts and lead upto 1000 metres and stacking of serviceable metre 50.00
material and unserviceable material separately under supervision of concerned
department)
Removal of Cement Concrete Pipe of Sewer Gutter (Removal of cement concrete
pipe of sewer gutter 1500 mm dia under the supervision of concerned department
2.13 including disposal with all lifts and up to a lead of 1000 metres and stacking of metre 64.00
serviceable and unserviceable material separately but excluding earth excavation and
dismantling of masonry works.)
Removal of Telephone / Electric Poles and Lines (Removal of telephone / Electric
2.14 poles including excavation and dismantling of foundation concrete and lines under the each 64.00
supervision of concerned department, disposal with all lifts and up to a lead of 1000
metres and stacking the serviceable and unserviceable material separately)

Page 35 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Excavation in Soil by Manual Means. (Excavation for roadway in soil using manual
3.1 means including loading in truck for carrying of cut earth to embankment site with all lifts cum 67.00
and lead upto1000 metres.)
Excavation in ordinary rock by manual means (Excavation in ordinary rock using
3.2 manual means including loading in a truck and carrying of excavated material to cum 93.00
embankment site with in all lifts and leads upto 1000 metres )
Excavation in Soil with Dozer with lead upto 100 metres (Excavation for road way
3.3 in soil by mechanical means including cutting and pushing the earth to site of cum 82.00
embankment upto a distance of 100 metres (average lead50 metres), including trimming
bottom and side slopes in accordance with requirements of lines, grades and cross
Excavation in Ordinary Rock with Dozer with lead upto 100 metres (Excavation
for roadway in ordinary rock by deploying a dozer, 80 HP including cutting and pushing
3.4 the cut earth to site of embankment upto a distance of 100 metres ( average lead 50 cum 138.00
metres ), trimming bottom and side slopes in accordance with the requirements of lines,
grades and cross sections.)
Excavation in Hard Rock (requiring blasting) with disposal upto 1000 metres
(Excavation for roadway in hard rock (requiring blasting) by drilling, blasting and
3.5 breaking, trimming of bottom and side slopes in accordance with requirements of lines, cum 94.00
grades and cross sections, loading and disposal of cut road with in all lifts and leads upto
1000 metres )
Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal
upto 1000 metres. (Excavation for roadwork in soil with hydraulic excavator of0.9 cum
3.6 bucket capacity including cutting and loading in tippers, trimming bottom and side cum 25.00
slopes, in accordance with requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts and lead upto 1000m)
Excavation in Ordinary Rockusing Hydraulic ExcavatorCK-90 and Tippers with
disposal upto 1000 metres. (Excavation for roadway in ordinary rock with hydraulic
3.7 excavator of 0.9 cum bucket capacity including cutting and loading in tippers, cum 33.00
transporting to embankment site within all lifts and lead upto 1000 m, trimming bottom
and side slopes in accordance with requirements of lines, grades and cross sections.)
Excavation in Hard Rock (blasting prohibited) (Excavation for roadway in hard rock
3.8 (blasting prohibited) with rock breakers including breaking rock, loading in tippers and
disposal within all lifts and lead upto 1000 metres, trimming bottom and side slopes in
accordance with requirements of lines, grades and cross sections.)
A Mechanised cum 126.00
B Manual Method cum 373.00
Excavation in Hard Rock (controlled blasting) with disposal upto 1000 metres
(Excavation for roadway in hard rock with controlled blasting by drilling, blasting and
3.9 breaking, trimming of bottom and side slopes in accordance with requirements of lines, cum 126.00
grades and cross sections, loading and disposal of cut road with in all lifts and leads upto
1000 metres )
Excavation in Marshy Soil (Excavation for roadway in marshy soil with hydraulic
3.10 excavator 0.9 cum bucket capacity including cutting and loading in tippers and disposal cum 28.00
with in all lifts and lead upto 1000 metres, trimming of bottom and side slopes in
accordance with requirements of lines, grades and cross sections.)
Removal of Unserviceable Soil with Disposal upto 1000 metres (Removal of
3.11 unserviceable soil including excavation, loading and disposal upto 1000 metres lead but cum 25.00
excluding replacement by suitable soil which shall be paid separately as per clause 305.)

Pre-splitting of Rock Excavation Slopes (Carrying out excavation in hard rock to


achieve a specified slope of the rock face by controlled use of explosives and blasting
3.12 accessories in properly aligned and spaced drill holes, collection of the excavated rock by sqm 79.00
a 80 HP dozer, loading in tipper by a front end loader and disposing of the material with
all lifts and lead upto 1000 m, all as specified in clause No. 303)
Excavation for Structures (Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out, construction of shoring and
3.13 bracing, removal of stumps and other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and utilising the remaining earth
locally for road work.)
(i) Ordinary soil
A Manual Means (Depth upto 3 m) cum 103.00
B Mechanical Means (Depth upto 3 m) cum 20.00
(ii) Ordinary rock (not requiring blasting)
A Manual Means (Depth upto 3 m) cum 128.00
B Mechanical Means cum 27.00
(iii) Hard rock ( requiring blasting )
A Manual Means cum 240.00
(iv) Hard rock ( blasting prohibited )
A Mechanical Means cum 246.00
(v) Marshy soil
A Manual means ( upto 3 m depth) cum 258.00
B Mechanical Means cum 132.00

Page 36 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means
3.14 (Scarifying the existing granular road surface to a depth of 50 mm and disposal of sqm 9.00
scarified material within all lifts and leads upto 1000 metres. )
Scarifying existing bituminous surface to a depth of 50 mm by mechanical
3.15 means (Scarifying the existing bituminous road surface to a depth of 50 mm and sqm 3.00
disposal of scarified material with in all lifts and lead upto 1000 metres.)

Embankment Construction with Material Obtained from Borrow Pits


3.16 (Construction of embankment with approved material obtained from borrow pits with all cum 168.00
lifts and leads, transporting to site, spreading, grading to required slope and compacting
to meet requirement of table 300-2)
Construction of Embankment with Material Deposited from Roadway Cutting
3.17 (Construction of embankment with approved materials deposited at site from roadway cum 59.00
cutting and excavation from drain and foundation of other structures graded and
compacted to meet requirement of table 300-2)
Construction of Subgrade and Earthen Shoulders (Construction of subgrade and
3.18 earthen shoulders with approved material obtained from borrow pits with all lifts & leads, cum 189.00
transporting to site, spreading, grading to required slope and compacted to meet
requirement of table No. 300-2)
3.19 Compacting Original Ground
Compacting original ground supporting subgrade (Loosening of the ground upto
Case-I a level of500 mm below the subgrade level, watered, graded and compacted in layers cum 37.00
to meet requirement of table 300-2 for subgrade construction.)

Case-II :Compacting original ground supporting embankment cum 21.00


Stripping and Storing Top Soil (Stripping, storing of top soil by road side at 15 m
3.20 internal and re-application on embankment slopes, cut slopes and other areas in cum 88.00
localities where the available embankment material is not conducive to plant growth)

Stripping, storing and re-laying top soil from borrow areas in agriculture fields.
3.21 (Stripping of top soil from borrow areas located in agriculture fields, storing at a suitable cum 49.00
place, spreading and re-laying after taking the borrow earth to maintain fertility of the
agricultural field, finishing it to the required levels and satisfaction of the farmer.)
Turfing with Sods (Furnishing and laying of the live sods of perennial turf forming grass
3.22 on embankment slope, verges or other locations shown on the drawing or as directed by sqm 16.00
the engineer including preparation of ground, fetching of rods and watering)

Seeding and Mulching (Preparation of seed bed on previously laid top soil, furnishing
3.23 and placing of seeds, fertilizer, mulching material, applying bituminous emulsion at the sqm 84.00
rate of0.23 litres per sqm and laying and fixing jute netting, including watering for 3
months all as per clause 308)
Surface Drains in Soil (Construction of unlined surface drains of average cross
3.24 sectional area 0.40 sqm in soil to specified lines, grades, levels and dimensions to the
requirement of clause 301 and 309. Excavated material to be used in embankment
within a lead of50 metres (average lead 25 metres))
A Mechanical means metre 31.00
B Manual Means metre 26.00
Surface Drains in Ordinary Rock (Construction of unlined surface drain of average
3.25 cross sectional area 0.4 sqm in ordinary rock to specified lines, grades, levels and
dimensions as per approved design and to the requirement of clause 301 to 309.
Excavated material to be used in embankment at site.)
A Mechanical Means metre 63.00
B Manual Means metre 38.00
3.26 Surface Drains in Hard Rock (Rate per metre may be worked out based on quantity of metre
hard Surface
Sub rock as per design.)
Drains with Perforated Pipe (Construction of subsurface drain with
perforated pipe of 100 mm internal diameter of metal/ asbestos cement/ cement
3.27 concrete/PVC, closely jointed, perforations ranging from 3 mm to 6 mm depending upon 313.00
size of material surrounding the pipe, with 150 mm bedding below the pipe and 300 mm
cushion above the pipe, cross section of excavation 450 x 550 mm. Excavated material
Aggregate Sub- Surface Drains (Construction of aggregate sub surface drain 300 mm
3.28 x 450 mm with aggregates conforming to table 300-4, excavated material to be utilised metre 45.00
in roadway )
Underground Drain at Edge of Pavement (Construction of an underground drain 1 m
3.29 x 1 m (inside dimensions) lined with RCC-20 cm thick and covered with RCC slab10 cm in metre 1430.00
thickness on urban roads)
Preparation and Surface Treatment of formation. (Preparation and surface
3.30 treatment of formation by removing mud and slurry, watering to the extent needed to sqm 1.00
maintain the desired moisture content, trimming to the required line, grade, profile and
rolling with 8-10 tonne smooth wheeled roller, complete as per clause 310.)
Construction of Rock fill Embankment (Construction of rock fill embankment with
3.31 broken hard rock fragments of size not exceeding 300 mm laid in layers not exceeding cum 36.00
500 mm thick including filling of surface voids with stone spalls, blinding top layer with
granular material, rolled with vibratory road roller, all complete as per clause 313)
Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area
3.32 by mechanical means including cutting and trimming of side slopes and disposing of cum 89.00
excavated earth with all lifts and lead upto 1000 metres)
Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring
3.33 Blasting. (Excavation in hilly area in ordinary rock not requiring ballasting by cum 136.00
mechanical means including cutting and trimming of slopes and disposal of cut material
with all lift and lead upto 1000 metres )

Page 37 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Excavation in Hilly Areas in Hard Rock Requiring Blasting (Excavation in hilly
3.34 areas in hard rock requiring blasting, by mechanical means including trimming of slopes cum 175.00
and disposal of cut material with all lifts and lead upto 1000 metres.)

Work in Urban Roads (The cost of earth work in urban roads inhabited area will be
3.35 comparatively higher due to following reasons:)
Embankment Construction with Fly ash/Pond ash available from coal or lignite
burning Thermal Plants as waste material. (Construction of embankment with fly
3.36 ash conforming to table 1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning cum 88.00
thermal power stations as waste material, spread and compacted in layer of 200mm
thickness each at OMC, all as specified in IRC: SP: 58-2001 and as per approved plans.)

Page 38 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
4.1 Granular Sub-base with Close Graded Material (Table:- 400-1)
Plant Mix Method (Construction of granular sub-base by providing close graded
A Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work
site, spreading in uniform layers with motor grader on prepared surface and compacting
with vibratory power roller to achieve the desired density, complete as per clause 401 )
(i) for grading- I Material cum 570.00
(ii) for grading- II Material cum 571.00
(iii) for grading-III Material cum 571.00
By Mix in Place Method (Construction of granular sub-base by providing close graded
B material, spreading in uniform layers with motor grader on prepared surface, mixing by
mix in place method with rotavator at OMC, and compacting with vibratory roller to
achieve the desired density, complete as per clause 401)
(i) for grading- I Material cum 380.00
(ii) for grading- II Material cum 380.00
(iii) for grading-III Material cum 380.00
Granular Sub-Base with Coarse Graded Material ( Table:- 400- 2) (Construction of
granular sub-base by providing coarse graded material, spreading in uniform layers with
4.2 motor grader on prepared surface, mixing by mix in place method with rotavator at OMC,
and compacting with vibratory roller to achieve the desired density, complete as per
clause 401)
(i) for grading- I Material cum 372.00
(ii) for grading- II Material cum 372.00
(iii) for grading-III Material cum 372.00
Lime Stabilisation for Improving Subgrade (Laying and spreading available soil in
the subgrade on a prepared surface, pulverising, mixing the spread soil in place with
4.3 rotavator with 3 % slaked lime having minimum content of 70% of CaO, grading with
motor grader and compacting with the road roller at OMC to the desired density to form a
layer of improved sub grade)
A By Mechanical Means cum 229.00
B By Manual Means cum 226.00
Lime Treated Soil for Sub- Base (Providing, laying and spreading soil on a prepared
sub grade, pulverising, mixing the spread soil in place with rotavator with 3 % slaked
4.4 lime with minimum content of 70% of CaO, grading with motor grader and compacting cum 298.00
with the road roller at OMC to achieve at least 98%of the max dry density to form a layer
of sub base.)
Cement Treated Soil Sub Base/ Base (Providing, laying and spreading soil on a
prepared sub grade, pulverising, adding the designed quantity of cement to the spread
4.5 soil, mixing in place with rotavator, grading with the motor grader and compacting with cum 500.00
the road roller at OMC to achieve the desired unconfined compressive strength and to
form a layer of sub-base/base.)
Cement Treated Crushed Rock or combination as per clause 403.2 and table
400.4in Sub base/ Base (Providing, laying and spreading Material on a prepared sub
4.6 grade, adding the designed quantity of cement to the spread Material, mixing in place
with rotavator, grading with the motor grader and compacting with the road roller at
OMC to achieve the desired unconfined compressive strength and to form a layer of sub-
(i) base/base.)
For Sub-Base course cum 797.00
(ii) For Base course cum 797.00
Making 50 mm x 50 mm Furrows (Making 50 mm x 50 mm furrows, 25mm deep, 450
4.7 to the center line of the road and at one metre interval in the existing thin bituminous sqm 283.00
wearing coarse including sweeping and disposal of excavated material within 1000
metres lead)
Inverted Choke (Construction of inverted choke by providing, laying, spreading and
4.8 compacting screening B type/ coarse sand of specified grade in uniform layer on a cum 279.00
prepared surface with motor grader and compacting with power roller etc)

Water Bound Macadam (Providing, laying, spreading and compacting stone


aggregates of specific sizes to water bound macadam specification including spreading in
4.9 uniform thickness, hand packing, rolling with vibratory roller 8-10 tonnes in stages to
proper grade and camber, applying and brooming requisite type of screening/ binding
Materials to fill up the interstices of coarse aggregate, watering and compacting to the
A required
By Manualdensity.)
Means
(i) Grading- I (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 666.00
(b) Using Screening Type-A (13.2mm Agg.) cum 765.15
(ii) Grading- II (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 701.00
(b) Using Screening Type-A (13.2mm Agg.) cum 747.00

Page 39 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
(c) Using Screening Type-B (11.2mm Agg.) cum 787.00
(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 789.00
(b) Using Screening Type-B (11.2mm Agg.) cum 875.00
B By Mechanical Means:
(i) Grading- I (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 611.00
(b) Using Screening Type-A (13.2mm Agg.) cum 710.46
(ii) Grading- II (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 647.00
(b) Using Screening Type-A (13.2mm Agg.) cum 692.00
(c) Using Screening Type-B (11.2mm Agg.) cum 732.00
(iii) Grading- III (Using Screening Crushable type such as Moorum or Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 735.00
(b) Using Screening Type-B (11.2mm Agg.) cum 820.00
Crushed Cement Concrete Sub-base / Base (Breaking and crushing of material
obtained by breaking damaged cement concrete slabs to size range not exceeding 75
4.10 mm as specified in table 400.7 transporting the aggregates obtained from breaking of cum 211.00
cement concrete slabs at a lead of L km., laying and compacting the same as sub base/
base course, constructed as WBM to clause 404 except the use of screening or binding
Material.)
Penetration Coat Over Top Layer of Crushed Cement Concrete Base (Spraying of
bitumen over cleaned dry surface of crushed cement concrete base at the rate of 25 kg
4.11 per 10 sqm by a bitumen pressure distributor, spreading of key aggregates at the rate of sqm 11.00
0.13 cum per 10 sqm by a mechanical gritter and rolling the surface as per clause
506.3.8)
Wet Mix Macadam (Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including premixing the Material with water
4.12 at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in cum 788.00
uniform layers with paver in sub- base / base course on well prepared surface and
compacting with vibratory roller to achieve the desired density.)
Construction of Median and Island with Soil Taken from Roadway Cutting
4.13 (Construction of Median and Island above road level with approved material deposited at cum 86.00
site from roadway cutting and excavation for drain and foundation of other structures,
spread, graded and compacted as per clause 407)
Construction of Median and Island with Soil Taken from Borrow Areas
4.14 (Construction of median and Island above road level with approved material brought cum 155.00
from borrow pits, spread, sloped and compacted as per clause 407)
4.15 Construction of Shoulders (A. Earthen Shoulders)
Footpaths and Separators (Construction of footpath/separator by providing a 150 mm
4.16 compacted granular sub base as per clause 401 and 25 mm thick cement concrete grade sqm 267.00
M15, over laid with precast concrete tiles in cement mortar 1:3 including provision of all
drainage arrangements but excluding kerb channel..)
Crusher Run Macadam Base (Providing crushed stone aggregate, depositing on a
4.17 prepared surface by hauling vehicles, spreading and mixing with a motor grader,
watering and compacting with a vibratory roller to clause 410 to form a layer of sub-
base/Base)
A By Mix in Place Method
(i) For 53 mm maximum size cum 624.00
(ii) For 45 mm maximum size cum 639.00
B By Mixing Plant :
(i) For 53 mm maximum size cum 813.00
(ii) For 45 mm maximum size cum 520.00
Lime, Fly ash stabalised soil sub-base (Construction of Sub-base using lime - fly
ash admixture with granular soil, free from organic matter/ deleterious
material or clayey silts and low plasticity clays having PI between 5 and 20 and
4.18 liquid limit less than 25 and commercial dry lime, slaked at site or pre-slaked cum 312.00
with CaO content not less than 50%, fly ash to conform to gradation as per
clause 4.3 of IRC: 88-1984, lime + fly ash content ranging between 10 to 30%,
the minimum un-confined compressive strength and CBR value after 28 days
curing and 4 days soaking to be 7.5kg/sq, cm and 25% respectively, all as
specified in IRC: 88-1984. )

Page 40 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Prime coat (Providing and applying primer coat with bitumen emulsion on prepared
5.1 surface of granular Base including clearing of road surface and spraying primer at the sqm 18.00
rate of 0.60 kg/sqm using mechanical means.)
5.2 Tack coat
Providing and applying tack coat with bitumen emulsion using emulsion
pressure distributor at the rate of 0.20 kg per sqm on the prepared sqm 7.00
bituminous/granular surface cleaned with mechanical broom.
Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH
hot mix plant producing an average output of 75 tonnes per hour using crushed
5.3 aggregates of specified grading premixed with bituminous binder, transported to site,
laid over a previously prepared surface with paver finisher to the required grade, level
and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired
(i) compaction)
for Grading I ( 40 mm nominal size ) cum 3550.00
(ii) for GradingII(19 mm nominal size) cum 3551.00
Bituminous Penetration Macadam (Construction of penetration macadam over
prepared Base by providing a layer of compacted crushed coarse aggregate using chips
5.4 spreader with alternate applications of bituminous binder and key aggregates and rolling
with a smooth wheeled steel roller 8-10 tonne capacity to achieve the desired degree of
compaction)
A 50 mm thick sqm 207.00
B 75 mm thick sqm 277.00
Built-Up-Spray Grout (Providing, laying and rolling of built-up-spray grout layer over
prepared base consisting of a two layer composite construction of compacted crushed
coarse aggregates using motor grader for aggregates. key stone chips spreader may be
5.5 sqm 163.00
used with application of bituminous binder after each layer, and with key aggregates
placed on top of the second layer to serve as a Base conforming to the line, grades and
cross-section specified, the compacted layer thickness being 75 mm)
Dense Graded Bituminous Macadam (Providing and laying dense bituminous
macadam with 100-120 TPH batch type HMP producing an average output of 75 tonnes
per hour using crushed aggregates of specified grading, premixed with bituminous binder
5.6 @ 4.0 to 4.5% by weight of total mix of mix and filler, transporting the hot mix to work
site, laying with a hydrostatic paver finisher with sensor control to the required grade,
level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MoRTH specification clause No. 507 complete in
all respects.)
(i) for Grading I ( 40 mm nominal size ) cum 4484.00
(ii) for GradingII(19 mm nominal size) cum 4507.00
Semi - Dense Bituminous Concrete (Providing and laying semi dense bituminous
concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes
per hour using crushed aggregates of specified grading, premixed with bituminous binder
5.7 @ 4.5 to 5 % of mix and filler, transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MoRTH specification clause No. 508 complete in all respects)
(i) for Grading I ( 13 mm nominal size ) cum 4694.00
(ii) for GradingII(10 mm nominal size) cum 5066.00
Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH
batch type hot mix plant producing an average output of 75 tonnes per hour using
crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6
5.8 % of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver
finisher with sensor control to the required grade, level and alignment, rolling with
smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per
(i) MORTH specification
for Grading-I clause
( 13 No. 509 complete
mm nominal size ) in all respects) cum 5174.00
(ii) for Grading-II(10 mm nominal size) cum 5168.00
Surface Dressing (Providing and laying surface dressing as wearing course in single
5.9 coat using crushed stone aggregates of specified size on a layer of bituminous binder laid
on prepared surface and rolling with 8-10 tonne smooth wheeled steel roller)

Case -1 :-19 mm nominal chipping size sqm 49.00


Case - II 13 mm nominal size chipping sqm 41.00
Open - Graded Premix Surfacing (Providing, laying and rolling of open - graded
premix surfacing of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either
5.10 using penetration grade bitumen or cut-back or emulsion to required line, grade and level
to serve as wearing course on a previously prepared base, including mixing in a suitable
plant, laying and rolling with a smooth wheeled roller 8-10 tonne capacity, finished to
required level and grades.)
Case - I: Mechanical method using Penetration grade Bitumen and HMP of
(i) appropriate capacity not less than 75 tonnes/hour . sqm 80.00

(ii) Case - II: Open-Graded Premix Surfacing using cationic Bitumen Emulsion sqm 84.00

Page 41 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Close Graded Premix Surfacing/Mixed Seal Surfacing (Mechanical means using
HMP of appropriate capacity not less than 75 tonnes/hour. Providing, laying
and rolling of close-graded premix surfacing material of 20 mm thickness
5.11 composed of 11.2 mm to 0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b) sqm 95.00
aggregates using penetration grade bitumen to the required line, grade and
level to serve as wearing course on a previously prepared base, including
mixing in a suitable plant, laying and rolling with a Smooth wheeled roller 8-10
tonne capacity, and finishing to required level and grade. )
Seal Coat (Providing and laying seal coat sealing the voids in a bituminous surface laid
5.12 to the specified levels, grade and cross fall using Type A and B seal coats)
(i) Case - I : Type A sqm 38.00
Case - II : Type B (Providing and laying of premix sand seal coat with HMP of
(ii) appropriate capacity not less than 75 tonnes/ hours using crushed stone chipping 6.7 sqm 29.00
mm size and penetration bitumen of suitable grade.)
Supply of Stone Aggregates for Pavement Courses (Supply of stone aggregates
from approved sources confirming to the physical requirement, specified in the
respective specified clauses, including royalties, fees rents, collection, transportation,
5.13 stacking and testing and measured in cum as per clause 514.5 Competitive market rates cum
to be ascertained. Alternatively, rates for stone crushing given in chapter 1may be
adopted, if found economical. In case for supply of aggregates at site are not available,
nearest crusher site may be ascertained. Loading and un-loading charges and cost of
carriage may be added to these rates to arrive at the cost at site.)
Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt wearing course with
paving grade bitumen meeting the requirements given in table 500-29, prepared by
using mastic cooker and laid to required level and slope after cleaning the surface,
5.14 including providing antiskid surface with bitumen precoated fine-grained hard stone sqm 318.00
chipping of 13.2 mm nominal size at the rate of 0.005cum per 10 sqm and at an
approximate spacing of 10 cm center to center in both directions, pressed into surface
when the temperature of surfaces not less than 1000C, protruding 1 mm to 4 mm over
mastic surface, all complete as per clause 515.)
Slurry Seal Providing and laying slurry seal consisting of a mixture of fine aggregates,
5.15 portland cement filler, bituminous emulsion and water on a road surface including
cleaning of surface, mixing of slurry seal in a suitable mobile plant, laying and
compacting to provide even riding surface)
(i) 5 mm thickness sqm 39.00
(ii) 3 mm thickness sqm 27.00
(iii) 1.5 mm thickness sqm 17.00
Recycling of Bituminous Pavement with Central Recycling Plant (Recycling
pavement by cold milling of exiting bituminous layers, planning the surface after cold
milling, reclaiming excavated material to the extent of 30 % of the required quantity,
5.16 hauling and stock piling the reclaimed material near the central recycling plant after cum 3670.00
carrying out necessary checks and evaluation, adding fresh material including
rejuvenators as required, mixing in a hot mix plant, transporting and laying at site and
compacting to the required grade, level and thickness, all as specified in clause 517.)
5.17 Fog Spray sqm 22.00
added 1.In case it is decided by the engineer to blind the fog spray, the following sqm 2.00
may be added
Bituminous Cold Mix ( Including Gravel Emulsion) (Providing, laying and rolling of
5.18 bituminous cold mix on prepared base consisting of a mixture of unheated mineral
aggregate and emulsified or cutback bitumen, including mixing in a plant of suitable type
and capacity, transporting, laying, compacting and finishing to specified grades and
(i) Using bitumen emulsion and 9.5 mm or 13.2 mm nominal size aggregate
levels.) cum 6214.00
(ii) Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate cum 6198.00
(iii) Using cutback bitumen and 9.5 mm or 13.2 mm nominal size aggregate cum 4324.00
(iv) Using cutback bitumen and 19 mm or 26.5 mm nominal size aggregate cum 4302.00
Sand Asphalt Base Course (Providing, laying and rolling sand-asphalt base course
5.19 composed of sand, mineral filler and bituminous binder on a prepared sub-grade or sub- cum 4489.00
base to the lines, levels, grades and cross sections as per the drawings including mixing
in a plant of suitable type and capacity, transporting, laying, compacting and finishing.)
Modified Binder (Supply of modified binder produced by mixing bitumen with modifier
such as natural rubber or crumb rubber or any other polymer found compatible with
bitumen and which allows properties given in clause 521.3 and IRC: SP: 53 blending of
5.20 modifier with bitumen to be done either at the refinery or at the site plant capable of tonne
producing the modified binder to be delivered in drums which shall be agitated in melted
condition using suitable device before use to ensure uniform dispersion.)
5.21 Crack Prevention Courses
Stress Absorbing Membrane (SAM) crack width less than 6 mm (Providing and
laying of a stress absorbing membrane over a cracked road surface, with crack width
below 6 mm after cleaning with a mechanical broom, using modified binder complying
(i) with clause 521, sprayed at the rate of 9 kg per 10 sqm and spreading 5.6 mm crushed sqm 38.00
stone aggregates @ 0.11 cum per 10 sqm with hydraulic chip spreader, sweeping the
surface for uniform spread of aggregates and surface finished to conform to clause
902.)

Page 42 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm (Providing
and laying of a stress absorbing membrane over a cracked road surface, with crack
width 6 to 9 mm after cleaning with a mechanical broom, using modified binder
(ii) complying with clause 521, sprayed at the rate of 11 kg per 10 sqm and spreading sqm 46.00
11.2 mm crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the surface for
uniform spread of aggregates and surface finished to conform to clause 902.)
Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area
above 50 % (Providing and laying a single coat of a stress absorbing membrane over
a cracked road surface, with crack width above 9 mm and cracked area above 50 %
(iii) after cleaning with a mechanical broom, using modified binder complying with clause sqm 61.00
521, sprayed at the rate of 15 kg per 10 sqm and spreading 11.2 mm crushed stone
aggregates @ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of
aggregates
Case - IV : and surface
Bitumen finished to conform
Impregnated to clause
Geotextile 902.) and laying a bitumen
(Providing
(iv) impregnated geotextile layer after cleaning the road surface, geotextile conforming to sqm 434.00
requirements of clause 704.3, laid over a tack coat with 1.05 kg per sqm of paving
grade bitumen 80 - 100 penetration and constructed to the requirement of clause
Recipe Cold Mix (Providing and laying of premix of crushed stone aggregates and
704.4.5)
5.22 emulsion binder, mixed in a batch type cold mixing plant, laid over prepared surface, by
paver finisher, rolled with a pneumatic tyred roller initially and finished with a smooth
steel wheel roller, all as per clause 519.3)
(i) 75 mm thickness cum 3775.00
(ii) 40 mm thickness cum 5449.00
(iii) 25 mm thickness cum 6269.00

Page 43 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-6
CEMENT CONCRETE PAVEMENTS
Dry Lean Cement Concrete Sub- base (Construction of dry lean cement concrete Sub-
base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383,
the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to
6.1 exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement cum 1509.00
content not to be less than 150 kg/ cum, optimum moisture content to be determined
during trial length construction, concrete strength not to be less than 10 Mpa at 7 days,
mixed in a batching plant, transported to site, laid with a paver with electronic sensor,
compacting with 8-10 tonnes vibratory roller, finishing and curing.)
Cement Concrete Pavement (Construction of un-reinforced, dowel jointed, plain
cement concrete pavement over a prepared sub base with 43 grade cement @ 400 kg
per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse
aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved
6.2 mix design, transported to site, laid with a fixed form or slip form paver, spread, cum 4088.00
compacted and finished in a continuous operation including provision of contraction,
expansion, construction and longitudinal joints, joint filler, separation membrane, sealant
primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing
compound, finishing to lines and grades as per drawing )
Rolled Cement Concrete Base (Construction of rolled cement concrete base course
with coarse and fine aggregate conforming to IS:383, the size of coarse aggregate not
exceeding 25 mm with minimum, aggregate cement ratio15:1 and minimum cement
6.3 content of 200 kg/cum, aggregate gradation to be as per table 600-4 after blending, cum 1762.00
mixing in batching plant at optimum moisture content, transporting to site, laying with a
paver with electronic sensor, compacting with 8-10 tonnes smooth wheeled vibratory
roller to achieve, the designed flexural strength, finishing and curing.)
Transition section between rigid and flexible pavement (Due to change in the
properties of materials and type of construction, a gradual changeover from rigid
pavement to flexible pavement is desirable to avoid any damage at the butting joint.
6.4
After provision of an expansion joint in the cement concrete slab, the thickness of slab
should be tapered to 10 cm over a length of 3 m towards the flexible pavement. The
deficiency of thickness caused due to tapering of the slab should be made up by the
asphaltic layers.)
Construction of Base/Sub-base of pavement with lean concrete - fly ash.
(Construction of Base/sub-base using cement, sand, fly ash and coarse aggregates
proportioned as per table 4 of IRC: 74/1979 and with water content ratio, slump and
6.5 compressive strength as defined in the said table, mix prepared in a batching and mixing cum 1434.00
plant and compacted with a vibratory roller 8-10 tonnes capacity within the time limit laid
down vide clause 7.6.3 of IRC: 74-1979, construction joints properly formed at the end of
day's work, cured for 14 days, all as specified in IRC: 74-1979 and as per approved
plans.)
Cement - Fly ash concrete pavement. (Construction reinforced-reinforced, dowel
jointed, plain cement concrete pavement over a prepared sub base with 43 grade
cement, coarse and fine aggregate conforming to IS 383, maximum size of coarse
aggregate not exceeding 25 mm, replacing cement by fly ash to the extent of 15% and
6.6 sand by 10%, mixed in a batching and mixing plant as per approved mix design, cum 3816.00
transported to site, laid with a fixed form or slip form paver, spread, compacted and
finished in a continuous operation including provision of contraction, expansion,
construction and longitudinal joints, joint filler, separation membrane, sealant primer,
joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing
CHAPTER-7
compound, finishing to lines and grades as per drawing )
GEOSYNTHETICS AND REINFORCED EARTH
Sub- Surface Drain with Geotextiles (Construction of sub surface drain 200 mm dia
using geotextiles treated with carbon black with physical properties as given in clause
7.1 702.2.3 formed in to a stable network and a planar geocomposite structure, joints metre 2327.00
wrapped with geotextile to prevent ingress of soil, all as per clause 702 and approved
drawings including excavation and backfilling)
Narrow Filter Sub- Surface Drain (Construction of a narrow filter sub- surface drain
7.2 consisting of porous or perforated pipe laid in narrow trench surrounded by a geotextile metre 738.00
filter fabric, with a minimum of 450 mm overlap of fabric and installed as per clause
702.3 and 309.3.5 including excavation and backfilling)
Laying Paving Fabric Beneath a Pavement Overlay (Providing and laying paving
fabric with physical requirements as per table 704-2 over a tack coat of paving grade
Bitumen 80-100 penetration, laid at the rate of 1 kg per sqm over thoroughly cleaned
7.3 and repaired surface to provide a water resistant membrane and crack retarding layer. sqm 224.00
Paving fabric to be free of wrinkling and folding and to be laid before cooling of tack coat,
brooming and rolling of surface with pneumatic roller to maximise paving fabric contact
with pavement surface)

Page 44 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Laying Boulder Apron in Crates of Synthetic Geogrids (Providing, preparing and
laying of geogrid crated apron 1 m x 5 m, 600 mm thick including excavation and
backfilling with baffles at 1 metre interval, made with geogrids having characteristics as
per clause 704.2, joining sides with connectors/ring staples, top corners to be tie
tensioned, placing of suitable cross interval ties in layers of 300 mm connecting opposite
7.4 cum 1648.00
side with lateral braces and tied with polymer braids to avoid bulging, constructed as per
clause 704.3. filled with stone with minimum size of 200 mm and specific gravity not less
than 2.65, packed with stone spalls, keyed to the foundation recess in case of sloping
ground and laid over a layer of geotextile to prevent migration of fines, all as per clause
704 and laid as per clause 2503.3 and approved design.)
Reinforced Earth Retaining Wall (Reinforced earth retaining walls have four main
components as under: a) Excavation for foundation, foundation concrete and cement
7.5 concrete grooved seating in the foundation for facing elements (facia material). b) Facia
material and its placement. c) Assembling, joining with facing elements and laying of
the reinforcing elements. d) Earthfill with granular material which is to be retained by
(i) the wall.) elements of RCC
Facing sqm 764.00
(ii) Assembling, joining and laying of reinforcing elements.
A With reinforcing element of steel / Aluminium strips / polymeric strips.
Type 1 1.Galvanised carbon steel strips metre 207.00
Type 2 2.Copper Strips metre 320.00
Type 3 3.Aluminium Strips metre 267.00
Type 4 4.Stainless steel strips metre 333.00
Type 5 5.Glass reinforced polymer/fibre reinforced polymer/polymeric strips metre 188.00
B With reinforcing elements of synthetic geogrids sqm 470.00

Page 45 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with
top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on
8.1 M-10 grade foundation 150 mm thick, foundation having 50 mm projection beyond kerb
stone, kerb stone laid with kerb laying machine, foundation concrete laid manually, all
complete as per clause 408)
A Using Concrete Mixer metre 145.00
B Using Concrete Batching and Mixing Plant metre 139.00
Cast in Situ Cement Concrete M 20 Kerb with Channel (Construction of cement
concrete kerb with channel with top and bottom width 115 and 165 mm respectively, 250
8.2 mm high in M 20 grade PCC on M10 grade foundation 150 mm thick, kerb channel 300
mm wide, 50 mm thick in PCC M20 grade, sloped towards the kerb, kerb stone with
channel laid with kerb laying machine, foundation concrete laid manually, all complete as
A per clause
Using 408)
Concrete Mixer metre 268.00
B Using Concrete Batching and Mixing Plant metre 258.00
Printing new letter and figures of any shade (Printing new letter and figures of any
8.3 shade with synthetic enamel paint black or any other approved colour to give an even
shade)
Hindi ( Matras commas and the like not to be measured and paid for Half letter shall cm height
(i) be counted as half ) 0.50
per letter
English and Roman cm height
(ii) 0.30
per letter
Retro- reflectorised Traffic signs (Providing and fixing of retro- reflectorised
cautionary, mandatory and informatory sign as per IRC :67 made of encapsulated lens
type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5 mm thick
8.4
supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the
ground by means of properly designed foundation with M15 grade cement concrete 45
cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing)
(i) 90 cm equilateral triangle each 1754.00
( ii ) 60 cm equilateral triangle each 1401.00
( iii ) 60 cm circular each 1632.00
( iv ) 80 mm x 60 mm rectangular each 1989.00
(v ) 60 cm x 45 cm rectangular each 1608.00
(vi ) 60 cm x 60 cm square each 1772.00
( vii ) 90 cm high octagon each 2338.00
Direction and Place Identification signs upto 0.9 sqm size board. (Providing and
erecting direction and place identification retro-reflectorised sign asper IRC:67 made of
encapsulated lens type reflective sheeting vide clause 801.3, fixed over aluminium
8.5 sqm 3053.00
sheeting, 2 mm thick with area not exceeding 0.9 sqm supported on a mild steel single
angle iron post 75 x 75 x 6 mm firmly fixed to the ground by means of properly designed
foundation with M15 grade cement concrete 45 x 45 x 60 cm, 60 cm below ground level
as per approved
Direction drawing)
and Place Identification signs with size more than 0.9 sqm size board.
(Providing and erecting direction and place identification retro- reflectorised sign asper
IRC :67 made of encapsulated lens type reflective sheeting vide clause 801.3, fixed over
8.6 aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported on a mild steel sqm 5477.00
angle iron post 75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the ground by means of
properly designed foundation with M 15 grade cement concrete45 cm x 45 cm x 60 cm,
60 cm below ground level as per approved drawing)
Overhead Signs (Providing and erecting overhead signs with a corrosion resistant
aluminium alloy sheet reflectorised with high intensity retro-reflective sheeting of
8.7 encapsulated lense type with vertical and lateral clearance given in clause 802.2 and
802.3 and installed as per clause 802.7 over a designed support system of aluminium
alloy or galvanised steel trestles and trusses of sections and type as per structural design
requirements and approved plans)
A Truss and Vertical Support tonne 60847.00
B Aluminium alloy plate for over head sign tonne 948.00
Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the
8.8 surface with synthetic enamel paint in all shades on new plastered concrete surfaces) sqm 45.00

Painting on Steel Surfaces (Providing and applying two coats of ready mix paint of
8.9 approved brand on steel surface after through cleaning of surface to give an even shade) sqm 37.00

Painting on Wood Surfaces (Providing and applying two coats of ready mix paint of
8.10 approved brand on wood surface after through cleaning of surface to give an even sqm 42.00
shade)
Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New Work
8.11 (Painting lines, dashes, arrows etc on roads in two coats on new work with ready mixed
road marking paint conforming to IS:164 on bituminous surface, including cleaning the
surface of all dirt, dust and other foreign matter, demarcation at site and traffic control )
(i) Over 10 cm in width sqm 61.00

Page 46 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
(ii) Up to 10 cm in width sqm 53.00
Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old Work (Painting
8.12 lines, dashes, arrows etc on roads in two coats on old work with ready mixed road
marking paint confirming to IS: 164 on bituminous surface, including cleaning the surface
of all dirt, dust and other foreign matter, demarcation at site and traffic control )
(i) Over 10 cm in width sqm 40.00
(ii) Up to 10 cm in width sqm 42.00
Road Marking with Hot Applied Thermoplastic Compound with Reflectorising
Glass Beads on Bituminous Surface (Providing and laying of hot applied
8.13 thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms sqm 470.00
per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per
IRC:35 .The finished surface to be level, uniform and free from streaks and holes.)
Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of standard
8.14 design as per IRC:8-1980, fixing in position including painting and printing etc)
(i) 5th kilometre stone (precast) each 1713.00
(ii) Ordinary Kilometer stone (Precast) each 1039.00
(iii) Hectometer stone (Precast) each 305.00
Road Delineators (Supplying and installation of delineators (road way indicators,
hazard markers, object markers), 80-100 cm high above ground level, painted black and
8.15 white in 15 cm wide stripes, fitted with 80 x 100 mm rectangular or 75 mm dia circular each 537.00
reflectorised panels at the top, buried or pressed into the ground and confirming toIRC-
79 and the drawings.)
Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of standard
8.16 design as per IRC:25-1967, fixed in position including finishing and lettering but each 244.00
excluding painting)
G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2 metres high GI
barbed wire fencing with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed every 3
metres center to center founded in M15 grade cement concrete, 0.6 metre below ground
8.17 level, every 15th post, last but one end post and corner post shall be strutted on both metre 170.00
sides and end post on one side only and provided with 9 horizontal lines and 2 diagonals
interwoven with horizontal wires, fixed with GI staples, turn buckles etc complete as per
clause 807 ) wire Fencing 1.8 metre high (Providing and fixing 1.8 metres high GI
G.I Barbed
barbed wire fencing with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed every 3
metres center to center founded in M15 grade cement concrete, 0.6 metre below ground
8.18 level, every 15th post, last but one end post and corner post shall be strutted on both metre 284.00
sides and end post on one side only and provided with 12 horizontal lines and 2
diagonals interwoven with horizontal wires, fixed with GI staples, turn buckles etc
complete as per
Fencing with clause 807
welded steel) wire Fabric 75 mm x 50 mm (Suggestive) (Providing
1.20 metre high fencing with angle iron posts 50 mm x 50 mm x 6 mm at 3 metre center
8.19 to center with 0.40 metre embedded in M15 grade cement concrete, corner, end and metre 439.00
every 10th post to be strutted, provided with welded steel wire fabric of 75 mm x 50 mm
mesh or 75 mm x 25 mm mesh and fixed to iron posts by flat iron 50 x 5 mm and bolts
etc. complete
Tubular SteelinRailing
all respects.)
on Medium Weight steel channel ( ISMC series) 100 mm x
8.20 50 mm (Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly painted metre 1371.00
on medium weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 metres high above
ground, 2 m centre to centre, complete as per approved drawings)
Tubular Steel Railing on Precast RCC posts, 1.2 m high above ground level
8.21 (Providing, fencing and erecting 50 mm dia painted steel pipe railing in 3 rows on precast metre 1036.00
M20 grade RCC vertical posts1.8 metres high (1.2 m above GL) with 3 holes 50 mm dia
for pipe, fixed 2 metres centre to, complete as per approved drawing)
Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement
concrete crash barrier at the edges of the road, approaches to bridge structures and
medians, constructed with M-20 grade concrete with HYSD reinforcement conforming to
8.22 IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled with pre-
moulded asphalt filler board, keyed to the structure on which it is built and installed as
per design given in the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III dated
24 June 1994 as per dimensions in the approved drawing and at locations directed by the
Engineer, all as specified)
(i) M 20 grade concrete metre 2152.00
8.23 Metal Beam Crash Barrier
Type - A, "W" : Metal Beam Crash Barrier (Providing and erecting a "W" metal
beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 70 cm
above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm
A spaced 2 m centre to centre, 1.8 m high, 1.1 m below ground/road level, all steel parts metre 1960.00
and fitments to be galvanised by hot dip process, all fittings to conform to IS:1367 and
IS:1364, metal beam rail to be fixed on the vertical post with a spacer of channel
section 150 x 75 x 5 mm, 330 mm long complete as per clause 810)

Page 47 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Type - B, "THRIE" : Metal Beam Crash Barrier (Providing and erecting a "Thrie"
metal beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail,
85 cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x
B 5 mm spaced 2 m centre to centre, 2 m high with 1.15 m below ground level, all steel metre 2772.00
parts and fitments to be galvanised by hot dip process, all fittings to conform to
IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post with a space of
channel section 150 x 75 x 5 mm, 546 mm long complete as per clause 810)
Road Traffic Signals electrically operated (Since it is a ready made item
8.24 commercially produced and erected by specialised firm in the electrical and electronic
field, rate may be taken based on market enquiry from firms specialised in this field and
ISI certified for the approved design and drawing.)
Flexible Crash Barrier, Wire Rope Safety Barrier (Providing and erecting a wire rope
safety barrier with vertical posts of medium weight RS Joist (ISMB series) 100 mm x 75
mm (11.50 kg/m), 1.50 m long 0.85 m above ground and 0.65 m below ground level, split
at the bottom for better grip, embedded in M 15 grade cement concrete 450 x 450 x 450
mm, 1.50 m center to center and with 4 horizontal steel wire rope 40 mm dia and
8.25 metre 1552.00
anchored at terminal posts 15 m apart. Terminal post to be embedded in M 15
gradecementconcretefoundation2400 x 450 x 900 mm (depth), strengthened by a strut
of RS joist 100 x 75 mm, 2 m long at 450 inclination and a tie 100 x 8 mm, 1.50 m long
at the bottom, all embedded in foundation concrete as per approved design and drawing,
rate excluding excavation and cement concrete.)
8.26 Anti - Glare Devices in Median
Plantation (Plantation of shrubs and plants of approved species in the median. apart
A from cutting off glare from vehicle coming from opposite direction, these plants provide a
pleasant envoirenment and are eco-friendly. The rate for this item is available in the
chapter 11 on horticulture. )
Anti - Glare Screen with 25 mm steel pipe framework fixed with circular and
rectangular vans (Providing and erecting an anti - glare screen with 25 mm dia
vertical pipes fabricated and framed in the form of panels of one metre length and 1.75
B mtr height fixed with circular vane 250 mm dia at top and rectangular vane 600 x 300 metre 1972.00
mm at the middle, made out of steel sheet of 3 mm thickness, end vertical pipes of the
panel made larger for embedding in foundation concrete, applying 2 coats of paint on
all exposed
Anti - Glaresurfaces,
Screenall as per
with approved design
Rectangular andMS
Vane of drawings.)
sheet (Providing and erecting
anti - glare screen with rectangular vanes of size 750 x 500 mm made from MS sheet,
3 mm thick and fixed on MS angle 50 x 50 x 6 mm at an angle of 450 to the direction
C of flow of traffic, 1.5 m center to center, top edge of the screen 1.75 m above ground metre 571.00
level, vertical post firmly embedded in cement concrete foundation 0.60 m below
ground level, applying 2 coats of paint on exposed faces, all complete as per approved
design
Street and drawings)
Lighting (Providing and erecting street light mounted on a steel circular hollow
8.27 pole of standard specifications for street lighting, 9 m high spaced 40 m apart, 1.8 m
overhang on both sides if fixed in the median and on one side if fixed on the footpath,
fitted with sodium vapour lamp and fixed firmly in concrete foundation.)
(i) For Fixing in Median each 11175.00
(ii) For fixing in Footpath each 11136.00
Lighting on Bridges (Providing and fixing lighting on bridges, mounted on steel hollow
8.28 circular poles of standard specifications, 5 m high fixed on parapets with cement each 7884.00
concrete, 20 m apart and fitted with sodium vapour lamp)
Cable Duct Across the Road (Providing and laying of a reinforced cement concrete
pipe duct, 300 mm dia, across the road (new construction), extending from drain to drain
in cuts and toe of slope to toe of slope in fills, constructing head walls at both ends,
providing a minimum fill of granular material over top and sides of RCC pipe as per
8.29 IRC:98-1997, bedded on a 0.3 m thick layer of granular material free of rock pieces, outer
to outer distance of pipe at least half dia of pipe subject to minimum 450 mm in case of
double and triple row ducts, joints to be made leak proof, invert level of duct to be above
higher than ground level to prevent entry of water and dirt, all as per IRC: 98 - 1997 and
approved drawings.)
(i) Single Row for one utility service metre 1295.00
(ii) Double Row for two utility services metre 2460.00
(iii) Triple Row for three utility services metre 3631.00
Highway Patrolling and Traffic Aid Post (It is proposed to locate one Traffic Aid Post
8.30 every 50-60 km of the highway. )
Items related to under pass/ subway/ overhead bridge/ overhead foot bridge
(The items involved for underpass/ subway/ overhead bridge/ overhead foot bridge are
8.31 earthwork, plain cement concrete, plastering, painting, information sign etc. The rates for
these items are available in respective chapters which can be adopted for the quantities
derived from the approved designs and drawings)
Traffic Control System and Communication system (Providing a traffic control
centre and communication system including telecommunication facilities and related
accessories, CCTV, radar, vehicle detection camera, central computer system These are
8.32 specialised item of telecommunication system and are the commercial products. The
designer is required to contact the manufacturers to ascertain market prices. In case of
civil works required to be executed for these installations, pricing may be done as per
rates in relevant chapters for quantities derived approved design and drawing.)

Page 48 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Gantry Mounted Variable Message Sign board (Providing and erecting gantry
8.33 mounted variable message sign board electronically operated capable of flashing the
desired message over a designed support system of aluminium alloy or galvanised steel,
erected as per approved design and drawings and with lateral clearance as per clause
(i) Gantry Support System
802.3) tonne 59620.00
Message Display (Message display board 6 sqm electronically operated with
(ii) complete electronic fitments for flashing the pre-determined messages.)
8.34 Traffic Impact Attenuators at Abutments and Piers
With Scrap Tyres (Provision and installation of traffic attenuators at abutment/pier of
A flyovers bridges using scrap tyres of size 100 x 20 retrieved from trucks laid in 2 rows sqm 1073.00
and 4 tiers, one above the other and tied with 20 mm wire rope as per approved
design and drawings.)
Using Plastic/Steel Barrel, Filled with Sand (Provision and installation of traffic
B impact attenuator at abutment/pier of flyovers bridges using plastic/steel barrels 0.60 sqm 777.00
m dia and 1.0 m in height, filled with sand in three rows and tied with20 mm steel wire
rope as per approved design and drawings)
With HI - DRO cell Sandwich (Patented) ((In this patented HI - DRO cell system,
C water gets discharged from plastic tubes on impact over a pre-determined time, thus sqm 2448.00
absorbing the energy))
Road Markers/Road Stud with Lense Reflector (Providing and fixing of road stud
100x 100 mm, die cast in aluminium, resistant to corrosive effect of salt and grit, fitted
8.35 with lense reflectors, installed in concrete or asphaltic surface by drilling hole 30 mm each 269.00
upto a depth of 60 mm and bedded in a suitable bituminous grout or epoxy mortar, all as
per BS 873 part 4:1973)
Traffic Cone (Provision of red fluorescent with white reflective sleeve traffic cone made
8.36 of low density polyethylene (LDPE) material with a square base of 390 x 390 x 35 mm each 485.00
and a height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all as per BS 873)

8.37 Roadside Amenities


Rest Areas (Providing plainly furnished accommodation for rest rooms, dormitories,
restaurants, stalls, shops, petrol pump, telephone booth, first aid room, traffic aid post,
A police assistance booth, including electricity, toilet and sewerage system Pricing may be
done based on current plinth area rates approved by PWD/CPWD/MES for a particular
zone. Area is required to be assessed for specific location as per actual site conditions)
Parking areas and Bus Laybyes for Trucks, Buses and Light vehicles (Pricing of
B parking areas may be done for the quantities of various items based on the approved
dimensions and pavement design for a particular terrain and soil. Rates for items may be
from respective chapters.)
C Lawn (Providing a lawn planted with grass and its maintenance )
Rumble Strips (Provision of 15 nos rumble strips covered with premix bituminous
8.38 carpet, 15-20 mm high at center, 250 mm wide placed at 1 m center to center at sqm
approved locations to control speed, marked with white strips of road marking paint.)

Policeman Umbrella (Provision of a 2 m high (floor to roof) umbrella for traffic


8.39 policeman at road crossings, where necessary, installed on a raised platform, built on a each
central support of a steel pipe 100 mm dia, roof made of 25 mm dia steel pipe to provide
covered area of 3 sqm, roofed with CGI sheets, all steel parts to be given 2 coats of
High
paint)Mast Pole Lighting at Interchanges and Flyovers (Providing and erecting a
high mast pole lighting with 30 m high hot dip galvanised mast designed to withstand
forces exerted with wind speeds of 180 km per hour with 3 seconds gust, as per IS:875
(Part 3) - 1978, fitted with a base flange, door at the base of mast with heavy duty
internal lock, lantern carriage, suitable winching arrangement for safe working load of
8.40 750 kg and high powered electrically driven power tools for raising and lowering of
lantern carriage, flexible 8 core electric cable, lightening conductor, earthing terminal,
and fixing 2 nos aviation obstruction lights on top of the mast, all complete as per
approved design and drawings This is a specialised work and is generally done by firms
who specialise in such jobs. The detailed designs and estimates are submitted by the
firms alongwith their tender for checks by the Department. The cost of this work is
required to be worked out based on approved design, drawings and estimate of the
Toll Plaza (The construction, operation and maintenance of Toll Plaza can be broken
8.41 lowest tender. A separate contract for this work is concluded as the contractors for road
into separate items of work as under based on the approved design and drawings:-)
and bridge works generally donot undertake such jobs.)
Safety Devices and signs in Construction Zones (Provision and fixing of traffic signs
for limited period at suitable locations in construction zone comprising of warning zone,
approach transition zone, working zone and terminal transition zone with a minimum
distance of 60 cm from the edge of the kerb in case of kerbed roads and 2 to 3 m from
8.42 the edge of the carriageway in case of un-kerbed roads, the bottom edge of the lowest
sign plate to be not less than 2 m above the road level, fixed on 60 mm x 60 mm x 6
mm angle iron post, founded and installed as per approved design and drawings,
removed and disposed of after completion of construction work, all as per IRC:SP:55-
2001)
Portable Barricade in Construction Zone (Installation of a steel portable barricade
with horizontal rail 300 mm wide, 2.5 m in length fitted on a 'A' frame made with 45 x 45
8.43 x 5 mm angle iron section, 1.5 m in height, horizontal rail painted (2 coats) with yellow each 1862.00
and white stripes, 150 mm in width at an angle of 450, 'A' frame painted with 2 coats of
yellow paint, complete as per IRC:SP:55-2001 )
8.44 Permanent Type Barricade in Construction Zone

Page 49 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
With Steel Components (Construction of a permanent type barricade made of steel
components, 1.5 m high from road level, fitted with 3 horizontal rails 200 mm wide
A and 4 m long on 50 x 50 x 5 mm angle iron vertical support, painted with yellow and each 2976.00
white strips, 150 mm in width at an angle of450, complete as per IRC:SP:55-2001 )

With Wooden Components (Construction of a permanent type barricade made of


wooden components, 1.5 m high from road level, fitted with 3 horizontal planks 200
B mm wide and 3.66 m long on 100 x 100mm wooden vertical post, painted with yellow each 1619.00
and white striups, 150 mm in width at an angle of450, complete as per IRC:SP:55-
2001 )
With Bricks (Construction of a permanent type barricade made with brick work in
C mud mortar, 1.5 m high, 4 m long, 600 mm thick, plastered with cement mortar 1:6, each 5963.00
painted with yellow and white strips)
Drum Delineator in Construction Zone (Provision of metal drum/empty bitumen
8.45 drum delineator, 300 mm in diameter, 800 mm high, filled with earth for stability, each 418.00
painted in circumferential strips of alternate black and white 100 mm wide fitted with
reflectors 3 Nos of 7.5 cm dia, all as per IRC:SP:55-2001)
Flagman (Positioning of a smart flagman with a yellow vest and a yellow cap and a red
8.46 flag 600 x 600 mm securely fastened to a staff 1 m in length for guiding the traffic) each 159.00

CHAPTER-9
PIPE CULVERTS
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 mix with crushed stone
9.1 aggregate 40 mm nominal size mechanically mixed, placed in foundation and cum 2186.00
compacted by vibration including curing for 14 days.)
Laying Reinforced Cement Concrete Pipe NP4/prestrssed concrete pipe on first
class bedding in single row . (Laying Reinforced cement concrete pipe NP4/prestrssed
9.2 concrete pipe for culverts on first class bedding of granular material in single row
including fixing collar with cement mortar 1:2 but excluding excavation, protection
works, backfilling, concrete and masonry works in head walls and parapets . )
A 1000 mm dia metre 4986.00
B 1200 mm dia metre 5640.00
Laying Reinforced Cement Concrete Pipe NP 4 /prestrssed concrete pipe on
first class bedding in double row . (Laying Reinforced cement concrete pipe NP4
9.3 /prestrssed concrete pipe for culverts on first class bedding of granular material in double
row including fixing collar with cement mortar 1:2 but excluding excavation, protection
works, backfilling, concrete and masonry works in head walls and parapets . )
A 1000 mm dia metre 10026.00
B 1200 mm dia metre 11338.00

Page 50 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-10
MAINTENANCE OF ROADS
Restoration of Rain Cuts (Restoration of rain cuts with soil, moorum, gravel or a
10.1 mixture of these, clearing the loose soil, benching for 300 mm width, laying fresh cum 71.00
material in layers not exceeding 250 mm and compacting with plate compactor or power
rammers to restore the original alignment, levels and slopes)
Maintenance of Earthen Shoulder (filling with fresh soil) (Making up loss of
10.2 material/ irregularities on shoulder to the design level by adding fresh approved soil and sqm 25.00
compacting it with appropriate equipment.)
Maintenance of Earth Shoulder (stripping excess soil) (Stripping excess soil from
10.3 the shoulder surface to achieve the approved level and compacting with plate sqm 7.00
compactor)
Filling Pot- holes and Patch Repairs with open - graded Premix surfacing,
20mm. (Removal of all failed material, trimming of completed excavation to provide
firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of
10.4 sqm 74.00
excavation as per clause 503, back filling the pot holes with hot bituminous material as
per clause 511, compacting, trimming and finishing the surface to form a smooth
continuous surface, all as per clause 3004.2)
Filling Pot- holes and Patch Repairs with - Bituminous concrete, 40mm.
(Removal of all failed material, trimming of completed excavation to provide firm
10.5 vertical faces, cleaning of surface, painting of tack coat on the sides and base of
excavation as per clause 503, back filling the pot holes with hot bituminous material as
per clause 504, compacting, trimming and finishing the surface to form a smooth
(i) continuous surface,
for grading all as per clause 3004.2)
I Material sqm 188.00
(ii) for grading II Material sqm 193.00
Crack Filling (Filling of crack using slow - curing bitumen emulsion and applying crusher
10.6 dust in case crack are wider than 3mm.) metre 2.00

10.7 Dusting (Applying crusher dust to areas of road where bleeding of excess bitumen has sqm 0.51
10.8 A occurred.)
Fog Seal (ref item 5.17) sqm 24.00
B Crack Prevention courses. (ref item 5.21)
(i) Stress Absorbing Membrane (SAM) crack width less than 6 mm sqm 38.00
(ii) Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm sqm 46.00
(iii) Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area sqm 61.00
(iv) above
Bitumen50Impregnated
% Geotextile sqm 434.00
C Slurry Seal (ref item 5.15)
(i) 5 mm thickness sqm 40.00
(ii) 3 mm thickness sqm 28.00
(iii) 1.5 mm thickness sqm 17.00
D Surface Dressing for maintance works. (ref item 5.9)
(i) 19 mm nominal chipping size sqm 49.00
(ii) 13 mm nominal size chipping sqm 41.00
Repair of joint Grooves with Epoxy Mortar Repair of spalled joint grooves of
10.9 contraction joints, longitudinal joints and expansion joints in concrete pavements using metre 471.00
epoxy mortar or epoxy concrete)
Repair of old Joints Sealant (Removal of existing sealant and re sealing of contraction,
10.10 longitudinal or expansion joints in concrete pavement with fresh sealant material) metre 77.00

Hill Side Drain Clearance (Removal of earth from the choked hill side drain and
10.11 disposing it on the valley side manually) metre 14.00

Land Slide Clearance in soil (Clearance of land slides in soil and ordinary rock by a
10.12 bull-dozer D 80 A-12, 180 HP and disposal of the same on the valley side) cum 42.00

Land slide Clearance in Hard Rock Requiring Blasting (Clearing of land slide in hard
10.13 rock requiring blasting for 50% of the boulders and disposal of the same on the valley cum 74.00
side.)
Snow Clearance on Roads with Dozer (Snow clearance from road surface by a bull-
10.14 dozer 165 Hp and disposing it on the valley side) cum 3.00

Snow Clearance on Roads with Snow Blowers (Snow clearance from road surface by
10.15 a snow blower and disposing on the valley side.) cum 1.00

Page 51 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-11
HORTICULTURE
Spreading of Sludge Farm Yard Manure or/and good Earth (Spreading of sludge
11.1 farm yard manure or/ and good earth in required thickness (cost of sludge, farm- yard cum 9.00
manure or/and good earth to be paid for separately))
Grassing with ' Doobs' Grass (Grassing with 'Doobs' grass including watering and
11.2 maintenance of the lawn for 30 days or more till the grass forms a thick lawn free from
weeds and fit for moving including supplying good earth if needed)

(i) In rows 15 cm apart in either direction sqm 76.00


(ii) In rows 7.5 cm apart in either direction sqm 149.00
Making Lawns including Ploughing and Dragging with 'Swagha' Breaking of
11.3 Clod (Making lawns including ploughing and breaking of clod, removal of rubbish, sqm 125.00
dressing and supplying doobs grass roots and planting at 15 cm apart, including
supplying and spreading of farm yard manure at rate of 0.18 cum per 100 sqm)
Maintenance of Lawns or Turfing of Slopes (Maintenance of lawns or Turfing of
11.4 slopes (rough grassing) for a period of one year including watering etc) sqm 92.00

Turfing Lawns with Fine Grassing including Ploughing, Dressing (Turfing lawns
11.5 with fine grassing including ploughing, dressing including breaking of clods, removal of sqm 128.00
rubbish, dressing and supplying doobs grass roots at 10 cm apart, including supplying
and spreading of farm yard manure at rate of0.6 cum per 100 sqm)
11.6 Maintenance of Lawns with Fine Grassing for the First Year sqm 80.00
a) Planting Permanent Hedges including Digging of Trenches (Planting
11.7 permanent hedges including digging of trenches, 60 cm wide and 45 cm deep, refilling metre 242.00
the excavated earth mixed with farmyard manure, supplied at the rate of 4.65 cum per
100 metres and supplying and planting hedge plants at 30 cm apart)
(b) Maintenance of Hedge for one year metre 94.00
11.8 a) Planting Flowering Plants and Shrubs in Central Verge km 49634.00
(b) Maintenance of Flowering Plants and Shrubs in Central Verge for one Year km 78977.00
Planting of Trees and their Maintenance for one Year (Planting of trees by the
11.9 road side (Avenue trees) in 0.60 m dia holes, 1 m deep dug in the ground, mixing the each 436.00
soil with decayed farm yard/sludge mannure, planting the saplings, backfilling the
trench, watering, fixing the tree guard and maintaining the plants for one year)
Renovation Lawns including, Weeding, Forking the Ground, Top Dressing with
Forked Soil (Renovation lawns including, weeding, forking the ground, top dressing
11.10 with forked soil, watering and maintenance the lawns, for 30 days or more, till the sqm 6.00
grass forms a thick lawn, free from weeds, and fit for moving and disposal of rubbish as
directed, including supplying good earth, if needed but excluding the cost of well
decayedat
Supply farm yard
Site manure)
Well Decayed Farm Yard Manure (Supply at site of work well
11.11 decayed farm yard manure, from any available source, approved by the engineer in cum
charge including screening and stacking)
Supply at Site of Work/ Store - Deoiled Neem Cake (Supply at site of work/ store-
11.12 deoiled neem cake duly packed in used gunny bags) quintal

11.13 Supplying Sludge (Supplying sludge duly stacked at site/ store) cum
Half Brick Circular Tree Guard, in 2nd class Brick, internal diametre 1.25
metres, and height 1.2 metres, above ground and 0.20 metre below ground
(Half brick circular tree guard, in 2nd class brick, internal diametre 1.25 metres, and
11.14 each 724.00
height 1.2 metres, above ground and 0.20 metre below ground, bottom two courses laid
dry, and top three courses in cement mortar 1:6 ( 1 cement 6 sand) and the
intermediate courses being in dry honey comb masonry, as per design complete)
Edging with 2nd class Bricks, laid dry lengthwise (Edging with 2nd class
11.15 bricks, laid dry lengthwise, including excavation, refilling, consolidation, metre 14.00
with a hand packing and spreading nearly surplus earth within a lead of 50
metres)
Making Tree Guard 53 cm dia and 1.3 m high as per design from empty
bitumen drum (Making tree guard 53 cm dia and 1.3 m high as per design from empty
11.16 bitumen drum, slit suitably to permit sun and air, (supplied by the department at stock each 333.00
issue rate) including providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with
rivets, complete in all respect)
Making Tree Guard 53 cm dia and 2 metres high as per design from empty
bitumen drums (Making tree guard 53 cm dia and 2 metres high as per design from
11.17 empty bitumen drums, slit suitably to permit sun and air, ( supplied by the department each 567.00
at stock issue rate) including providing and fixing four legs 40 cm long of 30 x 3 mm
MS riveted to tree guard and providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with
Wrought Iron and Mild Steel Welded Work (Wrought iron and mild steel welded
work) (using angles, square bars, tees and channel grills, grating frames, gates and
11.18 tree guards of any size and design etc. including cost of screens and welding rods or quintal 4948.00
bolts and nuts complete fixed in position but without the cost of excavation and concrete
for fixing which will be paid separately)
Tree Guard with MS Iron (Providing and fixing MS iron tree guard 60 cm dia and 2
metre high above ground level formed of 4 Nos (25 x 6 mm) and 8 Nos (25 x 3 mm) each tree
11.19 vertical MS riveted to 3 Nos (25 x 6 mm) iron rings in two halves, bolted together with 8 1269.00
guard
mm dia and 30 mm long bolts including painting two coats with paint of approved brand
over a coat of priming, complete in all respects.)

Page 52 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Tree Guard with MS Angle Iron and Steel Wire (Providing and fixing tree guard 0.60
metre square, 2.00 metre high fabricated with MS angle iron 30 x 30 x 3 mm, MS iron each tree
11.20 1775.00
25 x 3 mm and steel wire3 mm dia welded and fabricated as per design in two halves guard
bolted together)
Compensatory Afforestation (Planting trees as compensatory afforestation at the rate
of 290 trees per hectare at a spacing of 6 m by grubbing and leveling the ground upto a
11.21 depth of 150 mm, digging holes 0.9 m dia, 1 m deep, mixing farm yard/sludge manure hectare 67579.00
with soil, planting of sapling 2 m high with 25 cm dia stem, backfilling the hole and
watering)

Page 53 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-12
FOUNDATIONS
Excavation for Structures (Earth work in excavation of foundation of structures as per
12.1 drawing and technical specification, including setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing of sides and bottom
and backfilling with approved material.)
I Ordinary soil
A Manual Means
(i) upto 3 m depth cum 45.00
(ii) 3 m to 6 m depth cum 58.00
(iii) Above 6 m depth cum 77.00
B Mechanical Means
(i) Depth upto 3 m cum 25.00
(ii) Depth 3 m to 6 m cum 29.00
(iii) Depth above 6m cum 35.00
II Ordinary rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m cum 64.00
B Mechanical Means cum 33.00
III Hard rock ( requiring blasting )
A Manual Means cum 186.00
IV Hard rock ( blasting prohibited )
A Mechanical Means cum 173.00
V Marshy soil
(i) upto 3 m depth
A Manual means cum 177.00
B Mechanical Means cum 50.00
VI Back Filling in Marshy Foundation Pits cum 125.00
Filling Annular Space Around Footing in Rock (Lean cement concrete 1:3:6 nominal
12.2 mix. Rate may be taken as per items 13.4.)
12.3 Sand Filling in Foundation Trenches as per Drawing & Technical Specification cum 474.00
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with
12.4 crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation cum 2215.00
and compacted by vibration including curing for 14 days.)
Brick masonry work in cement mortar 1:3 in foundation complete excluding
12.5 pointing and plastering, as per drawing and technical specifications cum 2417.00

12.6 A Cement mortar1:3 (1cement :3 sand) cum 2595.00


B Cement mortar1:2 (1cement :2 sand) cum 3230.00
C Cement mortar1:4 (1cement :4 sand) cum 2173.00
D Cement mortar1:6 (1cement :6 sand) cum 1768.00
12.7 Stone masonry work in cement mortar 1:3 in foundation complete as drawing
(a) and Technical
Square Specification
Rubble Coursed rubble masonry( first sort ) cum 7216.00
(b) Random Rubble Masonry cum 2230.00
Plain/Reinforced cement concrete in open foundation complete as per drawing
12.8 and technical specifications
A PCC Grade M15 cum 2595.00
B PCC Grade M20 cum 2907.00
C RCC Grade M20
Case I Using concrete mixer cum 2951.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 2828.00
D PCC Grade M25
Case I Using concrete Mixer cum 3190.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3069.00
E RCC Grade M25
Case I Using concrete Mixer cum 3238.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3115.00
F PCC Grade M30
Case I Using Concrete Mixer cum 3214.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 3090.00
G RCC Grade M30
Case I Using Concrete Mixer cum 3248.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 3125.00
H RCC Grade M35
Case I Using Concrete Mixer cum 3312.00

Page 54 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 3190.00
Providing and constructing temporary island 16 m diameter for construction of
12.9 well foundation for 8m dia. Well.
A Assuming depth of water 1.0 m and height of island to be 1.25m. each 33413.00
B Assuming depth of water 4.0 m and height of island 4.5 m. each 146181.00
Providing and constructing one span service road to reach island location
C from one pier location to another pier location metre 1886.00

Providing and laying cutting edge of mild steel weighing 40 kg per metre for
12.10 well foundation complete as per drawing and technical specification. tonne 51283.00

12.11 Plain/Reinforced cement concrete, in well foundation complete as per drawing


A and
Welltechnical
curb specification
(i) RCC M20 Grade
Case I Using concrete mixer cum 3406.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3263.00
(ii) RCC M25 Grade
Case I Using concrete mixer cum 3746.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3720.00
(iii) RCC M35 Grade
Case I Using concrete mixer cum 3859.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3841.00
B Well steining
(I) PCC M15 Grade cum 2745.00
(ii) PCC M20 Grade cum 3075.00
(iii) RCC M20 Grade
Case I Using concrete mixer cum 3123.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 2991.00
(iv) PCC M25 Grade
Case I Using concrete mixer cum 3383.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3254.00
(v) RCC M25 Grade
Case I Using concrete mixer cum 3434.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3410.00
(vi) PCC M30 Grade
Case I Using concrete mixer cum 3417.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3285.00
(vii) RCC M30 Grade
Case I Using concrete mixer cum 3453.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3322.00
(viii) RCC M35 Grade
Case I Using concrete mixer cum 3538.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3520.00
(ix) RCC M40 Grade 3566.00
C Bottom Plug
(i) PCC Grade M20
Case I Using Concrete Mixer cum 3249.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 3035.00
(ii) PCC Grade M25
Case I Using Concrete Mixer cum 3417.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 3201.00
(iii) PCC Grade M30
Case I Using Concrete Mixer cum 3449.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 3235.00
(iv) PCC Grade M35
Case I Using Concrete Mixer cum 3523.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 3308.00
D Intermediate plug
(I) Grade M20 PCC
Case I Using Concrete Mixer cum 3111.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 2910.00
(ii) Grade M25 PCC
Case I Using Concrete Mixer cum 3272.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 3069.00

Page 55 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
(iii) Grade M30 PCC
Case I Using Concrete Mixer cum 3302.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 3101.00
E Top plug
(i) Grade M15 PCC
Case I Using Concrete Mixer cum 2495.00
(ii) Grade M20 PCC
Case I Using Concrete Mixer cum 2795.00
(iii) Grade M25 PCC
Case I Using Concrete Mixer cum 3076.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 2958.00
(iv) Grade M30 PCC
Case I Using Concrete Mixer cum 3106.00
Case II Using Batching Plant, Transit Mixer and Crane/concrete pump cum 2986.00
F Well cap
(i) RCC Grade M20
Case I Using concrete Mixer cum 2920.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 2795.00
(ii) RCC Grade M25
Case I Using concrete Mixer cum 3238.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 3116.00
(iii) RCC Grade M30
Case I Using Concrete Mixer cum 3248.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 3125.00
(iv) RCC Grade M35
Case I Using Concrete Mixer cum 3312.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump cum 3190.00
(v) RCC M40 Grade cum 3365.00
Sinking of 6 m external diameter well ( other than pneumatic method of sinking )
12.12 through all types of strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and technical specifications.
Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 2859.00
(ii) Beyond 3m upto 10m depth metre 4173.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking metre 5512.00
(iv) for the20m
Beyond previous
upto meter
30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking metre 10339.00
b for
Addthe
20%previous
of cost meter
for Kentledge including supports, loading arrangement and 12407.00
(v) Labour30m
Beyond . upto 40 m metre
a Add 10% for every additional meter depth of sinking over the rate of sinking 24563.00
b for the
Add 20%previous
of cost meter
for Kentledge including supports, loading arrangement and metre 29476.00
B Labour
Clayey . ( 6m dia. Well )
soil
(i) Depth below bed level upto 3.0 M metre 4175.00
(ii) Beyond 3m upto 10m depth metre 9015.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking metre 11906.00
b for
Addthe
forprevious
dewateringmeter
@ 5% of cost, if required. metre 12501.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking metre 22332.00
b for
Addthe
5%previous meter
of cost for dewatering of the cost, if required metre 29311.00
c Add 25% of cost for Kentledge including supports, loading arrangement and metre 27915.00
(v) Labour30m
Beyond ). upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking metre 53056.00
b for
Addthe
5%previous meter
of cost for dewatering, if required metre 66850.00
c Add 20% of cost for Kentledge including supports, loading arrangement and metre 63667.00
C Labour).
Soft rock (6m dia well )
(i) Depth of soft rock strata upto 3m metre 10050.00
D Hard rock (6m dia well )
(i) Depth of soft rock strata upto 3m metre 11689.00

Page 56 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Sinking of 7 m external diameter well ( other than pneumatic method of sinking )
12.13 through all types of strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and technical specifications.
Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 0.00
(ii) Beyond 3m upto 10m depth metre 6086.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking metre 8038.00
(iv) for the20m
Beyond previous meter
upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking metre 15078.00
b for
Addthe
20%previous
of cost meter
for Kentledge including supports, loading arrangement and metre 18093.00
(v) Labour) .
Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking metre 35824.00
b for the
Add 20%previous
of cost meter
for Kentledge including supports, loading arrangement, and metre 42989.00
B Labour
Clayey etc.
soil ( 7m dia. Well )
(I) Depth below bed level upto 3.0 M metre 6086.00
(ii) Beyond 3m upto 10m depth metre 8837.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking metre 11670.00
b for
Addthe
forprevious
dewatering meter
@ 5% of cost, if required. metre 12253.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking metre 21888.00
b for
Addthe
5%previous
of cost formeter
dewatering on the cost, if required metre 28728.00
c Add 25% of cost for Kentledge including supports, loading arrangement and metre 27360.00
(v) Labour30m
Beyond ). upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking metre 52003.00
b for
Addthe
5%previous
of cost formeter
dewatering, if required metre 65524.00
c Add 20% of cost for Kentledge including supports, loading arrangement and 62404.00
C Labour).
Soft rock ( 7m dia well )
(i) Depth of soft rock strata upto 3m metre 9353.00
D Hard rock ( 7m dia well )
(i) Depth upto 3 m metre 13043.00
Sinking of 8 m external diameter well ( other than pneumatic method of sinking )
12.14 through all types of strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and technical specifications.
Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 5487.00
(ii) Beyond 3m upto 10m depth metre 6808.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking metre 8990.00
(iv) for the20m
Beyond previous meter
upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking metre 16863.00
b for
Addthe
20%previous
of cost meter
for Kentledge including supports, loading arrangement and metre 20236.00
(v) Labour .
Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking metre 5928.00
b for
Addthe
20%previous
of cost meter
for Kentledge including supports, loading arrangement, and metre 7113.00
B Labour
Clayey etc.
soil ( 8m dia. Well )
(i) Depth upto 3.0 M metre 7439.00
(ii) Beyond 3m upto 10m depth metre 9442.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking metre 12471.00
b for
Addthe
forprevious
dewatering meter
@ 5% of cost, if required. metre 13095.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking metre 23395.00
b for
Addthe
5%previous
of cost formeter
dewatering on the cost, if required metre 30705.00
c Add 25% of cost for Kentledge including supports, loading arrangement and metre 29243.00
(v) Labour30m
Beyond ). upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking metre 55584.00
b for
Addthe
5%previous
of cost formeter
dewatering, if required metre 70035.00
c Add 20% of cost for Kentledge including supports, loading arrangement and metre 66700.00
C Labour).
Soft rock ( 8m dia well )
(i) Depth in soft rock strata upto 3m metre 10384.00

Page 57 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
D Hard rock ( 8m dia well )
(i) Depth in hard rock strata upto 3 m metre 12833.00
Sinking of 9 m external diameter well ( other than pneumatic method of sinking )
12.15 through all types of strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and technical specifications. Depth
of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 5525.00
(ii) Beyond 3m upto 10m depth metre 7483.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking metre 9883.00
(iv) for the20m
Beyond previous meter
upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking metre 18541.00
b for the
Add 20%previous
of cost meter
for Kentledge including supports, loading arrangement and metre 22249.00
(v) Labour30m
Beyond . upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking metre 44050.00
b for
Addthe
20%previous
of cost meter
for Kentledge including supports, loading arrangement, and metre 52861.00
B Labour etc.
Clayey soil ( 9m dia. Well )
(i) Depth below bed level upto 3.0 M metre 7816.00
(ii) Beyond 3m upto 10m depth metre 10200.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking metre 13471.00
b for
Addthe
forprevious
dewateringmeter
@ 5% of cost, if required. metre 14145.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking metre 25268.00
b for
Addthe
5%previous meter
of cost for dewatering on the cost, if required metre 33164.00
c Add 25% of cost for Kentledge including supports, loading arrangement and metre 31585.00
(v) Labour30m
Beyond ). upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking metre 60032.00
b for
Addthe
5%previous meter
of cost for dewatering, if required metre 75640.00
c Add 20% of cost for Kentledge including supports, loading arrangement and metre 72038.00
C Labour).
Soft rock ( 9m dia well )
(i) Depth upto 3m metre 13322.00
D Hard rock ( 9m dia well )
(i) Depth of hard rock strata upto 3 m metre 14930.00
Sinking of 10 m external diameter well ( other than pneumatic method of sinking )
12.16 through all types of strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and technical specifications.
Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 6761.00
(ii) Beyond 3m upto 10m depth metre 7864.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking metre 10386.00
(iv) for the20m
Beyond previous meter
upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking metre 19482.00
b for
Addthe
20%previous
of cost meter
for Kentledge including supports, loading arrangement and metre 23379.00
(v) Labour .
Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking metre 46287.00
b for the
Add 20%previous
of cost meter
for Kentledge including supports, loading arrangement, and metre 55544.00
B Labour
Clayey etc.
soil (10m dia. Well )
(i) Depth below bed level upto 3.0 M metre 8410.00
(ii) Beyond 3m upto 10m depth metre 9843.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking metre 13001.00
b for
Addthe
forprevious
dewateringmeter
@ 5% of cost, if required. metre 13651.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking metre 24388.00
'b for
Addthe
5%previous meter
of cost for dewatering on the cost, if required metre 32010.00
c Add 25% of cost for Kentledge including supports, loading arrangement and metre 30485.00
(v) Labour30m
Beyond ). upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking metre 57942.00
b for
Addthe
5%previous meter
of cost for dewatering, if required metre 73007.00
c Add 20% of cost for Kentledge including supports, loading arrangement and 69531.00
Labour).

Page 58 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
C Soft rock (10m dia well )
(i) Depth of soft rock strata upto 3m metre 13628.00
D Hard rock (10m dia well )
(i) Depth of hard rock strata upto 3 m metre 17899.00
Sinking of 11 m external diameter well ( other than pneumatic method of sinking )
12.17 through all types of strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and technical specifications.
Depth of sinking is reckoned from bed level.
A Sandy soil
(i) Depth from bed level upto 3.0 M metre 15863.00
(ii) Beyond 3m upto 10m depth metre 16403.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking metre 21663.00
(iv) for the20m
Beyond previous meter
upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking metre 40634.00
b for the
Add 20%previous
of cost meter
for Kentledge including supports, loading arrangement and metre 48760.00
(v) Labour30m
Beyond . upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking metre 96542.00
b for
Addthe
20%previous
of cost meter
for Kentledge including supports, loading arrangement, and metre 115851.00
B Labour etc.
Clayey soil (11 m dia. Well )
(i) Depth from bed level upto 3.0 M metre 13991.00
(ii) Beyond 3m upto 10m depth metre 20088.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking metre 26530.00
b for
Addthe
forprevious meter
dewatering @ 5% of cost, if required. metre 27856.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking metre 49762.00
b for
Addthe
5%previous meter
of cost for dewatering on the cost, if required metre 65313.00
c Add 25% of cost for Kentledge including supports, loading arrangement and metre 62203.00
(v) Labour30m
Beyond ). upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking metre 118227.00
b for
Addthe
5%previous meter
of cost for dewatering, if required metre 148966.00
c Add 20% of cost for Kentledge including supports, loading arrangement and metre 141873.00
C Labour).
Soft rock (11m dia well )
(i) Depth of soft rock strata upto 3m metre 30671.00
D Hard rock (11m dia well )
(i) Depth of hard rock upto 3 m metre 40657.00
Sinking of 12 m external diameter well ( other than pneumatic method of sinking )
12.18 through all types of strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and technical specifications.
Depth of sinking is reckoned from bed level.
A Sandy soil
(i) I) Depth below bed level upto 3.0 M metre 32291.00
(ii) Beyond 3m upto 10m depth metre 35685.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking metre 47128.00
(iv) for the20m
Beyond previous meter
upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking metre 88400.00
b for the
Add 20%previous
of cost meter
for Kentledge including supports, loading arrangement and metre 106080.00
(v) Labour30m
Beyond . upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking metre 210026.00
b for
Addthe
20%previous
of cost meter
for Kentledge including supports, loading arrangement, and metre 252031.00
B Labour etc.
Clayey soil (12 m dia. Well )
(i) Depth below bed level upto 3.0 M metre 34594.00
(ii) Beyond 3m upto 10m depth metre 52006.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking metre 68683.00
b for
Addthe
forprevious meter
dewatering @ 5% of cost, if required. metre 72118.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking metre 128832.00
b for
Addthe
5%previous meter
of cost for dewatering on the cost, if required metre 169092.00
c Add 25% of cost for Kentledge including supports, loading arrangement and metre 161040.00
(v) Labour30m
Beyond ). upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking metre 306088.00
for the previous meter

Page 59 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
b Add 5% of cost for dewatering, if required metre 385670.00
c Add 20% of cost for Kentledge including supports, loading arrangement and metre 367305.00
C Labour).
Soft rock (12m dia well )
(i) Depth of soft rock strata upto 3m metre 73329.00
D Hard rock (12m dia well )
(i) Depth of hard rock strata upto 3 m metre 95565.00
Sinking of Twin D Type well ( other than pneumatic method of sinking ) through all
12.19 types of strata namely sandy soil, clayey soil and rock as shown against each
case, complete as per drawing and technical specifications. Depth of sinking is
reckoned from bed level.
A Sandy soil
(i) Depth from bed level upto 3.0 M metre 7358.00
(ii) Beyond 3m upto 10m depth metre 7906.00
(iii) Beyond 10m upto 20m
a Add 5% for every additional meter depth of sinking over the rate of sinking metre 10442.00
(iv) for the20m
Beyond previous meter
upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking metre 19587.00
b for
Addthe
20%previous
of cost meter
for Kentledge including supports, loading arrangement and metre 23504.00
(v) Labour .
Beyond 30m upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking metre 46537.00
b for the
Add 20%previous
of cost meter
for Kentledge including supports, loading arrangement, and metre 55845.00
B Labour
Clayey etc.
soil (Twin D Type Well )
(i) Depth below bed level upto 3.0 M metre 8493.00
(ii) Beyond 3m upto 10m depth metre 10932.00
(iii) Beyond 10 m upto 20 m
a Add 5% for every additional meter depth of sinking over the rate of sinking metre 14438.00
b for
Addthe
forprevious
dewateringmeter
@ 5% of cost, if required. metre 15160.00
(iv) Beyond 20m upto 30 m
a Add 7.5% for every additional meter depth of sinking over the rate of sinking metre 27084.00
b for
Addthe
5%previous meter
of cost for dewatering on the cost, if required metre 35548.00
c Add 25% of cost for Kentledge including supports, loading arrangement and metre 33855.00
(v) Labour30m
Beyond ). upto 40 m
a Add 10% for every additional meter depth of sinking over the rate of sinking metre 64350.00
b for
Addthe
5%previous meter
of cost for dewatering, if required metre 81081.00
c Add 20% of cost for Kentledge including supports, loading arrangement and metre 77220.00
C Labour).
Soft rock (Twin D Type well )
(i) Depth of soft rock strata upto 3m metre 15861.00
D Hard rock (Twin D Type well )
(i) Depth of hard rock strata upto 3 m metre 19635.00
Pneumatic sinking of wells with equipment of approved design, drawing and
specifications worked by competent and trained personnel and comprising of
compression and decompression chambers, reducers, two air locks separately
for men and plant & materials, arrangement for supply of fresh air to working
12.20 chambers, check valves, exhaust valves, shafts made from steel plates of
riveted construction not less than 6 mm thick to withstand an air pressure of
0.50 MPa, controlled blasting of hard rock where required, staircases and 1 m
wide landing plate forms with railing, arrangement for compression and
decompression, electric lighting of 50 V maximum, proper rooms for rest and
medical examinations and compliance with safety precautions as per IS:4138,
12.21 Sand filling in wells complete as per drawing and technical specifications cum 474.00
Providing steel liner 10 mm thick for curbs and 6mm thick for steining of wells
12.22 including fabricating and setting out as per detailed drawing tonne 46907.00

Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as


12.23 per drawing and technical specifications and removal of excavated earth with metre 3577.00
all lifts and lead upto 1000 m. (Pile diameter-750 mm)
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as
12.24 per drawing and technical specifications and removal of excavated earth with metre 5881.00
all lifts and lead upto 1000 m. (Pile diameter-1000 mm)
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as
12.25 per drawing and technical specifications and removal of excavated earth with metre 7477.00
all lifts and lead upto 1000 m. (Pile diameter-1200 mm)
Driven cast-in-place vertical M35 grade R.C.C. pile excluding reinforcement
12.26 complete as per drawing and & Technical Specification (Pile diameter - 750 mm) metre 2354.00

Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement


12.27 complete as per drawing and & Technical Specification (Pile diameter - 1000 mm) metre 3797.00

Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement


12.28 complete as per drawing and & Technical Specification (Pile diameter - 1200 mm) metre 5537.00

Page 60 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement
12.29 complete as per drawing and & Technical Specification (Pile Diameter=500 mm) metre 1064.00

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement


12.30 complete as per drawing and & Technical Specification (Pile Diameter=750 mm) metre 1854.00

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement


12.31 complete as per drawing and & Technical Specification (Pile Diameter=1000 mm) metre 3137.00

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement


12.32 complete as per drawing and & Technical Specification (Size of pile - 300 mm x metre 699.00
300 mm)
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement
12.33 complete as per drawing and & Technical Specification (Size of pile - 500 mm x metre 1217.00
500 mm)
Driven precast vertical M35 grade R.C.C. piles excluding reinforcement
12.34 complete as per drawing and & Technical Specification (Size of pile - 750 mm x metre 2330.00
750 mm)
Driven vertical steel piles complete as per drawing and & Technical
12.35 Specification (Section of the pile - H Section steel column 400 x 250 mm (ISHB Series) ) metre 3452.00

Driven vertical steel piles complete as per drawing and & Technical
12.36 Specification (Section of the pile - H Section steel column 450 x 250 mm (ISHB Series) ) metre 3892.00

12.37 Pile load test on single vertical pile in accordance with IS:2911(Part-IV)
12.38 Cement concrete for reinforced concrete in pile cap complete as per drawing
A and
RCC Technical
Grade M20 Specification
(i) Using Concrete Mixer cum 2919.00
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 2812.00
B RCC Grade M25
(i) Using concrete mixer. cum 3224.00
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 3120.00
C RCC Grade M30
(i) Using concrete mixer. cum 3263.00
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 3156.00
D RCC Grade M35
(i) Using concrete mixer. cum 3344.00
(ii) Using Batching Plant, Transit Mixer and Concrete Pump cum 3240.00
12.39 Levelling course for Pile cap cum 2425.00
Supplying, fitting and placing un-coated HYSD bar reinforcement in
12.40 foundation complete as per drawing and technical specifications tonne 45284.00

Supplying, fitting and placing un-coated Mild steel reinforcement complete in


12.41 foundation as per drawing and technical specification tonne 39678.00

Page 61 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-13
SUB-STRUCTURE
Brick masonry work in 1:3 in sub-structure complete excluding pointing and
13.1 plastering, as per drawing and technical specifications cum 2429.00

13.2 Pointing with cement mortar (1:3 ) on brick work in substructure as per sqm 313.00
13.3 Technical specifications
Plastering with cement mortar (1:3 ) on brick work in sub-structure as per sqm 671.00
Technical specifications
Stone masonry work in cement mortar 1:3 for substructure complete as per
13.4 drawing and Technical Specifications
A Random Rubble Masonry cum 2289.00
B Coursed rubble masonry (first sort ) cum 2365.00
C Ashlar masonry ( first sort ) cum 8146.00
13.5 Plain/Reinforced cement concrete in sub-structure complete as per drawing
A and
PCC technical
Grade M15specifications
(p) Height upto 5m cum 2745.00
B PCC Grade M20
(p) Height upto 5m cum 3075.00
C PCC Grade M25
(p) Height upto 5m
Case I Using concrete Mixer cum 3383.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3254.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 3506.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3373.00
(r) Height above 10m
Case I Using concrete Mixer cum 3660.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3521.00
D PCC Grade M30
(p) Height upto 5m
Case I Using concrete Mixer cum 3417.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3285.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 3541.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3404.00
(r) Height above 10m
Case I Using concrete Mixer cum 3696.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3554.00
E RCC Grade M20
(p) Height upto 5m
Case I Using concrete Mixer cum 3123.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 2991.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 3236.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3100.00
(r) Height above 10m
Case I Using concrete Mixer cum 3378.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3235.00
F RCC Grade M25
(p) Height upto 5m
Case I Using concrete Mixer cum 3434.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3410.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 3546.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3522.00
(r) Height above 10m
Case I Using concrete Mixer cum 3715.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3689.00
G RCC Grade M30
(p) Height upto 5m
Case I Using concrete Mixer cum 3453.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3322.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 3550.00

Page 62 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3416.00
(r) Height above 10m
Case I Using concrete Mixer cum 3688.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3549.00
H RCC Grade M35
(p) Height upto 5m
Case I Using concrete Mixer cum 3538.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3520.00
(q) Height 5m to 10m
Case I Using concrete Mixer cum 3615.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3597.00
(r) Height above 10m
Case I Using concrete Mixer cum 3731.00
Case II With Batching Plant, Transit Mixer and Concrete Pump cum 3713.00
Supplying, fitting and placing HYSD bar reinforcement in sub-structure
13.6 complete as per drawing and technical specifications tonne 45334.00

Supplying, fitting and placing Mild steel reinforcement complete in sub-


13.7 structure as per drawing and technical specification tonne 39394.00

Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment,


13.8 wing wall/return wall with 100 mm dia AC pipe, extending through the full each 61.00
width of the structure with slope of 1V :20H towards drawing foce. Complete as
per drawing and Technical specifications
Back filling behind abutment, wing wall and return wall complete as per
13.9 drawing and Technical specification
A Granular material cum 345.00
B Sandy material cum 549.00
Providing and laying of Filter media with granular materials/stone crushed
aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH
specifications to a thickness of not less than 600 mm with smaller size towards
13.10 cum 339.00
the soil and bigger size towards the wall and provided over the entire surface
behind abutment, wing wall and return wall to the full height compacted to a
firm condition complete as per drawing and technical specification.
Supplying, fitting and fixing in position true to line and level cast steel rocker
bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH tonne
13.11 196.00
specifications complete including all accessories as per drawing and Technical capacity
Specifications.
Supplying, fitting and fixing in position true to line and level forged steel
roller bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 of tonne
13.12 294.00
MoRTH specifications complete including all accessories as per drawing and capacity
Technical Specifications.
Supplying, fitting and fixing in position true to line and level sliding plate
bearing with PTFE surface sliding on stainless steel complete including all tonne
13.13 385.00
accessories as per drawing and Technical Specifications and BS: 5400, section capacity
9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH Specifications.
Supplying, fitting and fixing in position true to line and level elastomeric cubic
13.14 bearing conforming to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH centimetr 0.80
specifications complete including all accessories as per drawing and Technical e
Specifications.
Supplying, fitting and fixing in position true to line and level sliding plate
bearing with stainless steel plate sliding on stainless steel plate with mild tonne
13.15 384.00
steel matrix complete including all accessories as per drawing and Technical capacity
Specifications.
Supplying, fitting and fixing in position true to line and level POT-PTFE bearing
consisting of a metal piston supported by a disc or unreinforced elastomer
confined within a metal cylinder, sealing rings, dust seals, PTFE surface
sliding against stainless steel mating surface, completre assembly to be of tonne
13.16 490.00
cast steel/fabricated structural steel, metal and elastomer elements to be as capacity
per IRC: 83 part-I & II respectively and other parts conforming to BS: 5400,
section 9.1 & 9.2 and clause 2006 of MoRTH Specifications complete asper
drawing and approved technical specifications.

Page 63 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-14
SUPER-STRUCTURE
Furnishing and Placing Reinforced/Prestressed cement concrete in super-
14.1 structure as per drawing and Technical Specification
A RCC Grade M20
Case I Using Concrete Mixer
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 3369.00
(q) Height 5m to 10m cum 3509.00
(r) Height above 10m cum 3650.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 3509.00
(q) Height 5m to 10m cum 3650.00
(r) Height above 10m cum 3790.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 3225.00
(q) Height 5m to 10m cum 3360.00
(r) Height above 10m cum 3494.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 3360.00
(q) Height 5m to 10m cum 3494.00
(r) Height above 10m cum 3628.00
B RCC Grade M25
Case I Using Concrete Mixer
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 3721.00
(q) Height 5m to 10m cum 3876.00
(r) Height above 10m cum 4031.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 3876.00
(q) Height 5m to 10m cum 4031.00
(r) Height above 10m cum 4186.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 3581.00
(q) Height 5m to 10m cum 3730.00
(r) Height above 10m cum 3880.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 3730.00
(q) Height 5m to 10m cum 3880.00
(r) Height above 10m cum 4029.00
C RCC Grade M 30
Case I Using Concrete Mixer
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 3776.00
(q) Height 5m to 10m cum 3933.00
(r) Height above 10m cum 4090.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 3933.00
(q) Height 5m to 10m cum 4090.00
(r) Height above 10m cum 4248.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump.
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 3626.00
(q) Height 5m to 10m cum 3777.00
(r) Height above 10m cum 3928.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 3777.00
(q) Height 5m to 10m cum 3928.00
(r) Height above 10m cum 4079.00
D RCC/PSC Grade M35

Page 64 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Case 1 Using concrete mixer.
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 3804.00
(q) Height 5m to 10m cum 3966.00
(r) Height above 10m cum 4127.00
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 3966.00
(q) Height 5m to 10m cum 4127.00
(r) Height above 10m cum 4288.00
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 4449.00
(q) Height 5m to 10m cum 4772.00
(r) Height above 10m cum 5094.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 3656.00
(q) Height 5m to 10m cum 3811.00
(r) Height above 10m cum 3966.00
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 3811.00
(q) Height 5m to 10m cum 3966.00
(r) Height above 10m cum 4121.00
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 4276.00
(q) Height 5m to 10m cum 4586.00
(r) Height above 10m cum 4895.00
E PSC Grade M-40
Case 1 Using concrete mixer.
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 4065.00
(q) Height 5m to 10m cum 4234.00
(r) Height above 10m cum 4404.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 4234.00
(q) Height 5m to 10m cum 4404.00
(r) Height above 10m cum 4573.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 3829.00
(q) Height 5m to 10m cum 3992.00
(r) Height above 10m cum 4154.00
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 3992.00
(q) Height 5m to 10m cum 4154.00
(r) Height above 10m cum 4316.00
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 4478.00
(q) Height 5m to 10m cum 4803.00
(r) Height above 10m cum 5128.00
F PSC Grade M-45
(i) For solid slab/voided slab super-structure, 16-26% of cost of concrete (a+b+c)
(p) Height upto 5m cum 3980.00
(q) Height 5m to 10m cum 4151.00
(r) Height above 10m cum 4323.00
For I-beam & slab including launching of precast girders by launching truss
(ii) upto 40 m span, 21-31% of cost of concrete.
(p) Height upto 5m cum 4151.00
(q) Height 5m to 10m cum 4323.00
(r) Height above 10m cum 4494.00
(iii) For cast-in-situ box girder, segmental construction and balanced cantilever,
(p) 36-56%
Heightofupto
cost5m
of concrete. cum 4666.00
(q) Height 5m to 10m cum 5009.00

Page 65 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
(r) Height above 10m cum 5352.00
G PSC Grade M-50
(i) For cast-in-situ box girder, segmental construction and balanced cantilever,
(p) 35-55%
Heightofupto
cost5m
of concrete cum 4810.00
(q) Height 5m to 10m cum 5167.00
(r) Height above 10m cum 5523.00
H PSC Grade M- 55
(i) For cast-in-situ box girder, segmental construction and balanced cantilever,
(p) 35-55%
Heightofupto
cost5m
of concrete cum 5091.00
(q) Height 5m to 10m cum 5468.00
(r) Height above 10m cum 5844.78
a) Supplying, fitting and placing HYSD bar reinforcement in super-structure
14.2 complete as per drawing and technical specifications tonne 45812.00

High tensile steel wires/strands including all accessories for stressing,


14.3 stressing operations and grouting complete as per drawing and Technical tonne 93153.00
Specifications
Providing and laying Cement concrete wearing coat M-30 grade including
14.4 reinforcement complete as per drawing and Technical Specifications cum 6661.00

Mastic Asphalt (Providing and laying 12 mm thick mastic asphalt wearing course on top
of deck slab excluding prime coat with paving grade bitumen meeting the requirements
given in table 500-29, prepared by using mastic cooker and laid to required level and
14.5 slope after cleaning the surface, including providing antiskid surface with bitumen sqm 157.00
precoated fine grained hard stone chipping of 9.5 mm nominal size at the rate of
0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both
directions, pressed into surface when the temperature of surfaces not less than 100 deg.
C, protruding 1 mm to 4 mm over mastic surface, all complete as per clause 515.)
Construction of precast RCC railing of M30 Grade, aggregate size not
exceeding 12 mm, true to line and grade, tolurence of vertical RCC post not to
14.6 exceed 1 in 500, centre to centre spacing between vertical post not to exceed metre 1151.00
2000 mm, leaving adequate space between vertical post for expansion,
complete as per approved drawings and technical specifications.
Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size
aggregate, true to line and grade, tolurence of vertical RCC post not to
14.7 exceed 1 in 500, centre to centre spacing between vertical post not to exceed metre 1114.00
2000 mm, leaving adequate space between vertical post for expansion,
complete as per approved drawings and technical specifications.
14.8 Providing, fitting and fixing mild steel railing complete as per drawing and metre 1910.00
14.9 Technical Specification
Drainage Spouts complete as per drawing and Technical specification each 1048.00
14.10 PCC M15 Grade leveling course below approach slab complete as per drawing cum 2495.00
and Technical
Reinforced specification
cement concrete approach slab including reinforcement and
14.11 formwork complete as per drawing and Technical specification cum 5371.00

Providing anti-corrosive treatment to HYSD reinforcement with Fusion Bonded


14.12 Epoxy Coating (FBEC) (To be taken as per the prevailing market rates.) tonne

Precast - pretensioned Girders (Providing, precasting, transportation and placing in


14.13 position precast pretensioned concrete girders as per drawing and technical cum 32093.00
specifications)
14.14 Providing and fixing Helical pipes in voided concrete slabs metre 1337.00
Crash Barriers (The rate analysis for rigid crash barrier in reinforced cement concrete,
14.15 semi-rigid crash barrier with metal beam and flexible crash barrier with wire ropes have
been made and included in chapter-8 on Traffic and Transportation.)

Painting on concrete surface (Providing and applying 2 coats of water based cement
14.16 paint to unplastered concrete surface after cleaning the surface of dirt, dust, oil, metre 31.00
grease, efflorescence and applying paint @ of 1 litre for 2 Sq.m. )
Burried Joint (Providing and laying a burried expansion joint, expansion gap being 20
mm, covered with 12 mm thick, 200 mm wide galvanised wieldable structural steel
14.17 plate as per IS: 2062, placed symmetrical to centre line of the joint, resting freely over metre 974.00
the top surface of the deck concrete, welding of 8 mm dia. 100 mm long galvanised nails
spaced 300 mm c/c along the centre line of the plate, all as specified in clause 2604.)
14.18 Filler joint
Providing & fixing 2 mm thick corrugated copper plate in expansion joint
(i) complete as per drawing & Technical Specification. metre 1676.00

Providing & fixing 20 mm thick compressible fibre board in expansion joint


(ii) complete as per drawing & Technical Specification. metre 131.00

Providing and fixing in position 20 mm thick premoulded joint filler in


(iii) expansion joint for fixed ends of simply supported spans not exceeding 10 m metre 80.00
to cater for a horizontal movement upto 20 mm, covered with sealant
complete as per drawing and technical specifications.
Providing and filling joint sealing compound as per drawings and technical
(iv) specifications with coarse sand and 6% bitumen by weight metre 10.00

Page 66 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
Asphaltic Plug joint (Providing and laying of asphaltic plug joint to provide for
horizontal movement of 25 mm and vertical movement of 2 mm, depth of joint varying
from 75 mm to 100 mm, width varying from 500 mm to 750 mm (in traffic direction),
14.19 metre 752.00
covered with a closure plate of 200mm x 6mm of wieldable structural steel conforming to
IS: 2062, asphaltic plug to consist of polymer modified bitumen binder, carefully
selected single size aggregate of 12.5 mm nominal size and a heat resistant foam
caulking/backer
Elastomeric Slab rod,Steel
all asExpansion
per approved drawings
Joint andand
(Providing specifications.)
laying of an elastomeric slab
steel expansion joint, catering to right or skew (less than 20 deg., moderately curved
with maximum horizontal movement upto 50 mm, complete as per approved drawings
14.20 metre 10181.00
and standard specifications to be installed by the manufacturer/supplier or their
authorised representative ensuring compliance to the manufacturer's instructions for
installation and clause 2606 of MoRTH specifications for road & bridge works.)
Compression Seal Joint (Providing and laying of compression seal joint consisting of
steel armoured nosing at two edges of the joint gap suitably anchored to the deck
14.21 concrete and a preformed chloroprene elastomer or closed cell foam joint sealer metre 2078.00
compressed and fixed into the joint gap with special adhesive binder to cater for a
horizontal movement upto 40 mm and vertical movement of 3 mm.)
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint catering
to maximum horizontal movement upto 70 mm, complete as per approved drawings and
14.22 standard specifications to be installed by the manufacturer/supplier or their authorised metre 8908.00
representative ensuring compliance to the manufacturer's instructions for installation.)

Modular Strip / Box Seal Joint (Providing and laying of a modular strip Box steel
expansion joint including anchorage catering to a horizontal movement beyond 70 mm
14.23 and upto 140mm, complete as per approved drawings and standard specifications to be metre 8486.00
installed by the manufacturer/supplier or their authorised representative ensuring
compliance to the manufacturer's instructions for installation.)
Modular Strip / Box Seal Joint (Providing and laying of a modular strip box seal
expansion joint catering to a horizontal movement beyond 140mm and upto 210mm,
14.24 complete as per approved drawings and standard specifications to be installed by the metre 9700.00
manufacturer/supplier or their authorised representative ensuring compliance to the
manufacturer's instructions for installation.)

Page 67 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-15
RIVER TRAINING AND PROTECTION WORKS
Providing and laying boulders apron on river bed for protection against scour
15.1 with stone boulders weighing not less than 40 kg each complete as per
drawing and Technical specification.
A Boulder laid dry without wire crates. cum 563.00
Boulder apron laid in wire crates (Providing and laying of boulder apron laid in wire
15.2 crates made with 4mm dia GI wire conforming to IS: 280 & IS:4826 in 100mm x 100mm cum 1416.00
mesh (weaved diagonally) including 10% extra for laps and joints laid with stone
boulders weighing not less than 40 kg each.)
Cement concrete blocks (size 0.5 x 0.5 x 0.5 m) (Providing and laying of apron with
15.3 cement concrete blocks of size 0.5x0.5x0.5 m cast in-situ and made with nominal mix of cum 2647.00
M-15 grade cement concrete with a minimum cement content of 250 kg/cum as per IRC:
21-2000.)
Providing and laying Pitching on slopes laid over prepared filter media
15.4 including boulder apron laid dry in front of toe of embankment complete as per
drawing and Technical specifications
A Stone/Boulder cum 563.00
B Cement Concrete blocks of size 0.3x0.3 x0.3 m cast in cement concrete of cum 2647.00
Grade M15
Providing and laying Filter material underneath pitching in slopes complete as
15.5 per drawing and Technical specification cum 400.00

Geotextile Filter (Laying of a geotextile filter between pitching and embankment slopes
15.6 on which pitching is laid to prevent escape of the embankment material through the sqm 471.00
voids of the stone pitching/cement concrete blocks as well as to allow free movement of
water without creating any uplift head on the pitching.)
Toe protection (A toe wall for toe protection can either be in dry rubble masonry in case
of dry rubble pitching or pitching with stones in wire crates or it can be in PCC M15
15.7 nominal mix if cement concrete block have been used for pitching . Rates for toe wall can
be adopted from respective clauses depending upon approved design. The rate for
excavation for foundation, dry rubble masonry and PCC M15 have been analysed and
Providing and laying Flooring complete as per drawing and Technical
15.8 specifications laid over cement concrete bedding.
A Rubble stone laid in cement mortar 1:3 cum 2439.00
B Cement Concrete blocks Grade M15 cum 3486.00
15.9 Dry rubble Flooring cum 714.00
15.10 Curtain wall complete as per drawing and Technical specification
A Stone masonry in cement mortar (1:3) cum 7216.00
B Cement concrete Grade M15 cum 2595.00
Flexible Apron :Construction of flexible apron 1 m thick comprising of loose
15.11 stone boulders weighing not less than 40 kg beyond curtain wall. cum 571.00

Gabian Structure for Retaining Earth (Providing and construction of a gabain


structure for retaining earth with segments of wire crates of size 7 m x 3 m x 0.6 m each
divided into 1.5 m compartments by cross netting, made from 4 mm galvanised steel
15.12 cum 1607.00
wire @ 32 kg per 10 sqm having minimum tensile strength of 300 Mpa conforming to
IS:280 and galvanizing coating conforming to IS:4826, woven into mesh with double
twist, mesh size not exceeding 100 x 100 mm, filled with boulders with least dimension
of 200 mm,
Gabian all loose
Structure ends
for to be Control,
Erosion tied with 4River
mm galvanised steel wire)
Training Works and Protection
works (Providing and constructing gabain structures for erosion control, river training
works and protection works with wire crates of size 2 m x 1 m x 0.3 m each divided into
15.13 1m compartments by cross netting, made from 4 mm galvanised steel wire @ 32 kg per cum 3061.00
10 sqm having minimum tensile strength of 300 Mpa conforming to IS:280 and
galvanizing coating conforming to IS:4826, woven into mesh with double twist, mesh
size not exceeding 100 mm x 100 mm, filled with boulders with least dimension of 200
mm, all loose ends to be securely tied with 4 mm galvanised steel wire.)

Page 68 of 361
Summary of Rate Analysis
Item No. Descriptions Unit Rate
CHAPTER-16
REPAIR AND REHABILITATION
Removal of existing cement concrete wearing coat including its disposal
16.1 complete as per Technical specification without causing any detrimental effect sqm 40.00
to any part of the bridge structure and removal of dismantled material with all
lifts and lead upto 1000m(Thickness 75 mm)
Removal of existing asphaltic wearing coat comprising of 50 mm thick asphaltic
16.2 concrete laid over 12 mm thick mastic asphalt including disposal with all lift sqm 30.00
and lead upto 1000m.
Guniting concrete surface with cement mortar applied with compressor after
16.3 cleaning surface and spraying with epoxy complete as per Technical sqm 547.00
specification
Providing and inserting nipples with approved fixing compound after drilling
16.4 holes for grouting as per Technical specifications including subsequent each 62.00
cutting/removal and sealing of the hole as necessary of nipples after
completion of grouting with Cement/Epoxy
Sealing of cracks/porous concrete by injection process through
16.5 nipples/Grouting complete as per Technical specification.
A Cement Grout kg 85.00
B Cement mortar (1:1) Grouting kg 82.00
Patching of damaged concrete surface with polymer concrete and curing
16.6 compounds, initiator and promoter, available in present formulations, to be sqm 11529.00
applied as per instructions of manufacturer and as approved by the Engineer.

Sealing of crack / porous concrete with Epoxy Grout by injection through


16.7 nipples complete as per clause 2803.1. kg 465.00

Applying epoxy mortar over leached, honey combed and spalled concrete
16.8 surface and exposed steel reinforcement complete as per Technical sqm 251.00
specification
Removal of defective concrete, cleaning the surface thoroughly, applying the
shotcrete mixture mechanically with compressed air under pressure,
comprising of cement, sand, coarse aggregates, water and quick setting
16.9 compound in the proportion as per clause 2807.1., sand and coarse aggregates sqm 140.00
conforming to IS: 383 and table 1 of IS: 9012 respectively, water cement ratio
ranging from 0.35 to 0.50, density of gunite not less than 2000 kg/cum,
strength not less than 25 Mpa and workmanship conforming to clause 2807.6.
Applying pre-packed cement based polymer mortar of strength 45 Mpa at 28
16.10 days for replacement of spalled concrete sqm 502.00

16.11 Eproxy bonding of new concrete to old concrete sqm 313.00


Providing external prestressing with high tensile steel wires/strands including
16.12 drilling for passage of prestessing steel, all accessories for stressing and tonne 198561.00
stressing operation and grouting complete as per drawing and Technical
specification
Providing external prestressing with high tensile steel wires/strands including
16.13 drilling for passage of prestessing steel, all accessories for stressing and tonne 191186.00
stressing operation and grouting complete as per drawing and Technical
specification
Providing external prestressing with high tensile steel wires/strands including
16.14 drilling for passage of prestessing steel, all accessories for stressing and tonne 173973.00
stressing operation and grouting complete as per drawing and Technical
specification
16.15 Replacement of bearings complete as per Technical specification each 52875.00
16.16 Rectification of bearings as per Technical specifications each 28675.00
16.17 Replacement of Expansion Joints complete as per drawings metre 1449.00
16.18 Replacement of damaged concrete railing. metre 82.00
16.19 Replacement of crash barrier. metre 146.00
16.20 Replacement of damaged mild steel railing metre 69.00
Repair of crash barrier (Repair of concrete crash barrier with cement concrete of M-30
16.21 grade by cutting and trimming the damaged portion to a regular shape, cleaning the metre 103.00
area to be repaired thoroughly, applying cement concrete after erection of proper form
work.)
16.22 Repair of RCC Railing (Carrying out repair of RCC M30 railing to bring it to the original metre 82.00
16.23 shape.)
Repair of steel Railing (Repair of steel railing to bring it to the original shape) metre 171.00

Page 69 of 361
CHAPTER-1
Ref. CARRIAGE OF MATERIALS
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
1.1 Spec. Loading and Unloading of Stone cum
Boulder/Stone
aggregates/Sand/Kanker/Moorum.
Placing tipper at loading point, loading with
front end loader, dumping, turning for
return trip, excluding time for haulage and
return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading 1 Min
point
ii) Loading by front end loader 1 cum 13 Min
bucket capacity @ 25 cum per hour
iii) Maneuvering, reversing, dumping 2 Min
and turning for return
iv) Waiting time, unforeseen 4 Min
contingencies
Total etc 20 Min
a) Machinery
Tipper 5.5 tonnes capacity hour 0.330 185.00 61.05 P&M-
Front end-loader 1 cum bucket capacity hour 0.330 700.00 231.00 048
P&M-
@ 25 cum/hour 017
b) Overhead charges @ 10 % on (a) 29.21
c) Contractor's profit @ 10 % on 32.13
(a+b)
Cost for 5.5 cum = a+b+c 353.38
Rate per cum = (a+b+c)/ 5.5 64.25
Note Unloading will be by tipping. say 64.00
1.2 Loading and Unloading of Boulders by
Manual Means
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate day 0.110 150.00 16.50 L-12
Mazdoor for loading and unloading day 0.750 100.00 75.00 L-13
b) Machinery
Tipper 5.5 tonne capacity hour 0.750 185.00 138.75 P&M-
c) Overhead charges @ 10 % on 23.03 048
(a+b)
d) Contractor's profit @ 10 % on 25.33
(a+b+c)
Cost for5.5 cum = a+b+c+d 278.60
Rate per cum = (a+b+c+d)/5.5 50.66
Note Unloading will be by tipping. say 51.00
1.3 Loading and Unloading of Cement or
Steel by Manual Means and Stacking.
Unit = tonne
Taking output = 10 tonnes
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor for loading and unloading day 2.000 100.00 200.00 L-13
b) Machinery
Truck 10 tonne capacity hour 2.000 185.00 370.00 P&M-
c) Overhead charges @ 10 % on 58.20 057
(a+b)
d) Contractor's profit @ 10 % on 64.02
(a+b+c)
Cost for10 tonnes = a+b+c+d 704.22
Rate per tonnes = (a+b+c+d)/10 70.42
say 70.00
1.4 Cost of Haulage Excluding Loading and
Unloading
Haulage of materials by tipper excluding
cost of loading, unloading and stacking.
Unit = t.km
Taking output 10 tonnes load and lead
10 km = 100 t.km
(i) Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty :35 km / hour.
a) Machinery.

Page 1 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Tipper 10 tonne capacity
Time taken for onward haulage with hour 0.400 185.00 74.00 P&M-
load
Time taken for empty return trip. hour 0.290 185.00 53.65 048
P&M-
b) Overhead charges @ 10 % on (a) 12.77 048
c) Contractor's profit @ 10 % on 14.04
(a+b)
cost for 100 t km = a+b+c 154.46
Rate per t.km = (a+b+c)/100 1.54
say 1.50
1.4 (ii) Unsurfaced Graveled Road
Speed with load: 20 km / hour
Speed for empty return trip :30 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with hour 0.500 185.00 92.50 P&M-
load
Time taken for empty return trip hour 0.330 185.00 61.05 048
P&M-
b) Overhead charges @ 10 % on (a) 15.36 048
c) Contractor's profit @ 10 % on 16.89
(a+b)
Cost for 100 t .km = a+b+c 185.80
Rate per t.Km = (a+b+c)/100 1.86
say 1.90
1.4 (iii) Katcha Track and Track in River
Bed/Nallah Bed and Choe Bed.
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a) Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage hour 1.000 185.00 185.00 P&M-
Time taken for empty return trip hour 0.670 185.00 123.95 048
P&M-
b) Overhead charges @ 10 % on (a) 30.90 048
c) Contractor's profit @ 10 % on 33.98
(a+b)
Cost for 100 t .km = a+b+c 373.83
Rate per t.Km = (a+b+c)/100 3.74
say 3.70
1.5 Hand Broken Stone Aggregates 63 mm
Nominal Size
Supply of quarried stone, hand breaking
into coarse aggregate 63 mm nominal size
(passing 80 mm and retained on 50 mm
sieve) and stacking as directed
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.060 150.00 9.00 L-12
Mazdoor day 1.500 100.00 150.00 L-13
b) Material
Supply of quarried stone 150 - 200 mm cum 1.100 210.00 231.00 M-002
c) size
Overhead charges @ 10 % on 39.00
(a+b)
d) Contractor's profit @ 10 % on 42.90
(a+b+c)
Rate per cum = a+b+c+d 471.90
say 472.00
1.6 Crushing of Stone Aggregates 13.2 mm
Nominal Size.
Crushing of stone boulders of 150 mm size
in an integrated stone crushing unit of 200
tonnes per hour capacity comprising of
primary and secondary crushing units, belt
conveyor and vibrating screens to obtain
stone aggregates of 13.2 mm nominal size.
Unit = cum
Taking Output = 600 cum at crusher
location.
a) Labour

Page 2 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Mate day 0.760 150.00 114.00 L-12
Mazdoor Skilled day 2.000 120.00 240.00 L-14
Mazdoor including breaking of any day 17.000 100.00 1700.00 L-13
oversize boulder.
b) Material
Stone Boulder of size 150 mm and cum 800.000 200.00 ### M-001
c) below
Machinery
Integrated stone crusher of 200 TPH Hour 6.000 11000.00 66000.00 P&M-
including belt conveyor and vibrating 028
screens
Front end loader 1 cum bucket capacity Hour 20.000 700.00 14000.00 P&M-
Tipper 5.5 cum capacity Hour 20.000 185.00 3700.00 017
P&M-
d) Overhead charges @ 10 % on 24575.40 048
(a+b+c)
e) Contractor's profit @ 10 % on 27032.94
(a+b+c+d)
Cost for 600 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)*0.95/600 470.82
say 471.00
Note 1. 800 cum of stone boulders are needed to
get 600 cum of stone chips of size 13.2
mm.
2. 95 per cent of above cost will be
attributed to the production of 600 cum of
stone chips of 13.2 mm size and balance 5
per cent to the production of stone dust
which comes out as a by-product.
3. The integrated stone crusher includes
primary and secondary crushing units.
1.7 Crushing of Stone Aggregates 20 mm
Nominal Size
Crushing of stone boulders of 150 mm size
in an integrated stone crushing unit of 200
tonnes per hour capacity comprising of
primary and secondary crushing units, belt
conveyor and vibrating screens to obtain
stone aggregates of 20 mm nominal size.
Unit = cum
Taking Output = 670 cum at crusher
location.
a) Labour
Mate day 0.760 150.00 114.00 L-12
Mazdoor Skilled day 2.000 120.00 240.00 L-14
Mazdoor including breaking of any size day 17.000 100.00 1700.00 L-13
b) boulder.
Material
Stone Boulder of size 150 mm and cum 800.000 200.00 ### M-001
c) below
Machinery
Integrated stone crusher of 200 TPH Hour 6.000 11000.00 66000.00 P&M-
including belt conveyor and vibrating 028
screens
Front end loader 1 cum bucket capacity Hour 20.000 700.00 14000.00 P&M-
Tipper 5.5 cum capacity Hour 20.000 185.00 3700.00 017
P&M-
d) Overhead charges @ 10 % on 24575.40 048
(a+b+c)
e) Contractor's profit @ 10 % on 27032.94
(a+b+c+d)
Cost for 670 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)*0.90/670 399.44
say 399.00
Note 1. 800 cum of stone boulders are needed to
get 600 cum of stone chips of size 20 and
40 mm.
2. 90 per cent of above cost will be
attributed to the production of 670 cum of
stone aggregates of 20mm size and balance
10 per cent will be for smaller size
aggregates and stone dust which comes out
as a by-product.
3. The integrated stone crusher includes
primary and secondary crushing units.
1.8 Crushing of Stone Aggregates 40 mm
Nominal Size

Page 3 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Crushing of stone boulders of 150 mm size
in an integrated stone crushing unit of 200
tonnes per hour capacity comprising of
primary and secondary crushing units, belt
conveyor and vibrating screens to obtain
stone aggregates of 40 mm nominal size.
Unit = cum
Taking Output = 750 cum at crusher
location.
a) Labour
Mate day 0.760 150.00 114.00 L-12
Mazdoor Skilled day 2.000 120.00 240.00 L-14
Mazdoor day 17.000 100.00 1700.00 L-13
b) Material
Stone Boulder of size 150 mm and cum 800.000 200.00 ### M-001
c) below
Machinery
Integrated stone crusher of 200 TPH Hour 6.000 11000.00 66000.00 P&M-
including belt conveyor and vibrating 028
screens
Front end loader 1 cum bucket capacity Hour 20.000 700.00 14000.00 P&M-
Tipper 5.5 cum capacity Hour 20.000 185.00 3700.00 017
P&M-
d) Overhead charges @ 10 % on 24575.40 048
(a+b+c)
e) Contractor's profit @ 10 % on 27032.94
(a+b+c+d)
Cost for 750 cum = (a+b+c+d+e)x0.85 ###
Rate per cum = 337.01
(a+b+c+d+e)x0.85/750 say 337.00
Note 1. 800 cum of stone boulders are needed to
get 600 cum of stone chips of size 13.2
mm.
2. 85 per cent of above cost will be
attributed to the production of 750 cum of
stone aggregates of 40mm size and balance
15 per cent will be for smaller size
aggregates and stone dust which comes out
as a by-product.
3. The integrated stone crusher includes
primary and secondary crushing units.

Page 4 of 361
CHAPTER-2
Ref. SITE CLEARANCE
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
2.1 Spec.
201 Cutting of Trees, including cutting of
Trunks, Branches and Removal
Cutting of trees, including cutting of trunks,
branches and removal of stumps, roots,
stacking of serviceable material with all lifts
and up to a lead of 1000 metres and earth
filling in the depression/pit.
Unit = Each
(i) Girth from 300 mm to 600 mm
a) Labour
Mate day 0.020 150.00 3.00 L-12
Mazdoors for cutting trees including day 0.600 100.00 60.00 L-13
cutting, refilling, compaction of
backfilling and stacking of serviceable
materials within 1000 metres lead by
manual means.
b) Machinery
Tractor-trolley hour 0.100 150.00 15.00 P&M-
c) Overhead charges @ 10 % on 7.80 053
(a+b)
d) Contractor's profit @ 10 % on 8.58
(a+b+c)
Rate for each tree = a+b+c+d 94.38
say 94.00
2.1 (ii) Girth from 600 mm to 900 mm
a) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoors for cutting trees including day 0.900 100.00 90.00 L-13
cutting, refilling, compaction of
backfilling, and stacking of serviceable
materials within 1000 metres lead by
manual means
b) Machinery
Tractor-trolley hour 0.300 150.00 45.00 P&M-
c) Overhead charges @ 10 % on 14.10 053
(a+b) Contractor's profit @ 10 % on
d) 15.51
(a+b+c)
Rate for each tree = a+b+c+d 170.61
say 171.00
2.1 (iii) Girth from 900 mm to 1800 mm
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoors for cutting trees including day 2.000 100.00 200.00 L-13
cutting, refilling, compaction of
backfilling and stacking of serviceable
materials within 1000 metres
b) Machinery
Tractor-trolley hour 0.400 150.00 60.00 P&M-
c) Overhead charges @ 10 % on 27.20 053
(a+b)
d) Contractor's profit @ 10 % on 29.92
(a+b+c)
Rate for each tree = a+b+c+d 329.12
say 329.00
2.1 (iv) Girth above 1800 mm
a) Labour
Mate day 0.160 150.00 24.00 L-12
Mazdoors for cutting trees including day 4.000 100.00 400.00 L-13
cutting, refilling, compaction of
backfilling and stacking of serviceable
materials within 1000 metres
b) Machinery
Tractor-trolley hour 0.600 150.00 90.00 P&M-
c) Overhead charges @ 10 % on 51.40 053
(a+b)
d) Contractor's profit @ 10 % on 56.54
(a+b+c)
Rate for each tree = a+b+c+d 621.94
say 622.00
2.2 201 Clearing Grass and Removal of Rubbish

Page 1 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Clearing grass and removal of rubbish up to
a distance of 50 metres outside the
periphery
By Manual of Means
the area .
Unit = Hectare
Taking output = 1 Hectare
a) Labour
Mate day 2.000 150.00 300.00 L-12
Mazdoor day 50.000 100.00 5000.00 L-13
b) Overhead charges @ 10 % on (a) 530.00
c) Contractor's profit @ 10 % on 583.00
(a+b)per Hectare = a+b+c
Rate 6413.00
say 6413.00
2.3 201 Clearing and Grubbing Road Land .
Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes,
shrubs, saplings and trees girth up to 300
mm, removal of stumps of trees cut earlier
and disposal of unserviceable materials and
stacking of serviceable material to be used
or auctioned, up to a lead of 1000 metres
including removal and disposal of top
organic soil not exceeding 150 mm in
thickness.
Unit = Hectare
Taking output = 1 Hectare
(i) By Manual Means:-
A In area of light jungle
a) Labour
Mate day 6.000 150.00 900.00 L-12
Mazdoor day 150.000 100.00 15000.00 L-13
b) Machinery
Tractor-trolley hour 1.000 150.00 150.00 P&M-
c) Overhead charges @ 10 % on 1605.00 053
(a+b)
d) Contractor's profit @ 10 % on 1765.50
(a+b+c)
Rate per Hectare = a+b+c+d 19420.50
say 19421.00
2.3 B In area of thorny jungle
(i) a) Labour
Mate day 8.000 150.00 1200.00 L-12
Mazdoor day 200.000 100.00 20000.00 L-13
b) Machinery
Tractor-trolley hour 2.000 150.00 300.00 P&M-
c) Overhead charges @ 10 % on 2150.00 053
(a+b)
d) Contractor's profit @ 10 % on 2365.00
(a+b+c)
Rate per Hectare = a+b+c+d 26015.00
say 26015.00
2.3 (ii) By Mechanical Means
A In area of light jungle
a) Labour
Mate day 0.160 150.00 24.00 L-12
Mazdoor day 4.000 100.00 400.00 L-13
b) Machinery
Dozer 80 HP with attachment for hour 10.000 2000.00 20000.00 P&M-
removal of trees & stumps 014
Tractor-trolley hour 1.000 150.00 150.00 P&M-
c) Overhead charges @ 10 % on 2057.40 053
(a+b)
d) Contractor's profit @ 10 % on 2263.14
(a+b+c)
Rate per Hectare = a+b+c+d 24894.54
say 24895.00
2.3 B In area of thorny jungle
(ii) a) Labour
Mate day 0.240 150.00 36.00 L-12

Page 2 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Mazdoor day 6.000 100.00 600.00 L-13
b) Machinery
Dozer 80 HP with attachment for hour 12.000 2000.00 24000.00 P&M-
removal of trees & stumps 014
Tractor-trolley hour 1.500 150.00 225.00 P&M-
c) Overhead charges @ 10 % on 2486.10 053
(a+b) Contractor's profit @ 10 % on
d) 2734.71
(a+b+c)
Rate per Hectare = a+b+c+d 30081.81
say 30082.00
2.4 202 Dismantling of Structures
Dismantling of existing structures like
culverts, bridges, retaining walls and other
structure comprising of masonry, cement
concrete, wood work, steel work, including
T&P and scaffolding wherever necessary,
sorting the dismantled material, disposal of
unserviceable material and stacking the
serviceable material with all lifts and lead of
1000 =
Unit metres
cum
Taking output = 1.25 cum
(i) Lime /Cement Concrete
I By Manual Means
A Lime Concrete, cement concrete grade
M-10 and below
a) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoor for dismantling and loading day 1.000 100.00 100.00 L-13
b) Machinery
Tractor-trolley hour 0.270 150.00 40.50 P&M-
c) Overhead charges @ 10 % on 14.65 053
(a+b)
d) Contractor's profit @ 10 % on 16.12
(a+b+c)
Cost for 1.25 cum = a+b+c+d 177.27
Rate per cum = (a+b+c+d)/ 1.25 141.81
say 142.00
2.4 B Cement Concrete Grade M-15 & M-20
(i) a) Labour
Mate day 0.050 150.00 7.50 L-12
Mazdoor for dismantling and loading day 1.250 100.00 125.00 L-13
b) Machinery
Tractor-trolley hour 0.270 150.00 40.50 P&M-
c) Overhead charges @ 10 % on 17.30 053
(a+b)
d) Contractor's profit @ 10 % on 19.03
(a+b+c)
Cost for 1.25 cum = a+b+c+d 209.33
Rate per cum = (a+b+c+d)/ 1.25 167.46
say 167.00
2.4 C Prestressed / Reinforced cement
(i) concrete grade M-20 & above
a) Labour
Mate day 0.150 150.00 22.50 L-12
Blacksmith day 0.250 150.00 37.50 L-02
Mazdoor for dismantling, loading and day 3.500 100.00 350.00 L-13
b) unloading
Machinery
Tractor-trolley hour 0.270 150.00 40.50 P&M-
c) Overhead charges @ 10 % on 45.05 053
(a+b)
d) Contractor's profit @ 10 % on 49.56
(a+b+c)
Cost for 1.25 cum = a+b+c+d 545.11
Rate per cum = (a+b+c+d)/ 1.25 436.08
say 436.00
2.4 II By Mechanical Means for items No.
202( b)& ( c)

Page 3 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec.
A Cement Concrete Grade M-15 & M-20
a) Labour
Mate day 0.020 150.00 3.00 L-12
Mazdoor for loading and unloading day 0.250 100.00 25.00 L-13
Mazdoor with Pneumatic breaker day 0.250 120.00 30.00 L-14
b) Machinery
Air Compressor 250 cfm with 2 leads of hour 0.670 150.00 100.50 P&M-
pneumatic breaker @ 1.5 cum per hour 001
Tractor-trolley hour 0.270 150.00 40.50 P&M-
c) Overhead charges @ 10 % on 19.90 053
(a+b) Contractor's profit @ 10 % on
d) 21.89
(a+b+c)
Cost for 1.25 cum = a+b+c+d 240.79
Rate per cum = (a+b+c+d)/ 1.25 192.63
say 193.00
2.4 II B Prestressed / reinforced cement
concrete grade M-20 & above
a) Labour
Mate day 0.050 150.00 7.50 L-12
Mazdoor with Pneumatic breaker day 0.660 120.00 79.20 L-14
Blacksmith day 0.250 150.00 37.50 L-02
Mazdoor for loading and unloading day 0.250 100.00 25.00 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of hour 1.000 150.00 150.00 P&M-
pneumatic breaker @ 1.00 cum per 001
hour
Tractor-trolley hour 0.270 150.00 40.50 P&M-
c) Overhead charges @ 10 % on 33.97 053
(a+b)
d) Contractor's profit @ 10 % on 37.37
(a+b+c)
Cost for 1.25 cum = a+b+c+d 411.04
Rate per cum = (a+b+c+d)/ 1.25 328.83
say 329.00
2.4 (ii) Dismantling Brick / Tile work
A In lime mortar
a) Labour
Mate day 0.020 150.00 3.00 L-12
Mazdoor for dismantling, loading and day 0.500 100.00 50.00 L-13
b) unloading
Machinery
Tractor-trolley hour 0.270 150.00 40.50 P&M-
c) Overhead charges @ 10 % on 9.35 053
(a+b)
d) Contractor's profit @ 10 % on 10.29
(a+b+c)
Cost for 1.25 cum = a+b+c+d 113.14
Rate per cum = (a+b+c+d)/ 1.25 90.51
say 91.00
2.4 B In cement mortar
(ii) a) Labour
Mate day 0.030 150.00 4.50 L-12
Mazdoor for dismantling, loading and day 0.750 100.00 75.00 L-13
b) unloading
Machinery
Tractor-trolley hour 0.270 150.00 40.50 P&M-
c) Overhead charges @ 10 % on 12.00 053
(a+b)
d) Contractor's profit @ 10 % on 13.20
(a+b+c)
Cost for 1.25 cum = a+b+c+d 145.20
Rate per cum = (a+b+c+d)/ 1.25 116.16
say 116.00
2.4 C In mud mortar
(ii) a) Labour
Mate day 0.016 150.00 2.40 L-12
Mazdoor for dismantling and loading day 0.400 100.00 40.00 L-13

Page 4 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. b) Machinery
Tractor-trolley hour 0.270 150.00 40.50 P&M-
c) Overhead charges @ 10 % on 8.29 053
(a+b)
d) Contractor's profit @ 10 % on 9.12
(a+b+c)
Cost for 1.25 cum = a+b+c+d 100.31
Rate per cum = (a+b+c+d)/ 1.25 80.25
say 80.00
2.4 D Dry brick pitching or brick soling
(ii) a) Labour
Mate day 0.014 150.00 2.10 L-12
Mazdoor for Dismantling, loading and day 0.350 100.00 35.00 L-13
b) unloading
Machinery
Tractor-trolley hour 0.270 150.00 40.50 P&M-
c) Overhead charges @ 10 % on 7.76 053
(a+b)
d) Contractor's profit @ 10 % on 8.54
(a+b+c)
Cost for 1.25 cum = a+b+c+d 93.90
Rate per cum = (a+b+c+d)/ 1.25 75.12
say 75.00
2.4 (iii) Dismantling Stone Masonry
A Rubble stone masonry in lime mortar
a) Labour
Mate day 0.024 150.00 3.60 L-12
Mazdoor for dismantling, loading and day 0.600 100.00 60.00 L-13
b) unloading.
Machinery
Tractor-trolley hour 0.270 150.00 40.50 P&M-
c) Overhead charges @ 10 % on 10.41 053
(a+b)
d) Contractor's profit @ 10 % on 11.45
(a+b+c)
Cost for 1.25 cum = a+b+c+d 125.96
Rate per cum = (a+b+c+d)/ 1.25 100.77
say 101.00
2.4 B Rubble stone masonry in cement
(iii) mortar.
a) Labour
Mate day 0.030 150.00 4.50 L-12
Mazdoor for dismantling, loading and day 0.750 100.00 75.00 L-13
b) unloading.
Machinery
Tractor-trolley hour 0.270 150.00 40.50 P&M-
c) Overhead charges @ 10 % on 12.00 053
(a+b)
d) Contractor's profit @ 10 % on 13.20
(a+b+c)
Cost for 1.25 cum = a+b+c+d 145.20
Rate per cum = (a+b+c+d)/ 1.25 116.16
say 116.00
2.4 C Rubble Stone Masonry in mud mortar.
(iii) a) Labour
Mate day 0.020 150.00 3.00 L-12
Mazdoor for dismantling, loading and day 0.500 100.00 50.00 L-13
b) unloading.
Machinery
Tractor-trolley hour 0.270 150.00 40.50 P&M-
c) Overhead charges @ 10 % on 9.35 053
(a+b)
d) Contractor's profit @ 10 % on 10.29
(a+b+c)
Cost for 1.25 cum = a+b+c+d 113.14
Rate per cum = (a+b+c+d)/ 1.25 90.51
say 91.00
2.4 D Dry rubble masonry
(iii) a) Labour
Mate day 0.018 150.00 2.70 L-12
Mazdoor for dismantling, loading and day 0.450 100.00 45.00 L-13
b) unloading.
Machinery

Page 5 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Tractor-trolley hour 0.270 150.00 40.50 P&M-
c) Overhead charges @ 10 % on 8.82 053
(a+b)
d) Contractor's profit @ 10 % on 9.70
(a+b+c)
Cost for 1.25 cum = a+b+c+d 106.72
Rate per cum = (a+b+c+d)/ 1.25 85.38
say 85.00
2.4 E Dismantling stone pitching/ dry stone
(iii) spalls.
a) Labour
Mate day 0.016 150.00 2.40 L-12
Mazdoor for dismantling, loading and day 0.400 100.00 40.00 L-13
b) unloading.
Machinery
Tractor-trolley hour 0.270 150.00 40.50 P&M-
c) Overhead charges @ 10 % on 8.29 053
(a+b)
d) Contractor's profit @ 10 % on 9.12
(a+b+c)
Cost for 1.25 cum = a+b+c+d 100.31
Rate per cum = (a+b+c+d)/ 1.25 80.25
say 80.00
2.4 F Dismantling boulders laid in wire
(iii) crates including opening of crates and
stacking dismantled materials.
a) Labour
Mate day 0.020 150.00 3.00 L-12
Mazdoor for dismantling, loading and day 0.500 100.00 50.00 L-13
b) unloading
Machinery
Tractor-trolley hour 0.270 150.00 40.50 P&M-
c) Overhead charges @ 10 % on 9.35 053
(a+b)
d) Contractor's profit @ 10 % on 10.29
(a+b+c)
Cost for 1.25 cum = a+b+c+d 113.14
Rate per cum = (a+b+c+d)/ 1.25 90.51
say 91.00
2.4 (iv) Wood Work wrought framed and fixed
in frames of trusses upto a height of 5
m above
a) plinth level
Labour
Mate day 0.060 150.00 9.00 L-12
Carpenter day 0.500 150.00 75.00 L-04
Mazdoor for dismantling, loading and day 1.000 100.00 100.00 L-13
b) unloading.
Machinery
Tractor-trolley hour 0.270 150.00 40.50 P&M-
c) Overhead charges @ 10 % on 22.45 053
(a+b)
d) Contractor's profit @ 10 % on 24.70
(a+b+c)
Cost for 1.25 cum = a+b+c+d 271.65
Rate per cum = (a+b+c+d)/ 1.25 217.32
say 217.00
2.4 (v) Steel Work in all types of sections upto
a height of 5 m above plinth level
excluding
Unit cutting of rivet.
= tonne
Taking output = 1 tonne
A Including dismembering
a) Labour
Mate day 0.140 150.00 21.00 L-12
Blacksmith day 1.000 150.00 150.00 L-02
Mazdoor for dismantling, loading and day 2.500 100.00 250.00 L-13
Add unloading
2.5 per cent of cost of labour for gas 10.53
cutting, ropes, pulleys etc.
b) Machinery
Tractor-trolley hour 0.170 150.00 25.50 P&M-
c) Overhead charges @ 10 % on 45.70 053
(a+b) Contractor's profit @ 10 % on
d) 50.27
(a+b+c)
Page 6 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Rate per tonne = a+b+c+d 553.00
say 553.00
2.4 B Excluding dismembering.
(v) a) Labour
Mate day 0.220 150.00 33.00 L-12
Mazdoor for dismantling, loading and day 2.000 100.00 200.00 L-13
unloading
Blacksmith day 0.500 150.00 75.00 L-02
Add 2.5 per cent of cost of labour for gas 7.70
cutting, ropes, pulleys etc.
b) Machinery
Tractor-trolley hour 0.170 150.00 25.50 P&M-
c) Overhead charges @ 10 % on 34.12 053
(a+b) Contractor's profit @ 10 % on
d) 37.53
(a+b+c)
Rate per tonne = a+b+c+d 412.85
say 413.00
2.4 C Extra over item No( v ) A and( v ) B for
(v) cutting rivets.
Unit = each
Taking output = 10 rivets
a) Labour
Mate day 0.010 150.00 1.50 L-12
Blacksmith day 0.130 150.00 19.50 L-02
Mazdoor day 0.130 100.00 13.00 L-13
b) Overhead charges @ 10 % on (a) 3.40
c) Contractor's profit @ 10 % on 3.74
(a+b)
Cost for 10 rivets = a+b+c 41.14
Rate for each rivet = ( a+b+c)/10 4.11
say 4.00
2.4 (vi) Scraping of Bricks Dismantled from
Brick Work including Stacking.
Unit = numbers
Taking output = 1000 numbers
A In lime/Cement mortar
a) Labour
Mate day 0.140 150.00 21.00 L-12
Mazdoor day 3.500 100.00 350.00 L-13
b) Overhead charges @ 10 % on (a) 37.10
c) Contractor's profit @ 10 % on 40.81
(a+b)per1000 Nos = a+b+c
Rate 448.91
say 449.00
2.4 B In mud mortar
(iv) a) Labour
Mate day 0.050 150.00 7.50 L-12
Mazdoor day 1.250 100.00 125.00 L-13
b) Overhead charges @ 10 % on (a) 13.25
c) Contractor's profit @ 10 % on 14.58
(a+b)per1000 Nos = a+b+c
Rate 160.33
say 160.00
2.4 (vii) Scraping of Stone from Dismantled
Stone
Unit = Masonry
cum
Taking output = 1 cum
A In cement and lime mortar
a) Labour
Mate day 0.060 150.00 9.00 L-12
Mazdoor day 1.400 100.00 140.00 L-13
b) Overhead charges @ 10 % on (a) 14.90
c) Contractor's profit @ 10 % on 16.39
(a+b)

Page 7 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Rate per cum = a+b+c 180.29
say 180.00
2.4 B In Mud mortar
(vii)
a) Labour
Mate day 0.010 150.00 1.50 L-12
Mazdoor day 0.300 100.00 30.00 L-13
b) Overhead charges @ 10 % on (a) 3.15
c) Contractor's profit @ 10 % on 3.47
(a+b)per cum = a+b+c
Rate 38.12
say 38.00
2.4 (viii) Scarping Plaster in Lime or Cement
Mortar from Brick/ Stone Masonry
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.160 150.00 24.00 L-12
Mazdoor for scarping and loading day 4.000 100.00 400.00 L-13
b) Machinery
Tractor-trolley hour 0.320 150.00 48.00 P&M-
c) Overhead charges @ 10 % on 47.20 053
(a+b)
d) Contractor's profit @ 10 % on 51.92
(a+b+c)
Cost for 100 sqm = a+b+c+d 571.12
Rate per sqm = (a+b+c+d)/100 5.71
say 6.00
2.4 (ix) Removing all type of Hume Pipes and
Stacking within a lead of 1000 metres
including Earthwork and Dismantling
of Masonry Works.
Unit = metre
Taking output = 1 metre
A Up to 600 mm dia
a) Labour
Mate day 0.020 150.00 3.00 L-12
Mazdoor day 0.520 100.00 52.00 L-13
b) Overhead charges @ 10 % on (a) 5.50
c) Contractor's profit @ 10 % on 6.05
(a+b)per metre = a+b+c
Rate 66.55
say 67.00
2.4 B Above 600 mm to 900 mm dia
(ix) a) Labour
Mate day 0.030 150.00 4.50 L-12
Mazdoor day 0.700 100.00 70.00 L-13
b) Overhead charges @ 10 % on (a) 7.45
c) Contractor's profit @ 10 % on 8.20
(a+b)per metre = a+b+c
Rate 90.15
say 90.00
2.4 C Above 900 mm
(ix) a) Labour
Mate day 0.050 150.00 7.50 L-12
Mazdoor day 1.200 100.00 120.00 L-13
b) Overhead charges @ 10 % on (a) 12.75
c) Contractor's profit @ 10 % on 14.03
(a+b)per metre = a+b+c
Rate 154.28
say 154.00
Note 1. The excavation of earth, dismantling of
stone masonry work in head walls and
protection works is not included which is to
be measured and paid separately.

Page 8 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 2. Credit for retrieved stone from masonry
work may be taken as per actual
2.5 202 availability. of Flexible Pavements
Dismantling
Dismantling of flexible pavements and
disposal of dismantled materials up to a
lead of 1000 metres, stacking serviceable
and unserviceable materials separately
Unit = cum
Taking output = 1 cum
I By Manual Means
A Bituminous courses
a) Labour
Mate day 0.060 150.00 9.00 L-12
Mazdoor for dismantling, loading and day 1.500 100.00 150.00 L-13
b) unloading
Machinery
Tractor-trolley hour 0.380 150.00 57.00 P&M-
c) Overhead charges @ 10 % on 21.60 053
(a+b)
d) Contractor's profit @ 10 % on 23.76
(a+b+c)
Rate per cum = a+b+c+d 261.36
say 261.00
2.5 I B Granular courses
a) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoor for dismantling, loading and day 1.000 100.00 100.00 L-13
b) unloading.
Machinery
Tractor-trolley hour 0.330 150.00 49.50 P&M-
c) Overhead charges @ 10 % on 15.55 053
(a+b)
d) Contractor's profit @ 10 % on 17.11
(a+b+c)
Rate per cum = a+b+c+d 188.16
say 188.00
2.5 II By Mechanical Means
A Bituminous course
a) Labour
Mate day 0.010 150.00 1.50 L-12
Mazdoor day 0.300 100.00 30.00 L-13
b) Machinery
Tractor-trolley hour 0.380 150.00 57.00 P&M-
Farm tractor with ripper @ 60 cum per hour 0.017 175.00 2.98 053
P&M-
c) hour
Overhead charges @ 10 % on 9.15 055
(a+b)
d) Contractor's profit @ 10 % on 10.06
(a+b+c)
Rate per cum = a+b+c+d 110.68
say 111.00
2.6 202 Dismantling of Cement Concrete
Pavement
Dismantling of cement concrete pavement
by mechanical means using pneumatic
tools, breaking to pieces not exceeding
0.02 cum in volume and stock piling at
designated locations and disposal of
dismantled materials up to a lead of 1000
metres, stacking serviceable and
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.030 150.00 4.50 L-12
Semi skilled mazdoor for operating day 0.500 120.00 60.00 L-14
pneumaticas
Mazdoors tools
helpers including loading day 0.500 100.00 50.00 L-13
and unloading
b) Machinery
Air compressor 250 cfm with two leads hour 1.000 150.00 150.00 P&M-
for pneumatic cutters/ hammers @ 1 001
cum per hour
Page 9 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Tractor-trolley hour 0.400 150.00 60.00 P&M-
Joint Cutting Machine with 2-3 blades hour 1.000 150.00 150.00 053
P&M-
c) Overhead charges @ 10 % on 47.45 083
(a+b)
d) Contractor's profit @ 10 % on 52.20
(a+b+c)
Rate per cum = a+b+c+d 574.15
say 574.00
Note The above analysis is for removal of
complete pavement. In case full depth
repair work is required to be done after
dismantling, provision of a concrete cutting
and sawing machine may be added for 0.25
hours.
2.7 202 Dismantling of Guard Rails
Dismantling guard rails by manual means
and disposal of dismantled material with all
lifts and up to a lead of 1000 metres,
stacking serviceable materials and
unserviceable materials separately.
Unit = running metre
Taking output = 1 metre
a) Labour
Mate day 0.006 150.00 0.90 L-12
Mazdoor including loading and day 0.150 100.00 15.00 L-13
b) unloading
Machinery
Tractor-trolley hour 0.050 150.00 7.50 P&M-
c) Overhead charges @ 10 % on 2.34 053
(a+b)
d) Contractor's profit @ 10 % on 2.57
(a+b+c)
Rate per metre = a+b+c+d 28.31
say 28.00
2.8 202 Dismantling of Kerb Stone
Dismantling kerb stone by manual means
and disposal of dismantled material with all
lifts and up to a lead of 1000 metre
Unit = running metre
Taking output = 10 metre
a) Labour
Mate day 0.010 150.00 1.50 L-12
Mazdoor including loading and day 0.150 100.00 15.00 L-13
b) unloading
Machinery
Tractor-trolley hour 0.200 150.00 30.00 P&M-
c) Overhead charges @ 10 % on 4.65 053
(a+b)
d) Contractor's profit @ 10 % on 5.12
(a+b+c)
Cost for 10 m = a+b+c+d 56.27
Rate per metre = (a+b+c+d)/10 5.63
say 6.00
2.9 202 Dismantling of Kerb Stone Channel
Dismantling kerb stone channel by manual
means and disposal of dismantled material
with all lifts and up to a lead of 1000 metre
Unit = running metre
Taking output = 10 metre
a) Labour
Mate day 0.015 150.00 2.25 L-12
Mazdoor including loading and day 0.225 100.00 22.50 L-13
b) unloading
Machinery
Tractor-trolley hour 0.300 150.00 45.00 P&M-
c) Overhead charges @ 10 % on 6.98 053
(a+b) Contractor's profit @ 10 % on
d) 7.67
(a+b+c)
Cost for 10 m = a+b+c+d 84.40
Rate per metre = (a+b+c+d)/10 8.44

Page 10 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. say 8.00
2.10 202 Dismantling of Kilometre Stone
Dismantling of kilometre stone including
cutting of earth, foundation and disposal of
dismantled material with all lifts and lead
upto 1000 m and back filling of pit.
Unit = Each
Taking output = one KM stone
A 5th KM stone
Quantity of cement concrete = 0.392 cum
a) Labour
Mate day 0.130 150.00 19.50 L-12
Mazdoor day 0.750 100.00 75.00 L-13
b) Machinery
Tractor-trolley hour 0.150 150.00 22.50 P&M-
c) Overhead charges @ 10 % on 11.70 053
(a+b)
d) Contractor's profit @ 10 % on 12.87
(a+b+c)
Rate for one 5th KM stone = a+b+c+d 141.57
say 142.00
B Ordinary KM Stone
Quantity of cement concrete = 0.269 cum
a) Labour
Mate day 0.020 150.00 3.00 L-12
Mazdoor day 0.500 100.00 50.00 L-13
b) Machinery
Tractor-trolley hour 0.100 150.00 15.00 P&M-
c) Overhead charges @ 10 % on 6.80 053
(a+b)
d) Contractor's profit @ 10 % on 7.48
(a+b+c)
Rate for one ordinary KM stone = 82.28
a+b+c+d say 82.00
C Hectometre Stone
Quantity of cement concrete = 0.048 cum
a) Labour
Mate day 0.004 150.00 0.60 L-12
Mazdoor day 0.100 100.00 10.00 L-13
b) Machinery
Tractor-trolley hour 0.020 150.00 3.00 P&M-
c) Overhead charges @ 10 % on 1.36 053
(a+b)
d) Contractor's profit @ 10 % on 1.50
(a+b+c)
Rate for one Hectometre stone = 16.46
a+b+c+d say 16.00
2.11 202 Dismantling of Fencing
Dismantling of barbed wire fencing/ wire
mesh fencing including posts, foundation
concrete, back filling of pit by manual
means including disposal of dismantled
material with all lifts and up to a lead of
1000 metres, stacking serviceable material
and unserviceable material separately.
Unit = running metre
Taking output = 30 metres
a) Labour
Mate day 0.150 150.00 22.50 L-12
Mazdoor including loading and day 3.000 100.00 300.00 L-13
unloading
Blacksmith day 0.750 150.00 112.50 L-02
b) Machinery
Tractor-trolley hour 0.150 150.00 22.50 P&M-
c) Overhead charges @ 10 % on 45.75 053
(a+b)
d) Contractor's profit @ 10 % on 50.33
(a+b+c)
Cost for 30 metres = a+b+c+d 553.58

Page 11 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Rate per metre = (a+b+c+d)/30 18.45
say 18.00
2.12 202 Dismantling of CI Water Pipe Line
Dismantling of CI water pipe line 600 mm
dia including disposal with all lifts and lead
upto 1000 metres and stacking of
serviceable material and unserviceable
material separately under supervision of
concerned department
Unit = running metre
Taking output = 10 metres
a) Labour
Mate day 0.090 150.00 13.50 L-12
Mazdoor day 2.000 100.00 200.00 L-13
Plumber day 0.250 150.00 37.50 L-02
b) Machinery
Truck 10 tonne capacity hour 0.250 185.00 46.25 P&M-
Light Crane 3 tonne capacity hour 0.500 225.00 112.50 057
P&M-
c) Overhead charges @ 10 % on 40.98 013
(a+b) Contractor's profit @ 10 % on
d) 45.07
(a+b+c)
Cost for 10 metres = a+b+c+d 495.80
Rate per metre = (a+b+c+d)/10 49.58
say 50.00
Note The rate analysis does not include any
excavation in earth or dismantling of
masonry works which are to be measured
and paid separately.
2.13 202 Removal of Cement Concrete Pipe of
Sewer
RemovalGutter
of cement concrete pipe of sewer
gutter 1500 mm dia under the supervision
of concerned department including disposal
with all lifts and up to a lead of 1000 metres
and stacking of serviceable and
unserviceable material separately but
excluding earth excavation and dismantling
Unit = running metre
Taking output = 10 metres
a) Labour
Mate day 0.100 150.00 15.00 L-12
Mazdoor day 2.500 100.00 250.00 L-13
b) Machinery
Crane 5 tonne capacity hour 0.300 250.00 75.00 P&M-
Truck flat body 10 tonne hour 1.000 185.00 185.00 070
P&M-
c) Overhead charges @ 10 % on 52.50 057
(a+b)
d) Contractor's profit @ 10 % on 57.75
(a+b+c)
Cost for 10 metres = a+b+c+d 635.25
Rate per metre = (a+b+c+d)/10 63.53
say 64.00
Note The rate analysis does not include any
excavation in earth or dismantling of
masonry works which are to be measured
and paid separately.
2.14 202 Removal of Telephone / Electric Poles
and Linesof telephone / Electric poles
Removal
including excavation and dismantling of
foundation concrete and lines under the
supervision of concerned department,
disposal with all lifts and up to a lead of
1000 metres and stacking the serviceable
and unserviceable material separately
Unit = each
Taking output = 30 Nos
a) Labour
Mate day 0.480 150.00 72.00 L-12

Page 12 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Mazdoor day 10.000 100.00 1000.00 L-13
Electrician/Lineman day 2.000 150.00 300.00 L-02
b) Machinery
Tractor-trolley hour 1.500 150.00 225.00 P&M-
c) Overhead charges @ 10 % on 159.70 053
(a+b)
d) Contractor's profit @ 10 % on 175.67
(a+b+c)
Cost for 30 poles = a+b+c+d 1932.37
Rate per pole = (a+b+c+d)/30 64.41
say 64.00

Page 13 of 361
CHAPTER - 3
Ref. EARTH WORK, EROSION CONTROL AND DRAINAGE
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
3.1 Spec.
301 Excavation in Soil by Manual Means .
Excavation for roadway in soil using manual
means including loading in truck for
carrying of cut earth to embankment site
with all lifts and lead upto1000 metres.
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 1.800 150.00 270.00 L-12
Mazdoor day 45.000 100.00 4500.00 L-13
b) Machinery
Truck 5.5 cum capacity hour 10.000 185.00 1850.00 P&M-
c) Overhead charges @ 10 % on 662.00 057
(a+b)
d) Contractor's profit @ 10 % on 728.20
(a+b+c)
Cost of 120 cum = a+b+c+d 8010.20
Rate per cum = (a+b+c+d)/120 66.75
say 67.00
Note In case there is a situation where the cross-
section is of cut and fill and cut earth is
required to be used in embankment in the
immediate vicinity, the item of carriage in
the truck shall be omitted.
3.2 301 Excavation in Ordinary Rock by Manual
Means
Excavation in ordinary rock using manual
means including loading in a truck and
carrying of excavated material to
embankment site with in all lifts and leads
upto 1000 metres
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 2.800 150.00 420.00 L-12
Mazdoor day 70.000 100.00 7000.00 L-13
b) Machinery
Truck 5.5 cum capacity hour 10.000 185.00 1850.00 P&M-
c) Overhead charges @ 10 % on 927.00 057
(a+b)
d) Contractor's profit @ 10 % on 1019.70
(a+b+c)
Cost for 120 cum = a+b+c+d 11216.70
Rate per cum = (a+b+c+d)/120 93.47
say 93.00
Note In case there is a situation where the cross-
section is of cut and fill and cut earth is
required to be used in embankment in the
immediate vicinity, the item of carriage in
the truck shall be omitted.
3.3 301 Excavation in Soil with Dozer with lead
upto 100 metres
Excavation for road way in soil by
mechanical means including cutting and
pushing the earth to site of embankment
upto a distance of 100 metres (average
lead50 metres), including trimming bottom
and side slopes in accordance with
requirements of lines, grades and cross
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor day 2.000 100.00 200.00 L-13
b) Machinery
Dozer, 80 HP @ 30 cum per hour hour 6.000 2000.00 12000.00 P&M-
c) Overhead charges @ 10 % on 1221.20 014
(a+b)
d) Contractor's profit @ 10 % on 1343.32
(a+b+c)
Cost for 180 cum = a+b+c+d 14776.52
Rate per cum = (a+b+c+d)/180 82.09
say 82.00

Page 1 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
3.4 Spec.
301 Excavation in Ordinary Rock with
Dozer with lead upto 100 metres
Excavation for roadway in ordinary rock by
deploying a dozer, 80 HP including cutting
and pushing the cut earth to site of
embankment upto a distance of 100 metres
( average lead 50 metres ), trimming
bottom and side slopes in accordance with
the requirements of lines, grades and cross
Unit = cum
Taking output = 108 cum
a) Labour
Mate day 0.120 150.00 18.00 L-12
Mazdoor day 3.000 100.00 300.00 L-13
b) Machinery
Dozer, 80 HP @ 20 cum per hour hour 6.000 2000.00 12000.00 P&M-
c) Overhead charges @ 10 % on 1231.80 014
(a+b)
d) Contractor's profit @ 10 % on 1354.98
(a+b+c)
Cost for 108 cum = a+b+c+d 14904.78
Rate per cum = (a+b+c+d)/108 138.01
say 138.00
3.5 301 Excavation in Hard Rock (requiring
blasting) with disposal upto 1000
metres
Excavation for roadway in hard rock
(requiring blasting) by drilling, blasting
and breaking, trimming of bottom and side
slopes in accordance with requirements of
lines, grades and cross sections, loading
and disposal of cut road with in all lifts and
Unit = cum
Taking 0utput = 180 cum
a) Labour
Mate day 0.220 150.00 33.00 L-12
Mazdoor day 3.000 100.00 300.00 L-13
Driller day 2.000 150.00 300.00 L-06
Blaster day 0.250 150.00 37.50 L-03
b) Machinery
Dozer, 80 HP @ 30 cum per hour hour 6.000 2000.00 12000.00 P&M-
Air compressor, 250 cfm with 2 jack hour 6.000 150.00 900.00 014
P&M-
hammer
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 001
P&M-
Tipper10 tonne capacity hour 11.250 185.00 2081.25 017
P&M-
c) Materials 048
Gelatin 80 per cent kg 63.000 100.00 6300.00 M-104
Electric Detonators @ 1 detonator for 2 each 252.000 5.00 1260.00 M-094 /
gelatin sticks of 125 gms each 100
Credit for excavated rock found suitable cum 90.000 (150.00) ### M-089
for use @ 50 per cent quantity blasted
d) Overhead charges @ 10 % on 1391.18
(a+b+c)
e) Contractor's profit @ 10 % on 1530.29
(a+b+c+d)
Cost for 180 cum = a+b+c+d+e 16833.22
Rate per cum = (a+b+c+d+e)/180 93.52
say 94.00
Note 1. The quality and availability of rock shall
be checked before affording credit.
2. In case some rock is issued to the
contractor at site, the item of carriage shall
be reduced/restricted to that extent.
3.6 301 Excavation in Soil using Hydraulic
Excavator CK 90 and Tippers with
Disposal upto 1000 metres.

Page 2 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Excavation for roadwork in soil with
hydraulic excavator of 0.9 cum bucket
capacity including cutting and loading in
tippers, trimming bottom and side slopes, in
accordance with requirements of lines,
grades and cross sections, and transporting
to the embankment location within all lifts
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor day 2.000 100.00 200.00 L-13
b) Machinery
Hydraulic excavator 0.9 cum bucket hour 6.000 700.00 4200.00 P&M-
capacity @ 60 cum per hour 026
Tipper 5.5 cum capacity, 4 trips per hour 16.000 185.00 2960.00 P&M-
c) hour.
Overhead charges @ 10 % on 737.20 048
(a+b)
d) Contractor's profit @ 10 % on 810.92
(a+b+c)
Cost for 360 cum = a+b+c+d 8920.12
Rate per cum = (a+b+c+d)/360 24.78
say 25.00
3.7 301 Excavation in Ordinary Rock using
Hydraulic Excavator CK-90 and Tippers
with Disposal upto 1000 metres.
Excavation for roadway in ordinary rock
with hydraulic excavator of 0.9 cum bucket
capacity including cutting and loading in
tippers, transporting to embankment site
within all lifts and lead upto 1000 m,
trimming bottom and side slopes in
accordance with requirements of lines,
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor day 2.000 100.00 200.00 L-13
b) Machinery
Hydraulic Excavator 0.90 cum bucket hour 6.000 700.00 4200.00 P&M-
capacity @ 36 cum per hour 026
Tipper 5.5 cum capacity, 4 trips per hour 11.000 185.00 2035.00 P&M-
c) hour.
Overhead charges @ 10 % on 644.70 048
(a+b)
d) Contractor's profit @ 10 % on 709.17
(a+b+c)
Cost for 240 cum = a+b+c+d 7800.87
Rate per cum = (a+b+c+d)/240 32.50
say 33.00
3.8 301 Excavation in Hard Rock (blasting
prohibited)
Excavation for roadway in hard rock
(blasting prohibited) with rock breakers
including breaking rock, loading in tippers
and disposal within all lifts and lead upto
1000 metres, trimming bottom and side
slopes in accordance with requirements of
A Mechanised
Unit = cum
Taking output = 36 cum
a) Labour
Mate day 0.400 150.00 60.00 L-12
Mazdoor for trimming slopes including day 10.000 100.00 1000.00 L-13
mannul loading in truck
b) Machinery
Hydraulic excavator with rock breaker hour 6.000 700.00 4200.00 P&M-
attachment @ 6 cum per hour 026
Tipper 5.5 cum capacity, 1 trip per hour. hour 6.500 185.00 1202.50 P&M-
048

Page 3 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Credit for excavated rock found suitable cum 18.000 (150.00) (2700.00) M-089
for use @ 50 per cent of excavated
c) quantity
Overhead charges @ 10 % on 376.25
(a+b)
d) Contractor's profit @ 10 % on 413.88
(a+b+c)
Cost for 36 cum = a+b+c+d 4552.63
Rate per cum = (a+b+c+d)/36 126.46
say 126.00
Note 1. The quality and availability of rock shall
be checked before affording credit.
2. In case some rock is issued to the
contractor at site, the item of carriage shall
be restricted/reduced to that extent.
3.Being small quantity, manual loading will
be economical in this case and has been
provided accordingly.
3.8 B Manual Method
Unit = cum
Taking output = 16 cum
a) Labour
Mate day 1.640 150.00 246.00 L-12
Mazdoor including loading in truck day 16.000 100.00 1600.00 L-13
Chiseller day 24.000 150.00 3600.00 L-05
Blacksmith day 1.000 150.00 150.00 L-02
b) Machinery
Tipper 5.5 cum capacity, 1 trip per hour. hour 2.900 185.00 536.50 P&M-
Credit for excavated rock found suitable cum 8.000 048
(150.00) (1200.00) M-089
for use @ 50 per cent of excavated
c) Overhead charges @ 10 % on 493.25
(a+b)
d) Contractor's profit @ 10 % on 542.58
(a+b+c)
Cost for 16 cum = a+b+c+d 5968.33
Rate per cum = (a+b+c+d)/16 373.02
say 373.00
Note 1. Credit is considered for 50 per cent of
quantity of work.
2. Loading for disposal will be done
manually, being small quantity.
3. In case some rock is issued to contractor
at site, the item of carriage shall be omitted
to the extent of quantity issued to the
contractor.
3.9 301 Excavation in Hard Rock (controlled
blasting) with disposal upto 1000
metres
Excavation for roadway in hard rock with
controlled blasting by drilling, blasting and
breaking, trimming of bottom and side
slopes in accordance with requirements of
lines, grades and cross sections, loading
and disposal of cut road with in all lifts and
leads upto 1000 metres
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.220 150.00 33.00 L-12
Mazdoor day 3.000 100.00 300.00 L-13
Driller day 2.000 150.00 300.00 L-06
Blaster day 0.500 150.00 75.00 L-03
b) Machinery
Dozer 80 HP @ 30 cum per hour hour 6.000 2000.00 12000.00 P&M-
Air compressor, 250 cfm with 2 jack hour 6.000 150.00 900.00 014
P&M-
hammers
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 001
P&M-
Tipper 5.5 cum capacity, 4 trips per hour 8.200 185.00 1517.00 017
P&M-
c) hour.
Materials 048

Page 4 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Gelatin 80 per cent kg 63.000 100.00 6300.00 M-104
Electric Detonators @ 1 detonator each 1008.000 5.00 5040.00 M-094 /
for1/2 gelatin stick of 125 gms each 100
Credit for excavated rock found suitable cum 90.000 (150.00) ### M-089
for use @ 50 per cent quantity blasted
Add 5 per cent of cost of a+b+c 1533.25
towards muffling arrangements to
guard against any rock fly off during
blasting
d) Overhead charges @ 10 % on 1869.83
(a+b+c)
e) Contractor's profit @ 10 % on 2056.81
(a+b+c+d)
Cost for 180 cum = a+b+c+d+e 22624.88
Rate per cum = (a+b+c+d+e)/180 125.69
say 126.00
Note 1. Credit is considered for 50 per cent of
quantity of blastered rock, if found suitable
for
2. construction..
In case some rock is issued to the
contractor at site, the item of carriage shall
3.10 301 be reduced tointhat
Excavation extent.
Marshy Soil
Excavation for roadway in marshy soil with
hydraulic excavator 0.9 cum bucket
capacity including cutting and loading in
tippers and disposal with in all lifts and lead
upto 1000 metres, trimming of bottom and
side slopes in accordance with
requirements of lines, grades and cross
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor day 2.000 100.00 200.00 L-13
b) Machinery
Hydraulic excavator 0.90 cum bucket hour 6.000 700.00 4200.00 P&M-
capacity @ 50 cum per hour 026
Tipper 5.5 cum capacity, 4 trips per hour 13.640 185.00 2523.40 P&M-
c) hour.
Overhead charges @ 10 % on 693.54 048
(a+b) Contractor's profit @ 10 % on
d) 762.89
(a+b+c)
Cost for 300 cum = a+b+c+d 8391.83
Rate per cum = (a+b+c+d)/300 27.97
say 28.00
3.11 301 Removal of Unserviceable Soil with
Disposal upto 1000 metres
Removal of unserviceable soil including
excavation, loading and disposal upto 1000
metres lead but excluding replacement by
suitable soil which shall be paid separately
as per clause 305.
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor day 2.000 100.00 200.00 L-13
b) Machinery
Excavator0.90 cum bucket capacity @ hour 6.000 700.00 4200.00 P&M-
60 cum per hour 026
Tipper 5.5 cum capacity, 4 trips per hour 16.360 185.00 3026.60 P&M-
c) hour.
Overhead charges @ 10 % on 743.86 048
(a+b) Contractor's profit @ 10 % on
d) 818.25
(a+b+c)
Cost for 360 cum = a+b+c+d 9000.71
Rate per cum = (a+b+c+d)/360 25.00
say 25.00

Page 5 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Note This item does not include replacement of
unsuitable soil by suitable soil.
Replacement, where required, is to be
provided and paid separately under clause
3.12 303 Presplitting of Rock Excavation Slopes
Carrying out excavation in hard rock to
achieve a specified slope of the rock face
by controlled use of explosives and blasting
accessories in properly aligned and spaced
drill holes, collection of the excavated rock
by a 80 HP dozer, loading in tipper by a
front end loader and disposing of the
material with all lifts and lead upto 1000 m,
all as =
Unit specified
sqm in clause No. 303
Taking output = 400 sqm( 120 cum
considering 300mm average depth of
excavation over the existing rock face)
a) Labour
Mate day 0.600 150.00 90.00 L-12
Mazdoor day 15.000 100.00 1500.00 L-13
b) Machinery
Air compressor 250 cfm with 2 leads @ hour 6.000 150.00 900.00 P&M-
20 cum per hour 001
Dozer, 80 HP hour 6.000 2000.00 12000.00 P&M-
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 014
P&M-
c) Materials 017
Gelatin 80 per cent kg 42.000 100.00 4200.00 M-104
Electric Detonators @ 1 detonator for each 672.000 5.00 3360.00 M-094 /
1/2 gelatin stick of 125 gms each 100
d) Overhead charges @ 10 % on 2625.00
(a+b+c)
e) Contractor's profit @ 10 % on 2887.50
(a+b+c+d)
Cost for 400 sqm = a+b+c+d+e 31762.50
Rate per sqm = (a+b+c+d+e)/400 79.41
say 79.00
Note In case blasted rock is used to the
contractor against payment for constructed
work, the cost of carriage shall be reduced
to that extent.
3.13 304 Excavation for Structures
Earth work in excavation of foundation of
structures as per drawing and technical
specification, including setting out,
construction of shoring and bracing,
removal of stumps and other deleterious
matter, dressing of sides and bottom,
backfilling the excavation earth to the
extent required and utilising the remaining
(i) earth locally
Ordinary for road work.
soil
Unit = cum
Taking output = 10 cum
A Manual Means (Depth upto 3 m)
a) Labour
Mate day 0.320 150.00 48.00 L-12
Mazdoor day 8.000 100.00 800.00 L-13
b) Overhead charges @ 10 % on (a) 84.80
c) Contractor's profit @ 10 % on 93.28
(a+b)
Cost for 10 cum = a+b+c 1026.08
Rate per cum = (a+b+c)/10 102.61
say 103.00
Note Cost of dewatering may be added where
required upto 10 per cent of labour cost
Assessment for dewatering shall be made
as per site conditions..
3.13 B Mechanical Means (Depth upto 3 m)
(i) Unit = cum

Page 6 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Taking output = 300 cum
a) Labour
Mate day 0.320 150.00 48.00 L-12
Mazdoor day 8.000 100.00 800.00 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket hour 6.000 700.00 4200.00 P&M-
c) capacity
Overhead charges @ 10 % on 504.80 026
(a+b)
d) Contractor's profit @ 10 % on 555.28
(a+b+c)
Cost for 300 cum = a+b+c+d 6108.08
Rate per cum = (a+b+c+d)/300 20.36
say 20.00
Note Cost of dewatering upto 5 per cent of (a+b)
may be added, where required.
Assessment for dewatering shall be made
as per site conditions..
3.13 (ii) Ordinary Rock (not requiring blasting)
A Manual Means (Depth upto 3 m)
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.400 150.00 60.00 L-12
Mazdoor day 10.000 100.00 1000.00 L-13
b) Overhead charges @ 10 % on (a) 106.00
c) Contractor's profit @ 10 % on 116.60
(a+b)
Cost for 10 cum = a+b+c 1282.60
Rate per cum = (a+b+c)/10 128.26
say 128.00
Note Cost of dewatering upto 10 per cent of
labour cost may be added, where required.
Assessment for dewatering shall be made
as per site conditions..
3.13 B Mechanical Means
(ii)
Unit = cum
Taking output = 216 cum
a) Labour
Mate day 0.240 150.00 36.00 L-12
Mazdoor day 6.000 100.00 600.00 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket hour 6.000 700.00 4200.00 P&M-
c) capacity
Overhead charges @ 10 % on 483.60 026
(a+b)
d) Contractor's profit @ 10 % on 531.96
(a+b+c)
Cost for 216 cum = a+b+c+d 5851.56
Rate per cum = (a+b+c+d)/216 27.09
say 27.00
Note 1.Cost of dewatering upto 5 per cent of
(a+b), may be added, where required
Assessment for dewatering shall be made
as per site conditions.
2.In case of rock, foundation beyond3 m is
not dug and hence not included.
3.13 (iii) Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
i) Mate day 0.530 150.00 79.50 L-12
ii) Driller day 0.840 150.00 126.00 L-06
iii) Blaster day 0.400 150.00 60.00 L-03
iv) Mazdoor day 12.000 100.00 1200.00 L-13
b) Machinery

Page 7 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Air Compressor 250 cfm with 2 jack hour 0.667 150.00 100.00 P&M-
hammer @ 15 cum per hour 001
c) Material
Blasting Material kg 3.500 100.00 350.00 M-104
Detonator electric each 14.000 5.00 70.00 M-094 /
100
d) Overhead charges @ 10 % on 198.55
(a+b+c)
e) Contractor's profit @ 10 % on 218.41
(a+b+c+d)
Cost for 10 cum = a+b+c+d+e 2402.46
Rate per cum = (a+b+c+d+e)/10 240.25
say 240.00
Note Cost of dewatering @ 10 per cent of labour
cost may be added, where required
Assessment for dewatering shall be made
as per site conditions.
3.13 (iv) Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum
A Mechanical Means
a) Labour
Mate day 0.200 150.00 30.00 L-12
Mazdoor day 5.000 100.00 500.00 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of hour 10.000 150.00 1500.00 P&M-
pneumatic breaker @ 1 cum per hour 001
c) Overhead charges @ 10 % on 203.00
(a+b)
d) Contractor's profit @ 10 % on 223.30
(a+b+c)
Cost for 10 cum = a+b+c+d 2456.30
Rate per cum = (a+b+c+d)/10 245.63
say 246.00
Note 1. Cost of dewatering upto 5 per cent of
(a+b), may be added, where required
Assessment for dewatering shall be made
as per site conditions.
2.In case of rock, foundation beyond 3 m is
not dug and hence not included.
3.13 (v) Marshy soil
Unit = cum
Taking output = 10 cum
A Manual means ( upto 3 m depth)
a) Labour
Mate/Supervisor day 0.400 150.00 60.00 L-12
Mazdoor day 10.000 100.00 1000.00 L-13
b) Machinery
Tractor-trolley hour 2.670 150.00 400.50 P&M-
c) Material 053
Selected earth for refilling cum 5.000 135.00 675.00 M-163
d) Overhead charges @ 10 % on 213.55
(a+b+c)
e) Contractor's profit @ 10 % on 234.91
(a+b+c+d)
Cost for 10 cum = a+b+c+d+e 2583.96
Rate per cum = ( a+b+c+d+e)/ 10 258.40
say 258.00
Note 1. Cost of dewatering @ 30 per cent of (a),
may be added, where required Assessment
for dewatering shall be made as per site
conditions.
2. Shoring & strutting 20 per cent of (a),
where required may be added
3. It is assumed that Marshy Soil will be
available upto 3 m depth only. For deeper
excavation below 3 m depth, refer analysis
in item (i) to (iv) for ordinary soil

Page 8 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
3.13 Spec. B Mechanical Means
(v)
a) Labour
i) Mate day 0.080 150.00 12.00 L-12
ii) Mazdoor for dressing sides, bottom day 2.000 100.00 200.00 L-13
and backfilling
b) Machinery
Hydraulic excavator 1.0 cum bucket hour 0.170 700.00 119.00 P&M-
capacity @ 60 cum per hour 026
Tipper 5.5 cum capacity, 4 trips per hour 0.450 185.00 83.25 P&M-
c) hour.
Material 048
Selected earth for refilling cum 5.000 135.00 675.00 M-163
d) Overhead charges @ 10 % on 108.93
(a+b+c)
e) Contractor's profit @ 10 % on 119.82
(a+b+c+d)
Cost for 10 cum = a+b+c+d+e 1317.99
Rate per cum = (a+b+c+d+e)/10 131.80
say 132.00
Note 1. Cost of dewatering @ 20 per cent of
(a+b) may be added, where required
2. Shoring & strutting @ 10 per cent of
(a+b), where required may be added
3. It is assumed that Marshy Soil will be
available upto 3 m depth only. For deeper
excavation below 3 m depth, refer analysis
in item (i) to (iv) for ordinary soil
3.14 305.4. Scarifying Existing Granular Surface to
3 a Depth of 50 mm by Manual Means
Scarifying the existing granular road
surface to a depth of 50 mm and disposal of
scarified material within all lifts and leads
upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.200 150.00 30.00 L-12
Mazdoor including loading and day 5.000 100.00 500.00 L-13
b) unloading
Machinery
Tractor-trolley hour 1.670 150.00 250.50 P&M-
d) Overhead charges @ 10 % on 78.05 053
(a+b+c)
e) Contractor's profit @ 10 % on 85.86
(a+b+c+d)
Cost for 100 sqm = a+b+c+d 944.41
Rate per sqm = (a+b+c+d)/100 9.44
say 9.00
Note In case material is to be reused at site,
transportation cost catered above for
3.15 305.4. disposal shall
Scarifying be deleted.
Existing Bituminous Surface
3 to a depth of 50 mm by Mechanical
Means
Scarifying the existing bituminous road
surface to a depth of 50 mm and disposal of
scarified material with in all lifts and lead
upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.010 150.00 1.50 L-12
Mazdoor day 0.250 100.00 25.00 L-13
b) Machinery
Tractor with ripper attachment @ 60 hour 0.080 175.00 14.00 P&M-
cum
Frontper
endhour
loader 1 cum bucket capacity hour 0.200 700.00 140.00 055
P&M-
@ 25 cum per hour 017
Tipper 5.5 cum capacity, 4 trips per hour 0.230 185.00 42.55 P&M-
c) hour.
Overhead charges @ 10 % on 22.31 048
(a+b) Contractor's profit @ 10 % on
d) 24.54
(a+b+c)
Page 9 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Cost for 100 sqm = a+b+c+d 269.89
Rate per sqm = (a+b+c+d)/100 2.70
say 3.00
3.16 305 Construction of Embankment with
Material obtained from Borrowpits
Construction of embankment with approved
material obtained from borrow pits with all
lifts and leads, transporting to site,
spreading, grading to required slope and
compacting to meet requirement of table
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoor day 1.000 100.00 100.00 L-13
b) Machinery
Hydraulic Excavator1 cum bucket hour 1.670 700.00 1169.00 P&M-
capacity @ 60 cum per hour 026
Tipper 10 tonne capacity tonne.k 160 x L 1.85 2960.00 Lead
m =10 km
& P&M-
058
Add 10 per cent of cost of carriage to 296.00
cover cost of loading and unloading
Dozer 80 HP for spreading @ 200 cum hour 0.500 2000.00 1000.00 P&M-
per hour
Motor grader for grading @ 100 cum hour 1.000 1200.00 1200.00 014
P&M-
per hour
Water tanker6 KL capacity hour 4.000 105.00 420.00 032
P&M-
Vibratory roller 8 -10 tonnes @ 100 cum hour 1.000 1000.00 1000.00 060
P&M-
c) perMaterial
hour 059
Cost of water KL 24.000 50.00 1200.00 M-189
Compensation for earth taken from cum 100.000 45.00 4500.00 M-092
d) private land charges @ 10 % on
Overhead 1385.10
(a+b+c)
e) Contractor's profit @ 10 % on 1523.61
(a+b+c+d)
Cost for 100 cum = a+b+c+d+e 16759.71
Rate per cum = (a+b+c+d+e)/100 167.60
say 168.00
Note Compensation for earth will vary from place
to place and will have to be assessed
realistically as per particular ground
situation. In case earth is available from
Govt. land, compensation for earth will not
be required. The position is required to be
clearly stated in the cost estimate.
3.17 305 Construction of Embankment with
Material Deposited from Roadway
Cutting
Construction of embankment with approved
materials deposited at site from roadway
cutting and excavation from drain and
foundation of other structures graded and
compacted to meet requirement of table
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.020 150.00 3.00 L-12
Mazdoor day 0.500 100.00 50.00 L-13
b) Machinery
Dozer 80 HP for spreading @ 200 cum hour 0.500 2000.00 1000.00 P&M-
per hour
Motor grader for grading @ 100 cum hour 1.000 1200.00 1200.00 014
P&M-
per hour
Water tanker6 KL capacity hour 4.000 105.00 420.00 032
P&M-
Vibratory roller 8-10 tonnes @ 100 cum hour 1.000 1000.00 1000.00 060
P&M-
c) perMaterial
hour 059
Cost of water KL 24.000 50.00 1200.00 M-189
d) Overhead charges @ 10 % on 487.30
(a+b+c)
e) Contractor's profit @ 10 % on 536.03
(a+b+c+d)
Page 10 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Rate for 100 cum = a+b+c+d+e 5896.33
Rate per cum = (a+b+c+d+e)/100 58.96
say 59.00
Note In case the earth cutting is done by dozer
and pushed for filling in the embankment,
the input of dozer in the cost of
embankment shall be deleted as the same
is already provided in the cost of
excavation. However, if the earth is
dumped by tippers from roadway cutting,
3.18 305 Construction of Subgrade and Earthen
Shoulders
Construction of sub-grade and earthen
shoulders with approved material obtained
from borrow pits with all lifts & leads,
transporting to site, spreading, grading to
required slope and compacted to meet
requirement of table No. 300-2
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoor day 1.000 100.00 100.00 L-13
b) Machinery
Hydraulic excavator1 cum bucket hour 1.670 700.00 1169.00 P&M-
capacity @ 60 cum per hour 026
Tipper 10 tonne capacity tonne.k 175xL 1.85 3237.50 Lead
m =10 km
& P&M-
058
Add 10 per cent of cost of carriage to 323.75
cover cost of loading and unloading
Dozer 80 HP for spreading @ 200 cum hour 0.500 2000.00 1000.00 P&M-
per hour
Motor grader for grading @ 50 cum per hour 2.000 1200.00 2400.00 014
P&M-
hour
Water tanker with 6 km lead hour 4.000 105.00 420.00 032
P&M-
Vibratory roller 8-10 tonnes @ 80 cum hour 1.250 1000.00 1250.00 060
P&M-
c) perMaterial
hour 059
Cost of water KL 24.000 50.00 1200.00 M-189
Compensation for earth taken from cum 100.000 45.00 4500.00 M-092
d) private land charges @ 10 % on
Overhead 1560.63
(a+b+c)
e) Contractor's profit @ 10 % on 1716.69
(a+b+c+d)
Cost for 100 cum = a+b+c+d+e 18883.56
Rate per cum = (a+b+c+d+e)/100 188.84
say 189.00
3.19 305.3. Compacting Original Ground
4 Case-I Compacting original ground supporting
sub-grade
Loosening of the ground upto a level of 500
mm below the sub-grade level, watered,
graded and compacted in layers to meet
requirement of table 300-2 for sub-grade
construction.
Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.120 150.00 18.00 L-12
Mazdoor day 3.000 100.00 300.00 L-13
b) Machinery
Tractor with ripper attachment hour 9.000 175.00 1575.00 P&M-
Motor grader for grading hour 6.000 1200.00 7200.00 055
P&M-
Water tanker 6 KL capacity hour 4.000 105.00 420.00 032
P&M-
Vibratory roller 8-10 tonne @ 80 hour 7.500 1000.00 7500.00 060
P&M-
c) cum/hour
Material 059
Cost of water KL 24.000 50.00 1200.00 M-189
d) Overhead charges @ 10 % on 1821.30
(a+b+c)

Page 11 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. e) Contractor's profit @ 10 % on 2003.43
(a+b+c+d)
Cost for 600 cum = a+b+c+d+e 22037.73
Rate per cum = (a+b+c+d+e)/600 36.73
say 37.00
3.19 Case- :Compacting original ground
II supporting embankment
Loosening, leveling and Compacting
original ground supporting embankment to
facilitate placement of first layer of
embankment, scarified to a depth of 150
mm, mixed with water at OMC and then
compacted by rolling so as to achieve
minimum dry density as given in Table 300-
Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor day 2.000 100.00 200.00 L-13
b) Machinery
Tractor with ripper attachment hour 6.000 175.00 1050.00 P&M-
Vibratory road roller 8-10 tonne hour 7.500 1000.00 7500.00 055
P&M-
capacity
Water tanker6 KL capacity hour 4.000 105.00 420.00 059
P&M-
c) Material 060
Cost of water KL 24.000 50.00 1200.00 M-189
d) Overhead charges @ 10 % on 1038.20
(a+b+c)
e) Contractor's profit @ 10 % on 1142.02
(a+b+c+d)
Cost for 600 cum = (a+b+c+d+e) 12562.22
Rate per sqm = (a+b+c+d+e)/600 20.94
say 21.00
3.20 305 Stripping and Storing Top Soil
Stripping, storing of top soil by road side at
15 m internal and re-application on
embankment slopes, cut slopes and other
areas in localities where the available
embankment material is not conducive to
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.200 150.00 30.00 L-12
Mazdoor day 5.000 100.00 500.00 L-13
b) Machinery
Dozer 80 HP @ 100 cum per hour hour 0.100 2000.00 200.00 P&M-
c) Overhead charges @ 10 % on 73.00 014
(a+b)
d) Contractor's profit @ 10 % on 80.30
(a+b+c)
Cost for 10 cum = (a+b+c+d) 883.30
Rate per cum = (a+b+c+d)/10 88.33
say 88.00
3.21 Stripping, Storing and Re-laying Top
Soil from Borrow Areas in Agriculture
Fields.
Stripping of top soil from borrow areas
located in agriculture fields, storing at a
suitable place, spreading and re-laying after
taking the borrow earth to maintain fertility
of the agricultural field, finishing it to the
required levels and satisfaction of the
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor day 2.000 100.00 200.00 L-13
b) Machinery
Dozer, 80 HP hour 6.000 2000.00 12000.00 P&M-
014

Page 12 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. c) Overhead charges @ 10 % on 1221.20
(a+b)
d) Contractor's profit @ 10 % on 1343.32
(a+b+c)
Cost for 300 cum = (a+b+c+d) 14776.52
Rate per cum = (a+b+c+d)/300 49.26
say 49.00
3.22 307 Turfing with Sods
Furnishing and laying of the live sods of
perennial turf forming grass on
embankment slope, verges or other
locations shown on the drawing or as
directed by the engineer including
preparation of ground, fetching of sods and
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 150.00 18.00 L-12
Mazdoor for preparation of ground and day 3.000 100.00 300.00 L-13
fetching of sods
b) Machinery
Water tanker including watering for 3 hour 2.000 105.00 210.00 P&M-
months
Tractor-trolley hour 1.000 150.00 150.00 060
P&M-
c) Material 053
Farm yard manure @ 0.18 cum per 100 cum 0.180 250.00 45.00 M-167
sqm at site of work
Cost of water KL 12.000 50.00 600.00 M-189
d) Overhead charges @ 10 % on 132.30
(a+b+c)
e) Contractor's profit @ 10 % on 145.53
(a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 1600.83
Rate per 100 sqm = (a+b+c+d+e)/100 16.01
say 16.00
3.23 308 Seeding and Mulching
Preparation of seed bed on previously laid
top soil, furnishing and placing of seeds,
fertilizer, mulching material, applying
bituminous emulsion at the rate of 0.23
litres per sqm and laying and fixing jute
netting, including watering for 3 months all
Unit = sqm
Taking output = 240 sqm
a) Labour
Mate day 0.400 150.00 60.00 L-12
Mazdoor day 10.000 100.00 1000.00 L-13
b) Machinery
Water tanker 6 KL capacity including hour 14.000 105.00 1470.00 P&M-
watering for 3 months 060
Tractor-trolley hour 2.400 150.00 360.00 P&M-
c) Material 053
Seeds kg 3.600 60.00 216.00 M-162
Sludge/Farm yard manure @ 0.18 cum cum 0.430 250.00 107.50 M-167
per 100 sqm
Bitumen Emulsion litre 55.200 24.00 1324.80 M-077
Jute netting, open weave, 2.5 cm sqm 264.000 30.00 7920.00 M-121
square
Cost of opening
water for 3 months KL 84.000 50.00 4200.00 M-189
d) Overhead charges @ 10 % on 1665.83
(a+b+c)
e) Contractor's profit @ 10 % on 1832.41
(a+b+c+d)
Cost for 240 sqm = a+b+c+d+e 20156.54
Rate per sqm = (a+b+c+d+e)/240 83.99
say 84.00
3.24 309 Surface Drains in Soil

Page 13 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Construction of unlined surface drains of
average cross sectional area 0.40 sqm in
soil to specified lines, grades, levels and
dimensions to the requirement of clause
301 and 309. Excavated material to be
used in embankment within a lead of 50
metres (average lead 25 metres)
Unit = metre
Taking output = 10 metres
A Mechanical means
a) Labour
Mate day 0.010 150.00 1.50 L-12
Mazdoor for dressing of bed and side of day 0.250 100.00 25.00 L-13
b) drain
Machinery
Hydraulic Excavator 0.3 cum bucket hour 0.330 700.00 231.00 P&M-
capacity @ 30 metres per hour 026
c) Overhead charges @ 10 % on 25.75
(a+b)
d) Contractor's profit @ 10 % on 28.33
(a+b+c)
Cost for 10 metres = a+b+c+d 311.58
Rate per metre = (a+b+c+d)/10 31.16
say 31.00
3.24 B Manual Means
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor day 2.000 100.00 200.00 L-13
b) Overhead charges @ 10 % on (a) 21.20
c) Contractor's profit @ 10 % on 23.32
(a+b)
Cost for 10 metres = a+b+c 256.52
Rate per metre = (a+b+c)/10 25.65
say 26.00
Note Where lining of drain is provided, quantity
shall be worked out based on approved
design and drawing and priced on rate of
cement concrete of approved grade or
stone/brick masonry as the case may be.
3.25 309 Surface Drains in Ordinary Rock
Construction of unlined surface drain of
average cross sectional area 0.4 sqm in
ordinary rock to specified lines, grades,
levels and dimensions as per approved
design and to the requirement of clause
301 to 309. Excavated material to be used
Unit = metre
Taking output = 10 metres
A Mechanical Means
a) Labour
Mate day 0.020 150.00 3.00 L-12
Mazdoor for dressing of bed and side of day 0.500 100.00 50.00 L-13
b) drain
Machinery
Hydraulic Excavator 0.3 cum bucket hour 0.670 700.00 469.00 P&M-
capacity @ 15 metres per hour 026
c) Overhead charges @ 10 % on 52.20
(a+b)
d) Contractor's profit @ 10 % on 57.42
(a+b+c)
Cost for 10 metres = a+b+c+d 631.62
Rate per metre = (a+b+c+d)/10 63.16
say 63.00
3.25 B Manual Means
a) Labour
Mate day 0.120 150.00 18.00 L-12
Mazdoor day 3.000 100.00 300.00 L-13
b) Overhead charges @ 10 % on (a) 31.80
c) Contractor's profit @ 10 % on 34.98
(a+b)

Page 14 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Cost for 10 metres = a+b+c 384.78
Rate per metre = (a+b+c)/10 38.48
say 38.00
3.26 309 Surface Drains in Hard Rock
Rate per metre may be worked out based
on quantity of hard rock as per design.
For rate of hard rock cutting, refer relevant
item in this chapter
3.27 309 Sub-Surface Drains with Perforated
Pipe
Construction of subsurface drain with
perforated pipe of 100 mm internal
diameter of metal/ asbestos cement/
cement concrete/PVC, closely jointed,
perforations ranging from 3 mm to 6 mm
depending upon size of material
surrounding the pipe, with 150 mm bedding
below the pipe and 300 mm cushion above
the pipe, cross section of excavation 450 x
550 mm.
Unit Excavated material to be utilised
= metre
Taking output = 10 metres
a) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoor for excavation and back filling day 2.000 100.00 200.00 L-13
c) Material
Perforated pipe of cement concrete, metre 10.000 200.00 2000.00 M-135
internal dia 100 mm
Crushed stone as per table 300-3 cum 2.400 160.00 384.00 M-012
d) Overhead charges @ 10 % on 259.00
(a+b+c)
e) Contractor's profit @ 10 % on 284.90
(a+b+c+d)
Cost for 10 metres = a+b+c+d+e 3133.90
Rate per metre = (a+b+c+d+e)/10 313.39
say 313.00
Note Type of pipe may be modified depending
upon provision in design.
3.28 309 Aggregate Sub-Surface Drains
Construction of aggregate sub surface drain
300 mm x 450 mm with aggregates
conforming to table 300-4, excavated
material to be utilised in roadway.
Unit = metre
Taking output = 10 metres
a) Labour
Mate day 0.020 150.00 3.00 L-12
Mazdoor for excavation and back filling day 1.500 100.00 150.00 L-13
with aggregates
b) Material
Crushed stone as per table 300-3 cum 1.350 160.00 216.00 M-012
c) Overhead charges @ 10 % on 36.90
(a+b) Contractor's profit @ 10 % on
d) 40.59
(a+b+c)
Cost for 10 metres = a+b+c+d 446.49
Rate per metre = (a+b+c+d)/10 44.65
say 45.00
3.29 309 Underground Drain at Edge of
Pavement
Construction of an underground drain 1 m x
1 m (inside dimensions) lined with RCC-20
cm thick and covered with RCC slab10 cm
in thickness on urban roads.
Unit = Running metre
Taking output = one metre
a) Earthwork in soil cum 1.500 20.00 30.00 Item No.
3.13
b) RCC work M-20 cum 0.495 2828.00 1399.86 Item
12.8 (C)
RCC

Page 15 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec.
Rate per metre = (a+b) 1429.86
Rates for these items may be taken from say 1430.00
chapters on earth work and substructures
3.30 310 respectively. and Surface Treatment of
Preparation
Formation.
Preparation and surface treatment of
formation by removing mud and slurry,
watering to the extent needed to maintain
the desired moisture content, trimming to
the required line, grade, profile and rolling
with 8-10 tonne smooth wheeled roller,
complete as per clause 310.
Unit = sqm
Taking output = 3500sqm
a) Labour
Mate day 0.280 150.00 42.00 L-12
Mazdoor day 6.000 100.00 600.00 L-13
Mazdoor skilled day 1.000 125.00 125.00 L-15
b) Machinery
Smooth 3 wheeled steel roller 8-10 hour 3.000 170.00 510.00 P&M-
tonnes
Water tanker 6 KL, one trip per hour hour 3.000 105.00 315.00 044
P&M-
c) Material 060
Cost of water KL 18.000 50.00 900.00 M-189
d) Overhead charges @ 10 % on 249.20
(a+b+c)
e) Contractor's profit @ 10 % on 274.12
(a+b+c+d)
Cost for 3500 sqm = a+b+c+d+e 3015.32
Rate per sqm = (a+b+c+d+e)/3500 0.86
say 1.00
3.31 313 Construction of Rock fill Embankment
Construction of rock fill embankment with
broken hard rock fragments of size not
exceeding 300 mm laid in layers not
exceeding 500 mm thick including filling of
surface voids with stone spalls, blinding top
layer with granular material, rolled with
vibratory road roller, all complete as per
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoor day 1.500 100.00 150.00 L-13
b) Machinery
Dozer 80 HP for spreading @ 200 cum hour 0.500 2000.00 1000.00 P&M-
per hour road roller 8-10 tonnes @ 100
Vibratory hour 1.000 1000.00 1000.00 014
P&M-
cum per hour 059
Water tanker 6 KL, one trip per hour hour 2.000 105.00 210.00 P&M-
c) Material 060
Cost of water KL 12.000 50.00 600.00 M-189
d) Overhead charges @ 10 % on 296.60
(a+b+c)
e) Contractor's profit @ 10 % on 326.26
(a+b+c+d)
Cost for 100 cum = a+b+c+d+e 3588.86
Rate per cum = (a+b+c+d+e)/100 35.89
say 36.00
Note It is assumed that rock is available locally at
site from roadway cutting. In case, portion
of the rock requires breaking to acceptable
size of 300 mm, breaking charges will have
to be added.
EARTH WORK ON HILL ROAD
3.32 301 Excavation in Hill Area in Soil by
Mechanical Means

Page 16 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Excavation in soil in hilly area by
mechanical means including cutting and
trimming of side slopes and disposing of
excavated earth with all lifts and lead upto
1000 metres.
Unit = cum
Taking output = 260 cum
a) Labour
Mate day 0.240 150.00 36.00 L-12
Mazdoor for trimming slopes and day 6.000 100.00 600.00 L-13
helping in excavation etc.
b) Machinery
Dozer 80 HP (D-80 A 12)@ 43.28 cum hour 6.000 2000.00 12000.00 P&M-
per hour
Front end loader hour 6.000 700.00 4200.00 014
P&M-
Tipper 5.5cum capacity, 4 trips per hour 12.000 185.00 2220.00 017
P&M-
c) hour.
Overhead charges @ 10 % on 1905.60 048
(a+b)
d) Contractor's profit @ 10 % on 2096.16
(a+b+c)
Cost for 260 cum = a+b+c+d 23057.76
Rate per cum = (a+b+c+d)/260 88.68
say 89.00
Note In case the land on the valley side is barren
and there is no objection for disposing of
excavated earth on the valley side, the
provision of front end loader and tipper
shall be deleted as excavated earth shall be
disposed off on the valley side.
3.33 301 Excavation in Hilly Area in Ordinary
Rock by Mechanical Means not
Requiring Blasting.
Excavation in hilly area in ordinary rock not
requiring blasting by mechanical means
including cutting and trimming of slopes
and disposal of cut material with all lift and
lead upto 1000 metres.
Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.320 150.00 48.00 L-12
Mazdoor day 8.000 100.00 800.00 L-13
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum hour 6.000 2000.00 12000.00 P&M-
per hour
Front end loader hour 7.000 700.00 4900.00 014
P&M-
Tipper 5.5cum capacity, 4 trips per hour 7.000 185.00 1295.00 017
P&M-
c) hour.
Overhead charges @ 10 % on 1904.30 048
(a+b)
d) Contractor's profit @ 10 % on 2094.73
(a+b+c)
Cost for 170 cum = a+b+c+d 23042.03
Rate per cum = (a+b+c+d)/170 135.54
say 136.00
Note In case the land on the valley side is barren
and there is no objection for disposing of
excavated earth on the valley side, the
provision of front end loader and tipper
shall be deleted as excavated earth can be
disposed off on the valley side.
3.34 301 Excavation in Hilly Areas in Hard Rock
Requiring Blasting
Excavation in hilly areas in hard rock
requiring blasting, by mechanical means
including trimming of slopes and disposal of
cut material with all lifts and lead upto 1000
metres.
Unit = cum
Taking output = 170 cum
a) Labour
Mate day 0.490 150.00 73.50 L-12
Mazdoor day 10.000 100.00 1000.00 L-13

Page 17 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Driller day 2.000 150.00 300.00 L-06
Blaster day 0.250 150.00 37.50 L-03
b) Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum hour 6.000 2000.00 12000.00 P&M-
per hour
Air compressor 250 cfm with two jack hour 5.000 150.00 750.00 014
P&M-
hammer @ 20 cum per hour 001
Front end loader hour 7.000 700.00 4900.00 P&M-
Tipper 5.5cum capacity, 4 trips per hour 7.000 185.00 1295.00 017
P&M-
c) hour.
Materials 048
Gelatine 80 per cent kg 35.000 100.00 3500.00 M-104
Electric Detonators @ 1 Detonator for 2 each 140.000 5.00 700.00 M-094 /
Gelatine sticks of 125 gms each 100
d) Overhead charges @ 10 % on 2455.60
(a+b+c)
e) Contractor's profit @ 10 % on 2701.16
(a+b+c+d)
Cost for 170 cum = a+b+c+d+e 29712.76
Rate per cum = (a+b+c+d+e)/170 174.78
say 175.00
Note In case the land on the valley side is barren
and there is no objection for disposing of
excavated earth on the valley side, the
provision of front end loader and tipper
shall be deleted as excavated earth can be
disposed off on the valley side.
In case of hill roads, the altitude effect
comes into play. The output of men and
machines decreases progressively after
2100 m elevation leading to increase in
cost . High altitude effect has been
explained in the basic approach.
3.35 Work in Urban Roads
The cost of earth work in urban roads
inhabited area will be comparatively higher
due toThere
a) following reasons:
is mixed traffic on urban roads
like slow moving hand and animal driven
carts, rickshaws, cycles, two/ three wheeler
apart from the usual vehicular traffic
resulting into traffic jams. This causes loss
of working time which may be in the range
of 10 -15 per cent
b) There is considerable disruption of
traffic adversely affecting the efficiency of
the working parties including machines due
to congestion caused by pedestrian traffic,
local road side venders, parking of vehicles
by the road side, encroachments by the
shopkeepers and local shops who make use
of the berms of the road in front of these
shops and unauthorised conversion of road
berms into mini local market The output of
manpower and machines is substantially
reduced due to factors mentioned above.
c) Cost of living in urban areas is
comparatively more resulting into higher
wages.
d) At times, work is executed during
night time due to heavy traffic during day
time. This involves extra expenditure by
way of making arrangement for lighting and
special transport for working parties due to
odd hour
In the light of above, the authorities
engaged in preparing the cost estimates
may exercise their judgment and cater for
the additional cost to the extent of 2 to 3
per cent, keeping in view the severity of
factors mentioned above. Supporting details
for the extra cost based on the actual
conditions in specific cases will have to give
in justification.

Page 18 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec.
3.36 Sugge Embankment Construction with
stive Flyash/Pond ash available from coal or
lignite burning Thermal Plants as
waste material.
Construction of embankment with Flyash
conforming to table 1 of IRC: SP: 58 - 2001
obtained from coal or lignite burning
thermal power stations as waste material,
spread and compacted in layer of 200mm
thickness each at OMC, all as specified in
IRC: SP: 58-2001 and as per approved
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.160 150.00 24.00 L-12
Mazdoor day 4.000 100.00 400.00 L-13
b) Machinery
Hydraulic Excavator 0.9 cum bucket hour 6.000 700.00 4200.00 P&M-
capacity @ 60 cum/hour 026
Tipper 10Tcapacity flyash 360 x 1.2 = tonne.k 432 x L 1.85 7992.00 Lead
432 tonnes m =10 km
& P&M-
058
Add 10 per cent of cost of carriagefor 799.20
loading and unloading
Dozer 80 HP for spreading @ 200 hour 1.800 2000.00 3600.00 P&M-
cum/hour
Motor Grader for grading @ 100 hour 3.600 1200.00 4320.00 014
P&M-
cum/hour
Water tanker6 KL capacity hour 12.000 105.00 1260.00 032
P&M-
Vibratory Roller 8-10 tonne @ 100 hour 3.600 1000.00 3600.00 060
P&M-
c) cum/hour
Overhead charges @ 10 % on 2619.52 059
(a+b)
d) Contractor's profit @ 10 % on 2881.47
(a+b+c)
Cost for 360 cum = a+b+c+d 31696.19
Rate per cum = (a+b+c+d)/360 88.04
say 88.00
Note 1.As flyash is available free of cost as waste
material from Thermal Plants, cost of
material has not been added.
2.The earth cover on sides and
intermediate layers of earth sandwiching
the flyash have not been included in this
analysis. The same are required to be
provided as per approved design and priced
separately as embankment construction.

Page 19 of 361
CHAPTER - 4
Ref. SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
4.1 Spec.
401 Granular Sub-Base with Close Graded
Material (Table:- 400-1)
A Plant Mix Method
Construction of granular sub-base by
providing close graded Material, mixing in a
mechanical mix plant at OMC, carriage of
mixed Material to work site, spreading in
uniform layers with motor grader on
prepared surface and compacting with
vibratory power roller to achieve the desired
Unit = cum
Taking output = 225 cum (450 tonne)
a) Labour
Mate day 0.400 150.00 60.00 L-12
Mazdoor skilled day 2.000 125.00 250.00 L-15
Mazdoor day 8.000 100.00 800.00 L-13
b) Machinery
Wet mix plant @ 75 tonne capacity per hour 6.000 1000.00 6000.00 P&M-
hour
Electric generator 125 KVA hour 6.000 650.00 3900.00 093
P&M-
Water tanker 6 KL capacity 5 km lead hour 4.500 105.00 472.50 018
P&M-
with one trip per hour 060
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-
Tipper 10 tonne tonne.k 450 x L 1.85 16650.00 017
Lead
m =20 km
& P&M-
058
Add 10 per cent of cost of carriage to 1665.00
cover loading and unloading
Motor Grader 110 HP hour 6.000 1200.00 7200.00 P&M-
Vibratory roller 8-10 t hour 6.000 1000.00 6000.00 032
P&M-
c) Material 059
Close graded Granular sub-base Material as
per table 400-1
For Grading-I Material
53 mm to 9.5 mm @ 50 per cent cum 144.000 200.00 28800.00 M-013
9.5 mm to 2.36 mm @ 20 per cent cum 57.000 200.00 11400.00 M-017
2.36 mm below @ 30 per cent cum 86.400 200.00 17280.00 M-020
Cost of water KL 27.000 50.00 1350.00 M-189
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 100.800 200.00 20160.00 M-015
9.5 mm to 2.36 mm @ 25 per cent cum 72.000 200.00 14400.00 M-017
2.36 mm below @ 40 per cent cum 115.200 200.00 23040.00 M-020
Cost of water KL 27.000 50.00 1350.00 M-189
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 35 per cent cum 100.800 200.00 20160.00 M-016
4.75 mm to 2.36 mm @ 12.5 per cent cum 36.000 200.00 7200.00 M-018
2.36 mm below @ 52.5 per cent cum 151.200 200.00 30240.00 M-020
Cost of water KL 27.000 50.00 1350.00 M-189
4.1A (i) Rate per cum for grading-I Material
d) Overhead charges @ 10 % on 10602.75
(a+b+c)
e) Contractor's profit @ 10 % on 11663.03
(a+b+c+d)
Cost for 225 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/225 570.19
say 570.00
4.1A (ii) Rate per cum for grading-II Material
d) Overhead charges @ 10 % on 10614.75
(a+b+c)
e) Contractor's profit @ 10 % on 11676.23
(a+b+c+d)
Cost for 225 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/225 570.84
say 571.00
4.1A (iii) Rate per cum for grading-III Material
d) Overhead charges @ 10 % on 10614.75
(a+b+c)
Page 1 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. e) Contractor's profit @ 10 % on 11676.23
(a+b+c+d)
Cost for 225 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/225 570.84
say 571.00
Note Any one of the grading for material may be
adopted as per design
4.1 B By Mix in Place Method
Construction of granular sub-base by
providing close graded material, spreading in
uniform layers with motor grader on
prepared surface, mixing by mix in place
method with rotavator at OMC, and
compacting with vibratory roller to achieve
the desired density, complete as per clause
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.480 150.00 72.00 L-12
Mazdoor skilled day 2.000 125.00 250.00 L-15
Mazdoor unskilled day 10.000 100.00 1000.00 L-13
b) Machinery
Motor Grader 110 HP @ 50 cum hour 6.000 1200.00 7200.00 P&M-
Vibratory roller 8 -10 tonne hour 6.000 1000.00 6000.00 032
P&M-
Tractor - Rotavator hour 12.000 150.00 1800.00 059
P&M-
Water tanker 6 KL capacity hour 3.000 105.00 315.00 054
P&M-
c) Material 060
Close graded Granular sub-base Material as
per table 400-1
For Grading-I Material
53 mm to 9.5 mm @ 50 per cent cum 192.000 200.00 38400.00 M-013
9.5 mm to 2.36 mm @ 20 per cent cum 76.000 200.00 15200.00 M-017
2.36 mm below @ 30 per cent cum 115.200 200.00 23040.00 M-020
Cost of water KL 18.000 50.00 900.00 M-189
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 134.400 200.00 26880.00 M-015
9.5 mm to 2.36 mm @ 25 per cent cum 96.000 200.00 19200.00 M-017
2.36 mm below @ 40 per cent cum 153.600 200.00 30720.00 M-020
Cost of water KL 18.000 50.00 900.00 M-189
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 35 per cent cum 134.400 200.00 26880.00 M-016
4.75 mm to 2.36 mm @ 12.5 per cent cum 48.000 200.00 9600.00 M-018
2.36 mm below @ 52.5 per cent cum 201.600 200.00 40320.00 M-020
Cost of water KL 18.000 50.00 900.00 M-189
4.1B (i) Rate per cum for grading-I Material
d) Overhead charges @ 10 % on 9417.70
(a+b+c)
e) Contractor's profit @ 10 % on 10359.47
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/300 379.85
say 380.00
4.1B (ii) Rate per cum for grading-II Material
d) Overhead charges @ 10 % on 9433.70
(a+b+c)
e) Contractor's profit @ 10 % on 10377.07
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/300 380.49
say 380.00
4.1B (iii) Rate per cum for grading-III Material
d) Overhead charges @ 10 % on 9433.70
(a+b+c)
e) Contractor's profit @ 10 % on 10377.07
(a+b+c+d)
Page 2 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Cost for 300 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/300 380.49
say 380.00
Note Any one of the grading for material may be
adopted as per design
4.2 401 Granular Sub-Base with Coarse Graded
Material (Table:- 400- 2)
Construction of granular sub-base by
providing coarse graded material, spreading
in uniform layers with motor grader on
prepared surface, mixing by mix in place
method with rotavator at OMC, and
compacting with vibratory roller to achieve
the desired density, complete as per clause
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.400 150.00 60.00 L-12
Mazdoor skilled day 2.000 125.00 250.00 L-15
Mazdoor day 8.000 100.00 800.00 L-13
b) Machinery
Mortar Grader 110 HP @ 50 cum per hour hour 6.000 1200.00 7200.00 P&M-
Vibratory roller 8 -10 tonne hour 6.000 1000.00 6000.00 032
P&M-
Water tanker 6 KL capacity hour 3.000 105.00 315.00 059
P&M-
c) Material 060
For coarse graded Granular sub-base
Materials per table 400-2
For grading-I Material
53 mm to 26.5 mm @ 35 per cent cum 134.400 200.00 26880.00 M-029
26.5 mm to 4.75 mm @ 45 per cent cum 172.800 200.00 34560.00 M-026
2.36 mm below @ 20 per cent (Coarse cum 76.800 200.00 15360.00 M-022
Sand)
Cost of water KL 18.000 50.00 900.00 M-189
OR
For Grading-II Material
26.5 mm to 4.75 mm @ 75 per cent cum 288.000 200.00 57600.00 M-026
2.36 mm below @ 25 per cent cum 96.000 200.00 19200.00 M-022
Cost of water KL 18.000 50.00 900.00 M-189
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 66 per cent cum 255.000 200.00 51000.00 M-025
2.36 mm below @ 34 per cent cum 129.000 200.00 25800.00 M-022
Cost of water KL 18.000 50.00 900.00 M-189
4.2 (i) Rate per cum for grading-I Material
d) Overhead charges @ 10 % on 9232.50
(a+b+c)
e) Contractor's profit @ 10 % on 10155.75
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/300 372.38
say 372.00
4.2 (ii) Rate per cum for grading-II Material
d) Overhead charges @ 10 % on 9232.50
(a+b+c)
e) Contractor's profit @ 10 % on 10155.75
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/300 372.38
say 372.00
4.2 (iii) Rate per cum for grading-III Material
d) Overhead charges @ 10 % on 9232.50
(a+b+c)
e) Contractor's profit @ 10 % on 10155.75
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/300 372.38

Page 3 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. say 372.00
Note Any one of the grading for material may be
adopted as per design
4.3 402 Lime Stabilisation for Improving Sub-
grade and spreading available soil in the
Laying
sub-grade on a prepared surface, pulverising,
mixing the spread soil in place with rotavator
with 3 per cent slaked lime having minimum
content of 70 per cent of CaO, grading with
motor grader and compacting with the road
roller at OMC to the desired density to form a
layer of improved sub grade
Unit = cum
Taking output = 300 cum (525 tonne)
A By Mechanical Means
a) Labour
Mate day 0.360 150.00 54.00 L-12
Skilled mazdoor for alignment and day 1.000 125.00 125.00 L-15
geometrics
Mazdoor for spraying lime day 8.000 100.00 800.00 L-13
b) Machinery
Tractor with ripper and rotavator hour 12.000 175.00 2100.00 P&M-
attachments @ 60 cum per hour for 055
ripping and 25 cum per hour for mixing
Motor Grader 110 HP @ 50 cum per hour hour 6.000 1200.00 7200.00 P&M-
Vibratory roller 8 - 10 tonne capacity hour6.00x0.65* 1000.00 3900.00 032
P&M-
Water tanker 6 KL capacity hour 12.000 105.00 1260.00 059
P&M-
c) Material 060
Lime at site tonne 15.750 2400.00 37800.00 M-188
Cost of water KL 72.000 50.00 3600.00 M-189
d) Overhead charges @ 10 % on 5683.90
(a+b+c)
e) Contractor's profit @ 10 % on 6252.29
(a+b+c+d)
Cost for 300 cum= a+b+c+d+e 68775.19
Rate per cum =( a+b+c+d+e)/300 229.25
say 229.00
Note * Though vibratory roller is required only for
3 hours as per norms, but the same has to be
available at site for 6 hours as other
machines for spreading and mixing will take
6 hours. The usage rates of roller have been
multiplied with a factor of 0.65.
4.3 B By Manual Means
Unit = cum
Taking output = 150 cum (263 tonnes)
a) Labour
Mate day 1.440 150.00 216.00 L-12
Mazdoor skilled day 1.000 125.00 125.00 L-15
Mazdoor day 35.000 100.00 3500.00 L-13
b) Machinery
Vibratory roller 8 - 10 tonne @ 60 cum hour 2.500 1000.00 2500.00 P&M-
per hour
Water tanker 6 KL capacity hour 6.000 105.00 630.00 059
P&M-
c) Material 060
Lime at site tonne 8.000 2400.00 19200.00 M-188
Cost of water KL 36.000 50.00 1800.00 M-189
d) Overhead charges @ 10 % on 2797.10
(a+b+c)
e) Contractor's profit @ 10 % on 3076.81
(a+b+c+d)
Cost for 150 cum= a+b+c+d+e 33844.91
Rate per cum =( a+b+c+d+e)/150 225.63
say 226.00
4.4 402 Lime Treated Soil for Sub- Base

Page 4 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Providing, laying and spreading soil on a
prepared sub grade, pulverising, mixing the
spread soil in place with rotavator with 3 per
cent slaked lime with minimum content of
70 per cent of CaO, grading with motor
grader and compacting with the road roller at
OMC to achieve at least 98 per cent of the
max dry density to form a layer of sub base.
Unit = cum
Taking output = 300 cum (525 tonnes)
a) Labour
Mate day 0.480 150.00 72.00 L-12
Mazdoor skilled day 2.000 125.00 250.00 L-15
Mazdoor day 10.000 100.00 1000.00 L-13
b) Machinery
Excavator 0.90 cum bucket capacity hour 6.000 700.00 4200.00 P&M-
Tipper for carriage of soil tonne.k 525 x L 1.85 9712.50 026
Lead
m =10 km
& P&M-
058
Add 10 per cent of cost of carriage to 971.25
cover cost of loading and unloading
Motor Grader 110 HP @ 50 cum per hour hour 6.000 1200.00 7200.00 P&M-
Vibratory roller 8 - 10 tonne hour 6.000 1000.00 6000.00 032
P&M-
Tractor with Rotavator and blade @ 25 hour 12.000 150.00 1800.00 059
P&M-
cum
Waterper hour 6 KL capacity
tanker hour 12.000 105.00 1260.00 054
P&M-
c) Material 060
Lime at site tonne 15.750 2400.00 37800.00 M-188
Cost of water KL 72.000 50.00 3600.00 M-189
d) Overhead charges @ 10 % on 7386.58
(a+b+c)
e) Contractor's profit @ 10 % on 8125.23
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e 89377.56
Rate per cum= (a+b+c+d+e)/300 297.93
say 298.00
4.5 403 Cement Treated Soil Sub Base/ Base
Providing, laying and spreading soil on a
prepared sub grade, pulverising, adding the
designed quantity of cement to the spread
soil, mixing in place with rotavator, grading
with the motor grader and compacting with
the road roller at OMC to achieve the desired
unconfined compressive strength and to form
a layer of sub-base/base.
Unit = cum
Taking output = 300 cum (525 tonnes)
For 4 per cent quantity of cement by
weight
a) of soil
Labour
Mate day 0.480 150.00 72.00 L-12
Mazdoor skilled day 2.000 125.00 250.00 L-15
Mazdoor day 10.000 100.00 1000.00 L-13
b) Machinery
Excavator 0.90 cum bucket capacity hour 6.000 700.00 4200.00 P&M-
Tipper for carriage of soil tonne.k 525 x L 1.85 9712.50 026
Lead
m =10 km
& P&M-
058
Add 10 per cent of cost of carriage to 971.25
cover cost of loading and unloading
Motor Grader 110 HP @ 50 cum per hour hour 6.000 1200.00 7200.00 P&M-
Vibratory roller 8 - 10 tonne hour 6.000 1000.00 6000.00 032
P&M-
Tractor with Rotavator and blade @ 25 hour 12.000 150.00 1800.00 059
P&M-
cum per
Water hour 6 KL capacity
tanker hour 12.000 105.00 1260.00 054
P&M-
c) Material 060

Page 5 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Cement at site (@ 4 per cent of 525 tonne 21.000 4180.00 87780.00 M-081
tonne)
Cost of water KL 72.000 50.00 3600.00 M-189
d) Overhead charges @ 10 % on 12384.58
(a+b+c)
e) Contractor's profit @ 10 % on 13623.03
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e ###
Rate per cum= (a+b+c+d+e)/300 499.51
say 500.00
4.6 403 Cement Treated Crushed Rock or
combination as per clause 403.2 and
table 400.4in
Providing, Sub
laying andbase/ BaseMaterial on a
spreading
prepared sub grade, adding the designed
quantity of cement to the spread Material,
mixing in place with rotavator, grading with
the motor grader and compacting with the
road roller at OMC to achieve the desired
unconfined compressive strength and to form
Unit = cum
Taking output = 300 cum (600 tonnes)
Quantity of cement assumed as 4 per
cent of quantity of crushed rock by
weight.
a) Labour
Mate day 0.480 150.00 72.00 L-12
Mazdoor skilled day 2.000 125.00 250.00 L-15
Mazdoor day 10.000 100.00 1000.00 L-13
b) Machinery
Motor Grader 110 HP @ 50 cum per hour hour 6.000 1200.00 7200.00 P&M-
Vibratory roller 8 - 10 tonne hour 6.000 1000.00 6000.00 032
P&M-
Tractor with Rotavator and blade @ 25 hour 12.000 150.00 1800.00 059
P&M-
cum per
Water hour 6 KL capacity
tanker hour 10.000 105.00 1050.00 054
P&M-
c) Material 060
Cement at site @ 4 per cent by weight of tonne 24.000 4180.00 ### M-081
crushed aggregate (600 tonne)
Grading of material for sub-base course
37.5 mm to 9.5 mm @ 55 per cent cum 211.200 200.00 42240.00 M-014
9.5 mm to 4.75 mm @ 20 per cent cum 76.800 200.00 15360.00 M-025
4.75 mm to 75 micron @ 25 per cent cum 96.000 200.00 19200.00 M-019
Cost of water KL 60.000 50.00 3000.00 M-189
or
Grading of material for Base course
37.5 mm to 9.5 mm @ 32.5 per cent cum 124.800 200.00 24960.00 M-028
9.5 mm to 4.75 mm @ 5 per cent cum 19.200 200.00 3840.00 M-025
4.75 mm to 75 micron @ 62.5 per cent cum 240.000 200.00 48000.00 M-023
Cost of water KL 60.000 50.00 3000.00 M-189
4.6 (i) For Sub-Base course
d) Overhead charges @ 10 % on 19749.20
(a+b+c)
e) Contractor's profit @ 10 % on 21724.12
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/300 796.55
say 797.00
4.6 (ii) For Base course
d) Overhead charges @ 10 % on 19749.20
(a+b+c)
e) Contractor's profit @ 10 % on 21724.12
(a+b+c+d)
Cost for 300 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/300 796.55
say 797.00
Note Quantities of aggregates provided under 'c'
above are uncompacted quantities.
4.7 404.3. Making 50 mm x 50 mm Furrows
1

Page 6 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Making 50 mm x 50 mm furrows, 25mm/
50mm deep, 450 to the center line of the
road and at one metre interval in the existing
thin bituminous wearing coarse including
sweeping and disposal of excavated material
within 1000 metres lead
Unit = sqm
Taking output = 30 m x 7 m = 210 sqm
(i) 25mm deep furrow cutting
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor day 2.000 100.00 200.00 L-13
b) Machinery
Tractor-trolley hour 0.200 150.00 30.00 P&M-
c) Overhead charges @ 10 % on 24.20 053
(a+b) Contractor's profit @ 10 % on
d) 26.62
(a+b+c)
Cost for 210 sqm= a+b+c+d 292.82
Rate per sqm =(a+b+c+d)/210 282.82
say 283.00
(ii) 50mm deep furrow cutting
a) Labour
Mate day 0.160 150.00 24.00 L-12
Mazdoor day 4.000 100.00 400.00 L-13
b) Machinery
Tractor-trolley hour 0.400 150.00 60.00 P&M-
c) Overhead charges @ 10 % on 48.40 053
(a+b)
d) Contractor's profit @ 10 % on 53.24
(a+b+c)
Cost for 210 sqm= a+b+c+d 585.64
Rate per sqm =(a+b+c+d)/210 575.64
say 576.00
4.8 404.3. Inverted Choke
2 Construction of inverted choke by providing,
laying, spreading and compacting screening
B type/ coarse sand of specified grade in
uniform layer on a prepared surface with
motor grader and compacting with power
Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.920 150.00 138.00 L-12
Mazdoor skilled day 2.000 125.00 250.00 L-15
Mazdoor day 21.000 100.00 2100.00 L-13
b) Machinery
Motor Grader 110 HP hour 6.000 1200.00 7200.00 P&M-
Vibratory roller 8-10 tonnes @ 60 cum hour 6.000 1000.00 6000.00 032
P&M-
per hour
Water tanker 6 KL capacity hour 18.000 105.00 1890.00 059
P&M-
c) Material 060
Screening type 'B' or coarse sand cum 720.000 160.00 ### M-004
Cost of water KL 108.000 50.00 5400.00 M-189
d) Overhead charges @ 10 % on 13817.80
(a+b+c)
e) Contractor's profit @ 10 % on 15199.58
(a+b+c+d)
Cost for 600 cum = a+b+c+d+e ###
Rate per cum = ( a+b+c+d+e)/600 278.66
say 279.00
4.9 404 Water Bound Macadam

Page 7 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Providing, laying, spreading and compacting
stone aggregates of specific sizes to water
bound macadam specification including
spreading in uniform thickness, hand
packing, rolling with 3 wheeled steel/
vibratory roller 8-10 tonnes in stages to
proper grade and camber, applying and
brooming requisite type of screening/ binding
Materials to fill up the interstices of coarse
aggregate, watering and compacting to the
required density.
A By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 10.080 150.00 1512.00 L-12
Mazdoor skilled day 2.000 125.00 250.00 L-15
Mazdoor day 250.000 100.00 25000.00 L-13
b) Machinery

Vibratory roller 8 - 10 tonne @ 60cum hour 6.000 1000.00 6000.00 P&M-


per hour or 059
Smooth 3 wheeled steel roller @ hour 12.000
30cum/hour
Water tanker 6 KL capacity hour 24.000 105.00 2520.00 P&M-
060
c) Material ( Refer table 400 - 7, 8 & 9 )
4.9A (i) Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum cum 435.600 325.00 ### M-039
per 10 sqm for compacted thickness of
100 mm
Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum 97.200 410.00 39852.00 M-052
cum per 10 sqm
OR
Crushable type such as Moorum or cum 108.000 130.00 14040.00 M-007
Gravel for grading-I @ 0.30 cum per 10
sqm
Binding material
Binding Material @ 0.08cum per 10 sqm cum 28.800 130.00 3744.00 M-007
for grading I material
Cost of water KL 144.000 50.00 7200.00 M-189
4.9A (a) Using Scrining Crushable type such as Moorum or Gravel
(i)
d) Overhead charges @ 10 % on 19809.20
(a+b+c)
e) Contractor's profit @ 10 % on 21790.12
(a+b+c+d)
Cost for 360 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/360 665.81
say 666.00
OR
4.9A (b) Using Scrining Type-A (13.2mm agg.)
(i)
d) Overhead charges @ 10 % on 22764.80
(a+b+c)
e) Contractor's profit @ 10 % on 25041.28
(a+b+c+d)
Cost for 360 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/360 765.15
say 765.00
4.9A (ii) Grading-II
Aggregate
Grading-II 63 mm to 45 mm /Grading-III cum 435.600 350.00 ### M-038
53 mm to 22.4 mm@ 0.91 cum per 10
sqm for compacted thickness of 75 mm

Page 8 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec.
Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum 57.600 410.00 23616.00 M-052
cum per 10 sqm
OR
Crushable type such as Moorum or cum 105.590 130.00 13726.70 M-007
Gravel for grading II &III @ 0.22 cum
per 10 sqm OR
Type B11.2 mm for grading-III @ 0.18 cum 86.400 410.00 35424.00 M-051
cum per 10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm cum 28.800 130.00 3744.00 M-007
for grading II material
Cost of water KL 144.000 50.00 7200.00 M-189
4.9A (a) Using Scrining Crushable type such as Moorum or Gravel
(ii)
d) Overhead charges @ 10 % on 20866.87
(a+b+c)
e) Contractor's profit @ 10 % on 22953.56
(a+b+c+d)
Cost for 360 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/360 701.36
say 701.00
OR
4.9A (b) Using Scrining Type-A (13.2mm agg.)
(ii)
d) Overhead charges @ 10 % on 22230.20
(a+b+c)
e) Contractor's profit @ 10 % on 24453.22
(a+b+c+d)
Cost for 360 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/360 747.18
say 747.00
4.9A (c) Using Scrining Type-B (11.2mm agg.)
(ii)
d) Overhead charges @ 10 % on 23411.00
(a+b+c)
e) Contractor's profit @ 10 % on 25752.10
(a+b+c+d)
Cost for 360 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/360 786.87
say 787.00
4.9A (iii) Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum 435.600 410.00 ### M-036
cum per 10 sqm for compacted thickness
of 75 mm
Stone Screening
Type B 11.2 mm for grading-III @ 0.18 cum 86.400 410.00 35424.00 M-051
cum per 10 sqm
OR
Crushable type such as Moorum or cum 105.590 130.00 13726.70 M-007
Gravel for grading II &III @ 0.22 cum per
10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm cum 28.800 130.00 3744.00 M-007
for grading II material
Cost of water KL 144.000 50.00 7200.00 M-189
4.9A (a) Using Scrining Crushable type such as Moorum or Gravel
(iii)
d) Overhead charges @ 10 % on 23480.47
(a+b+c)
e) Contractor's profit @ 10 % on 25828.52
(a+b+c+d)
Cost for 360 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/360 789.20
say 789.00

Page 9 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. OR
4.9A (b) Using Scrining Type-B (11.2mm agg.)
(iii)
d) Overhead charges @ 10 % on 26024.60
(a+b+c)
e) Contractor's profit @ 10 % on 28627.06
(a+b+c+d)
Cost for 360 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/360 874.72
say 875.00
( Anyone of the aggregate grading, screening
and binding material may be used as per
4.9 B design)
By Mechanical Means:
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.680 150.00 102.00 L-12
Mazdoor skilled day 2.000 125.00 250.00 L-15
Mazdoor day 15.000 100.00 1500.00 L-13
b) Machinery
Motor grader 110 HP @ 50cum/hr. for hour 7.200 1200.00 8640.00 P&M-
spreading
Vibratory roller 8-10 tonnes @ 60cum/hr. hour 6.000 1000.00 6000.00 032
P&M-
or 059
Smooth 3 wheeled steel roller @ hour 12.000
30cum/hr.
Water tanker 6 KL capacity hour 24.000 105.00 2520.00 P&M-
060
c) Material ( Refer table 400 - 7, 8 & 9 )
4.9B (i) Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum cum 435.600 325.00 ### M-039
per 10 sqm for compacted thickness of
100 mm
Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum 97.200 410.00 39852.00 M-052
cum per 10 sqm
OR
Crushable type such as Moorum or cum 108.000 130.00 14040.00 M-007
Gravel for grading-I @ 0.30 cum per 10
sqm
Binding material
Binding Material @ 0.08cum per 10 sqm cum 28.800 130.00 3744.00 M-007
for grading I material
Cost of water KL 144.000 50.00 7200.00 M-189
4.9B (a) Using Scrining Crushable type such as Moorum or Gravel
(i)
d) Overhead charges @ 10 % on 18182.20
(a+b+c)
e) Contractor's profit @ 10 % on 20000.42
(a+b+c+d)
Cost for 360 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/360 611.12
say 611.00
OR
4.9B (b) Using Scrining Type-A (13.2mm agg.)
(i)
d) Overhead charges @ 10 % on 21137.80
(a+b+c)
e) Contractor's profit @ 10 % on 23251.58
(a+b+c+d)
Cost for 360 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/360 710.46
say 710.00
4.9B (ii) Grading-II
Aggregate

Page 10 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Grading-II 63 mm to 45 mm /Grading-III cum 435.600 350.00 ### M-038
53 mm to 22.4 mm@ 0.91 cum per 10
sqm for compacted thickness of 75 mm

Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum 57.600 410.00 23616.00 M-052
cum per 10 sqm
OR
Crushable type such as Moorum or cum 105.590 130.00 13726.70 M-007
Gravel for grading II &III @ 0.22 cum
per 10 sqm OR
Type B11.2 mm for grading-III @ 0.18 cum 86.400 410.00 35424.00 M-051
cum per 10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm cum 28.800 130.00 3744.00 M-007
for grading II material
Cost of water KL 144.000 50.00 7200.00 M-189
4.9B (a) Using Scrining Crushable type such as Moorum or Gravel
(ii)
d) Overhead charges @ 10 % on 19239.87
(a+b+c)
e) Contractor's profit @ 10 % on 21163.86
(a+b+c+d)
Cost for 360 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/360 646.67
say 647.00
OR
4.9B (b) Using Scrining Type-A (13.2mm agg.)
(ii)
d) Overhead charges @ 10 % on 20603.20
(a+b+c)
e) Contractor's profit @ 10 % on 22663.52
(a+b+c+d)
Cost for 360 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/360 692.50
say 692.00
4.9B (c) Using Scrining Type-B (11.2mm agg.)
(ii)
d) Overhead charges @ 10 % on 21784.00
(a+b+c)
e) Contractor's profit @ 10 % on 23962.40
(a+b+c+d)
Cost for 360 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/360 732.18
say 732.00
4.9B (iii) Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum 435.600 410.00 ### M-036
cum per 10 sqm for compacted thickness
of 75 mm
Stone Screening
Type B11.2 mm for grading-III @ 0.18 cum 86.400 410.00 35424.00 M-051
cum per 10 sqm
OR
Crushable type such as Moorum or cum 105.590 130.00 13726.70 M-007
Gravel for grading II &III @ 0.22 cum per
10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm cum 28.800 130.00 3744.00 M-007
for grading II material
Cost of water KL 144.000 50.00 7200.00 M-189
4.9B (a) Using Scrining Crushable type such as Moorum or Gravel
(iii)
d) Overhead charges @ 10 % on 21853.47
(a+b+c)
e) Contractor's profit @ 10 % on 24038.82
(a+b+c+d)
Cost for 360 cum = a+b+c+d+e ###

Page 11 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Rate per cum = (a+b+c+d+e)/360 734.52
say 735.00
OR
4.9B (b) Using Scrining Type-B (11.2mm agg.)
(iii)
d) Overhead charges @ 10 % on 24397.60
(a+b+c)
e) Contractor's profit @ 10 % on 26837.36
(a+b+c+d)
Cost for 360 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/360 820.03
say 820.00
Note As three wheeled smooth rollers are also
very commonly used, the same has been
4.10 405 provided
Crushed asCement
an alternative.
Concrete Sub-base /
Base
Breaking and crushing of material obtained
by breaking damaged cement concrete slabs
to size range not exceeding 75 mm as
specified in table 400.7 transporting the
aggregates obtained from breaking of
cement concrete slabs at a lead of L km.,
laying and compacting the same as sub base/
base course, constructed as WBM to clause
404 except the use of screening or binding
Material.
Unit = cum
Taking output =360 cum
a) Labour
Mate day 4.160 150.00 624.00 L-12
Mazdoor skilled day 2.000 125.00 250.00 L-15
Mazdoor for crushing broken cement day 102.000 100.00 10200.00 L-13
concrete pavement/slabs into aggregate
b) Machinery
Motor Grader,110 HP @ 50 cum/hr. hour 6.000 1200.00 7200.00 P&M-
Vibratory roller 8 - 10 tonne@ 60 cum hour 6.000 1000.00 6000.00 032
P&M-
per hour or 059
Smooth 3 wheeled steel roller @ hour 12.000
30cum/hr.
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-
Tipper 10 tonne capacity tonne.k 720 x L 1.85 26640.00 017
Lead
m =20 km
& P&M-
058
Add 10 per cent of cost of carriage to 2664.00
cover cost of loading and unloading
Water tanker 6 KL capacity with 5 km hour 12.000 105.00 1260.00 P&M-
lead @ 1 trip per hour 060
c) Material
Material available from dismantled concrete
slab after crushing / breaking and only
carriage is required to be provided
Cost of water KL 72.000 50.00 3600.00 M-189
d) Overhead charges @ 10 % on 6263.80
(a+b+c)
e) Contractor's profit @ 10 % on 6890.18
(a+b+c+d)
Cost for 360 cum = a+b+c+d+e 75791.98
Rate per cum = (a+b+c+d+e)/360 210.53
say 211.00
Note 1. It is assumed that dismantling of concrete
slab/pavement has been considered
separately. Hence same is not added in this
analysis. Only labour for crushing the
dismantled slab into aggregate has been
added. Carriage from stock pile to work site
has been provided with a lead of L km.
2. In case of breaking of slabs is done locally
without involvement of transportation, the
provision of tipper, front end loader and
loading/unloading charges may be deleted.

Page 12 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 3. As three wheeled smooth steel rollers are
commonly in use, the same has been
4.11 405.2 provided as an Coat
Penetration alternative.
Over Top Layer of
Crushed Cement Concrete Base
Spraying of bitumen over cleaned dry surface
of crushed cement concrete base at the rate
of 25 kg per 10 sqm by a bitumen pressure
distributor, spreading of key aggregates at
the rate of 0.13 cum per 10 sqm by a
mechanical gritter and rolling the surface as
per clause 506.3.8
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate day 0.560 150.00 84.00 L-12
Mazdoor skilled day 2.000 125.00 250.00 L-15
Mazdoor day 12.000 100.00 1200.00 L-13
b) Machinery
Mechanical broom hydraulic @ 1250 sqm hour 6.000 150.00 900.00 P&M-
per hour self propelled chips spreader
Hydraulic hour 6.000 1200.00 7200.00 031
P&M-
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 025
P&M-
Tipper 10 tonne capacity hour 6.000 185.00 1110.00 017
P&M-
Vibratory roller 8 -10 tonnes @ 30 cum hour6.00x0.65* 1000.00 3900.00 048
P&M-
per hour pressure distributor @ 1750
Bitumen hour 4.280 580.00 2482.40 059
P&M-
c) sqm per hour
Material 004
Crushed stone aggregate 11.2 mm size cum 97.500 410.00 39975.00 M-051
Bitumen (60-70 grade) tonne 0.250 27030.00 6757.50 M-074
d) Overhead charges @ 10 % on 6805.89
(a+b+c)
e) Contractor's profit @ 10 % on 7486.48
(a+b+c+d)
Cost for 7500 sqm = a+b+c+d+e 82351.27
Rate per sqm = (a+b+c+d+e)/7500 10.98
say 11.00
Note Though vibratory roller is required only for 3
hours as per norms, the same is required to
be available at site for 6 hours to match with
other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65.
4.12 406 Wet Mix Macadam
Providing, laying, spreading and compacting
graded stone aggregate to wet mix macadam
specification including premixing the Material
with water at OMC in mechanical mix plant
carriage of mixed Material by tipper to site,
laying in uniform layers with paver in sub-
base / base course on well prepared surface
and compacting with vibratory roller to
achieve the desired density.
Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate day 0.480 150.00 72.00 L-12
Mazdoor skilled day 2.000 125.00 250.00 L-15
Mazdoor day 10.000 100.00 1000.00 L-13
b) Machinery
Wet mix plant of 75 tonne hourly hour 6.600 800.00 5280.00 P&M-
capacitygenerator 125 KVA
Electric hour 6.000 650.00 3900.00 094
P&M-
Front end loader 1 cum capacity hour 6.000 700.00 4200.00 018
P&M-
Paver finisher hour 6.000 580.00 3480.00 017
P&M-
Vibratory roller 8 - 10 tonne hour 6x0.65 1000.00 3900.00 035
P&M-
or 059
Smooth 3 wheeled steel roller @ 8-10 hour 12.000
tonnes.
Water tanker 6 KL capacity hour 3.000 105.00 315.00 P&M-
060

Page 13 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Tipper tonne.k 495 x L 1.85 18315.00 Lead
m =20 km
& P&M-
058
Add 10 per cent of cost of carriage to 1831.50
cover cost of loading and unloading
c) Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent cum 89.100 410.00 36531.00 M-034
22.4 mm to 2.36 mm @ 40 per cent cum 118.800 410.00 48708.00 M-031
2.36 mm to 75 micron@ 30 per cent cum 89.100 200.00 17820.00 M-022
Cost of water KL 18.000 50.00 900.00 M-189
d) Overhead charges @ 10 % on 14650.25
(a+b+c)
e) Contractor's profit @ 10 % on 16115.28
(a+b+c+d)
Cost for 225 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/225 787.86
say 788.00
Note 1. Though vibratory roller is required only for
3 hours as per norms, the same is required to
be available at site for 6 hours to match with
other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65
2. As three wheeled smooth steel rollers are
commonly in use, the same has been
provided as an alternative which can be used
if the thickness of individual layer does not
exceed 100 mm..
4.13 407 Construction of Median and Island with
Soil Taken from Roadway Cutting
Construction of Median and Island above
road level with approved material deposited
at site from roadway cutting and excavation
for drain and foundation of other structures,
spread, graded and compacted as per clause
407
Unit = cum
Taking output =21 cum
a) Labour
Mate day 0.240 150.00 36.00 L-12
Mazdoor day 6.000 100.00 600.00 L-13
b) Machinery
Water tanker 6 KL with 5 km lead and 1 hour 1.000 105.00 105.00 P&M-
trip
Plateper hour
compactor @ 3.5 cum per hour hour 6.000 75.00 450.00 060
P&M-
c) Material 086
Cost of water KL 6.000 50.00 300.00 M-189
d) Overhead charges @ 10 % on 149.10
(a+b+c)
e) Contractor's profit @ 10 % on 164.01
(a+b+c+d)
Cost for 21 cum = a+b+c+d+e 1804.11
Rate per cum = (a+b+c+d+e)/21 85.91
say 86.00
Note This analysis provides for median and island
with earthen top. In case the surface is
required to be turfed or planted with shrubs,
the same is required to be provided
separately as per analysis given in the
chapter on horticulture. In case granular fill is
required to be paved, quantities of paving
are required to be calculated as per
4.14 407 approved design
Construction ofand paid separately.
Median and Island with
Soil Taken from Borrow Areas
Construction of median and Island above
road level with approved material brought
from borrow pits, spread, sloped and
compacted as per clause 407
Unit = cum
Taking output = 21 cum
a) Labour

Page 14 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Mate day 0.160 150.00 24.00 L-12
Mazdoor day 4.000 100.00 400.00 L-13
b) Machinery
Water tanker with 5 km lead hour 1.000 105.00 105.00 P&M-
Plate Compactor @ 3.5 cum per hour hour 6.000 75.00 450.00 060
P&M-
Hydraulic Excavator1.0 cum bucket hour 0.500 700.00 350.00 086
P&M-
capacity @60 cum per hour 026
Tipper 10 tonne capacity tonne.k 52.5 x L 1.85 971.25 Lead
m =10 km
& P&M-
058
Add 10 per cent of cost of 97.13
transportation to cover cost of loading
and
c) unloading
Material
Cost of water KL 6.000 50.00 300.00 M-189
d) Overhead charges @ 10 % on 269.74
(a+b+c)
e) Contractor's profit @ 10 % on 296.71
(a+b+c+d)
Cost for 21 cum = a+b+c+d+e 3263.82
Rate per cum = (a+b+c+d+e)/ 21 155.42
say 155.00
Note This analysis provides for median and island
with earthen top. In case the surface is
required to be turfed or planted with shrubs,
the same is required to be provided
separately as per analysis given in the
chapter on horticulture. In case surface finish
is of hard type, the same may be provided
separately as per approved design.
4.15 Construction of Shoulders
A. Earthen Shoulders
The rate as applicable for sub-grade
construction may be adopted.
B. Hard Shoulders
Rate as applicable for sub-base and or base
may be adopted as per approved design.
C. Paved shoulders
The rate may be adopted as applicable for
different layers of pavement depending upon
approved design of paved shoulders.
4.16 409 Footpaths and Separators
Construction of footpath/separator by
providing a 150 mm compacted granular sub
base as per clause 401 and 25 mm thick
cement concrete grade M15, over laid with
pre-cast concrete tiles in cement mortar 1:3
including provision of all drainage
arrangements but excluding kerb channel..
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 1.360 150.00 204.00 L-12
Mason day 4.000 250.00 1000.00 L-11
Mazdoor day 30.000 100.00 3000.00 L-13
b) Machinery
Vibratory road roller 8 -10 tonnes @60 hour 0.750 1000.00 750.00 P&M-
cum per
Water hour 6 KL capacity @ 1 trip per
tanker hour 2.000 105.00 210.00 059
P&M-
hour
Concrete mixer 0.4/0.28 cum per hour hour 6.000 100.00 600.00 060
P&M-
c) Material 009
i) For Granular sub base material
53 mm to 26.5 mm @ 35 per cent cum 20.790 200.00 4158.00 M-029
26.5 mm to 4.75 mm @ 45 per cent cum 26.730 200.00 5346.00 M-026
2.36 mm below @ 20 per cent cum 11.880 200.00 2376.00 M-022
ii) For cement concrete grade M157.5
cum
Page 15 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Aggregate 12 mm crushed @ 0.9 cum of cum 6.750 410.00 2767.50 M-052
concrete
Sand @ 0.45 cum/cum of concrete cum 3.380 350.00 1183.00 M-005
Cement tonne 1.880 4180.00 7858.40 M-081
iii) For cement plaster 1:3
Sand cum 3.840 350.00 1344.00 M-005
Cement tonne 1.830 4180.00 7649.40 M-081
iv) Pre-cast cement concrete tiles
Tiles size 300 x 300 mm and 25 mm thick each 3300.000 8.00 26400.00 M-184
v) RCC pipes
Pipes 200 mm dia,2.5 m long for drainage metre 22.500 30.00 675.00 M-137
vi) Cost of water KL 12.000 50.00 600.00 M-189
d) Overhead charges @ 10 % on 6612.13
(a+b+c)
e) Contractor's profit @ 10 % on 7273.34
(a+b+c+d)
Cost for 300 sqm = a+b+c+d+e 80006.77
Rate per sqm = (a+b+c+d+e)/300 266.69
say 267.00
4.17 410 Crusher Run Macadam Base
Providing crushed stone aggregate,
depositing on a prepared surface by hauling
vehicles, spreading and mixing with a motor
grader, watering and compacting with a
vibratory roller to clause 410 to form a layer
of sub-base/Base
Unit = cum
Taking output = 360 cum
A By Mix in Place Method
a) Labour
Mate day 0.480 150.00 72.00 L-12
Mazdoor skilled day 2.000 125.00 250.00 L-15
Mazdoor day 10.000 100.00 1000.00 L-13
b) Machinery
Tractor attached with rotavator @ 25 hour 12.000 150.00 1800.00 P&M-
cum
Motorper hour 110 HP
grader hour 6.000 1200.00 7200.00 054
P&M-
Vibratory roller 8 -10 tonnes @ 60 cum hour 6.000 1000.00 6000.00 032
P&M-
per hour
Water tanker 6 KL capacity hour 6.000 105.00 630.00 059
P&M-
c) Material 060
Aggregate at site
i) For 53 mm maximum size
63 mm to 45 mm @ 33 per cent cum 157.460 350.00 55111.00 M-038
22.5 mm to 5.6 mm@ 32 per cent cum 151.060 410.00 61934.60 M-032
Below 5.6 mm @ 35 per cent cum 166.680 300.00 50004.00 M-030
Cost of water KL 36.000 50.00 1800.00 M-189
Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent cum 24.120 410.00 9889.20 M-034
22.4 mm to 5.6 mm@ 50 per cent cum 237.600 410.00 97416.00 M-032
Below 5.6 mm@ 45 per cent cum 213.480 300.00 64044.00 M-030
Cost of water KL 36.000 50.00 1800.00 M-189
4.17 (i) For 53 mm maximum size
A d) Overhead charges @ 10 % on 18580.16
(a+b+c)
e) Contractor's profit @ 10 % on 20438.18
(a+b+c+d)
Cost for 360.0cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/360 624.50
or say 624.00
4.17 (ii) For 45 mm maximum size
A d) Overhead charges @ 10 % on 19010.12
(a+b+c)
e) Contractor's profit @ 10 % on 20911.13
(a+b+c+d)
Cost for 360.0cum = a+b+c+d+e ###

Page 16 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Rate per cum = (a+b+c+d+e)/360 638.95
say 639.00
Note Any one of the aggregate grading may be
4.17 B adopted
By Mixing Plant :
Unit = cum
Taking output = 225 cum (450 tonnes)
a) Labour
Mate day 0.280 150.00 42.00 L-12
Mazdoor skilled day 1.000 125.00 125.00 L-15
Mazdoor day 6.000 100.00 600.00 L-13
b) Machinery
Wet mix plant @ 75 tonne per hour hour 6.000 1000.00 6000.00 P&M-
Electric generator 125 KVA hour 6.000 650.00 3900.00 093
P&M-
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 018
P&M-
Motor grader 110 HP hour 6.000 1200.00 7200.00 017
P&M-
Vibratory roller 8 - 10 tonne hour 6.000 1000.00 6000.00 032
P&M-
Water tanker 6 KL capacity hour 3.000 105.00 315.00 059
P&M-
Tipper 10 tonne capacity tonne.k 450 x L 1.85 16650.00 060
Lead
m =20 km
& P&M-
058
Add 10 per cent of cost of carriage to 1665.00
cover cost of loading and unloading
c) Material
Aggregate at site
i) For 53 mm maximum size
63 mm to 45 mm @ 33 per cent cum 98.400 350.00 34440.00 M-038
22.5 mm to 5.6 mm@ 32 per cent cum 94.410 410.00 38708.10 M-032
Below 5.6 mm @ 35 per cent cum 104.180 300.00 31254.00 M-030
Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent cum 15.060 410.00 6174.60 M-034
22.4 mm to 5.6 mm@ 50 per cent cum 148.500 410.00 60885.00 M-032
Below 5.6 mm@ 45 per cent cum 133.430 300.00 40029.00 M-030
Cost of water KL 18.000 50.00 900.00 M-189
4.17 (i) For 53 mm maximum size
B d) Overhead charges @ 10 % on 15109.91
(a+b+c)
e) Contractor's profit @ 10 % on 16620.90
(a+b+c+d)
Cost for 225cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/225 812.58
say 813.00
4.17 (ii) For 45 mm maximum size
B d) Overhead charges @ 10 % on 15468.56
(a+b+c)
e) Contractor's profit @ 10 % on 17015.42
(a+b+c+d)
Cost for 360.0cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/360 519.92
say 520.00
4.18 Sugge Lime, Flyash Stabilised Soil Sub-Base
stive

Page 17 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Construction of Sub-base using lime - Flyash
admixture with granular soil, free from
organic matter/ deleterious material or
clayey silts and low plasticity clays having PI
between 5 and 20 and liquid limit less than
25 and commercial dry lime, slaked at site or
pre-slaked with CaO content not less than 50
per cent, Flyash to conform to gradation as
per clause 4.3 of IRC: 88-1984, lime + Flyash
content ranging between 10 to 30 per cent,
the minimum un-confined compressive
strength and CBR value after 28 days curing
and 4 days soaking to be 7.5kg/sq, cm and
25 per cent respectively, all as specified in
Unit = cum
Taking output = 480 cum (720 tonnes,
density 1.50 t/cum)
Assumptions made
Total mass taken for analysis = 720 t
Lime + Flyash admixture @ 20 per cent =
0.2 x 720=144 t
Soil = 720 -144 = 576 t
576 /1.6 = 360 cum
Lime + Flyash = 144 t
Ratio Lime 4 : Flyash 16
Lime = 29 kg.
Flyash = 115 kg.
a) Labour
Mate day 0.240 150.00 36.00 L-12
Mazdoor day 6.000 100.00 600.00 L-13
Mazdoor (Skilled) day 1.000 125.00 125.00 L-15
b) Machinery
Hydraulic Excavator 0.90 cum bucket hour 6.000 700.00 4200.00 P&M-
capacity @ 60cum/hr. for 360 cum soil 026
Tipper 10T capacity for carriage of soil tonne.k 576 x L 1.85 10693.00 Lead
576 tonnes m =10 km
& P&M-
058
Tipper 10T capacity for carriage of 115 tonne.k 115 x L 1.85 2127.50 Lead
tonnes Flyash m =10 km
& P&M-
058
Tipper 10T capacity for carriage of 29 hour 3.000 185.00 555.00 P&M-
tonnes of lime from store to work site 048
Add 10 per cent of cost of carriage to 55.50
cover cost of loading and unloading
Tractor with disc harrows for hour 6.000 150.00 900.00 P&M-
pulverisation
Motor Grader 110 HP @ 50 cum per hour hour 9.600 1200.00 11520.00 053
P&M-
for mixing in-place and grading 032
Vibratory roller 8 - 10 tonne hour 6.000 1000.00 6000.00 P&M-
Water tanker 6 KL capacity hour 12.000 105.00 1260.00 059
P&M-
c) Material 060
Slaked Lime tonne 29.000 2400.00 69600.00 M-188
Compensation for earth taken from cum 360.000 45.00 16200.00 M-092
d) private sourcecharges @ 10 % on
Overhead 12387.20
(a+b+c)
e) Contractor's profit @ 10 % on 13625.92
(a+b+c+d)
Cost for 480 cum = a+b+c+d+e ###
Rate per cum= (a+b+c+d+e)/480 312.26
say 312.00
Note 1.Compensation for earth will vary from place
to place and will have to be assessed
realistically as per particular ground
situation. In case earth is available from
Govt. land, compensation for earth will not be
required. The position is required to be
clearly stated in the cost estimate.

Page 18 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 2.Cost of Flyash has not been considered as
same will be available free of cost. Only
carriage of Flyash has been provided.
3.Lime + Flyash has been taken as 20 per
cent of total mass and ratio of lime and
Flyash as 1:4 for estimating purposes. Total
quantities will be as per approved design.

Page 19 of 361
CHAPTER - 5
Ref. BASES AND SURFACE COURSES (BITUMINOUS)
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
5.1 Spec.
502 Prime Coat
Providing and applying primer coat
with bitumen emulsion on prepared
surface of granular Base including
clearing of road surface and spraying
primer at the rate of 0.60 kg/sqm
using mechanical means.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor day 2.000 100.00 200.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour 2.800 150.00 420.00 P&M-031
hour
Air compressor 250 cfm hour 2.800 150.00 420.00 P&M-001
Bitumen pressure distributor @ 1750 hour 2.000 580.00 1160.00 P&M-004
sqm
Waterper hour 6 KL capacity @ 1 trip per
tanker hour 1.000 105.00 105.00 P&M-060
c) hour
Material
Bitumen emulsion @ 0.6 kg per sqm tonne 2.100 24000.00 50400.00 M-077
Cost of water KL 6.000 50.00 300.00 M-189
d) Overhead charges @ 10 % on 5301.70
(a+b+c)
e) Contractor's profit @ 10 % on 5831.87
(a+b+c+d)
Cost for 3500 sqm = a+b+c+d+e 64150.57
Rate per sqm = (a+b+c+d+e)/3500 18.33
say 18.00
Note Bitumen primer has been provided @ 0.60
kg per sqm as per clause 502.8. Payment
shall be made with adjustment, plus or
minus, for the variation between this
quantity and the actual quantity approved
by the Engineer after the preliminary trials
referred to in clause No. 502.4.3.
5.2 503 Tack Coat
Providing and applying tack coat with
bitumen emulsion using emulsion pressure
distributor at the rate of 0.20 kg per sqm on
the prepared bituminous/granular surface
cleaned with mechanical broom.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor day 2.000 100.00 200.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour 2.800 150.00 420.00 P&M-031
hour
Air compressor 250 cfm hour 2.800 150.00 420.00 P&M-001
Emulsion pressure distributor @ 1750 hour 2.000 580.00 1160.00 P&M-004
sqm per hour
c) Material
Bitumen emulsion @ 0.2 kg per sqm tonne 0.700 24000.00 16800.00 M-077
d) Overhead charges @ 10 % on 1901.20
(a+b+c)
e) Contractor's profit @ 10 % on 2091.32
(a+b+c+d)
Cost for 3500 sqm = a+b+c+d+e 23004.52
Rate per sqm = (a+b+c+d+e)/3500 6.57
say 7.00
Note 1. Bitumen emulsion has been provided @
0.20 kg per sqm as per clause 503.8.
Payment shall be made with adjustment,
plus or minus, for the variation between this
quantity and actual quantity approved by
the Engineer after preliminary trials
2. An output of 3500 sqm has been
considered in case of prime coat and tack
coat which can be covered by bituminous
courses on the same day.
5.3 504 Bituminous Macadam

Page 1 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Providing and laying bituminous macadam
with 100-120 TPH hot mix plant producing
an average output of 75 tonnes per hour
using crushed aggregates of specified
grading premixed with bituminous binder,
transported to site, laid over a previously
prepared surface with paver finisher to the
required grade, level and alignment and
rolled as per clauses 501.6 and 501.7 to
achieve the desired compaction
Unit = cum
Taking output = 205 cum (450 tonnes)
a) Labour
Mate day 0.840 150.00 126.00 L-12
Mazdoor working with HMP, mechanical day 16.000 100.00 1600.00 L-13
broom, paver, roller, asphalt cutter and
assistance for setting out lines, levels
and layout of construction
Skilled mazdoor for checking line & day 5.000 125.00 625.00 L-15
b) levels
Machinery
Batch mix HMP 100-120 TPH @ 75 hour 6.000 6900.00 41400.00 P&M-021
tonne per hour actual output
Mechanical broom hydraulic @ 1250 hour 2.200 150.00 330.00 P&M-031
sqm per hour
Air compressor 250 cfm hour 2.200 150.00 330.00 P&M-001
Paver finisher hydrostatic with sensor hour 6.000 1500.00 9000.00 P&M-034
control @ 75 cum per hour
Generator 250 KVA hour 6.000 750.00 4500.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017
Tipper 10 tonne capacity tonne.k 450 x L 1.85 16650.00 Lead =20
m km & P&M-
Add 10 per cent of cost of carriage to 1665.00 058
cover cost of loading and unloading
Smooth wheeled roller 8-10 tonnes for hour6.00x0.65* 170.00 663.00 P&M-044
initial break down rolling.
Vibratory roller 8 tonnes for hour6.00x0.65* 1000.00 3900.00 P&M-059
intermediate rolling.
Finish rolling with 6-8 tonnes smooth hour6.00x0.65* 700.00 2730.00 P&M-045
wheeled tandem roller.
c) Material
i) Bitumen@ 3.3 per cent of mix tonne 14.850 27030.00 401395.50 M-074
weight of mix = 205 x 2.2 = 450 tonne
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes
Weight of aggregate = 450 -14.85 = 435.15
tonnes
Taking density of aggregate = 1.5
ton/cum
Volume of aggregate = 290.1 cum
*Grading I ( 40 mm nominal size )
37.5 - 25 mm 15 per cent cum 43.510 370.00 16098.70 M-049
25 - 10 mm 45 per cent cum 130.550 410.00 53525.50 M-046
10 - 5 mm 25 per cent cum 72.530 410.00 29737.30 M-040
5 mm and below15 per cent cum 43.510 300.00 13053.00 M-030
or
GradingII(19 mm nominal size)
25 - 10 mm 40 per cent cum 116.040 410.00 47576.40 M-046
10 - 5 mm 40 per cent cum 116.040 410.00 47576.40 M-040
5 mm and below 20 per cent cum 58.020 300.00 17406.00 M-030
* Any one of the alternative may be
adopted as per approved design
(i) for Grading I ( 40 mm nominal size )
d) Overhead charges @ 10 % on 60152.90
(a+b+c)
e) Contractor's profit @ 10 % on 66168.19
(a+b+c+d)
Cost for 205 cum = a+b+c+d+e 727850.09

Page 2 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Rate per cum = (a+b+c+d+e)/205 (For 3550.49
Grading I) say 3550.00
(ii) for GradingII(19 mm nominal size)
d) Overhead charges @ 10 % on 60167.33
(a+b+c)
e) Contractor's profit @ 10 % on 66184.06
(a+b+c+d)
Cost for 205 cum = a+b+c+d+e 728024.69
Rate per cum = (a+b+c+d+e)/205 (For 3551.34
Grading-II) say 3551.00
Note *1. Although the rollers are required only
for 3 hours as per norms of output, but the
same have to be available at site for six
hours as the hot mix plant and paver will
take six hours for mixing and paving the
output of 450 tonnes considered in this
analysis. To cater for the idle period of
these rollers, their usage rates have been
multiplied
2.Quantity by
of aBitumen
factor of has
0.65.been taken for
analysis purpose. The actual quantity will
depend upon job mix formula.
3. Labour for traffic control, watch and ward
and other miscellaneous duties at site
including sundries have been included in
administrative overheads of the contractor.
4. In case BM is laid over freshly laid tack
coat, provision of Mechanical broom and 2
mazdoors for the same shall be deleted as
the same has been included in the cost of
tack coat.
5.4 505 Bituminous Penetration Macadam
Construction of penetration macadam over
prepared Base by providing a layer of
compacted crushed coarse aggregate using
chips spreader with alternate applications
of bituminous binder and key aggregates
and rolling with a smooth wheeled steel
roller 8-10 tonne capacity to achieve the
desired degree of compaction
A 50 mm thick
Unit = sqm
Taking output = 4500 sqm (225 cum)
a) Labour
Mate day 0.320 150.00 48.00 L-12
Mazdoor including for brooming of key day 6.000 100.00 600.00 L-13
aggregates
Mazdoor skilled day 2.000 125.00 250.00 L-15
b) Machinery
Hydraulic self propelled chip spreader hour 6.000 1200.00 7200.00 P&M-025
both for aggregates and key
aggregates@ 1500 sqm per hour for
4500 x 2 sqm = 9000 sqm
Bitumen pressure distributor for @ 1750 hour 2.570 580.00 1490.60 P&M-004
sqm per hour
Tipper 5.5 cum capacity for carriage of hour 10.000 185.00 1850.00 P&M-048
aggregates from stockpile to chip
spreader
Vibratory roller 8 tonnes hour 6.000 1000.00 6000.00 P&M-059
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017
c) Material
Bitumen@ 5 kg per sqm tonne 22.500 27030.00 608175.00 M-074
Crushed stone coarse aggregate cum 270.000 410.00 110700.00 M-033
passing 45 mm and retained on 2.8 mm
sieve @ 0.06 cum per sqm
Key aggregates passing 22.4 mm and cum 67.500 410.00 27675.00 M-031
retained on 2.8 mm sieve @ 0.015 cum
d) perOverhead
sqm charges @ 10 % on 76818.86
(a+b+c)
e) Contractor's profit @ 10 % on 84500.75
(a+b+c+d)
Cost for 4500 sqm = a+b+c+d+e 929508.21

Page 3 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Rate per sqm = (a+b+c+d+e)/4500 206.56
say 207.00
Note 2 tippers will be needed to match the
capacity of chip spreader and front end
5.4 B loader.
75 mm thick
Unit = sqm
Taking output = 4500 sqm (337.5 cum
compacted).
a) Labour
Mate day 0.400 150.00 60.00 L-12
Mazdoor including for brooming of key day 8.000 100.00 800.00 L-13
aggregates
Mazdoor skilled day 2.000 125.00 250.00 L-15
b) Machinery
Hydraulic self propelled chip spreader hour 6.000 1200.00 7200.00 P&M-025
both for aggregates and key
aggregates@ 1500 sqm per hour for
4500 x 2 sqm
Bitumen pressure distributor for@ 1750 hour 2.570 580.00 1490.60 P&M-004
sqm per hour
Tipper 5.5 cum capacity for carriage of hour 10.000 185.00 1850.00 P&M-048
aggregates from stockpile to chip
spreader
Vibratory roller 8 tonnes hour 6.000 1000.00 6000.00 P&M-059
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017
c) Material
Bitumen@ 6.8 kg per sqm tonne 30.600 27030.00 827118.00 M-074
Crushed stone coarse aggregate (loose cum 405.000 410.00 166050.00 M-037
passing 63 mm and retained on 2.8 mm
sieve @ 0.09 cum per sqm
Key aggregates passing 26.5 mm and cum 81.000 200.00 16200.00 M-026
retained on 2.8 mm sieve @ 0.018 cum
d) perOverhead
sqm charges @ 10 % on 103121.86
(a+b+c)
e) Contractor's profit @ 10 % on 113434.05
(a+b+c+d)
Cost for 4500 sqm = a+b+c+d+e ###
Rate per sqm = (a+b+c+d+e)/4500 277.28
say 277.00
Note 2 tippers and 2 rollers will be needed to
match the capacity of chip spreader and
5.5 506 front end loader. Grout
Built-up-Spray
Providing, laying and rolling of built-up-
spray grout layer over prepared base
consisting of a two layer composite
construction of compacted crushed coarse
aggregates using motor grader for
aggregates. key stone chips spreader may
be used with application of bituminous
binder after each layer, and with key
aggregates placed on top of the second
layer to serve as a Base conforming to the
line, grades and cross-section specified, the
Unit = sqm
Taking output = 3000 sqm (225 cum)
a) Labour
Mate day 0.400 150.00 60.00 L-12
Mazdoor including for brooming of key day 8.000 100.00 800.00 L-13
aggregates
Mazdoor skilled day 2.000 125.00 250.00 L-15
b) Machinery
Hydraulic self propelled chip spreader hour 6.000 1200.00 7200.00 P&M-025
both for aggregates and key
aggregates@ 1500 sqm per hour for
3000 x 3 sqm
Bitumen pressure distributor for 3000 x hour 3.430 580.00 1989.40 P&M-004
2 sqm @ 1750 sqm per hour
Tipper 5.5 cum capacity hour 10.000 185.00 1850.00 P&M-048
Vibratory roller 8 tonnes hour 6.000 1000.00 6000.00 P&M-059
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017

Page 4 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. c) Material
Bitumen30 kg per 10 sqm @ 15 kg per tonne 9.000 27030.00 243270.00 M-074
10 sqm for each layer
Crushed stone coarse aggregate cum 300.000 410.00 123000.00 M-035
passing 53 mm and retained on 2.8 mm
sieve @ 0.5 cum per 10 sqm for each
layer
Key aggregates passing 22.4 mm and cum 39.000 410.00 15990.00 M-031
retained on 2.8 mm sieve @ 0.13 cum
d) perOverhead
10 sqm charges @ 10 % on 40460.94
(a+b+c)
e) Contractor's profit @ 10 % on 44507.03
(a+b+c+d)
Cost for 3000 sqm = a+b+c+d+e 489577.37
Rate per sqm = (a+b+c+d+e)/3000 163.19
say 163.00
Note 2 tippers will be needed to match the
capacity of hydraulic chip spreader and
5.6 507 front
Dense end loader.Bituminous Macadam
Graded
Providing and laying dense graded
bituminous macadam with 100-120 TPH
batch type HMP producing an average
output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed
with bituminous binder @ 4.0 to 4.5 per
cent by weight of total mix and filler,
transporting the hot mix to work site, laying
with a hydrostatic paver finisher with sensor
control to the required grade, level and
alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the
desired compaction as per MoRTH
specification clause No. 507 complete in all
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 150.00 126.00 L-12
Mazdoor working with HMP, mechanical day 16.000 100.00 1600.00 L-13
broom, paver, roller, asphalt cutter and
assistance for setting out lines, levels
and layout of construction
Skilled mazdoor for checking line & day 5.000 125.00 625.00 L-15
b) levels
Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 6700.00 40200.00 P&M-022
Paver finisher hydrostatic with sensor hour 6.000 1500.00 9000.00 P&M-034
control @ 75 cum per hour
Generator 250 KVA hour 6.000 750.00 4500.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017
Tipper 10 tonne capacity tonne.k 450 x L 1.85 16650.00 Lead =20
m km & P&M-
Add 10 per cent of cost of carriage to 1665.00 058
cover cost of loading and unloading
smooth wheeled roller 8-10 tonnes for hour6.00x0.65* 170.00 663.00 P&M-044
initial break down rolling.
Vibratory roller 8 tonnes for hour6.00x0.65* 1000.00 3900.00 P&M-059
intermediate rolling.
Finish rolling with 6-8 tonnes smooth hour6.00x0.65* 700.00 2730.00 P&M-045
wheeled tandem roller.
c) Materials
Bitumen @ 4.25 per cent of tonne 19.130 27030.00 517083.90 M-074
weight of mix
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87
tonnes
Taking density of aggregate = 1.5
ton/cum
Volume of aggregate = 287.25 cum
Grading - I40 mm (Nominal Size)
37.5 - 25 mm 22 per cent cum 63.190 370.00 23380.30 M-049

Page 5 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. 25 - 10 mm 13 per cent cum 37.340 410.00 15309.40 M-046
10 -4.75 mm 19 per cent cum 54.580 410.00 22377.80 M-040
4.75 mm and below 44 per cent cum 126.390 300.00 37917.00 M-030
Filler @ 2 per cent of weight of tonne 8.620 2400.00 20688.00 M-188
aggregates. or
Grading - II19 mm (Nominal Size)
25 - 10 mm 30 per cent cum 86.160 410.00 35325.60 M-046
10 - 5 mm 28 per cent cum 80.430 410.00 32976.30 M-040
5 mm and below 40 per cent cum 114.900 300.00 34470.00 M-030
Filler @ 2 per cent of weight of tonne 8.620 2400.00 20688.00 M-188
aggregates.
* Any one of the alternative may be
adopted as per approved design
(i) For Grading I ( 40 mm nominal size )
d) Overhead charges @ 10 % on 72261.54
(a+b+c)
e) Contractor's profit @ 10 % on 79487.69
(a+b+c+d)
Cost for 205 cum = a+b+c+d+e 874364.63
Rate per cum = (a+b+c+d+e)/195 (For 4483.92
Grading I) say 4484.00
(ii) For GradingII(19 mm nominal size)
d) Overhead charges @ 10 % on 72640.28
(a+b+c)
e) Contractor's profit @ 10 % on 79904.31
(a+b+c+d)
Cost for 205 cum = a+b+c+d+e 878947.39
Rate per cum = (a+b+c+d+e)/195 (For 4507.42
Grading-II) say 4507.00
Note *1. Although the roller are required only for
3 hours as per norms of output, but the
same have to be available at site for six
hours as the hot mix plant and paver will
take six hours for mixing and paving the
output of 450 tonnes considered in this
analysis. To cater for the idle period of
these rollers, their usage rates have been
multiplied
2.Quantity by
of aBitumen
factor of has
0.65.been taken for
analysis purpose. The actual quantity will
depend upon job mix formula.
3. Labour for traffic control, watch and ward
and other miscellaneous duties at site
including sundries have been included in
administrative overheads of the contractor.
4. In case DBM is laid over freshly laid tack
coat, provision of mechanical broom and 2
mazdoors shall be deleted as the same has
been included in the cost of tack coat.
5. The individual density for each size of
aggregates to be used for construction I.e.
37.5-25 mm, 25-10 mm etc. should be
found in the laboratory and accordingly the
quantities should be ammended for use in
field. The average density of 1.5 tonne/cum
is only a reference density in this Data
6. The individual percentage of aggregates
should be calculated from the total weight
of dry aggregates i.e.. excluding the weight
of bitumen. The weight of filler will also be
2 per cent by weight of dry aggregates.
5.7 508 Semi-Dense Bituminous Concrete

Page 6 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Providing and laying semi dense bituminous
concrete with 100-120 TPH batch type HMP
producing an average output of 75 tonnes
per hour using crushed aggregates of
specified grading, premixed with
bituminous binder @ 4.5 to 5 per cent of
mix and filler, transporting the hot mix to
work site, laying with a hydrostatic paver
finisher with sensor control to the required
grade, level and alignment, rolling with
smooth wheeled, vibratory and tandem
rollers to achieve the desired compaction as
per MoRTH specification clause No. 508
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 150.00 126.00 L-12
Mazdoor working with HMP, mechanical day 16.000 100.00 1600.00 L-13
broom, paver, roller, asphalt cutter and
assistance for setting out lines, levels
and layout of construction
Skilled mazdoor for checking line & day 5.000 125.00 625.00 L-15
b) levels
Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 6700.00 40200.00 P&M-022
Paver finisher hydrostatic with sensor hour 6.000 1500.00 9000.00 P&M-034
control @ 75 cum per hour
Generator 250 KVA hour 6.000 750.00 4500.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017
Tipper 10 tonne capacity tonne.k 450 x L 1.85 16650.00 Lead =20
m km & P&M-
Add 10 per cent of cost of carriage to 1665.00 058
cover cost of loading and unloading
Smooth wheeled roller 8-10 tonnes for hour6.00x0.65* 170.00 663.00 P&M-044
initial break down rolling.
Vibratory roller 8 tonnes for hour6.00x0.65* 1000.00 3900.00 P&M-059
intermediate
Finish rolling.
rolling with 6-8 tonnes smooth hour6.00x0.65* 700.00 2730.00 P&M-045
wheeled tandem roller
c) Material
* Grading I: 13 mm (Nominal Size)
i) Bitumen@ 4.5 per cent of tonne 20.250 27030.00 547357.50 M-074
weight of mix
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75
tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent cum 57.300 410.00 23493.00 M-044
10 - 5 mm 38 per cent cum 108.870 410.00 44636.70 M-040
5 mm and below 40 per cent cum 114.600 300.00 34380.00 M-030
Filler @ 2 per cent of weight of tonne 8.620 2400.00 20688.00 M-188
aggregates. or
Grading II: 10 mm (Nominal Size)
Bitumen@5 per cent of weight of tonne 22.500 27030.00 608175.00 M-074
mixof mix = 450 tonne
weight
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50
tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent cum 162.450 410.00 66604.50 M-040
4.75 and below@ 41 per cent cum 116.850 300.00 35055.00 M-030

Page 7 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Filler @ 2 per cent of weight of tonne 8.620 2400.00 20688.00 M-188
aggregates.
*Any one of the alternative may be
adopted as per approved design
(i) for Grading I ( 13 mm nominal size )
d) Overhead charges @ 10 % on 75641.42
(a+b+c)
e) Contractor's profit @ 10 % on 83205.56
(a+b+c+d)
Cost for 205 cum = a+b+c+d+e 915261.18
Rate per cum = (a+b+c+d+e)/195 (For 4693.65
Grading I) say 4694.00
5.7 (ii) for GradingII(10 mm nominal size)
d) Overhead charges @ 10 % on 81638.15
(a+b+c)
e) Contractor's profit @ 10 % on 89801.97
(a+b+c+d)
Cost for 205 cum = a+b+c+d+e 987821.62
Rate per cum = (a+b+c+d+e)/195 (For 5065.75
Grading-II) say 5066.00
Note *1. Although the rollers are required only
for 3 hours as per norms of output, but the
same have to be available at site for six
hours as the hot mix plant and paver will
take six hours for mixing and paving the
output of 450 tonnes considered in this
analysis. To cater for the idle period of
these rollers, their usage rates have been
multiplied
2.Quantity by
of aBitumen
factor of has
0.65been taken for
analysis purpose. The actual quantity will
depend upon job mix formula.
3. Labour for traffic control, watch and ward
and other miscellaneous duties at site
including sundries have been included in
administrative overheads of the contractor.
4. In case SDBC is laid over freshly laid tack
coat, provision of broom and 2 mazdoor
shall be deleted as the same has been
included in the cost of tack coat.
5. The quantity of Bitumen to be adjusted
as per job mix formula.
5.8 509 Bituminous Concrete
Providing and laying bituminous concrete
with 100-120 TPH batch type hot mix plant
producing an average output of 75 tonnes
per hour using crushed aggregates of
specified grading, premixed with
bituminous binder @ 5.4 to 5.6 per cent of
mix and filler, transporting the hot mix to
work site, laying with a hydrostatic paver
finisher with sensor control to the required
grade, level and alignment, rolling with
smooth wheeled, vibratory and tandem
rollers to achieve the desired compaction as
per MORTH specification clause No. 509
Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 150.00 126.00 L-12
Mazdoor working with HMP, mechanical day 16.000 100.00 1600.00 L-13
broom, paver, roller, asphalt cutter and
assistance for setting out lines, levels
and layout of construction
Skilled mazdoor for checking line & day 5.000 125.00 625.00 L-15
b) levels
Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 6700.00 40200.00 P&M-022
Paver finisher hydrostatic with sensor hour 6.000 1500.00 9000.00 P&M-034
control @ 75 cum per hour
Generator 250 KVA hour 6.000 750.00 4500.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017

Page 8 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Tipper 10 tonne capacity tonne.k 450 x L 1.85 16650.00 Lead =20
m km & P&M-
Add 10 per cent of cost of carriage to 1665.00 058
cover cost of loading and unloading
Smooth wheeled roller 8-10 tonnes for hour6.00x0.65* 170.00 663.00 P&M-044
initial break down rolling.
Vibratory roller 8 tonnes for hour6.00x0.65* 1000.00 3900.00 P&M-059
intermediate rolling.
Finish rolling with 6-8 tonnes smooth hour6.00x0.65* 700.00 2730.00 P&M-045
wheeled tandem roller.
c) Material
i) Bitumen@ 5 per cent of weight tonne 22.500 27030.00 608175.00 M-074
of mix
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50
tonnes
Taking density of aggregate = 1.5
ton/cum
Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 35 per cent cum 99.750 410.00 40897.50 M-045
10 - 5 mm 23 per cent cum 65.550 410.00 26875.50 M-040
5 mm and below 40 per cent cum 114.000 300.00 34200.00 M-030
Filler @ 2 per cent of weight of tonne 8.620 2400.00 20688.00 M-188
aggregates. or
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.500 410.00 35055.00 M-044
10 - 5 mm 25 per cent cum 71.250 410.00 29212.50 M-040
5 mm and below43 per cent cum 122.550 300.00 36765.00 M-030
Filler @ 2 per cent of weight of tonne 8.620 2400.00 20688.00 M-188
aggregates.
*Any one of the alternative may be
adopted as per approved design
(i) for Grading-I ( 19 mm nominal size )
d) Overhead charges @ 10 % on 81669.50
(a+b+c)
e) Contractor's profit @ 10 % on 89836.45
(a+b+c+d)
Cost for 205 cum = a+b+c+d+e 988200.95
Rate per cum = (a+b+c+d+e)/191 5173.83
say 5174.00
5.8 (ii) for Grading-II(13mm nominal size)
d) Overhead charges @ 10 % on 81575.45
(a+b+c)
e) Contractor's profit @ 10 % on 89733.00
(a+b+c+d)
Cost for 205 cum = a+b+c+d+e 987062.95
Rate per cum = (a+b+c+d+e)/191 (For 5167.87
Grading-II) say 5168.00
Note *1. Although the rollers are required only
for 3 hours as per norms of output, but the
same have to be available at site for six
hours as the hot mix plant and paver will
take six hours for mixing and paving the
output of 450 tonnes considered in this
analysis. To cater for the idle period of
these rollers, their usage rates have been
multiplied
2.Quantity by
of aBitumen
factor of has
0.65been taken for
analysis purpose. The actual quantity will
depend upon job mix formula.
3. Labour for traffic control, watch and ward
and other miscellaneous duties at site
including sundries have been included in
administrative overheads of the contractor.
4. In case BC is laid over freshly laid tack
coat, provision of mechanical broom and 2
mazdoors shall be deleted as the same has
been included in the cost of tack coat.

Page 9 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. 5. The individual density for each size of
aggregates to be used for construction i.e.
37.5-25 mm, 25-10 mm etc. should be
found in the laboratory and accordingly the
quantities should be ammended for use in
field. The average density of 1.5 tonne/cum
is only a reference density in this Data
6. The individual percentage of aggregates
should be calculated from the total weight
of dry aggregates i.e.. excluding the weight
of bitumen. The weight of filler will also be
2 per cent by weight of dry aggregates.
5.9 510 Surface Dressing
Providing and laying surface dressing as
wearing course in single coat using crushed
stone aggregates of specified size on a
layer of bituminous binder laid on prepared
surface and rolling with 8-10 tonne smooth
wheeled steel roller
Unit = sqm
Taking output = 9000 sqm
Case :-19 mm nominal chipping size
-1 a) Labour
Mate day 0.440 150.00 66.00 L-12
Mazdoor day 9.000 100.00 900.00 L-13
Mazdoor skilled day 2.000 125.00 250.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour 7.200 150.00 1080.00 P&M-031
hour
Air compressor 250 cfm hour 7.200 150.00 1080.00 P&M-001
Hydraulic self propelled chip spreader hour 6.000 1200.00 7200.00 P&M-025
@ 1500 sqm per hour
Tipper 10 tonne capacity for carriage of hour 6.000 185.00 1110.00 P&M-048
stone chips from stockpile on road side
to chipend
Front spreader
loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017
Bitumen pressure distributor hour 6.000 580.00 3480.00 P&M-004
Smooth wheeled roller 8-10 tonne hour 6.000 170.00 1020.00 P&M-044
c) weight
Material
Bitumen@ 1.20 kg per sqm tonne 10.800 27030.00 291924.00 M-074
Crushed stone chipping,19 mm nominal cum 135.000 410.00 55350.00 M-053
size @ 0.015 cum per sqm
d) Overhead charges @ 10 % on 36766.00
(a+b+c)
e) Contractor's profit @ 10 % on 40442.60
(a+b+c+d)
Cost for 9000 sqm = a+b+c+d+e 444868.60
Rate per sqm = (a+b+c+d+e)/9000 49.43
say 49.00
5.9 Case - 13 mm nominal size chipping
II a) Labour
Mate day 0.440 150.00 66.00 L-12
Mazdoor day 9.000 100.00 900.00 L-13
Mazdoor skilled day 2.000 125.00 250.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour 7.200 150.00 1080.00 P&M-031
hour
Air compressor 250 cfm hour 7.200 150.00 1080.00 P&M-001
Hydraulic self propelled chip spreader hour 6.000 1200.00 7200.00 P&M-025
@ 1500 sqm per hour
Tipper 10 tonne capacity for carriage of hour 6.000 185.00 1110.00 P&M-048
stone chips from stockpile on road side
to chipend
Front spreader
loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017
Bitumen pressure distributor @ 1750 hour 6.000 580.00 3480.00 P&M-004
sqm per hour
Vibratory roller 8-10 tonne weight hour 6.000 1000.00 6000.00 P&M-059
c) Material
Bitumen@ 1.00 kg per sqm tonne 9.000 27030.00 243270.00 M-074

Page 10 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Crushed stone chipping,13 mm nominal cum 90.000 410.00 36900.00 M-052
size @ 0.01 cum per sqm
d) Overhead charges @ 10 % on 30553.60
(a+b+c)
e) Contractor's profit @ 10 % on 33608.96
(a+b+c+d)
Cost for 9000 sqm = a+b+c+d+e 369698.56
Rate per sqm = (a+b+c+d+e)/9000 41.08
say 41.00
Note 1.Where the proposed aggregate fails to
pass the stripping test, an approved
adhesion agent may be added to the binder
as per clause 510.2.4. Alternatively, chips
may be pre-coated as per clause 510.2.5
2.Input for the second coat, where required, 0.00
will be the same as per the Ist coat
5.10 511 mentioned abovePremix Surfacing
Open - Graded
Providing, laying and rolling of open -
graded premix surfacing of 20 mm
thickness composed of 13.2 mm to 5.6 mm
aggregates either using penetration grade
bitumen or cut-back or emulsion to required
line, grade and level to serve as wearing
course on a previously prepared base,
including mixing in a suitable plant, laying
and rolling with a smooth wheeled roller 8-
10 tonne
Unit capacity, finished to required level
= sqm
Taking output = 10250 sqm (205 cum)
(i) Case - I: Mechanical method using
Penetration grade Bitumen and HMP of
appropriate capacity not less than 75
tonnes/hour .
a) Labour
Mate day 0.840 150.00 126.00 L-12
Mazdoor working with HMP, road day 16.000 100.00 1600.00 L-13
sweeper, paver and roller
Skilled mazdoor for checking line & day 5.000 125.00 625.00 L-15
b) levels
Machinery
i) Batch type HMP 75 tonne per hour hour 6.000 6900.00 41400.00 P&M-021
ii) Electric Generator Set 250 KVA hour 6.000 750.00 4500.00 P&M-081
iii) Front end loader 1 cum bucket hour 6.000 700.00 4200.00 P&M-017
capacity
iv) Tipper 10 tonne capacity tonne.k 450 x L 1.85 16650.00 Lead =20
m km & P&M-
Add 10 per cent of cost of carriage to 1665.00 058
cover cost of loading and unloading
v) Paver finisher hydrostatic with sensor hour 6.000 1500.00 9000.00 P&M-034
attachment
iv) Smooth wheeled/tandom roller 8-10 hour 6.000 700.00 4200.00 P&M-045
tonnes weight
c) Material
Bitumen@ 14.60 kg per 10 sqm tonne 14.970 31900.00 477543.00 M-074
Crushed stone chipping,13.2 mm to 5.6 cum 276.750 410.00 113467.50 M-043
mm @ 0.27 cum per 10 sqm
d) Overhead charges @ 10 % on 67497.65
(a+b+c)
e) Contractor's profit @ 10 % on 74247.42
(a+b+c+d)
Cost for 10250 sqm = a+b+c+d+e 816721.57
Rate per sqm = (a+b+c+d+e)/10250 79.68
say 80.00

Page 11 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Note If a premix sand seal coat of 'B' type is
proposed, the same is required to be
provided over the open graded premix
carpet immediately on the same day. As the
same HMP and other machines will be used
for laying of premix sand seal coat, out of 6
effective working hours, 4.00 hours may be
utilised for laying of premix carpet and
balance 2.00 hours for the seal coat. The
rate for the premix sand seal coat under
clause 513 (case II) has been worked out
accordingly by utilising the HMP for 2.00
hours for the purpose of seal coat. In case
type 'A' seal coat is proposed, HMP can be
worked for six hours for the premix carpet
5.10 (ii) as
Casetype -'A' seal
II: coat does not require
Open-Graded the
Premix
Surfacing using cationic Bitumen
Emulsion
Unit = sqm
Taking output = 900 sqm (24.3 cum)
a) Labour
Mate day 0.800 150.00 120.00 L-12
Mazdoor day 18.000 100.00 1800.00 L-13
Mazdoor skilled day 2.000 125.00 250.00 L-15
b) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 6.000 100.00 600.00 P&M-009
Smooth wheeled steel roller 8-10 tonne hour 6.000 170.00 1020.00 P&M-044
c) Material
Cationic Bitumen Emulsion @ 21.50 kg tonne 1.940 25000.00 48500.00 M-073
per 10 sqm
Crushed stone aggregates 13.2 mm to cum 24.300 410.00 9963.00 M-043
5.6 mm @ 0.27 cum per 10 sqm
d) Overhead charges @ 10 % on 6225.30
(a+b+c)
e) Contractor's profit @ 10 % on 6847.83
(a+b+c+d)
Cost for 900 sqm = a+b+c+d+e 75326.13
Rate per sqm = (a+b+c+d+e)/900 83.70
say 84.00
5.11 512 Close Graded Premix Surfacing/Mixed
Seal Surfacing
Case I Mechanical means using HMP of appropriate
capacity not less than 75 tonnes/hour.
Providing, laying and rolling of close-graded
premix surfacing material of 20 mm
thickness composed of 11.2 mm to 0.09
mm (Type-a) or 13.2 mm to 0.09 mm
(Type-b) aggregates using penetration
grade bitumen to the required line, grade
and level to serve as wearing course on a
previously prepared base, including mixing
in a suitable plant, laying and rolling with a
Smooth wheeled roller 8-10 tonne capacity,
and finishing to required level and grade.
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour
Mate day 0.840 150.00 126.00 L-12
Mazdoor working with HMP, road day 16.000 100.00 1600.00 L-13
sweeper, paver and roller
Skilled mazdoor for checking line & day 5.000 125.00 625.00 L-15
b) levels
Machinery
i) HMP of appropicate capacity. hour 6.000 6900.00 41400.00 P&M-021
ii) Electric Generator Set 250 KVA hour 6.000 750.00 4500.00 P&M-081
iii) Front end loader 1 cum bucket hour 6.000 700.00 4200.00 P&M-017
capacity
iv) Tipper 10 tonne capacity tonne.k 450 x L 1.85 16650.00 Lead =20
m km & P&M-
Add 10 per cent of cost of carriage to 1665.00 058
cover cost of loading and unloading

Page 12 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. v) Paver finisher hydrostatic with sensor hour 6.000 1500.00 9000.00 P&M-034
attachment
iv) Smooth wheeled8-10 tonnes weight hour 6.000 170.00 1020.00 P&M-044
c) Material
Type - A
* Bitumen@ 22 kg per 10 sqm tonne 22.500 27030.00 608175.00 M-074
Stone crushed aggregates 11.2 mm to cum 276.750 410.00 113467.50 M-041
0.09 @ 0.27 cum per 10 sqm
or
Type - B
Bitumen @ 19 kg per 10 sqm tonne 19.480 27030.00 526544.40 M-074
Stone crushed aggregates 13.2 mm to cum 276.750 410.00 113467.50 M-042
0.09 mm @ 0.27 cum per 10 sqm
d) Overhead charges @ 10 % on 80242.85
(a+b+c)
e) Contractor's profit @ 10 % on 88267.14
(a+b+c+d)
Cost for 10250 sqm = a+b+c+d+e 970938.49
Rate per sqm = (a+b+c+d+e)/10250 94.73
say 95.00
* Any one of the alternative may be
5.12 513 adopted
Seal Coat
Providing and laying seal coat sealing the
voids in a bituminous surface laid to the
specified levels, grade and cross fall using
Type A and B seal coats
Unit = sqm
Taking output = 10250 sqm (92.25
(i) cum)
Case - I : Type A
a) Labour
Mate day 0.240 150.00 36.00 L-12
Mazdoor day 6.000 100.00 600.00 L-13
b) Machinery
Hydraulic self propelled chip spreader hour 6.000 1200.00 7200.00 P&M-025
Tipper 5.5 cum capacity hour 6.000 185.00 1110.00 P&M-048
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017
Bitumen pressure distributor @ 1750 hour 6.000 580.00 3480.00 P&M-004
sqm per wheeled
Smooth hour roller 8 -10 tonne hour 6.000 170.00 1020.00 P&M-044
c) weight
Material
Bitumen@ 9.80 kg per 10 sqm tonne 10.050 27030.00 271651.50 M-074
Crushed stone chipping of 6.7 mm size cum 92.250 350.00 32287.50 M-050
defined as 100 per cent passing 11.2
mm sieve and retained on 2.36 mm
sieve applied @ 0.09 cum per 10 sqm
d) Overhead charges @ 10 % on 32158.50
(a+b+c)
e) Contractor's profit @ 10 % on 35374.35
(a+b+c+d)
Cost for 10250 sqm = a+b+c+d+e 389117.85
Rate per sqm = (a+b+c+d+e)/10250 37.96
say 38.00
Note Since seal coat is provided immediately
over the bituminous layers, mechanical
broom for clearing has not been catered.
5.12 (ii) Case - II : Type B
Providing and laying of premix sand seal
coat with HMP of appropriate capacity not
less than 75 tonnes/ hours using crushed
stone chipping 6.7 mm size and penetration
bitumen of suitable grade.
Unit = sqm
Taking output = 7858 sqm (47.16 cum)
a) Labour
Mate day 0.160 150.00 24.00 L-12
Mazdoor day 4.000 100.00 400.00 L-13
b) Machinery

Page 13 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. HMP of 75 tonnes/hour. hour 2.000 6700.00 13400.00 P&M-022
Electric Generator Set 250 KVA hour 2.000 750.00 1500.00 P&M-081
Front end loader 1 cum bucket capacity hour 2.000 700.00 1400.00 P&M-017
Tipper 10 tonne capacity tonne.k 104 x 'L' 1.85 3848.00 Lead =20
m km & P&M-
Add 10 per cent of cost of carriage to 384.80 058
cover cost of loading and unloading
Paver finisher hydrostatic with sensor hour 2.000 1500.00 3000.00 P&M-034
attachment
Smooth wheeled 8-10 tonnes capacity hour 2.000 170.00 340.00 P&M-044
c) Material
Bitumen@ 6.80 kg per 10 sqm tonne 5.340 27030.00 144340.20 M-074
Crushed stone chipping of 6.7 mm size cum 47.160 350.00 16506.00 M-050
defined as passing 11.2 mm sieve and
retained on 2.36 mm sieve applied @
0.06 cum per 10 sqm
d) Overhead charges @ 10 % on 18514.30
(a+b+c)
e) Contractor's profit @ 10 % on 20365.73
(a+b+c+d)
Cost for 7858 sqm = a+b+c+d+e 224023.03
Rate per sqm = (a+b+c+d+e)/7858 28.51
say 29.00
Note Since seal coat is required to be provided
over the premix carpet on the same day,
out of the 6 working hours of the HMP, 4.00
hours are proposed to be utilised for the
premix carpet and the balance 2.00 hours
for the seal coat. Hence 2.00 hours have
been considered for this case. This may be
linked to rate analysis worked out under
5.13 514 clause 511.of Stone Aggregates for
Supply
Pavement Courses
Supply of stone aggregates from approved
sources conforming to the physical
requirement, specified in the respective
specified clauses, including royalties, fees
rents, collection, transportation, stacking
and testing and measured in cum as per
Competitive market rates to be as
certained. Alternatively, rates for stone
crushing given in chapter 1may be adopted,
if found economical. In case for supply of
aggregates at site are not available,
nearest crusher site may be as certained.
Loading and un-loading charges and cost of
carriage may be added to these rates to
5.14 515 arrive
MasticatAsphalt
the cost at site.
Providing and laying 25 mm thick mastic
asphalt wearing course with paving grade
bitumen meeting the requirements given in
table 500-29, prepared by using mastic
cooker and laid to required level and slope
after cleaning the surface, including
providing antiskid surface with bitumen
precoated finegrained hard stone chipping
of 13.2 mm nominal size at the rate of
0.005cum per 10 sqm and at an
approximate spacing of 10 cm center to
center in both directions, pressed into
surface when the temperature of surfaces is
not less than 1000C, protruding 1 mm to 4
Unit = sqm
Taking output = 35.00 sqm (0.87 cum )
assuming a density of 2.3 tonnes/cum.-
2
a)tonnes
Labour
Mate day 0.440 150.00 66.00 L-12
Mazdoor day 10.000 100.00 1000.00 L-13
Mazdoor skilled day 1.000 125.00 125.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour 0.060 150.00 9.00 P&M-031
hour

Page 14 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Air compressor 250 cfm hour 0.060 150.00 9.00 P&M-001
Mastic cooker 1 tonne capacity hour 6.000 40.00 240.00 P&M-030
Bitumen boiler 1500 litres capacity hour 6.000 150.00 900.00 P&M-005
Tractor for towing and positioning of hour 1.000 150.00 150.00 P&M-053
mastic cooker and bitumen boiler
c) Material
Base mastic (without coarse aggregates) =
60 per cent
Coarse aggregate (6.3mm to 13.2 mm) =
40 per centof
Proportion . material required for mastic
asphalt with coarse aggregates (based on
mix design done by CRRI for a specific case)
I) Bitumen 85/25 or 30/40 @ 10.2 per tonne 0.204 27030.00 5514.12 M-074
cent by weight of mix. 2 x 10.2/100 =
0.204
ii) Fine aggregate passing 2.36mm and cum 0.390 200.00 78.00 M-021
retained on 0.075mm sieve @ 31.9 per
cent by weight of mix = 2 x 31.9/100 =
0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium tonne 0.360 2400.00 864.00 M-188
content not less than 80 per cent by
weight @ 17.92 per cent by weight of
mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 6.3 mm to 13.2 cum 0.550 410.00 225.50 M-043
mm @ 40 per cent by weight of mix =
2 x 40/100 = 0.8 MT = 0.8/1.456 =
0.55
v) Pre-coated stone chips of 13.2 mm cum 0.018 900.00 16.20 M-142
nominal size for skid resistance = 35 x
0.005/10
vi) = 0.018
Bitumen for coating of chips @ 2 per kg 0.500 27.00 13.50 M-074
cent by weight = 0.018 x 1.456 x
2/100 = 0.0005 MT = 0.5kg
d) Overhead charges @ 10 % on 921.03
(a+b+c)
e) Contractor's profit @ 10 % on 1013.14
(a+b+c+d)
Cost for 35.00 sqm = a+b+c+d+e 11144.49
Rate per sqm = (a+b+c+d+e)/35 318.41
say 318.00
Note 1.The rates for 50 mm & 40 mm thick
layers may be worked out on pro-rata basis.
2.Where tack coat is required to be
provided before laying mastic asphalt, the
same is required to be measured and paid
separately.
3.The quantities of binder, filler and
aggregates are for estimating purpose.
Exact quantities shall be as per mix design.
4.This rate analysis is based on design
made by CRRI for a specific case and is
meant for estimating purposes only. Actual
design is required to be done for each case.
5.15 516 Slurry Seal
Providing and laying slurry seal consisting
of a mixture of fine aggregates, portland
cement filler, bituminous emulsion and
water on a road surface including cleaning
of surface, mixing of slurry seal in a suitable
mobile plant, laying and compacting to
provide even riding surface
(i) 5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum
weight of mix = 176 tonnes
a) Labour
Mate day 0.240 150.00 36.00 L-12
Mazdoor day 6.000 100.00 600.00 L-13
b) Machinery

Page 15 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Mechanical broom hour 6.000 150.00 900.00 P&M-031
Air compressor 250 cfm hour 6.000 150.00 900.00 P&M-001
Mobile slurry seal equipment hour 6.000 550.00 3300.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017
Tipper 5.5 cum capacity for carriage of hour 6.000 185.00 1110.00 P&M-048
aggregate from stockpile on road side
to slurry equipment, bitumen emulsion
and filler.
Pneumatic tyred roller with individual hour 6.000 1000.00 6000.00 P&M-037
wheel load not exceeding 1.5 tonnes
Water tanker6 KL capacity hour 2.000 105.00 210.00 P&M-060
c) Material
Residual Binder @ 11 per cent of mix tonne 19.360 24000.00 464640.00 M-077
80 x 2.2 x 0.11
Fine aggregate 4.75 mm and below 87 cum 102.080 300.00 30624.00 M-030
per cent of total mix,80 x 2.2 x 0.87 =
153.12 tonnes. Taking density1.5, =
153.12/1.5 = 102.08 cum
Filler @ 2 per cent of total mix = 80 x tonne 3.520 2400.00 8448.00 M-188
2.2
Costxof0.02
water KL 12.000 50.00 600.00 M-189
d) Overhead charges @ 10 % on 52156.80
(a+b+c)
e) Contractor's profit @ 10 % on 57372.48
(a+b+c+d)
Cost for 16000 sqm = a+b+c+d+e 631097.28
Rate per sqm = (a+b+c+d+e)/16000 39.44
say 39.00
5.15 (ii) 3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
Mate day 0.200 150.00 30.00 L-12
Mazdoor day 5.000 100.00 500.00 L-13
b) Machinery
Mechanical broom hour 6.000 150.00 900.00 P&M-031
Air compressor 250 cfm hour 6.000 150.00 900.00 P&M-001
Mobile slurry seal equipment hour 6.000 550.00 3300.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017
Tipper 5.5 cum capacity for carriage of hour 6.000 185.00 1110.00 P&M-048
aggregate from stockpile on road side
to slurry equipment, bitumen emulsion
and filler
Water tanker6 KL capacity hour 2.000 105.00 210.00 P&M-060
c) Material
Residual Binder @ 13 per cent of mix tonne 17.160 24000.00 411840.00 M-077
= 60 x 2.2 x 0.13
Fine aggregate 3 mm and below 85 per cum 74.800 200.00 14960.00 M-022
cent of total mix, 60x 2.2 x 0.85 =
112.2 tonnes. Taking density 1.5,
Filler @ 2 per cent of total mix = 60x tonne 2.640 2400.00 6336.00 M-188
2.2 xof
Cost 0.02
water KL 12.000 50.00 600.00 M-189
d) Overhead charges @ 10 % on 44488.60
(a+b+c)
e) Contractor's profit @ 10 % on 48937.46
(a+b+c+d)
Cost for 30000 sqm = a+b+c+d+e 538312.06
Rate per sqm = (a+b+c+d+e)/20000 26.92
say 27.00
5.15 (iii) 1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
Mate day 0.200 150.00 30.00 L-12
Mazdoor day 5.000 100.00 500.00 L-13
b) Machinery
Mechanical broom hour 6.000 150.00 900.00 P&M-031

Page 16 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Air compressor 250 cfm hour 6.000 150.00 900.00 P&M-001
Mobile slurry seal equipment hour 6.000 550.00 3300.00 P&M-033
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017
Tipper 5.5 cum capacity for carriage of hour 6.000 185.00 1110.00 P&M-048
aggregate from stockpile on road side
to slurry equipment, bitumen emulsion
and filler.
Water tanker6 KL capacity hour 2.000 105.00 210.00 P&M-060
c) Material
Residual Binder @ 16 per cent of mix, tonne 12.670 24000.00 304080.00 M-077
36 x 2.2 x 0.16
Fine aggregate 2.36 mm and below,82 cum 43.300 200.00 8660.00 M-022
per cent of total mix,36x 2.2 x 0.82 =
64.94 tonnes. Taking density 1.5
Filler @ 2 per cent of total mix = 36x tonne 1.580 2400.00 3792.00 M-188
2.2 xof
Cost 0.02
water KL 12.000 50.00 600.00 M-189
d) Overhead charges @ 10 % on 32828.20
(a+b+c)
e) Contractor's profit @ 10 % on 36111.02
(a+b+c+d)
Cost for 24000 sqm = a+b+c+d+e 397221.22
Rate per sqm = (a+b+c+d+e)/24000 16.55
say 17.00
Note 1.Tack coat, if required to be provided,
before laying slurry seal may be measured
5.16 517 and paid separately
Recycling of Bituminous Pavement
with Central Recycling Plant
Recycling pavement by cold milling of
existing bituminous layers, planning the
surface after cold milling, reclaiming
excavated material to the extent of 30 per
cent of the required quantity, hauling and
stock piling the reclaimed material near the
central recycling plant after carrying out
necessary checks and evaluation, adding
fresh material including rejuvenators as
required, mixing in a hot mix plant,
transporting and laying at site and
compacting to the required grade, level and
Unit = cum
Taking output = 120 cum (276 tonnes)
a) Labour
Mate day 0.480 150.00 72.00 L-12
Mazdoor day 10.000 100.00 1000.00 L-13
Mazdoor skilled day 2.000 125.00 250.00 L-15
b) Machinery
Cold milling machine @ 20 cum per hour 6.000 150.00 900.00 P&M-069
hour
Mechanical broom @ 1250 sqm per hour 1.280 150.00 192.00 P&M-031
hour
Air compressor 250 cfm hour 1.280 150.00 192.00 P&M-001
Bitumen pressure distributor @ 1750 hour 0.910 580.00 527.80 P&M-004
sqm per plant
Hot mix hour 100-120 TPH producing hour 3.000 6900.00 20700.00 P&M-021
an average of 75 tonnes per hour
Electric generator set 250 KVA hour 3.000 750.00 2250.00 P&M-081
Front end loader 1.00 cum bucket hour 3.000 700.00 2100.00 P&M-017
capacity
Tipper 5.5 cum capacity hour 18.000 185.00 3330.00 P&M-048
Smooth wheeled roller 8-10 tonnes hour3.00x0.65* 170.00 331.50 P&M-044
Vibratory roller 8 tonnes hour3.00x0.65* 1000.00 1950.00 P&M-059
Smooth wheeled tandem roller 6-8 hour3.00x0.65* 700.00 1365.00 P&M-045
c) tonnes
Material
i) Bitumen
A bitumen content is 4.5 per cent bitumen
weight of mix. For reclaimed material, fresh
bitumen will be required to the extent of 60
per cent of normal requirement.

Page 17 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. In a mix of 276 tonnes, 82.8 tonne is
reclaimed and balance 193.2 tonne is fresh
mix.Bitumen required for reclaimed mix of tonne 1.987 27030.00 53714.02 M-074
82.8 tonne @ 60 per cent = 82.8 x
0.60 x0.04
Bitumen = 1.99for fresh mix of 193.2
required tonne 7.728 27030.00 208887.84 M-074
tonnes = 193.2 x 0.04 = 7.73
ii) Aggregates
Percentage of mix requiring fresh
aggregates - 70 per cent
Weight of fresh mix = 276 x 0.70 = 193.2
tonne
Weight of fresh aggregate in the mix =
193.2 x 0.96 = 185.47 tonne
Taking average density of 1.5
tonnes/cum, total volume of aggregate
= 123.65
Size cum.
wise requirement of fresh aggregates
37.5 - 25 mm @ 23 per cent cum 28.440 370.00 10522.80 M-049
25 - 10 mm @ 15 per cent cum 18.550 410.00 7605.50 M-046
10- 5 mm @ 20 per cent cum 24.730 410.00 10139.30 M-040
Below 5 mm @40 per cent cum 49.460 300.00 14838.00 M-030
Filler (cement) @ 2 per cent = tonne 5.520 4180.00 23073.60 M-081
5.52tonnes of 276 tonne
d) Overhead charges @ 10 % on 36394.14
(a+b+c)
e) Contractor's profit @ 10 % on 40033.55
(a+b+c+d)
Cost for 120 cum of DBM = a+b+c+d+e 440369.04
Rate per cum = (a+b+c+d+e)/120 3669.74
say 3670.00
Note Although the total rolling time is only 4
hours as per norms, all the three rollers
have to be available at site for 3 hours each
to match with the output of re-cycling plant.
To cater for their idling time, these have
been multiplied with a factor of 0.65.
5.17 518 Fog Spray
Providing and applying low viscosity
bitumen emulsion for sealing cracks less
than 3 mm wide or incipient fretting or
disintegration in an existing bituminous
surfacing.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.120 150.00 18.00 L-12
Mazdoor day 3.000 100.00 300.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour 6.000 150.00 900.00 P&M-031
hour
Air compressor 250 cfm hour 6.000 150.00 900.00 P&M-001
Bitumen emulsion pressure distributor tonne 6.000 580.00 3480.00 P&M-004
@ 1750 sqm per hour
c) Material
Bitumen emulsion @ 0.75 kg per sqm tonne 7.880 24000.00 189120.00 M-077
d) Overhead charges @ 10 % on 19471.80
(a+b+c)
e) Contractor's profit @ 10 % on 21418.98
(a+b+c+d)
Cost for 10500 sqm = a+b+c+d+e 235608.78
Rate per sqm = (a+b+c+d+e)/10500 22.44
say 22.00
1.In case it is decided by the engineer to
blind the fog spray, the following may be
added
a) Labour
Mate day 0.160 150.00 24.00 L-12
Mazdoor for precoating of grit day 4.000 100.00 400.00 L-13
b) Material
Crushed stone grit 3 mm size @ 3.75 kg cum 26.250 200.00 5250.00 M-024
per sqm
Page 18 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Bitumen emulsion for precoating grit @ tonne 0.790 24000.00 18960.00 M-077
2 per cent of grit,39.38 x 0.02
24634.00
2.35
say 2.00
5.18 519 Bituminous Cold Mix ( Including Gravel
Emulsion)
Providing, laying and rolling of bituminous
cold mix on prepared base consisting of a
mixture of unheated mineral aggregate and
emulsified or cutback bitumen, including
mixing in a plant of suitable type and
capacity, transporting, laying, compacting
and finishing to specified grades and levels.
Unit = cum
Taking output = 205 cum (450 tonne)
(i) Using bitumen emulsion and 9.5 mm or
13.2 mm size aggregate
Composition of mix (450 tonne) is
assumed to be as under:-
Bitumen Emulsion 8 per cent By
weight
Filler2 per cent of total
Total aggregates 90 per cent
Proportion of aggregates
19 mm to 9.5 mm25 per cent
9.5 mm to 6 mm29 per cent
6 mm to 0.075 mm 36 per cent
a) Labour
Mate day 0.840 150.00 126.00 L-12
Mazdoor day 16.000 100.00 1600.00 L-13
Mazdoor skilled day 5.000 125.00 625.00 L-15
b) Machinery
Drum mix plant for cold mixes of hour 6.000 4000.00 24000.00 P&M-077
appropriate capacity but not less than
75 tonnes/hour.
Electric generator 125 KVA hour 6.000 650.00 3900.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017
Tipper 10 tonne capacity tonne.k 450 x L 1.85 16650.00 Lead =20
m km & P&M-
Add 10 per cent of cost of carriage to 1665.00 058
cover cost of loading and unloading
Paver finisher hour 6.000 1500.00 9000.00 P&M-034
Pneumatic tyred roller 12-15 tonnes hour6.00x0.65* 1000.00 3900.00 P&M-037
Smooth wheeled steel tandem roller 6-8 hour6.00x0.65* 700.00 2730.00 P&M-045
c) tonnes
Material
Bitumen emulsion @ 8 per cent tonne 36.000 24000.00 864000.00 M-077
Filler (lime)@ 2 per cent tonne 9.000 2400.00 21600.00 M-188
Aggregates size 19 to 9.5 mm - 450 x cum 75.000 410.00 30750.00 M-045
0.25 x 1/1.5size 9.5 to 6 mm - 450 x
Aggregates cum 87.000 410.00 35670.00 M-040
0.29 x 1/1.5size 6 to 0.075 mm - 450 x
Aggregates cum 108.000 300.00 32400.00 M-030
0.36 x 1/1.5
d) Overhead charges @ 10 % on 105281.60
(a+b+c)
e) Contractor's profit @ 10 % on 115809.76
(a+b+c+d)
Cost for 205 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/205 6214.18
say 6214.00
(Applicable to cases I to IV)
Note 1.Density of aggregates has been assumed
1.5
2. gms/cc
Tack coat where provided will be
measured and paid separately.

Page 19 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. *3. Though the rollers are required only for
3.5 hours each as per norms of output, but
these are required to be available at site for
6 hours as the drum mix plant and the
paver would take 6 hours for mixing and
paving. To cater for the idle period, their
usage rates have been multiplied by a
5.18 (ii) Using bitumen emulsion and 19 mm or
26.5 mm nominal size aggregate
Composition of mix (450 tonne) is
assumed to be as under:-
Bitumen Emulsion 8 per cent
Filler2 per cent
Total aggregates 90 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 35 per cent
a) Labour
Mate day 0.840 150.00 126.00 L-12
Mazdoor day 16.000 100.00 1600.00 L-13
Mazdoor skilled day 5.000 125.00 625.00 L-15
b) Machinery
Drum mix plant for cold mixes 60-90 hour 6.000 4000.00 24000.00 P&M-077
tonne per hour producing average
output of 75 tonnes per hour
Electric generator 125 KVA hour 6.000 650.00 3900.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017
Tipper 10 tonne capacity tonne.k 450 x L 1.85 16650.00 Lead =20
m km & P&M-
Add 10 per cent of cost of carriage to 1665.00 058
cover cost of loading and unloading
Paver finisher hour 6.000 1500.00 9000.00 P&M-034
Pneumatic tyred roller 12-15 tonnes hour6.00x0.65* 1000.00 3900.00 P&M-037
Smooth wheeled steel tandom roller 6-8 hour6.00x0.65* 700.00 2730.00 P&M-045
c) tonnes
Material
Bitumen emulsion @ 8 per cent tonne 36.000 24000.00 864000.00 M-077
Filler (lime)@ 2 per cent tonne 9.000 2400.00 21600.00 M-188
Aggregates size 37.5 to 19 mm - 450 x cum 75.000 370.00 27750.00 M-048
0.25 x 1/1.5
Aggregates size 19 to 6 mm - 450 x 0.3 cum 90.000 410.00 36900.00 M-047
x 1/1.5
Aggregates size 6 to 0.075 mm - 450 x cum 105.000 300.00 31500.00 M-030
0.35 x 1/1.5
d) Overhead charges @ 10 % on 105014.60
(a+b+c)
e) Contractor's profit @ 10 % on 115516.06
(a+b+c+d)
Cost for 205 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/205 6198.42
say 6198.00
Note 1.Density of aggregates has been assumed
1.5 gms/cc
2. Tack coat where provided will be
measured and paid separately.
*3. Though the rollers are required only for
3.5 hours each as per norms of output, but
these are required to be available at site for
6 hours as the drum mix plant and the
paver would take 6 hours for mixing and
paving. To cater for the idle period, their
usage rates have been multiplied by a
5.18 (iii) Using cutback bitumen and 9.5 mm or
13.2 mm nominal size aggregate
Composition of mix (450 tonne) is
assumed to be as under:-

Page 20 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Cutback bitumen 5 per cent
Filler (lime) 2 per cent
Total aggregates 93 per cent
Proportion of aggregates
19 mm to 9.5 mm26 per cent
9.5 mm to 6 mm31 per cent
6 mm to 0.075 mm 36 per cent
a) Labour
Mate day 0.840 150.00 126.00 L-12
Mazdoor day 16.000 100.00 1600.00 L-13
Mazdoor skilled day 5.000 125.00 625.00 L-15
b) Machinery
Drum mix plant for cold mixes 60-90 hour 6.000 4000.00 24000.00 P&M-077
tonne per hour producing average
output of 75 tonnes per hour
Electric generator 125 KVA hour 6.000 650.00 3900.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017
Tipper 10 tonne capacity tonne.k 450 x L 1.85 16650.00 Lead =20
m km & P&M-
Add 10 per cent of cost of carriage to 1665.00 058
cover cost of loading and unloading
Paver finisher hour 6.000 1500.00 9000.00 P&M-034
Pneumatic tyred roller 12-15 tonnes hour6.00x0.65* 1000.00 3900.00 P&M-037
Smooth wheeled steel tandem roller 6-8 hour6.00x0.65* 700.00 2730.00 P&M-045
c) tonnes
Material
Cutback bitumen @ 5 per cent tonne 22.500 24000.00 540000.00 M-076
Filler (lime)@ 2 per cent tonne 9.000 2400.00 21600.00 M-188
Aggregates size 19 to 9.5 mm - 450 x cum 78.000 410.00 31980.00 M-045
0.26 x 1/1.5size 9.5 to 6 mm - 450 x
Aggregates cum 93.000 410.00 38130.00 M-040
0..31 x 1/1.5size 6 to 0.075 mm - 450 x
Aggregates cum 108.000 300.00 32400.00 M-030
0.36 x 1/1.5
d) Overhead charges @ 10 % on 73250.60
(a+b+c)
e) Contractor's profit @ 10 % on 80575.66
(a+b+c+d)
Cost for 205 cum = a+b+c+d+e 886332.26
Rate per cum = (a+b+c+d+e)/205 4323.57
say 4324.00
Note 1.Density of aggregates has been assumed
1.5
2. gms/cc
Tack coat where provided will be
measured and paid separately.
*3. Though the rollers are required only for
3.5 hours each as per norms of output, but
these are required to be available at site for
6 hours as the drum mix plant and the
paver would take 6 hours for mixing and
paving. To cater for the idle period, their
usage rates have been multiplied by a
5.18 (iv) Using cutback bitumen and 19 mm or
26.5 mm nominal size aggregate
Composition of mix (450 tonne) is
assumed to be as under:-
Cutback bitumen 5 per cent
Filler2 per cent
Total aggregates 93 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 38 per cent
a) Labour
Mate day 0.840 150.00 126.00 L-12
Mazdoor day 16.000 100.00 1600.00 L-13

Page 21 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Mazdoor skilled day 5.000 125.00 625.00 L-15
b) Machinery
Drum mix plant for cold mixes 60-90 hour 6.000 4000.00 24000.00 P&M-077
tonne per hour producing output of 75
tonnes per
Electric hour 125 KVA
generator hour 6.000 650.00 3900.00 P&M-018
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017
Tipper 10 tonne capacity tonne.k 450 x L 1.85 16650.00 Lead =20
m km & P&M-
Add 10 per cent of cost of carriage to 1665.00 058
cover cost of loading and unloading
Paver finisher hour 6.000 1500.00 9000.00 P&M-034
Pneumatic tyred roller 12-15 tonnes. hour6.00x0.65* 1000.00 3900.00 P&M-037
Smooth wheeled steel tandem roller 6-8 hour6.00x0.65* 700.00 2730.00 P&M-045
c) tonnes
Material
Cutback bitumen on @ 5 per cent tonne 22.500 24000.00 540000.00 M-076
Filler (lime)@ 2 per cent tonne 9.000 2400.00 21600.00 M-188
Aggregates size 37.5 to 19 mm - 450 x cum 75.000 370.00 27750.00 M-048
0.25 x 1/1.5
Aggregates size 19 to 6 mm - 450 x 0.3 cum 90.000 410.00 36900.00 M-047
x 1/1.5
Aggregates size 6 to 0.075 mm - 450 cum 114.000 300.00 34200.00 M-030
d) x0.38 x 1/1.5 charges @ 10 % on
Overhead 72884.60
(a+b+c)
e) Contractor's profit @ 10 % on 80173.06
(a+b+c+d)
Cost for 205 cum = a+b+c+d+e 881903.66
Rate per cum = (a+b+c+d+e)/205 4301.97
say 4302.00
Note 1.Density of aggregates has been assumed
1.5
2. gms/cc
Tack coat where provided will be
measured and paid separately.
*3. Though the rollers are required only for
3.5 hours each as per norms of output, but
these are required to be available at site for
6 hours as the drum mix plant and the
paver would take 6 hours for mixing and
paving. To cater for the idle period, their
usage rates have been multiplied by a
5.19 520 Sand Asphalt Base Course
Providing, laying and rolling sand-asphalt
base course composed of sand, mineral
filler and bituminous binder on a prepared
sub-grade or sub-base to the lines, levels,
grades and cross sections as per the
drawings including mixing in a plant of
suitable type and capacity, transporting,
Unit = cum
Taking output = 205 cum (450 tonne)
a) Labour
Mate day 0.840 150.00 126.00 L-12
Mazdoor day 16.000 100.00 1600.00 L-13
Mazdoor skilled day 5.000 125.00 625.00 L-15
b) Machinery
Hot Mix Plant of appropriate capacity hour 6.000 6500.00 39000.00 P&M-023
but not less than 75 tonnes/hour
Electric generator set 250 KVA hour 6.000 750.00 4500.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-017
Tipper 10 tonne capacity tonne.k 450 x L 1.85 16650.00 Lead =20
m km & P&M-
Add 10 per cent of cost of carriage to 1665.00 058
cover cost of loading and unloading
Paver finisher hour 6.000 1500.00 9000.00 P&M-034
smooth wheeled roller 8-10 tonnes for hour 6.00x0.65 170.00 663.00 P&M-044
initial break down rolling.
Vibratory roller 8 tonnes for hour 6.00x0.65 1000.00 3900.00 P&M-059
intermediate rolling.

Page 22 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Finish rolling with 6-8 tonnes smooth hour 6.00x0.65 700.00 2730.00 P&M-045
wheeled tandom rollers.
c) Material
Composition of mix (450 tonne) is
assumed to be as under:-
Density 2.20 tonne per cum
Weight450 tonne
Bitumen5 per cent
Filler2 per cent
Sand of size 4.75 to 0.075 mm 93 per cent
Bitumen@ 5 per cent tonne 22.500 27030.00 608175.00 M-074
Filler (lime)@ 2 per cent tonne 9.000 2400.00 21600.00 M-188
Sand of size 4.75 to 0.075 mm - 450 x cum 288.620 160.00 46179.20 M-004
d) 0.93 x 1/1.5 charges @ 10 % on
Overhead 76061.32
(a+b+c)
e) Contractor's profit @ 10 % on 83667.45
(a+b+c+d)
Cost for 205 cum = a+b+c+d+e 920341.97
Rate per cum = (a+b+c+d+e)/205 4489.47
say 4489.00
Note 1. Tack coat will be measured and paid
separately
2. Although the rollers are required only for
3 hours as per norms of output, but the
same have to be available at site for six
hours as the hot mix plant and paver will
take six hours for mixing and paving the
output of 450 tonnes considered in this
analysis. To cater for the idle period of this
roller, their usage rates has been multiplied
5.20 521 by a factorBinder
Modified of 0.65
Supply of modified binder produced by
mixing bitumen with modifier such as
natural rubber or crumb rubber or any other
polymer found compatible with bitumen and
which allows properties given in clause
521.3 and IRC:SP: 53 blending of modifier
with bitumen to be done either at the
refinery or at central unit with all facilities
by
Unitproper industrial process, is essential.
= tonne
The use of modified binder is expected to
result in an extended service life of
bituminous pavements subject to heavy
traffic loads in extreme climatic conditions,
thus justifying the entire cost of adding
modifiers/fibres. Other advantages include
lower temperature susceptibility, higher
resistance to aging, higher fatigue life,
higher resistance to cracking and better
adhesion
Detailed between aggregates
information and binder.
and inductive dose
level on the use of polymer modified binder
is available in IRC : SP-53 / 2002. A number
of proprietary products are now available in
the market. For such proprietary products,
test reports and cost effectiveness should
be the basis for their selection in road
The modifier, in the required quantity shall
be blended at the refinery or at central unit
with all facilities by proper industrial
process, is essential. If supplied in drums it
shall be agitated in melted condition with
suitable device for achieving homogeneity
Proposals to use glass fibre, polypropylene
fibres or any other similar material in a
bituminous mixture should be
substantiated, complete with all details
including test results, manufacturer's
recommendations for addition or means of
incorporating the fibres, homogeneously,

Page 23 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Before agreeing to the use of a fibre, it
should have been proved to be satisfactory
in use under circumstances, similar to the
work, elsewhere or it would have under
gone appropriate performance trials.
Documented evidence of use and trials of
the fibre, in any country having conditions
similar to Indian will be acceptable.
where information on use of trials is
inadequate or lacking, trials may be
required to be under taken before agreeing
to the use of the fibre.
Note 1. The modified binder is usually `
manufactured by specialised firms as a
proprietary product. The rate for this
product is required to be as certained from
the market.
2.The specifications for various item of road
works using polymer/rubber modified
bitumens are same as those for penetration
grade bitumen except those for any special
conditions which the manufacturer may
3.The other controls during mixing, laying
shall be same as specified in IRC - 14, 29,
94 and 95 for open graded premix carpet,
bituminous concrete, DBM and SDBC
respectively
4.The temperature of mixing and rolling will
be slightly higher than conventional
bituminous mixes as indicated in Table 8 of
IRC: SP: 53 - 2002
5.21 522 Crack Prevention Courses
(i) Stress absorbing membrane (SAM)
crack width less than 6 mm
Providing and laying of a stress absorbing
membrane over a cracked road surface,
with crack width below 6 mm after cleaning
with a mechanical broom, using modified
binder complying with clause 521, sprayed
at the rate of 9 kg per 10 sqm and
spreading 5.6 mm crushed stone
aggregates @ 0.11 cum per 10 sqm with
hydraulic chip spreader, sweeping the
surface for uniform spread of aggregates
and surface finished to conform to clause
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 150.00 36.00 L-12
Mazdoor day 6.000 100.00 600.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour 6.000 150.00 900.00 P&M-031
hour
Air compressor 250 cfm hour 6.000 150.00 900.00 P&M-001
Bitumen pressure distributor @ 1750 hour 6.000 580.00 3480.00 P&M-004
sqm per hour
Hydraulic Chip spreader hour 6.000 1200.00 7200.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 170.00 1020.00 P&M-044
c) Material
Modified binder tonne 9.450 29470.00 278491.50 M-078
Crushed stone aggregates 5.6 mm size cum 105.000 350.00 36750.00 M-050
d) Overhead charges @ 10 % on 32937.75
(a+b+c)
e) Contractor's profit @ 10 % on 36231.53
(a+b+c+d)
Cost for 10500 sqm = a+b+c+d+e 398546.78
Rate per sqm = (a+b+c+d+e)/10500 37.96
say 38.00
5.21 (ii) Stress absorbing membrane (SAM)
with crack width 6 mm to 9 mm

Page 24 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Providing and laying of a stress absorbing
membrane over a cracked road surface,
with crack width 6 to 9 mm after cleaning
with a mechanical broom, using modified
binder complying with clause 521, sprayed
at the rate of 11 kg per 10 sqm and
spreading 11.2 mm crushed stone
aggregates @ 0.12 cum per 10 sqm,
sweeping the surface for uniform spread of
aggregates
Unit = sqmand surface finished to conform
Taking output = 10500 sqm
a) Labour
Mate day 0.240 150.00 36.00 L-12
Mazdoor day 6.000 100.00 600.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour 6.000 150.00 900.00 P&M-031
hour
Air compressor 250 cfm capacity hour 6.000 150.00 900.00 P&M-001
Bitumen pressure distributor @ 1750 hour 6.000 580.00 3480.00 P&M-004
sqm per hour
Hydraulic Chip spreader hour 6.000 1200.00 7200.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 170.00 1020.00 P&M-044
c) Material
Modified binder tonne 11.550 29470.00 340378.50 M-078
Crushed stone chipping 11.2 mm size cum 105.000 410.00 43050.00 M-051
d) Overhead charges @ 10 % on 39756.45
(a+b+c)
e) Contractor's profit @ 10 % on 43732.10
(a+b+c+d)
Cost for 10500 sqm = a+b+c+d+e 481053.05
Rate per sqm = (a+b+c+d+e)/10500 45.81
say 46.00
5.21 (iii) Stress absorbing membrane (SAM)
crack width above 9 mm and cracked
area above
Providing 50 laying
and per cent
a single coat of a
stress absorbing membrane over a cracked
road surface, with crack width above 9 mm
and cracked area above 50 per cent after
cleaning with a mechanical broom, using
modified binder complying with clause 521,
sprayed at the rate of 15 kg per 10 sqm and
spreading 11.2 mm crushed stone
aggregates @ 0.12 cum per 10 sqm,
sweeping the surface for uniform spread of
aggregates and surface finished to conform
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 150.00 36.00 L-12
Mazdoor day 6.000 100.00 600.00 L-13
Mazdoor skilled day 2.000 125.00 250.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour 6.000 150.00 900.00 P&M-031
hour
Air compressor 250 cfm capacity hour 6.000 150.00 900.00 P&M-001
Bitumen pressure distributor @ 1750 hour 6.000 580.00 3480.00 P&M-004
sqm per hour
Hydraulic Chip spreader hour 6.000 1200.00 7200.00 P&M-025
Smooth wheeled road roller 8-10 tonne hour 6.000 170.00 1020.00 P&M-044
c) Material
Modified binder tonne 15.750 29470.00 464152.50 M-078
Crushed stone aggregates 11.2 mm size cum 126.000 410.00 51660.00 M-051
d) Overhead charges @ 10 % on 53019.85
(a+b+c)
e) Contractor's profit @ 10 % on 58321.84
(a+b+c+d)
Cost for 10500 sqm = a+b+c+d+e 641540.19
Rate per sqm = (a+b+c+d+e)/10500 61.10
say 61.00

Page 25 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Note In case 2nd coat is also required to be
provided, material provided for the 2nd coat
shall be as per table 500-47.
5.21 (iv) Case - IV : Bitumen impregnated
geotextile
Providing and laying a bitumen
impregnated geotextile layer after cleaning
the road surface, geotextile conforming to
requirements of clause 703.3, laid over a
tack coat with 1.05 kg per sqm of paving
grade bitumen 80 - 100 penetration and
constructed to the requirement of clause
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.560 150.00 84.00 L-12
Mazdoor day 12.000 100.00 1200.00 L-13
Mazdoor skilled day 2.000 125.00 250.00 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour 2.800 150.00 420.00 P&M-031
hour
Air compressor 250 cfm capacity hour 2.800 150.00 420.00 P&M-001
Bitumen pressure distributor @ 1750 tonne 2.000 580.00 1160.00 P&M-004
sqm per hour
Pneumatic roller hour 2.000 1000.00 2000.00 P&M-037
c) Material
Paving grade bitumen of 80 - 100 tonne 3.680 26030.00 95790.40 M-075
penetration @ 1.05 kg per sqm
Geotextile including 10 per cent for sqm 3850.000 300.00 ### M-108
d) overlaps
Overhead charges @ 10 % on 125632.44
(a+b+c)
e) Contractor's profit @ 10 % on 138195.68
(a+b+c+d)
Cost for 10500 sqm = a+b+c+d+e ###
Rate per sqm = (a+b+c+d+e)/3500 434.33
say 434.00
NOTE As bitumen overlay construction shall follow
closely the fabric placement on the same
day, an output of 3500 sqm only has been
considered for the analysis which will cover
a length of 500 m, of 7 m wide carriagway.
This can be conveniently overlaid by a
bitumenious course in a day
5.22 519.3 Recipe Cold Mix
Providing and laying of premix of crushed
stone aggregates and emulsion binder,
mixed in a batch type cold mixing plant,
laid over prepared surface, by paver
finisher, rolled with a pneumatic tyred roller
initially and finished with a smooth steel
wheel roller, all as per clause 519.3
Unit = cum
Taking output = 205 cum (450 tonnes)
(i) 75 mm thickness
a) Labour
Mate day 1.000 150.00 150.00 L-12
Mazdoor day 12.000 100.00 1200.00 L-13
Mazdoor skilled day 5.000 125.00 625.00 L-15
b) Machinery
Batch type cold mixing plant 100-120 hour 6.000 1200.00 7200.00 P&M-064
TPH capacity producing an average
output
Electricof 75 tonne125
generator per KVA
hour hour 6.000 650.00 3900.00 P&M-018
Front end loader 1 cum capacity hour 6.000 700.00 4200.00 P&M-017
Paver finisher hydrostatic with sensor hour 6.000 1500.00 9000.00 P&M-034
control @ 75 cum per hour
Tipper 10 tonne capacity tonne.k 450 x L 1.85 16650.00 Lead =20
m km & P&M-
058

Page 26 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. Add 10 per cent of cost of carriage to 1665.00
cover cost of loading and unloading
Pneumatic tyred roller12-15 tonnes. hour6.00x0.65* 1000.00 3900.00 P&M-037
Smooth wheeled steel roller6-8 tonnes. hour6.00x0.65* 170.00 663.00 P&M-044
Water tanker6 KL capacity hour 1.000 105.00 105.00 P&M-060
c) Material
Bitumen emulsion @ 45 litres per tonne tonne 20.250 24000.00 486000.00 M-077
Crushed stone aggregates 40 mm cum 297.000 350.00 103950.00 M-055
nominal size
Cost of water KL 6.000 50.00 300.00 M-189
d) Overhead charges @ 10 % on 63950.80
(a+b+c)
e) Contractor's profit @ 10 % on 70345.88
(a+b+c+d)
Cost for 10500 sqm = a+b+c+d+e 773804.68
Rate per sqm = (a+b+c+d+e)/205 3774.66
say 3775.00
Note (Case I to III)
1. These mixes are considered suitable for
minor repair work and temporary road
surface improvement.
2. In case concrete mixtures are required to
be used for mixing, a number of these will
be needed to match the capacity of road
rollers.
3. Tack coat, where provided, will be
measured and paid separately.
*4.Both the rollers have to be available at
site to match with the output of batch
mixing plant and paver finisher. A
multiplying factor of 0.65 has been adopted
to cater for the idling period of road rollers.
5.22 (ii) 40 mm thickness
a) Labour
Mate day 1.000 150.00 150.00 L-12
Mazdoor day 12.000 100.00 1200.00 L-13
Mazdoor skilled day 5.000 125.00 625.00 L-15
b) Machinery
Batch type cold mixing plant100-120 hour 6.000 1200.00 7200.00 P&M-064
TPH capacity producing an average
output
Electricof 75 tonne125
generator per KVA
hour hour 6.000 650.00 3900.00 P&M-018
Front end loader 1 cum capacity hour 6.000 700.00 4200.00 P&M-017
Paver finisher hydrostatic with sensor hour 6.000 1500.00 9000.00 P&M-034
control @ 75 cum per hour
Tipper 10 tonne capacity tonne.k 450 x L 1.85 16650.00 Lead =20
m km & P&M-
Add 10 per cent of cost of carriage to 1665.00 058
cover cost of loading and unloading
Pneumatic tyred roller 12-15 tonnes. hour6.00x0.65* 1000.00 3900.00 P&M-037
Smooth wheeled steel roller 6-8 tonnes. hour6.00x0.65* 170.00 663.00 P&M-044
Water tanker6 KL capacity hour 1.000 105.00 105.00 P&M-060
c) Material
Bitumen emulsion @ 70 litres per tonne tonne 31.500 24000.00 756000.00 M-077
Crushed stone aggregates 14 mm cum 287.000 410.00 117670.00 M-052
nominal size
Cost of water KL 6.000 50.00 300.00 M-189
d) Overhead charges @ 10 % on 92322.80
(a+b+c)
e) Contractor's profit @ 10 % on 101555.08
(a+b+c+d)
Cost for 10500 sqm = a+b+c+d+e ###
Rate per sqm = (a+b+c+d+e)/205 5449.30
say 5449.00
5.22 (iii) 25 mm thickness
a) Labour
Mate day 1.000 150.00 150.00 L-12
Mazdoor day 12.000 100.00 1200.00 L-13
Mazdoor skilled day 5.000 125.00 625.00 L-15

Page 27 of 361
Ref.
to
Remarks/
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs
Input ref.
H
Spec. b) Machinery
Batch type cold mixing plant 100-120 hour 6.000 1200.00 7200.00 P&M-064
TPH capacity producing an average
output of
Electric 75 tonne125
generator per KVA
hour hour 6.000 650.00 3900.00 P&M-018
Front end loader 1 cum capacity hour 6.000 700.00 4200.00 P&M-017
Paver finisher hydrostatic with sensor hour 6.000 1500.00 9000.00 P&M-034
control @ 75 cum per hour
Tipper 10 tonne capacity tonne.k 450 x L 1.85 16650.00 Lead =20
m km & P&M-
Add 10 per cent of cost of carriage to 1665.00 058
cover cost of loading and unloading
Pneumatic tyred roller hour6.00x0.65* 1000.00 3900.00 P&M-037
Smooth wheeled steel roller hour6.00x0.65* 170.00 663.00 P&M-044
Water tanker6 KL capacity hour 1.000 105.00 105.00 P&M-060
c) Material
Bitumen emulsion @ 85 litres per tonne tonne 38.250 24000.00 918000.00 M-077
Crushed stone aggregates 6 mm cum 270.000 350.00 94500.00 M-050
nominal size
Cost of water KL 6.000 50.00 300.00 M-189
d) Overhead charges @ 10 % on 106205.80
(a+b+c)
e) Contractor's profit @ 10 % on 116826.38
(a+b+c+d)
Cost for 10500 sqm = a+b+c+d+e ###
Rate per sqm = (a+b+c+d+e)/205 6268.73
say 6269.00

Page 28 of 361
CHAPTER- 6
CEMENT CONCRETE PAVEMENTS
Ref. to Remark
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs s/ Input
Spec. ref.
6.1 601 Dry Lean Cement Concrete Sub- base
Construction of dry lean cement concrete
Sub- base over a prepared sub-grade with
coarse and fine aggregate conforming to IS:
383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio
not to exceed 15:1, aggregate gradation
after blending to be as per table 600-1,
cement content not to be less than 150 kg/
cum, optimum moisture content to be
determined during trial length construction,
concrete strength not to be less than 10
Mpa at 7 days, mixed in a batching plant,
transported to site, laid with a paver with
electronic sensor, compacting with 8-10
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.120 150.00 168.00 L-12
Mazdoor skilled day 6.000 125.00 750.00 L-15
Mazdoor day 22.000 100.00 2200.00 L-13
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-
Cement concrete batch mix plant @ 75 hour 6.000 1500.00 9000.00 017
P&M-
cum per hour 068
Electric generator 100 KVA hour 6.000 600.00 3600.00 P&M-
Paver with electronic sensor hour 6.000 1500.00 9000.00 080
P&M-
Vibratory roller 8-10 t capacity hour 8.000 1000.00 8000.00 034
P&M-
Water tanker6 KL capacity hour 8.000 105.00 840.00 059
P&M-
Tipper tonne.k 990 x L 1.85 36630.00 060
Lead
m =20 km
& P&M-
058
Add 10 per cent of cost of carriage to 3663.00
cover cost of loading and unloading
c) Material
Crushed stone coarse aggregate of 25 cum 405.000 410.00 ### M-052
mm and 12.5 mm nominal sizes graded and M-
as per table 600-1 @ 0.90 cum/cum of 054
concrete conforming to clause 602.2.4.
Coarse Sand as per IS: 383 @ 0.45 cum 203.000 160.00 32480.00 M-004
cum/cum of concrete
Cement @ 150 kg/cum of concrete tonne 67.500 4180.00 ### M-081
Cost of water KL 48.000 50.00 2400.00 M-189
d) Overhead charges @ 10 % on 56113.10
(a+b+c)
e) Contractor's profit @ 10 % on 61724.41
(a+b+c+d)
Cost for 205 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/450 1508.82
say 1509.00
Note Quantity provided for aggregate is for
estimating purpose. Exact quantity shall be
6.2 602 as per mix
Cement design. Pavement
Concrete
Construction of un-reinforced, dowel
jointed, plain cement concrete pavement
over a prepared sub base with 43 grade
cement @ 400 kg per cum, coarse and fine
aggregate conforming to IS 383, maximum
size of coarse aggregate not exceeding 25
mm, mixed in a batching and mixing plant
as per approved mix design, transported to
site, laid with a fixed form or slip form
paver, spread, compacted and finished in a
continuous operation including provision of
contraction, expansion, construction and
longitudinal joints, joint filler, separation
membrane, sealant primer, joint sealant,
debonding strip, dowel bar, tie rod,
admixtures as approved, curing compound,
Page 1 of 361
Ref. to Remark
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs s/ Input
Spec. ref.
Unit = cum
Taking output = 1050 cum (2415
tonne)
a) Labour
Mate day 2.000 150.00 300.00 L-12
Mazdoor skilled day 15.000 125.00 1875.00 L-15
Mazdoor day 35.000 100.00 3500.00 L-13
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 150.00 420.00 P&M-
Front end loader 1 cum bucket capacity hour 18.000 700.00 12600.00 031
P&M-
Cement concrete batch mix plant @ hour 6.000 6000.00 36000.00 017
P&M-
175 cum per hour (effective output) 067
Electric generator 250 KVA hour 6.000 750.00 4500.00 P&M-
Slip form paver with electronic sensor hour 6.000 1600.00 9600.00 081
P&M-
Water tanker6 KL capacity hour 36.000 105.00 3780.00 006
P&M-
Transit truck agitator 5 cum capacity. tonne.k 2415xL 1.85 89355.00 060
Lead
m =20 km
& P&M-
058
Add 10 per cent of cost of carriage to 8935.50
cover cost of loading and unloading
Concrete joint cutting machine . hour 12.000 150.00 1800.00 P&M-
Texturing machine . hour 12.000 200.00 2400.00 083
P&M-
c) Material 088
Crushed stone coarse aggregates of cum 945.000 410.00 ### M-052
25mm and 12.5mm nominal size @ and M-
0.90 cum/cum of concrete conforming 054
to clause 602.2.4. .
Sand as per IS: 383 and conforming to cum 473.000 160.00 75680.00 M-004
clause 602.2.4 @ 0.45 cum/cum of
concrete
Cement 43 grade @ 400 kg/cum of tonne 414.000 4180.00 ### M-081
concrete
32 mm mild steel dowel bars of grade S tonne 9.450 30000.00 ### M-126
240
16 mm deformed steel tie bars of grade tonne 1.170 34500.00 40365.00 M-082
S 415
Separation Membrane of impermeable sqm 3675.000 15.00 55125.00 M-164
plastic sheeting 125 micron thick
Pre moulded Joint filler, 25 mm thick for sqm 16.330 210.00 3429.30 M-141
expansion joint.
Joint sealant kg 875.000 550.00 ### M-120
Sealant primer kg 116.670 300.00 35001.00 M-097
Plastic sheath,1.25 mm thick for dowel sqm 46.670 60.00 2800.20 M-138
bars
Curing compound liter 1850.000 70.00 ### M-090
Super plastisizer admixture IS marked kg 2070.000 50.00 ### M-180
as per 9103-1999 @ 0.5 per cent by
weight
Cost of of cement
water KL 216.000 50.00 10800.00 M-189
Add 1 per cent of material for cost of 33389.21
miscellaneous materials like tarpauline,
Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel
bars, work bridges for men to approach
concrete surface without walking over it,
cutting blades and bites, minor equipments
like scabbling machine, threads, ropes,
guide
d) wires andcharges
Overhead any other
@ 10unforeseen
% on ###
(a+b+c)
e) Contractor's profit @ 10 % on ###
(a+b+c+d)
Cost for 1050cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/1050 4087.93
say 4088.00
Note The quantities for cement, coarse
aggregate and fine aggregates are for
estimating only .The exact quantities will be
as per mix design.
6.3 603 Rolled Cement Concrete Base

Page 2 of 361
Ref. to Remark
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs s/ Input
Spec. ref.
Construction of rolled cement concrete base
course with coarse and fine aggregate
conforming to IS:383, the size of coarse
aggregate not exceeding 25 mm with
minimum, aggregate cement ratio15:1 and
minimum cement content of 200 kg/cum,
aggregate gradation to be as per table 600-
4 after blending, mixing in batching plant at
optimum moisture content, transporting to
site, laying with a paver with electronic
sensor, compacting with 8-10 tonnes
smooth wheeled vibratory roller to achieve,
the designed flexural strength, finishing and
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.200 150.00 180.00 L-12
Mazdoor skilled day 7.000 125.00 875.00 L-15
Mazdoor day 23.000 100.00 2300.00 L-13
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-
Cement concrete batch mix plant @ 75 hour 6.000 1500.00 9000.00 017
P&M-
cum per hour 068
Electric generator 100 KVA hour 6.000 600.00 3600.00 P&M-
Paver with electronic sensor @ 75 hour 6.000 1500.00 9000.00 080
P&M-
cum/hr. roller 8-10 t capacity
Vibratory hour 8.000 1000.00 8000.00 034
P&M-
Water tanker with 5 km lead 6 KL hour 8.000 105.00 840.00 059
P&M-
capacity
Tipper tonne.k 990xL 1.85 36630.00 060
Lead
m =20 km
& P&M-
058
Add 10 per cent of cost of carriage to 3663.00
cover cost of loading and unloading
c) Material
Crushed stone coarse aggregates of cum 405.000 410.00 ### M-052
25mm and 12.5mm nominal size @ and M-
0.90 cum/cum of concrete conforming 054
to clause 602.2.3.
Sand as per IS: 383 and conforming to cum 203.000 160.00 32480.00 M-004
clause 602.2.3 @ 0.45 cum/cum of
concrete
Cement @ 200 kg/cum of concrete tonne 90.000 4180.00 ### M-081
Cost of water KL 48.000 50.00 2400.00 M-189
d) Overhead charges @ 10 % on 65541.80
(a+b+c)
e) Contractor's profit @ 10 % on 72095.98
(a+b+c+d)
Cost for 450cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/450 1762.35
say 1762.00
Note The quantities for cement, coarse
aggregate and fine aggregates are for
estimating only .The exact quantities will be
as per mix design.
6.4 New Transition Section between Rigid and
Flexible Pavement
Due to change in the properties of materials
and type of construction, a gradual
changeover from rigid pavement to flexible
pavement is desirable to avoid any damage
at the butting joint. After provision of an
expansion joint in the cement concrete
slab, the thickness of slab should be
tapered to 10 cm over a length of 3 m
towards the flexible pavement. The
deficiency of thickness caused due to
tapering of the slab should be made up by
The quantities of items should be worked
out based on the approved design and
drawings and priced as per rates given
under respective clauses for cement
concrete and asphaltic work.

Page 3 of 361
Ref. to Remark
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs s/ Input
Spec. ref.
6.5 Suggesti Construction of Base/Sub-Base of
ve Pavement with Lean Concrete - Flyash.
Construction of Base/sub-base using
cement, sand, fly ash and coarse
aggregates proportioned as per table 4 of
IRC: 74/1979 and with water content ratio,
slump and compressive strength as defined
in the said table, mix prepared in a batching
and mixing plant and compacted with a
vibratory roller 8-10 tonnes capacity within
the time limit laid down vide clause 7.6.3 of
IRC: 74-1979, construction joints properly
formed at the end of day's work, cured for
14 days, all as specified in IRC: 74-1979
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.120 150.00 168.00 L-12
Mazdoor skilled day 6.000 125.00 750.00 L-15
Mazdoor day 22.000 100.00 2200.00 L-13
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 700.00 4200.00 P&M-
Cement concrete batch mix plant @ 75 hour 6.000 1500.00 9000.00 017
P&M-
cum per hour 068
Electric generator 100 KVA hour 6.000 600.00 3600.00 P&M-
Paver finisher with electronic sensor hour 6.000 1500.00 9000.00 080
P&M-
Vibratory roller 8-10 t capacity hour 8.000 1000.00 8000.00 034
P&M-
Water tanker6 KL capacity hour 8.000 105.00 840.00 059
P&M-
Tipper 10 T Capacity tonne.k 990 x L 1.85 36630.00 060
Lead
m =20 km
& P&M-
058
Add 10 per cent of cost of carriage to 3663.00
cover cost of loading and unloading
c) Material
Crushed stone coarse aggregate of 40 cum 405.000 350.00 ### M-055
mm nominal size @ 0.90 cum/cum of
concrete conforming to table 2 of IRC:
74-1979.
Coarse Sand as per IS: 383 - 1970 cum 110.960 160.00 17753.60 M-004
Cement @ 150 kg/cum of concrete tonne 67.500 4180.00 ### M-081
Fly ash conforming to IS: 3812 ( Part II ) cum 91.540 150.00 13731.00 M-011
( Total fine aggregates = 450 x 0.45 =
202.50 cum To be divided in ratio of 2
sand : 1.65 flyash. Refer table 4 of IRC: 74-
1979).
d) Overhead charges @ 10 % on 53343.56
(a+b+c)
e) Contractor's profit @ 10 % on 58677.92
(a+b+c+d)
Cost for 450cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/450 1434.35
say 1434.00
Note 1.Depending upon approved designs,
crushed stone aggregates of nominal size
20mm can also be used as per gradation
given in table 2 of IRC: 74-1979.
2.The ratio of specific gravities of fly ash
and sand has been assumed to be 0.827.
3.The quantities of materials given in the
analyses are for estimating purposes.
Actual quantities shall be as per job mix
formula.
4.Construction procedure as laid down in
clause, of IRC: 74-1979 shall be followed.
6.6 Suggesti Cement - Flyash Concrete Pavement.
ve

Page 4 of 361
Ref. to Remark
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs s/ Input
Spec. ref.
Construction reinforced-reinforced, dowel
jointed, plain cement concrete pavement
over a prepared sub base with 43 grade
cement, coarse and fine aggregate
conforming to IS 383, maximum size of
coarse aggregate not exceeding 25 mm,
replacing cement by fly ash to the extent of
15 per cent and sand by 10 per cent,
mixed in a batching and mixing plant as per
approved mix design, transported to site,
laid with a fixed form or slip form paver,
spread, compacted and finished in a
continuous operation including provision of
contraction, expansion, construction and
longitudinal joints, joint filler, separation
membrane, sealant primer, joint sealant,
debonding strip, dowel bar, tie rod,
admixtures as approved, curing compound,
Unit = cum
Taking output = 1050 cum (2415
tonne)
a) Labour
Mate day 2.000 150.00 300.00 L-12
Mazdoor skilled day 15.000 125.00 1875.00 L-15
Mazdoor day 35.000 100.00 3500.00 L-13
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 150.00 420.00 P&M-
Front end loader 1 cum bucket capacity hour 18.000 700.00 12600.00 031
P&M-
Cement concrete batch mix plant @ hour 6.000 6000.00 36000.00 017
P&M-
175 cum per hour (effective output) 067
Electric generator 250 KVA hour 6.000 750.00 4500.00 P&M-
Slip form paver with electronic sensor hour 6.000 1600.00 9600.00 081
P&M-
Water tanker6 KL capacity hour 36.000 105.00 3780.00 006
P&M-
Transit truck agitator 5 cum capacity. tonne.k 2415xL 1.85 89355.00 060
P&M-
m 050
Lead=
20 km
Add 10 per cent of cost of carriage to 8935.50
cover cost of loading and unloading
Concrete joint cutting machine . hour 12.000 150.00 1800.00 P&M-
Texturing machine . hour 12.000 200.00 2400.00 083
P&M-
c) Material 088
Crushed stone coarse aggregates of cum 945.000 410.00 ### M-052
25mm and 12.5mm nominal size @ and M-
0.90 cum/cum of concrete conforming 054
to clause 602.2.4. .
Sand as per IS: 383 and conforming to cum 425.000 160.00 68000.00 M-004
clause 602.2.4
Cement 43 grade tonne 357.000 4180.00 ### M-081
Fly ash conforming to IS: 3812-1966 tonne 109.000 150.00 16350.00 M-011
(Part-I)
32 mm mild steel dowel bars of grade S tonne 9.450 30000.00 ### M-126
240
16 mm deformed steel tie bars of grade tonne 1.170 34500.00 40365.00 M-082
S 415
Separation Membrane of impermeable sqm 3675.000 15.00 55125.00 M-164
plastic sheeting 125 micron thick
Pre moulded Joint filler, 25 mm thick for sqm 16.330 210.00 3429.30 M-141
expansion joint.
Joint sealant kg 875.000 550.00 ### M-120
Sealant primer kg 116.670 300.00 35001.00 M-097
Plastic sheath,1.25 mm thick for dowel sqm 46.670 60.00 2800.20 M-138
bars
Curing compound liter 1850.000 70.00 ### M-090
Super plastisizer admixture IS marked kg 2070.000 50.00 ### M-180
as per 9103-1999 @ 0.5 per cent by
weight
Cost of of cement
water KL 216.000 50.00 10800.00 M-189

Page 5 of 361
Ref. to Remark
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs s/ Input
Spec. ref.
Add 1 per cent of material for cost of 27218.81
miscellaneous materials like tarpauline,
Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel
bars, work bridges for men to approach
concrete surface without walking over it,
cutting blades and bites, minor equipments
like scabbling machine, threads, ropes,
guide
d) wires andcharges
Overhead any other
@ 10unforeseen
% on ###
(a+b+c)
e) Contractor's profit @ 10 % on ###
(a+b+c+d)
Cost for 1050cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/1050 3816.24
say 3816.00
Note 1.The quantities for cement, coarse
aggregate and fine aggregates are for
estimating only .The exact quantities will be
as per mix design.
2.IRC: 68-1976 may be referred for
guidelines on the design of cement-fly ash
concrete for rigid pavement construction.
*Calculation of cement, sand and fly
ash.
Cement @ 400 kg/cum = 1050 x 400 =
420 tonnes. 15 per cent of cement to
be replaced by fly ash = 63 tonnes.
Balance cement = 357 tonnes.
Quantity of fly ash = 63 x specific
gravity of fly ash /specific gravity of
Sand @ 0.45 cum / cum of concrete =
1050 x 0.45 = 472.50 x 1.6 = 756
tonnes.10 per cent to be replaced by
flyash. Balance sand = 756 x 0.9 =
680.4 tonnes = 680.4 / 1.6 = 425 cum.
Quantity of flyash = (756-680.4) x
specific gravity of fly ash/specific
gravity of sand = 76.4 x 2.25 / 2.687 =
63.97
Fly ashtonnes (say
Total fly 64=tonnes)
ash 45 + 64 = 109
tonnes.

Page 6 of 361
CHAPTER-7
Ref. GEOSYNTHETICS AND REINFORCED EARTH
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
7.1 Spec.
702 Sub-Surface Drain with Geotextiles
Construction of sub surface drain 200 mm
dia using geotextiles treated with carbon
black with physical properties as given in
clause 702.2.3 formed in to a stable
network and a planar geocomposite
structure, joints wrapped with geotextile to
prevent ingress of soil, all as per clause 702
and approved drawings including
excavation
Unit and backfilling
= Running metre
Taking output = one metre
a) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoor skilled day 0.250 125.00 31.25 L-15
Mazdoor day 0.500 100.00 50.00 L-13
b) Material
Geonets, geomembrane and geotextile to
make planar geocomposite stable network
for sub surface drain including wrapping of
joints with 160 mm over lapping with
geotextile .
Geonets sqm 1.000 450.00 450.00 M-107
Geomembrane sqm 1.000 750.00 750.00 M-106
Geotextile sqm 2.000 300.00 600.00 M-108
Add 2 per cent cost of material for 36.00
miscellaneous items like synthetic cord
c) Overhead charges @ 10 % on 192.33
(a+b)
d) Contractor's profit @ 10 % on 211.56
(a+b+c)
Rate per metre = a+b+c+d 2327.13
say 2327.00
Note Surplus excavated material to be used at
site. Hence seprate cost for disposal not
7.2 702.4 added. Filter Sub-Surface Drain
Narrow
Construction of a narrow filter sub- surface
drain consisting of porous or perforated
pipe laid in narrow trench surrounded by a
geotextile filter fabric, with a minimum of
450 mm overlap of fabric and installed as
per clause 702.3 and 309.3.5 including
excavation and backfilling
Unit = Running metre length
Taking output = one metre
a) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoor skilled day 0.250 125.00 31.25 L-15
Mazdoor day 0.500 100.00 50.00 L-13
b) Material
Perforated geosynthetic pipe 150 mm metre 1.000 200.00 200.00 M-134
dia
Geotextile filter fabric sqm 1.250 250.00 312.50 M-109
Add 2 per cent cost of material for 10.25
miscellaneous item like synthetic cord
c) Overhead charges @ 10 % on 61.00
(a+b)
d) Contractor's profit @ 10 % on 67.10
(a+b+c)
Rate per metre = a+b+c+d 738.10
say 738.00
Note Surplus excavated material to be used at
site. Hence Separate cost for disposal not
7.3 703 added.
Laying Paving Fabric Beneath a
Pavement Overlay

Page 1 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Providing and laying paving fabric with
physical requirements as per table 704-2
over a tack coat of paving grade Bitumen
80-100 penetration, laid at the rate of 1 kg
per sqm over thoroughly cleaned and
repaired surface to provide a water
resistant membrane and crack retarding
layer. Paving fabric to be free of wrinkling
and folding and to be laid before cooling of
tack coat, brooming and rolling of surface
with pneumatic roller to maximise paving
fabric contact with pavement surface
Unit = sqm
Taking output = 2800 sqm
a) Labour
Mate day 0.800 150.00 120.00 L-12
Mazdoor day 20.000 100.00 2000.00 L-13
b) Machinery
Road sweeper 1250 sqm per hour hour 2.240 150.00 336.00 P&M-
Pneumatic roller 14 tonnes 2000 sqm hour 1.400 1000.00 1400.00 031
P&M-
per hour pressure distributor 1750 sqm
Bitumen hour 1.680 580.00 974.40 037
P&M-
c) perMaterial
hour 004
Paving Fabric sqm 2940.000 150.00 ### M-133
Paving Bitumen 80-100 tonne 2.800 26030.00 72884.00 M-075
c) Overhead charges @ 10 % on 51871.44
(a+b)
d) Contractor's profit @ 10 % on 57058.58
(a+b+c)
Cost for 2800 sqm = a+b+c+d+e ###
Rate per sqm =(a+b+c+d+e)/2800 224.16
say 224.00
7.4 704 Laying Boulder Apron in Crates of
Synthetic Geogrids
Providing, preparing and laying of geogrid
crated apron 1 m x 5 m, 600 mm thick
including excavation and backfilling with
baffles at 1 metre interval, made with
geogrids having characteristics as per
clause 704.2, joining sides with
connectors/ring staples, top corners to be
tie tensioned, placing of suitable cross
interval ties in layers of 300 mm connecting
opposite side with lateral braces and tied
with polymer braids to avoid bulging,
constructed as per clause 704.3. filled with
stone with minimum size of 200 mm and
specific gravity not less than 2.65, packed
with stone spalls, keyed to the foundation
recess in case of sloping ground and laid
over a layer of geotextile to prevent
migration of fines, all as per clause 704 and
Unit = cum
Taking output = 3.00 cum
a) Labour
Mate day 0.060 150.00 9.00 L-12
Mazdoor skilled day 0.500 125.00 62.50 L-15
Mazdoor day 1.500 100.00 150.00 L-13
b) Material
Geo grids sqm 21.000 500.00 10500.00 M-105
Connectors/ Staples each 50.000 50.00 2500.00 M-085
Polymer braids metre 20.000 175.00 3500.00 M-140
Stones with minimum size of 200 mm cum 3.450 265.00 914.25 M-003
Stones spall for filling voids cum 0.450 160.00 72.00 M-008
c) Overhead charges @ 10 % on 1770.78
(a+b)
d) Contractor's profit @ 10 % on 1947.85
(a+b+c)
Cost for 3 cum = a+b+c+d 21426.38
Rate per cum = (a+b+c+d)/ 3 1648.18
say 1648.00
7.5 3100 Reinforced Earth Structures

Page 2 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Reinforced earth Structures have four main
components as under:
a) Excavation for foundation, foundation
concrete and cement concrete grooved
seating in the foundation for facing
elements (facia material).
b) Facia material and its placement.
c) Assembling, joining with facing
elements and laying of the reinforcing
elements.
d) Earth fill with granular material which
is to be retained by the wall.
Each component is analysed
separately Average
considering as under:
height of wall = 8 m.
7.5 3102 (i) Assembling, joining and laying of
reinforcing elements.
A With reinforcing element of steel /
Aluminium strips / polymeric strips.
Unit = Running Metre
Taking Output = 450 m
a) Labour
Mate day 0.360 150.00 54.00 L-12
Mazdoor day 6.000 100.00 600.00 L-13
Mazdoor skilled day 3.000 125.00 375.00 L-15
b) Material
@ Reinforcement strips 60 mm wide 5 mm
thick as per clause 3102.
1.Galvanised carbon steel strips metre 450*1.1 155.00 76725.00 M-154
or
2.Copper Strips metre 450*1.1 240.00 ### M-153
or
3.Aluminium Strips metre 450*1.1 200.00 99000.00 M-157
or
4.Stainless steel strips metre 450*1.1 250.00 ### M-156
or
5.Glass reinforced polymer/fibre metre 450*1.1 140.00 69300.00 M-155
reinforced polymer/polymeric strips
@ Any one of the above alternative may be
adopted as per approved design.
Add 10 per cent of the cost of reinforcing
strip towards accessories like tie-strips, nuts
and bolts and loops/lugs for joining
reinforcing elements with the facia pannels,
overlaps, heat bonding or extension.
Type 1 1.Galvanised carbon steel strips
c) Overhead charges @ 10 % on 7775.40
(a+b)
d) Contractor's profit @ 10 % on 7775.40
(a+b+c)
Cost of 450 m = a+b+c+d 93304.80
Rate per metre =(a+b+c+d)/450 207.34
say 207.00
Type 2 2.Copper Strips
c) Overhead charges @ 10 % on 11982.90
(a+b)
d) Contractor's profit @ 10 % on 11982.90
(a+b+c)
Cost of 450 m = a+b+c+d ###
Rate per metre =(a+b+c+d)/450 319.54
say 320.00
Type 3 3.Aluminium Strips
c) Overhead charges @ 10 % on 10002.90
(a+b)
d) Contractor's profit @ 10 % on 10002.90
(a+b+c)
Cost of 450 m = a+b+c+d ###
Rate per metre =(a+b+c+d)/450 266.74
say 267.00

Page 3 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Type 4 4.Stainless steel strips
c) Overhead charges @ 10 % on 12477.90
(a+b)
d) Contractor's profit @ 10 % on 12477.90
(a+b+c)
Cost of 450 m = a+b+c+d ###
Rate per metre =(a+b+c+d)/450 332.74
say 333.00
Type 5 5.Glass reinforced polymer/fibre
reinforced polymer/polymeric strips
c) Overhead charges @ 10 % on 7032.90
(a+b) Contractor's profit @ 10 % on
d) 7032.90
(a+b+c)
Cost of 450 m = a+b+c+d 84394.80
Rate per metre =(a+b+c+d)/450 187.54
say 188.00
7.5(i) B With reinforcing elements of synthetic
geogrids
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 0.360 150.00 54.00 L-12
Mazdoor day 6.000 100.00 600.00 L-13
Mazdoor skilled day 3.000 125.00 375.00 L-15
b) Material
Synthetic Geogrids as per clause sqm 300.000 350.00 ### M-181
3102.8 and approved design and
specifications.
Add 10 per cent of the cost of 10500.00
reinforcing elements (synthetic
geogrids) for accessories like tie-strips,
nuts and bolts and loops/lugs for joining
reinforcing elements with the facia
pannels, overlaps and other protective
c) Overhead charges @ 10 % on 11652.90
(a+b)
d) Contractor's profit @ 10 % on 12818.19
(a+b+c)
Cost of 300 sqm of Synthetic geogrids = ###
a+b+c+d
Rate per sqm = (a+b+c+d)/ 300 470.00
say 470.00
7.5 3104 (ii) Facing elements of RCC
Unit = sqm
Taking output = 75 sqm
a) Labour
Mate day 0.180 150.00 27.00 L-12
Mazdoor day 3.000 100.00 300.00 L-13
Mazdoor skilled day 1.500 125.00 187.50 L-15
b) Machinery
Light crane with lifting capacity upto 3 hour 6.000 225.00 1350.00 P&M-
c) tonne
Material 013
Pre-cast RCC M-35 facing elements of cu.m 13.500 2723.00 36760.50 Item
size as per design and 18 cm thick for 12.8 (H)
75 sqm. (Refer Item 12.8 (H))
HYSD steel @ 5 kg / sqm (Refer Item tonnes 0.380 45334.00 17226.92 Item
Add 12.6)
2 per cent of cost of facia pannels, for 1079.75 13.6
all necessary temporary form work,
scaffolding and provision of loops/lugs for
lifting of pannels and joining the reinforcing
elements.
d) Overhead charges @ 10 % on 186.45
(a+b)
e) Contractor's profit @ 10 % on 205.10
(a+b+d)
Cost for 75 sqm = a+b+c+d+e 57323.21
Rate per sqm = (a+b+c+d+e)/ 75 764.31
say 764.00
Note 1.The specification and construction details
to be adopted shall be as per section 3100
of MoRTH Specification.

Page 4 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 2.Drainage arrangement shall be made as
per approved design and drawings.
3.The quantity of filler media shall be
calculated as per approved design and
specifications and shall be priced
separately.The rate for same to be adopted
from chapter 15.
4.Excavation for foundation including
foundation concrete and groove in the
foundation for seating of bottom most facia
panel and capping beam to be calculated as
per design and priced separately. The rates
for excavation and foundation concrete
shall be taken from the chapter 12 & 13 in
5.The earth fill to be retained is not
included in this analysis. The same is to be
worked out and provided separately
complete as per clause 305.
, 6.For compaction of Earthwork, attention is
invited to clause 3105.5 of MoRTH
7.Length of reinforcing strips will vary with
Specification.
the height of wall and will be as per
approved design and drawings.
8.The type of reinforcing elements to be
adopted shall be as per approved design
and
9.Thespecifications.
market rate for supply of reinforcing
elements and their accessories are to be
ascertained from reputed firms in the field
of earth reinforcement.
10.The earth fill material shall be clean,
free draining, granular with high friction and
low cohesion, non-corrosive, coarse grained
with not 10 per cent of particles passing 75
micron sieve, free of any deleterious
matter, chlorides, salts, acids, alkalies,
mineral oil, fungus and microbes and shall
be of specified PH value.
11.Capping beam is to be priced separately
as per approved design. The rate for
cement concrete shall be taken from the
chapter of sub-structure in bridge section.
12.The cost of reinforced earth retaining
wall shall include following:
(I) Excavation for foundation including
backfilling.
(ii) Foundation concrete as per approved
design.
(iii) Cost of facial pannels and their
erection
(iv) Cost .of reinforcing elements including
their fixing and joining with the facial
pannels.
(v) Drainage arrangement including filter
media as per approved design and
drawings.
13. The compacted earth filling to be
retained shall form part of embankment.

Page 5 of 361
CHAPTER-8
Ref. TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Cast in Situ Cement Concrete M20
8.1 Spec.
408
Kerb
Construction of cement concrete kerb with
top and bottom width 115 and 165 mm
respectively, 250 mm high in M 20 grade
PCC on M-10 grade foundation 150 mm
thick, foundation having 50 mm projection
beyond kerb stone, kerb stone laid with
kerb laying machine, foundation concrete
laid manually, all complete as per clause
408
Unit = Running metre
Taking output = 360 metre
A. Using Concrete Mixer
Cement Concrete
Cement concrete of grade M20 = 12.60
cum
Cement concrete of grade M10 for base=
11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.720 150.00 108.00 L-12
Mason day 2.000 250.00 500.00 L-11
Mazdoor day 16.000 100.00 1600.00 L-13
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 200.00 1200.00 P&M-
Concrete mixer 0.48/0.28 cum capacity hour 12.000 100.00 1200.00 029
P&M-
Water tanker6 KL capacity hour 5.000 105.00 525.00 009
P&M-
c) Material 060
Crushed stone aggregate 20 mm 410.00 8933.90 M-053
cum 21.790
nominal size 59 per cent
Coarse sand 30 per cent cum 10.900 350.00 3815.00 M-005
Cement 11 per cent tonne 5.700 4180.00 23826.00 M-081
Cost of water KL 30.000 50.00 1500.00 M-189
d) Overhead charges @ 10 % on
4320.79
(a+b+c)
e) Contractor's profit @ 10 % on
4752.87
(a+b+c+d)
Cost for 360 meter = a+b+c+d+e 52281.56
Rate per metre = (a+b+c+d+e)/360 145.23
say 145.00
Using Concrete Batching and Mixing
B
Plant
Cement Concrete
Cement concrete of grade M20 = 12.60
cum
Cement concrete of grade M10 for base =
11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.120 150.00 18.00 L-12
Mason day 1.000 250.00 250.00 L-11
Mazdoor day 2.000 100.00 200.00 L-13
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 200.00 1200.00 P&M-
Concrete batching and mixing plant @ 029
hour 1.600 1200.00 1920.00 P&M-
15 cum/hr.
Water tanker6 KL capacity hour 5.000 105.00 525.00 003
P&M-
Tipper 5.5 cum capacity hour 6.000 185.00 1110.00 060
P&M-
c) Material 048
Crushed stone aggregate 20 mm 410.00 8933.90 M-053
cum 21.790
nominal size 59 per cent
Coarse sand 30 per cent cum 10.900 160.00 1744.00 M-004
Cement 11 per cent tonne 5.700 4180.00 23826.00 M-081
Cost of water KL 30.000 50.00 1500.00 M-189
d) Overhead charges @ 10 % on
4122.69
(a+b+c)
e) Contractor's profit @ 10 % on
4534.96
(a+b+c+d)
Cost for 360 meter = a+b+c+d+e 49884.55
Rate per metre = (a+b+c+d+e)/360 138.57
say 139.00
Cast in Situ Cement Concrete M 20
8.2 408
Kerb with Channel

Page 1 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Construction of cement concrete kerb with
channel with top and bottom width 115 and
165 mm respectively, 250 mm high in M 20
grade PCC on M10 grade foundation 150
mm thick, kerb channel 300 mm wide, 50
mm thick in PCCM20 grade, sloped towards
the kerb, kerb stone with channel laid with
kerb laying machine, foundation concrete
laid manually, all complete as per clause
408
A Using Concrete Mixer
Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base =
23.18 cum
Total Concrete = 40.66 cum
a) Labour
Mate day 0.720 150.00 108.00 L-12
Mason day 2.000 250.00 500.00 L-11
Mazdoor day 16.000 100.00 1600.00 L-13
b) Machinery
Kerb casting machine @ 50 metres/hour 200.00 1200.00 P&M-
hour 6.000
for laying kerb and channel 029
Concrete mixer 0.48/0.28 hour 16.000 100.00 1600.00 P&M-
Water tanker6 KL capacity hour 6.000 105.00 630.00 009
P&M-
c) Material 060

Crushed stone aggregate 20 mm 410.00 15001.90 M-053


cum 36.590
nominal size 60 per cent
Coarse sand 30 per cent cum 18.300 350.00 6405.00 M-005
Cement 10 per cent tonne 9.010 4180.00 37661.80 M-081
Cost of water KL 36.000 50.00 1800.00 M-189
d) Overhead charges @ 10 % on
6650.67
(a+b+c)
e) Contractor's profit @ 10 % on
7315.74
(a+b+c+d)
Cost for 360 meter = a+b+c+d+e 80473.11
Rate per metre = (a+b+c+d+e)/300 268.24
say 268.00
Using Concrete Batching and Mixing
8.2 B
Plant
Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base =
23.18 cum
Total Concrete = 40.66 cum
a) Labour
Mate day 0.120 150.00 18.00 L-12
Mason day 1.000 250.00 250.00 L-11
Mazdoor day 2.000 100.00 200.00 L-13
b) Machinery
Kerb casting machine @ 50 metres/hour 200.00 1200.00 P&M-
hour 6.000
for laying kerb and channel 029
Concrete batching and mixing plant @
hour 2.700 1200.00 3240.00 P&M-
15 cum/hr.
Water tanker6 KL capacity hour 6.000 105.00 630.00 003
P&M-
Tipper of 5.5 cum capacity hour 6.000 185.00 1110.00 060
P&M-
c) Material 048

Crushed stone aggregate 20 mm 410.00 15001.90 M-053


cum 36.590
nominal size 60 per cent
Coarse sand 30 per cent cum 18.300 160.00 2928.00 M-004
Cement 10 per cent tonne 9.010 4180.00 37661.80 M-081
Cost of water KL 36.000 50.00 1800.00 M-189
d) Overhead charges @ 10 % on
6403.97
(a+b+c)

Page 2 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. e) Contractor's profit @ 10 % on
7044.37
(a+b+c+d)
Cost for 300 meter = a+b+c+d+e 77488.04
Rate per metre = (a+b+c+d+e)/300 258.29
say 258.00
Printing New Letter and Figures of any
8.3 801
Shade
Printing new letter and figures of any shade
with synthetic enamel paint black or any
other approved colour to give an even
shade
Hindi ( Matras commas and the like not to
(i) be measured and paid for Half letter shall
be counted as half )
Details for 100 letters of 16 cm height
i.e. 1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.120 150.00 18.00 L-12
Painter day 2.000 200.00 400.00 L-18
Mazdoor day 1.000 100.00 100.00 L-13
b) Material
Paint Litre 0.700 135.00 94.50 M-131
c) Overhead charges @ 10 % on
61.25
(a+b)
d) Contractor's profit @ 10 % on
67.38
(a+b+c)
Cost for 1600 cm = a+b+c+d 741.13
Rate per cm height per letter =
0.46
(a+b+c+ d)/1600
say 0.50
8.3 (ii) English and Roman
Hyphens and the like not to be measured
and paid
Detail forfor100 letters of 16 cm height.
i.e.1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.070 150.00 10.50 L-12
Painter Ist class day 1.250 200.00 250.00 L-18
Mazdoor day 0.500 100.00 50.00 L-13
b) Material
Paint Litre 0.500 135.00 67.50 M-131
c) Overhead charges @ 10 % on
37.80
(a+b)
d) Contractor's profit @ 10 % on
41.58
(a+b+c)
Cost for 1600 cm = a+b+c+d 457.38
Rate per cm height per letter = (a+b+c
0.29
+d)/1600
say 0.30
8.4 801 Retro-Reflectorised Traffic Signs
Providing and fixing of retro- reflectorised
cautionary, mandatory and informatory sign
as per IRC :67 made of high intensity grade
sheeting vide clause 801.3, fixed over
aluminium sheeting, 1.5 mm thick
supported on a mild steel angle iron post 75
mm x 75 mm x 6 mm firmly fixed to the
ground by means of properly designed
foundation with M15 grade cement
concrete 45 cm x 45 cm x 60 cm, 60 cm
below ground level as per approved
drawing
Unit = Each
Taking output = one traffic sign
103.00 22.25 Item No.
i) Excavation for foundation cum 0.216
3.13
2595.00 311.40 Item
ii) Cement concrete M15 grade cum 0.120
12.8 (A)
iii) Painting angle iron post two
sqm 0.430 35.00 15.05 Item 8.9
coats
a) Labour (For fixing at site)
Mate day 0.010 150.00 1.50 L-12
Mazdoor day 0.250 100.00 25.00 L-13

Page 3 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. b) Material
32.00 608.00 M-179 /
Mild steel angle iron 75 x 75 x 6 mm kg 19.000
1000
Aluminium sheeting fixed with encapsulated
lens type reflective sheeting of size
including lettering and signs as applicable
Add 2 per cent of cost of angle iron
towards cost of drilling holes, nuts, bolts
etc.
(i) 90 cm equilateral triangle sqm 0.350 1500.00 525.00 M-061
or
( ii ) 60 cm equilateral triangle sqm 0.156 1500.00 234.00 M-061
or
( iii ) 60 cm circular sqm 0.283 1500.00 424.50 M-061
or
( iv ) 80 mm x 60 mm rectangular sqm 0.480 1500.00 720.00 M-061
or
(v) 60 cm x 45 cm rectangular sqm 0.270 1500.00 405.00 M-061
or
(vi ) 60 cm x 60 cm square sqm 0.360 1500.00 540.00 M-061
or
( vii ) 90 cm high octagon sqm 0.672 1500.00 1008.00 M-061
c) Machinery
Tractor-trolley hour 0.010 150.00 1.50 P&M-
(i) 90 cm equilateral triangle 053
d) Overhead charges @ 10 % on
116.10
(a+b+c)
e) Contractor's profit @ 10 % on
127.71
(a+b+c+d)
Rate per traffic sign =
1753.51
( i+ii+iii+a+b+c+d+e)
say 1754.00
( ii ) 60 cm equilateral triangle
d) Overhead charges @ 10 % on
87.00
(a+b+c)
e) Contractor's profit @ 10 % on
95.70
(a+b+c+d)
Rate per traffic sign =
1401.40
( i+ii+iii+a+b+c+d+e)
say 1401.00
( iii ) 60 cm circular
d) Overhead charges @ 10 % on
106.05
(a+b+c)
e) Contractor's profit @ 10 % on
116.66
(a+b+c+d)
Rate per traffic sign =
1631.90
( i+ii+iii+a+b+c+d+e)
say 1632.00
( iv ) 80 mm x 60 mm rectangular
d) Overhead charges @ 10 % on
135.60
(a+b+c)
e) Contractor's profit @ 10 % on
149.16
(a+b+c+d)
Rate per traffic sign =
1989.46
( i+ii+iii+a+b+c+d+e)
say 1989.00
( v ) 60 cm x 45 cm rectangular
d) Overhead charges @ 10 % on
104.10
(a+b+c)
e) Contractor's profit @ 10 % on
114.51
(a+b+c+d)
Rate per traffic sign =
1608.31
( i+ii+iii+a+b+c+d+e)
say 1608.00
(vi ) 60 cm x 60 cm square
d) Overhead charges @ 10 % on
117.60
(a+b+c)
e) Contractor's profit @ 10 % on
129.36
(a+b+c+d)
Rate per traffic sign =
1771.66
( i+ii+iii+a+b+c+d+e)
say 1772.00
( vii ) 90 cm high octagon
d) Overhead charges @ 10 % on
164.40
(a+b+c)
e) Contractor's profit @ 10 % on
180.84
(a+b+c+d)
Rate per traffic sign =
2337.94
( i+ii+iii+a+b+c+d+e)

Page 4 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. say 2338.00
1.Any one area of aluminium sheeting given
at (i) to (vii) may be adopted as per site
Note
requirement and in accordance with IRC :
67
2.Rate for excavation, cement concrete M-
15 and painting may be taken from
respective chapters
3. The depth of foundation and quantity of
cement concrete in the foundation are
indicative. These may be increased for
areas having higher wind velocities like in
coastal areas. This is applicable to all road
signs and directions boards.
Direction and Place Identification
8.5 801
Signs upto 0.9 sqm Size Board.
Providing and erecting direction and place
identification retro-reflectorised sign as per
IRC:67 made of high intensity grade
sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick with area
not exceeding 0.9 sqm supported on a mild
steel single angle iron post 75 x 75 x 6 mm
firmly fixed to the ground by means of
properly designed foundation with M15
grade cement concrete 45 x 45 x 60 cm, 60
cm below ground level as per approved
drawing
Unit = sqm
Taking output = 0.9 sqm
103.00 22.25 Item No.
i) Excavation for foundation cum 0.216
3.13
2595.00 311.40 Item
ii) Cement concrete M15 grade cum 0.120
12.8 (A)
iii) Painting angle iron post two
sqm 0.430 35.00 15.05 Item 8.9
coats
a) Labour (For fixing at site)
Mate day 0.010 150.00 1.50 L-12
Mazdoor day 0.200 100.00 20.00 L-13
b) Material
Mild steel angle iron 75 mm x 75 mm x 32.00 608.00 M-179 /
kg 19.000
6 mm,2.85 metres long 1000
Aluminium sheeting fixed with
1500.00 1350.00 M-061
encapsulated lens type reflective sqm 0.900
sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for
drilling holes, nuts, bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 150.00 3.00 P&M-
d) Overhead charges @ 10 % on 053
198.25
(a+b+c)
e) Contractor's profit @ 10 % on
218.08
(a+b+c+d)
Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e 2747.52
Rate per sqm (for sign having area
upto 0.9 sqm) = 3052.80
(I+ii+iii+a+b+c+d+e)/0.90
say 3053.00
I) Lettering and arrow marks on sign board
to be provided separately as per actual
Note
requirement. Rates for these items have
been analysed separately
ii) Rate for excavation, cement concrete M-
15 and painting may be taken from
respective
Direction chapters
and Place Identification
8.6 801 Signs with size more than 0.9 sqm size
Board.

Page 5 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Providing and erecting direction and place
Spec.
identification retro- reflectorised sign as per
IRC :67 made of high intensity grade
sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick with area
exceeding 0.9 sqm supported on a mild
steel angle iron post 75 mm x 75 mm x 6
mm, 2 Nos. firmly fixed to the ground by
means of properly designed foundation with
M 15 grade cement concrete45 cm x 45 cm
x 60 cm, 60 cm below ground level as per
approved drawing
Unit = sqm
Taking output = 1.50 sqm
103.00 44.29 Item No.
i) Excavation for foundation cum 0.430
3.13
2595.00 622.80 Item
ii) Cement concrete M15 grade cum 0.240
12.8 (A)
iii) Painting angle iron post 2
sqm 0.860 35.00 30.10 Item 8.9
coats
a) Labour (For fixing at site)
Mate day 0.010 150.00 1.50 L-12
Mazdoor day 0.300 100.00 30.00 L-13
b) Material
Mild steel angle iron 75 mm x 75 mm x 32.00 1216.00 M-179 /
kg 38.000
6 mm, 2.85 metres long, 2 nos 1000
Aluminium sheeting fixed with
1500.00 2250.00 M-061
encapsulated lens type reflective sqm 1.500
sheeting
Add 2 per cent of cost of materials for
drilling holes, nuts, bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 150.00 3.00 P&M-
d) Overhead charges @ 10 % on 053
346.90
(a+b+c)
e) Contractor's profit @ 10 % on
384.74
(a+b+c+d)
Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e 4929.33
Rate per sqm ( for sign having area
more than 0.9 sqm) = 5477.03
( i+ii+iii+a+b+c+d+e)/1.50
say 5477.00
i) Lettering and arrow marks on sign board
to be provided separately as per actual
Note
requirement. Rates for these items have
been analysed separately
ii) Rate for excavation, cement concrete M-
15 and painting may be taken from
respective chapters
8.7 802 Overhead Signs
Providing and erecting overhead signs with
a corrosion resistant 2mm thick aluminium
alloy sheet reflectorised with high intensity
retro-reflective sheeting of encapsulated
lense type with vertical and lateral
clearance given in clause 802.2 and 802.3
and installed as per clause 802.7 over a
designed support system of aluminium alloy
or galvanised steel trestles and trusses of
sections and type as per structural design
requirements and approved plans
A Truss and Vertical Support
Unit = tonne
Taking output = 1 tonne
a) Labour
Mate day 0.240 150.00 36.00 L-12
Blacksmith day 2.000 150.00 300.00 L-02
Mazdoor including for handling & fixing
day 4.000 100.00 400.00 L-13
at site.
b) Material
Aluminium alloy/galvanised steel 40000.00 42000.00 M-060
tonne 1.050
including 5 per cent wastage
Add 1 per cent on cost of material for nuts,
420.00
bolts and drilling and welding consumables

Page 6 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Add 15 per cent on cost of material for
fabrication of trusses as per approved 6363.00
design
c) Machinery
Crane 3 tonne capacity hour 3.000 225.00 675.00 P&M-
Truck hour 0.500 185.00 92.50 013
P&M-
d) Overhead charges @ 10 % on 057
5028.65
(a+b+c)
e) Contractor's profit @ 10 % on
5531.52
(a+b+c+d)
Rate per tonne = (a+b+c+d+e) 60846.67
say ###
Aluminium Alloy Plate for Over Head
8.7 B
Sign
Unit = sqm
Taking output = 1 sqm
a) Labour
Mate day 0.020 150.00 3.00 L-12
Blacksmith day 0.100 150.00 15.00 L-02
Mazdoor day 0.150 100.00 15.00 L-13
b) Material
Aluminium alloy plate,2 mm thick, fixed
750.00 750.00 M-059
with high intensity grade sheeting vide sqm 1.000
clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting
arrangement, like ladders, pulleys, ropes 0.33
etc
c) Overhead charges @ 10 % on
78.33
(a+b)
d) Contractor's profit @ 10 % on
86.17
(a+b+c)
Rate per sqm = (a+b+c+d) 947.83
say 948.00
1. The cost of excavation and foundation
concrete for fixing of vertical support
Note system to be worked out separately as per
the approved drawing/design and to be
included in the estimate.
2. Lettering and arrow marks on sign board
to be provided separately as per actual
requirement. Rates for these items have
been included separately in this chapter.
Painting Two Coats on New Concrete
8.8 803
Surfaces
Painting two coats after filling the surface
with synthetic enamel paint in all shades on
new plastered concrete surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.120 150.00 18.00 L-12
Painter day 2.000 200.00 400.00 L-18
Mazdoor day 1.000 100.00 100.00 L-13
b) Material
Paint conforming to requirement of
Litre 6.000 150.00 900.00 M-132
clause 803.3.
Add for scaffolding @ 1 per cent of
9.00
labour cost where required
Add @ 5 per cent cost of labour and 70.90
materials to prepare the surface by
filling minuts roughness on the surface
and priming the surface before laying 2
coats of painting.
c) Overhead charges @ 10 % on
149.79
(a+b)
d) Contractor's profit @ 10 % on
164.77
(a+b+c)
Cost for 40 sqm = a+b+c+d 1812.46
Rate per sqm = (a+b+c+d)/40 45.31
say 45.00
8.9 803 Painting on Steel Surfaces

Page 7 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Providing and applying two coats of ready
mix paint of approved brand on steel
surface after through cleaning of surface to
give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.030 150.00 4.50 L-12
Painter day 0.450 200.00 90.00 L-18
Mazdoor day 0.250 100.00 25.00 L-13
b) Material
Paint ready mixed approved brand. Litre 1.250 135.00 168.75 M-131
Add @ 1 per cent on cost of material
1.69
for scaffolding
Add @ 5 per cent cost of labour and 14.41
materials to prepare the surface by
filling minuts roughness on the surface
and priming the surface before laying 2
coats of painting.
c) Overhead charges @ 10 % on
30.44
(a+b)
d) Contractor's profit @ 10 % on
33.48
(a+b+c)
Cost for 10 sqm = a+b+c+d 368.26
Rate per sqm= (a+b+c+d)/10 36.83
say 37.00
8.10 803 Painting on Wood Surfaces
Providing and applying two coats of ready
mix paint of approved brand on wood
surface after thorough cleaning of surface
to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.030 150.00 4.50 L-12
Painter day 0.500 200.00 100.00 L-18
Mazdoor day 0.200 100.00 20.00 L-13
b) Material
Paint ready mixed of approved brand. Litre 1.500 135.00 202.50 M-131
Add @ 1 per cent on cost of material
2.03
for scaffolding
Add @ 5 per cent cost of labour and 16.35
materials to prepare the surface by
filling minuts roughness on the surface
and priming the surface before laying 2
coats of painting.
c) Overhead charges @ 10 % on
34.54
(a+b)
d) Contractor's profit @ 10 % on
37.99
(a+b+c)
Cost for 10 sqm = a+b+c+d 417.90
Rate per sqm = (a+b+c+d)/10 41.79
say 42.00
Painting Lines, Dashes, Arrows etc on
8.11 803
Roads in Two Coats on New Work
Painting lines, dashes, arrows etc on roads
in two coats on new work with ready mixed
road marking paint conforming to IS:164 on
bituminous surface, including cleaning the
surface of all dirt, dust and other foreign
matter, demarcation at site and traffic
control
(i) Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.090 150.00 13.50 L-12
Painter day 0.550 200.00 110.00 L-18
Mazdoor day 1.550 100.00 155.00 L-13
b) Material
Road marking Paint as per IS :164 Litre 1.480 150.00 222.00 M-132

Page 8 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. c) Overhead charges @ 10 % on
50.05
(a+b)
d) Contractor's profit @ 10 % on
55.06
(a+b+c)
Cost for 10 sqm = a+b+c+d 605.61
Rate per sqm= (a+b+c+d)/10 60.56
say 61.00
8.11 (ii) Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.070 150.00 10.50 L-12
Painter day 0.350 200.00 70.00 L-18
Mazdoor day 1.350 100.00 135.00 L-13
b) Material
Road marking paint Litre 1.480 150.00 222.00 M-132
c) Overhead charges @ 10 % on
43.75
(a+b)
d) Contractor's profit @ 10 % on
48.13
(a+b+c)
Cost for 10 sqm = a+b+c+d 529.38
Rate per sqm = (a+b+c+d)/10 52.94
say 53.00
Painting Lines, Dashes, Arrows etc on
8.12 803
Roads in Two Coats on Old Work
Painting lines, dashes, arrows etc on roads
in two coats on old work with ready mixed
road marking paint conforming to IS: 164 on
bituminous surface, including cleaning the
surface of all dirt, dust and other foreign
matter, demarcation at site and traffic
control
(i) Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.060 150.00 9.00 L-12
Painter Ist class day 0.300 200.00 60.00 L-18
Mazdoor day 1.250 100.00 125.00 L-13
b) Material
Road marking paint Litre 0.900 150.00 135.00 M-132
c) Overhead charges @ 10 % on
32.90
(a+b) Contractor's profit @ 10 % on
d)
36.19
(a+b+c)
Cost for 10 sqm = a+b+c+d 398.09
Rate per sqm = (a+b+c+d)/10 39.81
say 40.00
8.12 (ii) Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.070 150.00 10.50 L-12
Painter Ist class day 0.350 200.00 70.00 L-18
Mazdoor day 1.350 100.00 135.00 L-13
b) Material
Road marking Paint Litre 0.900 150.00 135.00 M-132
c) Overhead charges @ 10 % on
35.05
(a+b)
d) Contractor's profit @ 10 % on
38.56
(a+b+c)
Cost for 10 sqm= a+b+c+d 424.11
Rate per sqm = (a+b+c+d)/10 42.41
say 42.00
Road Marking with Hot Applied
Thermoplastic Compound with
8.13 803
Reflectorising Glass Beads on
Bituminous Surface

Page 9 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Providing and laying of hot applied
thermoplastic compound 2.5 mm thick
including reflectorising glass beads @ 250
gms per sqm area, thickness of 2.5 mm is
exclusive of surface applied glass beads as
per IRC:35 .The finished surface to be level,
uniform and free from streaks and holes.
Unit = sqm
Taking output = 600 sqm
a) Labour
Mate day 0.030 150.00 4.50 L-12
Mazdoor day 0.750 100.00 75.00 L-13
b) Machinery
Road marking machine @ 60 sqm per
hour 10.000 65.00 650.00 P&M-
hour
Tractor-trolley hour 0.500 150.00 75.00 043
P&M-
c) Material 053
Hot applied thermoplastic compound Litre 1500.000 150.00 ### M-118
Reflectorising glass beads kg 150.000 50.00 7500.00 M-152
d) Overhead charges @ 10 % on
23330.45
(a+b+c)
e) Contractor's profit @ 10 % on
25663.50
(a+b+c+d)
Cost for 600 sqm = a+b+c+d+e ###
Rate per sqm = a+b+c+d+e)/600 470.50
say 470.00
1. A sealing primer may be applied in
advance on cement concrete pavement to
ensure proper bonding. Any laitance and/or
Note
curing compound to be removed where
paint is required to be applied on concrete
surface.
2.Cost of painter is already included in hire
charges of road marking machine.
8.14 804 Kilometre Stone
Reinforced cement concrete M15grade
kilometre stone of standard design as per
IRC:8-1980, fixing in position including
painting and printing etc
(i) 5th kilometre stone (precast)
Unit = Nos.
Taking output = 6 Nos.
2595.00 6098.25 Item
a) M-15 grade of concrete cum 2.350
12.8 (A)
b) Steel reinforcement @ 5 kg 45.33 1000.97 Item
kg 22.080
per sqm 13.6 /
c) Excavation in soil for 103.00 1000
173.04 Item No.
cum 1.680
foundation 3.13
d) Painting two coats on
sqm 9.850 43.00 423.55 Item 8.8
concrete surface per cm
e) Lettering on km post (average 0.30 540.00 Item 8.3
per 1800.000
30 letters of 10 cm height each)
letter
Transportation and fixing
f) Labour
Mate day 0.260 150.00 39.00 L-12
Mason day 0.600 250.00 150.00 L-11
Mazdoor including loading/unloading day 6.000 100.00 600.00 L-13
g) Machinery
Tractor-trolley hour 6.000 150.00 900.00 P&M-
h) Overhead charges @ 10 % on 053
168.90
(f+g)Contractor's profit @ 10 % on
i)
185.79
(f+g+h)
Cost for 6 Nos. 5th km stone = a+b+c+
10279.50
d+e +f+g+h +i
Rate for each 5th km stone = (a+b+c+
1713.25
d+e +f+g+h +i ) /6
say 1713.00
8.14 (ii) Ordinary kilometer stone (precast)
Unit = Nos.

Page 10 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Taking output = 14 Nos.
2595.00 9783.15 Item
a) M-15 grade of concrete cum 3.770
12.8 (A)
b) Steel reinforcement @ 5 kg 45.33 1193.19 Item
kg 26.320
per sqm 13.6 /
c) Excavation in soil for 103.00 1000
285.31 Item No.
cum 2.770
foundation 3.13
d) Painting two coats on
sqm 11.410 43.00 490.63 Item 8.8
concrete
e) surface
Lettering on km post per cm
0.30 504.00 Item 8.3
( average 12 letters of 10 cm per 1680.000
height each) letter
Transportation and fixing
f) Labour
Mate day 0.320 150.00 48.00 L-12
Mason day 1.000 250.00 250.00 L-11
Mazdoor day 7.000 100.00 700.00 L-13
g) Machinery
Tractor-trolley hour 6.000 150.00 900.00 P&M-
h) Overhead charges @ 10 % on 053
189.80
(f+g)
i) Contractor's profit @ 10 % on
208.78
(f+g+h)
Cost for 14 Nos. ordinary km stone = (a+b+
14552.86
c +d+e+f+g+h+i)
Rate for each ordinary km stone =
1039.49
(a+b+ c +d+e+f+g+h+j) /14
say 1039.00
8.14 (iii) Hectometer stone (precast)
Unit = Nos.
Taking output = 33 Nos.
2595.00 4100.10 Item
a) M-15 grade of concrete cum 1.580
12.8 (A)
b) Steel reinforcement @ 5 kg 45.33 2992.04 Item
kg 66.000
per sqm 13.6 /
c) Excavation in soil for 103.00 1000
143.17 Item No.
cum 1.390
foundation 3.13
d) Painting two coats on
sqm 6.270 43.00 269.61 Item 8.8
concrete surface per cm
e) Lettering on km post (average 0.30 99.00 Item 8.3
per 330.000
1 letter of 10 cm height each)
letter
Transportation and fixing
f) Labour
Mate day 0.340 150.00 51.00 L-12
Mason day 1.500 250.00 375.00 L-11
Mazdoor day 7.000 100.00 700.00 L-13
g) Machinery
Tractor-trolley hour 6.000 150.00 900.00 P&M-
h) Overhead charges @ 10 % on 053
202.60
(f+g)
i) Contractor's profit @ 10 % on
222.86
(f+g+h)
Cost for 33 Nos. Hectometer stone = (a+b
10055.38
+c +d+e+f+ g+h+i)
Rate for each Hectometer stone =
304.71
(a+b +c +d+e+f+ g+h+i) 33
say 305.00
The rate for excavation, cement concrete,
Note steel reinforcement, painting and lettering
may be taken from respective chapters.
8.15 805 Road Delineators
Supplying and installation of delineators
(road way indicators, hazard markers,
object markers), 80-100 cm high above
ground level, painted black and white in 15
cm wide strips, fitted with 80 x 100 mm
rectangular or 75 mm dia circular
reflectorised panels at the top, buried or
pressed into the ground and conforming
toIRC-79 and the drawings.

Page 11 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Unit = Each
Taking output= 30 Nos.
a) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoor for fixing day 1.000 100.00 100.00 L-13
b) Material
Cost of approved type of delineators 400.00 12000.00 M-091
from ISI certified firm as per the each 30.000
standard drawing given in IRC - 79
Add 10 per cent cost of material for
1200.00
installation
c) Overhead charges @ 10 % on
1330.60
(a+b)
d) Contractor's profit @ 10 % on
1463.66
(a+b+c)
Cost for 30 Nos. delineators = (a+b+ c+d)
16100.26
Rate per delineators = (a+b+c+d) /30
536.68
say 537.00
In case of soft ground, a proper foundation
may be provided as per approved design. In
case foundation is required to be provided,
Note
the items of excavation and foundation
concrete are required to be measured and
paid separately.
8.16 806 Boundary pillar
Reinforced cement concrete M15 grade
boundary pillars of standard design as per
IRC:25-1967, fixed in position including
finishing and lettering but excluding
painting
Unit = Each
Taking output = 57 Nos.
a) M-15 grade of the boundary 2595.00 3243.75 Item
cum 1.250
stone 12.8 (A)
45.33 3617.65 Item
b) Steel reinforcement kg 79.800
13.6 /
103.00 1000
1104.16 Item No.
c) Excavation in soil cum 10.720
3.13
per 0.30 684.00 Item 8.3
letter
d) Lettering, each 10 cm high 2280.000
per cm
high
Transportation and fixing
e) Labour
Mate day 0.570 150.00 85.50 L-12
Mazdoor day 14.250 100.00 1425.00 L-13
f) Machinery
Tractor-trolley hour 6.000 150.00 900.00 P&M-
g) Material 053
Stone spall cum 11.970 160.00 1915.20 M-008
h) Overhead charges @ 10 % on
432.57
(e+f+g)
i) Contractor's profit @ 10 % on
475.83
(e+f+g+h)
Cost for 57 Nos. boundary pillar = (a+b
13883.66
+c+d +e+ f+g+h+i )
Rate for each boundary pillar =
243.57
(a+b+c+d+e+ f+g+h+i)/57
say 244.00
In case of soft ground, a proper foundation
may be provided as per approved design. In
case foundation is required to be provided,
Note
the items of excavation and foundation
concrete are required to be measured and
paid separately.
G.I Barbed Wire Fencing 1.2 Metre
8.17 807
High

Page 12 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Providing and fixing 1.2 metres high GI
Spec.
barbed wire fencing with 1.8 m angle iron
posts 40 mm x 40 mm x 6 mm placed every
3 metres center to center founded in M15
grade cement concrete, 0.6 metre below
ground level, every 15th post, last but one
end post and corner post shall be strutted
on both sides and end post on one side only
and provided with 9 horizontal lines and 2
diagonals interwoven with horizontal wires,
fixed with GI staples, turn buckles etc
complete as per clause 807
Unit = per running metre
Taking output = 30 metres
a) Labour
Mate day 0.090 150.00 13.50 L-12
Blacksmith day 0.250 150.00 37.50 L-02
Mazdoor day 2.000 100.00 200.00 L-13
b) Material
Barbed wire 335 metres length @ 9.38 40.00 1256.80 M-063
kg 31.420
kg per 100 metres
MS angle iron 40 mm x 40mm x 6 mm, 32.00 2576.00 M-179 /
kg 80.500
23 metres in length @ 3.5 kg per metre 1000
Add for GI staple binding wire, drilling holes
76.66
etc. @ 2 per cent of the cost of material
c) Painting
Applying two coats of painting on
35.00 73.85 Item 8.9
exposed surface of angle iron posts sqm 2.110
d) ( Rate as per item
Overhead no. 8.9)
charges @ 10 % on
416.05
(a+b)
e) Contractor's profit @ 10 % on
457.65
(a+b+d)
Cost for 30 metres fencing = a+b+c+d+e 5108.00
Rate per metre = (a+b+c+d+e)/30 170.27
say 170.00
Cost of excavation for foundation and
foundation concrete to be added separately
Note in the cost estimate as per approved
design. The rate for these items may be
taken from respective chapters.
G.I Barbed Wire Fencing 1.8 Metre
8.18 807
Providing and fixing 1.8 metres high GI
High
barbed wire fencing with 2.4 m angle iron
posts 50 mm x 50 mm x 6 mm placed every
3 metres center to center founded in M15
grade cement concrete, 0.6 metre below
ground level, every 15th post, last but one
end post and corner post shall be strutted
on both sides and end post on one side only
and provided with 12 horizontal lines and 2
diagonals interwoven with horizontal wires,
fixed with GI staples, turn buckles etc
complete as per clause 807
Unit = per running metre
Taking output = 30 metres
a) Labour
Mate day 0.120 150.00 18.00 L-12
Blacksmith day 0.400 150.00 60.00 L-02
Mazdoor day 2.500 100.00 250.00 L-13
b) Material
Barbed wire 428 metres length @ 9.38 40.00 1606.00 M-063
kg 40.150
kg per 100 metres
MS angle iron 50 mm x 50 mm x 6
32.00 4864.00 M-179 /
mm,33.8 metres in length @ 4.5 kg per kg 152.000
1000
metre
Add for GI staple, binding wire, drilling
holes etc. @ 2 per cent of the cost of 129.40
material
c) Painting
Applying two coats of painting on 35.00 138.60 Item 8.9
sqm 3.960
exposed surface of angle iron posts
d) Overhead charges @ 10 % on
692.74
(a+b)

Page 13 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. e) Contractor's profit @ 10 % on
762.01
(a+b+d)
Cost for 30 metres fencing = a+b+c+d+e 8520.75
Rate per metre fencing = (a+b+c
284.03
+d+e)/30
say 284.00
Cost of excavation for foundation and
foundation concrete to be added separately
Note in the cost estimate as per approved
design. The rate for these items may be
taken from respective chapters.
Fencing With Welded Steel Wire Fabric
8.19 Sugge
75 mm x 50 mm
stive
Providing 1.20 metre high fencing with
angle iron posts 50 mm x 50 mm x 6 mm at
3 metre center to center with 0.40 metre
embedded in M15 grade cement concrete,
corner, end and every 10th post to be
strutted, provided with welded steel wire
fabric of 75 mm x 50 mm mesh or 75 mm x
25 mm mesh and fixed to iron posts by flat
iron 50 x 5 mm and bolts etc. complete in
all respects.
Unit = Running metre
Taking output = 30 m
a) Labour
Mate day 0.120 150.00 18.00 L-12
Welder day 1.000 150.00 150.00 L-02
Mazdoor day 2.000 100.00 200.00 L-13
b) Material
32.00 3392.00 M-179 /
i) Angle iron for posts 50 x 50 x 6 mm kg 106.000
1000
32.00 832.00 M-179 /
ii) Runner flat 50 x 5 mm kg 26.000
1000
iii) Welded steel wire fabric 75x50 mm
40.00 6040.00 M-191
mesh @ 4 kg/sqm,4 x 30 x 1.2 + 5 per kg 151.000
cent wastage
OR
Welded steel wire fabric 75 x 25 mm
mesh @ 7.75 kg/sqm, 7.75 x 30 x 1.2 + kg 293.000
Add 52.5
per per
centcent
wastage
of cost of material for
drilling holes in angles, flats, splitting angle
at bottom, nuts and bolts and welded
consumables
c) Machinery
Tractor-trolley hour 0.100 150.00 15.00 P&M-
d) Painting 053
Painting two coats including priming sqm 8.000 35.00 280.00 Item 8.9
e) Overhead charges @ 10 % on
1064.70
(a+b+c)
f) Contractor's profit @ 10 % on
1171.17
(a+b+c+e)
Cost for 30 metre = a+b+c+d+e+f 13162.87
Rate per metre = (a+b+c+d+e+f)/30 438.76
say 439.00
i) Adopt any one type of welded steel wire
Note fabric 75 x 50 mm or 75 x 25 mm as per
approved design.
ii) The item of excavation and cement
concrete in foundation shall be measured
and paid separately
Tubular Steel Railing on Medium
8.20 808 Weight Steel Channel ( ISMC series)
100 mm x 50 mm
Providing, fixing and erecting 50 mm dia
steel pipe railing in 3 rows duly painted on
medium weight steel channels (ISMC series)
100 mm x 50 mm, 1.2 metres high above
ground, 2 m centre to centre, complete as
per approved drawings
Unit = Running metre
Taking output = 10metres

Page 14 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 103.00 133.49 Item No.
i) Excavation for foundation (6
cum 1.296
Nos)6 x 0.6 x 0.6 x 0.6 3.13
ii) Foundation concrete M-15 grade 2595.00 1681.56 Item
cum 0.648
PCC 6 x 0.6 x 0.6 x 0.3 12.8 (A)
iii) Painting of pipe sqm 4.710 35.00 164.85 Item 8.9
iv) Painting of channel section 6
35.00 75.60 Item 8.9
nos,1.8 metres each 0.2 x 1.8 x 6 = sqm 2.160
2.16
a) Labour (For fixing at site)
Mate day 0.010 150.00 1.50 L-12
Mazdoor day 0.250 100.00 25.00 L-13
Plumber day 0.010 150.00 1.50 L-02
b) Material
Steel pipe 50 mm external dia as per
metre 30.000 200.00 6000.00 M-175
IS:1239
Medium weight steel channel (ISMC 32.00 3179.52 M-179 /
series) 100 mm x 50 mm,10.8 metres kg 99.360 1000
length @ 9.2 kg per metre
Add for drilling holes @ 2 per cent of cost
63.59
of channels
c) Machinery
Tractor-trolley hour 0.040 150.00 6.00 P&M-
d) Overhead charges @ 10 % on 053
1132.66
(a+b+c)
e) Contractor's profit @ 10 % on
1245.93
(a+b+c+d)
Cost for 10 metre =i+ii+iii+iv+
13711.20
a+b+c+d+e
Rate per metre =
1371.12
(i+ii+iii+iv+a+b+c+d+e)/10
say 1371.00
Tubular Steel Railing on Precast RCC
8.21 808
Posts, 1.2 m High Above Ground Level
Providing, fencing and erecting 50 mm dia
painted steel pipe railing in 3 rows on
precast M20 grade RCC vertical posts1.8
metres high (1.2 m above GL) with 3 holes
50 mm dia for pipe, fixed 2 metres centre
to, complete as per approved drawing
Unit = Running metre
Taking output = 10metres
i) Excavation for foundation (6 103.00 133.49 Item No.
cum 1.296
Nos)6 x 0.6 x 0.6 x 0.6 3.13
ii) Foundation concrete M - 15 2595.00 1681.56 Item
cum 0.648
grade PCC 6 x 0.6 x 0.6 x 0.3 12.8 (A)
iii) RCC M - 20 for pre cast posts 6 3225.00 1032.00 Item
cum 0.320
nos of 1.8 metres each 14.1(A)
iv) Painting of pipe sqm 4.710 35.00 164.85 Item 8.9
a) Labour
Mate day 0.014 150.00 2.10 L-12
Mazdoor day 0.350 100.00 35.00 L-13
Plumber day 0.010 150.00 1.50 L-02
b) Material
Steel pipe 50 mm dia as per IS:1239 metre 30.000 200.00 6000.00 M-175
c) Machinery
Tractor-trolley hour 0.250 150.00 37.50 P&M-
d) Overhead charges @ 10 % on 053
607.61
(a+b+c)
e) Contractor's profit @ 10 % on
668.37
(a+b+c+d)
Cost for 10 metre =i+ii+iii+iv+
10363.98
a+b+c+d+e
Rate per metre =
1036.40
(i+ii+iii+iv+a+b+c+d+e)/10
say 1036.00
Reinforced Cement Concrete Crash
8.22 809
Barrier

Page 15 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. crash barrier at the edges of the road,
approaches to bridge structures and
medians, constructed with M-20 grade
concrete with HYSD reinforcement
conforming to IRC:21 and dowel bars 25
mm dia, 450 mm long at expansion joints
filled with pre-moulded asphalt filler board,
keyed to the structure on which it is built
and installed as per design given in the
enclosure to MOST circular No. RW/NH -
33022/1/94-DO III dated 24 June 1994 as
per dimensions in the approved drawing
and at locations directed by the Engineer,
Unit = Linear metre
Taking output = 10 m
(i) a) M 20 grade concrete
3225.00 9675.00 Item
M 20 grade concrete cum 3.000
14.1(A)
b) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoor day 1.000 100.00 100.00 L-13
c) Material
HYSD steel reinforcement including
tonne 0.280 34500.00 9660.00 M-082
dowel bars
Pre-moulded asphalt filler board sqm 0.320 70.00 22.40 M-144
d) Overhead charges @ 10 % on
978.84
(b+c) Contractor's profit @ 10 % on
e)
1076.72
(b+c+d)
Cost for 10 metre = a+b+c+d+e 21518.96
Rate per metre = (a+b+c+d+e)/10 2151.90
say 2152.00
i) Excavation and backfilling are incidental
Note
to work and not to be measured separately.
ii) Rate for RCC M 20 may be taken from
chapter on super structure.
8.23 810 Metal Beam Crash Barrier
Type - A, "W" : Metal Beam Crash
A
Barrier
Providing and erecting a "W" metal beam
crash barrier comprising of 3 mm thick
corrugated sheet metal beam rail, 70 cm
above road/ground level, fixed on ISMC
series channel vertical post, 150 x 75 x 5
mm spaced 2 m centre to centre, 1.8 m
high, 1.1 m below ground/road level, all
steel parts and fitments to be galvanised by
hot dip process, all fittings to conform to
IS:1367 and IS:1364, metal beam rail to be
fixed on the vertical post with a spacer of
channel section 150 x 75 x 5 mm, 330 mm
long complete as per clause 810
Unit = Running metre
Taking output = 4.5 metre length
a) Labour
Mate day 0.060 150.00 9.00 L-12
Blacksmith day 0.500 150.00 75.00 L-02
Mazdoor day 1.000 100.00 100.00 L-13
b) Machinery
Tractor-trolley hour 0.100 150.00 15.00 P&M-
c) Material 053
Corrugated sheet,3 mm thick, "W" 32.00 1318.72 M-179 /
kg 41.210
beam section railing,4.5 m in length 1000
Channel post 150 x 75 x 5 mm,1.8 m 32.00 2833.92 M-179 /
kg 88.560
long,3 Nos @ 16.4 kg per metre 1000
Spacer 150 x 75 x 5 mm channel 0.33 32.00 519.68 M-179 /
kg 16.240
m long,3 Nos @ 16.4 kg per metre 1000
Nuts and bolts kg 20.000 50.00 1000.00 M-130
Add 25 per cent of the cost of material for
1418.08
fabrication, nuts, bolts and washers etc.)

Page 16 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. d) Overhead charges @ 10 % on
728.94
(a+b+c)
e) Contractor's profit @ 10 % on
801.83
(a+b+c+d)
Cost for 4.5 metre = a+b+c+d+e 8820.17
Rate per metre = (a+b+c+d+e)/4.5 1960.04
say 1960.00
Type - B, "THRIE" : Metal Beam Crash
8.23 B
Barrier
Providing and erecting a "Thrie" metal
beam crash barrier comprising of 3 mm
thick corrugated sheet metal beam rail, 85
cm above road/ground level, fixed on ISMC
series channel vertical post, 150 x 75 x 5
mm spaced 2 m centre to centre, 2 m high
with 1.15 m below ground level, all steel
parts and fitments to be galvanised by hot
dip process, all fittings to conform to
IS:1367 and IS:1364, metal beam rail to be
fixed on the vertical post with a space of
channel section 150 x 75 x 5 mm, 546 mm
long complete as per clause 810
Unit = Running metre
Taking output = 4.5 metre length
a) Labour
Mate day 0.060 150.00 9.00 L-12
Blacksmith day 0.500 150.00 75.00 L-02
Mazdoor day 1.000 100.00 100.00 L-13
b) Machinery
Tractor-trolley hour 0.100 150.00 15.00 P&M-
c) Material 053

Corrugated sheet,3 mm thick, "Thrie" 45.00 3282.30 M-088


kg 72.940
beam section railing,4.5 m in length
Channel post 150 x 75 x 5 mm, 2 m 32.00 3148.80 M-179 /
kg 98.400
long,3 Nos @ 16.4 kg per metre 1000
Spacer 150 x 75 x 5 mm channel 0.546 32.00 859.52 M-179 /
kg 26.860
m long,3 Nos 1000
Nuts and bolts kg 30.000 50.00 1500.00 M-130
Add 15 per cent of the cost of material for
1318.59
fabrication, nuts, bolts and washers etc.)
d) Overhead charges @ 10 % on
1030.82
(a+b+c)
e) Contractor's profit @ 10 % on
1133.90
(a+b+c+d)
Cost for 4.5 metre = a+b+c+d+e 12472.94
Rate per metre= (a+b+c+d+e)/4.5 2771.76
say 2772.00
In the case of median crash barrier, 'W'
metal beam or thrie beam section should be
provided on both sides of the vertical posts
Note fixed in the median. Extra provision for
metal beam railing and spacer is required
to be made when fixed in the median
depending on approved design.
Road Traffic Signals electrically
8.24 811
operated
Since it is a ready made item commercially
produced and erected by specialised firm in
the electrical and electronic field, rate may
Note be taken based on market enquiry from
firms specialised in this field and ISI
certified for the approved design and
drawing.
Sugge Flexible Crash Barrier, Wire Rope
8.25
stive Safety Barrier

Page 17 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Providing and erecting a wire rope safety
Spec.
barrier with vertical posts of medium weight
RS Joist (ISMB series) 100 mm x 75 mm
(11.50 kg/m), 1.50 m long 0.85 m above
ground and 0.65 m below ground level, split
at the bottom for better grip, embedded in
M 15 grade cement concrete 450 x 450 x
450 mm, 1.50 m center to center and with
4 horizontal steel wire rope 40 mm dia and
anchored at terminal posts 15 m apart.
Terminal post to be embedded in M 15
grade cement concrete foundation 2400 x
450 x 900 mm (depth), strengthened by a
strut of RS joist 100 x 75 mm, 2 m long at
450 inclination and a tie 100 x 8 mm, 1.50
m long at the bottom, all embedded in
foundation concrete as per approved design
and drawing, rate excluding excavation and
cement concrete.
Unit = Running metre
Taking output = 15 metre
a) Labour
Mate day 0.120 150.00 18.00 L-12
Mazdoor day 2.000 100.00 200.00 L-13
Blacksmith day 1.000 150.00 150.00 L-02
b) Material
i) RS Joist 100 x 75 mm - 16.5 m @ 11.5 32.00 6080.00 M-179 /
kg 190.000
kg per metre 1000
ii) Struts - 2 Nos. for terminal posts,2 m 32.00 1472.00 M-179 /
kg 46.000
long each 2 x 2 x 11.50 1000
iii) Tie 2 Nos. of 8 mm steel plate,1.5
32.00 6028.80 M-179 /
sqm each for terminal posts @ 62.80 kg 188.400
1000
kg/sqm
iv) Steel(2 x 1.5)
wire rope 40 mm, including
60.00 3900.00 M-177
7.50 per cent extra for fixing at ends kg 65.000
Add 15
5 xper
4 x cent
1.075 @
of1 cost
kg perofmmaterial for
drilling, gripping, fixing, fabrication and 874.04
welding consumables
c) Painting
Applying 2 coats of painting on exposed
sqm 16.500 35.00 577.50 Item 8.9
surface
d) Machinery
Tractor-trolley hour 0.250 150.00 37.50 P&M-
e) Overhead charges @ 10 % on 053
1876.03
(a+b+d)
f) Contractor's profit @ 10 % on
2063.64
(a+b+d+e)
Cost for 15 m = a+b+c+d+e+f 23277.51
Rate per m = (a+b+c+d+e+f)/15 1551.83
say 1552.00
The items of excavations and cement
concrete works will be measured and
Note
included separately as per the approved
designs and drawings.
Sugge
8.26 Anti-Glare Devices in Median
stive
A Plantation
Plantation of shrubs and plants of approved
species in the median. apart from cutting
off glare from vehicle coming from opposite
direction, these plants provide a pleasant
envoirenment and are eco-friendly. The rate
for this item is available in the chapter 11
on horticulture.
Anti-glare screen with 25 mm steel
B pipe framework fixed with circular and
rectangular vans

Page 18 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Providing and erecting an anti - glare
Spec.
screen with 25 mm dia vertical pipes
fabricated and framed in the form of panels
of one metre length and 1.75 metre height
fixed with circular vane 250 mm dia at top
and rectangular vane 600 x 300 mm at the
middle, made out of steel sheet of 3 mm
thickness, end vertical pipes of the panel
made larger for embedding in foundation
concrete, applying 2 coats of paint on all
exposed surfaces, all as per approved
design and drawings.
Unit = Running metre
Taking output = one metre
a) Labour
Mate day 0.004 150.00 0.60 L-12
Mazdoor day 0.100 100.00 10.00 L-13
b) Material
i) 25 mm steel pipe metre 16.000 75.00 1200.00 M-174
ii) MS sheet for 600 x 300 x 3 mm
32.00 138.24 M-179 /
rectangular vane, one number @ kg 4.320
1000
24kg/sqm
iii) MS sheet for 250 mm dia circular
32.00 153.60 M-179 /
vane 3 mm thick,4 numbers @ 24 kg 4.800
1000
Add kg/sqm
5 per cent cost of material for
fabrication, welding, bending, nuts, bolts 74.59
etc
c) Painting
Applying 2 coats of painting on exposed
sqm 1.830 35.00 64.05 Item 8.9
d) surface
Overhead charges @ 10 % on
157.70
(a+b)
e) Contractor's profit @ 10 % on
173.47
(a+b+d)
Rate per metre = a+b+c+d+e 1972.26
say 1972.00
The items of excavation and cement
Note concrete as per approved design to be
measured and paid separately
Anti-glare screen with rectangular
8.26 C
vane of MS sheet
Providing and erecting anti - glare screen
with rectangular vanes of size 750 x 500
mm made from MS sheet, 3 mm thick and
fixed on MS angle 50 x 50 x 6 mm at an
angle of 450 to the direction of flow of
traffic, 1.5 m center to center, top edge of
the screen 1.75 m above ground level,
vertical post firmly embedded in M-15
cement concrete foundation 0.60 m below
ground level, applying 2 coats of paint on
exposed faces, all complete as per
approved design and drawings
Unit = Running metre
Taking output = 1.50 metre
a) Labour
Mate day 0.004 150.00 0.60 L-12
Mazdoor day 0.100 100.00 10.00 L-13
b) Material
i) Angle iron post,50 x 50 x 6 mm, 32.00 338.56 M-179 /
kg 10.580
length 2.35 m 1000
32.00 288.00 M-179 /
ii) MS sheet 3 mm thick @ 24 kg/sqm kg 9.000
1000
Add 5 per cent of cost of material for
31.33
fabrication, nuts, bolts etc
c) Machinery
Tractor-trolley hour 0.100 150.00 15.00 P&M-
d) Painting 053
Applying 2 coats of painting sqm 0.850 35.00 29.75 Item 8.9
e) Overhead charges @ 10 % on
68.35
(a+b+c)
f) Contractor's profit @ 10 % on
75.18
(a+b+c+e)
Cost for 1.5 m = a+b+c+d+e+f 856.77
Rate per metre = (a+b+c+d+e+f)/1.50 571.18

Page 19 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. say 571.00
The items of excavation and cement
concrete as per approved design to be
Note measured and paid separately. Rate of
painting has been analaysed separately in
this chapter.
Sugge
8.27 Street Lighting
stive
Providing and erecting street light mounted
on a steel circular hollow pole of standard
specifications for street lighting, 9 m high
spaced 40 m apart, 1.8 m overhang on both
sides if fixed in the median and on one side
if fixed on the footpath, fitted with sodium
vapour lamp and fixed firmly in concrete
foundation.
Unit = Each
Taking output = one light
a) Labour
Mate day 0.030 150.00 4.50 L-12
Mazdoor day 0.500 100.00 50.00 L-13
Electrician day 0.250 150.00 37.50 L-02
b) Material
i) Steel circular hollow pole of standard 8000.00 8000.00 M-171
specification for street lighting to mount each 1.000
light at 9 m height above road level
ii) Sodium vapour lamp each 1.000 550.00 550.00 M-168
Add 5 per cent of cost of material for
holder, electric cable, insulation, ladder, 427.50
scaffolding etc
c) Painting
For Fixing in Median
Providing two coats of alluminium paint
35.00 201.25 Item 8.9
over steel circular hollow pipe with sqm 5.750
overhang on both sides
For fixing in Footpath
Providing two coats of alluminium paint
35.00 162.05 Item 8.9
over steel circular hollow pipe with sqm 4.630
overhang on one side
(i) For Fixing in Median
d) Overhead charges @ 10 % on
906.95
(a+b)
e) Contractor's profit @ 10 % on
997.65
(a+b+d)
Rate per light for fixing in Median=
11175.35
a+b+c+d+e
say ###
(ii) For fixing in Footpath
Rate per light for Fixing in Footpath =
11136.15
a+b+c+d+e
say ###
The items of excavation and cement
concrete foundation will be measured and
Note included separately in the estimate as per
approved design and drawing. The rate for
painting has been analysed in this chapter.
Sugge
8.28 Lighting on Bridges
stive
Providing and fixing lighting on bridges,
mounted on steel hollow circular poles of
standard specifications, 5 m high fixed on
parapets with cement concrete, 20 m apart
and fitted with sodium vapour lamp
Unit = Each
Taking output = one light
a) Labour
Mate day 0.020 150.00 3.00 L-12
Mazdoor day 0.400 100.00 40.00 L-13
Electrician day 0.200 150.00 30.00 L-02
b) Material
i) Steel circular hollow pole of standard 5750.00 5750.00 M-170
specification for street lighting to mount each 1.000
light at 5 m above deck level

Page 20 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. ii) Sodium vapour lamp 70 watt each 1.000 550.00 550.00 M-168
Add 1 per cent of cost of material for
holder, electric cable, insulation, ladder, 63.00
scaffolding etc
c) Painting
Providing two coats of alluminium paint 35.00 96.60 Item 8.9
sqm 2.760
over steel circular hollow pipe
d) Overhead charges @ 10 % on
643.60
(a+b)
e) Contractor's profit @ 10 % on
707.96
(a+b+d)
Rate per light = a+b+c+d+e 7884.16
say 7884.00
The items of cement concrete to be
measured and paid separately as per
Note
approved design. The rate for painting has
already been analysed in this chapter.
Sugge
8.29 Cable Duct Across the Road
stive Providing and laying of a reinforced cement
concrete pipe duct, 300 mm dia, across the
road (new construction), extending from
drain to drain in cuts and toe of slope to toe
of slope in fills, constructing head walls at
both ends, providing a minimum fill of
granular material over top and sides of RCC
pipe as per IRC:98-1997, bedded on a 0.3 m
thick layer of granular material free of rock
pieces, outer to outer distance of pipe at
least half dia of pipe subject to minimum
450 mm in case of double and triple row
ducts, joints to be made leak proof, invert
level of duct to be above higher than
ground level to prevent entry of water and
dirt, all as per IRC: 98 - 1997 and approved
(i) drawings.
Single row for one utility service
Unit = Running metre
Taking output = 20metres
a) Random Rubble masonry/Brick
1902.00 4488.72 Item
masonry in cement mortar 1:6 for cum 2.360
12.7
head wall both side
b) Labour (Addl) B)

Mate day 0.050 150.00 7.50 L-12


Mazdoor day 1.000 100.00 100.00 L-13
Mazdoor skilled day 0.250 125.00 31.25 L-15
c) Material
Reinforced Cement Concrete pipe 300
metre 20.000 800.00 16000.00 M-151
mm dia soil with PI less than 6 for
Granular
160.00 1152.00 M-009
bedding and sides of pipe (0.6 x 0.6 x cum 7.200
20 m)
Collar for joints 300 mm dia each 9.000 30.00 270.00 M-083
3232.00 64.64 Item
Cement mortar 1:2 for joints cum 0.020
12.6 (B)
d) Machinery
Tractor-trolley hour 0.500 150.00 75.00 P&M-
e) Overhead charges @ 10 % on 053
1770.04
(b+c+d)
f) Contractor's profit @ 10 % on
1947.04
(b+c+d+e)
Cost for 20 metre = a+b+c+d+e+f 25906.19
Rate per metre = (a+b+c+d+e+f)/20 1295.31
say 1295.00
8.29 (ii) Double row for two utility services
Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick
1902.00 6409.74 Item
masonry in cement mortar 1:6 for cum 3.370
12.7
head wall both sides.
b) Labour (Addl) B)

Mate day 0.050 150.00 7.50 L-12


Mazdoor day 2.000 100.00 200.00 L-13
Mazdoor skilled day 0.250 125.00 31.25 L-15

Page 21 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. c) Material
Reinforced Cement Concrete pipe 300
metre 40.000 800.00 32000.00 M-151
mm dia soil with PI less than 6 for
Granular
160.00 2304.00 M-009
bedding and sides of pipe (0.6 x 0.6 x cum 14.400
40 m)
Collar for joints 300 mm dia each 18.000 30.00 540.00 M-083
3232.00 129.28 Item
Cement mortar 1:2 for joints cum 0.040
12.6 (B)
d) Machinery
Tractor-trolley hour 1.000 150.00 150.00 P&M-
e) Overhead charges @ 10 % on 053
3536.20
(b+c+d)
f) Contractor's profit @ 10 % on
3889.82
(b+c+d+e)
Cost for 20 metre = a+b+c+d+e+f 49197.80
Rate per metre = (a+b+c+d+e+f)/20 2459.89
say 2460.00
8.29 (iii) Triple rRow for three utility services
Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick
1902.00 8330.76 Item
masonry in cement mortar 1:6 for cum 4.380
12.7
head wall both sides.
b) Labour (Addl) B)

Mate day 0.160 150.00 24.00 L-12


Mazdoor day 3.000 100.00 300.00 L-13
Mazdoor skilled day 1.000 125.00 125.00 L-15
c) Material
Reinforced Cement Concrete pipe 300
metre 60.000 800.00 48000.00 M-151
mm dia soil with PI less than 6 for
Granular
160.00 3456.00 M-009
bedding and sides of pipe (0.6 x 0.6 x cum 21.600
60 m)
Collar for joints 300 mm dia each 27.000 30.00 810.00 M-083
3232.00 193.92 Item
Cement mortar 1:2 for joints cum 0.060
12.6 (B)
d) Machinery
Tractor-trolley hour 1.500 150.00 225.00 P&M-
e) Overhead charges @ 10 % on 053
5313.39
(b+c+d)
f) Contractor's profit @ 10 % on
5844.73
(b+c+d+e)
Cost for 20 metre = a+b+c+d+e+f 72622.80
Rate per metre = (a+b+c+d+e+f)/20 3631.14
say 3631.00
1.Inspection chamber at both ends is the
Note responsibility of the agency who is laying
the duct. Hence not included.
2.The rates for stone masonry / brick
masonry and cement mortar to be adopted
from respective clauses.
Sugge
8.30 Highway Patrolling and Traffic Aid Post
stive
It is proposed to locate one Traffic Aid Post
every 50-60 km of the highway.
The organisation and financial aspect are
required to be finalised in consultation with
administrative and traffic authorities .
Items Related to Underpass/ Subway/
Sugge
8.31 Overhead Bridge/ Overhead Foot
stive
Bridge
The items involved for underpass/ subway/
overhead bridge/ overhead foot bridge are
earthwork, plain cement concrete,
plastering, painting, information sign etc.
The rates for these items are available in
respective chapters which can be adopted
for the quantities derived from the
approved designs and drawings
Sugge Traffic Control System and
8.32
stive Communication System

Page 22 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Providing a traffic control centre and
communication system including
telecommunication facilities and related
accessories, CCTV, radar, vehicle detection
These are computer
camera, central specialised
systemitem of
telecommunication system and are the
commercial products. The designer is
required to contact the manufacturers to
ascertain market prices. In case of civil
works required to be executed for these
installations, pricing may be done as per
rates in relevant chapters for quantities
derived as per approved design and
As regards the locations where such
drawing.
devices are required to be installed, the
traffic control authority should be consulted
to finalise the location
Sugge Gantry Mounted Variable Message
8.33
stive Sign Board
Providing and erecting gantry mounted
variable message sign board electronically
operated capable of flashing the desired
message over a designed support system of
aluminium alloy or galvanised steel, erected
as per approved design and drawings and
with lateral clearance as per clause 802.3
(i) Gantry Support System
Unit = tonne
Taking output=1 tonne
a) Labour
Mate day 0.120 150.00 18.00 L-12
Mazdoor day 2.000 100.00 200.00 L-13
Blacksmith day 1.000 150.00 150.00 L-02
b) Material
Alluminium alloy/galvanised steel 40000.00 42000.00 M-060
tonne 1.050
including 5 per cent wastage
Add 15 per cent of cost of material for
6300.00
fabrication and erection.
Add 1 per cent of cost of material for
420.00
nuts, bolts and welding
c) Machinery
Truck 10 tonne hour 1.000 185.00 185.00 P&M-
d) Overhead charges @ 10 % on 057
4927.30
(a+b+c)
e) Contractor's profit @ 10 % on
5420.03
(a+b+c+d)
Rate per tonne = a+b+c+d+e 59620.33
say ###
8.33 (ii) Message Display
Message display board 6 sqm electronically
operated with complete electronic fitments
for flashing the pre-determined messages.
This is a specilised commercial product and
the lumpsum rate including erection at site
is required to be as certained from the
market and including in the rate analysis.
The size of the board will vary depending
upon specific location.
The rate for the gantry mounted variable
sign would be the addition of cost of gantry
support system as per approved design
determined at (i) above and the cost of
message display board as certained from
the market at (ii) above
Sugge Traffic Impact Attenuators at
8.34
stive Abutments and Piers
A With Scrap Tyres

Page 23 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Provision and installation of traffic
attenuators at abutment/pier of flyovers
bridges using scrap tyres of size 100 x 20
retrieved from trucks laid in 2 rows and 4
tiers, one above the other and tied with 20
mm wire rope as per approved design and
drawings.
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor day 1.500 100.00 150.00 L-13
Blacksmith day 0.250 150.00 37.50 L-02
b) Material
Scrap tyres of size 900 x 20 each 80.000 100.00 8000.00 M-161
20 mm steel wire rope kg 150.000 60.00 9000.00 M-176
Add 1 per cent of cost of wire rope for
90.00
clamps etc.
c) Machinery
Tractor-trolley hour 3.000 150.00 450.00 P&M-
d) Overhead charges @ 10 % on 053
1773.95
(a+b+c)
e) Contractor's profit @ 10 % on
1951.35
(a+b+c+d)
Cost for 20 sqm = a+b+c+d+e 21464.80
Rate per sqm = (a+b+c+d+e)/20 1073.24
say 1073.00
Using Plastic/Steel Barrel, Filled with
8.34 B
Sand
Provision and installation of traffic impact
attenuator at abutment/pier of flyovers
bridges using plastic/steel barrels 0.60 m
dia and 1.0 m in height, filled with sand in
three rows and tied with20 mm steel wire
rope as per approved design and drawings
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.130 150.00 19.50 L-12
Mazdoor day 3.000 100.00 300.00 L-13
Blacksmith day 0.250 150.00 37.50 L-02
b) Material
Plastic barrels each 50.000
or
Steel barrels each 50.000 200.00 10000.00 M-172
Sand cum 8.000 160.00 1280.00 M-004
20 mm steel wire rope kg 15.000 60.00 900.00 M-176
Add 1 per cent of cost of wire rope for
9.00
clamps etc.
c) Machinery
Tractor-trolley hour 2.000 150.00 300.00 P&M-
d) Overhead charges @ 10 % on 053
1284.60
(a+b+c)
e) Contractor's profit @ 10 % on
1413.06
(a+b+c+d)
Cost for 20 sqm = a+b+c+d+e 15543.66
Rate per sqm = (a+b+c+d+e)/20 777.18
say 777.00
With HI - DRO cell Sandwich
8.34 C
(Patented)
(In this patented HI - DRO cell system,
water gets discharged from plastic tubes on
impact over a pre-determined time, thus
absorbing the energy)
Providing and installing a patentend HI -
DRO cell system as a traffic impact
attenuators, using plastic tubes 50 cm dia,
1.2 m in height, 25 mm opening at the top,
placed in three rows, filled with water and
tied with a 20 mm steel wire rope
Unit = sqm
Taking output = 10sqm

Page 24 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. a) Labour
Mate day 0.100 150.00 15.00 L-12
Mazdoor day 2.500 100.00 250.00 L-13
b) Material
Plastic tubes 50 cm dia,1.2 m high each 40.000 320.00 12800.00 M-139
Cost of water KL 12.000 50.00 600.00 M-189
20 mm steel wire rope kg 100.000 60.00 6000.00 M-176
Add 1 per cent of cost of wire rope for
60.00
clamps etc.
c) Machinery
Tractor-trolley hour 2.000 150.00 300.00 P&M-
Water tanker6 KL capacity hour 2.000 105.00 210.00 053
P&M-
d) Overhead charges @ 10 % on 060
2023.50
(a+b+c)
e) Contractor's profit @ 10 % on
2225.85
(a+b+c+d)
Cost for 10 sqm = a+b+c+d+e 24484.35
Rate per sqm = (a+b+c+d+e)/10 2448.44
say 2448.00
Sugge Road Markers/Road Stud with Lense
8.35
stive Reflector
Providing and fixing of road stud 100x 100
mm, die-cast in aluminium, resistant to
corrosive effect of salt and grit, fitted with
lense reflectors, installed in concrete or
asphaltic surface by drilling hole 30 mm
upto a depth of 60 mm and bedded in a
suitable bituminous grout or epoxy mortar,
all as per BS 873 part 4:1973
Unit = Nos
Taking output = 50Nos
a) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoor day 1.000 100.00 100.00 L-13
b) Material
Aluminium studs 100 x 100 mm fitted 200.00 10000.00 M-062
each 50.000
with lense reflectors
Add 10 per cent of cost of material for
1000.00
fixing and installation
c) Overhead charges @ 10 % on
1110.60
(a+b)
d) Contractor's profit @ 10 % on
1221.66
(a+b+c)
Cost for 50 studs = a+b+c+d 13438.26
Rate per studs = (a+b+c+d)/50 268.77
say 269.00
Sugge
8.36 Traffic Cone
stive
Provision of red fluorescent with white
reflective sleeve traffic cone made of low
density polyethylene (LDPE) material
with a square base of 390 x 390 x 35 mm
and a height of 770 mm, 4 kg in weight,
placed at 1.5 m interval, all as per BS 873
Unit = Running metre
Taking output = 68 Nos.
a) Labour
Mate day 0.020 150.00 3.00 L-12
Mazdoor day 0.500 100.00 50.00 L-13
b) Material
Traffic cones with 150 mm reflective
each 68.000 400.00 27200.00 M-186
sleeve
c) Machinery
Tractor-trolley hour 0.100 150.00 15.00 P&M-
d) Overhead charges @ 10 % on 053
2726.80
(a+b+c)
e) Contractor's profit @ 10 % on
2999.48
(a+b+c+d)
Cost for 68 Nos. = a+b+c+d+e 32994.28
Rate per metre = (a+b+c+d+e)/68 485.21

Page 25 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. say 485.00
Sugge
8.37 Roadside Amenities
stive
A Rest areas
Providing plainly furnished accommodation
for rest rooms, dormitories, restaurants,
stalls, shops, petrol pump, telephone booth,
first aid room, traffic aid post, police
assistance booth, including electricity, toilet
and sewerage system
Pricing may be done based on current plinth
area rates approved by PWD/CPWD/MES for
a particular zone. Area is required to be
assessed for specific location as per actual
site conditions
Parking areas and bus laybyes for
B
trucks, buses and light vehicles
Pricing of parking areas may be done for
the quantities of various items based on the
approved dimensions and pavement design
for a particular terrain and soil. Rates for
items may be from respective chapters.
C Lawn
Providing a lawn planted with grass and its
maintenance
Pricing of lawn may be done as per rates
given in the chapter on horticulture for the
quantities as per approved dimensions in
the drawings
Sugge
8.38 Rumble Strips
stive
Provision of 15 nos rumble strips covered
with premix bituminous carpet, 15-20 mm
high at center, 250 mm wide placed at 1 m
center to center at approved locations to
control speed, marked with white strips of
road marking paint.
Unit = sqm
Taking output = 100 sqm (including gaps)
The rate per sqm of premix carpet and road
marking may be adopted from chapter 5 &
8 respectively for the quantities calculated
from approved drawings
Sugge
8.39 Policeman Umbrella
stive
Provision of a 2 m high (floor to roof)
umbrella for traffic policeman at road
crossings, where necessary, installed on a
raised platform, built on a central support of
a steel pipe 100 mm dia, roof made of 25
mm dia steel pipe to provide covered area
of 3 sqm, roofed with CGI sheets, all steel
parts to be given 2 coats of paint
Unit = each
Taking output = one number
Earthwork Quantities of these items to cum
be calculated as per
Cement Concrete cum
approved design and cost
brick masonry or
added as per rates of these cum
stone masonry items given in chapter 3 cum
Painting and 13 sqm 2.500
a) Labour
Mate day 0.090
Mazdoor day 1.000
Blacksmith day 1.000
Welder day 0.250
b) Material
Steel pipe 100 mm dia metre 3.500
Steel pipe 25 mm dia metre 10.000
CGI sheets kg 8.000
Add 25 per cent of cost of material for
fabrication

Page 26 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec.
Add 2 per cent of cost of material for
welding consumables, J-hooks, washers etc.
c) Machinery
Tractor-trolley hour 0.500
d) Overheads @ per cent on
(a+b+c)
e) Contractors Profit@ per cent on
(a+b+c+d)
Rate per policeman umbrella =
a+b+c+d+e
sugge High Mast Pole Lighting at
8.40
stive Interchanges and Flyovers
lighting with 30 m high hot dip galvanised
mast designed to withstand forces exerted
with wind speeds of 180 km per hour with 3
seconds gust, as per IS:875 (Part 3) - 1978,
fitted with a base flange, door at the base
of mast with heavy duty internal lock,
lantern carriage, suitable winching
arrangement for safe working load of 750
kg and high powered electrically driven
power tools for raising and lowering of
lantern carriage, flexible 8 core electric
cable, lightening conductor, earthing
terminal, and fixing 2 nos aviation
obstruction lights on top of the mast, all
complete as per approved
This is a specialised work and design and
is generally
done by firms who specialise in such jobs.
The detailed designs and estimates are
submitted by the firms along with their
tender for checks by the Department. The
cost of this work is required to be worked
out based on approved design, drawings
and estimate of the lowest tender. A
separate contract for this work is concluded
as the contractors for road and bridge
works generally donot undertake such jobs.
8.41 Toll Plaza
The construction, operation and
maintenance of Toll Plaza can be broken
into separate items of work as under based
on the approved design and drawings:-
a) Provision of toll collection service lane
to separate different categories of vehicles
for purpose of toll collection. This involves
considerable increase in carriage way width
b) Provision of 2.5 m wide separators for
different toll collection service lanes for
safety
c) Toll booths with integrated roof cover
d) Barrier gates for individual lanes
e) Provision of building to provide facility
to toll plaza personnel
f) Toll plaza office equipment and
furniture
g) Water supply, electricity, sanitation,
septic-tank system and drainage
h) Telephone, intercomes, wireless
communication system
i) High mast lighting
j) Pavement marking
k) Overhead signs
l) Fixed message signs (Advance)
m) Variable message signs
n) Traffic cones and pylons
o) First aid post
p) Traffic aid post and security
The quantities for the above mentioned
items may be calculated from the approved
design and drawings and their rates
adopted from respective chapters of the
Standard Data Book
Safety Devices and Signs in
8.42
Construction Zones

Page 27 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H Provision and fixing of traffic signs for ref.
Spec. limited period at suitable locations in
construction zone comprising of warning
zone, approach transition zone, working
zone and terminal transition zone with a
minimum distance of 60 cm from the edge
of the kerb in case of kerbed roads and 2 to
3 m from the edge of the carriageway in
case of un-kerbed roads, the bottom edge
of the lowest sign plate to be not less than
2 m above the road level, fixed on 60 mm x
60 mm x 6 mm angle iron post, founded
and installed as per approved design and
drawings, removed and disposed of after
completion of construction work, all as per
IRC:SP:55-2001
Unit = each
Taking output = one sign post
Following types of signs are required to be
fixed in construction zones for safety of
traffic
a) Diversion one km ahead
b) Traffic sign ahead
c) Road ahead closed
d) Men at work
e) Road narrow
f) Single file traffic
g) Right lane diverted
h) Left lane diverted
i) Right lane closed
j) Left lane closed
k) Median closed
l) Diversion to other carriageway
m) Traffic signal ahead
n) Two way traffic
o) Un - even road
p) Slippery road
q) Loose chippings
r) Dual carriageway ends
s) Diversion
t) Do not enter
u) Road closed
v) Stop
w) Slow
x) One way
y) Give way
z) Overtaking prohibited
aa) Speed limit
bb) Weight limit
cc) Height and length limit
dd) No stopping or standing
ee) Any other warning or regulatory
safety sign as per site requirement and
consistent with IRC:SP:55-2001 and IRC:67
The rate for traffic signs are already worked
out and given elsewhere in this chapter.
The same may be adopted.
sugge Portable Barricade in Construction
8.43
stive Zone

Page 28 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Installation of a steel portable barricade
with horizontal rail 300 mm wide, 2.5 m in
length fitted on a 'A' frame made with 45 x
45 x 5 mm angle iron section, 1.5 m in
height, horizontal rail painted (2 coats) with
yellow and white stripes, 150 mm in width
at an angle of 450, 'A' frame painted with 2
coats of yellow paint, complete as per
IRC:SP:55-2001
Unit = each
Taking output = one steel portable
barricade
a) Labour
Mate day 0.020 150.00 3.00 L-12
Mazdoor day 0.250 100.00 25.00 L-13
Painter day 0.500 200.00 100.00 L-18
Welder day 0.250 150.00 37.50 L-02
b) Material
32.00 800.00 M-179 /
Angle iron 45 x 45 x 5 mm kg 25.000
1000
MS sheet 300 mm wide,2.5 m long and 32.00 480.00 M-179 /
kg 15.000
2.6 mm thick 1000
Paint litre 0.500 135.00 67.50 M-131
Add 2 per cent of cost of steel for welding
25.60
consumables, nuts & bolts and drilling holes
c) Overhead charges @ 10 % on
153.86
(a+b) Contractor's profit @ 10 % on
d)
169.25
(a+b+c)
Rate per barricade = a+b+c+d 1861.71
say 1862.00
sugge Permanent Type Barricade in
8.44
stive Construction Zone
A With steel components
Construction of a permanent type barricade
made of steel components, 1.5 m high from
road level, fitted with 3 horizontal rails 200
mm wide and 4 m long on 50 x 50 x 5 mm
angle iron vertical support, painted with
yellow and white strips, 150 mm in width at
an angle of450, complete as per IRC:SP:55-
2001
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.050 150.00 7.50 L-12
Mazdoor day 0.300 100.00 30.00 L-13
Painter day 0.600 200.00 120.00 L-18
Welder day 0.300 150.00 45.00 L-02
b) Material
Angle iron 50 x 50 x 5 mm,2 m long,2 32.00 480.00 M-179 /
kg 15.000
Nos. 1000
MS sheet of 12 SWG,3 Nos of 200 mm 32.00 1600.00 M-179 /
kg 50.000
width and 4 m length 1000
Paint litre 1.000 135.00 135.00 M-131
Add 1 per cent of cost of steel for welding
41.60
consumables, nuts & bolts and drilling holes
c) Overhead charges @ 10 % on
245.91
(a+b) Contractor's profit @ 10 % on
d)
270.50
(a+b+c)
Rate per barricade = a+b+c+d 2975.51
say 2976.00
8.44 B With wooden components

Page 29 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Construction of a permanent type barricade
made of wooden components, 1.5 m high
from road level, fitted with 3 horizontal
planks 200 mm wide and 3.66 m long on
100 x 100mm wooden vertical post, painted
with yellow and white strips, 150 mm in
width at an angle of450, complete as per
IRC:SP:55-2001
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.050 150.00 7.50 L-12
Mazdoor day 0.300 100.00 30.00 L-13
Painter day 0.600 200.00 120.00 L-18
Carpenter day 0.600 150.00 90.00 L-04
b) Material
Timber cum 0.180 6000.00 1080.00 M-185
Add 1 per cent of cost of timber for nuts &
10.80
bolts, nails, etc.
c) Overhead charges @ 10 % on
133.83
(a+b)
d) Contractor's profit @ 10 % on
147.21
(a+b+c)
Rate per barricade = a+b+c+d 1619.34
say 1619.00
8.44 C With bricks
Construction of a permanent type barricade
made with brick work in mud mortar, 1.5 m
high, 4 m long, 600 mm thick, plastered
with cement mortar 1:6, painted with yellow
and white strips
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.240 150.00 36.00 L-12
Mazdoor day 3.000 100.00 300.00 L-13
Painter day 1.000 200.00 200.00 L-18
Mason day 2.000 250.00 500.00 L-11
b) Material
Brick each 1800.000 2.00 3600.00 M-079
4.18 91.96 M-081 /
Cement kg 22.000
1000
Sand cum 0.090 350.00 31.50 M-005
Paint litre 1.250 135.00 168.75 M-131
c) Overhead charges @ 10 % on
492.82
(a+b)
d) Contractor's profit @ 10 % on
542.10
(a+b+c)
Rate per barricade = a+b+c+d 5963.13
say 5963.00
sugge
8.45 Drum Delineator in Construction Zone
stive
Provision of metal drum/empty bitumen
drum delineator, 300 mm in diameter, 800
mm high, filled with earth for stability,
painted in circumferential strips of alternate
black and white 100 mm wide fitted with
reflectors 3 Nos of 7.5 cm dia, all as per
IRC:SP:55-2001
Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.020 150.00 3.00 L-12
Mazdoor day 0.250 100.00 25.00 L-13
Painter day 0.250 200.00 50.00 L-18
b) Material

Page 30 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 200.00 200.00 M-172
Steel drum 300 mm dia 1.2 m
each 1.000
high/empty bitumen drum
Paint litre 0.500 135.00 67.50 M-131
c) Overhead charges @ 10 % on
34.55
(a+b) Contractor's profit @ 10 % on
d)
38.01
(a+b+c)
Rate per drum delineator = a+b+c+d 418.06
say 418.00
sugge
8.46 Flagman
stive
Positioning of a smart flagman with a yellow
vest and a yellow cap and a red flag 600 x
600 mm securely fastened to a staff 1 m in
length for guiding the traffic
Unit = each
Taking output = one flagman
a) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoor day 1.000 100.00 100.00 L-13
b) Material
Flag of red color cloth 600 x 600 mm each 1.000 15.00 15.00 M-099
Wooden staff for fastening of flag 25 10.00 10.00 M-196
each 1.000
mm dia, one m long
c) Overhead charges @ 10 % on
13.10
(a+b)
d) Contractor's profit @ 10 % on
14.41
(a+b+c)
Rate per flagman = a+b+c+d 158.51
say 159.00

Page 31 of 361
CHAPTER-9
Ref. PIPE CULVERTS
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
9.1 Spec.
408 PCC 1:3:6 in Foundation
Plain cement concrete 1:3:6 mix with
crushed stone aggregate 40 mm nominal
size mechanically mixed, placed in
foundation and compacted by vibration
including curing for 14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.640 150.00 96.00 L-12
Mason day 1.000 250.00 250.00 L-11
Mazdoor day 15.000 100.00 1500.00 L-13
b) Material
40mm Aggregate at site cum 13.800 350.00 4830.00 M-055
Sand at site cum 6.900 350.00 2415.00 M-005
Cement at site tonne 3.300 4180.00 13794.00 M-081
Cost of water KL 18.000 50.00 900.00 M-189
c) Machinery
Concrete mixer0.4/ 0.28 cum hour 6.000 100.00 600.00 P&M-
Generator set 33 KVA hour 6.000 400.00 2400.00 009
P&M-
Water tanker6 KL capacity hour 3.000 105.00 315.00 079
P&M-
d) Overhead charges @ 10 % on 2710.00 060
(a+b+c)
e) Contractor's profit @ 10 % on 2981.00
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 32791.00
Rate per cum = (a+b+c+d+e)/15 2186.07
say 2186.00
Note Vibrator is a part of minor T & P which is
already included in overhead charges of the
9.2 2900 contractor.
Laying Reinforced Cement Concrete
Pipe NP4 / Prestressed Concrete Pipe
on First Class Bedding in Single Row .
Laying Reinforced cement concrete pipe
NP4/prestressed concrete pipe for culverts
on first class bedding of granular material in
single row including fixing collar with
cement mortar 1:2 but excluding
excavation, protection works, backfilling,
concrete and masonry works in head walls
Unit = metre
Taking output = 12.5 metres ( 5 pipes
of 2.5 m length each )
A 1000 mm dia
a) Labour
Mate day 0.180 150.00 27.00 L-12
Mason day 0.500 250.00 125.00 L-11
Mazdoor day 4.000 100.00 400.00 L-13
b) Material
Sand at site cum 0.070 350.00 24.50 M-005
Cement at site tonne 0.050 4180.00 209.00 M-081
RCC pipe NP-4 /prestressed concrete metre 12.500 4000.00 50000.00 M-149
pipe including collar at site
Granular material passing 5.6 mm sieve cum 4.500 160.00 720.00 M-009
for bedding
c) Overhead charges @ 10 % on 5150.55
(a+b)
d) Contractor's profit @ 10 % on 5665.61
(a+b+c)
Cost for 12.5 metres = a+b+c+d 62321.66
Rate per metre = (a+b+c+d)/12.5 4985.73
say 4986.00
Note 1. In case of cement craddle bedding,
quantity of PCC M15 is to be calculated as
per design and priced separately and added
.

Page 1 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 2. The rate analysis does not include
excavation, cement /masonry works in head
walls, backfilling, protection works and
parapet walls. The same are to be
calculated as per approved design and
drawings and priced separately on rates
available under respective sections
9.2 B 1200 mm dia
a) Labour
Mate day 0.280 150.00 42.00 L-12
Mason day 1.000 250.00 250.00 L-11
Mazdoor day 6.000 100.00 600.00 L-13
b) Material
Sand at site cum 0.090 350.00 31.50 M-005
Cement at site tonne 0.070 4180.00 292.60 M-081
RCC pipe NP-4/prestressed concrete metre 12.500 4500.00 56250.00 M-150
pipe including collar at site
Granular material passing 5-6 mm sieve cum 5.000 160.00 800.00 M-009
for class bedding
c) Overhead charges @ 10 % on 5826.61
(a+b)
d) Contractor's profit @ 10 % on 6409.27
(a+b+c)
Cost for 12.5 metres = a+b+c+d 70501.98
Rate per metre= (a+b+c+d)/12.5 5640.16
say 5640.00
Note 1. In case of cement craddle bedding,
quantity of PCC M15 is to be calculated as
per design and priced separately and added
.
2. The rate analysis does not include
excavation, cement /masonry works in head
walls, backfilling, protection works and
parapet walls. The same are to be
calculated as per approved design and
drawings and priced separately on rates
available under respective sections
9.3 2900 Laying Reinforced Cement Concrete
Pipe NP4 / Prestressed Concrete Pipe
on First Class Bedding in Double Row .
Laying Reinforced cement concrete pipe
NP4 / prestressed concrete pipe for culverts
on first class bedding of granular material in
double row including fixing collar with
cement mortar 1:2 but excluding
excavation, protection works, backfilling,
concrete and masonry works in head walls
Unit = metre
Taking output = 12.5 metres ( 10 pipes
of 2.5 m length each in two rows.)
A 1000 mm dia
a) Labour
Mate day 0.360 150.00 54.00 L-12
Mason day 1.000 250.00 250.00 L-11
Mazdoor day 8.000 100.00 800.00 L-13
b) Material
Sand at site cum 0.140 350.00 49.00 M-005
Cement at site tonne 0.100 4180.00 418.00 M-081
RCC pipe NP-4/prestressed concrete metre 25.000 4000.00 ### M-149
pipe including collar at site
Granular material passing 5.6 mm sieve cum 12.500 160.00 2000.00 M-009
for bedding
c) Overhead charges @ 10 % on 10357.10
(a+b) Contractor's profit @ 10 % on
d) 11392.81
(a+b+c)
Cost for 12.5 metres = a+b+c+d ###
Rate per metre = (a+b+c+d)/12.5 10025.67

Page 2 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Note 1. In case of cement craddle bedding, say ###
quantity of PCC M15 is to be calculated as
per design and priced separately and added
.
2. The rate analysis does not include
excavation, cement /masonry works in head
walls, backfilling, protection works and
parapet walls. The same are to be
calculated as per approved design and
drawings and priced separately on rates
available under respective sections
9.3 B 1200 mm dia
a) Labour
Mate day 0.560 150.00 84.00 L-12
Mason day 2.000 250.00 500.00 L-11
Mazdoor day 12.000 100.00 1200.00 L-13
b) Material
Sand at site cum 0.180 350.00 63.00 M-005
Cement at site tonne 0.140 4180.00 585.20 M-081
RCC pipe NP-4 /prestressed concrete metre 25.000 4500.00 ### M-150
pipe including collar at site
Granular material passing 5-6 mm sieve cum 13.750 160.00 2200.00 M-009
for class bedding
c) Overhead charges @ 10 % on 11713.22
(a+b) Contractor's profit @ 10 % on
d) 12884.54
(a+b+c)
Cost for 12.5 metres = a+b+c+d ###
Rate per metre= (a+b+c+d)/12.5 11338.40
Note 1. In case of cement craddle bedding, say ###
quantity of PCC M15 is to be calculated as
per design and priced separately and added
.
2. The rate analysis does not include
excavation, cement /masonry works in head
walls, backfilling, protection works and
parapet walls. The same are to be
calculated as per approved design and
drawings and priced separately on rates
available under respective sections

Page 3 of 361
CHAPTER- 10
Ref. MAINTENANCE OF ROADS
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
10.1 Spec.
3002 Restoration of Rain Cuts
Restoration of rain cuts with soil, moorum,
gravel or a mixture of these, clearing the
loose soil, benching for 300 mm width,
laying fresh material in layers not
exceeding 250 mm and compacting with
plate compactor or power rammers to
restore the original alignment, levels and
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor day 2.000 100.00 200.00 L-13
b) Machinery
Excavator1.0 cum bucket capacity @ 60 hour 0.130 700.00 91.00 P&M-
cum per hour 026
Tipper ( L is average lead in km for tonne.k 12 x L 1.85 222.00 Lead
borrow earth) m =10 km
& P&M-
058
Add 10 per cent of cost of carriage towards 22.20
loading and unloading charges.
Plate compactor hour 0.500 75.00 37.50 P&M-
c) Overhead charges @ 10 % on 58.47 086
(a+b)
d) Contractor's profit @ 10 % on 64.32
(a+b+c)
Cost for 10 cum = a+b+c+d 707.49
Rate per cum = (a+b+c+d)/10 70.75
say 71.00
Note Only 75 per cent of fresh material has
been provided as 25 per cent can be
retrieved at site from earth that is flown
down the slope in the form of slurry and
deposited at the foot of there in cuts
10.2 3003 Maintenance of Earthen Shoulder
(filling with fresh soil)
Making up loss of material/ irregularities on
shoulder to the design level by adding fresh
approved soil and compacting it with
appropriate equipment.
Unit = sqm
Taking output = 100 sqm
Assuming average thickness of filling to be
150 mm of fresh material = 15 cum
Quantity
a) Labour
Mate day 0.180 150.00 27.00 L-12
Mazdoor day 4.500 100.00 450.00 L-13
b) Machinery
Excavator1.0 cum bucket capacity @ 60 hour 0.250 700.00 175.00 P&M-
cum per hour 026
Tipper ( L is average lead in km for tonne.k 24xL 1.85 444.00 Lead
borrow earth) m =10 km
& P&M-
058
Add 10 per cent of cost of transportation 44.40
to cover cost of loading and unloading
Plate compactor @ 25 sqm per hour hour 12.000 75.00 900.00 P&M-
c) Overhead charges @ 10 % on 204.04 086
(a+b)
d) Contractor's profit @ 10 % on 224.44
(a+b+c)
Cost for 100 sqm = a+b+c+d 2468.88
Rate per sqm = (a+b+c+d)100 24.69
say 25.00
10.3 3003 Maintenance of Earth Shoulder
(stripping excess soil)
Stripping excess soil from the shoulder
surface to achieve the approved level and
compacting with plate compactor
Unit = sqm

Page 1 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Taking output = 100 sqm
Assuming average depth of stripping as 75
mm
Quantity of earth cutting involved = 7.5
cum Labour
a)
Mate day 0.100 150.00 15.00 L-12
Mazdoor day 2.500 100.00 250.00 L-13
b) Machinery
Plate compactor @ 25 sqm per hour hour 4.000 75.00 300.00 P&M-
c) Overhead charges @ 10 % on 56.50 086
(a+b)
d) Contractor's profit @ 10 % on 62.15
(a+b+c)
Cost for 100 sqm = a+b+c+d 683.65
Rate per sqm on = (a+b+c+d)100 6.84
say 7.00
Note The earth stripped from earthen shoulders
to be dumped on the side slopes locally for
10.4 3004. disposal.
Filling Pot-holes and Patch Repairs
2 with open-Graded Premix surfacing,
20mm.
Removal of all failed material, trimming of
completed excavation to provide firm
vertical faces, cleaning of surface, painting
of tack coat on the sides and base of
excavation as per clause 503, back filling
the pot holes with hot bituminous material
as per clause 511, compacting, trimming
and finishing the surface to form a smooth
continuous
Unit = Sqm surface, all as per clause 3004.2
Taking out put = 10250 sqm (205 cum)
(405 Labour
a) tonne)
Mate Day 3.760 150.00 564.00 L-12
Mazdoor Day 90.000 100.00 9000.00 L-13
Mazdoor skilled Day 4.000 125.00 500.00 L-15
b) Machinery
Air compressor 250 cfm hour 6.000 150.00 900.00 P&M-
HMP 100-110 TPH Capacity hour 6.000 6900.00 41400.00 001
P&M-
Tipper 10 tonnes capacity hour 45.000 185.00 8325.00 021
P&M-
Smooth wheeled roller 8-10 tonnes hour 12.000 170.00 2040.00 048
P&M-
c) Material 044
Crushed stone aggregates nominal size cum 184.500 410.00 75645.00 M-052
13.2mm
Crushed stone aggregates nominal size cum 92.250 410.00 37822.50 M-051
11.2mm 80/100
Bitumen tonne 14.970 26030.00 ### M-075
Bitumen emulsion for tack coat tonne 2.460 24000.00 59040.00 M-077
including vertical sides of pot hole.
d) Overhead charges @ 10 % on 62490.56
(a+b+c)
e) Contractor's profit @ 10 % on 68739.62
(a+b+c+d)
Cost for 10250 sqm = a+b+c+d+e ###
Rate per sqm = (a+b+c+d+e)/10250 73.77
say 74.00
10.5 3004. Filling Pot-holes and Patch Repairs
2 with Bituminous concrete, 40mm.
Removal of all failed material, trimming of
completed excavation to provide firm
vertical faces, cleaning of surface, painting
of tack coat on the sides and base of
excavation as per clause 503, back filling
the pot holes with hot bituminous material
as per clause 504, compacting, trimming
and finishing the surface to form a smooth
continuous
Unit = Sqm surface, all as per clause 3004.2
Taking out put = 4900 sqm (196 cum)
(450 Labour
a) Tonnes)
Mate Day 2.920 150.00 438.00 L-12
Mazdoor Day 70.000 100.00 7000.00 L-13
Mazdoor skilled Day 3.000 125.00 375.00 L-15

Page 2 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. b) Machinery
Air compressor 250 cfm hour 6.000 150.00 900.00 P&M-
HMP 100-110 TPH Capacity hour 6.000 6700.00 40200.00 001
P&M-
Tipper 10 tonnes capacity hour 45.000 185.00 8325.00 022
P&M-
Smooth wheeled roller 8-10 tonnes hour 12.000 170.00 2040.00 048
P&M-
c) Material 044
I) Bitumen tonne 22.500 26030.00 ### M-075
ii) Bitumen emulsion for tack coat . tonne 1.180 24000.00 28320.00 M-077
iii) Aggregates
Grading I - 19mm(Nominal size)
20-10mm 35 per cent cum 99.750 410.00 40897.50 M-
051,M-
052,M-
053 and
M-054
10-5 mm 23 per cent cum 65.550 200.00 13110.00 M-025
5mm and below40 per cent cum 114.000 267.00 30438.00 M-
021,M-
022 and
M-024
Add 5 per cent for wastage 4222.28
or
Grading-II 13mm (Nominal size)
13.2-10 mm 30 per cent cum 85.500 410.00 35055.00 M-051
and M-
052
10-5 mm 25 per cent cum 71.250 200.00 14250.00 M-025
5 mm and Below43 per cent cum 122.550 267.00 32720.85 M-
021,M-
022 and
M-024
Filler 2 per cent tonne 9.000 2400.00 21600.00 M-188
Add 5 per cent for wastage 5181.29
Any one of the above alternatives of
aggregate i.e. 19mm or 13mm nominal size
may be adopted as per approved design.
10.5 (i) for grading I Material
d) Overhead charges @ 10 % on 76194.08
(a+b+c)
e) Contractor's profit @ 10 % on 83813.49
(a+b+c+d)
Cost for 4900 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/4900 188.15
say 188.00
10.5 (ii) for grading II Material
d) Overhead charges @ 10 % on 78208.01
(a+b+c)
e) Contractor's profit @ 10 % on 86028.82
(a+b+c+d)
Cost for 4900 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/4900 193.13
say 193.00
Note For detailed working of quantities of
aggregates, refer item 5.8 of chapter 5
10.6 3004. Crack Filling
3.3
Filling of crack using slow - curing bitumen
emulsion and applying crusher dust in case
crack are wider than 3mm.
Unit = Running Meter
Taking out put = 500m
a) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoor day 1.000 100.00 100.00 L-13
b) Material
Slow-curing bitumen emulsion Kg 33.000 24.00 792.00 M-077

Page 3 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Stone crusher dust cum 0.020 200.00 4.00 M-021
c) Overhead charges @ 10 % on 90.20
(a+b)
d) Contractor's profit @ 10 % on 99.22
(a+b+c)
Cost for 500sqm = a+b+c+d 1091.42
Rate per meter = (a+b+c+d+e)/500 2.18
say 2.00
10.7 3004. Dusting
4 Applying crusher dust to areas of road
where bleeding of excess bitumen has
occurred.
Unit = Sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor day 2.000 100.00 200.00 L-13
b) Material
Stone crusher dust finer than 3mm cum 6.250 200.00 1250.00 M-021
with not more than 10 per cent
c) passing 0.075
Overhead sieve. @ 10 % on
charges 146.20
(a+b)
d) Contractor's profit @ 10 % on 160.82
(a+b+c)
Cost for 3500sqm = a+b+c+d 1769.02
Rate per meter = (a+b+c+d)/3500 0.51
say 0.51
10.8 (A) Fog Seal sqm 24.00 Item
3004. 5.17
3.2
(B) Crack Prevention courses.
3004.
3.4
(i) Stress Absorbing Membrane (SAM) crack sqm 38.00 Item
width less than 6 mm 5.21
(ii) Stress Absorbing Membrane (SAM) with sqm 46.00 Case-I
Item
crack width 6 mm to 9 mm 5.21
(iii) Stress Absorbing Membrane (SAM) crack sqm 61.00 Case-II
Item
width above 9 mm and cracked area above 5.21
(iv) 50 per cent
Bitumen Impregnated Geotextile sqm 434.00 Case-IV
Item
5.21
10.8 (C) Slurry Seal Case-IV
3004.
5 (i) 5 mm thickness sqm 40.00 Item
5.15
(ii) 3 mm thickness sqm 28.00 Case-I
Item
5.15
(iii) 1.5 mm thickness sqm 17.00 Case-II
Item
5.15
10.8 (D) Surface Dressing for maintenance Case-III
3004. works.
6 (i) 19 mm nominal chipping size sqm 49.00 Item 5.9
Case-I
(ii) 13 mm nominal size chipping sqm 41.00 Item 5.9
Case-II
The above mentioned items have already
been included in chapter 5.
10.9 3005. Repair of Joint Grooves with Epoxy
1 Mortar
Repair of spalled joint grooves of
contraction joints, longitudinal joints and
expansion joints in concrete pavements
using epoxy mortar or epoxy concrete
Unit = running metre
Taking output = 10 metres
a) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoor day 0.500 100.00 50.00 L-13

Page 4 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Chiseller day 0.500 150.00 75.00 L-05
b) Material
Epoxy primer kg 2.500 300.00 750.00 M-097
Epoxy compound with accessories for kg 10.000 300.00 3000.00 M-095
preparing epoxy mortar
c) Machinery
Air compressor 250 cfm for cleaning hour 0.050 150.00 7.50 P&M-
d) Overhead charges @ 10 % on 388.85 001
(a+b+c)
e) Contractor's profit @ 10 % on 427.74
(a+b+c+d)
Cost for 10 metres = a+b+c+d+e 4705.09
Rate per metre = (a+b+c+d+e)/10 470.51
say 471.00
10.1 3005. Repair of old Joints Sealant
0 2 Removal of existing sealant and re sealing
of contraction, longitudinal or expansion
joints in concrete pavement with fresh
sealant material
Unit = running metre
Taking output = 10 metres
a) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoor day 0.500 100.00 50.00 L-13
b) Material
Primer kg 0.250 95.00 23.75 M-146
Sealant kg 1.000 550.00 550.00 M-120
c) Machinery
Air compressor 250 cfm for cleaning hour 0.050 150.00 7.50 P&M-
d) Overhead charges @ 10 % on 63.73 001
(a+b+c)
e) Contractor's profit @ 10 % on 70.10
(a+b+c+d)
Cost for 10 metres = a+b+c+d+e 771.07
Rate per metre = (a+b+c+d+e)/10 77.11
say 77.00
10.1 3000 Hill Side Drain Clearance
1 Removal of earth from the choked hill side
drain and disposing it on the valley side
manually
Unit = running metre
Taking output = 10 metres
Assuming muck causing choking of drain to
be 0.2 cum per metre, quantity of earth to
be removed for 10 metres = 2 cum
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor day 1.000 100.00 100.00 L-13
b) Overhead charges @ 10 % on 11.20
(a+b)Contractor's profit @ 10 % on
c) 12.32
(a+b)
Cost for 10 metres = a+b+c 135.52
Rate per metre = (a+b+c)/10 13.55
say 14.00
10.1 3000 Land Slide Clearance in soil
2 Clearance of land slides in soil and ordinary
rock by a bull-dozer D 80 A-12, 180 HP and
disposal of the same on the valley side
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoor day 1.000 100.00 100.00 L-13
b) Machinery
Dozer 180 HP @ 60 cum per hour hour 1.670 2000.00 3340.00 P&M-
014

Page 5 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. c) Overhead charges @ 10 % on 344.60
(a+b)
d) Contractor's profit @ 10 % on 379.06
(a+b+c)
Cost for 100 cum = a+b+c+d 4169.66
Rate per cum = (a+b+c+d)/100 41.70
say 42.00
Note Land Slide clearance involves pushing of
loose earth slided on the road surface from
hill face on the valley side. Since no cutting
of original ground is involved, the output of
dozer has been taken as 60 cum per hour
for soil, ordinary rock and blasted hard rock.
However, if there are objection to disposing
of earth on valley side, additional resources
for its disposal shall be considered as per
10.1 3000 site conditions.
Landslide Clearance in Hard Rock
3 Requiring Blasting
Clearing of land slide in hard rock requiring
blasting for 50 per cent of the boulders and
disposal of the same on the valley side.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.090 150.00 13.50 L-12
Mazdoor day 1.500 100.00 150.00 L-13
Driller day 0.750 150.00 112.50 L-06
Blaster day 0.070 150.00 10.50 L-03
b) Machinery
Dozer D 80 A-12,180 HP @ 60 cum per hour 1.670 2000.00 3340.00 P&M-
hour
Air compressor 250 cfm with two jack hour 2.500 150.00 375.00 014
P&M-
c) hammer
Materials 001
Gelatine 80 per cent @ 35 kg per 100 kg 17.500 100.00 1750.00 M-104
cum
Electric Detonators @ 1 Detonator for 2 each 70.000 5.00 350.00 M-094 /
Gelatine sticks of 125 gms each 100
c) Overhead charges @ 10 % on 610.15
(a+b)
d) Contractor's profit @ 10 % on 671.17
(a+b+c)
Cost for 100 cum = a+b+c+d+e 7382.82
Rate per cum = (a+b+c+d+e)/100 73.83
say 74.00
Note Credit for the rock if found acceptable as
construction material shall be afforded
10.1 3000 Snow Clearance on Roads with Dozer
4 Snow clearance from road surface by a bull-
dozer 165 Hp and disposing it on the valley
side = cum
Unit
Taking output = 5000 cum
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor day 2.000 100.00 200.00 L-13
b) Machinery
Dozer D 80 A-12,180 HP @ 850 cum per hour 5.880 2000.00 11760.00 P&M-
c) hour
Overhead charges @ 10 % on 1197.20 014
(a+b)
d) Contractor's profit @ 10 % on 1316.92
(a+b+c)
Cost for 5000 cum = a+b+c+d 14486.12
Rate per cum = (a+b+c+d)/5000 2.90
say 3.00
Note i) Labour provided will not be cutting the
snow. They will be guiding the dozer
operator on the alignment of the road as
entire surface gets covered with snow and
the edges of the road are not visible and for
changing the blade angle. Also they will
keep a watch on the hill side for any

Page 6 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
10.1 Spec.
3000 Snow Clearance on Roads with Snow
5 Blowers
Snow clearance from road surface by a
snow blower and disposing on the valley
side. = cum
Unit
Taking output = 3600 cum
a) Labour
Mate day 0.080 150.00 12.00 L-12
Mazdoor day 2.000 100.00 200.00 L-13
b) Machinery
Snow blower equipment 140 HP @ 600 hour 6.000 500.00 3000.00 P&M-
cum per hour 087
c) Overhead charges @ 10 % on 321.20
(a+b)
d) Contractor's profit @ 10 % on 353.32
(a+b+c)
Cost for 3600 cum (a+b+c+d) 3886.52
Rate per cum = (a+b+c+d)/3600 1.08
say 1.00

Page 7 of 361
CHAPTER-11
Ref. HORTICULTURE
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
11.1 Spec.
307 Spreading of Sludge Farm Yard Manure
or/and good Earth
Spreading of sludge farm yard manure or/
and good earth in required thickness (cost
of sludge, farm yard manure or/and good
earth to be paid for separately)
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.040 150.00 6.00 L-12
Mazdoor day 1.000 100.00 100.00 L-13
b) Overhead charges @ 10 % on (a) 10.60
c) Contractor's profit @ 10 % on 11.66
(a+b)
Cost for 15 cum= a+b+c 128.26
Rate per cum = (a+b+c)/15 8.55
say 9.00
11.2 307 Grassing with ' Doobs' Grass
Grassing with 'Doobs' grass including
watering and maintenance of the lawn for
30 days or more till the grass forms a thick
lawn free from weeds and fit for moving
including supplying good earth if needed
Unit = sqm
Taking output = 100 sqm
(i) In rows 15 cm apart in either direction
a) Labour
Mate day 0.170 150.00 25.50 L-12
Mazdoor for grassing day 0.750 100.00 75.00 L-13
Mazdoor for maintenance for 30 days day 1.000 100.00 100.00 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 105.00 52.50 P&M-
c) Material 060
Doob grass kg 100.000 60.00 6000.00 M-112
d) Overhead charges @ 10 % on 625.30
(a+b+c)
e) Contractor's profit @ 10 % on 687.83
(a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 7566.13
Rate per sqm= (a+b+c+d+e)/100 75.66
say 76.00
11.2 (ii) In rows 7.5 cm apart in either
direction
a) Labour
Mate day 0.220 150.00 33.00 L-12
Mazdoor for grassing. day 1.250 100.00 125.00 L-13
for maintenance for 30 days day 1.000 100.00 100.00 L-13
b) Machinery
Water tanker6 KL capacity hour 0.750 105.00 78.75 P&M-
c) Material 060
Doob grass kg 200.000 60.00 12000.00 M-112
d) Overhead charges @ 10 % on 1233.68
(a+b+c)
e) Contractor's profit @ 10 % on 1357.04
(a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 14927.47
Rate per sqm = (a+b+c+d+e)/100 149.27
say 149.00
Note In the case of horticulture one mate has
been provided for every 10 mazdoors as
maintenance of grass and plants require
more care.
11.3 307 Making Lawns including Ploughing and
Dragging with 'Swagha' Breaking of
Clod
Making lawns including ploughing and
breaking of clod, removal of rubbish,
dressing and supplying doobs grass roots
and planting at 15 cm apart, including
supplying and spreading of farm yard
manure at rate of 0.18 cum per 100 sqm
Unit = sqm
Taking output = 100 sqm

Page 1 of 361
Spreading of sludge farm yard manure or/
and good earth in required thickness (cost
of sludge, farm yard manure or/and good
earth to be paid for separately)
a) Labour
Mate day 0.150 150.00 22.50 L-12
Mazdoor for preparation of ground day 0.500 100.00 50.00 L-13
Mali for fetching doobs grass roots and day 1.000 150.00 150.00 L-09
grassing at 15 cm apart
b) Machinery
Water tanker6 KL capacity hour 0.500 105.00 52.50 P&M-
Tractor with tiller hour 0.010 150.00 1.50 060
P&M-
c) Material 053
Supply of farm yard manure at site of cum 0.180 250.00 45.00 M-167
work
Fine grass kg 100.000 100.00 10000.00 M-113
d) Overhead charges @ 10 % on 1032.15
(a+b+c)
e) Contractor's profit @ 10 % on 1135.37
(a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 12489.02
Rate per sqm = (a+b+c+d+e)/100 124.89
say 125.00
11.4 307 Maintenance of Lawns or Turfing of
Slopes
Maintenance of lawns or Turfing of slopes
(rough grassing) for a period of one year
including watering etc
Unit = sqm
Taking output = 100 sqm
a) Labour
Mali day 10.000 150.00 1500.00 L-09
b) Machinery
Water tanker6 KL capacity hour 15.000 105.00 1575.00 P&M-
c) Material 060
Cost of water KL 90.000 50.00 4500.00 M-189
d) Overhead charges @ 10 % on 757.50
(a+b+c)
e) Contractor's profit @ 10 % on 833.25
(a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 9165.75
Rate per sqm = (a+b+c+d+e)/100 91.66
say 92.00
11.5 307 Turfing Lawns with Fine Grassing
including Ploughing, Dressing
Turfing lawns with fine grassing including
ploughing, dressing including breaking of
clods, removal of rubbish, dressing and
supplying doobs grass roots at 10 cm apart,
including supplying and spreading of farm
yard manure at rate of0.6 cum per 100 sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.250 150.00 37.50 L-12
Mazdoor for preparation of ground day 1.000 100.00 100.00 L-13
Mali for fetching doobs grass roots day 1.500 150.00 225.00 L-09
hedges and grassing at 10 cm apart
b) Machinery
Water tanker6 KL capacity hour 0.500 105.00 52.50 P&M-
Tractor with tiller hour 0.010 150.00 1.50 060
P&M-
c) Material 053
Supply of farm yard manure at site of cum 0.600 250.00 150.00 M-167
work @ 0.6 cum per 100 sqm
Fine grass kg 100.000 100.00 10000.00 M-113
d) Overhead charges @ 10 % on 1056.65
(a+b+c)
e) Contractor's profit @ 10 % on 1162.32
(a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 12785.47
Rate per sqm = (a+b+c+d+e)/100 127.85
say 128.00

Page 2 of 361
Spreading of sludge farm yard manure or/
and good earth in required thickness (cost
of sludge, farm yard manure or/and good
earth to be paid for separately)
11.6 307 Maintenance of Lawns with Fine
Grassing for the First Year
Maintenance of lawns with fine grassing for
the first year including watering etc
Unit = sqm
Taking output = 100 sqm
a) Labour
Mali day 10.000 150.00 1500.00 L-09
b) Machinery
Water tanker6 KL capacity hour 20.000 105.00 2100.00 P&M-
c) Material 060
Cost of water KL 60.000 50.00 3000.00 M-189
d) Overhead charges @ 10 % on 660.00
(a+b+c)
e) Contractor's profit @ 10 % on 726.00
(a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 7986.00
Rate per sqm = (a+b+c+d+e)/100 79.86
say 80.00
11.7 307 Planting and Maintaining of Permanent
(a) Hedges permanent hedges including
Planting
digging of trenches
Planting permanent hedges including
digging of trenches, 60 cm wide and 45 cm
deep, refilling the excavated earth mixed
with farmyard manure, supplied at the rate
of 4.65 cum per 100 metres and supplying
and planting hedge plants at 30 cm apart
Unit = Running metre
Taking output = 100metre
a) Labour
Mate day 1.400 150.00 210.00 L-12
Mazdoor for digging of trench 60 cm day 10.000 100.00 1000.00 L-13
wide and 45 cm deep
Mazdoor for refilling the excavated day 4.000 100.00 400.00 L-13
earth mixed with cow dung, preparation
of ground and digging of plant, from the
nursery carriage to site and planting in
position
b) Machinery
Water tanker6 KL capacity hour 0.500 105.00 52.50 P&M-
c) Material 060
Cost of hedge plants 2 rows at 30 cm each 2x340 25.00 17000.00 M-116
apart
Supply of farm yard manure at site of cum 4.670 250.00 1167.50 M-167
work
Pesticide kg 0.250 200.00 50.00 M-136
Cost of water KL 3.000 50.00 150.00 M-189
d) Overhead charges @ 10 % on 2003.00
(a+b+c)
e) Contractor's profit @ 10 % on 2203.30
(a+b+c+d)
Cost for 100 metres = a+b+c+d+e 24236.30
Rate per metre = a+b+c+d+e)/100 242.36
say 242.00
(b) Maintenance of hedge for one year
Unit = Running metre
Taking output = 100 m
a) Labour
Mate day 3.000 150.00 450.00 L-12
Mazdoor day 30.000 100.00 3000.00 L-13
b) Machinery
Water tanker6 KL capacity hour 5.000 105.00 525.00 P&M-
c) Material 060
Manure sludge/Farm yard manure cum 2.000 250.00 500.00 M-167
Pesticide kg 0.500 200.00 100.00 M-136
Cost of water KL 30.000 50.00 1500.00 M-189

Page 3 of 361
Spreading of sludge farm yard manure or/
and good earth in required thickness (cost
of sludge, farm yard manure or/and good
earth to be paid for separately)
Cost of hedge plants @ 10 per cent each 68.000 25.00 1700.00 M-116
d) casualty
Overhead charges @ 10 % on 777.50
(a+b+c)
e) Contractor's profit @ 10 % on 855.25
(a+b+c+d)
Cost for 100 metres = a+b+c+d+e 9407.75
Rate per metre = a+b+c+d+e)/100 94.08
say 94.00
11.8 307 Planting and Maintaining of Flowering
Plants and Shrubs
(a) Planting flowering plants and shrubs in
central verge
Unit = Running metres 200 plants and
800 shrubs in two rows in one km
length of road where width of verge is
3m and above.
Taking output = 1000 metres
a) Labour
Mate day 1.200 150.00 180.00 L-12
Mazdoor day 12.000 100.00 1200.00 L-13
b) Machinery
Water tanker6 KL capacity hour 6.000 105.00 630.00 P&M-
c) Material 060
Plants each 200.000 26.00 5200.00 M-100
Shrubs each 800.000 20.00 16000.00 M-166
Manure sludge/Farm yard manure cum 63.640 250.00 15910.00 M-167
Pesticide kg 0.500 200.00 100.00 M-136
Cost of water KL 36.000 50.00 1800.00 M-189
d) Overhead charges @ 10 % on 4102.00
(a+b+c)
e) Contractor's profit @ 10 % on 4512.20
(a+b+c+d)
Rate per Km = (a+b+c+d+e) 49634.20
say ###
11.8 (b) Maintenance of flowering plants and
shrubs in central verge for one year
Unit = km
Taking output = one km
a) Labour
Mate day 36.000 150.00 5400.00 L-12
Mazdoor day 365.000 100.00 36500.00 L-13
b) Machinery
Water tanker6 KL capacity hour 90.000 105.00 9450.00 P&M-
c) Material 060
Manure Sludge / farm yard manure at cum 10.000 250.00 2500.00 M-167
site
Cost of water KL 180.000 50.00 9000.00 M-189
Replacement of casualties @ 10 per cent
Plants each 20.000 26.00 520.00 M-100
Shrubs each 80.000 20.00 1600.00 M-166
Pesticides kg 1.500 200.00 300.00 M-136
d) Overhead charges @ 10 % on 6527.00
(a+b+c)
e) Contractor's profit @ 10 % on 7179.70
(a+b+c+d)
Rate per Km for one year = 78976.70
(a+b+c+d+e) say ###
11.9 307 Planting of Trees and their
Maintenance for one Year
Planting of trees by the road side (Avenue
trees) in 0.60 m dia holes, 1 m deep dug in
the ground, mixing the soil with decayed
farm yard/sludge manure, planting the
saplings, backfilling the trench, watering,
fixing the tree guard and maintaining the
Unit = Each
Taking output = 10 trees
a) Labour

Page 4 of 361
Spreading of sludge farm yard manure or/
and good earth in required thickness (cost
of sludge, farm yard manure or/and good
earth to be paid for separately)
Mate day 1.700 150.00 255.00 L-12
Mazdoor for planting day 2.000 100.00 200.00 L-13
Mazdoor for maintenance for one year day 15.000 100.00 1500.00 L-13
b) Machinery
Water tanker6 KL capacity hour 2.000 105.00 210.00 P&M-
c) Material 060
Sapling 2 m high 25 mm dia each 10.000 50.00 500.00 M-160
Farm yard manure cum 0.940 250.00 235.00 M-167
Pesticide kg 0.500 200.00 100.00 M-136
Cost of water KL 12.000 50.00 600.00 M-189
d) Overhead charges @ 10 % on 360.00
(a+b+c)
e) Contractor's profit @ 10 % on 396.00
(a+b+c+d)
Cost for 10 trees = a+b+c+d+e 4356.00
Rate per trees = (a+b+c+d+e)/10 435.60
say 436.00
11.1 308 Renovation Lawns including, Weeding,
0 Forking the Ground, Top Dressing with
Forked Soil lawns including, weeding,
Renovation
forking the ground, top dressing with forked
soil, watering and maintenance the lawns,
for 30 days or more, till the grass forms a
thick lawn, free from weeds, and fit for
moving and disposal of rubbish as directed,
including supplying good earth, if needed
but excluding the cost of well decayed farm
yard manure
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 150.00 18.00 L-12
Mazdoor day 3.000 100.00 300.00 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 105.00 52.50 P&M-
c) Material 060
Cost of water KL 3.000 50.00 150.00 M-189
d) Overhead charges @ 10 % on 52.05
(a+b+c)
e) Contractor's profit @ 10 % on 57.26
(a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 629.81
Rate per sqm = (a+b+c+d+e) 6.30
say 6.00
11.1 308.2 Supply at Site Well Decayed Farm Yard
1 Manure
Supply at site of work well decayed farm
yard manure, from any available source,
approved by the engineer in charge
including screening and stacking
Unit = cum
Taking output = one cum
a) Material
a) Cost of well decayed farm yard cum 1.000 250.00 250.00 M-167
manure duly screened, loading,
carriage, unloading and stacking at
site
b) Overhead charges @ 10 % on (a) 25.00
c) Contractor's profit @ 10 % on 27.50
(a+b)per cum = (a+b+c)
Rate 302.50
303.00
11.1 308.2 Supply at Site of Work/ Store-Deoiled
2 0 Neem Cake
Supply at site of work/ store-deoiled neem
cake duly packed in used gunny bags
Unit = quintal
Taking output = one quintal
a) Cost, carriage, loading, unloading quintal 1.000
and stacking in store/site

Page 5 of 361
Spreading of sludge farm yard manure or/
and good earth in required thickness (cost
of sludge, farm yard manure or/and good
earth to be paid for separately)
b) Overheads@ per cent on (a)
c) Contractors profit@ per cent on
(a+b)per quintal = a+b+c
Rate
11.1 308.2 Supplying Sludge
3 Supplying sludge duly stacked at site/ store
Unit = cum
Taking output = one cum
a) Cost of sludge including carriage, cum 1.000
loading, unloading and stacking at site
b) Overheads@ per cent on (a)
c) Contractors profit@ per cent on
(a+b)per cum = a+b+c
Rate
11.1 New Half Brick Circular Tree Guard, in 2nd
4 Class Brick, internal diametre 1.25
metres, and height 1.2 metres, above
ground and 0.20 metre below ground
Half brick circular tree guard, in 2nd class
brick, internal diametre 1.25 metres, and
height 1.2 metres, above ground and 0.20
metre below ground, bottom two courses
laid dry, and top three courses in cement
mortar 1:6 (1 cement 6 sand) and the
intermediate courses being in dry honey
comb masonry, as per design complete
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 150.00 7.50 L-12
Mason day 0.250 250.00 62.50 L-11
Mazdoor day 0.250 100.00 25.00 L-13
b) Material
Brick 2nd class including carriage each 230.000 2.00 460.00 M-079
Cement mortar 1:6 cum 0.025 1720.00 43.00 Item
12.6 (D)
c) Overhead charges @ 10 % on 59.80
(a+b)
d) Contractor's profit @ 10 % on 65.78
(a+b+c)
Rate per tree Guard = a+b+c+d 723.58
say 724.00
11.1 New Edging with 2nd Class Bricks, Laid Dry
5 Lengthwise
Edging with 2nd class bricks, laid dry
lengthwise, including excavation, refilling,
consolidation, with a hand packing and
spreading nearly surplus earth within a lead
of 50 metres
Unit = Metre
Taking output= 10 metres
a) Labour
Mate day 0.002 150.00 0.30 L-12
Mason day 0.050 250.00 12.50 L-11
Mazdoor day 0.050 100.00 5.00 L-13
b) Material
Brick 2nd class including carriage each 50.000 2.00 100.00 M-079
c) Overhead charges @ 10 % on 11.78
(a+b)
d) Contractor's profit @ 10 % on 12.96
(a+b+c)
Cost for 10 metre = a+b+c+d 142.54
Rate per metre = (a+b+c+d)/10 14.25
say 14.00
11.1 New Making Tree Guard 53 cm dia and 1.3
6 m High as per Design from Empty
Bitumen Drums

Page 6 of 361
Spreading of sludge farm yard manure or/
and good earth in required thickness (cost
of sludge, farm yard manure or/and good
earth to be paid for separately)
Making tree guard 53 cm dia and 1.3 m
high as per design from empty bitumen
drum, slit suitably to permit sun and air,
(supplied by the department at stock issue
rate) including providing and fixing 2 nos
MS sheet rings 50 x 0.5 mm with rivets,
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.020 150.00 3.00 L-12
Blacksmith day 0.150 150.00 22.50 L-02
Mazdoor day 0.070 100.00 7.00 L-13
b) Material
Empty bitumen drum each 1.000 200.00 200.00 M-172
MS sheet 50 x 0.5 mm kg 0.650 32.00 20.80 M-179 /
1000
Rivets 6 mm dia and 10 mm in length each 22.000 1.00 22.00 M-158
d) Overhead charges @ 10 % on 27.53
(a+b+c)
e) Contractor's profit @ 10 % on 30.28
(a+b+c+d)
Rate for each tree guard = a+b+c+d 333.11
say 333.00
11.1 New Making Tree Guard 53 cm dia and 2
7 Metre High as per Design from Empty
Bitumen
Making treeDrums
guard 53 cm dia and 2 metres
high as per design from empty bitumen
drums, slit suitably to permit sun and air,
( supplied by the department at stock issue
rate) including providing and fixing four
legs 40 cm long of 30 x 3 mm MS riveted to
tree guard and providing and fixing 2 nos
MS sheet rings 50 x 0.5 mm with rivets
complete
Unit in all respects
= Each
Taking output = one tree guard
a) Labour
Mate 0.040 150.00 6.00 L-12
Blacksmith day 0.200 150.00 30.00 L-02
Mazdoor 0.200 100.00 20.00 L-13
b) Material
Empty bitumen drum each 1.500 200.00 300.00 M-172
MS sheet50 x 0.5 mm kg 0.650 32.00 20.80 M-179 /
1000
Rivets 6 mm dia and 10 mm in length each 50.000 1.00 50.00 M-158
MSplate30 x 3 mm kg 1.300 32.00 41.60 M-179 /
1000
c) Overhead charges @ 10 % on 46.84
(a+b)
d) Contractor's profit @ 10 % on 51.52
(a+b+c)
Rate for each tree guard = a+b+c+d 566.76
say 567.00
11.1 New Wrought Iron and Mild Steel Welded
8 Work
Wrought iron and mild steel welded work
(using angles, square bars, tees and
channel grills, grating frames, gates and
tree guards of any size and design etc.
including cost of screens and welding rods
or bolts and nuts complete fixed in position
but without the cost of excavation and
concrete for fixing which will be paid
separately
Unit = quintal
Taking output = one quintal
a) Labour
Mate day 0.450 150.00 67.50 L-12
Blacksmith/ welder for cutting to design day 2.000 150.00 300.00 L-02
and shape and jointing

Page 7 of 361
Spreading of sludge farm yard manure or/
and good earth in required thickness (cost
of sludge, farm yard manure or/and good
earth to be paid for separately)
Mazdoor for fixing and helper for day 2.500 100.00 250.00 L-13
b) Blacksmith/welder
Material
Angle, tees, channels etc quintal 1.050 3200.00 3360.00 M-179 /
Deduct the cost of scrap quintal 0.050 (1066.67) (53.33) 10
M-
179/10/
Add 5 per cent of cost of material for 165.33 3
welding rods and other welding accessories
c) Overhead charges @ 10 % on 408.95
(a+b)
d) Contractor's profit @ 10 % on 449.85
(a+b+c)
Rate per quintal = a+b+c+d 4948.30
say 4948.00
11.1 New Tree Guard with MS Iron
9 Providing and fixing MS iron tree guard 60
cm dia and 2 metre high above ground level
formed of 4 Nos (25 x 6 mm) and 8 Nos (25
x 3 mm) vertical MS riveted to 3 Nos (25 x 6
mm) iron rings in two halves, bolted
together with 8 mm dia and 30 mm long
bolts including painting two coats with paint
of approved brand over a coat of priming,
complete
Unit in all respects.
= Each
Taking output = one tree guard
a) Labour
Mate day 0.050 150.00 7.50 L-12
Blacksmith day 0.250 150.00 37.50 L-02
Mazdoor day 0.250 100.00 25.00 L-13
b) Material
MS iron 25 x 6 mm kg 19.200 32.00 614.40 M-179 /
1000
MS iron 25 x 3 mm kg 9.600 32.00 307.20 M-179 /
1000
Add 5 per cent of cost of material for
riveting, bolting and welding
c) accessories
Machinery
Tractor-trolley hour 0.040 150.00 6.00 P&M-
d) Painting 053
Painting two coats including priming sqm 1.770 35.00 61.95 Item 8.9
e) Overhead charges @ 10 % on 99.76
(a+b+c)
f) Contractor's profit @ 10 % on 109.74
(a+b+c+e)
Rate per tree guard =a+b+c+d+e+f 1269.05
say 1269.00
Note 1 The items of excavation and concreting to
be measured and paid separately as per
design . of painting may be adopted from
2 . Rate
the chapter as Traffic signs.
11.2 New Tree Guard with MS Angle Iron and
0 Steel Wire
Providing and fixing tree guard 0.60 metre
square, 2.00 metre high fabricated with MS
angle iron 30 x 30 x 3 mm, MS iron 25 x 3
mm and steel wire3 mm dia welded and
fabricated as per design in two halves
bolted together
Unit = Each
Taking output = one
a) Labour
Mate day 0.050 150.00 7.50 L-12
Blacksmith day 0.250 150.00 37.50 L-02
Welder day 0.250 150.00 37.50 L-02
Mazdoor day 0.250 100.00 25.00 L-13
b) Material
MS angle 30 x 30 x 3 mm kg 13.500 32.00 432.00 M-179 /
1000

Page 8 of 361
Spreading of sludge farm yard manure or/
and good earth in required thickness (cost
of sludge, farm yard manure or/and good
earth to be paid for separately)
MS iron 25 x 3 mm kg 18.000 32.00 576.00 M-179 /
1000
Steel wire 3 mm dia kg 6.000 40.00 240.00 M-192
Add 5 per cent of cost of material for 62.40
riveting, bolting and welding
c) accessories
Machinery
Tractor-trolley hour 0.040 150.00 6.00 P&M-
d) Painting 053
Painting two coats including priming sqm 1.500 35.00 52.50 Item 8.9
e) Overhead charges @ 10 % on 142.39
(a+b+c)
f) Contractor's profit @ 10 % on 156.63
(a+b+c+e)
Rate per tree guard = a+b+c+d+e+f 1775.42
say 1775.00
11.2 New Compensatory Afforestation
1 Planting trees as compensatory
afforestation at the rate of 290 trees per
hectare at a spacing of 6 m by grubbing
and leveling the ground upto a depth of 150
mm, digging holes 0.9 m dia, 1 m deep,
mixing farm yard/sludge manure with soil,
planting of sapling 2 m high with 25 cm dia
stem, backfilling the hole and watering
Unit = Hectare
Taking output = one hectare
a) Labour
i) Planting
Mate day 2.500 150.00 375.00 L-12
Mazdoor day 25.000 100.00 2500.00 L-13
ii) For Maintenance for one year
Mate day 5.000 150.00 750.00 L-12
Mazdoor day 50.000 100.00 5000.00 L-13
b) Machinery
Dozer 80 HP @ 1000 sqm/hour hour 10.000 1400.00 14000.00 P&M-
Water tanker6 KL capacity (for planting) hour 3.000 105.00 315.00 015
P&M-
Water tanker6 KL capacity (for hour 25.000 105.00 2625.00 060
P&M-
c) maintenance)
Material 060
Sapling 1 to 1.5 m high 2 cm dia stem each 290.000 40.00 11600.00 M-160 x
0.8
Add 10 per cent of sapling each 29.000 40.00 1160.00 M-160 x
0.8
Decayed farm yard/sludge manure cum 60.900 250.00 15225.00 M-167
(planting)
Decayed farm yard/sludge manure cum 4.000 250.00 1000.00 M-167
(maintenance)
Pesticides for planting kg 0.500 200.00 100.00 M-136
Pesticides for maintenance kg 1.500 200.00 300.00 M-136
Cost of water KL 18.000 50.00 900.00 M-189
d) Overhead charges @ 10 % on 5585.00
(a+b+c)
e) Contractor's profit @ 10 % on 6143.50
(a+b+c+d)
Rate per hectare = a+b+c+d+e 67578.50
say ###
Note Cost of fencing to be provided as per size of
plot and approved design, measured and
paid separately

Page 9 of 361
CHAPTER-12
FOUNDATIONS
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
12.1 Spec.
304 Excavation for Structures
Earth work in excavation of foundation of
structures as per drawing and technical
specification, including setting out,
construction of shoring and bracing,
removal of stumps and other deleterious
matter, dressing of sides and bottom and
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.14 150.00 21.00 L-12
Mazdoor day 3.50 100.00 350.00 L-13
b) Overhead charges @ 10 % on (a) 37.10
c) Contractor's profit @ 10 % on 40.81
(a+b)
Cost for 10 cum = a+b+c 448.91
Rate per cum = (a+b+c)/10 44.89
say 45.00
Note 1. Cost of dewatering may be added where
required upto, 10 per cent of labour cost
Assessment for dewatering shall be made
as per site conditions.
2.The excavated earth can be used partially
for backfilling of foundation pit and partly
for road work except for marshy soil. Hence
cost of disposal has not been added except
for marshy soil. This remark is common to
all cases of item 12.1 excluding marshy soil.

3.The cost of shoring and shuttering, where


needed, may be added @ 1 per cent on
cost of excavation for open foundation.
12.1 (ii) Depth 3 m to 6 m
(I) A a) Labour
Mate/Supervisor day 0.18 150.00 27.00 L-12
Mazdoor day 4.50 100.00 450.00 L-13
b) Overhead charges @ 10 % on (a) 47.70
c) Contractor's profit @ 10 % on 52.47
(a+b)
Cost for 10 cum = a+b+c 577.17
Rate per cum = (a+b+c)/10 57.72
say 58.00
Note Cost of dewatering may be added where
required upto 15 per cent of labour cost.
Assessment for dewatering shall be done as
per actual ground conditions.
12.1 (iii) Depth above 6 m
(I) A a) Labour
Mate/Supervisor day 0.24 150.00 36.00 L-12
Mazdoor day 6.00 100.00 600.00 L-13
b) Overhead charges @ 10 % on (a) 63.60
c) Contractor's profit @ 10 % on 69.96
(a+b)
Cost for 10 cum = a+b+c 769.56
Rate per cum = (a+b+c)/10 76.96
say 77.00
Note 1. Cost of dewatering may be added where
required upto 20 per cent of labour cost.
Assessment for dewatering shall be made
as per site conditions..
12.1 B Mechanical Means
(I) (i) Depth upto 3 m
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.32 150.00 48.00 L-12
Mazdoor day 8.00 100.00 800.00 L-13

Page 1 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. b) Machinery
Hydraulic excavator 1.0 cum bucket hour 6.00 700.00 4200.00 P&M-
c) capacity
Overhead charges @ 10 % on 504.80 026
(a+b)
d) Contractor's profit @ 10 % on 555.28
(a+b+c)
Cost for 240 cum = a+b+c+d 6108.08
Rate per cum = (a+b+c+d)/240 25.45
say 25.00
Note Cost of dewatering upto 5 per cent of (a+b)
may be added, where required.
Assessment for dewatering shall be made
as per site conditions..
12.1 (ii) Depth 3 m to 6 m
(I) B Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.32 150.00 48.00 L-12
Mazdoor day 8.00 100.00 800.00 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket hour 6.00 700.00 4200.00 P&M-
c) capacity
Overhead charges @ 10 % on 504.80 026
(a+b) Contractor's profit @ 10 % on
d) 555.28
(a+b+c)
Cost for 210 cum = a+b+c+d 6108.08
Rate per cum = (a+b+c+d)/210 29.09
say 29.00
Note Cost of dewatering upto 7.5 per cent of
(a+b) may be added, where required.
Assessment for dewatering shall be made
as per site conditions..
12.1 (iii) Depth above 6m
(I) B Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 150.00 60.00 L-12
Mazdoor day 10.00 100.00 1000.00 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket hour 6.00 700.00 4200.00 P&M-
c) capacity
Overhead charges @ 10 % on 526.00 026
(a+b) Contractor's profit @ 10 % on
d) 578.60
(a+b+c)
Cost for 180 cum = a+b+c+d 6364.60
Rate per cum = (a+b+c+d)/180 35.36
say 35.00
Note 1. Cost of dewatering upto 10 per cent of
(a+b) may be added, where required.
Assessment for dewatering shall be made
as per site conditions..
2.Labour provided for excavation by
mechanical means includes that required
for trimming of bottom and side slopes.
12.1 II Ordinary Rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.20 150.00 30.00 L-12
Mazdoor day 5.00 100.00 500.00 L-13
b) Overhead charges @ 10 % on (a) 53.00
c) Contractor's profit @ 10 % on 58.30
(a+b)
Cost for 10 cum = a+b+c 641.30
Rate per cum = (a+b+c)/10 64.13
say 64.00

Page 2 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Note Cost of dewatering upto 10 per cent of
labour cost may be added, where required.
Assessment for dewatering shall be made
as per site conditions..
12.1(II B Mechanical Means
) Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.24 150.00 36.00 L-12
Mazdoor day 6.00 100.00 600.00 L-13
b) Machinery
Hydraulic excavator 1.0 cum bucket hour 6.00 700.00 4200.00 P&M-
c) capacity
Overhead charges @ 10 % on 483.60 026
(a+b)
d) Contractor's profit @ 10 % on 531.96
(a+b+c)
Cost for 180 cum = a+b+c+d 5851.56
Rate per cum = (a+b+c+d)/180 32.51
say 33.00
Note 1.Cost of dewatering upto 10 per cent of
(a+b), may be added, where required
Assessment for dewatering shall be made
as per site conditions.
2.In case of rock, foundation beyond3 m is
not dug and hence not included.
12.1 III Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.35 150.00 52.50 L-12
Driller day 0.50 150.00 75.00 L-06
Blaster day 0.25 150.00 37.50 L-03
Mazdoor day 8.00 100.00 800.00 L-13
b) Machinery
Air Compressor 250 cfm with 2 jack hour 1.00 150.00 150.00 P&M-
hammer for drilling. 001
c) Material
Blasting Material kg 3.50 100.00 350.00 M-104
Detonator electric each 14.00 5.00 70.00 M-
094/100
d) Overhead charges @ 10 % on 153.50
(a+b+c)
e) Contractor's profit @ 10 % on 168.85
(a+b+c+d)
Cost for 10 cum = a+b+c+d+e 1857.35
Rate per cum = (a+b+c+d+e)/10 185.74
say 186.00
Note Cost of dewatering @ 10 per cent of (a+b)
may be added, where required
Assessment for dewatering shall be made
as per site conditions.
12.1 IV Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum
A Mechanical Means
a) Labour
Mate day 0.20 150.00 30.00 L-12
Mazdoor day 5.00 100.00 500.00 L-13
b) Machinery
Air Compressor 250 cfm with 2 leads of hour 6.00 150.00 900.00 P&M-
pneumatic breaker 001
c) Overhead charges @ 10 % on 143.00
(a+b)
d) Contractor's profit @ 10 % on 157.30
(a+b+c)
Cost for 10 cum = a+b+c+d 1730.30
Rate per cum = (a+b+c+d)/10 173.03

Page 3 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. say 173.00
Note 1. Cost of dewatering upto10 per cent of
(a+b), may be added, where required
Assessment for dewatering shall be made
as per site conditions.
2.In case of rock, foundation beyond3 m is
not dug and hence not included.
12.1 V Marshy Soil
Unit = cum
Taking output = 10 cum
Depth upto 3 m
A Manual means
a) Labour
Mate/Supervisor day 0.40 150.00 60.00 L-12
Mazdoor day 10.00 100.00 1000.00 L-13
b) Machinery
Tractor-trolley for removal. hour 2.67 150.00 400.50 P&M-
c) Overhead charges @ 10 % on 146.05 053
(a+b) Contractor's profit @ 10 % on
d) 160.66
(a+b+c)
Cost for 10 cum = a+b+c+d 1767.21
Rate per cum = ( a+b+c+d)/ 10 176.72
say 177.00
Note 1. Cost of dewatering @ 30 per cent of (a),
may be added, where required Assessment
for dewatering shall be made as per site
conditions.
2. Shoring & strutting 15 per cent of (a),
where required may be added
3. It is assumed that Marshy Soil will be
available upto 3 m depth only. For deeper
excavation below 3 m depth, refer analysis
in item12.1 (i) to (iv) for ordinary soil
12.1 B Mechanical Means
(V) a) Labour
Mate day 0.08 150.00 12.00 L-12
Mazdoor for dressing sides, bottom and day 2.00 100.00 200.00 L-13
b) backfilling
Machinery
Hydraulic excavator 1.0 cum bucket hour 0.17 700.00 119.00 P&M-
capacity @ 60 cum per hour 026
Tipper 5.5 cum capacity, 4 trips per hour 0.45 185.00 83.25 P&M-
c) hour.
Overhead charges @ 10 % on 41.43 048
(a+b)
d) Contractor's profit @ 10 % on 45.57
(a+b+c)
Cost for 10 cum = a+b+c+d 501.24
Rate per cum = (a+b+c+d)/10 50.12
say 50.00
Note 1. Cost of dewatering @ 20 per cent of
(a+b) may be added, where required
2. Shoring & strutting @ 10 per cent of
(a+b), where required may be added
3. It is assumed that Marshy Soil will be
available upto 3 m depth only. For deeper
excavation below 3 m depth, refer analysis
in item 12.1 (i) to (iv) for ordinary soil
VI Back Filling in Marshy Foundation Pits
Unit : Cum
Taking Output : 6 cum
a) Labour
Mate day 0.12 150.00 18.00 L-12
Mazdoor for dressing sides, bottom and day 3.00 100.00 300.00 L-13
b) backfilling
Machinery
Tractor-trolley for transportation hour 2.00 150.00 300.00 P&M-
c) Overhead charges @ 10 % on 61.80 053
(a+b)
d) Contractor's profit @ 10 % on 67.98
(a+b+c)

Page 4 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Cost for 6 cum = a+b+c+d 747.78
Rate per cum = (a+b+c+d)/6 124.63
say 125.00
12.2 304 Filling Annular Space Around Footing
in Rock
Unit = cum
Taking out put = 1 cum
Lean cement concrete 1:3:6 nominal mix.
Rate may be taken as per item 12.4.
12.3 304 Sand Filling in Foundation Trenches as
per Drawing & Technical Specification
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.01 150.00 1.50 L-12
Mazdoor day 0.30 100.00 30.00 L-13
b) Material
Sand (assuming 20 per cent voids) cum 1.20 300.00 360.00 M-006
c) Overhead charges @ 10 % on 39.15
(a+b)
d) Contractor's profit @ 10 % on 43.07
(a+b+c)
Rate per cum = a+b+c+d 473.72
say 474.00
12.4 2100 PCC 1:3:6 in Foundation
Plain cement concrete 1:3:6 nominal mix in
foundation with crushed stone aggregate 40
mm nominal size mechanically mixed,
placed in foundation and compacted by
vibration including curing for 14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.64 150.00 96.00 L-12
Mason day 1.00 250.00 250.00 L-11
Mazdoor day 15.00 100.00 1500.00 L-13
b) Material
40 mm Aggregate cum 13.50 350.00 4725.00 M-055
coarse Sand cum 6.75 350.00 2362.50 M-005
cement tonne 3.45 4180.00 14421.00 M-081
Cost of water KL 18.00 50.00 900.00 M-189
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Water tanker 6 KL capacity hour 2.00 105.00 210.00 079
P&M-
d) Overhead charges @ 10 % on 2746.45 060
(a+b+c)
e) Contractor's profit @ 10 % on 3021.10
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 33232.05
Rate per cum = (a+b+c+d+e)/15 2215.47
say 2215.00
Note Vibrator is a part of minor T & P which is
already included in overhead charges of the
12.5 1300 contractor.
Brick Masonry Work in Cement Mortar
1:3 in Foundation complete excluding
Pointing and Plastering, as per
Drawing and Technical Specifications.
Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class each 2500.00 2.00 5000.00 M-079
Cement mortar 1:3 (Rate as in Item cum 1.20 2595.00 3114.00 Item
12.6 A sub-analysis) 12.6 (A)
b) Labour

Page 5 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Mate day 0.48 150.00 72.00 L-12
Mason day 4.00 250.00 1000.00 L-11
Mazdoor day 8.00 100.00 800.00 L-13
c) Overhead charges @ 10 % on 998.60
(a+b)
d) Contractor's profit @ 10 % on 1098.46
(a+b+c)
Cost for 5 cum = a+b+c+d 12083.06
Rate per cum (a+b+c+d)/5 2416.61
say 2417.00
12.6 Sub- (A) Cement Mortar 1:3 (1 cement : 3 sand)
analy
sis
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.51 4180.00 2131.80 M-081
Sand cum 1.05 350.00 367.50 M-005
b) Labour
Mate day 0.04 150.00 6.00 L-12
Mazdoor day 0.90 100.00 90.00 L-13
Total Material and Labour = (a+b) say 2595.00
Sub- (B) Cement Mortar1:2 (1cement :2 sand)
analy
sis
(Addl.
)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.67 4180.00 2808.96 M-081
Sand cum 0.93 350.00 325.50 M-005
b) Labour
Mate day 0.04 150.00 6.00 L-12
Mazdoor day 0.90 100.00 90.00 L-13
Total Material and Labour = (a+b) say 3230.00
Sub- (C) Cement Mortar1:4 (1cement :4 sand)
analy
sis
(Addl.
)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.40 4180.00 1685.38 M-081
Sand cum 1.12 350.00 392.00 M-005
b) Labour
Mate day 0.04 150.00 6.00 L-12
Mazdoor day 0.90 100.00 90.00 L-13
Total Material and Labour = (a+b) say 2173.00
Sub- (D) Cement Mortar1:6 (1cement :6 sand)
analy
sis
(Addl.
)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.29 4180.00 1203.84 M-081
Sand cum 1.34 350.00 468.00 M-005
b) Labour
Mate day 0.04 150.00 6.00 L-12
Mazdoor day 0.90 100.00 90.00 L-13

Page 6 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Total Material and Labour = (a+b) say 1768.00
12.7 1400 Stone Masonry Work in Cement Mortar
1:3 in Foundation complete as per
Drawing and Technical Specifications.
Unit = cum
Taking output = 5 cum
1405. (A) Square Rubble Coursed Rubble
4 Masonry (first sort)
a) Material
Stone cum 5.50 4000.00 22000.00 M-169
Through and bond stone each 35.00 30.00 1050.00 M-182
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item cum 1.50 2595.00 3892.50 Item
12.6 A sub-analysis) 12.6 (A)
b) Labour
Mate day 0.66 150.00 99.00 L-12
Mason day 7.50 250.00 1875.00 L-11
Mazdoor day 9.00 100.00 900.00 L-13
c) Overhead charges @ 10 % on 2981.65
(a+b)
d) Contractor's profit @ 10 % on 3279.82
(a+b+c)
Cost for 5 cum = a+b+c+d 36077.97
Rate per cum (a+b+c+d)/5 7215.59
say 7216.00
1405. (B) Random Rubble Masonry
3 ( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.50 300.00 1650.00 M-148
Through and bond stone each 35.00 30.00 1050.00 M-182
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item cum 1.55 2595.00 4022.25 Item
12.6 A sub-analysis) 12.6 (A)
b) Labour
Mate day 0.62 150.00 93.00 L-12
Mason day 6.00 250.00 1500.00 L-11
Mazdoor day 9.00 100.00 900.00 L-13
c) Overhead charges @ 10 % on 921.53
(a+b)
d) Contractor's profit @ 10 % on 1013.68
(a+b+c)
Cost for 5 cum = a+b+c+d 11150.45
Rate per cum (a+b+c+d)/5 2230.09
say 2230.00
Note The labour already considered in cement
mortar has been taken into account while
proposing labour for masonry works.
12.8 1500, Plain/Reinforced Cement Concrete in
1700 Open Foundation complete as per
& Drawing and Technical Specifications.
2100
A PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 4180.00 17263.40 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
40 mm Aggregate cum 8.10 350.00 2835.00 M-055
20 mm Aggregate cum 4.05 410.00 1660.50 M-053
10 mm Aggregate cum 1.35 410.00 553.50 M-051
b) Labour

Page 7 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Mate day 0.86 150.00 129.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 63 KVA hour 6.00 525.00 3150.00 009
P&M-
Per Cum Basic Cost of Labour, Material 2062.00 019
& Machinery (a+b+c)
d) Formwork @ 4 per cent on cost of 1237.16
concrete i.e. cost of material, labour and
machinery
e) Overhead charges @ 10 % on 3216.61
(a+b+c+d)
f) Contractor's profit @ 10 % on 3538.27
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 38920.93
Rate per cum = (a+b+c+d+e+f)/15 2594.73
say 2595.00
Note Needle Vibrator is an item of minor T & P
which is already included in overhead
charges. Hence not added in rate analysis
of cement concrete works.
12.8 B PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement tonne 5.16 4180.00 21568.80 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
40 mm Aggregate cum 5.40 350.00 1890.00 M-055
20 mm Aggregate cum 5.40 410.00 2214.00 M-053
10 mm Aggregate cum 2.70 410.00 1107.00 M-051
b) Labour
Mate day 0.86 150.00 129.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Per Cum Basic Cost of Labour, Material 2310.00 079
& Machinery (a+b+c)
d) Formwork @ 4 per cent on cost of 1385.85
concrete i.e. cost of material, labour and
machinery
e) Overhead charges @ 10 % on 3603.22
(a+b+c+d)
f) Contractor's profit @ 10 % on 3963.54
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 43598.90
Rate per cum = (a+b+c+d+e+f)/15 2906.59
say 2907.00
12.8 C RCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.21 4180.00 21777.80 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.86 150.00 129.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery

Page 8 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Per Cum Basic Cost of Labour, Material 2346.00 079
& Machinery (a+b+c)
d) Formwork @ 4 per cent on (a+b+c) 1407.17
e) Overhead charges @ 10 % on 3658.65
(a+b+c+d)
f) Contractor's profit @ 10 % on 4024.51
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 44269.63
Rate per cum = ( a+b+c+d+e+f )/15 2951.31
say 2951.00
12.8 C Case II With Batching Plant, Transit Mixer and
Concrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 4180.00 ### M-081
Coarse Sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
b) Labour
Mate day 0.84 150.00 126.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader 1 cum capacity hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer 4 cum capacity for lead hour 15.00 600.00 9000.00 017
P&M-
upto 1beyond
Lead km. 1 km, L-lead in km tonne.k 300L 1.85 11100.00 049
P&M-
m 050
Lead=
20 km
Concrete Pump hour 6 500.00 3000.00 P&M-
Per Cum Basic Cost of Labour, Material 2247.00 007
& Machinery (a+b+c)
d) Formwork @ 4 per cent on cost of 10785.39
concrete i.e. cost of material, labour and
machinery
e) Overhead charges @ 10 % on 28042.02
(a+b+c+d)
f) Contractor's profit @ 10 % on 30846.22
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f ###
Rate per cum = ( a+b+c+d+e+f )/120 2827.57
say 2828.00
12.8 D PCC Grade M25
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 4180.00 25038.20 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
40 mm Aggregate cum 5.40 350.00 1890.00 M-055
20 mm Aggregate cum 5.40 410.00 2214.00 M-053
10 mm Aggregate cum 2.70 410.00 1107.00 M-051
b) Labour
Mate day 0.86 150.00 129.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
079

Page 9 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Per Cum Basic Cost of Labour, Material 2542.00
& Machinery (a+b+c)
d) Formwork @ 3.75 per cent of 1429.34
(a+b+c)
e) Overhead charges @ 10 % on 3954.50
(a+b+c+d)
f) Contractor's profit @ 10 % on 4349.95
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 47849.50
Rate per cum = ( a+b+c+d+e+f )/15 3189.97
say 3190.00
12.8 D Case II With Batching Plant, Transit Mixer and
Concrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 47.95 4180.00 ### M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
40 mm Aggregate cum 43.20 350.00 15120.00 M-055
20 mm Aggregate cum 43.20 410.00 17712.00 M-053
10 mm Aggregate cum 21.60 410.00 8856.00 M-051
b) Labour
Mate day 0.84 150.00 126.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader 1 cum capacity hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer 4 cum capacity for lead hour 15.00 600.00 9000.00 017
P&M-
upto 1 km.
Transit Mixer 4 cum capacity lead tonne.k 300L 1.85 11100.00 049
P&M-
beyond 1 Km, L - lead in Kilometer m 050
Lead=
20 km
Concrete Pump hour 6 500.00 3000.00 P&M-
Per Cum Basic Cost of Labour, Material 2445.00 007
& Machinery (a+b+c)
d) Formwork @ 3.75 per cent of cost 11000.06
of concrete i.e. cost of material, labour and
machinery
e) Overhead charges @ 10 % on 30433.51
(a+b+c+d)
f) Contractor's profit @ 10 % on 33476.86
(a+b+c+d+e)
cost of 120 cum = a+b+c+d+e+f ###
Rate per cum = (a+b+c+d+e+f)/120 3068.71
say 3069.00
12.8 E RCC Grade M25
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 4180.00 25289.00 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.86 150.00 129.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Per Cum Basic Cost of Labour, Material 2580.00 079
& Machinery (a+b+c)

Page 10 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. d) Formwork @ 3.75 per cent of 1450.89
a+b+c.
e) Overhead charges @ 10 % on 4014.14
(a+b+c+d)
f) Contractor's profit @ 10 % on 4415.55
(a+b+c+d+e)
cost of 15 cum = a+b+c+d+e+f 48571.09
Rate per cum (a+b+c+d+e+f )/15 3238.07
say 3238.00
12.8 E Case II With Batching Plant, Transit Mixer and
Concrete Pump
Unit: cum
Taking Output = 120 cum
a) Material
Cement tonne 48.38 4180.00 ### M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
b) Labour
Mate day 0.84 150.00 126.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader 1 cum capacity 1 cum hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer 4 cum capacity for lead hour 15.00 600.00 9000.00 017
P&M-
upto 1 km.
Transit Mixer 4 cum capacity lead tonne.k 300L 1.85 11100.00 049
P&M-
beyond 1 Km, L - lead in Kilometer m 050
Lead=
20 km
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Per Cum Basic Cost of Labour, Material 2482.00 007
& Machinery (a+b+c)
d) Formwork @ 3.75 per cent on cost 11164.67
of concrete i.e. cost of material, labour and
machinery
e) Overhead charges @ 10 % on 30888.91
(a+b+c+d)
f) Contractor's profit @ 10 % on 33977.80
(a+b+c+d+e)
cost of 120 cum = a+b+c+d+e+f ###
Rate per cum (a+b+c+d+e+f )/120 3114.63
say 3115.00
12.8 F PCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 4180.00 25414.40 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
40 mm Aggregate cum 5.40 350.00 1890.00 M-055
20 mm Aggregate cum 5.40 410.00 2214.00 M-053
10 mm Aggregate cum 2.70 410.00 1107.00 M-051
b) Labour
Mate day 0.86 150.00 129.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Per Cum Basic Cost of Labour, Material 2567.00 079
& Machinery (a+b+c)
d) Formwork @ 3.50 per cent of cost 1347.22
of concrete i.e. cost of material, labour and
machinery

Page 11 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. e) Overhead charges @ 10 % on 3983.91
(a+b+c+d)
f) Contractor's profit @ 10 % on 4382.30
(a+b+c+d+e)
cost of 15 cum = a+b+c+d+e+f 48205.33
Rate per cum (a+b+c+d+e+f )/15 3213.69
say 3214.00
12.8 F Case II Using Batching Plant, Transit Mixer
and Concrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 48.60 4180.00 ### M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
40 mm Aggregate cum 43.20 350.00 15120.00 M-055
20 mm Aggregate cum 43.20 410.00 17712.00 M-053
10 mm Aggregate cum 21.60 410.00 8856.00 M-051
b) Labour
Mate day 0.84 150.00 126.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader 1 cum capacity hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer 4 cum capacity for lead hour 15.00 600.00 9000.00 017
P&M-
upto 1 km.
Transit Mixer 4 cum capacity lead tonne.k 300L 1.85 11100.00 049
P&M-
beyond 1 Km, L - lead in Kilometer m 050
Lead=
20 km
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Per Cum Basic Cost of Labour, Material 2468.00 007
& Machinery (a+b+c)
d) Formwork @ 3.50 per cent of cost 10361.82
of concrete i.e. cost of material, labour and
machinery
e) Overhead charges @ 10 % on 30641.38
(a+b+c+d)
f) Contractor's profit @ 10 % on 33705.52
(a+b+c+d+e)
cost of 120 cum = a+b+c+d+e+f ###
Rate per cum (a+b+c+d+e+f )/120 3089.67
say 3090.00
12.8 G RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 4180.00 25498.00 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.86 150.00 129.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Per Cum Basic Cost of Labour, Material 2594.00 079
& Machinery (a+b+c)
d) Formwork @ 3.5 per cent on cost of 1361.48
concrete i.e. cost of material, labour and
machinery
e) Overhead charges @ 10 % on 4026.10
(a+b+c+d)

Page 12 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. f) Contractor's profit @ 10 % on 4428.71
(a+b+c+d+e)
cost of 15 cum = a+b+c+d+e+f 48715.79
Rate per cum = (a+b+c+d+e+f)/15 3247.72
say 3248.00
12.8 G Case II Using Batching Plant, Transit Mixer
and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 4180.00 ### M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
b) Labour
Mate day 0.84 150.00 126.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader 1 cum capacity hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer 4 cum capacity for lead hour 15.00 600.00 9000.00 017
P&M-
upto 1 km.
Transit Mixer 4 cum capacity lead tonne.k 300L 1.85 11100.00 049
P&M-
beyond 1 Km, L - lead in Kilometer m 050
Lead=
20 km
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Per Cum Basic Cost of Labour, Material 2496.00 007
& Machinery (a+b+c)
d) Formwork @ 3.5 per cent of cost of 10481.80
concrete i.e. cost of material, labour and
machinery
e) Overhead charges @ 10 % on 30996.18
(a+b+c+d)
f) Contractor's profit @ 10 % on 34095.80
(a+b+c+d+e)
cost of 120 cum = a+b+c+d+e+f ###
Rate per cum (a+b+c+d+e+f )/120 3125.45
say 3125.00
12.8 H RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 4180.00 26459.40 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.86 150.00 129.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Per Cum Basic Cost of Labour, Material 2658.00 079
& Machinery (a+b+c)
d) Formwork @ 3 per cent on a+b+c 1195.83
e) Overhead charges @ 10 % on 4105.67
(a+b+c+d)
f) Contractor's profit @ 10 % on 4516.24
(a+b+c+d+e)
cost of 15 cum = a+b+c+d+e+f 49678.64
Rate per cum = (a+b+c+d+e+f)/15 3311.91

Page 13 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. say 3312.00
12.8 H Case II Using Batching Plant, Transit Mixer
and Concrete Pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 50.64 4180.00 ### M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
b) Labour
Mate day 0.84 150.00 126.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader1 cum capacity hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer 4 cum capacity for lead hour 15.00 600.00 9000.00 017
P&M-
upto 1 km.
Transit Mixer 4 cum capacity lead tonne.k 300L 1.85 11100.00 049
P&M-
beyond 1 Km, L - lead in Kilometer m 050
Lead=
20 km
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Per Cum Basic Cost of Labour, Material 2560.00 007
& Machinery (a+b+c)
d) Formwork @ 3 per cent on cost of 9215.14
concrete i.e. cost of material, labour and
machinery
e) Overhead charges @ 10 % on 31638.63
(a+b+c+d)
f) Contractor's profit @ 10 % on 34802.50
(a+b+c+d+e)
cost of 120 cum = a+b+c+d+e+f ###
Rate per cum = (a+b+c+d+e+f)/120 3190.23
say 3190.00
Note: Where ever concrete is carried out using
batching plant, transit mixer, concrete
pump, Admixtures @ 0.4 per cent of weight
of cement may be added for achieving
desired slump of concrete.
WELL FOUNDATION
12.9 1200 Providing and Constructing Temporary
Island 16 m diameter for Construction
of Well Foundation for 8m dia. Well.
A Assuming depth of water 1.0 m and
height of island to be 1.25 m.
Unit = 1 No
Taking output = 1 No.
a) Material
Earth (compacted) cum 251.20 45.0 11304.00 M-092
Sand bags each 750.00 6.00 4500.00 M-159
b) Labour
Mate day 0.40 150.00 60.00 L-12
Mazdoor for filling sand bags, stitching day 15.00 100.00 1500.00 L-13
c) and placing
Machinery
Crane with grab 1 cum capacity hour 20.00 500.00 10000.00 P&M-
Consumables @ 2.5 per cent of (c) above 250.00 012
d) Overhead charges @ 10 % on 2761.40
(a+b+c)
e) Contractor's profit @ 10 % on 3037.54
(a+b+c+d)
Rate per No. (a+b+c+d+e) 33412.94
say ###
Note It is assumed that earth will be available
within the working space of crane with grab
bucket.

Page 14 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
12.9 Spec. B Assuming depth of water 4.0 m and
height of island 4.5 m.
Unit = 1No
Taking output = 1 No
a) Material
Earth (compacted) cum 904.32 45.00 40694.40 M-092
Sand bags each 6000.00 6.00 36000.00 M-159
Wooden ballies 8" Dia and 9 m long each 95.00 10.00 950.00 M-194
Wooden ballies 2" Dia for bracing metre 190.00 2.00 380.00 M-193
b) Labour
Mate day 5.60 150.00 840.00 L-12
Mazdoor for piling 8" dia ballies for day 18.00 100.00 1800.00 L-13
piling 8" dia ballies
Mazdoor for bracing with 2" dia ballies day 12.00 100.00 1200.00 L-13
Mazdoor for filling sand bags, stitching day 110.00 100.00 11000.00 L-13
c) and placing
Machinery
Crane with grab 1 cum capacity hour 50.00 500.00 25000.00 P&M-
Consumables and other arrangements for 2946.61 012
piling ballies @ 2.5 per cent of (a+b+c).
d) Overhead charges @ 10 % on 12081.10
(a+b+c)
e) Contractor's profit @ 10 % on 13289.21
(a+b+c+d)
Rate per No. (a+b+c+d+e) ###
say ###
Note For other well diameters rate can be
worked out on the basis of cross-sectional
area of well. The diameter of the island
shall be in the conformity with clause
1203.2 of MoRTH specifications.
12.9 C Providing and constructing one span
service road to reach island location
from one pier location to another pier
location
Assuming span length 30 m, width of
service road 10m and depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a) Material
Earth cum 450.00 45.00 20250.00 M-092
Sand bags each 300.00 6.00 1800.00 M-159
b) Labour
Mate day 0.24 150.00 36.00 L-12
Mazdoor for filling sand bags, stitching day 6.00 100.00 600.00 L-13
c) and placing
Machinery
Front end Loader 1 cum capacity hour 27.00 700.00 18900.00 P&M-
Tipper 5.5 cum capacity hour 28.00 185.00 5180.00 017
P&M-
d) Overhead charges @ 10 % on 4676.60 048
(a+b+c)
e) Contractor's profit @ 10 % on 5144.26
(a+b+c+d)
Cost for 30 m (a+b+c+d+e) 56586.86
Rate per m (a+b+c+d+e)/30 1886.23
say 1886.00
12.10 1200 Providing and Laying Cutting Edge of
& Mild Steel weighing 40 kg per metre
1900 for Well Foundation complete as per
Drawing and Technical Specification.
Unit = 1 MT
Taking output = 1 MT
a) Material
Structural steel in plates, angles, etc tonne 1.05 32000.00 33600.00 M-179
including 5 per cent wastage
Nuts & bolts Kg 20.00 50.00 1000.00 M-130
b) Labour

Page 15 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. (for cutting, bending, making holes,
joining, welding and erecting in
position)
Mate day 1.32 150.00 198.00 L-12
Fitter day 5.50 150.00 825.00 L-08
Blacksmith day 5.50 150.00 825.00 L-02
Welder day 5.50 150.00 825.00 L-02
Mazdoor day 16.50 100.00 1650.00 L-13
Electrodes, cutting gas and other 3460.00
consumables @ 10 per cent of cost of (a)
above
c) Overhead charges @ 10 % on 4238.30
(a+b)
d) Contractor's profit @ 10 % on 4662.13
(a+b+c)
Rate per MT (a+b+c+d) 51283.43
say ###
12.11 1200, Plain/Reinforced Cement Concrete, in
1500 Well Foundation complete as per
& Drawing and Technical Specification.
1700
Unit = 1 cum
Taking output = 1 cum
A Well curb
(i) RCC M20 Grade
Same as for 12.8 (C) except for formwork
which shall be@ 20 per cent of the cost of
concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & 2346.00
Machinery (a+b+c)
d) formwork @ 20 per cent of the cost 469.20
of
e) concrete
Overhead charges @ 10 % on 281.52
(a+b+c+d)
f) Contractor's profit @ 10 % on 309.67
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3406.39
say 3406.00
12.11 Case II With Batching Plant, Transit Mixer and
A (i) Concrete Pump
Per Cum Basic Cost of Labour, Material & 2247.00
Machinery (a+b+c)
d) formwork @ 20 per cent of the cost 449.40
of
e) concrete
Overhead charges @ 10 % on 269.64
(a+b+c+d)
f) Contractor's profit @ 10 % on 296.60
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3262.64
say 3263.00
12.11 (ii) RCC M25 Grade
A Same as for 12.8 (E) except for formwork
which shall be@ 20 per cent of the cost of
concrete instead of 3.75 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & 2580.00
Machinery (a+b+c)
d) formwork @ 20 per cent of the cost 516.00
of
e) concrete
Overhead charges @ 10 % on 309.60
(a+b+c+d)
f) Contractor's profit @ 10 % on 340.56
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3746.16
say 3746.00
12.11 Case II With Batching Plant, Transit Mixer and
A (ii) Concrete Pump
Per Cum Basic Cost of Labour, Material & 2562.00
Machinery (a+b+c)
d) formwork @ 20 per cent of the cost 512.40
of
e) concrete
Overhead charges @ 10 % on 307.44
(a+b+c+d)
f) Contractor's profit @ 10 % on 338.18
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3720.02

Page 16 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. say 3720.00
12.11 (iii) RCC M35 Grade
A Same as for 12.8 (H) except for formwork
which shall be@ 20 per cent of the cost of
concrete instead of 3.0 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & 2658.00
Machinery (a+b+c)
d) formwork @ 20 per cent of the cost 531.60
of
e) concrete
Overhead charges @ 10 % on 318.96
(a+b+c+d)
f) Contractor's profit @ 10 % on 350.86
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3859.42
say 3859.00
12.11 Case II With Batching Plant, Transit Mixer and
A (iii) Concrete Pump
Per Cum Basic Cost of Labour, Material & 2645.00
Machinery (a+b+c)
d) formwork @ 20 per cent of the cost 529.00
of
e) concrete
Overhead charges @ 10 % on 317.40
(a+b+c+d)
f) Contractor's profit @ 10 % on 349.14
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3840.54
say 3841.00
Note. If curb concrete is carried out within steel
liner, cost of formwork shall be excluded.

12.11 B Well steining


(I) PCC M15 Grade
Same as for 12.8 (A) except for formwork
which shall be @ 10 per cent of the cost of
concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & 2062.00
Machinery (a+b+c)
d) formwork @ 10 per cent of the cost 206.20
of
e) concrete
Overhead charges @ 10 % on 226.82
(a+b+c+d)
f) Contractor's profit @ 10 % on 249.50
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 2744.52
say 2745.00
12.11 (ii) PCC M20 Grade
B Same as for 12.8 (B) except for formwork
which shall be @ 10 per cent of the cost of
concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & 2310.00
Machinery (a+b+c)
d) formwork @ 10 per cent of the cost 231.00
of
e) concrete
Overhead charges @ 10 % on 254.10
(a+b+c+d)
f) Contractor's profit @ 10 % on 279.51
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3074.61
say 3075.00
12.11 (iii) RCC M20 Grade
B Same as for 12.8 (C) except for formwork
which shall be @ 10 per cent of the cost of
concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & 2346.00
Machinery (a+b+c)
d) formwork @ 10 per cent of the cost 234.60
of
e) concrete
Overhead charges @ 10 % on 258.06
(a+b+c+d)
f) Contractor's profit @ 10 % on 283.87
(a+b+c+d+e)
Page 17 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Rate perm (a+b+c+d+e+f) 3122.53
say 3123.00
12.11 Case II With Batching Plant, Transit Mixer and
B (iii) Concrete Pump
Per Cum Basic Cost of Labour, Material & 2247.00
Machinery (a+b+c)
d) formwork @ 10 per cent of the cost 224.70
of
e) concrete
Overhead charges @ 10 % on 247.17
(a+b+c+d)
f) Contractor's profit @ 10 % on 271.89
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 2990.76
say 2991.00
12.11 (iv) PCC M25 Grade
B Same as for 12.8 (D) except for formwork
which shall be @ 10 per cent of the cost of
concrete instead of 4 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & 2542.00
Machinery (a+b+c)
d) formwork @ 10 per cent of the cost 254.20
of
e) concrete
Overhead charges @ 10 % on 279.62
(a+b+c+d)
f) Contractor's profit @ 10 % on 307.58
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3383.40
say 3383.00
12.11 Case II With Batching Plant, Transit Mixer and
B (iv) Concrete Pump
Per Cum Basic Cost of Labour, Material & 2445.00
Machinery (a+b+c)
d) formwork @ 10 per cent of the cost 244.50
of
e) concrete
Overhead charges @ 10 % on 268.95
(a+b+c+d)
f) Contractor's profit @ 10 % on 295.85
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3254.30
say 3254.00
'12.11 (v) RCC M25 Grade
B Same as for 12.8 (E) except for formwork
which shall be @ 10 per cent of the cost of
concrete instead of 3.5 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & 2580.00
Machinery (a+b+c)
d) formwork @ 10 per cent of the cost 258.00
of
e) concrete
Overhead charges @ 10 % on 283.80
(a+b+c+d)
f) Contractor's profit @ 10 % on 312.18
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3433.98
say 3434.00
12.11 Case II With Batching Plant, Transit Mixer and
B (v) Concrete Pump
Per Cum Basic Cost of Labour, Material & 2562.00
Machinery (a+b+c)
d) formwork @ 10 per cent of the cost 256.20
of
e) concrete
Overhead charges @ 10 % on 281.82
(a+b+c+d)
f) Contractor's profit @ 10 % on 310.00
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3410.02
say 3410.00
'12.11 (vi) PCC M30 Grade
B Same as for 12.8 (F) except for formwork
which shall be @ 10 per cent of the cost of
concrete instead of 3.5 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & 2567.00
Machinery (a+b+c)

Page 18 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. d) formwork @ 10 per cent of the cost 256.70
of
e) concrete
Overhead charges @ 10 % on 282.37
(a+b+c+d)
f) Contractor's profit @ 10 % on 310.61
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3416.68
say 3417.00
12.11 Case II With Batching Plant, Transit Mixer and
B (vi) Concrete Pump
Per Cum Basic Cost of Labour, Material & 2468.00
Machinery (a+b+c)
d) formwork @ 10 per cent of the cost 246.80
of
e) concrete
Overhead charges @ 10 % on 271.48
(a+b+c+d)
f) Contractor's profit @ 10 % on 298.63
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3284.91
say 3285.00
'12.11 (vii) RCC M30 Grade
B Same as for 12.8 (G) except for formwork
which shall be @ 10 per cent of the cost of
concrete instead of 3.5 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & 2594.00
Machinery (a+b+c)
d) formwork @ 10 per cent of the cost 259.40
of
e) concrete
Overhead charges @ 10 % on 285.34
(a+b+c+d)
f) Contractor's profit @ 10 % on 313.87
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3452.61
say 3453.00
12.11 Case II With Batching Plant, Transit Mixer and
B (vii) Concrete Pump
Per Cum Basic Cost of Labour, Material & 2496.00
Machinery (a+b+c)
d) formwork @ 10 per cent of the cost 249.60
of
e) concrete
Overhead charges @ 10 % on 274.56
(a+b+c+d)
f) Contractor's profit @ 10 % on 302.02
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3322.18
say 3322.00
'12.11 (viii) RCC M35 Grade
B Same as for 12.8 (H) except for formwork
which shall be @ 10 per cent of the cost of
concrete instead of 3 per cent.
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & 2658.00
Machinery (a+b+c)
d) formwork @ 10 per cent of the cost 265.80
of
e) concrete
Overhead charges @ 10 % on 292.38
(a+b+c+d)
f) Contractor's profit @ 10 % on 321.62
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3537.80
say 3538.00
12.11 Case II With Batching Plant, Transit Mixer and
B Concrete Pump
(viii) Per Cum Basic Cost of Labour, Material & 2645.00
Machinery (a+b+c)
d) formwork @ 10 per cent of the cost 264.50
of
e) concrete
Overhead charges @ 10 % on 290.95
(a+b+c+d)
f) Contractor's profit @ 10 % on 320.05
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3520.50
say 3520.00
'12.11 (ix) RCC M40 Grade
B Using Batching Plant, Transit Mixer
and Concrete Pump

Page 19 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 4180.00 ### M-081
Coarse Sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
Admixture kg 206.00 50.00 10300.00 M-180
b) Labour
Mate day 0.84 150.00 126.00 L-12
Meson day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader 1 cum capacity hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer 4 cum capacity for lead hour 15.00 600.00 9000.00 017
P&M-
upto 1 km.
Transit Mixer 4 cum capacity for lead tonne.k 300xL 1.85 11100.00 049
Lead=
beyond 1 km. m 20 ,
Concrete Pump hour 6.00 500.00 3000.00 P&M-
P&M-
Per Cum Basic Cost of Labour, Material ### 007
& Machinery (a+b+c)
d) Formwork @ 10 per cent on cost of 32148.40
concrete i.e. cost of material, labour and
machinery
e) Overhead charges @ 10 % on 35363.24
(a+b+c+d)
f) Contractor's profit @ 10 % on 38899.56
(a+b+c+d+e)
cost of 120 cum = a+b+c+d+e+f ###
Rate per cum = (a+b+c+d+e+f)/120 3565.79
say 3566.00
12.11 C Bottom Plug
C Concrete to be placed using tremie pipe
Note: 10% extra cement to be added where
under water concreting is involved
(i) PCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.55 4180.00 23199.00 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
40 mm Aggregate cum 5.40 350.00 1890.00 M-055
20 mm Aggregate cum 5.40 410.00 2214.00 M-053
10 mm Aggregate cum 2.70 410.00 1107.00 M-051
Admixture Kg 18.60 50.00 930.00 M-180
b) Labour
Mate day 0.90 150.00 135.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Light Crane 3 tonnes capacity for hour 6.00 225.00 1350.00 079
P&M-
handling tremie pipe 013
Per Cum Basic Cost of Labour, Material 2571.00
& Machinery (a+b+c)
Add 5 per cent of cost of material and 1710.63
labour towards cost of forming sump,
protective bunds, chiselling and making
arrangements for under water concreting
with tremie pipe..
Page 20 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. d) Overhead charges @ 10 % on 4027.31
(a+b+c)
e) Contractor's profit @ 10 % on 4430.04
(a+b+c+d)
cost of 15 cum = a+b+c+d+e 48730.48
Rate per cum = (a+b+c+d+e)/15 3248.70
say 3249.00
12.11 Case II Using Batching Plant, Transit Mixer
C (i) and Crane/concrete pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 44.40 4180.00 ### M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
Admixture Kg 148.80 50.00 7440.00 M-180
b) Labour
Mate day 0.88 150.00 132.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader 1 cum capacity hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer 4 cum capacity for lead hour 15.00 600.00 9000.00 017
P&M-
upto 1 km.
Transit Mixer 4 cum capacity, lead tonne.k 300L 1.85 11100.00 049
P&M-
beyond 1 Km, L - lead in Kilometer m 050
Lead=
20 km
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Per Cum Basic Cost of Labour, Material 2405.00 007
& Machinery (a+b+c)
Add 5 per cent of cost of material and 12431.70
labour towards cost of forming sump,
protective bunds, chiselling and making
arrangements for under water concreting
with tremie pipe..
d) Overhead charges @ 10 % on 30096.57
(a+b+c)
e) Contractor's profit @ 10 % on 33106.23
(a+b+c+d)
cost of 120 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/120 3034.74
say 3035.00
'12.11 (ii) PCC Grade M25
C Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 4180.00 25038.20 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
40 mm Aggregate cum 5.40 350.00 1890.00 M-055
20 mm Aggregate cum 5.40 410.00 2214.00 M-053
10 mm Aggregate cum 2.70 410.00 1107.00 M-051
Admixture Kg 21.60 50.00 1080.00 M-180
b) Labour
Mate day 0.90 150.00 135.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
079

Page 21 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Light Crane of 3 tonnes capacity for hour 6.00 225.00 1350.00 P&M-
handling tremie pipe 013
Per Cum Basic Cost of Labour, Material 2704.00
& Machinery (a+b+c)
Add 5 per cent of cost of material and 1810.09
labour towards cost of forming sump,
protective bunds, chiselling and making
arrangements for under water concreting
with tremie pipe..
d) Overhead charges @ 10 % on 4236.18
(a+b+c)
e) Contractor's profit @ 10 % on 4659.80
(a+b+c+d)
cost of 15 cum = a+b+c+d+e 51257.76
Rate per cum = (a+b+c+d+e)/15 3417.18
say 3417.00
12.11 Case II Using Batching Plant, Transit Mixer
C (ii) and Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.88 4180.00 ### M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
Admixture Kg 172.80 50.00 8640.00 M-180
b) Labour
Mate day 0.88 150.00 132.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader 1 cum capacity hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer 4 cum capacity for lead hour 15.00 600.00 9000.00 017
P&M-
upto 1 km.
Transit Mixer 4 cum capacity, lead tonne.k 300L 1.85 11100.00 049
P&M-
beyond 1 Km, L - lead in Kilometer m 050
Lead=
20 km
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Per Cum Basic Cost of Labour, Material 2536.00 007
& Machinery (a+b+c)
Add 5 per cent of cost of material and 13219.02
labour towards cost of forming sump,
protective bunds, chiselling and making
arrangements for under water concreting
with tremie pipe..
d) Overhead charges @ 10 % on 31749.94
(a+b+c)
e) Contractor's profit @ 10 % on 34924.94
(a+b+c+d)
cost of 120 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/120 3201.45
say 3201.00
'12.11 (iii) PCC Grade M30
C Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.08 4180.00 25414.40 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
40 mm Aggregate cum 5.40 350.00 1890.00 M-055
20 mm Aggregate cum 5.40 410.00 2214.00 M-053
10 mm Aggregate cum 2.70 410.00 1107.00 M-051
Admixture Kg 21.60 50.00 1080.00 M-180
b) Labour

Page 22 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Mate day 0.90 150.00 135.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Light Crane of 3 tonnes capacity for hour 6.00 225.00 1350.00 079
P&M-
handling tremie pipe 013
Per Cum Basic Cost of Labour, Material 2729.00
& Machinery (a+b+c)
Add 5 per cent of cost of material and 1828.90
labour towards cost of forming sump,
protective bunds, chiselling and making
arrangements for under water concreting
with tremie pipe..
d) Overhead charges @ 10 % on 4275.68
(a+b+c)
e) Contractor's profit @ 10 % on 4703.25
(a+b+c+d)
cost of 15 cum = a+b+c+d+e 51735.72
Rate per cum = (a+b+c+d+e)/15 3449.05
say 3449.00
12.11 Case II Using Batching Plant, Transit Mixer
C (iii) and Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.64 4180.00 ### M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
Admixture Kg 172.80 50.00 8640.00 M-180
b) Labour
Mate day 0.88 150.00 132.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader 1 cum capacity hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer 4 cum capacity for lead hour 15.00 600.00 9000.00 017
P&M-
upto 1 km.
Transit Mixer 4 cum capacity, lead tonne.k 300L 1.85 11100.00 049
P&M-
beyond 1 Km, L - lead in Kilometer m 050
Lead=
20 km
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Per Cum Basic Cost of Labour, Material 2563.00 007
& Machinery (a+b+c)
Add 5 per cent of cost of material and 13377.86
labour towards cost of forming sump,
protective bunds, chiselling and making
arrangements for under water concreting
with tremie pipe..
d) Overhead charges @ 10 % on 32083.51
(a+b+c)
e) Contractor's profit @ 10 % on 35291.86
(a+b+c+d)
cost of 120 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/120 3235.09
say 3235.00
'12.11 (iv) PCC Grade M35
C Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.29 4180.00 26292.20 M-081

Page 23 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Coarse sand cum 6.75 350.00 2362.50 M-005
40 mm Aggregate cum 5.40 350.00 1890.00 M-055
20 mm Aggregate cum 5.40 410.00 2214.00 M-053
10 mm Aggregate cum 2.70 410.00 1107.00 M-051
Admixture Kg 21.60 50.00 1080.00 M-180
b) Labour
Mate day 0.90 150.00 135.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Light Crane of 3 tonnes capacity for hour 6.00 225.00 1350.00 079
P&M-
handling tremie pipe 013
Per Cum Basic Cost of Labour, Material 2788.00
& Machinery (a+b+c)
Add 5 per cent of cost of material and 1872.79
labour towards cost of forming sump,
protective bunds, chiselling and making
arrangements for under water concreting
with tremie pipe..
d) Overhead charges @ 10 % on 4367.85
(a+b+c)
e) Contractor's profit @ 10 % on 4804.63
(a+b+c+d)
cost of 15 cum = a+b+c+d+e 52850.97
Rate per cum = (a+b+c+d+e)/15 3523.40
say 3523.00
12.11 Case II Using Batching Plant, Transit Mixer
C (iv) and Crane/concrete pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.28 4180.00 ### M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
Admixture Kg 172.80 50.00 8640.00 M-180
b) Labour
Mate day 0.88 150.00 132.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader 1 cum capacity hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer 4 cum capacity for lead hour 15.00 600.00 9000.00 017
P&M-
upto 1 km.
Transit Mixer 4 cum capacity, lead tonne.k 300L 1.85 11100.00 049
P&M-
beyond 1 Km, L - lead in Kilometer m 050
Lead=
20 km
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Per Cum Basic Cost of Labour, Material 2620.00 007
& Machinery (a+b+c)
Add 5 per cent of cost of material and 13720.62
labour towards cost of forming sump,
protective bunds, chiselling and making
arrangements for under water concreting
with tremie pipe..
d) Overhead charges @ 10 % on 32803.30
(a+b+c)
e) Contractor's profit @ 10 % on 36083.63
(a+b+c+d)
cost of 120 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/120 3307.67
say 3308.00

Page 24 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
12.11 Spec. D Intermediate plug
(i) Grade M20 PCC
Same as in bottom plug concrete, excluding
cost of forming sump, protective bunds,
chiseling
Case I Using etc.
Concrete Mixer
Per Cum Basic Cost of Labour, Material & 2571.00
Machinery (a+b+c)
d) Overhead charges @ 10 % on 257.10
(a+b+c)
e) Contractor's profit @ 10 % on 282.81
(a+b+c+d)
Rate per cum = (a+b+c+d+e) 3110.91
say 3111.00
12.11 Case II Using Batching Plant, Transit Mixer
D (i) and Crane/concrete pump
Per Cum Basic Cost of Labour, Material & 2405.00
Machinery (a+b+c)
d) Overhead charges @ 10 % on 240.50
(a+b+c)
e) Contractor's profit @ 10 % on 264.55
(a+b+c+d)
Rate per cum = (a+b+c+d+e) 2910.05
say 2910.00
'12.11 (ii) Grade M25 PCC
D Same as in bottom plug concrete, excluding
cost of forming sump, protective bunds,
chiseling
Case I Using etc.
Concrete Mixer
Per Cum Basic Cost of Labour, Material & 2704.00
Machinery (a+b+c)
d) Overhead charges @ 10 % on 270.40
(a+b+c)
e) Contractor's profit @ 10 % on 297.44
(a+b+c+d)
Rate per cum = (a+b+c+d+e) 3271.84
say 3272.00
12.11 Case II Using Batching Plant, Transit Mixer
D (ii) and Crane/concrete pump
Per Cum Basic Cost of Labour, Material & 2536.00
Machinery (a+b+c)
d) Overhead charges @ 10 % on 253.60
(a+b+c)
e) Contractor's profit @ 10 % on 278.96
(a+b+c+d)
Rate per cum = (a+b+c+d+e) 3068.56
say 3069.00
'12.11 (iii) Grade M30 PCC
D Same as in bottom plug concrete, excluding
cost of forming sump, protective bunds,
Case I chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & 2729.00
Machinery (a+b+c)
d) Overhead charges @ 10 % on 272.90
(a+b+c)
e) Contractor's profit @ 10 % on 300.19
(a+b+c+d)
Rate per cum = (a+b+c+d+e) 3302.09
say 3302.00
12.11 Case II Using Batching Plant, Transit Mixer
D (iii) and Crane/concrete pump
Per Cum Basic Cost of Labour, Material & 2563.00
Machinery (a+b+c)
d) Overhead charges @ 10 % on 256.30
(a+b+c)
e) Contractor's profit @ 10 % on 281.93
(a+b+c+d)
Rate per cum = (a+b+c+d+e) 3101.23
say 3101.00
12.11 E Top plug
(i) Grade M15 PCC
Same as Item 12.8(a) excluding formwork
Case I Using Concrete Mixer

Page 25 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Per Cum Basic Cost of Labour, Material & 2062.00
Machinery (a+b+c)
d) Overhead charges @ 10 % on 206.20
(a+b+c)
e) Contractor's profit @ 10 % on 226.82
(a+b+c+d)
Rate per cum = (a+b+c+d+e) 2495.02
say 2495.00
'12.11 (ii) Grade M20 PCC
E Same as Item 12.8(b) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & 2310.00
Machinery (a+b+c)
d) Overhead charges @ 10 % on 231.00
(a+b+c)
e) Contractor's profit @ 10 % on 254.10
(a+b+c+d)
Rate per cum = (a+b+c+d+e) 2795.10
say 2795.00
'12.11 (iii) Grade M25 PCC
E Same as Item 12.8 (d) excluding
Case I formwork
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & 2542.00
Machinery (a+b+c)
d) Overhead charges @ 10 % on 254.20
(a+b+c)
e) Contractor's profit @ 10 % on 279.62
(a+b+c+d)
Rate per cum = (a+b+c+d+e) 3075.82
say 3076.00
12.11 Case II Using Batching Plant, Transit Mixer
E (iii) and Crane/concrete pump
Per Cum Basic Cost of Labour, Material & 2445.00
Machinery (a+b+c)
d) Overhead charges @ 10 % on 244.50
(a+b+c)
e) Contractor's profit @ 10 % on 268.95
(a+b+c+d)
Rate per cum = (a+b+c+d+e) 2958.45
say 2958.00
'12.11 (iv) Grade M30 PCC
E Same as Item 12.8(f) excluding formwork
Case I Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & 2567.00
Machinery (a+b+c)
d) Overhead charges @ 10 % on 256.70
(a+b+c)
e) Contractor's profit @ 10 % on 282.37
(a+b+c+d)
Rate per cum = (a+b+c+d+e) 3106.07
say 3106.00
12.11 Case II Using Batching Plant, Transit Mixer
E (iv) and Crane/concrete pump
Per Cum Basic Cost of Labour, Material & 2468.00
Machinery (a+b+c)
d) Overhead charges @ 10 % on 246.80
(a+b+c)
e) Contractor's profit @ 10 % on 271.48
(a+b+c+d)
Rate per cum = (a+b+c+d+e) 2986.28
say 2986.00
12.11 F Well cap
(i) RCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 4180.00 21401.60 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051

Page 26 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. b) Labour
Mate day 0.86 150.00 129.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Form Work @ 4 per cent of a+b+c 1392.12 079
d) Overhead charges @ 10 % on 3619.52
(a+b+c)
e) Contractor's profit @ 10 % on 3981.47
(a+b+c+d)
cost of 15 cum = a+b+c+d+e 43796.22
Rate per cum = (a+b+c+d+e)/15 2919.75
say 2920.00
12.11 Case II Using Batching Plant, Transit Mixer
F (i) and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 4180.00 ### M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
b) Labour
Mate day 0.84 150.00 126.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader (capacity 1 cum) hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer ( capacity 4.0 cu.m ) 017
Transit Mixer 4 cum capacity for lead hour 15.00 600.00 9000.00 P&M-
upto
Lead 1beyond
km. 1 Km, L - lead in Kilometer tonne.k 300L 1.85 11100.00 049
P&M-
m 050
Lead=
20 km
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Formwork @ 4 per cent of (a+b+c) 10661.66 007
d) Overhead charges @ 10 % on 27720.33
(a+b+c)
e) Contractor's profit @ 10 % on 30492.36
(a+b+c+d)
cost of 120 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/120 2795.13
say 2795.00
12.11 (ii) RCC Grade M25
F Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 4180.00 25289.00 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.86 150.00 129.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
009

Page 27 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Generator 33 KVA hour 6.00 400.00 2400.00 P&M-
Form Work @ 3.75 per cent of a+b+c 1450.89 079
d) Overhead charges @ 10 % on 4014.14
(a+b+c)
e) Contractor's profit @ 10 % on 4415.55
(a+b+c+d)
cost of 15 cum = a+b+c+d+e 48571.09
Rate per cum = (a+b+c+d+e)/15 3238.07
say 3238.00
12.11 Case II Using Batching Plant, Transit Mixer
F (ii) and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.40 4180.00 ### M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
b) Labour
Mate day 0.84 150.00 126.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader (capacity 1 cum) hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer ( capacity 4.0 cu.m ) 017
Transit Mixer 4 cum capacity for lead hour 15.00 600.00 9000.00 P&M-
upto
Lead 1beyond
km. 1 Km, L - lead in Kilometer tonne.k 300L 1.85 11100.00 049
P&M-
m 050
Lead=
20 km
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Formwork @ 3.75 per cent of ( a+b+c) 11167.80 007
d) Overhead charges @ 10 % on 30897.58
(a+b+c)
e) Contractor's profit @ 10 % on 33987.34
(a+b+c+d)
cost of 120 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/120 3115.51
say 3116.00
12.11 (iii) RCC Grade M30
F Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 4180.00 25498.00 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.86 150.00 129.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Formwork @ 3.5 per cent of (a+b+c) 1361.48 079
d) Overhead charges @ 10 % on 4026.10
(a+b+c)
e) Contractor's profit @ 10 % on 4428.71
(a+b+c+d)
cost of 15 cum = a+b+c+d+e 48715.79
Rate per cum = (a+b+c+d+e)/15 3247.72

Page 28 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. say 3248.00
12.11 Case II Using Batching Plant, Transit Mixer
F (iii) and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 4180.00 ### M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
b) Labour
Mate day 0.84 150.00 126.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader (capacity 1 cum) hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer ( capacity 4.0 cu.m ) 017
Transit Mixer 4 cum capacity for lead hour 15.00 600.00 9000.00 P&M-
upto 1beyond
Lead km. 1 Km, L - lead in Kilometer tonne.k 300L 1.85 11100.00 049
P&M-
m 050
Lead=
20 km
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Formwork @ 3.5 per cent of (a+b+c) 10480.34 007
d) Overhead charges @ 10 % on 30991.85
(a+b+c)
e) Contractor's profit @ 10 % on 34091.04
(a+b+c+d)
cost of 120 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/120 3125.01
say 3125.00
12.11 (iv) RCC Grade M35
F Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 4180.00 26459.40 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.86 150.00 129.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Formwork @ 3 per cent of (a+b+c) 1195.83 079
d) Overhead charges @ 10 % on 4105.67
(a+b+c)
e) Contractor's profit @ 10 % on 4516.24
(a+b+c+d)
cost of 15 cum = a+b+c+d+e 49678.64
Rate per cum = (a+b+c+d+e)/15 3311.91
say 3312.00
12.11 Case II Using Batching Plant, Transit Mixer
F (iv) and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material

Page 29 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Cement tonne 50.64 4180.00 ### M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
b) Labour
Mate day 0.84 150.00 126.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader (capacity 1 cum) hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer ( capacity 4.0 cu.m ) 017
Transit Mixer 4 cum capacity for lead hour 15.00 600.00 9000.00 P&M-
upto
Lead 1beyond
km. 1 Km, L - lead in Kilometer tonne.k 300L 1.85 11100.00 049
P&M-
m 050
Lead=
20 km
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Formwork @ 3 per cent of (a+b+c) 9215.14 007
d) Overhead charges @ 10 % on 31638.63
(a+b+c)
e) Contractor's profit @ 10 % on 34802.50
(a+b+c+d)
cost of 120 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/120 3190.23
say 3190.00
Note Where ever concrete is carried out using
batching plant, transit mixer, concrete
pump, Admixtures @ 0.4 per cent of weight
of cement may be added for achieving
desired slump of concrete.
'12.11 (v) RCC M40 Grade
F Using Batching Plant, Transit Mixer
and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 52.20 4180.00 ### M-081
Coarse Sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
Admixture kg 206.00 50.00 10300.00 M-180
b) Labour
Mate day 0.84 150.00 126.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader 1 cum capacity hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer 4 cum capacity for lead hour 15.00 600.00 9000.00 017
P&M-
upto 1 km.
Transit Mixer 4 cum capacity for lead tonne.k 300.L 1.85 11100.00 049
P&M-
beyond 1 km. m 050
Lead=
20 km
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Formwork @ 3 per cent on cost of 9719.76 007
concrete i.e. cost of material, labour
d) and machinerycharges @ 10 % on
Overhead 33371.18
(a+b+c)
e) Contractor's profit @ 10 % on 36708.29
(a+b+c+d)
cost of 120 cum = a+b+c+d+e ###
Rate per cum = (a+b+c+d+e)/120 3364.93

Page 30 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. say 3365.00
12.12 Sectio Sinking of 6 m external diameter well
n (other than pneumatic method of
1200 sinking) through all types of strata
namely sandy soil, clayey soil and rock
as shown against each case, complete
as per drawing and technical
specifications. Depth of sinking is
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 6 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.50 m per hour.
a) Labour
Mate day 0.12 150.00 18.00 L-12
Sinker ( skilled ) day 1.00 125.00 125.00 L-15
Sinking helper ( semi-skilled ) day 2.00 120.00 240.00 L-14
b) Machinery
Hire & running charges of crane with hour 2.00 900.00 1800.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Consumables in sinking @10 per cent 180.00
c) of Overhead
(b) charges @ 10 % on 236.30
(a+b)
d) Contractor's profit @ 10 % on 259.93
(a+b+c)
Rate per metre = (a+b+c+d) 2859.23
say 2859.00
12.12 (ii) Beyond 3m upto 10m depth
A Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 150.00 22.50 L-12
Sinker day 1.25 125.00 156.25 L-15
Sinking helper ( semi-skilled ) day 2.50 120.00 300.00 L-14
b) Machinery
Hire & running charges of crane with hour 3.00 900.00 2700.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories in sinking @10 per cent of
Consumables 270.00
c) (b)Overhead charges @ 10 % on 344.88
(a+b) Contractor's profit @ 10 % on
d) 379.36
(a+b+c)
Rate per metre = (a+b+c+d) 4172.99
say 4173.00
12.12 (iii) Beyond 10m upto 20m
A a Add 5 per cent for every additional meter
depth of sinking over the rate of sinking for
the previous
11th m meter 5% 4382.00
12th m 5% 4601.00
13th m 5% 4831.00
14th m 5% 5073.00
15th m 5% 5327.00
16th m 5% 5593.00
17th m 5% 5873.00
18th m 5% 6167.00
19th m 5% 6475.00
20th m 5% 6799.00
Total Cost from 10m upto 20m 55121.00
Avg Rate per metre 5512.00
12.12 (iv) Beyond 20m upto 30 m
A a Add 7.5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious
20 per meter
cent of cost for Kentledge Including
including supports, loading arrangement 20% for
and Labour. Kentledge
Page 31 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 21st m 7.5% 7309.00 8771.00
22nd m 7.5% 7857.00 9428.00
23rd m 7.5% 8446.00 10135.00
24th m 7.5% 9079.00 10895.00
25th m 7.5% 9760.00 11712.00
26th m 7.5% 10492.00 12590.00
27th m 7.5% 11279.00 13535.00
28th m 7.5% 12125.00 14550.00
29th m 7.5% 13034.00 15641.00
30th m 7.5% 14012.00 16814.00
Total Cost from 20m upto 30m ### 124071.00
Avg Rate per metre ### 12407.00
12.12 (v) Beyond 30m upto 40 m
A a Add 10 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add 20 per meter
cent of cost for Kentledge Including
including supports, loading arrangement 20% for
and 31st
Labour.
m 10% 15413.00 Kentledge
18496.00
32nd 10% 16954.00 20345.00
33rd m 10% 18649.00 22379.00
34th m 10% 20514.00 24617.00
35th m 10% 22565.00 27078.00
36th m 10% 24822.00 29786.00
37th m 10% 27304.00 32765.00
38th m 10% 30034.00 36041.00
39th m 10% 33037.00 39644.00
40th m 10% 36341.00 43609.00
Total Cost from 30m upto 40m ### 294760.00
Avg Rate per metre ### 29476.00
12.12 B Clayey Soil ( 6m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.15 150.00 22.50 L-12
Sinker ( skilled ) day 1.50 125.00 187.50 L-15
Sinking helper ( semi-skilled ) day 2.25 120.00 270.00 L-14
b) Machinery
Hire & running charges of crane with hour 3.00 900.00 2700.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories
Consumables in sinking @ 10 per cent 270.00
c) of Overhead
(b) charges @ 10 % on 345.00
(a+b)
d) Contractor's profit @ 10 % on 379.50
(a+b+c)
Rate per metre = (a+b+c+d) 4174.50
say 4175.00
12.12 (ii) Beyond 3m upto 10m depth
B Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.30 150.00 45.00 L-12
Sinker day 3.00 125.00 375.00 L-15
Sinking helper ( semi-skilled ) day 4.50 120.00 540.00 L-14
b) Machinery
Hire & running charges of crane with hour 6.00 900.00 5400.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Air compressor with pneumatic chisel hour 2.00 250.00 500.00 P&M-
attachment for cutting hard clay. 063
Consumables in sinking @ 10 per cent 590.00
of (b)

Page 32 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. c) Overhead charges @ 10 % on 745.00
(a+b)
d) Contractor's profit @ 10 % on 819.50
(a+b+c)
Rate per metre = (a+b+c+d) 9014.50
say 9015.00
12.12 (iii) Beyond 10 m upto 20 m
B a Add 5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add meter @ 5 per cent of cost, if
for dewatering Including
required. for
dewatering
@ 5% of
cost, if
11th m 5% 9466.00 9939.00
12th m 5% 9939.00 10436.00
13th m 5% 10436.00 10958.00
14th m 5% 10958.00 11506.00
15th m 5% 11506.00 12081.00
16th m 5% 12081.00 12685.00
17th m 5% 12685.00 13319.00
18th m 5% 13319.00 13985.00
19th m 5% 13985.00 14684.00
20th m 5% 14684.00 15418.00
Total Cost from 10m upto 20m ### 125011.00
Avg Rate per metre ### 12501.00
12.12 (iv) Beyond 20m upto 30 m
B a Add 7.5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious meter
5 per cent of cost for dewatering of the
cost, if required
c Add 25 per cent of cost for Kentledge Including Including
including supports, loading arrangement 25% for 5% for
and Labour ). Kentledge dewaterin
g, if
required
21st m 7.5% 15785.00 19731.00 20718.00
22nd m 7.5% 16969.00 21211.00 22272.00
23rd m 7.5% 18242.00 22803.00 23943.00
24th m 7.5% 19610.00 24513.00 25739.00
25th m 7.5% 21081.00 26351.00 27669.00
26th m 7.5% 22662.00 28328.00 29744.00
27th m 7.5% 24362.00 30453.00 31976.00
28th m 7.5% 26189.00 32736.00 34373.00
29th m 7.5% 28153.00 35191.00 36951.00
30th m 7.5% 30264.00 37830.00 39722.00
Total Cost from 20m upto 30m ### 279147.00 ###
Avg Rate per metre ### 27915.00 ###
12.12 (v) Beyond 30m upto 40 m
B a Add 10 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious meterof cost for dewatering, if
5 per cent
c required
Add 20 per cent of cost for Kentledge Including Including
including supports, loading arrangement 20% for 5% for
and Labour). Kentledge dewaterin
g, if
required
31st m 10% 33290.00 39948.00 41945.00
32nd 10% 36619.00 43943.00 46140.00
33rd m 10% 40281.00 48337.00 50754.00
34th m 10% 44309.00 53171.00 55830.00
35th m 10% 48740.00 58488.00 61412.00
36th m 10% 53614.00 64337.00 67554.00
37th m 10% 58975.00 70770.00 74309.00

Page 33 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 38th m 10% 64873.00 77848.00 81740.00
39th m 10% 71360.00 85632.00 89914.00
40th m 10% 78496.00 94195.00 98905.00
Total Cost from 30m upto 40m ### 636669.00 ###
Avg Rate per metre ### 63667.00 ###
12.12 C Soft Rock (6m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.
a) Labour
Mate day 0.92 150.00 138.00 L-12
Sinker ( skilled ) day 3.00 125.00 375.00 L-15
Sinking helper ( semi-skilled ) day 20.00 120.00 2400.00 L-14
Diver day 0.50 150.00 75.00 L-07
b) Machinery
Hire & running charges of crane with hour 4.00 900.00 3600.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Air compressor with pneumatic hour 3.50 250.00 875.00 P&M-
breakers
Consumables in sinking @ 10 per cent 447.50 063
of (b)for dewatering @ of 5 per cent of
Add 395.53
(a+b), if required
c) Overhead charges @ 10 % on 830.60
(a+b)
d) Contractor's profit @ 10 % on 913.66
(a+b+c)
Rate per metre = (a+b+c+d) 10050.29
say ###
12.12 D Hard Rock (6m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 4.00 100.00 400.00 M-104
Electric Detonators each 18.00 5.00 90.00 M-
094/100
b) Labour
Mate day 1.56 150.00 234.00 L-12
Driller day 2.00 150.00 300.00 L-06
Blaster day 0.25 150.00 37.50 L-03
Mazdoor day 12.00 100.00 1200.00 L-13
Mazdoor (Skilled) day 4.00 125.00 500.00 L-15
c) Machinery
Hire & running charges of crane with hour 6.00 900.00 5400.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Hire & running charges of compressor hour 2.00 250.00 500.00 P&M-
with pneumatic breaker/Jack hammer 063
for drilling. @ 5 per cent of cost of
Dewatering 408.58
(b+c), if required.
Consumables in sinking @ 10 per cent 590.00
of cost of (b).
d) Overhead charges @ 10 % on 966.01
(a+b+c)
e) Contractor's profit @ 10 % on 1062.61
(a+b+c+d)
Rate per metre = (a+b+c+d+e) 11688.69
say ###

Page 34 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec.
12.13 Sectio Sinking of 7 m external diameter well (
n other than pneumatic method of
1200 sinking ) through all types of strata
namely sandy soil, clayey soil and rock
as shown against each case, complete
as per drawing and technical
specifications. Depth of sinking is
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 7 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.30 m per hour.
a) Labour
Mate day 0.15 150.00 22.50 L-12
Sinker ( skilled ) day 1.25 125.00 156.25 L-15
Sinking helper ( semi-skilled ) day 2.50 120.00 300.00 L-14
b) Machinery
Hire & running charges of crane with hour 3.25 900.00 2925.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Consumables in sinking @10 per cent 292.50
c) of Overhead
(b) charges @ 10 % on 369.63
(a+b)
d) Contractor's profit @ 10 % on 369.63
(a+b+c)
Rate per metre = (a+b+c+d) 4435.50
12.13 (ii) Beyond 3m upto 10m depth 4436.00
A Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 150.00 27.00 L-12
Sinker day 1.50 125.00 187.50 L-15
Sinking helper ( semi-skilled ) day 3.00 120.00 360.00 L-14
b) Machinery
Hire & running charges of crane with hour 4.50 900.00 4050.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories. in sinking @10 per cent of
Consumables 405.00
c) (b)Overhead charges @ 10 % on 502.95
(a+b) Contractor's profit @ 10 % on
d) 553.25
(a+b+c)
Rate per metre = (a+b+c+d) 6085.70
say 6086.00
12.13 (iii) Beyond 10m upto 20m
A a Add 5 per cent for every additional meter
depth of sinking over the rate of sinking for
the previous
11th m meter 5% 6390.00
12th m 5% 6710.00
13th m 5% 7046.00
14th m 5% 7398.00
0.17 15th m 5% 7768.00
16th m 5% 8156.00
17th m 5% 8564.00
18th m 5% 8992.00
19th m 5% 9442.00
20th m 5% 9914.00
Total Cost from 10m upto 20m 80380.00
Avg Rate per metre 8038.00
12.13 (iv) Beyond 20m upto 30 m
A a Add 7.5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious
20 per meter
cent of cost for Kentledge Including
including supports, loading arrangement 20% for
and 21st
Labour).
m 7.5% 10658.00 Kentledge
12790.00
22nd m 7.5% 11457.00 13748.00

Page 35 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 23rd m 7.5% 12316.00 14779.00
24th m 7.5% 13240.00 15888.00
25th m 7.5% 14233.00 17080.00
26th m 7.5% 15300.00 18360.00
27th m 7.5% 16448.00 19738.00
28th m 7.5% 17682.00 21218.00
29th m 7.5% 19008.00 22810.00
30th m 7.5% 20434.00 24521.00
Total Cost from 20m upto 30m ### 180932.00
Avg Rate per metre ### 18093.00
12.13 (v) Beyond 30m upto 40 m
A a Add 10 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add 20 per meter
cent of cost for Kentledge Including
including supports, loading arrangement, 20% for
and 31st
Labour
m etc. 10% 22477.00 Kentledge
26972.00
32nd 10% 24725.00 29670.00
33rd m 10% 27198.00 32638.00
34th m 10% 29918.00 35902.00
35th m 10% 32910.00 39492.00
36th m 10% 36201.00 43441.00
37th m 10% 39821.00 47785.00
38th m 10% 43803.00 52564.00
39th m 10% 48183.00 57820.00
40th m 10% 53001.00 63601.00
Total Cost from 30m upto 40m ### 429885.00
Avg Rate per metre ### 42989.00
12.13 B Clayey Soil ( 7m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
(I) Depth below bed level upto 3.0 M
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.18 150.00 27.00 L-12
Sinker ( skilled ) day 1.50 125.00 187.50 L-15
Sinking helper ( semi-skilled ) day 3.00 120.00 360.00 L-14
b) Machinery
Hire & running charges of crane with hour 4.50 900.00 4050.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Consumables in sinking @ 10 per cent 405.00
d) of (b)
Overhead charges @ 10 % on 502.95
(a+b)
e) Contractor's profit @ 10 % on 553.25
(a+b+c)
Rate per metre = (a+b+c+d) 6085.70
say 6086.00
12.13 (ii) Beyond 3m upto 10m depth
B Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.26 150.00 39.00 L-12
Sinker day 2.00 125.00 250.00 L-15
Sinking helper ( semi-skilled ) day 4.00 120.00 480.00 L-14
b) Machinery
Hire & running charges of crane with hour 6.00 900.00 5400.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Air compressor with pneumatic chisel hour 3.25 250.00 540.00 P&M-
attachment for cutting hard clay. 063
Consumables in sinking @ 10 per cent 594.00
c) of Overhead
(b) charges @ 10 % on 730.30
(a+b)
d) Contractor's profit @ 10 % on 803.33
(a+b+c)

Page 36 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Rate per metre = (a+b+c+d) 8836.63
say 8837.00
12.13 (iii) Beyond 10 m upto 20 m
B a Add 5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add meter @ 5 per cent of cost, if
for dewatering Including
required. for
dewatering
@ 5% of
cost, if
11th m 5% 9278.00 9742.00
12th m 5% 9742.00 10229.00
13th m 5% 10229.00 10740.00
14th m 5% 10740.00 11277.00
15th m 5% 11277.00 11841.00
16th m 5% 11841.00 12433.00
17th m 5% 12433.00 13055.00
18th m 5% 13055.00 13708.00
19th m 5% 13708.00 14393.00
20th m 5% 14393.00 15113.00
Total Cost from 10m upto 20m ### 122531.00
Avg Rate per metre ### 12253.00
12.13 (iv) Beyond 20m upto 30 m
B a Add 7.5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious meter
5 per cent of cost for dewatering on
the cost, if required
c Add 25 per cent of cost for Kentledge Including Including
including supports, loading arrangement 25% for 5% for
and Labour ). Kentledge dewaterin
g, if
required
31st m 7.5% 15472.00 19340.00 20307.00
32nd 7.5% 16632.00 20790.00 21830.00
33rd m 7.5% 17879.00 22349.00 23466.00
34th m 7.5% 19220.00 24025.00 25226.00
35th m 7.5% 20662.00 25828.00 27119.00
36th m 7.5% 22212.00 27765.00 29153.00
37th m 7.5% 23878.00 29848.00 31340.00
38th m 7.5% 25669.00 32086.00 33690.00
39th m 7.5% 27594.00 34493.00 36218.00
40th m 7.5% 29664.00 37080.00 38934.00
Total Cost from 30m upto 40m ### 273604.00 ###
Avg Rate per metre ### 27360.00 ###
12.13 (v) Beyond 30m upto 40 m
B a Add 10 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious meterof cost for dewatering, if
5 per cent
c required
Add 20 per cent of cost for Kentledge Including Including
including supports, loading arrangement 20% for 5% for
and Labour). Kentledge dewaterin
g, if
required
31st m 10% 32630.00 39156.00 41114.00
32nd 10% 35893.00 43072.00 45226.00
33rd m 10% 39482.00 47378.00 49747.00
34th m 10% 43430.00 52116.00 54722.00
35th m 10% 47773.00 57328.00 60194.00
36th m 10% 52550.00 63060.00 66213.00
37th m 10% 57805.00 69366.00 72834.00
38th m 10% 63586.00 76303.00 80118.00
39th m 10% 69945.00 83934.00 88131.00

Page 37 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 40th m 10% 76940.00 92328.00 96944.00
Total Cost from 30m upto 40m ### 624041.00 ###
Avg Rate per metre ### 62404.00 ###
12.13 C Soft Rock ( 7m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.58 150.00 87.00 L-12
Sinker ( skilled ) day 4.00 125.00 500.00 L-15
Sinking helper ( semi-skilled ) day 10.00 120.00 1200.00 L-14
Diver day 0.75 150.00 112.50 L-07
b) Machinery
Hire & running charges of crane with hour 4.50 900.00 4050.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Air compressor with pneumatic hour 3.75 250.00 937.50 P&M-
breakers
Consumables in sinking @ 10 per cent 498.75 063
of (b)for dewatering @ of 5 per cent of
Add 344.35
(a+b), if required
c) Overhead charges @ 10 % on 773.01
(a+b)
d) Contractor's profit @ 10 % on 850.31
(a+b+c)
Rate per metre = (a+b+c+d) 9353.42
say 9353.00
12.13 D Hard Rock ( 7m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent Kg 7.00 100.00 700.00 M-104
Electric Detonators each 30.00 5.00 150.00 M-
094/100
b) Labour
Mate day 1.60 150.00 240.00 L-12
Driller day 2.00 150.00 300.00 L-06
Blaster day 0.25 150.00 37.50 L-03
Mazdoor day 18.00 100.00 1800.00 L-13
Mazdoor (Skilled) day 4.00 125.00 500.00 L-15
Diver day 0.50 150.00 75.00 L-07
c) Machinery
Hire & running charges of crane with hour 6.00 900.00 5400.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Hire & running charges of compressor hour 2.00 250.00 500.00 P&M-
with pneumatic breaker/Jack hammer 063
for drilling. @ 5 per cent of cost of
Dewatering 442.63
(b+c), if required.
Consumables in sinking @ 10 per cent 634.26
of cost of (b).
d) Overhead charges @ 10 % on 1077.94
(a+b+c)
e) Contractor's profit @ 10 % on 1185.73
(a+b+c+d)
Rate per metre = (a+b+c+d+e) 13043.06
say ###
12.14 Sectio Sinking of 8 m external diameter well (
n other than pneumatic method of
1200 sinking ) through all types of strata
namely sandy soil, clayey soil and rock
as shown against each case, complete
as per drawing and technical
specifications. Depth of sinking is

Page 38 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Unit = Running Meter.
Taking output = 1 m
Diameter of well - 8 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.18 150.00 27.00 L-12
Sinker ( skilled ) day 1.50 125.00 187.50 L-15
Sinking helper ( semi-skilled ) day 3.00 120.00 360.00 L-14
b) Machinery
Hire & running charges of crane with hour 4.00 900.00 3600.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories. in sinking @10 per cent
Consumables 360.00
c) of Overhead
(b) charges @ 10 % on 453.45
(a+b) Contractor's profit @ 10 % on
d) 498.80
(a+b+c)
Rate per metre = (a+b+c+d) 5486.75
say 5487.00
12.14 (ii) Beyond 3m upto 10m depth
A Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.25 150.00 37.50 L-12
Sinker day 1.75 125.00 218.75 L-15
Sinking helper ( semi-skilled ) day 3.50 120.00 420.00 L-14
b) Machinery
Hire & running charges of crane with hour 5.00 900.00 4500.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Consumables in sinking @10 per cent of 450.00
c) (b)Overhead charges @ 10 % on 562.63
(a+b) Contractor's profit @ 10 % on
d) 618.89
(a+b+c)
Rate per metre = (a+b+c+d) 6807.76
say 6808.00
12.14 (iii) Beyond 10m upto 20m
A a Add 5 per cent for every additional meter
depth of sinking over the rate of sinking for
the previous
11th m meter 5% 7148.00
12th m 5% 7505.00
13th m 5% 7880.00
14th m 5% 8274.00
15th m 5% 8688.00
16th m 5% 9122.00
17th m 5% 9578.00
18th m 5% 10057.00
19th m 5% 10560.00
20th m 5% 11088.00
Total Cost from 10m upto 20m 89900.00
Avg Rate per metre 8990.00
12.14 (iv) Beyond 20m upto 30 m
A a Add 7.5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious
20 per meter
cent of cost for Kentledge Including
including supports, loading arrangement 20% for
and 21st
Labour.
m 7.5% 11920.00 Kentledge
14304.00
22nd m 7.5% 12814.00 15377.00
23rd m 7.5% 13775.00 16530.00
24th m 7.5% 14808.00 17770.00
25th m 7.5% 15919.00 19103.00
26th m 7.5% 17113.00 20536.00

Page 39 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 27th m 7.5% 18396.00 22075.00
28th m 7.5% 19776.00 23731.00
29th m 7.5% 21259.00 25511.00
30th m 7.5% 22853.00 27424.00
Total Cost from 20m upto 30m ### 202361.00
Avg Rate per metre ### 20236.00
12.14 (v) Beyond 30m upto 40 m
A a Add 10 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add 20 per meter
cent of cost for Kentledge Including
including supports, loading arrangement, 20% for
and 31st
Labour
m etc. 10% 25138.00 Kentledge
30166.00
32nd 10% 27652.00 33182.00
33rd m 10% 30417.00 36500.00
34th m 10% 33459.00 40151.00
35th m 10% 36805.00 44166.00
36th m 10% 40486.00 48583.00
37th m 10% 44535.00 53442.00
38th m 10% 48989.00 58787.00
39th m 10% 53888.00 64666.00
40th m 10% 59277.00 71132.00
Total Cost from 30m upto 40m 59277.00 71132.00
Avg Rate per metre 5928.00 7113.00
12.14 B Clayey Soil ( 8m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.22 150.00 33.00 L-12
Sinker ( skilled ) day 2.00 125.00 250.00 L-15
Sinking helper ( semi-skilled ) hour 3.50 120.00 420.00 L-14
b) Machinery
Hire & running charges of crane with 5.50 900.00 4950.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Consumables in sinking @ 10 per cent 495.00
c) of Overhead
(b) charges @ 10 % on 614.80
(a+b)
d) Contractor's profit @ 10 % on 676.28
(a+b+c)
Rate per metre = (a+b+c+d) 7439.08
say 7439.00
12.14 (ii) Beyond 3m upto 10m depth
B Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.32 150.00 48.00 L-12
Sinker day 2.50 125.00 312.50 L-15
Sinking helper ( semi-skilled ) day 4.50 120.00 540.00 L-14
b) Machinery
Hire & running charges of crane with hour 6.00 900.00 5400.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Air compressor with pneumatic chisel hour 3.50 250.00 875.00 P&M-
attachment for cutting hard clay. 063
Consumables in sinking @ 10 per cent 627.50
c) of Overhead
(b) charges @ 10 % on 780.30
(a+b)
d) Contractor's profit @ 10 % on 858.33
(a+b+c)
Rate per metre = (a+b+c+d) 9441.63
say 9442.00
12.14 (iii) Beyond 10 m upto 20 m
B

Page 40 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. a Add 5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add meter @ 5 per cent of cost, if
for dewatering Including
required. for
dewatering
@ 5% of
cost, if
11th m 5% 9914.00 10410.00
12th m 5% 10410.00 10931.00
13th m 5% 10931.00 11478.00
14th m 5% 11478.00 12052.00
15th m 5% 12052.00 12655.00
16th m 5% 12655.00 13288.00
17th m 5% 13288.00 13952.00
18th m 5% 13952.00 14650.00
19th m 5% 14650.00 15383.00
20th m 5% 15383.00 16152.00
Total Cost from 10m upto 20m ### 130951.00
Avg Rate per metre ### 13095.00
12.14 (iv) Beyond 20m upto 30 m
B a Add 7.5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious meter
5 per cent of cost for dewatering on
the cost, if required
c Add 25 per cent of cost for Kentledge Including Including
including supports, loading arrangement 25% for 5% for
and Labour ). Kentledge dewaterin
g, if
required
31st m 7.5% 16537.00 20671.00 21705.00
32nd 7.5% 17777.00 22221.00 23332.00
33rd m 7.5% 19110.00 23888.00 25082.00
34th m 7.5% 20543.00 25679.00 26963.00
35th m 7.5% 22084.00 27605.00 28985.00
36th m 7.5% 23740.00 29675.00 31159.00
37th m 7.5% 25521.00 31901.00 33496.00
38th m 7.5% 27435.00 34294.00 36009.00
39th m 7.5% 29493.00 36866.00 38709.00
40th m 7.5% 31705.00 39631.00 41613.00
Total Cost from 30m upto 40m ### 292431.00 ###
Avg Rate per metre ### 29243.00 ###
12.14 (v) Beyond 30m upto 40 m
B a Add 10 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious meterof cost for dewatering, if
5 per cent
c required
Add 20 per cent of cost for Kentledge Including Including
including supports, loading arrangement 20% for 5% for
and Labour). Kentledge dewaterin
g, if
required
31st m 10% 34876.00 41851.00 43944.00
32nd 10% 38364.00 46037.00 48339.00
33rd m 10% 42200.00 50640.00 53172.00
34th m 10% 46420.00 55704.00 58489.00
35th m 10% 51062.00 61274.00 64338.00
36th m 10% 56168.00 67402.00 70772.00
37th m 10% 61785.00 74142.00 77849.00
38th m 10% 67964.00 81557.00 85635.00
39th m 10% 74760.00 89712.00 94198.00
40th m 10% 82236.00 98683.00 ###
Total Cost from 30m upto 40m ### 667002.00 ###
Avg Rate per metre ### 66700.00 ###

Page 41 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
12.14 Spec. C Soft Rock ( 8m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.68 150.00 102.00 L-12
Sinker ( skilled ) day 4.00 125.00 500.00 L-15
Sinking helper ( semi-skilled ) day 12.00 120.00 1440.00 L-14
Diver day 1.00 150.00 150.00 L-07
b) Machinery
Hire & running charges of crane with hour 5.00 900.00 4500.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Air compressor with pneumatic hour 3.75 250.00 937.50 P&M-
breakers
Consumables in sinking @ 10 per cent 543.75 063
of (b)for dewatering @ of 5 per cent of
Add 408.66
(a+b), if required
c) Overhead charges @ 10 % on 858.19
(a+b)
d) Contractor's profit @ 10 % on 944.01
(a+b+c)
Rate per metre = (a+b+c+d) 10384.11
say ###
12.14 D Hard Rock ( 8m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour
a) Material
Gelatine 80 per cent Kg 8.00 100.00 800.00 M-104
Electric Detonators each 32.00 5.00 160.00 M-
094/100
b) Labour
Mate day 1.09 150.00 163.50 L-12
Driller day 2.00 150.00 300.00 L-06
Blaster day 0.25 150.00 37.50 L-03
Mazdoor day 20.00 100.00 2000.00 L-13
Mazdoor (Skilled) day 4.00 125.00 500.00 L-15
c) Machinery
Hire & running charges of crane with hour 6.00 900.00 5400.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Hire & running charges of compressor hour 2.00 250.00 500.00 P&M-
with pneumatic breaker/Jack hammer 063
for drilling. @ 5 per cent of cost of
Dewatering 445.05
(b+c), if required.
Consumables in sinking @ 10 per cent 300.10
of cost of (b).
d) Overhead charges @ 10 % on 1060.62
(a+b+c)
e) Contractor's profit @ 10 % on 1166.68
(a+b+c+d)
Rate per metre = (a+b+c+d+e) 12833.44
say ###
12.15 Sectio Sinking of 9 m external diameter well (
n other than pneumatic method of
1200 sinking ) through all types of strata
namely sandy soil, clayey soil and rock
as shown against each case, complete
as per drawing and technical
specifications. Depth of sinking is
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 9 m.
A Sandy Soil

Page 42 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. (i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.19 150.00 28.50 L-12
Sinker ( skilled ) day 1.50 125.00 187.50 L-15
Sinking helper ( semi-skilled ) day 3.25 120.00 390.00 L-14
b) Machinery
Hire & running charges of crane with hour 4.00 900.00 3600.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories. in sinking @10 per cent
Consumables 360.00
c) of Overhead
(b) charges @ 10 % on 456.60
(a+b) Contractor's profit @ 10 % on
d) 502.26
(a+b+c)
Rate per metre = (a+b+c+d) 5524.86
say 5525.00
12.15 (ii) Beyond 3m upto 10m depth
A Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.27 150.00 40.50 L-12
Sinker day 1.75 125.00 218.75 L-15
Sinking helper ( semi-skilled ) day 4.00 120.00 480.00 L-14
b) Machinery
Hire & running charges of crane with hour 5.50 900.00 4950.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Consumables in sinking @10 per cent of 495.00
c) (b)Overhead charges @ 10 % on 618.43
(a+b)
d) Contractor's profit @ 10 % on 680.27
(a+b+c)
Rate per metre = (a+b+c+d) 7482.94
say 7483.00
12.15 (iii) Beyond 10m upto 20m
A a Add 5 per cent for every additional meter
depth of sinking over the rate of sinking for
the previous
11th m meter 5% 7857.00
12th m 5% 8250.00
13th m 5% 8663.00
14th m 5% 9096.00
15th m 5% 9551.00
16th m 5% 10029.00
17th m 5% 10530.00
18th m 5% 11057.00
19th m 5% 11610.00
20th m 5% 12191.00
Total Cost from 10m upto 20m 98834.00
Avg Rate per metre 9883.00
12.15 (iv) Beyond 20m upto 30 m
A a Add 7.5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious
20 per meter
cent of cost for Kentledge Including
including supports, loading arrangement 20% for
and 21st
Labour.
m 7.5% 13105.33 Kentledge
15726.00
22nd m 7.5% 14088.00 16906.00
23rd m 7.5% 15145.00 18174.00
24th m 7.5% 16281.00 19537.00
25th m 7.5% 17502.00 21002.00
26th m 7.5% 18815.00 22578.00
27th m 7.5% 20226.00 24271.00
28th m 7.5% 21743.00 26092.00
29th m 7.5% 23374.00 28049.00
30th m 7.5% 25127.00 30152.00

Page 43 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Total Cost from 20m upto 30m ### 222487.00
Avg Rate per metre ### 22249.00
12.15 (v) Beyond 30m upto 40 m
A a Add 10 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add 20 per meter
cent of cost for Kentledge Including
including supports, loading arrangement, 20% for
and 31st
Labour
m etc. 10% 27639.70 Kentledge
33168.00
32nd 10% 30404.00 36485.00
33rd m 10% 33444.00 40133.00
34th m 10% 36788.00 44146.00
35th m 10% 40467.00 48560.00
36th m 10% 44514.00 53417.00
37th m 10% 48965.00 58758.00
38th m 10% 53862.00 64634.00
39th m 10% 59248.00 71098.00
40th m 10% 65173.00 78208.00
Total Cost from 30m upto 40m ### 528607.00
Avg Rate per metre ### 52861.00
12.15 B Clayey Soil ( 9m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.24 150.00 36.00 L-12
Sinker ( skilled ) day 2.25 125.00 281.25 L-15
Sinking helper ( semi-skilled ) day 3.75 120.00 450.00 L-14
b) Machinery
Hire & running charges of crane with hour 5.75 900.00 5175.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Consumables in sinking @ 10 per cent 517.50
c) of Overhead
(b) charges @ 10 % on 645.98
(a+b)
d) Contractor's profit @ 10 % on 710.57
(a+b+c)
Rate per metre = (a+b+c+d) 7816.30
say 7816.00
12.15 (ii) Beyond 3m upto 10m depth
B Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.34 150.00 51.00 L-12
Sinker day 2.50 125.00 312.50 L-15
Sinking helper ( semi-skilled ) day 5.00 120.00 600.00 L-14
b) Machinery
Hire & running charges of crane with hour 6.50 900.00 5850.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Air compressor with pneumatic chisel hour 3.75 250.00 937.50 P&M-
attachment for cutting hard clay. 063
Consumables in sinking @ 10 per cent 678.75
c) of Overhead
(b) charges @ 10 % on 842.98
(a+b)
d) Contractor's profit @ 10 % on 927.27
(a+b+c)
Rate per metre = (a+b+c+d) 10200.00
say ###
12.15 (iii) Beyond 10 m upto 20 m
B a Add 5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add meter @ 5 per cent of cost, if
for dewatering Including
required. for
dewatering
@ 5% of
cost, if
Page 44 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 11th m 5% 10710.00 11246.00
12th m 5% 11246.00 11808.00
13th m 5% 11808.00 12398.00
14th m 5% 12398.00 13018.00
15th m 5% 13018.00 13669.00
16th m 5% 13669.00 14352.00
17th m 5% 14352.00 15070.00
18th m 5% 15070.00 15824.00
19th m 5% 15824.00 16615.00
20th m 5% 16615.00 17446.00
Total Cost from 10m upto 20m ### 141446.00
Avg Rate per metre ### 14145.00
12.15 (iv) Beyond 20m upto 30 m
B a Add 7.5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add meter
5 per cent of cost for dewatering on
the cost, if required
c Add 25 per cent of cost for Kentledge Including Including
including supports, loading arrangement 25% for 5% for
and Labour ). Kentledge dewaterin
g, if
required
31st m 7.5% 17861.00 22326.00 23442.00
32nd 7.5% 19201.00 24001.00 25201.00
33rd m 7.5% 20641.00 25801.00 27091.00
34th m 7.5% 22189.00 27736.00 29123.00
35th m 7.5% 23853.00 29816.00 31307.00
36th m 7.5% 25642.00 32053.00 33656.00
37th m 7.5% 27565.00 34456.00 36179.00
38th m 7.5% 29632.00 37040.00 38892.00
39th m 7.5% 31854.00 39818.00 41809.00
40th m 7.5% 34243.00 42804.00 44944.00
Total Cost from 30m upto 40m ### 315851.00 ###
Avg Rate per metre ### 31585.00 ###
12.15 (v) Beyond 30m upto 40 m
B a Add 10 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add meterof cost for dewatering, if
5 per cent
c required
Add 20 per cent of cost for Kentledge Including Including
including supports, loading arrangement 20% for 5% for
and Labour). Kentledge dewaterin
g, if
required
31st m 10% 37667.00 45200.00 47460.00
32nd 10% 41434.00 49721.00 52207.00
33rd m 10% 45577.00 54692.00 57427.00
34th m 10% 50135.00 60162.00 63170.00
35th m 10% 55149.00 66179.00 69488.00
36th m 10% 60664.00 72797.00 76437.00
37th m 10% 66730.00 80076.00 84080.00
38th m 10% 73403.00 88084.00 92488.00
39th m 10% 80743.00 96892.00 ###
40th m 10% 88817.00 106580.00 ###
Total Cost from 30m upto 40m ### 720383.00 ###
Avg Rate per metre ### 72038.00 ###
12.15 C Soft Rock ( 9m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour

Page 45 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. a) Labour
Mate day 0.76 150.00 114.00 L-12
Sinker ( skilled ) day 4.00 125.00 500.00 L-15
Sinking helper ( semi-skilled ) day 14.00 120.00 1680.00 L-14
Diver day 1.20 150.00 180.00 L-07
b) Machinery
Hire & running charges of crane with hour 6.50 900.00 5850.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Air compressor with pneumatic hour 4.00 250.00 1000.00 P&M-
breakers
Consumables in sinking @ 10 per cent 685.00 063
of (b)for dewatering @ of 5 per cent of
Add 1000.90
(a+b), if required
c) Overhead charges @ 10 % on 1100.99
(a+b)
d) Contractor's profit @ 10 % on 1211.09
(a+b+c)
Rate per metre = (a+b+c+d) 13321.98
say ###
12.15 D Hard Rock ( 9m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a) Material
Gelatine 80 per cent Kg 10.00 100.00 1000.00 M-104
Electric Detonators each 40.00 5.00 200.00 M-
094/100
b) Labour
Mate day 1.17 150.00 175.50 L-12
Driller day 2.00 150.00 300.00 L-06
Blaster day 0.25 150.00 37.50 L-03
Mazdoor day 22.00 100.00 2200.00 L-13
Mazdoor (Skilled) day 4.00 125.00 500.00 L-15
Diver day 1.00 150.00 150.00 L-07
c) Machinery
Hire & running charges of crane with hour 7.00 900.00 6300.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Hire & running charges of compressor hour 2.50 250.00 625.00 P&M-
with pneumatic breaker/Jack hammer 063
for drilling. @ 5 per cent of cost of
Dewatering 514.40
(b+c), if required.
Consumables in sinking @ 10 per cent 336.30
of cost of (b).
d) Overhead charges @ 10 % on 1233.87
(a+b+c)
e) Contractor's profit @ 10 % on 1357.26
(a+b+c+d)
Rate per metre = (a+b+c+d+e) 14929.83
say ###
12.16 1200 Sinking of 10 m external diameter well
( other than pneumatic method of
sinking ) through all types of strata
namely sandy soil, clayey soil and rock
as shown against each case, complete
as per drawing and technical
specifications. Depth of sinking is
Unit = Running Meter
Taking output = 1 m
Diameter of well - 10 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.20 m / hour
a) Labour
Mate day 0.20 150.00 30.00 L-12

Page 46 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Sinker ( skilled ) day 1.50 125.00 187.50 L-15
Sinking helper ( semi-skilled ) day 3.50 120.00 420.00 L-14
b) Machinery
Hire & running charges of crane with hour 5.00 900.00 4500.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories. in sinking @10 per cent
Consumables 450.00
c) of Overhead
(b) charges @ 10 % on 558.75
(a+b) Contractor's profit @ 10 % on
d) 614.63
(a+b+c)
Rate per metre = (a+b+c+d) 6760.88
say 6761.00
12.16 (ii) Beyond 3m upto 10m depth
A Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.31 150.00 46.50 L-12
Sinker day 2.00 125.00 250.00 L-15
Sinking helper ( semi-skilled ) day 4.25 120.00 510.00 L-14
b) Machinery
Hire & running charges of crane with hour 5.75 900.00 5175.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Consumables in sinking @10 per cent of 517.50
c) (b)Overhead charges @ 10 % on 649.90
(a+b)
d) Contractor's profit @ 10 % on 714.89
(a+b+c)
Rate per metre = (a+b+c+d) 7863.79
say 7864.00
12.16 (iii) Beyond 10m upto 20m
A a Add 5 per cent for every additional meter
depth of sinking over the rate of sinking for
the previous
11th m meter 5% 8257.00
12th m 5% 8670.00
13th m 5% 9104.00
14th m 5% 9559.00
15th m 5% 10037.00
16th m 5% 10539.00
17th m 5% 11066.00
18th m 5% 11619.00
19th m 5% 12200.00
20th m 5% 12810.00
Total Cost from 10m upto 20m ###
Avg Rate per metre ###
12.16 (iv) Beyond 20m upto 30 m
A a Add 7.5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious
20 per meter
cent of cost for Kentledge Including
including supports, loading arrangement 20% for
and 21st
Labour.
m 7.5% 13771.00 Kentledge
16525.00
22nd m 7.5% 14804.00 17765.00
23rd m 7.5% 15914.00 19097.00
24th m 7.5% 17108.00 20530.00
25th m 7.5% 18391.00 22069.00
26th m 7.5% 19770.00 23724.00
27th m 7.5% 21253.00 25504.00
28th m 7.5% 22847.00 27416.00
29th m 7.5% 24561.00 29473.00
30th m 7.5% 26403.00 31684.00
Total Cost from 20m upto 30m ### 233787.00
Avg Rate per metre ### 23379.00
12.16 (v) Beyond 30m upto 40 m
A

Page 47 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. a Add 10 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add 20 per meter
cent of cost for Kentledge Including
including supports, loading arrangement, 20% for
and 31st
Labour
m etc. 10% 29043.00 Kentledge
34852.00
32nd 10% 31947.00 38336.00
33rd m 10% 35142.00 42170.00
34th m 10% 38656.00 46387.00
35th m 10% 42522.00 51026.00
36th m 10% 46774.00 56129.00
37th m 10% 51451.00 61741.00
38th m 10% 56596.00 67915.00
39th m 10% 62256.00 74707.00
40th m 10% 68482.00 82178.00
Total Cost from 30m upto 40m ### 555441.00
Avg Rate per metre ### 55544.00
12.16 B Clayey Soil (10m dia. Well )
Unit = Running Meter
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.18m/hour.
a) Labour
Mate day 0.25 150.00 37.50 L-12
Sinker ( skilled ) day 2.50 125.00 312.50 L-15
Sinking helper ( semi-skilled ) day 5.50 120.00 660.00 L-14
b) Machinery
Hire & running charges of crane with hour 6.00 900.00 5400.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Consumables in sinking @ 10 per cent 540.00
c) of Overhead
(b) charges @ 10 % on 695.00
(a+b)
d) Contractor's profit @ 10 % on 764.50
(a+b+c)
Rate per metre = (a+b+c+d) 8409.50
say 8410.00
12.16 (ii) Beyond 3m upto 10m depth
B Rate of sinking 0.15m/hour.
a) Labour
Mate day 0.40 150.00 60.00 L-12
Sinker day 3.00 125.00 375.00 L-15
Sinking helper ( semi-skilled ) day 5.50 120.00 660.00 L-14
b) Machinery
Hire & running charges of crane with hour 6.00 900.00 5400.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Air compressor with pneumatic chisel hour 4.00 250.00 1000.00 P&M-
attachment for cutting hard clay 063
Consumables in sinking @ 10 per cent 640.00
c) of Overhead
(b) charges @ 10 % on 813.50
(a+b) Contractor's profit @ 10 % on
d) 894.85
(a+b+c)
Rate per metre = (a+b+c+d) 9843.35
say 9843.00
12.16 (iii) Beyond 10 m upto 20 m
B a Add 5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious meter @ 5 per cent of cost, if
for dewatering Including
required. for
dewatering
@ 5% of
cost, if
11th m 5% 10336.00 10853.00
12th m 5% 10853.00 11396.00
13th m 5% 11396.00 11966.00

Page 48 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 14th m 5% 11966.00 12564.00
15th m 5% 12564.00 13192.00
16th m 5% 13192.00 13852.00
17th m 5% 13852.00 14545.00
18th m 5% 14545.00 15272.00
19th m 5% 15272.00 16036.00
20th m 5% 16036.00 16838.00
Total Cost from 10m upto 20m ### 136514.00
Avg Rate per metre ### 13651.00
12.16 (iv) Beyond 20m upto 30 m
B a Add 7.5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add meter
5 per cent of cost for dewatering on
the cost, if required
c Add 25 per cent of cost for Kentledge Including Including
including supports, loading arrangement 25% for 5% for
and Labour ). Kentledge dewaterin
g, if
required
31st m 7.5% 17239.00 21549.00 22626.00
32nd 7.5% 18532.00 23165.00 24323.00
33rd m 7.5% 19922.00 24903.00 26148.00
34th m 7.5% 21416.00 26770.00 28109.00
35th m 7.5% 23022.00 28778.00 30217.00
36th m 7.5% 24749.00 30936.00 32483.00
37th m 7.5% 26605.00 33256.00 34919.00
38th m 7.5% 28600.00 35750.00 37538.00
39th m 7.5% 30745.00 38431.00 40353.00
40th m 7.5% 33051.00 41314.00 43380.00
Total Cost from 30m upto 40m ### 304852.00 ###
Avg Rate per metre ### 30485.00 ###
12.16 (v) Beyond 30m upto 40 m
B a Add 10 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add meterof cost for dewatering, if
5 per cent
c required
Add 20 per cent of cost for Kentledge Including Including
including supports, loading arrangement 20% for 5% for
and Labour). Kentledge dewaterin
g, if
required
31st m 10% 36356.00 43627.00 45808.00
32nd 10% 39992.00 47990.00 50390.00
33rd m 10% 43991.00 52789.00 55428.45
34th m 10% 48390.00 58068.00 60971.40
35th m 10% 53229.00 63875.00 67068.75
36th m 10% 58552.00 70262.00 73775.10
37th m 10% 64407.00 77288.00 81152.40
38th m 10% 70848.00 85018.00 89268.90
39th m 10% 77933.00 93520.00 98196.00
40th m 10% 85726.00 102871.00 ###
Total Cost from 30m upto 40m ### 695308.00 ###
Avg Rate per metre ### 69531.00 ###
12.16 C Soft Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a) Labour
Mate day 0.86 150.00 129.00 L-12
Sinker ( skilled ) day 4.00 125.00 500.00 L-15

Page 49 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Sinking helper ( semi-skilled ) day 16.00 120.00 1920.00 L-14
Diver day 1.40 150.00 210.00 L-07
b) Machinery
Hire & running charges of crane with hour 7.00 900.00 6300.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Air compressor with pneumatic hour 4.25 250.00 1062.50 P&M-
breakers
Consumables in sinking @ 10 per cent 736.25 063
of (b)for dewatering @ 5 per cent of
Add 404.94
c) cost, if required
Overhead charges @ 10 % on 1126.27
(a+b) Contractor's profit @ 10 % on
d) 1238.90
(a+b+c)
Rate per metre = (a+b+c+d) 13627.85
say ###
12.16 D Hard Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a) Material
Gelatine 80 per cent Kg 11.00 100.00 1100.00 M-104
Electric Detonators each. 44.00 5.00 220.00 M-
094/100
b) Labour
Mate day 1.27 150.00 190.50 L-12
Driller day 2.00 150.00 300.00 L-06
Blaster day 0.25 150.00 37.50 L-03
Mazdoor day 24.00 100.00 2400.00 L-13
Mazdoor (Skilled) day 4.00 125.00 500.00 L-15
c) Machinery
Hire & running charges of crane with hour 8.50 900.00 7650.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Hire & running charges of compressor hour 3.00 250.00 750.00 P&M-
with pneumatic breaker/Jack hammer or 063
drill
Dewatering @ 5 per cent of cost (c), if 420.00
required.
Consumables in sinking @ 10 per cent 1224.80
of cost of (b+c).
d) Overhead charges @ 10 % on 1479.28
(a+b+c)
e) Contractor's profit @ 10 % on 1627.21
(a+b+c+d)
Rate per metre = (a+b+c+d+e) 17899.29
say ###
12.17 1200 Sinking of 11 m external diameter well
( other than pneumatic method of
sinking ) through all types of strata
namely sandy soil, clayey soil and rock
as shown against each case, complete
as per drawing and technical
specifications. Depth of sinking is
Unit = Running Meter
Taking output = 0.50 m
Diameter of well - 11 m.
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.21 150.00 31.50 L-12
Sinker ( skilled ) day 1.50 125.00 187.50 L-15
Sinking helper (semi-skilled) day 3.30 120.00 396.00 L-14
b) Machinery
Hire & running charges of crane with hour 6.00 900.00 5400.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories. in sinking @10 per cent
Consumables 540.00
of (b)
Page 50 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. d) Overhead charges @ 10 % on 655.50
(a+b+c)
e) Contractor's profit @ 10 % on 721.05
(a+b+c+d)
Cost for 0.5m = a+b+c+d 7931.55
Rate per metre = (a+b+c+d)/0.50 15863.10
say ###
12.17 (ii) Beyond 3m upto 10m depth
A Rate of sinking @ 0.13 m/hour
a) Labour
Mate day 0.32 150.00 48.00 L-12
Sinker day 2.00 125.00 250.00 L-15
Sinking helper (semi-skilled) day 4.50 120.00 540.00 L-14
b) Machinery
Hire & running charges of crane with hour 6.00 900.00 5400.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories. in sinking @10 per cent of
Consumables 540.00
c) (b)Overhead charges @ 10 % on 677.80
(a+b+c)
d) Contractor's profit @ 10 % on 745.58
(a+b+c+d)
Cost for 0.5m = a+b+c+d 8201.38
Rate per metre = (a+b+c+d)/0.50 16402.76
say ###
12.17 (iii) Beyond 10m upto 20m
A a Add 5 per cent for every additional meter
depth of sinking over the rate of sinking for
the previous
11th m meter 5% 17223.00
12th m 5% 18084.00
13th m 5% 18988.00
14th m 5% 19937.00
15th m 5% 20934.00
16th m 5% 21981.00
17th m 5% 23080.00
18th m 5% 24234.00
19th m 5% 25446.00
20th m 5% 26718.00
Total Cost from 10m upto 20m ###
Avg Rate per metre ###
12.17 (iv) Beyond 20m upto 30 m
A a Add 7.5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious
20 per meter
cent of cost for Kentledge Including
including supports, loading arrangement 20% for
and 21st
Labour.
m 7.5% 28722.00 Kentledge
34466.00
22nd m 7.5% 30876.00 37051.00
23rd m 7.5% 33192.00 39830.00
24th m 7.5% 35681.00 42817.00
25th m 7.5% 38357.00 46028.00
26th m 7.5% 41234.00 49481.00
27th m 7.5% 44327.00 53192.00
28th m 7.5% 47652.00 57182.00
29th m 7.5% 51226.00 61471.00
30th m 7.5% 55068.00 66082.00
Total Cost from 20m upto 30m ### 487600.00
Avg Rate per metre ### 48760.00
12.17 (v) Beyond 30m upto 40 m
A a Add 10 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious
20 per meter
cent of cost for Kentledge Including
including supports, loading arrangement, 20% for
and 31st
Labour
m etc. 10% 60575.00 Kentledge
72690.00

Page 51 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 32nd 10% 66633.00 79960.00
33rd m 10% 73296.00 87955.00
34th m 10% 80626.00 96751.00
35th m 10% 88689.00 106427.00
36th m 10% 97558.00 117070.00
37th m 10% ### 128777.00
38th m 10% ### 141654.00
39th m 10% ### 155820.00
40th m 10% ### 171402.00
Total Cost from 30m upto 40m ### ###
Avg Rate per metre ### ###
12.17 B Clayey Soil (11 m dia. Well )
Unit = Running Meter
Taking output = 0.50 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.10 m/hour
a) Labour
Mate day 0.26 150.00 39.00 L-12
Sinker ( skilled ) day 2.50 125.00 312.50 L-15
Sinking helper (semi-skilled) day 4.00 120.00 480.00 L-14
b) Machinery
Hire & running charges of crane with hour 5.00 900.00 4500.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Consumables in sinking @ 10 per cent 450.00
c) of Overhead
(b) charges @ 10 % on 578.15
(a+b)
d) Contractor's profit @ 10 % on 635.97
(a+b+c)
Cost for 0.5m = a+b+c+d 6995.62
Rate per metre = (a+b+c+d)/0.50 13991.23
say ###
12.17 (ii) Beyond 3m upto 10m depth
B Rate of sinking @ 0.08 m/hour
a) Labour
Mate day 0.43 150.00 64.50 L-12
Sinker day 3.50 125.00 437.50 L-15
Sinking helper (semi-skilled) day 5.75 120.00 690.00 L-14
b) Machinery
Hire & running charges of crane with hour 6.00 900.00 5400.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Air compressor with pneumatic chisel hour 4.25 250.00 1062.50 P&M-
attachment for cutting hard clay 063
Consumables in sinking @ 10 per cent 646.25
c) of Overhead
(b) charges @ 10 % on 830.08
(a+b)
d) Contractor's profit @ 10 % on 913.08
(a+b+c)
Cost for 0.5m = a+b+c+d 10043.91
Rate per metre = (a+b+c+d)/0.50 20087.82
say ###
12.17 (iii) Beyond 10 m upto 20 m
B a Add 5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious meter @ 5 per cent of cost, if
for dewatering Including
required. for
dewatering
@ 5% of
cost, if
11th m 5% 21092.00 22147.00
12th m 5% 22147.00 23254.00
13th m 5% 23254.00 24417.00
14th m 5% 24417.00 25638.00
15th m 5% 25638.00 26920.00

Page 52 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 16th m 5% 26920.00 28266.00
17th m 5% 28266.00 29679.00
18th m 5% 29679.00 31163.00
19th m 5% 31163.00 32721.00
20th m 5% 32721.00 34357.00
Total Cost from 10m upto 20m ### 278562.00
Avg Rate per metre ### 27856.00
12.17 (iv) Beyond 20m upto 30 m
B a Add 7.5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add meter
5 per cent of cost for dewatering on
the cost, if required
c Add 25 per cent of cost for Kentledge Including Including
including supports, loading arrangement 25% for 5% for
and Labour ). Kentledge dewaterin
g, if
required
31st m 7.5% 35175.00 43969.00 46167.00
32nd 7.5% 37813.00 47266.00 49629.00
33rd m 7.5% 40649.00 50811.00 53352.00
34th m 7.5% 43698.00 54623.00 57354.00
35th m 7.5% 46975.00 58719.00 61655.00
36th m 7.5% 50498.00 63123.00 66279.00
37th m 7.5% 54285.00 67856.00 71249.00
38th m 7.5% 58356.00 72945.00 76592.00
39th m 7.5% 62733.00 78416.00 82337.00
40th m 7.5% 67438.00 84298.00 88513.00
Total Cost from 30m upto 40m ### 622026.00 ###
Avg Rate per metre ### 62203.00 ###
12.17 (v) Beyond 30m upto 40 m
B a Add 10 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add meterof cost for dewatering, if
5 per cent
c required
Add 20 per cent of cost for Kentledge Including Including
including supports, loading arrangement 20% for 5% for
and Labour). Kentledge dewaterin
g, if
required
31st m 10% 74182.00 89018.00 93469.00
32nd 10% 81600.00 97920.00 ###
33rd m 10% 89760.00 107712.00 ###
34th m 10% 98736.00 118483.00 ###
35th m 10% ### 130332.00 ###
36th m 10% ### 143365.00 ###
37th m 10% ### 157702.00 ###
38th m 10% ### 173472.00 ###
39th m 10% ### 190819.00 ###
40th m 10% ### 209902.00 ###
Total Cost from 30m upto 40m 1182271 1418725 1489662
Avg Rate per metre ### ### ###
12.17 C Soft Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.06 m/hour
a) Labour
Mate day 0.95 150.00 142.50 L-12
Sinker ( skilled ) day 4.25 125.00 531.25 L-15
Sinking helper (semi-skilled) day 18.00 120.00 2160.00 L-14
Diver day 1.50 150.00 225.00 L-07

Page 53 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. b) Machinery
Hire & running charges of crane with hour 8.00 900.00 7200.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Air compressor with pneumatic hour 4.50 250.00 1125.00 P&M-
breakers
Consumables in sinking @ 10 per cent 832.50 063
of (b)for dewatering @ 5 per cent of
Add 457.88
c) cost, if required
Overhead charges @ 10 % on 1267.41
(a+b) Contractor's profit @ 10 % on
d) 1394.15
(a+b+c)
Cost for 0.5m = a+b+c+d 15335.69
Rate per metre = (a+b+c+d)/0.50 30671.38
say ###
12.17 D Hard Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a) Material
Gelatine 80 per cent Kg 12.00 100.00 1200.00 M-104
Electric Detonators each. 48.00 5.00 240.00 M-
094/100
b) Labour
Mate day 1.35 150.00 202.50 L-12
Driller day 2.00 150.00 300.00 L-06
Blaster day 0.25 150.00 37.50 L-03
Mazdoor day 26.00 100.00 2600.00 L-13
Mazdoor (Skilled) day 4.00 125.00 500.00 L-15
c) Machinery
Hire & running charges of crane with hour 10.00 900.00 9000.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Hire & running charges of compressor hour 3.50 250.00 875.00 P&M-
with pneumatic breaker/Jack hammer or 063
drill
Dewatering @ 5 per cent of cost (c), if 493.75
required.
Consumables in sinking @ 10 per cent 1351.50
of cost of (b+c).
d) Overhead charges @ 10 % on 1680.03
(a+b+c)
e) Contractor's profit @ 10 % on 1848.03
(a+b+c+d)
Cost for 0.5m = a+b+c+d 20328.30
Rate per metre = (a+b+c+d)/0.50 40656.61
say ###
12.18 1200 Sinking of 12 m external diameter well
( other than pneumatic method of
sinking ) through all types of strata
namely sandy soil, clayey soil and rock
as shown against each case, complete
as per drawing and technical
specifications. Depth of sinking is
Unit = Running Meter
Taking output = 0.25 m
Diameter of well - 12 m.
A Sandy Soil
(i) I) Depth below bed level upto 3.0 M
Rate of sinking @ 0.05 m/hour
a) Labour
Mate day 0.22 150.00 33.00 L-12
Sinker ( skilled ) day 1.75 125.00 218.75 L-15
Sinking helper (semi-skilled) day 4.00 120.00 480.00 L-14
b) Machinery
Hire & running charges of crane with hour 6.00 900.00 5400.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories. in sinking @10 per cent
Consumables 540.00
of (b)
Page 54 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. c) Overhead charges @ 10 % on 667.18
(a+b)
d) Contractor's profit @ 10 % on 733.89
(a+b+c)
Cost for 0.25m = a+b+c+d 8072.82
Rate per metre = (a+b+c+d)/0.25 32291.27
say ###
12.18 (ii) Beyond 3m upto 10m depth
A Rate of sinking @ 0.038 m/hour
a) Labour
Mate day 0.37 150.00 55.50 L-12
Sinker day 2.50 125.00 312.50 L-15
Sinking helper (semi-skilled) day 4.75 120.00 570.00 L-14
b) Machinery
Hire & running charges of crane with hour 6.50 900.00 5850.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories. in sinking @10 per cent of
Consumables 585.00
c) (b)Overhead charges @ 10 % on 737.30
(a+b) Contractor's profit @ 10 % on
d) 811.03
(a+b+c)
Cost for 0.25m = a+b+c+d 8921.33
Rate per metre = (a+b+c+d)/0.25 35685.32
say ###
12.18 (iii) Beyond 10m upto 20m
A a Add 5 per cent for every additional meter
depth of sinking over the rate of sinking for
the previous
11th m meter 5% 37469.00
12th m 5% 39342.00
13th m 5% 41309.10
14th m 5% 43374.56
15th m 5% 45543.28
16th m 5% 47820.45
17th m 5% 50211.47
18th m 5% 52722.04
19th m 5% 55358.14
20th m 5% 58126.05
Total Cost from 10m upto 20m ###
Avg Rate per metre ###
12.18 (iv) Beyond 20m upto 30 m
A a Add 7.5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious
20 per meter
cent of cost for Kentledge Including
including supports, loading arrangement 20% for
and 21st
Labour.
m 7.5% 62486.00 Kentledge
74983.00
22nd m 7.5% 67172.00 80606.00
23rd m 7.5% 72210.00 86652.00
24th m 7.5% 77626.00 93151.00
25th m 7.5% 83448.00 100138.00
26th m 7.5% 89707.00 107648.00
27th m 7.5% 96435.00 115722.00
28th m 7.5% ### 124402.00
29th m 7.5% ### 133732.00
30th m 7.5% ### 143761.00
Total Cost from 20m upto 30m ### ###
Avg Rate per metre ### ###
12.18 (v) Beyond 30m upto 40 m
A a Add 10 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious
20 per meter
cent of cost for Kentledge Including
including supports, loading arrangement, 20% for
and 31st
Labour
m etc. 10% Kentledge
### 158137.00

Page 55 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 32nd 10% ### 173951.00
33rd m 10% ### 191346.00
34th m 10% ### 210481.00
35th m 10% ### 231529.00
36th m 10% ### 254682.00
37th m 10% ### 280151.00
38th m 10% ### 308166.00
39th m 10% ### 338983.00
40th m 10% ### 372882.00
Total Cost from 30m upto 40m 2100257 2520308
Avg Rate per metre ### ###
12.18 B Clayey Soil (12 m dia. Well )
Unit = Running Meter.
Taking output = 0.25 meter.
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.04 m/hour
a) Labour
Mate day 0.30 150.00 45.00 L-12
Sinker ( skilled ) day 3.00 125.00 375.00 L-15
Sinking helper (semi-skilled) day 4.50 120.00 540.00 L-14
b) Machinery
Hire & running charges of crane with hour 6.25 900.00 5625.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Consumables in sinking @ 10 per cent 562.50
c) of Overhead
(b) charges @ 10 % on 714.75
(a+b)
d) Contractor's profit @ 10 % on 786.23
(a+b+c)
Cost for 0.25m = a+b+c+d 8648.48
Rate per metre = (a+b+c+d)/0.25 34593.90
say ###
12.18 (ii) Beyond 3m upto 10m depth
B Rate of sinking @ 0.03 m/hour
a) Labour
Mate day 0.48 150.00 72.00 L-12
Sinker day 3.75 125.00 468.75 L-15
Sinking helper (semi-skilled) day 6.00 120.00 720.00 L-14
b) Machinery
Hire & running charges of crane with hour 8.33 900.00 7497.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Air compressor with pneumatic chisel hour 4.50 250.00 1125.00 P&M-
attachment for cutting hard clay. 063
Consumables in sinking @ 10 per cent 862.20
c) of Overhead
(b) charges @ 10 % on 1074.50
(a+b)
d) Contractor's profit @ 10 % on 1181.94
(a+b+c)
Cost for 0.25m = a+b+c+d 13001.39
Rate per metre = (a+b+c+d)/0.25 52005.56
say ###
12.18 (iii) Beyond 10 m upto 20 m
B a Add 5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious meter @ 5 per cent of cost, if
for dewatering Including
required. for
dewatering
@ 5% of
cost, if
11th m 5% 54606.00 57336.00
12th m 5% 57336.00 60203.00
13th m 5% 60203.00 63213.00
14th m 5% 63213.00 66374.00
15th m 5% 66374.00 69693.00

Page 56 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 16th m 5% 69693.00 73178.00
17th m 5% 73178.00 76837.00
18th m 5% 76837.00 80679.00
19th m 5% 80679.00 84713.00
20th m 5% 84713.00 88949.00
Total Cost from 10m upto 20m ### 721175.00
Avg Rate per metre ### 72118.00
12.18 (iv) Beyond 20m upto 30 m
B a Add 7.5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add meter
5 per cent of cost for dewatering on
the cost, if required
c Add 25 per cent of cost for Kentledge Including Including
including supports, loading arrangement 25% for 5% for
and Labour ). Kentledge dewaterin
g, if
required
31st m 7.5% 91066.00 113833.00 ###
32nd 7.5% 97896.00 122370.00 ###
33rd m 7.5% ### 131548.00 ###
34th m 7.5% ### 141414.00 ###
35th m 7.5% ### 152020.00 ###
36th m 7.5% ### 163421.00 ###
37th m 7.5% ### 175678.00 ###
38th m 7.5% ### 188854.00 ###
39th m 7.5% ### 203018.00 ###
40th m 7.5% ### 218244.00 ###
Total Cost from 30m upto 40m 1288318 1610400 1690921
Avg Rate per metre ### ### ###
12.18 (v) Beyond 30m upto 40 m
B a Add 10 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add meterof cost for dewatering, if
5 per cent
c required
Add 20 per cent of cost for Kentledge Including Including
including supports, loading arrangement 20% for 5% for
and Labour). Kentledge dewaterin
g, if
required
31st m 10% ### 230466.00 ###
32nd 10% ### 253513.00 ###
33rd m 10% ### 278864.00 ###
34th m 10% ### 306751.00 ###
35th m 10% ### 337427.00 ###
36th m 10% ### 371170.00 ###
37th m 10% ### 408287.00 ###
38th m 10% ### 449116.00 ###
39th m 10% ### 494027.00 ###
40th m 10% ### 543430.00 ###
Total Cost from 30m upto 40m 3060875 3673051 3856704
Avg Rate per metre ### ### ###
12.18 C Soft Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a) Labour
Mate day 1.06 150.00 159.00 L-12
Sinker ( skilled ) day 4.50 125.00 562.50 L-15
Sinking helper (semi-skilled) day 20.00 120.00 2400.00 L-14
Diver day 1.75 150.00 262.50 L-07

Page 57 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. b) Machinery
Hire & running charges of crane with hour 10.00 900.00 9000.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Air compressor with pneumatic chisel hour 4.75 250.00 1187.50 P&M-
attachment for cutting hard clay. 063
Consumables in sinking @ 10 per cent 1018.75
of
Add(b)for dewatering @ 5 per cent, if 560.31
c) required
Overhead charges @ 10 % on 1515.06
(a+b)
d) Contractor's profit @ 10 % on 1666.56
(a+b+c)
Cost for 0.25m = a+b+c+d 18332.18
Rate per metre = (a+b+c+d)/0.25 73328.72
say ###
12.18 D Hard Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
(i) Depth in hard rock strata upto 3 m
Rate of sinking @ 0.020 m/hour
a) Material
Gelatine80 per cent Kg 14.00 100.00 1400.00 M-104
Electric detonator each. 56.00 5.00 280.00 M-
094/100
b) Labour
Mate day 1.44 150.00 216.00 L-12
Driller day 2.00 150.00 300.00 L-06
Blaster day 0.25 150.00 37.50 L-03
Mazdoor day 28.00 100.00 2800.00 L-13
Mazdoor (Skilled) day 4.50 125.00 562.50 L-15
c) Machinery
Hire & running charges of crane with hour 12.50 900.00 11250.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Hire & running charges of compressor hour 4.00 250.00 1000.00 P&M-
with pneumatic breaker/Jack hammer or 063
drill
Dewatering @ 5 per cent, if required. 612.50
Consumables in sinking @ 10 per cent 1286.25
d) of (c).
Overhead charges @ 10 % on 1974.48
(a+b+c)
e) Contractor's profit @ 10 % on 2171.92
(a+b+c+d)
Cost for 0.25m = a+b+c+d+e 23891.15
Rate per metre = (a+b+c+d+e)/0.25 95564.59
say ###
12.19 1200 Sinking of Twin D Type well (other
than pneumatic method of sinking)
through all types of strata namely
sandy soil, clayey soil and rock as
shown against each case, complete as
per drawing and technical
specifications. Depth of sinking is
Unit = Running Meter
Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.20 150.00 30.00 L-12
Sinker ( skilled ) day 1.25 125.00 156.25 L-15
Sinking helper (semi-skilled) day 3.75 120.00 450.00 L-14
b) Machinery

Page 58 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Hire & running charges of crane with hour 5.50 900.00 4950.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories. in sinking @10 per cent
Consumables 495.00
c) of Overhead
(b) charges @ 10 % on 608.13
(a+b) Contractor's profit @ 10 % on
d) 668.94
(a+b+c)
Rate per metre = (a+b+c+d) 7358.31
say 7358.00
12.19 (ii) Beyond 3m upto 10m depth
A Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.30 150.00 45.00 L-12
Sinker day 1.50 125.00 187.50 L-15
Sinking helper (semi-skilled) day 4.00 120.00 480.00 L-14
b) Machinery
Hire & running charges of crane with hour 5.88 900.00 5292.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Consumables in sinking @10 per cent of 529.20
c) (b)Overhead charges @ 10 % on 653.37
(a+b)
d) Contractor's profit @ 10 % on 718.71
(a+b+c)
Rate per metre = (a+b+c+d) 7905.78
say 7906.00
12.19 (iii) Beyond 10m upto 20m
A a Add 5 per cent for every additional meter
depth of sinking over the rate of sinking for
the previous
11th m meter 5% 8301.00
12th m 5% 8716.00
13th m 5% 9152.00
14th m 5% 9610.00
15th m 5% 10091.00
16th m 5% 10596.00
17th m 5% 11126.00
18th m 5% 11682.00
19th m 5% 12266.00
20th m 5% 12879.00
Total Cost from 10m upto 20m ###
Avg Rate per metre ###
12.19 (iv) Beyond 20m upto 30 m
A a Add 7.5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious
20 per meter
cent of cost for Kentledge Including
including supports, loading arrangement 20% for
and 21st
Labour.
m 7.5% 13845.00 Kentledge
16614.00
22nd m 7.5% 14883.00 17860.00
23rd m 7.5% 15999.00 19199.00
24th m 7.5% 17199.00 20639.00
25th m 7.5% 18489.00 22187.00
26th m 7.5% 19876.00 23851.00
27th m 7.5% 21367.00 25640.00
28th m 7.5% 22970.00 27564.00
29th m 7.5% 24693.00 29632.00
30th m 7.5% 26545.00 31854.00
Total Cost from 20m upto 30m ### 235040.00
Avg Rate per metre ### 23504.00
12.19 (v) Beyond 30m upto 40 m
A a Add 10 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add 20 per meter
cent of cost for Kentledge Including
including supports, loading arrangement, 20% for
and Labour etc. Kentledge

Page 59 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 31st m 10% 29200.00 35040.00
32nd 10% 32120.00 38544.00
33rd m 10% 35332.00 42398.00
34th m 10% 38865.00 46638.00
35th m 10% 42752.00 51302.00
36th m 10% 47027.00 56432.00
37th m 10% 51730.00 62076.00
38th m 10% 56903.00 68284.00
39th m 10% 62593.00 75112.00
40th m 10% 68852.00 82622.00
Total Cost from 30m upto 40m ### 558448.00
Avg Rate per metre ### 55845.00
12.19 B Clayey Soil (Twin D Type Well )
Unit = Running Meter
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.16 m/hour
a) Labour
Mate day 0.26 150.00 39.00 L-12
Sinker ( skilled ) day 2.50 125.00 312.50 L-15
Sinking helper (semi-skilled) day 4.00 120.00 480.00 L-14
b) Machinery
Hire & running charges of crane with hour 6.25 900.00 5625.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Consumables in sinking @ 10 per cent 562.50
c) of Overhead
(b) charges @ 10 % on 701.90
(a+b)
d) Contractor's profit @ 10 % on 772.09
(a+b+c)
Rate per metre = (a+b+c+d) 8492.99
say 8493.00
12.19 (ii) Beyond 3m upto 10m depth
B Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.45 150.00 67.50 L-12
Sinker day 3.25 125.00 406.25 L-15
Sinking helper (semi-skilled) day 6.00 120.00 720.00 L-14
b) Machinery
Hire & running charges of crane with hour 6.67 900.00 6003.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Air compressor with pneumatic chisel hour 4.50 250.00 1125.00 P&M-
attachment for cutting hard clay. 063
Consumables in sinking @ 10 per cent 712.80
c) of Overhead
(b) charges @ 10 % on 903.46
(a+b)
d) Contractor's profit @ 10 % on 993.80
(a+b+c)
Rate per metre = (a+b+c+d) 10931.81
say ###
12.19 (iii) Beyond 10 m upto 20 m
B a Add 5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the
Addprevious meter @ 5 per cent of cost, if
for dewatering Including
required. for
dewatering
@ 5% of
cost, if
11th m 5% 11478.00 12052.00
12th m 5% 12052.00 12655.00
13th m 5% 12655.00 13288.00
14th m 5% 13288.00 13952.00
15th m 5% 13952.00 14650.00
16th m 5% 14650.00 15383.00

Page 60 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. 17th m 5% 15383.00 16152.00
18th m 5% 16152.00 16960.00
19th m 5% 16960.00 17808.00
20th m 5% 17808.00 18698.00
Total Cost from 10m upto 20m ### 151598.00
Avg Rate per metre ### 15160.00
12.19 (iv) Beyond 20m upto 30 m
B a Add 7.5 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add meter
5 per cent of cost for dewatering on
the cost, if required
c Add 25 per cent of cost for Kentledge Including Including
including supports, loading arrangement 25% for 5% for
and Labour ). Kentledge dewaterin
g, if
required
31st m 7.5% 19144.00 23930.00 25127.00
32nd 7.5% 20580.00 25725.00 27011.00
33rd m 7.5% 22124.00 27655.00 29038.00
34th m 7.5% 23783.00 29729.00 31215.00
35th m 7.5% 25567.00 31959.00 33557.00
36th m 7.5% 27485.00 34356.00 36074.00
37th m 7.5% 29546.00 36933.00 38780.00
38th m 7.5% 31762.00 39703.00 41688.00
39th m 7.5% 34144.00 42680.00 44814.00
40th m 7.5% 36705.00 45881.00 48175.00
Total Cost from 30m upto 40m ### 338551.00 ###
Avg Rate per metre ### 33855.00 ###
12.19 (v) Beyond 30m upto 40 m
B a Add 10 per cent for every additional meter
depth of sinking over the rate of sinking for
b the previous
Add meterof cost for dewatering, if
5 per cent
c required
Add 20 per cent of cost for Kentledge Including Including
including supports, loading arrangement 20% for 5% for
and Labour). Kentledge dewaterin
g, if
required
31st m 10% 40376.00 48451.00 50874.00
32nd 10% 44414.00 53297.00 55962.00
33rd m 10% 48855.00 58626.00 61557.00
34th m 10% 53741.00 64489.00 67713.00
35th m 10% 59115.00 70938.00 74485.00
36th m 10% 65027.00 78032.00 81934.00
37th m 10% 71530.00 85836.00 90128.00
38th m 10% 78683.00 94420.00 99141.00
39th m 10% 86551.00 103861.00 ###
40th m 10% 95206.00 114247.00 ###
Total Cost from 30m upto 40m ### 772197.00 ###
Avg Rate per metre ### 77220.00 ###
12.19 C Soft Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a) Labour
Mate day 0.86 150.00 129.00 L-12
Sinker ( skilled ) day 4.50 125.00 562.50 L-15
Sinking helper (semi-skilled) day 15.00 120.00 1800.00 L-14
Diver day 1.50 150.00 225.00 L-07
b) Machinery

Page 61 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Hire & running charges of crane with hour 8.33 900.00 7497.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Air compressor with pneumatic hour 6.00 250.00 1500.00 P&M-
breakers
Consumables in sinking @ 10 per cent 899.70 063
of (b)for dewatering @ 5 per cent, if
Add 494.84
c) required
Overhead charges @ 10 % on 1310.80
(a+b) Contractor's profit @ 10 % on
d) 1441.88
(a+b+c)
Rate per metre = (a+b+c+d) 15860.72
say ###
12.19 D Hard Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a) Material
Geletine80 per cent Kg 10.00 100.00 1000.00 M-104
Electric detonators each. 40.00 5.00 200.00 M-
094/100
b) Labour
Mate day 1.34 150.00 201.00 L-12
Driller day 2.00 150.00 300.00 L-06
Blaster day 0.25 150.00 37.50 L-03
Mazdoor day 25.00 100.00 2500.00 L-13
Mazdoor (Skilled) day 4.25 125.00 531.25 L-15
c) Machinery
Hire & running charges of crane with hour 10.00 900.00 9000.00 P&M-
grab bucket of 0.75 cum capacity and 075
accessories.
Hire & running charges of compressor hour 3.00 250.00 750.00 P&M-
with pneumatic breaker/Jack hammer or 063
drill
Dewatering @ 5 per cent of cost of 665.99
(b+c), if required.
Consumables in sinking @ 10 per cent 1041.60
d) of (b).
Overhead charges @ 10 % on 1622.73
(a+b+c)
e) Contractor's profit @ 10 % on 1785.01
(a+b+c+d)
Rate per metre = (a+b+c+d+e) 19635.08
say ###
12.20 1200 Pneumatic sinking of wells with
equipment of approved design,
drawing and specifications worked by
competent and trained personnel and
comprising of compression and
decompression chambers, reducers,
two air locks separately for men and
plant & materials, arrangement for
supply of fresh air to working
chambers, check valves, exhaust
valves, shafts made from steel plates
of riveted construction not less than 6
mm thick to withstand an air pressure
of 0.50 MPa, controlled blasting of
hard rock where required, staircases
and 1 m wide landing plateforms with
railing, arrangement for compression
and decompression, electric lighting of
50 V maximum, proper rooms for rest
and medical examinations and
Unit - 1 cum
Taking output = 5 cum
a) Material
M35 grade RCC corbel provided for Cum 8.00 3295.00 26360.00 Item
supporting of equipment (Dimensions 12.8 (H)
as per ground conditions). Rate may be
adopted vide Item 12.8 (H)
HYSD bar reinforcement in corbel tonne 0.48 34500.00 16560.00 M-082

Page 62 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Blasting material
Gelatine 80 per cent Kg 1.50 100.00 150.00 M-104
Electric detonators each 6.00 5.00 30.00 M-
094/100
b) Labour
Medical Officer day 0.50 500.00 250.00 L-16
Para medical personnel day 1.00 250.00 250.00 L-19
Mate day 1.86 150.00 279.00 L-12
Driller day 1.00 150.00 150.00 L-06
Blaster day 0.50 150.00 75.00 L-03
Mazdoor (for cutting, blasting, cleaning, day 30.00 100.00 3000.00 L-13
removal of Material etc.)
Mazdoor (Skilled) (for fixation and day 10.00 125.00 1250.00 L-15
removal of adopter for air lock, carrying
out mechanical and electrical
operations and repairs and other skilled
jobs.)
Diver day 4.00 150.00 600.00 L-07
c) Machinery
(i) Induction, deinduction and hour 6.00 5000.00 30000.00 P&M-
erection of plant and equipment 082
including all components and
accessories for pneumatic method
of well sinking.
Induction and deinduction L.S ###
Erection at site and commissioning L.S ###
Usage of plant and equipment for hour 6.00 2500.00 15000.00 P&M-
pneumatic method of well sinking 038
Air compressor 250 cfm, 2 nos. hour 2x6 150.00 1800.00 P&M-
Hire and running charges of crane of 15 hour 6.00 400.00 2400.00 001
P&M-
tonne capacity 072
Motorised barge of 20 tonne capacity hour 6.00 1500.00 9000.00 P&M-
Boat to carry atleast 20 persons hour 6.00 1500.00 9000.00 066
P&M-
Electric generating set 33 KVA hour 6.00 400.00 2400.00 066
P&M-
Tipper 10 tonne capacity hour 6.00 185.00 1110.00 079
P&M-
d) Overhead charges @ 10 % on 34330.40 048
(a+b+c)
e) Contractor's profit @ 10 % on 37763.44
(a+b+c+d)
Cost for 5 cum = a+b+c+d+e (see notes
below)
Rate per cum = (a+b+c+d+e)/5
Note 1.The cost of induction, deinduction and
erection of equipment shall be divided by
the total quantity of pneumatic sinking for
all the wells of a particular bridge to arrive
at the per cum rate on account of this item.
2.Cost of pneumatic sinking per cum of
individual wells will be added to the cost
indicated at (1) above to arrive at the final
rate of pneumatic sinking per cum.
3.The cost of induction and deinduction will
depend upon the distance involved for
shifting of equipment which may be
assessed in individual cases as per actual
ground conditions at the time of making of
cost estimates.
4.In case pneumatic sinking is involved on a
dry bed, the provision of barge and boat
may be
5.The omitted.and dimensions of the
necessity
corbel will be as per actual ground
conditions.
6.Small equipments like welding sets,
pumps, vibrators, pneumatic tools, portable
lamps, fire extinguishers, hose pipes etc.,
have not been included as the same are
covered as items of minor T&P under
overhead charges.
7.Depth of sinking shall be restricted to 30
12.21 1207 m.
Sand Filling in Wells complete as per
Drawing and Technical Specifications.

Page 63 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Unit = 1 cum
Taking output = 1 cum
a) Material
Sand (assuming 20 per cent voids ) cum 1.20 300.00 360.00 M-006
b) Labour
Mate day 0.01 150.00 1.50 L-12
Mazdoor day 0.30 100.00 30.00 L-13
c) Overhead charges @ 10 % on 39.15
(a+b)
d) Contractor's profit @ 10 % on 43.07
(a+b+c)
Rate per cum (a+b+c+d) 473.72
say 474.00
12.22 1200 Providing Steel Liner 10 mm thick for
& Curbs and 6 mm thick for Steining of
1900 Wells including Fabricating and Setting
out as per Detailed Drawing.
Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent tonne 1.05 32000.00 33600.00 M-179
b) wastage
Labour
Mate day 1.24 150.00 186.00 L-12
Fitter day 6.00 150.00 900.00 L-08
Blacksmith day 5.00 130.00 650.00 L-01
Welder day 5.00 150.00 750.00 L-02
Mazdoor day 10.00 100.00 1000.00 L-13
Electrodes, cutting gas and other 1680.00
consumables @ 5 per cent on cost a (a)
c) above.
Overhead charges @ 10 % on 3876.60
(a+b)
d) Contractor's profit @ 10 % on 4264.26
(a+b+c)
Rate for per MT (a+b+c+d) 46906.86
say ###
12.23 1100 Bored cast-in-situ M35 grade R.C.C.
& Pile excluding Reinforcement complete
1700 as per Drawing and Technical
Specifications and removal of
excavated earth with all lifts and lead
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a) Materials
PCC Grade M35 cum 6.62 3308.00 21898.96 Item
12.11
Rate for concrete may be adopted same as (C) iv
for bottom plug vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe
200mm
b) dia.
Machinery( for boring and
construction )
Hire and running charges of hydraulic hour 6.00 3500.00 21000.00 P&M-
piling rig with power unit and complete 036
accessories including shifting from one
bore location to another.
Hire and running charges of light crane hour 0.50 225.00 112.50 P&M-
for lowering reinforcement cage 013
Hire and running charges of Bentonite hour 6.00 Rate
pump included in
Loader I cum bucket capacity. hour 0.30 piling rig
700.00 210.00 P&M-
Tipper 5.5 cum capacity for disposal of hour 0.30 185.00 55.50 017
P&M-
muck from pile bore hole 048
Bentonite kg 300.00 15.00 4500.00 M-071
c) Labour
Mate/Supervisor day 0.14 150.00 21.00 L-12
Mazdoor day 3.50 100.00 350.00 L-13

Page 64 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. d) Overhead charges @ 10 % on 2624.90
(b+c)
e) Contractor's profit @ 10 % on 2887.39
(b+c+d)
Cost for 15 m = a+b+c+d+d+e 53660.25
Rate per metre (a+b+c+d+e)/15 3577.35
say 3577.00
12.24 Bored cast-in-situ M35 grade R.C.C.
1100, Pile excluding Reinforcement complete
1600 as per Drawing and Technical
& Specifications and removal of
1700 excavated earth with all lifts and lead
Pile diameter-1000 mm
Unit = meter
Taking output = 10 m
a) Materials
PCC Grade M35 cum 7.85 3308.00 25967.80 Item
12.11
Rate for concrete may be adopted (C) iv
same as for bottom plug vide item no.
12.11( C to
Concrete ) (IV)
be cast with a tremie pipe
200mm
b) dia.
Machinery( for boring and
construction )
Hire and running charges of hydraulic hour 6.00 3500.00 21000.00 P&M-
piling rig with power unit and complete 036
accessories including shifting from one
bore location to another.
Hire and running charges of light crane hour 0.50 225.00 112.50 P&M-
for lowering reinforcement cage 013
Hire and running charges of Bentonite hour 6.00 Rate
pump included in
Loader I cum bucket capacity. hour 0.40 piling rig
700.00 280.00 P&M-
Tipper 5.5 cum capacity for disposal of hour 0.40 185.00 74.00 017
P&M-
muck from pile bore hole 048
Bentonite kg 350.00 15.00 5250.00 M-071
c) Labour
Mate/Supervisor day 0.16 150.00 24.00 L-12
Mazdoor day 4.00 100.00 400.00 L-13
d) Overhead charges @ 10 % on 2714.05
(b+c)
e) Contractor's profit @ 10 % on 2985.46
(b+c+d)
Cost for 10 m = a+b+c+d+d+e 58807.81
Rate per metre (a+b+c+d+e)/10 5880.78
say 5881.00
12.25 1100 Bored cast-in-situ M35 grade R.C.C.
& Pile excluding Reinforcement complete
1700 as per Drawing and Technical
Specifications and removal of
excavated earth with all lifts and lead
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a) Materials
PCC Grade M35 cum 10.17 3308.00 33642.36 Item
12.11
Rate for concrete may be adopted same as (C) iv
for bottom plug vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe
200mm
b) dia.
Machinery( for boring and
construction )
Hire and running charges of hydraulic hour 6.00 3500.00 21000.00 P&M-
piling rig with power unit and complete 036
accessories including shifting from one
bore location to another.
Hire and running charges of light crane hour 0.50 225.00 112.50 P&M-
for lowering reinforcement cage 013
Hire and running charges of Bentonite hour 6.00 Rate
pump included in
Loader I cum bucket capacity. hour 0.50 piling rig
700.00 350.00 P&M-
017

Page 65 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Tipper 5.5 cum capacity for disposal of hour 0.50 185.00 92.50 P&M-
muck from pile bore hole 048
Bentonite kg 385.00 15.00 5775.00 M-071
c) Labour
Mate/Supervisor day 0.18 150.00 27.00 L-12
Mazdoor day 4.50 100.00 450.00 L-13
d) Overhead charges @ 10 % on 2780.70
(b+c) Contractor's profit @ 10 % on
e) 3058.77
(b+c+d)
Cost for 9 m = a+b+c+d+d+e 67288.83
Rate per metre (a+b+c+d+e)/9 7476.54
say 7477.00
12.26 1100 Driven cast-in-place vertical M35 grade
& R.C.C. Pile excluding Reinforcement
1700 complete as per Drawing and &
Technical Specification
Pile diameter - 750 mm
Unit = Running meter
Taking output = 40 metre
a) Materials
PCC Grade M35 cum 17.66 3308.00 58419.28 Item
12.11
Rate for concrete may be adopted same as (C) iv
for bottom plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.00 40.00 6400.00 M-080
ii) M.S. clamps for shoe @ 35 Kg per Kg 70.00 35.00 2450.00 M-124
pile of 15helmet
iii) Steel m and cushion block on Kg 50.00 45.00 2250.00 M-173
top of casing head during driving
c) Machinery
Hire and running charges of piling rig hour 6.00 3000.00 18000.00 P&M-
Including double acting pile driving 085
hammer complete with power unit and
accessories..
Hiring and running charges for light hour 0.50 250.00 125.00 P&M-
crane 5 tonnes lifting capacity for 070
lowering reinforcement and handling
steel casing.
d) Labour
Mate/Supervisor day 0.12 150.00 18.00 L-12
Mazdoor day 3.00 100.00 300.00 L-13
e) Overhead charges @ 10 % on 2954.30
(b+c+d)
f) Contractor's profit @ 10 % on 3249.73
(b+c+d+e)
Cost for 40 m = a+b+c+d+e 94166.31
Rate per metre (a+b+c+d+e)/40 2354.16
say 2354.00
Note 1.The quantity of concrete required to be
removed above the designed top level of
concrete, if any, will be provided for in the
rate analysis.
2.In case steel lining is included in the
design for driven cast-in-situ pile and is
planned to be retained, the same may be
included in the rate analysis. In case the
temporary steel casing used during casting
is planned to be removed, an additional
cost @ 0.50 per cent of cost of concrete
12.27 1100 Driven cast-in-place vertical M35 grade
& R.C.C. Pile excluding Reinforcement
1700 complete as per Drawing and &
Technical Specification
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
a) Materials
PCC Grade M35 cum 23.55 3308.00 77903.40 Item
12.11
(C) iv

Page 66 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Rate for concrete may be adopted
same as for bottom plug vide item no.
12.11(
b) C ) (IV) Pile shoes
Materials
i) C.I. shoes for the pile Kg 160.00 40.00 6400.00 M-080
ii) M.S. clamps for shoe @ 35 Kg per Kg 70.00 35.00 2450.00 M-124
pileSteel
iii) of 15helmet
m and cushion block on Kg 50.00 45.00 2250.00 M-173
top of casing head during driving
c) Machinery
Hire and running charges of piling rig hour 6.00 3000.00 18000.00 P&M-
Including double acting pile driving 085
hammer complete with power unit and
accessories.
Hiring and running charges for light hour 0.50 250.00 125.00 P&M-
crane 5 tonnes lifting capacity for 070
lowering reinforcement and handling
steel casing.
Hire and running charges for light crane hour 0.50 225.00 112.50 P&M-
for lowering reinforcement cage. 013
d) Labour
Mate/Supervisor day 0.16 150.00 24.00 L-12
Mazdoor day 4.00 100.00 400.00 L-13
e) Overhead charges @ 10 % on 2976.15
(b+c+d)
f) Contractor's profit @ 10 % on 3273.77
(b+c+d+e)
Cost for 30 m = a+b+c+d+e ###
Rate per metre (a+b+c+d+e)/30 3797.16
say 3797.00
Note 1.The quantity of concrete required to be
removed above the designed top level of
concrete, if any, will be provided for in the
rate analysis.
2.In case steel lining is included in the
design for driven cast-in-situ pile and is
planned to be retained, the same may be
included in the rate analysis. In case the
temporary steel casing used during casting
is planned to be removed, an additional
cost @ 0.50 per cent of cost of concrete
12.28 1100 Driven cast-in-place vertical M35 grade
& R.C.C. Pile excluding Reinforcement
1700 complete as per Drawing and &
Technical Specification
Pile diameter - 1200 mm
Unit = Running meter
Taking output = 20 metre
a) Materials
PCC Grade M35 cum 22.61 3308.00 74793.88 Item
12.11
Rate for concrete may be adopted (C) iv
same as for bottom plug vide item no.
12.11(
b) C ) (IV) Pile shoes
Materials
i) C.I. shoes for the pile Kg 160.00 40.00 6400.00 M-080
ii) M.S. clamps for shoe @ 35 Kg per Kg 70.00 35.00 2450.00 M-124
pile of 15helmet
iii) Steel m on top of casing head Kg 50.00 45.00 2250.00 M-173
during driving
c) Machinery
Hire and running charges of piling rig hour 6.00 3000.00 18000.00 P&M-
Including double acting pile driving 085
hammer complete with power unit and
accessories.
Hiring and running charges for light hour 0.50 250.00 125.00 P&M-
crane 5 tonnes lifting capacity for 070
lowering reinforcement and handling
steel casing.
d) Labour
Mate/Supervisor day 0.18 150.00 27.00 L-12
Mazdoor day 4.50 100.00 450.00 L-13
e) Overhead charges @ 10 % on 2970.20
(b+c+d)
f) Contractor's profit @ 10 % on 3267.22
(b+c+d+e)

Page 67 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Cost for 20 m = a+b+c+d+e ###
Rate per metre (a+b+c+d+e)/20 5536.67
say 5537.00
Note 1.The quantity of concrete required to be
removed above the designed top level of
concrete, if any, will be provided for in the
rate analysis.
2.In case steel lining is included in the
design for driven cast-in-situ pile and is
planned to be retained, the same may be
included in the rate analysis. In case the
temporary steel casing used during casting
is planned to be removed, an additional
cost @ 0.50 per cent of cost of concrete
12.29 1100 Driven precast vertical M35 grade
& R.C.C. Piles excluding Reinforcement
1700 complete as per Drawing and &
Technical Specification
Pile Diameter = 500 mm
Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M35 cum 11.78 3190.00 37578.20 Item
12.11
Rate for concrete may be adopted same (F) iv
as for bottom plug vide item no.
12.11( F )Pile
b ) Material (IV) shoes
a) C.I Shoes Kg 240.00 40.00 9600.00 M-080
b) M.S. shoes Kg 105.00 35.00 3675.00 M-125
c) Steel helmet and cushion block on Kg 30.00 45.00 1350.00 M-173
top of pile head during driving.
c) Machinery
Crane20 t capacity hour 6.00 475.00 2850.00 P&M-
Vibrating Pile driving hammer complete hour 6.00 550.00 3300.00 073
P&M-
with power unit and accessories. 092
d) Labour
Mate/Supervisor day 0.12 150.00 18.00 L-12
Mazdoor day 3.00 100.00 300.00 L-13
Add 1 per cent of (a+b+c) for 586.71
carriage of piles from casting yard to
work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 10 % on 2167.97
(b+c+d)
f) Contractor's profit @ 10 % on 2384.77
(b+c+d+e)
Cost for 60 m = a+b+c+d+e+f 63810.65
Rate per metre (a+b+c+d+e+f)/60 1063.51
say 1064.00
Note The quantity of concrete required to be
removed above the designed top level of
concrete, if any, will be provided for in the
rate analysis.
12.30 1100 Driven precast vertical M35 grade
& R.C.C. Piles excluding Reinforcement
1700 complete as per Drawing and &
Technical Specification
Pile Diameter = 750 mm
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M35 cum 22.08 3190.00 70435.20 Item
12.11
Rate for concrete may be adopted same (F) iv
as for bottom plug vide item no.
12.11( F )Pile
b ) Material (IV) shoes
a) C.I. shoes Kg 160.00 40.00 6400.00 M-080
b) M.S. shoes Kg 70.00 35.00 2450.00 M-125

Page 68 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. c) Steel helmet and cushion block on Kg 40.00 45.00 1800.00 M-173
top of pile head during driving.
c) Machinery
Crane 40 T capacity hour 6.00 525.00 3150.00 P&M-
Vibrating Pile driving hammer complete hour 6.00 550.00 3300.00 074
P&M-
with power unit and accessories. 092
d) Labour
Mate/Supervisor day 0.16 150.00 24.00 L-12
Mazdoor day 4.00 100.00 400.00 L-13
Add 1 per cent of (a+b+c) for 879.59
carriage of piles from casting yard to
work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 10 % on 1840.36
(b+c+d)
f) Contractor's profit @ 10 % on 2024.40
(b+c+d+e)
Cost for 50 m = a+b+c+d+e+f 92703.55
Rate per metre (a+b+c+d+e+f)/50 1854.07
say 1854.00
Note The quantity of concrete required to be
removed above the designed top level of
concrete, if any, will be provided for in the
rate analysis.
12.31 1100 Driven precast vertical M35 grade
& R.C.C. Piles excluding Reinforcement
1700 complete as per Drawing and &
Technical Specification
Pile Diameter = 1000 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M35 cum 31.40 3190.00 ### Item
12.11
Rate for concrete may be adopted same (F) iv
as for bottom plug vide item no.
12.11( F )Pile
b ) Material (IV) shoes
a) C.I. shoes for the pile Kg 160.00 40.00 6400.00 M-080
b) M.S. shoes @ 35 Kg per pile of 15 m Kg 70.00 35.00 2450.00 M-125
c) Steel helmet and cushion block on Kg 50.00 45.00 2250.00 M-173
top of pile head during driving.
c) Machinery
Crane 50 t capacity. hour 6.00 800.00 4800.00 P&M-
Vibrating Pile driving hammer complete hour 6.00 550.00 3300.00 011
P&M-
with power unit and accessories. 092
d) Labour
Mate/Supervisor day 0.20 150.00 30.00 L-12
Mazdoor day 5.00 100.00 500.00 L-13
Add 1 per cent of (a+b+c) for 1198.96
carriage of piles from casting yard to
work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 10 % on 2092.90
(b+c+d)
f) Contractor's profit @ 10 % on 2302.19
(b+c+d+e)
Cost for 40 m = a+b+c+d+e+f ###
Rate per metre (a+b+c+d+e+f)/40 3137.25
say 3137.00
Note The quantity of concrete required to be
removed above the designed top level of
concrete, if any, will be provided for in the
rate analysis.
12.32 1100 Driven precast vertical M35 grade
&170 R.C.C. Piles excluding Reinforcement
0 complete as per Drawing and &
Technical Specification
Size of pile - 300 mm x 300 mm
Unit = Running Meter
Taking output = 60 m

Page 69 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. a) Materials
RCC Grade M-35
Rate for concrete may be adopted same cum 5.40 3190.00 17226.00 Item
as for bottom plug vide item no. 12.11
12.11( F )Pile
b ) Material (IV) shoes (F) iv
a) C I shoes kg 240.00 40.00 9600.00 M-080
b) M. S shoes kg 105.00 35.00 3675.00 M-125
c) Steel helmet and cushion block on Kg 30.00 45.00 1350.00 M-173
top of pile head during driving.
c) Machinery
Crane 10 tonne capacity hour 6.00 300.00 1800.00 P&M-
Vibrating Pile driving hammer complete hour 6.00 550.00 3300.00 071
P&M-
with power unit and accessories. 092
d ) Labour
Mate/Supervisor day 0.12 150.00 18.00 L-12
Mazdoor day 3.00 100.00 300.00 L-13
Add 1 per cent of (a+b+c) for 372.69
carriage of piles from casting yard to
work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 10 % on 2041.57
(b+c+d)
f) Contractor's profit @ 10 % on 2245.73
(b+c+d+e)
Cost for 60 m = a+b+c+d+e+f 41928.98
Rate per metre (a+b+c+d+e+f)/60 698.82
say 699.00
Note The quantity of concrete required to be
removed above the designed top level of
concrete, if any, will be provided for in the
rate analysis.
12.33 1100 Driven precast vertical M35 grade
&170 R.C.C. Piles excluding Reinforcement
0 complete as per Drawing and &
Technical Specification
Size of pile - 500 mm x 500 mm
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same cum 12.50 3190.00 39875.00 Item
as for bottom plug vide item no. 12.11
12.11( F )Pile
b ) Material (IV) shoes (F) iv
a) C I shoes kg 160.00 40.00 6400.00 M-080
b) M. S shoes kg 70.00 35.00 2450.00 M-125
c) Steel helmet and cushion block on Kg 30.00 45.00 1350.00 M-173
top of pile head during driving.
c) Machinery
Crane 20 tonne capacity hour 6.00 475.00 2850.00 P&M-
Vibrating Pile driving hammer complete hour 6.00 550.00 3300.00 073
P&M-
with power unit and accessories. 092
d ) Labour
Mate/Supervisor day 0.16 150.00 24.00 L-12
Mazdoor day 4.00 100.00 400.00 L-13
Add 1 per cent of (a+b+c) for 566.49
carriage of piles from casting yard to
work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 10 % on 1734.05
(b+c+d)
f) Contractor's profit @ 10 % on 1907.45
(b+c+d+e)
Cost for 50 m = a+b+c+d+e+f 60856.99
Rate per metre (a+b+c+d+e+f)/50 1217.14
say 1217.00
Note The quantity of concrete required to be
removed above the designed top level of
concrete, if any, will be provided for in the
rate analysis.

Page 70 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
12.34 Spec.
1100 Driven precast vertical M35 grade
&170 R.C.C. Piles excluding Reinforcement
0 complete as per Drawing and &
Technical Specification
Size of pile - 750 mm x 750 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same cum 22.50 3190.00 71775.00 Item
as for bottom plug vide item no. 12.11
13.11( F ) (IV)
b ) Material (F) iv
Pile shoes
a) C I shoes kg 160.00 40.00 6400.00 M-080
b) M. S shoes kg 70.00 35.00 2450.00 M-125
c) Steel helmet and cushion block on Kg 30.00 45.00 1350.00 M-173
top of pile head during driving.
c) Machinery
Crane 20 tonne capacity hour 6.00 475.00 2850.00 P&M-
Vibrating Pile driving hammer complete hour 6.00 550.00 3300.00 073
P&M-
with power unit and accessories. 092
d ) Labour
Mate/Supervisor day 0.18 150.00 27.00 L-12
Mazdoor day 4.50 100.00 450.00 L-13
Add 1 per cent of (a+b+c) for 886.02
carriage of piles from casting yard to
work site and stacking, and other
imponderables during installation.
e) Overhead charges @ 10 % on 1771.30
(b+c+d)
f) Contractor's profit @ 10 % on 1948.43
(b+c+d+e)
Cost for 40 m = a+b+c+d+e+f 93207.75
Rate per metre (a+b+c+d+e+f)/40 2330.19
say 2330.00
Note The quantity of concrete required to be
removed above the designed top level of
concrete, if any, will be provided for in the
rate analysis.
12.35 1100, Driven Vertical Steel Piles complete as
1900 per Drawing and & Technical
Specification
Section of the pile - H Section steel column
400 x 250 mm (ISHB Series)
Unit = Running Meter
Taking output = 70 m
a) Materials
Structural steel including 5 per cent tonnes 6.04 32000.00 ### M-179
wastage @ 82.20 kg/m
b) Machinery
Crane 10 T capacity hour 6.00 300.00 1800.00 P&M-
Vibrating Pile driving hammer complete hour 6.00 550.00 3300.00 071
P&M-
with power unit and other accessories. 092
c) Labour
Mate/Supervisor day 0.12 150.00 18.00 L-12
Mazdoor day 3.00 100.00 300.00 L-13
Add 0.5 per cent of (a+b+c) for 993.49
providing steel helmet on top of pile
head during driving, stacking of piles at
site, providing anti-corrosion treatment
and other imponderables during
d) Overhead charges @ 10 % on 19969.15
(a+b+c)
e) Contractor's profit @ 10 % on 21966.06
(a+b+c+d)
Cost for 70 m = a+b+c+d+e ###
Rate per metre (a+b+c+d+e)/70 3451.81
say 3452.00

Page 71 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
12.36 Spec.
1100 Driven Vertical Steel Piles complete as
&190 per Drawing and & Technical
0 Specification
Section of the pile - H Section steel column
450 x 250 mm (ISHB Series)
Unit = Running Meter
Taking output = 60 m
a) Materials
Structural steel including 5 per cent tonnes 5.83 32000.00 ### M-179
wastage @92.50 kg/m
b) Machinery
Crane 10 T capacity hour 6.00 300.00 1800.00 P&M-
Vibrating Pile driving hammer complete hour 6.00 550.00 3300.00 071
P&M-
with power unit and accessories. 092
c) Labour
Mate/Supervisor day 0.14 150.00 21.00 L-12
Mazdoor day 3.50 100.00 350.00 L-13
Add 0.5 per cent of (a+b+c) for 960.16
providing steel helmet and cushion
block on top of pile head during driving,
stacking of piles at site, providing anti-
corrosive treatment and other
imponderables during installation.
d) Overhead charges @ 10 % on 19299.12
(a+b+c)
e) Contractor's profit @ 10 % on 21229.03
(a+b+c+d)
Cost for 60 m = a+b+c+d+e ###
Rate per metre (a+b+c+d+e)/60 3891.99
say 3892.00
12.37 1100 Pile Load Test on single Vertical Pile in
accordance with IS:2911(Part-IV)
Unit = 1 MT
Taking output = 1 MT
a) Initial and routine load test tonne 1.00 300.00
b) Lateral load test tonne 1.00 5000.00
Note Although, this item is incidental to work and
is not required to be included in BOQ of
contract, the same is required to be added
in the estimate to assess cost of work.
12.38 1100, Cement Concrete for Reinforced
1500 Concrete in Pile Cap complete as per
&170 Drawing and Technical Specification
0
A RCC Grade M20
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 5.12 4180.00 21401.60 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.90 150.00 135.00 L-12
Mason day 1.50 175.00 262.50 L-10
Mazdoor for concreting day 20.00 100.00 2000.00 L-13
Mazdoor for breaking pile head, bending day 1.00 100.00 100.00 L-13
bars, cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator (capacity 33 KVA) hour 6.00 400.00 2400.00 009
P&M-
Formwork @ 4 per cent on cost of 1391.86 079
concrete i.e. cost of a) Material, b)
Labour and c) Machinery

Page 72 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. d) Overhead charges @ 10 % on 3618.85
(a+b+c)
e) Contractor's profit @ 10 % on 3980.73
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 43788.04
Rate per metre (a+b+c+d+e)/15 2919.20
say 2919.00
(ii) Using Batching Plant, Transit Mixer
12.38A and Concrete Pump
a) Material
Cement tonne 5.12 4180.00 21401.60 M-081
Coarse sand cum 6.75 160.00 1080.00 M-004
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.16 150.00 24.00 L-12
Mason day 0.38 175.00 66.50 L-10
Mazdoor for concreting day 2.50 100.00 250.00 L-13
Mazdoor for breaking pile head, bending day 1.00 100.00 100.00 L-13
bars, cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1500.00 1125.00 P&M-
Generator 100 KVA hour 0.75 600.00 450.00 002
P&M-
Loader (capacity 1 cum) hour 0.75 700.00 525.00 080
P&M-
Transit Mixer ( capacity 4.0 cu.m ) 017
Lead upto 1 Km hour 2.00 600.00 1200.00 P&M-
Lead beyond 1 Km, L - lead in Kilometer tonne.k 37.5L 1.85 1387.50 049
Lead
m =20 km
& P&M-
050
Concrete Pump hour 0.75 500.00 375.00 P&M-
Formwork @ 4 per cent on cost of 1340.78 007
concrete i.e. cost of a) Material, b)
Labour and c) Machinery
d) Overhead charges @ 10 % on 3486.04
(a+b+c)
e) Contractor's profit @ 10 % on 3834.64
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 42181.06
Rate per metre (a+b+c+d+e)/15 2812.07
say 2812.00
Note The value of a, b and c may be taken as
applicable i.e. either using concrete mixer
12.38 B or
RCCbatching
Gradeplant.
M25
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 5.99 4180.00 25038.20 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.90 150.00 135.00 L-12
Mason day 1.50 175.00 262.50 L-10
Mazdoor for concreting day 20.00 100.00 2000.00 L-13
Mazdoor for breaking pile head, bending day 1.00 100.00 100.00 L-13
bars, cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator (capacity 33 KVA) hour 6.00 400.00 2400.00 009
P&M-
Formwork @ 4 per cent on cost of 1537.33 079
concrete i.e. cost of a) Material, b)
Labour and c) Machinery

Page 73 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. d) Overhead charges @ 10 % on 3997.05
(a+b+c)
e) Contractor's profit @ 10 % on 4396.76
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 48364.34
Rate per metre (a+b+c+d+e)/15 3224.29
say 3224.00
12.38B (ii) Using Batching Plant, Transit Mixer
and Concrete Pump
a) Material
Cement tonne 5.99 4180.00 25038.20 M-081
Coarse sand cum 6.75 160.00 1080.00 M-004
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.16 150.00 24.00 L-12
Mason day 0.38 175.00 66.50 L-10
Mazdoor for concreting day 2.50 100.00 250.00 L-13
Mazdoor for breaking pile head, bending day 1.00 100.00 100.00 L-13
bars, cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1500.00 1125.00 P&M-
Generator 125 KVA hour 0.75 650.00 487.50 002
P&M-
Loader (capacity 1 cum) hour 0.75 700.00 525.00 018
P&M-
Transit Mixer ( capacity 4.0 cu.m ) 017
Lead upto 1 Km hour 2.00 600.00 1200.00 P&M-
Lead beyond 1 Km, L - lead in Kilometer tonne.k 37.5L 1.85 1387.50 049
Lead
m =20 km
& P&M-
050
Concrete Pump hour 0.75 500.00 375.00 P&M-
Formwork @ 4 per cent on cost of 1487.75 007
concrete i.e. cost of a) Material, b)
Labour and c) Machinery
d) Overhead charges @ 10 % on 3868.14
(a+b+c)
e) Contractor's profit @ 10 % on 4254.96
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 46804.55
Rate per metre (a+b+c+d+e)/15 3120.30
say 3120.00
Note The value of a, b and c may be taken as
applicable i.e. either using concrete mixer
12.38 C or
RCCbatching
Gradeplant.
M30
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 6.10 4180.00 25498.00 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.90 150.00 135.00 L-12
Mason day 1.50 175.00 262.50 L-10
Mazdoor for concreting day 20.00 100.00 2000.00 L-13
Mazdoor for breaking pile head, bending day 1.00 100.00 100.00 L-13
bars, cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator (capacity 33 KVA) hour 6.00 400.00 2400.00 009
P&M-
Formwork @ 4 per cent on cost of 1555.72 079
concrete i.e. cost of a) Material, b)
Labour and c) Machinery

Page 74 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. d) Overhead charges @ 10 % on 4044.87
(a+b+c)
e) Contractor's profit @ 10 % on 4449.36
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 48942.95
Rate per metre (a+b+c+d+e)/15 3262.86
say 3263.00
(ii) Using Batching Plant, Transit Mixer
'12.38 and Concrete Pump
C a) Material
Cement tonne 6.10 4180.00 25498.00 M-081
Coarse sand cum 6.75 160.00 1080.00 M-004
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.16 150.00 24.00 L-12
Mason day 0.38 175.00 66.50 L-10
Mazdoor for concreting day 2.50 100.00 250.00 L-13
Mazdoor for breaking pile head, bending day 1.00 100.00 100.00 L-13
bars, cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1500.00 1125.00 P&M-
Generator 100 KVA hour 0.75 600.00 450.00 002
P&M-
Loader (capacity 1 cum) hour 0.75 700.00 525.00 080
P&M-
Transit Mixer ( capacity 4.0 cu.m ) 017
Lead upto 1 Km hour 2.00 600.00 1200.00 P&M-
Lead beyond 1 Km, L - lead in Kilometer tonne.k 37.5L 1.85 1387.50 049
Lead
m =20 km
& P&M-
050
Concrete Pump hour 0.75 500.00 375.00 P&M-
Formwork @ 4 per cent on cost of 1504.64 007
concrete i.e. cost of a) Material, b)
Labour and c) Machinery
d) Overhead charges @ 10 % on 3912.06
(a+b+c)
e) Contractor's profit @ 10 % on 4303.27
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 47335.97
Rate per metre (a+b+c+d+e)/15 3155.73
say 3156.00
Note The value of a, b and c may be taken as
applicable i.e. either using concrete mixer
12.38 D or
RCCbatching
Gradeplant.
M35
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement tonne 6.33 4180.00 26459.40 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.90 150.00 135.00 L-12
Mason day 1.50 175.00 262.50 L-10
Mazdoor day 20.00 100.00 2000.00 L-13
Mazdoor for breaking pile head, bending day 1.00 100.00 100.00 L-13
bars, cleaning etc.
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator (capacity 33 KVA) hour 6.00 400.00 2400.00 009
P&M-
Formwork @ 4 per cent on cost of 1594.18 079
concrete i.e. cost of a) Material, b)
Labour and c) Machinery

Page 75 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. d) Overhead charges @ 10 % on 4144.86
(a+b+c)
e) Contractor's profit @ 10 % on 4559.34
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 50152.78
Rate per metre (a+b+c+d+e)/15 3343.52
say 3344.00
(ii) Using Batching Plant, Transit Mixer
'12.38 and Concrete Pump
D a) Material
Cement tonne 6.33 4180.00 26459.40 M-081
Coarse sand cum 6.75 160.00 1080.00 M-004
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.16 150.00 24.00 L-12
Mason day 0.38 175.00 66.50 L-10
Mazdoor for concreting day 2.50 100.00 250.00 L-13
Mazdoor for breaking pile head, bending day 1.00 100.00 100.00 L-13
bars, cleaning etc.
c) Machinery
Batching Plant @ 20 cum/hour hour 0.75 1500.00 1125.00 P&M-
Generator 125 KVA hour 0.75 650.00 487.50 002
P&M-
Loader (capacity 1 cum) hour 0.75 700.00 525.00 018
P&M-
Transit Mixer ( capacity 4.0 cu.m ) 017
Lead upto 1 Km hour 2.00 600.00 1200.00 P&M-
Lead beyond 1 Km, L - lead in Kilometer tonne.k 37.5L 1.85 1387.50 049
Lead
m =20 km
& P&M-
050
Concrete Pump hour 0.75 500.00 375.00 P&M-
Formwork @ 4 per cent on cost of 1544.60 007
concrete i.e. cost of a) Material, b)
d) Labour and c) charges
Overhead Machinery@ 10 % on 4015.95
(a+b+c)
e) Contractor's profit @ 10 % on 4417.54
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 48592.99
Rate per metre (a+b+c+d+e)/15 3239.53
say 3240.00
12.39 1100 Levelling Course for Pile cap
&170
0 Providing and laying of PCC M15
levelling course 100mm thick below
the pile
Unit cap.
= cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 4180.00 17263.40 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
40 mm aggregate cum 8.10 350.00 2835.00 M-055
20 mm Aggregate cum 4.05 410.00 1660.50 M-053
10 mm Aggregate cum 1.35 410.00 553.50 M-051
b) Labour
Mate day 0.86 150.00 129.00 L-12
Mason day 1.50 175.00 262.50 L-10
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
d) Overhead charges @ 10 % on 3006.64 079
(a+b+c)
e) Contractor's profit @ 10 % on 3307.30
(a+b+c+d)
Cost for 15 cum = a+b+c+d+e 36380.34
Rate per metre (a+b+c+d+e)/15 2425.36

Page 76 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. say 2425.00
12.40 1600 Supplying, Fitting and Placing un-
coated HYSD bar Reinforcement in
Foundation complete as per Drawing
and Technical Specifications.
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including5 per cent overlaps tonne 1.05 34500.00 36225.00 M-082
and wastage
Binding wire Kg 6.00 40.00 240.00 M-072
b) Labour for cutting, bending,
shifting to site, tying and placing in
position
Mate day 0.40 150.00 60.00 L-12
Blacksmith day 2.00 150.00 300.00 L-02
Mazdoor day 6.00 100.00 600.00 L-13
3742.50
4116.75
45284.25
say ###
12.41 1600 Supplying, fitting and placing un-
coated Mild steel reinforcement
complete in foundation as per drawing
and technical specification
Unit = 1 MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps tonne 1.05 30000.00 31500.00 M-126
and wastage
Binding wire Kg 6.00 40.00 240.00 M-072
b) Labour for straightening,
cutting, bending, shifting to site, tying
andMate
placing in position day 0.43 150.00 64.50 L-12
Blacksmith day 2.25 150.00 337.50 L-02
Mazdoor day 6.50 100.00 650.00 L-13
c) Overhead charges @ 10 % on 3279.20
(a+b)
d) Contractor's profit @ 10 % on 3607.12
(a+b+c)
Rate for per MT (a+b+c+d) 39678.32
say ###

Page 77 of 361
CHAPTER-13
Ref. SUB-STRUCTURE
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
13.1 Spec.
1300 Brick masonry work in 1:3 in sub-
& structure complete excluding pointing
2200 and plastering, as per drawing and
Technical Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class each 500.00 2.00 1000.00 M-079
Cement mortar 1:3 (Rate as in Item cum 0.24 2595.00 622.80 Item
12.6 A sub-analysis) 12.6 (A)
b) Labour
Mate day 0.06 150.00 9.00 L-12
Mason day 0.80 250.00 200.00 L-11
Mazdoor day 0.80 100.00 80.00 L-13
Add for scaffolding @ 5 per cent of cost 95.59
of material and labour
c) Overhead charges @ 10 % on 200.74
(a+b)
d) Contractor's profit @ 10 % on 220.81
(a+b+c)
Rate per cum (a+b+c+d) 2428.94
say 2429.00
13.2 1300 Pointing with cement mortar (1:3 ) on
& brick work in substructure as per
2200 Technical
Unit Specifications
= 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item cum 0.03 2595.00 77.85 Item
b) 12.6 )
Labour 12.6 (A)
Mate day 0.04 150.00 6.00 L-12
Mason day 0.50 250.00 125.00 L-11
Mazdoor day 0.50 100.00 50.00 L-13
c) Overhead charges @ 10 % on 25.89
(a+b)
d) Contractor's profit @ 10 % on 28.47
(a+b+c)
Rate per 10 sqm (a+b+c+d) 313.21
say 313.00
Note Scaffolding is already included in item 13.1
13.3 1300 Plastering with cement mortar (1:3 )
& on brick work in sub-structure as per
2200 Technical
Unit Specifications
= 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item cum 0.144 2595.00 373.68 Item
12.6) 12.6 (A)
b) Labour
Mate day 0.04 150.00 6.00 L-12
Mason day 0.50 250.00 125.00 L-11
Mazdoor day 0.50 100.00 50.00 L-13
c) Overhead charges @ 10 % on 55.47
(a+b)
d) Contractor's profit @ 10 % on 61.01
(a+b+c)
Rate per 10 sqm (a+b+c+d) 671.16
say 671.00
Note 1.Scaffolding is already included in item no.
13.1
2.The number of masons and Mazdoors
already catered in the cement mortar have
been taken into account while providing
these categories in brick masonry, pointing
and plastering.
13.4 1400 Stone masonry work in cement mortar
& 1:3 for substructure complete as per
2200 drawing and Technical Specifications
A Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material

Page 1 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Stone cum 1.00 300.00 300.00 M-148
Through and bond stone No 7.00 30.00 210.00 M-182
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item cum 0.33 2595.00 856.35 Item
12.6) 12.6 (A)
b) Labour
Mate day 0.10 150.00 15.00 L-12
Mason day 1.20 250.00 300.00 L-11
Mazdoor day 1.20 100.00 120.00 L-13
Add for scaffolding @ 5 per cent of cost 90.07
of a) Material and b) Labour
c) Overhead charges @ 10 % on 189.14
(a+b) Contractor's profit @ 10 % on
d) 208.06
(a+b+c)
Rate per cum (a+b+c+d) 2288.62
say 2289.00
13.4 B Coursed rubble masonry (first sort )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.10 300.00 330.00 M-148
Through and bond stone each 7.00 30.00 210.00 M-182
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item cum 0.30 2595.00 778.50 Item
12.6) 12.6 (A)
b) Labour
Mate day 0.12 150.00 18.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 1.50 100.00 150.00 L-13
Add for scaffolding @ 5 per cent of cost 93.08
of material and labour
c) Overhead charges @ 10 % on 195.46
(a+b)
d) Contractor's profit @ 10 % on 215.00
(a+b+c)
Rate per cum (a+b+c+d) 2365.04
say 2365.00
13.4 C Ashlar masonry ( first sort )
Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.11 4000.00 4440.00 M-169
Through and bond stone each 7.00 30.00 210.00 M-182
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item cum 0.33 2595.00 856.35 Item
12.6) 12.6 (A)
b) Labour for masonry work
Mate day 0.20 150.00 30.00 L-12
Mason day 2.50 250.00 625.00 L-11
Mazdoor day 2.50 100.00 250.00 L-13
Add for scaffolding @ 5 per cent of cost 320.57
of a) Material and b) Labour
c) Overhead charges @ 10 % on 673.19
(a+b)
d) Contractor's profit @ 10 % on 740.51
(a+b+c)
Rate per cum (a+b+c+d) 8145.62
say 8146.00
Note The labour already considered in the
cement mortar have been taken into
account while providing these categories in
the stone masonry works.
13.5 1500, Plain/Reinforced cement concrete in
1700 sub-structure complete as per drawing
& and Technical Specifications
2200
Page 2 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Unit = cum
Taking output = 1 cum
A PCC Grade M15
(p) Height upto 5m
Same as Item 12.8 (A) upto 5 m height,
except for formwork which shall be 10 per
cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material 2062.00 Item 12.8 (A)
& Machinery (a+b+c) of Item 12.8 (A)
d) formwork
Add 10 per cent of cost of material, 10.00 206.20
labour and machinery (a+b+c) for
e) Formwork
Overhead charges @ 10 % on 226.82
(a+b+c+d)
f) Contractor's profit @ 10 % on 249.50
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 2744.52
say 2745.00
13.5 B PCC Grade M20
(p) Height upto 5m
Same as Item 12.8 (B) upto 5 m height,
except for formwork which shall be 10 per
cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material 2310.00 Item 12.8 (B) PCC
& Machinery (a+b+c) of Item 12.8 (B)
d) formwork
Add 10 per cent of cost of material, 10.00 231.00
labour and machinery (a+b+c) for
e) Formwork
Overhead charges @ 10 % on 254.10
(a+b+c+d)
f) Contractor's profit @ 10 % on 279.51
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3074.61
say 3075.00
13.5 C PCC Grade M25
(p) Height upto 5m
Same as Item 12.8 (D) upto 5 m height with
the only change that the provision of form
work shall be 10 per cent instead of 3.75
per cent of cost of material, labour and
machinery.
Cas Using concrete Mixer
eI
Per Cum Basic Cost of Labour, Material 2542.00 Item 12.8 (D)
& Machinery (a+b+c) of Item 12.8 (D)
Case
d) I
formwork
Add 10 per cent of cost of material, 10.00 254.20
labour and machinery (a+b+c) for
e) Formwork
Overhead charges @ 10 % on 279.62
(a+b+c+d)
f) Contractor's profit @ 10 % on 307.58
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3383.40
say 3383.00
13.5 Cas With Batching Plant, Transit Mixer and
C (p) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2445.00 Item 12.8 (D)
& Machinery (a+b+c) of Item 12.8 (D)
Case
d) II
formwork
Add 10 per cent of cost of material, 10.00 244.50
labour and machinery (a+b+c) for
e) Formwork
Overhead charges @ 10 % on 268.95
(a+b+c+d)
f) Contractor's profit @ 10 % on 295.85
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3254.30
say 3254.00
13.5 (q) Height 5m to 10m
C

Page 3 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Same as Item 12.8 (D) with the following
changes: (i) Add 2 per cent of cost of
material, Labour and machinery excluding
form work to cater for extra lift. (ii) The
provision of form work shall be 12 per cent
instead of 3.75 per cent of cost of material,
labour and machinery
Cas Using concrete Mixer
eI
Per Cum Basic Cost of Labour, Material 2542.00 Item 12.8 (D)
& Machinery (a+b+c) of Item 12.8 (D)
Case
d) I
formwork
Add 12 per cent of cost of material, 12.00 305.04
labour and machinery (a+b+c) for
Formwork
Add 2 per cent of cost of material, 2.00 50.84
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 289.79
(a+b+c+d)
f) Contractor's profit @ 10 % on 318.77
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3506.43
say 3506.00
13.5 Cas With Batching Plant, Transit Mixer and
C (q) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2445.00
& Machinery (a+b+c) of Item 12.8 (D)
Case
d) II
formwork
Add 12 per cent of cost of material, 12.00 293.40
labour and machinery (a+b+c) for
Formwork
Add 2 per cent of cost of material, 2.00 48.90
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 278.73
(a+b+c+d)
f) Contractor's profit @ 10 % on 306.60
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3372.63
say 3373.00
13.5 (r) Height above 10m
C Same as Item 12.8 (D) with the following
changes: (i) Add 4 per cent of cost of
material, labour and machinery excluding
form work to cater for extra lift. (ii) The
provision of form work shall be 15 per cent
instead of 3.75 per cent of cost of material,
labour and machinery.
Cas Using concrete Mixer
eI
Per Cum Basic Cost of Labour, Material 2542.00 Item 12.8 (D)
& Machinery (a+b+c) of Item 12.8 (D)
Case
d) I
formwork
Add 15 per cent of cost of material, 15.00 381.30
labour and machinery (a+b+c) for
Formwork
Add 4 per cent of cost of material, 4.00 101.68
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 302.50
(a+b+c+d)
f) Contractor's profit @ 10 % on 332.75
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3660.23
say 3660.00
13.5 Cas With Batching Plant, Transit Mixer and
C (r) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2445.00 Item 12.8 (D)
& Machinery (a+b+c) of Item 12.8 (D)
Case
d) II
formwork
Add 15 per cent of cost of material, 15.00 366.75
labour and machinery (a+b+c) for
Formwork
Add 4 per cent of cost of material, 4.00 97.80
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 290.96
(a+b+c+d)
Page 4 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. f) Contractor's profit @ 10 % on 320.05
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3520.56
say 3521.00
13.5 D PCC Grade M30
(p) Height upto 5m
Same as Item 12.8 (F) upto 5 m height with
the only change that the provision of form
work shall be 10 per cent instead of 3.50
per cent of cost of material, labour and
machinery.
Cas Using concrete Mixer
eI
Per Cum Basic Cost of Labour, Material 2567.00
& Machinery (a+b+c) of Item 12.8 (F)
Case
d) I
formwork
Add 10 per cent of cost of material, 10.00 256.70
labour and machinery (a+b+c) for
e) Formwork
Overhead charges @ 10 % on 282.37
(a+b+c+d)
f) Contractor's profit @ 10 % on 310.61
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3416.68
say 3417.00
13.5 Cas With Batching Plant, Transit Mixer and
D (p) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2468.00
& Machinery (a+b+c) of Item 12.8 (F)
Case
d) II
formwork
Add 10 per cent of cost of material, 10.00 246.80
labour and machinery (a+b+c) for
e) Formwork
Overhead charges @ 10 % on 271.48
(a+b+c+d)
f) Contractor's profit @ 10 % on 298.63
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3284.91
say 3285.00
13.5 (q) Height 5m to 10m
D Same as Item 12.8 (F) with the following
changes: (i) Add 2 per cent of cost of
material, Labour and machinery excluding
form work to cater for extra lift. (ii) The
provision of form work shall be 12 per cent
instead of 3.50 per cent of cost of material,
labour and machinery.
Cas Using concrete Mixer
eI
Per Cum Basic Cost of Labour, Material 2567.00
& Machinery (a+b+c) of Item 12.8 (F)
Case
d) I
formwork
Add 12 per cent of cost of material, 12.00 308.04
labour and machinery (a+b+c) for
Formwork
Add 2 per cent of cost of material, 2.00 51.34
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 292.64
(a+b+c+d)
f) Contractor's profit @ 10 % on 321.90
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3540.92
say 3541.00
13.5 Cas With Batching Plant, Transit Mixer and
D (q) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2468.00
& Machinery (a+b+c) of Item 12.8 (F)
Case
d) II
formwork
Add 12 per cent of cost of material, 12.00 296.16
labour and machinery (a+b+c) for
Formwork
Add 2 per cent of cost of material, 2.00 49.36
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 281.35
(a+b+c+d)

Page 5 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. f) Contractor's profit @ 10 % on 309.49
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3404.36
say 3404.00
13.5 (r) Height above 10m
D Same as Item 12.8 (F) with the following
changes: (i) Add 4 per cent of cost of
material, labour and machinery excluding
form work to cater for extra lift. (ii) The
provision of form work shall be 15 per cent
instead of 3.50 per cent of cost of material,
labour and machinery
Cas Using concrete Mixer
eI
Per Cum Basic Cost of Labour, Material 2567.00
& Machinery (a+b+c) of Item 12.8 (F)
Case
d) I
formwork
Add 15 per cent of cost of material, 15.00 385.05
labour and machinery (a+b+c) for
Formwork
Add 4 per cent of cost of material, 4.00 102.68
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 305.47
(a+b+c+d)
f) Contractor's profit @ 10 % on 336.02
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3696.22
say 3696.00
13.5 Cas With Batching Plant, Transit Mixer and
D (r) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2468.00
& Machinery (a+b+c) of Item 12.8 (F)
Case
d) II
formwork
Add 15 per cent of cost of material, 15.00 370.20
labour and machinery (a+b+c) for
Formwork
Add 4 per cent of cost of material, 4.00 98.72
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 293.69
(a+b+c+d)
f) Contractor's profit @ 10 % on 323.06
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3553.67
say 3554.00
13.5 E RCC Grade M20
(p) Height upto 5m
Same as Item 12.8 (C) upto 5 m height,
except for formwork which shall be 10 per
cent instead of 4 per cent of cost of
material, labour and machinery.
Cas Using concrete Mixer
eI
Per Cum Basic Cost of Labour, Material 2346.00
& Machinery (a+b+c) of Item 12.8 (C)
Case
d) I
formwork
Add 10 per cent of cost of material, 10.00 234.60
labour and machinery (a+b+c) for
e) Formwork
Overhead charges @ 10 % on 258.06
(a+b+c+d)
f) Contractor's profit @ 10 % on 283.87
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3122.53
say 3123.00
13.5 Cas With Batching Plant, Transit Mixer and
E (p) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2247.00
& Machinery (a+b+c) of Item 12.8 (C)
Case
d) II
formwork
Add 10 per cent of cost of material, 10.00 224.70
labour and machinery (a+b+c) for
e) Formwork
Overhead charges @ 10 % on 247.17
(a+b+c+d)
f) Contractor's profit @ 10 % on 271.89
(a+b+c+d+e)

Page 6 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Rate perm (a+b+c+d+e+f) 2990.76
say 2991.00
13.5 (q) Height 5m to 10m
E For height, upto 10m, add 2 per cent of
cost as above excluding formwork. For cost
of formwork add 12 per cent of cost of
material, labour and machinery instead of 4
per cent .
Cas Using concrete Mixer
eI
Per Cum Basic Cost of Labour, Material 2346.00
& Machinery (a+b+c) of Item 12.8 (C)
Case
d) I
formwork
Add 12 per cent of cost of material, 12.00 281.52
labour and machinery (a+b+c) for
Formwork
Add 2 per cent of cost of material, 2.00 46.92
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 267.44
(a+b+c+d)
f) Contractor's profit @ 10 % on 294.19
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3236.07
say 3236.00
13.5 Cas With Batching Plant, Transit Mixer and
E (q) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2247.00
& Machinery (a+b+c) of Item 12.8 (C)
Case
d) II
formwork
Add 12 per cent of cost of material, 12.00 269.64
labour and machinery (a+b+c) for
Formwork
Add 2 per cent of cost of material, 2.00 44.94
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 256.16
(a+b+c+d)
f) Contractor's profit @ 10 % on 281.77
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3099.51
say 3100.00
13.5 (r) Height above 10m
E Same as Item 12.8 (C) with the following
changes: (i) Add 4 per cent of cost of
material, labour and machinery excluding
form work to cater for extra lift. (ii) The
provision of form work shall be 15 per cent
instead of 4 per cent of cost of material,
Cas Using concrete Mixer
eI
Per Cum Basic Cost of Labour, Material 2346.00
& Machinery (a+b+c) of Item 12.8 (C)
Case
d) I
formwork
Add 15 per cent of cost of material, 15.00 351.90
labour and machinery (a+b+c) for
Formwork
Add 4 per cent of cost of material, 4.00 93.84
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 279.17
(a+b+c+d)
f) Contractor's profit @ 10 % on 307.09
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3378.01
say 3378.00
13.5 Cas With Batching Plant, Transit Mixer and
E (r) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2247.00
& Machinery (a+b+c) of Item 12.8 (C)
Case
d) II
formwork
Add 15 per cent of cost of material, 15.00 337.05
labour and machinery (a+b+c) for
Formwork
Add 4 per cent of cost of material, 4.00 89.88
Labour and machinery excluding
formwork to cater for extra lift

Page 7 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. e) Overhead charges @ 10 % on 267.39
(a+b+c+d)
f) Contractor's profit @ 10 % on 294.13
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3235.46
say 3235.00
13.5 F RCC Grade M25
(p) Height upto 5m
Same as Item 12.8 (E) upto 5m height,
excluding formwork. For cost of formwork,
add 10 per cent of cost of material, labour
and machinery instead of 3.75 per cent .
Cas Using concrete Mixer
eI
Per Cum Basic Cost of Labour, Material 2580.00
& Machinery (a+b+c) of Item 12.8 (E)
Case
d) I
formwork
Add 10 per cent of cost of material, 10.00 258.00
labour and machinery (a+b+c) for
e) Formwork
Overhead charges @ 10 % on 283.80
(a+b+c+d)
f) Contractor's profit @ 10 % on 312.18
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3433.98
say 3434.00
13.5 Cas With Batching Plant, Transit Mixer and
F (p) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2562.00
& Machinery (a+b+c) of Item 12.8 (E)
Case
d) II
formwork
Add 10 per cent of cost of material, 10.00 256.20
labour and machinery (a+b+c) for
e) Formwork
Overhead charges @ 10 % on 281.82
(a+b+c+d)
f) Contractor's profit @ 10 % on 310.00
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3410.02
say 3410.00
13.5 (q) Height 5m to 10m
F For height, upto 10m, add 1.8 per cent of
cost as above excluding formwork. For cost
of formwork add 11.8 per cent of cost of
material, labour and machinery
Cas Using concrete Mixer
eI
Per Cum Basic Cost of Labour, Material 2580.00
& Machinery (a+b+c) of Item 12.8 (E)
Case
d) I
formwork
Add 11.8 per cent of cost of material, 11.80 304.44
labour and machinery (a+b+c) for
Formwork
Add 1.8 per cent of cost of material, 1.80 46.44
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 293.09
(a+b+c+d)
f) Contractor's profit @ 10 % on 322.40
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3546.36
say 3546.00
13.5 Cas With Batching Plant, Transit Mixer and
F (q) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2562.00
& Machinery (a+b+c) of Item 12.8 (E)
Case
d) II
formwork
Add 11.8 per cent of cost of material, 11.80 302.32
labour and machinery (a+b+c) for
Formwork
Add 1.8 per cent of cost of material, 1.80 46.12
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 291.04
(a+b+c+d)
f) Contractor's profit @ 10 % on 320.15
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3521.62

Page 8 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. say 3522.00
13.5 (r) Height above 10m
F For height, above 10m, add 4 per cent of
cost as above excluding formwork. For cost
of formwork add 15 per cent of cost of
material, labour and machinery
Cas Using concrete Mixer
eI
Per Cum Basic Cost of Labour, Material 2580.00
& Machinery (a+b+c) of Item 12.8 (E)
Case
d) I
formwork
Add 15 per cent of cost of material, 15.00 387.00
labour and machinery (a+b+c) for
Formwork
Add 4 per cent of cost of material, 4.00 103.20
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 307.02
(a+b+c+d)
f) Contractor's profit @ 10 % on 337.72
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3714.94
say 3715.00
13.5 Cas With Batching Plant, Transit Mixer and
F (r) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2562.00
& Machinery (a+b+c) of Item 12.8 (E)
Case
d) II
formwork
Add 15 per cent of cost of material, 15.00 384.30
labour and machinery (a+b+c) for
Formwork
Add 4 per cent of cost of material, 4.00 102.48
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 304.88
(a+b+c+d)
f) Contractor's profit @ 10 % on 335.37
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3689.02
say 3689.00
13.5 G RCC Grade M30
(p) Height upto 5m
Same as Item 12.8 (G) upto 5m height,
excluding formwork. For cost of formwork,
add 10 per cent of cost of material, labour
and machinery instead of 3.5 per cent .
Cas Using concrete Mixer
eI
Per Cum Basic Cost of Labour, Material 2594.00
& Machinery (a+b+c) of Item 12.8 (G)
Case
d) I
formwork
Add 10 per cent of cost of material, 10.00 259.40
labour and machinery (a+b+c) for
e) Formwork
Overhead charges @ 10 % on 285.34
(a+b+c+d)
f) Contractor's profit @ 10 % on 313.87
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3452.61
say 3453.00
13.5 Cas With Batching Plant, Transit Mixer and
G (p) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2496.00
& Machinery (a+b+c) of Item 12.8 (G)
Case
d) II
formwork
Add 10 per cent of cost of material, 10.00 249.60
labour and machinery (a+b+c) for
e) Formwork
Overhead charges @ 10 % on 274.56
(a+b+c+d)
f) Contractor's profit @ 10 % on 302.02
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3322.18
say 3322.00
13.5 (q) Height 5m to 10m
G

Page 9 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. For height, upto 10m, add 1.6 per cent of
cost as above excluding formwork. For cost
of formwork add 11.5 per cent of cost of
material, labour and machinery
Cas Using concrete Mixer
eI
Per Cum Basic Cost of Labour, Material 2594.00
& Machinery (a+b+c) of Item 12.8 (G)
Case
d) I
formwork
Add 11.5 per cent of cost of material, 11.50 298.31
labour and machinery (a+b+c) for
Formwork
Add 1.6 per cent of cost of material, 1.60 41.50
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 293.38
(a+b+c+d)
f) Contractor's profit @ 10 % on 322.72
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3549.91
say 3550.00
13.5 Cas With Batching Plant, Transit Mixer and
G (q) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2496.00
& Machinery (a+b+c) of Item 12.8 (G)
Case
d) II
formwork
Add 11.5 per cent of cost of material, 11.50 287.04
labour and machinery (a+b+c) for
Formwork
Add 1.6 per cent of cost of material, 1.60 39.94
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 282.30
(a+b+c+d)
f) Contractor's profit @ 10 % on 310.53
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3415.80
say 3416.00
13.5 (r) Height above 10m
G For height, above 10m, add 3.5 per cent of
cost as above excluding formwork. For cost
of formwork add 14 per cent of cost of
material, labour and machinery
Cas Using concrete Mixer
eI
Per Cum Basic Cost of Labour, Material 2594.00
& Machinery (a+b+c) of Item 12.8 (G)
Case
d) I
formwork
Add 14 per cent of cost of material, 14.00 363.16
labour and machinery (a+b+c) for
Formwork
Add 3.5 per cent of cost of material, 3.50 90.79
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 304.80
(a+b+c+d)
f) Contractor's profit @ 10 % on 335.27
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3688.02
say 3688.00
13.5 Cas With Batching Plant, Transit Mixer and
G (r) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2496.00
& Machinery (a+b+c) of Item 12.8 (G)
Case
d) II
formwork
Add 14 per cent of cost of material, 14.00 349.44
labour and machinery (a+b+c) for
Formwork
Add 3.5 per cent of cost of material, 3.50 87.36
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 293.28
(a+b+c+d)
f) Contractor's profit @ 10 % on 322.61
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3548.69
say 3549.00
13.5 H RCC Grade M35
(p) Height upto 5m

Page 10 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Same as Item 12.8 (H) upto 5m height,
excluding formwork. For cost of formwork,
add 10 per cent of cost of material, labour
and machinery instead of 3 per cent .
Cas Using concrete Mixer
eI
Per Cum Basic Cost of Labour, Material 2658.00
& Machinery (a+b+c) of Item 12.8 (H)
Case
d) I
formwork
Add 10 per cent of cost of material, 10.00 265.80
labour and machinery (a+b+c) for
e) Formwork
Overhead charges @ 10 % on 292.38
(a+b+c+d)
f) Contractor's profit @ 10 % on 321.62
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3537.80
say 3538.00
13.5 Cas With Batching Plant, Transit Mixer and
H (p) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2645.00
& Machinery (a+b+c) of Item 12.8 (H)
Case
d) II
formwork
Add 10 per cent of cost of material, 10.00 264.50
labour and machinery (a+b+c) for
e) Formwork
Overhead charges @ 10 % on 290.95
(a+b+c+d)
f) Contractor's profit @ 10 % on 320.05
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3520.50
say 3520.00
13.5 (q) Height 5m to 10m
H For height, upto 10m, add 1.4 per cent of
cost as above excluding formwork. For cost
of formwork add 11 per cent of cost of
material, labour and machinery .
Cas Using concrete Mixer
eI
Per Cum Basic Cost of Labour, Material 2658.00
& Machinery (a+b+c) of Item 12.8 (H)
Case
d) I
formwork
Add 11 per cent of cost of material, 11.00 292.38
labour and machinery (a+b+c) for
Formwork
Add 1.4 per cent of cost of material, 1.40 37.21
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 298.76
(a+b+c+d)
f) Contractor's profit @ 10 % on 328.64
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3614.99
say 3615.00
13.5 Cas With Batching Plant, Transit Mixer and
H (q) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2645.00
& Machinery (a+b+c) of Item 12.8 (H)
Case
d) II
formwork
Add 11 per cent of cost of material, 11.00 290.95
labour and machinery (a+b+c) for
Formwork
Add 1.4 per cent of cost of material, 1.40 37.03
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 297.30
(a+b+c+d)
f) Contractor's profit @ 10 % on 327.03
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3597.31
say 3597.00
13.5 (r) Height above 10m
H For height, above 10m, add 3 per cent of
cost as above excluding formwork. For cost
of formwork add 13 per cent of cost of
material, labour and machinery
Cas Using concrete Mixer
eI

Page 11 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Per Cum Basic Cost of Labour, Material 2658.00
& Machinery (a+b+c) of Item 12.8 (H)
Case
d) I
formwork
Add 13 per cent of cost of material, 13.00 345.54
labour and machinery (a+b+c) for
Formwork
Add 3 per cent of cost of material, 3.00 79.74
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 308.33
(a+b+c+d)
f) Contractor's profit @ 10 % on 339.16
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3730.77
say 3731.00
13.5 Cas With Batching Plant, Transit Mixer and
H (r) e II Concrete Pump
Per Cum Basic Cost of Labour, Material 2645.00
& Machinery (a+b+c) of Item 12.8 (H)
Case
d) II
formwork
Add 13 per cent of cost of material, 13.00 343.85
labour and machinery (a+b+c) for
Formwork
Add 3 per cent of cost of material, 3.00 79.35
Labour and machinery excluding
e) formwork to cater
Overhead for extra
charges @ 10 lift% on 306.82
(a+b+c+d)
f) Contractor's profit @ 10 % on 337.50
(a+b+c+d+e)
Rate perm (a+b+c+d+e+f) 3712.52
say 3713.00
Note The basic components of this analysis are
the same as those of items 13.8 (A to H).
The only changes are as under:
a) Ramps/Stairs: Extra expenditure on
structures which are more than 5 m high @
2 per cent of cost for height upto 10 m and
4 per cent for heights above 10 m will be
involved for approaching the work spot by
providing higher ramp/stair case for use by
the working parties.
b) The above mentioned percentages
have been suitably modified for different
categories as cost for various categories
varies, whereas effort for access for same
height will be similar. As the cost of richer
concrete is comparatively more, the
percentage to be added has been reduced
to maintain the same cost for extra efforts.
13.6 Sectio Supplying, fitting and placing HYSD
n bar reinforcement in sub-structure
1600 complete as per drawing and Technical
& Specifications
Output: MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent tonne 1.05 34500.00 36225.00 M-082
overlaps and wastage
Binding wire kg 6.00 40.00 240.00 M-072
b) Labour for cutting, bending,
shifting to site, tying and placing in
position
Mate day 0.34 150.00 51.00 L-12
Blacksmith day 2.00 150.00 300.00 L-02
Mazdoor day 6.50 100.00 650.00 L-13
c) Overhead charges @ 10 % on 3746.60
(a+b)
d) Contractor's profit @ 10 % on 4121.26
(a+b+c)
Rate for per MT (a+b+c+d) 45333.86
say ###
13.7 1600 Supplying, fitting and placing Mild
& steel reinforcement complete in sub-
2200 structure as per drawing and Technical
Specification

Page 12 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Unit = MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps tonne 1.05 30000.00 31500.00 M-126
and wastage
Binding wire kg 6.00 40.00 240.00 M-072
b) Labour for straightening, cutting,
bending, shifting to site, tying and
placing
Matein position day 0.28 150.00 42.00 L-12
Blacksmith day 1.50 150.00 225.00 L-02
Mazdoor day 5.50 100.00 550.00 L-13
c) Overhead charges @ 10 % on 3255.70
(a+b)
d) Contractor's profit @ 10 % on 3581.27
(a+b+c)
Rate for per MT (a+b+c+d) 39393.97
say ###
13.8 2706 Providing weep holes in Brick
& masonry/Plain/ Reinforced concrete
2200 abutment, wing wall/ return wall with
100 mm dia AC pipe, extending
through the full width of the structure
with slope of 1V :20H towards drawing
foce. Complete as per drawing and
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including metre 31.50 15.00 472.50 M-056
wastage @ 5 per cent )
Average length of weep hole is taken as
one metre for the purpose of estimating.
MS clamp each. 30.00 25.00 750.00 M-123
collar for AC pipe (average) taking 10% each. 10.00 1.50 15.00 M-
of above pipe rate 056/10
Cement mortar 1:3 (Rate as in Item cum 0.05 2595.00 129.75 Item
12.6) 12.6 (A)
b) Labour
Mate day 0.03 150.00 4.50 L-12
Mason day 0.50 250.00 125.00 L-11
Mazdoor day 0.25 100.00 25.00 L-13
c) Overhead charges @ 10 % on 152.18
(a+b)
d) Contractor's profit @ 10 % on 167.39
(a+b+c)
Cost for 30 m = a+b+c+d 1841.32
Rate per m (a+b+c+d)/30 61.38
say 61.00
Note 1. In case of stone masonry, the size of the
weep hole shall be 150 mm x 80 mm or
circular with 150 mm diameter.
2. For structure in stone masonry, the weep
holes shall be deemed to be included in the
item of stone masonry work and shall not
be paid separately.
13.9 710.1. Back filling behind abutment, wing
4.of wall and return wall complete as per
IRC:7 drawing and Technical Specification
8&
2200
Unit = cum
Taking output = 10 cum
A Granular material
a) Labour
Mate day 0.28 150.00 42.00 L-12
Mazdoor day 7.00 100.00 700.00 L-13
b) Material
Granular material cum 12.00 160.00 1920.00 M-009

Page 13 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. c) Machinery
Plate compactor/power rammer hour 2.50 75.00 187.50 P&M-
Water Tanker hour 0.05 105.00 5.25 086
P&M-
d) Overhead charges @ 10 % on 285.48 060
(a+b+c)
e) Contractor's profit @ 10 % on 314.02
(a+b+c+d)
Cost for 10 cum of granular backfill = 3454.25
a+b+c+d+e
Rate per cum = (a+b+c+d+e)/10 345.42
say 345.00
13.9 B Sandy material
a) Labour
Mate day 0.28 150.00 42.00 L-12
Mazdoor for filling, watering, ramming day 7.00 100.00 700.00 L-13
b) etc.
Material
Sand cum 12.00 300.00 3600.00 M-006
c) Machinery
Plate compactor/power rammer hour 2.50 75.00 187.50 P&M-
Water Tanker hour 0.06 105.00 6.30 086
P&M-
d) Overhead charges @ 10 % on 453.58 060
(a+b+c)
e) Contractor's profit @ 10 % on 498.94
(a+b+c+d)
Cost for 10 cum of sandy backfill = 5488.32
a+b+c+d+e
Rate per cum = (a+b+c+d+e)/10 548.83
say 549.00
13.1 710.1. Providing and laying of Filter media
0 4.of with granular materials/stone crushed
IRC:7 aggregates satisfying the
8 and requirements laid down in clause
2200 2504.2.2. of MoRTH specifications to a
thickness of not less than 600 mm with
smaller size towards the soil and
bigger size towards the wall and
provided over the entire surface
behind abutment, wing wall and return
wall to the full height compacted to a
firm condition complete as per drawing
Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 150.00 48.00 L-12
Mazdoor for filling, watering, ramming day 7.00 100.00 700.00 L-13
etc.
Mazdoor (Skilled) day 1.00 125.00 125.00 L-15
b) Material
Filter media of stone aggregate cum 12.00 160.00 1920.00 M-012
conforming to clause 2504.2.2. of
c) MoRTH specifications.
Machinery
Water Tanker of 6 KL capacity hour 0.06 105.00 6.30 P&M-
d) Overhead charges @ 10 % on 279.93 060
(a+b+c)
e) Contractor's profit @ 10 % on 307.92
(a+b+c+d)
cost for 10 cum of Fiter Media = 3387.15
a+b+c+d+e
Rate per cum = (a+b+c+d+e)/10 338.72
say 339.00
13.1 2000, Supplying, fitting and fixing in position
1 1000 true to line and level cast steel rocker
& bearing conforming to IRC: 83(Pt.-1)
2200 section IX and clause 2003 of MoRTH
specifications complete including all
accessories as per drawing and
Unit: one tonne capacity
Considering a 250 tonne capacity bearing
for this analysis
a) Labour
Mate day 0.06 150.00 9.00 L-12
Mazdoor (Skilled) day 0.50 125.00 62.50 L-15

Page 14 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Mazdoor day 1.00 100.00 100.00 L-13
b) Material
Cast steel rocker bearing assembly of each. 1.00 40000.00 40000.00 M-065
250 tonne design load capacity duly
painted complete with all its
components as per drawing and
Add 1 per cent of cost of bearing 400.00
assembly for foundation anchorage
bolts, lifting arrangements, grease and
other consumables.
c) Overhead charges @ 10 % on 4057.15
(a+b)
d) Contractor's profit @ 10 % on 4462.87
(a+b+c)
cost for 250 tonnes capacity bearing = 49091.52
a+b+c+d
Rate per tonne capacity = 196.37
(a+b+c+d)/250 say 196.00
13.1 2000 , Supplying, fitting and fixing in position
2 1000 true to line and level forged steel
& roller bearing conforming to IRC:
2200 83(Pt.-1) section IX and clause 2003 of
MoRTH specifications complete
including all accessories as per
Unit: one tonne capacity
Considering a 250 tonne capacity bearing
for this analysis
a) Labour
Mate day 0.06 150.00 9.00 L-12
Mazdoor day 1.00 100.00 100.00 L-13
Mazdoor (Skilled) day 0.50 125.00 62.50 L-15
b) Material
Forged steel roller bearing of 250 tonne each. 1.00 60000.00 60000.00 M-067
design load capacity duly painted
complete with all its components as per
drawing and specifications
Add 1 per cent of cost of bearing 600.00
assembly for foundation anchorage
bolts, lifting arrangements, grease and
other consumables.
c) Overhead charges @ 10 % on 6077.15
(a+b) Contractor's profit @ 10 % on
d) 6684.87
(a+b+c)
cost for 250 tonnes capacity bearing = 73533.52
a+b+c+dper
Rate tonne capacity = 294.13
(a+b+c+d)/250 say 294.00
13.1 2000 Supplying, fitting and fixing in position
3 & true to line and level sliding plate
2200 bearing with PTFE surface sliding on
stainless steel complete including all
accessories as per drawing and
Technical Specifications and BS: 5400,
section 9.1 & 9.2 (for PTFE) and
clause 2004 of MoRTH Specifications.
Unit: one tonne capacity
Considering a 80 tonne capacity bearing for
this analysis
a) Labour
Mate day 0.06 150.00 9.00 L-12
Mazdoor day 1.00 100.00 100.00 L-13
Mazdoor (Skilled) day 0.50 125.00 62.50 L-15
b) Material
PTFE sliding plate bearing assembly of each. 1.00 25000.00 25000.00 M-069
80 tonnes design load capacity duly
painted complete with all its
components as per drawing and
Technical Specifications
Add 1 per cent for foundation 250.00
anchorage bolts and consumables.
c) Overhead charges @ 10 % on 2542.15
(a+b)
d) Contractor's profit @ 10 % on 2796.37
(a+b+c)
cost for 80 tonnes capacity bearing = 30760.02
a+b+c+d
Page 15 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Rate per tonne capacity = 384.50
(a+b+c+d)/80 say 385.00
13.1 2000 Supplying, fitting and fixing in position
4 & true to line and level elastomeric
2200 bearing conforming to IRC: 83 (Part-II)
section IX and clause 2005 of MoRTH
specifications complete including all
accessories as per drawing and
Unit: one cubic centimetre
Considering an elastomeric bearing of size
500 x 400 x 96 mm for this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size
reinforcing steel plates = 4545 cu.cm.
Hence volume of elastometer = 14655
cu.cm.Labour
a)
Mate day 0.06 150.00 9.00 L-12
Mazdoor day 1.00 100.00 100.00 L-13
Mazdoor (Skilled) day 0.50 125.00 62.50 L-15
b) Material
Elastomeric bearing assembly each. 1.00 12000.00 12000.00 M-066
consisting of 7 layers of elastomer
bonded to 6 nos. internal reinforcing
steel laminates by the process of
vulcanisation, complete with all
components as per drawing and
Add 1 per cent of cost of bearing 120.00
assembly for foundation anchorage
c) bolts and consumables.
Overhead charges @ 10 % on 1229.15
(a+b)
d) Contractor's profit @ 10 % on 1352.07
(a+b+c)
cost for 19200cc of elastomeric bearing = 14872.72
a+b+c+d
Rate per cc of elastomeric bearing = 0.77
(a+b+c+d)/19200
say 0.80
13.1 2000 Supplying, fitting and fixing in position
5 & true to line and level sliding plate
2200 bearing with stainless steel plate
sliding on stainless steel plate with
mild steel matrix complete including
all accessories as per drawing and
Unit: one tonne capacity
Considering the sliding bearing of 80 tonnes
design capacity for this analysis.
a) Labour
Mate day 0.04 150.00 6.00 L-12
Mazdoor day 0.75 100.00 75.00 L-13
Mazdoor (Skilled) day 0.35 125.00 43.75 L-15
b) Material
Supply of sliding plate bearing of 80 each. 1.00 25000.00 25000.00 M-070
tonne design capacity complete as per
drawings and Technical Specifications.
Add 1 per cent of cost of bearing 250.00
assembly for foundation anchorage
c) bolts and consumables.
Overhead charges @ 10 % on 2537.48
(a+b)
d) Contractor's profit @ 10 % on 2791.22
(a+b+c)
cost for 80 tonnes of capacity bearing = 30703.45
a+b+c+d 383.79
say 384.00

Page 16 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
13.1 Spec.
2000 Supplying, fitting and fixing in position
6 & true to line and level POT-PTFE bearing
2200 consisting of a metal piston supported
by a disc or unreinforced elastomer
confined within a metal cylinder,
sealing rings, dust seals, PTFE surface
sliding against stainless steel mating
surface, complete assembly to be of
cast steel/fabricated structural steel,
metal and elastomer elements to be as
per IRC: 83 part-I & II respectively and
other parts conforming to BS: 5400,
section 9.1 & 9.2 and clause 2006 of
MoRTH Specifications complete as per
Unit: one tonne capacity 387.20
Considering a Pot bearing assembly of 250
tonne capacity for this analysis.
a) Labour
Mate day 0.08 150.00 12.00 L-12
Mazdoor day 1.50 100.00 150.00 L-13
Mazdoor (Skilled) day 0.50 125.00 62.50 L-15
b) Material
Pot type bearing assembly consisting of each. 1.00 100000.00 ### M-068
a metal piston supported by a disc,
PTFE pads providing sliding surfaces
against stainless steel mating together
with cast steel assemblies/fabricated
structural steel assemblies duly painted
with all components as per clause 2006
and complete as per drawings and
Technical
Add 1 per Specifications.
cent of cost of bearing 1000.00
assembly for foundation anchorage
c) bolts and consumables.
Overhead charges @ 10 % on 10122.45
(a+b)
d) Contractor's profit @ 10 % on 11134.70
(a+b+c)
cost for 250 tonnes capacity bearing = ###
a+b+c+d
Rate per tonne capacity = 489.93
(a+b+c+d)/250 say 490.00

Page 17 of 361
CHAPTER-14
Ref. SUPER-STRUCTURE
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec.
14.1 1500 Furnishing and Placing Reinforced/
&160 Prestressed cement concrete in super-
0 structure as per drawing and Technical
1700 Specification
A RCC Grade M20
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.12 4180.00 21401.60 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.86 150.00 129.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Basic Cost of Labour, Material & 34804.00 079
Machinery (a+b+c) for 15 cum
For formwork and staging add the
14.1A (i) following:
For solid slab super-structure, 20-30
Case I per cent of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery 34804.00
(a+b+c) for 15 cum
d) Formwork and staging 20 per 20.00 6960.80
cent of (a+b+c)
e) Overhead charges @ 10 % on 4176.48
(a+b+c+d)
f) Contractor's profit @ 10 % on 4594.13
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 50535.41
Rate per cum = (a+b+c+d+e+f)/15 3369.03
say 3369.00
14.1A (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery 34804.00
(a+b+c) for 15 cum
d) Formwork and staging 25 per 25.00 8701.00
cent of (a+b+c)
e) Overhead charges @ 10 % on 4350.50
(a+b+c+d)
f) Contractor's profit @ 10 % on 4785.55
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 52641.05
Rate per cum = (a+b+c+d+e+f)/15 3509.40
say 3509.00
14.1A (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery 34804.00
(a+b+c) for 15 cum
d) Formwork and staging 30 per 30.00 10441.20
cent of (a+b+c)
e) Overhead charges @ 10 % on 4524.52
(a+b+c+d)
f) Contractor's profit @ 10 % on 4976.97
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 54746.69
Rate per cum = (a+b+c+d+e+f)/15 3649.78
say 3650.00

Page 1 of 361
14.1A (ii) For T-beam & slab, 25-35 per cent of
Case I (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery 34804.00
(a+b+c) for 15 cum
d) Formwork and staging 25 per 25.00 8701.00
cent of (a+b+c)
e) Overhead charges @ 10 % on 4350.50
(a+b+c+d)
f) Contractor's profit @ 10 % on 4785.55
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 52641.05
Rate per cum = (a+b+c+d+e+f)/15 3509.40
say 3509.00
14.1A (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery 34804.00
(a+b+c) for 15 cum
d) Formwork and staging 30 per 30.00 10441.20
cent of (a+b+c)
e) Overhead charges @ 10 % on 4524.52
(a+b+c+d)
f) Contractor's profit @ 10 % on 4976.97
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 54746.69
Rate per cum = (a+b+c+d+e+f)/15 3649.78
say 3650.00
14.1A (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery 34804.00
(a+b+c) for 15 cum
d) Formwork and staging 35 per 35.00 12181.40
cent of (a+b+c)
e) Overhead charges @ 10 % on 4698.54
(a+b+c+d)
f) Contractor's profit @ 10 % on 5168.39
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 56852.33
Rate per cum = (a+b+c+d+e+f)/15 3790.16
say 3790.00
14.1A Case Using Batching Plant, Transit Mixer
II and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 4180.00 171045.60 M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
b) Labour
Mate day 0.84 150.00 126.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer ( capacity 4.0 cu.m ) 017
Transit Mixer 4 cum capacity lead upto1 hour 15.00 600.00 9000.00 P&M-
Km
Lead beyond 1 Km, L - lead in Kilometer tonne.k 300L 1.85 11100.00 049
Lead
m =20 km
& P&M-
050
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Basic Cost of Labour, Material & 266542.00 007
Machinery (a+b+c) for 120 cum
For formwork and staging add the
following:

Page 2 of 361
14.1A (i) For solid slab super-structure, 20-30
Case per cent of (a+b+c)
II (p) Height upto 5m
Basic Cost of Labour, Material & Machinery 266542.00
(a+b+c) for 120 cum
d) Formwork and staging 20 per 20.00 53308.40
cent of (a+b+c)
e) Overhead charges @ 10 % on 31985.04
(a+b+c+d)
f) Contractor's profit @ 10 % on 35183.54
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 387018.98
Rate per cum = (a+b+c+d+e+f)/120 3225.16
say 3225.00
14.1A (q) Height 5m to 10m
Case
II (i)
Basic Cost of Labour, Material & Machinery 266542.00
(a+b+c) for 120 cum
d) Formwork and staging 25 per 25.00 66635.50
cent of (a+b+c)
e) Overhead charges @ 10 % on 33317.75
(a+b+c+d)
f) Contractor's profit @ 10 % on 36649.53
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 403144.78
Rate per cum = (a+b+c+d+e+f)/120 3359.54
say 3360.00
14.1A (r) Height above 10m
Case
II (i)
Basic Cost of Labour, Material & Machinery 266542.00
(a+b+c) for 120 cum
d) Formwork and staging 30 per 30.00 79962.60
cent of (a+b+c)
e) Overhead charges @ 10 % on 34650.46
(a+b+c+d)
f) Contractor's profit @ 10 % on 38115.51
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 419270.57
Rate per cum = (a+b+c+d+e+f)/120 3493.92
say 3494.00
14.1A (ii) For T-beam & slab, 25-35 per cent of
Case (a+b+c)
II (p) Height upto 5m
Basic Cost of Labour, Material & Machinery 266542.00
(a+b+c) for 120 cum
d) Formwork and staging 25 per 25.00 66635.50
cent of (a+b+c)
e) Overhead charges @ 10 % on 33317.75
(a+b+c+d)
f) Contractor's profit @ 10 % on 36649.53
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 403144.78
Rate per cum = (a+b+c+d+e+f)/120 3359.54
say 3360.00
14.1A (q) Height 5m to 10m
Case
II (ii)
Basic Cost of Labour, Material & Machinery 266542.00
(a+b+c) for 120 cum
d) Formwork and staging 30 per 30.00 79962.60
cent of (a+b+c)
e) Overhead charges @ 10 % on 34650.46
(a+b+c+d)
f) Contractor's profit @ 10 % on 38115.51
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 419270.57
Rate per cum = (a+b+c+d+e+f)/120 3493.92
say 3494.00
14.1A (r) Height above 10m
Case
II (ii)

Page 3 of 361
Basic Cost of Labour, Material & Machinery 266542.00
(a+b+c) for 120 cum
d) Formwork and staging 35 per 35.00 93289.70
cent of (a+b+c)
e) Overhead charges @ 10 % on 35983.17
(a+b+c+d)
f) Contractor's profit @ 10 % on 39581.49
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 435396.36
Rate per cum = (a+b+c+d+e+f)/120 3628.30
say 3628.00
14.1 B RCC Grade M25
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 5.99 4180.00 25038.20 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.86 150.00 129.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Basic Cost of Labour, Material & 38440.00 079
Machinery (a+b+c) for 15 cum
For formwork and staging add the
14.1B (i) following:
For solid slab super-structure, 20-30
Case I per cent of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery 38440.00
(a+b+c) for 15 cum
d) Formwork and staging 20 per 20.00 7688.00
cent of (a+b+c)
e) Overhead charges @ 10 % on 4612.80
(a+b+c+d)
f) Contractor's profit @ 10 % on 5074.08
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 55814.88
Rate per cum = (a+b+c+d+e+f)/15 3720.99
say 3721.00
14.1B (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery 38440.00
(a+b+c) for 15 cum
d) Formwork and staging 25 per 25.00 9610.00
cent of (a+b+c)
e) Overhead charges @ 10 % on 4805.00
(a+b+c+d)
f) Contractor's profit @ 10 % on 5285.50
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 58140.50
Rate per cum = (a+b+c+d+e+f)/15 3876.03
say 3876.00
14.1B (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery 38440.00
(a+b+c) for 15 cum
d) Formwork and staging 30 per 30.00 11532.00
cent of (a+b+c)
e) Overhead charges @ 10 % on 4997.20
(a+b+c+d)
f) Contractor's profit @ 10 % on 5496.92
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 60466.12

Page 4 of 361
Rate per cum = (a+b+c+d+e+f)/15 4031.07
say 4031.00
14.1B (ii) For T-beam & slab, 25-35 per cent of
Case I (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery 38440.00
(a+b+c) for 15 cum
d) Formwork and staging 25 per 25.00 9610.00
cent of (a+b+c)
e) Overhead charges @ 10 % on 4805.00
(a+b+c+d)
f) Contractor's profit @ 10 % on 5285.50
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 58140.50
Rate per cum = (a+b+c+d+e+f)/15 3876.03
say 3876.00
14.1B (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery 38440.00
(a+b+c) for 15 cum
d) Formwork and staging 30 per 30.00 11532.00
cent of (a+b+c)
e) Overhead charges @ 10 % on 4997.20
(a+b+c+d)
f) Contractor's profit @ 10 % on 5496.92
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 60466.12
Rate per cum = (a+b+c+d+e+f)/15 4031.07
say 4031.00
14.1B (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery 38440.00
(a+b+c) for 15 cum
d) Formwork and staging 35 per 35.00 13454.00
cent of (a+b+c)
e) Overhead charges @ 10 % on 5189.40
(a+b+c+d)
f) Contractor's profit @ 10 % on 5708.34
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 62791.74
Rate per cum = (a+b+c+d+e+f)/15 4186.12
say 4186.00
14.1B Case Using Batching Plant, Transit Mixer
II and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 47.95 4180.00 200431.00 M-081
Coarse sand cum 54.20 160.00 8672.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
b) Labour
Mate day 0.84 150.00 126.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 18.00 100.00 1800.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer ( capacity 4.0 cu.m ) 017
Transit Mixer 4 cum capacity lead upto1 hour 15.00 600.00 9000.00 P&M-
Km
Lead beyond 1 Km, L - lead in Kilometer tonne.k 300L 1.85 11100.00 049
Lead
m =20 km
& P&M-
050
Concrete Pump hour 6.00 500.00 3000.00 P&M-
007

Page 5 of 361
Basic Cost of Labour, Material & 295959.00
Machinery (a+b+c) for 120 cum
For formwork and staging add the
14.1B (i) following:
For solid slab super-structure, 20-30
Case per cent of (a+b+c)
II (p) Height upto 5m
Basic Cost of Labour, Material & Machinery 295959.00
(a+b+c) for 120 cum
d) Formwork and staging 20 per 20.00 59191.80
cent of (a+b+c)
e) Overhead charges @ 10 % on 35515.08
(a+b+c+d)
f) Contractor's profit @ 10 % on 39066.59
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 429732.47
Rate per cum = (a+b+c+d+e+f)/120 3581.10
say 3581.00
14.1B (q) Height 5m to 10m
Case
II (i)
Basic Cost of Labour, Material & Machinery 295959.00
(a+b+c) for 120 cum
d) Formwork and staging 25 per 25.00 73989.75
cent of (a+b+c)
e) Overhead charges @ 10 % on 36994.88
(a+b+c+d)
f) Contractor's profit @ 10 % on 40694.36
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 447637.99
Rate per cum = (a+b+c+d+e+f)/120 3730.32
say 3730.00
14.1B (r) Height above 10m
Case
II (i)
Basic Cost of Labour, Material & Machinery 295959.00
(a+b+c) for 120 cum
d) Formwork and staging 30 per 30.00 88787.70
cent of (a+b+c)
e) Overhead charges @ 10 % on 38474.67
(a+b+c+d)
f) Contractor's profit @ 10 % on 42322.14
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 465543.51
Rate per cum = (a+b+c+d+e+f)/120 3879.53
say 3880.00
14.1B (ii) For T-beam & slab, 25-35 per cent of
Case (a+b+c)
II (p) Height upto 5m
Basic Cost of Labour, Material & Machinery 295959.00
(a+b+c) for 120 cum
d) Formwork and staging 25 per 25.00 73989.75
cent of (a+b+c)
e) Overhead charges @ 10 % on 36994.88
(a+b+c+d)
f) Contractor's profit @ 10 % on 40694.36
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 447637.99
Rate per cum = (a+b+c+d+e+f)/120 3730.32
say 3730.00
14.1B (q) Height 5m to 10m
Case
II (ii)
Basic Cost of Labour, Material & Machinery 295959.00
(a+b+c) for 120 cum
d) Formwork and staging 30 per 30.00 88787.70
cent of (a+b+c)
e) Overhead charges @ 10 % on 38474.67
(a+b+c+d)
f) Contractor's profit @ 10 % on 42322.14
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 465543.51
Rate per cum = (a+b+c+d+e+f)/120 3879.53
say 3880.00

Page 6 of 361
14.1B (r) Height above 10m
Case
II (ii)
Basic Cost of Labour, Material & Machinery 295959.00
(a+b+c) for 120 cum
d) Formwork and staging 35 per 35.00 103585.65
cent of (a+b+c)
e) Overhead charges @ 10 % on 39954.47
(a+b+c+d)
f) Contractor's profit @ 10 % on 43949.91
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 483449.03
Rate per cum = (a+b+c+d+e+f)/120 4028.74
say 4029.00
14.1 C RCC Grade M 30
Case I Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.10 4180.00 25498.00 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.90 150.00 135.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 21.00 100.00 2100.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Basic Cost of Labour, Material & 39006.00 079
Machinery (a+b+c) for 15 cum
For formwork and staging add the
14.1C (i) following:
For solid slab super-structure, 20-30
Case I per cent of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery 39006.00
(a+b+c) for 15 cum
d) Formwork and staging 20 per 20.00 7801.20
cent of (a+b+c)
e) Overhead charges @ 10 % on 4680.72
(a+b+c+d)
f) Contractor's profit @ 10 % on 5148.79
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 56636.71
Rate per cum = (a+b+c+d+e+f)/15 3775.78
say 3776.00
14.1C (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery 39006.00
(a+b+c) for 15 cum
d) Formwork and staging 25 per 25.00 9751.50
cent of (a+b+c)
e) Overhead charges @ 10 % on 4875.75
(a+b+c+d)
f) Contractor's profit @ 10 % on 5363.33
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 58996.58
Rate per cum = (a+b+c+d+e+f)/15 3933.11
say 3933.00
14.1C (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery 39006.00
(a+b+c) for 15 cum
d) Formwork and staging 30 per 30.00 11701.80
cent of (a+b+c)
e) Overhead charges @ 10 % on 5070.78
(a+b+c+d)
Page 7 of 361
f) Contractor's profit @ 10 % on 5577.86
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 61356.44
Rate per cum = (a+b+c+d+e+f)/15 4090.43
say 4090.00
14.1C (ii) For T-beam & slab, 25-35 per cent of
Case I (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery 39006.00
(a+b+c) for 15 cum
d) Formwork and staging 25 per 25.00 9751.50
cent of (a+b+c)
e) Overhead charges @ 10 % on 4875.75
(a+b+c+d)
f) Contractor's profit @ 10 % on 5363.33
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 58996.58
Rate per cum = (a+b+c+d+e+f)/15 3933.11
say 3933.00
14.1C (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery 39006.00
(a+b+c) for 15 cum
d) Formwork and staging 30 per 30.00 11701.80
cent of (a+b+c)
e) Overhead charges @ 10 % on 5070.78
(a+b+c+d)
f) Contractor's profit @ 10 % on 5577.86
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 61356.44
Rate per cum = (a+b+c+d+e+f)/15 4090.43
say 4090.00
14.1C (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery 39006.00
(a+b+c) for 15 cum
d) Formwork and staging 35 per 35.00 13652.10
cent of (a+b+c)
e) Overhead charges @ 10 % on 5265.81
(a+b+c+d)
f) Contractor's profit @ 10 % on 5792.39
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 63716.30
Rate per cum = (a+b+c+d+e+f)/15 4247.75
say 4248.00
14.1C Case Using Batching Plant, Transit Mixer
II and Concrete Pump.
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 4180.00 203942.20 M-081
Coarse sand cum 54.60 160.00 8736.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
b) Labour
Mate day 0.88 150.00 132.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 19.00 100.00 1900.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer ( capacity 4.0 cu.m ) 017
Transit Mixer 4 cum capacity lead upto1 hour 15.00 600.00 9000.00 P&M-
Km
Lead beyond 1 Km, L - lead in Kilometer tonne.k 300L 1.85 11100.00 049
Lead
m =20 km
& P&M-
050

Page 8 of 361
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Basic Cost of Labour, Material & 299641.00 007
Machinery (a+b+c) for 120 cum
For formwork and staging add the
14.1C (i) following:
For solid slab super-structure, 20-30
Case per cent of (a+b+c)
II (p) Height upto 5m
Basic Cost of Labour, Material & Machinery 299641.00
(a+b+c) for 120 cum
d) Formwork and staging 20 per 20.00 59928.20
cent of (a+b+c)
e) Overhead charges @ 10 % on 35956.92
(a+b+c+d)
f) Contractor's profit @ 10 % on 39552.61
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 435078.73
Rate per cum = (a+b+c+d+e+f)/120 3625.66
say 3626.00
14.1C (q) Height 5m to 10m
Case
II (i)
Basic Cost of Labour, Material & Machinery 299641.00
(a+b+c) for 120 cum
d) Formwork and staging 25 per 25.00 74910.25
cent of (a+b+c)
e) Overhead charges @ 10 % on 37455.13
(a+b+c+d)
f) Contractor's profit @ 10 % on 41200.64
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 453207.01
Rate per cum = (a+b+c+d+e+f)/120 3776.73
say 3777.00
14.1C (r) Height above 10m
Case
II (i)
Basic Cost of Labour, Material & Machinery 299641.00
(a+b+c) for 120 cum
d) Formwork and staging 30 per 30.00 89892.30
cent of (a+b+c)
e) Overhead charges @ 10 % on 38953.33
(a+b+c+d)
f) Contractor's profit @ 10 % on 42848.66
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 471335.29
Rate per cum = (a+b+c+d+e+f)/120 3927.79
say 3928.00
14.1C (ii) For T-beam & slab, 25-35 per cent of
Case (a+b+c)
II (p) Height upto 5m
Basic Cost of Labour, Material & Machinery 299641.00
(a+b+c) for 120 cum
d) Formwork and staging 25 per 25.00 74910.25
cent of (a+b+c)
e) Overhead charges @ 10 % on 37455.13
(a+b+c+d)
f) Contractor's profit @ 10 % on 41200.64
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 453207.01
Rate per cum = (a+b+c+d+e+f)/120 3776.73
say 3777.00
14.1C (q) Height 5m to 10m
Case
II (ii)
Basic Cost of Labour, Material & Machinery 299641.00
(a+b+c) for 120 cum
d) Formwork and staging 30 per 30.00 89892.30
cent of (a+b+c)
e) Overhead charges @ 10 % on 38953.33
(a+b+c+d)
f) Contractor's profit @ 10 % on 42848.66
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 471335.29
Rate per cum = (a+b+c+d+e+f)/120 3927.79

Page 9 of 361
say 3928.00
14.1C (r) Height above 10m
Case
II (ii)
Basic Cost of Labour, Material & Machinery 299641.00
(a+b+c) for 120 cum
d) Formwork and staging 35 per 35.00 104874.35
cent of (a+b+c)
e) Overhead charges @ 10 % on 40451.54
(a+b+c+d)
f) Contractor's profit @ 10 % on 44496.69
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 489463.57
Rate per cum = (a+b+c+d+e+f)/120 4078.86
say 4079.00
14.1 D RCC/PSC Grade M35
Case I Using Concrete Mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 4180.00 26459.40 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
b) Labour
Mate day 0.90 150.00 135.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 21.00 100.00 2100.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Basic Cost of Labour, Material & 39967.00 079
Machinery (a+b+c) for 15 cum
For formwork and staging add the
14.1D (i) following:
For solid slab super-structure, 18-28
Case I per cent of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery 39967.00
(a+b+c) for 15 cum
d) Formwork and staging 18 per 18.00 7194.06
cent of (a+b+c)
e) Overhead charges @ 10 % on 4716.11
(a+b+c+d)
f) Contractor's profit @ 10 % on 5187.72
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 57064.88
Rate per cum = (a+b+c+d+e+f)/15 3804.33
say 3804.00
14.1D (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery 39967.00
(a+b+c) for 15 cum
d) Formwork and staging 23 per 23.00 9192.41
cent of (a+b+c)
e) Overhead charges @ 10 % on 4915.94
(a+b+c+d)
f) Contractor's profit @ 10 % on 5407.54
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 59482.89
Rate per cum = (a+b+c+d+e+f)/15 3965.53
say 3966.00
14.1D (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery 39967.00
(a+b+c) for 15 cum
d) Formwork and staging 28 per 28.00 11190.76
cent of (a+b+c)

Page 10 of 361
e) Overhead charges @ 10 % on 5115.78
(a+b+c+d)
f) Contractor's profit @ 10 % on 5627.35
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 61900.89
Rate per cum = (a+b+c+d+e+f)/15 4126.73
say 4127.00
14.1D (ii) For T-beam & slab, 23-33 per cent of
Case I (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery 39967.00
(a+b+c) for 15 cum
d) Formwork and staging 23 per 23.00 9192.41
cent of (a+b+c)
e) Overhead charges @ 10 % on 4915.94
(a+b+c+d)
f) Contractor's profit @ 10 % on 5407.54
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 59482.89
Rate per cum = (a+b+c+d+e+f)/15 3965.53
say 3966.00
14.1D (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery 39967.00
(a+b+c) for 15 cum
d) Formwork and staging 28 per 28.00 11190.76
cent of (a+b+c)
e) Overhead charges @ 10 % on 5115.78
(a+b+c+d)
f) Contractor's profit @ 10 % on 5627.35
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 61900.89
Rate per cum = (a+b+c+d+e+f)/15 4126.73
say 4127.00
14.1D (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery 39967.00
(a+b+c) for 15 cum
d) Formwork and staging 33 per 33.00 13189.11
cent of (a+b+c)
e) Overhead charges @ 10 % on 5315.61
(a+b+c+d)
f) Contractor's profit @ 10 % on 5847.17
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 64318.89
Rate per cum = (a+b+c+d+e+f)/15 4287.93
say 4288.00
14.1D (iii) For box girder and balanced
Case I cantilever, 38-58 per cent of cost of
(p) concrete.
Height upto 5m
Basic Cost of Labour, Material & Machinery 39967.00
(a+b+c) for 15 cum
d) Formwork and staging 38 per 38.00 15187.46
cent of (a+b+c)
e) Overhead charges @ 10 % on 5515.45
(a+b+c+d)
f) Contractor's profit @ 10 % on 6066.99
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 66736.90
Rate per cum = (a+b+c+d+e+f)/15 4449.13
say 4449.00
14.1D (q) Height 5m to 10m
Case I
(iii)
Basic Cost of Labour, Material & Machinery 39967.00
(a+b+c) for 15 cum
d) Formwork and staging 48 per 48.00 19184.16
cent of (a+b+c)
e) Overhead charges @ 10 % on 5915.12
(a+b+c+d)
f) Contractor's profit @ 10 % on 6506.63
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 71572.90

Page 11 of 361
Rate per cum = (a+b+c+d+e+f)/15 4771.53
say 4772.00
14.1D (r) Height above 10m
Case I
(iii)
Basic Cost of Labour, Material & Machinery 39967.00
(a+b+c) for 15 cum
d) Formwork and staging 58 per 58.00 23180.86
cent of (a+b+c)
e) Overhead charges @ 10 % on 6314.79
(a+b+c+d)
f) Contractor's profit @ 10 % on 6946.26
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 76408.91
Rate per cum = (a+b+c+d+e+f)/15 5093.93
say 5094.00
Case Using Batching Plant, Transit Mixer
II and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 4180.00 211675.20 M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
b) Labour
Mate day 0.88 150.00 132.00 L-12
Mason day 3.00 250.00 750.00 L-11
Mazdoor day 19.00 100.00 1900.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer ( capacity 4.0 cu.m ) 017
Transit Mixer 4 cum capacity lead upto1 hour 15.00 600.00 9000.00 P&M-
Km
Lead beyond 1 Km, L - lead in Kilometer tonne.k 300L 1.85 11100.00 049
Lead
m =20 km
& P&M-
050
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Basic Cost of Labour, Material & 307278.00 007
Machinery (a+b+c) for 120 cum
For formwork and staging add the
14.1D (i) following:
For solid slab super-structure, 18-28
Case per cent of (a+b+c)
II (p) Height upto 5m
Basic Cost of Labour, Material & Machinery 307278.00
(a+b+c) for 120 cum
d) Formwork and staging 18 per 18.00 55310.04
cent of (a+b+c)
e) Overhead charges @ 10 % on 36258.80
(a+b+c+d)
f) Contractor's profit @ 10 % on 39884.68
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 438731.53
Rate per cum = (a+b+c+d+e+f)/120 3656.10
say 3656.00
14.1D (q) Height 5m to 10m
Case
II (i)
Basic Cost of Labour, Material & Machinery 307278.00
(a+b+c) for 120 cum
d) Formwork and staging 23 per 23.00 70673.94
cent of (a+b+c)
e) Overhead charges @ 10 % on 37795.19
(a+b+c+d)
f) Contractor's profit @ 10 % on 41574.71
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 457321.85

Page 12 of 361
Rate per cum = (a+b+c+d+e+f)/120 3811.02
say 3811.00
14.1D (r) Height above 10m
Case
II (i)
Basic Cost of Labour, Material & Machinery 307278.00
(a+b+c) for 120 cum
d) Formwork and staging 28 per 28.00 86037.84
cent of (a+b+c)
e) Overhead charges @ 10 % on 39331.58
(a+b+c+d)
f) Contractor's profit @ 10 % on 43264.74
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 475912.17
Rate per cum = (a+b+c+d+e+f)/120 3965.93
say 3966.00
14.1D (ii) For T-beam & slab, 23-33 per cent of
Case (a+b+c)
II (p) Height upto 5m
Basic Cost of Labour, Material & Machinery 307278.00
(a+b+c) for 120 cum
d) Formwork and staging 23 per 23.00 70673.94
cent of (a+b+c)
e) Overhead charges @ 10 % on 37795.19
(a+b+c+d)
f) Contractor's profit @ 10 % on 41574.71
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 457321.85
Rate per cum = (a+b+c+d+e+f)/120 3811.02
say 3811.00
14.1D (q) Height 5m to 10m
Case
II (ii)
Basic Cost of Labour, Material & Machinery 307278.00
(a+b+c) for 120 cum
d) Formwork and staging 28 per 28.00 86037.84
cent of (a+b+c)
e) Overhead charges @ 10 % on 39331.58
(a+b+c+d)
f) Contractor's profit @ 10 % on 43264.74
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 475912.17
Rate per cum = (a+b+c+d+e+f)/120 3965.93
say 3966.00
14.1D (r) Height above 10m
Case
II (ii)
Basic Cost of Labour, Material & Machinery 307278.00
(a+b+c) for 120 cum
d) Formwork and staging 33 per 33.00 101401.74
cent of (a+b+c)
e) Overhead charges @ 10 % on 40867.97
(a+b+c+d)
f) Contractor's profit @ 10 % on 44954.77
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 494502.49
Rate per cum = (a+b+c+d+e+f)/120 4120.85
say 4121.00
14.1D (iii) For box girder and balanced
Case cantilever, 38-58 per cent of cost of
II (p) concrete.
Height upto 5m
Basic Cost of Labour, Material & Machinery 307278.00
(a+b+c) for 120 cum
d) Formwork and staging 38 per 38.00 116765.64
cent of (a+b+c)
e) Overhead charges @ 10 % on 42404.36
(a+b+c+d)
f) Contractor's profit @ 10 % on 46644.80
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 513092.80
Rate per cum = (a+b+c+d+e+f)/120 4275.77
say 4276.00

Page 13 of 361
14.1D (q) Height 5m to 10m
Case
II (iii)
Basic Cost of Labour, Material & Machinery 307278.00
(a+b+c) for 120 cum
d) Formwork and staging 48 per 48.00 147493.44
cent of (a+b+c)
e) Overhead charges @ 10 % on 45477.14
(a+b+c+d)
f) Contractor's profit @ 10 % on 50024.86
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 550273.44
Rate per cum = (a+b+c+d+e+f)/120 4585.61
say 4586.00
14.1D (r) Height above 10m
Case
II (iii)
Basic Cost of Labour, Material & Machinery 307278.00
(a+b+c) for 120 cum
d) Formwork and staging 58 per 58.00 178221.24
cent of (a+b+c)
e) Overhead charges @ 10 % on 48549.92
(a+b+c+d)
f) Contractor's profit @ 10 % on 53404.92
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 587454.08
Rate per cum = (a+b+c+d+e+f)/120 4895.45
say 4895.00
14.1 E PSC Grade M-40
Case Using concrete mixer.
1 Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.45 4180.00 26961.00 M-081
Coarse sand cum 6.75 350.00 2362.50 M-005
20 mm Aggregate cum 8.10 410.00 3321.00 M-053
10 mm Aggregate cum 5.40 410.00 2214.00 M-051
Admixture @ 0.4 per cent of cement kg 25.80 50.00 1290.00 M-180
b) Labour
Mate day 0.96 150.00 144.00 L-12
Mason day 2.00 250.00 500.00 L-11
Mazdoor day 22.00 100.00 2200.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 100.00 600.00 P&M-
Generator 33 KVA hour 6.00 400.00 2400.00 009
P&M-
Basic Cost of Labour, Material & 41993.00 079
Machinery (a+b+c) for 15 cum
For formwork and staging add the
14.1E (i) following:
For solid slab super-structure, 20-30
Case I per cent of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery 41993.00
(a+b+c) for 15 cum
d) Formwork and staging 20 per 20.00 8398.60
cent of (a+b+c)
e) Overhead charges @ 10 % on 5039.16
(a+b+c+d)
f) Contractor's profit @ 10 % on 5543.08
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 60973.84
Rate per cum = (a+b+c+d+e+f)/15 4064.92
say 4065.00
14.1E (q) Height 5m to 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery 41993.00
(a+b+c) for 15 cum
d) Formwork and staging 25 per 25.00 10498.25
cent of (a+b+c)

Page 14 of 361
e) Overhead charges @ 10 % on 5249.13
(a+b+c+d)
f) Contractor's profit @ 10 % on 5774.04
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 63514.41
Rate per cum = (a+b+c+d+e+f)/15 4234.29
say 4234.00
14.1E (r) Height above 10m
Case I
(i)
Basic Cost of Labour, Material & Machinery 41993.00
(a+b+c) for 15 cum
d) Formwork and staging 30 per 30.00 12597.90
cent of (a+b+c)
e) Overhead charges @ 10 % on 5459.09
(a+b+c+d)
f) Contractor's profit @ 10 % on 6005.00
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 66054.99
Rate per cum = (a+b+c+d+e+f)/15 4403.67
say 4404.00
14.1E (ii) For T-beam & slab, 25-35 per cent of
Case I (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery 41993.00
(a+b+c) for 15 cum
d) Formwork and staging 25 per 25.00 10498.25
cent of (a+b+c)
e) Overhead charges @ 10 % on 5249.13
(a+b+c+d)
f) Contractor's profit @ 10 % on 5774.04
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 63514.41
Rate per cum = (a+b+c+d+e+f)/15 4234.29
say 4234.00
14.1E (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery 41993.00
(a+b+c) for 15 cum
d) Formwork and staging 30 per 30.00 12597.90
cent of (a+b+c)
e) Overhead charges @ 10 % on 5459.09
(a+b+c+d)
f) Contractor's profit @ 10 % on 6005.00
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 66054.99
Rate per cum = (a+b+c+d+e+f)/15 4403.67
say 4404.00
14.1E (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery 41993.00
(a+b+c) for 15 cum
d) Formwork and staging 35 per 35.00 14697.55
cent of (a+b+c)
e) Overhead charges @ 10 % on 5669.06
(a+b+c+d)
f) Contractor's profit @ 10 % on 6235.96
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 68595.57
Rate per cum = (a+b+c+d+e+f)/15 4573.04
say 4573.00
14.1E Case Using Batching Plant, Transit Mixer
II and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 4180.00 215688.00 M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
Admixture @ 0.4 per cent of cement kg 206.40 50.00 10320.00 M-180

Page 15 of 361
b) Labour
Mate day 0.94 150.00 141.00 L-12
Mason day 3.50 250.00 875.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer ( capacity 4.0 cu.m ) 017
Transit Mixer 4 cum capacity lead upto1 hour 15.00 600.00 9000.00 P&M-
Km
Lead beyond 1 Km, L - lead in Kilometer tonne.k 300L 1.85 11100.00 049
Lead
m =20 km
& P&M-
050
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Basic Cost of Labour, Material & 321844.00 007
Machinery (a+b+c) for 120 cum
For formwork and staging add the
14.1E (i) following:
For solid/voided slab super-structure,
Case 18-28 per cent of (a+b+c)
II (p) Height upto 5m
Basic Cost of Labour, Material & Machinery 321844.00
(a+b+c) for 120 cum
d) Formwork and staging 18 per 18.00 57931.92
cent of (a+b+c)
e) Overhead charges @ 10 % on 37977.59
(a+b+c+d)
f) Contractor's profit @ 10 % on 41775.35
(a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 459528.86
Rate per cum = (a+b+c+d+e+f)/120 3829.41
say 3829.00
14.1E (q) Height 5m to 10m
Case
II (i)
Basic Cost of Labour, Material & Machinery 321844.00
(a+b+c) for 120 cum
d) Formwork and staging 23 per 23.00 74024.12
cent of (a+b+c)
e) Overhead charges @ 10 % on 39586.81
(a+b+c+d)
f) Contractor's profit @ 10 % on 43545.49
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 479000.43
Rate per cum = (a+b+c+d+e+f)/120 3991.67
say 3992.00
14.1E (r) Height above 10m
Case
II (i)
Basic Cost of Labour, Material & Machinery 321844.00
(a+b+c) for 120 cum
d) Formwork and staging 28 per 28.00 90116.32
cent of (a+b+c)
e) Overhead charges @ 10 % on 41196.03
(a+b+c+d)
f) Contractor's profit @ 10 % on 45315.64
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 498471.99
Rate per cum = (a+b+c+d+e+f)/120 4153.93
say 4154.00
14.1E (ii) For T-beam & slab, 23-33 per cent of
Case (a+b+c)
II (p) Height upto 5m
Basic Cost of Labour, Material & Machinery 321844.00
(a+b+c) for 120 cum
d) Formwork and staging 23 per 23.00 74024.12
cent of (a+b+c)
e) Overhead charges @ 10 % on 39586.81
(a+b+c+d)
f) Contractor's profit @ 10 % on 43545.49
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 479000.43

Page 16 of 361
Rate per cum = (a+b+c+d+e+f)/120 3991.67
say 3992.00
14.1E (q) Height 5m to 10m
Case
II (ii)
Basic Cost of Labour, Material & Machinery 321844.00
(a+b+c) for 120 cum
d) Formwork and staging 28 per 28.00 90116.32
cent of (a+b+c)
e) Overhead charges @ 10 % on 41196.03
(a+b+c+d)
f) Contractor's profit @ 10 % on 45315.64
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 498471.99
Rate per cum = (a+b+c+d+e+f)/120 4153.93
say 4154.00
14.1E (r) Height above 10m
Case
II (ii)
Basic Cost of Labour, Material & Machinery 321844.00
(a+b+c) for 120 cum
d) Formwork and staging 33 per 33.00 106208.52
cent of (a+b+c)
e) Overhead charges @ 10 % on 42805.25
(a+b+c+d)
f) Contractor's profit @ 10 % on 47085.78
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 517943.55
Rate per cum = (a+b+c+d+e+f)/120 4316.20
say 4316.00
14.1E (iii) For cast-in-situ box girder, segment
Case construction and balanced cantilever,
II 38-58 per cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery 321844.00
(a+b+c) for 120 cum
d) Formwork and staging 38 per 38.00 122300.72
cent of (a+b+c)
e) Overhead charges @ 10 % on 44414.47
(a+b+c+d)
f) Contractor's profit @ 10 % on 48855.92
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 537415.11
Rate per cum = (a+b+c+d+e+f)/120 4478.46
say 4478.00
14.1E (q) Height 5m to 10m
Case
II (iii)
Basic Cost of Labour, Material & Machinery 321844.00
(a+b+c) for 120 cum
d) Formwork and staging 48 per 48.00 154485.12
cent of (a+b+c)
e) Overhead charges @ 10 % on 47632.91
(a+b+c+d)
f) Contractor's profit @ 10 % on 52396.20
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 576358.24
Rate per cum = (a+b+c+d+e+f)/120 4802.99
say 4803.00
14.1E (r) Height above 10m
Case
II (iii)
Basic Cost of Labour, Material & Machinery 321844.00
(a+b+c) for 120 cum
d) Formwork and staging 58 per 58.00 186669.52
cent of (a+b+c)
e) Overhead charges @ 10 % on 50851.35
(a+b+c+d)
f) Contractor's profit @ 10 % on 55936.49
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 615301.36
Rate per cum = (a+b+c+d+e+f)/120 5127.51
say 5128.00

Page 17 of 361
14.1F F PSC Grade M-45
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 55.80 4180.00 233244.00 M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
Admixture @ 0.4 per cent of cement kg 223.20 50.00 11160.00 M-180
b) Labour
Mate day 0.94 150.00 141.00 L-12
Mason day 3.50 250.00 875.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer ( capacity 4.0 cu.m ) 017
Transit Mixer 4 cum capacity lead upto1 hour 15.00 600.00 9000.00 P&M-
Km
Lead beyond 1 Km, L - lead in Kilometer tonne.k 300L 1.85 11100.00 049
Lead
m =20 km
& P&M-
050
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Basic Cost of Labour, Material & 340240.00 007
Machinery (a+b+c) for 120 cum
For formwork and staging add the
14.1F (i) following:
For solid slab/voided slab super-
structure, 16-26 per cent of cost of
(p) concrete (a+b+c)
Height upto 5m
Basic Cost of Labour, Material & Machinery 340240.00
(a+b+c) for 120 cum
d) Formwork and staging 16 per 16.00 54438.40
cent of (a+b+c)
e) Overhead charges @ 10 % on 39467.84
(a+b+c+d)
f) Contractor's profit @ 10 % on 43414.62
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 477560.86
Rate per cum = (a+b+c+d+e+f)/120 3979.67
say 3980.00
14.1F (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery 340240.00
(a+b+c) for 120 cum
d) Formwork and staging 21 per 21.00 71450.40
cent of (a+b+c)
e) Overhead charges @ 10 % on 41169.04
(a+b+c+d)
f) Contractor's profit @ 10 % on 45285.94
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 498145.38
Rate per cum = (a+b+c+d+e+f)/120 4151.21
say 4151.00
14.1F (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery 340240.00
(a+b+c) for 120 cum
d) Formwork and staging 26 per 26.00 88462.40
cent of (a+b+c)
e) Overhead charges @ 10 % on 42870.24
(a+b+c+d)
f) Contractor's profit @ 10 % on 47157.26
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 518729.90
Rate per cum = (a+b+c+d+e+f)/120 4322.75
say 4323.00

Page 18 of 361
14.1F (ii) For T-beam & slab including launching
of precast girders by launching truss
upto 40 m span, 21-31 per cent of
cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery 340240.00
(a+b+c) for 120 cum
d) Formwork and staging 21 per 21.00 71450.40
cent of (a+b+c)
e) Overhead charges @ 10 % on 41169.04
(a+b+c+d)
f) Contractor's profit @ 10 % on 45285.94
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 498145.38
Rate per cum = (a+b+c+d+e+f)/120 4151.21
say 4151.00
14.1F (q) Height 5m to 10m
(ii)
Basic Cost of Labour, Material & Machinery 340240.00
(a+b+c) for 120 cum
d) Formwork and staging 26 per 26.00 88462.40
cent of (a+b+c)
e) Overhead charges @ 10 % on 42870.24
(a+b+c+d)
f) Contractor's profit @ 10 % on 47157.26
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 518729.90
Rate per cum = (a+b+c+d+e+f)/120 4322.75
say 4323.00
14.1F (r) Height above 10m
(ii)
Basic Cost of Labour, Material & Machinery 340240.00
(a+b+c) for 120 cum
d) Formwork and staging 31 per 31.00 105474.40
cent of (a+b+c)
e) Overhead charges @ 10 % on 44571.44
(a+b+c+d)
f) Contractor's profit @ 10 % on 49028.58
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 539314.42
Rate per cum = (a+b+c+d+e+f)/120 4494.29
say 4494.00
14.1F (iii) For cast-in-situ box girder, segmental
construction and balanced cantilever,
36-56 per cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery 340240.00
(a+b+c) for 120 cum
d) Formwork and staging 36 per 36.00 122486.40
cent of (a+b+c)
e) Overhead charges @ 10 % on 46272.64
(a+b+c+d)
f) Contractor's profit @ 10 % on 50899.90
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 559898.94
Rate per cum = (a+b+c+d+e+f)/120 4665.82
say 4666.00
14.1F (q) Height 5m to 10m
(iii)
Basic Cost of Labour, Material & Machinery 340240.00
(a+b+c) for 120 cum
d) Formwork and staging 46 per 46.00 156510.40
cent of (a+b+c)
e) Overhead charges @ 10 % on 49675.04
(a+b+c+d)
f) Contractor's profit @ 10 % on 54642.54
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 601067.98
Rate per cum = (a+b+c+d+e+f)/120 5008.90
say 5009.00
14.1F (r) Height above 10m
(iii)
Basic Cost of Labour, Material & Machinery 340240.00
(a+b+c) for 120 cum

Page 19 of 361
d) Formwork and staging 56 per 56.00 190534.40
cent of (a+b+c)
e) Overhead charges @ 10 % on 53077.44
(a+b+c+d)
f) Contractor's profit @ 10 % on 58385.18
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 642237.02
Rate per cum = (a+b+c+d+e+f)/120 5351.98
say 5352.00
14.1 G PSC Grade M-50
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 58.80 4180.00 245784.00 M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
Admixture @ 0.4 per cent of cement kg 235.20 50.00 11760.00 M-180
b) Labour
Mate day 0.94 150.00 141.00 L-12
Mason day 3.50 250.00 875.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer ( capacity 4.0 cu.m ) 017
Transit Mixer 4 cum capacity lead upto1 hour 15.00 600.00 9000.00 P&M-
Km
Lead beyond 1 Km, L - lead in Kilometer tonne.k 300L 1.85 11100.00 049
Lead
m =20 km
& P&M-
050
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Basic Cost of Labour, Material & 353380.00 007
Machinery (a+b+c) for 120 cum
For formwork and staging add the
14.1G (i) following:
For cast-in-situ box girder, segmental
construction and balanced cantilever,
35-55 per cent of cost of concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery 353380.00
(a+b+c) for 120 cum
d) Formwork and staging 35 per 35.00 123683.00
cent of (a+b+c)
e) Overhead charges @ 10 % on 47706.30
(a+b+c+d)
f) Contractor's profit @ 10 % on 52476.93
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 577246.23
Rate per cum = (a+b+c+d+e+f)/120 4810.39
say 4810.00
14.1G (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery 353380.00
(a+b+c) for 120 cum
d) Formwork and staging 45 per 45.00 159021.00
cent of (a+b+c)
e) Overhead charges @ 10 % on 51240.10
(a+b+c+d)
f) Contractor's profit @ 10 % on 56364.11
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 620005.21
Rate per cum = (a+b+c+d+e+f)/120 5166.71
say 5167.00
14.1G (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery 353380.00
(a+b+c) for 120 cum

Page 20 of 361
d) Formwork and staging 55 per 55.00 194359.00
cent of (a+b+c)
e) Overhead charges @ 10 % on 54773.90
(a+b+c+d)
f) Contractor's profit @ 10 % on 60251.29
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 662764.19
Rate per cum = (a+b+c+d+e+f)/120 5523.03
say 5523.00
14.1 H PSC Grade M- 55
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 63.50 4180.00 265430.00 M-081
Coarse sand cum 54.00 160.00 8640.00 M-004
20 mm Aggregate cum 64.80 410.00 26568.00 M-053
10 mm Aggregate cum 43.20 410.00 17712.00 M-051
Admixture @ 0.4 per cent of cement kg 254.00 50.00 12700.00 M-180
b) Labour
Mate day 0.94 150.00 141.00 L-12
Mason day 3.50 250.00 875.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1500.00 9000.00 P&M-
Generator 100 KVA hour 6.00 600.00 3600.00 002
P&M-
Loader hour 6.00 700.00 4200.00 080
P&M-
Transit Mixer ( capacity 4.0 cu.m ) 017
Transit Mixer 4 cum capacity lead upto1 hour 15.00 600.00 9000.00 P&M-
Km
Lead beyond 1 Km, L - lead in Kilometer tonne.k 300L 1.85 11100.00 049
Lead
m =20 km
& P&M-
050
Concrete Pump hour 6.00 500.00 3000.00 P&M-
Basic Cost of Labour, Material & 373966.00 007
Machinery (a+b+c) for 120 cum
For formwork and staging add the
(i) following:
For cast-in-situ box girder, segmental
14.1H construction and balanced cantilever,
35-55 per cent of cost of concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery 373966.00
(a+b+c) for 120 cum
d) Formwork and staging 35 per 35.00 130888.10
cent of (a+b+c)
e) Overhead charges @ 10 % on 50485.41
(a+b+c+d)
f) Contractor's profit @ 10 % on 55533.95
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 610873.46
Rate per cum = (a+b+c+d+e+f)/120 5090.61
say 5091.00
(q) Height 5m to 10m
14.1H
(i) Basic Cost of Labour, Material & Machinery 373966.00
(a+b+c) for 120 cum
d) Formwork and staging 45 per 45.00 168284.70
cent of (a+b+c)
e) Overhead charges @ 10 % on 54225.07
(a+b+c+d)
f) Contractor's profit @ 10 % on 59647.58
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 656123.35
Rate per cum = (a+b+c+d+e+f)/120 5467.69
say 5468.00
(r) Height above 10m
14.1H
(i) Basic Cost of Labour, Material & Machinery 373966.00
(a+b+c) for 120 cum

Page 21 of 361
d) Formwork and staging 55 per 55.00 205681.30
cent of (a+b+c)
e) Overhead charges @ 10 % on 57964.73
(a+b+c+d)
f) Contractor's profit @ 10 % on 63761.20
(a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 701373.23
Rate per cum = (a+b+c+d+e+f)/120 5844.78
say 5845.00
Note 1.Where ever concrete is carried out using
batching plant, transit mixer, concrete
pump, admixers conforming IS: 9103 @ 0.4
per cent of weight of cement may be
added for achieving desired slump of
2. Cement provided for various components
of the super structure is for estimating
purpose only. Actual quantity of cement will
be as per approved mix design. Similarly,
the provision for coarse and fine aggregates
is for estimating purpose and the exact
quantity shall be as per the mix design.
3. The items like needle and surface
vibrators are part of minor T & P which is
already covered under the overhead
charges. As such these items have not been
added separately in the rate analysis.
14.2 1600 Supplying, fitting and placing HYSD
bar reinforcement in super-structure
complete as per drawing and technical
specifications
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent for laps tonne 1.05 34500.00 36225.00 M-082
and wastage
Binding wire Kg 8.00 40.00 320.00 M-072
b) Labour for cutting, bending,
tying and placing in position
Mate day 0.44 150.00 66.00 L-12
Blacksmith day 3.00 150.00 450.00 L-02
Mazdoor day 8.00 100.00 800.00 L-13
Basic Cost of Labour & Material (a+b) 37861.00
c) Overhead charges @ 10 % on 3786.10
(a+b)
d) Contractor's profit @ 10 % on 4164.71
(a+b+c)
Rate per MT = a+b+c+d 45811.81
say 45812.00
14.3 1800 High tensile steel wires/strands
including all accessories for stressing,
stressing operations and grouting
complete as per drawing and Technical
Specifications
Unit = 1 MT
Taking output = 0.377 MT
Details of cost for 12T13 strand 40 m long
cable (weight = 0.377 MT)
a) Material
H.T. Strand @ 9.42 kg/m including 2 per tonne 0.39 45000.00 17325.00 M-119
cent for wastage and extra length for
jacking
Sheathing duct ID 66 mm along with 5 metre 42.00 250.00 10500.00 M-165
per cent extra length 40 x 1.05 = 42
m.
Tube anchorage set complete with each 2.00 1000.00 2000.00 M-187
bearing plate, permanent wedges etc
Cement for grouting including 3 per tonne 0.125 4180.00 522.50 M-081
cent wastage @ 3.00 kg/m = 3 x 1.03 x
40 = 123.60 kg (say, = 125 kg)
Add 0.50 per cent cost of material for 1517.38
Spacers, Insulation tape and
b) miscellaneous
Labour items
i) For making and fixing cables,
anchorages
Mate day 0.16 150.00 24.00 L-12
Blacksmith day 1.00 150.00 150.00 L-02

Page 22 of 361
Mazdoor day 3.00 100.00 300.00 L-13
ii) For prestressing
Mate/Supervisor day 0.05 150.00 7.50 L-12
Prestressing operator / Fitter day 0.25 150.00 37.50 L-08
Mazdoor day 1.00 100.00 100.00 L-13
iii) For grouting
Mate/Supervisor day 0.05 150.00 7.50 L-12
Mason day 0.25 250.00 62.50 L-11
Mazdoor day 1.00 100.00 100.00 L-13
c) Machinery
Stressing jack with pump hour 2.50 80.00 200.00 P&M-
Grouting pump with agitator hour 1.00 300.00 300.00 040
M-111
Generator 33 KVA. hour 3.50 400.00 1400.00 P&M-
d) Overhead charges @ 10 % on 268.90 079
(a+b+c)
e) Contractor's profit @ 10 % on 295.79
(a+b+c+d)
Cost for 0.377 MT (a+b+c+d+e) 35118.57
Rate per MT = (a+b+c+d+e)/0.377 93152.69
say 93153.00
Note Cost of HT steel has been taken for delivery
at site. Hence carriage has not been
14.4 2702 considered. and laying Cement concrete
Providing
wearing coat M-30 grade including
reinforcement complete as per
drawing and Technical Specifications
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer cum 1.00 2650.00 2650.00 Item
relevant item of concrete in Item 14.1 14.1(C)
excluding formwork
HYSD bar reinforcement Rate as per tonne 0.075 37861.00 2839.58 Item
item No 14.2(Excluding OH & CP) 14.2 A
b) Labour
Mazdoor for cleaning deck slab concrete day 0.15 100.00 15.00 L-13
c) surface.
Overhead charges @ 10 % on 550.46
(a+b)
d) Contractor's profit @ 10 % on 605.50
(a+b+c)
Rate per cum (a+b+c+d) 6660.54
say 6661.00
14.5 515 & Mastic Asphalt
2702
Providing and laying 12 mm thick
mastic asphalt wearing course on top
of deck slab excluding prime coat with
paving grade bitumen meeting the
requirements given in table 500-29,
prepared by using mastic cooker and
laid to required level and slope after
cleaning the surface, including
providing antiskid surface with
bitumen precoated fine grained hard
stone chipping of 9.5 mm nominal size
at the rate of 0.005cum per 10 sqm
and at an approximate spacing of 10
cm center to center in both directions,
pressed into surface when the
temperature of surfaces not less than
100 deg. C, protruding 1 mm to 4 mm
Unit = sqm
Taking output = 72.46 sqm (2 tonnes)
(0.869 cum) assuming a density of 2.3
tonnes/cum.
a) Labour
Mate day 0.49 150.00 73.50 L-12
Mazdoor day 11.00 100.00 1100.00 L-13
Mazdoor (Skilled) day 1.25 125.00 156.25 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour 0.06 150.00 9.00 P&M-
hour
Air compressor 250 cfm hour 0.06 150.00 9.00 031
P&M-
001

Page 23 of 361
Mastic cooker 1 tonne capacity hour 6.00 40.00 240.00 P&M-
Bitumen boiler 1500 litres capacity hour 6.00 150.00 900.00 030
P&M-
Tractor for towing and positioning of hour 1.00 150.00 150.00 005
P&M-
mastic cooker and bitumen boiler 053
c) Material
Base mastic (without coarse aggregates) =
60 per cent
Coarse aggregate(3.35mm to 9.5 mm size)
= 40 per cent .
Proportion of material required for mastic
asphalt with coarse aggregates (based on
mix design done by CRRI for a specific case)
i) Bitumen 80/100 or 60/70 or 30/40 @ tonne 0.204 27030.00 5514.12 M-074
10.2 per cent by weight of mix. 2 x
10.2/100 = stone
ii) Crusher 0.204dust @ 31.9 per cent cum 0.39 200.00 78.00 M-021
by weight of mix = 2 x 31.9/100 =
0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium tonne 0.36 2400.00 864.00 M-188
carbonate content not less than 80 per
cent by weight @ 17.92 per cent by
weight of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 9.5 mm to 3.35 cum 0.55 410.00 225.50 M-051
mm size @ 40 per cent by weight of
mix = 2 x 40/100 = 0.8 MT = 0.8/1.456
= 0.55
v) Pre-coated stone chips of 9.5 mm cum 0.036 900.00 32.40 M-142
nominal size for skid resistance =
72.46x0.005/10 = 0.036of chips @ 2 per
vi) Bitumen for coating kg 1.05 27.03 28.38 M-
cent by weight = 0.036 x 1.456 x 074/100
2/100 = 0.001048MT = 1.05kg 0
d) Overhead charges @ 10 % on 938.02
(a+b+c)
e) Contractor's profit @ 10 % on 1031.82
(a+b+c+d)
Cost for 72.46 sqm = a+b+c+d+e 11349.98
Rate per sqm = (a+b+c+d+e)/72.46 156.64
say 157.00
Note 1.The rates for 6 mm or any other thickness
may be worked out on pro-rata basis.
2. Where tack coat is required to be
provided before laying mastic asphalt, the
same is required to be measured and paid
separately.
3.The quantities of binder, filler and
aggregates are for estimating purpose.
Exact quantities shall be as per mix design.
4.This rate analysis is based on design
made by CRRI for a specific case and is
meant for estimating purposes only. Actual
design is required to be done for each case.
5.The quantity of bitumen works out 17 per
cent of the mastic asphalt blocks without
aggregates and falls within the standards
laid down by MoRTH Specifications.
14.6 2703, Construction of precast RCC railing of
1500, M30 Grade, aggregate size not
1600 exceeding 12 mm, true to line and
& grade, tolerance of vertical RCC post
1700 not to exceed 1 in 500, centre to
centre spacing between vertical post
not to exceed 2000 mm, leaving
adequate space between vertical post
for expansion, complete as per
approved
Unit = 1 RM drawings and technical
Taking output = 2 x 24 m span = 48 m
a) Material
Cement concreteM30 Grade Refer cum 4.09 2497.00 10217.72 Item
relevant item of concrete in Item 14.1(C)
14.1(C) by using batching plant,
excluding formwork i.e. per cum basic

Page 24 of 361
No. of vertical posts = (12 + 2)2 = 28
Nos., External area of vertical post
0.25x0.275 = 0.069sqm, Concrete in
Vertical posts = 0.069 x 28 = 1.932
cum, Hand rail in 3 tiers = 3 x 24 = 72
m, External area = 0.170 x 0.175 =
0.03 sqm, Concrete in hand rails = 0.03
x 72 = 2.16 cum, Total Concrete =
1.932 + 2.16 = 4.092 cum. (Refer
MoRTH SDcent
Add 5 per / 202).
of above cost for form 510.89
work for casting in casting yard.
HYSD bar reinforcement Rate as per tonne 0.87 37861.00 32749.77 Item
item No 14.2(Excluding OH & CP) 14.2 A
Refer MoRTH SD / 202.
Add 5 per cent of (a) for handling and 2173.92
fixing of precast panels in position
b) Overhead charges @ 10 % on (a) 4565.23
c) Contractor's profit @ 10 % on 5021.75
(a+b)
Rate for 48 m (a+b+c) 55239.28
Rate per metre (a+b+c)/48 1150.82
say 1151.00
Note 1.Quantities of material have been adopted
from standard plans of MoRTH vide drawing
no. SD/202.
2.48 m length is the total linear length
adding both sides of 24 m span.
14.7 2703, Construction of RCC railing of M30
1500, Grade in-situ with 20 mm nominal size
1600 aggregate, true to line and grade,
& tolerance of vertical RCC post not to
1700 exceed 1 in 500, centre to centre
spacing between vertical post not to
exceed 2000 mm, leaving adequate
space between vertical post for
expansion, complete as per approved
drawings and technical specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a) Material
Cement concreteM30 Grade Refer cum 4.092 2497.00 10217.72 Item
relevant item of concrete in Item 14.1(C)
14.1(C) by using batching plant,
excluding formwork i.e. per cum basic
No. of vertical posts = (12 + 2)2 = 28
Nos., External area of vertical post
0.25x0.275 = 0.069sqm, Concrete in
vehicle posts = 0.069 x 28 = 1.932
cum, Hand rail in 3 tiers = 3 x 24 = 72
m, External area = 0.170 x 0.175 =
0.03 sqm, Concrete in hand rails = 0.03
x 72 = 2.16 cum, Total Concrete =
1.932 + 2.16 = 4.092 cum. (Refer
MoRTH
Add 12 SD
per /cent
202).of above cost for form 1226.13
work.
HYSD bar reinforcement Rate as per tonne 0.87 37861.00 32749.77 Item
item No 14.2(Excluding OH & CP) 14.2 A
refer MoRTH SD / 202.
b) Overhead charges @ 10 % on (a) 4419.36
c) Contractor's profit @ 10 % on 4861.30
(a+b)for 48 m (a+b+c)
Rate 53474.28
Rate per metre (a+b+c)/48 1114.05
say 1114.00
Note 1. Quantities of material have been
adopted from standard plans of MoRTH vide
drawing no. SD/202.
2. 48 m length is the total linear length
adding both sides of 24 m span.
14.8 2703. Providing, fitting and fixing mild steel
2& railing complete as per drawing and
1900 Technical Specification
Unit = 1 RM
Taking output = 2 x 50 m span = 100
m
a) Material:

Page 25 of 361
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT tonne 2.95 32000.00 94272.00 M-179
2) MS Flat = 0.964 x 1.05 = 1.012 MT tonne 1.01 32000.00 32384.00 M-179
3) MS bars = 0.17 x 1.05 = 0.180 MT tonne 0.18 32000.00 5760.00 M-179
4) MS bolts, nuts and washers tonne 0.15 50000.00 7500.00 M-
130*100
Add @ 5 per cent of cost of material 6995.80 0
for painting one shop coat with red
oxide primer and three coats of
synthetic enamel paint and
consumables to safeguard against
Add for cost of concrete for fixing 1399.16
vertical posts in the performed recess
@ 1 per cent of cost of material.
Add for electricity charges, welding and 1399.16
drilling equipment, electrodes and other
consumables @ 1 per cent of cost of
material.
b) Labour
Mate day 2.80 150.00 420.00 L-12
Mazdoor (Skilled) day 30.00 125.00 3750.00 L-15
Mazdoor day 40.00 100.00 4000.00 L-13
c) Overhead charges @ 10 % on 15788.01
(a+b)
d) Contractor's profit @ 10 % on 17366.81
(a+b+c)
Cost for 100 m steel railing = a+b+c+d 191034.95
Rate per metre (a+b+c+d)/100 1910.35
say 1910.00
14.9 2705 Drainage Spouts complete as per
drawing and Technical specification
Unit = 1 No.
Taking output = 1 No.
a) Material
Corrosion resistant Structural steel Kg 4.00 35.80 143.20 M-
including 5 per cent wastage 087/100
GI pipe 100mm dia metre 6.00 15.00 0
90.00 M-056
GI bolt 10 mm Dia each 6.00 10.00 60.00 M-110
Galvanised MS flat clamp each 2.00 250.00 500.00 M-101
b) Labour
For fabrication
Mate day 0.02 150.00 3.00 L-12
Skilled (Blacksmith, welder etc.) day 0.02 150.00 3.00 L-02
Mazdoor day 0.02 100.00 2.00 L-13
For fixing in position
Mate day 0.01 150.00 1.50 L-12
Mason day 0.01 250.00 2.50 L-11
Mazdoor day 0.20 100.00 20.00 L-13
Add @ 5 per cent of cost of material 41.26
and labour for electrodes, cutting gas,
sealant, anti-corrosive bituminous paint,
mild steel grating etc.
c) Overhead charges @ 10 % on 86.65
(a+b)
d) Contractor's profit @ 10 % on 95.31
(a+b+c)
Rate per metre (a+b+c+d) 1048.42
say 1048.00
Note 1. In case of viaducts in urban areas, the
drainage spouts should be connected with
suitably located pipelines to discharge the
surface run-off to drains provided at ground
level.
2. In case of bridges, sufficient length of G.I
Pipe shall be provided to ensure that there
is no splashing of water from the drainage
spout on the structure.
14.10 2700 PCC M15 Grade leveling course below
approach slab complete as per
drawing and Technical specification
Unit = 1 cum
Taking output = 1 cum
Material

Page 26 of 361
Concrete, Rate as per item No. 12.8 (A) cum 1.00 2495.00 2495.00 Item
excluding formworks 12.8 (A)
Rate per cum say 2495.00
14.11 1500, Reinforced cement concrete approach
1600, slab including reinforcement and
1700 formwork complete as per drawing and
& Technical specification
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concreteM30 Grade Refer cum 1.00 2496.00 2496.00 Item
relevant item of concrete in item 12.8 (G)
12.8(G)by using batching plant,
excluding formwork i.e. per cum basic
cost (a+b+c) (Excluding OH & CP)
( Refer relevant item of concrete in item 49.92
No. 13.8 (G) except that form work may
be added at the rate of 2 per cent of
cost against 3.5 per cent provided in
the foundation concrete.
HYSD bar reinforcement Rate as per tonne 0.05 37861.00 1893.05 Item
item No 14.2(Excluding OH & CP) 14.2 A
b) Overhead charges @ 10 % on (a) 443.90
c) Contractor's profit @ 10 % 488.29
on(a+b)
Rate per cum (a+b+c) 5371.15
say 5371.00
Note The grade of reinforced cement concrete
may be adopted as M30 for severe
conditions and M25 for moderate
conditions.
14.12 1600 Providing anti-corrosive treatment to
HYSD reinforcement with Fusion
Bonded Epoxy Coating (FBEC)
Unit = 1 MT
Taking output = 1 MT
To be taken as per the prevailing market
Note rates.
Contractors generally do not have expertise
for this item . The job is therefore, got done
from specialised firms who have the
expertise in the field of construction
chemicals. The prevailing rate in the market
is required to be ascertained from the
market and added in the cost estimate.
Detailed guidelines in this regard have been
issued by MoRTH vide their circular no.
14.13 1800 RW/NH-34041/44/91-S&R
Precast - pretensioned dated 21.3.2000.
Girders
&
2300 Providing, precasting, transportation
and placing in position precast
pretensioned concrete girders as per
drawing and technical specifications
Unit = 1 cum
Taking output = 1 cum
Grade of concrete - M40
a) Material
Cement tonne 0.47 4180.00 1964.60 M-081
Coarse sand cum 0.45 160.00 72.00 M-004
20 mm Aggregate cum 0.54 410.00 221.40 M-053
10 mm Aggregate cum 0.36 410.00 147.60 M-051
Admixture @ 0.4 per cent of cement Kg 1.88 50.00 94.00 M-180
HYSD steel . tonne 0.10 34500.00 3450.00 M-082
HT strand with 5 per cent as wastage tonne 0.06 45000.00 2700.00 M-119
and extra length for anchoring
LDO for steam curing Litre 37.00 28.00 1036.00 M-122
Add consumables such as binding wire, 96.86
foam, packing tape, shuttering oil,
HDPE pipe for unbonding of strand, bolt
& nuts etc @ 1 per cent of material
cost
b) Labour

Page 27 of 361
(i) Cutting, bending, making
reinforcement cage, placing in
position,
Taking bindingof
quantity etc. complete
steel 100 Kg/cum of
concrete including laps and wastage
Mate day 0.06 150.00 9.00 L-12
Mazdoor (Skilled) day 0.35 125.00 43.75 L-15
Mazdoor day 1.40 100.00 140.00 L-13
(ii) Cable cutting and threading in
position including binding by
insulation tape with HDPE pipes etc.,
prestessing and cutting of extra length
of HT strand after de-stressing.
Taking quantity of HT strand 60
Kg/cum
Mate day 0.02 150.00 3.00 L-12
Mazdoor (Skilled) day 0.14 125.00 17.50 L-15
Mazdoor day 0.50 100.00 50.00 L-13
(iii) Erection and dismantling of
shuttering
Taking shuttering area 10 sqm/cum of
concrete
Mate day 0.12 150.00 18.00 L-12
Mazdoor (Skilled) day 1.00 125.00 125.00 L-15
Mazdoor day 2.00 100.00 200.00 L-13
(iv) Concreting by Batching plant and
stationary concrete pump
Mate day 0.03 150.00 4.50 L-12
Mazdoor (Skilled) day 0.05 125.00 6.25 L-15
Mazdoor day 0.60 100.00 60.00 L-13
(v) Steam curing and manual curing
Mate day 0.01 150.00 1.50 L-12
Mazdoor day 0.35 100.00 35.00 L-13
(vi) Handling of precast girder,
stacking in stockyard and again
loading
Mate in trailor day 0.01 150.00 1.50 L-12
Mazdoor day 0.25 100.00 25.00 L-13
(vii) Placement of girders in position
over pier caps including placement of
sand jacks, channel, levelling etc.
Mate day 0.01 150.00 1.50 L-12
Mazdoor (Skilled) day 0.06 125.00 7.50 L-15
Mazdoor day 0.24 100.00 24.00 L-13
c) Machinery
i) At casting yard
Generator 100 KVA hour 0.05 600.00 30.00 P&M-
Batching Plant @ 20 cum/hour hour 0.05 1500.00 75.00 080
P&M-
Transit Mixer 4 cum capacity hour 0.10 600.00 60.00 002
P&M-
Concrete Pump stationary hour 0.05 500.00 25.00 049
P&M-
Crane 35 tonne capacity hour 0.10 500.00 50.00 007
P&M-
Trailor 30 tonne capacity hour 0.10 300.00 30.00 012
P&M-
Loader hour 0.05 700.00 35.00 089
P&M-
ii) For transportation and placement at 017
siteCrane 35 tonne capacity hour 0.15 500.00 75.00 P&M-
Trailer 30 tonne capacity for tonne.k 2.5xL 300.00 15000.00 012
Lead
transporting to site. m =20 km
& P&M-
090
(L - Lead in Kilometer)
Trailor 30 tonne capacity during hour 0.15 300.00 45.00 P&M-
placement.
Cost of formwork, steam curing 543.02 089
arrangement, pretensioning
arrangement etc @ 5 per cent of cost
material, labour and machinery
d) Overhead charges @ 10 % on 2652.35
(a+b+c)
e) Contractor's profit @ 10 % on 2917.58
(a+b+c+d)
Rate per cum = (a+b+c+d+e) 32093.41
say 32093.00

Page 28 of 361
14.14 1700 Providing and fixing Helical pipes in
& voided concrete slabs
1800 Unit = 1 RM
Taking output = 1 RM
a) Material
Helical pipes 600mm diameter metre 1.00 750.00 750.00 M-117
Tie rods 20mm diameter each 1.00 275.00 275.00 M-183
Consumables for sealing joints etc.@ 5 per 51.25
cent of cost of material
b) Labour
Mate day 0.01 150.00 1.50 L-12
Fitter day 0.05 150.00 7.50 L-08
Mazdoor day 0.20 100.00 20.00 L-13
c) Overhead charges @ 10 % on 110.53
(a+b)
d) Contractor's profit @ 10 % on 121.58
(a+b+c)
Rate per Rm (a+b+c+d) 1337.35
say 1337.00
14.15 800 Crash Barriers
The rate analysis for rigid crash barrier in
reinforced cement concrete, semi-rigid
crash barrier with metal beam and flexible
crash barrier with wire ropes have been
made and included in chapter-8 on Traffic
and Transportation.
14.16 800 Painting on concrete surface
Providing and applying 2 coats of
water based cement paint to
unplastered concrete surface after
cleaning the surface of dirt, dust, oil,
grease, efflorescence and applying
paint @ of 1 litre for 2 sqm.
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.01 150.00 1.50 L-12
Painter day 0.25 200.00 50.00 L-18
Mazdoor (Skilled) day 0.25 125.00 31.25 L-15
b) Material
Water based paint of approved quality Litres 5.00 35.00 175.00 M-190
for cement concrete surface
c) Overhead charges @ 10 % on 25.78
(a+b) Contractor's profit @ 10 % on
d) 28.35
(a+b+c)
Cost for 10 sqm (a+b+c+d) 311.88
Rate per sqm (a+b+c+d)/10 31.19
say 31.00
14.17 2604 Burried Joint
Providing and laying a burried
expansion joint, expansion gap being
20 mm, covered with 12 mm thick, 200
mm wide galvanised weldable
structural steel plate as per IS: 2062,
placed symmetrical to centre line of
the joint, resting freely over the top
surface of the deck concrete, welding
of 8 mm dia. 100 mm long galvanised
nails spaced 300 mm c/c along the
centre line of the plate, all as specified
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.02 150.00 3.00 L-12
Mazdoor day 0.40 100.00 40.00 L-13
Mazdoor (Skilled) day 0.20 125.00 25.00 L-15
b) Material
Galvanised M.S plate 200 mm wide,12 kg 237.50 40.00 9500.00 M-
mm thick @ 94.20 kg/sqm including 5 060/100
per cent wastage 0

Page 29 of 361
Add 1 per cent of cost of steel plate 95.00
cutting, welding consumables and
c) galvanised
Overhead nails.
charges @ 10 % on 966.30
(a+b)
d) Contractor's profit @ 10 % on 1062.93
(a+b+c)
Cost for 12 m = (a+b+c+d) 11692.23
Rate per m = (a+b+c+d)/12 974.35
say 974.00
Note Guidelines laid down vide the MoRTH
circular No. RW/NH-34059/1/96-S&R dated
30.11.2000 and subsequent corrigendum
dated 25.01.2001 may be reffered for
expansion joints.
14.18 2605 Filler joint
(i) Providing & fixing 2 mm thick
corrugated copper plate in expansion
joint complete as per drawing &
Technical Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
Cutting, bending, carrying & fixing etc.
Mate day 0.04 150.00 6.00 L-12
Mazdoor day 0.50 100.00 50.00 L-13
Mazdoor (Skilled) day 0.50 125.00 62.50 L-15
b) Material
Copper plate - 12m long x 250 mm wide kg 55.00 300.00 16500.00 M-086
Area = 12 x 0.25 = 3 sqm
Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5 per cent = 1.33 kg/54.73 kg
say = 55 kg.
c) Overhead charges @ 10 % on 1661.85
(a+b)
d) Contractor's profit @ 10 % on 1828.04
(a+b+c)
Cost for 12 m = (a+b+c+d) 20108.39
Rate per m = (a+b+c+d)/12 1675.70
say 1676.00
14.18 (ii) Providing & fixing 20 mm thick
compressible fibre board in expansion
joint complete as per drawing &
Technical Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
For carrying, placing & fixing.
Mate day 0.008 150.00 1.20 L-12
Mazdoor day 0.10 100.00 10.00 L-13
Mazdoor (Skilled) day 0.10 125.00 12.50 L-15
b) Material
20 mm thick compressible fibre board sqm 3.00 425.00 1275.00 M-084
12 m long x 25 cm deep.
Area = 12 x 0.25 = 3 sqm
c) Overhead charges @ 10 % on 129.87
(a+b)
d) Contractor's profit @ 10 % on 142.86
(a+b+c)
Cost for 12 m = (a+b+c+d) 1571.43
Rate per m = (a+b+c+d)/12 130.95
say 131.00
14.18 (iii) Providing and fixing in position 20 mm
thick premoulded joint filler in
expansion joint for fixed ends of
simply supported spans not exceeding
10 m to cater for a horizontal
movement upto 20 mm, covered with
sealant complete as per drawing and
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.01 150.00 1.50 L-12

Page 30 of 361
Mazdoor day 0.20 100.00 20.00 L-13
Mazdoor (Skilled) day 0.10 125.00 12.50 L-15
b) Material
Premoulded joint filler 12 m long,20 mm sqm 3.60 210.00 756.00 M-141
thick and 300 mm deep.
c) Overhead charges @ 10 % on 79.00
(a+b) Contractor's profit @ 10 % on
d) 86.90
(a+b+c)
Cost for 12 m = (a+b+c+d) 955.90
Rate per m = (a+b+c+d)/12 79.66
say 80.00
14.18 (iv) Providing and filling joint sealing
compound as per drawings and
technical specifications with coarse
sand and 6 per cent bitumen by
Unit = Running meter
Taking output = 12 m
12m long x 100 mm wide x 10mm deep
recessLabour
a)
Mate day 0.02 150.00 3.00 L-12
Mazdoor day 0.50 100.00 50.00 L-13
Mazdoor (Skilled) day 0.10 125.00 12.50 L-15
b) Material
Sand cum 0.012 350.00 4.20 M-005
Volume 12 x 0.1 x 0.01 = 0.012 cum
Weight 0.012 x 1400 = 16.8kg
Bitumen cum 0.001 27030.00 27.03 M-074
16.8 x 0.06 = 1 kg
c) Overhead charges @ 10 % on 9.67
(a+b)
d) Contractor's profit @ 10 % on 10.64
(a+b+c)
Cost for 12 m = (a+b+c+d) 117.04
Rate per m = (a+b+c+d)/12 9.75
say 10.00
Note For arriving at the final rate of filler joints
per m and per cm depth of joint filling
length
compound,
the rates at Sl. No. i), ii), iii) & iv) shall be
14.19 2600 added
Asphaltic Plug joint
Providing and laying of asphaltic plug
joint to provide for horizontal
movement of 25 mm and vertical
movement of 2 mm, depth of joint
varying from 75 mm to 100 mm, width
varying from 500 mm to 750 mm (in
traffic direction), covered with a
closure plate of 200mm x 6mm of
weldable structural steel conforming
to IS: 2062, asphaltic plug to consist of
polymer modified bitumen binder,
carefully selected single size
aggregate of 12.5 mm nominal size
and a heat resistant foam
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.052 150.00 7.80 L-12
Mazdoor day 1.00 100.00 100.00 L-13
Mazdoor (Skilled) day 0.30 125.00 37.50 L-15
b) Material
Crushed stone aggregate 12.5 mm cum 0.75 410.00 307.50 M-052
nominal
Polymer size
modified bitumen kg 77.50 29.47 2283.93 M-078/
1000
2.4 Galvanised structural steel plate 200 kg 113.00 40.00 4520.00 M-103
mm wide,6 mm thick, 12 m long (2.4
sqm) @ 47.10 kg/sqm including 5 per
cent wastage
Add 1 per cent for welding and foam 72.57
caulking/backer rod and other
incidentals.

Page 31 of 361
c) Machinery
Mastic cooker 1 tonne capacity hour 1.00 40.00 40.00 P&M-
Smooth 3-wheeled steel roller 8-10 hour 0.50 170.00 85.00 030
P&M-
d) capacity
Overhead charges @ 10 % on 745.43 044
(a+b+c)
e) Contractor's profit @ 10 % on 819.97
(a+b+c+d)
Cost for 12 m asphalt plug joint = 9019.69
(a+b+c+d+e)
Rate per m = (a+b+c+d+e)/12 751.64
say 752.00
Note The nominal size of aggregates shall be
12.5 mm for depth of joint upto 75 mm and
20 mm for joints of depth more than 75
mm.
14.20 2606 Elastomeric Slab Steel Expansion Joint
Providing and laying of an elastomeric
slab steel expansion joint, catering to
right or skew (less than 20 deg.,
moderately curved with maximum
horizontal movement upto 50 mm,
complete as per approved drawings
and standard specifications to be
installed by the manufacturer/supplier
or their authorised representative
ensuring compliance to the
manufacturer's instructions for
installation and clause 2606 of MoRTH
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.06 150.00 9.00 L-12
Mazdoor day 1.00 100.00 100.00 L-13
Mazdoor (Skilled) day 0.50 125.00 62.50 L-15
b) Material
Supply of elastomeric slab seal metre 12.00 8000.00 96000.00 M-093
expansion joint assembly manufactured
by using chloroprene, elastomer for
elastomeric slab unit conforming to
clause 915.1 of IRC: 83 (part II),
complete as per approved drawings and
standard specification conforming to
clause 2606 of MoRT&H Specification
Add 5 per cent of cost of material for 4800.00
anchorage reinforcement, welding and
c) other incidentals.
Overhead charges @ 10 % on 10097.15
(a+b)
d) Contractor's profit @ 10 % on 11106.87
(a+b+c)
Cost for 12 m = (a+b+c+d) 122175.52
Rate per m = (a+b+c+d)/12 10181.29
say 10181.00
14.21 2600 Compression Seal Joint
Providing and laying of compression
seal joint consisting of steel armoured
nosing at two edges of the joint gap
suitably anchored to the deck concrete
and a preformed chloroprene
elastomer or closed cell foam joint
sealer compressed and fixed into the
joint gap with special adhesive binder
to cater for a horizontal movement
upto
Unit =40Running
mm andmeter
vertical movement of

Taking output = 12 m
a) Labour
Mate day 0.036 150.00 5.40 L-12
Mazdoor day 0.60 100.00 60.00 L-13
Mazdoor (Skilled) day 0.30 125.00 37.50 L-15
b) Material
1. Galvanised angle sections 100mm x kg 446.00 40.00 17840.00 M-103
100mm of 12mm thickness weldable
structural steel as per IS: 2062, 2 nos.
of 12 m length each @ 17.7 kg/m and 5
per cent wastage.

Page 32 of 361
Add 5 per cent of cost of above for 897.15
structural steel for anchorage, welding
and other incidentals.
Preformed continuous chloroprene metre 12.00 146.00 1752.00 M-143
elastomer or closed cell foam sealing
element with high tear strength,
vulcanised in a single operation for the
full length of a joint to ensure water
Add 1 per cent of cost of sealing 17.52
element for lubricant-cum-adhesive and
c) other consumables.
Overhead charges @ 10 % on 2060.96
(a+b)
d) Contractor's profit @ 10 % on 2267.05
(a+b+c)
Cost for 12 m = (a+b+c+d) 24937.57
Rate per m = (a+b+c+d)/12 2078.13
say 2078.00
Note 1. The installation shall be done by the
manufacturer or his authorised
representative to the satisfaction of the
Engineer.
2. The concreting for joining the expansion
joint assembly with the deck has not been
included in this analysis as the same is
catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint
assembly shall be welded to the main
14.22 2607 reinforcement of the deck.
Strip Seal Expansion Joint
Providing and laying of a strip seal
expansion joint catering to maximum
horizontal movement upto 70 mm,
complete as per approved drawings
and standard specifications to be
installed by the manufacturer/supplier
or their authorised representative
ensuring compliance to the
manufacturer's instructions for
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.05 150.00 7.50 L-12
Mazdoor day 1.00 100.00 100.00 L-13
Mazdoor (Skilled) day 0.25 125.00 31.25 L-15
b) Material
Supply of complete assembly of strip metre 12.00 7000.00 84000.00 M-178
seal expansion joint comprising of edge
beams, anchorage, strip seal element
and complete accessories as per
approved specifications and drawings.

Add 5 per cent of cost of material for 4206.94


anchorage reinforcement, welding and
c) other incidentals.
Overhead charges @ 10 % on 8834.57
(a+b)
d) Contractor's profit @ 10 % on 9718.03
(a+b+c)
Cost for 12 m = (a+b+c+d) 106898.28
Rate per m = (a+b+c+d)/12 8908.19
say 8908.00
Note 1. The installation shall be done by the
manufacturer or his authorised
representative to the satisfaction of the
Engineer.
2. The concreting for joining the expansion
joint assembly with the deck has not been
included in this analysis as the same is
catered in the quantities of RCC deck.
14.23 2600 Modular Strip / Box Seal Joint
Providing and laying of a modular strip
Box seal expansion joint including
anchorage catering to a horizontal
movement beyond 70 mm and upto
140mm, complete as per approved
drawings and standard specifications
to be installed by the
manufacturer/supplier or their
authorised representative ensuring
compliance to the manufacturer's
Page 33 of 361
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.056 150.00 8.40 L-12
Mazdoor day 1.00 100.00 100.00 L-13
Mazdoor (Skilled) day 0.40 125.00 50.00 L-15
b) Material
Supply of a modular strip/box seal joint metre 12.00 7000.00 84000.00 M-127
assembly comprising of edge beams,
central beam,2 modules chloroprene
seal, anchorage elements, support and
control system, all steel sections
protected against corrosion and
installed by the manufacturer or his
c) Overhead charges @ 10 % on 8415.84
(a+b)
d) Contractor's profit @ 10 % on 9257.42
(a+b+c)
Cost for 12 m Modular strip/box seal joint = 101831.66
(a+b+c+d)
Rate per m = (a+b+c+d)/12 8485.97
say 8486.00
Note 1. The installation shall be done by the
manufacturer or his authorised
representative to the satisfaction of the
Engineer.
2. The concreting for joining the expansion
joint assembly with the deck has not been
included in this analysis as the same is
catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint
assembly shall be welded to the main
14.24 2600 reinforcement
Modular Stripof/ the
Boxdeck.
Seal Joint
Providing and laying of a modular strip
box seal expansion joint catering to a
horizontal movement beyond 140mm
and upto 210mm, complete as per
approved drawings and standard
specifications to be installed by the
manufacturer/supplier or their
authorised representative ensuring
compliance to the
Unit = Running manufacturer's
meter
Taking output = 12 m
a) Labour
Mate day 0.07 150.00 10.50 L-12
Mazdoor day 1.25 100.00 125.00 L-13
Mazdoor (Skilled) day 0.50 125.00 62.50 L-15
b) Material
Supply of a modular box/box seal joint metre 12.00 8000.00 96000.00 M-128
assembly containing 3 modules/cells
and comprising of edge beams, two
central beams, chloroprene seal,
anchorage elements, support and
control system, all steel sections
protected against corrosion and
installed by the manufacturer or his
c) authorised
Overhead representative.
charges @ 10 % on 9619.80
(a+b)
d) Contractor's profit @ 10 % on 10581.78
(a+b+c)
Cost for 12 m Modular strip/box seal joint = 116399.58
(a+b+c+d)
Rate per m = (a+b+c+d)/12 9699.97
say 9700.00
Note 1. The installation shall be done by the
manufacturer or his authorised
representative to the satisfaction of the
Engineer.
2. The concreting for joining the expansion
joint assembly with the deck has not been
included in this analysis as the same is
catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint
assembly shall be welded to the main
reinforcement of the deck.

Page 34 of 361
CHAPTER - 15
Ref. RIVER TRAINING AND PROTECTION WORKS
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
15.1 Spec.
2503 Providing and laying boulders apron
on river bed for protection against
scour with stone boulders weighing
not less than 40 kg each complete as
per drawing and Technical
A Boulder Laid Dry Without Wire Crates.
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 265.00 265.00 M-003
Stone Spalls cum 0.20 160.00 32.00 M-008
b) Labour
Mate day 0.04 150.00 6.00 L-12
Mason day 0.35 250.00 87.50 L-11
Mazdoor * day 0.75 100.00 75.00 L-13
c) Overhead charges @ 10 % on 46.55
(a+b)
d) Contractor's profit @ 10 % on 51.21
(a+b+c)
Rate per cum = (a+b+c+d) 563.26
say 563.00
* Including excavation for trimming for
preparation
Note Nominal of bed. required for
excavation
preparation of bed has been taken into
account while making provision for labour.
15.2 2503 Boulder Apron Laid in Wire Crates
Providing and laying of boulder apron laid in
wire crates made with 4mm dia GI wire
conforming to IS: 280 & IS:4826 in 100mm
x 100mm mesh (weaved diagonally)
including 10 per cent extra for laps and
joints laid with stone boulders weighing not
Unit = cum
Taking output = 3 mx1.5mx1.25m =
5.63 cum
a) Material
4mm GI wire crates woven in mesh size sqm 22.00 200.00 4400.00 M-102
of 100 mm x 100 mm.
Stone cum 5.63 265.00 1491.95 M-003
Stone Spalls cum 1.13 160.00 180.80 M-008
b) Labour
Mate day 0.18 150.00 27.00 L-12
Mazdoor (Skilled) day 1.50 125.00 187.50 L-15
Mazdoor day *3.00 100.00 300.0 L-13
c) Overhead charges @ 10 % on 658.7
(a+b)
d) Contractor's profit @ 10 % on 724.60
(a+b+c)
Cost for 5.63 cum = a+b+c+d 7970.57
Rate per cum = (a+b+c+d)/5.63 1415.73
say 1416.00
* Including excavation for trimming for
Note preparation
Readymade of bed. wire crate rolls have
woven
been considered in the rate analysis. In
case readymade rolls are not available, GI
wire 4mm dia. @ 32 kg per 10 sqm may be
provided. In that case 2 per cent of the
cost of GI wire may be added for weaving
the wire crates.
15.3 2503 Cement Concrete Blocks (size 0.5 x 0.5
x 0.5 m) and laying of apron with cement
Providing
concrete blocks of size 0.5x0.5x0.5 m cast
in-situ and made with nominal mix of M-15
grade cement concrete with a minimum
cement content of 250 kg/cum as per IRC:
21-2000.
Unit = cum
Taking out put = 1 cum
Concrete Grade M15 Rate as per item cum 1.00 2595.00 2595.00 Item
No. 12.8 (A) including OH & CP 12.8 (A)

Page 1 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Add 2 per cent of cost to account for 51.90
excavation for preparation of bed,
nominal surface reinforcement and
filling of granular material in recesses
between blocks.
Rate per cum 2646.90
say 2647.00
15.4 2504 Providing and laying Pitching on
slopes laid over prepared filter media
including boulder apron laid dry in
front of toe of embankment complete
as per drawing and Technical
A Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg cum 1.00 265.00 265.00 M-003
Stone spalls of minimum 25 mm size cum 0.20 160.00 32.00 M-008
b) Labour
Mate day 0.04 150.00 6.00 L-12
Mason day 0.35 250.00 87.50 L-11
Mazdoor day 0.75 100.00 75.00 L-13
c) Overhead charges @ 10 % on 46.55
(a+b)
d) Contractor's profit @ 10 % on 51.21
(a+b+c)
Rate per cum = (a+b+c+d) 563.26
say 563.00
15.4 B Cement Concrete Blocks of size
0.3x0.3 x0.3 m cast in cement concrete
of Grade
Unit M15
= cum
Taking output = 1 cum
Concrete Grade M15 Rate as per item cum 1.00 2595.00 2595.00 Item
No. 12.8 (A) 12.8 (A)
Add 2 per cent of cost to account for 51.90
nominal surface reinforcement and
filling of granular material in recesses
between blocks.
Rate per cum 2646.90
say 2647.00
15.5 2504 Providing and laying Filter material
underneath pitching in slopes
complete as per drawing and Technical
specification
Unit = cum
Taking output = 1 cum
a) Material
Graded stone aggregate of required size cum 1.20 160.00 192.00 M-012
b) Labour
Mate day 0.05 150.00 7.50 L-12
Mazdoor (Skilled) day 0.25 125.00 31.25 L-15
Mazdoor * day 1.00 100.00 100.00 L-13
c) Overhead charges @ 10 % on 33.08
(a+b) Contractor's profit @ 10 % on
d) 36.38
(a+b+c)
Rate per cum = (a+b+c+d) 400.21
say 400.00
Includes Mazdoor required for trimming of
slope to proper profile and preparation of
15.6 700 & bed.
Geotextile Filter
2504
Laying of a geotextile filter between
pitching and embankment slopes on which
pitching is laid to prevent escape of the
embankment material through the voids of
the stone pitching/cement concrete blocks
as well as to allow free movement of water
without creating any uplift head on the
Unit = sqm
Taking output = 10 sqm.

Page 2 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. a) Labour
Mate day 0.02 150.00 3.00 L-12
Mazdoor day 0.30 100.00 30.00 L-13
Mazdoor (Skilled) day 0.10 125.00 12.50 L-15
b) Material
Permeable synthetic geotextile sqm 11.00 350.00 3850.00 M-181
including 5 per cent for overlap and
c) wastage
Overhead charges @ 10 % on 389.55
(a+b) Contractor's profit @ 10 % on
d) 428.51
(a+b+c)
Cost for 10 sqm = a+b+c+d 4713.56
Rate per sqm = (a+b+c+d)/10 471.36
say 471.00
15.7 2504. Toe protection
4 A toe wall for toe protection can either be in
dry rubble masonry in case of dry rubble
pitching or pitching with stones in wire
crates or it can be in PCC M15 nominal mix
if cement concert block have been used for
pitching . Rates for toe wall can be adopted
from respective clauses depending upon
approved design. The rate for excavation
for foundation, dry rubble masonry and PCC
M15 have been analysed and given in
respective chapters.
15.8 2505 Providing and laying Flooring complete
as per drawing and Technical
specifications laid over cement concert
bedding.
A Rubble stone laid in cement mortar
1:3 = cum
Unit
Taking output = 1 cum
a) Cement mortor 1:3 (Rate as in Item cum 0.33 2595.00 856.35 Item
12.6 sub-analysis) excluding OH & CP 12.6 (A)
b) Add for cement concrete bedding cum 0.33 2062.00 680.46 Item
(M15 Nominal mix) vide Item 12.8 (A) 12.8 (A)
excluding OH & CP . Quantity shall be
adopted as per design ( Assume
Rubble stone Flooring thickness
300mm and cement concrete bedding
Add 1 per cent of cost to account for 15.37
excavation for preparation of bed.
c) Material
Stone cum 1.00 265.00 265.00 M-003
Stone Spalls cum 0.20 160.00 32.00 M-008
d) Labour
Mate day 0.08 150.00 12.00 L-12
Mason day 0.50 250.00 125.00 L-11
Mazdoor (for laying stones, filling of day 1.50 100.00 150.00 L-13
e) quarry spalls) charges @ 10 % on
Overhead 144.04
(a+c+d)
f) Contractor's profit @ 10 % on 158.44
(a+c+d+e)
Rate per cum = (a+b+c+d+e+f) 2438.65
say 2439.00
* Includes cement mortar for laying and filling
15.8 B of joints. Concrete blocks Grade M15
Cement
Concrete Grade M15 block. (Rate as per cum 1.00 2595.00 2595.00 Item
item No. 12.8 (A) including OH & CP. 12.8 (A)
Add for cement concrete bedding (M15 cum 0.33 2595.00 856.35 Item
Nominal mix) vide Item 12.8 (A) 12.8 (A)
including OH & CP. Quantity shall be
adopted as per design ( Assume
Cement Concrete blocks thickness
300mm and cement concrete bedding
Add 1 per cent of cost to account for 34.51
excavation for preparation of bed.
Rate per cum 3485.86

Page 3 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. say 3486.00
15.9 2506 Dry Rubble Flooring
Construction of dry rubble flooring at cross
drainage works for relatively less important
works.
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 265.00 265.00 M-003
Stone Spalls cum 0.20 160.00 32.00 M-008
b) Labour
Mate day 0.10 150.00 15.00 L-12
Mason day 0.50 250.00 125.00 L-11
mazdoor day 1.50 100.00 150.00 L-13
Add 1 per cent of (b) for trimming and 2.90
preparation of base.
c) Overhead charges @ 10 % on 58.99
(a+b)
d) Contractor's profit @ 10 % on 64.89
(a+b+c)
Rate per cum = (a+b+c+d) 713.78
say 714.00
15.1 2507. Curtain wall complete as per drawing
0 2 and Technical specification
A Stone masonry in cement mortar (1:3)
Coursed rubble masonry (1st sort) cum 1.00 7216.00 7216.00 Item
12.7 (A )
Rate same as per item No. 12.7 (A)
including OH & CP
Rate per cum say 7216.00
or
15.1 B Cement concrete Grade M15
0 Concrete Grade M15 Rate as per item cum 1.00 2595.00 2595.00 Item
No. 12.8 (A) including OH & CP 12.8 (A)
Rate per cum say 2595.00
Note Other items like excavation for foundation,
filling behind wall, filter media, weep holes
etc. shall be added separately as per
approved design.
15.1 2507. Flexible Apron :Construction of flexible
1 2 apron 1 m thick comprising of loose
stone boulders weighing not less than
40 kg beyond curtain wall.
Unit = cum
Taking Output = 1 cum
a) Material
Stone cum 1.00 265.00 265.00 M-003
Stone Spalls cum 0.20 160.00 32.00 M-008
b) Labour
Mate day 0.05 150.00 7.50 L-12
Mason day 0.25 250.00 62.50 L-11
Mazdoor day 1.00 100.00 100.00 L-13
Add 1 per cent of cost of (a+b) for 4.67
trimming and preparation of bed.
c) Overhead charges @ 10 % on 47.17
(a+b)
d) Contractor's profit @ 10 % on 51.88
(a+b+c)
Rate per cum = (a+b+c+d) 570.72
say 571.00
15.1 2503. Gabian Structure for Retaining Earth
2 3

Page 4 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Providing and construction of a gabian
structure for retaining earth with segments
of wire crates of size 7 m x 3 m x 0.6 m
each divided into 1.5 m compartments by
cross netting, made from 4 mm galvanised
steel wire @ 32 kg per 10 sqm having
minimum tensile strength of 300 Mpa
conforming to IS:280 and galvanizing
coating conforming to IS:4826, woven into
mesh with double twist, mesh size not
exceeding 100 x 100 mm, filled with
boulders with least dimension of 200 mm,
Unit = cum
Taking output = 7 x 3 x 0.6 = 12.60
cum Labour
a)
Mate day 0.28 150.00 42.00 L-12
Mazdoor day 5.00 100.00 500.00 L-13
Mazdoor (Skilled) day 2.00 125.00 250.00 L-15
b) Material
Galvanised steel wire crates of mesh sqm 61.00 200.00 12200.00 M-102
size 100 mm x 100 mm woven with
4mm dia. GI wire in rolls of required
size.
Stone boulders with least dimension of cum 12.60 265.00 3339.00 M-003
200 mm
Stone spalls of minimum size 25 mm cum 2.52 160.00 403.20 M-008
c) Overhead charges @ 10 % on 1673.42
(a+b) Contractor's profit @ 10 % on
d) 1840.76
(a+b+c)
Cost for 12.60 cum (a+b+c+d) 20248.38
Rate per cum (a+b+c+d)/12.60 1607.01
say 1607.00
Note Readymade woven wire crate rolls have
been considered in the rate analysis. In
case readymade rolls are not available, GI
wire 4mm dia. @ 32 kg per 10 sqm may be
provided. In that case 2 per cent of the
cost of GI wire may be added for weaving
the wire crates.
15.1 2503. Gabian Structure for Erosion Control,
3 3 River Training Works and Protection
works
Providing and constructing gabian
structures for erosion control, river training
works and protection works with wire crates
of size 2 m x 1 m x 0.3 m each divided into
1m compartments by cross netting, made
from 4 mm galvanised steel wire @ 32 kg
per 10 sqm having minimum tensile
strength of 300 Mpa conforming to IS:280
and galvanizing coating conforming to
IS:4826, woven into mesh with double twist,
mesh size not exceeding 100 mm x 100
mm, filled with boulders with least
dimension of 200 mm, all loose ends to be
Unit = cum
Taking output = 2 x 1 x 0.3 x 10 Nos. =
6.00 cum
a) Labour
Mate day 0.14 150.00 21.00 L-12
Mazdoor day 2.50 100.00 250.00 L-13
Mazdoor (Skilled) day 1.00 125.00 125.00 L-15
b) Material
Galvanised steel wire crates of mesh sqm 65.00 200.00 13000.00 M-102
size 100 mm x 100 mm woven with
4mm dia. GI wire in rolls of required
size to cover 6.00 cum.
Stone boulders with least dimension of cum 6.00 265.00 1590.00 M-003
200
Stonemmspalls of minimum size 25 mm cum 1.20 160.00 192.00 M-008
c) Overhead charges @ 10 % on 1517.80
(a+b)
d) Contractor's profit @ 10 % on 1669.58
(a+b+c)
Cost for 6.00 cum (a+b+c+d) 18365.38

Page 5 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Rate per cum (a+b+c+d)/6.00 3060.90
say 3061.00
Note Readymade woven wire crate rolls have
been considered in the rate analysis. In
case readymade rolls are not available, GI
wire 4mm dia. @ 32 kg per 10 sqm may be
provided. In that case 2 per cent of the
cost of GI wire may be added for weaving
the wire crates.

Page 6 of 361
CHAPTER-16
Ref. REPAIR AND REHABILITATION
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
16.1 Spec.
2809 Removal of existing cement concrete
wearing coat including its disposal
complete as per Technical
Specification without causing any
detrimental effect to any part of the
bridge structure and removal of
dismantled material with all lifts and
Unit = Sq m ( Thickness 75 mm)
Taking output = 10 sqm
a) Labour
Mate day 0.06 150.00 9.00 L-12
Mazdoor day 1.00 100.00 100.00 L-13
b) Machinery
Air Compressor 250 cfm with pneumatic hour 1.00 150.00 150.00 P&M-
breaker/jack hammer along with 001
accessories.
Tractor-trolley. hour 0.50 150.00 75.00 P&M-
c) Overhead charges @ 10 % on 33.40 053
(a+b)
d) Contractor's profit @ 10 % on 36.74
(a+b+c)
Cost for 10 sqm = (a+d+c+d) 404.14
Rate per sqm = (a+b+c+d)/10 40.41
say 40.00
16.2 2809 Removal of existing asphaltic wearing
coat comprising of 50 mm thick
asphaltic concert laid over 12 mm
thick mastic asphalt including disposal
with all lift and lead upto 1000 m.
Unit = Sq m
Taking output = 10 sqm
a) Labour
Mate day 0.03 150.00 4.50 L-12
Mazdoor day 0.75 100.00 75.00 L-13
b) Machinery
Air Compressor 250 cfm with pneumatic hour 0.75 150.00 112.50 P&M-
breaker.
Tractor-trolley. hour 0.40 150.00 60.00 001
P&M-
c) Overhead charges @ 10 % on 25.20 053
(a+b)
d) Contractor's profit @ 10 % on 27.72
(a+b+c)
Cost for 10 sqm = (a+d+c+d) 304.92
Rate per sqm = (a+b+c+d)/10 30.49
say 30.00
16.3 2807 Guniting concrete surface with cement
mortar applied with compressor after
cleaning surface and spraying with
epoxy complete as per Technical
Specification
Unit = Sq m
Taking output = 1 sqm
Assuming thickness 25 mm
a) Material
Cement kg 16.00 4.18 66.88 M-
081/100
Graded sand cum 0.04 350.00 0
14.00 M-005
Wire mesh 50mm x 50mm size of 3mm kg 2.00 40.00 80.00 M-192
wire
Epoxy kg 0.67 300.00 201.00 M-095
Accelerator compound for guniting @ 4 kg 0.64 50.00 32.00 M-180
per cent of weight of cement
Add 2 per cent of cost of material for 7.88
miscellaneous consumables like
nozzles, wire brush, cotton waste etc.
b) Labour
Mate day 0.01 150.00 1.50 L-12
Mason day 0.04 250.00 10.00 L-11
Mazdoor day 0.14 100.00 14.00 L-13
c) Machinery
Compressor with guniting equipment hour 0.10 250.00 25.00 P&M-
along with accessories 076

Page 1 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. d) Overhead charges @ 10 % on 45.23
(a+b+c)
e) Contractor's profit @ 10 % on 49.75
(a+b+c+d)
Rate per sqm = (a+b+c+d+e) 547.23
say 547.00
16.4 2800 Providing and inserting nipples with
approved fixing compound after
drilling holes for grouting as per
Technical Specifications including
subsequent cutting/removal and
sealing of the hole as necessary of
nipples after completion of grouting
Unit = Number
Taking output = 1 No.
a) Material
Nipples each 1.00 20.00 20.00 M-129
Cement, fixing compound and 3.00
consumables @ 15 per cent of cost of
b) nipple
Labour
Mate day 0.01 150.00 1.50 L-12
Mazdoor (Skilled) labour for drilling day 0.08 125.00 10.00 L-15
Mazdoor (Skilled) labour for fixing day 0.08 125.00 10.00 L-15
nipple and sealing inlets
Mazdoor for cutting and removing of day 0.04 100.00 4.00 L-13
nipples
Add 10 per cent of labour cost for 2.55
c) drilling holes etc
Overhead charges @ 10 % on 5.11
(a+b)
d) Contractor's profit @ 10 % on 5.62
(a+b+c)
Rate per No. = (a+b+c+d) 61.77
say 62.00
16.5 2806 Sealing of cracks/porous concrete by
injection process through
nipples/Grouting complete as per
Technical Specification.
A Cement Grout
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage kg 1.10 4.18 4.60 M-
081/100
Admixtures (anti shrinkage compound) 0.92 0
@ 20 per cent of cost of cement
b) Labour
Mate day 0.08 150.00 12.00 L-12
Mazdoor (Skilled) day 0.10 125.00 12.50 L-15
Mazdoor day 0.10 100.00 10.00 L-13
c) Machinery
Grout pump with agitator and hour 0.10 300.00 30.00 M-111
d) accessories
Overhead charges @ 10 % on 7.00
(a+b+c)
e) Contractor's profit @ 10 % on 7.70
(a+b+c+d)
Rate per kg = (a+b+c+d+e) 84.72
say 85.00
B Cement Mortar (1:1) Grouting
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage kg 0.55 4.18 2.30 M-
081/100
Sand including 10 per cent wastage kg 0.55 0.23 0.13 0
M-
005/150
Admixtures (anti shrinkage compound) 0.46 0
@ 20 per cent of cost of cement
b) Labour
Mate day 0.08 150.00 12.00 L-12
Mazdoor (Skilled) day 0.10 125.00 12.50 L-15

Page 2 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Mazdoor day 0.10 100.00 10.00 L-13
c) Machinery
Grout pump with agitator and hour 0.10 300.00 30.00 M-111
d) accessories
Overhead charges @ 10 % on 6.74
(a+b+c)
e) Contractor's profit @ 10 % on 7.41
(a+b+c+d)
Rate per kg = (a+b+c+d+e) 81.54
say 82.00
16.6 2800 Patching of damaged concrete surface
with polymer concrete and curing
compounds, initiator and promoter,
available in present formulations, to
be applied as per instructions of
manufacturer and as approved by the
Unit = sqm
Taking output = 10 sqm for an average
thickness of 25mm.
a) Labour
Mate day 0.06 150.00 9.00 L-12
Mazdoor (Skilled) day 0.75 125.00 93.75 L-15
Mazdoor day 0.75 100.00 75.00 L-13
b) Material
Pre-packed polymer concrete based on kg 315.00 300.00 94500.00 M-145
epoxy system complete with curing
compound, intiator and promoter
including 5 per cent wastage.
c) Machinery
Grout pump with agitator and hour 2.00 300.00 600.00 M-111
d) accessories
Overhead charges @ 10 % on 9527.78
(a+b+c)
e) Contractor's profit @ 10 % on 10480.55
(a+b+c+d)
Cost for 10 sqm = a+b+c+d+e ###
Rate per sqm = (a+b+c+d+e)/10 11528.61
say ###
Note This item is a proprietory item available in
market as pre-packed polymer concrete
and is required to be applied as per
instructions of the manufacturer.
16.7 2803 Sealing of crack / porous concrete with
Epoxy Grout by injection through
nipples complete as per clause 2803.1.
Unit = kg
Taking output = 1 kg
a) Material
Epoxy including 10 per cent wastage kg 1.10 300.00 330.00 M-095
b) Labour
Mate day 0.08 150.00 12.00 L-12
Mazdoor (Skilled) day 0.10 125.00 12.50 L-15
Mazdoor day 0.10 100.00 10.00 L-13
c) Machinery
Epoxy Injection gun hour 0.10 200.00 20.00 P&M-
d) Overhead charges @ 10 % on 38.45 078
(a+b+c)
e) Contractor's profit @ 10 % on 42.30
(a+b+c+d)
Rate per kg = (a+b+c+d+e) 465.25
say 465.00
16.8 2804 Applying epoxy mortar over leached,
honey combed and spalled concrete
surface and exposed steel
reinforcement complete as per
Technical Specification
Unit = sqm
Taking output = 10 sqm
Assume average 10mm thickness of epoxy
mortar
a) Material
Epoxy resin-hardener mix for prime kg 2.50 300.00 750.00 M-098
coat

Page 3 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Epoxy mortar kg 2.20 250.00 550.00 M-096
Epoxy resin -hardener mix for seal coat. kg 2.00 300.00 600.00 M-098
Add 3 per cent cost of material for 57.00
other consumables like acetone etc and
to cover wastage.
b) Labour
Mate day 0.04 150.00 6.00 L-12
Mazdoor (Skilled) day 0.50 125.00 62.50 L-15
Mazdoor day 0.50 100.00 50.00 L-13
c) Overhead charges @ 10 % on 207.55
(a+b)
d) Contractor's profit @ 10 % on 228.31
(a+b+c)
Cost for 10 sqm = a+b+c+d 2511.36
Rate per sqm = (a+b+c+d)/10 251.14
say 251.00
16.9 2807 Removal of defective concrete,
cleaning the surface thoroughly,
applying the shotcrete mixture
mechanically with compressed air
under pressure, comprising of cement,
sand, coarse aggregates, water and
quick setting compound in the
proportion as per clause 2807.1., sand
and coarse aggregates conforming to
IS: 383 and table 1 of IS: 9012
respectively, water cement ratio
ranging from 0.35 to 0.50, density of
gunite not less than 2000 kg/cum,
strength not less than 25 Mpa and
unit: sqm
Taking output = 10 sqm, 40 mm
average
a) thickness.
Labour
Mate day 0.04 150.00 6.00 L-12
Mazdoor day 0.50 100.00 50.00 L-13
Mazdoor (Skilled) day 0.50 125.00 62.50 L-15
b) Machinery
Air compressor 250 cfm hour 1.00 150.00 150.00 P&M-
Shotcreteing equipment hour 1.00 250.00 250.00 001
P&M-
water tanker 6 KL capacity hour 0.02 105.00 2.10 076
P&M-
c) Material 060
Cement kg 120.00 4.18 501.60 M-
081/100
Sand cum 0.15 350.00 0
52.50 M-005
Coarse aggregate of size 4.75mm cum 0.15 200.00 30.00 M-024
Quick setting compound kg 2.50 20.00 50.00 M-147
Water KL 0.10 50.00 5.00 M-189
d) Overhead charges @ 10 % on 115.97
(a+b+c)
e) Contractor's profit @ 10 % on 127.57
(a+b+c+d)
Cost for 10 sqm = a+b+c+d+e 1403.24
Rate per sqm = (a+b+c+d+e)/10 140.32
say 140.00
16.1 2800 Applying pre-packed cement based
0 polymer mortar of strength 45 Mpa at
28 days for replacement of spalled
concrete
Unit = sqm
Taking output = 10 sqm
Assumed thickness - 10 mm
a) Material
Acrylic polymer bonding coat Litre 1.40 225.00 315.00 M-057
pre-packed cement based polymer kg 12.00 300.00 3600.00 M-145
mortar of strength 45 Mpa at 28 days
Add 3 per cent of (a ) above for 117.45
wastage.

Page 4 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. b) Labour
Mate day 0.04 150.00 6.00 L-12
Mazdoor (Skilled) day 0.50 125.00 62.50 L-15
Mazdoor day 0.50 100.00 50.00 L-13
c) Overhead charges @ 10 % on 415.10
(a+b)
d) Contractor's profit @ 10 % on 456.60
(a+b+c)
Cost for 10 sqm = a+b+c+d 5022.65
Rate per sqm = (a+b+c+d)/10 502.26
say 502.00
16.1 2805 Eproxy bonding of new concrete to old
1 concrete
Unit = sqm
Taking output = 10 sqm
a) Material
Epoxy resin with pot life not less than kg 8.00 300.00 2400.00 M-098
60-90 minutes and satisfying testing as
Add per clause
3 per cent 2803.9
of (a ) above for wastage. 72.00
b) Labour
Mate day 0.04 150.00 6.00 L-12
Mazdoor (Skilled) day 0.50 125.00 62.50 L-15
Mazdoor day 0.50 100.00 50.00 L-13
c) Overhead charges @ 10 % on 259.05
(a+b) Contractor's profit @ 10 % on
d) 284.96
(a+b+c)
Cost for 10 sqm = a+b+c+d 3134.51
Rate per sqm = (a+b+c+d)/10 313.45
say 313.00
16.1 2810 Providing external prestressing with
2 high tensile steel wires/strands
including drilling for passage of
prestessing steel, all accessories for
stressing and stressing operation and
grouting complete as per drawing and
Span assumed: 25 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 1 MT
Assume 12.7mm dia. Strand in 12T13
system. Weight-9.42 kg/m of cable.
a) Material
HTS strand including 5 per cent tonne 1.05 45000.00 47250.00 M-119
wastage and extra length for jacking
HDPE pipes 75mm dia including 5 per metre 112.00 70.00 7840.00 M-114
cent wastage
Cement for grouting kg 400.00 4.18 1672.00 M-
081/100
Tube anchorage set complete with each 8.00 1000.00 0
8000.00 M-187
bearing plate, permanent wedges etc
Epoxy kg 6.00 300.00 1800.00 M-095
MS plates for deviator (where deviator tonne 2.10 32000.00 67200.00 M-179
blocks are not provided)
Add 20 per cent cost of material for 26752.40
other materials like lead sheet, sleeves,
deviator fixtures etc.
b) Labour
i) For making holes in the structure .
Mate day 0.24 150.00 36.00 L-12
Mazdoor Semi-skilled) day 3.00 120.00 360.00 L-14
Mazdoor day 3.00 100.00 300.00 L-13
ii) For making and fixing anchorages
for cables and placement of cables .

Page 5 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Mate day 0.44 150.00 66.00 L-12
Blacksmith day 3.00 150.00 450.00 L-02
Mazdoor day 8.00 100.00 800.00 L-13
iii) For prestressing
Mate/Supervisor day 0.13 150.00 19.50 L-12
Fitter day 0.70 150.00 105.00 L-08
Mazdoor day 2.65 100.00 265.00 L-13
iv) For grouting
Mate/Supervisor day 0.13 150.00 19.50 L-12
Mason day 0.70 250.00 175.00 L-11
Mazdoor day 2.65 100.00 265.00 L-13
c) Machinery
Stressing jack with pump hour 4.00 80.00 320.00 P&M-
Grouting pump with agitator hour 1.35 300.00 405.00 040
M-111
d) Overhead charges @ 10 % on 16410.04
(a+b+c)
e) Contractor's profit @ 10 % on 18051.04
(a+b+c+d)
Rate per MT = (a+b+c+d+e) ###
say ###
16.1 2810 Providing external prestressing with
3 high tensile steel wires/strands
including drilling for passage of
prestessing steel, all accessories for
stressing and stressing operation and
grouting complete as per drawing and
Span assumed: 50 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 3.10 MT
Assume 12.7mm dia. Strand in 19T13
system. Weight-14.73 kg/m of cable.
a) Material
HTS strand including 5 per cent tonne 3.10 45000.00 ### M-119
wastage and extra length for jacking
HDPE pipes 90mm dia including 5 per metre 224.00 100.00 22400.00 M-115
cent wastage
Cement for grouting tonne 1.01 4180.00 4221.80 M-081
Tube anchorage set complete with each 8.00 1000.00 8000.00 M-187
bearing plate, permanent wedges etc
Epoxy kg 10.00 300.00 3000.00 M-095
MS plates for deviator (where deviator tonne 7.00 32000.00 ### M-179
blocks are not provided)
Add 20 per cent cost of material for 80224.36
other materials like lead sheet, sleeves,
deviator fixtures etc.
b) Labour
i) For making holes in the structure .
Mate day 0.08 150.00 12.00 L-12
Mazdoor Semi-skilled) day 8.00 120.00 960.00 L-14
Mazdoor day 8.00 100.00 800.00 L-13
ii) For making and fixing anchorages
for cables and placement of cables .
Mate day 1.28 150.00 192.00 L-12
Blacksmith day 7.00 150.00 1050.00 L-02
Mazdoor day 25.00 100.00 2500.00 L-13
iii) For prestressing
Mate/Supervisor day 0.20 150.00 30.00 L-12
Fitter day 1.00 150.00 150.00 L-08
Mazdoor day 4.00 100.00 400.00 L-13
iv) For grouting

Page 6 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Mate/Supervisor day 0.26 150.00 39.00 L-12
Mason day 1.50 250.00 375.00 L-11
Mazdoor day 5.00 100.00 500.00 L-13
c) Machinery
Stressing jack with pump hour 7.00 80.00 560.00 P&M-
Grouting pump with agitator hour 3.00 300.00 900.00 040
M-111
d) Overhead charges @ 10 % on 48981.42
(a+b+c)
e) Contractor's profit @ 10 % on 53879.56
(a+b+c+d)
Cost for 3.10 MT = a+b+c+d+e ###
Rate per MT = (a+b+c+d+e)/3.10 ###
say ###
16.1 2810 Providing external prestressing with
4 high tensile steel wires/strands
including drilling for passage of
prestessing steel, all accessories for
stressing and stressing operation and
grouting complete as per drawing and
Span assumed: 100 m
No. of cables: 6 no.
No. of anchorages : 12 no.
Unit = MT
Taking output = 9.28 MT
Assume 12.7mm dia. Strand in 19T13
system. Weight-14.73 kg/m of cable.
a) Material
HTS strand including 5 per cent tonne 9.28 45000.00 ### M-119
wastage and extra length for jacking
HDPE pipes 90 mm dia including 5 per metre 672.00 100.00 67200.00 M-115
cent wastage
Cement for grouting tonne 3.04 4180.00 12707.20 M-081
Tube anchorage set complete with each 12.00 1000.00 12000.00 M-187
bearing plate, permanent wedges etc
Epoxy kg 14.00 300.00 4200.00 M-095
MS plates for deviator (where deviator tonne 20.00 32000.00 ### M-179
blocks are not provided)
Add 20 per cent cost of material for ###
other materials like lead sheet, sleeves,
deviator fixtures etc.
b) Labour
i) For making holes in the structure .
Mate day 1.72 150.00 258.00 L-12
Mazdoor Semi-skilled) day 18.00 120.00 2160.00 L-14
Mazdoor day 25.00 100.00 2500.00 L-13
ii) For making and fixing anchorages
for cables and placement of cables .
Mate day 4.00 150.00 600.00 L-12
Blacksmith day 20.00 150.00 3000.00 L-02
Mazdoor day 80.00 100.00 8000.00 L-13
iii) For prestressing
Mate/Supervisor day 0.30 150.00 45.00 L-12
Fitter day 1.50 150.00 225.00 L-08
Mazdoor day 6.00 100.00 600.00 L-13
iv) For grouting
Mate/Supervisor day 1.00 150.00 150.00 L-12
Mason day 5.00 250.00 1250.00 L-11
Mazdoor day 20.00 100.00 2000.00 L-13
c) Machinery
Stressing jack with pump hour 10.00 80.00 800.00 P&M-
Grouting pump with agitator hour 10.00 300.00 3000.00 040
M-111
d) Overhead charges @ 10 % on ###
(a+b+c)

Page 7 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. e) Contractor's profit @ 10 % on ###
(a+b+c+d)
Cost for 9.28 MT = a+b+c+d+e ###
Rate per MT = (a+b+c+d+e)/9.28 ###
say ###
16.1 2808 Replacement of Bearings complete as
5 per Technical Specification
Unit = No
Taking output = 3 No.
Lifting of superstructure span by jacking up
from below i.e. by placing the jacks on
pier/abutment caps for span length of 30m.
a) Lifting of span
i) Hire charges for jack of 40 tonne Day 3.00 3000.00 9000.00 P&M-
lifting capacity.
Mate day 0.64 150.00 96.00 084
L-12
Mazdoor (Skilled) day 4.00 125.00 500.00 L-15
Mazdoor day 12.00 100.00 1200.00 L-13
v) Wooden packing cum 0.15 2000.00 300.00 M-195
b) Replacement of bearing
Cost of bearing. each 3.00 40000.00 ### M-065
c) Overhead charges @ 10 % on 13109.60
(a+b)
d) Contractor's profit @ 10 % on 14420.56
(a+b+c)
Cost of repair of 3 bearings = a+b+c+d ###
Rate of repair per bearing = 52875.39
(a+b+c+d)/3 say ###
Note The work entails replacement of all the
bearings on one side of the span.
16.1 2808 Rectification of Bearings as per
6 Technical Specifications
Unit = 1 No
Taking output = 3 No.
a) Lifting of superstructure span by
jacking up from below i.e. by placing
the jacks on pier/abutment caps for
span length of 30m.
i) Hire charges for jack of 40 tonne each 3.00 3000.00 9000.00 P&M-
lifting
ii) Matecapacity. day 0.64 150.00 96.00 084
L-12
iii) Mazdoor (Skilled) day 4.00 125.00 500.00 L-15
iv) Mazdoor day 12.00 100.00 1200.00 L-13
v) Wooden packing cum 0.15 2000.00 300.00 M-195
b) Cost of parts to be replaced for 3 each 3.00 20000.00 60000.00 M-064
bearings.
c) Overhead charges @ 10 % on 7109.60
(a+b)
d) Contractor's profit @ 10 % on 7820.56
(a+b+c)
Cost of repair of 3 bearings = a+b+c+d 86026.16
Rate of repair per bearing = 28675.39
(a+b+c+d)/3 say ###
Note The rectification of 3 bearings included in
this analysis are on the same side of the
16.1 span.
Replacement of Expansion Joints
7 complete as per drawings
Unit -1 RM
Taking output = 12 RM
a) Material
Epoxy for bonding new concrete to old kg 9.60 300.00 2880.00 M-095
concrete @ 0.8 kg/sqm
M-30 grade cement concrete excluding cum 3.60 2996.00 10785.60 Item
OH & CP (Rate as per items 14.1 C (i) 14.1(C)
b) Labour
Removal of old expansion joint including
breaking of concrete, cutting of lugs and
shifting of broken material etc.

Page 8 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Mate day 0.26 150.00 39.00 L-12
Mazdoor day 6.00 100.00 600.00 L-13
Mazdoor (Skilled) day 0.50 125.00 62.50 L-15
c) Overhead charges @ 10 % on 1436.71
(a+b)
d) Contractor's profit @ 10 % on 1580.38
(a+b+c) 17384.19
Cost for replacement of 12 RM = a+b+c+d
Rate per RM = (a+b+c+d)/12 1448.68
say 1449.00
Note The rate for the installation of new
expansion joints may be taken from the
chapter on superstructure. Broken concrete
will have to be replaced which has been
included in this analysis.
16.1 Replacement of Damaged Concrete
8 Railing.
Unit = RM
Taking output = 10 RM
a) Labour
Labour for dismantling old railing and
disposal of dismantled material.
Mate day 0.20 150.00 30.00 L-12
Mazdoor day 5.00 100.00 500.00 L-13
b) Machinery
Tractor-trolley for disposal of hour 1.00 150.00 150.00 P&M-
c) dismantled
Overhead material
charges @ 10 % on 68.00 053
(a+b)
d) Contractor's profit @ 10 % on 74.80
(a+b+c)
Cost for 10 m = a+b+c+d 822.80
Rate per metre = (a+b+c+d)/10 82.28
say 82.00
Note The rate for the provision of new railing
may be adopted from the chapter on
16.1 superstructure.of Crash Barrier.
Replacement
9 Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and
disposal of dismantled material.
Mate day 0.40 150.00 60.00 L-12
Mazdoor day 10.00 100.00 1000.00 L-13
b) Machinery
Tractor-trolley for disposal of hour 1.00 150.00 150.00 P&M-
c) dismantled
Overhead material
charges @ 10 % on 121.00 053
(a+b) Contractor's profit @ 10 % on
d) 133.10
(a+b+c)
Cost for 10 m = a+b+c+d 1464.10
Rate per metre = (a+b+c+d)/10 146.41
say 146.00
Note The rate for the construction of new crash
barrier may be adopted from chapter 8 on
Traffic and Transportation.
16.2 Replacement of Damaged Mild Steel
0 Railing
Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and
disposal of dismantled material.
Mate day 0.16 150.00 24.00 L-12
Mazdoor day 4.00 100.00 400.00 L-13
b) Machinery
Tractor-trolley for disposal of hour 1.00 150.00 150.00 P&M-
c) dismantled
Overhead material
charges @ 10 % on 57.40 053
(a+b)

Page 9 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. d) Contractor's profit @ 10 % on 63.14
(a+b+c)
Cost for 10 m = a+b+c+d 694.54
Rate per metre = (a+b+c+d)/10 69.45
say 69.00
16.2 Repair of Crash Barrier
1 Repair of concrete crash barrier with
cement concert of M-30 grade by cutting
and trimming the damaged portion to a
regular shape, cleaning the area to be
repaired thoroughly, applying cement
concert after erection of proper form work.
Unit = Running meter.
Taking output = 10 M.
It is assumed that damage is to the extent
of 10 per cent of the volume of concrete
.This will require 0.30 cum of concrete.
a) Manpower*
Mate day 0.04 150.00 6.00 L-12
Mazdoor day 1.00 100.00 100.00 L-13
* For dismantling and trimming the surface to
a regular shape and removal of damaged
material.
b) Material
M-30 grade cement concrete excluding cum 0.30 2996.00 898.80 Item
OH & CP (Rate as per items 14.1 C (i) 14.1(C)
This may be priced based on the rate given
the chapter of superstructure.
c) Overhead charges @ 10 % on (a) 10.60
d) Contractor's profit @ 10 % on 11.66
(a+c)for 10 m = a+b+c+d
Cost 1027.06
Rate per m = (a+b+c+d)/10 102.71
say 103.00
16.2 Repair of RCC Railing
2 Carrying out repair of RCC M30 railing to
bring it to the original shape.
Unit = Running meter.
Taking output = 10 M.
It is assumed that damage is to the extent
of 10 per cent .
a) Material
M-30 grade cement concrete excluding cum 0.10 2996.00 299.60 Item
OH & CP (Rate as per items 14.1 C (i) 14.1(C)
HYSD bar reinforcement Rate as per tonne 0.01 37861.00 492.19 Item
item No 14.2(Excluding OH & CP) 14.2 A
b) Labour*
Mate day 0.016 150.00 2.40 L-12
mazdoor day 0.20 100.00 20.00 L-13
* For dismantling and trimming the surface to
a regular shape and removal of damaged
material.
c) Overhead charges @ 10 % on 2.24
(b)
d) Contractor's profit @ 10 % on 2.46
(b+c)
Cost for 10 m = a+b+c+d 818.90
Rate per m = (a+b+c+d)/10 81.89
say 82.00
16.2 Repair of Steel Railing
3 Repair of steel railing to bring it to the
original
It shapethat the damage to the steel
is assumed
railing is to the extent of 10 per cent .
Unit = Running meter.
Taking output = 10 M.
a) Material

Page 10 of 361
Ref.
to Remark
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs s/ Input
H ref.
Spec. Mild steel ISMC series kg 29.00 32.00 928.00 M-
179/100
Flat iron kg 10.00 32.00 320.00 0
M-
179/100
MS Bolt and nuts kg 1.00 50.00 0
50.00 M-130
Add 5 per cent of cost of material for 64.90
b) painting.
Labour
Mate day 0.016 150.00 2.40 L-12
Mazdoor (Skilled) day 0.20 125.00 25.00 L-15
Mazdoor day 0.20 100.00 20.00 L-13
c) Overhead charges @ 10 % on 141.03
(a+b)
d) Contractor's profit @ 10 % on 155.13
(a+b+c)
Cost of repair for10m = a+b+c+d 1706.46
Cost of meter = (a+b+c+d)/10 170.65
say 171.00

Page 11 of 361

S-ar putea să vă placă și