ID Task Name Duration Start Finish Qtr 4, 2015 Qtr 1, 2016 Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016

Finish Qtr 4, 2015 Qtr 1, 2016 Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
1 CONTSRUCTION OF DISTRICT COURT AT 707 days Nov 17 '15 Aug 26 '17
DEHRADUN, UK
2 Contractual Activities 30 days Nov 17 '15 Dec 14 '15
3 Issue of LOA by NBCC 0 days Nov 17 '15 Nov 17 '15 11/17
4 Contractual Start Date 0 days Nov 27 '15 Nov 27 '15 11/27
5 Submission of Performance BG 30 days Nov 17 '15 Dec 14 '15
6 Submission of Power of Attorney 10 days Nov 17 '15 Nov 26 '15
7 Signing of Contract Agreement 30 days Nov 17 '15 Dec 14 '15
8 Contractual Submittals 10 days Nov 17 '15 Nov 27 '15
9 Submission of Detailed Construction Program 10 days Nov 17 '15 Nov 27 '15

10 Submission of Quality Assurance Plan 10 days Nov 17 '15 Nov 27 '15


11 Submission of Organogram 10 days Nov 17 '15 Nov 27 '15
12 Mobilization and Setup 40 days Nov 17 '15 Dec 24 '15
13 Initial staff mobilization 10 days Nov 17 '15 Nov 27 '15
14 Setup of Site office, Laboratory, Store, 15 days Nov 27 '15 Dec 10 '15
Cement Godown etc
15 Mobilization, erection & comissioning of 30 days Nov 27 '15 Dec 24 '15
Batching Plant
16 Setup of Reinforcement yard 10 days Nov 27 '15 Dec 6 '15
17 Mobilization plant and machinery 30 days Nov 27 '15 Dec 24 '15
18 Survey & Setting Out Work 7 days Nov 27 '15 Dec 3 '15
19 Clearing and Grubbing of site 5 days Nov 27 '15 Dec 1 '15
20 Initial survey and set out, fixing of 2 days Dec 1 '15 Dec 3 '15
co-ordinates
21 Mix design 41 days Nov 28 '15 Jan 5 '16
22 Approval of Source for aggregates 2 days Nov 28 '15 Nov 30 '15
23 Finalization of Mix Design for P.C.C 35 days Dec 2 '15 Jan 3 '16
24 Finalization of Mix Design for R.C.C 35 days Dec 4 '15 Jan 5 '16
25 Construction of Court Complex 689 days Dec 3 '15 Aug 26 '17
26 CIVIL WORKS 689 days Dec 3 '15 Aug 26 '17
27 Earth Work 90 days Dec 3 '15 Feb 23 '16
28 PCC 90 days Dec 12 '15 Mar 4 '16
29 RCC Work 365 days Dec 26 '15 Nov 24 '16
30 Brick Work 395 days Jan 27 '16 Jan 23 '17
31 Stone Work & Wall Cladding 395 days Feb 24 '16 Feb 20 '17
32 Marble and Granite 395 days Mar 8 '16 Mar 5 '17
33 Wood & PVC Work 210 days Aug 20 '16 Mar 1 '17
34 Steel Work 210 days Aug 20 '16 Mar 1 '17
35 Aluminium Work 180 days Aug 20 '16 Feb 1 '17
36 Flooring 270 days Jun 26 '16 Mar 1 '17
37 Roofing 210 days Nov 11 '16 May 22 '17
38 Finishing Work 210 days Feb 1 '17 Aug 13 '17
39 Water Proofing Work 150 days Nov 25 '16 Apr 11 '17
40 Horticulture & Landscaping 150 days Apr 10 '17 Aug 26 '17
41 Road Works 210 days Jan 8 '17 Jul 20 '17
42 EXTERNAL PLUMBING 390 days Jun 13 '16 Jun 5 '17
43 External Water Supply 320 days Jun 13 '16 Apr 2 '17
44 External Sewer Drainage 320 days Jul 10 '16 Apr 29 '17
45 External Rain Water Disposal 320 days Jul 28 '16 May 18 '17
46 Misscellaneous Items 320 days Aug 16 '16 Jun 5 '17
47 INTERNAL PLUMBING 180 days Oct 28 '16 Apr 11 '17
48 Sanitary Fixtures & CP Brass Fittings 120 days Oct 28 '16 Feb 15 '17

49 Soil, Waste, Vent & Rain Water Pipes 120 days Nov 25 '16 Mar 14 '17

50 Water Supply System 120 days Dec 22 '16 Apr 11 '17


51 ELECTRICAL WORKS 240 days Aug 7 '16 Mar 14 '17
52 Internal Electrical Works 210 days Aug 7 '16 Feb 15 '17

Task Project Summary Inactive Milestone Manual Summary Rollup Progress

Project: Construction L1 Schedule Split External Tasks Inactive Summary Manual Summary Deadline
Date: Dec 3 '15 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task Name Duration Start Finish Qtr 4, 2015 Qtr 1, 2016 Qtr 2, 2016 Qtr 3, 2016 Qtr 4, 2016 Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017 Qtr 4, 2
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
53 External Electrical Works 210 days Sep 3 '16 Mar 14 '17
54 BUILDING MANAGEMENT SYSTEM (BMS) 180 days Aug 7 '16 Jan 18 '17

55 HEATING VENTILATION & AC SYSTEM 210 days Dec 22 '16 Jul 2 '17

56 EXTERNAL FIRE FIGHTING 90 days Mar 15 '17 Jun 5 '17


57 INTERNAL FIRE FIGHTING 90 days Jan 19 '17 Apr 11 '17
58 LIFT WORKS 210 days Feb 19 '16 Aug 29 '16
59 Completion of Entire Work as per contract 0 days Aug 26 '17 Aug 26 '17 8/26

Task Project Summary Inactive Milestone Manual Summary Rollup Progress

Project: Construction L1 Schedule Split External Tasks Inactive Summary Manual Summary Deadline
Date: Dec 3 '15 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only