Documente Academic
Documente Profesional
Documente Cultură
This year (2018) JCT has shown a marked growth, and is now at levels not seen since 2011. NEC,
which had been growing year on year, has contracted and has returned to the levels that we saw in
2011. Use of bespoke contracts has fallen from 11% to 5%.
Main works contracts
JCT (2016) NEC3 (2013)
• Standard Building Contract - 3 NEC3/NEC4 Engineering and
versions Construction Contract
• Intermediate Building Contract - 2
versions (1 with Contractor design)
• Major Project Construction contract
• Design and Build Contract
• Management building Contract
• Construction Management Contract
• Constructing Excellence Contract
JCT NEC
Select a CA with the skill to tightly control It’s important that the Project Manager
the account throughout the project - has appropriate qualities, project
goodwill can disappear when the parties management skills and understanding of
have unresolved claims for time and NEC contracts to pro actively manage the
money (arising from relevant events), contract and to foster collaborative
which are difficult to unravel, and there is working with the contractor.
pressure to close the account and switch
attention to other projects
So choose your project manager
carefully, as the contract depends on
solid project management. PM’s often
administer NEC contracts in a similar way
to JCT contracts which is best avoided.
Management input
= Similar
management
input overall
Collaboration/ Partnering
JCT NEC
“The Parties shall work with each other & “The Employer, the Contractor, the Project
with other project team members in a co- Manager and the Supervisor shall act as
operative and collaborative manner, in stated in this contract and in a spirit of
good faith & in a spirit of trust & respect. mutual trust and co-operation.”
To that end each shall support (Clause 10.1 – Core Clause)
collaborative behaviour & address
behaviour which is not collaborative”
(Schedule 8, Supplemental Provisions,
item 1)
This is included as an option – the This is included as the first of the core
default is that it applies, but it can be clauses reflecting the importance of such
omitted. relationships as an integral aspect of the
• the contract is limited in terms of processes for managing NEC contracts,
processes that involve a collaborative e.g. in relation to early warnings and
approach to manage issues. compensation events.
Pricing
JCT NEC
• With quantities (Lump sum contract) Option A – Priced Contract With Activity
• Employer provides drawings and bills Schedule
of quantities specifying quantity and
quality of work Option B – Priced Contract With Bill of
Quantities
• Without Quantities (Lump sum contract) Option C – Target Contract With Activity
• Employer provides drawings together Schedule
with a description of works and either
a specification or work schedules Option D – Target Contract With Bill of
Quantities
• With Approximate Quantities (Re-
measurable) Option E – Cost Reimbursable Contract
• Employer provides drawings and
Option F – Management Contract
approximate bills of quantities.
The NEC Contract doesn’t include provisional
• The JCT Contract contains provisional sums
sums
Payment
JCT (2016) NEC
• The JCT contract payment section is • In the NEC contract it is located in three
clear, is all in one section (clause 4) different locations – clause 5, Y(UK)2
and easy to follow. Listed items – and Contract Data Part 1.
permits payment for materials off site
• Option A - Activity schedule - items
• Payments are generally calculated by need to be 100% complete before
QS based upon assessment of work payment is made. Encourages
done plus materials, following an Contractor to stick to programme
application made by the Contractor.
• Option B – BofQ – payment is based on
a remeasure + proportions of lump
sums
16
Comparison
• The following slides compare
• Deemed acceptance
• If the PM does not respond to a notification of an event notified by the
contractor in accordance with the required timetable then the event is
treated as a CE and the contractor submits a quotation.
Claims for extensions of the contract period are notified and evaluated under separate
conditions of contract to those for cost; there’s no specific requirement to use the contractor’s
programme to evaluate extensions.
The provisions for “loss and expense” payments are without prejudice to any other rights and
remedies that the contractor may possess.
Except when the quotation procedure is used the absence of a clear timetable for evaluating all
variations and claims (for both cost and time concurrently) in real time increases the potential
for issues to build up during the contract and increase uncertainty as to the final outcome.
Programme/ Delays
JCT (2016) NEC3
• In the JCT contract ground risk is with • Early warning is required if time, quality
the contractor. However, the NEC or cost could be impaired. Failure to
contract uses the ICE foreseeability notify an issue may adversely the affect
test in relation to ground conditions. the valuation of a compensation event
arising from it in relation to the contractor
• It is not uncommon for JCT contracts or Employer (depending on the party
to be extensively modified to transfer failing to give notice).
risk
• Both parties are required to list matters
to be included in Risk Register in Contract
Data
Early warning
JCT (2016) NEC3
JCT contracts don’t include a proactive One of the stimuli to “good management”
early warning procedure (to pre-empt under NEC is the early warning system.
problems) and generally rely on the The aim is to pre-empt potential problems
provisions in the contract to deal with and mitigate their impact.
issues when they occur.
Early warning provisions involve the
• The exception to this is the JCT maintenance of a risk register and place
Construction Excellence contract which obligations to notify each other if a
contains some risk management relevant issue occurs and to attend and
provisions. co-operate at a risk reduction meeting.