Sunteți pe pagina 1din 36

NEC vs JCT

15th November 2018


NEC v JCT
Fergus Aitken BSc MRICS MAPM
YORbuild2 Programme Manager
East Riding of Yorkshire Council
‘Mr NEC’

Chris Bourne BSc (Hons) MRICS


YORbuild2 Framework Manager
Scarborough Borough Council
‘Mr JCT’
Opening remarks
History
JCT NEC
Main contract used within the building The New Engineering Contact /
sector of the UK construction industry Engineering and Construction Contract
since 1931 was first published in 1991
Latest editions were published in 2016. Now in its 4th edition published June 2017
Over 60 different versions
JCT claims pre-eminence due to its NEC is the modern kid on the block (but
longevity emerged from previous ICE conditions)
Traditional’ (or ‘master and servant’) style Aims to create a collaborative/partnering
of contract ethos, with a proactive approach
Building industry are used to JCT as it’s NEC3 is now all but mandated for public
been around for a while and the building sector projects (following the Cabinet
industry’s set up complements its use, but Office’s endorsement in 2008).
NEC is now well established Civils sector are used to NEC
National Construction Contracts and
Law Survey 2015

This year (2018) JCT has shown a marked growth, and is now at levels not seen since 2011. NEC,
which had been growing year on year, has contracted and has returned to the levels that we saw in
2011. Use of bespoke contracts has fallen from 11% to 5%.
Main works contracts
JCT (2016) NEC3 (2013)
• Standard Building Contract - 3 NEC3/NEC4 Engineering and
versions Construction Contract
• Intermediate Building Contract - 2
versions (1 with Contractor design)
• Major Project Construction contract
• Design and Build Contract
• Management building Contract
• Construction Management Contract
• Constructing Excellence Contract

Minor Works building Contract - 2 NEC3/NEC4 Engineering and


versions (1 with Contractor design) Construction Short Contract

= 12 works contracts = 2 works contracts


Contract structure
JCT (2016) NEC3 (2013)
Articles of Agreement Core clauses
Recitals Main option clauses A-F
Articles Secondary option clauses
Contract particulars Schedule/Shorter schedule of cost
components
Conditions Contract Data
Schedules
Generally
JCT (2016) NEC3
• Use traditional contract terminology • Contracts are intended to provide
(legalese), improvement/ dispute avoidance
through three main aspects –
• As contracts tested by legal challenges
over a considerable period, it’s argued Flexibility – cover building and
that JCT contracts provide greater civils/ pick and mix approach
certainty of legal meaning than NEC
contracts. Clarity and simplicity – use of
ordinary language, no cross
• However they are very detailed,
references, avoid subjective terms
contain lengthy sentences, lots of
defined terms, lots of cross referencing
Stimulus to good management –
& can be difficult to understand
collaborative approach, PM regime,
• Have limited details for processes with proactive processes to agree
timetables to manage issues. variations and claims as work
progresses
Project Management/ Contract Administration
JCT NEC
Are administered by an Architect / Include roles for:
Contract Administrator. There is also a
Quantity Surveyor to carry out valuations • a Project Manager to manage and
(including variations and loss and administer the contract and
expenses matters).

• A clerk of works may also be appointed • a Supervisor to check that work is


to act as an inspector. carried out in accordance with the Works
Information.

The Architect / Contract Administrator NEC contracts are driven by a set of


role generally doesn’t involve the pro processes that involve the parties working
active process driven approach required together to resolve issues as they occur.
for the Project Manager to NEC
contracts.
Project Management/ Contract Administration

JCT NEC
Select a CA with the skill to tightly control It’s important that the Project Manager
the account throughout the project - has appropriate qualities, project
goodwill can disappear when the parties management skills and understanding of
have unresolved claims for time and NEC contracts to pro actively manage the
money (arising from relevant events), contract and to foster collaborative
which are difficult to unravel, and there is working with the contractor.
pressure to close the account and switch
attention to other projects
So choose your project manager
carefully, as the contract depends on
solid project management. PM’s often
administer NEC contracts in a similar way
to JCT contracts which is best avoided.
Management input

= Similar
management
input overall
Collaboration/ Partnering
JCT NEC
“The Parties shall work with each other & “The Employer, the Contractor, the Project
with other project team members in a co- Manager and the Supervisor shall act as
operative and collaborative manner, in stated in this contract and in a spirit of
good faith & in a spirit of trust & respect. mutual trust and co-operation.”
To that end each shall support (Clause 10.1 – Core Clause)
collaborative behaviour & address
behaviour which is not collaborative”
(Schedule 8, Supplemental Provisions,
item 1)
This is included as an option – the This is included as the first of the core
default is that it applies, but it can be clauses reflecting the importance of such
omitted. relationships as an integral aspect of the
• the contract is limited in terms of processes for managing NEC contracts,
processes that involve a collaborative e.g. in relation to early warnings and
approach to manage issues. compensation events.
Pricing
JCT NEC
• With quantities (Lump sum contract) Option A – Priced Contract With Activity
• Employer provides drawings and bills Schedule
of quantities specifying quantity and
quality of work Option B – Priced Contract With Bill of
Quantities
• Without Quantities (Lump sum contract) Option C – Target Contract With Activity
• Employer provides drawings together Schedule
with a description of works and either
a specification or work schedules Option D – Target Contract With Bill of
Quantities
• With Approximate Quantities (Re-
measurable) Option E – Cost Reimbursable Contract
• Employer provides drawings and
Option F – Management Contract
approximate bills of quantities.
The NEC Contract doesn’t include provisional
• The JCT Contract contains provisional sums
sums
Payment
JCT (2016) NEC
• The JCT contract payment section is • In the NEC contract it is located in three
clear, is all in one section (clause 4) different locations – clause 5, Y(UK)2
and easy to follow. Listed items – and Contract Data Part 1.
permits payment for materials off site
• Option A - Activity schedule - items
• Payments are generally calculated by need to be 100% complete before
QS based upon assessment of work payment is made. Encourages
done plus materials, following an Contractor to stick to programme
application made by the Contractor.
• Option B – BofQ – payment is based on
a remeasure + proportions of lump
sums

• Options C-F payment is based upon


forecast of defined cost to be paid
before next assessment + Fee
Key bits
Key requirements
Time These areas are key:

• Cost - timely agreement of the value of


changes
+Risk • Time - how it deals with the programme
• Quality – inspection arrangements and
defects resolution
• Risk – how these are identified and resolved
Cost Quality

16
Comparison
• The following slides compare

• the JCT Standard Building Contract (SBC) without


quantities 2016 with

• NEC3 Engineering and Construction Contract 2013 with


Main Option A

• as these are understood the most widely used (JCT D&B


being a close second)
Cost - variations/ claims generally
JCT (2016) NEC3
Variations are valued by: Assessment of change is radically
different in NEC
• agreement between the Employer
and the Contactor, • Based upon the pre-assessment of
change based on forecast costs not
• quotations accepted by the Architect/ tendered rates and prices
CA,
• A Contractor should be neither better
• or by the QS using the Valuation Rules nor worse off for an Employer-driven
on the basis of: change event occurring
• relevant rates and prices in the
contract for work of a similar • Any ‘extension of time’ & associated
character costs must be included in each CE
• or in the absence of such at fair
rates and prices • However tendered rates and prices
• or Dayworks. can be used if parties agree
Cost - variations/ claims generally
JCT (2016) NEC3
Loss and expense payment is allowed where there is Dealt with under the compensation events
delay in providing possession of the site to the procedure and payment is assessed on the basis of
contractor or where progress is affected by “Relevant the effect on forecast / actual cost (at open market /
Matters.” competitively prices or rates in the Contract Data as
relevant) plus a tendered fee percentage (for profit
and any costs not covered elsewhere). Any loss and
expense is captured in compensation events
JCT provides a number of subjective tests for
determining if certain events give grounds for NEC generally relies on more objective tests e.g. NEC
recompense to the contractor. An example of this is uses a worse than 1 in 10 year approach to weather,
weather, JCT refers to ‘exceptional adverse weather which is objective.
conditions, which is subjective
Compensation events are allowed for a range of
In JCT the contractor is only obliged to claim for issues defined in the contract including a catch all for
more time and money after the risk event has “a breach of contract by the Employer which is not
occurred, which puts the employer in an extremely one of the compensation events in this contract.”
difficult management position There’s no other provision for the contractor to
recover payment in respect of such issues.
Cost - pros
JCT (2016) NEC3
The JCT provisions to value variations may be As variations shouldn’t occur because of the
less onerous in terms of input than fault of the contractor, the effect on forecast /
compensation events procedure under NEC actual cost is a fairer basis for valuation (rates
contracts, for example where this is on the for similar work may be skewed to benefit
basis of existing rates and prices either the contractor or the Employer
depending on the tendering contractor’s
pricing strategy / cash-flow requirements).

NEC includes a defined process with a clear


timetable (extendable by agreement) for
notifying, evaluating and implementing
compensation events. Compensation events
are evaluated in terms of both cost and time
(delays to the Completion Date and key
dates);
Cost – pros
NEC3 (2013)
Both the contractor and the PM have responsibilities to notify and respond to
relevant compensation events, for example:

• Time barring - if the contractor fails to notify an existing or expected CE within 8


weeks of becoming aware of it, he is not entitled to claim for the event unless the
PM should have notified the contractor of the event, but failed to do so.

• Deemed acceptance
• If the PM does not respond to a notification of an event notified by the
contractor in accordance with the required timetable then the event is
treated as a CE and the contractor submits a quotation.

• If the PM fails to respond to a quotation by the contractor in accordance with


the required timetable (except for a proposed change / instruction) then
quotation is deemed to be accepted.
Cost - cons
JCT (2016)
The inclusion of several pricing options for variations may result in disagreements as to which
option applies.

Claims for extensions of the contract period are notified and evaluated under separate
conditions of contract to those for cost; there’s no specific requirement to use the contractor’s
programme to evaluate extensions.

The provisions for “loss and expense” payments are without prejudice to any other rights and
remedies that the contractor may possess.

Except when the quotation procedure is used the absence of a clear timetable for evaluating all
variations and claims (for both cost and time concurrently) in real time increases the potential
for issues to build up during the contract and increase uncertainty as to the final outcome.
Programme/ Delays
JCT (2016) NEC3

The contractor is only required to submit Include detailed requirements for


a programme at the start of the contract programmes (including resources for each
and provide a revised programme if an operation).
extension is granted (although the
preliminaries may require the contractor Revised programmes, showing actual
to update the programme to show progress for each operation and its effects
progress). on the timing of remaining work are
required including at specified intervals
The contract doesn’t require the and in relation to compensation events;
programme to be accepted by the
Architect / CA, or to be used for each programme is subject to acceptance
monitoring progress, or assessing by the Project Manager.
extensions.
Programme/ Delays
JCT (2016) NEC3

• The absence of a requirement for • The programme is a key tool for


an accepted detailed programme managing the contract; the accepted
updated to show actual progress, to programme is used to assess delays
be used for evaluating delays and and extensions to the contract in real
extensions, increases the potential time under the compensation events
for issues to build up through the procedures.
contract and increase uncertainty as
to the final outcome. The programme is often described as
the ‘beating heart’ of the contract.
Practical Completion

JCT NEC3 (2013)

• JCT which relies upon a subjective • NEC identifies a state at completion


judgement of practical completion which is defined within the works
determined at the time. information

• JCT requires the issue of a non


completion certificate before LAD’s can
be withheld
Quality/ Defects
JCT (2016) NEC3

• Defects after completion are to be • Defects after completion are to be


rectified within a reasonable time rectified within the defects correction
period, a specific time period

• With NEC, there is an obligation on


both contractor and supervisor to
notify each another of defects as soon
as they are aware of them, providing
a more open process for highlighting
and dealing with defects.

• This same obligation is not found in


JCT.
Risk management
JCT NEC3 (2013)

• Risk allocation is largely fixed • Risk allocation can be better tailored

• In the JCT contract ground risk is with • Early warning is required if time, quality
the contractor. However, the NEC or cost could be impaired. Failure to
contract uses the ICE foreseeability notify an issue may adversely the affect
test in relation to ground conditions. the valuation of a compensation event
arising from it in relation to the contractor
• It is not uncommon for JCT contracts or Employer (depending on the party
to be extensively modified to transfer failing to give notice).
risk
• Both parties are required to list matters
to be included in Risk Register in Contract
Data
Early warning
JCT (2016) NEC3

JCT contracts don’t include a proactive One of the stimuli to “good management”
early warning procedure (to pre-empt under NEC is the early warning system.
problems) and generally rely on the The aim is to pre-empt potential problems
provisions in the contract to deal with and mitigate their impact.
issues when they occur.
Early warning provisions involve the
• The exception to this is the JCT maintenance of a risk register and place
Construction Excellence contract which obligations to notify each other if a
contains some risk management relevant issue occurs and to attend and
provisions. co-operate at a risk reduction meeting.

Failure to notify an issue may adversely


the affect the valuation of a compensation
event .
Summary pros and
cons
Summary – JCT - pros

• Building industry is arguably better geared up for it


• Arguably provide greater certainty of legal meaning
• Some may prefer its specific contract structure
• More familiarity within the industry
Summary – JCT - cons
• Contain legalese
• Are very detailed, contain lengthy sentences, lots of defined
terms, lots of cross referencing & can be difficult to understand
• Have limited details for processes with timetables to manage
issues.
• Contracts tend to get left in drawer
• Programme is not a binding contract document
• Late claims not time barred
• Rigid risk management procedures
Summary – NEC - pros
• Endorsed for public sector by government
• Are flexible
• Claim to be clearer and simpler to understand
• Act as a stimulus to good management, potentially providing
greater certainty of outcome in terms of cost and time
• Contain good procedures for managing risk
• Encourage parties to work together
• Use objective tests (rather than subjective)
Summary – NEC - cons
• Contract needs to sit on desk
• If not proactively managed, properly understood and
resourced from outset problems can arise
• Requires careful drafting (e.g. Works Information)
• Lack of industry awareness in some quarters (even now)
• Disputes often get resolved by Adjudication so findings remain
private
Summing up
Contract choice
So which contract would you choose?:

1. Time – which contract is more likely to ensure the project is


finished on time
2. Cost – which contract will give better value/ more cost
certainty
3. Quality – which contract will give me a better product
4. Risk – which contract is better at dealing with risk

Both can be used on the YORbuild2 framework.


Q&A/ Close

S-ar putea să vă placă și