Documente Academic
Documente Profesional
Documente Cultură
ON
LT NETWORK STUDIES
By
P Abhishek 2K12/EE/096
The undersigned certify that the winter training project entitled LT NETWORK
STUDIES submitted by P. Abhishek to the Zonal Manager (Z-509), TATA Power
Distribution Limited, in partial fulfillment of requirement for the winter training
program certification at TATA Power Delhi Distribution Limited. The project was
carried out under special supervision and within the time frame prescribed by the
program.
We found the student to be hardworking, skilled, and ready to undertake any
commercial and industrial work related to their field of study.
………………………………
Mr. Davinder Bhatia
Zonal Manager, Z-509
LT NETWORK STUDIES 2
ACKNOWLEDGEMENT
P. ABHISHEK
(2K12/EE/096)
LT NETWORK STUDIES 3
LIST OF FIGURES
S. NO. FIG. NO. FIGURE NAME PAGE
NO.
1 1a Single line diagram of a typical power system 09
2 1b Peak demand v/s peak demand met in NCT of Delhi 10
3 1c Actual power supply position of NCT of Delhi 10
4 2a Power distribution companies in NCT of Delhi 12
5 4a Typical layout of a distribution substation 15
6 4b Power transformer 16
7 4c Instrument transformer 17
8 4d Autotransformer 17
9 4e Core type 18
10 4f Shell type 18
11 4g Bus bars 19
12 4h Insulator string 20
13 4i Oil circuit breaker 21
14 4j Air blast circuit breaker 22
15 4k SF6 circuit breaker 22
16 4l Vacuum circuit breaker 23
17 4m Capacitor bank panel 23
18 4n CG Lucy Ring Main Unit 25
19 5a Compact fault locating system 26
20 5b Compact fault locating system capacitor bank 27
21 5c Compact fault locating system control computer 27
22 5d Compact fault locating system Digi phone 28
23 5e Types of cables 28
24 5f Process flow 30
25 5g HV Teleflex method plot 32
26 5h Arc reflection method plot 33
27 5i Impulse current method plot 34
28 5j Cable route tracer 35
29 5k Cable route tracing 35
30 7a Barricading of the transformer under test 50
31 7b Extraction of oil sample 50
32 7c Oil sample under test in DGA kit 51
33 7d Result 1: Gas concentrations 51
34 7e Result 2: Roger’s ratios 52
35 7f Result 3: Duval’s triangle 52
36 7g Result 4: Final result analysis 53
37 8a An opened up 3 phase transformer 54
38 8b Megger instrument 56
39 8c Oil BDV tester 56
40 8d Oil filtration machine 58
LT NETWORK STUDIES 4
LIST OF TABLES
LT NETWORK STUDIES 5
CONTENTS
S. NO. CONTENTS PAGE
NO.
1 Acknowledgement 3
2 List of figures 4
3 List of tables 5
4 1. Introduction 7-10
1.1. Growth Scenario: Indian power sector
1.2. Regional power systems development
1.3. All India capacity region wise
1.4. Power demand – Supply position of NCT of Delhi
5 2. Organization profile 11-12
2.1. Background
2.2. Awards and recognitions
6 3. Objective of this project 13-14
3.1. Scope of this project
3.2. Importance of this project
7 4. Zonal Office/Centre 15-25
4.1. Transformers
4.1.1. Types of transformers
4.2. Bus bars
4.3. Insulators
4.4. Circuit breakers
4.4.1. Oil circuit breaker
4.4.2. Air blast circuit breaker
4.4.3. SF6 circuit breaker
4.4.4. Vacuum circuit breaker
4.5. Capacitor bank
4.6. Ring Main Unit (RMU)
8 5. Fault Locating Cell (FLC) 26-35
5.1. Compact system
5.2. About cables
5.2.1. Essential power cable components
5.2.2. Basic requirements of healthy cable
5.2.3. Causes of cable fault
5.3. Process flow
5.3.1. Cable fault location using compact system
5.3.2. Mandatory checks before starting of test
5.4. Testing
5.4.1. Insulation resistance (IR) measurement
5.4.2. HVDC testing
5.4.3. Prelocation
LT NETWORK STUDIES 6
5.4.4. Pin pointing
5.4.5. Fault confirmation
5.5. Cable route tracing using audio frequency
generator (AF 200)
9 6. Network Engineering Group 36-45
6.1. State wise AT&C losses
6.2. Major reasons of high technical losses on LT level
6.2.1. Unbalancing load on transformer LT side
6.2.2. Unbalancing load on LT feeders
6.2.3. High loading on existing feeders due to less no.
of feeders at substation
6.2.4. Low loading on existing feeders due to high no.
of feeders at substation
6.2.5. Large length of existing LT feeders
6.2.6. Using of bare conductor as a LT feeder
6.2.7. Sick cable
6.2.8. Faulty LT ACB’s/MCCB’s
6.2.9. Higher level of theft
6.3. Case study of Pitampura
6.3.1. For technical loss reduction on LT level
6.3.2. Discussion with zone & verification of LT feeders
load
6.3.2.1. New feeder proposals
6.3.2.2. Interconnector proposals
6.3.2.3. Shifting of NOP’s
6.3.2.4. Replacement of sick cable/de-rated cable
6.3.3. Proposed scenario
6.3.4. Benefits to costumer and government
10 7. Maintenance and Planning Group (MPG) 46-53
7.1. Process flow
7.2. Dissolved gas analysis
11 8. Transformer workshop 54-58
8.1. Transformer testing and process/steps of
transformer overhauling
8.1.1. Series lamp test
8.1.2. Megger
8.1.3. Oil BDV test
8.1.4. Interpretation of the tests
8.1.5. Transformer testing post overhauling
8.1.6. Transformer oil filtration
12 9. Conclusion 59
13 10. References 60
LT NETWORK STUDIES 7
1. INTRODUCTION
India possesses one of the largest power generation capacities in the world (its
current ranking is Third) with an installed capacity of 237 GW as on Feb 2014,
which is about 4.8 percent of global power generation. The top developed
countries, viz., China & USA, Japan and Russia together consume about 60
percent of the total power generated globally. As of January 2012, it was reported
that the per capita total consumption in India to be 778 kWh.
1.1. GROWTH SCENARIO: INDIAN POWER SECTOR:
Development of Power Sector is the key to the economic development. The power
Sector has been receiving adequate priority ever since the process of planned
development began in 1950. The Power Sector has been getting 18-20% of the total
Public Sector outlay in initial plan periods. Remarkable growth and progress have
led to extensive use of electricity in all the sectors of economy in the successive
five years plans. Over the years (since 1950) the installed capacity of Power Plants
(Utilities) has increased to 89090 MW (31.3.98) from meagre 1713 MW in 1950,
registering a 52d fold increase in 48 years. Similarly, the electricity generation
increased from about 5.1 billion units to 420 Billion units – 82 fold increase. The
per capita consumption of electricity in the country also i ncreased from 15 kWh
in 1950 to about 338 kWh in 1997-98, which is about 23 times. In the field of
Rural Electrification and pump set energisation, country has made a tremendous
progress. About 85% of the villages have been electrified except far -flung areas in
North Eastern states, where it is difficult to extend the grid supply.
LT NETWORK STUDIES 8
1.3. ALL INDIA CAPACITY REGION WISE:
THERMAL
Region Nuclear Hydro RES Grand Total
Coal Gas Diesel Total
ALL INDIA 140723.4 21381.85 1199.75 163305 4780 40195.4 29462.55 237742.90
LT NETWORK STUDIES 9
1.4. POWER DEMAND- SUPPLY POSITION OF NCT OF DELHI:
The NCT of Delhi has been facing peak demand and availability deficits over the
last few years. Peak demand deficit in the state has increased from 2% in FY 2005-
06 to 5% in 2012-13. Between 2005-06 and 2012-13, peak electricity demand
grew at a compound annual growth rate (CAGR) of 7%, while peak demand met at
CAGR of 6%. (See graph below)
There were very minute electricity deficits in Delhi as compared to other states.
Between 2005-06 and 2012-13, electricity requirement and availability, both grew
at CAGR of 3%. (See graph below).
LT NETWORK STUDIES 10
2. ORGANISATION PROFILE
2.1. BACKGROUND:
North Delhi Power Limited (NDPL) is a joint venture between Tata Power
Company and the Government of the National Capital Territory (NCT) of Delhi,
with the majority stake being held by Tata Power. It distributes electricity in
the north and northwest parts of Delhi and serves a population of about 5
million people. The company started operations on July 1, 2002, after the
unbundling of the previously established Delhi Vidyut Board. With a registered
customer base of around 1,200,000 and a peak load of around 1401 MW, the
company provides electric service throughout an area of 510 square kilometres.
NDPL has been the frontrunner in implementing power distribution reforms in
the capital city and is acknowledged for its implementation of advanced
distribution system technologies and best practices. Since privatization, the
aggregate technical and commercial (AT&C) losses in the NDPL service area
have shown a record decline. Today they stand at about 13.25%, which is a
significant reduction from a previous loss level of 54%. This decrease in loss
levels and a subsequent increase in the reliability of the network have been
made possible by the efforts of NDPL to incorporate new technologies and
innovative systems into its distribution framework.
Increasing demand for electricity and energy resource constraints at the global
level has prompted the need for significant improvements in the efficiency of
the power sector. The ability to connect renewable energy resources and
distributed generation systems as part of a total power delivery mechanism,
and use of electricity in the most efficient way based on demand-side
management concepts, are critical parts of the Smart Grid concept. The vision
of a Smart Grid is gaining credibility from pilot projects being implemented in
several different European and U.S. utilities. NDPL wants to be a front runner
in implementing the Smart Grid vision in India.
The proposed project has been identified by NDPL as a top priority and is
designed to improve the efficiency and reliability of its one-million customer
distribution system and to help provide application models for other
distribution networks in India. The Feasibility Study would develop
requirements and specifications for a smart grid implementation roadmap for
NDPL and would address a range of improvements and investments including
integrating smart meters and automated meter reading into NDPL's
distribution system as well as greater system integration with distributed
generators and other smart grid applications.
LT NETWORK STUDIES 11
2.2. AWARDS AND RECOGNITIONS:
• Tata Power’s Singapore-based subsidiary Trust Energy Resources was
conferred the 'International Maritime Awards 2013' by the Singapore
Government. The award grants the company tax exemption for shipping
operations, besides incentives.
• Tata Power won two awards at the Power Line Award 2013: Best Performing
Private Discom' award for its Delhi distribution arm Tata Power Delhi
Distribution Limited and Runners up award for 'Best Performing Renewable
Company'.
• Trombay Thermal Power Station received Greentech Safety Award 2011 in
the gold category (in thermal power sector) for Safety Management.
LT NETWORK STUDIES 12
3. OBJECTIVE OF THIS PROJECT
The objective of this project is to study and analyse the low tension networks in
NCT of Delhi under the authority of TATA Power Delhi Distribution Limited. The
project also deals with various functional blocks of a distribution system, its
integrated planning and equipment maintenance techniques involved in the
system. Low tension networks may also be referred to as distribution networks.
Distribution networks can be further classified as
i. Primary Distribution (33 KV and above)
ii. Secondary Distribution (11 KV/ 6.6 KV/ 3.3 KV)
iii. Tertiary Distribution (400 volts 3 phase)
LT NETWORK STUDIES 13
upgraded which applies a large cost. Installation of DGs and capacitors in
a distribution network can alleviate this issue while the other benefits are
gained.
In this project, analysis of a case study for network revision scheme of
Pitampura has been done. Apart from this, this project also presents some
of the aspects involved in a distribution network mentioned below:
LT NETWORK STUDIES 14
4. ZONAL OFFICE/CENTRE
LT NETWORK STUDIES 15
Further, we will be discussing some of the power components and equipment that
are used in a distribution substation.
4.1. TRANSFORMERS:
Transformer is a static machine, which transforms the potential of
alternating current at same frequency. It means the transformer transforms
the low voltage into high voltage & high voltage to low voltage at same
frequency. It works on the principle of static induction principle. When the
energy is transformed into a higher voltage, the transformer is called step
up transformer but in case of other is known as step down transformer.
4.1.1. Types of transformers:
• Power transformer
• Instrument transformer
• Auto transformer
• On the basis of working
• On the basis of structure
LT NETWORK STUDIES 16
4.1.1.2. Instrument Transformer:
Fig. 4 d Autotransformer
Types of autotransformers:
• Single phase transformer
• Three phase transformer
LT NETWORK STUDIES 17
4.1.1.4. On The Basis Of Working:
• Step down: Converts high voltage into low voltage.
• Step up: Converts low voltage into high voltage.
LT NETWORK STUDIES 18
Fig. 4 g Bus bars
4.3. INSULATORS:
The insulator serves two purposes. They support the conductors (bus bar) and
confine the current to the conductors. The most common used material for the
manufacture of insulator is porcelain. There are several types of insulators (e.g.
pin type, suspension type, post insulator etc.) and their use in substation will
depend upon the service requirement. For example, post insulator is used for bus
bars. A post insulator consists of a porcelain body, cast iron cap and flanged cast
iron base. The hole in the cap is threaded so that bus bars can be directly bolted
to the cap.
LT NETWORK STUDIES 19
Fig. 4 h Insulator string
LT NETWORK STUDIES 20
4.4.1. Oil Circuit Breaker:
A high-voltage circuit breaker in which the arc is drawn in oil to
dissipate the heat and extinguish the arc; the intense heat of the arc
decomposes the oil, generating a gas whose high pressure produces a
flow of fresh fluid through the arc that furnishes the necessary
insulation to prevent a restrike of the arc.
The arc is then extinguished, both because of its elongation upon
parting of contacts and because of intensive cooling by the gases and oil
vapor.
LT NETWORK STUDIES 21
neighboring equipment. Since there exists a very high voltage between
the conductor and the air reservoir, the entire arc extinction chambers
assembly is mounted on insulators.
Vacuum circuit breakers are circuit breakers which are used to protect
medium and high voltage circuits from dangerous electrical situations.
Like other types of circuit breakers, vacuum circuit breakers literally
break the circuit so that energy cannot continue flowing through it,
thereby preventing fires, power surges, and other problems which may
emerge. These devices have been utilized since the 1920s, and several
companies have introduced refinements to make them even safer and
more effective.
4.5. CAPACITOR BANK:
LT NETWORK STUDIES 23
The load on the power system is varying being high during morning and evening
which increases the magnetization current. This result in the decreased power
factor. The low power factor is mainly due to the fact most of the power loads are
inductive and therefore take lagging currents. The low power factor is highly
undesirable as it causes increases in current, resulting in additional losses. So in
order to ensure most favorable conditions for a supply system from engineering
and economic point of view, it is important to have power factor as close to unity
as possible. In order to improve the power factor come device taking leading power
should be connected in parallel with the load. One of the device can be capacitor
bank. The capacitor draws a leading current and partly or completely neutralize
the lagging reactive component of load current.
Capacitor bank accomplishes following operations:
• Supply reactive power
• Increases terminal voltage
• Improve power factor
LT NETWORK STUDIES 24
Fig. 4 n CG Lucy Ring Main Unit
LT NETWORK STUDIES 25
5. FAULT LOCATING CELL (FLC)
This department has the responsibility to find out the location of a cable fault
using various apparatus /compact system. Apart from this, underground cable
route tracing is also done by the job. All these activities are discussed in detail as
shown below.
5.1. COMPACT SYSTEM:
• Compact instrument is used for underground cable fault location.
• The system is supplied by SEBAKMT GERMANY.
• It uses most modern technology for cable testing, fault pre-location &
fault location.
• It is operated by software so operation is very simple.
• Compact System is a latest technology, is a self-contained cable testing
system.
• It is incased in a small instrument with relatively light computer aided
system.
• Exact pre-location of the fault can be found using new method i.e. Arm
plus.
• The system provides an easy method for testing, adjusting surge
voltages and capacitor charging and discharging time.
LT NETWORK STUDIES 26
Fig. 5 b Compact fault locating system capacitor bank
LT NETWORK STUDIES 27
Fig. 5 d Compact fault locating system Digi phone
LT NETWORK STUDIES 28
5.2.1. Essential power cable components:
• Conductor: Either Copper or Aluminium is used.
• Insulation: The insulation used for power cables can be PAPER
or cross linked poly-ethylene (XLPE)
• SHEATH / ARMOUR
• FILLERS
• OUTER SHEATH
5.2.2. Basic requirements of healthy cables:
• Electrical continuity from one point to another point.
• Continuity of insulation between Core to core and core to earth.
Loss of any of these condition result in cable fault to OPEN CIRCUIT
and SHORT CIRCUIT or EARTH FAULT.
5.2.3. Causes of cable fault:
• Mechanical damage
• Damaging of sheath or insulation - External agents.
• Sheath corrosion- due to chemical action
• Vibration- due to heavy traffic on road
• Thermal damage- Increase in thermal Resist. Of soil, hot pipe
• Operational Problem
• Cable deterioration- due to overloading
• Joint deterioration- migration of semi fluid compounds from
joints, electrical tracking along the insulation owing to poor stress
control.
• Terminal defects
• Poor workmanship - joints
• Manufacturing defect - cracked lead sheath
LT NETWORK STUDIES 29
5.3. PROCESS FLOW:
LT NETWORK STUDIES 30
5.4. TESTING:
5.4.1. Insulation resistance (IR) measurement:
• IR measurement is done by using MEGGER.
• Phase to phase & phase to ground is tested using 5 KV megger
for 1 minute/or till reading stabilizes.
• Min. IR value for healthy phase is 50 Mohm (11 KV), 100 Mohm
(33 KV), 500 Mohm (66 KV).
5.4.2. HVDC Testing:
• High Voltage DC testing (Pressure Testing) is done only after IR
values are not found satisfactory.
• Each phase is tested for 5 min. w.r.t. ground & other phases
grounded at 6.5 KV (11 KV cable), 19.5 KV (33 KV), 38 KV (66
KV).
• The leakage current pattern is observed during the testing period
(shown graphically in compact System).
• If the leakage current has a rising trend, the cable is faulty & if
downward trend, cable may become healthy.
• By testing faulty phase(s) is detected.
5.4.3. Prelocation:
Test Conducted from one end to ascertain the location of the fault
i.e. The fault distance from the cable testing end in meters.
Methods of Pre-Location:
• HV Teleflex or pulse echo/TDR: Suitable measuring pulses are
transmitted into the cable. The pulses pass along the cable at a
propagation Velocity that is dependent on the type of cable. Parts
of the transmitted pulse are reflected whenever the electrical
characteristics of the cable change or change in impedance of
cable and travel back to the source, where they are shown on the
display.
LT NETWORK STUDIES 31
Fig. 5 g HV teleflex method plot
LT NETWORK STUDIES 32
Fig. 5 h Arc reflection method plot
LT NETWORK STUDIES 33
Fig. 5 i Impulse current method plot
LT NETWORK STUDIES 34
whose output is fed into a suitable receiver/amplifier and presented as
an audible tone in headphones and as a signal strength in DB in the
receiver (FLE-10).
LT NETWORK STUDIES 35
6. NETWORK ENGINEERING GROUP (NEG)
LT NETWORK STUDIES 36
6.1. STATE WISE AT & C LOSSES:
Electricity is a concurrent subject and the responsibility of sub-transmission and
distribution segment and reduction of Aggregate Transmission and Commercial
(AT&C) losses in distribution network rest with the State Government and Power
Departments/Utilities. Government of India acts as a facilitator in supplementing
the efforts of States to provide power to consumers in an improved manner.
LT NETWORK STUDIES 37
6.2. MAJOR REASONS OF HIGH TECHNICAL LOSSES ON LT LEVEL:
6.2.1. Unbalancing load on Transformer LT side: Previously, some of the
transformer were unbalanced causing high neutral current
producing high losses. This unbalancing is due to unequal
distribution of load on the three phases. Let us take an example of
balance transformer of capacity 400 KVA having equal current in
three phases suppose R – 250 Amp, Y – 250 Amp, B – 250 Amp then
current in neutral N – 0 Amp. Now load on same
6.2.2. Unbalancing load on LT feeders: Previously, some of the LT feeder
were high loaded & some LT feeders having less loading fed from
same DT is main reason on production of LT losses.
For example A 630kVA DT having 4 LT feeders A, B, C & D having
following loadings:-
▪ Feeder A having loading 150 Amp.
▪ Feeder B having loading 250 Amp.
▪ Feeder C having loading 100 Amp.
▪ Feeder D having loading 70 Amp.
This shows unequal loadings of LT Feeders of a DT .Unloading due
to unequal load allocation on LT feeders.
6.2.3. High loadings on existing feeders due to less no. of feeders at
substation: In substation where low no of feeders exists but actual
requirement of feeders is more due to high load growth of the area.
For example A substation having 3 No’s of LT feeders but actual
requirement of the area is 4 No’s of LT feeder.
6.2.4. Low loadings on existing feeders due to high no. of feeders at
substation: In substation where large no’s of feeders exists but
actual requirement of feeders is more due to high load growth of the
area. For example A substation having 4 No’s of LT feeders but
actual requirement of the area is 3 No’s of LT feeder.
6.2.5. Large length of existing LT feeders: In area where LT feeder having
large length also one of the reason of the AT & C losses on the
distribution lines. Average length of the one LT feeder is approximate
is 300-500 meters.
6.2.6. Using of bare conductor as a LT feeder: High level of theft was
increases due to using of LT bare conductor. It is easier for the
peoples to theft the electricity direct from the bare conductor.
LT NETWORK STUDIES 38
6.2.7. Sick Cable: Sick cable or underrated cables are also one of the
reason of the AT & C losses. Many portion of the feeder consisting
sick cable having multiple joints or de-rated cable.
6.2.8. Faulty LT ACB’s/MCCB’s: During Fault or overloading of a LT
feeder, LT ACB’s/MCCB’s not tripped and sometimes LT-ACB burns.
This is also one of the reason for increase in the Technical losses.
6.2.9. Higher Level of theft: High level of theft were due to mainly Non-
Installation of Temper Proof meter & Non-Installation of Temper
Proof meter.
LT NETWORK STUDIES 39
• Based upon summer’13 peak load, analysis was done on LT
network and found that 50 no. of feeders are overloaded (> 250
amperes).
• Load growth for Zone 530 is 4 % (calculated from 11 kV feeder
peak loading).
• After applying load growth for two years, 58 no. of feeders are
found overloaded (> 250 amperes).
• Technical loss (with load growth) in LT NW including service lines
is assessed as 994 KW (3.273%).
Losses:-
1. Base-1 Network 3.06%(843KW)
2. Base-2 Network 3.27%(994KW)
LT NETWORK STUDIES 40
6.3.2. Discussion with Zone & verification of LT feeders load:
A joint discussion done with the zonal representatives to verify the
loadings of the LT feeders in BASE-1 Network & BASE-2 Network.
Planned Network in the Network Analysis Software:
After discussion with zonal representatives, modifications done in
the LT Feeder Loadings.
A planned network prepared in the system contains following types
of the proposals:-
• New Feeder proposal
• Interconnector proposal
• Shifting on NOP’s
• Replacement of Sick cable/De-rated cable.
6.3.2.1. New Feeder proposals: New LT feeders are proposed for relief of
the existing overloaded feeders with new ACB’s .Generally New
LT feeders are proposed in mid of the existing overloaded
feeders, to bifurcate the loading of the existing feeder.
The major advantages of ABC are:-
▪ Total elimination of faults on LT lines
▪ Improved reliability
▪ Avoidance of Theft by direct tapping
▪ Avoidance of Overloading of Distribution transformer
6.3.2.2. Interconnector proposals: In this type of proposals load of an
overloaded feeder is shifted to a low loaded feeder by using an
interconnector.
For example if an overloaded feeder having loading of 280 Amps
and one unloaded feeder nearby this overloaded feeder having
loading of 60 Amps. In this case we are creating an
interconnector between both of them & load shifted to unloaded
feeder by changing suitable NOP.
6.3.2.3. Shifting of NOP’s: In this type of proposals, two feeders touching
each other not electrically, only physically (NOP between them)
one feeder is overloaded and another is under loaded. By using
shifting of NOP’s we can shift load of overloaded feeder on under
loaded feeder.
LT NETWORK STUDIES 41
6.3.2.4. Replacement of Sick cable/de-rated cable: In this type of
proposals, for best utilization of existing feeders, sick portion &
de-rated portion of the cable is replaced with the required
capacity of cable or conductor.
Proposal No's
NOP Changes 13
NOP Changes after execution of proposal given
7
against other feeders
Revive faulty feeder 1
Work executed 3
BOQ already available in proposed DT scheme 2
Proposal not required 2
Total 28
Table 7 New scheme (Not Required)
LT NETWORK STUDIES 42
Contribution of proposals for Reduction in Technical Losses.
• New Feeders 35%
• Interconnectors 27%
• NOP Changes 23.5%
• Other Proposals 13.5%
After execution of above mentioned proposals, loading wise breakup of
feeders would be as given below:-
Existing NW with
Peak Load – 2013
Parameter and Two Years Load Planned NW (2015)
Growth (4% Each
Year)
LT NETWORK STUDIES 43
Major Material Description Unit QTY
ACB LT 400A EA 17
ACB LT 800A EA 4
CABLE 1.1KV AL 1X300 SQMM UNAR M 156
CABLE 1.1KV AL 1X630 SQMM UNAR XLPE M 165
CABLE 1.1KV AL 4CX300 SQMM XLPE ARM M 1465
CABLE ABC 1.1KVXLPE 3X150+1X150+1X16SQMM M 2420
POLE PCC 11 M LONG EA 2
POLE PCC 9 M LONG 160 KG EA 22
Table 9 Major materials used in the scheme
Calculation
LT NETWORK STUDIES 44
6.3.4. BENEFITS TO CUSTOMER & GOVERNMENT:
LT NETWORK STUDIES 45
7. MAINTENANCE AND PLANNING GROUP (MPG)
This group/department has the job to carry out maintenance and testing of the
various power transformers present in the TPDDL network. The power transformer
summary of TPDDL is shown below.
KV MVA NO. OF
TRANSFORMERS
11/6.6 5 1
33/6.6 10 2
33/11 1464 72
66/11 145 7
66/33 100 2
Total 1724 84
Table 11 Summary - North (N)
KV MVA NO. OF
TRANSFORMERS
33/11 166 9
66/11 1570 70
66/33 200 4
Total 1936 83
Table 12 Summary - North West (NW)
KV MVA NO. OF
TRANSFORMERS
11/6.6 5 1
33/6.6 10 2
66/33 300 6
66/11 1715 77
33/11 1630 81
Total 3660 167
Table 13 Summary - N+NW
LT NETWORK STUDIES 46
7.1. PROCESS FLOW:
LT NETWORK STUDIES 47
The remaining diagnostic tools have a more effective diagnostic accuracy
rate. They involve more calculation and therefore aren’t always the first
choice. However, these tools can offer superior results and there are now
more automated means of calculating these results. Many DGA toolkits
today provide some or all of these diagnostic tool results with their reports
on the gas data.
The ratios that make up the first three methods are listed below. The process
for each method uses a subset of these ratios with diagnosis of fault type
based on the fit of each ratio result to a specific range of values. One
important point to remember when using ratio-based diagnostic tools is that
minimum gas levels are required, and are generally defined in the guides,
for the ratio analysis to be considered valid. The ratios are as follows:
Ratio 1 (R1) = CH4/H2
Ratio 2 (R2) = C2H2/C2H4
Ratio 3 (R3) = C2H2/CH4
Ratio 4 (R4) = C2H6/C2H2
Ratio 5 (R5) = C2H4/C2H6
The Rogers (IEEE) and Basic Gas Ratios (IEC) methods utilize ratios R1, R2
and R5 which are implemented by the process listed above. The Rogers
method evolved from the Doernenburg method and the Basic Gas Ratios are
an improvement over the Rogers method. The research that led to the
changes in each case was to better correlate specific ratio value ranges for
fault types with databases of inspected cases of transformer failures.
The final ratio-based method is the Duval Triangle. The Triangle method
was developed empirically in the early 1970’s. It is based on the use of 3
gases (CH4, C2H4 and C2H2) corresponding to the increasing energy levels
of gas formation. One advantage of this method is that it always provides a
diagnosis, with a low percentage of wrong diagnoses. The triangle method
plots the relative % of the 3 gases on each side of the triangle, from 0% to
100%. The 6 main zones of faults are indicated in the triangle, plus a DT
zone (mixture of thermal and electrical faults). Approximately 200+
inspected cases in service were used to develop the Triangle. An example of
the Triangle method is below:
If, for example, the DGA results are:
CH4 = 100 ppm First calculate: CH4+ C2H4 + C2H2 = 300ppm
C2H4 = 100 ppm Then calculate the relative % of each gas:
C2H2 = 100 ppm Relative % of CH4 = 100/300 = 33.3 %
Relative % of C2H4 = 100/300 = 33.3 %
LT NETWORK STUDIES 48
Relative % of C2H2 = 100/300 = 33.3 %
These values are the triangular coordinates to be used on each side of the
triangle. To verify that the calculation was done correctly, the sum of these
3 values should always give 100%, and should correspond to only one point
in the triangle. Fig. 7 f shows a graphical plot of the Duval Triangle utilizing
data from an actual transformer with a poorly grounded part.
Typical results of DGA, as per the standards, have been tabulated as shown
below.
LT NETWORK STUDIES 49
Fig. 7 a Barricading of the transformer under test
LT NETWORK STUDIES 50
Fig. 7 c Oil Sample under test in DGA kit
LT NETWORK STUDIES 51
Fig. 7 e Result 2: Roger's ratios
LT NETWORK STUDIES 52
Fig. 7 g Result 4: Final result analysis
LT NETWORK STUDIES 53
8. TRANSFORMER WORKSHOP
LT NETWORK STUDIES 54
8.1. TRANSFORMER TESTING AND PROCESS/STEPS OF TRANSFORMER
OVERHAULING:
Before the start of Overhauling, Transformers are tested to analyze its
healthiness. Tests such as Series Lamp test, Megger are done, Oil BDV is
also checked.
8.1.1. Series lamp test:
This test is also known as Continuity test and is done to check the
healthiness of windings. Instruments used in this test are 230 volts
single phase supply, 40W lamp and shorting lead. 230 volt single
phase supply is fed between each phase of HV winding one-by-one
with a 40W lamp in series. The corresponding phase of LV winding
is shorted.
Deductions: The lamp must glow only when the LV winding is
shorted. If the lamp glows when LV winding is not shorted, it
indicates a short circuit in the winding. If the lamp does not glow
when LV winding is shorted, it indicates open circuit in the winding.
8.1.2. Megger:
The test voltage for performing the IR check is as follows:
HT-E: 5000V
LT-E: 1000V
HT-LT: 5000V
Minimum acceptable values for all distribution transformers are
shown below:
LT NETWORK STUDIES 55
Fig. 8 b Megger instrument
LT NETWORK STUDIES 56
8.2. INTERPRETATION OF THE TESTS:
• If the IR values of transformer are less than acceptable limit, the core -
coil assembly is washed with hot oil. This process is known as “hot oil
bathe”. It cleanses the winding from all sorts of dirt, sludge, moisture etc.
which improves the IR values. Further the transformer is subjected to
hot oil filtration with new oil to improve its IR values.
• If the BDV of oil is lower than 30 KV and if it does not possess the
desirable properties as mentioned in the previous section, the oil is
changed.
• Hot oil bathe is generally preferred for all the transformers.
LT NETWORK STUDIES 57
Fig. 8 d Oil filtration machine
LT NETWORK STUDIES 58
9. CONCLUSION
Now from this report we can conclude that electricity plays an important role in
our life. We are made aware of how the distribution of electricity is done. We also
came to know about the various parts of the Substation system. Through this
report, we learn about power system apparatus and equipment like transformers,
circuit breaker, ring main units etc.
FLC department contributed to our knowledge by making us aware of various
causes of faults in cables and conductors and how to locate those faults. We also
learned to successfully trace route of an underground cable and upload it into
GIS.
NEG helped us understand the basic concepts of LT network planning and
scheming. The analysis of case study indulges us into following conclusions:
1. Reduction in Technical Losses of LT feeders: The Over loading of LT
Network has almost been removed for the subject area and forced outage
of LT network have been on least.
2. Safety:-Safety of consumers is also increased by removing Bare
Conductors/Multiple Jointed conductors/Cables near to consumer’s
premises.
3. Reliability:-Reliability of network is also increased by creating backup of
existing LT feeder’s .Current carrying capacity of existing network is also
increased by replacing existing sick cables, de-rated cables & conductors.
4. Overload Mitigation of DT: - Some LT feeders of Overloaded DT’s is shifted
to on nearest low loaded DT’s. Which also help in overload mitigation of LT
feeders as well as DT’s.
MPG and transformer workshops are the places that taught us the intricate
details, structure and testing of transformers, both single phase and three phase.
LT NETWORK STUDIES 59
10. REFERENCES
1. Selectivity Analysis in Low Voltage Power Distribution Systems with Fuses &
Circuit Breakers, Paper No. 2008-PSPC-224, Marcelo Valdes, PE, Cindy Cline,
Steve Hansen, and Tom Papallo.
2. Seba KMT manual: Small cable test and fault location system for vehicle
installation.
3. Planning of distribution networks for medium and low voltage, Iman Ziari.
4. Tata Power-Distribution: Application for Distribution Licence: Case No 90 of
2014- Public Hearing.
5. A training report on Uttar Pradesh Power Corporation limited, Prateek
Agarwal, Babu Banarasi Das Northern Institute of Technology, Lucknow.
6. Serveron White Paper: DGA Diagnostic Methods.
7. Distribution Simulation Package for Low Voltage Distribution Network,
International Journal of Computational Engineering Research / ISSN: 2250–
3005, R. Chitra, R. Neelaveni.
8. Distribution system, Wikipedia.
9. Generation, Distribution and Utilization of Electrical Energy, C. L. Wadhwa
10. Power System Analysis, John J. Grainger and William D. Stevenson, Jr.
11. Electrical Power Systems, C. L. Wadhwa.
LT NETWORK STUDIES 60