Sunteți pe pagina 1din 1

Widening to two Lane with Paved Shoulders from Km.24.600 to km.70.

063 of Mudigere-Kadur section on NH-


NAME OF WORK:
173 on EPC mode in the state of Karnataka.
CLIENT: NH Zone PWD (Govt. Of Karnataka)
EPC CONTRACTOR: M/s.JMC Construction Pvt Ltd & CHVN Reddy (JV)
Minor Bridge: 58+430 (2x3x4.143)

S.No. Description UNIT No. Length Width Depth Quantity Remarks

1 PCC M15 FOR MNB & RETURNS


Cu.m. 1 13.700 7.45 0.100 10.207
MNB Cu.m. 2 1.200 7.45 0.100 1.788
Cu.m. 2 0.300 7.45 0.100 0.447
Returns Cu.m. 4 3.600 4.965 0.100 7.150
Approach Slab Cu.m. 2 16 3.300 0.100 10.560

TOTAL = 30.151 Cu.m.


2 M30 FOR MNB & RETURNS
Raft Cu.m. 1 16.000 7.45 0.350 41.720
Top Slab Cu.m. 1 16.000 6.85 0.300 32.880
End Walls Cu.m. 2 16.000 0.3 4.143 39.773
Mid Wall Cu.m. 1 16.000 0.25 4.143 16.572
Corbel Cu.m. 2 16.000 0.45 0.300 4.320
Shear Key Cu.m. 1 7.450 1.45 0.850 9.182
Haunch Cu.m. 8 16.000 0.3 0.150 5.760
Cu.m. 2 3.400 4.865 0.425 14.060 Raft
Cu.m. 2 4.865 0.437 2.571 10.919
Returns Cu.m. 2 5.740 0.348 0.875 3.496
Cu.m. 2 6.615 0.312 1.000 4.121
Cu.m. 2 6.615 0.180 2.381
Approach Slab Cu.m. 2 16 3.5 0.3 33.600
Hand Rails Cu.m. 6 17.040 0.175 0.17 3.042
Vertical posts Cu.m. 24 0.250 0.275 1.1 1.815

TOTAL = 223.641 Cu.m.


3 M20 FOR FOOTPATH
RCC FOOTPATH Cu.m. 2 20.080 1.5 0.075 60.240

TOTAL = 60.240 Cu.m.


4 M40 FOR RCC CRASH BARRIERS
RCC Crash Barrier Cu.m. 2 20.080 0.283 11.365

TOTAL = 11.365 Cu.m.