Sunteți pe pagina 1din 8

Name : FREDERIC REYES ROSLYN

Gender : Male
Marital Status : Married
Date of Birth : 28/Feb/1966
Nationality : FILIPINO
Tel No. : +639085656816 / +639128089117
Address : Greenville Subd. San Isidro Lubao Pampanga Philippines
Position Desired : SMP Supervisor/ Welding Supervisor
Email Address : frederickroslyn21@gmail.com

OBJECTIVE:
My objective is always provide quality & reliable product & service that meet requirement and
specification of our costumer. We aim to achieve and sustain total customer satisfaction.

 Commitment, Competency, Continuous learning, Concern, Compliance and People


Development.
 Implementation and maintain our Quality Management Program.
 Achieve continual improvement through periodic system assessment and implementation.

EDUCATIONAL BACKGROUND:

Period Qualification Name of Institution

June 2007 – December National Supervisory PSB Academy Singapore


2007 Course

April 1987 – May 1987 Welding Training National Manpower Youth


Council

1981 – 1985 Secondary School Luakan High School

1974 – 1980 Primary School Luakan Elementary School

TRAINING AND SEMINAR:

Period Description
October 7 - 10, 2013 Building Construction Safety Supervisors

September 9 – 21, 2013 Supervisor Workplace Safety and Health in Process


Plant

September 1 – 8, 2013 Work-At Height Course for Supervisors

April 17, 2013 Safety Orientation Course (OIL / PETROCHEMICAL)

January 9, 2013 Safety Orientation Course (CONSTRUCTION)


May 3, 2012 Behavioral Based Safety Observation

May 3, 2012 EM – SIC/S – HDS Project SIC

December 7, 2011 Technical Talk on Production Process and Advantages of


Seamless Flux-cored Wires

April 4, 2011 Radiographic Interpretation Course – Level 2

June 18, 2010 In-Hse – Metallurgy of Stainless Steel

March 25, 2010 Oil / Petrochemical Industry Safety Course for Supervisors

December 2, 2008 Industrial First Aid

December 30, 2008 In-HSE – Understanding of Welding Symbols

November 12, 2008 EM / OPMT – ESOC (Supervisory Level)

September 22 – 23, 2008 Liquid Penetrant Testing (PT) ASNT LEVEL 2

June 7, 2007 – December 18, 2007 National Certificate in Supervisor

September 26, 2007 Carbon Steel A – 2 (GTAW/SMAW) – P1A-2A2

May 02, 2007 INCOLLOY A -1 (GTAW)

October 13, 2007 Aluminium S - 1 (GTAW)

August 16, 2006 Alloy A -2 (GTAW / SMAW) – P9A – 2A2

October 10, 2005 People Developer – PD Renewal Audit

September 30, 2005 Flux Core – S4-1A2-25mm

August 11, 2004 ARC Welding (GTAW)

August 13, 2002 INCONNEL A – 2 (GTAW / SMAW) – P43A- 2A2

August 13, 2002 INCONNEL B – 1 (GTAW) – P43B – 1A2

July 7, 2001 Alloy A – 3 (GTAW / SMAW) – P9A – 2A30

July 7, 2001 Carbon Steel B – 1 (GTAW) – P1B – 1A1

July 7, 2001 Stainless Steel B – 1 (GTAW) – P8B – 1A2

EMPLOYMENT HISTORY:
Company : Lycopodium Minerals Pty.Ltd
Period : Oct, 8 2017 To Feb, 5 2018
Designation : SMP Supervisor
Client : Toro Mako Gold Mining Project ( Senegal West Africa)

Company : Orion Project Service (PNG) Ltd


Period : March 30, 2017 To May 16, 2017
Designation : SMP Supervisor ( Shut down )
Client : Monadelphous PNG Ltd, Kutubu

Company : ARCC-EEI Co. Ltd.


Period : July 7 2015 – July 28 2016
Designation : Welding Supervisor

Project Accomplished:

Duration Client / Project Title

October 2015 – Present Upgrade Onshore Flare Gas Recovery System

Company : TAMIA Co. Ltd.


Period : September 12, 2014 – February 14, 2015
Designation : Piping Superintendent

Project Accomplished:

Duration Client / Project Title

September 12, 2014 – Petrochemical Elastomer Plant Project


February 14, 2015

Company : TAMIA Co. Ltd.


Period : April 12, 2014 – August 17, 2015
Designation : Piping Superintendent

Project Accomplished:

Duration Client / Project Title

April 12, 2014 – August 17, 2014 YASREF Sinopec Project KSA

Company : Plant Engineering Ltd,


Period : July 12 2001 – July 12 2005
Designation : Tig Welder

July 12 2005 – July 12 2007


Welding Foreman

July 12 2007 – Aug 12 2009


Welding Supervisor
Oct 23 2009 – Nov 23 2011
Senior Welding Supervisor

Nov 23 2011 – Dec 2013


Piping Superintendent

Project Accomplished:

Duration Client / Project Title

July 01, 2013 – February 15, 2014 Leo & Silver Project / Shell Seraya Connected to Petro
Chemical Singapore

March 15, 2012 – April 30, 2013 Singapore Hydropolization Service Exxon Mobil Oil
Refinery (Jurong Island Singapore)

November 8, 2011 – March 6, 2012 Pump House 43 Recovery Project Phase 3 (Shell
Bukom Singapore)

January 8, 2008 – December 20, 2010 MPO6 Project Exxon Mobil Oil Refinery (16 Shipyard
road Singapore)

January 7, 2008 – August 9, 2008 ISBL Project Exxon Mobil Oil Refinery (Jurong Island
Singapore)

September 15, 2005 – December 6, 2007 Fabrication Shop of any shutdown work, feed
injector, GSK Vessel Repair, Atopia Project, Soxal
Shutdown, PCS Shutdown (Singapore Location)

August 14, 2002 – September 04, 2005 SRC Shutdown (Jurong Island Singapore)

July 12, 2001 – August 08, 2002 PFIZER Medicine Plant No. 19 Tuas Singapore

Company : Bechtel Company (Engineering Equipment Inc.)


Period : December 1999 – May 2001
Designation : Tig Welder

Duration Client / Project Title

May 12, 1999 – May 14, 2001 Rastanura Power Plant (Saudi Arabia)

Company : Hiap Seng PTE Ltd.


Period : Mar 1998 – Mar 1999
Designation : Tig Welder

Duration Client / Project Title

March 20, 1998 – March 03, 1999 SMP Project Smag. TPC, Asahi
Company : Takada Kogyo Company (Japan)
Period : November 1996 – December 1997
Designation : Tig / Mig Welger / Auto Machine weld

Duration Client / Project Title

November11, 1996 Only on Takada Fabrication Shop Work

Company : Bechtel Company (Engineering Equipment Inc.)


Period : November 1995 – Oct 1996
Designation : Tig Welder

Duration Client / Project Title

June 1994 – October 1995 Al Shoiba Power Plant

Company : Abdullah Al-Shuwayer Company (Damman, Jubail Saudi


Arabia)
Period : July 1992 – May 1995
Designation : Tig Welder

Duration Client / Project Title

July 1992 – May 1995 ARAMCO Piping and Tankage Project

Summary of Professional Experiences:

In our project we’re monitoring the installation of Piping, Mechanical, structural in gold mining
project. To the sub. contractor of local company. Alignment of agitator motor. Motor pump belts.
Installation of screen gravity. gravity concentrator. Screen trasher. Loaded screen. Pebble screen
Dewatering Screen. Cyclone. Thickener tank CIL Tank. SMBS Tank Water tank. Acid Tank Cynide tank
Mill Structural. Detox Tank. Elution area. Gold Room. COV 01.COV 02 COV.03.COV 04. COV05.
Primary Crusher. Stationary Crusher. Pebble Crusher. Compressor area. Diesel tank area.

Piping Summary Installation: ( Water Lines, Gland water, Process Water, Potable Water, Raw
Water,
Monitor Water,Fire Water, Cooling Water, Flotation water,
High Pressure Water, Threated Water, Waste Water, Sewage )
Process Slurry Line: ( Process Slurry, Carbon Slurry)
Compressed Air &Gases: ( Plant Air, Instrument Air, Flotation air, Agitatioin Aeration & airlift air
Nitrogen, Sulphur Dioxide)
Lubricant & Fuel Lines: ( High Pressure Lube Oil, Low pressure Lube oil, Fuel oil , Fuel Gas (LPG.
LNG. Methane. Hydrolic Fluid.)
Reagent And Solution Lines: ( Flocculant, Cyanide, Pregnant Solution, Caustic, Hydrochoric Acid,
Strip Solution, Acid Effluent, Barren Eluate, Diesel, Sulphamic Acid,
Biocide, Anti Scalant, Sodium Metabisulphite, Copper Sulphate
Lime Slurry.)
During Shut down at ( OIL SEARCH ) were doing the mechanical work Removing And erection of old
& new Valve at Main header, Discharge Cooler, Pig Receiver, Flare Area. And Pipe rack. Deployment
of manpower by grouping for good direction of task activity to avoid any un finish work for the
whole night and to monitor the sequence of work, conducting of pre task talk for workers
preparation of tools that needed to install the valve. Monitor the torqueing sequence of bolt
tightening using of torch wrench before the inspection & acceptance of operator & QC.all permit
must be in place of work area.

Preparation of document for project ( Manpower plan, Target Plan Base on Engineering plan, Site
Visit, Drawing From General plan, Piping Arrangement Plan, Iso drawing, Material request by
Material Bill Wise, attending the Client Meeting with top management, Monitoring of Spool
Fabricated from Laydown to painting area, Monitoring of daily production from erection wise to fit
up And welding production, Monitoring of NDT, Hydro test and monitoring of Weekly And monthly
plan base on supervisor activity work plan execution for manpower work.

● Understanding of project procedure, DEP, (Design Engineering Process) Method Statement,


project work flow, S, Curve Plan, Manpower & man hour Plan per Dia Inch ,Down Time& Area Of
Concern, fabrication shop activity & field execution work, Iso man system material wise spool
delivery from painting area to site laydown production & NDE DWR Log sheet monitoring, Permit to
work (Hot Work & Cold Work) and review the PTW assessment 5X5 Matrix before I approve in the
system & sign, Inspection test plan, Welding procedure specification, Welder Qualification test base
on material specification, QC NDE, Understanding of welding symbol. Welding metallurgy, Visual
Inspection Penetrant liquid test, Radiography interpretation. Hydro test, preparation of WPS &WQT
if clientrequirement, Buttering weld for tankage, hot topping Work Safety procedure execution.as a
Shop superintendent all the project activity must be in a proper way of control, from material store
project color code identification to easily recognized which project belong the material fittings. All
the equipment and tools are in safe condition with valid LEW stickers before the workers used to
avoid the injury or incident.

● Currently my previous position in my company is a shop superintendent also I’m a member of


manpower committee. Before the project will be executed we need to review all the DEP (Design
Engineering Process) of the owner follow the client procedure document& Work Flow review.
Monitor all work execution specially the material deliver receiving from client that should be
inspected by our QC before the final inspection of Client QC for acceptance before we fabricate the
priority area based on site work flow priority, specially the jacketed pipe fabrication with two
different type of materials. The inner pipe is a stainless steel outer pipe is a carbon steel material,
monitoring the NDE requirement based ITP & client requirement before the fabricated spool will be
mobilize to painting area or site, preparing of down time for every area of concern also with some
mock up test that being requested by client. As of now our current project is Shell Shreya going thru
PCS Refinery. That being called (LEO & SILVER PROJECT) in jurong island of Singapore under CHIYODA
SINGAPORE LTD as our main con. Consumable material and materials will be issued by the
authorized person with knowledge & understanding on project procedure to avoid the mis-issuance
of wrong material. QC shall be monitor the material controller daily if the material & consumable
are correct issued. Welder list Procedure must be in place into bulletin board for more
understanding of welders & Pipe fitters.

● In March 13 2012 till May 16 2013: The company appointed me as a shop superintendent in a
project of Exxon Mobil under JGC as a Main contractor. ( SHDS Project) after the awarded of project
our team should prepare a document base on (DEP) Design Engineering Process, Work procedure,
QC Inspection Test Plan Procedure & Welding Procedure Specification, Welder List & Qualification
for client review And Approval. On further understanding of work execution under shop Fabrication.
Manpower, Work plan, Material Request, Work execution to their daily work activity and monitor
the daily fit up report & Daily Welding report Progress. Material Issuance monitoring all the NDE
requirement must be in place of work shop Like ITP, Welder List and any kind of procedure that
been approve by the client for more understanding of the welders & Pipe fitters or white helmet,
Material delivery must be inspected by the company QC if there some Manufactured defect or
damage, QC must inform & record with photo attachment on their report before the final inspection
of QC client, all material will be withdrawn by the authorized person like piping foreman or the
supervisor with their drawing to make it sure that material issued by material controller is correct
base on the identification of material to avoid the mis-issuance of wrong materials to the pipe
fitters. Welding consumable must be check by QC if required the PMI or Bottom test for Alloy & SS
materials .also the authorized person like welding foreman, welding supervisor or QC are allowed to
request & sign the request form to electrode control store, QC must check the baking oven if the
electrode baking is in correct temperature of 350 deg. Fahrenheit before they issue to the welder
also must check if the calibration is still valid. consumable controller make sure all the filler wire &
electrode are correct base to the request of authorized person to avoid the wrong consumable will
be welded on joint required WPS. Supervisor & Foreman will assign the welder with valid
certification or Qualification base on materials identification. Before the execution of pipe fitter
supervisor must be brief on their work activity same on other group, lifting supervisor will be submit
all the procedure including the lifting plan execution.

●In Nov.15 2011 till March 12 2012:I also handled the project of the fabrication of PH43 Recovery
under shell bukom after explosion of Pump43 in 2011. Shell are awarded to PEC the recovery project
of all the pipe line that being affected by the explosion. due of urgently of the project the fabrication
team immediately execute the fabrication once the material received from Client since the
procedure are preparing by the project team. All the QC requirement still follow base to the DEP of
Shell owner,

● In Aug 16 2008 Till Jan 9 2010: MPO6 Project as a senior welding supervisor of fabrication & Field
I’ve been monitoring 110 welder, I need to monitor all the field area & Shop for distribution of their
needed welder, the monitoring of critical flange activity, welder rejection rate, welder performance,
hot topping , buttering weld on tank, monthly welder KPI, daily welding report, Pre task Talk.
Improving of welder for any type of materials & Update their Primos certificate From Carbon Steel to
any different type of high grade materials. Tie – in shall be monitoring closely to avoid any rejection
and delayed of target date of achievement.

● As a senior welding supervisor must have a knowledge on basic & technical of welding process for
(Gtaw & Smaw) to guide the welder to improve their welding technique.

● Supervise the daily routine of welders & conduct the Pre task talk, Tool box meeting & discuss how
to be safe on their welding work to prevent the incident Before the execution of workers need to
conduct the daily activities and remind them on their work.

AS a piping Supervisor I need to monitor the daily fit up progress check the pipe spool, materials bill
base on materials wise on the system. Check the coordination from north. east. west And south.
Hauling of materials to erection of pipe spool check the piping arrangement on pipe rack. Check the
3D on the system
Report the daily progress to my superior.
Frederic Roslyn
Applicant

S-ar putea să vă placă și