Data Preparation on 2015

Date :19-10-2015

S.No ConstantPer Description Rate Per S.floor

Excavation Works
1 Earth Work Excavation upto 6'0"
level in all soils except SDR
Rate for 100Cft
100.00 Cft Labour Charges for Excavation 8.50 Cft 850.00
Total 850.00
Rate /Cft 8.50

Labour Charges for filling with


2 available earth including
&Consolidation
Rate for 100Cft
100.00 Cft Labour Charges for filling & levelling 4.00 Cft 400.00
100.00 Cft Labour Charges for Consolidation 2.00 Cft 200.00
Total 600.00
Rate/Cft 6.00

Refilling the trenches & basement


3 with imported earth including
consolidation,Earth brought from
outside
Rate for 100Cft
100.00 Cft Cost of imported earth 9.00 Cft 900.00
100.00 Cft Machinery Hire Charges 2.00 Cft 200.00
100.00 Cft Labour charges towards filling 4.00 Cft 400.00
100.00 Cft Labour charges for Consolidation 2.00 Cft 200.00
Total 1700.00
Rate/Cft 17.00
Over head & Profit 15% 2.55
Rate/Cft 19.55

4 Sand Filling
Rate for 100 Cft
100.00 Cft River Sand 45.00 Cft 4500.00
Labour Charges for filling &
100.00 Cft Consolidation 6.00 Cft 600.00
Total 5100.00
Rate /Cft 51.00

5 Plain Cement Concrete 1:4:8


Foundation base concrete PCC 1:4:8,
using 1½" metal for foundation
Rate for 100Cft
90.00 Cft 1½" metal 24.00 Cft 2160.00
58.50 Cft River Sand 45.00 Cft 2632.50
9.18 Bags Cement 390.00 Bags 3580.20
100.00 Cft Machinery Hire charges 2.00 Cft 200.00
100.00 Cft Labour Charges 8.00 Cft 800.00
100.00 Cft Curing Charges 1.00 Cft 100.00
Total 9472.70
Rate/Cft 94.73
Over head & Profit 15% 14.21
Rate/Cft 108.94

Foundation base concrete


6 PCC 1:5:10,Using 1½" metal
for foundation
Rate for 100Cft
90.00 Cft 1½" metal 24.00 Cft 2160.00
58.50 Cft River sand 45.00 Cft 2632.50
7.34 Bags Cement 390.00 Bags 2862.60
100.00 Cft Machinery Hire Charges 2.00 Cft 200.00
100.00 Cft Labour Charges 8.00 Cft 800.00
100.00 Cft Curing Charges 1.00 Cft 100.00
Total 8755.10
Rate/Cft 87.55
Over head & Profit 15% 13.13
Rate/Cft 100.68

Reinforced Cement Concrete(Site Mix) M20


7 CC-M20,1:1½:3 SiteMix excluding
centring& fabrication
Rate for 100Cft
90.00 Cft 20mm metal 24.00 Cft 2160.00
58.50 Cft River Sand 45.00 Cft 2632.50
23.00 Bags Cement 390.00 Cft 8970.00
100.00 Cft Machinery Hire Charges 2.00 Cft 200.00
100.00 Cft Curing Charges 1.00 Cft 100.00
Total 14062.50
Rate/Cft 140.63

8 Column Footing with CC 1:1½:3


Rate for 100Cft
100.00 Cft CC 1:1½:3 140.63 Cft 14062.50
100.00 Cft Labour Charges 28.00 Cft 2800.00
Total 16862.50
Rate/Cft 168.63
Over head & Profit 15% 25.29
Rate/Cft 193.92

9 Plinth beam concrete with C.C.1:1½:3


Rate for 100Cft
100.00 Cft CC 1:1½:3 140.63 Cft 14062.50
100.00 Cft Labour charges 30.00 Cft 3000.00
100.00 Cft Machinery Hire Charges 2.00 Cft 200.00
Total 17262.50
Rate /Cft 172.63
Over head & Profit 15% 25.89
Rate/Cft 198.52

10 Column concrete with CC1:1½:3


Rate for 100Cft
100.00 Cft CC 1:1½:3 140.63 Cft 14062.50
100.00 Cft Labour Charges 32.00 Cft 3200.00
100.00 Cft Machinery Hire Charges 2.00 Cft 200.00
Total 17462.50
Rate /Cft 174.63
Over head & Profit 15% 26.19
Rate/Cft 200.82

11 Rcc wall concrete with CC1:1½:3


Rate for 100Cft
100.00 Cft CC 1:1½:3 140.63 Cft 14062.50
100.00 Cft Labour Charges 35.00 Cft 3500.00
100.00 Cft Machinery Hire Charges 2.00 Cft 200.00
Total 17762.50
Rate /Cft 177.63
Over head & Profit 15% 26.64
Rate/Cft 204.27

12 Lintel conc. With CC 1:1½:3


Rate for 100Cft
100.00 Cft CC 1:1½:3 140.63 Cft 14062.50
100.00 Cft Labour Charges 30.00 Cft 3000.00
Total 17062.50
Rate /Cft 170.63
Over head & Profit 15% 25.59
Rate/Cft 196.22

13 Sill Slab with CC1:1½:3


12.50 Cft CC 1:1½:3 140.63 Cft 1757.81
36.00 kg Steel 49.00 kg 1764.00
100.00 Rft Labour Charges 10.00 Rft 1000.00
Total Rate for 100sft. 4521.81
Rate /Sft 45.22
Over head & Profit 15% 6.78
Rate/Sft 52.00

14 Roof Slab With CC 1:1½:3


Rate for 100Cft
100.00 Cft CC 1:1½:3 140.63 Cft 14062.50
100.00 Cft Labour Charges 24.00 Cft 2400.00
100.00 Cft Machinery Hire Charges 2.00 Cft 200.00
Total 16662.50
Rate /Cft 166.63
Over head & Profit 15% 24.99
Rate/Cft 191.62

15 Roof Beams with CC1:1½:3


Rate for 100Cft
100.00 Cft CC 1:1½:3,M20(RMC) 140.63 Cft 14062.50
100.00 Cft Labour Charges 25.00 Cft 2500.00
100.00 Cft Machinery Hire Charges 2.00 Cft 200.00
Total 16762.50
Rate/Cft 167.63
Over head & Profit 15% 25.14
Rate/Cft 192.77

16 Sunshade 50mm thick (average) with


CC1:1½:3
Rate for 100Sft
16.67 Cft CC 1:1½:3 140.63 Cft 2344.22
100.00 Sft Labour Charges 21.00 Sft 2100.00
Total rate for 100sft. 4444.22
Rate/Sft 44.44
Over head & Profit 15% 6.67
Rate/Sft 51.11

Brick Work
17 Brickwork 9" thick wall in CM
1:6,for superstructure works
Rate for 100Cft
1250.00 Nos Brick 5.50 Nos 6875.00
32.50 Cft River Sand 45.00 Cft 1462.50
3.40 Bags Cement 390.00 Bags 1326.00
100.00 Sft Scaffolding Charges 9.00 Sft 900.00
100.00 Cft Labour Charges 22.00 Cft 2200.00
100.00 Cft Curing Charges 1.00 Cft 100.00
Total 12863.50
Rate/Cft 128.64
Over head & Profit 15% 19.30
Rate/Cft 147.93

18 Brick partition wall 4 ½" thick in CM


1:5 including hoop iron
Rate for 100Sft
470.00 Nos Brick 5.50 Nos 2585.00
13.00 Cft River Sand 45.00 Cft 585.00
1.54 Bags Cement 390.00 Bags 600.60
140.00 Rft Hoop iron 5.00 Rft 700.00
100.00 Sft Labour Charges 16.00 Sft 1600.00
100.00 Sft Scaffoding Charges 9.00 Sft 900.00
100.00 Sft Curing Charges 1.00 Sft 100.00
Total 7070.60
Rate/Sft 70.71
Over head & Profit 15% 10.61
Rate/Sft 81.31

Ceiling Plastering in CM 1:3, 15mm


19 thick (Average) both internal &
External surfaces
Rate for 100Sft
6.25 Cft River Sand 45.00 Cft 281.25
1.70 Bags Cement 390.00 Bags 663.00
100.00 Sft Labour Charges 10.00 Sft 1000.00
100.00 Sft Scaffolding Charges 9.00 Sft 900.00
100.00 Sft Curing Charges 1.00 Sft 100.00
Total 2944.25
Rate/Sft 29.44
Over head & Profit 15% 4.42
Rate/Sft 33.86

Wall Plastering in CM 1:5,15mm


20 thick (Average) both internal &
External surfaces
Rate for 100Sft
6.50 Cft River Sand 45.00 Cft 292.50
0.80 Bags Cement (JSW) 390.00 Bags 312.00
100.00 Sft Labour Charges 8.00 Sft 800.00
100.00 Sft Scaffolding Charges 9.00 Sft 900.00
100.00 Sft Curing Charges 1.00 Sft 100.00
Total 2404.50
Rate/Sft 24.05
Over head & Profit 15% 3.61
Rate/Sft 27.65

21 Beam Plastering in CM 1:3


Rate for 100Sft
1.25 Bags Cement (JSW) 390.00 Bags 487.50
5.30 Cft River Sand 45.00 Cft 238.50
100.00 Sft Labour Charges 10.00 Sft 1000.00
100.00 Sft Scaffolding Charges 9.00 Sft 900.00
100.00 Sft Curing Charges 1.00 Sft 100.00
Total 2726.00
Rate/Sft 27.26
Over head & Profit 15% 4.09
Rate/Sft 31.35

22 Column plastering with CM 1:4, 15mm thick


Rate for 100Sft
1.14 Bags Cement 390.00 Bags 444.60
6.50 Cft River Sand 45.00 Cft 292.50
100.00 Sft Labour charges 10.00 Sft 1000.00
100.00 Sft Scaffolding Charges 9.00 Sft 900.00
100.00 Sft Curing Charges 1.00 Sft 100.00
Total 2737.10
Rate /Sft 27.37
Over head & Profit 15% 4.11
Rate/Sft 31.48
23 S/F of steel for RCC works including
cost of MS binding wire
Rate for 1 MT
1.03 MT Steel 45000.00 MT 46350.00
0.012 MT MS Binding wire 60000.00 MT 720.00
1.00 MT Labour Charges 7000.00 MT 7000.00
Total/MT 54070.00
Over head & Profit 15% 8110.50
Total/MT 62180.50

Weathering course using brick jelly


24 lime concrete for an average of 75mm
thick
Rate for 100Sft
25.00 Cft Brick Bats 20.00 Cft 500.00
250.00 Cft Lime 5.00 Cft 1250.00
100.00 Sft Labour for laying &Finishing 10.00 Sft 1000.00
100.00 Sft Curing Charges 1.00 Sft 100.00
Total 2850.00
Rate/Sft 28.50
Over head & Profit 15% 4.28
Rate/Sft 32.78

25 Weathering Tiles
Rate for 100 Sft
185.00 Nos Pressed tiles 18.00 Nos 3330.00
9.10 Cft River Sand 45.00 Cft 409.50
1.47 Bags Cement 390.00 Bags 573.30
100.00 Sft Labour for laying &Finishing 12.00 Sft 1200.00
0.29 Litres Approved WPC 250.00 Litres 72.50
100.00 Sft Curing Charges 1.00 Sft 100.00
Total 5585.30
Rate /Sft 55.85
Over head & Profit 15% 8.38
Rate/Sft 64.23

Grano Floor finish with CC 1:1.5:3


26 using 6mm chips 50 mm thick - Rate
for 100 sft.
16.67 Cft Chips 24.00 Cft 400.08
9.75 Cft River Sand 45.00 Cft 438.75
4.08 Bags Cement 390.00 Bags 1591.20
100.00 Sft Machinery Hire Charges 4.00 Sft 400.00
100.00 Sft Flooring laying & finishing 15.00 Sft 1500.00
100.00 Sft Curing Charges 1.00 Sft 100.00
Total 4430.03
Rate /Sft 44.30
Over head & Profit 15% 6.65
Rate/Sft 50.95

27 Providing & Laying of vitrified tiles


for flooring in CM 1:4
Rate for 100 Sft
105.00 Sft Cost of vitrified tiles 60.00 Sft 6300.00
10.79 Cft River Sand 45.00 Cft 485.55
2.05 Bags Cement 390.00 Bags 799.50
100.00 Sft Labour Charges 20.00 Sft 2000.00
100.00 Sft Curing Charges 1.00 Sft 100.00
100.00 Sft Average of lifting charge 3.50 Sft 350.00
100.00 Sft Misc. materials 3.00 Sft 300.00
100.00 Sft White cement 1.00 Sft 100.00
Total 10435.05
Rate /Sft 104.35
Over head & Profit 15% 15.65
Rate/Sft 120.00

28 Providing & Laying of Antiskirt tiles


for flooring in CM 1:4
Rate for 100 Sft
105.00 Sft Cost of Antiskirt tiles 40.00 Sft 4200.00
10.79 Cft River Sand 45.00 Cft 485.55
2.05 Bags Cement 390.00 Bags 799.50
100.00 Sft Labour Charges 20.00 Sft 2000.00
100.00 Sft Curing Charges 1.00 Sft 100.00
100.00 Sft Average of lifting charge 3.50 Sft 350.00
100.00 Sft Misc. materials 3.00 Sft 300.00
100.00 Sft White cement 1.00 Sft 100.00
Total 8335.05
Rate /Sft 83.35
Over head & Profit 15% 12.50
Rate/Sft 95.85

Providing & Laying of Vetrified


29 skirting tiles for flooring in CM 1:4,
100mm height
Rate for 100 Sft
36.00 Sft Cost of Antiskirt tiles 60.00 Sft 2160.00
3.00 Cft River Sand 45.00 Cft 135.00
0.60 Bags Cement 390.00 Bags 234.00
100.00 Sft Labour Charges 20.00 Sft 2000.00
100.00 Sft Curing Charges 1.00 Sft 100.00
100.00 Sft White cement 1.00 Sft 100.00
Total 4729.00
Rate /Sft 47.29
Over head & Profit 15% 7.09
Rate/Sft 54.38

Providing & Laying of Antiskirt


30 skirting tiles for flooring in CM
1:4,100m height
Rate for 100 Sft
36.00 Sft Cost of Antiskirt tiles 40.00 Sft 1440.00
3.00 Cft River Sand 45.00 Cft 135.00
0.60 Bags Cement 390.00 Bags 234.00
100.00 Sft Labour Charges 20.00 Sft 2000.00
100.00 Sft Curing Charges 1.00 Sft 100.00
100.00 Sft White cement 1.00 Sft 100.00
Total 4009.00
Rate /Sft 40.09
Over head & Profit 15% 6.01
Rate/Sft 46.10

31 Providing & Laying of Wall tiles in


CM 1:4
Rate for 100 Sft
105.00 Sft cost of glazed tiles 40.00 Sft 4200.00
8.53 Cft River Sand 45.00 Cft 383.85
1.80 Bags Cement 390.00 Bags 702.00
100.00 Sft Labour for laying & finishing 18.00 Sft 1800.00
100.00 Sft Curing Charges 1.00 Sft 100.00
100.00 Sft White Cement 1.00 Sft 100.00
100.00 Sft Average of lifting charge 2.50 Sft 250.00
100.00 Sft Misc. Material 2.00 Sft 200.00
Total 7735.85
Rate /Sft 77.36
Over head & Profit 15% 11.60
Rate/Sft 88.96
Providing & Laying of Black colour
32 Granite slab for Kitchen table top in
CM 1:4, 20mm thick
Rate for 100Sft
105.00 Sft Cost of Granite slab 100.00 Sft 10500.00
8.53 Cft Sand 45.00 Cft 383.85
1.80 Bag Cement 390.00 Bags 702.00
100.00 Sft Labour Charges for laying & polishing 50.00 Sft 5000.00
100.00 Sft Average of lifting charge 5.00 Sft 500.00
100.00 Sft White Cement 1.00 Sft 100.00
charges for making holes for wash
50.00 Sft basin, nosing & Edge polishing 35.00 Sft 1750.00
Total 18935.85
Rate /Sft 189.36
Over head & Profit 15% 28.40
Rate/Sft 217.76

33 Soild block 8" thick wall in CM


1:6,for superstructure works
Rate for 100Cft
60.00 Nos Soild block 8" 38.00 Nos 2280.00
32.50 Cft River Sand 45.00 Cft 1462.50
3.40 Bags Cement 390.00 Bags 1326.00
100.00 Sft Scaffolding Charges 9.00 Sft 900.00
100.00 Cft Labour Charges 24.00 Cft 2400.00
100.00 Cft Curing Charges 1.00 Cft 100.00
Total 8468.50
Rate/Cft 84.69
Over head & Profit 15% 12.70
Rate/Cft 97.39

34 Soild block 4" thick wall in CM


1:6,for superstructure works
Rate for 100Cft
30.00 Nos Soild block 4" 26.00 Nos 780.00
32.50 Cft River Sand 45.00 Cft 1462.50
3.40 Bags Cement 390.00 Bags 1326.00
100.00 Sft Scaffolding Charges 9.00 Sft 900.00
100.00 Cft Labour Charges 18.00 Cft 1800.00
100.00 Cft Curing Charges 1.00 Cft 100.00
Total 6368.50
Rate/Cft 63.69
Over head & Profit 15% 9.55
Rate/Cft 73.24
So.N DESCRIPTION RATE PER

1 Earth work excavation 8.50 Cft


2 Earth work Filling 4.00 Cft
3 Earth work Consolidation 2.00 Cft
4 Machinery Hire Charges 2.00 Cft
5 River sand Filling & Conslidation 6.00 Cft
6 Curing 1.00 Cft
7 PCC for footing 1:5:10 8.00 Cft
8 PCC for footing 1:4:8 8.00 Cft
9 Column footing concrete 28.00 Cft
10 Plinth beam 30.00 Cft
11 column concrete 32.00 Cft
12 Rcc wall concrete 35.00 Cft
13 lintel concrete 30.00 Cft
14 Sill concrete 10.00 Rft
15 Roof slab 24.00 Cft
16 Roof beam 25.00 Cft
17 Sunshade concrete 21.00 Sft
18 Scaffolding Charges(labour & rent) 9.00 Sft
19 9" Brick work 22.00 Cft
20 4½" Brick work 16.00 Sft
21 Steel work for roof 7000.00 tonne
22 Ceilling plastering 10.00 Sft
23 Inner wall plastering 8.00 Sft
24 Beam plastering 10.00 Sft
25 Column plastering 10.00 Sft
26 Labour for laying &Finishing for surki 10.00 Sft
27 Weathering tiles 12.00 Sft
28 Grano flooring Machinery Hire Charges 4.00 Sft
29 Grano flooring laying & Finishing 15.00 Sft
30 Vertified & Antiskirt tiles Laying 20.00 Sft
31 Granites Slab laying with polish 50.00 Sft
32 Average of lifting charge for flooring 3.50 Sft
33 Average of lifting charge for wall 2.50 Sft
34 Wall tiles laying 18.00 Sft
35 Average of lifting charge for granites 5.00 Sft
36 Granite nosing and edge polishing 35.00 sft
37 Soild block 8" 24.00 Cft
38 Soild block 4" 18.00 Cft
So.N DESCRIPTION RATE PER

1 Gravel 9.00 Cft


2 River Sand 45.00 Cft
3 40mm Metal 24.00 Cft
4 Cement 390.00 Beg
5 20mm 24.00 Cft
6 Brick 5.50 nos
7 Hoop iron 5.00 Rft
8 Steel 45000.00 tonne
9 Ms binding wire 60000.00 tonne
10 Brick Bats 20.00 Cft
11 Lime 5.00 Cft
12 Pressed tiles 18.00 nos
13 Approved WPC 250.00 lit
14 Chips 12mm 24.00 Cft
15 Vertified Tiles 60.00 Sft
16 Granites slab 100.00 Sft
17 Misc. materials for flooring 3.00 Sft
18 White cement 1.00 Sft
19 Antiskirt tiles 40.00 Sft
20 Wall Tiles 40.00 Sft
21 Misc. materials for glazzed 2.00 Sft

26 Weathering tiles 12.00 Sft


27 Soild block 8" 38.00 nos
28 Soild block 4" 26.00 nos