ZABARTE PODIUM

WEEKLY ACCOMPLISHMENT REPORT


(FOR THE PERIOD OF 03Aug2019 to 09Aug2019)

REPORT PREPARED BY: Edgardo T. Barachina/Site Engineer.

1
STRUCTURAL WORK ACCOMPLISHMENT REPORT

Percentage
Item This To date
Description Wt % of Remarks
No. Week Percentage
Completion

I. GENERAL REQUIREMENTS
1.00 Mobilization 0.252% 0.252% 100.000%
2.00 Temporary Site Office, Warehouse, Etc. 0.307% 0.0000% 0.307% 100.000%
3.00 Temp. Utilities, Tel., Power & Water 0.702% 0.0037% 0.5311% 75.655%
4.00 Construction Security & Safety 0.564% 0.0030% 0.3850% 68.262%
5.00 Site Management & Supervision 4.769% 0.0250% 3.2500% 68.148%
6.00 Equipment & Tower Crane 1.510% 0.0070% 1.1196% 74.146%
7.00 Plant & Equipment Maintenance 0.622% 0.0000% 0.6130% 98.553%
8.00 Tools & Material Testing 0.082% 0.0006% 0.0370% 45.122%
9.00 Office Supplies & Representation 0.175% 0.0009% 0.1148% 65.600%
10.00 Final Clearing & Turn Over 0.095%
11.00 Demobilization 0.117%
II. EXCAVATION WORKS
1.00 Excavation (Incl. Site Clearing, Layout & Trimming) 5.899% 0.0000% 5.8990% 100.000%
2.00 Gravel Bedding / Lean Concreting 0.149% 0.0000% 0.1490% 100.000%
3.00 Vapor Barrier 0.071% 0.0000% 0.0710% 100.000%
III. STRUCTURAL WORKS
1.00 Basement - 2 ( Ftng, Footing Tie Beam & Slab)
1.01 Formworks 0.832% 0.0000% 0.8320% 100.000%
1.02 Rebar Works 6.390% 0.0000% 6.3900% 100.000%
1.03 Concrete Works 7.759% 0.0000% 7.7590% 100.000%
1.04 Waterproofing / Tank Lining 1.023%
2.00 Basement - 1
2.01 Formworks 1.768% 0.0321% 1.4320% 80.995%
2.02 Rebar Works 4.927% 0.0500% 3.9900% 80.982%
2.03 Post Tension Beam / Girder 0.132% 0.0990% 75.000%
2.04 Concrete Works 3.759% 0.0310% 2.6700% 71.030%
3.00 Ground Floor
3.01 Formworks 1.880% 0.0188% 1.3350% 71.011%
3.02 Rebar Works 5.756% 0.0570% 4.1200% 71.577%
3.03 Post Tension Beam / Girder 0.132%
3.04 Concrete Works 4.111% 0.0000% 2.5320% 61.591%
4.00 Second Floor
4.01 Formworks & Scaffolding 1.803% 0.0200% 0.9600% 53.245%
4.02 Rebar Works 5.756% 0.0580% 2.9700% 51.598%
4.03 Post Tension Beam / Girder 0.264% 0.0000% 0.2376% 90.000%
4.04 Concrete Works 2.977% 0.0530% 1.3700% 46.019%
5.00 Third Floor
5.01 Formworks & Scaffolding 1.727% 0.0084% 0.0860% 4.980%
5.02 Rebar Works 5.959% 0.0600% 0.2900% 4.867%
5.03 Post Tension Beam / Girder 0.264% 0.000%
5.04 Concrete Works 2.695% 0.000%

2
6.00 Upper Third Floor
6.01 Formworks & Scaffolding 1.167%
6.02 Rebar Works 3.435%
6.03 Post Tension Beam / Girder 0.088%
6.04 Concrete Works 1.701%
7.00 Upper Roof Beam
7.01 Formworks & Scaffolding 0.586%
7.02 Rebar Works 1.466%
7.03 Concrete Works 0.821%
8.00 Roofing Works
8.01 Roof Framing 3.824%
8.02 Accessories 1.379%
IV. ARCHITECTURAL WORKS
1.00 Basement - 2
1.01 Masonry Works 0.185%
1.02 Paint 0.290%
2.00 Basement - 1
2.01 Masonry Works 0.495%
2.02 Waterproofing 0.245%
2.03 Paint 0.290%
3.00 Ground Floor
3.01 Masonry Works 0.970%
3.02 Waterproofing 0.055%
3.03 Paint 0.288%
4.00 Second Floor
4.01 Masonry Works 0.895%
4.02 Waterproofing 0.201%
4.03 Paint 0.288%
5.00 Third Floor
5.01 Masonry Works 1.550%
5.02 Waterproofing 0.085%
5.03 Paint 0.288%
6.00 Upper Third Floor
6.01 Masonry Works 1.250%
6.02 Waterproofing 0.105%
6.03 Paint 0.288%
7.00 Upper Roof Beam
7.01 Masonry Works 0.586%
7.02 Paint 0.067%
8.00 Other Works
8.01 Exterior Plastering 0.817%
8.02 Exterior Paint 1.067%
TOTAL 100.00% 49.80%

3
MANPOWER SCHEDULE MONITORING
03-Aug-19 05-Aug-19 06-Aug-19 07-Aug-19 08-Aug-19 09-Aug-19
279 322 303 345 236 243

 Average No. of Steelman: 96


 Average No. of Carpenter: 92
 Average Weekly Manpower: 288

A. ON GOING ACTIVITIES
 Formworks and Rebar works along GL 7-8/I-K 3rd Floor Slab and Beams.
 Column Works along GL 5-6, 8-10/I-K 1st and 2nd Lift 2nd Floor.
 Formworks and Scaffolding works along GL C-E/9-11 2nd Floor Slab and Beams.
 Formworks and Scaffolding works along GL A-B/9-11 Ground Floor Slab and Beams.
 Concreting works along GL 9-11/A-B Basement 01 Retaining walls/Ramp.
 Formworks and Rebar works along GL 1-2/E-J Basement 01 Slab and Beams.
 Formworks and Rebar installation along GL 2/A-D, A/2-4 Basement 02 Retaining walls.
 Formworks and Scaffolding works along GL 3/G-H Basement 02 Shear walls.

B. ACTIVITIES FOR NEXT WEEK


 Formworks and Rebar works along GL 7-8/I-K 3rd Floor Slab and Beams.
 Formworks and Scaffolding works along GL C-E/9-11 2nd Floor Slab and Beams.
 Concreting works along GL A-B/9-11 Ground Floor Slab and Beams.
 Concrete pouring works along GL 3-4/G-H Basement 02 Shear wall and Columns.
 Formworks and Rebar works along GL 1-2/E-J Basement 01 Slab and Beams.
C. PROGRESS PHOTOS

Concreting works along GL 9-11/F-H 2nd Floor Slab and Concreting works along GL A-B/9-11 Basement 01 Retaining walls
Beams and Ramp.

4
Formworks and Rebar works along GL A-B/9-11 Slab and Beams
Column works along GL 9-11/C-E Ground Floor.
Ground Floor.

Completed Slab and Beams along GL 9-11/F-H 2nd Floor. Formworks, Rebar and Column works along GL 6-7/I-K 2nd Floor.

Formworks and Rebar works along GL 9-11/C-E 2nd Floor


Column and Scaffolding works along GL 9-11/C-E 2nd Floor.
Slab and Beams.

5
Completed Ramp and Retaining walls @ GL 9-11/A-B
Form installation along GL 2-4/A-C Basement 02 Retaining walls.
Basement 01.

Rebar, Formworks, and Post Tensioning works along GL 1- Formworks along GL 3/G-H Basement 02 Shear wall.
2/E-J Basement 01 Slab and Beams.