Documente Academic
Documente Profesional
Documente Cultură
Measurement book
Rate Unit Rate, Rs. Cost, Rs. Total Cost, Rs. Norms
Cost Unit
SN Description Catagory m.d. Type Quantity IncludingVAT(for
per m.d. Including Excluding Including Excluding No.
UC)
Rs. Rs. VAT VAT VAT VAT in m in ft
1 Site clearance for1Sqm Unskill 0.23 700 161.00 Tools & Plant 3 % of labour cost 4.83 4.83 16.58 1.54 U/D A.(3)
1 Site clearance for1Sqm Unskill 0.04 700 28.00 Tools & Plant 3 % of labour cost 0.84 0.84 28.84 2.68 DoLIDAR 1-1.6
dismentaling of old
bldg(mud mortar) Unskill 1.06 700 742.00 Tools & Plant 3 % of labour cost 22.26 22.26 m3 764.26
Skill 0.054 955 51.57 Tools & Plant 3 % of labour cost 1.55 1.55 53.12
roof dismentaling work Unskill 0.081 700 56.70 Tools & Plant 3 % of labour cost 1.70 1.70 m2 58.40
111.52
2
Earthwork in excavation in
a ordinary soft soil- For 1 m3 Unskill 0.50 700 350.00 Tools & Plant 3 % of labour cost 10.50 10.50 360.50 10.22 5.2-1.2.2(a)
b Hard soil- For 1 m3 Unskill 0.60 700 420.00 Tools & Plant 3 % of labour cost 12.60 12.60 432.60 12.26 5.2-1.2.2(b)
c Soft Rock- For 1 m3 Unskill 0.80 700 560.00 Tools & Plant 3 % of labour cost 16.80 16.80 576.80 16.35 5.2-1.2.2(c)
d Medium Rock- For 1 m3 Unskill 3.00 700 2100.00 Tools & Plant 3 % of labour cost 63.00 63.00 2163.00 61.30 5.2-1.2.2(d)
9
Plain cement concrete work Skill 1.00 955 955.00 Cement 0.32 22387.0 20099.0 7163.84 6431.68 MT
M15(P.C.C. 1:2:4) Unskill 4.00 700 2800.00 Agg.40mm 0.52 4073.0 4073.0 2117.96 2117.96 cu.m U/D
and wall - For 1 m3 Agg.20mm 0.22 3014.6 3014.6 663.21 663.21 cu.m D1 7-2d
For Foundation Agg.10mm 0.11 3014.6 3014.6 331.61 331.61 cu.m
Sand 0.445 6398.40 6398.40 2847.29 2847.29 cu.m
Total 3755.00 13123.91 12391.75 16878.91 478.32
14 Skill 0.50 955 477.50 Blockstone 1.00 1845 1845 1845.00 1845.00 cu.m DoLIDAR
Dry stone masonry work
with rubble stone For 1 m3 Unskill 1.50 700 1050.00 Bondsotne 0.10 1845 1845 184.50 184.50 cu.m 38. 8
Total 1527.50 2029.50 2029.50 cu.m 3557.00
Government of Nepal
Ministry of Local Development
Office of District Development Committee
District Technical Office
Gorkha
Rate of Materials
148207.7184 52931.328 FY : 2069/70
Rate/kg/km
By Tractor By Poters
General Rate for Analysis Rate for Analysis Weight Load /
SN Particular VAT 13% Unit
Rate ( VAT+Trans.) (WithTrans.) per unit Unload
Tractor Porter
Dist(KM) Amount Dist(KM)
1 Skill Labour 955.00 955.00 955.00 md
2 Unskilled Labour 700.00 700.00 700.00 md
3 Painter 955.00 955.00 955.00 md
4 Sand 2400.00 6398.40 6,398.40 m3 1600.00 0.147 0.75 17.00 3998.40 0.00
5 Aggregate 40mm 2750.00 4073.00 4,073.00 m3 1800.00 0.147 0.59 5.00 1323.00 0.00
6 Aggregate 20mm 2750.00 3014.60 3,014.60 m3 1800.00 0.147 0.59 1.00 264.60 0.00
7 Aggregate 10mm 2750.00 3014.60 3,014.60 m3 1800.00 0.147 0.59 1.00 264.60 0.00
8 Stone 1500.00 1844.70 1,844.70 m3 1800.00 0.147 0.59 0.50 132.30 0.20
9 Mud for masonry 280.00 445.20 445.20 m3 1400.00 0.147 0.59 0.00 0.20
10 Sal wood 45000.00 45070.80 45,070.80 m3 600.00 0 0.59 3.00 0.00 0.20
11 Local Wood 45000.00 45000.00 45,000.00 m3 600.00 0 0.59 3.00 0.00
12 Sisau 70560.00 70560.00 70,560.00 m3 600.00 0 0.59 0.00
13 Cement(NS Mark OPC) 17600.00 2288.00 22387.00 20,099.00 mt 1000.00 0.147 0.59 17.00 2499.00 0.00
14 Brick(Chimney ) 13.00 1.69 22.19 20.50 Nos 2.50 0.147 0.59 20.00 7.35 0.10
15 Nail 100.00 13.00 113.00 100.00 kg 1.00 0.147 0.59 0.00 0.00
31 Reinforcement Bar(10-40mm) 86000.00 11180.00 100120.00 88,940.00 mt 1000.00 0.147 0.59 20.00 2940.00 0.00
32 GI Wire 12Swg (Heavy Coating) 105.00 13.65 118.65 105.00 kg 1.00 0.147 0.59 0.00 0.00
33 GI Wire 10Swg (Heavy Coating) 100.00 13.00 113.00 100.00 kg 1.00 0.147 0.59 0.00 0.00
34 GI Wire 8Swg (Heavy Coating) 100.00 13.00 113.00 100.00 kg 1.00 0.147 0.59 0.00 0.00
35 3mm Glass 500.00 65.00 565.00 500.00 m2 8.40 0.147 0.59 0.00 0.00
36 4mm Glass 640.00 83.20 723.20 640.00 m2 11.20 0.147 0.59 0.00 0.00
37 5mm Glass 750.00 97.50 847.50 750.00 m2 14.00 0.147 0.59 0.00 0.00
38 Lime 18.00 2.34 21.81 19.47 kg 1.00 0.147 0.59 10.00 1.47 0.00
39 Gum (Rathicol) 200.00 26.00 227.47 201.47 kg 1.00 0.147 0.59 10.00 1.47 0.00
40 Primer (wood) 290.00 37.70 329.17 291.47 Ltr 1.00 0.147 0.59 10.00 1.47 0.00
41 Enamel 425.00 55.25 480.25 425.00 Ltr 1.00 0.147 0.59 0.00 0.00
42 Alumunium Paint 500.00 65.00 565.00 500.00 Ltr 1.00 0.147 0.59 0.00 0.00
43 Sand Paper 10.00 1.30 11.30 10.00 Sheet 0.147 0.59 0.00 0.00
44 Red Oxide No 1 350.00 45.50 395.50 350.00 Ltr 1.00 0.147 0.59 0.00 0.00
Amount
0.00
0.00
0.00
0.00
212.40
165.20
70.80
0.00
0.00
0.00
0.15
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Amount
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.12
0.30
0.18
0.00
0.00
4 Formworks m2 9.0000 626.50 5638.50 10.50000 626.50 6578.25 1.500 0.00 939.75
5 M15 PCC work(c/s/a 1/2/4) m3 50.7300 16878.91 856267.10 49.50000 16878.91 835506.05 -1.230 0.00 -20761.05
s'n /sd 1,436,228.22 1,454,368.85 18,140.63
Formworks m2
4 9.00 10.5000 626.50 6,578.25 10.50 6,578.25
5 M15 PCC work(c/s/a 1/2/4) m3 50.73 49.5000 16878.91 835,506.05 49.50 835,506.05
hDdf /sd 1,454,368.85 s§f ug'{ kg]{ ?- 1,454,368.85
=ag sfof{no ‐
! of] lan jdf]lhd e'QmfgL h 1454368.85 $ afun'ª 400000
@ hg;|dbfg 354368.85 s= k]ZsL
# afFsL lbg' kg]{ ?= 700000.00 v= dfn;fdfgsf] df]n
afFsL lbg' kg] ‐sf7]vf]nf 100000 u= cGo
afFsL lbg' kg]{ ?= ‐ag sfo 600000 % v'b lbg'
afun'ª
gf]6
ufp+kflnsfsf] sfof{non] pkef]Qmf ;ldlt;+u ;Demf}tf
ubf{ lgDgfg';f/sf] zt{x?sf] clgjfo{ kfngf u/fpg] k|ltj4tf lnP/
dfq ;Demf}tf
!=pkef]Qmf u/fpgsf
;ldltn] gS;f tyfnflu
nfut cg'/f]w
Ol:6d]6 adf]lhd lgdf{0f ubf{ k'/fgf
vfg]kfgL, l;+rfO{, ljBfno ejg, lghL 3/, uf]7, cf+“ug cfbL k"jf{wf/ ;+/rgf Iflt
k'¥ofPsf] v08df ;f]xL pkef]Qmf ;ldltn] cfkm";+u ePsf] ;Demf}tf /sd leqsf]
ah]6af6 dd{t, lgdf{0f jf k'glg{df{0f ul/lbg' kg]{5 . ;f] ;DjGwdf s'g} ph'/L
kg{ cfPdf pQm Iflt ePsf] lgdf{0f ug{ nfUg] /sd ;DjlGwt pkef]Qmf ;ldltsf]
vftfaf6 s§f u/]/ dfq clGtd km/kmf/s ug]{ Joj:yf ldnfpg'x'g .
@= ;DjlGwt k|fljlws 6f]nLn] ;fO{6df u/]sf] ;e]{, sfof{nosf] :jLs[t nfut cg'dfg
Pj+ gS;fx? cg';f/ g} lgdf{0f sfo{ u/fpg] k|ltj4tf lng' x'g .
#= :jLs[t nfut cg'dfg / gS;f eGbf km/s sfo{ u/L sfof{non] d"Nof+sg gu/]sf]
v08df s'g} lsl;dsf] ph'/ nfUg]5}g eGg] k|ltj4tf lng'x'g .
$= ;Demf}tf adf]lhdsf] lgdf{0f ubf{ u/fpbf jftfj/0f ;+/If0f P]g @)%# /
jftfj/0f lgodfjnL @)%$adf]lhd jftfj/0fdf gsf/fTds k|efj gkg]{ul/ u/fpg] k|ltj4tf
lng'x'g .
B..Hard Soil
Norms No: 5.2-1.2.2(b) DoLIDAR
Unit :cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md 0.000 870.00 -
Unskill Md 0.60 650.00 390.00
Tools andSub-Total
plants 390.00
@3% 11.70
Total 401.70
Item: Dry Stone Pitching/Soling & Levelling Works
Norms No: 49.17-6 DoLIDAR
Unit :m3
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md - 870.00 -
Unskill Md 1.00 650.00 650.00
Material Stone m3 1.10 1,602.00 1,762.20
Sub-Total
Tools and plants 2,412.20
@3% 72.37
Total 2,484.57
15 % Overhead
Unit Rate 2,484.57
Item: plain cement concrete works in foundation including material collection & 30m lead
A.1:4:8
Norms No: 41(7-2)c
Unit : Cu.m.
Item: plain cement concrete works in foundation including material collection & 30m lead
A.1:3:6
Norms No: 42(7-2)c
Unit : Cu.m.
Item: plain cement concrete works in superstructure including material collection &30m lead
B. 1:1.5:3 mix
Norms No: 7(4)b,45
Unit : Cu.m.
A) Stone Masonry works including material collection,preparation of mortar with 5m lift and 10m lead
A. Un-coursed rubble Masonary 1:4
Norms No : 38.8-A. c DoLIDAR
Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 1.50 md 870.00 1,305.00
Unskill 3.24 md 650.00 2,106.00
A) Stone Masonry works including material collection,preparation of mortar with 5m lift and 10m lead
A. Un-coursed rubble Masonary 1:6
Norms No : 38.8-A. d DoLIDAR
Unit : Cu.m.
C)pointing works with cement sand mortar on brick wall with all required operation including full compensation
for all labour, materials , scafolding and otter incidental required to complete tte works as per the specifications
b.) For every subsequent pipe having length of minimum 1m, Dia 30 cm. dia
Norms No : 47. 15-5 ,15- 6 b. DoLIDAR
Unit :1.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 0.02 md 870.00 17.40
Un-skill 0.10 md 650.00 65.00
Material Cement 0.001 MT 20,804.00 20.80
Sand 0.002 m3 2,300.00 4.60
Jute, Bitumin LS 30.00 30.00
Sub-Total 82.40
15 % Overhead 12.36
Unit Rate 94.76
b.) For every subsequent pipe having length of minimum 1m Dia 60 cm. dia
Norms No : 47. 15-5 ,15- 6 b. DoLIDAR
Unit :1.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 0.050 md 870.00 43.50
Un-skill 0.200 md 650.00 130.00
Material Cement 0.003 MT 20,804.00 62.41
Sand 0.004 m3 2,300.00 9.20
Jute, Bitumin LS 40.00 40.00
Sub-Total 285.11
15 % Overhead 42.77
Unit Rate 327.88
Hence,
Total cost of 30cmdia.1m H.P. 94.76
Total cost of 60cmdia.1m H.P. 327.88
Total 45mm dia. H.P.1m(Average cost) 422.64 211.32
44.2.a Assembling of wire crates/gabion/revetment and placing them in position including streching
,binding them together and tying down lids. Box size(2X1X 1) (11 m2)
Unit :Per m3 44.2.a DoLIDAR
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0 md 870.00 0.00
Unskilled 0.09 md 650.00 58.50
Binding wire
Materials 0.95 kg 121.170 115.11
12swg(Heavy Coated)
Sub-Total 173.61
15 % Overhead -
Rate per Box
Size(2X1X1) 173.61
Rate per m3 86.81
44.2.a Assembling of wire crates/gabion/revetment and placing them in position including streching
,binding them together and tying down lids. Box size(3X1X 1) (16 m2)
Binding wire
Materials 1.3 121.17 157.52
12swg(Heavy Coated)
kg
Sub-Total 242.02
15 % Overhead -
Rate per Box
Size(3X1X1) 242.02
Rate per m3 80.67
item : laying of locally available granular materials for gravelling in Roadway for gravelling including
j10m lead & 1.5m lift-per m3
particular unit Qantity Rate Amount Remarks
subgrade preparation 10 cm depth
labour unskill md 0.05 650.00 32.5
S.N Description of items No Length Breadth Height Quantity Unit Rate Amount Remarks
1 Earthwork
land development 813 1.50 0.45 0.6 329.265 thamdanda
stone soling 1 50.00 1.5 0.2 15
total 344.265 m3 432.6 148929.039
2 Dry stone masonary work
for stairs 813 1.50 0.45 0.2 109.755 m3 3557.00 390398.535
Earthwork in excavation for Hard clay and silty soil with 10 m lead and 1.5 m lift per m3, (S.N.2, item no.2 )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 0.80 md 650.00 520.00 0.80
2 Tools & Plant @3% 15.60
3 Rate Per m3 535.60
4 Contractor's Overhead @15 % 80.34
5 Grand Total 615.94
Earthwork in excavation for Medium Rock without blasting with 10 m lead and 1.5 m lift per m3, (S.N.2, item no.4 )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 3.00 md 650.00 1950.00 3.00
2 Tools & Plant @3% 58.50
3 Sub Total 2008.50
4 Contractor's Overhead @15 % 301.28
5 Grand Total 2309.78
Earthwork in excavation for Hard Rock without cheseling with 10 m lead and 1.5 m lift per m3, (S.N.2, item no.6, Ka )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 5.00 md 650.00 3250.00 5.00
2 Tools & Plant @3% 97.50
3 Sub Total 3347.50
4 Contractor's Overhead @15 % 502.13
5 Grand Total 3849.63
Earthwork in excavation for Hard Rock with cheseling with 10 m lead and 1.5 m lift per m 3, (S.N.2, item no.6, Kha )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 24.20 md 650.00 15730.00 24.20
2 Tools & Plant @3% 471.90
3 Sub Total 16201.90
4 Contractor's Overhead @15 % 2430.29
5 Grand Total 18632.19
Earthwork in excavation for trench in Soft Soil with 10 m lead and 1.5 m lift per m3, (S.N.2, item no.9 )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 1.00 md 650.00 650.00 1.00
2 Tools & Plant @3% 19.50
3 Sub Total 669.50
4 Contractor's Overhead @15 % 100.43
5 Grand Total 769.93
Earthwork in excavation for trench in Soft Rock with cracking with 10 m lead and 1.5 m lift per m3, (S.N.2, item no.10 )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 2.50 md 650.00 1625.00 2.50
2 Tools & Plant @3% 48.75
3 Sub Total 1673.75
4 Contractor's Overhead @15 % 251.06
5 Grand Total 1924.81
Earthwork in excavation for trench in BMS with 10 m lead and 1.5 m lift per m3, (S.N.2, item no.14)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 1.59 md 650.00 1033.50 1.59
2 Tools & Plant @3% 31.01
3 Sub Total 1064.51
4 Contractor's Overhead @15 % 159.68
5 Grand Total 1224.19
Earthwork in filling with layerwise of 15 cm compaction with water with 10 m lead and 1.5 m lift per m 3, (S.N. 2 item no.25 Ka )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 0.50 md 650.00 325.00 0.50
2 Tools & Plant @3% 9.75
3 Sub Total 334.75
4 Contractor's Overhead @15 % 50.21
5 Grand Total 384.96
.
Earthwork in filling with layerwise of 15 cm compaction without water with 10 m lead and 1.5 m lift per m3, (S.N. 2 item no.25 Kha )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 0.25 md 650.00 162.50 0.25
2 Tools & Plant @3% 4.88
3 Sub Total 167.38
4 Contractor's Overhead @15 % 25.11
5 Grand Total 192.49
Stone Masonary work in 1:4 mortar per M3 (S.N.6, item no. 3 Ka)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.50 md 870.00 1305.00 1.50
2 Labour 5.00 md 650.00 3250.00 5.00
3 Cement 3.18 Bag 790.00 2512.20 3.18
4 Sand 0.45 m3 1550.00 697.50 0.45
5 Block Stone 1.00 m3 1500.00 1500.00 1.00
6 Bond Stone 0.10 m3 1500.00 150.00 0.10
7 Total 9414.70
8 Tools & Plant @3% 282.44
9 Sub Total 9697.14
10 Contractor's Overhead @15 % 1454.57
11 Grand Total 11151.71
Stone Masonary work in 1:6 mortar per M3 (S.N.6 item no. Ka-3)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.50 md 870.00 1305.00 1.50
2 Labour 5.00 md 650.00 3250.00 5.00
3 Cement 2.12 Bags 790.00 1674.80 2.12
4 Sand 0.47 m3 1550.00 728.50 0.47
5 Block Stone 1.00 m3 1500.00 1500.00 1.00
6 Bond Stone 0.10 m3 1500.00 150.00 0.10
7 Total 8608.30
8 Tools & Plant @3% 258.25
9 Sub Total 8866.55
10 Contractor's Overhead @15 % 1329.98
11 Grand Total 10196.53
Stone soling (pitching) work in foundation with 30m lead per M 3 (S.N.6 item no.5 )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason
2 Labour 1.50 md 650.00 975.00 1.50
3 Block Stone 1.10 m 3
1500.00 1650.00 1.10
4 Bond Stone m 3
0.00 0.00
5 Total 2625.00
6 Tools & Plant @3% 78.75
7 Rate per m3 2703.75
8 Contractor's Overhead @15 % 405.56
9 Grand Total 3109.31
Brick Masonary work in Mud mortar per M3 (S.N.5 item no. Kha-6 )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 P.C.C. for R.C.C. (1:3:6) Works for dr 1.00 md 870.00 870.00 1.00
2 Labour 1.70 md 650.00 1105.00 1.70
3 Cement Bag 790.00
4 Sand m3 1550.00
5 Brick (Local) 560.00 Nos 14.00 7840.00 560.00
6 Mud 0.42 m3 450.00 189.00 0.42
7 Total 10004.00
8 Tools & Plant @3% 300.12
9 Sub Total 10304.12
10 Contractor's Overhead @15 % 1545.62
11 Grand Total 11849.74
PCC. work For Foundation in 1:3:6 with 30m lead per M 3 (S.N.7, item no.2,Ga )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.00 md 870.00 870.00 1.00
2 Labour 4.00 md 650.00 2600.00 4.00
3 Cement 4.40 Bag 790.00 3476.00 4.40
4 Sand 0.47 m3 1550.00 728.50 0.47
5 Stone aggregate (40 mm) 0.65 m3 1750.00 1137.50 0.65
6 Stone aggregate (20 mm) 0.24 m3 1850.00 444.00 0.24
7 Total 9256.00
8 Tools & Plant @3% 277.68
9 Sub Total 9533.68
10 Contractor's Overhead @15 % 1430.05
11 Grand Total 10963.73
PCC. work for structure 1:1.5:3 (Slab,Beam etc ) per M3 (S.N.7, item no.4,Kha)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 0.80 md 955.00 764.00 0.80
2 Labour 7.00 md 700.00 4900.00 7.00
3 Cement 8.00 Bags 790.00 6320.00 8.00
4 Sand 0.43 m3 1550.00 666.50 0.43
5 Stone aggregate (20 mm) 0.57 m3 1850.00 1054.50 0.57
6 Stone aggregate (10 mm) 0.29 m3 1850.00 536.50 0.29
7 Total 14241.50
8 Tools & Plant @3% 427.25
9 Sub Total 14668.75
10 Contractor's Overhead @15 % 2200.31
11 Grand Total 16869.06
PCC. work For structure 1:2:4 (Slab,Beam etc ) per M3 (S.N.7, item no.4,Ka)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 0.80 md 955.00 764.00 0.80
2 Labour 7.00 md 700.00 4900.00 7.00
3 Cement 6.40 Bags 790.00 5056.00 6.40
4 Sand 0.445 m3 1550.00 689.75 0.445
5 Stone aggregate (40 mm) 0.52 m3 1750.00 910.00 0.52
6 Stone aggregate (20 mm) 0.22 m3 1850.00 407.00 0.22
7 Stone aggregate (10 mm) 0.11 m3 1850.00 203.50 0.11
8 Total 12930.25
9 Tools & Plant @3% 387.91
10 Sub Total 13318.16
11 Contractor's Overhead @15 % 1997.72
12 Grand Total 15315.88
Tor Steel bars for bending & placing in required position per 1 MT (S.N.7, item no.5 )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 12.00 md 955.00 11460.00 12.00
2 Labour 12.00 md 700.00 8400.00 12.00
3 Tor Bars 1.05 MT 80000.00 84000.00 1.05
4 Binding wire 10.00 kg 92.00 920.00 10.00
5 Total 104780.00
6 Tools & Plant @3% 3143.40
7 Rate per MT 107923.40
8 Rate per Kg 107.92
9 Contractor's Overhead @15 % 16.19
10 Grand Total 124.11
Form work for RCC or PCC including all complete with 30m lead per 10 m 2 (S.N.8, item no.2-Ka)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.72 md 955.00 1642.60 1.72
2 Labour 2.57 md 700.00 1799.00 2.57
3 Local wood 0.53 m 3
8534.38 753.87 0.53
4 Nails 2.50 kg 105.00 262.50 2.50
5 Total 4457.97
6 Tools & Plant @3% 133.74
7 Rate per 10 m2 4591.71
8 Sub Total 459.17
9 Contractor's Overhead @15 % 68.88
10 Grand Total 528.05
12.5 mm thick plastering work for walls & floor in 1:3 C/M per 100 M 2 (S.N.12-1-kha)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 12.00 md 955.00 11460.00 12.00
2 Labour 16.00 md 700.00 11200.00 16.00
3 Cement 12.50 Bags 790.00 9875.00 12.50
4 Sand 1.28 m 3
1550.00 1984.00 1.28
5 Rate per 100 m2 34519.00
6 Total per m2 345.19
7 Tools & Plant @3% 10.36
8 Sub Total 355.55
9 Contractor's Overhead @15 % 53.33
10 Grand Total 408.88
12.5 mm thick plastering work for walls & floor in 1:4 C/M per 100 M 2 (S.N.12-1-Ga )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 12.00 md 955.00 11460.00 12.00
2 Labour 16.00 md 700.00 11200.00 16.00
3 Cement 10.76 Bags 790.00 8500.40 10.76
4 Sand 1.46 m3 1550.00 2263.00 1.46
5 Rate per 100 m2 33423.40
6 Total per m2 334.23
7 Tools & Plant @3% 10.03
8 Sub Total 344.26
4 Contractor's Overhead @15 % 51.64
5 Grand Total 395.90
12.5 mm thick plastering work for walls & floor in 1:6 C/M per 100 M 2 (S.N.12-1-Gha )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 12.00 md 955.00 11460.00 12.00
2 Labour 16.00 md 700.00 11200.00 16.00
3 Cement 7.64 Bags 790.00 6035.60 7.64
4 Sand 1.57 m 3
1550.00 2433.50 1.57
5 Rate per 100 m2 31129.10
6 Sub Total 311.29
7 Tools & Plant @3% 9.34
8 Rate per m2 320.63
9 Contractor's Overhead @15 % 48.09
10 Grand Total 368.72
12.5 mm thick plastering work for ceiling in1:3 per 100 M 2 (S.N.12-1-kha)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 15.00 md 955.00 14325.00 15.00
2 Labour 20.00 md 700.00 14000.00 20.00
3 Cement 12.50 Bags 790.00 9875.00 12.50
4 Sand 1.28 m3 1550.00 1984.00 1.28
5 Rate per 100 m2 40184.00
6 Total per m2 401.84
7 Tools & Plant @3% 12.06
8 Sub Total 413.90
9 Contractor's Overhead @15 % 62.09
10 Grand Total 475.99
12.5 mm thick plastering work for ceiling in1:4 per 100M 2 (S.N.12-1-kha )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 15.00 md 955.00 14325.00 15.00
2 Labour 20.00 md 700.00 14000.00 20.00
3 Cement 10.76 Bags 790.00 8500.40 10.76
4 Sand 1.46 m3 1550.00 2263.00 1.46
5 Rate per 100 m2 39088.40
6 Total per m2 390.88
7 Tools & Plant @3% 11.73
8 Sub Total 402.61
9 Contractor's Overhead @15 % 60.39
10 Grand Total 463.00
12.5 mm thick plastering work for ceiling in1:6 per 100 M 2 (S.N.12-1,Gha )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 15.00 md 955.00 14325.00 15.00
2 Labour 20.00 md 700.00 14000.00 20.00
3 Cement 7.64 Bags 790.00 6035.60 7.64
4 Sand 1.57 m3 1550.00 2433.50 1.57
5 Rate per 100 m2 36794.10
6 Total per m2 367.94
7 Tools & Plant @3% 11.04
8 Sub Total 378.98
9 Contractor's Overhead @15 % 56.85
10 Grand Total 435.83
20 mm thick plastering work for walls & floor in 1:3 per 100 M 2 (S.N.12-4,ka )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 14.00 md 955.00 13370.00 14.00
2 Labour 19.00 md 700.00 13300.00 19.00
3 Cement 19.20 Bags 790.00 15168.00 19.20
4 Sand 1.95 m3 1550.00 3022.50 1.95
5 Rate per 100 m2 44860.50
6 Total per m2 448.61
7 Tools & Plant @3% 13.46
8 Sub Total 462.07
9 Contractor's Overhead @15 % 69.31
10 Grand Total 531.38
20 mm thick plastering work for walls & floor in 1:4 per 100 M 2 (S.N.12-4,kha)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 14.00 md 955.00 13370.00 14.00
2 Labour 19.00 md 700.00 13300.00 19.00
3 Cement 16.20 Bags 790.00 12798.00 16.20
4 Sand 2.20 m3 1550.00 3410.00 2.20
5 Rate per 100 m2 42878.00
6 Total per m2 428.78
7 Tools & Plant @3% 12.86
8 Sub Total 441.64
9 Contractor's Overhead @15 % 66.25
10 Grand Total 507.89
20 mm thick plastering work for walls & floor in 1:6 per 100M 2 (S.N.12-4,Ga )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 14.00 md 955.00 13370.00 14.00
2 Labour 19.00 md 700.00 13300.00 19.00
3 Cement 11.40 Bags 790.00 9006.00 11.40
4 Sand 2.35 m3 1550.00 3642.50 2.35
5 Rate per 100 m2 39318.50
6 Total per m2 393.19
7 Tools & Plant @3% 11.80
8 Sub Total 404.99
9 Contractor's Overhead @15 % 60.75
10 Grand Total 465.74
Cement Pointing works 1:1 per 100 M2 (S.N.14-2,ka)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 10.00 md 955.00 9550.00 10.00
2 Labour 14.00 md 700.00 9800.00 14.00
3 Cement 12.24 Bags 790.00 9669.60 12.24
4 Sand 0.43 m3 1550.00 666.50 0.43
5 Rate per 100 m2 29686.10
6 Total per m2 296.86
7 Tools & Plant @3% 8.91
8 Sub Total 305.77
9 Contractor's Overhead @15 % 45.87
10 Grand Total 351.64
White washing work in new surface ( Two coat) per 100 M 2 (S.N.13-1-kha)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.50 md 955.00 1432.50 1.50
2 Labour 1.10 md 700.00 770.00 1.10
3 lime 22.00 kg 23.00 506.00 22.00
4 Gum 0.88 kg 220.00 193.60 0.88
5 Rate per 100 m2 2902.10
6 Total per m2 29.02
7 Tools & Plant @3% 0.87
8 Sub Total 29.89
9 Contractor's Overhead @15 % 4.48
10 Grand Total 34.37
Distemper painting work (Second and others Coat) per 100 m2 (S.N.13-3,Ga)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.80 md 955.00 1719.00 1.80
2 Labour 1.80 md 700.00 1260.00 1.80
3 Distemper 5.00 Kg 280.00 1400.00 5.00
5 Rate per 100 m2 4379.00
6 Total per m2 43.79
7 Tools & Plant @3% 1.31
8 Sub Total 45.10
9 Contractor's Overhead @15 % 6.77
10 Grand Total 51.87
Water proof Cement Painting works per 100 m2 (One coat) (S.N.13, item no.4-Ka)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.70 md 955.00 1623.50 1.70
2 Labour 1.70 md 700.00 1190.00 1.70
3 Cement paint 30.00 kg 140.00 4200.00 30.00
5 Rate per 100 m2 7013.50
6 Total per m2 70.14
7 Tools & Plant @3% 2.10
8 Sub Total 72.24
9 Contractor's Overhead @15 % 10.84
10 Grand Total 83.08
Water proof Cement Painting works per 100 m2 (Two coat) (S.N.13, item no.4-Kha)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 5.00 md 955.00 4775.00 5.00
2 Labour 5.00 md 700.00 3500.00 5.00
3 Cement paint 48.50 kg 140.00 6790.00 48.50
5 Rate per 100 m2 15065.00
6 Total per m2 150.65
7 Tools & Plant @3% 4.52
8 Sub Total 155.17
9 Contractor's Overhead @15 % 23.28
10 Grand Total 178.45
Enamel Painting works ( one coat aster including two coat enamel ) per 100 M 2 (S.N.13-5,ka-Ga)
Tender Rate
Aster coat First coat
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 3.00 md 955.00 2865.00 5.00
2 Labour 3.00 md 700.00 2100.00 2.00
3 Aster 8.10 Lit 370.00 2997.00
4 Enamel Lit 490.00 9.00
5 Rate per 100 m2 7962.00
6 Total per m2 79.62
7 Tools & Plant @3% 2.39
8 Sub Total 82.01
9 Contractor's Overhead @15 % 12.30
10 Grand Total 94.31
Enamel Painting works ( one coat aster including two coat enamel ) per 100 M 2 (S.N.13-5-ka-Ga)
User's Rate
Aster coat First coat
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 3.00 md 955.00 2865.00 5.00
2 Labour 3.00 md 700.00 2100.00 2.00
3 Aster 8.10 kg 418.10 3386.61
4 Enamel kg 553.70 9.00
5 Rate per 100 m2 8351.61
6 Total per m2 83.52
7 Tools & Plant @3% 2.51
8 Sub Total 86.03
9 Contractor's Overhead @15 % 0.00
10 Grand Total 86.03
Wood work for chaukhat (sal wood) per M3 (S.N.10-1)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 34.00 md 955.00 32470.00 34.00
2 Labour 3.40 md 700.00 2380.00 3.40
3 Wood (sal) 1.10 m3 194230.67 213653.74 1.10
4 Screw 184.00 No 1.20 220.80 184.00
5 Hold fast 92.00 No 23.00 2116.00 92.00
6 Total per m3 250840.54
7 Tools & Plant @3% 7525.22
8 Sub Total 258365.76
9 Contractor's Overhead @15 % 38754.86
10 Grand Total 297120.62
Wood work for chaukhat (Local wood) per M3 (S.N.10-1)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 34.00 md 955.00 32470.00 34.00
2 Labour 3.40 md 700.00 2380.00 3.40
3 Wood 1.10 m3 51206.27 56326.90 1.10
4 Screw 184.00 No 1.20 220.80 184.00
5 Hold fast 92.00 No 23.00 2116.00 92.00
6 Total per m3 93513.70
7 Tools & Plant @3% 2805.41
8 Sub Total 96319.11
9 Contractor's Overhead @15 % 14447.87
10 Grand Total 110766.98
Sal Wood work for Beam per M3 (S.N.10,17)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 17.65 md 955.00 16855.75 17.65
2 Labour 1.76 md 700.00 1232.00 1.76
3 Wood 1.05 m3 194230.67 203942.20 1.05
4 Screw L/S 80.00 L/S
5 Total per m3 222109.95
6 Tools & Plant @3% 6663.30
7 Sub Total 228773.25
8 Contractor's Overhead @15 % 34315.99
9 Grand Total 263089.24
4mm thick glass Shutter fix with listic per m2 (S.N.10,11 Kha)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 0.06 md 955.00 57.30 0.06
2 Labour 0.01 md 700.00 7.00 0.01
3 Wood m3 51206.27 0.00 0.00
4 Glass (4mm plain) 1.00 m2 850.00 850.00 1.00
5 Hinge No 48.00 0.00 0.00
6 Chheskini 300mm No 115.00 0.00
7 Chheskini 150mm No 60.00 0.00 0.00
8 Locking set No 200.00 0.00
9 Handle No 55.00 0.00 0.00
10 Screw L/s 40.00
11 Listic 4.05 m 12.00 48.60 4.05
12 26 gauge plain sheet m2 445.00
14 Rate per m2 1002.90
15 Tools & Plant @3% 30.09
16 Sub Total 1032.99
17 Contractor's Overhead @15 % 154.95
18 Grand Total 1187.94
Local Wood work for 38mm mosquito proof wire mesh Shutter (S.N.10,10)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 5.00 md 955.00 4775.00 5.00
2 Labour 0.50 md 700.00 350.00 0.50
3 Wood 0.03 m3 51206.27 1536.19 0.03
4 Wire mesh 2.13 m2 152.00 323.76 2.13
5 Spring 1.00 No 218.00 218.00 1.00
6 Hinge 100mm 3.00 No 48.00 144.00 3.00
7 Chheskini 150mm 2.00 No 60.00 120.00 2.00
8 Nails L/S 30.00
9 Handle 2.00 No 55.00 110.00 2.00
13 Rate per 2.245m2 7606.95
14 Rate per m2 3388.40
15 Tools & Plant @3% 101.65
16 Sub Total 3490.05
17 Contractor's Overhead @15 % 523.51
18 Grand Total 4013.56
Local Wood work for 38mm freame flush Shutter including 3mm ply wood on both sides per m2 (S.N.10,7)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 7.00 md 955.00 6685.00 7.00
2 Labour 0.70 md 700.00 490.00 0.70
3 Wood 0.03 m3 51206.27 1536.19 0.03
4 Commercial Ply wood,3mm thick 4.65 m2 265.00 1232.25 4.65
5 Mortis lock 1.00 No 535.00 535.00 1.00
6 Hinge 100mm 3.00 No 48.00 144.00 3.00
7 Chheskini 150mm 2.00 No 60.00 120.00 2.00
8 Nails L/S 30.00
9 Handle 1.00 No 55.00 55.00 1.00
13 Rate per 2.245m2 10827.44
14 Rate per m2 4822.91
15 Tools & Plant @3% 144.69
16 Sub Total 4967.60
17 Contractor's Overhead @15 % 745.14
18 Grand Total 5712.74
Plum Concrete works in 40% / 60% Mass Concrete including Boulder cleaning works.(P.C.C. in 1:3:6),(60% Concrete & 40% Boulder ston
Norms No. 7(a),41 &25(14), 251 (60% Concrete & 40% Boulder stone)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 0.30 md 955.00 286.50 0.30
2 Labour 4.00 md 700.00 2800.00 4.00
3 Cement 4.40 Bag 790.00 3476.00 4.40
4 Sand 0.47 m 3
1550.00 728.50 0.47
5 Boulder stone 0.14 m 3
1500.00 210.00 0.14
6 Stone aggregate (20 mm) 0.60 m 3
1850.00 1110.00 0.60
7 Stone aggregate (10 mm) 0.20 m3 1850.00 370.00 0.20
8 Total 8981.00
9 Tools & Plant @3% 269.43
10 Sub Total 9250.43
11 Contractor's Overhead @15 % 1387.56
12 Grand Total 10637.99
Making & fixing 3*20 mm iron gril including one coat Red oxide paint after rubbing with sand paper.
Norms No. 24/1(a), 238
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 iron gril including labour cost. 10.00 Sqm 2695.38 26953.80 10.00
8 Total 26953.80
9 Tools & Plant @3% 808.61
10 Sub Total 2776.24
11 Contractor's Overhead @15 % 416.44
12 Grand Total 3192.68
Making & fixing of rolling shutter including one coat red oxide paint after rubbing with sand paper .
Norms No. 24/1(a), 238
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
18-20 gauge iron shutter including
1 labour cost. 10.00 Sqm 2730.00 27300.00 10.00
8 Total 27300.00
9 Tools & Plant @3% 819.00
10 Sub Total 2811.90
11 Contractor's Overhead @15 % 421.79
12 Grand Total 3233.69
Making & fixing of collapsiable channel gate including one coat red oxide paint after rubbing with sand paper.
Norms No. 24/1(a), 238
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 channel gate including labour cost 10.00 Sqm 4750.00 47500.00 10.00
8 Total 47500.00
9 Tools & Plant @3% 1425.00
10 Sub Total 4892.50
11 Contractor's Overhead @15 % 733.88
12 Grand Total 5626.38
22. ITEM Laying, fitting and fixing of hume pipe having a dia. 60cm for 5 m length.
UNIT 5 R.M.
S.N. 47 Resp. Clause of Spec. 15-5 and 15-6
Source Type Quntity unit Rate Amount Total(Rs)
Labour Skilled 0.25 M-day 870.00 217.50 217.50
Unskilled 1.00 M-day 650.00 650.00 650.00
Construction Hume pipe 600 mm NP3 1.00 No. 38632.44 38632.44 38632.44
Materials Cement 0.02 MT 17854.00 357.08 357.08
Sand 0.02 m3 1550.00 31.00 31.00
Jute 12.50 Kg. 106.22 1327.75 1327.75
Bitumen 2.50 Kg. 81.36 203.40 203.40
Actual Rate 41419.17
Tools, Plants & Equipments @ 3% 1242.58
Sub Total 42661.75
Rate per 5m 42661.75
Rate per m 8532.35
23. ITEM Laying, fitting and fixing of hume pipe having a dia. 90cm for 5 m length.
UNIT 5 R.M.
S.N. 47 Resp. Clause of Spec. 15-5 and 15-6
Source Type Quntity unit Rate Amount Total(Rs)
Labour Skilled 0.75 M-day 870.00 652.50 652.50
Unskilled 2.50 M-day 650.00 1625.00 1625.00
Construction Hume pipe 900 mm NP3 1.00 No. 70478.10 70478.10 70478.10
Materials Cement 0.03 MT 17854.00 535.62 535.62
Sand 0.05 cu.m 1550.00 77.50 77.50
Jute 20.00 Kg. 106.22 2124.40 2124.40
Bitumen 5.00 Kg. 81.36 406.80 406.80
Actual Rate 75899.92
Tools, Plants & Equipments @ 3% 2277.00
Sub Total for 5 m 78176.92
Rate per 5 m 78176.92
Rate per m 15635.38
20. ITEM Packing and filling of gabion craties with rubble stones.
UNIT Cu m.
S.N. 45 Resp. Clause of Spec. 17-1.4,17-5 & 17-6
Source Type Quntity unit Rate Amount Total(Rs)
Labour Skilled 0.30 M-day 870.00 261.00 261.00
Unskilled 0.75 M-day 650.00 487.50 487.50
Materials
Construction Boulder 1.10 m3 1500.00 1650.00 1650.00
Actual Rate 2398.50
Tools, Plants & Equipments @ 3% 71.96
Sub Total 2470.46
Rate per m3 2470.46
Rate per box 4940.92
Total Gabion works all comp. / m3 4330.33
Total Gabion works all comp. / box 8660.66
A-2 2" thick 1:2:4 Cement Concrete floor Carting including finishing by
Norms No. 11/1(c), 96
Unit 10 Sqm
Particular Description Unit Quantity Rate Amount
Labour Skilled Md 1.25 0.00 0.00
Unskilled Md 2.50 0.00 0.00
Material cement(N.S.) M.T. 0.170 0.00 0.00
sand(Crusher
screen) Cu.m 0.230 0.00 0.00
Aggregate 20
mm M.T. 0.460 0.00 0.00
Sub-Total 0.00
Tools & Plants @ 3% 0.00
Sub-Total (Dept. Rate) 0.00
Contractor's Profit @ 1 0.00
Sub-Total 0.00
Grand Total (Cont. Rat 0.00
A-3 3" thick 1:2:4 Cement Concrete floor Carting including finishing by
Norms No. 11/1(d), 97
Unit 10 Sqm
Particular Description Unit Quantity Rate Amount
Labour Skilled Md 1.25 0.00 0.00
Unskilled Md 3.00 0.00 0.00
Material cement(N.S.) M.T. 0.260 0.00 0.00
sand(Crusher
screen) Cu.m 0.340 0.00 0.00
Aggregate 20
mm M.T. 0.680 0.00 0.00
Sub-Total 0.00
Tools & Plants @ 3% 0.00
Sub-Total (Dept. Rate) 0.00
Contractor's Profit @ 1 0.00
Sub-Total 0.00
Grand Total (Cont. Rat 0.00
25 mm th.mosaic flooring with 12.5mm th cement plaster (1:2) base course & 6
B cement (1:1) surface course including rubbing & polis
Norms No. 11/3, 99
Unit 10 Sqm
Particular Description Unit Quantity Rate Amount
Labour Skilled Md 3.50 0.00 0.00
Unskilled Md 36.00 0.00 0.00
Cement
Material ( Nepali ) M.T. 0.121 0.00 0.00
sand(Crusher
screen) Cu.m 0.165 0.00 0.00
white cement M.T. 0.069 42000.00 2898.00
3mm marble
chips Cu.m 0.047 9000.00 423.00
oxalic acid kg 0.340 269.00 91.46
mein polish kg 0.110 445.00 48.95
terpaintain lit 0.500 100.00 50.00
rubbing stone L.S. 60.00
Sub-Total 3571.41
Tools & Plants @ 3% 107.14
Sub-Total (Dept. Rate) 3678.55
Contractor's Profit @ 1 551.78
Sub-Total 4230.33
Grand Total (Cont. Rat 4230.33
20 mm th.mosaic (Terrajo Tile) flooring with 20 mm th cement plaster (1:4)
B-1 base course including rubbing & polishing
Norms No. 11/5, 101
Unit 10 Sqm
Particular Description Unit Quantity Rate Amount
Labour Skilled Md 2.00 0.00 0.00
Unskilled Md 12.60 0.00 0.00
Cement(N.S.
Material marks) M.T. 0.081 0.00 0.00
sand (Crusher
screen) Cu.m 0.220 0.00 0.00
Mosaic(terrajo)
tile sqm 11.000 800.00 8800.00
oxalic acid kg 0.370 269.00 99.53
mein polish kg 0.118 445.00 52.51
terpaintain lit 0.538 100.00 53.80
rubbing stone L.S. 60.00
Rubbinng
Equipment Labour md 13.500 0.00 0.00
Sub-Total 9065.84
Tools & Plants @ 3% 271.98
Sub-Total (Dept. Rate) 9337.82
Contractor's Profit @ 1 1400.67
Sub-Total 10738.49
Grand Total (Cont. Rat 10738.49
25 mm th. marble with cement sand (1:2) surface course including rubbing &
C polishing
Norms No. 11/6, 102
Unit 10 Sqm
Particular Description Unit Quantity Rate Amount
Labour Skilled Md 2.00 0.00 0.00
Unskilled Md 21.50 0.00 0.00
Cement(N.S.
Material marks) M.T. 0.031 0.00 0.00
sand (Crusher
screen) Cu.m 0.183 0.00 0.00
2 5 mm thick
marble sqm 11.000 2500.00 27500.00
oxalic acid kg 0.370 269.00 99.53
mein polish kg 0.118 445.00 52.51
terpaintain lit 0.538 100.00 53.80
rubbing stone L.S. 60.00
Sub-Total 27765.84
Tools & Plants @ 3% 832.98
Sub-Total (Dept. Rate) 28598.82
Contractor's Profit @ 1 4289.82
Sub-Total 32888.64
Grand Total (Cont. Rat 32888.64
ii In Floor
Norms No. 11/7, 103
Unit 10 Sqm
Particular Description Unit Quantity Rate Amount
Labour Skilled Md 13.00 0.00 0.00
Unskilled Md 4.50 0.00 0.00
Material Cement(N.S. markM.T. 0.056 0.00 0.00
sand (Crusher scrCu.m 0.152 0.00 0.00
Porcelain white
glazed tile sqm 11.000 764.24 8406.64
white cement kg 3.228 42.00 135.57
Sub-Total 8542.21
Tools & Plants @ 3% 256.27
Sub-Total (Dept. Rate) 8798.48
Contractor's Profit @ 1 1319.77
Sub-Total 10118.25
Grand Total (Cont. Rat 10118.25
, item no.10 )
User's Rate Remarks
Rate Amount
650.00 1625.00
48.75
1673.75
650.00 975.00
1500.00 1650.00
0.00 0.00
2625.00
78.75
2703.75
13308.98
399.27
13708.25
Remarks
Rate Amount
955.00 1432.50
700.00 770.00
25.99 571.78
248.60 218.77
2993.05
29.93
0.90
30.83
2776.24
2730.00 27300.00 1
Sq.m.=16.14
27300.00 kg
819.00
2811.90
4750.00 47500.00 1
Sq.m.=16.14
47500.00 kg
1425.00
4892.50
0.00
0.00
0.00
0.00
0.00
0.00
plaster (1:2) base course & 6 mm th marble chips with white
rse including rubbing & polishing
423.03
423.03
cement plaster (1:4)
1073.85
1073.85
3288.86
3288.86
6350.80
6350.80
1011.83
1011.83
1011.83
1011.83
d mortar
1175.26
1175.26
3387.67
Kathekhola Rural Municipality
Office of the Rural Municipality Executive
Bihunkot, Baglung
Gandaki Province, Nepal
\
Quantity Measurement
Project Name:- Homestay paryatan purbadhar karyakaram sanchalan
Homestay Name:- Shivadhuri samudayik homestay
Location:- Kathekhola Rural Municipality-5, Bihu
S.N Description of items No Length Breadth Height Quantity Unit Rate Amount Remarks
1 Earthwork
land development 825 1.50 0.45 0.6 334.125
stone soling 1 12.00 1.5 0.2 3.6
total 337.725 m3 432.6 146099.835
2 Dry stone masonary work
for stairs 825 1.50 0.4 0.26 128.7 m3 3557.00 457785.9