Sunteți pe pagina 1din 91

Kathekhola Rural Municipality

Office of the Rural Municipality Executive


Bihunkot, Baglung
Gandaki Province, Nepal

Measurement book

Project Name:- Homestay paryatan purbadhar karyakaram sanchalan


Homestay Name:- Shivadhuri samudayik homestay

Location:- Kathekhola Rural Municipality-5, Bihu


Allocated budget(division ban karyalaya, Baglung):-1000000
Allocated budget(kathekhola rural municipality):-min 10% of 1000000
RATE ANALYSIS
Name of Project : F./Y.:-
Item Labour (L) Materials (M) Total (L+M)

Rate Unit Rate, Rs. Cost, Rs. Total Cost, Rs. Norms
Cost Unit
SN Description Catagory m.d. Type Quantity IncludingVAT(for
per m.d. Including Excluding Including Excluding No.
UC)
Rs. Rs. VAT VAT VAT VAT in m in ft
1 Site clearance for1Sqm Unskill 0.23 700 161.00 Tools & Plant 3 % of labour cost 4.83 4.83 16.58 1.54 U/D A.(3)
1 Site clearance for1Sqm Unskill 0.04 700 28.00 Tools & Plant 3 % of labour cost 0.84 0.84 28.84 2.68 DoLIDAR 1-1.6
dismentaling of old
bldg(mud mortar) Unskill 1.06 700 742.00 Tools & Plant 3 % of labour cost 22.26 22.26 m3 764.26
Skill 0.054 955 51.57 Tools & Plant 3 % of labour cost 1.55 1.55 53.12
roof dismentaling work Unskill 0.081 700 56.70 Tools & Plant 3 % of labour cost 1.70 1.70 m2 58.40
111.52

2
Earthwork in excavation in

a ordinary soft soil- For 1 m3 Unskill 0.50 700 350.00 Tools & Plant 3 % of labour cost 10.50 10.50 360.50 10.22 5.2-1.2.2(a)
b Hard soil- For 1 m3 Unskill 0.60 700 420.00 Tools & Plant 3 % of labour cost 12.60 12.60 432.60 12.26 5.2-1.2.2(b)
c Soft Rock- For 1 m3 Unskill 0.80 700 560.00 Tools & Plant 3 % of labour cost 16.80 16.80 576.80 16.35 5.2-1.2.2(c)
d Medium Rock- For 1 m3 Unskill 3.00 700 2100.00 Tools & Plant 3 % of labour cost 63.00 63.00 2163.00 61.30 5.2-1.2.2(d)

e Hard Rock- For 1 m3 (no


chino) Unskill 5.00 700 3500.00 Tools & Plant 3 % of labour cost 105.00 105.00 3605.00 102.16 5.2-1.2.2(e)
with chino Unskill 24.00 700 16800.00 Tools & Plant 4 % of labour cost 504.00 504.00 17304.00 490.37 5.2-1.2.2(e)
f. BMS- For 1 m3 Unskill 0.80 700 560.00 Tools & Plant 3 % of labour cost 16.80 16.80 576.80 16.35 U/D B1)2-2
Stone Solling in foundation
4
& Leveling Unskill 1.50 700 1050.00 Tools & Plant 3 % of labour cost 31.50 31.50 1081.50
Blockstone 1.00 1844.70 1500.00 1844.70 1844.70 1844.70 DoLIDAR
Bondstone 0.10 1844.70 1500.00 184.47 184.47 184.47
Total 1050.00 2060.67 3110.67 88.15 49)17-6
Formworks of Local wood
5
for Beam/Slab Skill 0.150 955 143.25 Local Wood 0.0070 45000.00 45000.00 315.00 315.00 m3 U/D+DoLIDAR
For 1 Sq.m. Unskill 0.200 700 140.00 Nails 0.25 113.00 100.00 28.25 25.00 kg 39)9.a
Total 283.25 343.25 340.00 626.50 58.23
Quantity of wood required for 1 sqm formwork = 0.0526 cum.
Wood can be used 6 times for the formwork and after then 25% cost
of the wood is recovered. So the quantity of wood required for 1 sqm = 0.00658 cum.

9
Plain cement concrete work Skill 1.00 955 955.00 Cement 0.32 22387.0 20099.0 7163.84 6431.68 MT
M15(P.C.C. 1:2:4) Unskill 4.00 700 2800.00 Agg.40mm 0.52 4073.0 4073.0 2117.96 2117.96 cu.m U/D
and wall - For 1 m3 Agg.20mm 0.22 3014.6 3014.6 663.21 663.21 cu.m D1 7-2d
For Foundation Agg.10mm 0.11 3014.6 3014.6 331.61 331.61 cu.m
Sand 0.445 6398.40 6398.40 2847.29 2847.29 cu.m
Total 3755.00 13123.91 12391.75 16878.91 478.32
14 Skill 0.50 955 477.50 Blockstone 1.00 1845 1845 1845.00 1845.00 cu.m DoLIDAR
Dry stone masonry work
with rubble stone For 1 m3 Unskill 1.50 700 1050.00 Bondsotne 0.10 1845 1845 184.50 184.50 cu.m 38. 8
Total 1527.50 2029.50 2029.50 cu.m 3557.00
Government of Nepal
Ministry of Local Development
Office of District Development Committee
District Technical Office
Gorkha
Rate of Materials
148207.7184 52931.328 FY : 2069/70
Rate/kg/km
By Tractor By Poters
General Rate for Analysis Rate for Analysis Weight Load /
SN Particular VAT 13% Unit
Rate ( VAT+Trans.) (WithTrans.) per unit Unload
Tractor Porter
Dist(KM) Amount Dist(KM)
1 Skill Labour 955.00 955.00 955.00 md
2 Unskilled Labour 700.00 700.00 700.00 md
3 Painter 955.00 955.00 955.00 md
4 Sand 2400.00 6398.40 6,398.40 m3 1600.00 0.147 0.75 17.00 3998.40 0.00
5 Aggregate 40mm 2750.00 4073.00 4,073.00 m3 1800.00 0.147 0.59 5.00 1323.00 0.00
6 Aggregate 20mm 2750.00 3014.60 3,014.60 m3 1800.00 0.147 0.59 1.00 264.60 0.00
7 Aggregate 10mm 2750.00 3014.60 3,014.60 m3 1800.00 0.147 0.59 1.00 264.60 0.00
8 Stone 1500.00 1844.70 1,844.70 m3 1800.00 0.147 0.59 0.50 132.30 0.20
9 Mud for masonry 280.00 445.20 445.20 m3 1400.00 0.147 0.59 0.00 0.20
10 Sal wood 45000.00 45070.80 45,070.80 m3 600.00 0 0.59 3.00 0.00 0.20
11 Local Wood 45000.00 45000.00 45,000.00 m3 600.00 0 0.59 3.00 0.00
12 Sisau 70560.00 70560.00 70,560.00 m3 600.00 0 0.59 0.00
13 Cement(NS Mark OPC) 17600.00 2288.00 22387.00 20,099.00 mt 1000.00 0.147 0.59 17.00 2499.00 0.00
14 Brick(Chimney ) 13.00 1.69 22.19 20.50 Nos 2.50 0.147 0.59 20.00 7.35 0.10
15 Nail 100.00 13.00 113.00 100.00 kg 1.00 0.147 0.59 0.00 0.00
31 Reinforcement Bar(10-40mm) 86000.00 11180.00 100120.00 88,940.00 mt 1000.00 0.147 0.59 20.00 2940.00 0.00
32 GI Wire 12Swg (Heavy Coating) 105.00 13.65 118.65 105.00 kg 1.00 0.147 0.59 0.00 0.00
33 GI Wire 10Swg (Heavy Coating) 100.00 13.00 113.00 100.00 kg 1.00 0.147 0.59 0.00 0.00
34 GI Wire 8Swg (Heavy Coating) 100.00 13.00 113.00 100.00 kg 1.00 0.147 0.59 0.00 0.00
35 3mm Glass 500.00 65.00 565.00 500.00 m2 8.40 0.147 0.59 0.00 0.00
36 4mm Glass 640.00 83.20 723.20 640.00 m2 11.20 0.147 0.59 0.00 0.00
37 5mm Glass 750.00 97.50 847.50 750.00 m2 14.00 0.147 0.59 0.00 0.00
38 Lime 18.00 2.34 21.81 19.47 kg 1.00 0.147 0.59 10.00 1.47 0.00
39 Gum (Rathicol) 200.00 26.00 227.47 201.47 kg 1.00 0.147 0.59 10.00 1.47 0.00
40 Primer (wood) 290.00 37.70 329.17 291.47 Ltr 1.00 0.147 0.59 10.00 1.47 0.00
41 Enamel 425.00 55.25 480.25 425.00 Ltr 1.00 0.147 0.59 0.00 0.00
42 Alumunium Paint 500.00 65.00 565.00 500.00 Ltr 1.00 0.147 0.59 0.00 0.00
43 Sand Paper 10.00 1.30 11.30 10.00 Sheet 0.147 0.59 0.00 0.00
44 Red Oxide No 1 350.00 45.50 395.50 350.00 Ltr 1.00 0.147 0.59 0.00 0.00

______________ _______________ ______________


Prepared By Checked by Approved By
Rate of Materials
148207.7184 52931.328 FY : 2069/70
Rate/kg/km
By Tractor By Poters
General Rate for Analysis Rate for Analysis Weight Load /
SN Particular VAT 13% Unit
Rate ( VAT+Trans.) (WithTrans.) per unit Unload
Tractor Porter
Dist(KM) Amount Dist(KM)
45 Binding wire 105.00 13.65 121.59 107.94 kg 1.00 0.147 0.59 20.00 2.94 0.00
CGI Sheet 0.38 mm th
46 9500.00 1235.00 10926.10 9,691.10 bun. 0.147 0.59
Colour,26gauge 65.00 20.00 191.10 0.00
47 CGI Sheet 0.4 mm th Colour 9300.00 1209.00 10509.00 9,300.00 bun. 60.00 0.147 0.59 0.00 0.00
48 Plain sheet 28 gauge 340.00 44.20 387.14 342.94 rm 1.00 0.147 0.59 20.00 2.94 0.00
49 3mm plywood 193.68 25.18 218.86 193.68 m2 2.00 0.147 0.59 0.00 0.00
50 Snowcem Paint 77.00 10.01 88.48 78.47 kg 1.00 0.147 0.59 10.00 1.47 0.00
51 Chimney Brick 12.00 1.56 16.03 14.47 nos 2.80 0.147 0.59 6.00 2.47 0.00
52 Wall Tile (Indian) 8"x6" 645.83 83.96 729.79 645.83 m2 12.00 0.147 0.59 0.00 0.00
53 Tile floor (Indian) 8"x8" 839.59 109.15 948.74 839.59 m2 15.00 0.147 0.59 0.00 0.00
54 White Cement 26.00 3.38 29.38 26.00 kg 1.00 0.147 0.59 0.00 0.00
55 2X 500 gauge polythene 83.00 10.79 93.79 83.00 m2 0.147 0.59 0.00 0.00
56 Railing with GI & Black Pipe 250.00 32.50 282.50 250.00 sqft 2.50 0.147 0.59 0.00 0.00
57 Nut Bolt 8 mm 25.00 3.25 28.25 25.00 No 0.147 0.59 5.00 0.00 0.20
58 Bitumin Washer 1.00 0.13 1.13 1.00 No 0.147 0.59 0.00 0.20
59 J-Hook 4" 22.00 2.86 24.86 22.00 No 0.147 0.59 0.00 0.20
60 J-Hook 6" 26.00 3.38 29.38 26.00 No 0.147 0.59 0.00 0.20
61 Iron Grill(Ready made) 120.00 15.60 135.72 120.12 kg 1.00 0.147 0.59 0.00 0.20
38 mm dia 16Gauge thick
62 350.00 45.50 395.80 350.30 Rm 0.147 0.59
stainless steel pipe 2.50 0.00 0.20
25 mm dia 16Gauge
63 200.00 26.00 226.18 200.18 Rm 0.147 0.59
thickstainless steel pipe 1.50 0.00 0.20
Gas welding for stainless steel
64 150.00 19.50 169.50 150.00 sq m 0.147
pipe 0.00 0.20
65 Black Iron Pipe 1.8 mm Thick 95.00 12.35 107.35 95.00 kg 1.00 0.147 0.00 0.20

______________ _______________ ______________


Prepared By Checked by Approved By
By Poters

Amount

0.00
0.00
0.00
0.00
212.40
165.20
70.80
0.00
0.00
0.00
0.15
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

______________ _______________ ______________


Prepared By Checked by Approved By
By Poters

Amount
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.12

0.30

0.18

0.00
0.00

______________ _______________ ______________


Prepared By Checked by Approved By
sfo{;DkGg k|ltj]bg
sfof{nosf] gfd M– ufp+kflnsfsf] sfo{no d=n]=k=kmf=g+= M–
Homestay Name:- Shivadhuri samudayik homestay
Location:- Kathekhola Rural Municipality-5, Bihu
nfut cfg"dfg /sdM– 1436228.22 sfd z'?ePsf] ldltM–
sfo{ ;DkGg ePsf] /sd 1454368.85 sfd ;DkGg ug'{+kg] ldltM–
Oi6d]6 eGbf 36L jf a9 18140.6 sfd ;DkGg ePsf] ldltM–

nfut sfof{ ;DkGg ePsf] km/s


qm= sfdsf] lhh/0f PsfO{ s}lkmot
kl/df0f :jLst b/ nfut ? kl/df0f :jLst b/ /sd kl/df0f :jLst b/ /sd
1 Earthwork m3 344.2650 432.60 148929.04 337.72500 432.60 146099.84 -6.540 0.00 -2829.20
2 Dry stone masonary work m3 109.7550 3557.00 390398.54 128.70000 3557.00 457785.90 18.945 0.00 67387.36
3 Stone soling works m3 11.2500 3110.67 34995.04 2.70000 3110.67 8398.81 -8.550 0.00 -26596.23

4 Formworks m2 9.0000 626.50 5638.50 10.50000 626.50 6578.25 1.500 0.00 939.75
5 M15 PCC work(c/s/a 1/2/4) m3 50.7300 16878.91 856267.10 49.50000 16878.91 835506.05 -1.230 0.00 -20761.05
s'n /sd 1,436,228.22 1,454,368.85 18,140.63

gf]6M–n=O= eGbf a9L eP-±_ jf sd eP-–_ lrGx n]Vg].


!= ljnsf] qmd ;+Vof M clGtd Kathekhola Rural Municipality &= ;Demf}tf ldlt M
Homestay Name:- Shivadhuri samudayik
homestay Office of the Rural Municipality Executive *= sfd ;dfKt ug'{kg]{ ldlt M
#= pkef]Qmf ;ldltsf] cWoIfsf] g Bihunkot, Baglung (= sfd gfkL ePsf] ldlt M
$= ;Demf}tf g+= M Gandaki Province, Nepal e'QmfgL ef}r/ g+= M
%= cl3Nnf] e'QmfgL ljnsf] qmd e'QmfgL ldlt M
^= cl3Nnf] e'QmfgL ljnsf] ef}r pkef]Qmf ;DaGwL lan gfkL lstfj g+= M
cfO6 cBfjlws sfd ePsf] cl3Nnf] ljnsf] r9]sf] xfn ePsf] sfd
n=O{=
d sfdsf] ljj/0f PsfO{
kl/df0f kl/df0f b/ hDdf d"No kl/df0fhDdf d"Nokl/df0f hDdf d"No
g+=
1 Earthwork m3 344.27 337.7250 432.60 146,099.84 337.73 146,099.84
2 Dry stone masonary work m3 109.76 128.7000 3557.00 457,785.90 128.70 457,785.90
3 Stone soling works m3 11.25 2.7000 3110.67 8,398.81 2.70 8,398.81

Formworks m2
4 9.00 10.5000 626.50 6,578.25 10.50 6,578.25
5 M15 PCC work(c/s/a 1/2/4) m3 50.73 49.5000 16878.91 835,506.05 49.50 835,506.05
hDdf /sd 1,454,368.85 s§f ug'{ kg]{ ?- 1,454,368.85
=ag sfof{no ‐
! of] lan jdf]lhd e'QmfgL h 1454368.85 $ afun'ª 400000
@ hg;|dbfg 354368.85 s= k]ZsL
# afFsL lbg' kg]{ ?= 700000.00 v= dfn;fdfgsf] df]n
afFsL lbg' kg] ‐sf7]vf]nf 100000 u= cGo
afFsL lbg' kg]{ ?= ‐ag sfo 600000 % v'b lbg'

k]z ug]{sf] ;xL M hfFr ug]{sf] ;xL M :jLs[t ug]{sf] ;xL M


bhf{ M bhf{ M bhf{ M
hDdf cIf?kL r]s g+= =======================af6 k||fKt eof] egL ;xL ug]{ .
s}lkmot

afFsL lbg' kg] ‐sf7]vf]nf uf=kf=_

afFsL lbg' kg]{ ?= ‐ag sfof{no afun'ª

afun'ª

Kt eof] egL ;xL ug]{ .


Salient Features of Project
Homestay Name:- Shivadhuri samudayik homestay
Location:- Kathekhola Rur
sfo{qmdsf] gfd
sfd ug]{ lgsfo pkef]Qmf ;ldlt
cfly{s aif{ 075/076
ljlgof]lht jh]6 #REF!
cg'dflgt nfut 1436228.22
sG6LGh]G;L 0.00
pkef]Qmf >dbfg #REF!
v'b e'QmfgL x'g;Sg] /sd #REF!
l;=g sfdsf] ljj/0f

gf]6
ufp+kflnsfsf] sfof{non] pkef]Qmf ;ldlt;+u ;Demf}tf
ubf{ lgDgfg';f/sf] zt{x?sf] clgjfo{ kfngf u/fpg] k|ltj4tf lnP/
dfq ;Demf}tf
!=pkef]Qmf u/fpgsf
;ldltn] gS;f tyfnflu
nfut cg'/f]w
Ol:6d]6 adf]lhd lgdf{0f ubf{ k'/fgf
vfg]kfgL, l;+rfO{, ljBfno ejg, lghL 3/, uf]7, cf+“ug cfbL k"jf{wf/ ;+/rgf Iflt
k'¥ofPsf] v08df ;f]xL pkef]Qmf ;ldltn] cfkm";+u ePsf] ;Demf}tf /sd leqsf]
ah]6af6 dd{t, lgdf{0f jf k'glg{df{0f ul/lbg' kg]{5 . ;f] ;DjGwdf s'g} ph'/L
kg{ cfPdf pQm Iflt ePsf] lgdf{0f ug{ nfUg] /sd ;DjlGwt pkef]Qmf ;ldltsf]
vftfaf6 s§f u/]/ dfq clGtd km/kmf/s ug]{ Joj:yf ldnfpg'x'g .
@= ;DjlGwt k|fljlws 6f]nLn] ;fO{6df u/]sf] ;e]{, sfof{nosf] :jLs[t nfut cg'dfg
Pj+ gS;fx? cg';f/ g} lgdf{0f sfo{ u/fpg] k|ltj4tf lng' x'g .
#= :jLs[t nfut cg'dfg / gS;f eGbf km/s sfo{ u/L sfof{non] d"Nof+sg gu/]sf]
v08df s'g} lsl;dsf] ph'/ nfUg]5}g eGg] k|ltj4tf lng'x'g .
$= ;Demf}tf adf]lhdsf] lgdf{0f ubf{ u/fpbf jftfj/0f ;+/If0f P]g @)%# /
jftfj/0f lgodfjnL @)%$adf]lhd jftfj/0fdf gsf/fTds k|efj gkg]{ul/ u/fpg] k|ltj4tf
lng'x'g .
B..Hard Soil
Norms No: 5.2-1.2.2(b) DoLIDAR
Unit :cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md 0.000 870.00 -
Unskill Md 0.60 650.00 390.00
Tools andSub-Total
plants 390.00
@3% 11.70
Total 401.70
Item: Dry Stone Pitching/Soling & Levelling Works
Norms No: 49.17-6 DoLIDAR
Unit :m3
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md - 870.00 -
Unskill Md 1.00 650.00 650.00
Material Stone m3 1.10 1,602.00 1,762.20
Sub-Total
Tools and plants 2,412.20
@3% 72.37
Total 2,484.57
15 % Overhead
Unit Rate 2,484.57

Item: plain cement concrete works in foundation including material collection & 30m lead
A.1:4:8
Norms No: 41(7-2)c
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 1.00 870.00 870.00
Unskill Md 4.00 650.00 2,600.00
Material Cement ( OPC NS MT 0.17 - -
mark)
Agg 40 mm cu.m 0.65 - -
Agg 20 mm cu.m 0.24 - -
Coarse sand cu.m 0.47 - -
Total 3,470.00 cft
Unit Rate 3,470.00 98.26

Item: plain cement concrete works in foundation including material collection & 30m lead
A.1:3:6
Norms No: 42(7-2)c
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 1.00 870.00 870.00
Unskill Md 4.00 650.00 2,600.00
Material Cement ( OPC NS MT 0.22 - -
mark)
Agg 40 mm cu.m 0.65 - -
Agg 20 mm cu.m 0.24 - -
Coarse sand cu.m 0.47 - -
Sub-Total 3,470.00
15 % Overhead 520.50
Unit Rate 3,990.50
Item: plain cement concrete works in foundation including material collection &30m lead
B.M 15 Grade (1:2:4 mix by volume)
Norms No: 41.11.b DoLIDAR
Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill Md 1.00 870.00 870.00
Unskill Md 4.06 650.00 2,639.00
Cement ( OPC NS
Material mark) MT 0.32 20,804.00 6,657.28
Agg 40 mm cu.m 0.52 - -
Agg 20 mm cu.m 0.22 1,850.00 407.00
Agg 10 mm cu.m 0.11 - -
Coarse sand cu.m 0.440 2,300.00 1,012.00
Sub-Total 11,585.28
15 % Overhead 1,737.79
Unit Rate 13,323.07
Item: plain cement concrete works in superstructure including material collection &30m lead
A. 1:2:4 mix
Norms No: 44(7-4)a,
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 0.80 870.00 696.00
Unskill Md 7.00 650.00 4,550.00
Material Cement ( OPC NS MT 0.32 20,804.00 6,657.28
mark)
Agg 40 mm cu.m 0.52 - -
Agg 20 mm cu.m 0.22 1,850.00 407.00
Agg 10 mm cu.m 0.11 - -
Coarse sand cu.m 0.445 2,300.00 1,023.50
Sub-Total 13,333.78
15 % Overhead 2,000.07
Unit Rate 15,333.85

Item: plain cement concrete works in superstructure including material collection &30m lead
B. 1:1.5:3 mix
Norms No: 7(4)b,45
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 0.80 870.00 696.00
Unskill Md 7.00 650.00 4,550.00
Material Cement ( OPC NS MT 0.40 20,804.00 8,321.60
mark)
Agg 20 mm cu.m 0.57 1,850.00 1,054.50
Agg 10 mm cu.m 0.29 - -
Coarse sand cu.m 0.425 2,300.00 977.50
Sub-Total 15,599.60
15 % Overhead 2,339.94
Unit Rate 17,939.54
Item: Reinforcement for RCC works including procuring steel, bending, placing, bindibg and fixing in
position all complite RCC works
Norms No: 40-10
Unit : Kg.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill Md 0.0070 870.00 6.09
Unskill Md 0.0070 650.00 4.55
Material M.S. Rod MT 0.00105 93,790.00 98.48
Binding wire kg 0.01000 113.00 1.13
-
-
Sub-Total 110.25
15 % Overhead 16.54
Unit Rate 126.79

A) Stone Masonry works including material collection,preparation of mortar with 5m lift and 10m lead
A. Un-coursed rubble Masonary 1:4
Norms No : 38.8-A. c DoLIDAR
Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 1.50 md 870.00 1,305.00
Unskill 3.24 md 650.00 2,106.00

Material Cement ( OPC NS


mark) 0.116 MT 20,804.00 2,413.26
RubbleStone 1.10 M3 1,602.00 1,762.20
Sand 0.47 M3 2,300.00 1,081.00
Sub-Total 8,667.46
15 % Overhead 1,300.12
Unit Rate 9,967.58

B. Random rubble Masonary 1:6


Norms No : 6(1)a-3,32
Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 1.50 md 870.00 1,305.00
Unskill 5.00 md 650.00 3,250.00
Material Cement ( OPC NS 0.106 MT 20,804.00 2,205.22
mark)
Blockstone 1.00 M3 20,804.00 20,804.00
Bondstone 0.10 M3 1,602.00 160.20
Sand 0.47 M3 2,300.00 1,081.00
Sub-Total 28,805.42
15 % Overhead 4,320.81
Unit Rate 33,126.23

A) Stone Masonry works including material collection,preparation of mortar with 5m lift and 10m lead
A. Un-coursed rubble Masonary 1:6
Norms No : 38.8-A. d DoLIDAR
Unit : Cu.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill 1.50 md 870.00 1,305.00
Unskill 3.29 md 650.00 2,138.50
Cement ( OPC NS
Material mark) 0.092 MT 20,804.00 1,913.97
Rubble Stone 1.10 M3 1,602.00 1,762.20
Sand 0.50 M3 2,300.00 1,150.00
Sub-Total 8,269.67
15 % Overhead 1,240.45
Unit Rate 9,510.12
B)12.5 mm thick plastering with cement sand mortar on brick wall or concrete surfaces including full
compensation for all labour, materials , scafolding and otter incidental required to complete tte works as per the
specifications
d). In 1:6 mix ratio
Norms No : 37.7-9.4 d) DoLIDAR
Unit :100 Sq.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill 15.00 md 870.00 13,050.00
Un-skill 13.70 md 650.00 8,905.00
Cement ( OPC NS
Material mark) 0.288 MT 20,804.00 5,991.55
Sand 1.58 M3 2,300.00 3,634.00
Sub-Total 31,580.55
15 % Overhead 4,737.08
Total 36,317.63
Unit Rate 363.18

C)pointing works with cement sand mortar on brick wall with all required operation including full compensation
for all labour, materials , scafolding and otter incidental required to complete tte works as per the specifications

c .In 1:3 mix ratio


Norms No : 37.7-9.3d) DoLIDAR
Unit :100 Sq.m.

Particular Description Unit Quantity Rate Amount Remarks


Labour Skill 8.00 md 870.00 6,960.00
Un-skill 8.88 md 650.00 5,772.00
Cement ( OPC NS
Material
mark) 0.096 MT 20,804.00 1,997.18
Sand 0.29 M3 2,300.00 667.00
Sub-Total 15,396.18
15 % Overhead 2,309.43
Total 17,705.61
Unit Rate 177.06
Preparation of bedding for pipe with granular materials . It includes all labour,materials.
Norms No : 46 .15-4 DoLIDAR
Unit :1 Cub.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill md 870.00 -
Un-skill 1.00 md 650.00 650.00
Well grage granular
materials passing
Material 4.75mm sieve and
down 1.100 M3 1,400.00 1,540.00
Sub-Total 2,190.00
15 % Overhead 328.50
Unit Rate 2,518.50
Laying,fitting and fixing of hume pipe having a length of 1 m or more. Its includes all operations required to
complete the works upto atrench depth of 2.2 m below the ground level and jointing of pipes with 1:2
cement sand ratio

b.) For every subsequent pipe having length of minimum 1m, Dia 30 cm. dia
Norms No : 47. 15-5 ,15- 6 b. DoLIDAR
Unit :1.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 0.02 md 870.00 17.40
Un-skill 0.10 md 650.00 65.00
Material Cement 0.001 MT 20,804.00 20.80
Sand 0.002 m3 2,300.00 4.60
Jute, Bitumin LS 30.00 30.00
Sub-Total 82.40
15 % Overhead 12.36
Unit Rate 94.76

b.) For every subsequent pipe having length of minimum 1m Dia 60 cm. dia
Norms No : 47. 15-5 ,15- 6 b. DoLIDAR
Unit :1.m.
Particular Description Unit Quantity Rate Amount Remarks
Labour Skill 0.050 md 870.00 43.50
Un-skill 0.200 md 650.00 130.00
Material Cement 0.003 MT 20,804.00 62.41
Sand 0.004 m3 2,300.00 9.20
Jute, Bitumin LS 40.00 40.00
Sub-Total 285.11
15 % Overhead 42.77
Unit Rate 327.88

Hence,
Total cost of 30cmdia.1m H.P. 94.76
Total cost of 60cmdia.1m H.P. 327.88
Total 45mm dia. H.P.1m(Average cost) 422.64 211.32

44.2.a Assembling of wire crates/gabion/revetment and placing them in position including streching
,binding them together and tying down lids. Box size(2X1X 1) (11 m2)
Unit :Per m3 44.2.a DoLIDAR
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0 md 870.00 0.00
Unskilled 0.09 md 650.00 58.50

Binding wire
Materials 0.95 kg 121.170 115.11
12swg(Heavy Coated)
Sub-Total 173.61
15 % Overhead -
Rate per Box
Size(2X1X1) 173.61
Rate per m3 86.81

44.2.a Assembling of wire crates/gabion/revetment and placing them in position including streching
,binding them together and tying down lids. Box size(3X1X 1) (16 m2)

Unit :Per m3 44.1.A.ii.b DoLIDAR


Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0 md 870.00 0.00
Unskilled 0.13 md 650.00 84.50

Binding wire
Materials 1.3 121.17 157.52
12swg(Heavy Coated)
kg
Sub-Total 242.02
15 % Overhead -
Rate per Box
Size(3X1X1) 242.02
Rate per m3 80.67

Unit rate/m3 Gabion Box


Size(2x1x1) NRs. 86.81
Gabion Box
Size(3x1x1) NRs. 80.67

Average Unit Rate 167.48 86.81 m3


45) Packing and filling of Gabion crates with stone
Unit :1m3 45.17-6 DoLIDAR
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0.3 md 870.00 261.00
Unskilled 0.75 md 650.00 487.50
Materials Stone 1.10 m3 1602.00 1762.20
Sub-Total 2,510.70
15 % Overhead -
Unit Rate 2,510.70 m3
Providing Mechine Made Heavy coated gabion Box Hexagonal Mesh size 10X12 cm,Mesh wire 10swg
(Heavy Coated),Selvedge wire 8swg (Heavy Coated),Binding wire 12swg(Heavy Coated) at site.

Size Sq.m/box Rate/Sq.


m Rate/Box Rate/Cu.m
Gabion Box 8
Size(1.5x1x1) 297.457 2379.65935 1586.44
Gabion Box 11
Size(2x1x1) 297.457 3272.0316 1,636.02
Gabion Box 16
Size(3x1x1) 297.457 4759.31869 1,586.44
1602.96667

Mechine Made Heavy coated gabion Box 1,602.97 m3


Packing and filling of Gabion crates with stone 2,510.70 m3
Sub Total Cost 4113.67
Assembling 86.81
Total Cost 4200.48
38.8 Dry Uncoursed Rubble Stone Masonry

Norms No : 38-8 DoLIDAR


Unit : Cu.m.
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0.5 md 870.00 435.00
Unskilled 1.5 md 650.00 975.00
Materials Stone 1.10 m3 1602.00 1762.20
Sub-Total 3,172.20
15 % Overhead -
Unit Rate 3,172.20 m3

26.3-1 Riverbed Material


Unit :1m3 38-8 DoLIDAR
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0 md 870.00 0.00
Unskilled 1 md 650.00 650.00
Materials River Bed Materials 1.00 m3 1400.00 1400.00
Sub-Total 2,050.00
15 % Overhead 307.50
Unit Rate 2,357.50 m3

1 .Transportation of BM Soil by truck or Tractor (15 KMpH)


DoLIDAR
Unit: 10 Cu. M. Norms S.N: 56.2
Spec.C No: G-13.2
Lead source Type Quantity Unit Rate Amount
First 1KM Labour Unskill 1.36 md 650.00 884.00
Material Disel 2.35 LTR 86.50 203.28
Truck/Tractor -
Equipment Working Hr. 0.39 Hr. 300 117.00
Idle HR. 2.21 Hr. 150 331.50
Actul Rate 1,535.78
Unit Rate 153.58

item : laying of locally available granular materials for gravelling in Roadway for gravelling including
j10m lead & 1.5m lift-per m3
particular unit Qantity Rate Amount Remarks
subgrade preparation 10 cm depth
labour unskill md 0.05 650.00 32.5

laying of sub base for gravelling 15cm 0


thick 0
labour unskill md 1.5 650.00 975 pouring &
Material kg km levelling
Transportation upto 4
km for 1m3=1800kg/m3

1800 3.5 0.047 296.1


Sub-total 1303.6
15%overhead 195.54
unit rate 1499.14
3.24
Kathekhola Rural Municipality
Office of the Rural Municipality Executive
Bihunkot, Baglung
Gandaki Province, Nepal
\
Quantity Estimate
Project Name:- Homestay paryatan purbadhar karyakaram sanchalan
Homestay Name:- Shivadhuri samudayik homestay
Location:- Kathekhola Rural Municipality-5, Bihu

S.N Description of items No Length Breadth Height Quantity Unit Rate Amount Remarks
1 Earthwork
land development 813 1.50 0.45 0.6 329.265 thamdanda
stone soling 1 50.00 1.5 0.2 15
total 344.265 m3 432.6 148929.039
2 Dry stone masonary work
for stairs 813 1.50 0.45 0.2 109.755 m3 3557.00 390398.535

3 Stone soling works 1 50.00 1.5 0.15 11.25 m3 3110.67 34995.0375


4 Formworks 30 1.50 0.2 9 m2 626.5 5638.5
5 M15 PCC work(c/s/a 1/2/4)
riser 813 1.50 0.08 0.2 19.512
tread 813 1.50 0.32 0.08 31.2192
total 50.73 m3 16878.91 856267.1043
Total Estimated amount 1436228.22
Baglung Municipality
Office Of Municipal Executive
Ratmata, Baglung
4 No. Province, Nepal
2073
Rate Analysis
Fiscal Year:-207
Earthwork in excavation for Soft clay and silty soil with 10 m lead and 1.5 m lift per m3, (S.N.2, item no.1 )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 0.70 md 650.00 455.00 0.70
2 Tools & Plant @3% 13.65
3 Sub Total 468.65
4 Contractor's Overhead @15 % 70.30
5 Grand Total 538.95

Earthwork in excavation for Hard clay and silty soil with 10 m lead and 1.5 m lift per m3, (S.N.2, item no.2 )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 0.80 md 650.00 520.00 0.80
2 Tools & Plant @3% 15.60
3 Rate Per m3 535.60
4 Contractor's Overhead @15 % 80.34
5 Grand Total 615.94

Earthwork in excavation for Medium Rock without blasting with 10 m lead and 1.5 m lift per m3, (S.N.2, item no.4 )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 3.00 md 650.00 1950.00 3.00
2 Tools & Plant @3% 58.50
3 Sub Total 2008.50
4 Contractor's Overhead @15 % 301.28
5 Grand Total 2309.78

Earthwork in excavation for Hard Rock without cheseling with 10 m lead and 1.5 m lift per m3, (S.N.2, item no.6, Ka )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 5.00 md 650.00 3250.00 5.00
2 Tools & Plant @3% 97.50
3 Sub Total 3347.50
4 Contractor's Overhead @15 % 502.13
5 Grand Total 3849.63

Earthwork in excavation for Hard Rock with cheseling with 10 m lead and 1.5 m lift per m 3, (S.N.2, item no.6, Kha )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 24.20 md 650.00 15730.00 24.20
2 Tools & Plant @3% 471.90
3 Sub Total 16201.90
4 Contractor's Overhead @15 % 2430.29
5 Grand Total 18632.19

Earthwork in excavation for trench in Soft Soil with 10 m lead and 1.5 m lift per m3, (S.N.2, item no.9 )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 1.00 md 650.00 650.00 1.00
2 Tools & Plant @3% 19.50
3 Sub Total 669.50
4 Contractor's Overhead @15 % 100.43
5 Grand Total 769.93
Earthwork in excavation for trench in Soft Rock with cracking with 10 m lead and 1.5 m lift per m3, (S.N.2, item no.10 )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 2.50 md 650.00 1625.00 2.50
2 Tools & Plant @3% 48.75
3 Sub Total 1673.75
4 Contractor's Overhead @15 % 251.06
5 Grand Total 1924.81

Earthwork in excavation for trench in BMS with 10 m lead and 1.5 m lift per m3, (S.N.2, item no.14)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 1.59 md 650.00 1033.50 1.59
2 Tools & Plant @3% 31.01
3 Sub Total 1064.51
4 Contractor's Overhead @15 % 159.68
5 Grand Total 1224.19

Earthwork in filling with layerwise of 15 cm compaction with water with 10 m lead and 1.5 m lift per m 3, (S.N. 2 item no.25 Ka )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 0.50 md 650.00 325.00 0.50
2 Tools & Plant @3% 9.75
3 Sub Total 334.75
4 Contractor's Overhead @15 % 50.21
5 Grand Total 384.96
.
Earthwork in filling with layerwise of 15 cm compaction without water with 10 m lead and 1.5 m lift per m3, (S.N. 2 item no.25 Kha )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 0.25 md 650.00 162.50 0.25
2 Tools & Plant @3% 4.88
3 Sub Total 167.38
4 Contractor's Overhead @15 % 25.11
5 Grand Total 192.49

Stone collection in site lead upto 10 m per m3 (S.N. 3, item no.4)


Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Labour 1.40 md 650.00 910.00 1.40
2 Tools & Plant @3% 27.30
3 Sub Total 937.30
4 Contractor's Overhead @15 % 140.60
5 Grand Total 1077.90

Stone mosonry works in dry wall per M3 (S.N.6 item no.2,1 )


Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.00 md 870.00 870.00 1.00
2 Labour 2.00 md 650.00 1300.00 2.00
3 Block Stone 1.00 m3 1500.00 1500.00 1.00
4 Bond Stone 0.10 m3 1500.00 150.00 0.10
5 Total 3820.00
6 Tools & Plant @3% 114.60
7 Sub Total 3934.60
8 Contractor's Overhead @15 % 590.19
9 Grand Total 4524.79

Stone Masonary work in Mud mortar M3 (S.N.6 item no.2,2 )


Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.00 md 870.00 870.00 1.00
2 Labour 2.25 md 650.00 1462.50 2.25
4 Block Stone 1.00 m3 1500.00 1500.00 1.00
5 Bond Stone 0.10 m3 1500.00 150.00 0.10
6 Mud 0.42 m3 450.00 189.00 0.42
7 Total 4171.50
8 Tools & Plant @3% 125.15
9 Sub Total 4296.65
10 Contractor's Overhead @15 % 644.50
11 Grand Total 4941.15

Stone Masonary work in 1:4 mortar per M3 (S.N.6, item no. 3 Ka)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.50 md 870.00 1305.00 1.50
2 Labour 5.00 md 650.00 3250.00 5.00
3 Cement 3.18 Bag 790.00 2512.20 3.18
4 Sand 0.45 m3 1550.00 697.50 0.45
5 Block Stone 1.00 m3 1500.00 1500.00 1.00
6 Bond Stone 0.10 m3 1500.00 150.00 0.10
7 Total 9414.70
8 Tools & Plant @3% 282.44
9 Sub Total 9697.14
10 Contractor's Overhead @15 % 1454.57
11 Grand Total 11151.71

Stone Masonary work in 1:6 mortar per M3 (S.N.6 item no. Ka-3)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.50 md 870.00 1305.00 1.50
2 Labour 5.00 md 650.00 3250.00 5.00
3 Cement 2.12 Bags 790.00 1674.80 2.12
4 Sand 0.47 m3 1550.00 728.50 0.47
5 Block Stone 1.00 m3 1500.00 1500.00 1.00
6 Bond Stone 0.10 m3 1500.00 150.00 0.10
7 Total 8608.30
8 Tools & Plant @3% 258.25
9 Sub Total 8866.55
10 Contractor's Overhead @15 % 1329.98
11 Grand Total 10196.53

Stone soling (pitching) work in foundation with 30m lead per M 3 (S.N.6 item no.5 )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason
2 Labour 1.50 md 650.00 975.00 1.50
3 Block Stone 1.10 m 3
1500.00 1650.00 1.10
4 Bond Stone m 3
0.00 0.00
5 Total 2625.00
6 Tools & Plant @3% 78.75
7 Rate per m3 2703.75
8 Contractor's Overhead @15 % 405.56
9 Grand Total 3109.31

Brick Masonary work in Mud mortar per M3 (S.N.5 item no. Kha-6 )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 P.C.C. for R.C.C. (1:3:6) Works for dr 1.00 md 870.00 870.00 1.00
2 Labour 1.70 md 650.00 1105.00 1.70
3 Cement Bag 790.00
4 Sand m3 1550.00
5 Brick (Local) 560.00 Nos 14.00 7840.00 560.00
6 Mud 0.42 m3 450.00 189.00 0.42
7 Total 10004.00
8 Tools & Plant @3% 300.12
9 Sub Total 10304.12
10 Contractor's Overhead @15 % 1545.62
11 Grand Total 11849.74

Brick Masonary work in 1:4 mortar per M3 (S.N.5 item no.Kha-2 )


Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.50 md 870.00 1305.00 1.50
2 Labour 2.20 md 650.00 1430.00 2.20
3 Cement 2.00 Bag 790.00 1580.00 2.00
4 Sand 0.28 m3 1550.00 434.00 0.28
5 Brick (Local) 560.00 Nos 14.00 7840.00 560.00
6 Mud m3 450.00
7 Total 12589.00
8 Tools & Plant @3% 377.67
9 Sub Total 12966.67
10 Contractor's Overhead @15 % 1945.00
11 Grand Total 14911.67

Brick Masonary work in 1:6 mortar per M3 (S.N.5 item no.Kha-3)


Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.50 md 870.00 1305.00 1.50
2 Labour 2.20 md 650.00 1430.00 2.20
3 Cement 1.40 Bag 790.00 1106.00 1.40
4 Sand 0.30 m3 1550.00 465.00 0.30
5 Brick (Local) 560.00 Nos 14.00 7840.00 560.00
6 Mud m3 450.00
7 Total 12146.00
8 Tools & Plant @3% 364.38
9 Sub Total 12510.38
10 Contractor's Overhead @15 % 1876.56
11 Grand Total 14386.94

PCC. work For Foundation in 1:3:6 with 30m lead per M 3 (S.N.7, item no.2,Ga )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.00 md 870.00 870.00 1.00
2 Labour 4.00 md 650.00 2600.00 4.00
3 Cement 4.40 Bag 790.00 3476.00 4.40
4 Sand 0.47 m3 1550.00 728.50 0.47
5 Stone aggregate (40 mm) 0.65 m3 1750.00 1137.50 0.65
6 Stone aggregate (20 mm) 0.24 m3 1850.00 444.00 0.24
7 Total 9256.00
8 Tools & Plant @3% 277.68
9 Sub Total 9533.68
10 Contractor's Overhead @15 % 1430.05
11 Grand Total 10963.73

PCC. Work for Foundation in 1:2:4 per M3 (S.N.7, item no.2,Gha )


Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.00 md 955.00 955.00 1.00
2 Labour 4.00 md 700.00 2800.00 4.00
3 Cement 6.40 Bag 790.00 5056.00 6.40
4 Sand 0.45 m3 1550.00 697.50 0.45
5 Stone aggregate (40 mm) 0.52 m3 1750.00 910.00 0.52
6 Stone aggregate (20 mm) 0.22 m3 1850.00 407.00 0.22
7 Stone aggregate (10 mm) 0.11 m3 1850.00 203.50 0.11
8 Total 11029.00
9 Tools & Plant @3% 330.87
10 Sub Total 11359.87
11 Contractor's Overhead @15 % 1703.98
12 Grand Total 13063.85

PCC. work for structure 1:1.5:3 (Slab,Beam etc ) per M3 (S.N.7, item no.4,Kha)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 0.80 md 955.00 764.00 0.80
2 Labour 7.00 md 700.00 4900.00 7.00
3 Cement 8.00 Bags 790.00 6320.00 8.00
4 Sand 0.43 m3 1550.00 666.50 0.43
5 Stone aggregate (20 mm) 0.57 m3 1850.00 1054.50 0.57
6 Stone aggregate (10 mm) 0.29 m3 1850.00 536.50 0.29
7 Total 14241.50
8 Tools & Plant @3% 427.25
9 Sub Total 14668.75
10 Contractor's Overhead @15 % 2200.31
11 Grand Total 16869.06

PCC. work For structure 1:2:4 (Slab,Beam etc ) per M3 (S.N.7, item no.4,Ka)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 0.80 md 955.00 764.00 0.80
2 Labour 7.00 md 700.00 4900.00 7.00
3 Cement 6.40 Bags 790.00 5056.00 6.40
4 Sand 0.445 m3 1550.00 689.75 0.445
5 Stone aggregate (40 mm) 0.52 m3 1750.00 910.00 0.52
6 Stone aggregate (20 mm) 0.22 m3 1850.00 407.00 0.22
7 Stone aggregate (10 mm) 0.11 m3 1850.00 203.50 0.11
8 Total 12930.25
9 Tools & Plant @3% 387.91
10 Sub Total 13318.16
11 Contractor's Overhead @15 % 1997.72
12 Grand Total 15315.88

Tor Steel bars for bending & placing in required position per 1 MT (S.N.7, item no.5 )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 12.00 md 955.00 11460.00 12.00
2 Labour 12.00 md 700.00 8400.00 12.00
3 Tor Bars 1.05 MT 80000.00 84000.00 1.05
4 Binding wire 10.00 kg 92.00 920.00 10.00
5 Total 104780.00
6 Tools & Plant @3% 3143.40
7 Rate per MT 107923.40
8 Rate per Kg 107.92
9 Contractor's Overhead @15 % 16.19
10 Grand Total 124.11
Form work for RCC or PCC including all complete with 30m lead per 10 m 2 (S.N.8, item no.2-Ka)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.72 md 955.00 1642.60 1.72
2 Labour 2.57 md 700.00 1799.00 2.57
3 Local wood 0.53 m 3
8534.38 753.87 0.53
4 Nails 2.50 kg 105.00 262.50 2.50
5 Total 4457.97
6 Tools & Plant @3% 133.74
7 Rate per 10 m2 4591.71
8 Sub Total 459.17
9 Contractor's Overhead @15 % 68.88
10 Grand Total 528.05
12.5 mm thick plastering work for walls & floor in 1:3 C/M per 100 M 2 (S.N.12-1-kha)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 12.00 md 955.00 11460.00 12.00
2 Labour 16.00 md 700.00 11200.00 16.00
3 Cement 12.50 Bags 790.00 9875.00 12.50
4 Sand 1.28 m 3
1550.00 1984.00 1.28
5 Rate per 100 m2 34519.00
6 Total per m2 345.19
7 Tools & Plant @3% 10.36
8 Sub Total 355.55
9 Contractor's Overhead @15 % 53.33
10 Grand Total 408.88
12.5 mm thick plastering work for walls & floor in 1:4 C/M per 100 M 2 (S.N.12-1-Ga )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 12.00 md 955.00 11460.00 12.00
2 Labour 16.00 md 700.00 11200.00 16.00
3 Cement 10.76 Bags 790.00 8500.40 10.76
4 Sand 1.46 m3 1550.00 2263.00 1.46
5 Rate per 100 m2 33423.40
6 Total per m2 334.23
7 Tools & Plant @3% 10.03
8 Sub Total 344.26
4 Contractor's Overhead @15 % 51.64
5 Grand Total 395.90

12.5 mm thick plastering work for walls & floor in 1:6 C/M per 100 M 2 (S.N.12-1-Gha )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 12.00 md 955.00 11460.00 12.00
2 Labour 16.00 md 700.00 11200.00 16.00
3 Cement 7.64 Bags 790.00 6035.60 7.64
4 Sand 1.57 m 3
1550.00 2433.50 1.57
5 Rate per 100 m2 31129.10
6 Sub Total 311.29
7 Tools & Plant @3% 9.34
8 Rate per m2 320.63
9 Contractor's Overhead @15 % 48.09
10 Grand Total 368.72
12.5 mm thick plastering work for ceiling in1:3 per 100 M 2 (S.N.12-1-kha)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 15.00 md 955.00 14325.00 15.00
2 Labour 20.00 md 700.00 14000.00 20.00
3 Cement 12.50 Bags 790.00 9875.00 12.50
4 Sand 1.28 m3 1550.00 1984.00 1.28
5 Rate per 100 m2 40184.00
6 Total per m2 401.84
7 Tools & Plant @3% 12.06
8 Sub Total 413.90
9 Contractor's Overhead @15 % 62.09
10 Grand Total 475.99
12.5 mm thick plastering work for ceiling in1:4 per 100M 2 (S.N.12-1-kha )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 15.00 md 955.00 14325.00 15.00
2 Labour 20.00 md 700.00 14000.00 20.00
3 Cement 10.76 Bags 790.00 8500.40 10.76
4 Sand 1.46 m3 1550.00 2263.00 1.46
5 Rate per 100 m2 39088.40
6 Total per m2 390.88
7 Tools & Plant @3% 11.73
8 Sub Total 402.61
9 Contractor's Overhead @15 % 60.39
10 Grand Total 463.00
12.5 mm thick plastering work for ceiling in1:6 per 100 M 2 (S.N.12-1,Gha )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 15.00 md 955.00 14325.00 15.00
2 Labour 20.00 md 700.00 14000.00 20.00
3 Cement 7.64 Bags 790.00 6035.60 7.64
4 Sand 1.57 m3 1550.00 2433.50 1.57
5 Rate per 100 m2 36794.10
6 Total per m2 367.94
7 Tools & Plant @3% 11.04
8 Sub Total 378.98
9 Contractor's Overhead @15 % 56.85
10 Grand Total 435.83

20 mm thick plastering work for walls & floor in 1:3 per 100 M 2 (S.N.12-4,ka )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 14.00 md 955.00 13370.00 14.00
2 Labour 19.00 md 700.00 13300.00 19.00
3 Cement 19.20 Bags 790.00 15168.00 19.20
4 Sand 1.95 m3 1550.00 3022.50 1.95
5 Rate per 100 m2 44860.50
6 Total per m2 448.61
7 Tools & Plant @3% 13.46
8 Sub Total 462.07
9 Contractor's Overhead @15 % 69.31
10 Grand Total 531.38
20 mm thick plastering work for walls & floor in 1:4 per 100 M 2 (S.N.12-4,kha)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 14.00 md 955.00 13370.00 14.00
2 Labour 19.00 md 700.00 13300.00 19.00
3 Cement 16.20 Bags 790.00 12798.00 16.20
4 Sand 2.20 m3 1550.00 3410.00 2.20
5 Rate per 100 m2 42878.00
6 Total per m2 428.78
7 Tools & Plant @3% 12.86
8 Sub Total 441.64
9 Contractor's Overhead @15 % 66.25
10 Grand Total 507.89
20 mm thick plastering work for walls & floor in 1:6 per 100M 2 (S.N.12-4,Ga )
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 14.00 md 955.00 13370.00 14.00
2 Labour 19.00 md 700.00 13300.00 19.00
3 Cement 11.40 Bags 790.00 9006.00 11.40
4 Sand 2.35 m3 1550.00 3642.50 2.35
5 Rate per 100 m2 39318.50
6 Total per m2 393.19
7 Tools & Plant @3% 11.80
8 Sub Total 404.99
9 Contractor's Overhead @15 % 60.75
10 Grand Total 465.74
Cement Pointing works 1:1 per 100 M2 (S.N.14-2,ka)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 10.00 md 955.00 9550.00 10.00
2 Labour 14.00 md 700.00 9800.00 14.00
3 Cement 12.24 Bags 790.00 9669.60 12.24
4 Sand 0.43 m3 1550.00 666.50 0.43
5 Rate per 100 m2 29686.10
6 Total per m2 296.86
7 Tools & Plant @3% 8.91
8 Sub Total 305.77
9 Contractor's Overhead @15 % 45.87
10 Grand Total 351.64

Cement Pointing work 1:2 per 100 M2 (S.N.14-2, kha)


Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 10.00 md 955.00 9550.00 10.00
2 Labour 14.00 md 700.00 9800.00 14.00
3 Cement 8.16 Bags 790.00 6446.40 8.16
4 Sand 0.57 m3 1550.00 883.50 0.57
5 Rate per 100 m2 26679.90
6 Total per m2 266.80
7 Tools & Plant @3% 8.00
8 Sub Total 274.80
9 Contractor's Overhead @15 % 41.22
10 Grand Total 316.02

Cement Pointing works 1:3 per 100 m2 (S.N.14-2,Ga)


Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 10.00 md 955.00 9550.00 10.00
2 Labour 14.00 md 700.00 9800.00 14.00
3 Cement 6.12 Bags 790.00 4834.80 6.12
4 Sand 0.63 m3 1550.00 976.50 0.63
5 Rate per 100 m2 25161.30
6 Total per m2 251.61
7 Tools & Plant @3% 7.55
8 Sub Total 259.16
9 Contractor's Overhead @15 % 38.87
10 Grand Total 298.03
3 mm thick Cement Punning works per 10 m2 (S.N.11 item 20)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.00 md 955.00 955.00 1.00
2 Labour 1.00 md 700.00 700.00 1.00
3 Cement 1.06 Bags 790.00 837.40 1.06
4 Rate per 10 m2 2492.40
5 Total per m2 249.24
6 Tools & Plant @3% 7.48
7 Sub Total 256.72
8 Contractor's Overhead @15 % 38.51
9 Grand Total 295.23
White washing work in new surface ( One coat) per 100 M 2 (S.N.13-1-ka)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 0.80 md 955.00 764.00 0.80
2 Labour 0.70 md 700.00 490.00 0.70
3 Lime 12.00 kg 23.00 276.00 12.00
4 Gum(Cement Solution) 0.48 kg 220.00 105.60 0.48
5 Rate per 100 m2 1635.60
6 Total per m2 16.36
7 Tools & Plant @3% 0.49
8 Sub Total 16.85
9 Contractor's Overhead @15 % 2.53
10 Grand Total 19.38

White washing work in new surface ( Two coat) per 100 M 2 (S.N.13-1-kha)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.50 md 955.00 1432.50 1.50
2 Labour 1.10 md 700.00 770.00 1.10
3 lime 22.00 kg 23.00 506.00 22.00
4 Gum 0.88 kg 220.00 193.60 0.88
5 Rate per 100 m2 2902.10
6 Total per m2 29.02
7 Tools & Plant @3% 0.87
8 Sub Total 29.89
9 Contractor's Overhead @15 % 4.48
10 Grand Total 34.37

White washing work in Old surface per 100 M2 (S.N.13-2)


Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 0.80 md 955.00 764.00 0.80
2 Labour 0.70 md 700.00 490.00 0.70
3 lime 10.00 kg 23.00 230.00 10.00
4 Gum 0.40 kg 220.00 88.00 0.40
5 Rate per 100 m2 1572.00
6 Total per m2 15.72
7 Tools & Plant @3% 0.47
8 Sub Total 16.19
9 Contractor's Overhead @15 % 2.43
10 Grand Total 18.62

Distemper painting work (Prime Coat) per 100 m2 (S.N.13-3,Ka)


Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 2.00 md 955.00 1910.00 2.00
2 Labour 2.00 md 700.00 1400.00 2.00
3 Asthar primer paint 8.00 Lit. 370.00 2960.00 8.00
5 Rate per 100 m2 6270.00
6 Total per m2 62.70
7 Tools & Plant @3% 1.88
8 Sub Total 64.58
4 Contractor's Overhead @15 % 9.69
5 Grand Total 74.27
Distemper painting work (First Coat) per 100 m2 (S.N.13-3,Kha)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 2.00 md 955.00 1910.00 2.00
2 Labour 2.00 md 700.00 1400.00 2.00
3 Distemper 6.50 Kg 280.00 1820.00 6.50
5 Rate per 100 m2 5130.00
6 Total per m2 51.30
7 Tools & Plant @3% 1.54
8 Sub Total 52.84
9 Contractor's Overhead @15 % 7.93
10 Grand Total 60.77

Distemper painting work (Second and others Coat) per 100 m2 (S.N.13-3,Ga)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.80 md 955.00 1719.00 1.80
2 Labour 1.80 md 700.00 1260.00 1.80
3 Distemper 5.00 Kg 280.00 1400.00 5.00
5 Rate per 100 m2 4379.00
6 Total per m2 43.79
7 Tools & Plant @3% 1.31
8 Sub Total 45.10
9 Contractor's Overhead @15 % 6.77
10 Grand Total 51.87

Water proof Cement Painting works per 100 m2 (One coat) (S.N.13, item no.4-Ka)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.70 md 955.00 1623.50 1.70
2 Labour 1.70 md 700.00 1190.00 1.70
3 Cement paint 30.00 kg 140.00 4200.00 30.00
5 Rate per 100 m2 7013.50
6 Total per m2 70.14
7 Tools & Plant @3% 2.10
8 Sub Total 72.24
9 Contractor's Overhead @15 % 10.84
10 Grand Total 83.08

Water proof Cement Painting works per 100 m2 (Two coat) (S.N.13, item no.4-Kha)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 5.00 md 955.00 4775.00 5.00
2 Labour 5.00 md 700.00 3500.00 5.00
3 Cement paint 48.50 kg 140.00 6790.00 48.50
5 Rate per 100 m2 15065.00
6 Total per m2 150.65
7 Tools & Plant @3% 4.52
8 Sub Total 155.17
9 Contractor's Overhead @15 % 23.28
10 Grand Total 178.45

Enamel Painting works ( one coat aster including two coat enamel ) per 100 M 2 (S.N.13-5,ka-Ga)
Tender Rate
Aster coat First coat
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 3.00 md 955.00 2865.00 5.00
2 Labour 3.00 md 700.00 2100.00 2.00
3 Aster 8.10 Lit 370.00 2997.00
4 Enamel Lit 490.00 9.00
5 Rate per 100 m2 7962.00
6 Total per m2 79.62
7 Tools & Plant @3% 2.39
8 Sub Total 82.01
9 Contractor's Overhead @15 % 12.30
10 Grand Total 94.31

Enamel Painting works ( one coat aster including two coat enamel ) per 100 M 2 (S.N.13-5-ka-Ga)
User's Rate
Aster coat First coat
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 3.00 md 955.00 2865.00 5.00
2 Labour 3.00 md 700.00 2100.00 2.00
3 Aster 8.10 kg 418.10 3386.61
4 Enamel kg 553.70 9.00
5 Rate per 100 m2 8351.61
6 Total per m2 83.52
7 Tools & Plant @3% 2.51
8 Sub Total 86.03
9 Contractor's Overhead @15 % 0.00
10 Grand Total 86.03
Wood work for chaukhat (sal wood) per M3 (S.N.10-1)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 34.00 md 955.00 32470.00 34.00
2 Labour 3.40 md 700.00 2380.00 3.40
3 Wood (sal) 1.10 m3 194230.67 213653.74 1.10
4 Screw 184.00 No 1.20 220.80 184.00
5 Hold fast 92.00 No 23.00 2116.00 92.00
6 Total per m3 250840.54
7 Tools & Plant @3% 7525.22
8 Sub Total 258365.76
9 Contractor's Overhead @15 % 38754.86
10 Grand Total 297120.62
Wood work for chaukhat (Local wood) per M3 (S.N.10-1)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 34.00 md 955.00 32470.00 34.00
2 Labour 3.40 md 700.00 2380.00 3.40
3 Wood 1.10 m3 51206.27 56326.90 1.10
4 Screw 184.00 No 1.20 220.80 184.00
5 Hold fast 92.00 No 23.00 2116.00 92.00
6 Total per m3 93513.70
7 Tools & Plant @3% 2805.41
8 Sub Total 96319.11
9 Contractor's Overhead @15 % 14447.87
10 Grand Total 110766.98
Sal Wood work for Beam per M3 (S.N.10,17)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 17.65 md 955.00 16855.75 17.65
2 Labour 1.76 md 700.00 1232.00 1.76
3 Wood 1.05 m3 194230.67 203942.20 1.05
4 Screw L/S 80.00 L/S
5 Total per m3 222109.95
6 Tools & Plant @3% 6663.30
7 Sub Total 228773.25
8 Contractor's Overhead @15 % 34315.99
9 Grand Total 263089.24

Local Wood work for Beam per M3 (S.N. 10,17)


Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 17.65 md 955.00 16855.75 17.65
2 Labour 1.76 md 700.00 1232.00 1.76
3 Wood 1.05 m3 51206.27 53766.58 1.05
4 Screw L/S 80.00 L/S
5 Total per m3 71934.33
6 Tools & Plant @3% 2158.03
7 Sub Total 74092.36
8 Contractor's Overhead @15 % 11113.85
9 Grand Total 85206.21
Sal Wood work for 38mm Pannalled Shutter per m2 (S.N.10,2)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 10.00 md 955.00 9550.00 10.00
2 Labour 1.00 md 700.00 700.00 1.00
3 Wood 0.08 m 194230.67
3
15538.45 0.08
4 Glass (4mm plain) m2 850.00
5 Hinge 100mm 6.00 No 48.00 288.00 6.00
6 Chheskini 300mm 1.00 No 115.00 115.00 1.00
7 Chheskini 150mm 1.00 No 60.00 60.00 1.00
8 Locking set 250mm 1.00 No 200.00 200.00 1.00
9 Handle 2.00 No 55.00 110.00 2.00
10 Screw L/s 80.00
11 Listic Mtr 12.00
12 26 gauge plain sheet m 2
445.00
13 Rate per 2.114m2 26641.45
14 Sub Total 12602.39
15 Tools & Plant @3% 378.07
16 Rate per m2 12980.46
17 Contractor's Overhead @15 % 1947.07
18 Grand Total 14927.53
Local Wood work for 38mm Pannalled Shutter m2 (S.N.10,2)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 10.00 md 955.00 9550.00 10.00
2 Labour 1.00 md 700.00 700.00 1.00
3 Wood 0.08 m3 51206.27 4096.50 0.08
4 Glass (4mm plain) m2 850.00
5 Hinge 100mm 6.00 No 48.00 288.00 6.00
6 Chheskini 300mm 1.00 No 115.00 115.00 1.00
7 Chheskini 150mm 1.00 No 60.00 60.00 1.00
8 Locking set 250 mm 1.00 No 200.00 200.00 1.00
9 Handle 2.00 No 55.00 110.00 2.00
10 Screw L/s 80.00
11 Listic m 12.00
12 26 gauge plain sheet m2 445.00
13 Rate per 2.114m2 15199.50
14 Rate per m2 7189.92
15 Tools & Plant @3% 215.70
16 Sub Total 7405.62
17 Contractor's Overhead @15 % 1110.84
18 Grand Total 8516.46
4mm thick glass Shutter (Sal wood) per m2 (S.N.10,4)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 9.00 md 955.00 8595.00 9.00
2 Labour 0.90 md 700.00 630.00 0.90
3 Wood 0.05 m 194230.67
3
9711.53 0.05
4 Glass (4mm plain) 1.09 m2 850.00 926.50 1.09
5 Hinge 75mm 8.00 No 48.00 384.00 8.00
6 Chheskini 300mm No 115.00 0.00
7 Chheskini 100mm 4.00 No 60.00 240.00 4.00
8 Locking set No 200.00 0.00
9 Handle 2.00 No 55.00 110.00 2.00
10 Screw L/s 40.00
11 Listic m 12.00
12 26 gauge plain sheet m 2
445.00
13 Rate per 2.23m2 20637.03
14 Rate per m2 9254.27
15 Tools & Plant @3% 277.63
16 Sub Total 9531.90
17 Contractor's Overhead @15 % 1429.79
18 Grand Total 10961.69

4mm thick glass Shutter (Local wood) per m2 (S.N.10,4)


Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 9.00 md 955.00 8595.00 9.00
2 Labour 0.90 md 700.00 630.00 0.90
3 Wood 0.05 m3 51206.27 2560.31 0.05
4 Glass (4mm plain) 1.09 m2 850.00 926.50 1.09
5 Hinge 8.00 No 48.00 384.00 8.00
6 Chheskini 300mm No 115.00 0.00
7 Chheskini 100mm 4.00 No 60.00 240.00 4.00
8 Locking set No 200.00 0.00
9 Handle 2.00 No 55.00 110.00 2.00
10 Screw L/s 40.00
11 Listic m 12.00
12 26 gauge plain sheet m2 445.00
13 Rate per 2.23m2 13485.81
14 Rate per m2 6047.45
15 Tools & Plant @3% 181.42
16 Sub Total 6228.87
17 Contractor's Overhead @15 % 934.33
18 Grand Total 7163.20

GI Plain sheet Shutter ( Local wood ) per m2 (S.N.10,9)


Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 7.00 md 955.00 6685.00 7.00
2 Labour 0.70 md 700.00 490.00 0.70
3 Wood 0.03 m3 51206.27 1536.19 0.03
4 Glass (4mm plain) m2 850.00 0.00 0.00
5 Hinge 100mm 3.00 No 48.00 144.00 3.00
6 Chheskini 300mm No 115.00 0.00
7 Chheskini 150mm 2.00 No 60.00 120.00 2.00
8 Locking set 1.00 No 200.00 200.00 1.00
9 Handle 1.00 No 55.00 55.00 1.00
10 Screw L/s 60.00
11 Listic m 12.00
12 26 gauge plain sheet 4.65 m2 445.00 2069.25 4.65
13 Rate per 2.245 m2 11359.44
14 Sub Total 5059.88
15 Tools & Plant @3% 151.80
16 Rate per m2 5211.68
17 Contractor's Overhead @15 % 781.75
18 Grand Total 5993.43

4mm thick glass Shutter fix with listic per m2 (S.N.10,11 Kha)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 0.06 md 955.00 57.30 0.06
2 Labour 0.01 md 700.00 7.00 0.01
3 Wood m3 51206.27 0.00 0.00
4 Glass (4mm plain) 1.00 m2 850.00 850.00 1.00
5 Hinge No 48.00 0.00 0.00
6 Chheskini 300mm No 115.00 0.00
7 Chheskini 150mm No 60.00 0.00 0.00
8 Locking set No 200.00 0.00
9 Handle No 55.00 0.00 0.00
10 Screw L/s 40.00
11 Listic 4.05 m 12.00 48.60 4.05
12 26 gauge plain sheet m2 445.00
14 Rate per m2 1002.90
15 Tools & Plant @3% 30.09
16 Sub Total 1032.99
17 Contractor's Overhead @15 % 154.95
18 Grand Total 1187.94

Local Wood work for 38mm mosquito proof wire mesh Shutter (S.N.10,10)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 5.00 md 955.00 4775.00 5.00
2 Labour 0.50 md 700.00 350.00 0.50
3 Wood 0.03 m3 51206.27 1536.19 0.03
4 Wire mesh 2.13 m2 152.00 323.76 2.13
5 Spring 1.00 No 218.00 218.00 1.00
6 Hinge 100mm 3.00 No 48.00 144.00 3.00
7 Chheskini 150mm 2.00 No 60.00 120.00 2.00
8 Nails L/S 30.00
9 Handle 2.00 No 55.00 110.00 2.00
13 Rate per 2.245m2 7606.95
14 Rate per m2 3388.40
15 Tools & Plant @3% 101.65
16 Sub Total 3490.05
17 Contractor's Overhead @15 % 523.51
18 Grand Total 4013.56

Local Wood work for 38mm freame flush Shutter including 3mm ply wood on both sides per m2 (S.N.10,7)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 7.00 md 955.00 6685.00 7.00
2 Labour 0.70 md 700.00 490.00 0.70
3 Wood 0.03 m3 51206.27 1536.19 0.03
4 Commercial Ply wood,3mm thick 4.65 m2 265.00 1232.25 4.65
5 Mortis lock 1.00 No 535.00 535.00 1.00
6 Hinge 100mm 3.00 No 48.00 144.00 3.00
7 Chheskini 150mm 2.00 No 60.00 120.00 2.00
8 Nails L/S 30.00
9 Handle 1.00 No 55.00 55.00 1.00
13 Rate per 2.245m2 10827.44
14 Rate per m2 4822.91
15 Tools & Plant @3% 144.69
16 Sub Total 4967.60
17 Contractor's Overhead @15 % 745.14
18 Grand Total 5712.74

26 Gauge CGI sheet roofing work per 10 m2 (S.N.9,1)(non colour)


Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.10 md 955.00 1050.50 1.10
2 Labour 1.25 md 700.00 875.00 1.25
3 26 gauge CGI sheet 12.00 m2 406.75 4881.00 12.00
4 8mm Bolt nut 30.00 No 18.00 540.00 30.00
5 J-Hook 25.00 No 13.00 325.00 25.00
6 Bitumen washer 55.00 No 1.50 82.50 55.00
7 Total 7754.00
8 Tools & Plant @3% 232.62
9 Total per 10 m2 7986.62
10 Sub Total 798.66
11 Contractor's Overhead @15 % 119.80
12 Grand Total 918.46

26 Gauge CGI sheet roofing work per 10 m2 (S.N.9,1)Colour


Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.10 md 955.00 1050.50 1.10
2 Labour 1.25 md 700.00 875.00 1.25
3 26 gauge CGI sheet 12.00 rm 508.43 6101.16 12.00
4 8mm Bolt nut 30.00 No 18.00 540.00 30.00
5 J-Hook 25.00 No 13.00 325.00 25.00
6 Bitumen washer 55.00 No 1.50 82.50 55.00
7 Total 8974.16
8 Tools & Plant @3% 269.22
9 Total per 10 m2 9243.38
10 Sub Total 924.34
11 Contractor's Overhead @15 % 138.65
12 Grand Total 1062.99
26 Gauge Plain sheet for ridge 10 m2 (S.N.9,2 )(non colour)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 2.00 md 955.00 1910.00 2.00
2 Labour 3.00 md 700.00 2100.00 3.00
3 26 gauge Plain sheet 12.00 Rm 494.44 5933.28 12.00
4 Nut bolt L/S 50.00
5 Total 9993.28
6 Tools & Plant @3% 299.80
7 Total per 10 m2 10293.08
8 Sub Total 1029.31
9 Contractor's Overhead @15 % 154.40
10 Grand Total 1183.71
26 Gauge Plain sheet for ridge 10 m2 (S.N.9,2 )Colour
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 2.00 md 955.00 1910.00 2.00
2 Labour 3.00 md 700.00 2100.00 3.00
3 26 gauge Plain sheet 12.00 Rm 616.67 7400.04 12.00
4 Nut bolt L/S 50.00
5 Total 11460.04
6 Tools & Plant @3% 343.80
7 Total per 10 m2 11803.84
8 Sub Total 1180.38
9 Contractor's Overhead @15 % 177.06
10 Grand Total 1357.44
Site clearance work per m2 (S.N.1,3)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason md 955.00 0.00
2 Labour 0.04 md 700.00 28.00 0.04
3 Rate per M2 28.00
4 Tools & Plant @3% 0.84
5 Sub Total 28.84
6 Contractor's Overhead @15 % 4.33
7 Grand Total 33.17
Dismentalling of masonry in cement mortar (S.N..19,2)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 0.00 md 955.00 0.00 0.00
2 Labour 2.12 md 700.00 1484.00 2.12
3 Rate per M3 1484.00
4 Tools & Plant @3% 44.52
5 Sub Total 1528.52
6 Contractor's Overhead @15 % 229.28
7 Grand Total 1757.80
Dismentalling of RCC or RBC work per m3 (S.N..19,3)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 0.00 md 955.00 0.00 0.00
2 Labour 11.00 md 700.00 7700.00 11.00
3 Rate per M3 7700.00
4 Tools & Plant @3% 231.00
5 Sub Total 7931.00
6 Contractor's Overhead @15 % 1189.65
7 Grand Total 9120.65
Dismentalling of PCC work per m3 (S.N..19,3)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 0.00 md 955.00 0.00 0.00
2 Labour 4.00 md 700.00 2800.00 4.00
3 Rate per M3 2800.00
4 Tools & Plant @3% 84.00
5 Sub Total 2884.00
6 Contractor's Overhead @15 % 432.60
7 Grand Total 3316.60
Dismentalling of Plastering work per m2 (S.N..19,3)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 0.00 md 955.00 0.00 0.00
2 Labour 0.11 md 700.00 77.00 0.11
3 Rate per M2 77.00
4 Tools & Plant @3% 2.31
5 Sub Total 79.31
6 Contractor's Overhead @15 % 11.90
7 Grand Total 91.21

Concrete Block Masonary work in 1:4 mortar per M3


Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.50 md 955.00 1432.50 1.50
2 Labour 3.25 md 700.00 2275.00 3.25
3 Cement 2.00 bag 790.00 1580.00 2.00
4 Sand 0.28 m3 1550.00 434.00 0.28
5 Concrete Block (6"*8"*16") 84.00 nos. 55.00 4620.00 84.00
7 Total 10341.50
8 Tools & Plant @3% 310.25
9 Sub Total 10651.75
10 Contractor's Overhead @15 % 1597.76
11 Grand Total 12249.51
HDPE pipe laying & jointing works for50 m(63mm,75mm&90mm dia)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Plumber 1.00 md 900.00 900.00 1.00
2 Helper 1.00 md 570.00 570.00 1.00
3 Labour 2.00 md 700.00 1400.00 2.00
Total of labour 2870.00
4 Fuel petrol 0.05 lit 100.00 5.00 0.05
4 Miscellaneous 2.51% of labour 72.04
5 Total 5817.04
6 Tools & Plant @3% 0.00
7 Total per 50 m 5817.04
8 Sub Total 116.34
9 Contractor's Overhead @15 % 17.45
10 Grand Total 133.79
HDPE pipe laying & jointing works for50 m(140mm,160mm&180mm dia)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Plumber 2.00 md 900.00 1800.00 2.00
2 Helper 2.00 md 570.00 1140.00 1.00
3 Labour 4.00 md 700.00 2800.00 4.00
Total of labour 5740.00
4 Fuel petrol 1.00 lit 100.00 100.00 1.00
4 Miscellaneous 2.51% of labour 144.07
5 Total 11724.07
6 Tools & Plant @3% 0.00
7 Total per 50 m 11724.07
8 Sub Total 234.48
9 Contractor's Overhead @15 % 35.17
10 Grand Total 269.65
HDPE pipe laying & jointing works for1000m(32mm dia)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Plumber 1.00 md 900.00 900.00 1.00
2 Helper 1.00 md 570.00 570.00 1.00
3 Labour 3.00 md 700.00 2100.00 3.00
Total of labour 3570.00
4 Fuel petrol 0.25 lit 100.00 25.00 0.25
4 Miscellaneous 2.51% of labour 89.61
5 Total 7254.61
6 Tools & Plant @3% 0.00
7 Total per 50 m 7254.61
8 Sub Total 7.25
9 Contractor's Overhead @15 % 1.09
10 Grand Total 8.34

Plum Concrete works in 40% / 60% Mass Concrete including Boulder cleaning works.(P.C.C. in 1:3:6),(60% Concrete & 40% Boulder ston
Norms No. 7(a),41 &25(14), 251 (60% Concrete & 40% Boulder stone)
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 0.30 md 955.00 286.50 0.30
2 Labour 4.00 md 700.00 2800.00 4.00
3 Cement 4.40 Bag 790.00 3476.00 4.40
4 Sand 0.47 m 3
1550.00 728.50 0.47
5 Boulder stone 0.14 m 3
1500.00 210.00 0.14
6 Stone aggregate (20 mm) 0.60 m 3
1850.00 1110.00 0.60
7 Stone aggregate (10 mm) 0.20 m3 1850.00 370.00 0.20
8 Total 8981.00
9 Tools & Plant @3% 269.43
10 Sub Total 9250.43
11 Contractor's Overhead @15 % 1387.56
12 Grand Total 10637.99

Making & fixing 3*20 mm iron gril including one coat Red oxide paint after rubbing with sand paper.
Norms No. 24/1(a), 238
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 iron gril including labour cost. 10.00 Sqm 2695.38 26953.80 10.00
8 Total 26953.80
9 Tools & Plant @3% 808.61
10 Sub Total 2776.24
11 Contractor's Overhead @15 % 416.44
12 Grand Total 3192.68

Making & fixing of rolling shutter including one coat red oxide paint after rubbing with sand paper .
Norms No. 24/1(a), 238
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
18-20 gauge iron shutter including
1 labour cost. 10.00 Sqm 2730.00 27300.00 10.00
8 Total 27300.00
9 Tools & Plant @3% 819.00
10 Sub Total 2811.90
11 Contractor's Overhead @15 % 421.79
12 Grand Total 3233.69

Making & fixing of collapsiable channel gate including one coat red oxide paint after rubbing with sand paper.
Norms No. 24/1(a), 238
Tender Rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity

1 channel gate including labour cost 10.00 Sqm 4750.00 47500.00 10.00
8 Total 47500.00
9 Tools & Plant @3% 1425.00
10 Sub Total 4892.50
11 Contractor's Overhead @15 % 733.88
12 Grand Total 5626.38

Barbed wire fencing work (14*14*8 m.m)


Norms No. 24/1(a), 238
unit per m User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.08 md 870.00 939.60 1.08
2 Labour 5.38 md 650.00 3497.00 5.38
3 G.I bared wire 110.00 kg 10.50 1155.00 110.00
4 Nails/hooks ls 40.00 0.00
8 Total 5631.60
9 Tools & Plant @3% 168.95
10 Sub Total 5800.55
11 Contractor's Overhead @15 % 870.08
12 Grand Total 6670.63

Barbed wire fencing work (12*12*8 m.m) unit: per m


Norms No. 24/1(a), 238
Tender rate User's Rate
S.N Description Quantity Unit Rate Amount Quantity
1 Mason 1.08 md 870.00 939.60 1.08
2 Labour 5.38 md 650.00 3497.00 5.38
3 G.I bared wire 110.00 kg 13.13 1444.30 110.00
4 Nails/hooks ls 40.00
8 Total 5920.90
9 Tools & Plant @3% 177.63
10 Sub Total 6098.53
11 Contractor's Overhead @15 % 914.78
12 Grand Total 7013.31

22. ITEM Laying, fitting and fixing of hume pipe having a dia. 60cm for 5 m length.
UNIT 5 R.M.
S.N. 47 Resp. Clause of Spec. 15-5 and 15-6
Source Type Quntity unit Rate Amount Total(Rs)
Labour Skilled 0.25 M-day 870.00 217.50 217.50
Unskilled 1.00 M-day 650.00 650.00 650.00
Construction Hume pipe 600 mm NP3 1.00 No. 38632.44 38632.44 38632.44
Materials Cement 0.02 MT 17854.00 357.08 357.08
Sand 0.02 m3 1550.00 31.00 31.00
Jute 12.50 Kg. 106.22 1327.75 1327.75
Bitumen 2.50 Kg. 81.36 203.40 203.40
Actual Rate 41419.17
Tools, Plants & Equipments @ 3% 1242.58
Sub Total 42661.75
Rate per 5m 42661.75
Rate per m 8532.35

23. ITEM Laying, fitting and fixing of hume pipe having a dia. 90cm for 5 m length.
UNIT 5 R.M.
S.N. 47 Resp. Clause of Spec. 15-5 and 15-6
Source Type Quntity unit Rate Amount Total(Rs)
Labour Skilled 0.75 M-day 870.00 652.50 652.50
Unskilled 2.50 M-day 650.00 1625.00 1625.00
Construction Hume pipe 900 mm NP3 1.00 No. 70478.10 70478.10 70478.10
Materials Cement 0.03 MT 17854.00 535.62 535.62
Sand 0.05 cu.m 1550.00 77.50 77.50
Jute 20.00 Kg. 106.22 2124.40 2124.40
Bitumen 5.00 Kg. 81.36 406.80 406.80
Actual Rate 75899.92
Tools, Plants & Equipments @ 3% 2277.00
Sub Total for 5 m 78176.92
Rate per 5 m 78176.92
Rate per m 15635.38

18.ITEM Fabrication of gabion boxes including rolling, cutting and weaving


A. Hexagonal Mesh Size -100mm. X 120mm. Box size (m×m×m)
UNIT: Cu.m. a. 2X1X1
S.N. 44.1 Resp. Clause of Spec. 17-1.4, 17-5 & 17-6
Source Type Quntity unit Rate Amount Total(Rs)
Labour Skilled 0.39 M-day 870.00 339.30 339.30
Unskilled 0.20 M-day 650.00 130.00 130.00
Construction Mesh Wire (10SWG) 23.43 Kg. 113.00 2647.59 2647.59
Materials Salvage wire (8SWG) 2.88 Kg. 113.00 325.44 325.44
Actual Rate 3442.33
Tools, Plants & Equipments @ 3% 103.27
Sub Total 3545.60
Rate per m3 1772.80
Rate per box 3545.60
19. ITEM Assembling of wire crates/gabion/revetment and placing them in position including
a) 2X1X1
UNIT box
S.N. 44.2 Resp. Clause of Spec. 17-1.4,17-5 & 17-6
Source Type Quntity unit Rate Amount Total(Rs)
Labour Skilled
Unskilled 0.090 M-day 650.00 58.50 58.50
Construction
Materials Binding Wire (12SWG) 0.95 Kg. 116.39 110.57 110.57
Actual Rate 169.07
Tools, Plants & Equipments @ 3% 5.07
Sub Total 174.14
Rate per m3 87.07

20. ITEM Packing and filling of gabion craties with rubble stones.
UNIT Cu m.
S.N. 45 Resp. Clause of Spec. 17-1.4,17-5 & 17-6
Source Type Quntity unit Rate Amount Total(Rs)
Labour Skilled 0.30 M-day 870.00 261.00 261.00
Unskilled 0.75 M-day 650.00 487.50 487.50
Materials
Construction Boulder 1.10 m3 1500.00 1650.00 1650.00
Actual Rate 2398.50
Tools, Plants & Equipments @ 3% 71.96
Sub Total 2470.46
Rate per m3 2470.46
Rate per box 4940.92
Total Gabion works all comp. / m3 4330.33
Total Gabion works all comp. / box 8660.66

Item: Flooring Works


A-1 1" thick 1:2:4 Cement Concrete floor Carting including finishing by
Norms No. 11/1(a), 96
Unit 10 Sqm
Particular Description Unit Quantity Rate Amount
Labour Skilled Md 1.10 0.00 0.00
Unskilled Md 1.50 0.00 0.00
Material cement(N.S.) M.T. 0.090 0.00 0.00
sand(Crusher
screen) Cu.m 0.120 0.00 0.00
Aggregate 12
mm M.T. 0.230 0.00 0.00
Sub-Total 0.00
Tools & Plants @ 3% 0.00
Sub-Total (Dept. Rate) 0.00
Contractor's Profit @ 1 0.00
Sub-Total 0.00
Grand Total (Cont. Rat 0.00

A-2 2" thick 1:2:4 Cement Concrete floor Carting including finishing by
Norms No. 11/1(c), 96
Unit 10 Sqm
Particular Description Unit Quantity Rate Amount
Labour Skilled Md 1.25 0.00 0.00
Unskilled Md 2.50 0.00 0.00
Material cement(N.S.) M.T. 0.170 0.00 0.00
sand(Crusher
screen) Cu.m 0.230 0.00 0.00
Aggregate 20
mm M.T. 0.460 0.00 0.00
Sub-Total 0.00
Tools & Plants @ 3% 0.00
Sub-Total (Dept. Rate) 0.00
Contractor's Profit @ 1 0.00
Sub-Total 0.00
Grand Total (Cont. Rat 0.00

A-3 3" thick 1:2:4 Cement Concrete floor Carting including finishing by
Norms No. 11/1(d), 97
Unit 10 Sqm
Particular Description Unit Quantity Rate Amount
Labour Skilled Md 1.25 0.00 0.00
Unskilled Md 3.00 0.00 0.00
Material cement(N.S.) M.T. 0.260 0.00 0.00
sand(Crusher
screen) Cu.m 0.340 0.00 0.00
Aggregate 20
mm M.T. 0.680 0.00 0.00
Sub-Total 0.00
Tools & Plants @ 3% 0.00
Sub-Total (Dept. Rate) 0.00
Contractor's Profit @ 1 0.00
Sub-Total 0.00
Grand Total (Cont. Rat 0.00
25 mm th.mosaic flooring with 12.5mm th cement plaster (1:2) base course & 6
B cement (1:1) surface course including rubbing & polis
Norms No. 11/3, 99
Unit 10 Sqm
Particular Description Unit Quantity Rate Amount
Labour Skilled Md 3.50 0.00 0.00
Unskilled Md 36.00 0.00 0.00
Cement
Material ( Nepali ) M.T. 0.121 0.00 0.00
sand(Crusher
screen) Cu.m 0.165 0.00 0.00
white cement M.T. 0.069 42000.00 2898.00
3mm marble
chips Cu.m 0.047 9000.00 423.00
oxalic acid kg 0.340 269.00 91.46
mein polish kg 0.110 445.00 48.95
terpaintain lit 0.500 100.00 50.00
rubbing stone L.S. 60.00
Sub-Total 3571.41
Tools & Plants @ 3% 107.14
Sub-Total (Dept. Rate) 3678.55
Contractor's Profit @ 1 551.78
Sub-Total 4230.33
Grand Total (Cont. Rat 4230.33
20 mm th.mosaic (Terrajo Tile) flooring with 20 mm th cement plaster (1:4)
B-1 base course including rubbing & polishing
Norms No. 11/5, 101
Unit 10 Sqm
Particular Description Unit Quantity Rate Amount
Labour Skilled Md 2.00 0.00 0.00
Unskilled Md 12.60 0.00 0.00
Cement(N.S.
Material marks) M.T. 0.081 0.00 0.00
sand (Crusher
screen) Cu.m 0.220 0.00 0.00
Mosaic(terrajo)
tile sqm 11.000 800.00 8800.00
oxalic acid kg 0.370 269.00 99.53
mein polish kg 0.118 445.00 52.51
terpaintain lit 0.538 100.00 53.80
rubbing stone L.S. 60.00
Rubbinng
Equipment Labour md 13.500 0.00 0.00
Sub-Total 9065.84
Tools & Plants @ 3% 271.98
Sub-Total (Dept. Rate) 9337.82
Contractor's Profit @ 1 1400.67
Sub-Total 10738.49
Grand Total (Cont. Rat 10738.49

25 mm th. marble with cement sand (1:2) surface course including rubbing &
C polishing
Norms No. 11/6, 102
Unit 10 Sqm
Particular Description Unit Quantity Rate Amount
Labour Skilled Md 2.00 0.00 0.00
Unskilled Md 21.50 0.00 0.00
Cement(N.S.
Material marks) M.T. 0.031 0.00 0.00
sand (Crusher
screen) Cu.m 0.183 0.00 0.00
2 5 mm thick
marble sqm 11.000 2500.00 27500.00
oxalic acid kg 0.370 269.00 99.53
mein polish kg 0.118 445.00 52.51
terpaintain lit 0.538 100.00 53.80
rubbing stone L.S. 60.00
Sub-Total 27765.84
Tools & Plants @ 3% 832.98
Sub-Total (Dept. Rate) 28598.82
Contractor's Profit @ 1 4289.82
Sub-Total 32888.64
Grand Total (Cont. Rat 32888.64

D 25 mm th. granaite with cement sand (1:2) surface course including r


Norms No. 11/6, 102
Unit 10 Sqm
Particular Description Unit Quantity Rate Amount
Labour Skilled Md 2.00 0.00 0.00
Unskilled Md 21.50 0.00 0.00
Cement(N.S.
Material marks) M.T. 0.031 0.00 0.00
sand (Crusher
screen) Cu.m 0.183 0.00 0.00
15 mm thick
granaite sqm 11.000 4850.00 53350.00
oxalic acid kg 0.370 269.00 99.53
mein polish kg 0.118 445.00 52.51
terpaintain lit 0.538 100.00 53.80
rubbing stone L.S. 60.00
Sub-Total 53615.84
Tools & Plants @ 3% 1608.48
Sub-Total (Dept. Rate) 55224.32
Contractor's Profit @ 1 8283.65
Sub-Total 63507.97
Grand Total (Cont. Rat 63507.97

E Porcelain glazed tile flooring in 1:4 cement sand mor


i In Wall
Norms No. 11/7, 103
Unit 10 Sqm
Particular Description Unit Quantity Rate Amount
Labour Skilled Md 13.00 0.00 0.00
Unskilled Md 4.50 0.00 0.00
Cement(N.S.
Material marks) M.T. 0.056 0.00 0.00
sand (Crusher
screen) Cu.m 0.152 0.00 0.00
Porcelain white
glazed tile sqm 11.000 764.24 8406.64
white cement kg 3.228 42.00 135.57
Sub-Total 8542.21
Tools & Plants @ 3% 256.27
Sub-Total (Dept. Rate) 8798.48
Contractor's Profit @ 1 1319.77
Sub-Total 10118.25
Grand Total (Cont. Rat 10118.25

ii In Floor
Norms No. 11/7, 103
Unit 10 Sqm
Particular Description Unit Quantity Rate Amount
Labour Skilled Md 13.00 0.00 0.00
Unskilled Md 4.50 0.00 0.00
Material Cement(N.S. markM.T. 0.056 0.00 0.00
sand (Crusher scrCu.m 0.152 0.00 0.00
Porcelain white
glazed tile sqm 11.000 764.24 8406.64
white cement kg 3.228 42.00 135.57
Sub-Total 8542.21
Tools & Plants @ 3% 256.27
Sub-Total (Dept. Rate) 8798.48
Contractor's Profit @ 1 1319.77
Sub-Total 10118.25
Grand Total (Cont. Rat 10118.25

F 37.5 mm th Flagstone paving in 1:4 cement sand mortar


Norms No. 11/9, 104
Unit 10 Sqm
Particular Description Unit Quantity Rate Amount
Labour Skilled Md 2.00 0.00 0.00
Unskilled Md 4.50 0.00 0.00
Material Cement(N.S. markM.T. 0.060 0.00 0.00
sand (Crusher scrCu.m 0.165 0.00 0.00
Flag stone Sqm 11.000 902.00 9922.00
Sub-Total 9922.00
Tools & Plants @ 3% 297.66
Sub-Total (Dept. Rate) 10219.66
Contractor's Profit @ 1 1532.95
Sub-Total 11752.61
Grand Total (Cont. Rat 11752.61

G Brick ballast filling works.


Unit 10 Cu. M.
Particular Description Unit Quantity Rate Amount
Labour Skilled Md 10.00 0.00 0.00
Material Brick ballast Cu.M. 11.00 2600.00 28600.00
Sub-Total 28600.00
Tools & Plants @ 3% 858.00
Sub-Total (Dept. Rate) 29458.00
Contractor's Profit @ 1 4418.70
Sub-Total 33876.70
Grand Total (Cont. Rat 33876.70
Fiscal Year:-2074/075

User's Rate Remarks


Rate Amount
650.00 455.00
13.65
468.65

User's Rate Remarks


Rate Amount
650.00 520.00
15.60
535.60

User's Rate Remarks


Rate Amount
650.00 1950.00
58.50
2008.50

User's Rate Remarks


Rate Amount
650.00 3250.00
97.50
3347.50

User's Rate Remarks


Rate Amount
650.00 15730.00
471.90
16201.90
User's Rate Remarks
Rate Amount
650.00 650.00
19.50
669.50

, item no.10 )
User's Rate Remarks
Rate Amount
650.00 1625.00
48.75
1673.75

User's Rate Remarks


Rate Amount
650.00 1033.50
31.01
1064.51

(S.N. 2 item no.25 Ka )


User's Rate Remarks
Rate Amount
650.00 325.00
9.75
334.75

m3, (S.N. 2 item no.25 Kha )


User's Rate Remarks
Rate Amount
650.00 162.50
4.88
167.38

User's Rate Remarks


Rate Amount
650.00 910.00
27.30
937.30
User's Rate Remarks 10.83333
Rate Amount
870.00 870.00
650.00 1300.00
1500.00 1500.00
1500.00 150.00
3820.00
114.60
3934.60

User's Rate Remarks


Rate Amount
870.00 870.00
650.00 1462.50
1500.00 1500.00
1500.00 150.00
450.00 189.00
4171.50
125.15
4296.65

User's Rate Remarks


Rate Amount
870.00 1305.00
650.00 3250.00
892.70 2838.79
1550.00 697.50
1500.00 1500.00
1500.00 150.00
9741.29
292.24
10033.53

User's Rate Remarks


Rate Amount
870.00 1305.00
650.00 3250.00
892.70 1892.52
1550.00 728.50
1500.00 1500.00
1500.00 150.00
8826.02
264.78
9090.80

User's Rate Remarks


Rate Amount

650.00 975.00
1500.00 1650.00
0.00 0.00
2625.00
78.75
2703.75

User's Rate Remarks


Rate Amount
870.00 870.00
650.00 1105.00
892.70
1550.00
15.82 8859.20
450.00 189.00
11023.20
330.70
11353.90

User's Rate Remarks


Rate Amount
870.00 1305.00
650.00 1430.00
892.70 1785.40
1550.00 434.00
15.82 8859.20
450.00
13813.60
414.41
14228.01

User's Rate Remarks


Rate Amount
870.00 1305.00
650.00 1430.00
892.70 1249.78
1550.00 465.00
15.82 8859.20

13308.98
399.27
13708.25

User's Rate Remarks


Rate Amount
870.00 870.00
650.00 2600.00
892.70 3927.88
1550.00 728.50
1750.00 1137.50
1850.00 444.00
9707.88
291.24
9999.12

User's Rate Remarks


Rate Amount
955.00 955.00
700.00 2800.00
892.70 5713.28
1550.00 697.50
1750.00 910.00
1850.00 407.00
1850.00 203.50
11686.28
350.59
12036.87

User's Rate Remarks


Rate Amount
955.00 764.00
700.00 4900.00
892.70 7141.60
1550.00 666.50
1850.00 1054.50
1850.00 536.50
15063.10
451.89
15514.99

User's Rate Remarks


Rate Amount
955.00 764.00
700.00 4900.00
892.70 5713.28
1550.00 689.75
1750.00 910.00
1850.00 407.00
1850.00 203.50
13587.53
407.63
13995.16

User's Rate Remarks


Rate Amount
955.00 11460.00
700.00 8400.00
90400.00 94920.00
103.96 1039.60
115819.60
3474.59
119294.19
119.29
User's Rate Remarks
Rate Amount
955.00 1642.60
700.00 1799.00
8534.38 753.87 40611.8667
118.65 296.63 6768.64445
4492.10
134.76
4626.86
462.69

User's Rate Remarks


Rate Amount
955.00 11460.00
700.00 11200.00
892.70 11158.75
1550.00 1984.00
35802.75
358.03
10.74
368.77

User's Rate Remarks


Rate Amount
955.00 11460.00
700.00 11200.00
892.70 9605.45
1550.00 2263.00
34528.45
345.28
10.36
355.64

User's Rate Remarks


Rate Amount
955.00 11460.00
700.00 11200.00
892.70 6820.23
1550.00 2433.50
31913.73
319.14
9.57
328.71
User's Rate Remarks
Rate Amount
955.00 14325.00
700.00 14000.00
892.70 11158.75
1550.00 1984.00
41467.75
414.68
12.44
427.12

User's Rate Remarks


Rate Amount
955.00 14325.00
700.00 14000.00
892.70 9605.45
1550.00 2263.00
40193.45
401.93
12.06
413.99

User's Rate Remarks


Rate Amount
955.00 14325.00
700.00 14000.00
892.70 6820.23
1550.00 2433.50
37578.73
375.79
11.27
387.06

User's Rate Remarks


Rate Amount
955.00 13370.00
700.00 13300.00
892.70 17139.84
1550.00 3022.50
46832.34
468.32
14.05
482.37
User's Rate Remarks
Rate Amount
955.00 13370.00
700.00 13300.00
892.70 14461.74
1550.00 3410.00
44541.74
445.42
13.36
458.78

User's Rate Remarks


Rate Amount
955.00 13370.00
700.00 13300.00
892.70 10176.78
1550.00 3642.50
40489.28
404.89
12.15
417.04

User's Rate Remarks


Rate Amount
955.00 9550.00
700.00 9800.00
892.70 10926.65
1550.00 666.50
30943.15
309.43
9.28
318.71

User's Rate Remarks


Rate Amount
955.00 9550.00
700.00 9800.00
892.70 7284.43
1550.00 883.50
27517.93
275.18
8.26
283.44

User's Rate Remarks


Rate Amount
215.00 9550.00
700.00 9800.00
892.70 5463.32
1550.00 976.50
25789.82
257.90
7.74
265.64

User's Rate Remarks


Rate Amount
955.00 955.00
700.00 700.00
892.70 946.26
2601.26
260.13
7.80
267.93

User's Rate Remarks


Rate Amount
955.00 764.00
700.00 490.00
25.99 311.88
248.60 119.33
1685.21
16.85
0.51
17.36

Remarks
Rate Amount
955.00 1432.50
700.00 770.00
25.99 571.78
248.60 218.77
2993.05
29.93
0.90
30.83

User's Rate Remarks


Rate Amount
215.00 764.00
700.00 490.00
25.99 259.90
248.60 99.44
1613.34
16.13
0.48
16.61

User's Rate Remarks


Rate Amount
215.00 1910.00
700.00 1400.00
418.10 3344.80
6654.80
66.55
2.00
68.55

User's Rate Remarks


Rate Amount
215.00 1910.00
700.00 1400.00
316.40 2056.60
5366.60
53.67
1.61
55.28

User's Rate Remarks


Rate Amount
215.00 1719.00
700.00 1260.00
316.40 1582.00
4561.00
45.61
1.37
46.98

User's Rate Remarks


Rate Amount
955.00 1623.50
700.00 1190.00
158.20 4746.00
7559.50
75.60
2.27
77.87

User's Rate Remarks


Rate Amount
955.00 4775.00
700.00 3500.00
158.20 7672.70
15947.70
159.48
4.78
164.26

First coat Second coat


Amount Quantity Amount
4775.00 4.00 3820.00
1400.00 3.00 2100.00
418.10
4410.00 7.00 3430.00
11003.10 9350.00
110.03 93.50
3.30 2.81
113.33 96.31
17.00
130.33 96.31

First coat Second coat


Amount Quantity Amount
4775.00 4.00 3820.00
1400.00 3.00 2100.00
459.91
4983.30 7.00 3875.90
11618.21 9795.90
116.18 97.96
3.49 2.94
119.67 100.90

User's Rate Remarks


Rate Amount
955.00 32470.00
700.00 2380.00
194230.67 213653.74
1.36 250.24
25.99 2391.08
251145.06
7534.35
258679.41

User's Rate Remarks


Rate Amount
955.00 32470.00
700.00 2380.00
51206.27 56326.90
1.36 250.24
25.99 2391.08
93818.22
2814.55
96632.77

User's Rate Remarks


Rate Amount
955.00 16855.75
700.00 1232.00
194230.67 203942.20
90.40
222120.35
6663.61
228783.96

User's Rate Remarks


Rate Amount
955.00 16855.75
700.00 1232.00
51206.27 53766.58
90.40
71944.73
2158.34
74103.07

User's Rate Remarks


Rate Amount
200.00 9550.00
140.00 700.00
194230.67 15538.45
960.50
54.24 325.44
129.95 129.95
67.80 67.80
226.00 226.00
62.15 124.30
90.40
12.00
502.85
26752.34
12654.84
379.65
13034.49

User's Rate Remarks


Rate Amount
955.00 9550.00
700.00 700.00
51206.27 4096.50
960.50
54.24 325.44
129.95 129.95
67.80 67.80
226.00 226.00
226.00 452.00
90.40
12.00
502.85
15638.09
7397.39
221.92
7619.31

User's Rate Remarks


Rate Amount
955.00 8595.00
700.00 630.00
194230.67 9711.53
960.50 1046.95
54.24 433.92
129.95
67.80 271.20
226.00
62.15 124.30
45.20
12.00
502.85
20858.10
9353.41
280.60
9634.01

User's Rate Remarks


Rate Amount
955.00 8595.00
700.00 630.00
51206.27 2560.31
960.50 1046.95
54.24 433.92
129.95
67.80 271.20
226.00
62.15 124.30
45.20
12.00
502.85
13706.88
6146.58
184.40
6330.98

User's Rate Remarks


Rate Amount
955.00 6685.00
700.00 490.00
51206.27 1536.19
960.50 0.00
54.24 162.72
129.95
67.80 135.60
226.00 226.00
62.15 62.15
67.80
12.00
502.85 2338.25
11703.71
5213.23
156.40
5369.63

User's Rate Remarks


Rate Amount
955.00 57.30
700.00 7.00
51206.27 0.00
960.50 960.50
54.24 0.00
129.95
67.80 0.00
226.00
62.15 0.00
45.20
13.56 54.92
502.85
1124.92
33.75
1158.67

User's Rate Remarks


Rate Amount
955.00 4775.00
700.00 350.00
51206.27 1536.19
171.76 365.85
246.34 246.34
54.24 162.72
67.80 135.60
33.90
62.15 124.30
7729.90
3443.16
103.29
3546.45
User's Rate Remarks
Rate Amount
955.00 6685.00
700.00 490.00
51206.27 1536.19
299.45 1392.44
604.55 604.55
54.24 162.72
67.80 135.60
L/S 33.90
62.15 62.15
11102.55
4945.46
148.36
5093.82

User's Rate Remarks


Rate Amount
955.00 1050.50
700.00 875.00
459.63 5515.56
20.34 610.20
14.69 367.25
1.70 93.50
8512.01
255.36
8767.37
876.74

User's Rate Remarks


Rate Amount
955.00 1050.50
700.00 875.00
574.53 6894.36
20.34 610.20
14.69 367.25
1.70 93.50
9890.81
296.72
10187.53
1018.75

User's Rate Remarks


Rate Amount
955.00 1910.00
700.00 2100.00
558.72 6704.64 489.5
L/S 56.50
10771.14
323.13
11094.27
1109.43

User's Rate Remarks


Rate Amount
955.00 1910.00
700.00 2100.00
696.84 8362.08
L/S 56.50
12428.58
372.86
12801.44
1280.14

User's Rate Remarks


Rate Amount
955.00 0.00
700.00 28.00
28.00
0.84
28.84

User's Rate Remarks


Rate Amount
955.00 0.00
700.00 1484.00
1484.00
44.52
1528.52

User's Rate Remarks


Rate Amount
955.00 0.00
700.00 7700.00
7700.00
231.00
7931.00
User's Rate Remarks
Rate Amount
955.00 0.00
700.00 2800.00
2800.00
84.00
2884.00

User's Rate Remarks


Rate Amount
955.00 0.00
700.00 77.00
77.00
2.31
79.31

User's Rate Remarks


Rate Amount
955.00 1432.50
700.00 2275.00
892.70 1785.40
1550.00 434.00
62.15 5220.60
11147.50
334.43
11481.93

User's Rate Remarks


Rate Amount
900.00 900.00
570.00 570.00
700.00 1400.00
2870.00
113.00 5.65
72.04
5817.69
0.00
5817.69
116.35

User's Rate Remarks


Rate Amount
900.00 1800.00
570.00 570.00
700.00 2800.00
5740.00
113.00 113.00
144.07
11167.07
0.00
11167.07
223.34

User's Rate Remarks


Rate Amount
900.00 900.00
570.00 570.00
700.00 2100.00
3570.00
113.00 28.25
89.61
7257.86
0.00
7257.86
7.26

% Concrete & 40% Boulder stone)


oulder stone)
User's Rate Remarks
Rate Amount
955.00 286.50
700.00 2800.00
892.70 3927.88
1550.00 728.50
1500.00 210.00
1850.00 1110.00
1850.00 370.00
9432.88
282.99
9715.87

User's Rate Remarks


Rate Amount
2695.38 26953.80 1
26953.80 Sq.m.=16.14
808.61 kg
1
Sq.m.=16.14
kg

2776.24

User's Rate Remarks


Rate Amount

2730.00 27300.00 1
Sq.m.=16.14
27300.00 kg
819.00
2811.90

User's Rate Remarks


Rate Amount

4750.00 47500.00 1
Sq.m.=16.14
47500.00 kg
1425.00
4892.50

User's Rate Remarks


Rate Amount
870.00 939.60
650.00 3497.00
11.87 1305.70
1 kg = 10 m
40.00
5782.30
173.47
5955.77

User's Rate Remarks


Rate Amount
870.00 939.60
650.00 3497.00
14.84 1632.40
1 kg = 8 m
40.00
6109.00
183.27
6292.27
Tender rate
Quntity unit Rate Amount Total(Rs)
0.25 M-day 870.00 217.50 217.50
1.00 M-day 650.00 650.00 650.00
1.00 No. 34188.00 34188.00 34188.00
0.02 MT 15800.00 316.00 316.00
0.02 m3 1550.00 31.00 31.00
12.50 Kg. 94.00 1175.00 1175.00 0.5474026
2.50 Kg. 72.00 180.00 180.00
Actual Rate 36757.50 1428571
Tools, Plants & Equipments @ 3% 1102.73
Sub Total 37860.23
Rate per 5m 37860.23
Rate per m 7572.05
Contractor's Overhead @15 % 1135.8075
Grand Total 8707.86

Quntity unit Rate Amount Total(Rs)


0.75 M-day 870.00 652.50 652.50
2.50 M-day 650.00 1625.00 1625.00
1.00 No. 62370.00 62370.00 62370.00
0.03 MT 15800.00 474.00 474.00
0.05 cu.m 1550.00 77.50 77.50
20.00 Kg. 94.00 1880.00 1880.00
5.00 Kg. 72.00 360.00 360.00
Actual Rate 67439.00
Tools, Plants & Equipments @ 3% 2023.17
Sub Total 69462.17
Rate per 5m 69462.17
Rate per m 13892.43
Contractor's Overhead @15 % 2083.8645
Grand Total 15976.29

Quntity unit Rate Amount Total(Rs)


0.39 M-day 870.00 339.30 339.30
0.20 M-day 650.00 130.00 130.00
23.43 Kg. 100 2343.00 2343.00
2.88 Kg. 100 288.00 288.00
Actual Rate 3100.30
Tools, Plants & Equipments @ 3% 93.01
Sub Total 3193.31
Rate per m3 1596.66
Rate per box 3193.32
Contractor's Overhead @15 % 239.499
Grand Total 1836.16

Quntity unit Rate Amount Total(Rs)

0.090 M-day 650.00 58.50 58.50


0.95 Kg. 103 97.85 97.85

Actual Rate 156.35


Tools, Plants & Equipments @ 3% 4.69
Sub Total 161.04
Rate per m3 80.52
Contractor's Overhead @15 % 12.08
Grand Total 92.60

Quntity unit Rate Amount Total(Rs)


0.30 M-day 870.00 261.00 261.00
0.75 M-day 650.00 487.50 487.50

1.10 m3 1500.00 1650.00 1650.00


Actual Rate 2398.50
Tools, Plants & Equipments @ 3% 71.96
Sub Total 2470.46
Rate per m3 2470.46
Rate per box 4940.92
Contractor's Overhead @15 % 370.57
Rate per m3 2841.03
Rate per box 5682.06
Total Gabion works all comp. / m3 4769.79
Total Gabion works all comp. / box 9539.58

Carting including finishing by rubbing Cement.

User's Rate Remarks


Quantity Rate Amount
1.10 0.00 0.00
1.50 0.00 0.00
0.09 0.00 0.00

0.12 0.00 0.00

0.23 0.00 0.00


0.00
0.00
0.00 0.00 0.00

0.00
0.00

Carting including finishing by rubbing Cement.

User's Rate Remarks


Quantity Rate Amount
1.25 0.00 0.00
2.50 0.00 0.00
0.17 0.00 0.00

0.23 0.00 0.00

0.46 0.00 0.00


0.00
0.00
0.00 0.00 0.00

0.00
0.00

Carting including finishing by rubbing Cement.

User's Rate Remarks


Quantity Rate Amount
1.25 0.00 0.00
3.00 0.00 0.00
0.26 0.00 0.00

0.34 0.00 0.00

0.68 0.00 0.00


0.00
0.00
0.00 0.00 0.00

0.00
0.00
plaster (1:2) base course & 6 mm th marble chips with white
rse including rubbing & polishing

User's Rate Remarks


Quantity Rate Amount
3.50 0.00 0.00
36.00 0.00 0.00

0.12 0.00 0.00


0.17 0.00 0.00
0.07 47460.00 3322.20

0.05 10170.00 508.50


0.34 303.97 103.35
0.11 502.85 55.31
0.50 113.00 56.50
60.00
4105.86
123.18
367.86 4229.04 422.90

423.03
423.03
cement plaster (1:4)

User's Rate Remarks


Quantity Rate Amount
2.00 0.00 0.00
12.60 0.00 0.00

0.081 0.00 0.00

0.22 0.00 0.00

11.00 904.00 9944.00


0.37 303.97 112.47
0.118 502.85 59.34
0.538 113.00 60.79
L.S. 0.00 60.00

13.500 0.00 0.00


10236.60
307.10
933.78 10543.70 1054.37

1073.85
1073.85

rse including rubbing &

User's Rate Remarks


Quantity Rate Amount
2.00 0.00 0.00
21.50 0.00 0.00 13.5 for machine

0.03 0.00 0.00

0.18 0.00 0.00


11.00 2825.00 31075.00
0.37 303.97 112.47
0.12 502.85 60.34
0.54 100.00 54.00
L.S. 60.00
31361.81
940.85
2859.88 32302.66 3230.27

3288.86
3288.86

:2) surface course including rubbing & polishing

User's Rate Remarks


Quantity Rate Amount
2.00 0.00 0.00
21.50 0.00 0.00 13.5 for machine

0.03 0.00 0.00

0.18 0.00 0.00

11.00 5480.50 60285.50


0.37 303.97 112.47
0.12 502.85 60.34
0.54 100.00 54.00
L.S. 60.00
60572.31
1817.17
5522.43 62389.48 6238.95

6350.80
6350.80

oring in 1:4 cement sand mortar

User's Rate Remarks


Quantity Rate Amount
13.00 0.00 0.00
4.50 0.00 0.00

0.06 0.00 0.00

0.15 0.00 0.00

11.00 863.59 9499.49


3.23 47.46 153.29
9652.78
289.58
879.85 9942.36 994.24

1011.83
1011.83

User's Rate Remarks


Quantity Rate Amount
13.00 0.00 0.00
4.50 0.00 0.00
0.06 0.00 0.00
0.15 0.00 0.00

11.00 863.59 9499.49


3.23 47.46 153.29
9652.78
289.58
879.85 9942.36 994.24

1011.83
1011.83

d mortar

User's Rate Remarks


Quantity Rate Amount
2.00 0.00 0.00
4.50 0.00 0.00
0.06 0.00 0.00
0.17 0.00 0.00
11.00 1019.26 11211.86
11211.86
336.36
1021.97 11548.22 1154.82

1175.26
1175.26

User's Rate Remarks


Quantity Rate Amount
10.00 0.00 0.00
11.00 2600.00 28600.00
28600.00
858.00
29458.00 2945.8

3387.67
Kathekhola Rural Municipality
Office of the Rural Municipality Executive
Bihunkot, Baglung
Gandaki Province, Nepal
\
Quantity Measurement
Project Name:- Homestay paryatan purbadhar karyakaram sanchalan
Homestay Name:- Shivadhuri samudayik homestay
Location:- Kathekhola Rural Municipality-5, Bihu

S.N Description of items No Length Breadth Height Quantity Unit Rate Amount Remarks
1 Earthwork
land development 825 1.50 0.45 0.6 334.125
stone soling 1 12.00 1.5 0.2 3.6
total 337.725 m3 432.6 146099.835
2 Dry stone masonary work
for stairs 825 1.50 0.4 0.26 128.7 m3 3557.00 457785.9

3 Stone soling works 1 12.00 1.5 0.15 2.7 m3 3110.67 8398.809


4 Formworks 35 1.50 0.2 10.5 m2 626.5 6578.25
5 M15 PCC work(c/s/a 1/2/4)
tread 825 1.50 0.5 0.08 49.5
total 49.50 m3 16878.91 835506.045
Total Evaluated amount 1454368.84

S-ar putea să vă placă și