Sunteți pe pagina 1din 6

APPENDIX 4

GC3 – THE HEALTH AND Candidate’s observation


SAFETY PRACTICAL APPLICATION sheet

Sheet number of _____

Student name MUHAMMED ANAS EBRAHIM KUTTY Student number _________________

Place inspected Diamond District, Pangappara Date of inspection _15_ / _02_ /_2016_

Observations Control measures Time Scale


Hazards & consequences Immediate and longer term actions

1. The carpentry work was going  Provide PPE such as mask, safety glass and Immediate
on at the parking area of block ensure they are using it.
B2. During the work, lot of dust  Provide Local exhaust ventilation. One week
was produced and the workers  Provide machines which absorb the dust from
are exposed to it. This will result where it is produced. One month
in breathing illness such as  Conduct health surveillance. One month
asthma, coughing, sneezing and
possible damage to the lung.

2. At the parking area of B2 the


carpentry work was going on and  Reducing the working hours by job rotation and Immediate
during the work high noise is providing adequate break time.
produced. The workers are  Provide PPE such as ear muff, ear plug etc. Immediate
exposed to the high noise and  Regularly maintain the equipment by using
long term exposure will lead to lubricants at the moving parts of equipment. One week
many health problems such as
 Replace the machine with new one.
stress, hearing loss, tinnitus etc. Three months

3. Lubricant oil is leaked from the


machine which is used for the Immediate
 Protect the area by barricading.
carpentry work. One week
The oil is spread over the floor of  Place sign boards.
parking area of B2. If someone  Clean the floor and place container to avoid One week
comes in contact with the oil spreading of oil.
while walking will result in slip  Repair or replace the machine part. One months
and fall. It may leads to injuries,
fracture and even death.

4. At the parking area of block B2


the carpentry work was going on  Instruct the workers to lift the load as a team Immediate
and workers are lifting and work.
moving heavy wooden pieces  Reduce the work time by job rotation and Immediate
manually. This will result in providing adequate break.
prolapsed disc, strains to  Provide trolley’s to shift the load. One months
tendons, muscles or ligaments  Provide training and supervision. Weekly
etc.
APPENDIX 4
GC3 – THE HEALTH AND Candidate’s observation
SAFETY PRACTICAL APPLICATION sheet

Sheet number of _____

Student name MUHAMMED ANAS EBRAHIM KUTTY Student number _________________

Place inspected Diamond District, Pangappara Date of inspection _15_ / _02_ /_2016_

Observations Control measures Time Scale


Hazards & consequences Immediate and longer term actions

5. The drilling machine used for


the carpentry work at the parking  Provide PPE such as rubber gloves and safety Immediate
area of B2 is missing insulation shoes
at cable.  Insulate the damaged part of wire with Immediate
If someone comes in contact with insulation tape.
the uninsulated part of wire while  Replace the wire with insulated wire. Two weeks
working will result in electric
shock, injury or even death.

6. The good practise noted is that


good welfare facilities are  Continue practise.
provided through out the work
site, such as water, toilet
facilities, smoking areas etc.

7. The workers are working at the


scaffold without any safety  Provide and ensure that workers are wearing Immediate
precaution such as safety belt fall safety belts while working at scaffold.
arrest net at the back side of  Built fall arrest net. One week
block B3. If anyone slips from the  Provide proper training and supervision
scaffold then he will fall down One week
and it will result in injuries
fracture or even death.

8. At the backside of block B3


there is no catching net to protect
 Barricade the area.
the falling object. Immediate
 Place sign boards about the work.
So there is chance of hitting One week
someone by the object which is  Provide catching net to protect falling object to One week
falling from height. reach ground.
It will result in injuries or even
death.

9. The entry and exit of the


scaffold at the back side of B3
was obstructed by work  Remove the obstruction from the scaffold. Immediate
materials. There is a chance of  Provide training and supervision. One week
being struck against the
obstruction while entering and
existing. It will lead to injuries,
APPENDIX 4
GC3 – THE HEALTH AND Candidate’s observation
SAFETY PRACTICAL APPLICATION sheet

Sheet number of _____

Student name MUHAMMED ANAS EBRAHIM KUTTY Student number _________________

Place inspected Diamond District, Pangappara Date of inspection _15_ / _02_ /_2016_

Observations Control measures Time Scale


Hazards & consequences Immediate and longer term actions
fracture or even death.

10. Welding work was


progressing at the ground floor of  Stop the work immediately and shift any one of Immediate
B2 and the spray painting work the work to a safe zone.
was also progressing at the  Provide ventilation to avoid vapours to One week
same floor near to the welding concentrate over the air.
work. There is a chance of fire if  Introduce permit to work system. One week
the vapours of spray painting  Provide training and supervision . weekly
come into contact with the spark
produced during welding. It will
result in huge fire and explosion
and it will result in injuries and
death to several.

11. The first aid kit where absent  Place first aid kit throughout the site.
throughout the site.  Provide training to the workers to use the first Immediate
If any accident occurs then due aid.
to the lack of first aid it may  Provide supervision to ensure that everything is Weekly
increase the effect of injury and it up to date and sufficient for the number of
may even lead to death. workers. Weekly

12. Lack of necessary


 Place the information throughout the site and it
information throughout the site Immediate
should be up to date and clear.
such as exit, emergency
 Provide training and supervision to ensure that
procedures, site rules policies
informations are up to date and at the correct
etc. If an emergency situation Weekly
place.
occurs people may not be aware
of what they should do and
where the emergency exits are.
This will make the scene worst
and it may increase the depth of
accident.

13. The demolishing process was  Reduce the work time by job rotation and
going on near the swimming providing adequate break.
pool. The workers where using  Provide PPE such as shock resistive gloves. Immediate
jack hammer without gloves. The  Replace the equipments with which are having
continuous exposure to this less vibration. Immediate
vibration may lead to hand arm One week
APPENDIX 4
GC3 – THE HEALTH AND Candidate’s observation
SAFETY PRACTICAL APPLICATION sheet

Sheet number of _____

Student name MUHAMMED ANAS EBRAHIM KUTTY Student number _________________

Place inspected Diamond District, Pangappara Date of inspection _15_ / _02_ /_2016_

Observations Control measures Time Scale


Hazards & consequences Immediate and longer term actions
vibration syndrome numbness,  Provide proper training and supervision.
tingling, blanching etc.  Conduct health surveillance. Weekly
Monthy

14. There is lack of signage and


barricade at the place where  Barricade the area to restrict the entry. Immediate
excavation is done for swimming  Place sign boards about the hazard. One day
pool. There is a chance of  Provide proper lighting. One week
someone falling into the
excavated area. This may result
in injuries or even death
 Provide PPE such as gloves, respiratory mask
15. The workers are handling  Provide trolleys to shift cement from one place Immediate
cement without any PPE behind to another.
the block B3.The direct contact One week
 Provide training and supervision.
with cement will result in burns,
irritations. Weekly

16. The workers are not using Immediate


 Provide and ensure workers are using PPE.
any type of PPE throughout the Weekly
work site. Due to the lack of PPE  Provide training and supervision.
if any accident occurs it will
increase the severity of accident
and it may increase the chance
of risk and it will lead to injuries,
burns etc.
Immediate
17. Throughout the site there is  Appoint a flagman to control the movement of
lack of separate pedestrian route vehicles and pedestrians. One week
and pedestrians crossing.  Place warning boards and speed limiting bump.
So there is a chance of  Provide designated safe crossing points. One week
pedestrians being hit by vehicles.
It can lead to injuries or even
death.
Immediate
18. The painting work was  Secure the ladder by fixing it to a support. One week
progressing at ground floor of B2  Avoid the need to work at ladder by using by
where a worker is standing at the using roller brush, using that he can paint from
ladder. The ladder is not secured the ground itself . One week
so there is a chance of slip and  Provide and ensure the correct selection and
APPENDIX 4
GC3 – THE HEALTH AND Candidate’s observation
SAFETY PRACTICAL APPLICATION sheet

Sheet number of _____

Student name MUHAMMED ANAS EBRAHIM KUTTY Student number _________________

Place inspected Diamond District, Pangappara Date of inspection _15_ / _02_ /_2016_

Observations Control measures Time Scale


Hazards & consequences Immediate and longer term actions
fall, it will result in injury, fracture use of access equipments such as step ladder. Weekly
and even death.  Provide training and supervision.

19. The transformer is placed Immediate


near the entrance gate and it is  Place sign board about the danger. Two days
not protected by any fencing.  Cover the area by temporary barricade. One month
So everyone can interfere with  Guard the area by permanent fencing.
the functioning of transformer
and during that time there is a
chance of coming in contact with
electricity and it will result in
burn, injuries or even death.

20. The demolishing work was  Instruct to lift the waste material as a team Immediate
near the swimming pool and the work.
heavy waste materials removed  Reduce the work period by providing adequate One week
manually by the workers. This break.
will result in prolapsed disc,  Provide trolleys to move the load. One week
strains to tendons, muscles or Weekly
 Provide training and supervision.
ligaments.

21. The noise produced by the Immediate


 Reduce the exposure by reducing the work
jack hammer is very high, The
hour by job rotation and by providing adequate
workers are exposed to this high
brake.
noise and the overexposure will
result in stress, hearing loss,  Provide PPE such as earmuff, ear plug. Immediate
tinnitus.  Maintain the equipment by using lubricants at One week
the moving part.
 Replace the equipment. One month

22. The generator room near  Shift the operator from generator room. Immediate
security room doesn’t have  Provide Local exhaust ventilation. One month
proper ventilation and a  Replace the manual machine with automated Two months
generator operator is always machine.
present near the generator.
The exposure to the
concentrated toxic gas will result
in suffocation and even death.
APPENDIX 4
GC3 – THE HEALTH AND Candidate’s observation
SAFETY PRACTICAL APPLICATION sheet

Sheet number of _____

Student name MUHAMMED ANAS EBRAHIM KUTTY Student number _________________

Place inspected Diamond District, Pangappara Date of inspection _15_ / _02_ /_2016_

Observations Control measures Time Scale


Hazards & consequences Immediate and longer term actions

23. In the 3rd floor of block B2 the  Avoid trailing cables Immediate
welding work was progressing.  Provide adequate lighting. One week
The wire which is obstructing the  Give training and supervision. Weekly
walkway. If someone struck
against the trailing cable there is
a chance of trip and fall. That will
lead to injuries, Fracture or even
death.

24. In the 3rd floor of block B2 the  Provide PPE such as safety gloves and safety Immediate
welding work was progressing shoes.
.The welding cable doesn’t have  Repair the cable by connecting plug. One week
plug. So there is a chance of  Provide training and instruct to check the
getting shock from the cable equipments before use. Daily
while connecting it to the plug  Replace the cable.
point. This will result in injuries, One week
burn and even death.

25. The bricks needed for the Immediate


 Shift the bricks from there.
construction is obstructing the One week
 Place sign boards about the emergency exit.
emergency exit at the back side Daily
of block B1. If an emergency  Provide training and supervision.
situation occurs then the people
present in the block b1 will not be
able to exit out through the
emergency exit. This could make
the situation more worst and it
will result in injuries, or even
death.

26. The painting workers at the  Provide and ensure that the workers are using Immediate
2nd floor are handling chemicals PPE’s such as gloves, respiratory mask etc.
such as paints, solvents without  Provide moisturising creams and washing One week
any PPE. This exposure to facilities.
chemicals will lead to irritations,  Provide hand tools to minimise the Two weeks
contact dermatitis etc.

S-ar putea să vă placă și