Product Roadmapping Using

Agile Principles
Product Roadmapping Using Agile Principles
Anupam Kundu & Tiffany Lentz

Abstract

As agile practices become more prevalent across organizations, Product Management divisions face
increasing challenges to adapt to these agile techniques and respond to their partners in IT. Sure, both
groups seek the values of agile, in terms of higher productivity, improved product quality and predictable
business values. We must ask, however, are agile techniques inherent to the way Product Managers
create and manage their product portfolio? The quick answer is No. A change in mindset and technique
are needed. Given that strategic objectives are frequently set at an executive level, Agile product/portfolio
managers struggle to address the dual requirements of defining a product roadmap aligned to those
strategic objectives while simultaneously addressing the constraints of resources and budgets consumed
at the release and sprint levels. This dual challenge is testing the bandwidth of current practitioners of the
Product Management discipline. More often than not, most Agile project teams look forward to direct
collaboration with the strategy makers for quick and effective decision making over reporting extensive
metrics for each and every project/program; the reality is that only a few product/portfolio managers are
actually capable of making that shift to accommodate this drift. What is needed to make that shift?

This paper outlines a modest agile-enabled framework adopted by the product wing of the digital division
of a publishing house to charter their product roadmap and simultaneously enable their project team with
the “big picture”. We adopted highly collaborative, feedback dependent, iterative and time boxed activities
geared to developing and maintaining a rapidly evolving product roadmap. This report reinforces the
necessity of embracing agile product management principles as being central to successful agile projects
and teams. Without appropriate product management that integrates continuous feedback loops, agile
teams might end up delivering the wrong products faster. This article provides the tools to enable medium
sized practicing agile teams and their product owner(s) to steer their product portfolio in the right
direction.

Introduction
i
In his book “Agile Estimating and Planning, ” Mike Cohn stresses that the accuracy of a plan decreases
rapidly the further we attempt to plan beyond what we can see. Hence agile teams usually get involved in
the elaboration of planning at three distinct horizons (if you cannot see past the horizon, you need to look
up and adjust your plan) – daily, iteration (sprint), and release. By planning across these time horizons,
agile teams focus only on what’s visible and important to the plan they are creating. Though most agile
teams are usually concerned with only these three levels of planning, an Agile Product Manager doesn’t
stop at release planning; product managers need to plan with equal ease at multiple levels. They have to
scale from release planning to creating a full product roadmap, portfolio management, and finally to
executive strategy making. The scale of activities for the Product Manager now spans across all the
following horizons: daily, iteration (sprint), release, product, portfolio, and strategy.

Figure 1 highlights the different levels at which an Agile Product Manager is expected to work; the outer
levels (product/ portfolio/ strategy) usually have a different audience and different rates of progression
than the inner circles. This makes it more important for the Product Manager to be agile in their
communication and deliverables. Unfortunately, it is more often the case that enterprises have traditional

Agile Product Roadmapping 2009 ThoughtWorks Inc. All rights reserved


product owners or managers who are unable to catch this fast drift from release planning to product
pr
strategy and vice versa. Agile Product/Portfolio Management is geared to address a number of these
concerns of product managers by embedding key agile principles of iterative feedback, constant
collaboration and prioritization into product/portfolio management.

Figure 1: Planning Onion shows possible multiple planning horizons


ii
In an article in the Agile Journal , Joe Krebs explains how Agile project management and Agile Portfolio
Management practices enable organizations to define their corporate strategy by using a pyramid like the
one shown in Figure 2. This pyramid is dysfunctional without close and continuous bi-directional
bi
collaboration between the portfolio managers and the actual project members so that the latter are able to
execute projects that achieve strategic corporate objectives while providing detailed insight into the state
of the projects. The direction of the
he two arrows in the pyramid shows the flow of information and feedback
across the different units.

Corporate Strategy

Agile portfolio
management

Agile project management

Agile software engineering

Figure 2: Agile Portfolio Management is build on agile software engineering and drives corporate strategy

We can derive a formal definition for agile portfolio planning from this pyramid:

Agile Product Roadmappi


Roadmapping 2009 ThoughtWorks Inc. All rights reserved
Product/Portfolio planning is a key activity for the Agile Product Manager,
which usually consists of planning and management of existing product sets,
and defining new products for the portfolio.

Now, in order to define the portfolio, the product manager has to develop a product roadmap in
collaboration with her stakeholders that consists of new upcoming products and existing product plan
updates based on the their current status. The product roadmap thus enables identifying future release
th
windows and drives planning for tactical development. The company referenced in this article is the 4
largest publishing house in U.S. based in New York whom we will refer as the client company. At the
client company, the team – working alongside the product owner and other business stakeholders –
adopted an agile roadmapping model for building and sharing the digital strategy.

How did it start?

It all started with re-engineering of the existing consumer facing website of the client company. The
primary goals of the new site were to simultaneously give a voice to the authors, outside of their books,
as well as to provide a richer and more compelling user experience to both readers and authors. This was
achieved through the use of multimedia, author- and user-generated content, social marketing, and
content syndication. Conceptualized in-house, the project was outsourced for both design direction and
development implementation.

When the site went live and was considered a success in the media industry, the business sponsors were
eager to execute new projects while riding high on the waves of success. Within a short period of time,
the project backlog grew longer than expected. Eventually, the development team was confronted with
multiple backlogs prioritized by multiple stakeholders with little or no consolidated prioritization.

The main backlog was a long list of specialized new projects with multiple degrees of business impact. A
second – and steadily expanding – backlog consisted of enhancements to the existing site. Finally, a third
backlog consisted of ad-hoc multiple small projects with various goals and objectives. With the desire to
satisfy all the various stakeholders, the teams started delivering products from all the backlogs with no
overall product strategy in mind. All the stakeholders were equally involved in prioritization exercises, and
soon realized that although the project teams involved were delivering releases in a timely manner, the
business impact of those releases was hard to realize. This is when the team, the product owners, and
the stakeholders decided to put agile product/portfolio management principles into practice to enable the
definition (and subsequent execution) of a product roadmap.

Building a Product Roadmap

Building a product roadmap for the digital division of a large publishing firm is a strenuous process that is
fraught with dangers. There are work items that need immediate attention, new marketing outreach
initiatives, and then strategic projects to organize and develop the internal infrastructure. Correct
prioritization of feature set, and planning a proper release that will address the executive strategy, are
serious challenges for the product manager and the agile project teams.

Agile Product Roadmapping 2009 ThoughtWorks Inc. All rights reserved


Lack of fast feedback, inability to change course direction based on new priorities, and reluctance to
gather inputs from multiple stakeholders can throw the team off track quite easily. To deal with this, the
agile team introduced a tiered approach to develop and execute the roadmap. The tiered approach made
sure that everyone’s voice was heard. To support this approach, the project moved from its initial one-
week sprint to a two-week sprint to ensure the availability of sufficient lag to alter priorities for the teams
without overburdening the release cycles.

At the client company, each product request in the roadmap was judged on multiple parameters to make
sure that the roadmap consisted of feature sets that delivered maximum business value and remained
aligned with the corporate strategy. A few of the key questions that were considered for building and
prioritizing the roadmap are:

• What is the business value for the product?


• Is the new feature considered a legal obligation for the market?
• Does the new product provide a distinct competitive advantage in the marketplace?
• How much can the proposed product leverage the newly created infrastructure?
• Which product can help launch or promote new or emerging lines of business?
• Will the new product allow the stakeholders to reach and exploit new marketing geographies?
• How much will it cost to launch the new product?
• Is there a need to build follow-up modules to the product?
• Is this a new product a catch-up with rest of the players in the market?
• Is there a partner obligation for the product launch schedule?
• Are all necessary resources available for the product to be implemented?
• Which product addresses the most demanding stakeholder group in the company?

The idea was to initially create and maintain two backlogs for the product roadmap: one for all the bugs
and enhancement requests; the second for all high business value products and new feature requests.
Unless the bugs and enhancements were deemed to be critical, or if there was not enough work for the
whole team, the sprint focus of the project team was always dedicated to new features and high value
business products based on prioritization from the product manager.

The team adopted a quick feedback model to ensure that the project teams, distributed across the world,
had visibility into the prioritized product roadmap, enabling them to them to stay focused on delivering the
right projects. This provided the product owner and the stakeholders bandwidth to prioritize the project
backlog based on the business realities of cost and implementation timeline.

What to work on from the product roadmap?

Once an initial draft of the roadmap was created, loaded with multiple new products and features, the
challenge facing the organization was to make sure that the agile project teams were dedicated to
working on the right products selected from that roadmap. This is where we had to extend the bandwidth
of the product manager by introducing full time business analysts to the project. Figure 3 outlines the
different phases, and the key groups involved in active collaboration in each of these phases. The
process of selection of projects from the roadmap for implementation consisted of four logical and
overlapping phases, to which each product is subjected. We divided our effort to make a project Go/No-
Go decision into 4 different, yet cohesively connected buckets:

Agile Product Roadmapping 2009 ThoughtWorks Inc. All rights reserved


• Identification
• Prioritization
• Exploration
• Confirmation.

Identification: This is the phase where business stakeholders brainstorm and define the business goals
for a new product. The initial tensions between different stakeholders about getting their projects in the
priority list are overcome during this identification process, as the business and technology stakeholders
come into close contact with the product owner (portfolio/product manager). Based on the initial round of
discussions and evaluations every project idea is assigned a priority ranking.

Key Outputs: A ranked product roadmap with high level business visions and
goals outlined for the highest priority projects and features. Also included are
initial definitions of targeted user roles, initial workflow for prioritized
product(s).

At the client company, the business stakeholders during this phase conceptualize the need of a product
to enhance their digital presence and drive corporate strategy. Primary business goals are defined and
initial user flows are identified.

Prioritization: During this phase the whole team is normally brought into the roadmapping process. A
quick kickoff is arranged to make the team aware of the roadmapping process. Based on priority inputs
from the product owner, the team evaluates the project ideas and generated epic backlogs to provide
initial “order of magnitude” estimates (estimating in T-Shirt sizes). All the risks are identified and
assumptions are laid out. It is at this stage the product manager reassesses the risks, estimates, and
potential business values. This reassessment results in revised priorities for one or more projects, through
collaboration with the other stakeholders.

Key Outputs: An initial story backlog that has been prioritized by the business
owners in collaboration with the team and the product owner. The backlog is
supported by initial coarse-grain estimates, and lists of risks and assumptions
to make sure that everyone understands the work scope.

At the client company, all of these (re)prioritization activities are incorporated as part of the regular sprint
work, so that the entire project team has more visibility into the potential pipeline of work and can provide
quick feedback to the product owners on the ‘current’ state of the backlog and team capacity. Also first
draft of user workflows and wireframes are created to aid in estimation.

Exploration: At this stage, the risks get well defined as the team performs early technical spikes for
integration touch points. Refined estimates are available as user attributes and user interface workflows

Agile Product Roadmapping 2009 ThoughtWorks Inc. All rights reserved


are defined to the next level of detail. This results in a tentative release plan based on the current sprint
backlog and team capacity.

Key Outputs: A new version of the story backlog with refined granular level
estimates and risk lists and a draft of the release plan.

At the client company, this phase is used to share the initial release plan with the teams for feedback.
Also the outputs of the technical spikes are shared with the product owner to make them aware of the
potential technology choices.

Confirmation: This is the phase when the business stakeholders review all the available information
(business value, risks, estimates, product definition, and suggested release plan) to reach a Go or No-Go
decision. It is the responsibility of the Product Owner along with the team to refine the release timelines
and resource scheduling based on the decisions taken.

Key Outputs: The approved project backlog is the main output of this phase,
which drives a formalized release plan owned by the team and the
product/portfolio owner.

At the client company, if the project is a Go, the portfolio owner refines the release timelines and resource
scheduling. If the project is a No-Go, the portfolio owner puts the project back into hibernation for
reconsideration at a later time.

All four phases are interrelated and interdependent, each drawing input from the one before and providing
output back to refine the decision making process at this stage. Constant feedback, collaboration, free
exchange of information and artifacts, and a centralized dashboard are among the key factors that make
these phases work seamlessly across multiple sprints and release cycles.

Agile Product Roadmapping 2009 ThoughtWorks Inc. All rights reserved


Figure 3: A diagrammatic representation of the steps followed to adapt agile product/portfolio
iii
management

Agile Product Roadmapping 2009 ThoughtWorks Inc. All rights reserved


Advantages of collaborative roadmapping

This feedback oriented, collaborative roadmapping process was a learning experience for all of us
involved in the projects at the client company. We were quickly able to adapt the implementation direction
based on learning from constant feedback sessions during roadmap meetings. All the team members felt
empowered and considered themselves to be in the ‘thick of the mix’ rather than just doing vanilla
implementation projects. Following are a number of the positive effects we witnessed.

• Rapid portfolio management: Usually portfolio planning is a slow process as portfolio decisions
are slower and more deliberate - involving a broad range of inputs from multiple stakeholders -
and more impactful than product level decisions. However, agile product roadmaps are created
and maintained iteratively with close collaboration between the stakeholders and project teams,
hence portfolio planning progresses rapidly.

• Ability to change roadmap direction: Agile portfolio management offers the flexibility to
frequently update the roadmap based on close feedback and strong collaboration from the agile
teams and the stakeholders. The product roadmap can undergo updates at any time during the
release cycles; current project status, change in future financial projections, change in
prioritization by the stakeholders, or a new legal requirement can be factored into the roadmap.
Each of the phases provides enough information to the stakeholders to change their priorities
based on reality checks.

• Knowledge sharing: The goal of each of the phases overlaps with the next one; they are not
water tight containers of activities guarded by gatekeepers, but rather collaborative, feedback-
based time boxes geared to moving forward in the project selection process. At this client
company, these logical phases not only provided our team with the perspective of the overall road
map and the proverbial ‘big’ picture from a business value view point, they also enabled our
understanding of the nature of the potential work, and the risks attached, during early analysis
and estimation processes.

Overcoming Challenges

All these great advantages brought with them multiple challenges, both for the agile team and for the
product managers and stakeholders at the client company. Most of these challenges were related to a
lack of timely and effective communication between the different participants, and to overstretching of the
available bandwidth of the team and the product owners. We could reach quick solutions for some of
them, while others took a little bit of time to earn buy-in from stakeholders.

Challenge: An agile product/portfolio manager has to constantly balance the demands of both the project
teams and the stakeholders; she has to switch between specifics of stories and sprints and more grueling
new product definitions and prioritizations of product roadmap with ease. Suddenly she is not just
communicating with sprint schedules and reporting on tactical development activities, but is also involved
in strategic planning with other stakeholders using the quintessential product roadmap.

Solution adopted: This was effectively handled by creating product owner proxies, which included
full time business analysts in product teams to scale the product manager to achieve her goals.
Expanding this role was a relatively small price to pay compared to the increased effectiveness of the

Agile Product Roadmapping 2009 ThoughtWorks Inc. All rights reserved


project team and faster delivery cycles, ensuring the delivery of priority business values. So business
analysts became these key resources who could move with equal ease between the development
teams and the product management team.

Challenge: Stakeholders, in traditional mode, will be involved only once or twice to define product
roadmaps. In this agile roadmapping process, on the other hand, it is expected that the roadmap will
continuously evolve and change based on feedback from agile teams and on changes in market realities.
The product roadmap becomes a ‘live’ artifact to which the stakeholders were held accountable along
with the product manager.

Solution adopted: Weekly meetings were introduced to discuss and dissect the product roadmap
and reprioritize the backlog based on inputs from different departments within the organization. This
top-down input to the product roadmap process increased the overall trust and accountability of the
stakeholders. Few or all of these meetings happened within the scope of the sprint activities
depending on the duration of the sprint and current sprint backlog. Soon, we adopted a two-week
sprint schedule to accommodate the product roadmap prioritizations into the sprint backlog.

Challenge: Agile project teams - used to working in daily, sprint, and release modes - usually have low
visibility into the product roadmap and hence corporate strategy. With Agile roadmapping they are
involved in early estimation and release planning which affect the overall velocity of delivery.

Solution adopted: We successfully introduced this phased approach so that the team could get
involved in the roadmapping process without significant delivery impact. Introduction of dedicated
business analysts also enabled the project team to understand not only project backlog, sprint
backlogs and release plans, but also business plans that provided overview of product vision, goals
and how they fit into the overall corporate strategy, and the product roadmap. This new insight
increased the confidence of the team as they were now sure that in every sprint their effort was
directed towards building the prioritized product roadmap to deliver the most optimum business value.

Conclusion

We experimented with this approach by moving over to two week sprints (instead of the usual one week
sprint cycles) and involving the business analysts more closely in the roadmapping process. The
business analysts enabled the product owners to significantly extend their bandwidth. We also modified
the sprint planning meetings to accommodate discussion on the roadmap projects. These changes
yielded positive results for our whole team and the stakeholders at the client company. As a whole, we
saw marked improvement in productivity by adopting this phased model; the count of the number of new
products released in a quarter went up, the highest priority products got quicker release timelines
compared to the less important ones, and the team morale got a big boost. However, we recognize that
this model is not a silver bullet for other projects or other business situations. It is important to remain
aware that they are not guaranteed to give the same results every time for all teams. So product owners
and project team members, feel free to adopt this model for your portfolio planning and then tweak it, if
need be, as per the local sensitivities to achieve your goals.

___________________________________________________________________________________________

Agile Product Roadmapping 2009 ThoughtWorks Inc. All rights reserved


About the authors

Anupam Kundu is a Certified Scrum Master and Lead Consultant with ThoughtWorks Inc, a global IT
services firm focused on end-to-end software delivery. He has more than 10 years of experience in
various stages of software development life-cycle and post-implementation activities and is focused on
enabling multiple teams through active adoption of Agile practices in the field of global outsourcing
services and global software delivery models with distributed teams. Anupam's primary focus has always
been to get a good understanding of the business processes, both core and supporting, and the data
points needed to run them efficiently before looking into the technology choices to achieve them. He has
recently contributed three different articles to "97 Things Every Project Manager Should Know" book.

Tiffany Lentz is proudly employed as a Principal Consultant and Program Manager with ThoughtWorks, a
global IT services firm focused on end-to-end software delivery. She has worked extensively for large
clients in the US, Canada and China, delivering solutions for both disparate system delivery projects and
agile enablement and transformation efforts to incorporate and enhance efficiency and delivery
processes. She is an author, mentor, coach and trainer of agile methodologies, processes and practices.
Tiffany is the author of Iteration Management Chapter in the ThoughtWorks anthology book and believes
that the Iteration Manager’s job is to build a well-oil delivery machine.

i
Agile Estimating and Planning, Mike Cohn
ii
Agile Portfolio Management / Product Strategy Pyramid: http://www.agilejournal.com/articles/columns/articles/415-
the-agile-pyramid-aligning-the-corporate-strategy-with-agility
iii
Diagrams and review courtesy of Steven “Doc” List

Agile Product Roadmapping 2009 ThoughtWorks Inc. All rights reserved