TECHNOLOGICAL INSTITUTE OF THE PHILIPPINES INCLUDES

938 Aurora Boulevard, Cubao, Quezon City  PERSPECTIVE

 SITE
COLLEGE OF ENGINEERING AND ARCHITECTURE DEVELOPMENT
Civil Engineering Department
PLAN

 VICINITY MAP
CE 505
 FLOOR PLAN
CONSTRUCTION PROJECT MANAGEMENT
 ELEVATION PLAN

 STAIR DETAILS
FINAL DESIGN PROJECT
 FOUNDATION

PLAN

 FRAMING PLAN

 FOOTING BEAM

DETAIL

 COLUMN
SUBMITTED BY: SCHEDULE
CALIMA, ROTSEN A.
 WALL FOOTING
CE51FC1
DETAIL
SUBMITTED TO:
 BEAM SCHEDULE
ENGR. BRYLLE JERALD P. TIMBAL
 SLAB SCHEDULE
Instructor
March 17, 2018
MATERIAL
ESTIMATES
PROJECT
SCHEDULE
Task Name Start End Duration (days)
Start date 21/09/2017 30/09/2017 9
Demo Prep 01/10/2017 06/10/2017 5
Demolition 06/10/2017 24/10/2017 18
Excavation 25/10/2017 29/10/2017 4
Concrete 01/11/2017 13/11/2017 12
Pre backfill 13/11/2017 15/11/2017 2
Framing 25/10/2017 05/12/2017 41
Roof 19/11/2017 10/12/2017 21
Plumbing 29/10/2017 09/12/2017 41
Windows 22/11/2017 15/12/2017 23
HVAC 29/11/2017 20/12/2017 21
Electrical 10/12/2017 22/12/2017 12
A/V 10/12/2017 15/12/2017 5
House wrap 27/12/2017 30/12/2017 3
Insulation 03/12/2017 21/12/2017 18
Drywall 03/01/2018 23/01/2018 20
Exterior stone 03/01/2018 17/01/2018 14
Exterior case work 04/01/2018 13/01/2018 9
Laundry/furnace room flooring 16/02/2018 11/03/2018 23
Hardwoods 19/01/2018 10/03/2018 50
Tile 03/02/2018 14/02/2018 11
Cabinets 18/01/2018 06/03/2018 47
Plumbing -hang sinks 16/02/2018 23/02/2018 7
Interior doors 25/02/2018 09/03/2018 12
Millwork 15/02/2018 17/02/2018 2
Interior painting 28/02/2018 14/04/2018 45
Stone Counters 21/03/2018 31/03/2018 10
Schedule Buffer 28/02/2018 10/03/2018 10
Decks 28/02/2018 18/03/2018 18
Interior doors- hang & hardware 03/05/2018 13/05/2018 10
Appliances 02/05/2018 03/05/2018 1
Plumbing 02/05/2018 05/05/2018 3
Electrical 03/05/2018 11/05/2018 8
Bathroom Glass 09/05/2018 13/05/2018 4
Garage Door dress up 13/05/2018 18/05/2018 5
FINAL Inspections 02/05/2018 02/05/2018 0
Wrap up 09/05/2018 05/06/2018 27
House Cleaning 29/05/2018 10/06/2018 12
Complete 01/06/2018 01/06/2018 0
PROJECT
SPECIFICATIONS
I. MOBILIZATION
II. TEMPORARY FACILITIES
III. SITE LAY-OUT
IV. EARTHWORKS
a. COLUMN FOOTINGS
b. WALL FOOTINGS
V. REBAR WORKS
a. COLUMN FOOTINGS
b. COLUMNS
c. SECOND FLOOR BEAMS
d. ROOF BEAMS
VI. CONCRETE WORKS
a. COLUMN FOOTINGS
b. COLUMNS
c. SECOND FLOOR BEAMS
d. ROOF BEAMS
VII. FORMWORKS
VIII. MASONRY WORKS
a. EXTERIOR WALLS
b. INTERIOR WALLS
IX. ROOF FRAMING WORKS
X. CONCRETE STAIRS
XI. ROOFING WORKS
XII. DOORS AND WINDOWS
XIII. CARPENTRY WORKS
XIV. TILEWORKS
XV. KITCHEN COUNTER
XVI. PAINTING WORKS
XVII. ELECTRICAL WORKS
XVIII. PLUMBING WORKS
TOTAL FLOOR AREA of the Project

508.1025 m²

TOTAL PROJECT COST


TOTAL CONSTRUCTION COST(A-C) PHP 10,021,702.54
(12% VAT) PHP 1,202,604.31

TOTAL NUMBER OF DAYS (Duration)

From and including: Thursday, 21 September 2017


To and including: Friday, 1 June 2018
Result: 254 days
MANPOWER
AND
EQUIPMENT
SCHEDULE