Sunteți pe pagina 1din 6

SEDIMENT

MANAGEMENT

CASE STUDY
NATHPA JHAKRI, INDIA

Key project features Nathpa Jhakri hydropower plant suffered its first sediment
problems a year after commissioning, in 2004. The high soil
Name: Nathpa Jhakri
erosion during the snowmelt in the Himalayas results in
Country: India
large sediment loads, in particular quartz particles that can
Category: reduce sediment production
(watershed management); upstream severely damage the plant’s technical equipment.
sediment trapping; bypass channel/ Protecting the hydraulic machinery from abrasion and
tunnel; empty flushing; adaptive
strategies
preserving the reservoir storage in the future called for
Reservoir volume (original): 343 Mm3 effective sediment management strategies.
Installed capacity: 1,500 MW
Date of commissioning: 2003 At 1,500 MW capacity, Nathpa Jhakri is the 486 m3/s, to the desilting complex which
largest hydropower project on the Sutlej comprises four chambers each of
River in the state of Himachal Pradesh in dimensions 525 m long, 16.31 m wide and
northern India. The Sutlej River rises in the 27.5 m deep. Then, the headrace tunnel of
Tibetan Plateau at an elevation of about 27.4 km long conveys the water to the
4,570 masl, meeting the Chenab River to underground power station, where six 250
form the Panjnad River before the MW Francis turbines generate about 6,778
confluence with the Indus River. GWh annually. The water from the turbines
is released back to the Sutlej River through
The project is owned by the SJVN Ltd, a joint
the 982 m-long tailrace tunnel. The scheme
venture between the government of India
is shown in figure 1.
and the government of Himachal Pradesh.
The government of India envisages a total of The 2.5 km-long reservoir is located in a very
around 30 projects on the Sutlej River. narrow valley, and has a total live capacity of
343 Mm3 and a live storage capacity of 303
The USD 2 billion Nathpa Jhakri project
Mm3. In addition, the flood control pool
includes a 62.5 m-high concrete gravity
capacity is 5,660 m3. The maximum
dam, a large underground desilting complex
operating level is 1,495.5 masl and the
International Hydropower and a hydropower plant with an installed
minimum drawdown level is 1,474 masl. The
Association capacity of 1,500 MW. The water flow is
reservoir is normally operated at full regime
diverted through the intake structure,
Chancery House, St Nicholas Way, to benefit from the 493 m design head.
composed of four intakes and a capacity of
Sutton, London
SM1 IJB, United Kingdom
T: +44 20 8652 5290
F: +44 20 8643 5600
E: iha@hydropower.org
August 2017
hydropower.org
CASE STUDY: NATHPA JHAKRI

Nathpa Jhakri dam and instake structure on the left bank

Hydrology and sediment The river flow is comprised of glacier estimated at about 430,000 tons per
The Sutlej River basin represents a major melt, snowmelt (estimated to be about year due to a lack of historical records
part of the Indus River basin. It is 50 per cent of the runoff) and rainfall, and monitoring in the catchment.
considered a perennial river because the and is subject to a high hydrological
In 2005, a flash flood caused by an
upper catchment contains a large seasonal variability. The mean annual
artificial lake breach increased silt load
glacierised area. The catchment has a flow varies from 700 to 2,500 m3/s
to over 25,000 ppm because of
high soil erosion rate as a result of its during snowmelt and the monsoon
destabilisation of river banks. Twenty
fragile geology and a steep topography, season, and drops to 100-150 m3/s
days after the flood the silt load was
as shown in figure 2. At the location of during the winter months, with the
5,000 ppm, which is the limit for power
the Nathpa Jhakri project, more than 40 mean annual inflow from inter-basin
generation. As a result, the power plant
per cent of the suspended sediment transfers accounting for 40 per cent.
had to be shut down for several weeks.
load has been observed as During the winter season, all the water
corresponding to fine fraction sediment, inflow is required for power generation. After the first year of operation, all of
while only about 20 per cent The average total annual runoff of the the technical equipment (runners, guide
corresponds to coarse fraction sediment, Sutlej River is about 16,000 Mm3. vanes, plates and sealing rings) were
rising to 33 per cent during floods. severely damaged despite their plasma
Sediment problems
Often, landslides heavily increase the coating, due to the high sediment load
The Sutlej River is known for its high that passed through the turbines. Some
sediment concentration in the river flow.
sediment loads, and the current mean of this damage is shown in figure 3. In
The total catchment tributary to the annual suspended sediment load is on the monsoon season in 2004, the
Nathpa Jhakri dam is 49,820 km2, of the order of 700,000 tons per year. average monthly sediment load was
which 74 per cent is unregulated area. However, the design sediment load was

hydropower.org
CASE STUDY: NATHPA JHAKRI

213,000 tons. The quartz content in the was about 40 per cent. The inside of the reach. These measures would reduce
silt is on average 38 per cent according desilting chamber number IV is shown the number of flushing operations
to historical data, but later observations in figure 4. needed. Catchment treatment includes
have reported over 50 per cent quartz reforestation by the regional forestry
In order to minimise silt entry into the
content. In 2005, the annual silt load department, maintaining walls to
intakes and maintain the live storage
that passed through the turbines was prevent bank erosion and checking
capacity, flushing operations were
850,000 tons, although the design dams on tributaries with the help of
adopted at the dam. Sediment is
sediment load was estimated at around government regional entities of the
flushed effectively every year through
half of that, at 430,000 tons per year. Himachal Pradesh region.
the low-level gates at the dam. The
Sediment management strategies hydraulic model estimates that 2.5 Mm3
In the second year of operation, all units of sediment can be flushed out in one
were refurbished with HVOF-type day with a discharge of 1,500 m3/s.
Tungsten carbide coating and the The dams envisaged upstream of
performance of the components Nathpa Jhakri will trap sediment,
improved by up to 90 per cent. In therefore reducing the sediment inflow
addition, the upper limit of 5,000 ppm into Nathpa Jhakri. For example, the
at the intake was decreased to 3,500 Khab dam will be 275 m high with a
ppm. For coarser particles above 0.2 gross storage of 625 million m3 that will
mm, the upper limit was established at be able to store silt particles for about
600 ppm at the intake. Despite the 28 years for a storage of 340 Mm3. Khab
HVOF coating, the limit for total silt load is mainly built for power generation,
passing through the turbines was set to control flooding and to reduce silt
700,000 tons. The limit for uncoated damage and increase the lifespan of
runners was 400,000 tons. projects downstream.
The underground desilting complex, Watershed management to reduce
shown in figure 3, was part of the bank erosion and the creation of a new
original Nathpa Jhakri project. It was diversion tunnel are also envisaged. The
designed to remove particles above 0.2 diversion tunnel could divert up to 1000
mm and up to 60 mm. Hydraulic model Mm3 of excess water from about 750
studies showed that the overall metres upstream to the downstream
trapping efficiency of the prototype

Graphs and figures >

hydropower.org
CASE STUDY: NATHPA JHAKRI

Graphs and figures


Figure 1 - Nathpa Jhakri hydroelectric project layout

Figure 2 - Nathpa Jhakri surroundings with fragile geology

Graphs and figures cont. >

hydropower.org
CASE STUDY: NATHPA JHAKRI

Figure 3 - turbine damage at Nathpa Jhakri

Figure 4- Nathpa Jhakri desilting complex

Graphs and figures cont. >

hydropower.org
CASE STUDY: NATHPA JHAKRI

Figure 5 - inside the desilting chamber number IV

This is part of a series of sediment management case studies collated by International


Hydropower Association with support from the South Asia Water Initiative (SAWI), trust funds
to the World Bank. www.hydropower.org/sediment-management

hydropower.org

S-ar putea să vă placă și