CONCRETE PROPORTION – MIXTURE RATIO

1: 1½ : 3
1: 2 : 4
1: 2½ : 5
1: 3 : 6
ESTIMATING CONCRETE – BY AREA METHOD
ESTIMATING CONCRETE (M2) – BY LINEAR METHOD
SAMPLES

Rectangular Beam and Girder

16m
GIRDER
Concrete slab

8m Beams

GIRDER

40mm
PLAN
25mm

80mm
40mm

CROSS SECTION OF CROSS SECTION OF


BEAM GIRDER

Solve by Volume Method:


Solve by Linear Method:
Volume of Beam
Length of Beam
Volume = 5pcs. x .25 x .40 x 8m span
L: 5pcs. x 8m
V = 4 cu.m.
L= 40m
Class A Concrete (table 1-4) for BEAM
Volume of Girder
Cement: 40m x .900 = 36 bags
V =2pcs. x .40 x .60 x 16m span
Sand: 40m x .050 = 2 cu.m.
V = 7.68 cu.m.
Gravel: 40m x .100 = 4 cu.m.
Length of Girder
Total volume of beam and girder
L: 16m x 2pcs.
Total Volume = 4cu.m. + 7.68 cu.m.
L = 32 m
V = 11.68 cu.m.
Class A Concrete (table 1-4) for GIRDER
Cement: 32 x 2.160 = 69.12 bags
Using Cement class “A” Concrete (table 1-2):
Sand: 32 x .120 = 3.84 cu.m.
Cement: 11.68 x 9.0 = 105.12 bags
Gravel: 32 x .240 = 7.68 cu.m.
Sand: 11.68 x .50 = 5.84 cu.m.
Gravel: 11.68 x 1.0 = 11.68 cu.m.
SAMPLES

Circular Column

6m

Solve by Volume Method: Solve by Linear Method:


Area of Column
A = π r2 Length of Circular Column
A = (0.7854 x .602) = .283 sq.m. L = 6m

Volume of Column Class A Concrete (table 1-5) @40kg


V = .283 x 6m.ht. = 1.698 cu.m. Cement: 6m x 2.545 = 15.27 bags
Sand: 6m x .141 = 0.846 cu.m.
Class A Cement (table 1-2) @ 40kg Gravel: 6m x .282 = 1.692 cu.m.
Cement: 1.698 x 9.0 = 17.712 bags

Sand: 1.698 x .50 = 0.849 cu.m.

Gravel: 1.698 x 1.0 = 1.698 cu.m.

Source:
Fajardo, Max B. (n.d.), Simplified Construction Estimate 2000 Edition
ADAMSON UNIVERSITY
College of Architecture

BUILDING TECHNOLOGY 4

ESTIMATING
CONCRETE
Submitted by:
Ramos, Cedric Jeff C.
Mon / 2-7pm

Submitted to:
Ar. Christopher P. Coma

December 18,2017

S-ar putea să vă placă și