Documente Academic
Documente Profesional
Documente Cultură
NATIONAL DIPLOMA IN
CIVIL ENGINEERING
TECHNOLOGY
YEAR I- SEMESTER I
PRACTICAL
Table of Contents
WEEK 1 PRACTICAL
Set out a building
WEEK 2 PRACTICAL
Set out building (3-4-5) method
WEEK 3 PRACTICAL
Set up a moving profile for circular building
WEEK 4 PRACTICAL
Building a brick wall
WEEK 5 PRACTICAL
Making a precast lintel
WEEK 6 PRACTICAL
Insitu concrete lintel
WEEK 7 PRACTICAL
Laying bituminous felt
WEEK 8 PRACTICAL
Applying asphalt finish
WEEK 9 PRACTICAL
Fixing timber staircase on site
WEEK 10 PRACTICAL
Making concrete staircase
WEEK 11 PRACTICAL
SETTING OUT USING THEODOLITE METHOD
WEEK 12
TESTING DRAINS
WEEK 14
WEEK 15
PRACTICAL
tape
PROCEDURES:
2. Find out the distance from the site boundary to the building line on the working
Drawing. Use the tape to measure the same distance from the site boundary to
the location of the building line on the ground. Select a corner on the ground to
be corner A.
3. Place a peg in the ground at corner A and hammer a nail into the top of the peg.
5. Tie the string between pegs A and B. Check that the distance on the ground is
8. Use the builder’s square to check that the corners are at right angles.
WEEK 2
PROCEDURES:
1. Nail three pieces of timber together which you cut to these lengths to make a
frame
750mm
1000mm
1250mm
2. Place the right angle of the square against the lines between the corners. If the
corners are not at right angles then move the corner pegs until they make right
angles.
3. Measure the diagonals to check that they are the same length.
WEEK 3
BUILDING.
PROCEDURES:
1. Find out the radius of the building from the working drawings
3. Place a stake securely in the ground at the end of the radius in the centre of
the building.
8. Loop a piece of rope which is the length of the radius of the building over
9. Measure the distance to the inner and outer sides of the foundation from the
working drawing
10. Use the rope to measure the same distances on the ground
PROCEDURES:
1. Use the profile lines to locate an external corner on the strip foundation
of the external corner with wet mortar. Repeat steps 1 and 2 for all four
corners.
3. Stretch a line between the corners to provide a position for the first
course of brick. Secure the line by wrapping it around a brick and putting
another brick on top. Remove the line after the first course of bricks is
laid
4. Lay the bricks in a row. Adjust their position by tapping the bricks back
for 8 or 10 courses. Check that they are level horizontally and vertically
5. Build up the corners by racking the brick back for 8 or 10 courses. Check
your accuracy with builder’s level. Use a gauge rod to control the height.
6. Insert metal pegs in the mortar joint on the corners for each completed
of brickwork.
PROCEDURES:
1. Make a timber box in an open top, which is the same size as the
2. Paint the inside of the box with releasing oil. This stop the concrete
3. Bend the end of the reinforcement bars to right angles (900). If the
lintel contains more than one bar, then make short cross bars and wire
4. Insert spacers that holds the bars 25mm from the bottom of the
formwork. Spacers are small cement block embedded with tie wires
5. Place the reinforcement in the formwork and check that the bars are
7. Pour the concrete into the timber box and make sure that it flows
down around and under the rods, then pack it down to remove any
trapped air.
8. Make a smooth finish on the top of the concrete with a wood float and
9. Cover the box with wet sacking and leave to set for seven days.
WEEK 6
PROCEDURES:
1. Erect the timber formwork across the opening and support it from the floor
2. Seal all the joint with building paper or mastic between the timber formwork
and the brickwork to stop the cement and water leaking out.
4. Place the reinforcement in the formwork using the same method describe in
5. Pour the concrete and cover it with wet sacking and leave it for seven days.
WEEK SEVEN
PROCEDURES:
1. Roll out the first sheet of felt over the roof boarding and nail it with large
2. Roll out the next sheet of felt so that it overlaps the first by 50mm and nail it
down
3. Continue step 1 and 2 until the entire roof is covered in a layer of felt
4. Apply hot bitumen to the first layer of felt. Then roll out another layer, but
do not nail it. The sheets in this layer should overlap the first layer by 50mm.
6. Spread a layer of white marble or limestone chips set in bitumen over the top
PROCEDURES:
3. Lay an under felt cover over the roof surface that prevents the penetration of the
6. Apply the second layer to the same thickness so that it melts into the first layer
and weld the edges of the two layers together to a 20mm thickness.
7. Make a 450 wedge or fillet at the junction with vertical upstands that increase
the thickness of the asphalt at week points. Vertical upstands should be at least
8. Spread a 12 mm layer of white crushed stone over the surface or paint the
PROCEDURES:
2. Tightly fix against the staircase trimmer joist at the top and be cut and shaped to
5. Insert the outer string in the newel posts at the top and bottom. The stair wall
trimmer slots into the top newel post and they are screwed or nailed together.
7. Finally, fit the handrail and balustrade to the string and newels to complete the
PROCEDURES:
TITLE: SETTING OUT USING THEODOLITE METHOD
AIM: Know How To Setout Building Using Theodolite
PROCEDURES:
1. Mount and set the instrument at point A, sight the telescope, range and peg
out point E and B to establish the building line
2. turn the theodolite screws, set and adjust the degree reading to 0” to 00” turn
the telescope of the instrument on the tripod stand towards the right axis until
you can sight 900 00’ 00” using the instrument range to establish and peg out
point F and C
3. transfer the instrument to point C, and following the same procedure at A,
range A and F, set the angle 00 000 00”, turn forwards the right axis to sight
and obtain 900 00000” and to establish point G and D
4. point H could be established by using a measuring tape.
5. check the whole measurement again by mounting the instrument on points B
and D and repeat the whole process
WEEK 12
TITLE: EXCAVATING DRAIN POSITIONS
AIM: Know How To Excavate Drain Positions
PROCEDURES:
1. Mark out the position of the drain runs on the ground and mark the manhole
positions.
2. Calculate the depth of the inverts at the manholes positions.
3. Calculate the depth of the excavation and add 100mm for bedding if required.
4. measure the height of the upper sight rail above the datum
5. set up sight rails on the first straight drain run and calculate the length of the
traveler.
6. excavate the trench until you reach the correct level by lining up the traveler
or boning rod with the line between the sight rails
7. insert some pegs in the bottom of the trench that project 100mm off the
bottom
8. fill the bottom of the trench with 100mm granular material until it covers the
pegs.
9. attach a batten to the bottom of the rod so that it can sit drains on the
bedding and keep checking the levels with the boning rod. Joint the pipes so
that socket faces the flow
10.test the drains and backfill
11.repeat procedure for the next drain run
WEEK 13
TITLE: TESTING DRAINS
AIM: Know How Drains are tested for leakage using the hydraulic test method
THEORY: Drains that carry sewage must not leak into surrounding ground. To
ensure that the joints are secured, drains should be tested before they are
covered.
They are three method of testing drains:
1. the ball test
2. the hydraulic test
3. the mirror and torch test
PROCEDURE: Hydraulic test
1. plug the lower end of a drain run
2. insert a temporary joint and a 1.5 meter length of pipe at the higher end
3. pour water in the drain until the upright pipe is full.
4. leave it for two hours
5. check the level
6. top the water level up
7. check the levels again after half an hour
the level should drop less than 6.4mm per metre of 100mm pipe or 4.5mm per
150mm pipe.
If the drop in the water level is greater than 6.4mm or 4.5mm then the pipe
must be inspected for leak and you repair or replace it.
WEEK 14
TITLE: DOOR CONSTRUCTION
AIM: Know how to make a ledged, braced and battened door.
THEORY: This is a very simple door for internal or external use and is cheap to
make
It consist of the following:
1. Tongued, grooved and V‐joint battens measuring 100×25mm
2. Diagonal piles pieces called braces that measure about 100×25mm. braces
should be fixed so that they slope up away from the hinges
PROCEDURES:
1. assemble battens that are the right size for the door
2. glue the tongues and grooves together
3. screw or nail the battens to the ledges
4. cut out and fit the braces between the ledges
5. nail the battens to the braces.
This type of door does not have any special wood working joints.
WEEK 15
TITLE: DOOR CONSTRUCTION
AIM: Know how to make framed, braced and battened door.
THEORY: This door is strong then the ledged, braced and battened door because
the battens are set inside a timber frame
The framed, braced and battened door consist of the following pieces:
1. Battens that form the surface of the door
2. A frame with a head rail, bottom rail and two stiles
3. A ledge
4. Braces
PROCEDURE:
1. cut and assemble the pieces of the frame to fit the door size
2. insert the head and bottom rail into recesses in the stiles
3. fit the braces
4. nail the battens on the braces and stile.