HANDOVER NOTES

Site / Place of Handover : Handil


Department / Service : CST/OPB/SPS
From :I Gede Andi Dipayadnya
Date / Time : 13 June 2019
To : Rinaldi
CC : Mr. Handy K.

I. HSE Matters

ALWAYS REMINDER ALL OF THE CREW ABOUT “ZERO TOLERANCE” CAMPIGN

II. Work In progress and Today Activities


 Item. 18-0745/H
Assist CPA/INS for inspection 4”gas lift header due to corrosion under pipe
support
Status:
- The job started today.
- Install scaffolding for inspection puposes. In case of existing pipe’s thickness below the
Treq (thickness requirement), the pipe section will be replaced.
- As per info from Foreman, all materials for this item is ready.
- This morning LCT total 1 will be moved to CPA for lifting of 20”piping spool ex. ENI tie
ins, to be transferred to Meindo for modification.

Progress reported: 0 %

III. Main Events on the Period.

 Item. 18-0570/H
Gas lift pack off Installation at HPA-311
Status:
Completed

 Item. 19-0251/H
Repair leaking at 4”FL of HA-3 SS by removing check valve then install rated
spade.
Status:
Completed
 Item. 18-0335/H
Gas lift pack off installation at HH-445G
Status:
- Currently, activity for this item was put ON HOLD, due to WLI/WLC activity.
- Remaining activity:
a. Tie ins for 4”flow line, 2 joints
b. Tie ins 2”gas lift line , 1 joint
c. Leak test and touch up painting
d.NDT and dismantled scaffolding.

Progress reported: 50%

 Item. 18-0412/H
Gas lift pack off installation at HG-361S
Status:
- De-spading at 2”gas lift line and 3”relief line, done.
- Leak test at spading point, done
- The remaining scope is WLI to install last spool to top cap, and leak test accordingly.
- Remove temporary support.

Progress reported: 95%

 Item. 19-0245/H
Scaffolding activity for WLI activity at HM-353
Status:
- Completed

 Item. 19-0258/H
Scaffolding activity for WLI at HLB-175
Status:
- Completed

IV. High Priority Job to be done in forthcoming days


 Item. 18-0335/H
Installation of gas lift pack off at HH-445G

 Item. 18-0220/H
Assist for gas lift scrubber inspection V-46320 at HR

V. Pending Job and to be solved


NIL

VI. Miscellaneous Items

- Contractor’s team under PT. Meindo, foreman: Sudirman


- MOP LCT. Total 1 will be valid until April 2019

VII. Signature of Leaving Personnel Signature of Incoming Personnel

( I Gede Andi Dipayadnya ) ( Jarot Edy )