Sunteți pe pagina 1din 21

Kathekhola Rural Municipality

Office Of The Rural Municipality Executive


Bihunkot, Baglung

Cost Estimate

Project Name:-Hile danda dekhi dhamja gaon samma ko motor bato marmat (gabionjali
nirman)
Location:-Kathekhola Rural Municipality- 3, Dhamja
Fiscal Year : 2075 to2076
Rate per m3 89.12

44.2.a Assembling of wire crates/gabion/revetment and placing them in position including streching
,binding them together and tying down lids. Box size(3X1X 1) (16 m2)

Unit :Per m3 44.1.A.ii.b DoLIDAR


Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0 md 955.00 0.00
Unskilled 0.13 md 700.00 91.00

Binding wire
Materials 1.3 121.30 157.69
12swg(Heavy Coated)
kg
Sub-Total 248.69
15 % Overhead -
Rate per Box
Size(3X1X1) 248.69
Rate per m3 82.90

Unit rate/m3 Gabion Box


Size(2x1x1) NRs. 89.12
Gabion Box
Size(3x1x1) NRs. 82.90

Average Unit Rate 172.02 86.01 m3


45) Packing and filling of Gabion crates with stone
Unit :1m3 45.17-6 DoLIDAR
Particular Description Unit Quantity Rate Amount Remarks
Labours Skilled 0.3 md 955.00 286.50
Unskilled 0.75 md 700.00 525.00
Materials Stone 1.10 m3 1731.30 1904.43
Sub-Total 2,715.93
15 % Overhead -
Unit Rate 2,715.93 m3
Providing Mechine Made Heavy coated gabion Box Hexagonal Mesh size 10X12 cm,Mesh wire 10swg
(Heavy Coated),Selvedge wire 8swg (Heavy Coated),Binding wire 12swg(Heavy Coated) at site.

Size Sq.m/box Rate/Sq.


m Rate/Box Rate/Cu.m
Gabion Box 8
Size(1.5x1x1) 326.003 2608.02631 1738.68
Gabion Box 11
Size(2x1x1) 326.003 3586.03618 1,793.02
Gabion Box 16
Size(3x1x1) 326.003 5216.05263 1,738.68

Mechine Made Heavy coated gabion Box 1,765.85 m3


Packing and filling of Gabion crates with stone 2,715.93 m3
Sub Total Cost 4481.78
Assembling 86.01
Total Cost 4567.79

Prepared by:- Checked by:- Approved by:-


Prepared by:- Checked by:- Approved by:-
Rates5 of21
Government of Nepal
Ministry of Local Development
Office of District Development Committee
District Technical Office
Baglung

Rate of Materials
F/Y:-2071/072
Rate for Vat @
SN Particular Unit Rate Unit Unit Rate/kg/km Dist Km Load / Transportation Cost
Analysis 13% Remarks
Weight Unload
Tractor Porter Tractor Porter Tractor Porter
1 Skill Labour 955.00 955.00 md
2 Unskill Labour 700.00 700.00 md
3 Painter 955.00 955.00 md
4 Cement ( OPC NS mark) 18026.00 14200.00 mt 1,846.00 1000 0.132 0.5938 15 1980 -
5 Sand #VALUE! 2100.00 m3 1600 0.132 0.5938 #VALUE! -
6 Aggrigate 40mm 2380.80 1800.00 m3 2200 0.132 0.55 2 580.8 -
7 Aggrigate 20mm 2380.80 1800.00 m3 2200 0.132 0.55 2 580.8 -
8 Aggrigate 10mm 2380.80 1800.00 m3 2200 0.132 0.55 2 580.8 -
9 Stone 1731.30 1500.00 m3 1800 0.147 0.55 0.5 0.10 132.3 99.00
10 River Bed Material 1200.00 1200.00 m3 2200 0.147 0.55 0 0 -
11 Sal wood 36000.00 36000.00 m3 800 0.147 0.90 0 -
12 Local Wood 36000.00 36000.00 m3 600 0.147 0.90 0 -
13 Nail 118.65 105.00 kg 13.65 1 0.147 0.90 0 -
14 Reinforcement Bar 93790.00 83000.00 mt 10790 1000 0.147 0.90 0 -
15 Binding wire(Black) 113.00 100.00 kg 13 1 0.147 0.90 0 -
16 Snowcem Paint 70.06 62.00 kg 8.06 1 0.147 0.90 0 -
17 White Cement 29.38 26.00 kg 3.38 1 0.147 0.90 0 -
18 2X 500 gauge polythene 93.79 83.00 m2 10.79 0.147 -
19 Chicken wire 113.00 100.00 sq.m 13 0.147 -
20 Plain wire 214.70 190.00 Kg 24.7 1 0.147 0.90 0 -
21 Barbed wire 126.95 110.00 Kg 14.3 1 0.147 0.90 18 2.646 -
22 Iron angled post (13 kg) 1429.95 1235.00 nos 160.55 13 0.147 0.90 18 34.398 -

Prepared By Checked By Approved By


Rates6 of21
23 Mesh wire 10swg (Heavy Coated 115.65 100.00 Kg 13 1 0.147 0.00 18 2.646
24 Selvedge wire 8swg (Heavy Coate 115.65 100.00 Kg 13 1 0.147 0.00 18 2.646
25 Binding wire 12swg(Heavy Coated 121.30 105.00 Kg 13.65 1 0.147 0.90 18 2.646
Kg/m2 of machine made 0.147 0.90 18 6.213289
26 hexagonal mesh size 326.003289 283 Kg 36.79 2.3482
510 306 549.9

Prepared By Checked By Approved By


Government of Nepal
Ministry of Federal Affairs and Local Developoment
Office of District Development Committee
District Technical Office
Gorkha
RATE ANALYSIS
Name of Project : 2070/071
Item Labour (L) Materials (M) Total (L+M)
Total Cost,
Rate Unit Rate, Rs. Cost, Rs. Norms
m.d. Cost Type Rs. Unit
SN Description Catagory Quantity
per m.d. Including Including Including No.
Rs. Rs. VAT VAT VAT(for UC) DoLIDAR
1 Site clearance for1Sqm Unskill 0.04 610 24.40 Tools & Plant 3 % of labour cost 0.73 25.13 1-1.6

2
Earthwork in excavation in
a ordinary soft soil- For 1 m3 Unskill 0.50 610 305.00 Tools & Plant 3 % of labour cost 9.15 314.15 5.2-1.2.2(a)
b Hard soil- For 1 m3 Unskill 0.60 610 366.00 Tools & Plant 3 % of labour cost 10.98 376.98 5.2-1.2.2(b)
c Soft Rock- For 1 m3 Unskill 2.00 610 1220.00 Tools & Plant 3 % of labour cost 36.60 1256.60 5.2-1.2.2(c)
d Medium Rock- For 1 m3 Unskill 4.00 610 2440.00 Tools & Plant 3 % of labour cost 73.20 2513.20 5.2-1.2.2(d)
e Hard Rock- For 1 m3 Unskill 17.00 610 10370.00 Tools & Plant 3 % of labour cost 311.10 10681.10 5.2-1.2.2(e)
Refilling of trench with
3
excavaited materials Unskill 0.25 700 175.00 Tools & Plant 3 % of labour cost 5.25 180.25 10) 2 -5
4 Stone Solling& Leveling Unskill 1.25 700 875.00 Tools & Plant 3 % of labour cost 26.25 901.25
Blockstone 1.10 1200.00 1320.00 1320.00
Total 875.00 1346.25 2221.25 49)17-6
Formworksof Local wood for
5
Beam/Slab Skill 0.150 815 122.25 Local Wood 0.0070 38808.00 271.66 m3 U/D+DoLIDAR
For 1 Sq.m. Unskill 0.200 700 140.00 Nails 0.25 118.65 29.66 kg
Total 262.25 301.32 563.57 39)9.a
Quantity of wood required for 1 sqm formwork = 0.0526 cum.
Wood can be used 6 times for the formwork and after then 25% cost
of the wood is recovered. So the quantity of wood required for 1 sqm = 0.00658 cum.

6
Plain cement concrete work Skill 1.00 815 815.00 Cement 0.22 17628 3878.16 MT
M10(P.C.C. 1:3:6) Unskill 4.00 700 2800.00 Agg.40mm 0.65 2700.00 1755.00 cu.m DoLIDAR
and wall - For 1 m3 Agg.20mm 0.24 2700.00 648.00 cu.m 41.11A.a
Sand 0.47 1700.00 799.00 cu.m
Total 3615.00 7080.16 10695.16
7
Plain cement concrete work Skill 1.00 815 815.00 Cement 0.32 17628 5640.96 MT
M15(P.C.C. 1:2:4) Unskill 4.06 700 2842.00 Agg.40mm 0.52 2700 1404.00 cu.m DoLIDAR
and wall - For 1 m3 Agg.20mm 0.22 2700 594.00 cu.m 41.11A.b
Agg.10mm 0.11 2700 297.00 cu.m
Sand 0.44 1700.00 748.00 cu.m
Total 3657.00 8683.96 12340.96

8
Plain cement concrete work Skill 1.00 815 815.00 Cement 0.40 17628 7051.20 MT
M20(P.C.C. 1:11/2:3) in
foundation Unskill 5.12 700 3584.00 Agg.20mm 0.57 2700.00 1539.00 cu.m DoLIDAR
and wall - For 1 m3 Agg.10mm 0.29 2700.00 783.00 cu.m 41.11B.b
Sand 0.425 1700.00 722.50 cu.m
Total 4399.00 10095.70 14494.70

9
Stone masonry work in 1:4 Skill 1.50 815 1222.50 Cement 0.116 17628 2044.85 MT 38-8-A.c
cement mortar - For 1 m3 Unskill 3.24 700 2268.00 Sand 0.47 #VALUE! #VALUE! cu.m
Blockstone 1.00 1731.30 1731.30 cu.m
Bondsotne 0.10 1731.30 173.13 cu.m
Total 3490.50 #VALUE! #VALUE! cu.m

10
Stone masonry work in 1:6 Skill 1.50 815 1222.50 Cement 0.092 17628 1621.78 MT 38-8-A.d
cement mortar - For 1 m3 Unskill 3.29 700 2303.00 Sand 0.50 #VALUE! #VALUE! cu.m
Blockstone 1.00 1731 1731.00 cu.m
Bondsotne 0.10 1731 173.10 cu.m
Total 3525.50 #VALUE! #VALUE! cu.m
Dry stone masonry work with
11
rubble stone Skill 0.50 815 407.50 Blockstone 1.00 1731 1731.00 cu.m DoLIDAR
For 1 m3 Unskill 1.50 700 1050.00 Bondsotne 0.10 1731 173.10 cu.m 38. 8
Total 1457.50 1904.10 3361.60 cu.m

Random rubbel Stone


12
masonry in mud Skill 1.00 815 815.00 Blockstone 1.00 1731 1731.00 cum Urban Devemt
mortar - For 1 m3 Unskill 2.25 700 1575.00 Bondstone 0.10 1731 173.10 cum C6 6-2-2
Mud 0.42 350.00 147.00 cum
Total 2,390.00 2,051.10 4441.10
Chimney Bhatta Brick masonry work
17 in 1:4 C/S mortar - For 1 m3 Skill 1.50 815 1222.50 Cement 0.100 17628.00 1762.80 MT DoLIDAR
including material Unskill 4.99 700 3493.00 Sand 0.35 #VALUE! #VALUE! cu.m 37-7 c
collection,preparation of mortar with Brick 530.00 13.56 7186.80 cu.m
30m lead Total 4715.50 #VALUE! #VALUE! cu.m
Chimney Bhatta Brick masonry work
18 in 1:6 C/S mortar - For 1 m3 Skill 1.50 815 1222.50 Cement 0.070 17628.00 1233.96 MT DoLIDAR
including material Unskill 4.99 700 3493.00 Sand 0.38 #VALUE! #VALUE! cu.m 37-7 b
collection,preparation of mortar with Brick 530.00 13.56 7186.80 cu.m
30m lead Total 4715.50 #VALUE! #VALUE! cu.m
13 Snowcem painting on Skill 0.050 815 40.75 Snowcem 0.4850 67.80 32.88 Kg Urban Devemt
plastered surface (Twocoats) -
For 1 m2 Unskill 0.050 700 35.00 J4 13(4)b
Total 75.75 32.88 108.63 m2

14 Flush ruled pointing in 1:3 C/S


mortar On stone masonry wall Skill 0.080 815 65.20 Cement 0.00110 17628 19.39 MT Urban Devemt
For 1 m2 Unskill 0.100 700 70.00 Sand 0.00200 #VALUE! #VALUE! cu.m I 10. 14(2)c
Total 135.20 #VALUE! #VALUE! m2

15 Pointing in 1:2 C/S mortar on


brick masonry wall Skill 0.080 815 65.20 Cement 0.00122 17628 21.51 MT 37)7-13.3b
For 1 m2 Unskill 0.089 700 62.30 Sand 0.00260 #VALUE! #VALUE! cu.m DoLIDAR
Total 127.50 #VALUE! #VALUE! m2
16 12.5 mm thick cement Skill 0.15 815 122.25 Cement 0.00665 17628 117.23 MT 37)7-13.2.a

plaster in 1:2 cement sand Unskill 0.1344 700 94.08 Sand 0.01330 #VALUE! #VALUE! cu.m DoLIDAR
mortar -For 1 m2 Total 216.33 #VALUE! #VALUE! m2
17 12.5 mm thick cement Skill 0.150 815 122.25 Cement 0.00625 17628 110.18 MT 37)7-13.2.b

plaster in 1:3 cement sand Unskill 0.135 700 94.50 Sand 0.01280 #VALUE! #VALUE! cu.m DoLIDAR
mortar -For 1 m2 Total 216.75 #VALUE! #VALUE! m2
18 12.5 mm thick cement Skill 0.15 815 122.25 Cement 0.00363 17628 63.99 MT 37)7-13.2.c

plaster in 1:4 cement sand Unskill 0.1359 700 95.13 Sand 0.01460 #VALUE! #VALUE! cu.m DoLIDAR
mortar -For 1 m2 Total 217.38 #VALUE! #VALUE!
19 20 mm thick cement Skill 0.14 815 114.10 Cement 0.0081 17628 142.79 MT Urban Devemt

plaster in 1:4cement sand Unskill 0.19 700 133.00 Sand 0.0220 #VALUE! #VALUE! cu.m I 4. 12(4)b
mortar -For 1 m2 Total 247.10 #VALUE! #VALUE!

20
3 mm thick cement punning Skill 0.10 815 81.50 Cement 0.00532 17628 93.78 MT Urban Devemt

in 1:1 cement sand mortar - Unskill 0.10 700 70.00 Sand - #VALUE! #VALUE! cu.m H20 11-20
For 1 m2 151.50 #VALUE! #VALUE!

21
Reinfocement for RCC work Skill 7.000 815 5705.00 M.S. Rod 1.05 93790 98480 MT 40.10
in position and binding of Unskill 7.000 700 4900.00 Binding wire 10.00 113.00 1130.00 Kg DoLIDAR

M.S. rod for R.C.C. works -


For 1 M.T. 10605.00 99610 110215.00
For 1 Kg 110.22
22 Reinfocement for FCRT Skill 0.250 815 203.75 Binding wire 0.111 113.00 12.54 Kg Dept.N.
For 1m2 Unskill 0.083 700 58.10 Steel bar 21-02
8&10 mm Dia 2.593 93.79 243.20 Kg
Chicken wire
90 cm wide 1.806 79.10 142.85 m2
Plain wire
3.5 mm Dia. 2.083 146.90 305.99 Kg
Total 261.85 704.58 966.43

23
Formworks for ferrocement Skill 0.167 815 136.11 Bamboo 0.333 175.00 58.28 Dept.N.
works - For 1 m2 Unskill 0.111 700 77.70 Nails 4.000 118.65 474.60 21-01
Binding wire 0.083 113.00 9.38
HDPE pipe 32mmke/cm2 from Stock
Total 213.81 542.26 756.07
including
VAT
Formworks of Local wood for
5
Beam/Slab Skill 0.150 815 122.25 Local Wood 0.0070 38808.00 271.66 m3
For 1 Sq.m. Unskill 0.200 610 122.00 Nails 0.25 118.65 29.66 kg
Total 244.25 301.32 545.57
Barbed wire fencing
24 (5Hori,2Diag line) Sal wood Barbed
post c/c 3m dist Skill 0.0333 815 27.14 wire8.33m 8.33 118.65 988.35 kg 24-6
work - For 1 m Unskill 0.0667 700 46.69 U hook 2.57 2.26 5.81 nos
Sal wood post 0.0063 134064.00 844.60 m3
Total 73.83 1838.76 1912.59

25 Barbed wire fencing Barbed wire


(5Hori,2Diag line) without post Skill 0.0333 815 27.14 8.33m 1.00 118.65 118.65 kg 24-6
work - For 1 m Unskill 0.0667 700 46.69 U hook 2.57 2.26 5.81
Total 73.83 124.46 198.29
26 Fabrication of gabion boxes with partition including rolling, cutting, and weaving with binding. For Hexagonal mesh size 100mmx120mm DoLIDAR
Mesh Wire - 10 SWG, Selvedge
Wire 8 SWG 44.1.Aii.a,b
Box size: 2mx1mx1m(11m2) Skill 0.39 815 317.85 GI meshWire 23.43 113.00 2647.59
Unskill 0.20 700 140.00 Selvedge Wire 2.40 113.00 271.20
Total 457.85 2918.79 3376.64

Box size: 3mx1mx1(16m2)m


Skill Skill 0.57 815 464.55 GI meshWire 34.08 113.00 3851.04
Unskill Unskill 0.28 700 196.00 Selvedge Wire 3.36 113.00 379.68
Total 660.55 4230.72 4891.27
27 Gabion Construction works including placing inposition, tying gabion bindinging wire -12 SWG :
Box size: 2mx1mx1m Unskill 0.09 815 73.35 Binding Wire 0.95 118.65 112.72 186.07
Box size:3mx1mx1m Unskill 0.13 815 105.95 Binding Wire 1.30 118.65 154.25 260.20

28 Packing filling in gabion crates Stone - For 1 cum


Skill 0.30 815 244.50 DoLIDAR
Unskill 0.75 700 525.00 Blockstone 1.10 1200.00 1320.00 45.17-6
Total 769.50 1320.00 2089.50
Laying & Jointing of HDPE Pipes - For 1m 17-2
1 16,20 , 25 mm O.D. Plumber 0.001 815 0.82 0.00
(Outer Diameter) Pipes Helper 0.001 700 0.70 Fuel 0.00025 60.00 0.02
Unskill 0.002 700 1.40 Contingencies 2.51 % of labour cost 0.07
Total 2.92 0.09 3.01

2 32 mm O.D. Pipes Plumber 0.001 815 0.82 0.00


Helper 0.001 700 0.70 Fuel 0.00025 60.00 0.02
Unskill 0.003 700 2.10 Contingencies 2.51 % of labour cost 0.09
Total 3.62 0.11 3.73

3 40 & 50 mm O.D. Pipes Plumber 0.0015 815 1.22 0.00


Helper 0.0015 700 1.05 Fuel 0.00037 60.00 0.02
Unskill 0.0030 700 2.10 Contingencies 2.51 % of labour cost 0.11
Total 4.37 0.13 4.50

4 63 & 75 & 90 mm O.D. Plumber 0.0300 815 24.45 0.00


Pipes Helper 0.0300 700 21.00 Fuel 0.001000 60.00 0.06
Labourer 0.0600 700 42.00 Contingencies 2.51 % of labour cost 2.19
Total 87.45 2.25 89.70
5 110 & 125 mm O.D. Plumber 0.0200 815 16.30 0.00
Pipes Helper 0.0200 700 14.00 Fuel 0.001000 0.00 0.00
Labourer 0.0400 700 28.00 Contingencies 2.51 % of labour cost 1.46
Total 58.30 1.46 59.76
Laying & Jointing of G.I.Pipes - For 1 m 17-4ka
1 15 & 20 mm I.D. Pipes Plumber 0.017 815 13.86 Red lead paint,
Helper 0.033 700 23.10 hemp, etc. 10% of labour cost 6.01
Labourer 0.033 700 23.10 Contigencies 2.5% of labour cost 1.50
Total 60.06 7.51 67.57
2 25 & 32 mm I.D. pipes Plumber 0.017 815 13.86 Red lead paint,
Helper 0.050 700 35.00 hemp, etc. 10% of labour cost 8.39
Labourer 0.050 700 35.00 Contigencies 2.5% of labour cost 2.10
Total 83.86 10.49 94.35
3 40 & 50 mm I.D. pipes Plumber 0.025 815 20.38 Red lead paint,
Helper 0.067 700 46.90 hemp, etc. 10% of labour cost 11.42
Labourer 0.067 700 46.90 Contigencies 2.5% of labour cost 2.85
Total 114.18 14.27 128.45
4 65 & 80 mm I.D. pipes Plumber 0.042 815 34.23 Red lead paint,
Helper 0.067 700 46.90 hemp, etc. 10% of labour cost 15.11
Labourer 0.100 700 70.00 Contigencies 2.5% of labour cost 3.78
Total 151.13 18.89 170.02
U/D+DoLIDAR
U/D+DoLIDAR
39)9.a
0.00
Salient Feature Of Project
Project Name:-Hile danda dekhi dhamja gaon samma ko motor bato marmat (gabionjali nirman)
Location:-Kathekhola Rural Municipality- 3, Dhamja
sfo{qmdsf] gfd
sfd ug]{ lgsfo pkef]Qmf ;ldlt
cfly{s aif{ 075/076
ljlgof]lht jh]6 274000.00
cg'dflgt nfut 304787.95
sG6LGh]G;L 0.0
pkef]Qmf
v'b e'QmfgL>dbfg
x'g;Sg] 30787.95
/sd 274000.0
l;=g sfdsf] ljj/0f
!=pkef]Qmf ;ldltn] gS;f tyf nfut Ol:6d]6 adf]lhd lgdf{0f
gf]6
ubf{ k'/fgf vfg]kfgL,
ufpkflnsfsf] sfof{non] l;+rfO{,
pkef]QmfljBfno ejg, lghL
;ldlt;+u 3/, uf]7, cf+ug
;Demf}tf
ubf{ lgDgfg';f/sf] zt{x?sf] clgjfo{ kfngf u/fpg] k|ltj4tf lnP/
cfbL k"jf{wf/ ;+/rgf Iflt k'¥ofPsf] v08df ;f]xL pkef]Qmf ;ldltn]
dfq ;Demf}tf u/fpgsf nflu cg'/f]w
cfkm";+u ePsf] ;Demf}tf /sd leqsf] ah]6af6 dd{t, lgdf{0f jf
k'glg{df{0f ul/lbg' kg]{5 . ;f] ;DjGwdf s'g} ph'/L kg{ cfPdf
pQm Iflt ePsf] lgdf{0f ug{ nfUg] /sd ;DjlGwt pkef]Qmf
;ldltsf] vftfaf6 s§f u/]/ dfq clGtd km/kmf/s ug]{ Joj:yf
ldnfpg'x'g
@= ;DjlGwt . k|fljlws 6f]nLn] ;fO{6df u/]sf] ;e]{, sfof{nosf]
:jLs[t nfut cg'dfg Pj+ gS;fx? cg';f/ g} lgdf{0f sfo{ u/fpg] k|
ltj4tf lng' x'g
#= :jLs[t nfut. cg'dfg / gS;f eGbf km/s sfo{ u/L sfof{non]
d"Nof+sg gu/]sf] v08df s'g} lsl;dsf] ph'/ nfUg]5}g eGg] k|
ltj4tf lng'x'g .
$= ;Demf}tf adf]lhdsf] lgdf{0f ubf{ u/fpbf jftfj/0f ;+/If0f
P]g @)%# / jftfj/0f lgodfjnL @)%$adf]lhd jftfj/0fdf gsf/fTds
k|efj gkg]{ul/ u/fpg] k|ltj4tf lng'x'g .
at (gabionjali nirman)
Kathekhola Rural Municipality
Office of Rural Municipality Executive
Bihunkot, Baglung

Detailed Quantity Estimate

Project Name:-Hile danda dekhi dhamja gaon samma ko motor bato marmat (gabionjali nirman)

Location:-Kathekhola Rural Municipality- 3, Dhamja

F./Y.:-2075/ 076
S.N. Description of items No Length Breadth Height Quantity Unit Rate Amount Remarks
1 Earthwork 1 18 1.5 2 54 m3 90.4 4881.60

2 Gabion wall construction layer layer size volume no


d]n sf] 8f8f 1st layer 1.5*1*1 1.5 18 27
2nd layer 2*1*1 2 9 18
gairabari ghumti 2nd layer 2*1*1 2 10 20
65 m3 4567.79 296906.35
3 Project mgmt cost 1 1 job 3000 3000.00

Estimated Amount 304787.95


Amount without UC 274000.00
UC Contribution 30787.95
10.10%
sfo{;DkGg k|ltj]bg
sfof{nosf] gfd M–sf7]vf]nf ufpkflnsfsf] sfof{no, afUn'ª d=n]=k=kmf=g+= M–
of]hgfsf] gfd M pg'jf b]vL kmfk/v]t df]6/ af6f] :t/f]GgtL
7]ufgf M sf=uf=kf= $ t+u|fd
nfut cfg"dfg /sdM– #REF! sfd z'?ePsf] ldltM–
sfo{ ;DkGg ePsf] /sd #REF! sfd ;DkGg ug'{+kg] ldltM–
Oi6d]6 eGbf 36L jf a #REF! sfd ;DkGg ePsf] ldltM–
nfut sfof{ ;DkGg ePsf] km/s
qm= sfdsf] lhh/0f PsfO{ :jLst s}lkmot
kl/df0f :jLst b/ nfut ? kl/df0f :jLst b/ /sd kl/df0f /sd
b/
1 #REF! m3 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
2 #REF! m3 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3 #REF! LS 1.00 3000.00 3000.00 1.00 3000.00 3000.00 0.00 0.00 0.00
E/W in excavation (grade
4 maintenance, extrawidening) in
Roadway
Soft Soil m3 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Hard Soil m3 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Soft Rock m3 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Medium Rock m3 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
Hard Rock m3 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
s'n /sd #REF! #REF! #REF!

gf]6M–n=O= eGbf a9L eP-±_ jf sd eP-–_ lrGx n]Vg].


=g+= M–

#REF!
!= ljnsf] qmd ;+Vof MclGtd Kathekhola Rural Municipality &= ;Demf}tf ldlt M
of]hgfsf] gfd M pg'jf b]vL
Office of Rural Municipality Executive
kmfk/v]t df]6/ af6f] :t/f]GgtL *= sfd ;dfKt ug'{kg]{ ldlt M
7]ufgf M sf=uf=kf= $ t+u|fd Bihunkot, Baglung (= sfd gfkL ePsf] ldlt M
$= ;Demf}tf g+= M e'QmfgL ef}r/ g+= M
%= cl3Nnf] e'QmfgL ljnsf] qmd ;+Vo e'QmfgL ldlt M
^= cl3Nnf] e'QmfgL ljnsf] ef}r/ g+=
cf pkef]Qmf ;DaGwL lan gfkL lstfj g+= M
O6 cBfjlws sfd ePsf] cl3Nnf] ljnsf] r9]sf] xfn ePsf] sfd
n=O{=
d sfdsf] ljj/0f PsfO{ s}lkmot
kl/df0f kl/df0f b/ hDdf d"No kl/df0fhDdf d"No kl/df0f hDdf d"No
g+
=1 #REF! m3 #REF! #REF! #REF! #REF! #REF! #REF!
2 #REF! m3 #REF! #REF! #REF! #REF! #REF! #REF!
3 #REF! LS 1.00 1.00 3000.00 3000.00 1.00 3000.00

E/W in excavation (grade maintenance,


4
extrawidening) in Roadway

Soft Soil m3 #REF! #REF! #REF! #REF! #REF! #REF!


Hard Soil m3 #REF! #REF! #REF! #REF! #REF! #REF!
Soft Rock m3 #REF! #REF! #REF! #REF! #REF! #REF!
Medium Rock m3 #REF! #REF! #REF! #REF! #REF! #REF!
Hard Rock m3 #REF! #REF! #REF! #REF! #REF! #REF!

hDdf /sd #REF! #REF!


! of] lan jdf]lhd e'QmfgL hDdf ?= #REF! $ s§f ug'{ kg]{ ?=
@ hg;|dbfg #REF! s= k]ZsL
# afFsL lbg' kg]{ ?= 200000.00 v= dfn;fdfgsf] df]n
u= cGo
% v'b lb

k]z ug]{sf] ;xL M hfFr ug]{sf] ;xL M :jLs[t ug]{sf] ;xL M


bhf ;a–O{lGhlgo/ bhf{ M bhf{ M
hDd cIf?kL r]s g+= =======================af6 k||fKt eof] egL ;xL ug]{ .

S-ar putea să vă placă și