Employer: Contractor:

132/11kV GARDEN TOWER


(GRDNTOWR) S/S

Engineer: METHOD STATEMENT FOR Civil Sub Contractor:


MAIN BUILDING RAFT
CONCRETE WORK

DATE 22/05/2017 Doc Reference No: IASLC/MS/012 Page :1 of 6

METHOD STATEMENT FOR MAIN BUILDING RAFT CONCRETE


WORK
DESIGN, SUPPLY, INSTALATION, TESTING AND
COMMISSIONING OF TWO 132/11KV SUBSTATIONS
PROJECT TITLE
(GARDNCTY & GRDNTOWR) AT SATWA ZONE S PROJECT
FOR MERAAS DEVELOPMENT LLC
MERAAS DEVELOPMENT LLC
CLIENT

ENERGOPROJEKT ENTEL
ENGINEER

CONTRACTOR

Authority

Authority

Rev. No Rev Status of


SIEMENS Consultant
IAS LOOTAH CONTRACTING Status Approval

Prepared By Reviewed By Approved By Site Manager

0 QA/QC Site Manager Project Manager

Date

22.05.2017

REVISION CONTROL SHEET

Rev.No. Date Page/s No. Description


0 22.05.2017 6+ Attachments Issued for Review/Comments
Employer: Contractor:
132/11kV GARDEN TOWER
(GRDNTOWR) S/S

Engineer: METHOD STATEMENT FOR Civil Sub Contractor:


MAIN BUILDING RAFT
CONCRETE WORK

DATE 22/05/2017 Doc Reference No: IASLC/MS/012 Page :2 of 6

CONTENTS

1. OBJECTIVE
2. SCOPE
3. RESPONSIBILITIES
4. HEALTH,SAFETY & ENVIRONMENT
5. WORK METHOD
a. EQUIPMET
b. MANPOWER
c. WORK PROCEDURE FOR RAFT CONCRETE
6. REFERENCES
7. RISK ASSESSMENT
8. ATTACHMENTS
Employer: Contractor:
132/11kV GARDEN TOWER
(GRDNTOWR) S/S

Engineer: METHOD STATEMENT FOR Civil Sub Contractor:


MAIN BUILDING RAFT
CONCRETE WORK

DATE 22/05/2017 Doc Reference No: IASLC/MS/012 Page :3 of 6

1) OBJECTIVE:
The purpose of this method of statement is to define the procedures to ensure that the
proposed materials and workmanship to be used at the site are complying with the condition /
requirements as stipulated in the specifications.

2) SCOPE:
This method statement covers the requirements for all Raft Foundation. This method
statement is to be adopted during Raft Foundation activities for 132/11 kV GARDEN TOWER
(GRDNTOWR) SUBSTATION AT Al SATWA, DUBAI.
This statement describes the methods to cast the concrete of raft foundation, utility all
resources (manpower, equipment, machinery required for complete casting)
3) RESPONSIBILITIES
The Site in Charge along with his team is responsible for ensuring Raft Foundation is done as
per this statement and compliance is recorded on quality documents.
The safety officer is responsible to ensure that all the safety precautions are in place, Tool box
talks given, people are aware of Hazards involved and appropriate PPE are worn all the time.

4) HEALTH, SAFETY & ENVIRONMENT


One of the main aspects of this procedure is Safety and Health Control. This is to control
occurrence of injuries as well as damage to equipment and properties during the entire
construction period. In order to ensure a safe working environment during the entire
construction work is obtained, the safety measures will be implemented as follows.
 Barricades/Signs will be provided sufficiently and maintained, as precautionary measures
during the entire stage of construction, to protect the work, workmen and safety of the
public. In case of precaution against failure of lights, barricades will be equipped with
suitable reflecting material .Barricade will be made to indicate the construction boundary.
 Personal Protective Equipment (PPE including mask gas filter type) will be issued to all
workers such as safety shoes, hardhat, working gloves, safety goggles (if required),ear
muffs/ear plugs(if required).
 Wearing of the basic PPE shall be fully enforced.
 Regularly check that safe working condition is obtained prior to working.
 Emergency Response Plan has been developed and implemented to all personnel
acquainted with the relevant provisions and knows what to do in case of any emergency.
 IAS Lootah has suitably trained fire wardens among the crew at all times during on site
operations.
 IAS Lootah displays emergency evacuation procedures at strategic locations on the site
and ensure arrangements are in place to call for outside help if needed in any emergency
associated with the work on site.
 IAS Lootah keeps updating the Contractors/Customer with list of addresses and phone
numbers of all staff who are responsible for organizing emergency response at site
Employer: Contractor:
132/11kV GARDEN TOWER
(GRDNTOWR) S/S

Engineer: METHOD STATEMENT FOR Civil Sub Contractor:


MAIN BUILDING RAFT
CONCRETE WORK

DATE 22/05/2017 Doc Reference No: IASLC/MS/012 Page :4 of 6

5) WORK METHOD
The method statement includes safety aspects during the work, Preparation of the work,
Equipment, Manpower utilized and all related necessary to complete the entire work.
5.1) EQUIPMENT
 Transit mixe – 24 Nos
 Concrete pump – 4 Nos
 Water tank – 1 No
 Air Compressor – 1 No
 Flood Lights – 15 Nos
 Auto level instrument – 1 No
 Masonry Tools
 Mechanical Vibrator - 10 Nos
 Wheel Barrow – 4 Nos
 Cube Moulds – 186 Nos
 Tamping Rod -2 Nos
 Slump Cone – 2 Nos
 Thermometer – 2 Nos
5.2) MANPOWER

 Project Engineer – 1 No
 QA/QC Engineer – 1 No
 Supervisor / Foreman – 2 Nos
 Surveyor – 1 No
 Safety Officer – 1 No
 Mason – 17 Nos
 Carpenter – 10 Nos
 Steel Fixer – 10 Nos
 Unskilled Worker – 30 Nos
5.3) PROCEDURE

Prior to the commencement of all construction activities, necessary work permit shall be
obtained.
All materials identified for the permanent works shall be approved by the client / Engineer,
prior to the procurement / use
All Quality assurance and quality control activities will be in line with the specified
requirements of the contract
Employer: Contractor:
132/11kV GARDEN TOWER
(GRDNTOWR) S/S

Engineer: METHOD STATEMENT FOR Civil Sub Contractor:


MAIN BUILDING RAFT
CONCRETE WORK

DATE 22/05/2017 Doc Reference No: IASLC/MS/012 Page :5 of 6

5.4) EXECUTION

An approval of mix design of specified grades of concrete and trial mix shall be carried out
and the test result shall be submitted to the company / contractor for approval.
On approval, the mix design details shall be issued to the concerned personnel of the
concrete supplier for production. Ensure that prior to trial mix all the ingredients of concrete
including admixtures are got approved by the Owner / Engineer.

Marking shall be carried out for RCC walls, Columns, Pedestal &upstands over the
protection screed before commencing the reinforcement work. The prefabricated
reinforcement bars shall be laid & fixed with the required 75mm minimum cover as per the
approved RFC drawings. Erect the water tight formwork around the rebar’s, true to line,
plumb and dimensions in accordance with the RFC drawings.
.
250mm PVC Water stopper shall be placed in middle of periphery RCC wall kickers with
proper alignment& level. The joints of water bar shall be carried out by welding kit with 200
mm lap,and the construction joint locations are shown in the attached approved drawing.
Half of the water stopper shall be exposed from the top of kicker. The kickers for periphery
RCC walls and columns shall be 150 mm high and shall be cast monolithically with the raft.
Dowels for retaining wall, column ,transformer plinth,up stands, & staircase shall be checked

Adequate lighting shall be provided all around the base, and area near the concrete pump
shall also be provided with the light so that the banks man can guide and position the transit
mixer at right location. Also the concrete testing and sampling area shall be sufficiently
illuminated.

Wet the formwork just before the commencement of concreting and ensure that water is not
pooling inside the formwork area and the reinforcement & embedded items are adequately
secured to prevent movement during concrete placing.

On completion of inspection and subsequent approval by the Owner / Engineer carryout the
raft Concreting will be done by the pump with approved ready mix concrete of grade C40/20,
cement content 400kg/m³ (OPC128kg+GGBS240kg+MS32kg) and 0.35 water/cement ratio
with 125±25mm slump.While on the delivery of concrete at site an area shall be designated
near the pouring area for testing of slump,temprature and cubes will be made for testing as 6
cubes/ 40m³.The testing of cubes including durability test,12 Nos of cube samples shall be
taken for conducting durability test.We shall deploy sufficiant number of technician with
helper for this work.

Concrete pouring shall be done by 3 Pumps simultaneously,additional of one pump (1) as


spare.Pumps location are shown in the attached sketch and will be shifted during concreting
if required.Total estimated quantity for main building raft foundation is 1065m³.Pump
estimated capacity is 60m³/hr.Estimated concreting time will be Six (6) hours.Five (5)
masons and eight (8) helpers will be deployed for each as a team for each pump to
pour,compact,level and finishing of the fresh concrete on their assign zones.Each team will
be provided with 2 vibrators and 1 will be standing by.
Employer: Contractor:
132/11kV GARDEN TOWER
(GRDNTOWR) S/S

Engineer: METHOD STATEMENT FOR Civil Sub Contractor:


MAIN BUILDING RAFT
CONCRETE WORK

DATE 22/05/2017 Doc Reference No: IASLC/MS/012 Page :6 of 6

Placing of concrete in horizontal layers and ensure that concrete will not fall freely for height
more than 1.0 Mts to avoid damage to shutter and displacement of top reinforcement. The
concrete shall be placed and compacted / vibrated in horizontal layers of not more than
400mm thickness each. Concrete shall be compacted with mechanical vibration equipment
to max practicable density so that it is in complete contact with the forms, reinforcement and
other embedded parts, the vibrator shall be operated by experienced personnel to ensure
that the concrete is well compacted and not over vibrated. While compacting the concrete, it
shall be ensured that the poker goes down at 100 to 150mm in the previously laid layer, so
that these two layers gets mixed up. Arrange interval between the batches shall be
minimized to avoid the cold joints. Concrete shall be levelled and finished as per the levels
indicated in the RFC drawings, the concrete surface shall be levelled using Aluminum
straight edge trowelled by wooden float if required. The finished level should be confirmed
through level instrument.

After pouring the fresh concrete immediately covered with polythene sheet to avoid the loss
of moisture.Ones the concrete is stiffened,polythene sheet shall be replaced with wet
hessian cloth and water cured for the minimum of 10 days.Designate a special work force for
the purpose of continuous water curing.

6) REFERENCES:
 DEWA Specification
 Construction Drawing.
7) RISK ASSESSMENT:
Please refer the attached risk assessment reference # IASLC/SS/RA/012.
8) ATTACHMENTS:
 Risk Assessment

 Sketch for Pump location

 Approved Mix design

 Construction joint details for retaining wall