Sunteți pe pagina 1din 3

OUTSTANDING WORK BEFORE SEA TRIAL PROJECT NO : H.125 / H.

126
RENC.SEA TRIAL TGL.: 10 SEPT '15
UP DATE : 21 AUGUST 2015
FAST PATROL BOAT 60 M
KIND OF STATUS
NO ITEM OF INSPECTION REMARK
INSPECTION 125 DATE 126 DATE
I. HULL CONSTRUCTION
1 Construction Joint Welding O 31-Jul-15 O 31-Jul-15
2 Tank Test Pressure Test O 31-Jul-15 O 31-Jul-15
3 FOT-1 & 2 Final Painting O 20-Aug-15 O 20-Aug-15
4 Water Ballast Tank Final Painting ∆ ∆ wbt-2 proses
5 Stability Inclining Test ~ ~
6 X – Ray X-Ray O 7-Apr-15 O 7-Apr-15
II. MACHINERY OUTFITTING
1 Main Engine Safety device
2 Diesel Generator Engine Load Test O 4-Jun-15 O 10-Jun-15
3 Emergency Generator Load Test O 5-Jun-15 O 11-Jun-15
4 Harbor Generator Load Test O 5-Jun-15 O 11-Jun-15
5 Propeller Function Test O 10-Jun-15 O 10-Jun-15
6 Sea Water Cooling Pump. AC Function Test
7 Sea Water Cooling Pump. AC (Stand-by) Function Test
8 Bilge / Ballast Pump Function Test O 14-Jul-15 O 20-Aug-15
9 GS/Fire Pump (FM) Function Test
10 M/E Lub. Oil Pump Priming/stanby Function Test
11 FO Purifier Function Test
12 FO Transfer Pump Function Test O 6-Aug-15 O 6-Aug-15
13 FO Transfer Pump (Stand-by) Function Test
14 Fresh Water Hydrophore Unit Function Test
15 Sea Water Hydrophore Unit Function Test
16 External Fire Fighting pump Function Test
17 Emergency Shut Off Valve Function Test
18 Oil Water Separator (OWS) Function Test
19 Dirty / Sludge pump Function Test
20 Bilge Suction System +Emerg'cy bilge E/R Function Test O 14-Jul-15 O 20-Aug-15
21 Air Ducting Vent Function Test
22 Sewage Pump. Function Test
23 Sewage Transfer Pump. Function Test
24 Sewage Treathment Plant Function Test
25 L.O. Pump for Curter Function Test
26 Fresh Water Generator Function Test
27 Insulation in E/R Install Check ∆ ∆
28 Grating & Railing E/R Install Check ∆ ∆

III. HULL OUTFITTING

D:\PROJECT FPB 60 M\LAP. INTERN\CHECK SHEET PERSYARATAN SEA TRIAL.xlsx 1 of 3


KIND OF STATUS
NO ITEM OF INSPECTION REMARK
INSPECTION 125 DATE 126 DATE
A. Deck Machinery
1 Windlass & Anchor Function Test
2 Capstan Function Test
3 Steering gear system Function Test
4 Ballast System Function Test
5 Chain Wash System Function Test
6 Compressor Air System (service) Function Test
7 Sounding Pipe Function Test O 10-Aug-15 O 10-Aug-15
8 Deck crane Function Test O 2-Jul-15 O 2-Jul-15
9 Emergency Fire Pump Function Test
10 Bow Thruster Function Test
11 CO2 system Function Test
B.Deck Accomodation
1 Bilge System (Scuper) Function Test
2 Galley Equipment Function Test
3 Lavatory & Sanitary Function Test
4 Live Saving Appliance Install Check
5 Fire Extinguisher Install Check
6 Wooden Furniture / Door Install Check ∆ ∆
7 Ceiling& Lining Install Check ∆ ∆
8 Windows Hose Test O 2-Jul-15 O 2-Jul-15
9 Steel Door + Small Hatch Hose Test ∆ ∆
10 AC & Ducting Function Test
11 Clinometer Function Test
12 Ladder (Imbargasi) Function Test
13 RIB Function Test

IV. ELECTRICAL
A.Electric
1 MSB & ESB Load Test O O
2 Battery & Battery Charge Function Test
3 Group Starter Function Test
4 ECC Function Test
5 Main Lighting Function Test
6 Socket Function Test
7 Emergency Lighting Function Test
8 Navigation & Search Lighting Function Test
9 BCC Function Test
B.Nav.Equip
1 VHF Radio Telephone Function Test
2 SART & EPIRB Function Test

D:\PROJECT FPB 60 M\LAP. INTERN\CHECK SHEET PERSYARATAN SEA TRIAL.xlsx 2 of 3


KIND OF STATUS
NO ITEM OF INSPECTION REMARK
INSPECTION 125 DATE 126 DATE
3 SSB Radio Communication Function Test
4 TV & Radio Equipment Function Test
5 Echo Sounder Install Check O O
6 Speed log Install Check O O
7 GPS Function Test
8 Inmarsat C Function Test
9 SSAS Function Test
C.Internal Communication System
1 Talk Back System / PA System Function Test
2 Electric Engine Telegraph Function Test
3 Sound Power Telephone Function Test
4 Automatic telp Function Test
D.Nautical Equipment
1 Echo Sounder with GPS Function Test
2 Electric Horn / Air horn Function Test
3 Clear View Screen & Window Wiper Function Test
4 Radar Function Test
5 Compass Magnet Install Check
6 Gyro Compass Function Test
7 Electric Rudder Angle Function Test
E.Fire Alarm
1 General & Fire Alarm System Function Test
V. LAIN - LAIN
1 Peralatan Tambat Available
2 Tools Permesinan Available
3 Peta Pelayaran Available
4 Bendera & Tanda Navigasi Available
5 Surat ijin berlayar / Sea trial Available

NOTES :
~ = Not Yet Started
Δ = In Process
O = ACC. by Classification / OS
 = Ready to be checked to Class / OS

OWNER SURVEYOR CLASS SURVEYOR CLASS SURVEYOR QA/QC


(RINA) (BKI)

( …………………………….) ( …………………………….) ( …………………………….) ( ………………………….)

D:\PROJECT FPB 60 M\LAP. INTERN\CHECK SHEET PERSYARATAN SEA TRIAL.xlsx 3 of 3