Vina-PSMC

Meeting agenda on Wednedsay 09 Nov, 2016

1. P.S.Mitsubishi: Mr. Kakuta, Mr. Trang


2. Vina - PSMC: Mr. Hau, Mr. Tuan Anh, Mr. Quyet, Ms. Ngoc Anh
5. Content:
No. Item PIC

I Sleeper preparation
- Project Overall Schedule Mr. Kakuta

0 - Sleeper Contract Mr.Vinh, Mr. Kakuta


Sleeper testing frame & pull-out test Mr.Hau, Mr.Tuan Anh
1

Layout arrangement for equipments and apparatus for Mr. Phuoc/ Mr. Trang
2 new laboratory

3 Tensioning programme Mr. Hau


Material & mix design Mr. Trang, Mr. Hau, Ms.
Optimize PC sheet pile mix design upon the new plant Ngoc Anh
4 is completely set up

5 Formwork marking Mr. Hau, Mr. Tuan Anh


3rd party laboratory for materials
6
7 3rd party laboratory for loading tests
Vina-PSMC
Meeting agenda on Wednedsay 09 Nov, 2016

1. P.S.Mitsubishi: Mr. Kakuta, Mr. Trang


2. Vina - PSMC: Mr. Hau, Mr. Tuan Anh, Mr. Quyet, Ms. Ngoc Anh
5. Content:
8 Concrete Bucket Mr.Hau, Mr.Tuan Anh
9 Quality control documents Mr. Phuoc/ Mr. Trang
Equipment procurement & preparation Mr.Hau, Mr.Tuan Anh, Mr.
10 Kakuta
11 Additional stock yard for sleepers Mr. Vinh/ Mr. Kakuta
12 Plan for additional manpower Mr. Vinh/ Mr. Kakuta
/Mr.Hau
13 5 tons forklift
Claim-on measuring gauge for tensioning jack for
14 elongation
15 Training in VN
16 Sleeper organization chart
17 Certification of measure gauge
18 Test curing compoung, form oil ..

II Items already resolved or to be discussed later


- Polyfoam for shoulder (elevated type)

- Camera for visual checking concrete appreance


- Camera and additional roof for aggregate storage
- Lifting devices in bundle, vibrator holder, steel
pipe(strand puller)
- Sprinkling to keep cooling down stone
Monitoring movement during construction period Mr. Hau,
Mr. Quyet
Vina-PSMC
Meeting agenda on Wednedsay 09 Nov, 2016

1. P.S.Mitsubishi: Mr. Kakuta, Mr. Trang


2. Vina - PSMC: Mr. Hau, Mr. Tuan Anh, Mr. Quyet, Ms. Ngoc Anh
5. Content:
Concrete floor Plan of investment construction Mr. Vinh/ Mr. Phuc/ Mr.
Tung
Overall test information
Meeting agenda on Wednedsay 09 Nov, 2016

3. Location: Vina PSMC factory office


4. Time: PM, 09 Nov 2016

Describe Remark

(0) Trial Mix - Middle of Nov Up-to-date


(0) Material test approval - Middle of Nov
(1) End of Jan - workshop is handed over to sleeper preparation after concrete slab
finishes, recevie formwork from JP
(2) Feb - renovation of production lines
(3) Beginning of March - start trial production
(4) Beginning of May - start official production

Contract, middle of Nov Up-to-date


Hitachi may consider more frequency for proof loadin testing (everyday), but PSM
insists 1time/1,000 sleepers. If more frequency, we will consider setting frame in
factory.
Coordinate with Mr.Tung for finishing of building construction.
Plan for equipment layout and procurement, after laboratory is ready, set up
equipment soon.
Awaiting for Mr. Vinh from Bach Khoa university
6 mix design already submit to HTC.
We will continue to check additional source for aggregate to propose to HTC later.
3rd party test result is necessary to propose to HTC.
VINA has to burden 3rd part laboratory test fee.

All markings are confirmed and made in JP.


VIBM is proposed tby Nghi Son Cement. HTC proposing VIBM to NJPT. If accepted,
3 options, Quatest3, SGS, VIBM.
Check Bach Khoa, VIBM
Meeting agenda on Wednedsay 09 Nov, 2016

3. Location: Vina PSMC factory office


4. Time: PM, 09 Nov 2016

Check supplier and finalize design and make order


All quality documents including internal test have to be finalized
Roller conveyor samples yet to be recievede equipment prepare schedule in very
detail to ensure everything's on time
To ask An Hoa or Ha Tien for additional storage spaces at their stock yard
Has to start Plan for Staff, supervisors, Workers, overall organization
To check mast height and fork length, capacity and recommend by Mr. Hau
To study on tensioning jacks from Nghi Son, finish in Sep

Has to start planning training in VN


Introduce org chart, discuss on roles and responsibilities each person

To avoid concrete come into the back void of shoulder (upside down location), to To be discussed later
carry out some trials as shoulder arrived from Sumitomo
To be discussed on later stages To be discussed later

To study while training in Japan, to make coppies as 2 pcs of Lifting devices to be To be checked in JP
arrived during trial production stage
Spare pump and water pipeline to be prepared To be discussed later
Should be started when starting piling adjacent to existing workshop
To be doing later
Meeting agenda on Wednedsay 09 Nov, 2016

3. Location: Vina PSMC factory office


4. Time: PM, 09 Nov 2016

During investment meeting, has to be finished in Jan In progress

Electric conductivity test, dynamic loadin test now plan in JP