PROJECT:
GROUP 12
GROUP LEADER: ORACION,SHAELLA KATE ALA
MEMBERS CANTINA,DENECILLE MAE FLORES
EBGRACIAL,ELLA MAE T.
FRIAS,ALDRIAN C.
1 Creation of Title 3 -
2 Title Defense 1 1
3 Creation of Gant Chart 2 1
4 Finding Internal and External Adviser 1 2
5 Gathering Data From the Project Location 2 2
6 Creation of Chapter 1
6.1 The Project 2 2,5
6.2 Project Location 1 2,5
6.3 Project Objective 1 2,5
6.4 The Client 2 2,5
6.5 Scope and Limitation 2 6.3
6.6 Project Development 2 6.1,6.2,6.3,6.4,6.5
9 Checking of Chapter 1 1 6.1,6.2,6.3,6.4,6.5,6.6
10 Revision of Chapter 1 2 6.1,6.2,6.3,6.4,6.5,6.6,9
11 Creation of Chapter 2
11.1 Review of Related Studied and Literature 3 -
11.2 Design Data 6 10
12 Checking of Chapter 2 1 11.1,11.2
13 Revision of Chapter 2 2 11.1,11.2,12
14 Creation of Chapter 3
14.1 Design Contraints 3 13
14.2 Trade-offs 3 13,14.1
14.3 Significance of Chosen Trade-offs to the Design Constraints 2 14.1
14.4 Ranking Scale 2 14.1,14.2,14.3
14.5 Initial Assessmenta of Trade-offs 2 14.2,14.3
14.6 Raw Designer's Ranking 2 14.1,14.2,14.4
14.7 Design Standards 2 14.1,14.2,14.3,14.4,14.5,14.6
15 Checking of Chapter 3 1 14.1,14.2,14.3,14.4,14.5,14.6,14.7
16 Revision of Chapter 3 2 14.1,14.2,14.3,14.4,14.5,14.6,14.7,15
17 Creation of PowerPoint Presentation 3 10,13,16
18 Defence of the Project 1 17
19 Final Revsion of Chapter 1 to 3 5 10,13,16,17
20 Submittion of Hardbound Copy and Soft Copy 1 19
TECHNOLOGICAL INSTTUTE OF THE PHILIPPINES
QUEZON CITY
PROJECT:
GROUP 12
GROUP LEADER: ORACION,SHAELLA KATE ALA
MEMBERS CANTINA,DENECILLE MAE FLORES
ENGRACIAL,ELLA MAE TAMOLANG
FRIAS,ALDRIAN CAMBA
Thurs
Thurs
Tues
Tues
Wed
Wed
Mon
Mon
Sun
Sun
Sun
Sat
Sat
Sat
Fri
Fri
DURATION(
NO. ACTIVITIES PREDECESSOR
days)
6/22/19
6/23/19
6/25/19
6/26/19
6/27/19
6/28/19
6/29/19
6/30/19
6/24/19
7/1/19
7/2/19
7/3/19
7/4/19
7/5/19
7/6/19
7/7/19
1 Creation of Title 3 -
2 Title Defense 1 1
3 Creation of Gant Chart 2 1
4 Finding Internal and External Adviser 1 2
5 Gathering Data From the Project Location 2 2
6 Creation of Chapter 1
6.1 The Project 2 2,5
6.2 Project Location 1 2,5
6.3 Project Objective 1 2,5
6.4 The Client 2 2,5
6.5 Scope and Limitation 2 6.3
6.6 Project Development 2 6.1,6.2,6.3,6.4,6.5
9 Checking of Chapter 1 1 6.1,6.2,6.3,6.4,6.5,6.6
10 Revision of Chapter 1 2 6.1,6.2,6.3,6.4,6.5,6.6,9