Sunteți pe pagina 1din 8

Back to Menu IPA09-E-131

PROCEEDINGS, INDONESIAN PETROLEUM ASSOCIATION


Thirty-Third Annual Convention & Exhibition, May 2009

DYNAMIC OPTIMIZATION MODEL AND ECONOMIC ANALYSIS


FOR GAS PIPELINE: CASE STUDY OF MATINDOK BLOCK

Arsegianto*
Evi Wahyuningsih*
Kunarto*
Widia Kusumastuti*
Suprapto Sumardan**

ABSTRACT INTRODUCTION

The design of gas pipeline requires information of Recently, natural gas demands have been increasing
gas rate and pressure of gas to be delivered. significantly as the government lunched the policy
Investment for pipeline and compressor are not of diversifying energy sources. Lower price and
inexpensive, therefore economic study through environmentally more benign makes gas become
optimization process is required to minimize the more competitive and ready to substitute for oil
cost. fuel. This situation has driven the energy
management planner as well as oil and gas
In reality, gas demand increases over time so contractors to conceive more progressive plan and
“static” optimization of pipe size to deliver the gas strategy to supply natural gas with abundant
will not fit to the condition. New pipeline might be demand.
installed to serve the increased demand in the future
if the existing pipe size is designed just to serve the Pipeline is still the best production facility to
current demand, while oversized pipe diameter transmit gas for long distance consumers. Pipeline
would be wasteful to serve the current demand. An construction is depending on the quantity of gas, the
optimization using dynamic model, then, would suit condition of produced fluid, topography, and
for the problem raised. distances from produced field to gas buyers. The
gas transmission network system includes source of
This paper explains how dynamic model can assist gas, delivery point and compressor station used to
gas pipeline design for increasing demand. This reach the desire pressure to deliver the gas.
model wraps up the long term period of fulfilling
gas demand with an optimum strategy of pipeline The development of gas transmission pipeline
development. network consumes a huge investment cost. Two
main components of cost are the cost related to
A case study presented in this paper outlines the pipeline system and the cost related to compressor
dynamic model to optimize gas pipeline in system. The cost of pipeline depends on its
Matindok Block, in Sulawesi. The economic aspect diameter, which increases with respect to the
is also discussed as objective parameter in the diameter of pipe. The cost of compressor depends
optimization model. The study gives on its power. The use of small pipe will increase the
recommendation of constructed pipeline and pressure drop and consequently will need
compressor design based on technical aspect and compressor with high power, which then increases
economic analysis which satisfies all design the compressor cost. In order to minimize the total
constrains. cost, we have to find the proper balance between
pipeline cost and the compressor cost.
Keywords: gas transmission pipeline, dynamic
optimization Somehow, the design of pipeline network should
also satisfy some constraints. The constraints are
pipeline flow equation and allowed maximum
pressure related to the pipe strength.
* Institute of Technology Bandung
** PT. Pertamin EP
Back to Menu

By using pipeline optimization result the operator the least difference heuristic algorithm. Using this
can set the size of pipeline and compressor to method, the solutions can be used to give
anticipate increasing demand along the life cycle of alternatives pipe sizes which close to possible
the project. This method is also able to handle optimum answer. In this case, the pipe sizes
future problem when gas demand and new (diameter and wall thickness) are available in data
consumers join the pipeline network. base and pipe design is determined based on API
classification.
Gas demanded by consumers must be considered
the reservoir capacity to produce gas. Generally, investment in pipe gas transmission
comprises of investment cost for pipe and
Important components that must be considered investment cost for compressor. Investment cost for
before flowing the gas to consumers as follows: pipe depends on the line and terrain as well as its
location. Cost generally increases with size and is
1. Gas quantity (MMSCFD) and yearly gas much higher in densely populated areas. The
quantity (BSCFY) optimum diameter of pipe can be determined based
2. Contract period ( 15, 20, 0r 25 years) on economic and technical consideration. Economic
3. Gross Heating Value (GHV) and Net Heating pipe diameter can minimize capital cost and
Value( NHV) operational cost. Larger the size of pipe diameter
4. Gas composition interval (C1,C2,….,C5+) will increase the capital cost, but will minimize
5. Pressure and temperature at gas sale gate operational cost since the pressure drop is lower.
6. Minimum and maximum allowable gas flow
rate Cost formulas used in this paper as follows:
7. Location and distance from gas source
1. The annual capital cost for pipeline depends on
METHOD its diameter and wall thickness.
CI P = 15,894 C p L ( OD- t ) t (1)
Minimization in gas transmission pipeline is one of 2. Total operating cost is linear function of
problems faced by several gas industries in compressor horse power and pipeline maintenance
Indonesia. The features needed in gas transmission cost.
system including;
OCcomp = 0.74569885 (1+Ch p ) ghp Ce Hy (2)
1. The optimal diameter sizes. OCpipe = Cfp× CIP (3)
2. The minimum recommended diameter size and
thickness of the pipeline. 3. Total Cost is calculated as follows.
3. The operating pressure of the compressor and
the gas in pipeline. TotalCost =CIP +CIC+OCpipe +OCcomp + ROW + Labor + Misc (4)
4. The maximum number of compressor and
horsepower required.
Case Study
The parameters to be considered for network
Figure 1 gives an illustration of Matindok Block
optimization are initial investment cost, operating
gas pipeline development. Topography data shows
and maintenance cost of pipeline and compressor,
that Donggi Field is the furthest field from
as well as other cost included in this system.
consumer with 60.5 km of distance followed by
The variables that associate with gas transmission
Minahaki with 48. 3 km. The gas rate demand at
system are:
first year is set to 45 MMSCF sent from Donggi
Field and 46 MMSCF of gas delivered from
1. Gas flow rate (Qg)
Matindok Field. For the next five years it is
2. Inlet pressure (Pinlet)
predicted that gas production from Donggi Field
3. Outlet Pressure (Poutlet)
will be increased to 60 MMSCFD to satisfy gas
4. Pipe diameter (ID, OD) demand. Gas composition for each field is shown in
5. Pipeline segment
Table 1. Pipeline design and cost properties are
6. Suction pressure of compressor (Ps)
shown in Table 2 and 3 respectively.
7. Discharge pressure of compressor (Pd)

The method used is a non linier programming called Using Transgas method, gas pipeline is optimized to
double heuristic method, which is a modification of obtain the optimum diameter and compressor size.
Back to Menu

Since gas rate design is not constant due to McAllister, E.W., 2002, Pipeline Rules of Thumb
increasing gas demand in future, a dynamic Handbook, 5th edition, p.575-576
programming is applied to solve the optimization
problem. Steiner, H.M., 1996, Engineering Economic
Principles, 2nd edition, p.143-162; 239-241; 267.
Each pipe is optimized using pertinent data and pipe
constraints. To find optimum diameter API 56 XL
American Petroleum Institute., 1980, API
data base is used with range of 10 in – 40 in of
Specification for Line Pipe,p.15
diameter. Applying dynamic optimization method
the optimum diameter result for each pipe segment
is the available diameter and thickness that exist in
pipeline industry. Using gas rate design for each Nomenclature
field as shown in Table 4 and also considering the
increase of gas production at year 5, the method Ce = electricity price (US$/Kwh)
gives pipeline optimal design as shown in Table 5. Cfp = fraction of pipe operating cost to annual
TransGas program shows that the constructed investment cost of pipeline
pipeline for each segment is 12.75 inch. It means Chp = compressor price (US$/hp)
the only variable that will be changed due to Cins = Pipe installation cost (US$/inch/m)
changes in gas rate is the compressor size for each Cp = pipe unit price (US$/ton)
gas source which gives different compressor sizes d = pipe inside diameter (in)
for year 1, 5 and 20 as shown in Table 6 D = pipe outside diameter (in)
E = join factor
The case also presents the economic calculation for F = design factor
pipe and compressor investment and operating cost ghp = compressor horsepower (hp)
as its objective function as shown in Table 7. h = elevation (ft)
Hy = operating hours compressor in a year
CONCLUSION (hour)
k = adiabatic (isentropic) exponent
Pipeline optimization is a method to minimize total L = pipe length (mile)
cost (all cost incurred) along the project life cycle. M = non-linear constant between pipe’s
For the dynamic case represented by the increasing price and pipe diameter
demand of gas delivery through the pipeline, n = life time of the equipment
information of future value this parameter has to be pd = compressor discharge pressure (psia)
carefully predetermined since this parameter ps = compressor suction pressure (psia)
determines the optimum value of pipe diameter and pb = base pressure (psia)
compressor size and location. Qg = gas flow rate (MMSCFD)
r = discount rate
REFERENCES S = yield strength pipe (psia)
t = wall thickness (inch)
Arsegianto, 2000, Diktat Kuliah: Ekonomi Minyak T = temperature of gas (oR)
dan Gas Bumi, p.2-8 – 2-9; 2-19 Departemen Tb = base temperature (oR)
Energi dan Sumber Daya Mineral., 2004, Kebijakan Td = temperature derating factor
Energi Nasional 2003-2020, p.3;43 Z = gas deviation factor
Back to Menu

TABLE 1 - GAS COMPOSITION

Donggi Field gas Matindok Field gas Gas mixture


Component composition (% composition (% composition
mole) mole) (%mole )
Hydrogen Sulfide 0.1391 0.384 0.22910
Carbondioxide 3.18 2.23043 2.83104
Nitrogen 1.14213 3.03 1.83591
Methane 91.22076 80.97919 87.45706
Ethane 1.5158 6.49778 3.34664
Propane 1.20215 3.06306 1.88602
i-Butane 0.34065 0.7275 0.48281
n-Butane 0.33898 0.94917 0.56322
i-Pentane 0.18483 0.65306 0.35690
n-Pentane 0.1087 0.39829 0.21512
Hexanes 0.08113 0.34852 0.17939
Heptane plus 0.54367 0.73681 0.61465

TABLE 2 - COMPRESSOR PROPERTIES

Maximum HP 20,000 hp
Ep 0.85
k 1.4
Hy 8,670 hours
Pb 14.7 psia
Tb 520 Rankine
Back to Menu

TABLE 3 - COST PROPERTIES

Allowed IRR 12%

r 10%

n 20 years

Cfp 4%

Ce 0.1 US$/Kwh

Cp 5,000 US$/ton

Chp 1,000 US$/hp

ROW 10 US$/m

CIns 20 US$/inch/m

TABLE 4 - GAS PRODUCTION YEAR 1-20

Year Qg Donggi ((MMSCFD) Qg Matindok (MMSCFD)

0 45 46
5 45 60
20 60 60

TABLE 5 - PIPE OPTIMUM DIAMETER

Pipe Segment Optimum Diameter (inch)

Donggi - Junction 12.75


Matindok Junction 12.75
Junction - LNG 12.75
Back to Menu

TABLE 6 - COMPRESSOR OPTIMUM SIZE

Donggi Matindok
Year

Pd hp Pd hp
1 976 2704 841 1900
5 1056 3846 879 2256
20 1056 3846 917 2256

TABLE7 - PIPELINE CONSTRUCTION TOTAL COST

Pipe Cost 92 (Million US$)


Pipe Installation Cost 15.6 (Million US$)
Pipe Investment Cost 76.4 (Million US$)
Pipe Operation Cost 3.05 (Million US$)
Compressor Investment Cost 3.1 (Million US$)
Compressor Operation Cost 2.4 (Million US$)
Back to Menu

Compressor Design

A1= 0.31506237
A2= -1.04670990
A3= -0.57832729
A4= 0.53530771
A5= -0.61232032
A6= -0.10488813
A7= 0.68157001
A8= 0.68446549

Gas Flow Equation


Back to Menu

BS Matindok
Ps= 400 psia

4.763 km

LNG plant
15.07 km

45.4 km
Pout= 700 psia
BS Donggi

Ps= 500 psia

Figure 1 - Matindok Block Gas Pipeline Plan

S-ar putea să vă placă și