PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Excavate and Remove


Excavate Spoil Heaps to Transport, 0.6m3 bucket, Sand/Soil m3 hours 14.50 20.00 25.60 0.0690 0.0500 0.0391
Excavate Spoil Heaps to Transport, 0.6m3 bucket, Gravel Beds m3 hours 15.20 20.40 25.60 0.0658 0.0490 0.0391
Excavate Spoil Heaps to Transport, 0.6m3 bucket, Clay/Chalk m3 hours 12.30 18.50 23.20 0.0813 0.0541 0.0431
Excavate Spoil Heaps to Transport, 0.6m3 bucket, Boulder Clay m3 hours 11.20 16.90 21.30 0.0893 0.0592 0.0469
Excavate Spoil Heaps to Transport, 1.1m3 bucket, Sand/Soil m3 hours 25.40 30.30 35.70 0.0394 0.0330 0.0280
Excavate Spoil Heaps to Transport, 1.1m3 bucket, Gravel Beds m3 hours 25.60 31.30 37.00 0.0391 0.0319 0.0270
Excavate Spoil Heaps to Transport, 1.1m3 bucket, Clay/Chalk m3 hours 22.50 27.80 33.30 0.0444 0.0360 0.0300
Excavate Spoil Heaps to Transport, 1.1m3 bucket, Boulder Clay m3 hours 18.90 24.40 30.30 0.0529 0.0410 0.0330
Load Spoil to Barge, capacity 2,000m3 hours - 8.00 - - 0.1250 -
Load Spoil to Barge, capacity 1,500m3 hours - 6.50 - - 0.1538 -
Load Spoil to Barge, capacity 1,000m3 hours - 5.50 - - 0.1818 -
Spoil conveyor, 600mm belt, 150m/min m3 hours - 260.00 - - 0.0038 -

Concrete Road surfacing


Concrete Road surfacing, Kerbs or Side Haunches m3 hours 0.40 - 2.5000 -
Concrete Road surfacing, 150mm thick m2 hours 12.50 - 0.0800 -
Concrete Road surfacing, 200mm thick m2 hours 7.70 - 0.1299 -
Concrete Road surfacing, 300mm thick m2 hours 6.70 - 0.1493 -

Basecourse Production Rates


Urban environment:
Spread & Compact Production = 30m3/hr m3 hours 30.00 - 0.0333 -
Trimming Production = 250m2/hr m2 hours 250.00 - 0.0040 -
Rural environment:
Spread & Compact Production = 50m3/hr m3 hours 50.00 - 0.0200 -
Trimming Production = 350m2/hr m2 hours 350.00 - 0.0029 -

Working Platforms
Metal KwikStage, 5 Boards with 2m lifts m run hours 11.10 11.90 12.50 0.0901 0.0840 0.0800
Metal KwikStage, 5 Boards with 3m lifts m run hours 9.10 10.00 10.50 0.1099 0.1000 0.0952
Metal KwikStage, House Scaffold with 3 lifts m run hours 2.80 3.20 3.80 0.3571 0.3125 0.2632
Metal Tube and Fittings, 5-6 Boards wide m run hours 3.20 3.70 4.60 0.3125 0.2703 0.2174
Tube and Fitting Platforms, 50-250m3 m3 hours 10.60 12.50 18.50 0.0943 0.0800 0.0541
Tube and Fitting Platforms, 250-1000m3 m3 hours 18.50 22.50 24.50 0.0541 0.0444 0.0408
Tube and Fitting Platforms, over 1000m3 m3 hours 24.50 30.00 33.50 0.0408 0.0333 0.0299
Tube and Fitting Platforms, striking % x erect - 200.00 - - 200.00 -

Waterproofing
Asphalt coatings, horizontal surfaces m2 hours 3.50 4.20 5.80 0.2857 0.2381 0.1724
Asphalt coatings, vertical surfaces m2 hours 1.20 1.70 2.20 0.8333 0.5882 0.4545
Bituminous Brushed application, 2 coats m2 hours 4.80 5.00 6.30 0.2083 0.2000 0.1587
Bituminous Brushed application, 3 coats m2 hours 3.30 3.50 4.40 0.3030 0.2857 0.2273
Bituminous Sheets, horizontal surfaces m2 hours 3.80 4.00 4.80 0.2632 0.2500 0.2083
Bituminous Sheets, vertical surfaces m2 hours 3.30 3.50 4.20 0.3030 0.2857 0.2381
Polythene Sheets, horizontal surfaces m2 hours - 20.00 - - 0.0500 -
Bentonite Sheets, horizontal surfaces m2 hours 18.70 25.00 31.30 0.0535 0.0400 0.0319
Bentonite Sheets, vertical surfaces m2 hours 11.20 15.00 17.30 0.0893 0.0667 0.0578
Epoxy Based application, 1 coat m2 hours - 75.00 - - 0.0133 -
Epoxy Based application, 2 coat m2 hours - 38.00 - - 0.0263 -

Wallpapering
Strip Existing Wallpaper (3 layers) & Prepare Walls m2 hours - 5.00 - - 0.2000 -
Fix Wallpaper and lining paper m2 hours - 5.00 - - 0.2000 -
Fix Vinyl and Washable paper m2 hours - 4.20 - - 0.2381 -
Fix Ceiling Lining Paper m2 hours - 4.00 - - 0.2500 -

Wall Finishes
Mosaic Tiling, 0.045x0.045m no hours - 1.10 1.50 - 0.9091 0.6667
Clay, quarry Tiles, Window Cills, setout and level m hours - 55.50 - - 0.0180 -
Clay, quarry Tiles, Window Cills, fix, grout and clean m2 hours - 1.50 - - 0.6667 -
Ceramic Tiles 150x150mm, Ledges/Upstands no hours 20.40 27.10 32.00 0.0490 0.0369 0.0313
Ceramic Tiles 150x150mm, Areas under 1.5m2 per room m2 hours 0.90 1.00 1.20 1.1111 1.0000 0.8333
2
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Ceramic Tiles 150x150mm, Areas of 1.5-2.5m2 per room m2 hours 1.40 1.60 1.90 0.7143 0.6250 0.5263
Ceramic Tiles 150x150mm, Areas over 2.5m2 per room m2 hours 1.50 1.70 2.10 0.6667 0.5882 0.4762
Ceramic Tiles 150x150mm, Extra Over for Cutting no hours - 41.60 - - 0.0240 -
Ceramic Tiles 108x108mm, Ledges/Upstands no hours - 62.50 - - 0.0160 -
Ceramic Tiles 108x108mm, Areas under 1.5m2 per room m2 hours 1.00 1.30 1.50 1.0000 0.7692 0.6667
Ceramic Tiles 108x108mm, Areas of 1.5-2.5m2 per room m2 hours 1.60 1.80 2.10 0.6250 0.5556 0.4762
Ceramic Tiles 108x108mm, Areas over 2.5m2 per room m2 hours 1.70 1.90 2.20 0.5882 0.5263 0.4545
Ceramic Tiles 108x108mm, Extra Over for Cutting no hours - 125.00 -  - 0.0080 -
Ceramic Tiles, Grouting Works m2 hours 2.20 2.50 2.60 0.4545 0.4000 0.3846
3
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Underpinning
Concrete Pinning, 4th or 5th pin cycles m day - 1.20 2.20 - 0.8333 0.4545
Brickwork Pinning, 1.0 brick thick m2 hours - 0.40 0.70 - 2.5000 1.4286
Brickwork Pinning, 1.5 brick thick m2 hours 0.10 0.30 - 10.0000 3.3333 -
Brickwork Pinning, 2.0 brick thick m2 hours - 0.20 - - 5.0000 -
Wedge and Pin Method, 102mm wall m hours - 0.80 - - 1.2500 -
Wedge and Pin Method, 215mm wall m hours - 0.70 - - 1.4286 -
Wedge and Pin Method, 317mm wall m hours - 0.50 - - 2.0000 -

Trench Excavation
Hydraulic Excavator, 0.3m3 bucket, Sand/Soil m3 hours 5.60 7.10 8.20 0.1786 0.1408 0.1220
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds m3 hours 4.80 6.10 7.30 0.2083 0.1639 0.1370
Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk m3 hours 4.80 6.10 7.10 0.2083 0.1639 0.1408
Hydraulic Excavator, 0.3m3 bucket, Hard Ground m3 hours 9.70 5.40 6.40 0.1031 0.1852 0.1563
Hydraulic Excavator, 0.4m3 bucket, Sand/Soil m3 hours 20.50 25.00 29.20 0.0488 0.0400 0.0342
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds m3 hours 18.20 22.20 26.00 0.0549 0.0450 0.0385
Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk m3 hours 18.20 22.20 26.00 0.0549 0.0450 0.0385
Hydraulic Excavator, 0.4m3 bucket, Hard Ground m3 hours 17.00 20.00 23.40 0.0588 0.0500 0.0427
Hydraulic Excavator, 0.5m3 bucket, Sand/Soil m3 hours 26.00 28.60 33.10 0.0385 0.0350 0.0302
Hydraulic Excavator, 0.5m3 bucket, Gravel Beds m3 hours 26.30 28.60 33.20 0.0380 0.0350 0.0301
Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk m3 hours 26.30 28.60 33.20 0.0380 0.0350 0.0301
Hydraulic Excavator, 0.5m3 bucket, Hard Ground m3 hours 22.70 25.00 28.80 0.0441 0.0400 0.0347
Excavate and Board Trench, 0.5-1.5m deep, < 2.0m wide m2 hours 3.30 4.50 6.80 0.3030 0.2222 0.1471
Excavate and Board Trench, 1.5-3.0m deep, < 2.0m wide m2 hours 3.00 4.20 6.50 0.3333 0.2381 0.1538
Excavate and Board Trench, 3.0-4.5m deep, < 2.0m wide m2 hours 2.70 4.00 6.00 0.3704 0.2500 0.1667
Excavate and Board Trench, 0.5-1.5m deep, > 2.0m wide m2 hours 6.60 7.10 8.80 0.1515 0.1408 0.1136
Excavate and Board Trench, 1.5-3.0m deep, > 2.0m wide m2 hours 6.20 6.70 9.20 0.1613 0.1493 0.1087
Excavate and Board Trench, 3.0-4.5m deep, > 2.0m wide m2 hours 5.80 6.20 10.50 0.1724 0.1613 0.0952

Trackwork
FST Floating Track Slab, side restraints m days 9.60 - - 0.1042 - -
FST Floating Track Slab, resin pads m days 10.20 - - 0.0980 - -
FST Floating Track Slab, slab units m days 10.60 - - 0.0943 - -
PCBT - Pre-cast Concrete Block Track, in Bored Tunnels m days 17.10 41.00 - 0.0585 0.0244 -
PCBT - Pre-cast Concrete Block Track, in Cut and Cover Tunnels m days - 35.00 - - 0.0286 -
PCBT - Pre-cast Concrete Block Track, in Station Tunnels m days - 35.00 - - 0.0286 -
IST - Isolated Slab Track, in Bored Tunnels m days - 20.00 - - 0.0500 -
IST - Isolated Slab Track, in Cut and Cover Tunnels m days - 34.00 - - 0.0294 -
IST - Isolated Slab Track, in Station m days - 29.00 - - 0.0345 -
FST - Floating Slab Track, in Station m days 3.60 4.60 5.70 0.2778 0.2174 0.1754
Ballasted Track, in Mainline m days 57.00 71.00 115.00 0.0175 0.0141 0.0087
Ballasted Track, in Depot m days - 28.00 - - 0.0357 -
Non-Ballasted Track, in Depot m days 8.50 12.80 17.40 0.1176 0.0781 0.0575
Embedded / Paved Track, in Depot m days - 71.00 - - 0.0141 -
Heavy Maintenance / Train Wash Track, in Depot m days - 29.00 - - 0.0345 -
Maintenance Pit, in Depot m days - 52.00 - - 0.0192 -
Siding Trackwork, in Depot m days - 38.00 - - 0.0263 -

Tower Cranes
Erect and Setup 50m gib days - - - - 11.00 7.50
Dismantle 50m gib days - - - - 10.00 -
Lifting, Reinforcement Bins and Cages, 1st 15m lift lift mins - - - - 3.20 -
Lifting, Reinforcement Bins and Cages, above 1st 15m lift 15m mins - - - - 0.50 -
Lifting, Crane Tracking Time m seconds - - - - 3.30 -

Timber Frames
Roof Trusses no hours - 1.30 - - 0.7692 -
Wall Plates m hours - 2.70 - - 0.3704 -
Roof Rafters m hours - 1.20 - - 0.8333 -
Ceiling Joists m hours - 32.10 - - 0.0312 -
Roof Carcass, Common Rafters, under 3m no hours 18.20 20.00 21.70 0.0549 0.0500 0.0461
Roof Carcass, Common Rafters, 3-6mm no hours 13.30 16.60 18.20 0.0752 0.0602 0.0549
Roof Carcass, Common Rafters, over 6m no hours 14.10 15.60 16.10 0.0709 0.0641 0.0621
Roof Carcass, Jack Rafters, under 3m no hours 18.80 20.10 21.70 0.0532 0.0498 0.0461
4
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Roof Carcass, Jack Rafters, 3-6mm no hours 10.40 16.10 16.60 0.0962 0.0621 0.0602
Roof Carcass, Purlins, under 3m no hours 5.10 5.40 5.80 0.1961 0.1852 0.1724
Roof Carcass, Purlins, 3-6mm no hours 4.30 4.80 5.10 0.2326 0.2083 0.1961
Roof Carcass, Purlins, over 6m no hours 3.50 4.30 4.60 0.2857 0.2326 0.2174
Roof Carcass, Binders, under 3m no hours 5.70 6.60 7.60 0.1754 0.1515 0.1316
Roof Carcass, Binders, 3-6mm no hours 2.10 2.30 2.50 0.4762 0.4348 0.4000
Roof Carcass, Binders, over 6m no hours 1.30 1.50 1.60 0.7692 0.6667 0.6250
Roof Carcass, Hangers, under 3m no hours 8.20 9.00 9.60 0.1220 0.1111 0.1042
Roof Carcass, Collars under 3m no hours 7.60 8.00 9.10 0.1316 0.1250 0.1099
Roof Carcass, Collars 3-m no hours 6.50 7.40 8.30 0.1538 0.1351 0.1205
Roof Carcass, Ridge Boards under 3m no hours 12.00 13.10 15.30 0.0833 0.0763 0.0654
Roof Carcass, Cut Rafter Feet to line no hours 142.00 166.00 175.00 0.0070 0.0060 0.0057

Roof Soffits, Softwood, nailed m hours - 9.20 - - 0.1087 -

Roof Soffits, Softwood, screwed m hours - 3.90 - - 0.2564 -

Roof Soffits Asbestos, under 300mm nailed m hours - 9.10 - - 0.1099 -

Roof Soffits Asbestos, under 300mm screwed m hours - 3.80 - - 0.2632 -

Roof Soffits, Asbestos, over 300mm nailed m hours - 3.50 - - 0.2857 -

Roof Soffits, Asbestos, over 300mm screwed m hours - 1.30 - - 0.7692 -

Roof Facia Panels, Softwood m hours 5.10 7.20 9.30 0.1961 0.1389 0.1075

Roof Facia Panels, Asbestos m hours 1.30 2.50 3.90 0.7692 0.4000 0.2564

Roof Facia Panel Studding, nailed m hours 7.30 8.10 9.00 0.1370 0.1235 0.1111

Roof Facia Panel Studding, screwed m hours 4.60 5.20 5.80 0.2174 0.1923 0.1724

Roof Facia Panel Studding, bolted to beams m hours 5.40 5.90 6.60 0.1852 0.1695 0.1515

Roof Works, Fix Herringbone Strutting m hours - 5.10 - - 0.1961 -

Roof Works, Fix Firing Strips m hours - 25.00 - - 0.0400 -

Roof Works, Fix Drip/Tilt Filleting m hours - 20.50 - - 0.0488 -

Structural Steelwork
Simple Universal Beam Steel Bridge, erect support steel H frames no days - 0.8333 - - 1.2000 -
Simple Universal Beam Steel Bridge, erect 15m truss m days - 3.30 - - 0.3030 -

Stonework
Fix 0.5m2 Stones to Metal Support Frame m2 days 5.60 7.00 7.80 0.1786 0.1429 0.1282
Fix 0.5-0.75m2 Stones to Metal Support Frame m2 days 7.20 9.00 10.10 0.1389 0.1111 0.0990
Fix 0.75-1.0m2 Stones to Metal Support Frame m2 days 6.90 8.70 9.70 0.1449 0.1149 0.1031
Fix Complex Stonework to Metal Support Frame m2 days - 1.80 - - 0.5556 -
Fix Curved Stone Cladding m2 days 6.90 8.00 9.20 0.1449 0.1250 0.1087
Fix Stone Edge Beams/Window Reveals m2 days - 2.30 3.20 - 0.4348 0.3125
Fix Stone Soffits m2 days - 4.00 - - 0.2500 -
Stone Floors m2 days 6.90 10.40 12.20 0.1449 0.0962 0.0820
Granite Wall Panels, First Fix m2 hours - 1.30 - - 0.7692 -
Granite Wall Panels, Second Fix m2 hours - 1.10 - - 0.9091 -

Steel Strutting

Horizontal heavy duty strutting no days - 0.5000 - - 2.00 -

Diagonal heavy duty strutting no days - 0.1667 - - 6.00 -

Steel Frames

Steel Frame and Roof Members Tons days 3.40 - 4.60 0.2941 - 0.2174

Wall Frame, Bow String Truss and Frame Tons days - 1.60 - - 0.6250 -

Roof Frame, Curved Truss and Frame Tons days - 5.20 - - 0.1923 -

Wall Frame, Glazed Frame and Atrium Tons days - 0.30 - - 3.3333 -

Spread and Level

Crawler Shovel, 0.8m3 bucket, Sand/Soil, pushed 5-50m to stockpile m3 hours 13.90 20.40 25.00 0.0719 0.0490 0.0400

Crawler Shovel, 0.8m3 bucket, Sand/Soil, pushed 50-120m to stockpile m3 hours 7.60 9.50 12.60 0.1316 0.1053 0.0794

Crawler Shovel, 0.8m3 bucket, Gravel, pushed 5-50m to stockpile m3 hours 14.20 20.40 25.60 0.0704 0.0490 0.0391

Crawler Shovel, 0.8m3 bucket, Gravel, pushed 50-120m to stockpile m3 hours 7.60 10.20 12.80 0.1316 0.0980 0.0781

Crawler Shovel, 0.8m3 bucket, Clay/Chalk, pushed 5-50m to stockpile m3 hours 12.70 18.40 23.20 0.0787 0.0543 0.0431

Crawler Shovel, 0.8m3 bucket, Clay/Chalk, pushed 50-120m to stockpile m3 hours 6.90 8.90 11.60 0.1449 0.1124 0.0862
5
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Crawler Shovel, 0.8m3 bucket, Boulder Clay, pushed 5-50m to stockpile m3 hours 11.60 16.90 21.30 0.0862 0.0592 0.0469

Crawler Shovel, 0.8m3 bucket, Boulder Clay, pushed 50-120m to stockpile m3 hours 6.30 8.20 10.40 0.1587 0.1220 0.0962

Crawler Shovel, 1.2m3 bucket, Sand/Soil, pushed 5-50m to stockpile m3 hours 23.80 28.50 35.70 0.0420 0.0351 0.0280

Crawler Shovel, 1.2m3 bucket, Sand/Soil, pushed 50-120m to stockpile m3 hours 16.70 18.50 20.40 0.0599 0.0541 0.0490

Crawler Shovel, 1.2m3 bucket, Gravel, pushed 5-50m to stockpile m3 hours 25.00 32.00 37.00 0.0400 0.0313 0.0270

Crawler Shovel, 1.2m3 bucket, Gravel, pushed 50-120m to stockpile m3 hours 17.20 19.30 21.20 0.0581 0.0518 0.0472

Crawler Shovel, 1.2m3 bucket, Clay/Chalk, pushed 5-50m to stockpile m3 hours 21.70 27.50 33.30 0.0461 0.0364 0.0300

Crawler Shovel, 1.2m3 bucket, Clay/Chalk, pushed 50-120m to stockpile m3 hours 15.10 16.90 18.80 0.0662 0.0592 0.0532

Crawler Shovel, 1.2m3 bucket, Boulder Clay, pushed 5-50m to stockpile m3 hours 19.60 24.50 30.30 0.0510 0.0408 0.0330

Crawler Shovel, 1.2m3 bucket, Boulder Clay, pushed 50-120m to stockpile m3 hours 13.70 15.90 17.50 0.0730 0.0629 0.0571

Crawler Shovel, 0.6m3 bucket, 50-200m2, Sand/Soil m3 hours 18.60 28.50 38.50 0.0538 0.0351 0.0260

Crawler Shovel, 0.6m3 bucket, over 200m2, Sand/Soil m3 hours 24.40 37.20 50.00 0.0410 0.0269 0.0200

Crawler Shovel, 0.6m3 bucket, 50-200m2, Gravel m3 hours 18.90 28.60 38.40 0.0529 0.0350 0.0260

Crawler Shovel, 0.6m3 bucket, over 200m2, Gravel m3 hours 24.20 37.20 50.00 0.0413 0.0269 0.0200

Crawler Shovel, 0.6m3 bucket, 50-200m2, Hardcore m3 hours 15.80 23.50 31.20 0.0633 0.0426 0.0321

Crawler Shovel, 0.6m3 bucket, over 200m2, Hardcore m3 hours 19.20 29.60 40.00 0.0521 0.0338 0.0250

Crawler Shovel, 0.6m3 bucket, 50-200m2, Boulder Clay m3 hours 17.20 26.40 35.70 0.0581 0.0379 0.0280

Crawler Shovel, 0.6m3 bucket, over 200m2, Boulder Clay m3 hours 22.20 33.80 45.40 0.0450 0.0296 0.0220

Crawler Shovel, 1.2m3 bucket, 50-200m2, Sand/Soil m3 hours 43.50 48.00 52.60 0.0230 0.0208 0.0190

Crawler Shovel, 1.2m3 bucket, over 200m2, Sand/Soil m3 hours 55.50 61.10 66.70 0.0180 0.0164 0.0150

Crawler Shovel, 1.2m3 bucket, 50-200m2, Gravel m3 hours 43.80 48.30 52.90 0.0228 0.0207 0.0189

Crawler Shovel, 1.2m3 bucket, over 200m2, Gravel m3 hours 55.50 61.10 66.70 0.0180 0.0164 0.0150

Crawler Shovel, 1.2m3 bucket, 50-200m2, Hardcore m3 hours 37.10 40.30 43.50 0.0270 0.0248 0.0230

Crawler Shovel, 1.2m3 bucket, over 200m2, Hardcore m3 hours 47.60 51.60 55.60 0.0210 0.0194 0.0180

Crawler Shovel, 1.2m3 bucket, 50-200m2, Boulder Clay m3 hours 43.80 45.70 47.60 0.0228 0.0219 0.0210

Crawler Shovel, 1.2m3 bucket, over 200m2, Boulder Clay m3 hours 55.60 59.10 62.50 0.0180 0.0169 0.0160

Soil Mix Walls

Three Auger Drill, cement and cure m days 3.80 4.50 6.40 0.2632 0.2222 0.1563

Small or Deep Excavation

Hydraulic Excavator, 0.3m3 bucket, Sand/Soil m3 hours 6.70 8.40 9.90 0.1493 0.1190 0.1010

Hydraulic Excavator, 0.3m3 bucket, Gravel Beds m3 hours 3.20 4.50 5.00 0.3125 0.2222 0.2000

Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk m3 hours 3.30 4.10 5.20 0.3030 0.2439 0.1923

Hydraulic Excavator, 0.3m3 bucket, Hard Ground m3 hours 3.30 4.10 5.20 0.3030 0.2439 0.1923

Hydraulic Excavator, 0.4m3 bucket, Sand/Soil m3 hours 8.20 10.00 11.70 0.1220 0.1000 0.0855

Hydraulic Excavator, 0.4m3 bucket, Gravel Beds m3 hours 7.10 8.70 10.20 0.1408 0.1149 0.0980

Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk m3 hours 6.50 8.30 9.40 0.1538 0.1205 0.1064

Hydraulic Excavator, 0.4m3 bucket, Hard Ground m3 hours 6.30 7.70 9.10 0.1587 0.1299 0.1099

Hydraulic Excavator, 0.5m3 bucket, Sand/Soil m3 hours 12.20 13.30 15.40 0.0820 0.0752 0.0649

Hydraulic Excavator, 0.5m3 bucket, Gravel Beds m3 hours 10.20 11.10 12.90 0.0980 0.0901 0.0775

Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk m3 hours 9.70 10.50 12.10 0.1031 0.0952 0.0826

Hydraulic Excavator, 0.5m3 bucket, Hard Ground m3 hours 6.10 6.70 7.70 0.1639 0.1493 0.1299

Slurry Mix Walls

Crane grab, cement/bentonite and sheet piles m days 1.80 2.50 3.40 0.5556 0.4000 0.2941

Slates and Tiling

Slate Roofs, Welsh Slate 3-5mm m2 days - 18.00 - - 0.0556 -

Slate Roofs, Cumbrian Slate 8-11mm m2 days - 8.50 - - 0.1176 -

Slate Roofs, Asbestos Slates m2 days - 36.00 - - 0.0278 -

Tiled Roofs, Concrete Tiles m2 days - 52.00 - - 0.0192 -

Tiled Roofs, Clay Pan Tiles m2 days - 26.00 - - 0.0385 -

Site Investigation

Pre Drilling, Rercussive or Rotary, soft deposits m hours 8.00 10.00 14.00 0.1250 0.1000 0.0714

Pre Drilling, Wash Boring, grade V/IV rock m hours 2.50 3.20 3.90 0.4000 0.3125 0.2564

Pre Drilling, Triple Tube Sampling, grade V/IV rock m hours 0.40 0.80 0.90 2.5000 1.2500 1.1111

Pre Drilling, Rotary, grade III/II rock m hours 0.20 0.50 0.70 5.0000 2.0000 1.4286
6
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Pre Drilling, Triple Tube Sampling, grade III/II rock m hours 0.10 0.40 0.70 10.0000 2.5000 1.4286

Site Clearance

Shrubs and Bushes, dig up and removal m2 hours - 25.00 38.00 - 0.0400 0.0263

Turf, lifting and removal m2 hours - 2.90 - - 0.3448 -

Trees, small sizes and shrubs m2 hours - 14.00 - - 0.0714 -

Trees and Shrubs, 500mm - 900mm girth no hours - 0.0556 - - 18.00 -

Trees and Shrubs, 900mm - 1200mm girth no hours - 0.0455 - - 22.00 -

Trees and Shrubs, 1200mm - 1500mm girth no hours - 0.0385 - - 26.00 -

Hedges and Roots, 0.5-1.0m high m hours - 0.90 - - 1.1111 -

Hedges and Roots, 1.0-1.5m high m hours - 0.80 - - 1.2500 -

Hedges and Roots, 1.5-2.0m high m hours - 0.60 - - 1.6667 -

Sheeted Roofs

PVC Sheeted Roofs, large areas m2 days - 50.00 - - 0.0200 -

PVC Sheeted Roofs, small areas m2 days - 40.00 - - 0.0250 -

Plastic Profiled Sheet Systems m2 days - 54.00 - - 0.0185 -

Sheet Piling

Vibro/Drop Hammer, 10m deep Sand m days - 55.00 60.00 - 0.0182 0.0167

Vibro/Drop Hammer, 35m deep Sand m days 3.50 32.00 10.50 0.2857 0.0313 0.0952

Secant Piling

Construct 30m dia cofferdam, 255 piles/concrete base weeks - - - - 12.00 -

Screeding

Sand/Cement Floor Screed, 15-20mm thick m2 hours - 4.80 5.70 - 0.2083 0.1754

Sand/Cement Floor Screed, 20-30mm thick m2 hours - 4.60 5.50 - 0.2174 0.1818

Sand/Cement Floor Screed, 30-40mm thick m2 hours 3.20 4.20 5.30 0.3125 0.2381 0.1887

Sand/Cement Floor Screed, 40-50mm thick m2 hours 2.00 3.80 5.20 0.5000 0.2632 0.1923

Sand/Cement Floor Screed, 50-65mm thick m2 hours - 3.30 3.90 - 0.3030 0.2564

Sand/Cement Floor Screed, 65-100mm thick m2 hours - 3.00 3.60 - 0.3333 0.2778

Fix/Setout Screed Battens m hours - 10.00 - - 0.1000 -

Rule of Thumb

Site Investigation Pre Drilling no. days 0.2000 0.2500 0.3333 5.00 4.00 3.00

Ground Excavation, Hydraulic Backhoe m3 days - 50.00 - - 0.0200 -

Bored Piling, 25-70m deep no. days 0.1000 0.1250 0.1667 10.00 8.00 6.00

Formwork Fixing m2 days - 12.00 - - 0.0833 -

Reinforcement Fixing Tonnes days - 0.70 - - 1.4286 -

Concrete Placement m3 days - 16.00 - - 0.0625 -

Scaffold Erection, Steel Falsework m3 days - 140.00 - - 0.0071 -

Blockwork Laying m2 days - 7.00 - - 0.1429 -

Plastering and Rendering m2 days - 12.00 - - 0.0833 -

Blockwork Laying m2 days 7.00 12.00 17.50 0.1429 0.0833 0.0571

Stonework Cladding m2 days - 5.10 - - 0.1961 -

Window Glazing m2 hours - 1.50 - - 0.6667 -

Granolithic Flooring m2 hours - 4.50 - - 0.2222 -

Floor Screeding m2 hours - 4.50 - - 0.2222 -

Floor Screeding m2 days - 60.00 - - 0.0167 -

Ceramic Wall Tiling m2 hours - 1.50 - - 0.6667 -

Rock Tunnels
7
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Excavation, non explosive chemical method, cycle time mins - - - 8.00 6.00 5.50

Excavation, non explosive chemical method, Class I Granite m3 cycle 0.30 0.90 1.20 3.3333 1.1111 0.8333

Excavation, non explosive chemical method, Class II Granite m3 cycle 2.00 2.60 2.90 0.5000 0.3846 0.3448

Excavation, non explosive chemical method, Class III Granite m3 cycle 1.20 1.40 1.80 0.8333 0.7143 0.5556

Restoration Works

Façade Cleaning, Water Jetting m2 days - 25.00 - - 0.0400 -

Façade Cleaning, Acid Etching m2 days - 9.00 - - 0.1111 -

Façade Cleaning, Grit Blasting m2 days - 12.00 - - 0.0833 -

Cladding Restoration, Brickwork m2 days - 6.50 - - 0.1538 -

Cladding Restoration, Stonework courses m days - 20.00 - - 0.0500 -

Rendering

Large Wall Areas, applied in 2 coats m2 hours - 2.20 2.70 - 0.4545 0.3704

Small Wall Areas, applied in 2 coats m2 hours - 1.50 1.70 - 0.6667 0.5882

Narrow Widths, applied in 2 coats m2 hours - 1.20 1.40 - 0.8333 0.7143

Columns and Beams, applied in 2 coats m2 hours - 1.50 1.70 - 0.6667 0.5882

Staircase and Soffits, applied in 2 coats m2 hours - 1.40 - - 0.7143 -

Removable Anchors

Drill 30m shaft hours - - - - 7.00 -

Install strands/setup anchor hours - - - - 6.00 -

Grout in strands hours - - - - 2.00 -

Reinforcement Ratios

Pile Cap, Concrete m3 x Ratio = Rebar Tonnes % ratio - 14.80 - - - -

Base Slab, Concrete m3 x Ratio = Rebar Tonnes % ratio - 13.20 14.10 - - -

Suspended Slab, Concrete m3 x Ratio = Rebar Tonnes % ratio - 20.60 25.60 - - -

Platform Slab, Concrete m3 x Ratio = Rebar Tonnes % ratio - 15.60 - - - -

Columns, Concrete m3 x Ratio = Rebar Tonnes % ratio 15.80 18.70 28.70 - - -

Walls, Concrete m3 x Ratio = Rebar Tonnes % ratio 14.70 15.00 - - - -

Reinforcement

Slabs/Foundations, steelfixing, 6mm tonne hours 0.0248 0.0260 0.0274 40.30 38.40 36.50

Slabs/Foundations, steelfixing, 8mm tonne hours 0.0355 0.0372 0.0388 28.20 26.90 25.80

Slabs/Foundations, steelfixing, 10mm tonne hours 0.0444 0.0485 0.0498 22.50 20.60 20.10

Slabs/Foundations, steelfixing, 12mm tonne hours 0.0592 0.0613 0.0649 16.90 16.30 15.40

Slabs/Foundations, steelfixing, 16mm tonne hours 0.0833 0.0870 0.0917 12.00 11.50 10.90

Slabs/Foundations, steelfixing, 20mm tonne hours 0.1087 0.1163 0.1220 9.20 8.60 8.20

Slabs/Foundations, steelfixing, 25mm tonne hours 0.1449 0.1493 0.1538 6.90 6.70 6.50

Slabs/Foundations, steelfixing, 32mm tonne hours 0.1754 0.1818 0.1923 5.70 5.50 5.20

Slabs/Foundations, steelfixing, 40mm tonne hours 0.1887 0.1961 0.2041 5.30 5.10 4.90

Slabs/Foundations, steelfixing, 50mm tonne hours 0.1923 0.2041 0.2174 5.20 4.90 4.60

Beams/Columns, steelfixing, 6mm tonne hours 0.0181 0.0189 0.0198 55.40 52.80 50.60

Beams/Columns, steelfixing, 8mm tonne hours 0.0258 0.0270 0.0285 38.80 37.00 35.10

Beams/Columns, steelfixing, 10mm tonne hours 0.0339 #VALUE! 0.0372 29.50 28.4 26.90

Beams/Columns, steelfixing, 12mm tonne hours 0.0427 0.0446 0.0457 23.40 22.40 21.90

Beams/Columns, steelfixing, 16mm tonne hours 0.0602 0.0633 0.0662 16.60 15.80 15.10

Beams/Columns, steelfixing, 20mm tonne hours 0.0806 0.0840 0.0885 12.40 11.90 11.30

Beams/Columns, steelfixing, 25mm tonne hours 0.1010 0.1087 0.1149 9.90 9.20 8.70

Beams/Columns, steelfixing, 32mm tonne hours 0.1471 0.1515 0.1613 6.80 6.60 6.20

Beams/Columns, steelfixing, 40mm tonne hours 0.1639 0.1695 0.1786 6.10 5.90 5.60

Beams/Columns, steelfixing, 50mm tonne hours 0.1639 0.1695 0.1786 6.10 5.90 5.60

Walls, steelfixing, 6mm tonne hours 0.0243 0.0245 0.0256 41.20 40.80 39.10

Walls, steelfixing, 8mm tonne hours 0.0342 0.0350 0.0365 29.20 28.60 27.40

Walls, steelfixing, 10mm tonne hours 0.0441 0.0455 0.0472 22.70 22.00 21.20

Walls, steelfixing, 12mm tonne hours 0.0568 0.0578 0.0592 17.60 17.30 16.90

Walls, steelfixing, 16mm tonne hours 0.0806 0.0820 0.0847 12.40 12.20 11.80

Walls, steelfixing, 20mm tonne hours 0.1064 0.1087 0.1149 9.40 9.20 8.70

Walls, steelfixing, 25mm tonne hours 0.1351 0.1389 0.1429 7.40 7.20 7.00

Walls, steelfixing, 32mm tonne hours 0.1429 0.1471 0.1563 7.00 6.80 6.40

Walls, steelfixing, 40mm tonne hours 0.1563 0.1639 0.1695 6.40 6.10 5.90

Walls, steelfixing, 50mm tonne hours 0.1887 0.1961 0.2083 5.30 5.10 4.80

Staircases, steelfixing, 6mm tonne hours 0.0204 0.0208 0.0220 48.90 48.00 45.50
8
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Staircases, steelfixing, 8mm tonne hours 0.0291 0.0298 0.0313 34.40 33.60 31.90

Staircases, steelfixing, 10mm tonne hours 0.0376 0.0388 0.0412 26.60 25.80 24.30

Staircases, steelfixing, 12mm tonne hours 0.0478 0.0490 0.0513 20.90 20.40 19.50

Staircases, steelfixing, 16mm tonne hours 0.0685 0.0694 0.0725 14.60 14.40 13.80

Staircases, steelfixing, 20mm tonne hours 0.0885 0.0926 0.0952 11.30 10.80 10.50

Staircases, steelfixing, 25mm tonne hours 0.1163 0.1190 0.1220 8.60 8.40 8.20

Rainwater Works

UPVC Downpipes, 75mm m hours - 3.30 - - 0.3030 -

UPVC Guttering, 75mm m hours - 3.10 - - 0.3226 -

UPVC RWP Fittings, 75mm no hours - 3.10 - - 0.3226 -

Cast Iron Downpipes, 75mm m hours - 2.10 - - 0.4762 -

Cast Iron Guttering, 75mm m hours - 2.50 - - 0.4000 -

Cast Iron RWP Fittings, 75mm no hours - 2.20 - - 0.4545 -

Aluminium Downpipes, 72mm m hours - 2.50 - - 0.4000 -

Aluminium Guttering, 72mm m hours - 2.90 - - 0.3448 -

Aluminium RWP Fittings, 72mm no hours - 1.90 - - 0.5263 -

Power Supply

AC Install 2 no Service transformers, 6 men days - - - - 12.00 -

AC Install 2 no Switchgear, 7 men days - - - - 12.00 -

AC Install Associated Trays and ladders, 3 men days - - - 11.00 5.00 -

AC Cable Terminations in Tx and SWG Rooms, 3 men days - - - 12.00 6.00 -

DC Install Insulated Flooring in DC Room, 1 men days - - - - 5.00 -

DC Install 1 set Rectifier Transformer and Rectifier, 7 men days - - - - 1.00 -

DC Install Switchgear, 7 men days - - - - 10.00 -

DC Primary Cable Terminations and Busduct, 18 men days - - - 12.0 9.00 -

DC Secondary Cable Terminations and Connections, 9 men days - - - 12.0 6.00 -

Trackside Cabling 33kV/Pilot Cables, 10 men m run days 2,100.00 - - 0.0005 - -

Trackside Cabling Terminations, 6 men days - - - - 1.0 -

Post Tensioning

Lag for Initial Stress Tensioning after 1st bay cast hrs - - - - 48.00 -

Lag for Final Stress Tensioning after Initial Stress hrs - - - - 120.00 -

Plastering

Browning (undercoat), Internal Walls under 2.5m high m2 hours 2.20 2.80 3.10 0.4545 0.3571 0.3226

Browning (undercoat), Internal Walls over 2.5m high m2 hours 2.10 2.60 2.80 0.4762 0.3846 0.3571

Browning (undercoat), Reveals and Columns less than 100mm wide m2 hours 9.90 10.00 10.10 0.1010 0.1000 0.0990

Browning (undercoat), Reveals and Columns 100-200mm wide m2 hours 5.20 5.40 6.40 0.1923 0.1852 0.1563

Browning (undercoat), Reveals and Columns 200-300mm wide m2 hours 3.30 3.60 3.90 0.3030 0.2778 0.2564

Covings m2 hours - 5.00 - - 0.2000 -

Skimming (topcoat), Internal Walls under 2.5m high m2 hours 6.10 6.70 7.30 0.1639 0.1493 0.1370

Skimming (topcoat), Internal Walls over 2.5m high m2 hours 5.50 6.10 6.70 0.1818 0.1639 0.1493

Skimming (topcoat), Reveals and Columns less than 100mm wide m2 hours 12.60 13.80 15.40 0.0794 0.0725 0.0649

Skimming (topcoat), Reveals and Columns 100-200mm wide m2 hours 7.70 8.30 9.80 0.1299 0.1205 0.1020

Skimming (topcoat), Reveals and Columns 200-300mm wide m2 hours 4.50 5.00 5.50 0.2222 0.2000 0.1818

Plaster Board to Ceilings m2 hours 3.20 4.50 5.50 0.3125 0.2222 0.1818

Plastering Ceilings, 1 Bonding, 1 Skimming m2 hours 1.10 1.70 2.40 0.9091 0.5882 0.4167

Plastering Ceilings, Topcoat Skimming m2 hours 2.70 3.20 5.40 0.3704 0.3125 0.1852

Plasterboard

Boarding to Plaster dabs m2 hours 3.60 4.00 5.50 0.2778 0.2500 0.1818

Boarding to Stud-work/Metal Lathes m2 hours 4.00 5.00 6.70 0.2500 0.2000 0.1493

Boarding 12mm nailed to studding m2 hours - 12.50 - - 0.0800 -

Boarding 19mm nailed to studding m2 hours - 16.50 - - 0.0606 -

Tape, Jointing and Sanding m hours - 10.00 - - 0.10 -

Partitioning

Timber Studding m hours 5.90 6.20 6.80 0.1695 0.1613 0.1471

Metalwork System (MF) Studding m2 hours 1.60 2.00 2.50 0.6250 0.5000 0.4000

Tape, Joint Sand and Top Coat Plasterboard m2 hours 1.10 1.50 2.10 0.9091 0.6667 0.4762
9
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Skimming to Plasterboards m2 hours 5.50 6.10 6.70 0.1818 0.1639 0.1493

5mm Hardboard Paneling, excluding studding time m2 hours - 3.20 3.60 - 0.3125 0.2778

100mm Pine Paneling, excluding studding time m2 hours 0.80 1.10 1.40 1.2500 0.9091 0.7143

Quality Hardwood Paneling, excluding studding time m2 hours 0.30 0.50 0.60 3.3333 2.0000 1.6667

Fix 50mm Rocksil Insulation to cavities m2 hours - 17.80 20.20 - 0.0562 0.0495

Fix Timber Studding and Paramount Partitions m2 hours 2.60 3.00 3.40 0.3846 0.3333 0.2941

Fix Timber Studding and Demountable Partitions m2 hours 0.80 1.10 1.60 1.2500 0.9091 0.6250

Fix Timber Studding and Hills Duraboard Partitions m2 hours 3.00 3.50 3.90 0.3333 0.2857 0.2564

Fix Timber Studding and Gyproc Laminated Partitions m2 hours 2.20 2.60 2.90 0.4545 0.3846 0.3448

Stud Partitions, Butt Jointed, nailed m hours 5.90 7.30 9.10 0.1695 0.1370 0.1099

Stud Partitions, Butt Jointed, screwed m hours 3.50 4.60 5.80 0.2857 0.2174 0.1724

Stud Partitions, T&G Jointed, nailed m hours 2.90 3.60 4.80 0.3448 0.2778 0.2083

Stud Partitions, T&G Jointed, screwed m hours 2.10 2.80 3.70 0.4762 0.3571 0.2703

Stud Partitions, Fix Sole Plates m hours - 11.10 - - 0.0901 -

Stud Partitions, Fix Noggins m hours - 16.60 - - 0.0602 -

Stud Partitions, Drill 25-40mm Holes no hours - 28.50 - - 0.0351 -

Fix Toilet Partition System, Separation panels no hours - 1.25 - - 0.80 -

Fix Toilet Partition System, Wall Front Panels no hours - 1.43 - - 0.70 -

Fix Toilet Partition System, Separation Front Panels no hours - 1.67 - - 0.60 -

Fix Toilet Partition System, End Front Panels no hours - 1.67 - - 0.60 -

Fix Toilet Partition System, Hang Door to Panel no hours - 2.50 - - 0.40 -

Fix Toilet Partition System, Hand Door plugged to wall no hours - 1.67 - - 0.60 -

Fix Toilet Partition System, Fix Head Rails no hours - 10.00 - - 0.10 -

Painting

Prepare Walls m2 hours - 14.20 - - 0.0704 -

Prepare Doors m2 hours - 12.50 - - 0.0800 -

Prepare Door Frames m hours - 25.00 - - 0.0400 -

Burn Off / Heat Strip Paintwork m2 hours - 1.10 - - 0.9091 -

Internal Timber, 1 coat primer before fixing, generally m2 hours - 6.70 - - 0.1493 -

Internal Timber, 1 coat primer before fixing, timber lengths m hours - 20.00 - - 0.0500 -

Internal Timber, knot, 1 primer, stop, 1 undercoat, 1 gloss m2 hours - 1.70 2.10 - 0.5882 0.4762

Internal Timber, touchup primer, 1 undercoat, 1 coat gloss m2 hours - 3.10 3.80 - 0.3226 0.2632

Internal Timber, polyurethane varnish, 2 coats m2 hours - 3.30 - - 0.3030 -

Internal Timber, polyurethane varnish, 3 coats m2 hours - 2.20 - - 0.4545 -

Internal Timber, linseed oil to hardwood, 2 coats m2 hours - 3.60 - - 0.2778 -

External Timber, windows and frames m2 hours - 2.40 - - 0.4167 -

External Timber, knot, 1 primer, 2 undercoats, 1 coat gloss, m2 hours - 1.50 - - 0.6667 -

External Timber, touchup primer, 2 undercoats, 1 coat gloss, m2 hours - 2.00 - - 0.5000 -

External Timber, 2 coats wood preservative m2 hours - 4.00 - - 0.2500 -

External Timber, 3 coats polyurethane varnish m2 hours - 2.00 - - 0.5000 -

Internal Walls, 2 coats emulsion to plaster m2 hours - 8.00 - - 0.1250 -

Internal Walls, 2 coats emulsion to brick/blockwork m2 hours - 6.00 - - 0.1667 -

Internal Walls, 1 mist, 2 coats emulsion to plaster m2 hours - 6.00 - - 0.1667 -

Internal Walls, 1 mist, 2 coats emulsion to brick/blockwork m2 hours - 4.50 - - 0.2222 -

Internal Walls, 1 primer, 1 undercoat, 1 gloss to plaster m2 hours - 2.30 - - 0.4348 -

Internal Walls, undercoat to door frame m hours - 20.00 - - 0.0500 -

Internal Walls, gloss to door frame m hours - 16.50 - - 0.0606 -

Internal Walls, undercoat to door m2 hours - 7.10 - - 0.1408 -

Internal Walls, gloss to door m2 hours - 6.20 - - 0.1613 -

External Walls, 2 coats sandtex to render/concrete m2 hours - 2.50 - - 0.4000 -

External Walls, 2 coats sandtex to brick/blockwork m2 hours - 2.00 - - 0.5000 -

External Walls, 1 sealer, 2 emulsion to render/concrete m2 hours - 2.00 - - 0.5000 -

External Walls, 1 sealer, 2 emulsion to brick/blockwork m2 hours - 1.70 - - 0.5882 -

Floors, epoxy paint m2 hours - 2.90 - - 0.3448 -

Ceilings, emulsion paint, 2 coats m2 hours - 6.10 - - 0.1639 -

Ceilings, emulsion paint, 3 coats m2 hours - 5.00 - - 0.2000 -

Ceilings, textured paint m2 hours - 4.20 - - 0.2381 -

Ceilings, artex finish m2 hours - 4.10 - - 0.2439 -

Internal Steelwork, 1 primer, 1 undercoat, 1 gloss m2 hours 1.30 2.40 - 0.7692 0.4167 -

External Steelwork, 1 primer, 2 undercoats, 1 gloss m2 hours 0.90 1.70 - 1.1111 0.5882 -

Guttering Steelwork, 1 coat primer, 2 undercoats, 1 gloss m hours - 2.50 - - 0.4000 -

NATM Tunnels

Standard Advance Method, used on tunnels with max diameter m - 7.00 - - - -

Half Face Advance Method, used on tunnels with max diameter m - 10.00 - - - -

Double side Drift Advance Method, used on tunnels with diameter over m - 10.00 - - - -

Double side Drift Advance Method, used on tunnels with diameter over m - 10.00 - - - -

Excavation, London Clay, internal diameter under 7.0m m days 2.50 2.90 3.20 0.4000 0.3448 0.3125
10
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Excavation, London Clay, internal diameter 7.0-10.0m m days 1.50 2.00 2.50 0.6667 0.5000 0.4000

Excavation, London Clay, internal diameter over 10.0m m days 1.00 1.30 1.5 1.0000 0.7692 -

Excavation, Woolwich/Reading Beds, internal diameter 2.0-7.0m m days 1.50 1.80 2.0 0.6667 0.5556 -

Excavation, Woolwich/Reading Beds, internal diameter 7.0-10.0m m days - 1.50 - - 0.6667 -

Excavation, Woolwich/Reading Beds, internal diameter over 10.0m m days - 1.00 1.5 - 1.0000 -

Excavation, London Clay, Inclined Tunnels, diameter 2.0-7.0m m days 1.50 2.00 3.2 0.6667 0.5000 -

Excavation, London Clay, Inclined Tunnels, diameter 7.0-10.0m m days 0.50 1.00 2.2 2.0000 1.0000 -

Excavation, London Clay, Vertical Shafts, diameter 2.0-9.0m m days 1.00 1.50 2.2 1.0000 0.6667 -

Excavation, London Clay, Vertical Shafts, diameter 9.0-15.0m m days 0.50 1.00 2.6 2.0000 1.0000 -

Excavation, London Clay, Circulation Halls m of circumf days 0.80 1.00 1.2 1.2500 1.0000 -

Excavation, London Clay, Junction Excavation m days - 0.20 - - 5.0000 -

Mucking Capacity, 1 access with 2 crews m3 days 190.00 225.00 279.0 0.0053 0.0044 -

Mucking Capacity, 1 access with 4 crews m3 days 255.00 300.00 366.0 0.0039 0.0033 -

Mucking Capacity, 2 access with 4 crews m3 days 382.00 450.00 549.0 0.0026 0.0022 -

Sprayed Secondary Lining, Tunnels, diameter under 6.5m m days 2.10 2.50 2.8 0.4762 0.4000 -

Sprayed Secondary Lining, Tunnels, diameter over 6.5m m days 1.50 2.00 2.4 0.6667 0.5000 -

Sprayed Secondary Lining, Inclined Tunnels, diameter under 6.5m m days 1.50 2.00 2.3 0.6667 0.5000 -

Sprayed Secondary Lining, Inclined Tunnels, diameter over 6.5m m days 1.00 1.50 1.9 1.0000 0.6667 -

Sprayed Secondary Lining, Vertical Shafts, diameter under 6.5m m days 1.80 2.00 2.5 0.5556 0.5000 -

Sprayed Secondary Lining, Vertical Shafts, diameter over 6.5m m days 2.20 2.50 3.1 0.4545 0.4000 -

Sprayed Secondary Lining, Circulation Halls, diameter under 11.0m m days - 2.00 2.3 - 0.5000 -

Sprayed Secondary Lining, Intermediate Landing Tunnels with columns m days 1.70 2.00 2.1 0.5882 0.5000 -

Sprayed Secondary Lining, Intermediate Landing Tunnels without columns m days 1.60 2.10 2.3 0.6250 0.4762 -

Sprayed Secondary Lining, Tunnel Junctions m days - 0.20 0.3 - 5.0000 -

Insitu Permanent Lining, 12m bays, 350-400mm reinforced with PCV backingm days - 8.40 12.0 - 0.1190 -

Insitu Permanent Lining, extra over excavate/lining time to allow for permanent
% lining - 25.00 - - - -

Excavate and Line Cycle Time , Running Tunnels m days 3.20 4.00 4.9 0.3125 0.2500 -

Excavate and Line Cycle Time, Station Access Adits m days 3.30 3.90 4.2 0.3030 0.2564 -

Excavate and Line Cycle Time, Concourse Tunnels m days 2.20 2.50 2.7 0.4545 0.4000 -

Excavate and Line Cycle Time, Escalator Tunnels m days 1.20 1.50 1.7 0.8333 0.6667 -

Metal Decking

Metal Decking, large areas m2 days - 70.00 - - 0.0143 -

Metal Decking, small or complicated m2 days - 28.00 - - 0.0357 -

Titanium Sheeted Roofs m2 days - 9.50 - - 0.1053 -

Copper Roofs, flat work m2 days - 3.00 - - 0.3333 -

Copper Roofs, sloping work m2 days - 2.70 - - 0.3704 -

Zinc Roofs, flat work m2 days - 2.40 - - 0.4167 -

Zinc Roofs, sloping work m2 days - 2.10 - - 0.4762 -

Aluminium Roofs, flat work m2 days - 2.80 - - 0.3571 -

Aluminium Roofs, sloping work m2 days - 1.90 - - 0.5263 -

Lead Roofs, flat work m2 days - 2.50 - - 0.4000 -

Lead Roofs, sloping work m2 days - 2.10 - - 0.4762 -

Lead Roofs, dormer cheeks m2 days - 1.30 - - 0.7692 -

Lead Roofs, flat gutters m days - 88.00 - - 0.0114 -

Lead Roofs, flat copings m days - 76.00 - - 0.0132 -

Lead Roofs, stepped gutters m days - 3.50 - - 0.2857 -

Lead Roofs, shaped copings m days - 3.30 - - 0.3030 -

Lead Roofs, cover step flashings m days - 3.20 - - 0.3125 -

Lead Roofs, rooflight flashings no days - 0.80 - - 1.2500 -

Lead Roofs, domed roof coverings m2 days - 0.70 - - 1.4286 -

Manholes and Gulleys

Concrete Pre-Cast Manhole Units, 610 x 455 x 51 mm no hours - 0.8333 - - 1.20 -

Concrete Pre-Cast Manhole Units, 990 x 610 x 64 mm no hours - 0.6250 - - 1.60 -

Brickwork Manhole, 1.0 brick engineering m2 hours - 0.30 - - 3.3333 -

Brickwork Manhole, 1.5 brick engineering m2 hours - 0.20 - - 5.0000 -

Brickwork Manhole, 2.0 brick engineering m2 hours - 0.20 - - 5.0000 -

Benching to Manhole, under 0.5m2 no hours - 1.1111 - - 0.90 -

Benching to Manhole, 0.5-0.75m2 no hours - 0.8333 - - 1.20 -

Benching to Manhole, 0.75-1.0m2 no hours - 0.5556 - - 1.80 -

Brickwork Manhole, build in pipes, under 150mm dia no hours - 10.0000 - - 0.10 -

Brickwork Manhole, build in pipes, 150-225mm dia no hours - 5.0000 - - 0.20 -

Brickwork Manhole, build in pipes, over 225mm dia no hours - 3.3333 - - 0.30 -

Brickwork Manhole, build in cast iron covers no hours 3.33 1.6667 0.83 0.30 0.60 1.20

Yard Gulleys, 75-150mm dia pipes, bed and level no hours - 2.20 - - 0.4545 -

Yard Gulleys, 150-225mm dia pipes, bed and level no hours - 1.80 - - 0.5556 -

Yard Gulleys, 225-300mm dia pipes, bed and level no hours - 1.50 - - 0.6667 -

Road Gulleys, 600mm deep, bed and level no hours - 1.20 - - 0.8333 -

Road Gulleys, 750mm deep, bed and level no hours - 0.80 - - 1.2500 -
11
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Road Gulleys, 900mm deep, bed and level no hours - 0.40 - - 2.5000 -

Road Gulleys, 1,200mm deep, bed and level no hours - 0.30 - - 3.3333 -

Road Gulleys, install gratings no hours - 5.00 - - 0.2000 -

PVC Manhole no minutes - 0.0667 - - 15.00 -

Lift Installation

Hydraulic Lift, Install 2 to 3 storeys floor weeks - 0.3333 - - 3.00 -

Hydraulic Lift, Install 4 storeys and above floor weeks - 0.5000 - - 2.00 -

Hydraulic Lift, Testing allow 2 wks plus floor days - 1.0000 - - 1.00 -

Standard Lift, Manufacture, test and deliver weeks - - - - 12.00 -

Non-Standard Lift, Manufacture, test and deliver weeks - - - 75.00 65.00 52.00

Landscaping

Top Soil, spread, level and prepare for turf or seeding m2 hours - 2.50 - - 0.4000 -

Top Soil, rake in fertilizer for seeding m2 hours - 25.00 - - 0.0400 -

Planting, Shrubs and Hedges, under 750mm high no hours - 4.00 - - 0.2500 -

Planting, Shrubs and Hedges, over 750mm high no hours - 1.50 - - 0.6667 -

Planting, Saplings, under 3.0m high no hours - 1.70 - - 0.5882 -

Turfing, including for minor preparations m2 hours - 16.80 - - 0.0595 -

Land Drains

Land Drains, Concrete, butt jointed, under 150mm dia, 0-5m run m hours - 11.60 - - 0.0862 -

Land Drains, Concrete, butt jointed, under 150mm dia, 5-30m run m hours - 14.10 - - 0.0709 -

Land Drains, Concrete, butt jointed, under 150mm dia, over 30m run m hours - 18.80 - - 0.0532 -

Land Drains, Concrete, butt jointed, 150-225mm dia, 0-5m run m hours - 8.40 - - 0.1190 -

Land Drains, Concrete, butt jointed, 150-225mm dia, 5-30m run m hours - 10.20 - - 0.0980 -

Land Drains, Concrete, butt jointed, 150-225mm dia, over 30m run m hours - 11.90 - - 0.0840 -

Land Drains, Concrete, butt jointed, 225-300mm dia, 0-5m run m hours - 5.40 - - 0.1852 -

Land Drains, Concrete, butt jointed, 225-300mm dia, 5-30m run m hours - 6.50 - - 0.1538 -

Land Drains, Concrete, butt jointed, 225-300mm dia, over 30m run m hours - 7.90 - - 0.1266 -

Kerbs & Paving

Concrete Slabs, laid on bedding, to slight falls m2 hours 2.70 - 4.20 0.3704 - 0.2381

Concrete Slabs, laid on bedding, to steep falls m2 hours 2.30 - 2.70 0.4348 - 0.3704

Concrete Slabs, laid in mortar, to slight falls m2 hours 1.50 - 2.30 0.6667 - 0.4348

Concrete Slabs, laid in mortar, to steep falls m2 hours 1.10 - 1.50 0.9091 - 0.6667

Concrete Slabs, laid on sand, to slight falls m2 hours 1.70 - 2.80 0.5882 - 0.3571

Concrete Slabs, laid on sand, to steep falls m2 hours 1.60 - 1.90 0.6250 - 0.5263

Cobble Stones, laid in mortar, no patterns m2 hours - 0.30 - - 3.3333 -

Cobble Stones, laid in mortar, with patterns m2 hours - 0.20 - - 5.0000 -

Artificial Stone, laid on sand, with patterns m2 hours - 2.50 - - 0.4000 -

Brick Paviors, in mortar, straight joints m2 hours 0.90 1.30 1.90 1.1111 0.7692 0.5263

Brick Paviors, in mortar, herringbone pattern m2 hours - 1.00 1.20 - 1.0000 0.8333

Gravel Paths, including preparation of sub-base m2 hours - 10.50 - - 0.0952 -

Concrete Paths, 100mm thick, including preparation of sub-base m2 hours - 2.50 - - 0.4000 -

Concrete Kerbs or Channels, laid straight m hours - 6.20 - - 0.1613 -

Concrete Kerbs or Channels, laid to 5m radius m hours - 4.50 - - 0.2222 -

Concrete Kerbs or Channels, laid to 10m radius m hours - 5.00 - - 0.2000 -

Concrete Kerbs or Channels, laid to 20m radius m hours - 5.50 - - 0.1818 -

Stone/Granite Kerbs or Channels, laid straight m hours - 3.50 - - 0.2857 -

Concrete Edging, laid straight m hours - 7.70 - - 0.1299 -

Concrete Edging, laid to 5m radius m hours - 5.80 - - 0.1724 -

Concrete Edging, laid to 10m radius m hours - 6.20 - - 0.1613 -

Concrete Edging, laid to 20m radius m hours - 7.10 - - 0.1408 -

Cutting and Fitting Ends, Concrete Kerbs no hours - 6.60 - - 0.1515 -

Cutting and Fitting Ends, Channels no hours - 5.80 - - 0.1724 -

Cutting and Fitting Ends, Concrete Edging no hours - 8.30 - - 0.1205 -

Ground Compaction

Deep Vibroflot, 3m centres m3 hours 330.00 380.00 465.00 0.0030 0.0026 0.0022

Vibro-Roller, Sand m2 hours 28.50 31.20 45.20 0.0351 0.0321 0.0221

Vibro-Roller, Soil m2 hours - 58.80 - - 0.0170 -

Vibro-Roller, Clay m2 hours - 55.60 - - 0.0180 -

Vibro-Roller, Hardcore m2 hours - 38.40 - - 0.0260 -


12
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Vibro-Roller, Ash m2 hours - 57.80 - - 0.0173 -

Formwork

Pilecaps, < 0.7m2 m2 hours 0.90 1.60 2.00 1.1111 0.6250 0.5000

Pilecaps, 0.7-2.5m2 m2 hours 1.60 2.00 2.30 0.6250 0.5000 0.4348

Pilecaps, 2.5-3.0m2 m2 hours 2.00 2.30 2.50 0.5000 0.4348 0.4000

Pilecaps, > 3.0m2 m2 hours 2.30 2.50 3.10 0.4348 0.4000 0.3226

Ground Beams, < 0.7m2 m2 hours 1.10 1.70 1.80 0.9091 0.5882 0.5556

Ground Beams, 0.7-1.5m2 m2 hours 1.70 1.80 2.50 0.5882 0.5556 0.4000

Ground Beams, 1.5-3.0m2 m2 hours 1.80 2.50 2.60 0.5556 0.4000 0.3846

Ground Beams, 3.0-5.0m2 m2 hours 2.50 2.60 3.50 0.4000 0.3846 0.2857

Elevated Plain Slab Soffit m2 hours 0.60 0.80 1.20 1.6667 1.2500 0.8333

Beams, on erected falsework, width 100-200mm m2 hours 0.90 1.00 1.10 1.1111 1.0000 0.9091

Beams, on erected falsework, width 200-300mm m2 hours 1.00 1.10 1.30 1.0000 0.9091 0.7692

Beams, on erected falsework, width 300-500mm m2 hours 1.20 1.30 1.50 0.8333 0.7692 0.6667

Beams, on erected falsework, width 500-750mm m2 hours 1.50 1.60 1.80 0.6667 0.6250 0.5556

Beams, on erected falsework, width over 750mm m2 hours 1.40 1.50 1.70 0.7143 0.6667 0.5882

Walls, Construct Kickers m2 hours 5.30 7.10 10.00 0.1887 0.1408 0.1000

Walls, Fully Framed Formwork/Struts, 1.0-2.0m2 m2 hours 0.90 1.80 1.90 1.1111 0.5556 0.5263

Walls, Fully Framed Formwork/Struts, 2.0-5.0m2 m2 hours 1.00 2.20 2.50 1.0000 0.4545 0.4000

Walls, Fully Framed Formwork/Struts, over 5.0m2 m2 hours 1.20 2.50 2.90 0.8333 0.4000 0.3448

Walls, StoriForm Shutters, 1.0-3.0m2 m2 hours 1.00 1.40 2.00 1.0000 0.7143 0.5000

Walls, StoriForm Shutters, 3.0-5.0m2 m2 hours 1.90 2.30 3.30 0.5263 0.4348 0.3030

Walls, StoriForm Shutters, 5.0-10.0m2 m2 hours 2.30 2.80 3.50 0.4348 0.3571 0.2857

Walls, StoriForm Shutters, 10.0-15.0m2 m2 hours 3.20 4.50 4.00 0.3125 0.2222 0.2500

Walls, StoriForm Shutters, over 15.0m2 m2 hours 3.80 4.80 5.40 0.2632 0.2083 0.1852

Ground Slabs m2 hours 1.00 1.50 1.80 1.0000 0.6667 0.5556

Columns, Construct Kickers, direct to slab no hours 3.20 4.10 5.40 0.3125 0.2439 0.1852

Columns, Construct Kickers, suspended from soffit slab no hours 1.20 2.80 3.20 0.8333 0.3571 0.3125

Columns, Square Sides, Timber Clamp/Prop, csa < 0.1m2 m2 hours 1.30 1.60 1.80 0.7692 0.6250 0.5556

Columns, Square Sides, Timber Clamp/Prop, csa 0.1-0.4m2 m2 hours 1.80 2.10 2.40 0.5556 0.4762 0.4167

Columns, Square Sides, Timber Clamp/Prop, csa over 0.4m2 m2 hours 2.00 2.30 2.50 0.5000 0.4348 0.4000

Columns, Square Sides, Steel Forms, 1.5 x 1.5 x 9.0m high m2 hours 7.90 9.50 10.30 0.1266 0.1053 0.0971

Columns, Square Sides, Steel Forms, 2.0 x 2.0 x 9.0m high m2 hours 6.90 7.50 8.30 0.1449 0.1333 0.1205

Columns, Square Sides, Steel Forms, 2.0 x 4.0 x 9.0m high m2 hours 8.50 10.20 12.00 0.1176 0.0980 0.0833

Columns, Round Sides, Sacrificial Plastic Mould, 3.0-4.0m dia m2 hours 3.50 4.50 6.00 0.2857 0.2222 0.1667

Columns, Round Sides, Steel Mould, 3.0-4.0m dia m2 hours 5.20 6.50 7.50 0.1923 0.1538 0.1333

Columns, Sloping Column Heads, extra over rate no hours - 0.40 0.29 - 2.50 3.50

Staircases, Stair Soffit, Sloping m2 hours 0.70 0.80 1.00 1.4286 1.2500 1.0000

Staircases, Stair Soffit, Flat Landing m2 hours 0.80 0.90 1.20 1.2500 1.1111 0.8333

Staircases, Wall Strings m2 hours 0.40 0.60 - 2.5000 1.6667 -

Staircases, Open Strings m2 hours 0.70 0.80 - 1.4286 1.2500 -

Staircases, Riser Boards fixed to strings m2 hours - 2.50 2.80 - 0.4000 0.3571

Staircases, Risers fixed to Strings m2 hours - 2.30 2.60 - 0.4348 0.3846

Waffle Flooring, 2.4m grid m2 hours 1.10 1.40 1.80 0.9091 0.7143 0.5556

Shaft Slip Forming mm hours - 300.00 500.00 - 0.0033 0.0020

Table Form, Aluminum System, 400m2 bays m2 hours 2.10 3.20 3.80 0.4762 0.3125 0.2632

Table Form, H-Frame Steel Falsework, 400m2 bays m2 hours 1.90 3.00 3.50 0.5263 0.3333 0.2857

Tunnel Forms, Wall and Slab poured as one m2 hours - 15.60 17.50 - 0.0641 0.0571

Hollorib Decking, lay deck m2 hours - 43.50 47.50 - 0.0230 0.0211

Hollorib Decking, shear connecting studs m2 hours - 29.30 31.20 - 0.0341 0.0321

Stop Ends, no perforations m2 hours 2.80 3.50 4.20 0.3571 0.2857 0.2381

Stop Ends, minor perforations m2 hours 1.20 1.50 1.90 0.8333 0.6667 0.5263

Stop Ends, dense perforations m2 hours 0.90 1.10 1.40 1.1111 0.9091 0.7143

Box Outs, 0.01-0.05m2 no hours 7.60 8.20 9.10 0.1316 0.1220 0.1099

Box Outs, over 0.05m2 no hours 3.10 3.90 4.50 0.3226 0.2564 0.2222

Dummy Frames, under 3.0m2 no hours 4.50 6.20 7.10 0.2222 0.1613 0.1408

Dummy Frames, over 3.0m2 no hours 3.10 3.70 4.50 0.3226 0.2703 0.2222

Floor Finishes

Granolithic Flooring m2 hours - 3.10 - - 0.3226 -

Terrazzo Flooring, in-situ m2 hours - 3.60 - - 0.2778 -

Terrazzo Flooring, pre-cast m2 hours - 4.60 5.10 - 0.2174 0.1961

Mosaic Tiling, 0.045x0.045m m2 hours - 1.50 2.20 - 0.6667 0.4545

Clay, quarry Tiles, small areas, much cutting m2 hours - 0.80 1.10 - 1.2500 0.9091

Clay, quarry Tiles, large areas, little cutting m2 hours - 2.20 2.80 - 0.4545 0.3571

Raised Floor System m2 hours - 2.60 - - 0.3846 -

Linolium/Thermo-Plastic Flooring m2 hours - 3.10 5.00 - 0.3226 0.2000

Thermo-Plastic Floor Tiles m2 hours - 3.30 5.60 - 0.3030 0.1786

Wood Block Flooring, lay blocks m2 hours - 1.50 2.10 - 0.6667 0.4762
13
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Wood Block Flooring, sand and polish m2 hours - 3.10 - - 0.3226 -

Carpeting, Underlay & Gripper m2 hours - 5.60 6.10 - 0.1786 0.1639

Carpeting, Adhesive Fixing m2 hours - 3.50 4.20 - 0.2857 0.2381

Carpeting, Fully Fitted m2 hours - 2.00 2.80 - 0.5000 0.3571

Hardboard Sheeting Coverings, small areas m2 hours - 3.70 4.10 - 0.2703 0.2439

Hardboard Sheeting Coverings, large areas m2 hours - 6.60 7.20 - 0.1515 0.1389

Floor Sheeting Coverings, Lay Lino m2 hours - 9.50 10.50 - 0.1053 0.0952

Flat and Layered Roofs

Asphalt Roof in layers m2 days - 45.00 - - 0.0222 -

Asbestos Sheets in layers m2 days - 39.00 - - 0.0256 -

Felt Roofs, large areas m2 days - 52.00 - - 0.0192 -

Felt Roofs, small or complicated m2 days - 35.00 - - 0.0286 -

Felt Roofs, Gravel roof chippings Tons days - 1.40 - - 0.7143 -

Fencing Works

Site Hoarding, timber posts, plywood nailed to horizontal rails m hours 1.00 1.20 - 1.0000 0.8333 -

Post Erection, Timber / Metal, dig, erect, fix no hours 3.30 4.50 - 0.3030 0.2222 -

Post Erection, Concrete, dig, erect, fix no hours 3.20 4.00 - 0.3125 0.2500 -

Fence Erection, Chainlink, posts at 1.5m m hours - 4.20 - - 0.2381 -

Fence Erection, Chainlink, posts at 2.0m m hours - 4.40 - - 0.2273 -

Fence Erection, Chainlink, posts at 3.0m m hours - 5.50 - - 0.1818 -

Fence Erection, Chestnut Pailings, posts at 1.5m m hours - 23.80 - - 0.0420 -

Fence Erection, Chestnut Pailings, posts at 2.0m m hours - 33.30 - - 0.0300 -

Fence Erection, Chestnut Pailings, posts at 3.0m m hours - 41.60 - - 0.0240 -

Fence Erection, Barbed Wire, posts at 1.5m m hours - 71.40 - - 0.0140 -

Fence Erection, Barbed Wire, posts at 2.0m m hours - 100.00 - - 0.0100 -

Fence Erection, Barbed Wire, posts at 3.0m m hours - 125.00 - - 0.0080 -

Gate Erection, Chainlink on frame no hours - 4.10 - - 0.2439 -

Escalators

Truss type, Overall Installation (excl arch finishes) wks - - - 14.00 12.00 11.00

Truss type, Manufacture, test and deliver wks - - - - 60.00 48.00

Truss type, Phase A assemble truss , position/level wks - - - - 1.00 -

Truss type, Stop-Work for surrounding finishes wks - - - 8.00 6.00 4.00

Truss type, Phase B decking and glazing etc wks - - - - 5.00 -

Truss type, Phase C performance testing wks - - - - 2.00 -

Truss type, Phase D full load testing wks - - - - 2.00 -

Truss type, Phase E final test and inspection wks - - - - 2.00 -

Electrical System

Railway Station 1st Fix wks - - - - 38.0 -

Railway Station 2nd Fix wks - - - - 16.0 -

Railway Station T&C wks - - - - 8.0 -

Cable Installation, 1 cable laid in trench and protect m hours - 6.20 - - 0.1613 -

Cable Installation, 2 cable laid in trench and protect m hours - 5.60 - - 0.1786 -

Cable Installation, 5 cable laid in trench and protect m hours - 4.30 - - 0.2326 -

Cable Installation, 7 cable laid in trench and protect m hours - 3.70 - - 0.2703 -

Cable Installation, 8 cable laid in trench and protect m hours - 3.50 - - 0.2857 -

Cable Installation, 2 cable laid in trench and protect, 100mm dia m hours - 1.80 - - 0.5556 -

Cable Installation, 2 cable laid in trench and protect, 135mm dia m hours - 1.60 - - 0.6250 -

Cable Installation, 3 cable laid in trench and protect, 100mm dia m hours - 1.00 1.50 - 1.0000 0.6667

Cable Installation, 6 cable laid in trench and protect, 100mm dia m hours - 0.70 1.20 - 1.4286 0.8333

Cable Installation, 4 cable laid in trench and protect, 150mm dia m hours 0.70 1.20 3.10 1.4286 0.8333 0.3226

Cable Installation, 36 cable laid in trench and protect, 100mm dia m hours - 0.20 - - 5.0000 -

Cable Installation, 10 cable laid in trench and protect, 100mm dia m hours - 0.50 - - 2.0000 -

Cable Installation, 1 cable laid in trench and protect, 300mm dia m hours - 1.30 - - 0.7692 -

Drainage

PVC Drainage, 1m pipes, 100-150mm dia, 0-5m run m hours - 5.70 - - 0.1754 -

PVC Drainage, 1m pipes, 100-150mm dia, 5-30m run m hours - 8.10 - - 0.1235 -

PVC Drainage, 1m pipes, 100-150mm dia, over 30m run m hours - 9.50 - - 0.1053 -

PVC Drainage, 3m pipes, 100-150mm dia, 0-5m run m hours - 12.20 - - 0.0820 -

PVC Drainage, 3m pipes, 100-150mm dia, 5-30m run m hours - 15.20 - - 0.0658 -
14
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

PVC Drainage, 3m pipes, 100-150mm dia, over 30m run m hours - 18.20 - - 0.0549 -

PVC Drainage, 6m pipes, 100-150mm dia, 0-5m run m hours - 22.20 - - 0.0450 -

PVC Drainage, 6m pipes, 100-150mm dia, 5-30m run m hours - 27.70 - - 0.0361 -

PVC Drainage, 6m pipes, 100-150mm dia, over 30m run m hours - 33.30 - - 0.0300 -

PVC Drainage, 3m pipes, 150-200mm dia, 5-30m run m hours - 10.60 - - 0.0943 -

PVC Drainage, 3m pipes, 150-200mm dia, over 30m run m hours - 12.80 - - 0.0781 -

PVC Drainage, 6m pipes, 150-200mm dia, 5-30m run m hours - 21.20 - - 0.0472 -

PVC Drainage, 6m pipes, 150-200mm dia, over 30m run m hours - 25.60 - - 0.0391 -

Stoneware Drainage, Cement/Sand Joints, 75mm dia, 0-5m run m hours - 4.70 - - 0.2128 -

Stoneware Drainage, Cement/Sand Joints, 75mm dia, 5-30m run m hours - 5.50 - - 0.1818 -

Stoneware Drainage, Cement/Sand Joints, 75mm dia, over 30m run m hours - 6.60 - - 0.1515 -

Stoneware Drainage, Cement/Sand Joints, 100mm dia, 0-5m run m hours - 4.40 - - 0.2273 -

Stoneware Drainage, Cement/Sand Joints, 100mm dia, 5-30m run m hours - 5.00 - - 0.2000 -

Stoneware Drainage, Cement/Sand Joints, 100mm dia, over 30m run m hours - 6.20 - - 0.1613 -

Stoneware Drainage, Cement/Sand Joints, 150mm dia, 0-5m run m hours - 3.20 - - 0.3125 -

Stoneware Drainage, Cement/Sand Joints, 150mm dia, 5-30m run m hours - 3.80 - - 0.2632 -

Stoneware Drainage, Cement/Sand Joints, 150mm dia, over 30m run m hours - 4.50 - - 0.2222 -

Stoneware Drainage, Cement/Sand Joints, 225mm dia, 0-5m run m hours - 2.10 - - 0.4762 -

Stoneware Drainage, Cement/Sand Joints, 225mm dia, 5-30m run m hours - 2.60 - - 0.3846 -

Stoneware Drainage, Cement/Sand Joints, 225mm dia, over 30m run m hours - 3.10 - - 0.3226 -

Stoneware Drainage, Cement/Sand Joints, 300mm dia, 0-5m run m hours - 1.40 - - 0.7143 -

Stoneware Drainage, Cement/Sand Joints, 300mm dia, 5-30m run m hours - 1.70 - - 0.5882 -

Stoneware Drainage, Cement/Sand Joints, 300mm dia, over 30m run m hours - 2.40 - - 0.4167 -

Stoneware Drainage, Cement/Sand Joints, over 375mm dia, 0-5m run m hours - 1.10 - - 0.9091 -

Stoneware Drainage, Cement/Sand Joints, over 375mm dia, 5-30m run m hours - 1.30 - - 0.7692 -

Stoneware Drainage, Cement/Sand Joints, over 375mm dia, over 30m run m hours - 1.60 - - 0.6250 -

Stoneware Drainage, Flexible Joints, 75mm dia, 0-5m run m hours - 8.30 - - 0.1205 -

Stoneware Drainage, Flexible Joints, 75mm dia, 5-30m run m hours - 10.00 - - 0.1000 -

Stoneware Drainage, Flexible Joints, 75mm dia, over 30m run m hours - 12.50 - - 0.0800 -

Stoneware Drainage, Flexible Joints, 100mm dia, 0-5m run m hours - 7.70 - - 0.1299 -

Stoneware Drainage, Flexible Joints, 100mm dia, 5-30m run m hours - 9.10 - - 0.1099 -

Stoneware Drainage, Flexible Joints, 100mm dia, over 30m run m hours - 10.00 - - 0.1000 -

Stoneware Drainage, Flexible Joints, 150mm dia, 0-5m run m hours - 5.20 - - 0.1923 -

Stoneware Drainage, Flexible Joints, 150mm dia, 5-30m run m hours - 6.20 - - 0.1613 -

Stoneware Drainage, Flexible Joints, 150mm dia, over 30m run m hours - 7.70 - - 0.1299 -

Stoneware Drainage, Flexible Joints, 225mm dia, 0-5m run m hours - 2.70 - - 0.3704 -

Stoneware Drainage, Flexible Joints, 225mm dia, 5-30m run m hours - 3.30 - - 0.3030 -

Stoneware Drainage, Flexible Joints, 225mm dia, over 30m run m hours - 4.00 - - 0.2500 -

Stoneware Drainage, Flexible Joints, 300mm dia, 0-5m run m hours - 1.70 - - 0.5882 -

Stoneware Drainage, Flexible Joints, 300mm dia, 5-30m run m hours - 2.10 - - 0.4762 -

Stoneware Drainage, Flexible Joints, 300mm dia, over 30m run m hours - 2.50 - - 0.4000 -

Stoneware Drainage, Flexible Joints, over 375mm dia, 0-5m run m hours - 1.40 - - 0.7143 -

Stoneware Drainage, Flexible Joints, over 375mm dia, 5-30m run m hours - 1.60 - - 0.6250 -

Stoneware Drainage, Flexible Joints, over 375mm dia, over 30m run m hours - 2.10 - - 0.4762 -

PVC, Stoneware, Pitch Fibre & Concrete Joints no minutes - 0.4167 - - 2.40 -

Pitch Fibre Pipes, 75mm dia, 0-5m run m hours - 9.10 - - 0.1099 -

Pitch Fibre Pipes, 75mm dia, 5-30m run m hours - 16.60 - - 0.0602 -

Pitch Fibre Pipes, 75mm dia, over 30m run m hours - 20.00 - - 0.0500 -

Pitch Fibre Pipes, 100mm dia, 0-5m run m hours - 9.10 - - 0.1099 -

Pitch Fibre Pipes, 100mm dia, 5-30m run m hours - 16.60 - - 0.0602 -

Pitch Fibre Pipes, 100mm dia, over 30m run m hours - 20.00 - - 0.0500 -

Pitch Fibre Pipes, 150mm dia, 0-5m run m hours - 6.60 - - 0.1515 -

Pitch Fibre Pipes, 150mm dia, 5-30m run m hours - 12.50 - - 0.0800 -

Pitch Fibre Pipes, 150mm dia, over 30m run m hours - 14.30 - - 0.0699 -

Pitch Fibre Pipes, 200mm dia, 0-5m run m hours - 6.20 - - 0.1613 -

Pitch Fibre Pipes, 200mm dia, 5-30m run m hours - 11.10 - - 0.0901 -

Pitch Fibre Pipes, 200mm dia, over 30m run m hours - 12.50 - - 0.0800 -

Pitch Fibre Pipes, 225mm dia, 0-5m run m hours - 5.80 - - 0.1724 -

Pitch Fibre Pipes, 225mm dia, 5-30m run m hours - 10.00 - - 0.1000 -

Pitch Fibre Pipes, 225mm dia, over 30m run m hours - 12.10 - - 0.0826 -

Hepsleve Rubber Joint System, 75mm dia, 0-5m run m hours - 12.50 - - 0.0800 -

Hepsleve Rubber Joint System, 75mm dia, 5-30m run m hours - 14.30 - - 0.0699 -

Hepsleve Rubber Joint System, 75mm dia, over 30m run m hours 11.20 16.60 30.10 0.0893 0.0602 0.0332

Hepsleve Rubber Joint System, 100mm dia, 0-5m run m hours - 10.00 - - 0.1000 -

Hepsleve Rubber Joint System, 100mm dia, 5-30m run m hours - 12.50 - - 0.0800 -

Hepsleve Rubber Joint System, 100mm dia, over 30m run m hours - 14.30 - - 0.0699 -

Hepsleve Rubber Joint System, 150mm dia, 0-5m run m hours - 7.10 - - 0.1408 -

Hepsleve Rubber Joint System, 150mm dia, 5-30m run m hours - 9.10 - - 0.1099 -

Hepsleve Rubber Joint System, 150mm dia, over 30m run m hours 8.30 10.00 13.80 0.1205 0.1000 0.0725

Hepsleve Rubber Joint System, 225mm dia, 0-5m run m hours - 6.80 - - 0.1471 -

Hepsleve Rubber Joint System, 225mm dia, 5-30m run m hours - 4.50 - - 0.2222 -

Hepsleve Rubber Joint System, 225mm dia, over 30m run m hours - 5.50 - - 0.1818 -

Hepsleve Rubber Joint System, 300mm dia, 0-5m run m hours - 2.50 - - 0.4000 -

Hepsleve Rubber Joint System, 300mm dia, 5-30m run m hours - 2.90 - - 0.3448 -
15
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Hepsleve Rubber Joint System, 300mm dia, over 30m run m hours - 3.70 - - 0.2703 -

Hepsleve Rubber Joint System, over 375mm dia, 0-5m run m hours - 1.90 - - 0.5263 -

Hepsleve Rubber Joint System, over 375mm dia, 5-30m run m hours - 2.30 - - 0.4348 -

Hepsleve Rubber Joint System, over 375mm dia, over 30m run m hours - 2.70 - - 0.3704 -

Concrete Pipes, 1.5m pipes, 375mm dia, 0-5m run m hours - 2.80 - - 0.3571 -

Concrete Pipes, 1.5m pipes, 375mm dia, 5-30m run m hours - 3.40 - - 0.2941 -

Concrete Pipes, 1.5m pipes, 375mm dia, over 30m run m hours - 3.80 - - 0.2632 -

Concrete Pipes, 1.5m pipes, 450mm dia, 0-5m run m hours - 2.70 - - 0.3704 -

Concrete Pipes, 1.5m pipes, 450mm dia, 5-30m run m hours - 3.20 - - 0.3125 -

Concrete Pipes, 1.5m pipes, 450mm dia, over 30m run m hours - 3.60 - - 0.2778 -

Concrete Pipes, 1.5m pipes, 525mm dia, 0-5m run m hours - 2.50 - - 0.4000 -

Concrete Pipes, 1.5m pipes, 525mm dia, 5-30m run m hours - 2.90 - - 0.3448 -

Concrete Pipes, 1.5m pipes, 525mm dia, over 30m run m hours - 3.40 - - 0.2941 -

Concrete Pipes, 1.5m pipes, 600mm dia, 0-5m run m hours - 2.40 - - 0.4167 -

Concrete Pipes, 1.5m pipes, 600mm dia, 5-30m run m hours - 2.70 - - 0.3704 -

Concrete Pipes, 1.5m pipes, 600mm dia, over 30m run m hours - 3.30 - - 0.3030 -

Concrete Pipes, 1.5m pipes, 675mm dia, 0-5m run m hours - 2.20 - - 0.4545 -

Concrete Pipes, 1.5m pipes, 675mm dia, 5-30m run m hours - 2.60 - - 0.3846 -

Concrete Pipes, 1.5m pipes, 675mm dia, over 30m run m hours - 2.90 - - 0.3448 -

Concrete Pipes, 1.5m pipes, 750mm dia, 0-5m run m hours - 1.10 - - 0.9091 -

Concrete Pipes, 1.5m pipes, 750mm dia, 5-30m run m hours - 2.40 - - 0.4167 -

Concrete Pipes, 1.5m pipes, 750mm dia, over 30m run m hours - 2.50 - - 0.4000 -

Concrete Pipes, 1.5m pipes, 1,050mm dia m days - 2.90 4.20 - 0.3448 0.2381

Concrete Pipes, 1.5m pipes, 1,500mm dia m days - 2.50 3.80 - 0.4000 0.2632

Concrete Pipes, 1.5m pipes, 1,800mm dia m days - 2.10 2.60 - 0.4762 0.3846

Concrete Pipes, 2.5m pipes, 375mm dia, 0-5m run m hours - 3.60 - - 0.2778 -

Concrete Pipes, 2.5m pipes, 375mm dia, 5-30m run m hours - 4.30 - - 0.2326 -

Concrete Pipes, 2.5m pipes, 375mm dia, over 30m run m hours - 5.00 8.00 - 0.2000 0.1250

Concrete Pipes, 2.5m pipes, 450mm dia, 0-5m run m hours - 3.40 - - 0.2941 -

Concrete Pipes, 2.5m pipes, 450mm dia, 5-30m run m hours - 4.10 - - 0.2439 -

Concrete Pipes, 2.5m pipes, 450mm dia, over 30m run m hours - 4.50 9.00 - 0.2222 0.1111

Concrete Pipes, 2.5m pipes, 525mm dia, 0-5m run m hours - 3.30 - - 0.3030 -

Concrete Pipes, 2.5m pipes, 525mm dia, 5-30m run m hours - 3.80 - - 0.2632 -

Concrete Pipes, 2.5m pipes, 525mm dia, over 30m run m hours - 4.10 - - 0.2439 -

Concrete Pipes, 2.5m pipes, 600mm dia, 0-5m run m hours - 3.00 - - 0.3333 -

Concrete Pipes, 2.5m pipes, 600mm dia, 5-30m run m hours - 3.50 - - 0.2857 -

Concrete Pipes, 2.5m pipes, 600mm dia, over 30m run m hours - 4.00 - - 0.2500 -

Concrete Pipes, 2.5m pipes, 675mm dia, 0-5m run m hours - 2.80 - - 0.3571 -

Concrete Pipes, 2.5m pipes, 675mm dia, 5-30m run m hours - 3.30 - - 0.3030 -

Concrete Pipes, 2.5m pipes, 675mm dia, over 30m run m hours - 3.70 - - 0.2703 -

Concrete Pipes, 2.5m pipes, 750mm dia, 0-5m run m hours - 2.60 - - 0.3846 -

Concrete Pipes, 2.5m pipes, 750mm dia, 5-30m run m hours - 3.10 - - 0.3226 -

Concrete Pipes, 2.5m pipes, 750mm dia, over 30m run m hours - 3.60 - - 0.2778 -

Lay Shingle Around Pipework, under 150mm dia m hours - 7.00 - - 0.1429 -

Lay Shingle Around Pipework, over 150mm dia m hours 4.00 5.50 9.00 0.2500 0.1818 0.1111

Doors and Windows

Mastic Pointing to Frames m hours - 9.50 - - 0.1053 -

Fix Metal and Timber Windows After Wall Complete m2 hours - 2.00 - - 0.5000 -

Window Glazing m2 hours - 1.30 - - 0.7692 -

Window Glazing, Single Glazed Units m2 hours - 2.00 - - 0.5000 -

Window Glazing, Double Glazed Units m2 hours - 1.30 - - 0.7692 -

Blockwork

Thermalite Blockwork, under 100mm thick m2 hours 1.80 2.50 3.20 0.5556 0.4000 0.3125

Thermalite Blockwork, under 100-150mm thick m2 hours 1.40 1.90 2.50 0.7143 0.5263 0.4000

Thermalite Blockwork, over 150mm thick m2 hours 1.20 1.60 2.10 0.8333 0.6250 0.4762

Lightweight Concrete Blockwork, under 100mm thick m2 hours 1.50 2.20 2.90 0.6667 0.4545 0.3448

Lightweight Concrete Blockwork, under 100-150mm thick m2 hours 1.40 1.90 2.10 0.7143 0.5263 0.4762

Lightweight Concrete Blockwork, over 150mm thick m2 hours 1.20 1.60 2.00 0.8333 0.6250 0.5000

Heavyweight Concrete Blockwork, under 100mm thick m2 hours 1.40 2.10 2.90 0.7143 0.4762 0.3448

Heavyweight Concrete Blockwork, under 100-150mm thick m2 hours 1.20 1.60 2.10 0.8333 0.6250 0.4762

Heavyweight Concrete Blockwork, over 150mm thick m2 hours 1.10 1.40 1.80 0.9091 0.7143 0.5556

Face Finish, Raked Out m2 hours - 71.40 - - 0.0140 -

Face Finish, Bag Rubbed m2 hours - 29.40 - - 0.0340 -

Face Finish, Flush Pointing m2 hours - 17.60 - - 0.0568 -

Dewatering
16
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Setup small 2 hole system days - - - 10.00 8.00 6.00

Setup large 15 hole system days - - - - 21.00 -

Calculate system times per pump pump days - 0.4000 - - 2.50 -

Setup Recharge System pump days - 0.2857 - - 3.50 -

Demolition

Weight, Structural Steel Tonnes m3 - 2.50 - - 0.4000 -

Remove & Cart away, Ceramic Wall Tiles m2 hours 2.00 2.50 3.40 0.5000 0.4000 0.2941

Remove & Cart away, Wallpaper, 1 layer m2 hours - 8.70 - - 0.1149 -

Remove & Cart away, Wallpaper, 2 layers m2 hours - 7.10 - - 0.1408 -

Remove & Cart away, Wallpaper, 3 layers m2 hours - 5.70 - - 0.1754 -

Remove & Cart away, Lathe and Plaster Ceilings m2 hours 3.20 4.60 5.00 0.3125 0.2174 0.2000

Remove & Cart away, Plaster to Walls m2 hours 2.10 3.10 5.90 0.4762 0.3226 0.1695

Remove & Cart away, External Render m2 hours - 3.90 - - 0.2564 -

Remove & Cart away, Floor Screed m2 hours - 3.20 - - 0.3125 -

Remove & Cart away, Concrete Paving m2 hours - 4.00 - - 0.2500 -

Remove & Cart away, Brickwork Walls, 1.0 brick thick m2 hours - 1.30 - - 0.7692 -

Remove & Cart away, Brickwork Walls, 0.5 brick thick m2 hours - 2.60 - - 0.3846 -

Remove & Cart away, Brickwork Walls, Sand/Lime Mortar 100 hours - 0.5556 - - 1.80 -

Remove & Cart away, Fireplace and Hearth no hours - 0.5263 - - 1.90 -

Remove & Cart away, Floor Boards m2 hours - 6.20 - - 0.1613 -

Remove & Cart away, Skirting, Architrave, Dado rail etc m hours - 16.50 - - 0.0606 -

Remove & Cart away, Staircase no hours - 0.1370 - - 7.30 -

Remove & Cart away, Windows, 0-1m2 no hours - 1.6667 - - 0.60 -

Remove & Cart away, Windows 1-2m2 no hours - 1.2500 - - 0.80 -

Remove & Cart away, Windows 2-3m2 no hours - 1.1111 - - 0.90 -

Remove & Cart away, Doors no hours - 3.3333 - - 0.30 -

Remove & Cart away, Door Frame no hours - 10.0000 - - 0.10 -

Remove & Cart away, Floor and Ceiling Joists m hours - 0.9091 - - 1.10 -

Remove & Cart away, Wall Plates m hours - 0.2564 - - 3.90 -

Remove & Cart away, Iron Bath no hours - 0.7143 - - 1.40 -

Remove & Cart away, Wash Basin/Sink no hours - 1.2500 - - 0.80 -

Remove & Cart away, Pipework including brackets etc m hours - 6.10 - - 0.1639 -

Decking

Simple Universal Beam Steel Bridge, concrete bridge deck, grano cover m days - 7.10 - - 0.1408 -

Cutting Switchboxes

Cutting in Concrete, small box no hours 7.10 9.50 12.50 0.1408 0.1053 0.0800

Cutting in Concrete, large box no hours 3.60 4.50 5.60 0.2778 0.2222 0.1786

Cutting in Brickwork, small box no hours 6.60 9.50 12.50 0.1515 0.1053 0.0800

Cutting in Brickwork, large box no hours 4.20 5.30 6.30 0.2381 0.1887 0.1587

Cutting in Lightweight Blockwork, small box no hours 20.00 23.00 25.00 0.0500 0.0435 0.0400

Cutting in Lightweight Blockwork, large box no hours 10.00 12.50 14.30 0.1000 0.0800 0.0699

Cutting in Heavyweight Blockwork, small box no hours 7.70 10.00 12.50 0.1299 0.1000 0.0800

Cutting in Heavyweight Blockwork, large box no hours 3.80 4.80 5.90 0.2632 0.2083 0.1695

Cutting Chases

Concrete, cutting by hand, < 25mm wide m hours 1.50 2.10 3.10 0.6667 0.4762 0.3226

Concrete, cutting by hand, 25-50mm wide m hours 1.20 1.60 2.50 0.8333 0.6250 0.4000

Concrete, cutting by hand, 50-75mm wide m hours 1.00 1.40 2.10 1.0000 0.7143 0.4762

Concrete, cutting by hand, 75-100mm wide m hours 0.90 1.20 1.80 1.1111 0.8333 0.5556

Concrete, cutting by machine, < 25mm wide m hours 3.10 4.00 5.80 0.3226 0.2500 0.1724

Concrete, cutting by machine, 25-50mm wide m hours 2.50 3.30 5.00 0.4000 0.3030 0.2000

Concrete, cutting by machine, 50-75mm wide m hours 2.10 2.90 4.20 0.4762 0.3448 0.2381

Concrete, cutting by machine, 75-100mm wide m hours 1.80 2.40 3.70 0.5556 0.4167 0.2703

Brickwork, cutting by hand, < 25mm wide m hours 2.10 2.70 4.10 0.4762 0.3704 0.2439

Brickwork, cutting by hand, 25-50mm wide m hours 1.60 2.30 3.50 0.6250 0.4348 0.2857

Brickwork, cutting by hand, 50-75mm wide m hours 1.40 1.90 2.80 0.7143 0.5263 0.3571

Brickwork, cutting by hand, 75-100mm wide m hours 1.20 1.60 2.50 0.8333 0.6250 0.4000

Brickwork, cutting by machine, < 25mm wide m hours 4.20 5.50 11.10 0.2381 0.1818 0.0901

Brickwork, cutting by machine, 25-50mm wide m hours 3.30 4.50 6.70 0.3030 0.2222 0.1493

Brickwork, cutting by machine, 50-75mm wide m hours 3.30 4.50 6.70 0.3030 0.2222 0.1493

Brickwork, cutting by machine, 75-100mm wide m hours 2.50 3.30 5.00 0.4000 0.3030 0.2000

Light Blockwork, cutting by hand, < 25mm wide m hours 3.80 5.00 7.70 0.2632 0.2000 0.1299

Light Blockwork, cutting by hand, 25-50mm wide m hours 3.20 4.20 6.30 0.3125 0.2381 0.1587
17
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Light Blockwork, cutting by hand, 50-75mm wide m hours 2.60 3.40 5.30 0.3846 0.2941 0.1887

Light Blockwork, cutting by hand, 75-100mm wide m hours 2.30 3.10 4.50 0.4348 0.3226 0.2222

Light Blockwork, cutting by machine, < 25mm wide m hours 7.70 10.00 14.20 0.1299 0.1000 0.0704

Light Blockwork, cutting by machine, 25-50mm wide m hours 5.90 7.70 11.10 0.1695 0.1299 0.0901

Light Blockwork, cutting by machine, 50-75mm wide m hours 5.20 7.20 10.00 0.1923 0.1389 0.1000

Light Blockwork, cutting by machine, 75-100mm wide m hours 4.70 6.30 9.10 0.2128 0.1587 0.1099

Heavy Blockwork, cutting by hand, < 25mm wide m hours 1.90 2.60 3.80 0.5263 0.3846 0.2632

Heavy Blockwork, cutting by hand, 25-50mm wide m hours 1.60 2.10 3.20 0.6250 0.4762 0.3125

Heavy Blockwork, cutting by hand, 50-75mm wide m hours 1.30 1.80 2.70 0.7692 0.5556 0.3704

Heavy Blockwork, cutting by hand, 75-100mm wide m hours 1.20 1.50 2.30 0.8333 0.6667 0.4348

Heavy Blockwork, cutting by machine, < 25mm wide m hours 3.80 5.00 7.70 0.2632 0.2000 0.1299

Heavy Blockwork, cutting by machine, 25-50mm wide m hours 3.20 4.20 6.20 0.3125 0.2381 0.1613

Heavy Blockwork, cutting by machine, 50-75mm wide m hours 2.70 3.60 5.20 0.3704 0.2778 0.1923

Heavy Blockwork, cutting by machine, 75-100mm wide m hours 2.30 3.10 4.50 0.4348 0.3226 0.2222

Cutting Back

Concrete Pile Caps, 50-300mm deep and 0.6m dia no hours 1.6667 - 3.3333 0.60 - 0.30

Concrete Pile Caps, 300-750mm deep and 0.6m dia no hours 0.6667 - 2.5000 1.50 - 0.40

Concrete Pile Caps, > 750mm deep and 0.6m dia no hours 0.5556 - 1.2500 1.80 - 0.80

Concrete Pile Caps, 50-300mm deep and 1.1m dia no hours 0.5263 - 1.2500 1.90 - 0.80

Concrete Pile Caps, 300-750mm deep and 1.1m dia no hours 0.4000 - 0.9091 2.50 - 1.10

Concrete Pile Caps, > 750mm deep and 1.1m dia no hours 0.2381 - 0.4348 4.20 - 2.30

Concrete Pile Caps, 50-300mm deep and 2.5m dia no hours 0.1087 - 0.1220 9.20 - 8.20

Concrete Pile Caps, 300-750mm deep and 2.5m dia no hours 0.0990 - 0.1053 10.10 - 9.50

Concrete Pile Caps, > 750mm deep and 2.5m dia no hours 0.0870 - 0.0980 11.50 - 10.20

Concrete, Cutting Slabs, 5-25m deep m hours - 15.20 - - 0.0658 -

Concrete, Cutting Slabs, 25-50m deep m hours - 11.50 - - 0.0870 -

Concrete, Cutting Slabs, 50-75m deep m hours - 6.70 - - 0.1493 -

Concrete, Cutting Holes, coring machine m3 hours - 0.20 - - 5.0000 -

Concrete, Cutting Back to expose couplers 0.7m slab m days - 2.50 - - 0.4000 -

Curtain Walling

Vertical Glazed Lights, 6m x 2.5m m2 days - 14.50 - - 0.0690 -

Vertical Glazed Walls, large scale m2 days - 70.00 - - 0.0143 -

Clerestory Frame/Glazing, 3m x 4m m2 days - 28.00 - - 0.0357 -

Oriel Window Frame/Glazing, 4m x 2m m2 days - 35.00 - - 0.0286 -

Glazed Curtain Wall, First Fix m2 hours - 1.20 - - 0.8333 -

Glazed Curtain Wall, Second Fix m2 hours - 1.10 - - 0.9091 -

High Quality Glazed Curtain Walling m2 days - 25.00 - - 0.0400 -

Concrete Placement

Placing concrete, lorry based pump m3 hours 30.00 40.00 50.00 0.0333 0.0250 0.0200

Hollorib Decking, concrete topping m2 hours 85.00 100.00 120.00 0.0118 0.0100 0.0083

Hollorib Decking, concrete topping, incl PowerFloat m2 hours 40.00 50.00 70.00 0.0250 0.0200 0.0143

Placing Concrete, By Wheelbarrow over 1-10m m3 hours 2.10 2.30 2.50 0.4762 0.4348 0.4000

Placing Concrete, By Wheelbarrow over 10-20m m3 hours 1.50 1.80 2.10 0.6667 0.5556 0.4762

Placing Concrete, By Wheelbarrow over 20-50m m3 hours 0.80 1.10 1.50 1.2500 0.9091 0.6667

Placing Direct From Readymix Lorry, Mass Fill m3 hours 2.80 3.10 3.30 0.3571 0.3226 0.3030

Placing Direct From Readymix Lorry, 50mm Blinding m3 hours - 1.30 1.60 - 0.7692 0.6250

Placing Direct From Readymix Lorry, Ground Beams m3 hours 1.50 - 1.70 0.6667 - 0.5882

Placing Direct From Readymix Lorry, Pile Caps m3 hours 1.00 1.50 2.30 1.0000 0.6667 0.4348

Placing Direct From Readymix Lorry, Duct Walls m3 hours - 0.80 1.10 - 1.2500 0.9091

Placing Direct From Readymix Lorry, Stub Columns m3 hours - 0.40 0.60 - 2.5000 1.6667

Placing Direct From Readymix Lorry, Ground Slab m3 hours 2.10 2.30 2.60 0.4762 0.4348 0.3846

Placing Direct From Readymix Lorry,Drains Bed and Cover m3 hours - 0.90 1.00 - 1.1111 1.0000

Placing From Tower Crane, Pile Caps m3 hours 1.20 1.40 1.60 0.8333 0.7143 0.6250

Placing From Tower Crane, Mass Fill m3 hours 4.00 4.50 5.50 0.2500 0.2222 0.1818

Placing From Tower Crane, Slabs under 150mm thick m3 hours 0.90 1.30 1.70 1.1111 0.7692 0.5882

Placing From Tower Crane, Slabs over 150mm thick m3 hours 1.20 1.50 1.80 0.8333 0.6667 0.5556

Placing From Tower Crane, Trough/Coffered Slabs m3 hours 0.90 1.10 1.20 1.1111 0.9091 0.8333

Placing From Tower Crane, Stairs and Landings m3 hours 0.60 0.70 0.90 1.6667 1.4286 1.1111

Placing From Tower Crane, Blinding m3 hours 0.80 1.00 1.10 1.2500 1.0000 0.9091

Placing From Tower Crane, Beams under 150mm thick m3 hours 0.50 0.60 0.80 2.0000 1.6667 1.2500

Placing From Tower Crane, Beams over 150mm thick m3 hours 0.60 0.80 1.00 1.6667 1.2500 1.0000

Placing From Tower Crane, Walls m3 hours 0.60 1.10 1.50 1.6667 0.9091 0.6667

Placing From Tower Crane, Columns m3 hours 0.40 0.50 0.60 2.5000 2.0000 1.6667
18
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Concrete Mixing

Concrete Weight, 1m3 Tonnes - 2.40 - - - -

Readymix Lorry, Length m - 8.30 - - - -

Readymix Lorry, Width m - 2.50 - - - -

Readymix Lorry, Height m - 3.70 - - - -

Readymix Lorry, Length Tonnes - 24.40 - - - -

Readymix Lorry, Turning Circle m - 16.40 - - - -

Readymix Lorry, Allowable Access Ramp Gradient degrees - 17.00 20.00 - - -

Mixing Concrete, By Hand m3 hours - 0.30 - - 3.3333 -

Mixing Concrete, Single Drum Paddle Mixer m3 hours 158.00 180.00 210.00 0.0063 0.0056 0.0048

Mixing Concrete, Double Drum Paddle Mixer m3 hours 315.00 370.00 420.00 0.0032 0.0027 0.0024

Mixing Concrete, Single Drum Plant Pan Mixer m3 hours - 120.00 - - 0.0083 -

Mixing Concrete, Dry Mix Plant m3 hours - 90.00 - - 0.0111 -

Concrete Finishing

Surface Finishing, Steel Float By Hand m2 hours 9.20 13.90 25.00 0.1087 0.0719 0.0400

Surface Finishing, Wood Float By Hand m2 hours 11.70 17.20 29.40 0.0855 0.0581 0.0340

Surface Finishing, Power Float m2 hours 13.90 20.80 37.00 0.0719 0.0481 0.0270

Surface Finishing, Light Brush on Trowel m2 hours 55.80 90.10 170.00 0.0179 0.0111 0.0059

Surface Finishing, Brush on Trowel Margin m2 hours 28.80 48.50 85.00 0.0347 0.0206 0.0118

Surface Finishing, Sprayed By Pump, expose aggregate m2 hours 65.00 95.00 145.00 0.0154 0.0105 0.0069

Surface Finishing, Wire Brush, expose aggregate m2 hours 15.00 25.00 30.00 0.0667 0.0400 0.0333

Making Good Walls, prepare, shutter, pour m2 hours - 5.50 8.60 - 0.1818 0.1163

Making Good Columns, prepare, shutter, pour m2 hours - 2.80 6.90 - 0.3571 0.1449

Making Good Sides of Beams, prepare, shutter, pour m2 hours - 2.80 7.00 - 0.3571 0.1429

Making Good Slab Soffits, prepare, shutter, pour m2 hours - 4.20 5.50 - 0.2381 0.1818

Making Good Bolt Holes, prepare, shutter, pour no/hr hours 14.80 16.80 25.80 0.0676 0.0595 0.0388

Making Good Rubdown Precast Concrete, prepare, shutter, pour m2 hours - 18.00 - - 0.0556 -

Making Good Scabble 3 head brush hammer, prepare, shutter, pour m2 hours 30.70 59.50 73.80 0.0326 0.0168 0.0136

Commercial Kitchen

Overall Installation for 100 persons or 50m2 wks - - - - 3.00 -

Overall Installation for 500 persons or 150m2 wks - - - - 5.00 -

Overall Installation for 1000 persons or 250m2 wks - - - - 8.00 -

Install Ovens, friers and large mixers etc mandays - - - - 1.00 -

Install Sinks, bain maries and washers etc mandays - - - - 2.00 -

Ceiling Finishes

Suspended Ceilings, office situations m2 hours - 2.60 3.50 - 0.3846 0.2857

Suspended Ceilings, First Fix m2 hours - 0.70 - - 1.4286 -

Suspended Ceilings, Second Fix m2 hours - 1.20 - - 0.8333 -

Carpentry Final Fixing

Windows, Softwood, 3.0-7.0m2 no hours 1.6667 2.5000 3.3333 0.60 0.40 0.30

Windows, Softwood, 7.0-10.0m2 no hours 0.7692 1.1111 1.6667 1.30 0.90 0.60

Windows, Hardwood, 1.0-3.0m2 no hours 2.5000 3.3333 - 0.40 0.30 -

Windows, Hardwood, 3.0-7.0m2 no hours 1.4286 2.0000 2.5000 0.70 0.50 0.40

Windows, Hardwood, 7.0-10.0m2 no hours 0.6250 0.8333 1.4286 1.60 1.20 0.70

Windows, Aluminum, 1.0-3.0m2 no hours 5.0000 3.3333 - 0.20 0.30 -

Windows, Aluminum, 3.0-7.0m2 no hours 2.0000 2.5000 3.3333 0.50 0.40 0.30

Windows, Aluminum, 7.0-10.0m2 no hours 0.8333 1.2500 2.0000 1.20 0.80 0.50

Windows, Steel, 1.0-3.0m2 no hours 2.5000 3.3333 5.0000 0.40 0.30 0.20

Windows, Steel, 3.0-7.0m2 no hours 0.8333 1.6667 2.0000 1.20 0.60 0.50

Windows, Steel, 7.0-10.0m2 no hours 0.7143 0.8333 1.0000 1.40 1.20 1.00

Window Boards, nailed m hours - 3.3333 5.0000 - 0.30 0.20

Window Boards, screwed m hours - 2.5000 3.3333 - 0.40 0.30

Mouldings, Softwood, Nailed m hours - 6.30 8.50 - 0.1587 0.1176

Mouldings, Softwood, Screwed m hours - 4.60 5.60 - 0.2174 0.1786

Mouldings, Softwood, Gun Nailed m hours - 8.20 11.10 - 0.1220 0.0901

Mouldings, Hardwood, Nailed m hours - 3.30 5.50 - 0.3030 0.1818

Mouldings, Hardwood, Screwed m hours - 2.40 3.70 - 0.4167 0.2703

Mouldings, Hardwood, Gun Nailed m hours - 8.50 11.30 - 0.1176 0.0885

Skirting, Aluminum, Screwed 150-300mm centres m hours - 7.60 - - 0.1316 -

Skirting, Aluminum, Screwed 300-450mm centres m hours - 4.50 - - 0.2222 -

Skirting, Plastic, Adhesive Fixing m hours - 8.60 - - 0.1163 -


19
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Architrave Mouldings m hours 9.50 12.20 18.20 0.1053 0.0820 0.0549

Architrave, Fix to Doors door hours - 0.8333 - - 1.20 -

Door Stop Mouldings m hours 10.10 16.90 25.00 0.0990 0.0592 0.0400

Glazed Bead Mouldings m hours 15.50 18.60 20.40 0.0645 0.0538 0.0490

Hanging Doors, Softwood, Single Pair Butts no hours 0.7692 1.1111 1.6667 1.30 0.90 0.60

Hanging Doors, Hardwood, Single Pair Butts no hours 0.5263 0.8333 1.1111 1.90 1.20 0.90

Cut Mortice to Receive Lock, Softwood no hours - 5.0000 - - 0.20 -

Cut Mortice to Receive Lock, Hardwood no hours - 1.6667 - - 0.60 -

Cut & Fix Formica Bath Panel no hours - 2.5000 - - 0.40 -

Kitchen Cupboards, Floor Units no hours - 1.2500 1.6667 - 0.80 0.60

Kitchen Cupboards, Wall Units no hours - 1.4286 2.0000 - 0.70 0.50

Kitchen Cupboards, Shelf Units no hours - - 1.4286 - 0.8 0.70

Staircase, pre-made, simple, straight flight no hours 0.5263 0.6667 0.9091 1.90 1.50 1.10

Staircase, pre-made, 2 straight flights, 1 landing no hours 0.2703 0.3448 0.3846 3.70 2.90 2.60

Staircase, pre-made, 2 straight flights, 2 landings no hours - 0.1587 - - 6.30 -

Staircase, Balustrades/Handrails, fix horizontal no hours 0.8333 1.6667 10.0000 1.20 0.60 0.10

Staircase, Balustrades/Handrails, fix raking no hours 1.1111 2.0000 3.3333 0.90 0.50 0.30

Staircase, Cut and Fix Newel to Walls no hours 1.1111 - 5.0000 0.90 - 0.20

Windows, Softwood, 1.0-3.0m2 no hours 3.3333 5.0000 - 0.30 0.20 -

Raised Flooring, metal system m2 hours - 0.50 - - 2.0000 -

Carpentry Carcassing

Windows, Timber Frames for Bricklaying no hours 0.9091 2.0000 10.0000 1.10 0.50 0.10

Windows, Drill, Screw & Plug extra over no hours 3.3333 10.0000 - 0.30 0.10 -

Door Frames, Softwood, 1.0-3.0m2 no hours - 5.0000 - - 0.20 -

Door Frames, Softwood, 3.0-7.0m2 no hours 2.0000 2.5000 - 0.50 0.40 -

Door Frames, Softwood, 7.0-10.0m2 no hours 0.8333 1.2500 - 1.20 0.80 -

Door Frames, Hardwood, 1.0-3.0m2 no hours - 3.3333 - - 0.30 -

Door Frames, Hardwood, 3.0-7.0m2 no hours 1.6667 3.3333 - 0.60 0.30 -

Door Frames, Hardwood, 7.0-10.0m2 no hours 0.7143 1.0000 - 1.40 1.00 -

Erect Water Tank Platform no hours - 2.30 - - 0.4348 -

Fix Studding For Bath m hours - 10.00 - - 0.10 -

Cut Access Hatch no hours - 0.30 - - 3.3333 -

Floor Joists, under 3m no hours 9.00 9.60 11.60 0.1111 0.1042 0.0862

Floor Joists, 3.0-4.5m no hours 6.80 7.20 9.70 0.1471 0.1389 0.1031

Floor Joists, 4.5-6.0m no hours 5.50 5.80 7.30 0.1818 0.1724 0.1370

Ceiling Joists, under 3m no hours 12.80 14.00 14.70 0.0781 0.0714 0.0680

Ceiling Joists, 3.0-4.5m no hours 10.80 12.10 12.60 0.0926 0.0826 0.0794

Ceiling Joists, 4.5-6.0m no hours 9.60 10.80 11.10 0.1042 0.0926 0.0901

Ceiling Joists, Notch to Beams no hours 20.00 25.00 28.50 0.0500 0.0400 0.0351

Ceiling Joists, Pack Joist Ends no hours 20.10 23.80 26.30 0.0498 0.0420 0.0380

Ceiling Joists, Nailing Joists together m hours - 23.00 - - 0.0435 -

Ceiling Joists, Bolting Joists Together m hours - 12.60 - - 0.0794 -

Floor Boards, Butt Jointed m2 hours - 1.70 - - 0.5882 -

Floor Boards, T&G Boards, under 75mm wide m2 hours - 3.40 - - 0.2941 -

Floor Boards, T&G Boards, 75-100mm wide m2 hours - 3.80 - - 0.2632 -

Floor Boards, T&G Boards, 100-125mm wide m2 hours - 4.20 - - 0.2381 -

Floor Boards, T&G Boards, 125-150mm wide m2 hours - 5.50 - - 0.1818 -

Plywood Sheeting, Butt Jointed, nailed m2 hours - 9.10 10.20 - 0.1099 0.0980

Plywood Sheeting, Butt Jointed, screwed m2 hours - 4.10 4.80 - 0.2439 0.2083

Plywood Sheeting, T&G Jointed, nailed m2 hours - 8.30 9.10 - 0.1205 0.1099

Plywood Sheeting, T&G Jointed, screwed m2 hours - 4.00 4.60 - 0.2500 0.2174

Chipboard Sheeting, Butt Jointed, nailed m2 hours - 10.00 11.50 - 0.1000 0.0870

Chipboard Sheeting, Butt Jointed, screwed m2 hours - 5.10 5.80 - 0.1961 0.1724

Chipboard Sheeting, T&G Jointed, nailed m2 hours - 9.30 9.10 - 0.1075 0.1099

Chipboard Sheeting, T&G Jointed, screwed m2 hours - 5.50 5.90 - 0.1818 0.1695

Carpentry & Joinery

Formwork to Soffit of Manhole m2 hours - 1.80 - - 0.5556 -

Formwork to Walls of Manhole m2 hours 11.20 14.20 20.20 0.0893 0.0704 0.0495

Formwork to Road Edges, straight m hours - 7.70 - - 0.1299 -

Formwork to Road Edges, curves m hours - 6.20 - - 0.1613 -

Bulk Excavation

Excavation Bulking Factor, Sand/Soil % - 15.00 20.00 - - -

Excavation Bulking Factor, Gravel % - 33.00 - - - -

Excavation Bulking Factor, Clay/Chalk % - 40.00 - - - -

Excavation Bulking Factor, Boulder Clay % - 45.00 - - - -


20
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Excavation Bulking Factor, Rock % - 60.00 - - - -

Spoil Weight, Rock Tonnes/m3 - 2.50 - - - -

Spoil Weight, Concrete Tonnes/m3 - 2.40 - - - -

Spoil Weight, Landfill/CDG Tonnes/m3 - 1.90 - - - -

Spoil Weight, Sand Tonnes/m3 - 1.80 - - - -

Rail Mounted Grab, 2.0m3 bucket 2.4min lift cycle m3 hours 30.00 48.00 59.00 0.0333 0.0208 0.0169

Crane Mounted Clamshell Grab, 2.0m3 bucket 2.9min lift cycle m3 hours 25.00 33.00 41.00 0.0400 0.0303 0.0244

Crane Mounted Clamshell Grab, 2.5m3 bucket 2.9min lift cycle m3 hours 34.00 42.00 52.00 0.0294 0.0238 0.0192

Hydraulic Excavator, 0.3m3 bucket, Sand/Soil m3 hours 6.90 8.70 10.20 0.1449 0.1149 0.0980

Hydraulic Excavator, 0.4m3 bucket, Sand/Soil m3 hours 23.40 28.60 33.40 0.0427 0.0350 0.0299

Hydraulic Excavator, 0.5m3 bucket, Sand/Soil m3 hours 45.50 50.00 58.00 0.0220 0.0200 0.0172

Hydraulic Excavator, 0.3m3 bucket, Gravel Beds m3 hours 5.60 7.10 8.20 0.1786 0.1408 0.1220

Hydraulic Excavator, 0.4m3 bucket, Gravel Beds m3 hours 20.50 25.00 29.00 0.0488 0.0400 0.0345

Hydraulic Excavator, 0.5m3 bucket, Gravel Beds m3 hours 36.80 40.00 46.00 0.0272 0.0250 0.0217

Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk m3 hours 5.60 7.10 8.30 0.1786 0.1408 0.1205

Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk m3 hours 20.50 25.00 28.70 0.0488 0.0400 0.0348

Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk m3 hours 37.00 40.00 46.00 0.0270 0.0250 0.0217

Hydraulic Excavator, 0.3m3 bucket, Hard Ground m3 hours 4.50 6.10 7.20 0.2222 0.1639 0.1389

Hydraulic Excavator, 0.4m3 bucket, Hard Ground m3 hours 17.90 22.20 25.00 0.0559 0.0450 0.0400

Hydraulic Excavator, 0.5m3 bucket, Hard Ground m3 hours 25.70 28.60 32.90 0.0389 0.0350 0.0304

Breaking Out

Concrete Slabs, unreinforced 50-150mm m3 hours 0.3125 - 0.5263 3.20 - 1.90

Concrete Slabs, unreinforced 150-300mm m3 hours 0.1818 0.2439 0.2703 5.50 4.10 3.70

Concrete Slabs, reinforced 50-150mm m3 hours 0.1923 - 0.2564 5.20 - 3.90

Concrete Slabs, reinforced 150-300mm m3 hours 0.1099 0.1613 0.2128 9.10 6.20 4.70

Concrete Walls, unreinforced m3 hours 0.2128 0.2564 0.3226 4.70 3.90 3.10

Concrete Walls, reinforced m3 hours 0.1786 0.2128 0.2564 5.60 4.70 3.90

Concrete Foundations, unreinforced m3 hours 0.2778 0.3030 0.3333 3.60 3.30 3.00

Concrete Foundations, reinforced m3 hours 0.1852 0.1961 0.2083 5.40 5.10 4.80

Concrete Beams m3 hours 0.1333 0.1538 0.1786 7.50 6.50 5.60

Concrete Columns m3 hours 0.1087 0.1220 0.1370 9.20 8.20 7.30

Tarmac paving 20-50mm thick m3 hours 0.5263 0.5882 0.6667 1.90 1.70 1.50

Tarmac paving 50-100mm thick m3 hours 0.4762 - 0.6250 2.10 - 1.60

Tarmac paving 100-150mm thick m3 hours 0.4762 - 0.5882 2.10 - 1.70

Tarmac roadway 150mm thick m3 hours - 0.2778 - - 3.60 -

Brickwork, walls and columns m3 hours 0.4167 0.5556 0.7692 2.40 1.80 1.30

Brickwork, foundations m3 hours 0.3704 0.4762 0.6667 2.70 2.10 1.50

Barrette Piles

Rule of Thumb, overall rate by Mill no hours 2.0000 0.9091 0.8333 0.50 1.10 1.20

Fabricate reinforcement cages cage hours - 0.2500 - - 4.00 -

Concreting barrette panels m3 hours 40.00 50.00 55.00 0.0250 0.0200 0.0182

Trimming top of barrette panels no days - 0.4167 - - 2.40 -

Concrete Testing, Coring Test no days 0.2500 0.2857 0.5000 4.00 3.50 2.00

Concrete Testing, Sonic Logging Test no days - 1.4286 - - 0.70 -

Basement Excavation

Hydraulic Excavator, 0.3m3 bucket, Sand/Soil - Basement Works m3 hours 6.40 8.00 9.40 0.1563 0.1250 0.1064

Hydraulic Excavator, 0.3m3 bucket, Gravel Beds - Basement Works m3 hours 5.50 6.90 8.10 0.1818 0.1449 0.1235

Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk - Basement Works m3 hours 5.20 6.50 7.90 0.1923 0.1538 0.1266

Hydraulic Excavator, 0.3m3 bucket, Hard Ground - Basement Works m3 hours 4.70 5.90 8.20 0.2128 0.1695 0.1220

Hydraulic Excavator, 0.4m3 bucket, Sand/Soil - Basement Works m3 hours 12.60 15.40 18.90 0.0794 0.0649 0.0529

Hydraulic Excavator, 0.4m3 bucket, Gravel Beds - Basement Works m3 hours 11.70 14.30 16.70 0.0855 0.0699 0.0599

Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk - Basement Works m3 hours 10.90 13.30 15.60 0.0917 0.0752 0.0641

Hydraulic Excavator, 0.4m3 bucket, Hard Ground - Basement Works m3 hours 9.70 11.80 14.00 0.1031 0.0847 0.0714

Hydraulic Excavator, 0.5m3 bucket, Sand/Soil - Basement Works m3 hours 18.20 20.00 23.00 0.0549 0.0500 0.0435

Hydraulic Excavator, 0.5m3 bucket, Gravel Beds - Basement Works m3 hours 16.50 18.10 20.00 0.0606 0.0552 0.0500

Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk - Basement Works m3 hours 15.40 16.70 19.30 0.0649 0.0599 0.0518

Hydraulic Excavator, 0.5m3 bucket, Hard Ground - Basement Works m3 hours 13.30 15.40 17.70 0.0752 0.0649 0.0565

Bell Ground Anchors

Uncased Anchors, 10m long no days - 2.00 - - 0.5000 -

Top Cased Anchors, 15m long no days - 1.00 - - 1.0000 -

Anchors stressing no days - 2.20 - - 0.4545 -


21
PRODUCTION RATES

UNIT FOR UNIT FOR PRODUCTION RATES (Qty per Time) PRODUCTION RATES (Time per Quantity)
ITEM NO. DESCRIPTION REMARKS
QUANTITY TIME Slow Average Fast Slow Average Fast

Bored Piling

Cycle Time, 5-20m deep no days 0.1250 0.2500 0.2500 8.00 4.00 4.00

Cycle Time, 20-40m deep no days 0.1000 0.1250 - 10.00 8.00 -

Cycle Time, 40-70m deep no days 0.0400 0.1000 - 25.00 10.00 -

Cycle Time, 70-90m deep no days 0.0222 0.0400 - 45.00 25.00 -

Cycle Time, 90-135m deep no days 0.0167 0.0222 - 60.00 45.00 -

Move piling setup to next location hours - 2.00 -

Excave shaft by grab, general fill/uppr levels m hours - 3.50 - - 0.2857 -

Excave shaft by grab, sand/minor rubble m hours - 2.10 - - 0.4762 -

Excave shaft by grab, marinve/aluvium m hours - 2.50 - - 0.4000 -

Excave shaft by grab/RCD, CDT m hours - 0.50 - - 2.0000 -

Excave shaft by grab/RCD, CDG <150 m hours - 1.50 - - 0.6667 -

Excave shaft by RCD, CDG 150-200 m hours - 1.00 - - 1.0000 -

Excave shaft by RCD, CDG >200/gravel m hours - 0.50 - - 2.0000 -

Excave shaft by RCD/Chisel, corestones m hours - 0.50 - - 2.0000 -

Excave Rock Socket by RCD, grade IV/V rock m hours - 0.20 0.30 - 5.0000 3.3333

Excave Rock Socket by RCD, grade II/III rock m hours - 0.10 0.20 - 10.0000 5.0000

Excave Rock Socket by RCD, tendering rate m hours - 0.10 - - 10.0000 -

Add/remove RCD plant hours - - - - 2.00 -

Add/remove RCD drill string/drill bit hours - - - - 5.00 -

Remove Obstruction, above water hand hammers m hours - 0.80 - - 1.2500 -

Remove Obstruction, below water heavy chisel m hours - 0.50 - - 2.0000 -

Concrete Plug, RCD off/tremmie/concrete/cure/RCD on hours - - - 60.00 53.00 50.00

Install air lift tremmie tube hours - - - - 5.00 -

Fabricate reinforcement cages cage hours - 0.4000 - - 2.50 -

Install reinforcement cages no hours - 0.5000 - - 2.00 -

Shaft cleaning, air lifting after excavation hours - - - - 8.0 -

Shaft cleaning, air lifting after cage installed hours - - - - 2.0 -

Shaft concreting/extract casing 5-70m deep hours - - - - 12.0 -

Shaft concreting/extract casing 70-95m deep hours - - - - 14.0 -

Shaft concreting/extract casing 95-135m deep hours - - - - 48.0 -

Concrete curing prior to remove telescopic casing hours - - - - 72.0 -

Concrete Testing, Coring Test m hours - 3.20 2.20 - 0.3125 0.4545

Concrete Testing, Sonic Logging Test no hours - 0.4000 - - 2.50 -

Concrete Testing, Vibration Test no hours - 0.1538 - - 6.50 -