Sunteți pe pagina 1din 1

COMMENTARY AWS D1.1/D1.

1M:2015

C-6.1.5 Inspector Responsibility. This subclause re- mentation may cause serious delays in the acceptance
quires that the Inspector verify that all fabrication and weldments.
erection by welding is pelformed in conformance with
the requirements of the contract documents. This in- C-6.4.2 Retesting Based on Quality of Work. Exam-
cludes not only welding but also materials, assembly, ples of methods the inspector may choose to demo~
preheating, NDT, and all other requirements of the code the ability to produce sound welds include the following:
and provisions of the contract documents.
(1) an interview of the welder,
C-6.1.6 Items to be Furnished to the Inspector. In-
(2) increased visual inspection for a limited time
spectors need a complete set of approved drawings to en-
period,
able them to properly do their work. They need be
furnished only the portion of the contract documents de- (3) observation of the welding, or a simplified weld
scribing the requirements of products that they will in- test developed to evaluate the issue of concern,
spect. Much of the contract documents deal with matters
that are not the responsibility of the Inspector; these por- (4) requalification in compliance with Clause 4 or
tions need not be furnished. Clause 9 for tubulars.

C-6.1.7 Inspector Notification. If the Inspectors are not C-6.4.3 Retesting Based on Qualification Expiration.
notified in advance of the start of operations, they cannot If evidence cannot be supplied that shows a welder,
properly pelform the functions required of them by the welding operator, or tack welder has used the welding
code. process within the last six months, he or she is not con-
sidered qualified to weld using that process without new
qualification testing. Because active welders can main-
tain their certification as long as they continue to do good
work, it is important that Inspectors regularly evaluate
C-6.2 Inspection of Materials the quality of the welds produced by each welder, weld-
and Equipment ing operator, and tack welder.
This code provision is all-encompassing. It requires in-
spection of materials and review of materials certifica-
tion and mill test reports. It is important that this work be
done in a timely manner so that unacceptable materials C-6.5 Inspection of Work and Records
are not incorporated in the work. Except for final visual inspection, which is required for
every weld, the Inspector inspect§. the work at suitable
intervals to ensure that the requirements of the applicable
sections of the code are met. Such inspections should be
C-6.3 Inspection of WPS Qualification conducted, on a sampling basis, prior to assembly, dur-
ing assembly, and during welding. The inspector identi-
The requirements of this section, including any qualifica- fies final acceptance or rejection of the work either by
tion testing required by Clause 4, should be completed marking on the work or with other recording methods.
before any welding is begun on any weldments required The method of identification should not be destmctive to
by the contract documents. Qualification should always the weldment. Die stamping of welds is not recom-
be done before work is started, but all qualification does mended since die stamp marks may form sites for crack
not have to be completed before any work can be started. initiation.

C-6.5.4 Inspector Identification of Inspections Per-


formed. Die stamp marks may form sites for crack
initiation.
C-6.4 Inspection of Welder, Welding
Operator, and Tack Welder
Qualifications
C-6.6 Obligations of the Contractor
C-6.4.1 Determination of Qualification. It is important
that the Inspector determine that all welders are qualified C-6.6.1 Contractor Responsibilities. The Contractor(
before work is begun on the project. If discovered after conduct§. inspection to the extent necessary to ensure\
welding has begun, lack of welder qualification docu- conformance with the code, except as provided in 6.6.5.

522

S-ar putea să vă placă și