Documente Academic
Documente Profesional
Documente Cultură
VOLUME – III
1
VOLUME – INDEX
CONTENTS
NO OF
SLNO TITLE
PAGES
2
TECHNICAL SPECIFICATION
SL. PAGE
DESCRIPTION
NO. NO.
1 TECHNICAL SPECIFICATION 4
2 DRAWINGS 28
3
TECHNICAL SPECIFICATION
A. SCOPE OF WORK
The following are the nature of works involved.
The terrain is highly undulated and the area has to be levelled to three different RLs
as shown in the enclosed drawing for the construction of Power plant structures.
B. GENERAL SPECIFICATION.
1.0. General
All the works shall be carried out as per the relevant I.S. Codes. The contractor
is to carry out the work as per the approved drawings and as per the Engineer’s
instructions. All the material required for the work shall be as per IS
specifications and approved by the Engineer.
4.0. De-watering
All excavation shall be kept free of water. Grading in the vicinity of
excavations shall be controlled to prevent surface water running into the
excavated areas. The Contractor shall remove by pumping or other means
approved by the Engineer any water inclusive of rainwater and subsoil water
accumulated in excavation without any extra cost. The Engineer shall
approve Method of de-watering but in no case, the pumping arrangement
shall be such that there is any movement of subsoil or blowing in due to
differential head of water during pumping. Sumps made for de-watering
shall be kept clear of the foundations.
8
Contractor to repair/restore it to original condition or compensate the damage
at his own cost.
If the embankment is to be constructed under water, Clause 1.4.2 shall
apply.
Compacting ground supporting embankment/filling low level areas:
Where necessary, the original ground shall be leveled to facilitate placement
of first layer of filling/ embankment, scarified, mixed with water and then
compacted by rolling so as to achieve the required density to satisfy the
compaction requirements.
Where so directed by the Engineer, any unsuitable material occurring in the
embankment foundation shall be removed and replaced by approved materials
laid in layers to the required degree of compaction.
Embankment or filling work shall not proceed until the foundations for
embankment/filling work have been inspected by the Engineer for satisfactory
condition and approved.
Spreading material in layers and bringing to appropriate moisture content
The embankment and filling up material shall be spread in layers of uniform
thickness not exceeding 200 mm loose thickness over the entire width of
embankment by mechanical means, finished by a motor grader and
compacted as per Clause 1.3.5. The motor grader blade shall have hydraulic
control suitable for initial adjustment and maintain the same so as to achieve
the specific slope and grade. Successive layers shall not be placed until the
layer under construction has been thoroughly compacted to the specified
requirements as in Table-1 and got approved by the Engineer. Each
compacted layer shall be finished parallel to the final cross-section of the
embankment.
Moisture content of the material shall be checked at the site of placement prior to
commencement of compaction; if found to be out of agreed limits, the same
shall be made good. Where water is required to be added in such
constructions, water shall be sprinkled from a water tanker fitted with
sprinkler capable of applying water uniformly with a controllable rate of
flow to variable widths of surface but without any flooding. The water shall
be added uniformly and thoroughly mixed in soil by blading, discing or
harrowing until uniform moisture content is obtained throughout the depth
of the layer.
If the material delivered to the site is too wet, it shall be dried, by aeration
and exposure to the sun, till the moisture content is acceptable for
compaction. Should circumstances arise, where owing to wet weather, the
moisture content cannot be reduced to the required amount by the above
procedure, compaction work shall be suspended.
9
Moisture content of each layer of soil shall be checked in accordance with
IS: 2720 (Part 2), and unless otherwise mentioned, shall be so adjusted,
making due allowance for evaporation losses, that at the time of compaction
it is in the range of 1 per cent above to 2 per cent below the optimum
moisture content determined in accordance with IS: 2720 (Part 8) as the case
may be. Expansive clays shall, however, be compacted at moisture content
corresponding to the specified dry density, but on the wet side of the
optimum moisture content obtained from the laboratory compaction curve.
After adding the required amount of water, the soil shall be processed by
means of graders, harrows, rotary mixers or as otherwise approved by the
Engineer until the layer is uniformly wet.
Clods or hard lumps of earth shall be broken to have a maximum size of
75 mm
Embankment and other areas of fill shall, unless otherwise required in the Contract
or permitted by the Engineer, be constructed evenly over their full width and
their fullest possible extent and the Contractor shall control and direct
construction plant and other vehicular traffic uniformly over them. Damage
by construction plant and other vehicular traffic shall be made good by the
Contractor with material having the same characteristics and strength as the
material had before it was damaged.
Embankments and other areas of unsupported fills shall not be con-
structed with steeper side slopes, or to greater widths than those shown in the
Contract, except to permit adequate compaction at the edges before
trimming back, or to obtain the final profile following any settlement of the
fill and the underlying material.
Whenever fill is to be deposited against the face of a natural slope, or
sloping earthworks face including embankments, cuttings, other fills and
excavations steeper than 1 vertical on 4 horizontal, such faces shall be
benched as per Clause 1.4.1 immediately before placing the subsequent fill.
All permanent faces of side slopes of embankments and other areas of fill
formed shall, subsequent to any trimming operations, be reworked and sealed
to the satisfaction of the Engineer by tracking a tracked vehicle, considered
suitable by the Engineer, on the slope or any other method approved by the
Engineer.
Compaction of Earth -Only the compaction equipment approved by the Engineer
shall be employed to compact the different material types encountered during
construction. Smooth wheeled, vibratory, pneumatic tyred, sheep foot or pad
foot rollers, etc. of suitable size and capacity as approved by the Engineer
shall be used for the different types and grades of materials required to be
compacted either individually or in suitable combinations.
10
The compaction shall be done with the help of vibratory roller of 80 to 100
KN static weight with plain or pad foot drum or heavy pneumatic tyred roller
of adequate capacity capable of achieving required compaction.
The Contractor shall demonstrate the efficacy of the equipment he intends
to use by carrying out compaction trials.
Earthmoving plant shall not be accepted as compaction equipment nor shall
the use of a lighter category of plant to provide any preliminary compaction
to assist the use of heavier plant be taken into account.
When each layer of material has been conditioned so as to have the proper
moisture content uniformly distributed throughout the material, it shall be
compacted by a suitable compacting equipment. The exact number of passes
shall be determined from the trial compaction to have density equal to 95% of
maximum dry density (Modified Proctor). Rollers shall always be pulled.
Turns shall be made to ensure uniform compaction. Field density test shall be
made after rolling and the dry density obtained should be corresponding to a
density equal to 95% of maximum dry density (Modified Proctor). If not, then
additional number of passes has to be made get the density equal to 95% of
maximum dry density (Modified Proctor).
Each layer of the material shall be thoroughly compacted to the densities to
satisfy the requirements as in Table-1.Subsequent layers shall be placed only
after the finished layer has been tested according to clause 2.4.2.2 and
accepted by the Engineer. The Engineer may permit measurement of field dry
density by a nuclear moisture/density gauge/Proctor Compaction needle used
in accordance with agreed procedure and the gauge is calibrated to provide
results identical to that obtained from tests in accordance with IS: 2720 (Part
28) or IS: 2720 (Part 29).A record of the same shall be maintained by the
Contractor.
When density measurements reveal any soft areas in the embankment/filling
the low level areas, further compaction shall be carried out as directed by the
Engineer. If in spite of that the specified compaction is not achieved, the
material in the soft areas shall be removed and replaced by approved material,
compacted to the density requirements and satisfaction of the Engineer.
Drainage: The surface of the embankment/filling the low level areas at all times
during construction shall be maintained at such a cross fall (not flatter than
that required for effective drainage of an earthen surface) as will shed water
and prevent ponding.
Repairing of damages caused by rain/spillage of water:
The soil in the affected portion shall be removed in such areas as directed
by the Engineer before next layer is laid and refilled in layers and compacted
using appropriate mechanical means such as small vibratory roller, plate
compactor or power rammer to achieve the required density. If the cut is not
sufficiently wide for use of required mechanical means for compaction, the
11
same shall be widened suitably to permit their use for proper compaction.
Tests shall be carried out as directed by the Engineer to ascertain the density
requirements of the repaired area. The work of\ repairing the damages
including widening of the cut, if any, shall be carried out by the Contractor at
his own cost, including the arranging of machinery/equipment for the purpose.
Finishing operations:
Finishing operations shall include the work of shaping and dressing the side
slopes to conform to the alignment, levels, cross-sections and dimensions
shown on the drawings or as directed by the Engineer.
The slopes of the embankment shall be neatly dressed to line after reaching the
final height. Compaction shall extend over the full width of filling, and the
material in the slopes shall be compacted as for rest of the structure.
To ensure proper compaction at the outer edge, the fill shall be kept
adequately wider by at least 0.5M on sloping sides and the outer edge
dressed to true width and slope after compaction. Slopes shall be maintained
until completion and final acceptance
When earthwork operations have been substantially completed, the area shall
be cleared of all debris, and ugly scars in the construction area responsible
for objectionable appearance eliminated.
Construction of Embankment / filling the low level areas under\Special
Conditions
Construction of embankment/filling low level areas over ground incapable of
supporting construction equipment: Where embankment is to be
constructed/ filling low level areas across ground which will not support the
weight of repeated heavy loads of construction equipment, the first layer of
the fill may be constructed by placing successive loads of material in a
uniformly distributed layer of a minimum thickness required to support the
construction equipment as permitted by the Engineer.
Embankment construction underwater: Where filling or backfilling is to be
placed under water, only acceptable granular material or rock shall be used
unless otherwise approved by the Engineer. Acceptable granular material
shall consist of graded, hard durable particles with maximum particle size
not exceeding 75 mm. The material should be non-plastic having uniformity
coefficient of not less than 10. The material placed in open water shall be
deposited by end tipping without compaction.
Test fill section:
Earth filling
A test fill section of approximately 15M X 8M X 2M height shall be
carried out, and this can be a part of the embankment itself. By trials, a
definite compaction procedure, lift thickness, moisture application and
12
number of passes required to achieve 95% of Modified proctor maximum
dry density should be obtained.
Rates
The Contract unit rates for the items of embankment, filling low lying areas shall
be payment in full for carrying out the required operations including. full
compensation for :
(i) Setting out;
(ii) Compacting ground supporting embankment/low level areas except
where removal and replacement of unsuitable material or loosening and
recomposing is involved;
(iii) Scarifying or cutting continuous horizontal benches 300 mm wide on
side slopes of existing embankment and low level areas as applicable;
(iv)Cost of watering or drying of material in borrow areas and/or,
embankment
(v) Spreading in layers, bringing to appropriate moisture content and
compacting To Specification requirements;
(vi) Shaping and dressing top and slopes of the embankment and filling low
level areas including rounding of comers;
(vii) Restricted working at sites of structures;
(vii) Working on narrow width of embankment and filling;
(vii) All labour, materials, tools, equipment and incidentals necessary to
complete the work to the Specifications;
(ix) Dewatering.
(x) Keeping the embankment/completed formation free of water.
(xi) The slopes of the embankment shall be neatly dressed to line after
reaching the final height. Compaction shall extend over the full width
of filling, and the material in the slopes shall be compacted as for rest
of the structure.
(xii) To ensure proper compaction at the outer edge, the fill shall be kept
adequately wider by at least 0.5M on sloping sides and the outer edge
dressed to true width and slope after compaction. Slopes shall be
maintained until completion and final acceptance. Any material lost by
weathering or other cause shall be replaced. Payment will be made for
only compacted portion of embankment.
13
may be specified on the drawings or by the Engineer., It shall include
necessary excavation, backfilling of pits resulting from uprooting of trees and
stumps to required compaction, handling, salvaging, and disposal of cleared
materials. Top soil removal shall be performed in advance of earthwork
operations and in accordance with the requirements of these specifications.
Preservation of Property/Amenities
All trees, shrubs, any other plants, pole lines, fences, signs, monuments,
buildings, pipelines, sewers and all facilities within or adjacent to the work
places which are not to be disturbed shall be protected from injury or damage.
The Contractor shall provide and install at his own expense, suitable
safeguards approved by the Engineer for this purpose. During clearing and
grubbing, the Contractor shall take all adequate precautions against soil
erosion, water pollution, etc., and where required, undertake additional works
to that effect. Before start of operations, the Contractor shall submit to the
Engineer for approval, his work plan including the procedure to be followed
for disposal of waste materials, etc., and the schedules for carrying out
temporary and permanent erosion control works.
Methods, Tools and Equipments
Only such methods, tools and equipment as are approved by the Engineer
and which will not affect the property to be preserved shall be adopted for the
Work. If the area has thick vegetation/roots/trees, a crawler or pneumatic tyred
dozer of adequate capacity may be used for clearance purposes. The dozer
shall have ripper attachments for removal of tree stumps. All trees, stumps,
etc., falling within excavation and fill lines shall be cut to such depth below
ground level that in no case these fall within 500 mm of the existing ground
level. Also, all vegetation such as roots, under-growth, grass and other
deleterious matter unsuitable for incorporation in the embankment/filling low
level areas shall be removed between fill lines to the satisfaction of the
Engineer.
All excavations below the general ground level arising out of the removal of
trees, stumps, etc., shall be filled with suitable material and compacted
thoroughly so as to make the surface at these points conform to the
surrounding area.
Ant-hills both above and below the ground, as are liable to collapse and
obstruct free subsoil water flow shall be removed and their workings, which
may extend to several metres, shall be suitably treated.
Disposal of Materials
All materials arising from top soil removal operations shall be the property of
NLCIL/NUPPL and shall be disposed of by the Contractor as hereinafter
provided or directed by the Engineer. Also boulders, stones and other materials
usable for construction shall be neatly stacked as directed by the Engineer.
Stacking of stumps, boulders, stones etc., shall be done at specified spots with
all lifts and up to a lead of 3000 m.
14
All products of clearing and grubbing which, in the opinion of the Engineer,
cannot be used or auctioned shall be cleared away from the site in a manner as
directed by the Engineer, Care shall be taken to see that unsuitable waste
materials are disposed of in such a manner that there is no likelihood of these
getting mixed up with the materials
meant for embankment, filling works.
Rates
The Contract unit rates for the various items of top soil removal shall be payment
in full for carrying out the required operations including full compensation
for all labor, materials, tools, Equipment and incidentals necessary to
complete the work. These will also include removal of stumps of trees less
than 300 mm in girth as well as stumps left over after cutting of trees carried
out by another agency, excavation and back-filling to required density, where
necessary, and handling, salvaging, piling and disposing of the cleared
materials with all lifts and up to a lead of 2000 m.
2.2 Setting out: The limits of excavation shall be set out true to lines, curves,
slopes, grades and sections as shown on the drawing or as directed by the
Engineer. The contractor shall provide all labour, survey instruments and
materials such as strings, pegs, nails, bamboos, stones, lime, mortor,
concrete, etc,. Required in connection with the setting out of works and the
establishment of bench marks. The contractor shall be responsible for the
maintenance of bench mark and other marks and stakes as long as in the
opinion of the Engineer, they are required for the work.
16
3.0.0 Excavation - General: All excavations shall be carried out in conformity with
the directions laid here-in -under and in a manner approved by the Engineer.
The work shall be so done that the suitable materials available from excavation
are satisfactorily utilized as decided upon beforehand. While planning or
executing excavations, the Contractor shall take all adequate precautions
against soil erosion, water pollution etc. and take appropriate drainage
measures to keep the site free of water in accordance with Clause 2.5.The
excavations shall conform to the lines, grades, side slopes and levels shown on
the drawings or as directed by the Engineer. The Contractor shall not excavate
outside the limits of excavation. Subject to the permitted tolerances, any excess
depth/ width excavated beyond the specified levels/dimensions on the
drawings shall be made good at the cost of the Contractor with suitable
material of characteristics similar to that removed and compacted to the
requirements of Clause 1.All debris and loose material on the slopes of
cuttings shall be removed. No backfilling shall be allowed to obtain required
slopes excepting that when boulders or soft materials are encountered in cut
slopes, these shall be excavated to approved depth on instructions of the
Engineer and the resulting cavities filled with suitable material and thoroughly
compacted in an approved manner.
After excavation, the surface area of site and the sides of excavated area shall
be trimmed and the area graded to the specified level allowing for natural
drainage to take place.
Rates
The Contract unit rates for the items of site grading, deepening of pond, drain
excavation shall be payment in full for carrying out the operations required
for the individual items including full compensation for:
(i) Setting out;
(ii) Transporting the excavated materials and depositing the same on sites
of embankments, filling areas or stacking as directed within all lifts and
lead upto 1000 m or as otherwise specified;
(iii) Trimming bottoms and slopes of excavation;
(iv) Dewatering;
(v) Keeping the work free of water as per Clause 2.5; and
(vi) All labour, materials, tools, equipment, safety measures, testing and
incidentals necessary to complete the work to Specifications.
4.0 LABORATORY
The contractor shall set up the laboratory with at least the following equipments
in order to carry out all required tests and quality control wok as per the
specification and/or as directed by the engineer.
17
Sl.N Description Qty
o
1 Oven-(Electrically operated thermostatically controlled) IS:2720 (Part-5) 1No
2 Electronic Balance IS:2720 (Part-3) 2Nos
3 Set of IS Sieve with lid and pan
i) 450mm diameter 1Set
75mm,63mm,53mm,37,5mm,26.5mm,19mm,13.2mm,9.5mm,6.7mm and
4.75mm size.
ii) 200mm diameter 2Sets
2.36mm,2.0mm,1.18mm,600micron,425mcron,300micron,150micron and
75micron
5 Dry Bulk Density apparatus (Sand pouring cylinder, tray, can etc.) complete. 1Set
IS:2720 (Part-28)
6 Core Cutter apparatus 10cm dia,10/15 cm height, complete with dolly rammer 1Set
etc. IS:2720 (Part-29)
7 Proctor needle to measure the penetration resistance 1Set
8 Desiccators with suitable desiccating agent. 1Set
9 All the apparatus required for determination of water content- dry density 1Set
relation using heavy compaction. IS:2720 (Part-8)
10 All the apparatus required for determination of moisture content. IS:2720 1Set
(Part-2)
11 All the apparatus required for determination of density index (relative density) 1Set
of cohesion less soil. IS:2720 (Part-14)
1.0 GENERAL:
1.1. Scope:
This part deals with the requirement of materials for use in construction work
with regard to quality, testing, approval and storage before they are used on
work. The Bureau of Indian Standard Code Specification shall be considered
as the requirement for any material that are not covered in this specification.
Standard:
A high standard of quality is required for all materials used in construction
work. They shall be the best of the kind obtainable indigenously in each case
and shall be procured from manufacturers of repute in order to ensure
uniformity of quality and assurance of timely supply.
Rejection of materials:
(a) Any material brought to site which, in the opinion of the Engineer is
damaged, contaminated, deteriorated or does not comply with the
requirement of this specification shall be rejected.
(b) If the routine tests or random site tests show that any of the materials brought
to the site, do not comply in any way with the requirements of this
specification or BIS codes as applicable, then that material should be
rejected.
(c) The contractor at his own cost shall remove from the site any and all such
rejected material within the time specified by the Engineer.
2.0 Water:
Water will be supplied by NLCIL/NUPPL at one point as mentioned in the
Conditions of Contract. The contractor has to make his own arrangements at
his cost for conveying and storing properly for use in the work either by
constructing sump or tanks.
19
E. SPECIFICATIONS FOR CONSTRUCTION
GENERAL
Standard
A high standard of workmanship in all trades will be required. The
Contractor shall ensure that only skilled and experienced workmen
employed.
Supervision
The Contractor’s supervising staff shall be fully qualified and experienced in
the types of work being carried out under their supervision and shall be
capable of ensuring that work is executed efficiently and as per specification.
Temporary works.
Where required, the Contractor shall furnish such details of his temporary
works as may be called for by the Engineer and the Contractor shall satisfy
the Engineer as to their safety and efficiency. The Engineer may direct that
temporary works, which he considers unsafe or insufficient, shall be removed
and replaced in a satisfactory manner.
Codes.
The years of publication against various standards, referred in this
specification, correspond to the latest standards as on date of preparation of
this specification. During use of this specification in future, the latest
publication as on date shall be referred to. Where standards are not yet
published by the BIS or IRC, adaptable British Standards or other
International Standards shall apply.
Base lines and benchmarks.
The Contractor shall establish and maintain, to the satisfaction of Engineer,
the base lines and benchmarks based on which the works are set out. Where
such base- lines and bench-marks are provided by the Engineer, the
Contractor shall maintain these throughout the period of construction without
causing any disturbance to them.
Setting out.
The Contractor shall set out all the works to be executed by him, in line with
the standard base lines, levels, position and benchmarks and truly as per
drawings within the accepted tolerance limits at no extra cost to owner. The
Contractor shall be solely responsible for the setting out of all the works, to
be executed by him and the approval of such setting out by the Engineer shall
in no way absolve the Contractor his responsibility for carrying the work to
the true lines, levels and positions as per drawings.
De-watering.
The Contractor shall carry out all the works, in dry and workable condition
and maintain the same in dry condition till the final handing over of works at
20
no extra cost to the owner. For this the contractor shall make all the necessary
arrangements, to the entire satisfaction of the Engineer.
No water shall enter the excavated pit or the adjoining area where the
foundation of any structure is proposed. The dewatering shall be a continuous
process and foundation pits shall be maintained dry till the excavation, laying
of concrete and back filling is completed. The rate quoted for earthwork
excavation shall be inclusive of all the above and including all leads and lifts.
EARTH WORK.
Scope
This chapter deals with earthwork and excavation for civil works in site,
formation /site levelling, foundations, cutting and grading for roads/
pavement and canals, embankments other than water retaining embankments
trenching for drainage and other buried services and the like.
General
The Contractor shall carry out the excavation strictly to the lines and levels,
in conformity with the drawings and as per the instructions of the Engineer.
Setting out.
Before commencement of earthwork blocks levels of existing ground shall be
taken by the Contractor jointly with the Engineer plotted and signed in token
of acceptance of ground levels. Excavation shall not be commenced until the
initial ground levels have been recorded and accepted. Reference lines,
benchmarks and base levels shall be set out by the Contractor for control of
the earthwork operation. Setting out shall be done with pegs, blocks, bamboo
21
poles or rails, marking boundaries or centre lines as the case may be, and the
same maintained for reference and future checking. Chainage stones at
regular intervals shall be set up for embankments. All setting out
operation shall be got checked and approved by Engineer. However, such
checking and approval by the Engineer shall in no way absorb the Contractor
of his responsibilities for carrying out the work to the true lines, levels and
positions as per drawing, and in case any error is noticed at any stage in the
Contractor’s work, it shall be corrected/ rectified by him without any cost to
the owner.
22
This comprises of rock or boulders which may be quarried or split with crow
bars, pavement breakers etc., this includes lime stones, sand stones,
weathered rocks and hard conglomerates, etc., and existing structures
embedded in earth and tarred macadam roads, pavements, met in the
excavation. The fact that Contractor resorts to blasting for his own reasons
shall not mean that the rock is hard and classified as hard rock.
23
may result in side collapse or settlement of adjoining ground or endanger
adjoining structures and foundation, they shall be left permanently in
position. The last 150mm of excavation shall be done and the bottom
trimmed to the required level only when concreting is imminent. If at any
point the natural ground is disturbed or loosened for any reason it shall be
consolidated by tamping, or rolling or made good with sand filling and well
compacted at no extra cost. Where the soil encountered at depths indicated in
drawing is loose or weak it shall be further excavated to levels of firm strata
as may be directed by the Engineer and filled with lean concrete of M5 grade
(1:5:10) cement concrete or sand as directed. If the bottom of excavation has
been left exposed on neglect or fault of the Contractor and it has become
deleteriously affected by the atmospheric action and water, such portion of
deteriorated foundation material shall be removed and made good by lean
concrete of grade M5/1:5:10 Cement Concrete or sand as directed.
Excess excavation
All excavation done beyond the specified limits or directions of Engineer
shall be considered as excess excavation. They shall be made good as
prescribed below by the Contractor at his cost:
i. Excess excavation in case of site leveling shall be made good by filling and
compacting with material same as the surrounding material. Degree of
compaction shall be at least the same as the surrounding material.
ii. Excess excavation in case of trenches shall be made good by filling and
compacting with selected earth to the same compaction as the
surrounding material or as directed by the Engineer. This shall be done in
layers not exceeding 200mm thick moistened and thoroughly compacted
by tamping.
iii. Excess excavation in case of foundation beyond required depths shall be
made good by sand filling and well compacted.
Disposal of excavated material.
Excavated materials that are unsuitable for use in construction works or in
excess of construction requirements shall be disposed off in dumping yards
or in locations indicated by Engineer. Waste piles/heaps shall be located in
such places where they will not interfere with natural flow of rainwater
access or transport or with the access to nearby structure. When required,
they shall be levelled and trimmed to such lines and levels as indicated by
Engineer.
Protection of slopes:
The filling shall be carried out preferably maintaining the slopes under the
natural angle of repose. However in any case the slope shall be not more
than 20º. The slopes on the sides shall be carefully monitored and
maintained and any damage or repairs that may occur due to monsoon or
any other reason before the entire filling is taken up shall be attended to
immediately.
F. Special conditions
1. The drawing showing the site grading details ( boundary with final graded level)
shall be given to the contractor by NLCIL/NUPPL . It is the duty of the contractor
to do the surveying of the area using ‘total station’ and quantity of cutting and
filling shall be calculated using specialised software and report thereof shall be
got approved by NLCIL/NUPPL before the commencement of site grading .
Proper record/drawings on levels and quantities shall be submitted to
NLCIL/NUPPL for approval.
2. An indicative drawing showing the embankment slopes, drains, slope protection,
lining details etc. will be furnished to the contractor before the commencement of
concerned work at site on priority basis. It is the duty of the contractor to finalise
the alignment of drains based on site condition and get it approved from
NLCIL/NUPPL before execution.
3. The contractor shall execute all the works based on approved drawings issued by
NLCIL/NUPPL.
25
4. Contractor shall depute qualified supervisors at the site and the whole work shall
be done under the constant supervision of site supervisors.
5. All the test results and lab records shall be verified by NLCIL/NUPPL at least
once in a week and the record thereof shall be maintained by the contractor.
6. NLCIL/NUPPL shall have the right to check the quality at any time during the
time of execution and necessary tests shall be done by the contractor.
7. NLCIL/NUPPL will hold review meeting on the progress of work at least once in
a month and authorised representative of the contractor must present during the
review.
8. If at any stage, the progress is found to be unsatisfactory, NLC/NUPPL has all the
right to take necessary action against the contractor.
All the Indian Standards referred to will be the latest revision (including all
amendments issued thereto) on the date of submission of each documents.
Reference to only some of the codes in this document and various clauses of
design criteria will not limit or restrict the scope or applicability of other relevant
codes. It will be ensured that all other codes relevant to a specific job, in addition
to those already mentioned, are followed wherever applicable.
Where British / American / DIN or other codes and standards are referred to in this
document, equivalent Indian Standards may be substituted if available. In case of
any deviation / conflict between provisions of IS codes and the design criteria, the
provisions that are more stringent will be followed unless specifically directed
otherwise.
The Codes and Standards listed below are applicable for the design and
construction of structures and buildings in general. Codes and Standards applicable
for specific design and construction are listed elsewhere in reference sections.
Specifications for materials supplied from India will follow the Indian Standard
Specifications.
Field and laboratory testing procedures for materials follow Indian Standard
Specifications.
The list of codes will also be read in conjunction with the list of codes given in the
respective detailed technical specifications.
LOADS
IS: 1911 Schedule of unit weights of building materials
FOUNDATIONS
IS: 1080 Code of Practice for design and construction of shallow foundations on
soils (other than raft, ring and shell)
26
IS: 1904 Code of Practice for design and construction of foundations in soils
general requirement
IS: 8009 Code of Practice for calculation of settlement of foundations: (All parts)
PCC
IS: 456 Code of Practice for plain and reinforced concrete
MISCELLANEOUS
IS: 1905 Code of Practice for structural use of unreinforced masonry
SP: 6 Handbook for structural engineers (all parts)
SP: 7 National Building Code of India
SP: 16 Design Aids for reinforced concrete to IS: 456-1978
SP: 20 Handbook on masonry design and construction
SP: 22 Explanatory handbook on codes for earthquake engineering (IS: 1982-1975
and IS:4326-1976) engineering (IS: 1982-1975 and IS: 4326-1976)
SP: 24 Explanatory handbook on Indian Standard code of Practice for plain and
reinforced concrete
SP: 25 Handbook on causes and prevention of cracks in buildings
SP: 34 Handbook of concrete reinforcement and detailing (SCIP)
General Manager/Civil
27
DRAWING
28