Sunteți pe pagina 1din 2

Project : Single Storey Residential

Description of Material Quantity Unit Unit Cost Total Cost

GENERAL REQUIREMENTS

Mobilization & demobilization 1 lot 10,000.00 10,000.00

Temporary facilities 1 lot 15,000.00 15,000.00

Electrical consumption 1 lot 50,000.00 50,000.00

Water consumption 1 lot 25,000.00

Others

TOTAL AMOUNT 100,000.00

EARTH WORKS

Excavation 150 cu.m. 400.00 60,000.00

backfill 120 cu.m. 200.00 24,000.00

Others

TOTAL AMOUNT 24,000.00

CONCRETE COLUMN AND FOOTINGS

COLUMN

Cement 50 bags 250.00 12,500.00

Sand 4 cu.m. 1,500.00 6,000.00

Gravel 8 cu.m. 1,800.00 14,400.00

FOOTINGS

Cement 50 bags 250.00 12,500.00

Sand 4 cu.m. 1,500.00 6,000.00

Gravel 6 cu.m. 1,800.00 10,800.00

CONCRETE HALLOW BLOCKS

CBH (exterior) 1,680 pcs. 10.00 16,800.00

Cement 108 bags 250.00 45,000.00

Sand 11 cu.m. 1,500.00 16,500.00

CBH (interior) 1,600 pcs. 10.00 16,000.00

Cement 43 bags 250.00 10,750.00

Sand 4 cu.m. 1,500.00 6,000.00

CBH Wall Footing

Cement 72 bags 250.00 18,000.00

Sand 5 cu.m. 1,500.00 7,500.00

Gravel 8 cu.m. 1,800.00 14,400.00

STEEL REINFORCING BARS


BEAM

Ø10mm x 7.60 37 pcs. 150.00 5,550.00

FOOTING

Ø16mm x 6.00M 76 pcs. 250.00 19,000.00

ON CBH WALLS (Horizontal)

EXTERIOR: Ø10mm. X 6.00m 32 pcs. 150.00 4,800.00

INTERIOR: Ø10mm. X 6.00m 19 pcs. 150.00 2,850.00

ON CBH WALLS (Vertical)

EXTERIOR: Ø10mm. X 6.00m 34 pcs. 150.00 5,100.00

INTERIOR: Ø10mm. X 6.00m 20 pcs. 150.00 3,000.00

WALL FOOTING

Ø10mm. X 6.00m 25 pcs. 150.00 3,750.00

Ø12mm. X 7.60m 50 pcs. 250.00 12,500.00

COLUMN

Ø10mm. X 6.00m 86 pcs. 250.00 21,500.00

TIES Ø10mm 76 pcs. 150.00 11,400.00

Sub-total 303,100.00