ID Operation Number Task Name Duration Predecessors Jun 5, '16 Jun 12, '16 Jun 19, '16 Jun

Duration Predecessors Jun 5, '16 Jun 12, '16 Jun 19, '16 Jun 26, '16
S S M T W T F S S M T W T F S S M T W T F S S M T W T
0 C295 #10 17.55 days
1 BASIC AIRCRAFT 17.55 days
2 FINAL ASSEMBLY LINE (BASIC) 17.55 days
3 STATION‐50 17.55 days
4 INSPECTION 0.14 days
5 95-00120-0001GBR1P1001F01 VISUAL CHECK FUSE. AFTER TRANS.& LGT OPS TAIL 1 hr
6 CENTER FUSELAGE 16.21 days 4
7 95-05321-0001ID02P1182F01 REMOVAL OF FLOORS &INSTL.OF DUMMY FLOORS 8.5 hrs

8 95-25002-0001GBR150173F01 INSTALLATION OF MBDU BOXES 9.5 hrs 7


9 95-05601-0039ID0250170F01 INSTL. OF CONTROL UNITS ON UNDER FLOORS 4.5 hrs 7
10 95-20008-0001GBR150250F01 INSTALLATION OF WINCH 0.5 hrs 7
11 95-21001-0001GBR150250F01 INSTALLATION OF WINCH CONTROL BOX 1.5 hrs 10
12 95-21001-0001GBR1P1077E01 CHECKING OF PILOT DOOR 28.5 hrs
13 95-00120-0001GBR1P1038R01 CHECKING OF LH PARATROOPER DOOR 5.5 hrs
14 95-00120-0001GBR1P1048R01 CHECKING OF RH PARATROOPER DOOR 5.5 hrs
15 95-25002-0001GBR150486C01 CONNECTION OF GBRI PC BOXES 12.5 hrs 8
16 95-05601-0039ID0250900C01 CONNECTION OF DCMBDU BOX 14 hrs 9
17 Wing 2.93 days
18 95-00120-0001GBR1P1155W01 EQUIPPING & POSITIONING OF WING 7.75 hrs
19 95-00120-0001GBR1P1156W01 FINAL INSTALLATION OF WING 4.75 hrs 18
20 95-25002-0001GBR1P1162E01 RE-INSTALLATION OF FORWARD SIDE BRIDGES 2.5 hrs 19

21 95-25002-0001GBR1P1093C01 RE-INSTALLATION OF CABLE GUIDES 4.5 hrs 19


22 95-00120-0001GBR150328M01 CONNECTION OF PROPELLER BRAKE HYDR 2.5 hrs 19
INSTL
23 95-60025-0001GBR150517W01 PREVIOUS WORKS OF FUSELAGE-CWB 3.5 hrs 20
INTERFACE
24 95-20008-0001GBR150083F01 PREVIOUS INSTL.OF ENGINE CONT.CABLES RH 4.5 hrs 22

25 95-20008-0001GBR150084F01 PREVIOUS INSTL.OF ENGINE CONT.CABLES LH 4.5 hrs 22

26 Engine 13.29 days 17


27 Mechanic 4.21 days
28 95-00120-0001GBR1P1330W01 PREVIOUS WORKS OF LH ENGINE 1.5 hrs
29 95-00120-0001GBR1P1336W01 PREVIOUS WORKS OF RH ENGINE 1.5 hrs
30 95-00120-0001GBR150331W01 POSITIONING OF LH ENGINE 9.5 hrs 28
31 95-00120-0001GBR150337W01 POSITIONING OF RH ENGINE 9.5 hrs 29
32 95-00120-0001GBR1P1346W01 ALIGNMENT OF RH ENGINE AIR INTAKE 2.5 hrs 31
33 95-00120-0001GBR1P1347W01 ALIGNMENT OF LH ENGINE AIR INTAKE 2.5 hrs 30
34 95-00120-0001GBR150332W01 FINAL EQUIPPING OF LH ENGINE 6 hrs 33
35 95-00120-0001GBR150338W01 FINAL EQUIPPING OF RH ENGINE 6 hrs 32
36 95-00120-0001GBR1P1356W01 INSTALLATION OF PROPELLER ON RH ENGINE 4 hrs 35
37 95-00120-0001GBR1P1357W01 INSTALLATION OF PROPELLER ON LH ENGINE 4 hrs 34
38 95-20008-0001GBR150085F01 FNL. INSTL.OF ENG CONTROL.CABLE RH SIDE 3.5 hrs 36
39 95-20008-0001GBR150086F01 FNL. INSTL.OF ENG CONTROL.CABLE LH SIDE 3.5 hrs 37
40 95-00120-0001GBR150218M01 RE-CONNEC. OF PROPELLER BRAKE HYD. INS 2.5 hrs 38,39
41 Electric 9.07 days 27
42 95-50001-0005GBR150615E01 INSTL. OF HARNESS 95-W1334-0003 (1M/1S) 3.5 hrs
43 95-50001-0005GBR150620E01 INSTL. OF HARNESS 95-W1339-0005 (1M) 3.5 hrs 42
44 95-50001-0005GBR150616E01 INSTL. OF HARNESS 95-W1335-0003 (1M/1S) 3.5 hrs 43
45 95-50001-0005GBR150619E01 INSTL. OF HARNESS 95-W1338-0007 (1P) 3.5 hrs 44
46 95-50001-0005GBR150618E01 INSTL. OF HARNESS 95-W1337-0001 (1G) 3.5 hrs 45
47 95-50001-0005GBR150802E01 ROUTING OF HARNESSES ON LH ENGINE 20.5 hrs 46
48 95-50001-0005GBR150617E01 INSTL. OF HARNESS 95-W1336-0001 (1G) 3.5 hrs 47
49 95-50002-0005GBR150625E01 INSTL. OF HARNESS 95-W1348-0005 (2M) 3.5 hrs
50 95-50002-0005GBR150626E01 INSTL. OF HARNESS 95-W1349-0005 (2M/2S) 3.5 hrs 49
51 95-50002-0005GBR150621E01 INSTL. OF HARNESS 95-W1344-0003 (2M) 3.5 hrs 50
52 95-50002-0005GBR150622E01 INSTL. OF HARNESS 95-W1345-0001 (2G) 3.5 hrs 51
53 95-50002-0005GBR150624E01 INSTL. OF HARNESS 95-W1347-0007 (2P) 3.5 hrs 52
54 95-50002-0005GBR150802E01 ROUTING OF HARNESSES ON RH ENGINE 20.5 hrs 53

Task Rolled Up Progress Inactive Task Manual Summary Rollup Deadline


Milestone Split Inactive Milestone Manual Summary
Project: C295 #10
Summary External Tasks Inactive Summary Start-only
Date: Tue 6/20/17
Rolled Up Task Project Summary Manual Task Finish-only
Rolled Up Milestone Group By Summary Duration-only Progress

Page 1
ID Operation Number Task Name Duration Predecessors Jun 5, '16 Jun 12, '16 Jun 19, '16 Jun 26, '16
S S M T W T F S S M T W T F S S M T W T F S S M T W T
55 95-50002-0005GBR150623E01 INSTL. OF HARNESS 95-W1346-0001 (2G) 3.5 hrs 54
56 REAR FUSELAGE 17.4 days 4
57 Tail Unit 17.4 days
58 95-31001-0001GBR1P1901H01 INSTL. OF RH ELEVATOR ON RH HTP & CHECK 5.5 hrs
59 95-31001-0001GBR1P1900H01 INSTL. OF LH ELEVATOR ON LH HTP & CHECK 5.5 hrs
60 95-00120-0001GBR1P1151H01 EQUIPPING & POSITION OF HTP BOTH SIDE 11.5 hrs 58,59
61 95-33001-0001GBR1P1902V01 INSTL. OF RUDDER ON VTP & CHECKING 1.5 hrs
62 95-00120-0001GBR1P1153V01 EQUIPPING & POSITIONING OF VTP 15.5 hrs 61
63 95-00120-0001GBR1P1152H01 FINAL INSTALLATION OF HTP 7.75 hrs 60,64
64 95-00120-0001GBR1P1154V01 FINAL INSTALLATION OF VTP 7.75 hrs 19,62
65 95-24002-0001GBR150385E01 INSTALLATION OF RH STRAKE 34.33 hrs 63
66 95-24002-0001GBR150384E01 INSTALLATION OF LH STRAKE 34.33 hrs 63
67 95-25800-0001GBR1P1152E01 FINAL INSTALLATION OF DORSAL FIN 11.5 hrs 64

Task Rolled Up Progress Inactive Task Manual Summary Rollup Deadline


Milestone Split Inactive Milestone Manual Summary
Project: C295 #10
Summary External Tasks Inactive Summary Start-only
Date: Tue 6/20/17
Rolled Up Task Project Summary Manual Task Finish-only
Rolled Up Milestone Group By Summary Duration-only Progress