Duration Predecessors Jun 5, '16 Jun 12, '16 Jun 19, '16 Jun 26, '16
S S M T W T F S S M T W T F S S M T W T F S S M T W T
0 C295 #10 17.55 days
1 BASIC AIRCRAFT 17.55 days
2 FINAL ASSEMBLY LINE (BASIC) 17.55 days
3 STATION‐50 17.55 days
4 INSPECTION 0.14 days
5 95-00120-0001GBR1P1001F01 VISUAL CHECK FUSE. AFTER TRANS.& LGT OPS TAIL 1 hr
6 CENTER FUSELAGE 16.21 days 4
7 95-05321-0001ID02P1182F01 REMOVAL OF FLOORS &INSTL.OF DUMMY FLOORS 8.5 hrs
Page 1
ID Operation Number Task Name Duration Predecessors Jun 5, '16 Jun 12, '16 Jun 19, '16 Jun 26, '16
S S M T W T F S S M T W T F S S M T W T F S S M T W T
55 95-50002-0005GBR150623E01 INSTL. OF HARNESS 95-W1346-0001 (2G) 3.5 hrs 54
56 REAR FUSELAGE 17.4 days 4
57 Tail Unit 17.4 days
58 95-31001-0001GBR1P1901H01 INSTL. OF RH ELEVATOR ON RH HTP & CHECK 5.5 hrs
59 95-31001-0001GBR1P1900H01 INSTL. OF LH ELEVATOR ON LH HTP & CHECK 5.5 hrs
60 95-00120-0001GBR1P1151H01 EQUIPPING & POSITION OF HTP BOTH SIDE 11.5 hrs 58,59
61 95-33001-0001GBR1P1902V01 INSTL. OF RUDDER ON VTP & CHECKING 1.5 hrs
62 95-00120-0001GBR1P1153V01 EQUIPPING & POSITIONING OF VTP 15.5 hrs 61
63 95-00120-0001GBR1P1152H01 FINAL INSTALLATION OF HTP 7.75 hrs 60,64
64 95-00120-0001GBR1P1154V01 FINAL INSTALLATION OF VTP 7.75 hrs 19,62
65 95-24002-0001GBR150385E01 INSTALLATION OF RH STRAKE 34.33 hrs 63
66 95-24002-0001GBR150384E01 INSTALLATION OF LH STRAKE 34.33 hrs 63
67 95-25800-0001GBR1P1152E01 FINAL INSTALLATION OF DORSAL FIN 11.5 hrs 64