Documente Academic
Documente Profesional
Documente Cultură
FOR ESTABLISHMENT OF
VARANASI, U.P.
Implementing Agency
UTTAR PRADESH TRADE PROMOTION AUTHORITY
Directorate of Industries, G.T. Road, Kanpur, U.P.-208005
Tel.: 0512 221 8401
CONTENTS
V Technical Offer
Financial Offer
SECTION – I
NOTICE INVITING TENDER
(On Turn Key Basis)
The Tender(s) duly filled in and completed in the prescribed manner, must be
submitted on the e-tender website (http://etender.up.nic.in) as per the time line
shown on the website.
The tender(s) received after stipulated time and date will not be entertained
under any circumstances and shall be summarily rejected.
SECTION – II
1.0 GENERAL
1.2. The different components of the work shall be executed under the
control and supervision of the following: -
1.3. The Contractor shall be basically liable to the Implementing Agency for
satisfactory completion of the work(s).
2.2 The cost of any civil works or any allied works required for
operationalisation of the Machine should be separately included in the
financial bid along with the rate(s) of the concerned
machine(s)/equipment with complete details and specifications of such
works so as to enable the UPTPA to make a comparative analysis of
the rates of different parties for such works. In case, a Tenderer has not
quoted rate(s) for such works, it shall be presumed that the cost of
such works has been included in the cost of the Machine(s)/Equipment
itself and no representation to the contrary shall be entertained
subsequently under any circumstances.
2.3 In case of D.G. Sets, a Tenderer must also necessarily quote the
cost of the work of connecting the same to the mains while giving
detailed break-up of the quoted rates.
3.0 MODE OF TENDERING
As per details given at S.N. 3.0 of NOTICE INVITING TENDER under Section–I.
5.1 The rates should be quoted by the Tenderer at the destination site
and it will include freight, transportation, labour cost, taxes etc., in
totality.
5.2 The tenderer shall bear all the costs associated with the preparation and
delivery of its Bid. The UPTPA will not be responsible or liable for
any such costs, whatsoever.
5.3 However, the UPTPA may assist the Contractor(s) in procuring Form No.
31/32 from the concerned Department of the State Government for ease
of bringing the goods into the State of Uttar Pradesh.
5.4 The UPTPA shall not provide any Form for any purpose.
5.5 The Rates quoted by the Tenderer and accepted by the UPTPA shall
hold good till the completion of the entire Work and no claim will be
admissible on account of fluctuation in market rates, increase in taxes/
any other levies/tools and tackles etc.
5.7 The submission of the Tender implies that the Tenderer has carefully
read the Tender Document including amendments if any and has
made himself/herself aware of the scope and specifications of the Work
to be executed, local conditions and other factors having bearing or
impact on the execution of the Work.
7.1 The Work, Bidding Procedure, Terms and Conditions of the Contract etc.
are described in the Tender Document. The intending Tenderers are
advised to examine the Tender Document and satisfy themselves
about the completeness of the Set consisting of all the Sections as
mentioned above.
7.2 The Tender is to be prepared strictly in accordance with the instructions
contained therein. Failure to prepare the Tender as per the instructions
and submission of Bid(s) not substantially responsive to the
requirements of Tender Document in every respect shall be summarily
rejected.
8.1 At any time prior to the expiry of the prescribed period for submission of
the Bids, the UPTPA may, for any reason whatsoever, modify the
Tender Document by suitable amendments under due
intimation and may also suitably extend the time limit for submission
thereof with due notice.
8.2 The amendment(s) shall be placed on the Website of the UPTPA and
also sent to the parties which by that time might have submitted the
Tender Document to the UPTPA and shall be binding on the Tenderers.
Such Tenderers may submit a revised Bid, if so desired.
9.1 While filling the Rates in the “Financial Offer”, the Tenderers shall ensure
that there are no discrepancies in the Rates mentioned in figures
and words. In case of any discrepancy in the Rates thus mentioned,
the Rates mentioned in words shall be taken as final and binding.
9.2 The Tender shall not contain any interlineations, erasing or over- writing
except as necessary to correct the errors made by the Tenderers
in which case such corrections shall be rewritten, initials and stamped by
the person who has signed the Tender. While writing Rates in
words, “only” should be used as the last word and it should be on the
same line.
9.3 The Tenderers must fill and s ub m it the Tender Document without
making any additions or alterations in the Tender Document. The
Rates should be filled in by the Tenderers as required in the Tender
Document.
9.4 All entries by the Tenderers should be in one ink and should be
written in a legible manner.
The Tenderer should clearly read all the terms and conditions mentioned in
the Tender Document. If he has any apprehensions/observations about the
specifications, conditions, etc., these should be clarified beforehand. The
clarifications as may be issued by the UPTPA shall also form an integral part
of the Contract. All such clarifications shall also be submitted, duly signed in
the prescribed manner, along with the Tender. No deviations in the Tender on
part of the Tenderers are allowed.
SL.
REQUIREMENT QUANITTY SPECIFICATIONS
NO.
Last Date, Time and Place of The bids shall be submitted till Date 23.09.2019
Submission of Bid 14.15 hours on the website
www.etender.up.nic.in
(Bid Submission can be done only from the Bid
Submission start date and time till the Bid
submission end date and time given in the bid.
Bidders should start the Bid Submission process
well in advance so that they can submit their Bid
in time. The bidders should submit their Bid
considering the server time displayed in the
website. This server time is the time by which
the Bid submission activity will be allowed till
the permissible time on the last/end date of
submission indicated in the e-bid schedule. Once
the bid submission date and time is over, the
bidders can not submit their Bid. For delay in
submission of Bid due to any reasons, the
bidders shall only be held responsible. )
Tender Fee INR1,790/- in the form of Demand Draft issued
by any nationalized / Scheduled Bank favouring
“UPTPA” payable at KANPUR.
Earnest Money Deposit (EMD) Earnest Money Deposit (EMD:Rs. 1,50,000/-) in
the form of FDR / Bank Guarantee issued by any
nationalized / Scheduled Bank favouring
“UPTPA” payable at KANPUR.
Date, Time and Place of Opening Directorate of Industries & Enterprise
of Tender: Promotion, U.P.
Uttar Pradesh Trade Promotion Authority
GT Road Sarvodaya Nagar, Kanpur- 208005
1- Opening of Technical Bid Date : 23.09.2019 Time : 14.15 hrs
2- Date of Meeting of Purchase Date: 27.09.2019 Time : 11.00 hrs.
Committee (Technical)
3- Date of Opening of Financial Date : 03.10.2019 Time : 14.00 hrs.
Bid
4- Date of Meeting of Purchase Date : 04.10.2019 Time : 11.00 hrs.
Committee (Financial)
Venue for PCM (T) & PCM (F) Directorate of Industries & Enterprise
Promotion, U.P.
Uttar Pradesh Trade Promotion Authority
GT Road Sarvodaya Nagar, Kanpur- 208005
Validity of Tender 120 days from the date of submission of tender
13.1 The technical offer must contain all the requisite documents/ papers viz.
Tender fees, EMD, Performance, statutory requirements (Registrations,
PAN, GST, Trade, others etc), necessary clearances, supporting
evidences in proof of annual turnover, other documents which the
Tenderer deem fit for Technical qualification duly attested and stamped
failing which the tender may be rejected.
13.2 As stated above, the Packet No. 1 shall contain Earnest Money Deposit
(EMD: Rs. 150000/-); the Tender Fee Money of Rs. 1790/- (Non-
Refundable) both in the form of Pay Order/ Demand Draft in Favour of
UPTPA, Payable at KANPUR ; complete Tender Document along with the
Amendments, if any, attested documentary evidence regarding having
supplied similar machines/ equipment to Governmental agencies,
attested copies of any registration/clearances as may be required for
due execution of the work.
13.4 The Tenders should be duly signed with date and sealed by an
authorized signatory of the Tenderer and also witnessed. The proof
of such authorization, in favour of the person, signing the Tender
should also be submitted along with the Tender.
14.1 Financial offer shall contain the Price/Financial Bid duly filled, in words
and figures on the BOQ.
14. 2 The Rates quoted by the Tenderers shall be for the complete job
inclusive of cost of the machines/equipment; labour charges,
transport charges, erection cost etc., and nothing more than the
quoted rates shall be payable to the Contractor(s).
The Director of Industries, UPTPA reserves the right to accept, cancel or reject
any or all Tenders or any of the work partly/fully at any time prior to award the
Work without assigning any reason or incurring any liability/obligation to the
Tenderers.
On receipt of the Letter of Acceptance, the successful Tenderer shall enter into
the Contract with the UPTPA on the date and time to be intimated by the
UPTPA for the purpose.
The Tender shall remain valid for 120 calendar days after the date of the
opening of the Tender.
SECTION – III
PART – A
GENERAL
1.0 DEFINITIONS
1.1 For the purpose of the Contract, the following words and expressions shall have
the m e a n i n g hereby assigned to them except where the context otherwise
requires: -
1.1.3 “Testing & Certifying Agency” means the Central Glass & Ceramic
Research Institute (CGCRI) having its office at G.T. Road, Khurja,
Bulandshahar, Uttar Pradesh.
1.1.5 “Contract” shall mean and include inter-alia the Notice Inviting Tenders,
Instructions to the Tenderers, Conditions of the Contract, Bill
of Quantities etc. constituting the Tender Document.
1.1.7 “Contract Value” means the value at which the work has been
awarded to the Contractor(s).
1.1.8 “Singular” shall also include the plural and vice-versa and the
masculine shall include feminine wherever the context requires.
2.0 CIVIL WORKS
All the civil works necessary for or incidental to the Work under this contract
shall form integral part of the Contract and executed by the Contractor(s).
3.0 SUB-CONTRACTING
The Contractor(s) shall not sub-contract, the whole or part of the Work except
wherever otherwise provided in the Contract.
During the execution of the Work, the Contractor(s) shall keep the Site
reasonably free from obstructions and shall store or dispose of all surplus
material and clear away and remove from Site all rubbish or temporary work,
no longer required for the purpose of this Contract.
On the completion of the Work, the Contractor(s) shall clear away and
remove from Site within a reasonable period of time, all plants, surplus
materials, rubbish and temporary work of every kind. The Contractor(s) shall
leave whole of the Site, work of every kind clear in conditions to the
satisfaction of the UPTPA.
All Specifications etc. and copies thereof furnished by the UPTPA to the
Contractor(s) shall be deemed to be the property of the UPTPA and shall not be
issued to any other person, body, firm etc. or used by the Contractor(s) for any
purpose except in connection with the Work of the UPTPA and no copies thereof
shall be supplied to anybody/person not connected with the Work, without the
express permission of the UPTPA. These shall be returned by the
Contractor(s) to the UPTPA on completion of the work or termination of
the Contract, whichever is earlier.
The UPTPA shall furnish desired details with reasonable promptness after
receipt of the Contractors’ request for additional instructions, necessary for the
proper execution of the Work or any part thereof.
If any ambiguity arises as to the meaning and intent of any part of the
Specifications or as to execution or quality of any work or material or as to the
measurements of the Work, the decision of the UPTPA thereon shall be final
and binding on the Contractor(s).
The Contractor(s) shall work in close co-ordination at all times with other
Contractors, Sub-Contractors and persons engaged on separate Contract(s) on
Site so that desired objectives are fully achieved.
6.1 The entire Work shall be completed in all respects within 06 Months from the
date of execution of the Contract.
The time period prescribed for execution and completion of the Work or part thereof
as specified in the Contract shall be essence of the Contract on the part of the
Contractor(s). Subject to any requirement in the Contract as to completion of any
portion or portions of the Work before completion of the whole, the Contractor(s)
shall fully and finally complete the whole of the Work comprised in the Contract by
date stipulated in the Contract in accordance with the Contract. In case of delay on
the part of the Contractor(s), the Contractor(s) shall render himself/herself liable to any
action including payment of Liquidated Damages/Compensation as may be decided
by the UPTPA in the circumstances of the case, in addition to any other
penalty/remedy available in the Contract for such delay.
8.1 The UPTPA reserves the right to suspend or reinstate, with prior notice to the
Contractor(s) in writing of its intention to do so, execution of the whole or any
part of the Contract/Work. In such a circumstance, the time for completion of
the activities of the Work shall be suitably extended.
The Contractor(s) shall, on the receipt of such notice from the UPTPA suspend,
within the reasonable time, the Work or any part thereof, for such time, and in
such manner, as the UPTPA may consider necessary and shall during such
suspension, properly protect and secure the Works, machines/equipment so far
as it is necessary in the opinion of the UPTPA.
8.4.2 For any such Suspension of Work not exceeding three days at any
one time, the Contractor(s) will not be entitled to any extension of
time prescribed for completion of the Work except unless
specifically agreed to by the UPTPA.
9.0
[[
OCCUPATION AND USE OF SITE
9.1 It is hereby expressly declared that the entry of the Contractor(s) on the Site
will merely be a lic-ense for carrying out the activities under this Contract and
they shall not by their being so allowed acquire any right, lien or interest
either in or the completed work undertaken by them under this Contract or
anything appurtenant or attached thereto.
9.2 The Contractor(s) shall not use, or allow Site to be used for any
purpose other than that of executing the Works under the Contract.
10.1 The Contractor(s) shall be responsible for all risks to the Work and for
trespass and shall make good, at his/her own expense, all loss or damage to
the Work themselves or to any other Works at the Site or any other
completed Work or Works-in-Progress or the lives, persons and property
of others from any reason in connection with the Work until they have
been taken over by the UPTPA.
10.2 In case, the UPTPA is called upon to make good any such costs, loss or
damage or compensation, to any person or persons sustaining injury or
damage etc. as aforesaid by reason of any act, omission or negligence
on the part of the Contractor(s), the amount of such costs or charges
(including costs and charges in connection with the legal proceedings) which
the UPTPA may incur in reference thereto, shall be charged to the Contractor(s).
11.1 The Contractor(s) shall comply with all the provisions of any Statute,
Regulation and Bye-law of any local Authority and Undertaking,
including those controlling the utilities such as water supply, etc. The
Contractor(s) shall be bound to give all notices required by Statute, Regulation
or Bye-law, as aforesaid and to pay for all fees, charges and bills to any
Authority or Undertaking in respect thereof.
12.1.2 The Specifications etc. of the Work assume a proper degree of skill
on the part of Contractor(s) and workmen employed by him. The
C o n t r a c t o r (s) s h a l l consult UPTPA, whenever in his
judgment variation in the methods of execution or in the quality
of materials would be beneficial or necessary to fulfil the
guarantees called for. Such variations may be made by the
Contractor(s) only when authorized by the UPTPA beforehand.
12.2 Any failure on the part of the Contractor(s) in this respect shall be
dealt with in accordance with provisions of this Contract.
The Contractor(s) shall keep the UPTPA indemnified against any claim(s) by a third
party regarding infringement of its intellectual property rights or otherwise either with
regard to designs of the machines/equipment etc. or execution of the works under the
Contract.
PART – C
COMMENCEMENT OF THE WORK
14.0 COMMENCEMENT OF THE WORK
15.1.1 The Contractor(s) shall appoint and keep on the Site at all times,
efficient, competent and qualified personnel to give the necessary
directions to his workmen and to ensure that they execute their work
in a sound and proper manner as per the specifications etc. and also
in accordance with the prescribed time schedule.
15.1.2 In the event of the UPTPA being of the opinion that the
Contractor(s) is not employing on the Site sufficient number of
staff and workmen as are necessary for the proper completion of
the Work, the Contractor(s) shall forthwith, on receiving intimation
to this effect, take on the additional number of staff and labour
specified by the UPTPA within three days of being so required and
failure on the part of the Contractor(s) to comply with such instructions
will entitle the UPTPA to rescind the Contract under relevant
provisions of the Contract.
16.1.1 The Contractor(s) shall make his own arrangements for the
engagement of all labour except as provided otherwise in the Contract
and, shall provide for their transport, housing, payments etc.
16.2.1 The Contractor(s) shall comply fully with all Laws and Statutory
Regulations as may be in force from time to time dealing with
any aspect of engagement of Labour whether promulgated by the
Central or State Government(s).
The Contractor(s) shall be solely responsible for setting out works and for the
correctness of the positions, levels, dimensions and alignment according to
the specifications etc. and shall provide without any charges all necessary
instruments and equipment as may be required for the purpose.
19.1 The Contractor(s) shall provide all the facilities including equipments for
inspection and testing of Work during the execution, so as to permit close
supervision and quality assurance during execution.
19.2 The UPTPA also reserves the right to undertake pre-delivery inspection of the
machines etc. while these are being fabricated at the place of the
Contractor(s). The Contractor(s) shall extend all the due assistance for the
purpose.
Site Inspection Register will be maintained by the Contractor(s) who will sign
day-to-day entries- s made therein by the UPTPA or its representative.
The Contractor(s) will be bound to take into account all the instructions given to
him through the Site Inspection Register(s) and would comply with the same
within a reasonable time.
20.1 The CGCRI reserves the right to carry out such inspections of the material,
quality of the Work and other connected matters as it may deem fit in
association with any party identified by it for the purpose. The Contractor(s)
shall render all possible assistance in this regard.
20.2 The Contractor(s) shall provide free access to the Officers and representatives
o f the CGCRI to visit and inspect the Work being carried out by the
Contractor(s)/Suppliers.
20.3 However, this shall not absolve the Contractor(s) of the responsibility
for the quality control, timely completion of the Works and other jobs agreed
to be rendered in terms of the provisions of this Contract.
21.1 The UPTPA shall not be liable or responsible for any accident or loss, injury
resulting in death or damage of any kind whatsoever happening or
occurring during the period of execution of the Works and even
thereafter before delivery of the possession of the Works, to persons and/or
property, materials and equipment and the Contractor(s) shall fully indemnify
and hold harmless the UPTPA against the same.
21.2 In addition to the liability imposed by any law upon the Contractor(s) for injury
(including death) to person or damage to property by reason of their
negligence which liability is not impaired or otherwise affected hereby,
the Contractor(s) shall be liable for and agrees to keep the UPTPA harmless
and indemnified from every expense, liability and payment by reasons of
any damage to property/person suffered through any act or omission of the
Contractor(s).
21.3 If the Contractor(s) or any person or persons working at Site on their behalf shall
break, deface, injure or destroy any part of building/other machines/equipment
in which they may be working or any road, road- kerb, sewer, main
closure, water pipe, cables, drains, electric or telephone posts or wires, trees,
grass or grass land or cultivated ground contiguous to the premises and/or the
work or any part of it being executed or if any damage shall happen to the
Works while in progress from any course, the Contractor(s) shall upon receipt
of a notice in writing in that behalf, make the same good at his own
expense.
21.4 The Contractor(s) at his own cost shall get fully insured against claims for
death, injury and property damage in respect of the operations under the
Contract for any reason whatsoever, including acts of nature.
21.5 All the policies covering above stipulations shall be executed with any of the
Nationalized Insurance Companies in the joint name of the UPTPA and
Contractor(s) and submitted to the UPTPA coinciding with the commencement of
the activities under the Contract. The policies cannot be cancelled until 20 days
after written notice of such intent of cancellation has been given to the UPTPA and
shall be valid till the period the Work is satisfactorily completed and taken
over by the UPTPA.
21.6 The Contractor(s) shall be responsible for anything that may be excluded from
the insurance policies above referred to and all other damage to any
property/person arising out of and incidental to their carrying out the
execution of the Works i n a negligent or defective manner. The UPTPA
shall also be indemnified in respect of any costs, charges, or expenses
arising out of any claim or proceedings and also in respect of any Award
or Compensation or Damages arising there from. The UPTPA shall be at
liberty and is hereby authorized to deduct cost, charges and expenses
arising or accruing from or in respect of any such claim or damage(s),
from any sum due or as may become due to the Contractor(s).
22.1 The UPTPA shall provide a proper and lockable accommodation to the
Contractor(s) for storage etc. of his/her equipment, spares etc. till they are
suitably assimilated in the Works.
22.2 The UPTPA, however, does not assume any responsibility whatsoever of any
loss/damage to the same either due to negligence or otherwise for which
eventuality, the Contractor(s) is required to take necessary Insurance etc. or
steps required for protecting the goods etc.
PART – E
PAYMENTS TO THE CONTRACTOR
23.1 The total value of the work shall be released to the Contractor(s) in the
following manner: -
23.2 No interest shall accrue to the Contractor(s) on any sum retained by the UPTPA
by way of Earnest Money or otherwise.
All the applicable Taxes shall be deducted at source by the UPTPA from the
gross amount of each bill against Work in accordance with the existing
Statutes or as may be promulgated during the currency of the Work and as may be
amended from time to time.
The UPTPA may on account of subsequently discovered evidence nullify the whole
or part of any verification to such extent as may be necessary to protect the UPTPA
from loss of account of any sub-standard work or any work carried out contrary to or
without the instructions of the UPTPA.
PART – F
COMPLETION OF WORK
27.1 The delivery of possession shall not be construed to mean the acceptance and
the consequent taking over of the Work and Materials.
27.2 The Contractor(s) shall continue to be responsible for the quality and
performance of such machines, equipment etc. and to comply with the
specifications until taking over of the Work and fulfilment of Maintenance
Period as provided in this Contract.
28.1 The Maintenance Period shall be one year from the date of successful
commissioning of the works.
28.2 Any defect or other faults including manufacturing defects/faults which may
appear within the Maintenance Period, shall upon the directions in writing of
the UPTPA, within such reasonable time as shall be specified therein, be
rectified and made good by the Contractor(s) at his own cost and in case of
failure to do so, the UPTPA may employ and pay any other persons to
amend and make good such defects, shrinkages, settlements or other
faults and all damages, loss and expenses consequent thereon or
incidental thereto, shall be made good and borne by the Contractor(s)
and such damages, loss and expenses shall be recoverable by the UPTPA
from any money due or that may become due to the Contractor(s) or
adjusted against the amount retained as Security Deposit as provided
hereinbefore and in the event of the amount thus retained being insufficient,
recover the balance from the Contractor(s) together with any expense, the
UPTPA may have incurred in connection therewith.
The Contractor(s) shall abide by all instructions given by the UPTPA during
currency of work and furnish details in the prescribed forms as may be
deemed necessary from time to time, for documentation of records in connection
with the Work.
PART—G
MISCELLANEOUS
30.1 The Contractor(s) shall be responsible for providing 72 hours training to the
personnel on the installed machines with respect to its operations,
maintenance etc.
30.2 The appropriate duration and cost per day of training be quoted separately for
machines in different parts.
31.1 The UPTPA without prejudice to any other remedy available against the
Contractor(s) in terms of the provisions of this Contract or otherwise shall
have right to determine the Contract after issuing a written notice to the
Contractor(s) to this effect in any of the following circumstances: -
31.2 If the Contractor(s) have made themselves liable for action under any of the
cases aforesaid, the UPTPA shall have powers to:-
ii) Engage any other Contractor(s) to carry out the balance of the Work.
31.3 In such a circumstance, the Earnest Money & Security Money of the
Contractor(s) shall stand forfeited to the UPTPA without prejudice to the
UPTPA’s right to recover from the Contractor(s) any amount by which the
cost of completing the- residual work by any other agency shall exceed the
amount that would have been payable to the Contractor(s) for the residual work.
33.1 The standard Force Majeure Clause subject to the express provisions of
this Clause shall apply and in such an eventuality, the rights and
obligations of the respective parties shall subject to the express provisions of
this Contract, be determined in a mutually agreed manner.
33.2 “Force Majeure” for the purpose of this Clause shall also include any
cause/factor which is beyond the control of the UPTPA or the Contractor(s) as
the case may be, which they could not foresee or with due diligence could not
have foreseen and which substantially affects the due performance of the
respective duties under the Contract such as :-
b) Strikes
33.3 Either party to the Contract shall not be liable for delay in performance of
its respective obligations under the Contract from any Force Majeure as
indicated above and the time frame stipulated for completion of the activities will
be appropriately extended in such a circumstance.
33.4 In the unlikely event of such a factor persisting even beyond a reasonable
period of time, either party shall have the right to terminate the Contract
and the right or liabilities of the parties upon such termination shall be
determined in a mutually agreed manner.
34.2 The UPTPA shall then be entitled to deduct the amount so payable
from any amount otherwise due to the Contractor(s) under the Contract.
35.1 In the event of any dispute or difference whatsoever arising between the
parties out of or pertaining to any Clause of this Contract including any
question relating to meaning and interpretation of this Contract or any alleged
breach thereof, except those the decisions whereof have been specifically
provided in the Contract, the same shall be settled as far as possible by
mutual discussions and consultations between the parties.
35.3 The Award, if any, of the Arbitrator, so appointed, shall be final and binding on
all the parties.
35.4 If any question, difference or dispute still remains unresolved, the same shall
be subject to the jurisdiction of the Courts in the State of U.P.
Note:
All the tenderers will have to remain present during purchase committee meeting as referred. The
Opening of tenders shall only be attended by an authorized representative of the firm whose name,
designation and address should be indicated in the offer of the firm. Tendering firm shall issue a letter of
authority to such representative (Authorization letter must be issued by the competent authority
photograph & signature attested with indentity & address proof )that for Tender
No…………………dated………/………/………… due to be opened on ………../………/…...for the
Item……………………….proceedings shall be attended by the representative whose signatures shall be
attested by the principal firm. The representative shall always possess such authority letter while
attending tender opening meeting. Unauthorized persons shall not be allowed to enter in tender opening
room. The same process shall also apply to Purchase Committee Meeting (Technical) & Purchase
Committee Meeting (Financial).
To
Dear Sirs,
In accordance with the Notice Inviting Tender, M/s. having its head
Office at (hereinafter called the Tenderer) is participating in
the tender for in UPTPA, at Directorate of Industries, G.T.
Road, Kanpur, U.P.-208005, you, as a special favour have agreed to
accept an irrevocable and unconditional bank guarantee for an amount
of Rs. (Rupees only) valid
up to on behalf of the Tenderer in lieu of Earnest Money Deposit
required to be made by the Tenderer, as a condition precedent for
participation in the said tender.
3. W e are liable to pay the guaranteed amount or any part thereof under
this Bank Guarantee only and only if you serve upon us a written claim
or demand on or bef ore i.e. The date of
expiry of guarantee.
In witness whereof the Bank, through its authorized officer has set its
hand and stamp on this at .
For
Signature
Witnesses
Name
Designation
Stamp of the Bank
C. REFUND OF SECURITY AMOUNT
Dear Sirs,
W e, (Bank),
(complete address) having its head office at
(hereinafter referred to as “Bank” which expression wherever the context so
requires, shall include its successors, administrators, executors and assigns)
do hereby bind ourselves irrevocably as guarantor and hereby unconditionally
guarantee and undertake to pay the UPTPA on demand any and all money
payable by the Contractor on this account to the extent of
Rs._ (Rupees_ ) as aforesaid at any time
up to (date) without any demur, protest reservation,
recourse, contest and or without any reference to the Contractor.
Any such demand made by the UPTPA on the bank shall be final,
conclusive and binding on the Bank notwithstanding any difference between
the UPTPA and the Contractor or existence of dispute or difference between
the Contractor and the UPTPA or any such difference or any dispute pending
before any Court; Tribunal, Arbitrator or any other authority/authorities. This
bank guarantee shall not be revocable by notice or otherwise and shall be a
continuing guarantee, until discharged by the UPTPA earlier in writing.
The UPTPA shall have the fullest liberty, without affecting in any way
the liability of the Bank under this Guarantee, from time to time, to vary the
obligations/terms and conditions of the Contract. The UPTPA shall have the
fullest liberty, without affecting this Guarantee, to postpone from time to time
the exercise of any powers vested in them or of any right which they might
have against the said Contractor, and to exercise the same at any time in any
manner and either to enforce or to forebear to enforce any covenants,
contained or implied in the Contract between the UPTPA and the Contractor
or any other course or remedy or security available to the UPTPA. The Bank
shall not be released of its obligations under these presents by any exercise
by the UPTPA of its liberty with reference to the matters aforesaid or any of
them or by reason of any other act of omission or commission, on the part of
the UPTPA or any other indulgences shown by the UPTPA or by any other
matter or thing whatsoever which under law would, but for this provision have
the effect of relieving the Bank.
The Bank also agrees that the UPTPA at its option shall be entitled
to enforce this Guarantee against the Bank as a principal debtor in the
first instance without proceeding against the Contractor and notwithstanding
any security or other Guarantee the UPTPA may have in relation to
the Contractors liabilities.
1. Our liabilities under this unconditional Bank Guarantee shall not exceed
Rs. (Rupees )
Witness
For Bank
Signature, Name, Designation and
Signature
Date:
Name of Firm
Address
Tel. No.(s)
Telegram
Fax No.
If the tendering Firm is Agent/Distributor then please fill up the details of your principal
manufacturer in left column.
(b) GST
Details of Previous Supply of similar Items during the last two years if any:
Seal
Technical Offer
2. Address
3. Registration
(Company/SSI/MSME)
7. GST No.
Note: If the Tenderer feel any extra work to be done for the establishment of plant, machinery,
and Equipments etc., or any other things required to be furnished in the Technical Offer, please
indicate and mention underneath and enclose separate sheet for the purpose.