Sunteți pe pagina 1din 91

2015 IPC Design, Installation and Inspection Principles

Description
 The 2015 International Plumbing Code® (IPC®)
2015 Design, IPC® continues to emphasize both prescriptive and
performance-related provisions.
Installation and Inspection  The 2015 IPC encompass the initial design of the
Principles plumbing system, the installation and construction of
plumbing systems and the maintenance of operating
Based on the 2015 International Plumbing systems.
Code® (IPC®)  All plumbing systems that are provided for utilization by
and for the general safety and wellbeing of the
occupants of a building are intended to be governed by
the code.

2015 IPC Design, Installation and Inspection Principles 2

Goal Objectives
 The goal of this seminar is to provide key  Upon completion, participants will be better able
information on the design, installation and to:
inspection principles based on the 2015 IPC.
 Identify code enforcement issues and key code
sections

 Describe the application of the code to inspection,


plan review and code enforcement

2015 IPC Design, Installation and Inspection Principles 3 2015 IPC Design, Installation and Inspection Principles 4

Copyright 2015 International Code Council 1
2015 IPC Design, Installation and Inspection Principles

Marginal Markings within


Table of Contents
the codebook
 Solid vertical lines indicate a technical change  Module I – Administration, Definitions and
from the requirements of the 2009 edition. General Regulations
 Arrows indicate where a section, paragraph,  Module 2 – Fixtures,
item in a list, exception or table has been  Module 3 – Water Systems, Sanitary Drainage
deleted. and Venting
 Module 4 – Storm Drainage, Special Piping and

*
 A single asterisk [*] indicates that text or a table
has been relocated elsewhere in the code. Storage Systems and Gray Waste Recycling

**
Systems.
 A double asterisk [**] indicates that the section
or table immediately following has been
relocated here from a different section.
2015 IPC Design, Installation and Inspection Principles 5 2015 IPC Design, Installation and Inspection Principles 6

Part 1 Chapter One

Administration, Definitions Administration


and General Regulations
7 8

Copyright 2015 International Code Council 2
2015 IPC Design, Installation and Inspection Principles

Chapter One — Administration Scope 101.2


 Applies to the code official Code applies to: Code doesn’t apply to:
 Establishes the rights and privileges of the  Erection  fuel gas systems
design professional, contractor and building  Installation  Residential buildings
owner  Alterations
 Establishes the responsibilities of various  Repairs
professionals  Relocation
 Replacement
 Addition to
 Use or maintenance

2015 IPC Design, Installation and Inspection Principles 9 2015 IPC Design, Installation and Inspection Principles 10

Existing installations 102.2 Maintenance 102.3


 Existing Inspector’s Challenge:  The owner or  Inspector’s challenge:
installations that  Installations that did authorized agent shall  The code official has
were installed per the not meet code at the maintain the system the right to re-inspect
code in effect during time of construction and all of its parts in a the plumbing systems
its construction do not will need to be safe operating and may be called on
need to be changed, brought up to the condition to force compliance
provided it is current code. with the code when
maintained in good the plumbing systems
operating condition. are unsafe.

2015 IPC Design, Installation and Inspection Principles 11 2015 IPC Design, Installation and Inspection Principles 12

Copyright 2015 International Code Council 3
2015 IPC Design, Installation and Inspection Principles

Additions, alterations or repairs


Change of occupancy 102.5
102.4
 The new work shall Inspector’s challenge:  A change of Inspector’s challenge:
comply with the Determining what has occupancy requires Determining what
current code, the been altered or that all parts of the plumbing elements, if
existing parts may repaired, may require a plumbing system any, can have their use
continue unchanged if preliminary inspection meet the current code continued is sometimes
they are safe before new work for that occupancy hampered by limited
commences. access to the systems
involved. (buried in
walls, underground)

2015 IPC Design, Installation and Inspection Principles 13 2015 IPC Design, Installation and Inspection Principles 14

Duties and Powers of the Code


Administration – Chapter 1
Official Section 104
 The code official shall:  Section 105 – Approval
 Receive applications, review plans and issue permits  Section 108 – Violations
 Conduct inspections and record the results  Section 109 – Means of Appeal
 Have the right of entry to inspect (within the law)
 Section 110 – Temporary Equipment, Systems
 Carry identification
and Uses
 Issue the appropriate notices to ensure compliance
 Keep and retain records of activities

2015 IPC Design, Installation and Inspection Principles 15 2015 IPC Design, Installation and Inspection Principles 16

Copyright 2015 International Code Council 4
2015 IPC Design, Installation and Inspection Principles

Chapter One —
Administration
 Discuss the following questions:

 What are the Duties and Power of the Code


Official?

 What are your challenges as a code official? Chapter Two

Definitions

2015 IPC Design, Installation and Inspection Principles 17 18

Branch intervals Depth of Trap Seal


 Change from depth of
water seal
 Allows other liquids to
maintain the seal,
such as in a waterless
urinal

2015 IPC Design, Installation and Inspection Principles 19 2015 IPC Design, Installation and Inspection Principles 20

Copyright 2015 International Code Council 5
2015 IPC Design, Installation and Inspection Principles

Grease Interceptor Plumbing Appliance


 There is difference between a
 Fats, oils and grease (FOG) disposal systems plumbing fixture and a plumbing
 Gravity appliance.
 Hydromechanical  A dishwasher is a plumbing
appliance.
 Because a jetted whirlpool tub
does not depend upon energized
components to be a bathtub, it is
a plumbing fixture.

2015 IPC Design, Installation and Inspection Principles 21 2015 IPC Design, Installation and Inspection Principles 22

Plumbing Fixture Toilet Facility


 Plumbing fixture could have only a water supply
 A room or space that
connected to it, only a waste line connected to it,
contains not less than
or both.
one water closet and
one lavatory.

2015 IPC Design, Installation and Inspection Principles 23 2015 IPC Design, Installation and Inspection Principles 24

Copyright 2015 International Code Council 6
2015 IPC Design, Installation and Inspection Principles

Alternate Onsite Nonpotable


Gravity GREASE INTERCEPTOR
Water
Alternative Onsite
Nonpotable Water.
 A way to collect waste
water for partial
treatment and reuse
for flushing toilets and
urinals.

2015 IPC Design, Installation and Inspection Principles 25 2015 IPC Design, Installation and Inspection Principles 26

Waste Receptor Parts of a plumbing system


 Waste Receptor. A
floor sink, standpipe,
hub drain or a floor
drain that receives the
discharge of one or
more indirect waste
pipes.

2015 IPC Design, Installation and Inspection Principles 27 2015 IPC Design, Installation and Inspection Principles 28

Copyright 2015 International Code Council 7
2015 IPC Design, Installation and Inspection Principles

Section 301.3 – Connections to


drainage system
 An exception is
included to allow
gray-water-producing
fixtures to be
connected to a gray
Chapter 3 water collection

General Regulations

29 2015 IPC Design, Installation and Inspection Principles 30

Section 303.4 – Third-party


Section 303.1 – Identification
certification
 This requires all plumbing products and
materials be listed by a third-party certification
agency such are the ICC-ES PMG Listing
Program.

2015 IPC Design, Installation and Inspection Principles 31 2015 IPC Design, Installation and Inspection Principles 32

Copyright 2015 International Code Council 8
2015 IPC Design, Installation and Inspection Principles

Section 304.4 – Section 305.3 – Pipes through


Openings for pipes foundation walls
 All spaces between pipes and the sides of the
openings through walls, floors or ceilings shall
be caulked or closed with appropriate material.

 All pipes traveling through a foundation wall must


be sleeved or have a relieving arch that supports
the foundation.

2015 IPC Design, Installation and Inspection Principles 33 2015 IPC Design, Installation and Inspection Principles 34

Section 305.6 – Protection


Section 305.4 – Freezing
against physical damage

2015 IPC Design, Installation and Inspection Principles 35 2015 IPC Design, Installation and Inspection Principles 36

Copyright 2015 International Code Council 9
2015 IPC Design, Installation and Inspection Principles

Section 305.7 – Protection of Section 306 — Trenching,


plumbing system components excavation and backfill
CONCRETE-FILLED
STEEL POST

WALL BEYOND PROTECTED


RECESSED IN BY A GUARD
BUILDING
WALL
DRIVEWAY
DRIVEWAY

NOTE: OTHER METHODS OF PROTECTION OF PLUMBING COMPONENTS ARE


POSSIBLE, SUBJECT TO APPROVAL BY THE CODE OFFICIAL.

2015 IPC Design, Installation and Inspection Principles 37 2015 IPC Design, Installation and Inspection Principles 38

Section 307.2 – Cutting, notching


Section 307 — Structural safety
or bored holes

2015 IPC Design, Installation and Inspection Principles 39 2015 IPC Design, Installation and Inspection Principles 40

Copyright 2015 International Code Council 10
2015 IPC Design, Installation and Inspection Principles

Section 307.3 – Penetration of


Section 307.2 – Cutting, notching
floor/ceiling assemblies and fire-
or bored holes resistance-rated assemblies

2015 IPC Design, Installation and Inspection Principles 41 2015 IPC Design, Installation and Inspection Principles 42

Section 307.3 – Penetration of Section 307.3 – Penetration of


floor/ceiling assemblies and fire- floor/ceiling assemblies and fire-
resistance-rated assemblies resistance-rated assemblies

2015 IPC Design, Installation and Inspection Principles 43 2015 IPC Design, Installation and Inspection Principles 44

Copyright 2015 International Code Council 11
2015 IPC Design, Installation and Inspection Principles

Section 307.5 Protection of


Piping support—Section 308
footings
 Trenches installed
parallel to footings
must remain outside
the bearing plane of
the bottom of the
footing

2015 IPC Design, Installation and Inspection Principles 45 2015 IPC Design, Installation and Inspection Principles 46

Location of hangers Table 308.5 –


Hanger spacing
 The spacing of
supports, listed in
Table 308.5, is based
on reducing the sag
of the piping system

For SI: I inch =25.4 mm

2015 IPC Design, Installation and Inspection Principles 47 2015 IPC Design, Installation and Inspection Principles 48

Copyright 2015 International Code Council 12
2015 IPC Design, Installation and Inspection Principles

Midway guides Section 308.6 –Sway bracing


 Midway guides shall be installed on
2015 IPC
Table 308.5 a number of products when the size
Footnote b
midway is 2 inches or less. Midway between
guides the required vertical supports (5’).
These guides should not be tight,
vertical movement should be
unimpeded.

2015 IPC Design, Installation and Inspection Principles 49 2015 IPC Design, Installation and Inspection Principles 50

Section
308.7 – Section
Anchorage 308.7.1 –
Location

2015 IPC Design, Installation and Inspection Principles 51 2015 IPC Design, Installation and Inspection Principles 52

Copyright 2015 International Code Council 13
2015 IPC Design, Installation and Inspection Principles

Section 308.9 – Parallel water


Section 309.2 – Flood hazard
distribution systems
 The code refers to an elevation as required by
 Where hot water piping is bundled with other hot
Section 1612 of the International Building Code
water piping or cold water piping, each
as such required elevations may be above the
individual hot water pipe must be insulated.
actual design flood elevation.
 309.3 restricts plumbing from penetrating or
being mounted to walls that are designed to
break away in flood conditions.

2015 IPC Design, Installation and Inspection Principles 53 2015 IPC Design, Installation and Inspection Principles 54

Washroom and toilet room


requirements—Section 310 Section 311 —
Toilet facilities
 Toilet room
requirements are for workers
regulated by building
and mechanical code.

2015 IPC Design, Installation and Inspection Principles 55 2015 IPC Design, Installation and Inspection Principles 56

Copyright 2015 International Code Council 14
2015 IPC Design, Installation and Inspection Principles

Section 312 – Tests and Section 312.9 —


Inspections Shower liner test
 Section 312.1 – Required tests
 Section 312.2 – Drainage and vent water test
 Section 312.3 – Drainage and vent air test
 Section 312.4 – Drainage and vent final test
 Section 312.5 – Water supply system test
 Section 312.6 – Gravity sewer test
 Section 312.7 – Forced sewer test
 Section 312.8 – Storm drainage system test
 Section 312.9 – Shower liner test
 Section 312.10 – Inspection and testing of backflow
prevention assemblies

2015 IPC Design, Installation and Inspection Principles 57 2015 IPC Design, Installation and Inspection Principles 58

Section 312.9 — Shower liner Section 314.2.2 – Drain pipe


test materials and sizes
2015 IPC
Table
314.2.2
Page 22

2015 IPC Design, Installation and Inspection Principles 59 2015 IPC Design, Installation and Inspection Principles 60

Copyright 2015 International Code Council 15
2015 IPC Design, Installation and Inspection Principles

Section 315.1 — Sealing of


Section 315 – Penetrations
annular spaces
 Brings the plumbing code into alignment with the
energy code, by sealing openings in wall plates.
 Any penetration of fire-rated assemblies shall
sealed per the building code.

2015 IPC Design, Installation and Inspection Principles 61 2015 IPC Design, Installation and Inspection Principles 62

Module 1 — Administration, Module 1 — Administration,


Definitions and General Definitions and General
Regulations Regulations
1. After final approval of a plumbing system, the 2. Requirements needed for plumbing safety that
code does not provide for any reinspection of are not in the code shall be determined by the
the system. Code Official
__________________.

True False

According to Section 102.3, the code official shall have


the authority to require any plumbing system to be
reinspected.

2015 IPC Design, Installation and Inspection Principles 63 2015 IPC Design, Installation and Inspection Principles 64

Copyright 2015 International Code Council 16
2015 IPC Design, Installation and Inspection Principles

Module 1 — Administration, Module 1 — Administration,


Definitions and General Definitions and General
Regulations Regulations
3. Define the following words: 4. A pipe sleeve used for protection shall be two
Conductor– A _______________________
Conductor pipe inside the building that conveys pipe sizes greater than the pipe passing through
Graywater
storm waterfrom________________________
the roof to a storm or combined the wall.
building
Plumbingdrain.
fixture ___________________
Gray water – Water waste discharged from lavatories,
bathtubs, showers, clothes washers and laundry traps. True False
Plumbing fixtures – A receptacle or device that is
connected to a water supply system or discharge to a
drainage system or both.

2015 IPC Design, Installation and Inspection Principles 65 2015 IPC Design, Installation and Inspection Principles 66

Module 1 — Administration, Module 1 — Administration,


Definitions and General Definitions and General
Regulations Regulations
5. Gravity sewer tests consist of filling the pipe with 6. An air test may be used to test plastic plumbing
10
no less than a ________foot head of water. systems.
3048 mm
True False

2015 IPC Design, Installation and Inspection Principles 67 2015 IPC Design, Installation and Inspection Principles 68

Copyright 2015 International Code Council 17
2015 IPC Design, Installation and Inspection Principles

Module 1 — Administration, Module 1 — Administration,


Definitions and General Definitions and General
Regulations Regulations
gray water
7. A potable water system or a _____________ 8. Penetrations of the building envelope that leave
system may be used to flush water closets. gaps between the sides of the opening and the
sealed
pipe shall be _______________.

2015 IPC Design, Installation and Inspection Principles 69 2015 IPC Design, Installation and Inspection Principles 70

Module 1 — Administration, Module 1 — Administration,


Definitions and General Definitions and General
Regulations Regulations
9. An alternative engineered design for a plumbing 10. A shower liner test must be plugged below the
system may be used if it provides the flange clamping the liner and filled with water
equivalent level of quality, strength,
_____________ to the overflow point.
effectiveness, fire resistance, durability and
safety. True False

2015 IPC Design, Installation and Inspection Principles 71 2015 IPC Design, Installation and Inspection Principles 72

Copyright 2015 International Code Council 18
2015 IPC Design, Installation and Inspection Principles

Module 2 Chapter 4

Fixtures, Water Heaters, Fixtures, Faucets and


Indirect/Special Wastes and Fixture Fittings
Separators
73 74

Table 403.1 — Minimum


Table 403.1 — Minimum Number
Number of Plumbing Fixtures
of Plumbing Fixtures (portion)
 The number of fixtures provided shall be
determined based on the actual use of the 2015 IPC
Table 403.1
building Pages
25-27
 Ex. A gymnasium with a stage for assemblies at a
school without permanent seating would be an A-3

d. The occupant load for seasonal outdoor seating and entertainment areas shall be included when
determining the minimum number of facilities required.

2015 IPC Design, Installation and Inspection Principles 75 2015 IPC Design, Installation and Inspection Principles 76

Copyright 2015 International Code Council 19
2015 IPC Design, Installation and Inspection Principles

Table 403.1 — Minimum Table 403.1 — Minimum


Number of Plumbing Fixtures Number of Plumbing
(portion)
Fixtures
2015 IPC
Table 403.1

 A mixed-use building with a Group E (education)


Pages
25-27

occupant load of 538, Group A-3 (gymnasiums,


halls, museums) occupant load of 115 and
Group S-1 (storage) occupant load of 82.
e. For business and mercantile occupancies with an occupant load of 15 or fewer, service sinks shall not  What are the minimum numbers of fixtures
be required.
required for each sex? See previous slides.

2015 IPC Design, Installation and Inspection Principles 77 2015 IPC Design, Installation and Inspection Principles 78

Section 403.2.1 — Family or


Section 403.2 — Separate
assisted-use toilet facilities
facilities serving as separate facilities.

 Item 3 changed to allow a mercantile occupant  Added to allow two “no sex designated”
load of up to 100 persons before separate sex family or assisted-use toilet rooms to
facilities are required. serve a space that requires only one water
 This relaxes the burden on small retail spaces closet per sex.
so that they do not require two accessible toilet  Advantage is that because either toilet room can
rooms, which take up a disproportionate amount be used by either sex, there is more availability
of space. of facilities in smaller spaces without needing to
offer multiple-user toilet facilities.

2015 IPC Design, Installation and Inspection Principles 79 2015 IPC Design, Installation and Inspection Principles 80

Copyright 2015 International Code Council 20
2015 IPC Design, Installation and Inspection Principles

Section 403.3 — Required public Section 403.3.2 — Toilet room


toilet facilities locations new drawing show lavs
Exceptions:
 To clarify that parking lots and parking garage
buildings (without attendants) do not require
public toilet facilities.
 Structures and tenant spaces intended for quick
transactions, including take out, pick up and
drop off, having a public access area less than
or equal to 300 sq. ft. do not need to provide
public facilities (employee restrooms still apply)

2015 IPC Design, Installation and Inspection Principles 81 2015 IPC Design, Installation and Inspection Principles 82

Section 403.5 —
Section 403.3.6 — Door locking
Drinking fountain location
 Doors of multiple-  The code requires drinking fountains to be
occupant toilet rooms located within 500’ of the most remote tenant
must not be capable space.
of being locked from
the inside.

Within a travel distance of


500 feet of the most remote
location in the tenant space.

2015 IPC Design, Installation and Inspection Principles 83 2015 IPC Design, Installation and Inspection Principles 84

Copyright 2015 International Code Council 21
2015 IPC Design, Installation and Inspection Principles

Section 405.3.1 — Fixture Section 405.3.5 — Urinal


Clearances Partitions
Index
A. All fixtures shall not be closer than  Each urinal
15” from center to sidewall. utilized by the
B. All fixtures shall not be closer than public or
30’’ center to center between
adjacent fixtures. employees shall
C. All fixtures shall have at least 21“ of occupy a separate
clearance in front.
area with walls or
D. Water closet compartments shall
not be less than 30“ wide and 60’’ partitions to
deep. provide privacy.
E. Urinal partitions shall extend at
least 18“ from sidewall or 6’’ out
from the lip.

2015 IPC Design, Installation and Inspection Principles 85 2015 IPC Design, Installation and Inspection Principles 86

Section 405.3.5 — Urinal Section 405.4 — Floor and wall


Partitions (cont.) drainage connections

At least 18”  A new type of


from wall

6”
water closet drain
connection is
added to this
At least 60”
from floor
section.

No more
than 12”
From floor

2015 IPC Design, Installation and Inspection Principles 87 2015 IPC Design, Installation and Inspection Principles 88

Copyright 2015 International Code Council 22
2015 IPC Design, Installation and Inspection Principles

Section 406.2 — Waste Section 407.2 — Bathtub waste


Connections outlets and overflows
Note: Where a connection is
made to a fixture branch,
horizontal branch drain or
 Overflows for
drainage stack, the minimum bathtubs are
required size is 3 inches required as a
safeguard against
the overfilling of
bathtubs.

2-inch minimum 3-inch minimum

2015 IPC Design, Installation and Inspection Principles 89 2015 IPC Design, Installation and Inspection Principles 90

Dishwashing Machines— Section 410.1 — Approved


Section 409 drinking fountains
 Although the IPC indicates the minimum number
of drinking fountains for an occupancy, the
International Building Code required additional
drinking fountains to comply with accessibility
regulations.
 The International Building Code requirement
was brought into the IPC for clarity.

2015 IPC Design, Installation and Inspection Principles 91 2015 IPC Design, Installation and Inspection Principles 92

Copyright 2015 International Code Council 23
2015 IPC Design, Installation and Inspection Principles

Section 410.3 — Minimum Section 410.3 — Substitution for


number of drinking fountains drinking fountains
 Restaurants where water is served with the meal
may omit a drinking fountain.
 Water dispensers can be substituted for half the
required drinking fountains.

2015 IPC Design, Installation and Inspection Principles 93 2015 IPC Design, Installation and Inspection Principles 94

Section 412.3 — Size of Floor


Section 412.2 — Floor Drains
Drains

2015 IPC Design, Installation and Inspection Principles 95 2015 IPC Design, Installation and Inspection Principles 96

Copyright 2015 International Code Council 24
2015 IPC Design, Installation and Inspection Principles

Section 413.4 – Water supply Section 416.1 — Group Wash-up


required Fixture
Group wash up equipment shall conform to the
requirements of Section 416.

20 inches of rim
equals one
lavatory

2015 IPC Design, Installation and Inspection Principles 97 2015 IPC Design, Installation and Inspection Principles 98

Section 416.5 — Tempered water


417.2 — Water supply riser
for public handwashing facilities
 Riser must be fastened using screws or a device
specifically designed for such purpose.
 This section was revised to clarify what is
considered to be a public hand-washing facility.
 Tempered water is required for lavatories and
group wash up fixtures in public toilet facilities
provided for customer, patrons and visitors.
 Maximum temperature at the outlet: 110 degrees

2015 IPC Design, Installation and Inspection Principles 99 2015 IPC Design, Installation and Inspection Principles 100

Copyright 2015 International Code Council 25
2015 IPC Design, Installation and Inspection Principles

Section 417.4 — Shower


Exception:
compartments

2015 IPC Design, Installation and Inspection Principles 101 2015 IPC Design, Installation and Inspection Principles 102

417.4.1 Floor and wall area Section 417.4.2 — Access


 The shower compartment
 Smooth, corrosion access and egress
resistant, and non- opening shall have a
absorbent materials minimum clear and
shall extend to at least unobstructed finished
6 feet above floor level width of 22 inches.
and not less that 70  Shower compartments
inches above the drain required to be designed
of the tub or shower in conformance to
joints made water tight accessibility provisions
shall comply with Section
404.1.

2015 IPC Design, Installation and Inspection Principles 103 2015 IPC Design, Installation and Inspection Principles 104

Copyright 2015 International Code Council 26
2015 IPC Design, Installation and Inspection Principles

Section 419.1 — Approval Section 420.1 – Approval


 Urinals shall conform to
 Electro-hydraulic water
ANSI Z124.9, ASME
closets (a water closet of
A112.19.2M, CSA B45.1 or the siphonic or washdown
CSA B45.5. Urinals shall type that utilizes motors,
conform to the water pumps, and controllers to
consumption requirements assist the flushing action)
of Section 604.4.  And dual flush water closets
 Water-supplied urinals shall (two flushing actions, one
conform to the hydraulic using less water than 1.6
performance requirements gal/flush) are addressed Dual flush water closets
of ASME A112.19.6, CSA and the relevant standards
B45.1 or CSA B45.5. are cited.

2015 IPC Design, Installation and Inspection Principles 105 2015 IPC Design, Installation and Inspection Principles 106

Section 421.5 —
Section 421.5 — Access to Pump
Access to Pump (cont.)

2015 IPC Design, Installation and Inspection Principles 107 2015 IPC Design, Installation and Inspection Principles 108

Copyright 2015 International Code Council 27
2015 IPC Design, Installation and Inspection Principles

Section 424.3 – Individual Section 424.4 – Multiple (gang)


shower valves showers

2015 IPC Design, Installation and Inspection Principles 109 2015 IPC Design, Installation and Inspection Principles 110

Maximum Temperatures Allowed Section 424.9 — Water closet


At Use Locations personal hygiene devices
Maximum
Plumbing Fixture Discharge
Temperature
Reference Standard IPC Section  ASME A112.4.2 was added to the code to cover
1. Bidet ≤ 110°F (43.33°C) ASSE 1070 408.3 specialized water closets or water closet seats
2. Public hand-
> 85°F (29.44°C) having sprays for personal hygiene.
and ASSE 1070 or CSA B125.3 416.5
washing facilities
< 110°F (43.33°C)
3. Individual shower ASSE 1016 or ASME A112.18.1 /
≤ 120°F (48.89°C) 424.3
valves CSA B125
4. Multiple (gang)
≤ 120°F (48.89°C) ASSE 1069 or CSA B125 424.3
showers

≤ 120°F (48.89°C) ASSE 1070 or CSA B125.3


5. Bathtub/whirlpool
except as allowed by Section 424.5
bathtubs
424.3.

2015 IPC Design, Installation and Inspection Principles 111 2015 IPC Design, Installation and Inspection Principles 112

Copyright 2015 International Code Council 28
2015 IPC Design, Installation and Inspection Principles

Section 501.2 – Water heater as


space heater

Chapter 5
Water-to-Air
Water Heaters Heat
Exchanger

113 2015 IPC Design, Installation and Inspection Principles 114

502.5 Clearance for Maintenance


502.1.1 Elevation and protection
and Replacement
 Elevation of water
heater ignition sources
and mechanical
damage protection
requirements for water
heaters shall be in
accordance with the
International
Mechanical Code and
the International Fuel
Gas Code.

2015 IPC Design, Installation and Inspection Principles 115 2015 IPC Design, Installation and Inspection Principles 116

Copyright 2015 International Code Council 29
2015 IPC Design, Installation and Inspection Principles

Section 503.1 – Cold water Section 504.4.1 - Installation of


line valve temperature and pressure relief valves

Water Heater Valve

2015 IPC Design, Installation and Inspection Principles 117 2015 IPC Design, Installation and Inspection Principles 118

Section 504.4.1 - Installation of


temperature and pressure relief valves Section 504.4.1 – Installation
CORRECT INSTALLATION

2015 IPC Design, Installation and Inspection Principles 119 2015 IPC Design, Installation and Inspection Principles 120

Copyright 2015 International Code Council 30
2015 IPC Design, Installation and Inspection Principles

Section 504.6 - Requirements for


Section 504.7- Required pan
discharge piping
 The language states that
where drain pans are
required for water heaters
they are only required for
storage tank-type water
heaters or hot water
storage tanks. Tank-less
water heaters are exempt.

2015 IPC Design, Installation and Inspection Principles 121 2015 IPC Design, Installation and Inspection Principles 122

Section 505.1 - Unfired vessel


insulation

 Unfired hot water storage tanks shall be


insulated to R-12.5 (h × ft2 × °F)/Btu
(R-2.2 m2 × K/W).

Chapter 8

Indirect/Special Wastes

2015 IPC Design, Installation and Inspection Principles 123 124

Copyright 2015 International Code Council 31
2015 IPC Design, Installation and Inspection Principles

Section 801.1 - Scope Section 802.1 - Where required


 Food-handling establishments
 Sterilizers
 Clear-water waste
 Swimming pools
 Methods of providing air breaks or air gaps
 Neutralizing devices for corrosive waste

2015 IPC Design, Installation and Inspection Principles 125 2015 IPC Design, Installation and Inspection Principles 126

Section 802.1.2 – Floor drains in Section 802.1.3 - Potable clear-


food storage areas water waste

2015 IPC Design, Installation and Inspection Principles 127 2015 IPC Design, Installation and Inspection Principles 128

Copyright 2015 International Code Council 32
2015 IPC Design, Installation and Inspection Principles

Section 802.1.8 - Food utensils,


Section 802.2 – Installation
dishes, pots and pans sinks
 Sinks used for the washing, rinsing or sanitizing
of utensils, dishes, pots, pans or service ware
used in the preparation, serving or eating of food
must connect indirectly to the drainage system
through an air gap or air break.

2015 IPC Design, Installation and Inspection Principles 129 2015 IPC Design, Installation and Inspection Principles 130

Section 802.2.1 – Air gap Section 802.2.2 - Air Break

2D

Waste
Receptor

2015 IPC Design, Installation and Inspection Principles 131 2015 IPC Design, Installation and Inspection Principles 132

Copyright 2015 International Code Council 33
2015 IPC Design, Installation and Inspection Principles

Section 802.3 - Waste receptors


Section 802.3 –
 In addition to waste receptors prohibited from Waste
being in bathrooms or toilet rooms, they are now
prohibited from being in plenums, crawl spaces,
receptors
attics, interstitial spaces above ceilings and
below floors.
 Waste receptors in those locations can dry out
or overflow without knowledge of the occupants.

2015 IPC Design, Installation and Inspection Principles 133 2015 IPC Design, Installation and Inspection Principles 134

Section 802.4 - Standpipes

Chapter 10

Traps, Interceptors and


Separators
2015 IPC Design, Installation and Inspection Principles 135 136

Copyright 2015 International Code Council 34
2015 IPC Design, Installation and Inspection Principles

Section 1002.1, Exception 4 for Floor


Section 1002.1 - Fixture traps Drain Traps in Parking Garages
 An exception for parking garage floors drains
allows them to run without traps when they run
to a storm sewer.
 Traps for individual floor drains are not required
provided that the drains are connected to a main
trap before discharge to a combined sewer.

2015 IPC Design, Installation and Inspection Principles 137 2015 IPC Design, Installation and Inspection Principles 138

Section 1002.1 - Fixture traps Section 1002.3 - Prohibited traps


INLET
INLET
VENT
WATER SEAL
OUTLET

CROWN WEIR
SEAL WATER CLOSETS HAVE
AN INTEGRAL TRAP TRAP WITH FLOAT BALL
DIP
BELL TRAP (MOVING PARTS)
EXCEPTION #1 CROWN-VENTED TRAP

TWO-COMPARTMENT SINK
SINK

“OLD STYLE” FLOOR


“DRUM TRAP”
”S” TRAP TENDS TO DRAIN WITH INTERIOR
MAX. VERTICAL SELF-SIPHON PARTITION EXCEPTION:
DISTANCE - 24" WHEN USED AS A SOLIDS
INTERCEPTOR
MAX. DISTANCE - 30"
MAX. DISTANCE - 6"

EXCEPTION #2

2015 IPC Design, Installation and Inspection Principles 139 2015 IPC Design, Installation and Inspection Principles 140

Copyright 2015 International Code Council 35
2015 IPC Design, Installation and Inspection Principles

Section 1002.4 - Trap seals Trap seal barrier


 Minimum liquid seal is 2 inches (51 mm)
 Maximum liquid seal is 4 inches (102 mm)
 When evaporation threatens the trap seal, the
seal shall be protected by one of four methods
 Trap seal protection shall conform to ASSE
1018, ASSE 1044, or ASSE 1072

2015 IPC Design, Installation and Inspection Principles 141 2015 IPC Design, Installation and Inspection Principles 142

Section 1003.1 -
Section 1002.4 - Trap seals
Interceptors and separators
 Trap seal primer valve discharge piping must connect  Provided to prevent the discharge of:
to the trap above the trap seal water line.  Oil
 Grease
 Sand
 Substances harmful to the system, e.g. acid, heavy
metals

2015 IPC Design, Installation and Inspection Principles 143 2015 IPC Design, Installation and Inspection Principles 144

Copyright 2015 International Code Council 36
2015 IPC Design, Installation and Inspection Principles

Section 1003.2 - Approval Section - 1003.3.1


 Grease interceptors and automatic grease
removal devices required
 A list of equipment and fixtures that require their
waste water be treated in commercial settings

 grease interceptors can be installed in series, instead


of requiring the replacement of an existing grease
interceptor that is too small.

2015 IPC Design, Installation and Inspection Principles 145 2015 IPC Design, Installation and Inspection Principles 146

Section 1003.3.1 - Grease interceptors


Grease Interceptor In Series and automatic grease removal device

2015 IPC Design, Installation and Inspection Principles 147 2015 IPC Design, Installation and Inspection Principles 148

Copyright 2015 International Code Council 37
2015 IPC Design, Installation and Inspection Principles

Section 1003.3.2 - Food waste


Outside Grease Interceptors
grinders

2015 IPC Design, Installation and Inspection Principles 149 2015 IPC Design, Installation and Inspection Principles 150

Section 1003.3.5 - Automatic grease


removal devices
Gravity grease interceptors

2015 IPC Design, Installation and Inspection Principles 151 2015 IPC Design, Installation and Inspection Principles 152

Copyright 2015 International Code Council 38
2015 IPC Design, Installation and Inspection Principles

Section 1003.4.2 - Oil separator Section 1003.6 – clothes washer


design discharge interceptor
 Oil separators not  Applies to
designed in commercial and
accordance with industrial clothes
Sections 1003.4.2.1 washers
and 1003.4.2.2, must  Applies to
be listed and labeled. residential clothes
washers when there
is more than one in
a laundry room

2015 IPC Design, Installation and Inspection Principles 153 2015 IPC Design, Installation and Inspection Principles 154

Section 1003.9 - Venting of Venting of Interceptors and


grease interceptor Separators
FLOOR
DRAINS

DISHWASHER

FLOOR
DRAINS
PRE-RINSE AND
FOOD WASTE
GRINDER 3 COMPARTMENT
SINK

POT WELL
SINK

GREASE INTERCEPTOR

2015 IPC Design, Installation and Inspection Principles 155 2015 IPC Design, Installation and Inspection Principles 156

Copyright 2015 International Code Council 39
2015 IPC Design, Installation and Inspection Principles

Module 2 - Fixtures, Water Heaters, Module 2 - Fixtures, Water


Indirect/Special Waste and Heaters, Indirect/Special
Separators Waste and Separators
1. There shall be at least 21 inches (533 mm) of 2. The waste outlet of a pressure, temperature or
clearance in front of a lavatory to any wall or other relief valve shall be indirectly connected to
fixture. drainage system (Section 504.6).
the __________________

True False

2015 IPC Design, Installation and Inspection Principles 157 2015 IPC Design, Installation and Inspection Principles 158

Module 2 - Fixtures, Water Module 2 - Fixtures, Water


Heaters, Indirect/Special Heaters, Indirect/Special
Waste and Separators Waste and Separators
3. Standpipes shall extend a minimum of 4. The vertical distance from the fixture outlet to
18 inches (457 mm) and a maximum of
_________________ the trap weir shall not exceed
_________________
42 inches (1067 mm) inches above a trap. 24 inches (610 mm)
______________________ .

2015 IPC Design, Installation and Inspection Principles 159 2015 IPC Design, Installation and Inspection Principles 160

Copyright 2015 International Code Council 40
2015 IPC Design, Installation and Inspection Principles

Module 2 - Fixtures, Water Module 2 - Fixtures, Water


Heaters, Indirect/Special Heaters, Indirect/Special
Waste and Separators Waste and Separators
5. Bathtubs require a waste outlet and an 6. An indirect waste receptor installed below the
overflow outlet both connected to 1½ inch
_________ floor in a crawl space is a code violation.
(38 mm) pipe.
True False

2015 IPC Design, Installation and Inspection Principles 161 2015 IPC Design, Installation and Inspection Principles 162

Module 2 - Fixtures, Water Module 2 - Fixtures, Water


Heaters, Indirect/Special Heaters, Indirect/Special
Waste and Separators Waste and Separators
7. When a water heater is connected to an 8. When lack of space or capacity is a factor, an
additional storage tank, both the water heater additional grease interceptor may be added
and the tank must have temperature and upstream of the existing grease interceptor.
pressure relief valves.
Yes No
True False

2015 IPC Design, Installation and Inspection Principles 163 2015 IPC Design, Installation and Inspection Principles 164

Copyright 2015 International Code Council 41
2015 IPC Design, Installation and Inspection Principles

Module 2 - Fixtures, Water


Heaters, Indirect/Special
Waste and Separators
9. A tankless water heater (does or does not)
require a water heater pan.

Does Does Not Module 3

Water Systems, Sanitary


Drainage and Venting
2015 IPC Design, Installation and Inspection Principles 165 166

601.5 Rehabilitation
 Existing water piping
systems may be
rehabilitated using an
epoxy liner system
that complies with
Chapter 6 ASTM F 2831.

Water Supply and


Distribution
167 2015 IPC Design, Installation and Inspection Principles 168

Copyright 2015 International Code Council 42
2015 IPC Design, Installation and Inspection Principles

Section 602.2 – Potable Water


602.3.4 Disinfection of system
Required
 Only potable water shall be supplied to plumbing  All newly constructed water supply systems shall
fixtures that provide water for drinking, bathing be disinfected as outlined in this code.
or culinary purposes, or for the processing of
food, medical or pharmaceutical products.
 Unless otherwise provided in this code, potable
water shall be supplied to all plumbing fixtures.

2015 IPC Design, Installation and Inspection Principles 169 2015 IPC Design, Installation and Inspection Principles 170

Section 603.1 - Size of Water Section 603.2 - Separation of Water


Service Pipe Supply and Building Sewer
UNEXCAVATED OR COMPACTED
EARTH SEPARATING TRENCHES COMMON TRENCH

Exception 1

12" MIN.
WATER SERVICE
ON SHELF

BUILDING SEWER IN BUILDING SEWER


SEPARATE TRENCH WATER SERVICE IN
SEPARATE TRENCH

5' MINIMUM

2015 IPC Design, Installation and Inspection Principles 171 2015 IPC Design, Installation and Inspection Principles 172

Copyright 2015 International Code Council 43
2015 IPC Design, Installation and Inspection Principles

Section 603.2 - Separation of Water Section 603.2.1 - Water Service


Service and Building Sewer Near Sources of Pollution
 Potable water service pipes shall not be
located in, under or above:
 Cesspools
 Septic tanks
 Septic tank drainage fields or seepage pits
Sewer pipe not
listed in Table
702.2

2015 IPC Design, Installation and Inspection Principles 173 2015 IPC Design, Installation and Inspection Principles 174

Section 604 - Design of Building Example of E201.1


Water Distribution System (Residential Method)
 Shall conform to accepted engineering practice.
The following example utilizes Appendix E
 Appendix E describes two methods of sizing a (Residential Method).
water supply system.
 Section E103.3 (Segmented loss method)  A building with 15’ elevation difference to the
 Section E 201.1 (Based on water fixture units or old highest water supply outlet.
method)  Available Pressure = 65 psi low, 70 psi high.
 Developed length of 40’.
 Combined fixture unit value of 27.5.

2015 IPC Design, Installation and Inspection Principles 175 2015 IPC Design, Installation and Inspection Principles 176

Copyright 2015 International Code Council 44
2015 IPC Design, Installation and Inspection Principles

Step Task
1 Obtain the minimum service pressure (psig) available from the local water authority. Example of E201.1 (Residential Method) cont.
2 Adjust for elevation conditions (Subtract 0.5 psi for each foot of height. If the highest water supply
outlet is below the meter, add .5 psi for each foot of difference. Take in consideration the pressure Steps
reducing valve.
Results
3 Deduct for all pressure losses caused by special equipment, such as backflow preventers, water
softeners, filters, etc. The loss is determined in accordance with the manufacture’s. specifications. Step 1. 65 Example 65
Table 604.3
4 Determine if fixture water controls require more than 8 psig minimum to operate. (Note the resulting Step 2. 15’ x 0.5 - 7.5
figure). Temperature-controlled shower valve deduct in excess of 8 psi (12).
Step 3. 3 psi -3
5 Note the resulting figure.
6 Determine the approximate length of piping from the water main to the most remote fixture in house. Step 4. Temperature-controlled showers deduct in excess of 8 psi -12
(The hot water circuit may be the longest length.)
Step 5. Resulting pressure 42.5
7 Using the “Combined” column of Table E103.3(2) add the water system fixture units (wsfu ) of all
fixtures that are a part of the system, and note the resulting figure. Step 6. 48’ = (40’ x 1.2) Table E103.3(2) 48’
8 In the appropriate pressure range (from step 5) of the Table E201.1, find the maximum developed Step 7. 1 bathroom group = 2 x 3.6 (private use) 7.2
length through water heater or cold water branches and multiply by 1.2 to account for fittings. Read
down this column until you find the (wsfu) that is equal to or greater than the total (wsfu) obtained Kitchen sink = 1 x 1.4 1.4
in Step 7.
9 Read across this row to obtain the minimum meter and service pipe size from column one. Dishwasher = 1 x 1.4 1.4
10 Determine required size of each branch, by starting at the most remote outlet and work back to the Hose bibb = 3 x 2.5 7.5
main distribution pipe. Determine the (wsfu) on a given section of piping and using the same
pressure range and maximum developed length column as in Step 8, locate the (wsfu) and read Sprinkler head = 5 x 2.0 10
across that row to obtain the pipe size for that section. Total 27.5
2015 IPC Design, Installation and Inspection Principles 177 2015 IPC Design, Installation and Inspection Principles 178

TABLE E103.3(2) (Private) WATER SUPPLY


FIXTURE UNIT VALUES FOR VARIOUS
Presure (pounds per square inch = 0.5 x head (feet) PLUMBING FIXTURES AND FITURE GROUPS
WATER SUPPLY FIXTURE UNIT VALUE
TYPE OF FIXTURES OR GROUP OF FIXTURES (w.s.f.u.)
HOT COLD COMBINED

Elevation Bathtub (with/without overhead shower head) Private 1.0 1.0 1.4
Loss of Pressure (-)
Example:
Pressure at meter = 80 psi
Clothes washer (Private) 1.0 1.0 1.4
Elevation change = 20 feet
P = 0.5 X Head (feet)
Dishwasher (Private) 1.4 — 1.4
P = 0.5 X 20 feet
P = 10 psi Bathroom group (Private), (Flush tank) with bathtub or shower stall 1.5 2.7 3.6
Pressure for sizing, then, is
Meter Static Pressure Loss
80 psi - 10 psi = 70 psi Half-bath group (water closet and lavatory) 0.5 2.5 2.6
Hose bibb (Silcock)ª — 2.5 2.5
Kitchen group (dishwasher and sink with/without garbage grinder) 1.9 1.0 2.5
Kitchen sink (private) 1.0 1.0 1.4
Laundry group (clothes washer standpipe and laundry tub) 1.8 1.8 2.5
Meter Gain in Pressure (+)
Elevation Pressure for sizing. then, is
80 psi +10 psi = 90 psi
Laundry tub (private) 1.0 1.0 1.4
Lavatory (private) 0.5 0.5 0.7
Shower stall (private) 1.0 1.0 1.4
Back Water closet (tank type), (private) — 2.2 2.2
Back
Static Pressure Gain
2015 IPC Design, Installation and Inspection Principles 179 2015 IPC Design, Installation and Inspection Principles 180

Copyright 2015 International Code Council 45
2015 IPC Design, Installation and Inspection Principles

TABLE E201.1
Example of E201.1 (Residential MINIMUM SIZE OF WATER METERS, MAINS AND
DISTRIBUTION PIPING BASED ON WATER SUPPLY
Method) cont FIXTURE UNIT VALUES (w.s.f.u.)
Pressure Range-40 to 49
 Step 8. From the “Pressure Range 40-49 psi”
MAXIMUM DEVELOPMENT LENGTH (feet)
(from step 5) column, read down the 60’ column. METER AND
DISTRIBUTION
PIPE
Table E201.1 SERVICE PIPE
(INCHES) 40 60 80 100 150 200 250 300 400 500
(INCHES)

 Step 9. The meter size from column one is ¾” ¾ ½ª 3 2.5 2 1.5 1.5 1 1 .5 .5 .5

¾ ¾ 9.5 9.5 8.5 7 5.5 4.5 3.5 3 2.5 2


and the main distribution pipe shall be 1 inch. ¾ 1 32 32 32 26 18 13.5 10.5 9 7.5 6

1 1 32 32 32 32 21 15 11.5 9.5 7.5 6.5


¾ 1¼ 32 32 32 32 32 32 32 27 21 16.5

1 1¼ 80 80 80 80 65 52 42 35 26 20
1½ 1¼ 80 80 80 80 75 59 48 39 28 21

1 1½ 87 87 87 87 87 87 87 78 65 55

1½ 1½ 151 151 151 151 151 130 109 93 75 63

2015 IPC Design, Installation and Inspection Principles 181 2015 IPC Design, Installation and Inspection Principles Step 8 182

Section 604.5 - Size of Fixture Table 604.5


Supply Minimum Sizes
of Fixture Water
Supply Pipes

Table 604.5
Back

2015 IPC Design, Installation and Inspection Principles 183 2015 IPC Design, Installation and Inspection Principles 184

Copyright 2015 International Code Council 46
2015 IPC Design, Installation and Inspection Principles

Chapter 6 – Water Supply and


Section 604.9 – Water Hammer
Distribution
2015 Section Title Description of Change

Table 605.3 Water Service Chlorinated polyvinyl


Pipe chloride/aluminum/chlorinated
polyvinyl chloride
Table 605.4 Water Distribution
Pipe

Table 605.7 Valves

2015 IPC Design, Installation and Inspection Principles 185 2015 IPC Design, Installation and Inspection Principles 186

605.2.1 Lead content of drinking


Valves
water pipe and fittings
 Valves must be  Everything used in a
compatible with the water supply shall
type of piping being comply with NSF 372
used which stipulates no
 Valves shall meet the more than .25 of a
standards in Table percent of lead
605.7 content
 Valve shall comply
with NSF 61

2015 IPC Design, Installation and Inspection Principles 187 2015 IPC Design, Installation and Inspection Principles 188

Copyright 2015 International Code Council 47
2015 IPC Design, Installation and Inspection Principles

Section 605.24.1 – Copper or copper- Section 606 - Installation of the


alloy tubing to galvanized steel pipe Building Water Distribution System
Section 606.1 Location
of Full Open Valves
 Full-open valves shall
be installed in the
following locations:
 Curb Valve

2015 IPC Design, Installation and Inspection Principles 189 2015 IPC Design, Installation and Inspection Principles 190

Section 606.2 - Section 606.2 - Location of Shutoff


Location of Shutoff Valves Valves Shutoff Valves For Each Fixture
 Shutoff valves shall be installed in the following
locations:
 On the fixture supply to each plumbing fixture other
than bathtubs and showers in one- and two-family
residential occupancies, and other than in individual
sleeping units that are provided with unit shutoff
valves in hotels, motels, boarding houses and similar
occupancies.
 On the water supply pipe to each sillcock.
 On the water supply pipe to each appliance or
mechanical equipment.

2015 IPC Design, Installation and Inspection Principles 191 2015 IPC Design, Installation and Inspection Principles 192

Copyright 2015 International Code Council 48
2015 IPC Design, Installation and Inspection Principles

Valve at Entrance to Building and


Dwelling Unit Valve
on Discharge Side of Meter

2015 IPC Design, Installation and Inspection Principles 193 2015 IPC Design, Installation and Inspection Principles 194

Valves for Each Riser & Down Section 606.4 -


Feed Valve Identification

Section 606.4
requires valve
to be identified

2015 IPC Design, Installation and Inspection Principles 195 2015 IPC Design, Installation and Inspection Principles 196

Copyright 2015 International Code Council 49
2015 IPC Design, Installation and Inspection Principles

Section 606.7 – Labeling of water


Section 607.1 – Where required
distribution pipes in bundles
 This new section requires that water distribution
piping that is in bundles have labels to identify the
direction of flow and contents.

2015 IPC Design, Installation and Inspection Principles 197 2015 IPC Design, Installation and Inspection Principles 198

Section 607.1.1 - Temperature Section 607.2 – Hot water supply


limiting means temperature maintenance
 This section was  The threshold for where a hot water temperature
added to prohibit a maintenance system is required was lowered
water heater from 100 feet to 50 feet (30 480 mm to 15 240
thermostat from being mm).
used as the
temperature limiting
device where the
code requires a limit
for hot or tempered
water.

2015 IPC Design, Installation and Inspection Principles 199 2015 IPC Design, Installation and Inspection Principles 200

Copyright 2015 International Code Council 50
2015 IPC Design, Installation and Inspection Principles

Section 607.2 – Hot or Tempered 607.2.1 maintaining heated water


Water Supply to Fixture temperature
 Residential
occupancies shall
comply with the
energy code section
R403.5 .1
 Commercial
occupancies shall
comply with the
energy code section
C404.6
2015 IPC Design, Installation and Inspection Principles 201 2015 IPC Design, Installation and Inspection Principles 202

Section 607.3 - Example of Pressure Reducing Valve with


Thermal Expansion Control Thermal Expansion Bypass
Example of
closed system

2015 IPC Design, Installation and Inspection Principles 203 2015 IPC Design, Installation and Inspection Principles 204

Copyright 2015 International Code Council 51
2015 IPC Design, Installation and Inspection Principles

607.5 [E] - Pipe insulation Section 607.5 - Pipe insulation


 The International Energy Conservation
Code regulates pipe insulation, which is
sometimes installed by the plumbing
contractor.

2015 IPC Design, Installation and Inspection Principles 205 2015 IPC Design, Installation and Inspection Principles 206

Section 608.7 – Stop-and-waste Section 608.8 - Identification of


valves prohibited nonpotable water
 Wherever nonpotable water systems are
installed the piping must be identified.
 Signage is required at outlets
 Color of piping, letters and letter size is
addressed in this section
 Identification tape is allowed
 Potable water used for cooling equipment can
not be returned to the potable water system

2015 IPC Design, Installation and Inspection Principles 207 2015 IPC Design, Installation and Inspection Principles 208

Copyright 2015 International Code Council 52
2015 IPC Design, Installation and Inspection Principles

Air Gap for a Faucet Air Gap in Piping System

2015 IPC Design, Installation and Inspection Principles 209 2015 IPC Design, Installation and Inspection Principles 210

Section 608.13.2 – Reduced pressure Section 608.13.3 – Backflow preventer


principle backflow prevention assemblies with intermediate atmospheric vent

2015 IPC Design, Installation and Inspection Principles 211 2015 IPC Design, Installation and Inspection Principles 212

Copyright 2015 International Code Council 53
2015 IPC Design, Installation and Inspection Principles

Section 608.13.6 – Atmospheric- Section 608.14.2 – Protection of


type vacuum breakers backflow preventers

2015 IPC Design, Installation and Inspection Principles 213 2015 IPC Design, Installation and Inspection Principles 214

Section 608.14.2 – Protection of Table 608.15.1 -


backflow preventers Minimum Required Air Gaps
Minimum Air Gap
Fixture
Away from a walla (inches) Close to a wall (inches)

Lavatories and other fixtures with effective openings not greater


than 1/2 inch in diameter 1 1½
Sinks, laundry trays, gooseneck back faucets and other fixtures
with effective openings not greater than ¾ inch in diameter 1.5 2.5
Over-rim bath fillers and other fixtures with effective openings not
greater than 1 inch in diameter 2 3
Drinking water fountains, single orifice not greater than 7/16 inch
in diameter or multiple orifices with a total area of 0.150 square 1 1½
inch (area of circle 7/16 inch in diameter)

Two times the diameter of the Three times the diameter of


Effective openings greater than 1 inch
effective opening the effective opening

For SI: 1 inch = 25.4 mm


a. Applicable where walls or obstructions are spaced from the nearest inside-edge of the spout opening a
distance greater than three times the diameter of the effective opening for a single wall, or a distance
greater than four times the diameter of the effective opening for two intersecting walls.

2015 IPC Design, Installation and Inspection Principles 215 2015 IPC Design, Installation and Inspection Principles 216

Copyright 2015 International Code Council 54
2015 IPC Design, Installation and Inspection Principles

Example 1 Example 2
Example 1 Example 2 Intersecting Wall Intersecting Wall
Cross Section of Supply Outlet Cross Section of Supply Outlet

9”
8”

2”
2”
7” 2”
6” 2”
9”
8”

Air gap = 4 inches


Air gap = 6 inches Air gap = 4 inches
Air gap = 6 inches

For SI: 1 inch = 25.4 mm For SI: 1 inch = 25.4 mm

6018.15.1(3) 6018.15.1(4)
Air Gap: Located Near Single Wall Air Gaps: Located Near Intersecting Wall

2015 IPC Design, Installation and Inspection Principles 217 2015 IPC Design, Installation and Inspection Principles 218

Section 608.15.4.1 – Deck-mounted Section 608.15.4.2 – Hose


and integral vacuum breakers connections
 Lavatory and kitchen
sink faucets with the  These devices consist
primary outlet attached of two check valves
to a flexible hose must with an atmospheric
be protected by an vent located between
integral vacuum the check valves.
breaker or be provided
with a dedicated
vacuum breaker.

2015 IPC Design, Installation and Inspection Principles 219 2015 IPC Design, Installation and Inspection Principles 220

Copyright 2015 International Code Council 55
2015 IPC Design, Installation and Inspection Principles

Section 608.16.1 – Beverage Section 608.16.3 – Heat


dispensers exchangers

2015 IPC Design, Installation and Inspection Principles 221 2015 IPC Design, Installation and Inspection Principles 222

Section 608.16.4 – Connections to


Section automatic fire sprinkler systems and
608.16.4 – standpipe systems
Connections to
automatic fire
sprinkler
systems and
standpipe
systems

2015 IPC Design, Installation and Inspection Principles 223 2015 IPC Design, Installation and Inspection Principles 224

Copyright 2015 International Code Council 56
2015 IPC Design, Installation and Inspection Principles

Section 608.16.5 – Connections


Section 609.2 – Water service
to lawn irrigation systems

2015 IPC Design, Installation and Inspection Principles 225 2015 IPC Design, Installation and Inspection Principles 226

Section 701 - Sanitary Drainage

Soil
Stack

Waste stack
Horizontal Branch
Drain
Stack
Branch Interval

Chapter 7
Building Drain
Building Sewer

Sanitary Drainage Gate Valve


Check valve

Building Subdrain

227 2015 IPC Design, Installation and Inspection Principles 228

Copyright 2015 International Code Council 57
2015 IPC Design, Installation and Inspection Principles

Branch Interval Review


SOIL OR WASTE STACK
10’- 0” S TORY HEIG HT (TYP.) FLOOR

THIS IS A BRANCH
INTERVAL

8’- 0” OR MORE
7’-0”

FLOOR
THIS IS
NOT A
BRANCH
INTERVAL

2015 IPC Design, Installation and Inspection Principles 229 230

Common Building Sewer Location


within an Approved Public Sewer
Easement LOT LINES

BUILDING BUILDING
A B

BUILDING BUILDING
SEWER
DEDICATED
SEWER
PUBLIC SEWER
EASEMENT

BUILDING BUILDING
C D

BUILDING BUILDING
SEWER SEWER

PUBLIC SEWER

2015 IPC Design, Installation and Inspection Principles 231 2015 IPC Design, Installation and Inspection Principles 232

Copyright 2015 International Code Council 58
2015 IPC Design, Installation and Inspection Principles

Building on Same Lot Section 701.4 - Sewage


Example 2 Treatment
 Sewage or other waste from a plumbing system
LOT that is deleterious to surface or subsurface
LINE
PUBLIC
SEWER BUILDING BUILDING
waters shall not be discharged into the ground
A B
or into any waterway unless it has first been
rendered innocuous through subjection to an
BUILDING A
SEWER
BUILDING B
SEWER
approved form of treatment.

PRIVATELY CONTROLLED
COMMON SEWER PERMITTED

2015 IPC Design, Installation and Inspection Principles 233 2015 IPC Design, Installation and Inspection Principles 234

Section 701.9 – Drainage Piping


Section 701.7 - Connections
In Food Service Areas
 No direct connection of a steam exhaust, blow-  Exposed soil or waste piping shall not be
off or drip pipe to the building drain. installed above any working, storage or eating
 Waste water discharge shall not be higher than surfaces in food service establishments.
140°F (60°C).
 When higher temperatures exist, approved
cooling methods shall be provided.

2015 IPC Design, Installation and Inspection Principles 235 2015 IPC Design, Installation and Inspection Principles 236

Copyright 2015 International Code Council 59
2015 IPC Design, Installation and Inspection Principles

Above- Underground
Drainage &
ground
Vent Pipe
Drainage &
 The materials listed
2015 IPC
Table 702.1 Vent Pipe 2015 IPC
Table 702.2 in this table are for
Page 57 Page 58 underground use
 Table 702.1 within a building.
identifies the The materials not
materials that are allowed
approved and the underground that
were allowed above
standards with
ground in Table
which these 702.1 are the
materials must following:
comply.

2015 IPC Design, Installation and Inspection Principles 237 2015 IPC Design, Installation and Inspection Principles 238

Building 702.5 Temperature rating


Sewer Pipe
 Where wastewater is more than 140°, the
2015 IPC
Table 702.3  Table 702.3 drainage piping material shall be rated for the
Page 58
identifies the higher temperature.
materials that  If the drainage system piping is properly chosen
are permitted for the high temperatures that will be
and the encountered, the need for cooling is eliminated.
standards with
which these
materials must
comply.

2015 IPC Design, Installation and Inspection Principles 239 2015 IPC Design, Installation and Inspection Principles 240

Copyright 2015 International Code Council 60
2015 IPC Design, Installation and Inspection Principles

703.6 combined sanitary and Section 704.1 - Slope of


storm public sewer Horizontal Drainage Piping
 The storm water and the sanitary sewer from the  Horizontal drainage piping shall be installed in
2015 IPC
building must enter the public sewer Table 704.1
uniform alignment at uniform slopes. The
Page 59 minimum slope of a horizontal drainage pipe
independently when the public sewer conveys
shall be in accordance with Table 704.1.
both storm water and sewage.

2015 IPC Design, Installation and Inspection Principles 241 2015 IPC Design, Installation and Inspection Principles 242

Section 704.3 - Connections to


Horizontal Branch Connections
offsets and bases of stacks

2015 IPC Design, Installation and Inspection Principles 243 2015 IPC Design, Installation and Inspection Principles 244

Copyright 2015 International Code Council 61
2015 IPC Design, Installation and Inspection Principles

Section 706.3 - Installation


Back-to-Back Fixtures
of fittings
2015 IPC
Table 706.3
Page 62

DOUBLE SANITARY
TEE PERMITTED WHERE DEVELOPED LENGTH
Figure 706.3(5) BETWEEN OUTLET OF WATER CLOSET AND
CONNECTION IS 18 INCHES OR GREATER

2015 IPC Design, Installation and Inspection Principles 245 2015 IPC Design, Installation and Inspection Principles 246

706.4 Heel- 706.4 Heel- or Side-Inlet Quarter


or Side-Inlet Bends
Quarter
Bends

2015 IPC Design, Installation and Inspection Principles 247 2015 IPC Design, Installation and Inspection Principles 248

Copyright 2015 International Code Council 62
2015 IPC Design, Installation and Inspection Principles

706.4 Heel- or Side-Inlet Quarter Section 708.1.1 -


Bends Cleanouts for Horizontal Drains

2015 IPC Design, Installation and Inspection Principles 249 2015 IPC Design, Installation and Inspection Principles 250

Section 708.1.3 - Cleanouts at Section 708.1.4 - Change of


Sewer Junction Direction

2015 IPC Design, Installation and Inspection Principles 251 2015 IPC Design, Installation and Inspection Principles 252

Copyright 2015 International Code Council 63
2015 IPC Design, Installation and Inspection Principles

Table 709.1 - Drainage Fixture


Section 708.1.9 - Clearances Units For Fixtures and Groups
2015 IPC
Table 709.1
Page 65

2015 IPC Design, Installation and Inspection Principles 253 2015 IPC Design, Installation and Inspection Principles 254

Table 709.1 - Drainage Fixture Units


For Fixtures and Groups (cont.)
Table 709.2

2015 IPC
Table 709.2
Page 64

2015 IPC Design, Installation and Inspection Principles 255 2015 IPC Design, Installation and Inspection Principles 256

Copyright 2015 International Code Council 64
2015 IPC Design, Installation and Inspection Principles

Table 710.1(2) – Horizontal Table 710.1(1) Building Drains and


Fixture Branch and Stacksª Sewers
Diameter of Pipe Maximum Number of Drainage Fixture Units Connected To Any Portion of The
Maximum Number of Drainage Fixture Units (dfu) (Inches)
Building Drain or the Building Sewer, Including Branches of The Building Drain
Stacks (b)
Slope per foot
2015 IPC
Table Total for Stack Total for Stack 1/16 inch 1/8 inch ¼ inch ½ inch
Diameter of Total Discharge Three Greater Than
710.1(2) Pipe Total For Horizontal into One Branch Branch Intervals Three Branch 1 1/4 ___ ___ 1 1
Page 66 (Inches) Branch Interval or Less Intervals 1 1/2 ___ ___ 3 3
1-1/2 3 2 4 8 2 ___ ___ 21 26
2 6 6 10 24 2 1/2 ___ ___ 24 31
2-1/2 12 9 20 42 3 ___ 36 42 50
3 20 20 48 72 4 ___ 180 216 250
4 160 90 240 500 5 ___ 380 DFU 390 480 575
5 360 200 540 1,100 6 ___ 700 840 1,000
6 620 350 960 1,900 8 1,400 1,600 1,920 2,300
8 1,400 600 2,200 3,600 10 2,500 2,900 3,500 4,200
10 2,500 1,000 3,800 5,600 12 3, 900 4,600 5.600 6,700
12 3,900 1,500 6,000 8,400 15 7,000 8,300 10,000 12,000
15 7,000 Note C Note C Note C

2015 IPC Design, Installation and Inspection Principles 257 2015 IPC Design, Installation and Inspection Principles 258

Sizing Example:
Stack Sizing 710.1(2)
Branch Interval 710.1(2)
STACK
FLOOR

THE TOTAL D.F.U. OF HORIZONTAL


BRANCHES A, B & C CANNOT
EXCEED THE TOTAL LISTED IN THE
6’ THIRD COLUMN OF TABLE 710.1(2)
BRANCH
INTERVAL = 8’
FLOOR

2015 IPC Design, Installation and Inspection Principles 259 2015 IPC Design, Installation and Inspection Principles 260

Copyright 2015 International Code Council 65
2015 IPC Design, Installation and Inspection Principles

Sizing of Stack Greater Than Sizing of Stack Three Branch


Three Branch Intervals 710.1(2) Intervals or Less 710.1(2)

2015 IPC Design, Installation and Inspection Principles 261 2015 IPC Design, Installation and Inspection Principles 262

Offsets in Drainage Piping Offsets in Drainage Piping


(Buildings of 5 Stories or More) (Buildings of 5 Stories or More)
UPPER STACK HAS
5 OR MORE UPPER STACK HAS 5 OR MORE
BRANCH BRANCH INTERVALS
INTERVALS
SIZED AS A VERTICAL STACK
VERTICAL OFFSET SIZED AS PER 713.1(2)
A VERTICAL STACK PER
HORIZONTAL HORIZONTAL OFFSET SIZED AS A
TABLE 710.1(2)
BRANCH BUILDING DRAIN PER 710.1(1)
CONNECTIONS
PROHIBITED
UNLESS RELIEF HORIZONTAL BRANCH
VENT IS INSTALLED CONNECTIONS NOT SIZED AS A VERTICAL
OR OFFSET SIZED PERMITTED STACK FOR ALL DFU IN
AS BUILDING DRAIN THE STACK, BUT NOT
LESS THAN THE SIZE
OF OFFSET

VERTICAL STACK OFFSET HORIZONTAL STACK OFFSET

2015 IPC Design, Installation and Inspection Principles 263 2015 IPC Design, Installation and Inspection Principles 264

Copyright 2015 International Code Council 66
2015 IPC Design, Installation and Inspection Principles

Section 711.1.1 - Omission of


Sewer Ejector Installation
vents for horizontal stack offsets
 Horizontal branches can now connect at any point in
a stack above or below a horizontal offset. Horizontal
branches can connect to a horizontal offset provided
that the connection point is 10 stack diameters
downstream of the upper stack.

2015 IPC Design, Installation and Inspection Principles 265 2015 IPC Design, Installation and Inspection Principles 266

Section 712.3.5 - Pump connection


Section 715.1 - Sewage backflow
to the drainage system
 Pumps connected to the drainage system can now  This section changed to require a backwater
connect to a building sewer, building drain, soil stack, valve where the floor elevation of the plumbing
waste stack or horizontal branch drain.
fixtures is at or below the level for the next
 For a connection near the base of a stack, the
upstream manhole cover.
distance has been reduced from 10 feet (3048 mm) to
10 stack diameters.

2015 IPC Design, Installation and Inspection Principles 267 2015 IPC Design, Installation and Inspection Principles 268

Copyright 2015 International Code Council 67
2015 IPC Design, Installation and Inspection Principles

Section 715 – Backwater Valves Section 715.1 - Sewage backflow

2015 IPC Design, Installation and Inspection Principles 269 2015 IPC Design, Installation and Inspection Principles 270

717 Pipe bursting existing


716 Vacuum Drainage Systems
sewers
 Drain fixtures by vacuum
 Installed per the manufacturer’s installation
instructions
 Fixtures are accorded the same DFU, as the
chapter specifies, counted where they discharge
from the vacuum system
 A vacuum test is required to demonstrate a tight
system

2015 IPC Design, Installation and Inspection Principles 271 2015 IPC Design, Installation and Inspection Principles 272

Copyright 2015 International Code Council 68
2015 IPC Design, Installation and Inspection Principles

Vents – Chapter Nine


 Venting protects the trap seal by reducing
differential pressures within the drainage
system.
 Only plumbing systems with traps require vents,
example: rainwater systems
Chapter 9

Vents

273 2015 IPC Design, Installation and Inspection Principles 274

Distance from Trap to Vent Separation of Vent Terminal


10' MINIMUM

10' MINIMUM

2' MINIMUM
2' MINIMUM
AIR INTAKE

VENT ROOFTOP UNIT WITH


OUTDOOR AIR INTAKE
10' MINIMUM

2015 IPC Design, Installation and Inspection Principles 275 2015 IPC Design, Installation and Inspection Principles 276

Copyright 2015 International Code Council 69
2015 IPC Design, Installation and Inspection Principles

Section 903.4 - Prohibited use of


Frost closure
vent terminals
 Increase to 3” min.
 Vent terminals are prohibited from being used
 Must be increased
for any purpose other than venting.
one foot below the
thermal envelope  Condensate drains included.

2015 IPC Design, Installation and Inspection Principles 277 2015 IPC Design, Installation and Inspection Principles 278

Section 903.5 - Location of vent Section 903.6 – Extension


terminal through the wall
 The vertical distance increased from 2 feet to 3
feet (610 mm to 914 mm) to coordinate with
similar requirements for IMC vent terminal
requirements.

2015 IPC Design, Installation and Inspection Principles 279 2015 IPC Design, Installation and Inspection Principles 280

Copyright 2015 International Code Council 70
2015 IPC Design, Installation and Inspection Principles

Vent Terminal Stack Vent

2015 IPC Design, Installation and Inspection Principles 281 2015 IPC Design, Installation and Inspection Principles 282

Vent Stack 903.2 Grade of Vents


VENT STACK SIZED
PER TABLE 916.1
• TOTAL DFU
• SIZE OF DRAIN STACK
• LENGTH OF VENT STACK

N
E
V
IO
-S
R
P
T
L T
E
Z
.K
6
1
9
B
U
L
IC
A
R
D
S
N
V
F
O
H
G A
K
C

IF
R
O

IM
R
B
O
N A

I
U
B
R
D A
G
D
P
s
X
0
1
IN
L E
P U
M
K
C
A
S
T
N
E
V

T
E
M
IA
D E
R M
Y
G
A
D
F
R
P
S
IH
W
T
E
N
O
C

FIVE OR MORE
BRANCH
INTERVALS

BUILDING
DRAIN VENT STACK MUST CONNECT
10 Xs PIPE WITHIN THIS PORTION OF
DIAMETER DRAINAGE SYSTEM

2015 IPC Design, Installation and Inspection Principles 283 2015 IPC Design, Installation and Inspection Principles 284

Copyright 2015 International Code Council 71
2015 IPC Design, Installation and Inspection Principles

Vent Connections Vertical


Rise of
Vent

2015 IPC Design, Installation and Inspection Principles 285 2015 IPC Design, Installation and Inspection Principles 286

Improperly
Connected Properly
Vent Connected
Serving Vent
a Drain Serving a
Drain

2015 IPC Design, Installation and Inspection Principles 287 2015 IPC Design, Installation and Inspection Principles 288

Copyright 2015 International Code Council 72
2015 IPC Design, Installation and Inspection Principles

Vent Sizing
Horizontal
Offset of
Branch
Vent

2015 IPC Design, Installation and Inspection Principles 289 2015 IPC Design, Installation and Inspection Principles 290

Section 907 —
Vent Sizing
Vents for Stack Offsets

1 1/2" MAIN VENT

N OTE: AL L VENT S SHOWN


LESS TH AN 40'-0 " IN
D EVELOPED LENGT H. BUILDING DRAIN

2015 IPC Design, Installation and Inspection Principles 291 2015 IPC Design, Installation and Inspection Principles 292

Copyright 2015 International Code Council 73
2015 IPC Design, Installation and Inspection Principles

Section 908 - Relief Vent Section 909.1 – Distance of Trap


Connection from Vent

2015 IPC Design, Installation and Inspection Principles 293 2015 IPC Design, Installation and Inspection Principles 294

Violation: Shower Drain Does Not


Distance from Vent to Trap Connect Independently to Wet Valve

2015 IPC Design, Installation and Inspection Principles 295 2015 IPC Design, Installation and Inspection Principles 296

Copyright 2015 International Code Council 74
2015 IPC Design, Installation and Inspection Principles

Section 909.2 – Maximum Fall of


Fixture Drain Between Trap and Vent
Vent Connection

2015 IPC Design, Installation and Inspection Principles 297 2015 IPC Design, Installation and Inspection Principles 298

Individual Fixture as Dry Vent for Dry Vent for Vertical Wet Vent of
Horizontal Wet Vent Two Bathroom Groups

2015 IPC Design, Installation and Inspection Principles 299 2015 IPC Design, Installation and Inspection Principles 300

Copyright 2015 International Code Council 75
2015 IPC Design, Installation and Inspection Principles

Crown Vent Individual Vents

2015 IPC Design, Installation and Inspection Principles 301 2015 IPC Design, Installation and Inspection Principles 302

Improperly Installed Common Vents with Fixture


Individual Vents Drains Connecting at Same Level
1 1/4" 1 1/4"
1 1/4"
1 1/2"
LAV 1 1/4" BT SH
BT KS
2"

DOUBLE BT 2" CO
LAV CO 2"
SANITARY CO KS CO
TEE 2"
1 1/2" 2"
1 1/2" DOUBLE WYE

SANITARY TEE 1 1/4"


LAV 1 1/4" WITH SIDE INLET
1 1/2" 2"
SH
CO WC
WC 1 1/2"

DOUBLE CO
SANITARY BT WC
TEE LAV SH
2"
1 1/2" 2"
3"
3" DOUBLE WYE

2015 IPC Design, Installation and Inspection Principles 303 2015 IPC Design, Installation and Inspection Principles 304

Copyright 2015 International Code Council 76
2015 IPC Design, Installation and Inspection Principles

Common Vents with Fixture Drains


Single Bathroom Group Wet Vent
Connecting at Different Level
MINIMUM DFUs
ITEM SIZE TABLE 709.1
LAV FIXTURE DRAIN 1¼” 1
SH FIXTURE DRAIN 2” 2
WC FIXTURE DRAIN 3” 3
A-Ba 1½”a 1
B-Ca 2”a 2
C-Da 3”a 6
A-X 1½” N/A

a = from Table 909.3


N/A = Not Applicable

2015 IPC Design, Installation and Inspection Principles 305 2015 IPC Design, Installation and Inspection Principles 306

Double Bathroom Group


Section 913 - Waste Stack Vent
(Private) Wet Vent
DRAIN MINIMUM DFUs
COMPONENT SIZE TABLE 709.1
LAV DRAIN 1¼” 1
BT DRAIN 1½” 2
WC DRAIN 3” 3
A-Ba 2”a 2
B-Ca 2”a 2
C-Da 2½”a 6
D-Ea 3”a 9
A-X 1½” N/A
a = from Table 909.3
N/A = Not Applicable

2015 IPC Design, Installation and Inspection Principles 307 2015 IPC Design, Installation and Inspection Principles 308

Copyright 2015 International Code Council 77
2015 IPC Design, Installation and Inspection Principles

Section 911 Circuit Venting (Back-To-


Back Water Closets Circuit Vented) Sizing A Circuit Vent System
A maximum of eight
fixtures are permitted to
be circuit vented The vent shall connect
between the two most
4 upper stream fixture
drains
3

7
6
Each fixture drain shall
connect horizontally to
5 the horizontal branch
being circuit vented

2015 IPC Design, Installation and Inspection Principles 309 2015 IPC Design, Installation and Inspection Principles 310

Sizing a Circuit Vent System Multiple Circuit Venting


Each separate circuit-vented horizontal
branch that is interconnected shall be sized
independently in accordance with Section
911.3.

The downstream circuit-vented


horizontal branch shall be sized
for the total discharge into the
branch, including the upstream
branches and the fixtures within
the branch.

2015 IPC Design, Installation and Inspection Principles 311 2015 IPC Design, Installation and Inspection Principles 312

Copyright 2015 International Code Council 78
2015 IPC Design, Installation and Inspection Principles

Multiple Circuit Venting In Parallel

Circuit Vent with Relief Vent Connection


The relief vent shall connect to the horizontal branch drain between the stack and the most downstream
fixture drain of the circuit vent.
Each separate circuit-vented horizontal
branch that is interconnected shall be sized
independently in accordance with Section
911.3.

Entire length of vent section is uniformly sized A relief vent shall be provided for circuit vented horizontal branches receiving the discharge of four or
based on total d.f.u. load on branch. more water closets and connecting to a drainage stack that receives the discharge of soil or waste from
upper horizontal branches.

2015 IPC Design, Installation and Inspection Principles 313 2015 IPC Design, Installation and Inspection Principles 314

Circuit-vented Branch with Section 915 – Combination


Additional Fixture Connections Waste and Vent System
FIXTURE DRAIN ISLAND SINK

COMBINATION DRAIN
AND VENT (OVERSIZED
DRAIN)
FIXTURE DRAIN FOR SINK - 1 1/2"
COMBINATION DRAIN AND VENT - 2"

FIXTURE DRAIN 1 1/4"


WITHIN DISTANCE 1 1/2"
FROM TRAP TO LAV
VENT SINK
SINK
2"

1 1/2" 2" 2"


FD
3"
(2 1/2" PERMITTED) 2"
FD
COMBINATION DRAIN
AND VENT
EXTENSION OF
BUILDING DRAIN

2015 IPC Design, Installation and Inspection Principles 315 2015 IPC Design, Installation and Inspection Principles 316

Copyright 2015 International Code Council 79
2015 IPC Design, Installation and Inspection Principles

Section 915 – Vertical Fixture Drain


Section 915 – Combination
Component in Combination Waste and
Vent System Waste and Vent System
 In a combination waste and vent system, the
drain also serves as the vent for the fixture.
 The system is commonly used when floor drains
are installed.
 It is also practical to use in laboratories
equipped with island sinks.

2015 IPC Design, Installation and Inspection Principles 317 2015 IPC Design, Installation and Inspection Principles 318

Section 915 – Combination Section 915 – Combination


Waste and Vent Waste and Vent

2015 IPC Design, Installation and Inspection Principles 319 2015 IPC Design, Installation and Inspection Principles 320

Copyright 2015 International Code Council 80
2015 IPC Design, Installation and Inspection Principles

Section 915.2.4 – Combination


Section 916 – Island Fixture Vent
Waste and Vent

2015 IPC Design, Installation and Inspection Principles 321 2015 IPC Design, Installation and Inspection Principles 322

Section 917 Module 3


 Single Stack Vent System
 Single-stack venting was added to 1. All water supply pipe installed underground and
the code. outside of the structure shall have a working
 This type of venting is similar to the pressure rating of not less than 160 psi.
Philadelphia-stack drainage system
that has been used in the
Philadelphia, PA area for more than True False
a century.

2015 IPC Design, Installation and Inspection Principles 323 2015 IPC Design, Installation and Inspection Principles 324

Copyright 2015 International Code Council 81
2015 IPC Design, Installation and Inspection Principles

Module 3 Module 3

2. A sanitary tee may be used for a horizontal-to- 3. What is the minimum size of a building drain
horizontal change in direction. with a total of 36 dfu connected thereto with a
3 inches
1/8-inch slope? _________________________
True False

2015 IPC Design, Installation and Inspection Principles 325 2015 IPC Design, Installation and Inspection Principles 326

Module 3 Module 3

4. A waste stack must not receive the discharge of 5. Polyethylene of raised temperature plastic may
water closets and urinals
______________________. flared
be joined by ____________ or mechanical
joints.

2015 IPC Design, Installation and Inspection Principles 327 2015 IPC Design, Installation and Inspection Principles 328

Copyright 2015 International Code Council 82
2015 IPC Design, Installation and Inspection Principles

Module 3 Module 3

labeled
6. Bundles of PEX must be _____________ to 7. The water heater thermostat may be used to
indicate direction of flow. temper the water at the shower.

True False

2015 IPC Design, Installation and Inspection Principles 329 2015 IPC Design, Installation and Inspection Principles 330

Module 3 Module 3

8. What code regulates the installation of solar 9. On a single stack vent system, if there were
heating systems? three water closets on the stack, the minimum
IMC
________________ size of the stack would be
_________________
4 inches diameter.

2015 IPC Design, Installation and Inspection Principles 331 2015 IPC Design, Installation and Inspection Principles 332

Copyright 2015 International Code Council 83
2015 IPC Design, Installation and Inspection Principles

Module 3

10. A plumbing system utilizing air admittance


valves does not need to have a vent to the
outdoors.

True False Module 4


Storm Drains, Special Piping and
Storage Systems and Gray Water
Recycling Systems
2015 IPC Design, Installation and Inspection Principles 333 334

Section 1105.1
 Roof drains are to be installed in accordance
with the manufacturer’s installation instructions
and that roofing membrane materials must not
block the opening of the drain.

Chapter 11

Storm Drainage

335 2015 IPC Design, Installation and Inspection Principles 336

Copyright 2015 International Code Council 84
2015 IPC Design, Installation and Inspection Principles

Section 1105.2 Size of storm drain piping


 The flow rate of the specific roof drain must be Based on:
provided by the manufacturer  The size of the roof and contributing areas
 This rate determines the storm drain piping that  The rainfall rate per hour for the specific area
can be connected to it  Slope of horizontal piping connected to the drain
 Flow rate is determined at specific head  The flow rate or the specific roof drain at the
elevations above the inlet established head over the inlet
 More head - greater flow rate  The GPM of the roof is plugged into Table
1106.2 to determined vertical and horizontal
piping diameters

2015 IPC Design, Installation and Inspection Principles 337 2015 IPC Design, Installation and Inspection Principles 338

How to calculate GPM for the roof Sizing the drain and piping
 A = roof and contributory area ( vertical walls  Determine the GPM of the roof
and parapets) leading to the drain  Pick a roof drain with a flow rate equal to or
 .623 gal.= 1 inch of water over 1 square foot greater than the GPM of the roof
 HR= rain delivered by 100 year event in inches  Determine if horizontal piping is present and the
per hour as determined by this chapter or slope of that piping
appendix B  Use the table to determine the diameter of the
A X { (HR X .623) divided by 60 minutes} = storm piping, the pipe rated GPM must be at
GPM load on roof drain and piping least as great as the roof drain

2015 IPC Design, Installation and Inspection Principles 339 2015 IPC Design, Installation and Inspection Principles 340

Copyright 2015 International Code Council 85
2015 IPC Design, Installation and Inspection Principles

What’s in the section


Medical Gases—Section 1202
 This section refers to NFPA 99 for medical gas
systems, inhalation anesthetic systems and
vacuum piping systems.
Oxygen Systems—Section 1203
Chapter 12  This section refers to NFPA 55 and NFPA 51 for
nonmedical oxygen system requirements.
Special Piping and Storage
Systems
341 342

Section 1301.1 through 1303.11


 Gray water, nonpotable rainwater and reclaimed
water systems requirements such as:
 Water quality
 Materials
 Storage
 Permit
Chapter 13
 Connection
 Disinfection and treatment
Nonpotable Water Systems  Water testing
 Manuals for operation and maintenance

343 2015 IPC Design, Installation and Inspection Principles 344

Copyright 2015 International Code Council 86
2015 IPC Design, Installation and Inspection Principles

Gray Water Recycling System for Section 1302 – Systems for Flushing
Flushing Water Closets and Urinals Water Closets and Urinals

 This section is about the specific details for on-


site nonpotable water reuse systems. Refer to
the definition of “On-site nonpotable water reuse
system” in Chapter 2.

2015 IPC Design, Installation and Inspection Principles 345 2015 IPC Design, Installation and Inspection Principles 346

Section 1303 – Subsurface


Module 4
Landscape Irrigation
Design based on:
 Amount of nonpotable water available daily 1. A vertical leader with a diameter of 3 inches in
an area with a rainfall rate of 2 inches (51 mm)
 The percolation rate of the specific soil
per hour is capable of draining a projected roof
Installation covers: area of 2,930 square feet (272 m2).
 Trench width, depth and spacing
 Aggregate and backfill True False
 Distribution piping

2015 IPC Design, Installation and Inspection Principles 347 2015 IPC Design, Installation and Inspection Principles 348

Copyright 2015 International Code Council 87
2015 IPC Design, Installation and Inspection Principles

Module 4 Module 4

2. A 40 by 80 foot (102 by 203 mm) roof is 3. The water from a nonpotable water system used
attached to a building on the 80 foot side of the to flush a urinal will be blue or green
wall which rises another 30 feet (762 mm) above
the lower roof. The adjusted area (leaving out True False
other parapets) for the roof would now
4,400 (409)
be_______________ square feet (m2).

2015 IPC Design, Installation and Inspection Principles 349 2015 IPC Design, Installation and Inspection Principles 350

Module 4
International Code Council is a Registered Provider with The American
Institute of Architects Continuing Education Systems. Credit earned on
4. A nonpotable water system could be used for an completion of this program will be reported to CES Records for AIA
members. Certificates of Completion for non-AIA members are available on
irrigation system that includes sprinklers. request.

This program is registered with the AIA/CES for continuing professional


True False education. As such, it does not include content that may be deemed or
construed to be an approval or endorsement by the AIA of any material of
construction or any method or manner of handling, using, distributing, or
dealing in any material or product. Questions related to specific materials,
methods, and services will be addressed at the conclusion of this
presentation.

2015 IPC Design, Installation and Inspection Principles 351 352

Copyright 2015 International Code Council 88
2015 IPC Design, Installation and Inspection Principles

Copyright Materials Thank you for participating

To schedule a seminar, contact:


This presentation is protected by US and International
Copyright laws. Reproduction, distribution, display and use of
the presentation without written permission of the speaker is
prohibited. The ICC Training & Education
Department
© International Code Council 2016 1-888-ICC-SAFE (422-7233) Ext.
33818
or
E-mail: icctraining@iccsafe.org

353 2015 IPC Design, Installation and Inspection Principles 354

Hyperlinked Slides
Table 608.1 Application of
Backflow Preventers
Beyond This Point

2015 IPC Design, Installation and Inspection Principles 355 2015 IPC Design, Installation and Inspection Principles 356

Copyright 2015 International Code Council 89
2015 IPC Design, Installation and Inspection Principles

Table 608.1 Application of Table 608.8.3 Size of Pipe


Backflow Preventers (cont) Identification
Pipe Diameter Length Background Size of Letters
(inches) Color Field (inches) (inches)

¾ to 1 1/4 8 0.5

1 ½ to 2 8 0.75

2 ½ to 6 12 1.25

8 to 10 24 2.5

Over 10 32 3.5

Back
2015 IPC Design, Installation and Inspection Principles 357 2015 IPC Design, Installation and Inspection Principles 358

Table 906.1(1-1/4” thru 5”only) Table 916.(1 1-1/4” thru 5”only)

Return Return
2015 IPC Design, Installation and Inspection Principles 359 2015 IPC Design, Installation and Inspection Principles 360

Copyright 2015 International Code Council 90
2015 IPC Design, Installation and Inspection Principles

Table 909.3 Table 909.3


Table 909.3 Wet Vent Size Table 909.3 Wet Vent Size

Wet Vent Pipe Size Drainage Fixture Unit Load (dfu) Wet Vent Pipe Size Drainage Fixture Unit Load (dfu)
(inches) (inches)

1-1/2 1 1-1/2 1

2 4 2 4

2-1/2 6 2-1/2 6

3 12 3 12

2015 IPC Design, Installation and Inspection Principles 361 2015 IPC Design, Installation and Inspection Principles 362

Table 910.4 Waste Stack Vent Size


Stack Size Maximum Number of Drainage Fixture Units
(inches) (dfu)
Total Discharge into One Total Discharge for stack
Branch Interval
1-1/2 1 2

2 2 4

2-1/2 No limit 8

3 No limit 24

4 No limit 50

5 No limit 75

6 No limit 100

2015 IPC Design, Installation and Inspection Principles 363

Copyright 2015 International Code Council 91

S-ar putea să vă placă și