Radical Innovation:
• New Technology
• Digital technology, New equipment, Robotics
• New Systems
• Artificial Intelligence, Industrial Internet of Things
• Modern Data Architecture, Data Driven Management
What about Radical Innovation of the World of
Management?
100
6
www.tocpractice.com 42 TOCPA International Conference
Results over 20 Years
Monthly Production Tons ‘000/month
15
12 16 12 13 13 12
IN 14 15 16 14 10 13 12 13 OUT
11 12 14 15
16
10
10 10 10 10 10 10
IN 10 10 10 10 10 10 10 10 OUT
10 10 10 10
10
12
Performance
10
Time
11
www.tocpractice.com 42 TOCPA International Conference
Combined Effect of
Variation and Interdependence
10 10 10 10 10 10
12
Performance
10
Time
12
www.tocpractice.com 42 TOCPA International Conference
Daily Production Output:
Operations
Production Output: Units/Day
Budget Actual
120
100
80
60
40
20
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
14
www.tocpractice.com 42 TOCPA International Conference
Shovel / Dump Crusher
Source Loader Truck & Screen Product
100t/h & 80% 100t/h & 80% 100t/h & 80%
availability availability availability
Resource
Shovel Down Truck Down Crusher Down Availability
2 Hours 2 Hours 2 Hours 80% EACH
100 (8 out of
10 hours)
Performance
Total
1 Hour 1 Hour 1 Hour 1 Hour
= 100t = 100t = 100t = 100t
Output
= 400t
0
0 1 2 3 4 5 6 7 8 9 10
Time
15
www.tocpractice.com 42 TOCPA International Conference
Relating the Example to
Narrow Reef Mining
100 100 100
Potential
80 80
80 Statistical 80%
Actual
60
44
40
40
23
20 18.4
10
0
Example Crew Advance (%)Crew Advance (m)
16
www.tocpractice.com 42 TOCPA International Conference
Balanced Capacity
10
10 10 10 10 10 10
IN 10 10 10 10 10 10 10 10 OUT
10 10 10 10
10
Mineral
resource 15 16 14 10 13 12 Product
18
www.tocpractice.com 42 TOCPA International Conference
On the Constraint
10
Running Time?
Implication of Standing Time?
Maintenance?
Operator availability and skill?
Quality control?
Product value?
19
www.tocpractice.com 42 TOCPA International Conference
Subordination to Flow
? ? ? 10 ? ?
10
Protective Protective
Capacity
10 Capacity
(Flexibility) (Flexibility)
20
www.tocpractice.com 42 TOCPA International Conference
? ? ? 10 ? ?
12
10
Performance
Time
21
www.tocpractice.com 42 TOCPA International Conference
Radically Different
Shovel /
Loader
100t/h & 80%
availability
Mine A
Drill &
Shovel Truck Crusher Screen Process
Blast
Mine B
Load & Bench Drill &
Shovel Truck Crusher
Haul Prep Blast
23
www.tocpractice.com 42 TOCPA International Conference
The Radically NEW
15
13
12 16 12 13 12
IN 16 16 15 14 10 13 12 13 OUT
11 12 14 15
16
IN 10 10 10 10 10 10 10 10 OUT IN 16 16 15 14 10 13 12 13 OUT
10 10 10 10 11 14 15
10 12
16
25
www.tocpractice.com 42 TOCPA International Conference
Two totally different worlds !!!
Mineral
resource 10 10 10 10 10 10 Product
A B C D E F
Protective Capacity
26
www.tocpractice.com 42 TOCPA International Conference
Optimised Flow in a Mine
A B C D E F
Protective Capacity
F E D C B A
Protective Capacity
27
www.tocpractice.com 42 TOCPA International Conference
DBR in a Platinum Mine
Drilled Staked
Waste Charge Ore
Blocks & Blast Blocks
Blasted Stake
Waste Prepared
Drill
Blocks 3-5
7-10 Exposed Days Drill
3-5
Days 7-10 Ore
Drill Days
Days Drilled
Prepare 10-14 Ore
Load
Drill Pad ORE Days Blocks
WASTE & Haul
Staked CYCLE
3-5 CYCLE
Waste 10-14
Days Cleaned
Blocks 2-5 Cleaned Days Ore 3-5
Days Waste Days Charge
Blocks 14-21
Blocks & Blast
2-5 Days
Stake
Days
Load
Prepare & Haul
Drill Pad
Blasted
Prepared Ore
Drill 2 000 000t Other Plant
Blocks Finger Stockpiles Feed
Stockpile
29
www.tocpractice.com 42 TOCPA International Conference
Why do so many Mining Companies struggle?
“Efficiencies, Costs, Utilisation, Availability …. “If you want to make money, ...
These measurements tell you NOTHING about
MOST of your resources MUST be IDLE from time to
the overall performance of the business”
– Dr Eli Goldratt
time”
– Dr Eli Goldratt
“The closer you are to a balanced “If a company tells me they experience moving
capacity chain, the closer you are to bottlenecks, my response is:
bankruptcy” You have NO bottlenecks and most of your resources
have at least 30% spare capacity”
– Dr Eli Goldratt
– Dr Eli Goldratt
www.tocpractice.com 42 TOCPA International Conference
How do we handle Complex
Corporate Environments?
15 15
12 16 13 12 12 16 13 12
17 17
IN 11 15 16 14 10 13 12 9 OUT IN 11 15 16 14 10 13 12 9 OUT
11 18 11 20 11 18 11 20
19 19
15 15 15
12 16 13 12 12 16 13 12
12 16 13 12
17 17 17
11 11 20 11 18 11 20 11 18 11 20
18
19 19 19
15 15
12 16 13 12 12 16 13 12
17 17
IN 11 15 16 14 10 13 12 9 OUT IN 11 15 16 14 10 13 12 9 OUT
11 11 20 11 18 11 20
18
19 19
15
12 16 12 13 13 12
IN 14 15 16 14 10 13 12 13 OUT
11 12 14 15
16
10
10 10 10 10 10 10
IN 10 10 10 10 10 10 10 10 OUT
10 10 10 10
10
10
10 10 10 10 10 10
IN 10 10 10 10 10 10 10 10 OUT
10 10 10 10
10
10 10 10 10 10 10 A Significant
Switch in the
IN 10 10 10 10 10 10 10 10 OUT way we do
Business!!!
10 10
10 10
10
15
13
12 16 13 12
12
IN 16 16 15 14 10 13 12 13 OUT
11 14 15
12
16
15
13
12 16 13 12
12
IN 16 16 15 14 10 13 12 13 OUT
11 14 15
12
16
- 50 - 20 -2 1 50 100 150
Supporting implementation during the 100-day Helping leaders lock
Mobilisation & Direction setting
journey in the gains
Weekly Bi-weekly
Team meetings Sponsor-team leaders feedback
Results dashboards Sponsor check-in
Leaders check-in
What If:
• We can give people an experience of a new reality
of their own environment
• The same configuration with different management
philosophies
• Different Measures, Focus, Decisions, Outcomes
• Create a Safe playing field - No risk of real numbers
• Challenging impact that will enable new behaviours