Sunteți pe pagina 1din 13

CONTINUOUS FLOW FOR STRUCTURAL

DESIGN IN PREFABRICATED CONCRETE


STRUCTURES
Iamara Rossi Bulhões1 and Flavio Augusto Picchi2

ABSTRACT
In industrial building, the assembly process is often carried out in large batches, i.e. a
large number of structural elements (columns and beams) are assembled before
placing slabs and roof parts, increasing the amount of work in progress. One of the
factors that contribute for that is the large size of design batches. Often the first
elements to be designed are the ones that have more repetition. This paper discusses
the implementation of the principle of continuous flow on the structural design of
prefabricated industrial buildings, emphasizing the reduction of design batch size. An
action research empirical study was carried out in a large prefabricated concrete
structure manufacturer from the State of São Paulo, Brazil. This study was divided
into three stages: (a) an overall analysis of the design activities; (b) a detailed analysis
of the design process of one project; and (c) preliminary results of the implementation
of design, prefabrication and assembly continuous flow in a construction project. The
implementation process is based on core Lean Thinking concepts and principles. The
expected results are the reduction of total (design, prefabrication and assembly) cycle
time, increase in productivity, work in progress reduction, and improved process
stability.

KEY WORDS
lean thinking, continuous flow, small batch, design process,

process small batches, increasing both


INTRODUCTION flexibility and efficiency.
Several companies from the In the manufacturing industry the
manufacturing industry have adopted production of unitary items in a
Lean Thinking concepts, principles production line can be regarded as a
and tools (Womack e Jones, 1996), reasonable way of production (cars,
developed from the Toyota Production pens, mobile phones, etc). However,
System (TPS), for improving the the implementation of continuous flow
performance of their plants regarding in manufacturing is not something
the elimination of waste, including trivial and also involves the
production inventory. One of the key introduction of major changes in
elements in this system is to work in production management, including
continuous flow, by introducing plant layout, and also behavioral

1
Ph.D. candidate, Faculty of Civil Engineering, Architecture and Urbanism, University of Campinas
(UNICAMP), Group of Building Management and Technology, iamara@fec.unicamp.br
2
Director, Lean Institute Brazil, Rua Topázio 911, São Paulo-SP, Brazil, CEP 04105-063, Tel.: +55 11
5571-6887, Fax: +55 11 5571-0804, fpicchi@lean.org.br

169
Continuous Flow for Structural Design in Prefabricated Concrete Structures

Iamara Rossi Bulhões, Flavio Augusto Picchi

changes in the people involved, from the point of view of the client (Koskela
line workers to company’s senior and Huovila, 1997). Therefore, the
management (Liker, 1996). time spent in transferring information,
Transferring the concept of the waiting for the development of
continuous flow to the construction subsequent process steps, inspections
industry is a major challenge. It is and other non value-adding activities
necessary to understand core Lean should be considered as waste and be
Thinking ideas at an abstract level and eliminated whenever it is possible
adapt them so that they can be (Koskela and Huovila, 1997).
applicable in the construction context This article discusses the
(Lilrank, 1995). preliminary results of a research
Previous IGLC papers from the project that involves the adaptation and
same authors (Bulhões et al., 2005; application of Lean Thinking concepts
and Bulhões et al., 2006) proposed and tools for both modeling the design
adaptations of the principle of process and supporting the
continuous flow in construction sites. implementation of continuous flow in
In the first study, tools proposed by the design of prefabricated concrete
Rother e Shook (1999) were used to structures. Two empirical studies
model and design flows in a fairly carried out in a company that produces
conventional building project. In the and assembles concrete structures are
second one, the results of the presented. In the first study an analysis
implementation of continuous flow in of the current situation was
the assembly of reinforced concrete undertaken, while in the second one
prefabricated structure were described, several changes have been introduced
emphasizing the strategies adopted to in the design process.
reduce the assembly batch size. A
major limitation in the implementation CONTINUOUS FLOW IN DESIGN
of continuous flow in the later was the The concept of continuous flow
lack of integration between design and presented by Rother and Shook (2002)
production management, since there assumes that each process produces
was a overlap between those two only what is required by the following
processes. The design in this type of processes or the final client, without
project is often produced in large creating inventory. In this context, the
batches, and the parts that have more production system needs to be flexible
repetition are usually designed first. enough in order to change (speed and
Considering the flow view of product type) according to the client
production, a process is generally demand.
regarded as a flow of materials and Reis (2004) suggests that a major
information from raw materials to the difference of implementing continuous
final product (Koskela, 2000). Based flow in manufacturing processes and
on this concept, both design and administrative processes is the fact that
production processes can be managed in the former there is not client pulling
by using the same principles. It means a piece. Therefore, it is necessary to
that the design process can be understand upstream and downstream
improved by reducing waste (non processes well so that the service is
value-adding activities), reducing performed and its results are available
duration, and increasing the value from at the right time, not before, nor after.

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


170
Continuous Flow for Structural Design in Prefabricated Concrete Structures

Iamara Rossi Bulhões, Flavio Augusto Picchi

One of the key aspects of design proposed a set of guidelines for


management is the reduction of lead adapting VSM to administrative
time, which is the time required for a processes:
product to move along all process
• The value stream for
stages, from beginning to start (Rother
administrative processes is an
and Shook, 2002). In design, the lead
information flow, that should be
time is the time needed to produce
defined from the left to the right;
information, make decisions and
produce design solutions, from the • Each activity should be
identification of client requirements to represented by a block,
the delivery of the complete design separating activities carried out
(architectural, structural, building by different people or in
services, etc.). different moments;
This study adopted the model for
• Each block should contain the
implementing continuous flow
following information: activity
proposed by Rother and Shook (2000)
name; number of people
and Rother and Harris (2002) as a
involved; brief description of
starting point. This model adopts value
how it is performed, as well as
stream mapping (VSM) as the first
materials and tools used; time for
step for developing improvements.
effectively carrying the activity
VSM represents graphically all steps
(AD), and time that it stays at
involved in material and information
each workplace (W);
flows from order reception to delivery.
Generally, two maps are prepared: (a) • Connections between activities,
current-state map that represents as well as their inputs and
existing value stream and points out outputs should be documented,
process waste, and (b) future-state map describing the type of materials
that proposes improvements in the or information that is produced
value stream, through the and existing loops.
implementation of Lean Thinking According to Reis (2004) W is the time
ideas. The following concepts, among that the information takes, from the
others, are useful to understand VSM end of the previous activity to the end
(LEI, 2003; Rother and Shook, 2000; of the current one, being indicated at
Rother and Harris, 2002): (a) the cycle the VSM blocks and at the time scale.
time (C/T) measures how often a part It indicates the period of time that the
is completed by a process; and (b) the information is waiting, queuing, or
takt time (TT) is the rate of demand by being transported, without adding any
the customer. value. The process lead time is
According to Shook (2003), calculated by the sum of all Ws, and it
devising value stream maps for is indicated in the map time scale. The
administrative processes is very same author describes AD as the total
similar to the way it is done for time spent in work elements that
production processes, both for the effectively transform a unit in the
current-state and future-state maps. process, which is smaller than W. In
The main difference is the difficulty of fact, W includes AD.
information flows. Based on Rother
and Shook (2002), Picchi (2002)

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


171
Continuous Flow for Structural Design in Prefabricated Concrete Structures

Iamara Rossi Bulhões, Flavio Augusto Picchi

RESEARCH METHOD of these studies. In 2005, a new set of


studies started, involving a partnership
Action research was the research
between Munte and the University of
strategy adopted in this investigation.
Campinas (UNICAMP). The initial
Action research is a strategy for
focus was the implementation of
obtaining, at the same time, both
continuous flow in the assembly of
knowledge and change in social
prefabricated structures (see Bulhões
systems. It is a cyclic process,
et al., 2005; and Bulhões et al., 2006).
involving an analysis of the problem,
Due to problems of integration of
planning, action, and an assessment of
design and production (see
the results (Eden and Huxham, 1997).
introduction section), the focus has
This research study was carried out
changed to the implementation of
in two job sites of Munte Construções
continuous flow in the structural
Industrializadas, a construction
design process.
company specialized in prefabrication
The study was divided into three
and assembly of industrialized
stages. In the first stage, an overall
concrete structures. This company was
analysis of the design activities carried
founded in 1975, and currently has two
out by the company and by external
prefabrication plants (F1 and F2)
designers was carried out. In the
located in State of São Paulo, Brazil.
second one, a detailed analysis of the
In 2004 the company had the
design process of one project (named
support of the Lean Institute Brazil in
Project A) was carried out, from the
the implementation of some Lean
demand made by the client for a quote
Thinking principles in one of the
to the final delivery of the project. The
plants of the company. This included
third stage has involved the
training courses on VSM and
implementation of improvements in
continuous flow for the company
another project (Project B), aiming to
production managers. The initial
improve the design information flow.
implementation of those principles
This implementation process is still
resulted in a productivity increase of
going on. The main tool used in this
around 30%. The fact that the
study was VSM for administrative
company had received those training
processes. Table 1 briefly describes the
courses made it easier the development
two projects that were investigated.
Table 1 Brief description of projects A and B

Project A Project B
Job description Extension industrial building , Assembly of a prefabricated concrete
including the following components: structure of a warehouse, including the
columns, beams, slabs, roof tiles and following components: columns,
stairs beams, slabs, roof tiles and stairs
Project duration 22 days 225 days
Building area 2, 842.7 m² 89,846.9 m²
Concrete volume 385.9 m³ 7,759.8 m³
Number of parts 223 6,569
Design duration 68 days 193 days
Design team 1 design manager, 1 designer checking 1 design manager, 1 designer, and 4
company drawing technicians
Design team 1 structural designer, 2 designers and 4 1 structural designer
external drawing technicians

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


172
Continuous Flow for Structural Design in Prefabricated Concrete Structures

Iamara Rossi Bulhões, Flavio Augusto Picchi

between the company and the client.


RESULTS The duration of the project (design,
O VERALL ANALYSIS fabrication and assembly) is a key
information in the process, since it is
In the first meeting with the company the starting point for producing design
internal design team the value stream drawings. Regarding the information
map of the existing design process flow, the production planning and
(Figure 1) was produced, with the aim control process produced all design
of having an overview of this process, schedules. This information is usually
including its main stages, critical steps, based on goals established in the
and participants. Therefore, this map is production long term plans. In the
mostly based on the perception of this lower part of the map, the main design
design team. processes are represented: it starts by
The client is represented in the the initial design coordination meeting
right side of the map, making explicit and finishes at the final design
the production volume, based on the checking.
long term production plan agreed

Production
planning control
(PPC)
Client
Long term plan
Duration:
Foundation
Initial date:
Final date:
2

Decision making Initial defini- Columns Beams Slabs Roof tiles. Checking Fabrication Assembly
Modeling Detailing OSD
meeting tions of OSD
2 2 2 2 n 6
5a6 2 2 2 2
E E E
Overall structural design (OSD) Design individual pieces

Figure 1 Value stream map of the overall project


Figure 1 indicates that the design of The internal design team of the
the prefabricated structure is divided company is usually involved in design
into two stages: overall design of the coordinating meetings and in design
verification (checking). The initial
structure, that involves the definition
of its spatial geometry, and the design design coordination meeting usually
involves: the company design
of individual parts (columns, beams
and slabs). Those stages are normally manager, the designer in charge of
conceiving the overall structure, the
carried out by external structural
designer in charge of calculating loads,
design offices, which hire different
types of professionals: experienced and the sales person. Before delivering
designers that conceive the structure, design drawings to production these
are checked by the internal design
designers that calculate loads on the
team. The design manager is in charge
structure and on the foundations,
designers of individual parts, drawing of managing the whole design process.
technicians, and foundations designers A second version of the map was
(usually from a different company). then produced (Figure 2), in which the
design of the overall structure is kept

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


173
Continuous Flow for Structural Design in Prefabricated Concrete Structures

Iamara Rossi Bulhões, Flavio Augusto Picchi

in one large batch (the whole representatives of an external


building), but the design of individual structural design office for presenting
parts is delivered in small batches, and discussing the new process map,
compatible with the batch sizes and all agreed that it was feasible.
defined for the assembly process. When the external designers were
The research team was not sure asked why they did not usually
whether it was possible from a delivered design drawings in the same
technical point of view to implement sequence of the assembly process, they
small batches in this kind of design stated that they usually start by the
process, and follow the sequence parts that are the easiest to design.
defined by the assembly process. In Two months later another meeting was
October 2006 a meeting was held held with other external designers and
involving the internal design team and the same answer was given.

Production
Assembly plan for planning control
small batches (PPC)
Client
Long term plan
Production
scheduling Duration:
• Classification of project type (A, B and Initial date:
C)
Final date:
• Definition of project batch size
• Definition of project resources (time,
labour, etc) R R
• Meeting between designers and batch: S S
clients for decision making (1, 2, etc) B B
project
C C

Decision making Initial defini- Columns Beams Slabs Roof tiles. Checking Fabrication Assembly
Modeling Detailing OSD
meeting tions of OSD
2 2 2 2 n 6
5a6 2 2 2 2
C/T=10min
T/C = C/T = 15 days C/T = C/T = C/T= 2 a 5h C/T= 1 a 3 h C/T= 1 a 2 h C/T= 1 a 2 h C/T = C/T=
a2h
Batch = Batch = Batch = Batch = Batch = Batch = Batch = Batch = Batch = Batch = Batch =
project project project project Random Random Random Random Random Random Random
Overall structural design (OSD) Design individual pieces
Reduced
Foundation Batch

Figure 2 Future value stream map of the overall project after the reduction of batch sizes

At that stage, some other • Define duration of the design


improvements in the design process stage and the design team
were proposed: involved according to the type of
project;
• Create a classification of projects
by type according to size, • Involve designers in the
complexity, location, definition of design batch sizes;
accessibility, etc. Currently, in
• If necessary, hold other design
general the same design lead
coordinating meetings in order to
time is established for any kind
improve the exchange of
of project. For instance, the
information and decision
duration of the overall structural
making.
design is assumed to be ten days.

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


174
Continuous Flow for Structural Design in Prefabricated Concrete Structures

Iamara Rossi Bulhões, Flavio Augusto Picchi

DETAILED ANALYSIS Once the new job was confirmed,


the period named dependent
In this stage, a new value stream map
information cycle started. Then most
was produced, containing more details
activities are managed internally in the
in comparison to the first one. This
company (including hired external
map was based on information that
designers). Therefore, this agreement
was collected in a project from
should be the starting point for the
beginning (first contact by the client
internal process, although sometimes a
organization) to the end (delivery of
formal contract is not signed. In
the project). Part of the data for
Project 1 there was a delay of 6 days
producing this map was collected by
between the agreement date and the
the external design team. Despite this
communication of the job from the
map is concerned with the whole
sales person to the design team,
project, the focus of this study is the
although the delivery time had started
design process (0).
in the former date. The initial design
The design process started in the
coordinating meeting should be
4th of August 2006, when the client
arranged as soon as possible after the
asked the company a cost estimate for
communication of the job. In Project 1
Project 1. The agreement was reached
it took 5 days to hold this meeting,
only on the 22nd of January 2007, due
which was when the external design
to the long period that was spent in
team started working in the project.
negotiation (94 days). This period was
named independent information cycle,
since there is much interference from
the client and the company has little
control over decision making.

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


175
Continuous Flow for Structural Design in Prefabricated Concrete Structures

Iamara Rossi Bulhões, Flavio Augusto Picchi

Pre-design of
pieces
Designer

Communicate Communication
6d of new job
Direct Sales Visit to Cost Proposal Purchase
consultation definition client estimation meeting confirmatio Sales
Y n
Sales assistant Sales Sales Cost Sales and Client ID: 31/01
Director estimating client
ID: 04/08/06 ID: 10/8 N ID: 22/01
ID: 07/08 ID: 11/08 ID: 14/09
AD: 75 min FD: 13/09
Producing Contract
TRA: 45 min contract signing
Sales Client
3 x LT: 94 days ID: 31/01
ID: 02/02
FD: 01/02
IIC: Independent information cycle DIC: Dependent information cycle

Structural load Calculation Foundation


Production calculation design
planning
Designer Structural Designer
Planning designer
engineer ID: 01/03 ID: 01/03
ID: 07/02
ID: 02/02 FD: 09/02 FD: 20/04 FD: 19/03
FD: 30/04 AD: 60 h AD: 40 h
DA: 4 h
AD: 3 h LT: 36d LT: 13d
LT: 3 h

Design OSD – Analysis OSD – Analysis Approval Final OSD


meeting Review 1 of OSD1 Review 2 of OSD 2 of OSD 2
Client, designer Designer Client Designer Client Client Designer
manager,
structural ID: 07/02 ID: 13/02
designers and FD: 13/02 FD: 21/02 ID: 21/02 ID: 23/02 ID: 01/03 ID: 01/03
5d sales person FD: 23/02 FD: 01/03 FD: 05/03
AD: 24 h
ID: 07/02 AD: 10h AD: 14 h AD: 10h AD: 5 h AD: 8 h
LT: 5d
LT: 5d LT: 3d LT: 6d LT: 1 d LT: 2d
AD: 3 h LT: 17 Days
LT: 3 h
Designer manager: exchange
information

DIC: Dependent information cycle

Calculation

DIP Design rework

Designer Designer
individual parts
ID: 03/04 ID: 2/5
2 FD: 2/5
4d FD:26/04
AD: 111 h AD: 4h
LT: 16d LT: 1d
Contracting Meeting for
design of design Design
individual parts integration
(DIP) checking
Design manager, Company
Design manager designer, design team
structural ID: 10/4
ID: 21/03 designer and DIP FD:26/4 2
4d
ID: 27/03 AD:50 h
AD: 2 h
LT: 13 d
AD: 3 h Fabrication Repair pieces

DIC: Dependent information Team of Team of produce


produce pieces pieces
cycle ID: 05/04 58
FD: 30/04
AD: 9040 h
LT: 13 d Assembly Repair pieces

Assembly team Assembly team


ID: 23/04
FD: 12/05 6
AD: 186 h
LT: 13 d

Figure 3 Current value stream map of the Project A


manager and the designer responsible
The expected duration of the overall
design of the structure was 10 days, for the overall structural design was
made by electronic mail.
but it took 17 days. The design
manager was in charge of the The calculation of loads started at
the end of the overall design and lasted
communication between external
until the beginning of the design of
designers and the client. The
individual pieces.
communication between the design

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


176
Continuous Flow for Structural Design in Prefabricated Concrete Structures

Iamara Rossi Bulhões, Flavio Augusto Picchi

After the development of the some pieces have been produced and
overall structural design, it took 19 others have been already been
days to start the design of individual assembled. This problem resulted in
parts, although it could have started re-work in both the prefabrication
immediately. In general, a single plant and in the construction site.
structural design office is hired to 0 presents the current value stream
develop the whole structural design, map of the design process for Project
including overall design, calculation of A. It indicates that the design lead time
loads and design of individual pieces. is 69 days and the value adding time
However, in this project, three only 24 days, resulting in a waiting
different structural designers were time of 30 days, from which the
hired to do each one of the design process was totally stopped for 11
stages, with the aim of reducing the days. It means that non-adding value
design lead time. This change time corresponded to 65% of the lead
demanded a new set of activities, such time. The value adding time for
as coordination meetings. Also, it took parallel activities was calculated
11 days to hire the designer in charge considering the longest average
of the design of individual parts. activity duration per day. The lead
Besides this delay, the division of time for individual process was
design work was the main cause of a calculated from the initial date and the
mistake in the design of a number of finish date.
parts, which was only discovered after
OSD Calculation of loads on structure

Designer Designer
ID:07/02 DI: 01/03
FD: 23/02 DF: 20/04
AD:38 h AD: 60 h
LT: 11d LT: 36

Communication Design Final Contraction Meeting for


Ei DIP design DIP
of new job meeting OSD
Designer integration
6d 5d Client, design manager 11d Designer 4d Designer of
Sales Designer manager Design manager, 4d
manager, ID: 07/02 designer, IP
ID: 31/01 structural FD: 01/03 ID: 01/03 ID: 21/03 structural ID: 03/04
designers, FD: 05/03 designer and DIP FD: 26/04
AD: 10 min sales person AD: 10 h AD: 2 h AD: 111 h
LT: 15d AD: 8 h DI: 27/03
ID: 07/02 LT: 2d LT: 16d
AD: 3 h Design
AD: 3 h
checking
Analysis Approval
of OSD of OSD 2 Company
design team
Client Client DI 10/04
ID: 13/2 FD: 26/04
FD: 01/03 ID: 1/03 AD: 50 h
AD: 11 h LT: 13d LT= 69d
LT: 12d AD: 5 h
Waiting = 30d
6d 5d 0 0 11 d 4d 4d VAT = 193 h
10 min
3h 42 h 10 h 25h 9h 116 h = 24 d

Figure 4 Current value stream map of the design process for Project A
In this type of commercial of industrial 0 presents a proposal for the future
state value stream map for the design
project the assembly lead time and the
process. The main changes introduced
delivery time is relatively short, and
concurrency between activities is in the process are presented bellow:
necessary. By contrast, 0 and 0 • Reduce the batch size for the
indicate that the design decision cycles design of individual parts and
tend to be relatively long. design verification, based on the
assembly batch size and

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


177
Continuous Flow for Structural Design in Prefabricated Concrete Structures

Iamara Rossi Bulhões, Flavio Augusto Picchi

sequence. The designer of drawings delivery. Since


individual parts sends production designers work in small batches,
drawings to the company via a they deliver drawings in a
project extranet. There is a preestablished periods (e.g. once
person in charge of receiving a week, twice a week, etc.),
those drawing, who prints and which makes it much easier to do
delivers them to the design such control. In fact, by reducing
verification team – this activity small batches this activity could
is named control of production be eliminated in the future;
Calculation of loads on structure

Structural
designer

Calculate loads on
structure

Design OSD Approval Final OSD Meeting for defining


design and assembly DIP
meeting meeting
flows
Client, design Designer Client, design Designer Designer of IP
manager, manager and Design manager,
S designers, site manager, Produce design of
structural designers Produce final
designer and Produce OSD planning engineer and individual parts
OSD client
sales person Approve OSD N
Meeting for Meeting for defining
discussing design and assembly
design detailing flows, considering
reduction of batch sizes Design checking

Company design
team
Check design

Pull system with small batches

Figure 5 Future state value stream map for the design process

• Reduce or eliminate waiting • Define criteria for assessing the


time, since the causes of those level of project complexity,
delays could be easily which could be considered in the
eliminated; preparation of proposals and cost
estimates, and also bids and also
• Improve the management of
when hiring designers. Currently
concurrent processes, including
there is a standard duration for
prefabrication, design of
the production of overall design,
individual parts, and assembly.
without considering the
This requires the formalization
differences between projects.
of information, managing
The criteria initially defined in
commitments. For that reason
the meetings by designers,
some meetings were included in
design manager and the research
map with the aim of improving
team were: duration (speed),
design management;
degree of uncertainty, size, level
• Reduce the duration decision of standardized parts, level of
cycles also by including repetitiveness (number of
meetings for expediting decision parts/number different types of
making. The design manager is pieces), project type (warehouse,
expected to have a much more multi-story buildings, or
active role in this process, supermarkets).
instead of being only an
information manager.

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


178
Continuous Flow for Structural Design in Prefabricated Concrete Structures

Iamara Rossi Bulhões, Flavio Augusto Picchi

IMPROVEMENTS IN PROJECT B the building. In fact, the assembly of


Based on the actions suggested in the the mezzanine was expected to start on
the 3rd of March, but by the 22nd of
previous section, a set of
improvements were implemented in February the staircase had not been
defined yet.
Project B. This project is still going on
and the design is expected to finish in By contrast, the warehouse has a
much larger area, but the number of
July 2008. It will be delivered in two
repetitive parts is much higher, making
stages.
it easier to design individual parts.
The priority in terms of delivery is
However the production of parts for
the mezzanine, which is part of project
stage one, since most of building building the warehouse takes a longer
time due to the large number of parts.
works are concentrated in this area.
However, this is the most complex part 0 provides an overview of the design
batches and the estimated delivery
of the design, since it contains a larger
dates.
number of parts, and the client tends to
interfere more, compared to the rest of

Figure 6 Design batches

site), planning (prefabrication plant),


Initially, the definition of design
and design.
batches was based only on the
Eight design batches have been
assembly sequence, which is defined
defined for the project. Despite the fact
in agreement with the client. However,
that the assembly process starts by the
in this type of project it is important
mezzanine (production batches PB1 to
also to consider the combined capacity
PB4), due to the large volume of parts
of the prefabrication plant and the
assembly equipment available. For that to be prefabricated for the production
batches PB7, PB6 and PB5, the design
reason, in the implementation process,
for the latter had to be produced
the definition of design batches
before.
involved representatives from three
different departments of the company: Currently, the planned sequence of
production management (construction design batches has not been followed
completely, due to some delays of

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


179
Continuous Flow for Structural Design in Prefabricated Concrete Structures

Iamara Rossi Bulhões, Flavio Augusto Picchi

client decisions. As a result, there is an large number of different professionals


overlapping between PB2 and PB3: the involved, including external designers,
beams of the former had not been and frequent changes demanded by the
finished, but the production of the client.
columns of the later had already VSM was very useful for
started. Despite this problem, by mid understanding and representing the
January 2008 the assembly schedule design process, playing a key role in
and the batch sizes have not suffered the proposal for improvements towards
major changes getting continuous flow in design. The
Another important change reduction of design batch sizes was
introduced in the design process was successful, although the concept of
the adoption of design batches, instead batch size in production is slightly
of the design of individual parts, as the different, since is strongly based in
unit for paying external designers and standardized work. In the design
also controlling design delivery. process, the batch size should be more
flexible, allowing changes demanded
CONCLUSIONS by the client to be considered.
This paper presented the initial results Moreover, design batches are pulled
of the implementation of continuous by both prefabrication and assembly
flow on the structural design of system, rather than only by the second
prefabricated industrial buildings, one. This is because the timing for
emphasizing the reduction of design producing some parts define a design
batch size. Although this research sequence that is not necessarily the
project is still going on, there are same sequence of on-site assembly.
indications that the principle of The results of this study are
continuous flow adopted in the promising, indicating that the proposed
production and assembly of analysis steps and tools are effective
prefabricated structure can be extended for identifying waste and support the
to the design process, despite the implementation of continuous flow in
complexity of this process, due to the the design of prefabricated structures.
to Research of the State of Bahia) for
ACKNOWLEDGEMENTS the financial support and Munte
The authors would like to thank Construções Industrializada for being a
FAPESB (Foundation for the Support partner in this research project.

REFERENCES
Bulhoes, I. R.; Picchi, F.; Folch, A. T. Actions to implement continuous flow in the
assembly of pre-fabricated concrete structure. In: 13th Annual Conference of the
International Group for Lean Construction, 2006, Santiago. IGLC, Santiago, Chile,
2006.
Bulhoes, I. R.; Picchi, F. A.; Granja, A. D. Achieving continuous flow in construction: an
exploratory case study. In: 13th Annual Conference of the International Group for
Lean Construction, 2005, Sidney. IGLC, Sidney, Australia, 2005.
Koskela, L. An exploration towards a production theory and its application to
construction. Espoo, Finlândia: VTT, 2000. (VTT Publications, 408).

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


180
Continuous Flow for Structural Design in Prefabricated Concrete Structures

Iamara Rossi Bulhões, Flavio Augusto Picchi

Koskela, L.; Huovila, P. On foundations of concurrent engineering. In: Concurrent


Engineering in Construction. London: The Institution of Structural Engineers, 1997.
Picchi, F. Lean in administration. In: Lean Summit 2002, Gramado, Brazil, 17-19 Nov.
Presentations... Lean Institute Brazil, 2002. (in Portuguese)
Reis, T. dos. Aplicação da Mentalidade Enxuta no fluxo de negócios da construção civil
a partir do mapeamento do fluxo de valor (Application of Lean Thinking to the
business flow in construction from value stream mapping). Campinas, São Paulo,
2004. 125 p. M.Sc. Dissertation – Faculty of Civil Engineering, Architeture and
Urbanism, State University of Campinas (UNICAMP).
Rother, M.; Shook, J. Learning to See: Value stream mapping to create value and
eliminate muda. The Lean Enterprise Inst., Brookline, Mass, 1998.
Santos, A. Application of flow principles in the production management of construction
sites, 1999, Thesis (Ph.D.), School of Construction and Property Management, The
University of Salford.
Shook, J. Helpful Hints on Mapping off the plant floor in Support or Administrative
Operations. Disponível em:
<http://www.lean.org/Community/Registered/Article.cfm? Articled=3>. Acesso em:
17 março 2003.
Womack, J. P.; Jones D. T. Lean Thinking: Banish waste and create wealth in your
corporation, Simon & Schuster, New York, 1996.

Proceedings for the 16th Annual Conference of the International Group for Lean Construction

Production System Design


181

S-ar putea să vă placă și