*WEEKLY PROGRESS REPORT*

NH Division Sambalpur.
NH-153(B) EPC Project.
Date of Report:
Name of the work -Widening & Strengthening of two lane to two lane with paved shoulder from km 58/000 to km 116/1
153(B) on EPC mode in the state of Odisha. ( Naktideul to Boudh)
Name of Division :-Sambalpur

Sanction Amount :- Rs. 160.98 Cr

Contract Amount:- Rs. 117.82 Cr.

Name of Agency:- M/S SRIDURGA CONDEV(P) LIMITED, Jagatpur, Cuttack

Date of commencement:- 04.04.2018.

Stipulated date of Completion: 03.04.2020.

Authority Engineer:- PIDCL in Associate with Subudhi Associates

Effective Date of AE :- 07-05-2018

Project Progress For 1st Week of September 2019 ( From 27.08.2019 to 02.09.2019 )
(A) Physical Progress on Road Works in Length :
Scope of Work Balance Work In
S.No. Section Details of Work UOM Remarks
Work completed Work Progress
1 Earthwork Upto Sub-Grade Km 52.533 42.100 10.433 0.100

2 Sub-Base Course - GSB Km 52.533 42.050 10.483 0.100


Non- Bituminous Base Course
3 Widening and Km 51.171 41.920 9.251 0.100
(WMM)
Strengthening of
4 Existing road Bituminous Base Course (DBM) Km 51.171 40.600 10.571 0.000

5 Waering Coat (BC) Km 51.171 35.447 15.724 0.000

6 Rigid Pavement ( DLC+PQC) Km 1.362 0.000 1.362 0.000 Work In Progre

7 Earthwork Upto Sub-Grade Km 2.833 0.280 2.553 0.000

8 Sub-Base Course - GSB Km 2.833 0.280 2.553 0.000


Reconstruction /
New Non- Bituminous Base Course
9 Km 2.833 0.280 2.553 0.000
Alignment / (WMM)
Bypass
10 Bituminous Base Course (DBM) Km 2.833 0.280 2.553 0.000

11 Waering Coat (BC) Km 2.833 0.280 2.553 0.000

(B) Physical Progress of Structural Work :


Scope of Work Balance Work In
S.No. Section Details of Structural Works UOM Yet to Start
Work completed Work Progress
1 HP Culverts Nos 15 15 0 0 0
Widening of
2 Box Culverts Nos 20 20 0 0 0
Culverts
3 Slab Culverts Nos 28 28 0 0 0

4 HP Culverts Nos 11 10 1 0 1
New
5 Construction of Box Culverts Nos 1 0 1 0 1
Culverts
New
Construction of
Culverts
6 Slab Culverts Nos 1 0 1 0 1

New
7 Construction of Minor Bridges Nos 8 0 8 1 7
Culverts

Repair &
8 Major Bridges - Mahanadi River Nos 2 0 2 0 2
Rehabilitation
(C) Physical Progress of Other Misc. Work :
Scope of Work Balance Work In
S.No. Section Details of Other Misc. Works UOM Yet to Start
Work completed Work Progress
1 Toll Plaza location @ Nos 1 0 1 0 1

2 Other Works Road Side Drains Rmt. 6860 2900 3960 0 3960
Road Signs, Marking, Km stones &
3 kms 58.100 0 58.100 0 58.100
Safety devices & etc.
4 Bus Bays / Passenger Shelters Nos 13 0 13 0 13

5 Truck Lay byes Nos 2 0 2 0 2


Project Facilities
6 Junction Development Nos 82 0 82 0 82

7 Water Harvesting Structures Nos 116 0 116 0 116


Metal Beam (W-Beam) Crash
8 Rmt. 21482 0 21482 0 21482
Barrier
9 Guard Post Nos 1235 0 1235 0 1235
Protection
10 Works Retaining Wall / Breast Wall Rmt. 5891 2520 3371 100 3271

11 Toe Wall Rmt. 5303 4600 703 0 703

( D) Financial Progress
Milestone
% of Contract Achieved as on
Mile Stone Milestone Date Amount in Achieved In Crs.
Price (Target) Milestone date
Crs

11.90 Cr.of work


Project Milestone-I Milestone achieved
( 150 Days )
01-09-2018 10% 11.782 excuted.Overall
by 30-09-2018
progess 10.10%

Project Milestone-II Milestone achieved Amount of work done


28-02-2019 30% 35.346
( 330 Days ) by 19.03.2019 RS.35.60cr / 30.21%

Project Milestone-III In Progress(Grace Amount of work done


28-07-2019 60% 70.692
( 480 Days ) Period) RS.55.23 cr / 46.87%

Project Completion
03-04-2020 100% 117.820
date (730 Days)

NOTE:-MS-III Traget slipped.


PROGRESS REPORT*
vision Sambalpur.
3(B) EPC Project.
Date of Report: 03.09.2019
e to two lane with paved shoulder from km 58/000 to km 116/100 of NH
Boudh)

gatpur, Cuttack

es

eptember 2019 ( From 27.08.2019 to 02.09.2019 )

Remarks

Work In Progress.

Remarks
MNB work in Progress
( 3 span slab casted out
of 3 at Ch.68/722)
Remarks

Remarks
NH Division Sambalpur
Naktideul to Boudh of NH-153 (B)
General Information
Name of the work -Widening & Strengthening of two lane to two lane
Name of the Work - with paved shoulder from km 58/000 to km 116/100 of NH 153(B) on E
mode in the state of Odisha. ( Naktideul to Boudh)
Sanction Amount - Rs. 160.98 Cr
Tender Awarded for - Rs. 117.82 Cr.
Name of Agency - Sri Durga Condev(P) Ltd
Appointed Date - 04.04.2018
Construction Period - 24 Months
Stipulated date of Completion - 03.04.2020
M/s - Planning and Infrastructureral Development Consultants Limited
Authority Engineer - association with Subudhi Associates
Effective Date of AE - 07.05.2018
Report on Progress of Pre construction activity till 1st Week of September, 2019 ( From 27.08.2019 to 02.09.2019 )

1.a Total Area Required in Ha - Not started

1.b Project length affected in Km - Nil

Land
1.c Land handed Over to EPC Contractor - 92.22% as per agreement.
Acquisition

1.d Date of Handing over of Site - 04-04-2018


1.e Balance Land to be handover if any - In Process
1.f Likely date of handing over - -
2.a Project length affected in Km - 4.72Km.
2.b Diversion of Date of approval of diversion - -
2.c Forest Land already diverted in Ha - -
2.d Proposal Balance land if any to be handed over - -
2.e Likely Date of handing over - Yet to be final.
3.a Total nos. of trees to be felled - 4198
3.b Tree Cutting Project length affected in Km - 9.230
3.c in non forest Nos. Of trees already been cut - 4072
3.d area Balance to be cut - 126
3.e Likely date of cutting of trees - No Work In progress.
4.a Length of shifting estimate in Km - 15.66 Km.
Date of handing over of estimate to In progress. Estimate is initiated and
4.b -
Shifting of Contr. approval awaited.
4.c electrical Length in Km shifted - -
4.d Utility Balance Length in Km to be shifted - -

4.e Likely date if shifting of balance length - Not yet Final

5.a Length of shifting estimate in Km - 3.5Km.


Date of handing over of estimate to PHED Dept.submitted an estimate to
5.b -
Contr. Authority
Shifting of
5.c PHED Length in Km shifted - -
5.d Utility Balance Length in Km to be shifted - -

5.e Likely date of shifting of balance length - Work In progress

6.a Length of shifting estimate in Km - 2.54 Km.

Shifting of
Date of handing over of estimate to RWSS Dept.submitted an estimate to
6.b -
Contr. Authority
Shifting of
6.c RWSS Length in Km shifted - Not yet Started
6.d Utility Balance Length in Km to be shifted - -

6.e Likely date of shifting of balance length - Work In progress


)

Strengthening of two lane to two lane


000 to km 116/100 of NH 153(B) on EPC
tideul to Boudh)

al Development Consultants Limited in


es

( From 27.08.2019 to 02.09.2019 )


STATUS OF PROJECT UNDER NHIIP PHASE -I as on 15-06-2016 (NH-200)

"Rehabilitation and Upgrading to 2 lanes / 2 lane with Paved Shoulders Configuration and Strengthening
1 Name of the work : of Bhojpur- Chhatabar Section (km 131.0 to km 192.0) of NH-200 in the State of Odisha under Phase-I of
National Highways Inter-connectivity Improvement Projects (NHIIP)"

2 Chainage : 131+000 to 192+000


3 Length : 61 km
4 Sanctioned Cost of Project : Rs. 251.92 cr
Cost of civil works as per sanction
5 : Rs. 218.63 cr
estimate
6 Status of tender : Contract signed on 24-04-2015

7 Civil Contractor : Sri Durga Condev (P) Ltd.- Shree Balaji Engicon (P) Ltd.-Joint Venture (SDCPL-SBEPL-JV)
8 Contract price of civil works Rs. 218.63 cr
Date of commencement of civil
9 26-10-2015
works.
10 Scheduled date of completion 24-10-2017 (730 days)
Supervision Consultant
11 : LEA Associates South Asia Pvt Ltd.
( Authority's Engineer)
Contract price of Supervision
12 : Rs. 7,82,50,000.00
Consultants (AE)
13 Effective date of assignment of AE : 18-06-2015

14 RAP Implementation Consultant Krushi Aadivashi Self Help Society

15 Contract Price of RAP Consultant Rs. 31.87 Lakhs


Mobilisation Advance to EPC
16 Rs. 4,37,26,172 (1st Installment).
contractor:
17 Financial Targets for Mile Stone Amount (in Cr) Cumulative Physical Progress (in Km) Mile stone date

Target Achievement Description of Item Target Achievement Progress


Embankment 17.66 15.57 2.00
Subgrade 17.26 14.96 1.50
GSB 16.86 10.01 2.00
WMM Top layer 12.36 7.49 3.50
1st Mile stone (10 % contract price) DBM 6.2 6.1 3.00 03/23/2016
21.863 26.78 Crs.
(150 days from the Appointed : BC 6.2
(10%) (12.25%)
date ) Box culvert 31 Nos 63 5 ACHIEVED
HP culvert
Minor Bridge 24 (LM) 14 (LM) 81 (LM)
Major Bridge
WHS
Target Achievement Description of Item Target Achievement Progress
Embankment 29.16 24.14 0.50
Subgrade 28.76 23 0.66
GSB 33.01 22.46 0.24
WMM Top layer 30.49 20.9 0.16
2nd Mile stone (30% of contract
65.589 61.43 Crs DBM 22.1 20.5 4.34
price) : 08/20/2016
(30%) (28.10%) BC 6.2 0 3.70
(300 days from the Appointed date)
Box culvert 100 88 11
HP culvert
Minor Bridge (LM) 121(LM) 143.6 (LM) 62.7 (LM)
Major Bridge
3rd Mile stone (60% of contract
price)
: 131.18 03/08/2017
(500 days from the Appointed
date)

Scheduled completion date (100%)


: 218.63 10/24/2017
(730 days from start date)

Deogarh district: Tree cutting of non foresting area estimate have been obtained by the Ministry vide
letter No.RW/NH-12013/26/6/2010 sp(D)/EAP dt.15.03.2016. Due payment has been deposited to the
18 Tree cutting in non forest area :
Forest Department, Odisha. Tree cutting of 2180 Nos. has been completed so far out of 2422 trees.
Sambalpur district: Tree cutting work of non forestry area of Sambalpur District has been completed.

For Deogarh District:


Deogarh: 14.66 Lakhs deposited in CALA account and till date 10.53 Lakhs disbursed and remaing in
progress
Reamal: 78.84 Lakhs deposited in CALA account and till date 75.51 Lakhs disbursed and remaing in
19 Land Aquisition progress.
For Sambalpur District:
Jamankira: 15.94 lakhs deposited in CALA account and till date 13.29 Lakhs disbursed and remaing in
progress.

Stage I clearance: Stage-I clearance approval conveyed by F&E Deptt., Govt of Odisha on dated 12-04-16
20 Forest land diversion :
and for Stage-II, Estimate for NPV, Compensatory afforestation submitted to MoRT&H on dated: 16-06-16
STATUS OF PROJECT UNDER NHIIP PHASE -I as on 15-06-2016 (NH-200)

(i) Electric Pole shifting : Work in Sambalpur District has been completed. Balance work in Deogarh District
recently handed over to EPC Contractor for execution. Route Map of relocation of Electric Poles of Deogarh
21 Shifting of utility :
District was handed over to EPC Contractor during Jan.'2016
(ii) 1.5 Km. of Sec-1 & 6.5 Km. of Sec-II of live water pipe line is yet to be relocated.

Status of valuation of title and non-title holders: Done


Status of valuation of CPRs: Done
Micro Plan status: Will be finalized after receipt of valuation of structure from Independent valuer. Valuation
22 Rehabilitation & Resettlement
of structures is completed as per DPR. RCC meeting not yet decided due to assembly session by DM &
Collector, Deogarh & Sambalpur.
Status of R&R payments: Not done
Physical Activity by the agency at
23 :
site
Construction camp site completed in Sec-I & Sec-II.The submission of camp lay-out Plan complying to
a) Camp Establishment: :
environmental mitigation plan has been done to AE for review.

b) Laboratory set up: : Set up of lab equipments (100% completed) in Section-I & Section-II.

Existing Batching Plant duly established at Konarajro for Section-I & Rengalibeda for Section-II has been
c) Batching Plant: :
intimated by the EPC Contractor to use for this project corridor.

Existing WMM Plant & Batch type HMP Plant duly established at Badabahal for Section-I is under operation
d) WMM Plant & Batch type HMP: :
& WMM Plant at Rengalibeda for Section-II is under operation.

ROW pillars already established as per schedule. Its painting & lettering confirming to IRC provision is still
e) ROW :
to be complied.
f) Road maintenance Work: : The necessary instruction of PIU & AE has been given for its early regular maintenance
g) Sampling of existing Soil: : Sampling of existing soil of 11 km in Sec-I & 20 km in Sec-II have been completed.
h) Diversion Plan: : Temporary Traffic Diversion Plan for the construction of structures has been Approved.
Status of ESMP (Equipment safety
i) : Being complied & Submitted.
Monitoring plan)
j) Bridge Soil Investigation: : Already Completed.
Source Approval of Manufactured
Source of Admixture, Course Aggregate, Fine Aggregate, Water, Steel, Cement, Hume Pipe have been
k) Materials like (cement,steel,Hume :
approved.
pipes etc)
Aggregate resourse/sampling testing
l) : Approved.
i.e. sand,gravels etc
Quarry for Section-I is at Kusumdih & for section-II is at Khindo. Crusher for Section-I is at Kusumdih &
Section-II is at Chhatripita. The existing crusher plant of Sec-I have been assembled with VSI system &
m) Quarry & crusher : 4.75 mm screening facility. The Crusher of Sec-I is under operation. The assembling of VSI system of
existing crusher plant of Sec-II & 4.75 mm screening facility is under progress.

n) Fixing of control points : Completed

o) Classified Traffic volume Count : 7 days Traffic survey already done.

p) Axle load survey : Completed by EPC Contractor and submitted to AE for review.

1)The soft copy of final review report the P & P of balance 30 Km. from Km.142+000 to Km.172+000, 106
Nos. of Box Culverts, 10 Nos. of Minor Bridges, Pavement Design of Sec-I from Km.131+000 to
Km.142+000 has been handed over to the EPC Contractor on 10.04.2016 for formal submission to AE for
Pavement Design, Plan Profile and
q) : final review.
Work Programme:
2) (i) The Design and GAD of Major Bridge, (ii) Working drawing and detail co-ordinates of major and minor
junctions, (iii) Bus lay bye & Truck lay-bye, (iv) Drainage Plan of the entire Project Cooridor, (v) Pavement
design of Sec-I from Km.142+000 to Km.156+447 is yet to be completed and submitted by the EPC

24 Appointment of Proof Consultant : M/S-STUP has been appointed as Proof Consultant

25 Appoinment of Safety Consultant : M/S-STUP has been appointed as Safety Consultant

Appointment of Design Director by


26 : Yogesh V. K. of M/s. Arkitechno Consultant has been appointed as Design Director by the agency .
the agency

27 Mobilisation of machineries : Required machineries mobilized at site.

28 Mobilisation of Man power : Mobilized as per requirement in Sec-II. However, it is inadequate in Sec-I to achieve the month's target.

Status of Project Statutory


Applicable Permits & Renewals 90% of documentation is complied except few. Balance documents are "Applied for" under different Dept.
25 :
according to Schedule-F of Contract for compliance.
Agreement.

The Mobilization of AE has been completed except the Resident Engineer as per direction of Chief Engineer,
NH Division, Odisha. The obligations in respect of reporting & deliveries is being complied in time in
confirmity to consultancy Aggrement. The Assistance & supporting guidance in technical & contractual
29 Activities performed by AE :
matters are being provided always to the Authority in all respect. The site supervision & Monitoring of
Project Progress keeping in mind for the achievement of the Monthly target as well as 2 nd Milestone is also
being expedited by Authority's Engineer.
STATUS OF PROJECT UNDER NHIIP PHASE -I as on

Rehabilitation and upgrading to 2 lan


1 Name of the work : configuration and strengthening of
of NH-217.

2 Chainage : Km 90.0-Km 158.0


3 Length : 68.00 km

4 Sanctioned Cost of Project : Rs.176.16 Cr.

Cost of civil works as per sanction


5 : Rs.135.78 Cr.
estimate

6 Status of tender : LOA issued on 14.02.14

7 Civil Contractor : M/s. GVR Infra Projects Limited

8 Contract price of civil works Rs.135.78 Cr.

9 Date of commencement of civil works. 6/13/2014

10 Scheduled date of completion 6/12/2016

Supervision Consultant M/s. EPTISA Servicios de Ingenieria S.L i


11 :
(Construction Supervision Consultant) Limited

Contract price of Supervision


12 : 72,935,000.0
Consultants (CSC)
13 Effective date of assignment of CSC : Effective date of assigment is 10-04-2014

14 RAP Implementation Consultant Krushi Adivasi Self Helf Society

15 Contract Price of RAP Consultants 3,692,306


Mobilisation Advance to Civil Works
16 Rs 6.65 cr for Moblization Advance
contractor:

17 Physical & Financial Progress


a) Financial Progress

Financial in Crores

Schedule progress during the month


7.98
(Jun'16)
Actual progress during the
5.73
month
Cumulative scheduled
135.78
progress including the month
Actual cumulative progress
44.10
including the month
Linear Progress
a) C & G = 42.64 Km
b) Embankment = 37.08 Km
c) Subgrade = 36.42 Km
d) GSB = 36.22 Km
e) WMM(1st layer) = 34.07 Km
b) Physical Progress f) WMM (Top) = 31.24 Km
g) DBM = 36.31 Km

18 Tree cutting in non forest area : Completed

Stage I clearance obtained from Forest D


22/8/2015.
19 Forest land diversion : Stage II clearance: NPV, Compensato
deposited to concerned deptt and also
DFO, Khariar by PIU Head on 10-06-16

Electical: Work Completed except disma


Water pipe line: Estimate for an am
20 Shifting of utility :
07.12.2012. Works will be laid simultan
road works.

Micro plan for non title holders and CPRs


21 Rehabilitation & Resettlement
1st installment disbursed 50% of PAPs.
22 Status of Drawings

a) CD Works Submitted by
: As per DPR
Contractor

Hume Pipe Culverts 21 18


Slab Culverts 14 8

Box Culverts 41 39
Minor Bridges 6 6
Major Bridge 1 Repair & Rehabilitatio
b) Plan & Profiles Submitted by
Chainage
Contractor

07/00 to 11/00 11/20/2014

00/00 to 07/00
12/19/2014
11/00 to 12/00

132/0 to 133/0
134/0 to 135/0 2/19/2015
137/0 to 141/0

126/0 to 132/0 7/4/2015

133/0 to 134/0
6/25/2015
136/0 to 137/0

90/0 to 109/0 8/18/2015

23 Physical Activity by the agency at site :

a) Camp Establishment: : Camp construction work completed and s

b) Laboratory set up: : Site laboratory is functioning at 139/350

c) Batching Plant: : Concrete batching plant is moblized at sit

d) WMM Plant & Batch type HMP: : WMM Plant & HMP mobilized and functio

43.95 Km Handed over on Commenceme


e) ROW : 14.25 Km Handed over on 12-11-14
7.25 Km Handed over on 21-01-16

f) Road maintenance Work: : Repairs of potholes or other maintenance

g) Sampling of existing Soil: : Under progress


Second submission for culvert/Humepipe
h) Diversion Plan: :
reviewed & approved by CSC
Status of ESMP (Equipment safety
i) : Submitted. Reviewed & approved by CSC
Monitoring plan)
j) Bridge Soil Investigation : Completed

Source Approval of Manufactured


k) Materials like (cement,steel,Hume : Approved
pipes etc)
Aggregate resourse/sampling testing
l) : In Progress & being attended by CSC.
i.e. sand,gravels etc
m) Quarry & crusher : Crusher was installed at Km 145+470 LH

Submitted & approved by CSC. However


n) Work Programme: :
submitted by Contractor

24 Mobilization of Man power : Not yet fully mobilized by the Civil Works
1) The Monthly progress Report upto May
for the period Jan'16-Mar'16 is furnished.
2) The Monthly progress Report for Envir
month of Apr-2015 and quarterly progres
25 Activities performed by CSC :
Jan'16-Mar'16 is furnished.
3) Profile checking of all 68 Km is comple
R NHIIP PHASE -I as on 24-06-16 (NH-217)

bilitation and upgrading to 2 lane/2 lane with paved shoulders


guration and strengthening of Nuapada – Bango Munda section
H-217.

0.0-Km 158.0
km

6.16 Cr.

5.78 Cr.

ssued on 14.02.14

GVR Infra Projects Limited

5.78 Cr.

2014

2016

EPTISA Servicios de Ingenieria S.L in cooperation with Eptisa India Private


ed

ive date of assigment is 10-04-2014

i Adivasi Self Helf Society

65 cr for Moblization Advance

Percentage of Progress

5.88%

4.22%

100.00%

32.48%
r Progress CD Works:
&G = 42.64 Km (i) Box Culverts - 19 Nos
bankment = 37.08 Km completed & 5 no. in progress
bgrade = 36.42 Km (ii) Hume Pipe Culverts - 11 Nos
B = 36.22 Km Completed and 2 no in progress.
MM(1st layer) = 34.07 Km (iii) Slab Culvert 4 nos.
M (Top) = 31.24 Km Completed, 2 no in progress
M = 36.31 Km (iv) Minor Bridge-6 no. in progress

leted

I clearance obtained from Forest Department of Government of Orissa on


2015.
e II clearance: NPV, Compensatory afforestation, Tree cutting amounts
ited to concerned deptt and also compliance for Stage-II submitted to
Khariar by PIU Head on 10-06-16

ical: Work Completed except dismantling of old poles.


r pipe line: Estimate for an amount of Rs.22.96 lakh sanctioned on
.2012. Works will be laid simultaneously during the execution of project
works.

plan for non title holders and CPRs sanctioned by MoTH&H on 08-03-16.
stallment disbursed 50% of PAPs.
Approved
by CSC

18
8

39
6
Repair & Rehabilitation
Approved
by CSC

11/28/2014

12/30/2014

Total 45 kms of Plan and


3/12/2015 profile Approved by CSC

7/7/2015

7/13/2015

8/29/2015

construction work completed and situated at km 139/350 RHS on NH-353

aboratory is functioning at 139/350 RHS on NH-353

ete batching plant is moblized at site

Plant & HMP mobilized and functioning

Km Handed over on Commencement date i.e 13-06-14


Km Handed over on 12-11-14
Km Handed over on 21-01-16

rs of potholes or other maintenance in progress

progress
d submission for culvert/Humepipes submitted by the contractor and
wed & approved by CSC
itted. Reviewed & approved by CSC.

leted

ved

gress & being attended by CSC.

er was installed at Km 145+470 LHS on NH-353

itted & approved by CSC. However revised work programme to be


tted by Contractor

et fully mobilized by the Civil Works Contractor


e Monthly progress Report upto May-2016 and quarterly progress report
e period Jan'16-Mar'16 is furnished.
e Monthly progress Report for Environmental Monitoring Reports for the
h of Apr-2015 and quarterly progress report for the same for period
6-Mar'16 is furnished.
ofile checking of all 68 Km is completed.
STATUS REPORT OF EPC PROEJCTS UNDER IMPLEMENTATIO

Rehabilitation and upgrading to 2-lanes/2-lane with


1 Name of the work : Koksara Section from 25/0 to 80/0 Km. of N.H. 20
dated.27.05.2015.

2 Chainage : From 25/0 to 80/0 Km.

3 Length : 55.276 Km.

4 Sanctioned Cost of Project : Rs.26535.22 Lakhs

5 Cost of civil works as per sanction estimate : Rs 229.41 Crores

6 Status of tender : Agreement drawn on 15.04.2015

7 Civil Contractor : M/s. BACKBONE ENTERPRISES LIMITED

8 Contract price of civil works Rs.229.41 Crores

9 Date of commencement of civil works. 02.11.2015

10 Scheduled date of completion 03.05.2018. (913 days)

Supervision Consultant
11 : M/s Euroestudios S.L(Spain) & Theme Engineering
( Authority's Engineer)

Contract price of Supervision Consultants


12 :-
(AE)

13 Effective date of assignment of AE : 2/8/2016

14 Mobilization Advance to EPC contractor: : 1st Mobilization of Rs4,58,81,300/- & 2nd Mobilization o

15 Financial Targets for Mile Stone Amount (Cr)

Balance to
Target Achievement
Achieved
1st Mile stone (10 % contract price)
24.66
( 200 days from start date i.e. : 22.94
(10.75%)
20.05.2016)

2nd Mile stone (30% of contract price)


(400 days from start date i.e. : 68.82 68.82
06.12.2016)
3rd Mile stone (60% of contract price)
(600 days from start date i.e. : 137.65 137.65
24.06.2017)
Scheduled completion date (100%) -
: 229.41 229.41
03.05.2018 (913 days from start date)

16 Tree cutting in non forest area : Cutting & felling of road side trees has been completed up

Permission granted for Stage-I clearance vide letter No


17 Forest land diversion :
Government F&E Department, Bhubaneswar. NPV & CA de

Electric shifting work completed & estimate for water sup


18 Shifting of utility :
25-05-16
19 Physical Activity by the agency at site :

a) Camp Establishment: : Camp construction work near 47/500 Km.(At Semela) is c

b) Laboratory set up: : The Agency has set up the Laboratory at Semela camp.

c) Batching Plant: : installed and functioning

d) WMM Plant & Batch type HMP: : installed.

e) ROW : 98% ROW handed over on appointed date i.e. 02.11.2015

f) Road maintenance Work: : It is being maintained by Agency.

g) Sampling of existing Soil: : completed

h) Diversion Plan: : In progress.

Status of ESMP (Equipment safety


i) : submitted.
Monitoring plan)

j) Bridge Soil Investigation: : Done by Agency.

Source Approval of Manufactured Materials


k) : Submitted and approved
like (cement,steel,Hume pipes etc)

Aggregate resources/sampling testing i.e.


l) : Completed.
sand,gravels etc

m) Quarry & crusher : lease taken up at 48/500Km. At Ushigoan crusher and pr

n) Fixing of control points : Done

o) Classified Traffic volume Count : Done

p) Axle load survey : Done

Pavement Design, Plan Profile and Work


q) : Submitted for 10 kms and approved and revised work pro
Programme:

20 Appointment of Proof Consultant : Approved

21 Appointment of Safety Consultant : Approved


Appointment of Design Director by the
22 : Approved
agency

23 Mobilization of machineries : Deployed in work site.

24 Mobilization of Man power : Deployed

25 Activities performed by AE : Authority Engineer is appointed and performing their du


NDER IMPLEMENTATION BY NH WING Dated. 18.06.2016

ding to 2-lanes/2-lane with paved shoulders configuration strengthening of Nabarangpur-


/0 to 80/0 Km. of N.H. 201 in the state of Odisha under phase -1 of NHIIP-OD-201-09

2015

RISES LIMITED

in) & Theme Engineering Service Pvt Ltd ( JV)

1,300/- & 2nd Mobilization of Rs 6,88,21,950/- has been paid to EPC contractor.

Mile stone
Physical
Target date

Achievement

Earthwork 14.00 Km

GSB 11.25 KM

WMM Bottom layer 8.0 Km

WMM Top layer 6.5 Km


DBM 6.0 Km

BC NIL
20.05.2015
RCC slab culvert
3nos completed
RCC Box culvert
10nos completed / 2 in Progress

HP culvert 5 nos completed/ 2 No in Progress

Minor Bridge 3 nos in progress

Major Bridge

Misc. ornamental work

06.12.2016

24.06.2017

03.05.2018

trees has been completed up to 200 nos out of 224 and others are in pogress.

ge-I clearance vide letter No. (CONST) 319-18885/2015 dated.28.10.2015 of Joint Secretary to
t, Bhubaneswar. NPV & CA deposited to concerned DFOs for Stage-II Clearance.

ted & estimate for water supply pipe line shifting work has been sanctioned by RO, BBSR on dated:
r 47/500 Km.(At Semela) is completed.

Laboratory at Semela camp.

ppointed date i.e. 02.11.2015.& balance 2% was handed over on 28/01/2016

ency.

m. At Ushigoan crusher and production is in progress.

pproved and revised work programme submiited by EPC and under scrutiny by AE
ted and performing their duties.