Documente Academic
Documente Profesional
Documente Cultură
NH Division Sambalpur.
NH-153(B) EPC Project.
Date of Report:
Name of the work -Widening & Strengthening of two lane to two lane with paved shoulder from km 58/000 to km 116/1
153(B) on EPC mode in the state of Odisha. ( Naktideul to Boudh)
Name of Division :-Sambalpur
Project Progress For 1st Week of September 2019 ( From 27.08.2019 to 02.09.2019 )
(A) Physical Progress on Road Works in Length :
Scope of Work Balance Work In
S.No. Section Details of Work UOM Remarks
Work completed Work Progress
1 Earthwork Upto Sub-Grade Km 52.533 42.100 10.433 0.100
4 HP Culverts Nos 11 10 1 0 1
New
5 Construction of Box Culverts Nos 1 0 1 0 1
Culverts
New
Construction of
Culverts
6 Slab Culverts Nos 1 0 1 0 1
New
7 Construction of Minor Bridges Nos 8 0 8 1 7
Culverts
Repair &
8 Major Bridges - Mahanadi River Nos 2 0 2 0 2
Rehabilitation
(C) Physical Progress of Other Misc. Work :
Scope of Work Balance Work In
S.No. Section Details of Other Misc. Works UOM Yet to Start
Work completed Work Progress
1 Toll Plaza location @ Nos 1 0 1 0 1
2 Other Works Road Side Drains Rmt. 6860 2900 3960 0 3960
Road Signs, Marking, Km stones &
3 kms 58.100 0 58.100 0 58.100
Safety devices & etc.
4 Bus Bays / Passenger Shelters Nos 13 0 13 0 13
( D) Financial Progress
Milestone
% of Contract Achieved as on
Mile Stone Milestone Date Amount in Achieved In Crs.
Price (Target) Milestone date
Crs
Project Completion
03-04-2020 100% 117.820
date (730 Days)
gatpur, Cuttack
es
Remarks
Work In Progress.
Remarks
MNB work in Progress
( 3 span slab casted out
of 3 at Ch.68/722)
Remarks
Remarks
NH Division Sambalpur
Naktideul to Boudh of NH-153 (B)
General Information
Name of the work -Widening & Strengthening of two lane to two lane
Name of the Work - with paved shoulder from km 58/000 to km 116/100 of NH 153(B) on E
mode in the state of Odisha. ( Naktideul to Boudh)
Sanction Amount - Rs. 160.98 Cr
Tender Awarded for - Rs. 117.82 Cr.
Name of Agency - Sri Durga Condev(P) Ltd
Appointed Date - 04.04.2018
Construction Period - 24 Months
Stipulated date of Completion - 03.04.2020
M/s - Planning and Infrastructureral Development Consultants Limited
Authority Engineer - association with Subudhi Associates
Effective Date of AE - 07.05.2018
Report on Progress of Pre construction activity till 1st Week of September, 2019 ( From 27.08.2019 to 02.09.2019 )
Land
1.c Land handed Over to EPC Contractor - 92.22% as per agreement.
Acquisition
Shifting of
Date of handing over of estimate to RWSS Dept.submitted an estimate to
6.b -
Contr. Authority
Shifting of
6.c RWSS Length in Km shifted - Not yet Started
6.d Utility Balance Length in Km to be shifted - -
"Rehabilitation and Upgrading to 2 lanes / 2 lane with Paved Shoulders Configuration and Strengthening
1 Name of the work : of Bhojpur- Chhatabar Section (km 131.0 to km 192.0) of NH-200 in the State of Odisha under Phase-I of
National Highways Inter-connectivity Improvement Projects (NHIIP)"
7 Civil Contractor : Sri Durga Condev (P) Ltd.- Shree Balaji Engicon (P) Ltd.-Joint Venture (SDCPL-SBEPL-JV)
8 Contract price of civil works Rs. 218.63 cr
Date of commencement of civil
9 26-10-2015
works.
10 Scheduled date of completion 24-10-2017 (730 days)
Supervision Consultant
11 : LEA Associates South Asia Pvt Ltd.
( Authority's Engineer)
Contract price of Supervision
12 : Rs. 7,82,50,000.00
Consultants (AE)
13 Effective date of assignment of AE : 18-06-2015
Deogarh district: Tree cutting of non foresting area estimate have been obtained by the Ministry vide
letter No.RW/NH-12013/26/6/2010 sp(D)/EAP dt.15.03.2016. Due payment has been deposited to the
18 Tree cutting in non forest area :
Forest Department, Odisha. Tree cutting of 2180 Nos. has been completed so far out of 2422 trees.
Sambalpur district: Tree cutting work of non forestry area of Sambalpur District has been completed.
Stage I clearance: Stage-I clearance approval conveyed by F&E Deptt., Govt of Odisha on dated 12-04-16
20 Forest land diversion :
and for Stage-II, Estimate for NPV, Compensatory afforestation submitted to MoRT&H on dated: 16-06-16
STATUS OF PROJECT UNDER NHIIP PHASE -I as on 15-06-2016 (NH-200)
(i) Electric Pole shifting : Work in Sambalpur District has been completed. Balance work in Deogarh District
recently handed over to EPC Contractor for execution. Route Map of relocation of Electric Poles of Deogarh
21 Shifting of utility :
District was handed over to EPC Contractor during Jan.'2016
(ii) 1.5 Km. of Sec-1 & 6.5 Km. of Sec-II of live water pipe line is yet to be relocated.
b) Laboratory set up: : Set up of lab equipments (100% completed) in Section-I & Section-II.
Existing Batching Plant duly established at Konarajro for Section-I & Rengalibeda for Section-II has been
c) Batching Plant: :
intimated by the EPC Contractor to use for this project corridor.
Existing WMM Plant & Batch type HMP Plant duly established at Badabahal for Section-I is under operation
d) WMM Plant & Batch type HMP: :
& WMM Plant at Rengalibeda for Section-II is under operation.
ROW pillars already established as per schedule. Its painting & lettering confirming to IRC provision is still
e) ROW :
to be complied.
f) Road maintenance Work: : The necessary instruction of PIU & AE has been given for its early regular maintenance
g) Sampling of existing Soil: : Sampling of existing soil of 11 km in Sec-I & 20 km in Sec-II have been completed.
h) Diversion Plan: : Temporary Traffic Diversion Plan for the construction of structures has been Approved.
Status of ESMP (Equipment safety
i) : Being complied & Submitted.
Monitoring plan)
j) Bridge Soil Investigation: : Already Completed.
Source Approval of Manufactured
Source of Admixture, Course Aggregate, Fine Aggregate, Water, Steel, Cement, Hume Pipe have been
k) Materials like (cement,steel,Hume :
approved.
pipes etc)
Aggregate resourse/sampling testing
l) : Approved.
i.e. sand,gravels etc
Quarry for Section-I is at Kusumdih & for section-II is at Khindo. Crusher for Section-I is at Kusumdih &
Section-II is at Chhatripita. The existing crusher plant of Sec-I have been assembled with VSI system &
m) Quarry & crusher : 4.75 mm screening facility. The Crusher of Sec-I is under operation. The assembling of VSI system of
existing crusher plant of Sec-II & 4.75 mm screening facility is under progress.
p) Axle load survey : Completed by EPC Contractor and submitted to AE for review.
1)The soft copy of final review report the P & P of balance 30 Km. from Km.142+000 to Km.172+000, 106
Nos. of Box Culverts, 10 Nos. of Minor Bridges, Pavement Design of Sec-I from Km.131+000 to
Km.142+000 has been handed over to the EPC Contractor on 10.04.2016 for formal submission to AE for
Pavement Design, Plan Profile and
q) : final review.
Work Programme:
2) (i) The Design and GAD of Major Bridge, (ii) Working drawing and detail co-ordinates of major and minor
junctions, (iii) Bus lay bye & Truck lay-bye, (iv) Drainage Plan of the entire Project Cooridor, (v) Pavement
design of Sec-I from Km.142+000 to Km.156+447 is yet to be completed and submitted by the EPC
28 Mobilisation of Man power : Mobilized as per requirement in Sec-II. However, it is inadequate in Sec-I to achieve the month's target.
The Mobilization of AE has been completed except the Resident Engineer as per direction of Chief Engineer,
NH Division, Odisha. The obligations in respect of reporting & deliveries is being complied in time in
confirmity to consultancy Aggrement. The Assistance & supporting guidance in technical & contractual
29 Activities performed by AE :
matters are being provided always to the Authority in all respect. The site supervision & Monitoring of
Project Progress keeping in mind for the achievement of the Monthly target as well as 2 nd Milestone is also
being expedited by Authority's Engineer.
STATUS OF PROJECT UNDER NHIIP PHASE -I as on
Financial in Crores
a) CD Works Submitted by
: As per DPR
Contractor
Box Culverts 41 39
Minor Bridges 6 6
Major Bridge 1 Repair & Rehabilitatio
b) Plan & Profiles Submitted by
Chainage
Contractor
00/00 to 07/00
12/19/2014
11/00 to 12/00
132/0 to 133/0
134/0 to 135/0 2/19/2015
137/0 to 141/0
133/0 to 134/0
6/25/2015
136/0 to 137/0
d) WMM Plant & Batch type HMP: : WMM Plant & HMP mobilized and functio
24 Mobilization of Man power : Not yet fully mobilized by the Civil Works
1) The Monthly progress Report upto May
for the period Jan'16-Mar'16 is furnished.
2) The Monthly progress Report for Envir
month of Apr-2015 and quarterly progres
25 Activities performed by CSC :
Jan'16-Mar'16 is furnished.
3) Profile checking of all 68 Km is comple
R NHIIP PHASE -I as on 24-06-16 (NH-217)
0.0-Km 158.0
km
6.16 Cr.
5.78 Cr.
ssued on 14.02.14
5.78 Cr.
2014
2016
Percentage of Progress
5.88%
4.22%
100.00%
32.48%
r Progress CD Works:
&G = 42.64 Km (i) Box Culverts - 19 Nos
bankment = 37.08 Km completed & 5 no. in progress
bgrade = 36.42 Km (ii) Hume Pipe Culverts - 11 Nos
B = 36.22 Km Completed and 2 no in progress.
MM(1st layer) = 34.07 Km (iii) Slab Culvert 4 nos.
M (Top) = 31.24 Km Completed, 2 no in progress
M = 36.31 Km (iv) Minor Bridge-6 no. in progress
leted
plan for non title holders and CPRs sanctioned by MoTH&H on 08-03-16.
stallment disbursed 50% of PAPs.
Approved
by CSC
18
8
39
6
Repair & Rehabilitation
Approved
by CSC
11/28/2014
12/30/2014
7/7/2015
7/13/2015
8/29/2015
progress
d submission for culvert/Humepipes submitted by the contractor and
wed & approved by CSC
itted. Reviewed & approved by CSC.
leted
ved
Supervision Consultant
11 : M/s Euroestudios S.L(Spain) & Theme Engineering
( Authority's Engineer)
14 Mobilization Advance to EPC contractor: : 1st Mobilization of Rs4,58,81,300/- & 2nd Mobilization o
Balance to
Target Achievement
Achieved
1st Mile stone (10 % contract price)
24.66
( 200 days from start date i.e. : 22.94
(10.75%)
20.05.2016)
16 Tree cutting in non forest area : Cutting & felling of road side trees has been completed up
b) Laboratory set up: : The Agency has set up the Laboratory at Semela camp.
2015
RISES LIMITED
1,300/- & 2nd Mobilization of Rs 6,88,21,950/- has been paid to EPC contractor.
Mile stone
Physical
Target date
Achievement
Earthwork 14.00 Km
GSB 11.25 KM
BC NIL
20.05.2015
RCC slab culvert
3nos completed
RCC Box culvert
10nos completed / 2 in Progress
Major Bridge
06.12.2016
24.06.2017
03.05.2018
trees has been completed up to 200 nos out of 224 and others are in pogress.
ge-I clearance vide letter No. (CONST) 319-18885/2015 dated.28.10.2015 of Joint Secretary to
t, Bhubaneswar. NPV & CA deposited to concerned DFOs for Stage-II Clearance.
ted & estimate for water supply pipe line shifting work has been sanctioned by RO, BBSR on dated:
r 47/500 Km.(At Semela) is completed.
ency.
pproved and revised work programme submiited by EPC and under scrutiny by AE
ted and performing their duties.