ID Task Name Duration Month 2 Month 3 Month 4 Month 5

W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15


1 RENOVATION OF GUBIO II PRIMARY SCHOOL, GUBIO LGA, 75 days
BORNO STATE
2 SITE MOBILISATION AND DEMOBILISATION 5 days
3 SITE LAYOUT 5 days
4 BLOCK I 18 days
5 ALTERATIONS AND DEMOLITION 3 days
6 WALLING AND MASONRY WORKS 2 days
7 ROOF CONCRETE WORK 3 days
8 ROOF AND ROOF COVERINGS 5 days
9 WINDOWS AND DOORS INSTALLATIONS 4 days
10 ELECTRICAL SERVICES 2 days
11 SURFACE FINISHES 4 days
14 BLOCK II 18 days
15 REMOVING FINISHING 2 days
16 WALLING AND MASONRY WORKS 2 days
17 ROOF CONCRETE WORK 3 days
18 ROOF AND ROOF COVERINGS 5 days
19 WINDOWS AND DOORS INSTALLATIONS 4 days
20 ELECTRICAL SERVICES 2 days
21 SURFACE FINISHES 4 days
24 BLOCK III 24 days
25 ALTERATIONS AND DEMOLITION 3 days
26 FRAMES AND UPPER FLOORS 7 days
27 WALLING AND MASONRY WORKS 2 days
28 ROOF CONCRETE WORK 3 days
29 ROOF AND ROOF COVERINGS 5 days
30 WINDOWS AND DOORS INSTALLATIONS 4 days
31 ELECTRICAL SERVICES 2 days
32 SURFACE FINISHES 4 days
35 BLOCK IV 17 days
36 REMOVING FINISHING 2 days
37 WALLING AND MASONRY WORKS 2 days
38 ROOF CONCRETE WORK 3 days
39 ROOF AND ROOF COVERINGS 5 days
40 WINDOWS AND DOORS INSTALLATIONS 4 days
41 ELECTRICAL SERVICES 2 days
42 SURFACE FINISHES 4 days
45 BLOCK V 24 days
46 ALTERATIONS AND DEMOLITION 3 days
47 FRAMES AND UPPER FLOORS 7 days
48 WALLING AND MASONRY WORKS 2 days
49 ROOF CONCRETE WORK 3 days
50 ROOF AND ROOF COVERINGS 5 days
51 WINDOWS AND DOORS INSTALLATIONS 4 days
52 ELECTRICAL SERVICES 2 days
53 SURFACE FINISHES 4 days
56 BLOCK VI 25 days
57 ALTERATIONS AND DEMOLITION 3 days
58 FRAMES AND UPPER FLOORS 7 days
59 WALLING AND MASONRY WORKS 2 days
60 ROOF CONCRETE WORK 3 days
61 ROOF AND ROOF COVERINGS 5 days
62 WINDOWS AND DOORS INSTALLATIONS 4 days
63 ELECTRICAL SERVICES 2 days
64 SURFACE FINISHES 4 days
67 BLOCK VII 17 days
68 REMOVING FINISHING 2 days
69 WALLING AND MASONRY WORKS 2 days
70 ROOF CONCRETE WORK 3 days
71 ROOF AND ROOF COVERINGS 5 days
72 WINDOWS AND DOORS INSTALLATIONS 4 days
73 ELECTRICAL SERVICES 2 days
74 SURFACE FINISHES 4 days
77 BLOCK VIII 25 days
78 ALTERATIONS AND DEMOLITION 3 days
79 FRAMES AND UPPER FLOORS 7 days
80 WALLING AND MASONRY WORKS 2 days
81 ROOF CONCRETE WORK 3 days
82 ROOF AND ROOF COVERINGS 5 days
83 WINDOWS AND DOORS INSTALLATIONS 4 days
84 ELECTRICAL SERVICES 2 days
85 SURFACE FINISHES 4 days
88 BLOCK IX 19 days
89 REMOVING FINISHING 2 days
90 WALLING AND MASONRY WORKS 2 days
91 ROOF CONCRETE WORK 3 days
92 ROOF AND ROOF COVERINGS 5 days
93 WINDOWS AND DOORS INSTALLATIONS 4 days
94 ELECTRICAL SERVICES 2 days
95 SURFACE FINISHES 6 days
98 SITE CLEANING 4 days
99 SITE HAND OVER 1 day