Documente Academic
Documente Profesional
Documente Cultură
CAPM® & PMBOK® are registered trademarks of the Project Management Institute, Inc. Copyright 2014, Simplilearn, All rights reserved.
After completing this ● Differentiate between Project Life Cycle and Project Management Process
lesson, you will be able ● Name the five Project Management Process Groups
to:
● Describe the Process Group Interactions
● Recognize processes aligned to different Process Groups and Knowledge Areas
● Identify the inputs and actions of Project Management Process Groups
Given below are the differences between project lifecycle and project management process:
In the software industry, project lifecycle includes In the develop schedule process, one needs to develop the
understanding requirement in the requirement analysis project schedule, irrespective of the industry or domain you
phase, implementing requirement in the design phase, are working.
writing code and implementing the functionality in the
coding phase, debugging of code in the testing phase,
installation of the software at customer location, and
providing support in the operations and support phase.
The iteration of processes within the phases is dependent on the scale of the projects. Small projects may
! have only one iteration, while bigger projects may have multiple iterations before they enter a new phase.
4 Copyright 2014, Simplilearn, All rights reserved.
Process Group Interactions
Process Groups have overlapping activities that occur throughout the project life cycle. The output of one process acts
as an input to another process or a deliverable of the project.
47 processes in project management are grouped into 10 Knowledge Areas, and mapped to 5 Process Groups.
Study the table to identify processes under project management and the knowledge area they
belong to.
Exam Tips
6 Copyright 2014, Simplilearn, All rights reserved.
Project Management Process Groups
Monitoring and
Initiating Process Planning Process Executing Closing Process
Controlling
Group Group Process Group Group
Process Group
Initiating Process Group defines a new project or phase. When the project charter is approved, the project is officially
authorized.
The inputs and activities of initiating process group are important from the exam perspective.
Exam Tips
8 Copyright 2014, Simplilearn, All rights reserved.
Planning Process Group
Planning Process Group establishes the total scope of effort, objectives, and course of action required to attain those
objectives.
Executing Process Group completes the work defined in the project management plan to satisfy the project
specifications.
Monitoring and Controlling Process Group tracks, reviews, and regulates the progress and performance of the project;
identifies and initiates the changes to the plan when required.
Closing Process Group finalizes the activities across all Project Management Process Groups to
formally complete the project, phase, or contractual obligations.
Inputs Actions taken
● Project plan and documents ● Confirm that all project requirements are met
● Accepted project deliverables ● Obtain formal signoff from customer
● Procurement documentation ● Make payment to all parties and update cost
● Organizational process assets records
● Enterprise environmental factors ● Complete contract closure
● Update lessons learned database
● Measure customer satisfaction
● Handover project deliverables to operations team
● Release resources from the project
a. Planning
d. Closing
a. Planning
d. Closing
Answer: b.
Explanation: Monitoring and Controlling (see PMBOK® Guide section 3.6). During project closure the
project manager reviews the acceptance documentation from scope validation to ensure that all project
requirements are completed.
a. Project charter
d. Procurement documents
a. Project charter
d. Procurement documents
Answer: a.
Explanation: All other options are inputs to the initiating process group.
a. Project manager
b. Functional manager
c. Team members
d. Stakeholders
a. Project manager
b. Functional manager
c. Team members
d. Stakeholders
Answer: a.
Explanation: The project manager is in control of the project throughout the project life cycle.
a. Planning
b. Closing
c. Monitoring and Controlling
d. Initiating
a. Planning
b. Closing
c. Monitoring and Controlling
d. Initiating
Answer: d.
Explanation: The high level constraints of schedule and budget are determined during the initiating
process group. The detailed planning is done during the planning process group.
a. Cost and staffing levels are low at the start, peak as the work is carried out, and drop rapidly as the
project draws to a close
b. Stakeholder influences are greatest towards the end of the project
a. Cost and staffing levels are low at the start, peak as the work is carried out, and drop rapidly as the
project draws to a close
b. Stakeholder influences are greatest towards the end of the project
Answer: b.
Explanation: Stakeholder influences are greatest towards the beginning of the project.
Answer: a.
Explanation: In every project, all five process groups must be included but the level of attention given to
each process group will be governed by the project manager depending on the project size and complexity.
CAPM® & PMBOK® are registered trademarks of the Project Management Institute, Inc. Copyright 2014, Simplilearn, All rights reserved.
[1] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth
Edition, Project Management Institute, Inc., 2013, Page 50.
[2] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth
Edition, Project Management Institute, Inc., 2013, Page 51.