Documente Academic
Documente Profesional
Documente Cultură
Content List
Document Title 1
Content List 2
1. Objectivity 3
1.1 Purposed 3
1.2 Objectivities 3
2. Scope 3
3. Reference 3
4. Responsibility 3
5. Procedure of welding control 4
5.1 Welding Procedure Qualification SMAW 4
5.2 Qualification of Welder SMAW 4
5.3 Re Qualification of Welder SMAW 5
5.4 Supervision of welder Qualification 5
5.5 Production Welding SMAW 5
5.6 Material Welding SMAW 5
5.7 Field Portable dryer 5
5.8 Equipment Welding Machine 5
5.9 Joint Preparation 7
5.10 Table Inspection welding 7
5.11 NDT Nonconforming 7
6. General Flow of Welding control material 8
7. General Flow of Welding control on site 9
8. Related Documents 10
. Page 1 of 12
Welding SMAW On Site Procedure
1. OBJECTIVITY
1.1 PURPOSED
Welding control procedure is made as standard all welding production process.
Welder operator on site must be qualified according AWS D1.1 structural welding
code steel.
1.2 OBJECTIVITY
Ascertaining of quality an substance as according to criteria standard which have
been specified by company.
2. SCOPE
All supporting document in this procedure on welding on site for steel structure Station
MRT Block M:
● Welding Procedure Specification (WPS) - SMAW
● Procedure Qualification Record (PQR) - SMAW
● Welder performance qualification record (WPQR) - SMAW
3. REFERENCE
3.1 AWS D1.1
4. RESPONSIBILITY
QC Inspector will observe of the welder qualification periodically and make the Welder Log
(welder document)
5. PROCEDURE
5.1 Welding Procedure Specification SMAW (Shield Metal Arc Welding)
5.1.1 QC inspector, welding Inspector prepares qualification of Welder
Procedure Specification (WPS), Procedure Qualification Record (PQR), and
Welder Performance Qualification Record (WPQ) to be submitted to
production department then used by welder.
5.1.2 QC Inspector , welding inspector should always do supervision toward
implementation of Welding Procedure Specification (WPS) and Procedures
Qualification Record (PQR).
5.1.3 Welding Procedure Specification (WPS) made by QC Inspector, welding
inspector as one of requirement on standardization code. Inside, there are
many things that should be done before production process runs,
including :
. Page 2 of 12
Welding SMAW On Site Procedure
. Page 3 of 12
Welding SMAW On Site Procedure
5.6.2 If the store receives low hydrogen electrode, the process of storage
should be as per recommendation of manufacturer before submitted to
welder.
5.6.3 Each welder should be minimize its use would be required to store, the
electrodes are not used and returned back to the store to be kept in the
ware house.
5.6.4 Warehouse keeper on site shall examine the conditions of return of the
electrode should be clean and identified. The damaged electrodes and no
identification must be removed
. Page 4 of 12
Welding SMAW On Site Procedure
. Page 5 of 12
Welding SMAW On Site Procedure
. Page 6 of 12
Welding SMAW On Site Procedure
Legend
CJP Complete Joint Penetration ( AWS D1.1 )
FPBW Full Penetration Butt Weld (Client Spec – General Notes 3STO-STR-1002-TB1)
. Page 7 of 12
Welding SMAW On Site Procedure
5.9.3 Joint End Plate to End Plate with under Gap 45mm include
5.9.4 Joint End Plate to End Plate with above Gap 45mm
. Page 8 of 12
Welding SMAW On Site Procedure
. Page 9 of 12
Welding SMAW On Site Procedure
. Page 10 of 12
Welding SMAW On Site Procedure
. Page 11 of 12
Welding SMAW On Site Procedure
8. Related Documents
Form 6.2-08 : Welding Qualification Test
Form 7.5-05 : Procedure Qualification Record
Form 7.5-04 : Welding Procedure Specification
Form 8.2-06 : Liquid Penetran Examination Report
. Page 12 of 12