DAFTAR ISIAN 3 : DAFTAR HARGA


DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4

1 150 KV SWITCHYARD STEEL STRUCTURES, BUSBAR, OVERHEAD GROUND WIRE (SHIELD WIRE)

Galvanized steel structure to complete the specified scope of work for switchyard with 7 Bay Double
1.1 Busbar Type U of :
2x 150 kV Line Bays to PLTU Lontar
2x 150 kV Line Bays to Teluk Naga
2x 150 kV Transformer Bay
1x 150 kV Coupler Bay
Consist of :
- Post steel Structure Type TW-1, high 14,0 m' + steel Structure for earth wires high 4 m' Sets 24
- Post steel Structure Type TW-2, high 10,0 m' Sets 0
- Post steel Structure Type TW-3, high 14,0 m' (earthing tower) Sets 1
- Beam steel Structure for Busbar dan Crossbar, 12 m' Sets 20
- Beam steel Structure for Busbar dan Crossbar, 14 m' Sets 12
Sub total items 1.1
1.2 Overhead Ground Wire (Shield Wire) and Accessories
Consist of :
- Over Head Ground Wire ( with used GSW 55 mm2), Install from Post steel Structure Type1 (18m) to Post steel
Structure Type1 (parallel with Busbar and Parallel with Crossbar) lot 1

- Tension string set for GSW 55 mm2 (Complete jumper/ joint GSW 55 mm2 to structure and to GSW 55 mm2
other's) Sets 80

Name of Bidder : Rev.1


1 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
Sub total items 1.2
Substation and Building Earthing System (Mesh/ Grid System and Rod Electrode) and Complete with all
1.3 Connector Type
lot 1

- Copper strip or flexible conductors of the cross section specified, installed so as to form a grid system laid
directly in the ground enclosing the complete substation together with all electrodes for surge arester/LA, CVT
and Transformator equipment direct earthing (Rod Electroda).

- Copper strip of flexible conductors to connect metalclad parts of all equipment and structures to main Earth
System.Copper strip of flexible conductors to connect metalclad parts of all equipment and structures to main
Earth System (minimum CU 150 mm2).
- Copper strip of flexible conductors installed around the Building, metalclad parts of all equipment in the Building
and structures to connect to main Earth System (minimum CU 150 mm2).
- Copper strip or flexible conductors to bond all overhead line towers direct to the substation Earth System.

Sub total items 1.3

Name of Bidder : Rev.1


2 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4

1.4 150 kV Double Busbar Type U (Conductor 2 x TAL 850 mm2/phase)


- Conductor 2 x TAL 850 mm2/phase for Double Busbar Type U lot 1
- Dropper to CVT Bus from Busbar I & II (3 phase) with Conductor 2 x TAL 850 mm2 (Complete with Connector
for Jumper ) lot 1

- Double Tension Insulator String for Busbar 2 x TAL 850 mm2/phase, with 2 x 12 Insulator/ set, 120 kN,
31mm/kV. (Complete with Connector for Jumper Busbar) Sets 54

- Single Suspension String Insulator Set 2 x TAL 850 mm2/phase for Jumpers of Busbar (Complete with
Sets 24
Connector Jumper)
- Spacer 20 cm for conductor busbar Sets 45
- 150kV capacitor voltage transformer with 2 secondary winding, ratio 150kV : √3 / 100V : √3 or 110V : √3,
Burden 15 VA ( for protection and instrument and metering), cl. 0.2, cl. 3P, rated capacitance 4000 up to 10000
pF, complete with clamps, supporting structure. units 6

- Miscellaneous equipment, LV power cable and accessories and necessary equipment (cable ladder, jumper,
clamp, cable lug, terminal, … etc)set of clamps, connectors and accessories for complete installation scope of lot 1
work.
Sub total items 1.4
TOTAL PRICE ITEMS 1.1 - 1.4

Name of Bidder : Rev.1


3 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4

2 150 KV LINE BAY TO PLTU LONTAR : 2 BAYS

2.1 Crossbar Conductor 2 x TAL 850 mm2/phase + Dropper's Busbar and Crossbar to DS & CB. lot 1
2.2 Conductor 2 x TAL 850 mm2/phase jumper for Inter HV Equipment (from CB to LA) and dropper from Transmission
line lot 1

2.3 Double Tension Insulator String Set for installation the Crossbar, Conductor 2 x TAL 850 mm2/phase Sets 12
2.4 Single Suspension Insulator String Set with Conductor 2 x TAL 850 mm2/phase to CB and to DS Sets 6
2.5 Spacer 20 cm for conductor Sets 12
2.6 Disconnecting switch 150 kV 3 phase motor operated, 3150 Amp, 40 kA, Creepage distance 31 mm/kV, without
earthing switch, complete with clamps and supporting steel structure (DS Busbar). Sets 4

2.7 150 kV Post Insulator complete with clamps, and supporting structure for dropper to bus disconnector switch (DS)
Sets 4
2.8 Circuit Breaker 3 phase 150 kV, single pole for line bay, SF6, cap. 3150 Amp, 40 kA, Creepage distance 31 mm/kV,
complete with clamps and supporting structure. Sets 2

2.9 Current Transformer 150 kV, 40 kA for Line Bay, 3 core, Creepage distance 31 mm/kV, complete with clamps and
supporting steel structure.
Core-1 : Class PX, 2000-4000/1 A
units 6
Core-2 : Class 5P20, 2000-4000/1 A
Core-3 : Class 0,5, 2000-4000/1 A

2.10 Disconnecting switch 150 kV 3 phase motor operated, cap. 3150 Amp, 40 kA, Creepage distance 31 mm/kV, with
earthing switch, complete with clamps and supporting steel structure (DSE). sets 2

Name of Bidder : Rev.1


4 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
2.11 150kV capacitor voltage transformer with 2 secondary winding, ratio 150kV : √3 / 100V : √3 or 110V : √3, Burden 15
VA ( for protection and instrument and metering), cl. 0.2, cl. 3P, rated capacitance 4000 up to 10000 pF, complete
with clamps, supporting structure. units 6

2.12 Lightning Arrester 150 kV, 20 kA for Line bay, complete with clamp, surge counter, supporting steel structure,and all
necessary equipment. units 6

2.13 Set of clamps, connectors and accessories for complete all installation lot 1
2.14 Protection and Control Cubicle for Line bay Comprising : (Semi Digital) sets 2
- 2 Ethernet switch for station level
- 2 Ethernet switch for process level
- IED Main line protection (MPU) - Distance Relay, include DEF, Autorecloser, Synchrocheck, etc.
- IED Back-up line protection (BPU) - Over Current, GFR, Fault Recorder, etc
- IED Bay control (BCU, Instrument)
- 1 Redundant Box
- Optical distribution frame
- Panel
Including but not limited to:
- miscellaneous equipment, optical cables and cord, control control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay
- all necessary work (dismantling, installation, integration, adaptation) to the existing system (SAS, Busbar
Protection, etc) in GI Lontar and adaptation in control center to complete the scope of works.

2.15 Marshaling kiosk for 150 kV Line Bay Comprising : set 2


- IED Merging unit (number of port as required to complete scope of work)

Name of Bidder : Rev.1


5 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
- IED Switchgear Control Unit (number of port as required to complete scope of work)
- Local mimic (BCM)
- Optical distribution frame
- Panel and cooling system
Including, miscellaneous equipment, optical cables and cord, control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.

Note: price of all Merging Unit and Switchgear Control Unit needed on 150 KV LINE BAY TO PLTU LONTAR is
include in item 2.15
2.16 Fiber Optic Armoured (FA) Cable 16 12 cores (multi mode) to connect marshalling kiosk to ethernet switch. lot 1
2.17 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, cable lug, terminal,
… etc) to complete the scope of works lot 1

TOTAL PRICE ITEMS 2

Name of Bidder : Rev.1


6 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4

3 150 KV LINE BAY TO TELUK NAGA : 2 BAYS

3A 150 KV LINE BAY TO TELUK NAGA : 1 BAY ( Digital Substation )

3A.1 Crossbar Conductor 2 x TAL 850 mm2/phase + Dropper's Busbar and Crossbar to DS & CB. lot 1
3A.2 Conductor 2 x TAL 850 mm2/phase jumper for Inter HV Equipment (from CB to LA) and dropper from Transmission
line lot 1

3A.3 Double Tension Insulator String Set for installation the Crossbar, Conductor 2 x TAL 850 mm2/phase Sets 6
3A.4 Single Suspension Insulator String Set with Conductor 2 x TAL 850 mm2/phase to CB and to DS
Sets 3
3A.5 Spacer 20 cm for conductor Sets 6
3A.6 Disconnecting switch 150 kV 3 phase motor operated, 3150 Amp, 40 kA, Creepage distance 31 mm/kV, without
earthing switch, complete with clamps and supporting steel structure (DS Busbar). Sets 2

3A.7 150 kV Post Insulator complete with clamps, and supporting structure for dropper to bus disconnector switch (DS)
Sets 5
3A.8 Circuit Breaker 3 phase 150 kV, single pole for line bay, SF6, cap. 3150 Amp, 40 kA, Creepage distance 31 mm/kV,
complete with clamps and supporting structure. Sets 1

3A.9 Optical Current Transformer and Voltage Transformer 150 kV, 40 kA for Line Bay for metering and protection (equal
to CT --> class 0.5 and PX, and equal to VT --> cl. 0.2, and cl. 3P) Creepage distance 31 mm/kV. units 3

3A.10 Steel structure complete with clamps for Post Insulator (suitable for conventional CT or VT) 150 kV, 3 phase
units 1

Name of Bidder : Rev.1


7 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
3A.11 Steel structure complete with clamps for Combined Digital CT/VT (CMO) 150 kV, 3 phase units 1
3A.12 Disconnecting switch 150 kV 3 phase motor operated, cap. 3150 Amp, 40 kA, Creepage distance 31 mm/kV, with
earthing switch, complete with clamps and supporting steel structure (DSE). sets 1

3A.13 Lightning Arrester 150 kV, 20 kA for Line bay, complete with clamp, surge counter, supporting steel structure,and all
necessary equipment. units 3

3A.14 Set of clamps, connectors and accessories for complete all installation lot 1
3A.15 Protection and Control Cubicle for Line bay Comprising : (Full Digital) sets 1
- 2 Ethernet switch for station level
- 2 Ethernet switch for process level
- IED Main line protection (MPU) - Current differential, syncrocheck, etc
- IED Back-up line protection (BPU) - Over Current, GFR, Fault Recorder, etc
- IED Bay control (BCU, Instrument)
- 1 Merging Unit Digital
- 1 Redundant Box
- Optical distribution frame
- Panel
Including, miscellaneous equipment, rack cabinet, optical cables and cord, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.

3A.16 IED Main Line Protection - Current differential, syncrocheck, etc, for installed in GI Teluk Naga sets 1

Name of Bidder : Rev.1


8 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
Including but not limited to:
- miscellaneous equipment, optical cables and cord, control control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay
- all additional hardware and software needed to connect to the existing system (SAS, Busbar Protection, etc) on GI
150 kV Teluk Naga and to operated properly with MPU IED on GI 150 kV Teluk Naga 2
- all necessary work (dismantling, installation, integration, adaptation) to the existing system (SAS, Busbar
Protection, etc) in GI Teluk Naga and adaptation in control center to complete the scope of works.

3A.17 Marshaling kiosk for 150 kV Line Bay Comprising : set 1


- IED Merging unit (number of port as required to complete scope of work)
- IED Switchgear Control Unit (number of port as required to complete scope of work)
- Local mimic (BCM)
- Optical distribution frame
- Panel
Including, miscellaneous equipment, optical cables and cord, control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.

Note: price of all Merging Unit and Switchgear Control Unit needed on 150 KV LINE BAY TO TELUK NAGA is
include in item 3.16
3A.18 Fiber Optic Armoured (FA) Cable 16 12 cores (multi mode) to connect marshalling kiosk to ethernet switch. lot 1
3A.19 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, cable lug, terminal,
… etc) to complete the scope of works lot 1

Name of Bidder : Rev.1


9 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4

3B 150 KV LINE BAY TO TELUK NAGA : 1 BAYS ( Conventional CT & CVT )

3B.1 Crossbar Conductor 2 x TAL 850 mm2/phase + Dropper's Busbar and Crossbar to DS & CB. lot 1
3B.2 Conductor 2 x TAL 850 mm2/phase jumper for Inter HV Equipment (from CB to LA) and dropper from Transmission
line lot 1

3B.3 Double Tension Insulator String Set for installation the Crossbar, Conductor 2 x TAL 850 mm2/phase Sets 6
3B.4 Single Suspension Insulator String Set with Conductor 2 x TAL 850 mm2/phase to CB and to DS
Sets 3
3B.5 Spacer 20 cm for conductor Sets 6
3B.6 Disconnecting switch 150 kV 3 phase motor operated, 3150 Amp, 40 kA, Creepage distance 31 mm/kV, without
earthing switch, complete with clamps and supporting steel structure (DS Busbar). Sets 2

3B.7 150 kV Post Insulator complete with clamps, and supporting structure for dropper to bus disconnector switch (DS)
Sets 5
3B.8 Circuit Breaker 3 phase 150 kV, single pole for line bay, SF6, cap. 3150 Amp, 40 kA, Creepage distance 31 mm/kV,
complete with clamps and supporting structure. Sets 1

3B.9 Current Transformer 150 kV, 40 kA for Line Bay, 3 core, Creepage distance 31 mm/kV, complete with clamps and
supporting steel structure.
Core-1 : Class PX, 2000-4000/1 A
Core-2 : Class 5P20, 2000-4000/1 A units 3
Core-3 : Class 0,5, 2000-4000/1 A

3B.10 Disconnecting switch 150 kV 3 phase motor operated, cap. 3150 Amp, 40 kA, Creepage distance 31 mm/kV, with
earthing switch, complete with clamps and supporting steel structure (DSE). sets 1

Name of Bidder : Rev.1


10 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
3B.11 150kV capacitor voltage transformer with 2 secondary winding, ratio 150kV : √3 / 100V : √3 or 110V : √3, Burden 15
VA ( for protection and instrument and metering), cl. 0.2, cl. 3P, rated capacitance 4000 up to 10000 pF, complete
with clamps, supporting structure. units 3

3B.12 Lightning Arrester 150 kV, 20 kA for Line bay, complete with clamp, surge counter, supporting steel structure,and all
necessary equipment. units 3

3B.13 Set of clamps, connectors and accessories for complete all installation lot 1
3B.14 Protection and Control Cubicle for Line bay Comprising : (Conventional) sets 1
- 2 Ethernet switch for station level
- 2 Ethernet switch for process level
- IED Main line protection (MPU) - Current differential, syncrocheck, etc
- IED Back-up line protection (BPU) - Over Current, GFR, Fault Recorder, etc
- IED Bay control (BCU, Instrument)
- 1 Redundant Box
- Optical distribution frame
- Panel
Including, miscellaneous equipment, rack cabinet, optical cables and cord, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.

3B.15 IED Main Line Protection - Current differential, syncrocheck, etc, for installed in GI Teluk Naga sets 1

Name of Bidder : Rev.1


11 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
Including but not limited to:
- miscellaneous equipment, optical cables and cord, control control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay
- all additional hardware and software needed to connect to the existing system (SAS, Busbar Protection, etc) on GI
150 kV Teluk Naga and to operated properly with MPU IED on GI 150 kV Teluk Naga 2
- all necessary work (dismantling, installation, integration, adaptation) to the existing system (SAS, Busbar
Protection, etc) in GI Teluk Naga and adaptation in control center to complete the scope of works.

3B.16 Marshaling kiosk for 150 kV Line Bay Comprising : set 1


- IED Merging unit (number of port as required to complete scope of work)
- IED Switchgear Control Unit (number of port as required to complete scope of work)
- Local mimic (BCM)
- Optical distribution frame
- Panel
Including, miscellaneous equipment, optical cables and cord, control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.

Note: price of all Merging Unit and Switchgear Control Unit needed on 150 KV LINE BAY TO TELUK NAGA is
include in item 3.16
3B.17 Fiber Optic Armoured (FA) Cable 16 12 cores (multi mode) to connect marshalling kiosk to ethernet switch. lot 1
3B.18 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, cable lug, terminal,
… etc) to complete the scope of works lot 1

TOTAL PRICE ITEMS 3

Name of Bidder : Rev.1


12 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4

4 150 kV BUS COUPLER BAY : 1 BAY


4.1 Crossbar Conductor 2 x TAL 850 mm2/phase + Dropper's Busbar and Crossbar. lot 1
4.2 Conductor 2 x TAL 850 mm2/phase for Inter HV Equipment lot 1
4.3 Double Tension Insulator String Set for Crossbar 2 x TAL 850 mm2/phase
Sets 18
4.4 Single Suspension Insulator String Set for Crossbar 2 x TAL 850 mm2/phase
Sets 9
4.5 Spacer 20 cm for conductor Sets 18
4.6 Disconnecting switch 150 kV 3 phase motor operated, cap. 4000 Amp, 40 kA, Creepage distance 31 mm/kV,
Sets 2
without earthing switch, complete with clamps and supporting steel structure (DS Busbar).
4.7 Circuit Breaker 3 phase 150 kV, three pole for Couple bay, SF6, cap. 4000 Amp, 40 kA, Creepage distance 31
Set 1
mm/kV, complete with clamps and supporting structure.
4.8 Current Transformer 150 kV, 50 kA 40kA for bus coupler bay, 2 core, Creepage distance 31 mm/kV, complete with
clamps and supporting steel structure.
Core-1 : Class 5P20, 2000-4000/1 units 6
Core-2 : Class PX, 2000-4000/1

4.9 Set of clamps, connectors and accessories for all installation (including Inter HV equipment) lot 1
4.10a Protection and Control Cubicle for Line bay Comprising : sets 1
- 2 Ethernet switch for station level
- 2 Ethernet switch for process level
- IED Main line protection (MPU) for 10 bays - Busbar Protection, DFR, etc
- IED Back-up line protection (BPU) - Over Current, GFR, Fault Recorder, etc
Name of Bidder : Rev.1
13 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
- IED Bay control (BCU, Instrument)
- Optical distribution frame
- 1 Redundant Box
- Panel
Including, miscellaneous equipment, rack cabinet, optical cables and cord, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.

4.10b Protection and Control Cubicle for Line bay Comprising : sets 1
- IED Main line protection (MPU) for 10 bays - Busbar Protection, DFR, etc
- Optical distribution frame
- 2 Panel Proteksi
- 1 Ethernet switch per panel for Station Bus (Double Ring)
- 1 Ethernet switch per panel for Process Bus (Double Ring)
Including, miscellaneous equipment, rack cabinet, optical cables and cord, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.

4.11 Marshaling kiosk for 150 kV Coupler Bay Comprising : set 1


- IED Merging unit (number of port as required to complete scope of work)
- IED Switchgear Control Unit (number of port as required to complete scope of work)
- Local mimic (BCM)
- Optical distribution frame
- Panel

Name of Bidder : Rev.1


14 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
Including, miscellaneous equipment, optical cables and cord, control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.

Note: price of all Merging Unit and Switchgear Control Unit needed on 150 kV BUS COUPLER BAY and CVT Bus is
include in item 4.11
4.12 Fiber Optic Armoured (FA) Cable 16 12 cores (multi mode) to connect marshalling kiosk to ethernet switch. lot 1
4.13 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, cable lug, terminal,
… etc) to complete the scope of works. lot 1

TOTAL PRICE ITEMS 4

Name of Bidder : Rev.1


15 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
5 150 kV TRANSFORMER BAY : 2 BAY(S)
5.1 Crossbar Conductor 1 x TAL 850 mm2/phase + Dropper's Busbar to DS and Crossbar Conductor to DS & CB. lot 1
5.2 Conductor 1 x TAL 850 mm2/phase for Inter HV Equipment (from CB to Bushing Trafo) lot 1
5.3 Single Tension Insulator String Set for installation the Crossbar, Conductor 1 x TAL 850 mm2/phase sets 12
5.4 Single Suspension Insulator String Set with Conductor 1 x TAL 850 mm2/phase to DS & CB sets 6
5.5 Spacer 20 cm for conductor Sets 0
5.6 Disconnecting switch 150 kV 3 phase motor operated, cap. 1250 Amp, 40 kA, Creepage distance 31 mm/kV,
without earthing switch, complete with clamps and supporting steel structure (DS Busbar). sets 4

5.7 150 kV Post Insulator complete with clamps, and supporting structure for dropper to bus disconnector switch (DS)
sets 4
5.8 Circuit Breaker 3 phase 150 kV, three pole for trafo bay, SF6, cap. 1250 Amp, 40 kA, Creepage distance 25
mm/kV, complete with clamps and supporting structure. sets 2

5.9 Current transformer 150 kV, 40 kA for transformer bay, 4 core, Creepage distance 31 mm/kV complete with clamps
and supporting steel structure.
Core-1 : Class PX, 150-300/1 A
Core-2 : Class 5P20, 150-300/1 A
Core-3 : Class PX, 2000-4000/1 A units 6
Core-4 : Class 0.5, 150-300/1 A

5.10 Lightning Arrester 150 kV, 20 kA for Line bay, complete with clamp, surge counter, supporting steel structure, and
units 6
all necessary equipment.
5.11 Set of clamps, connectors and accessories for installation lot 1
5.12 Protection and Control Cubicle for 150/20 kV Transformer Bay Comprising : sets 2
Name of Bidder : Rev.1
16 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
- 2 Ethernet switch for station level
- 2 Ethernet switch for process level
- IED Main Transformer Protection - MPU (Trafo Differential, REF HV/LV side, DFR, etc.).
- IED Back Up Protection - BPU 1 for HV Side (Over Current, Earth Fault, Circuit Breaker Failure, DFR,
Instrument, etc.).
- IED Back Up Protection - BPU 2 for LV Side ( Over Current, Earth Fault, Stand by Earth Fault, etc).
- IED Bay Control - BCU + AVR
- IED AVR
- Optical distribution frame
- 1 Redundant Box
- Panel
Including, miscellaneous equipment, test block, test plug, rack cabinet, optical cables and cord, clamps,
connectors, connection to individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to
complete the scope of works.
5.13 Marshaling kiosk for 150 kV Transformer Bay Comprising : set 2
- IED Merging unit (number of port as required to complete scope of work)
- IED Switchgear Control Unit (number of port as required to complete scope of work)
- Local mimic (BCM)
- Optical distribution frame
- Panel
Including, miscellaneous equipment, optical cables and cord, control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.

Name of Bidder : Rev.1


17 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
Note: price of all Merging Unit and Switchgear Control Unit needed on 150 kV side of TRANSFORMER BAY is
include in item 5.13
5.14 Fiber Optic Armoured (FA) Cable 16 12 cores (multi mode) to connect marshalling kiosk to ethernet switch. lot 1
5.15 LV power cable, control cable and accessories and necessary equipment (cable ladder, clamp, cable lug, terminal,
… etc) to complete the scope of works. lot 1

TOTAL PRICE ITEMS 5

Name of Bidder : Rev.1


18 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
6 150/20 KV POWER TRANSFORMERS AND AUXILIARIES
6.1 150/20 kV, 60 MVA 3-Phase power transformer complete with automatic voltage regulator relay, necessary
units 0
accessories and supporting structure for mounting 150 kV and 20 kV NCT.
6.2 Single phase neutral CT for 20 kV side Class x, 2000-4000/5 A complete with clamps for restricted earth fault
protection suitable for mounting outdoor on transformer tank or can be put inside the 20 kV neutral earthing resistor units 2
cubicle.
6.3 Single phase neutral CT for 20 kV side Class 10P20, 1000/5A complete with clamps for neutral earth fault
protection suitable for mounting outdoor on transformer tank or can be put inside the 20 kV neutral earthing resistor units 2
cubicle.
6.4 Single phase neutral CT for 150 kV side Class x 150-300/1A complete with clamps for restricted earth fault
units 2
protection suitable for mounting outdoor on transformer tank.
6.5 20 kV stainless steel neutral earthing resistor rated 12 Ohm, 10 seconds. sets 2
6.6 Transformer online monitoring system comprising : sets 2
- Tan Delta and capacitance for HV and LV Bushing and Winding
- Dissolve Gas Analysis For Transformer Oil
- Moisture/Water Content in Transformer Oil
- Partial discharge monitoring
- Oil Level Monitoring
- Oil Temperature & Winding Temperature
- OLTC monitoring
- IED Device, Including Panel
- Diagnostic Software
- Support Material

Name of Bidder : Rev.1


19 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
- Industrial Class Server, Rack Mounted
- Workstatuin & VDU
6.7 CPU & VDU for transformer monitoring system set 1
6.8 IED for transformer monitoring system, including panel set 1
6.9 Transformer Blast and Fire Prevention equipment, complete with accessories sets 2
TOTAL PRICE ITEM 6

Name of Bidder : Rev.1


20 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
7 20 kV SWITCHGEARS AND POWER CABLES
7.1 3 phase, 4 x single core of 630 SQMM ALU 20 kV XLPE power cable/phase between 150/20 kV power transformer
and 20 kV incoming cubicle, including cable support, 20 kV post insulators, metal bars, cable terminations and
accessories, cable rack etc.. to complete scope of work. (Cable length approximately 2 x 3 x 4 x 1 x 100 m' ) m 2400

7.2 3 phase, 1 x single core of 95 SQMM copper 20 kV XLPE power cable/phase between 20 kV auxiliary transformer
cubicle and the auxiliary transformer, including cable support, cable termination and accessories, cable rack, etc..
to complete scope of work sets 2

7.3 Power cable 20 kV XLPE Alluminium single core 1 x 630 sqmm (for Neutral Cable), between 150/20 kV Power
transfomer and NGR sets 2

7.4 20 kV Indoor Metalclad Switchgear Single-Busbar Scheme Comprising :


- Incoming Cubicle. set 2
- CB 25 kA, 24 kV/2000 A
- IED (Protection and control) Include in Bay Level Trafo
- KWh Meter (Include in Bay Level Trafo)
- IED Power Meter
- Incoming VT 24 KV, 3 FASA
- CT 20 KV, 3 Core for mesuring and protection (2000-4000/5 Class X; 5P20; 0.2)
- 3 VT 24 kV (Class 0,2 ; Class 3P)
- Trip Circuit Supervision
- Local switch, remote and supervisory
- LED for voltage indicator

Name of Bidder : Rev.1


21 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
- Megawatt and mvar meter 3 phase (Digital Power Meter) Class 0.5
- Test facility for metering and protection
- Busbar PT + Earthing Switch Cubicle. set 2
- Cubicle VT/LA 24 KV
- IED I/O, Power Meter
- 3 VT (Class 0.2; Class 3P)
- 3 Voltmeter
- Under Frequency Relay, Over Voltage and Under Voltage Relay
- Voltage Indicator for LED
- Test facility for metering and protection
- Auxiliary Transformer Cubicle. set 2
- LBS 25 kA, 24 kV/50 A
- IED I/O
- IED Power Meter
- Outgoing Feeder Cubicle set 16
- CB 25 kA, 24 kV/630 A
- IED (protection and control)
- KWh Meter
- IED Power Meter
- CT 20 KV, 2 CORE, for relay and measuring (Ratio : 300-600/5 A; Class : 5P20; Class : 0.5)
- Selector for Load Sheding and wiring to UFR
- Trip Circuit Supervision
- Local Switch, remote and supervisory
- Auto-Reclose and accessories

Name of Bidder : Rev.1


22 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
- LED for voltage indicator
- Megawatt and MVAR meter 3 phase (Digital Power Meter ) Class 0.5
- Metering and Protection for test facility

Name of Bidder : Rev.1


23 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
- Bus Section set 2
- Megawatt and MVAR meter 3 phase (Digital Power Meter ) Class 0.5
- Local Switch, remote and supervisory
- Auto-Reclose and accessories
- LED for voltage indicator
- Metering and Protection for test facility
- CB 25 kA, 24 kV/2000 A
- IED (Proteksi dan kontrol)
- IED Power Meter
- CT 20 KV, 2 Core, for relay and measuring (Ratio 2000-4000/5 A; Class 5P20; Class 0.5)
- Trip Circuit Supervision
- Megawatt and MVAR meter 3 phase (Digital Power Meter ) Class 0.5
- Local Switch, remote and supervisory
- Auto-Reclose and accessories
- LED for voltage indicator
- Metering and Protection for test facility
- Bus Riser Cubicle set 2
- 25 kA, 24 kV/2000 A
Miscellanious item including cable, accessories and necessary equipment to complete the scope of works.
7.5 Wall mounting panel Comprising : set 2
- IED Merging unit (number of port as required to complete scope of work) 1
- IED Switchgear Control Unit (number of port as required to complete scope of work) 1
- Optical distribution frame 1
- Panel and cooling system 1

Name of Bidder : Rev.1


24 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
Including, miscellaneous equipment, optical cables and cord, control cables, clamps, connectors, connection to
individual item of equipment, terminals, auxiliary relay, interior lamp, heater,.. etc to complete the scope of works.

Note: price of all Merging Unit and Switchgear Control Unit needed on 20 kV side of TRANSFORMER BAY is
include in item 7.5
7.6 3 phase, 4 x single core of 630 SQMM ALU 20 kV XLPE power cable/phase between bus-section cubicle and bus
riser cubicle, including cable terminations and accessories for connection between sets of 20 kV switchgear to set 1
complete the specified scope of work
7.7 20/0.4 kV 200 kVA 3-phase station auxiliary transformer complete with necessary accessories (vector group DYn 5) sets
2

TOTAL PRICE ITEMS 7

8 ENERGY METERS FOR ALL TRANSFORMER FEEDER BAYS sets 1


Including one energy meter panel, two ethernet switch for connection station level and miscellaneous equipment &
material, rack cabinet, clamps, connectors, compression terminal, connection to individual items of equipment, test
terminal, auxiliary relay, interior lamp, heater… etc.
2 kWH meter
2 IED Merging unit (for 20 kV Incoming)
Router
TOTAL PRICE ITEMS 8

Name of Bidder : Rev.1


25 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
9 SUBSTATION AUTOMATION HARDWARE Set 1
9.1 Redundant HMI-Operator Station consist of : lot 1
- 2 Sets Operator Work Station.
- 2 Sets VDU, Keyboard & Mouse, Industrial grade KVM extender
9.2 Redundant Station unit/Server lot 1
- 2 Sets CPU
9.3 IED I/O lot 1
9.4 Ethernet Switch for station level (manageable). set 2
9.5 Colour Laser Printer. set 1
9.6 GPS Time reference clock complete with Antenna (redundant) set 21
9.7 Gateway or Gateway Protocol set 1
9.8 Router set 1
9.9 Modem. set 4
9.10 Panel, Rack/Cubicle for IED I/O, Gate Way, GPS, Modem and Ethernet Switch, etc. set 1
9.11 Panel, Rack/Cubicle for Work Station, Server, etc. set 1
9.12 Furniture. lot 1
9.13 Engineering Tools, Test Equipment (including but not limited to injecting sampling value, testing, measuring) and set 1
Laptop for configurating, testing and operation maintenance including software (for IED, telecommunication and
SAS equipment).
9.14 Miscellaneous item, equipment and material including cables, patch cord, pig tail, telephone cable, connectors, lot 1
compression terminal, connection to individual items of equipment, all necessary work (dismantling, installation,
integration, adaptation, etc in partner substation and control center), etc, to complete the scope of works.

9.15 Redundant Box set 2


Name of Bidder : Rev.1
26 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
9.16 Common Service panel comprising: lot 1
- BCU
- 2 Ethernet switches
- Panel

TOTAL PRICE ITEMS 9


10 20 KV SUBSTATION AUTOMATION HARDWARE
10.1 1 Gareway or Gateway protokol Set 1
- Slave IEC 870-5-101, IEC 870-5-104 dan DNP3
- Master IEC 61850, IEC 870-5-101 dan DNP3
- DCC: 2 port serial, 1 port ethernet
10.2 2 Workstation Set 2
- CPU
- Keyboard & Mouse
- VDU LED 24"
- Active speaker.
- KVM extender
10.3 9 Common Lot 1
- IED I/O
10.4 ###Ethernet switch Set 4
Note : 10 cubicle 1 Ethernet
include :
- control cable and data cable
- I/O 1 system or modular
Name of Bidder : Rev.1
27 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
10.5 ###GPS Set 1
10.6 Wall mounted panel for housing Ethernet Switches set 1
TOTAL PRICE ITEMS 10

11 SUBSTATION AUTOMATION SOFTWARE


11.1 Operating System Lot 1
1.2 Basic SA Software and Licences Lot 1
- SCADA
- Historical data
- Statistik & pelaporan
- Update data base
11.3 HMI Software Lot 1
11.4 Communication Protocol with Control Center Consist of Lot 1
IEC 60870 - 5 - 101, IEC 60870 - 5 - 104 and existing
Proprietary protocol (if any)
11.5 SAS Software for operation, maintenance, diagnostic, simulation and configuration Lot 1
TOTAL PRICE ITEMS 11

Name of Bidder : Rev.1


28 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
12 INVERTER FOR SUBSTATION AUTOMATION
12.1 Inverter including AC Distribution Board set 1
(Capacity subject to calculation result)
TOTAL PRICE ITEM 12
13 TELECOMMUNICATION EQUIPMENT
SDH ADM MUX complete with terminal : (Should be identic with existing MUX in GI 150KV PLTU LONTAR and GI
13.1 Set 1
150KV Teluk Naga)
- STM-4 Line Interface Port 3
- 2 MB Interface Port 8
- DIU Data Interfacing Unit 64 Kbps (V.24 / RS 232) Port 4
- 64 Kbps G.703 Port 8
- VF 2/4 Wire E/M Interface Port 8
- VF/Subsc Interface Port 4
- VF /Exch.Interface Port 4
- Ethernet Interface + Router Port 2
13.2 PAX (16 trunks - 12 subscriber) complete with telephone set of each subsriber Set 1
13.3 MDF Main Distribution Frame Set 1
13.4 Panel, Rack/Cabinet for telecomunication equipment Lot 1
13.5 Digital Teleprotection Set 2
Note : 1 Sets to be installed in 150 kV Teluk Naga substation
Including integration and adaptation to eksisting system to complte the scope of works

Name of Bidder : Rev.1


29 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
13.6 Relocation, instalation and adaptation of eksisting Digital teleprotection equipment fom Teluk Naga substation to Lot 1
Teluk Naga 2 substation
Fiber Optic Armoured (FA) Cable 16 cores to connect OPGW (GB) to ODF in telecommunication room / substation
13.7 building, approx.200 m length
m 400
13.8 Optical Distribution Frame (ODF) (16 port) Set 4
13.9 Gantry Box for OPGW set 2
Miscellaneous item, equipment and material including cables, patch cord, pig tail, telephone cable, connectors,
13.1 compression terminal, connection to individual items of equipment to complete the scope of works. Lot 1

TOTAL PRICE ITEMS 13


14 RADIO TRANCEIVER (Low Band Frekuensi), Tower, dan Aksesoris
14.1 Radio Tranceiver (equal to Simoco) set 1
Frequancy : 66-68 Mhz (programmable)
Power Output max : 25 W
(programmable, microphone, external speaker, power cable)
14.2 Antena Diple SMD set 1
14.3 Cross mount antenna set 1
14.4 Coaxial RG-8 Cable m 40
14.5 Connector PL set 1
14.6 Connector BNC set 1
14.7 Stop contact & Steker set 1
14.8 Tower Radio SST 25 m
1. Foundation for 25 m Tower lot 1
Name of Bidder : Rev.1
30 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
2. 25 m SST Tower lot 1
3. Earthing system lot 1
4. 25 m Tower Instalation lot 1

TOTAL PRICE ITEM 14

Name of Bidder : Rev.1


31 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
15 150 kV SUBSTATION AUXILIARIES EQUIPMENT
15.1 110 V DC Battery suitable for supplying all 110 V DC load for 8 hours discharge. (Capacity of batetery is subject for
calculation for 10 bays and emergency lamp, and not less than 110V DC, 240 AH). set 2

15.2 Battery charger 3 step voltage dropper (Capacity of batetery charger is subject for calculation for 110V DC Battery,
and not less than 60 A ) complete with Panel Board metering and indicators. set 2

15.3 110V DC Switch Board complete, incl. ATS, 2 MCB's incoming,1 MCB section and 2 x 12 MCB outgoing MCB's
minimum for 10 bays and emergency lamp. set 2
15.4 48 V DC Battery suitable for supplying all 48 V DC load for 8 hours discharge. (Capacity of batetery is subject for
calculation for SCADATEL of substation complete and not less than 48V DC, 200 AH). set 1

15.5 Battery charger 3 step voltage dropper (Capacity of batetery charger is subject for calculation for 48V DC Battery,
and not less than 60 A ) complete with Panel Board metering and indicators. set 2
15.6 48V DC Switch Board complete, incl. ATS, outgoing MCB's minimum for 10 bays. set 1
15.7 400V AC Switch MCB's Distribution Board suitable for the 2 units station service transformer interchangeable to
supply the control building, yard lighting and HV equipment of minimum 10 bays, to complete the specified scope of set 1
work, including necessary spare MCB.
15.8 Miscellaneous material, LV power cable, control cable and accesorries and necessary equipment (cable ladder,
clamp, cable lug, terminal, etc.) to complete the specified scope of work. lot 1

TOTAL PRICE ITEMS 15

16 MISCELLANEOUS
16.1 Fault Recorder Equipment for 10 bays and Panel Set 1
Name of Bidder : Rev.1
32 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
- 2 Ethernet switch for process level
- Fault Recording equipment comprising necessary quantity of fault recordes equipped with oscillograph printer
to record the information of the 150 kV Bays
- The recorder shall be provided with date and line indicators and time synchronizing equipment clock via satellite

- Redundant Box set 1


- Desktop PC + VDU set 1
- Printer set 1
- GPS set 1
16.2 CCTV and Thermal and visual monitoring system compressed : set 1
- Thermal camera set 2
- 360 degree outdoor visual camera set 6
- 360 degree indoor visual camera set 4
- PC Server including operating system, antivirus, management and recording software set 1
- PC Client including operating system, antivirus, vewing and office work software set 1
Miscellaneous equipment and material required for completion Thermal and visual monitoring system including
Power supply, Cable Power, Cable Data, Cables, Swttch Hub, I/O Board For Alarm, Server Rack, UPS, Speakers, lot 1
etc scope of work
16.3 Miscellaneous equipment and material required for completion the scope of work. lot 1
TOTAL PRICE ITEMS 16
17 Training FOR ALL SCOPE OF PROJECT
TOTAL PRICE ITEMS 13.1 - 13.4
- Digital Substation Engineering and Design (TSS 3.3.1) : for 4 PLN engineers, 14 days Man - day 56
Name of Bidder : Rev.1
33 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 K
DAFTAR ISIAN 3 : DAFTAR HARGA
DAFTAR ISIAN 3.1 : DAFTAR KUANTITAS DAN HAR

GI 150 KV TELUK NAGA II

ITEM URAIAN PEKERJAAN SATUAN VOLUME

1 2 3 4
- Substation automation and telecommunication engineering (TSS 3.3.2 and TSS 5.17) : for 4 PLN engineers,
14 days Man - day 56

- Substation operation and maintenance (TSS 3.3.2) : for 8 PLN staff, 14 days Man - day 112
TOTAL PRICE ITEMS 17
18 TEST AND COMISSIONING FOR ALL SCOPE OF PROJECT lot 1
TOTAL PRICE ITEMS 18
As Built Drawing FOR ALL SCOPE OF PROJECT in hard and soft copy (3 sets hardcopy and 2 sets
19
softcopy) lot 1
consist of :
- Soil investigation Report
- Test Report for foundation and Switchgear equipment
- Test Commissioning report
- Design Calculation
- Design Drawing
- Construction Drawing
TOTAL PRICE ITEMS 19

GRAND TOTAL ITEMS 1 - 19

Name of Bidder : Rev.1


34 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

83,112,000 1,994,688,000 1,326,000 31,824,000 13,076,000 313,824,000


N.A
82,730,000 82,730,000 1,320,000 1,320,000 13,076,000 13,076,000
57,748,000 1,154,960,000 922,000 18,440,000 7,561,000 151,220,000
57,748,000 692,976,000 922,000 11,064,000 7,561,000 90,732,000

23,075,000 23,075,000 369,000 369,000 19,214,000 19,214,000

294,000 23,520,000 5,000 400,000 2,242,000 179,360,000

Name of Bidder : Rev.1


35 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

2,307,765,000 2,307,765,000 145,686,000 145,686,000 240,971,000 240,971,000

Name of Bidder : Rev.1


36 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

180,923,000 180,923,000 2,887,000 2,887,000 54,484,000 54,484,000

19,529,000 19,529,000 312,000 312,000 12,454,000 12,454,000

10,803,000 583,362,000 173,000 9,342,000 4,804,000 259,416,000

9,854,000 236,496,000 158,000 3,792,000 2,402,000 57,648,000


2,103,000 94,635,000 34,000 1,530,000 2,242,000 100,890,000

50,587,000 303,522,000 7,735,000 46,410,000 1,468,000 8,808,000

387,010,000 387,010,000 6,175,000 6,175,000 8,896,000 8,896,000

Name of Bidder : Rev.1


37 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

361,845,000 361,845,000 5,773,000 5,773,000 2,224,000 2,224,000

Included in Price of Item 2.1

10,803,000 129,636,000 173,000 2,076,000 4,804,000 57,648,000


9,854,000 59,124,000 158,000 948,000 2,402,000 14,412,000
2,103,000 25,236,000 34,000 408,000 2,242,000 26,904,000

122,519,000 490,076,000 1,955,000 7,820,000 3,203,000 12,812,000

10,845,000 43,380,000 174,000 696,000 890,000 3,560,000

497,394,000 994,788,000 7,936,000 15,872,000 3,736,000 7,472,000

84,855,000 509,130,000 13,320,000 79,920,000 1,602,000 9,612,000

154,894,000 309,788,000 2,472,000 4,944,000 3,736,000 7,472,000

Name of Bidder : Rev.1


38 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

50,587,000 303,522,000 7,735,000 46,410,000 1,468,000 8,808,000

34,740,000 208,440,000 5,113,000 30,678,000 934,000 5,604,000


113,533,000 113,533,000 1,812,000 1,812,000 2,562,000 2,562,000
919,644,000 1,839,288,000 14,672,000 29,344,000 3,203,000 6,406,000

793,103,000 1,586,206,000 12,654,000 25,308,000 712,000 1,424,000

Name of Bidder : Rev.1


39 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

274,876,000 274,876,000 4,386,000 4,386,000 Include in item 2.14 Include in item 2.14

774,020,000 774,020,000 12,349,000 12,349,000 26,686,000 26,686,000

Name of Bidder : Rev.1


40 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

361,845,000 361,845,000 5,773,000 5,773,000 2,224,000 2,224,000

Include in price of Item 3.1

10,803,000 64,818,000 173,000 1,038,000 4,804,000 28,824,000


9,854,000 29,562,000 158,000 474,000 2,402,000 7,206,000
2,103,000 12,618,000 34,000 204,000 2,242,000 13,452,000

122,519,000 245,038,000 1,955,000 3,910,000 3,203,000 6,406,000

10,845,000 54,225,000 174,000 870,000 890,000 4,450,000

497,394,000 497,394,000 7,936,000 7,936,000 3,736,000 3,736,000

965,406,000 2,896,218,000 15,402,000 46,206,000 1,602,000 4,806,000

3,307,000 3,307,000 53,000 53,000 1,468,000 1,468,000

Name of Bidder : Rev.1


41 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9
3,307,000 3,307,000 53,000 53,000 1,468,000 1,468,000

154,894,000 154,894,000 2,472,000 2,472,000 3,736,000 3,736,000

34,740,000 104,220,000 5,113,000 15,339,000 934,000 2,802,000


113,533,000 113,533,000 1,812,000 1,812,000 2,562,000 2,562,000
798,414,000 798,414,000 12,738,000 12,738,000 3,203,000 3,203,000

249,478,000 249,478,000 3,981,000 3,981,000 3,203,000 3,203,000

Name of Bidder : Rev.1


42 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

793,103,000 793,103,000 12,654,000 12,654,000 712,000 712,000

274,876,000 274,876,000 4,386,000 4,386,000 Include in item 3A.15 Include in item 3A.15

774,020,000 774,020,000 12,349,000 12,349,000 26,686,000 26,686,000

Name of Bidder : Rev.1


43 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

361,845,000 361,845,000 5,773,000 5,773,000 2,224,000 2,224,000

Include in price of Item 3.1

10,803,000 64,818,000 173,000 1,038,000 4,804,000 28,824,000


9,854,000 29,562,000 158,000 474,000 2,402,000 7,206,000
2,103,000 12,618,000 34,000 204,000 2,242,000 13,452,000

122,519,000 245,038,000 1,955,000 3,910,000 3,203,000 6,406,000

10,845,000 54,225,000 174,000 870,000 890,000 4,450,000

497,394,000 497,394,000 7,936,000 7,936,000 3,736,000 3,736,000

84,855,000 254,565,000 13,320,000 39,960,000 1,602,000 4,806,000

154,894,000 154,894,000 2,472,000 2,472,000 3,736,000 3,736,000

Name of Bidder : Rev.1


44 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

50,587,000 151,761,000 7,735,000 23,205,000 1,468,000 4,404,000

34,740,000 104,220,000 5,113,000 15,339,000 934,000 2,802,000


113,533,000 113,533,000 1,812,000 1,812,000 2,562,000 2,562,000
798,414,000 798,414,000 12,738,000 12,738,000 3,203,000 3,203,000

249,478,000 249,478,000 3,981,000 3,981,000 3,203,000 3,203,000

Name of Bidder : Rev.1


45 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

793,103,000 793,103,000 12,654,000 12,654,000 712,000 712,000

274,876,000 274,876,000 4,386,000 4,386,000 Include in item 3B.14 Include in item 3B.14

774,020,000 774,020,000 12,349,000 12,349,000 26,686,000 26,686,000

Name of Bidder : Rev.1


46 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

180,923,000 180,923,000 2,887,000 2,887,000 1,112,000 1,112,000


Include in Priceof Item 4.1
10,803,000 194,454,000 173,000 3,114,000 4,804,000 86,472,000

9,854,000 88,686,000 158,000 1,422,000 2,402,000 21,618,000


2,103,000 37,854,000 34,000 612,000 2,242,000 40,356,000
125,050,000 250,100,000 1,996,000 3,992,000 3,203,000 6,406,000

405,885,000 405,885,000 6,476,000 6,476,000 3,736,000 3,736,000

60,241,000 361,446,000 9,321,000 55,926,000 1,602,000 9,612,000

56,767,000 56,767,000 906,000 906,000 2,562,000 2,562,000


1,277,882,000 1,277,882,000 20,388,000 20,388,000 3,203,000 3,203,000

Name of Bidder : Rev.1


47 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

1,277,882,000 1,277,882,000 20,388,000 20,388,000 3,203,000 3,203,000

1,555,892,000 1,555,892,000 24,823,000 24,823,000 712,000 712,000

Name of Bidder : Rev.1


48 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

137,438,000 137,438,000 2,193,000 2,193,000 Include in item 4.10b Include in item 4.10b

387,010,000 387,010,000 6,175,000 6,175,000 13,343,000 13,343,000

Name of Bidder : Rev.1


49 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

80,151,000 80,151,000 1,279,000 1,279,000 2,224,000 2,224,000


Include in Price of Item 5.1
9,297,000 111,564,000 149,000 1,788,000 2,402,000 28,824,000
9,854,000 59,124,000 158,000 948,000 2,402,000 14,412,000
N.A

91,624,000 366,496,000 1,462,000 5,848,000 3,203,000 12,812,000

10,845,000 43,380,000 174,000 696,000 890,000 3,560,000

389,736,000 779,472,000 6,218,000 12,436,000 3,736,000 7,472,000

109,770,000 658,620,000 17,368,000 104,208,000 1,602,000 9,612,000

34,740,000 208,440,000 5,113,000 30,678,000 934,000 5,604,000

113,533,000 113,533,000 1,812,000 1,812,000 2,562,000 2,562,000


1,182,534,000 2,365,068,000 18,866,000 37,732,000 3,203,000 6,406,000
Name of Bidder : Rev.1
50 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

1,174,498,000 2,348,996,000 18,738,000 37,476,000 712,000 1,424,000

Name of Bidder : Rev.1


51 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

274,876,000 274,876,000 4,386,000 4,386,000 Include in item 5.12 Include in item 5.12

774,020,000 774,020,000 12,349,000 12,349,000 26,686,000 26,686,000

Name of Bidder : Rev.1


52 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

N.A

Include in Price of Item 6.5

Include in Price of Item 6.5

36,029,000 72,058,000 575,000 1,150,000 1,335,000 2,670,000


331,678,000 663,356,000 5,292,000 10,584,000 3,736,000 7,472,000
2,053,863,000 4,107,726,000 333,690,000 667,380,000 28,465,000 56,930,000

Name of Bidder : Rev.1


53 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

Include
Include
2,172,589,000 4,345,178,000 34,662,000 69,324,000 65,450,000 130,900,000

Name of Bidder : Rev.1


54 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

261,000 626,400,000 5,000 12,000,000 61,000 146,400,000

38,599,000 77,198,000 616,000 1,232,000 6,085,000 12,170,000

8,806,000 17,612,000 141,000 282,000 726,000 1,452,000

465,847,000 931,694,000 7,433,000 14,866,000 2,224,000 4,448,000

Name of Bidder : Rev.1


55 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

220,665,000 441,330,000 3,521,000 7,042,000 2,224,000 4,448,000

196,146,000 392,292,000 3,130,000 6,260,000 2,224,000 4,448,000

306,479,000 4,903,664,000 4,890,000 78,240,000 2,224,000 35,584,000

Name of Bidder : Rev.1


56 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

Name of Bidder : Rev.1


57 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9
343,256,000 686,512,000 5,477,000 10,954,000 2,224,000 4,448,000

174,693,000 349,386,000 2,788,000 5,576,000 2,224,000 4,448,000

Include in item 10.6 Include in item 10.6 Include in item 10.6 Include in item 10.6 Include in item 10.6 Include in item 10.6

Name of Bidder : Rev.1


58 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

134,341,000 134,341,000 2,144,000 2,144,000 17,542,000 17,542,000

92,625,000 185,250,000 1,478,000 2,956,000 4,893,000 9,786,000

203,166,000 203,166,000 3,242,000 3,242,000 3,825,000 3,825,000

Name of Bidder : Rev.1


59 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9
3,867,478,000 3,867,478,000 61,702,000 61,702,000 22,238,000 22,238,000
Included

Included

Included
Included
Included
Included
Included
Included
Included
Included
Included
Included

Included

Include
Name of Bidder : Rev.1
60 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9
Include

Included

Included

Included

Included

Name of Bidder : Rev.1


61 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9
Included
Included

Included
Included

Included
Included

Included

Name of Bidder : Rev.1


62 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

71,139,000 71,139,000 1,135,000 1,135,000 1,668,000 1,668,000

580,245,000 580,245,000 9,258,000 9,258,000 12,009,000 12,009,000

Included
Included
Included
Included
Included
Included
Included
Included
440,972,000 440,972,000 7,036,000 7,036,000 Included
121,677,000 121,677,000 1,942,000 1,942,000 Included
433,066,000 433,066,000 6,910,000 6,910,000 Included

145,662,000 291,324,000 2,324,000 4,648,000 Included

Name of Bidder : Rev.1


63 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9
Included

766,000 306,400,000 13,000 5,200,000 Included


24,979,000 99,916,000 399,000 1,596,000 Included
33,447,000 66,894,000 534,000 1,068,000 Included

184,921,000 184,921,000 2,951,000 2,951,000 Included

199,438,000 199,438,000 3,182,000 3,182,000 12,009,000 12,009,000

Included
Included
Included
Included
Included
Included

136,780,000 136,780,000 2,183,000 2,183,000 47,675,000 47,675,000


Name of Bidder : Rev.1
64 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9
Included
Included
Included

Name of Bidder : Rev.1


65 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

550,041,000 1,100,082,000 8,776,000 17,552,000 8,451,000 16,902,000

171,086,000 342,172,000 2,730,000 5,460,000 1,668,000 3,336,000

423,281,000 846,562,000 6,753,000 13,506,000 3,892,000 7,784,000

149,619,000 149,619,000 2,387,000 2,387,000 7,228,000 7,228,000

136,150,000 272,300,000 2,173,000 4,346,000 1,668,000 3,336,000

267,658,000 267,658,000 4,271,000 4,271,000 2,780,000 2,780,000

689,235,000 689,235,000 10,996,000 10,996,000 55,595,000 55,595,000

388,854,000 388,854,000 6,204,000 6,204,000 16,012,000 16,012,000

855,624,000 855,624,000 13,651,000 13,651,000 8,896,000 8,896,000


Name of Bidder : Rev.1
66 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

Included in item 16.1


Included in item 16.1
Included in item 16.1
Included in item 16.1
824,590,000 824,590,000 13,156,000 13,156,000 26,686,000 26,686,000
Included in item 16.2
Included in item 16.2
Included in item 16.2
Included in item 16.2
Included in item 16.2

Included in item 16.2

Include in item 16.2

0 0 0 - 3,406,000 190,736,000
Name of Bidder : Rev.1
67 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) ELEKTROMEKANIK GIS 150 KV

HARGA PENGADAAN SAMPAI SITE HARGA JASA PEMASANGAN


MATERIAL TRANSPORTASI
SATUAN TOTAL SATUAN TOTAL SATUAN TOTAL
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
5 6 = 4x5 7 8 = 4x7 9 10 = 4x9

0 0 0 - 3,406,000 190,736,000

0 0 0 - 3,406,000 381,472,000

0 0 0 - 1,224,550,000 1,224,550,000

Included

Name of Bidder : Rev.1


68 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

2,340,336,000

97,126,000
1,324,620,000
794,772,000
4,556,854,000

42,658,000

203,280,000

Name of Bidder : Rev.1


69 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10
245,938,000

2,694,422,000

2,694,422,000

Name of Bidder : Rev.1


70 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

238,294,000

32,295,000

852,120,000

297,936,000
197,055,000

358,740,000

402,081,000

2,378,521,000
9,875,735,000

Name of Bidder : Rev.1


71 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

369,842,000

189,360,000
74,484,000
52,548,000

510,708,000

47,636,000

1,018,132,000

598,662,000

322,204,000

Name of Bidder : Rev.1


72 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

358,740,000

244,722,000
117,907,000
1,875,038,000

1,612,938,000

Name of Bidder : Rev.1


73 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

279,262,000

813,055,000

8,485,238,000

Name of Bidder : Rev.1


74 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

369,842,000

94,680,000
37,242,000
26,274,000

255,354,000

59,545,000

509,066,000

2,947,230,000

4,828,000

Name of Bidder : Rev.1


75 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10
4,828,000

161,102,000

122,361,000
117,907,000
814,355,000

256,662,000

Name of Bidder : Rev.1


76 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

806,469,000

279,262,000

813,055,000

Name of Bidder : Rev.1


77 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

369,842,000

94,680,000
37,242,000
26,274,000

255,354,000

59,545,000

509,066,000

299,331,000

161,102,000

Name of Bidder : Rev.1


78 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

179,370,000

122,361,000
117,907,000
814,355,000

256,662,000

Name of Bidder : Rev.1


79 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

806,469,000

279,262,000

813,055,000

5,201,877,000

Name of Bidder : Rev.1


80 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

184,922,000

284,040,000

111,726,000
78,822,000
260,498,000

416,097,000

426,984,000

60,235,000
1,301,473,000

Name of Bidder : Rev.1


81 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

1,301,473,000

1,581,427,000

Name of Bidder : Rev.1


82 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

139,631,000

406,528,000

6,553,856,000

Name of Bidder : Rev.1


83 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

83,654,000

142,176,000
74,484,000

385,156,000

47,636,000

799,380,000

772,440,000

244,722,000

117,907,000
2,409,206,000
Name of Bidder : Rev.1
84 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

2,387,896,000

Name of Bidder : Rev.1


85 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

279,262,000

813,055,000

8,556,974,000

Name of Bidder : Rev.1


86 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

75,878,000
681,412,000
4,832,036,000

Name of Bidder : Rev.1


87 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

4,545,402,000
10,134,728,000

Name of Bidder : Rev.1


88 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

784,800,000

90,600,000

19,346,000

951,008,000

Name of Bidder : Rev.1


89 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

452,820,000

403,000,000

5,017,488,000

Name of Bidder : Rev.1


90 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

Name of Bidder : Rev.1


91 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10
701,914,000

359,410,000

Name of Bidder : Rev.1


92 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

154,027,000

197,992,000

9,132,405,000

210,233,000

210,233,000

Name of Bidder : Rev.1


93 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10
3,951,418,000

Name of Bidder : Rev.1


94 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

3,951,418,000

Name of Bidder : Rev.1


95 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

Name of Bidder : Rev.1


96 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

73,942,000

73,942,000

601,512,000

448,008,000
123,619,000
439,976,000

295,972,000

Name of Bidder : Rev.1


97 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

311,600,000
101,512,000
67,962,000

187,872,000

2,578,033,000

214,629,000

186,638,000
Name of Bidder : Rev.1
98 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

401,267,000

Name of Bidder : Rev.1


99 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

1,134,536,000

350,968,000

867,852,000

159,234,000

279,982,000

274,709,000

755,826,000

411,070,000

4,234,177,000

878,171,000
Name of Bidder : Rev.1
100 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

864,432,000

1,742,603,000

190,736,000
Name of Bidder : Rev.1
101 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
KV

GRAND
TOTAL

( Rp. )
11 = 6+8+10

190,736,000

381,472,000
762,944,000
1,224,550,000
1,224,550,000

73,119,980,000

Name of Bidder : Rev.1


102 of 237
Signature of Bidder :
__________________________________________________________________________________________________________________________
_____________________________________________________________
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BO
DAFTAR ISIAN 3.2 : DAFTAR HARGA DAN KUANTITAS (BOQ) CIVIL W
BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 2

GI 150 kV Teluk Naga II

NO DESCRIPTION

I Control Building SAS include corridor

1 Foundation work
Excavation of soil
Backfill filling (compacted)
Soil disposal
Import Soil Fill (compacted)
Compacted sand layer (t = 10 cm)
Lean concrete (t = 10 cm)
Foundation work, concrete K 300, Fe : 150 kg/m3, Formwork
Sloof work, concrete K 300, Fe : 150 kg/m3, Formwork
Stone masonry ad 1 pc : 3 sand

2 Structure and wall work


Column work, concrete K 300, Fe : 180 kg/m3, Formwork
Beam work, concrete K 300, Fe : 180 kg/m3, Formwork
Practical work, concrete K 225, Fe :120 kg/m3, Formwork
Cannopy work, concrete K 300, Fe : 125 kg/m3, Formwork
A half brick wall ad 1 pc : 3 sand

3 Roof Work
Spandex metal sheet complete with accessories
Steel Structure frame, complete with bolt & galvanizing
Purlin complete with plat simpul and steel painting
Wind bracing and tie rod
Nok Spandek Metal
Thermal Insulation Glasswool, aluminium foil (single sided) with 2 (two) layer and roof
mesh
Listplank Metal
Aluminium flashing t=0.50 mm including filler in both side
Water proofing membran type t= 3 mm and mortar screed
PVC pipe dia 4 inc include elbows

Name of Bidder : Rev.1


Signature of Bidder : 103 of 237
____________________________________________________________________________________________________
BUKU I
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BO
DAFTAR ISIAN 3.2 : DAFTAR HARGA DAN KUANTITAS (BOQ) CIVIL W
BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 2

GI 150 kV Teluk Naga II

NO DESCRIPTION

4 Floor Work
Slab floor work, concrete K 300, Fe : 150 kg/m3, Formwork
Rabat Concrete K 225
Ceramic floor tiles 300 x 300 mm (Control, PLC, terace, lobby, egineer room, AC/DC,
Pantry, Corridor, Battery room)
Ceramic floor tiles 200 x 200 mm - anti-slip (Toilet)
Ceramic wall tiles 200 x 250 mm (Toilet & Battery Room)
Plint Ceramic 150 x 300 mm (control room, PLC, terace, lobby, egineer room, AC/DC,
Pantry)
Stepnosing 100 x 300 mm (terrace)

5 Plastering & Grouting


Plaster ad 1 pc : 3 sand
Acian

6 Doors and windows


Door complete with frame and accessories:
- Type P1
- Type P2
- Type P3
- Type P4 (Fibre door complete with frame and accessories)
Glass window complete with aluminium frame and accessories:
- Type J1
- Type J2
Glass ventilations complete with aluminium frame and accessories:
- Type V1

Name of Bidder : Rev.1


Signature of Bidder : 104 of 237
____________________________________________________________________________________________________
BUKU I
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BO
DAFTAR ISIAN 3.2 : DAFTAR HARGA DAN KUANTITAS (BOQ) CIVIL W
BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 2

GI 150 kV Teluk Naga II

NO DESCRIPTION

7 Ceiling work
Ceilling Gypsum GRC, hollow frame
Ceiling Accoustic, alluminium frame

8 Piping & Sanitary work


Closet Duduk Complete
Wash Sink Complete (kitchen)
Wastafel Complete
Urinoir Complete
Tempat Tisu Roll
Tempat Sabun
Gantungan Pakaian (multi hook)
Installation of water supply pipe PVC dia 1/2 inc and fittings (include for all pipes,
bends, tees, albows, reducers, adaptors, taps and connections to fittings, appliances,
etc.)
Installation of water waste pipe PVC dia 3 inc and fittings (include for all pipes, bends,
tees, albows, reducers, adaptors, metal grill and connections to fittings, appliances,
etc.)
Water tank and steel structures tower ( cap : 2 m3 ) and installation of pipe
Deepwell including submersible water pump 150 lt/m capacity and accessories
Septictank cap 3 m3 included infiltrate cap 2 m3 complete with PVC, palm fibre and
sand stone
Submersible Sewage Pump
Open Drainage (brick) 30/40 cm2 for control building
PVC AW diameter 6''

9 Cable Duct Indoor Include Metal Works


Cable Duct Type I
Cable Duct Type II
Cable Duct Type III

10 Painting Works
Wall and Ceiling interior painting
Wall and Ceiling exterior painting
Steel Painting

Name of Bidder : Rev.1


Signature of Bidder : 105 of 237
____________________________________________________________________________________________________
BUKU I
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BO
DAFTAR ISIAN 3.2 : DAFTAR HARGA DAN KUANTITAS (BOQ) CIVIL W
BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 2

GI 150 kV Teluk Naga II

NO DESCRIPTION

11 Electrical
Light type Led 9 watt including installation wiring and switch
Stop contact including installation wiring
Emergency lighting (30 W) including installation
Panel Box MCB complete with R.S.T lamp indicator and contactor grounding

12 Air Conditioner and Exhaust fan


AC split 2 PK
AC split 1 PK
Exhaust fan wall 60 W/220 Volt (16") industrial
Exhaust fan ceiling 40 W/220 Volt (10") very low noice
13 Lightning Protection

Arder/ground rod icluded pipa and cable BC 25 mm2 and all accessories clamps steel
plate, material support and pole, grounding system for control building

14 Fire Alarm
Alarm bell 6" (150 mm) diameter including installation wiring
Smoke detector including installation wiring
Fixed and rate of rise temperature detector including installation wiring
MCFA (Master Control Fire Alrm) Including indication lamp, batttery rectifier and all
accessories

Name of Bidder : Rev.1


Signature of Bidder : 106 of 237
____________________________________________________________________________________________________
BUKU I
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BO
DAFTAR ISIAN 3.2 : DAFTAR HARGA DAN KUANTITAS (BOQ) CIVIL W
BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 2

GI 150 kV Teluk Naga II

NO DESCRIPTION

15 Fire Fighting Equipment


Portable fire extinghuister type dry chemical ( 5 kg hallon )
Mobile unit powder fire extinghuister ( 50 kg hallon )
Hydrant and accessories included installation of pipe, Fortable Pump for Fire Hidrant
complete = 1 unit, Hydrant Box Type C (Out Door) = 3 unit, Gate valve dia 2 1/2" kitz +
Control box ( for Pipa Distribution Hidrant ) = 3 pieces
Submersible sewage pump
Underground Water Tank (cap : 24 m3) include jet pump

16 Sundries
Flagpole Stainless Steel ø 3" with acc + Foundation

Name plate "GI 150 kV TELUK NAGA II" work complete with stainless steel pipe ø 2",
stainless steel plate 1.2 mm, PLN's logo & block letter and foundation of column

Key box

TOTAL Item 1-16 for Control Building SAS

II Control Building MV Cell


1 Foundation work
Excavation of soil
Backfill filling (compacted)
Soil disposal
Import Soil Fill (compacted)
Compacted sand layer (t = 10 cm)
Lean concrete (t = 10 cm)
Foundation work, concrete K 300, Fe : 150 kg/m3, Formwork
Sloof work, concrete K 300, Fe : 150 kg/m3, Formwork
Stone masonry ad 1 pc : 3 sand

2 Structure and wall work


Column work, concrete K 300, Fe : 180 kg/m3, Formwork
Beam work, concrete K 300, Fe : 180 kg/m3, Formwork
Practical work, concrete K 225, Fe :120 kg/m3, Formwork
Cannopy work, concrete K 300, Fe : 125 kg/m3, Formwork
Name of Bidder : Rev.1
Signature of Bidder : 107 of 237
____________________________________________________________________________________________________
BUKU I
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BO
DAFTAR ISIAN 3.2 : DAFTAR HARGA DAN KUANTITAS (BOQ) CIVIL W
BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 2

GI 150 kV Teluk Naga II

NO DESCRIPTION

A half brick wall ad 1 pc : 3 sand

3 Roof Work
Spandex metal sheet complete with accessories
Steel Structure frame, complete with bolt & galvanizing
Purlin complete with plat simpul and steel painting
Wind bracing and tie rod
Nok Spandek Metal
Thermal Insulation Glasswool, aluminium foil (single sided) with 2 (two) layer and roof
mesh
Listplank Metal
Aluminium flashing t=0.50 mm including filler in both side
Water proofing membran type t= 3 mm and mortar screed
PVC pipe dia 4 inc include elbows

4 Floor Work
Slab floor work, concrete K 300, Fe : 150 kg/m3, Formwork
Rabat Concrete K 225
Floor hardener finished

5 Plastering & Grouting


Plaster ad 1 pc : 3 sand
Acian

Name of Bidder : Rev.1


Signature of Bidder : 108 of 237
____________________________________________________________________________________________________
BUKU I
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BO
DAFTAR ISIAN 3.2 : DAFTAR HARGA DAN KUANTITAS (BOQ) CIVIL W
BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 2

GI 150 kV Teluk Naga II

NO DESCRIPTION

6 Doors and windows


Door complete with frame and accessories:
- Type P1
- Type P5 Steel folding door complete with frame, accessories and steel
painting (3 x 2.70 m)
Ventilations complete with frame and accessories:
- Type V2

7 Ceiling work
Ceilling Gypsum GRC, hollow frame
Ceiling Accoustic, alluminium frame

8 Sanitary work
Open Drainage (brick) 30/40 cm2 for control building
PVC AW diameter 6'

9 Cable Duct Incd Metal Works


Cable Duct Type I
Cable Duct Type II
Cable Duct Type III

10 Painting Works
Wall and Ceiling interior painting
Wall and Ceiling exterior painting
Steel Painting

11 Electrical
Light type Led 9 watt including installation wiring and switch
Stop contact including installation wiring
Emergency lighting (30w) including installation
Panel Box MCB complete with R.S.T lamp indicator and contactor grounding

12 Air Conditioner and Exhoust fan


Exhaus fan wall 60 W/220 Volt (16") industrial

13 Lightning Protection

Name of Bidder : Rev.1


Signature of Bidder : 109 of 237
____________________________________________________________________________________________________
BUKU I
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BO
DAFTAR ISIAN 3.2 : DAFTAR HARGA DAN KUANTITAS (BOQ) CIVIL W
BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 2

GI 150 kV Teluk Naga II

NO DESCRIPTION

Arder/ground rod icluded pipa and cable BC 25 mm2 and all accessories clamps steel
plate, material support and pole, grounding system for control building

14 Fire Alarm
Alarm bell 6" (150 mm) diameter including installation wiring
Smoke detector including installation wiring
Fixed and rate of rise temperature detector including installation wiring
MCFA (Master Control Fire Alrm) Including indication lamp, batttery rectifier and all
accessories

15 Fire Fighting Equipment


Portable fire extinghuister type dry chemical ( 5 kg hallon )
Mobile unit powder fire extinghuister ( 50 kg hallon )

TOTAL Item 1-15 for Control Building MV Cell

Total Price for 150 KV CONTROL BUILDING SAS & 20 KV MV CELL BUILDING

Name of Bidder : Rev.1


Signature of Bidder : 110 of 237
____________________________________________________________________________________________________
BUKU I
ANGUNAN GI 150 KV TELUK NAGA II
3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
R HARGA DAN KUANTITAS (BOQ) CIVIL WORK GI 150 KV
NTROL BUILDING AND SAS & MV CELL 20KV

TOTAL
UNIT PRICE
UNIT QTY PRICE LOCAL

(RUPIAH) (RUPIAH)

m3 265 14,983 3,970,593


m3 106 51,080 5,414,445
m3 159 61,296 9,746,000
m 3
261 141,929 37,043,542
m 3
34 553,635 18,823,606
m3 34 1,503,309 51,112,517
m 3
25 6,216,498 155,412,438
m 3
17 6,216,498 105,680,458
m 3
81 1,291,588 104,618,644

m3 19 6,778,112 128,784,134
m3 18 6,778,112 122,006,022
m 3
5 5,193,021 25,965,105
m3 4 5,748,485 22,993,941
m2 507 214,641 108,822,840

m2 514 291,762 149,965,466


kg 4,240 34,747 147,328,801
kg 3,016 34,747 104,798,034
kg 207 34,747 7,192,703
m' 58 555,600 32,224,781

m2 514 239,557 123,132,209

m' 135 89,077 12,025,461


m' 135 102,159 13,791,510
m' 12 159,857 1,918,283
m' 4 93,510 374,039

Name of Bidder : Rev.1


Signature of Bidder : 111 of 237
____________________________________________________________________________________________________
BUKU I
ANGUNAN GI 150 KV TELUK NAGA II
3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
R HARGA DAN KUANTITAS (BOQ) CIVIL WORK GI 150 KV
NTROL BUILDING AND SAS & MV CELL 20KV

TOTAL
UNIT PRICE
UNIT QTY PRICE LOCAL

(RUPIAH) (RUPIAH)

m3 55 6,216,498 341,907,364
m3 10 1,630,995 16,309,951

m2 225 293,878 66,122,629

m2 4 300,436 1,201,742
m2 78 278,812 21,747,370

m' 124 334,280 41,450,763

m' 22 273,631 6,019,890

m2 1,014 119,790 121,466,913


m 2
936 54,328 50,851,001

unit 5 11,350,583 56,752,915


unit - -
unit 2 6,006,969 12,013,938
unit 1 4,827,029 4,827,029

unit 13 10,845,916 140,996,907


unit 2 3,754,356 7,508,711

unit 2 1,072,673 2,145,346

Name of Bidder : Rev.1


Signature of Bidder : 112 of 237
____________________________________________________________________________________________________
BUKU I
ANGUNAN GI 150 KV TELUK NAGA II
3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
R HARGA DAN KUANTITAS (BOQ) CIVIL WORK GI 150 KV
NTROL BUILDING AND SAS & MV CELL 20KV

TOTAL
UNIT PRICE
UNIT QTY PRICE LOCAL

(RUPIAH) (RUPIAH)

m2 92 365,319 33,609,365
m2 242 501,327 121,321,210

No 1 11,418,579 11,418,579
No 1 945,314 945,314
No 2 1,818,436 3,636,872
No - -
No 1 340,531 340,531
No 1 340,531 340,531
No 2 340,531 681,062

ls 1 13,822,839 13,822,839

ls 1 16,723,347 16,723,347

unit 1 21,227,226 21,227,226


set 1 11,237,867 11,237,867

unit 1 21,331,490 21,331,490

unit 2 4,767,436 9,534,871


m' 96 535,883 51,444,730
m' 8 207,520 1,660,157

m' 30 4,591,777 137,753,314


m' 29 2,811,391 81,530,338
m' 18 1,402,184 25,239,309

m2 795 62,994 50,080,365


m 2
634 84,533 53,594,203
m 2
24 111,529 2,676,705

Name of Bidder : Rev.1


Signature of Bidder : 113 of 237
____________________________________________________________________________________________________
BUKU I
ANGUNAN GI 150 KV TELUK NAGA II
3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
R HARGA DAN KUANTITAS (BOQ) CIVIL WORK GI 150 KV
NTROL BUILDING AND SAS & MV CELL 20KV

TOTAL
UNIT PRICE
UNIT QTY PRICE LOCAL

(RUPIAH) (RUPIAH)

Sets 99 704,899 69,785,041


Sets 29 442,690 12,838,023
Sets 10 1,089,700 10,896,996
Set 1 6,129,560 6,129,560

Sets 8 19,069,742 152,557,938


Sets 3 10,215,933 30,647,800
Sets 2 12,940,182 25,880,364
Sets 2 4,767,436 9,534,871

Lot 1 55,662,254 55,662,254

Set 2 4,767,436 9,534,871


Sets 11 3,405,311 37,458,422
Sets 11 3,405,311 37,458,422

Set 1 16,345,493 16,345,493

Name of Bidder : Rev.1


Signature of Bidder : 114 of 237
____________________________________________________________________________________________________
BUKU I
ANGUNAN GI 150 KV TELUK NAGA II
3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
R HARGA DAN KUANTITAS (BOQ) CIVIL WORK GI 150 KV
NTROL BUILDING AND SAS & MV CELL 20KV

TOTAL
UNIT PRICE
UNIT QTY PRICE LOCAL

(RUPIAH) (RUPIAH)

Sets 4 9,943,508 39,774,034


Set 1 47,674,356 47,674,356

Lot 1 586,769,386 586,769,386

unit 2 4,767,436 9,534,871


unit 1 174,968,364 174,968,364

Set 1 2,043,187 2,043,187

Set 1 10,215,933 10,215,933

Set 1 817,275 817,275

-16 for Control Building SAS 4,401,145,727

m3 140 14,983 2,097,672


m3 56 51,080 2,860,461
m 3
84 61,296 5,148,830
m 3
199 141,929 28,243,927
m3 30 553,635 16,609,064
m3 30 1,503,309 45,099,280
m 3
24 6,216,498 149,195,941
m 3
5 6,216,498 31,082,488
m3 48 1,291,588 61,996,233

m3 17 6,778,112 115,227,910
m3 6 6,778,112 40,668,674
m3 2 5,193,021 10,386,042
m 3
2 5,748,485 11,496,970
Name of Bidder : Rev.1
Signature of Bidder : 115 of 237
____________________________________________________________________________________________________
BUKU I
ANGUNAN GI 150 KV TELUK NAGA II
3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
R HARGA DAN KUANTITAS (BOQ) CIVIL WORK GI 150 KV
NTROL BUILDING AND SAS & MV CELL 20KV

TOTAL
UNIT PRICE
UNIT QTY PRICE LOCAL

(RUPIAH) (RUPIAH)
m 2
310 214,641 66,538,620

m2 395 291,762 115,245,835


kg 3,331 34,747 115,743,452
kg 2,404 34,747 83,532,650
kg 180 34,747 6,254,525
m' 46 555,600 25,557,585

m2 395 239,557 94,624,946

m' 106 89,077 9,442,214


m' 106 102,159 10,828,889
m' 11 159,857 1,758,426
m' 4 93,510 374,039

m3 42 6,216,498 261,092,896
m3 9 1,630,995 14,678,956
m2 218 254,062 55,385,535
-

m2 568 119,790 68,040,638


m2 568 54,328 30,858,300

Name of Bidder : Rev.1


Signature of Bidder : 116 of 237
____________________________________________________________________________________________________
BUKU I
ANGUNAN GI 150 KV TELUK NAGA II
3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
R HARGA DAN KUANTITAS (BOQ) CIVIL WORK GI 150 KV
NTROL BUILDING AND SAS & MV CELL 20KV

TOTAL
UNIT PRICE
UNIT QTY PRICE LOCAL

(RUPIAH) (RUPIAH)

unit 1 11,350,583 11,350,583

unit 1 16,090,095 16,090,095

unit 16 3,098,833 49,581,330

m2 80 365,319 29,225,535
m 2
210 501,327 105,278,736

m' 80 535,883 42,870,608


m' 5 207,520 1,037,598

m' 6 4,591,777 27,550,663


m' 46 2,811,391 129,323,984
m' 14 1,402,184 19,630,574

m2 494 62,994 31,119,120


m 2
364 84,533 30,770,173
m 2
26 111,529 2,899,764

Sets 82 704,899 57,801,751


Sets 4 442,690 1,770,762
Sets 6 1,089,700 6,538,197
Set 1 6,129,560 6,129,560

Sets 16 12,940,182 207,042,916

Name of Bidder : Rev.1


Signature of Bidder : 117 of 237
____________________________________________________________________________________________________
BUKU I
ANGUNAN GI 150 KV TELUK NAGA II
3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
R HARGA DAN KUANTITAS (BOQ) CIVIL WORK GI 150 KV
NTROL BUILDING AND SAS & MV CELL 20KV

TOTAL
UNIT PRICE
UNIT QTY PRICE LOCAL

(RUPIAH) (RUPIAH)

Lot 1 55,662,254 55,662,254

No 2 4,767,436 9,534,871
No 6 3,405,311 20,431,867
No 6 3,405,311 20,431,867

No 1 16,345,493 16,345,493

No 2 9,943,508 19,887,017
No 1 47,674,356 47,674,356

5 for Control Building MV Cell 2,446,050,671

L BUILDING SAS & 20 KV MV CELL BUILDING 6,847,196,397

Name of Bidder : Rev.1


Signature of Bidder : 118 of 237
____________________________________________________________________________________________________
BUKU I
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.2 : DAFTAR HARGA DAN KUANTITAS (BOQ) CIVIL WORK
BILL NO 2 : SWITCHYARD FOR CIVIL WORKS

GI 150 kV Teluk Naga II

NO DESCRIPTION UNIT QTY

1 2 3 4

I Preparatory work for Control Building , MV Cell and Switchyard

1 Site Clearing & Grubbing (Pengupasan t=20 cm) m2 19000


2 Topographical Survey Ls 1
3 Bowplank m' 463
4 Direksi Keet (4m x 6m) m2
24
5 Site Storage (4m x 15 m) m2 60
6 Soil Investigation for control building :
Sondir pcs 6
Boring and Test Lab. pcs 3
Laporan Soil Investigation pcs 3
7 Design (calculation, detail design and drawing must be economical design) Ls 1
8 Exit permit, IMB and coordination to instansion Pemda Ls 1

Total Item I ( 1 - 8 )

II Site Works

1 Earthworks :
Excavation of Soil m3 3565
Soil Disposal m3
2384
Backfill filling (compacted) m3 1181
2 Embankment Construction :
Import Soil Fill (include compaction per layer of 20 cm) m3 40133
Test Sand Cone (per-layer of 20 cm) pcs 90
Retaining wall (stone masonry) m3 1458
3 Road Works :
Compacted Subgrade m2 3098
Compacted Sandgravel / sirtu (t=20cm) m2 3098
Lean Concrete (t =10cm) m2 3098
Reinforced Concrete Road K 300 m2
3098
4 Kerbs :

Name of Bidder :
Signature of Bidder :
Rev.1
_________________________________________________________________________________________________
119 of 237
___________________________
BUKU I
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.2 : DAFTAR HARGA DAN KUANTITAS (BOQ) CIVIL WORK
BILL NO 2 : SWITCHYARD FOR CIVIL WORKS

GI 150 kV Teluk Naga II

NO DESCRIPTION UNIT QTY

1 2 3 4
Concrete Kerbs for switchyard (30x20 cm) m' 234
Concrete Kerbs for road and control building (40x25 cm) m' 673
5 Fence :
BRC 1.90 m height m' 28
BRC 1.50 m height m' 312
Brick wall 2.40 m + barbed wire 0.60 m m' 534
6 Gate :
Single gate BRC 1.50 m height, 1.1 m width Sets 4
Double gate BRC 1.50 m height, 3 m width Set 1
Sliding gate 2.4 m height, 6 m width Set 1
7 Landscaping (sodding grass) m 2
586
8 Gravelling :
Compacted Gravel (dia 3 - 5 cm); thickness = 20 cm m3 1346
Sand layer below gravel (compacted sand); thickness = 5 cm m 3
337

Name of Bidder :
Signature of Bidder :
Rev.1
_________________________________________________________________________________________________
120 of 237
___________________________
BUKU I
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.2 : DAFTAR HARGA DAN KUANTITAS (BOQ) CIVIL WORK
BILL NO 2 : SWITCHYARD FOR CIVIL WORKS

GI 150 kV Teluk Naga II

NO DESCRIPTION UNIT QTY

1 2 3 4
9 Cable trench for 150 kV (incld cover, galvanized L 50.50.5) :
Type 1 (Large, ±120 cm width ) m' 137
Type 2 (Medium, ± 80 cm width ) m' 94
Type 3 (Small, ± 60 cm width ) m' 177
Type 4 (Crossing road, ± 120 cm width) m' 12
10 Drainage :
Open Drainage stone masonry (40 x 70 cm) m' 540
Open Drainage brick (30 x 40 cm) m' 336
Sub soil Drainage dia 30 cm including gravel and Palm fibre m' 1056
Control Box Brick with cover (60 x 60 cm, height 70 cm) Unit 14
11 Post security (3,5m x 3,5 m) complete, included toilet (1,5m x 1,5m), septic tank Ls 1
Oil Pit Capacity 45 ton K 300, fe : 120kg/m3, Complete flashplate,
12 Unit 1
Galvanized steel pipe 6''
13 Phase name plate complete with fixing facilities pcs 21
14 Bay name plate complete with fixing facilities pcs 7
15 Site and Road Lighting :
1. Mercury Vapour Flouresent light 1 x 250 W Sets 6
complete with lighting column 9 m high, fuse
box, grounding system and installation of cable
conduit and wiring and all accessories and
foundation of column

2. Mercury flood light 1x400 W complete with Sets 14


15 m height, fuse box, grounding system and
installation of cable conduit and wiring and
all accessories and foundation of column

3. Mercury Vapour Flouresent light 1 x 80 W Sets 10


complete with lighting column 2 m high, fuse
box, grounding system and installation of cable
conduit and wiring and all accessories and
foundation of column

4. Lighting panel outdoor complete with folo cell Set 1


switch fuse, mcb, grouding system
indicator wiring and all accessories (foto cell)

Name of Bidder :
Signature of Bidder :
Rev.1
_________________________________________________________________________________________________
121 of 237
___________________________
BUKU I
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.2 : DAFTAR HARGA DAN KUANTITAS (BOQ) CIVIL WORK
BILL NO 2 : SWITCHYARD FOR CIVIL WORKS

GI 150 kV Teluk Naga II

NO DESCRIPTION UNIT QTY

1 2 3 4
and foundation of panel

TOTAL ITEM II ( 1 - 16 )

III Foundation for 150 kV

1 Surge Arrester Unit 18


2 Capacitor Voltage Transformer Unit 18
3 Disconnecting Earthing Switches ( 1 set = 3 unit) Sets 4
4 Disconnecting Switches ( 1 set = 3 unit) Sets 14
5 Current Transformer Unit 24
6 Post Insulator Unit 12
7 Circuit Breaker ( 1 set = 3 unit) Sets 7
8 Post For Gantries TW1 (18m) Unit 24
9 Post For Gantries TW2 (10m) Unit 0
10 Post For Gantries TW3 Earthing (14m) Unit 1
11 Power Transformer 60 MVA Sets 2
12 Fire Wall Unit 1
13 Marshalling Kiosk Unit 7
14 Neutral Grounding Resistors (NGR) Unit 2
15 Support 20 kV Sets 2
16 Service transformers (include metal roofing and fence BRC 1.5 m) Sets 2

TOTAL ITEM III ( 1 - 16 )

TOTAL BILL NO 2 (Item I + II + III )

Name of Bidder :
Signature of Bidder :
Rev.1
_________________________________________________________________________________________________
122 of 237
___________________________
BUKU I
NAN GI 150 KV TELUK NAGA II
FTAR HARGA DAN KUANTITAS (BOQ)
GA DAN KUANTITAS (BOQ) CIVIL WORK GI 150 KV
WITCHYARD FOR CIVIL WORKS

UNIT PRICE TOTAL PRICE


(RUPIAH) LOCAL
(RUPIAH)
5 6=4x5

6,811 129,401,822
74,916,844 74,916,844
76,012 35,193,679
2,453,296 58,879,099
1,675,722 100,543,336

3,405,311 20,431,867
24,518,240 73,554,720
3,405,311 10,215,933
- include
68,106,222 68,106,222

(1-8) 571,243,522

14,983 53,415,710
61,296 146,128,710
51,080 60,325,086

141,929 5,696,047,824
749,168 67,425,160
1,291,588 1,883,135,584

57,204 177,218,360
165,970 514,174,303
150,331 465,725,229
799,103 2,475,621,721

Name of Bidder :
Signature of Bidder :
Rev.1
_________________________________________________________________________________________________
123 of 237
___________________________
BUKU I
NAN GI 150 KV TELUK NAGA II
FTAR HARGA DAN KUANTITAS (BOQ)
GA DAN KUANTITAS (BOQ) CIVIL WORK GI 150 KV
WITCHYARD FOR CIVIL WORKS

UNIT PRICE TOTAL PRICE


(RUPIAH) LOCAL
(RUPIAH)
5 6=4x5
188,093 44,013,683
313,613 211,061,300

1,690,446 47,332,502
1,156,266 360,755,062
2,530,400 1,351,233,596

1,498,337 5,993,348
4,495,011 4,495,011
26,197,412 26,197,412
74,917 43,901,271

647,145 871,316,464
553,635 186,575,157

Name of Bidder :
Signature of Bidder :
Rev.1
_________________________________________________________________________________________________
124 of 237
___________________________
BUKU I
NAN GI 150 KV TELUK NAGA II
FTAR HARGA DAN KUANTITAS (BOQ)
GA DAN KUANTITAS (BOQ) CIVIL WORK GI 150 KV
WITCHYARD FOR CIVIL WORKS

UNIT PRICE TOTAL PRICE


(RUPIAH) LOCAL
(RUPIAH)
5 6=4x5

3,393,172 464,864,519
2,186,771 205,556,479
1,438,766 254,661,595
3,921,212 47,054,544

948,065 511,955,349
535,883 180,056,556
229,698 242,560,844
730,703 10,229,849
121,878,406 121,878,406

262,452,546 262,452,546

408,637 8,581,384
2,043,187 14,302,307

17,420,551 104,523,308

8,993,195 125,904,731

11,290,991 112,909,914

10,215,933 10,215,933

Name of Bidder :
Signature of Bidder :
Rev.1
_________________________________________________________________________________________________
125 of 237
___________________________
BUKU I
NAN GI 150 KV TELUK NAGA II
FTAR HARGA DAN KUANTITAS (BOQ)
GA DAN KUANTITAS (BOQ) CIVIL WORK GI 150 KV
WITCHYARD FOR CIVIL WORKS

UNIT PRICE TOTAL PRICE


(RUPIAH) LOCAL
(RUPIAH)
5 6=4x5

I ( 1 - 16 ) 17,369,800,757

11,068,229 199,228,127
12,360,015 222,480,274
35,462,085 141,848,340
35,462,085 496,469,189
12,360,015 296,640,365
11,068,229 132,818,751
35,462,085 248,234,595
83,570,887 2,005,701,279
65,255,846 -
39,519,435 39,519,435
148,455,219 296,910,437
125,901,299 125,901,299
3,821,842 26,752,897
11,575,009 23,150,017
6,705,249 13,410,499
44,549,285 89,098,570

II ( 1 - 16 ) 4,358,164,075

Item I + II + III ) 22,299,208,354

Name of Bidder :
Signature of Bidder :
Rev.1
_________________________________________________________________________________________________
126 of 237
___________________________
BUKU I
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.2 : DAFTAR KUANTITAS DAN HARGA (BOQ) SIPIL GI 1
BILL NO 3 : MISCELLANEOUS WORKS

GI 150 kV Teluk Naga II

NO DESCRIPTION UNIT QTY

1 2 3 4

I Miscellaneous Works

1 Concrete Works
- Concrete K 225 m3 15
- Concrete K 300 m3 20
2 Stone masonry 1 pc : 3 ps m3 35
3 Reinforcement Work
- Reinforcement steel work U-24 kg 750
- Reinforcement steel work U-32 kg 3,750
4 Excavation Work
- Excavation of Soil m3 20
5 Filling Work
- Import Soil Fill (include compaction in layer of 20 cm) m3 100
6 Steel structures kg 1,500
7 Driven Pile 30x30 K 450 m' 7,266
8 Bored Pile Dia 40 cm K 225 m' 40
TOTAL BILL NO 3 (Item I )

Name of Bidder :
Rev.1
Signature of Bidder : 127 of 237
_______________________________________________________________________________________________
___________________________________
BUKU I
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
AR KUANTITAS DAN HARGA (BOQ) SIPIL GI 150 KV
NO 3 : MISCELLANEOUS WORKS

UNIT PRICE TOTAL PRICE


(RUPIAH) LOCAL
(RUPIAH)
5 6=4x5

1,630,995 24,464,927
1,716,981 34,339,612
1,291,588 45,205,587

18,720 14,040,370
18,720 70,201,851

14,983 299,667

141,929 14,192,928
34,747 52,121,038
599,769 4,357,918,987
1,020,757 40,830,281
BILL NO 3 (Item I ) 4,653,615,248

Name of Bidder :
Rev.1
Signature of Bidder : 128 of 237
_______________________________________________________________________________________________
___________________________________
BUKU I
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.2 : DAFTAR KUANTITAS DAN HARGA (BOQ) SIPIL GI 150 KV
BILL NO 4 : REKAPITULASI HARGA CIVIL WORK GI 150 KV

GI 150 kV Teluk Naga II


TOTAL PRICE
NO. DESCRIPTION
(Rp)
(1) (2) (3)

1 BILL NO 1 : CONTROL BUILDING AND SAS & MV CELL 20KV 6,847,196,397

2 BILL NO 2 : SWITCHYARD FOR CIVIL WORKS GI BUNAR BARU 22,299,208,354

3 BILL NO 4 : MISCELLANEOUS WORKS 4,653,615,248

Total Price for Civil Work GI 150 kV 33,800,020,000

Name of Bidder :
Rev.1
Signature of Bidder : 129 of 237
________________________________________________________________________________________
BUKU I
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00
1 1 (one) unit plank name of project
- Material :
- Wooden / Kayu m3 0.22
- Colour paint kg 3.00
- Nail kg 1.00
- Concrete 1 pc : 3 sand : 5 split m 3
0.40
- Remuneration :
- Paint worker man/day 1.00
- Worker man/day 2.00
- Supervisor man/day 0.10

2 1 (one) m Bouwplank
- Material :
- Wooden / Kayu m3 0.01
- Nail kg 0.02
- Remuneration :
- Carpenter man/day 0.05
- Worker man/day 0.05
- Worker Chief man/day 0.01
- Supervisor man/day 0.01

3 1 m2 Direksi Keet
- Material :
- Wooden / Kayu m3 0.18
- Nail kg 0.50
- Portland cement kg 1.00
- Sand m 3
0.25
- Split m 3
0.15
- Red Brick bh 30.00
- Asbes roof sheet 0.80
- Window & Door set 0.04
- Glass 5 mm m 2
0.08
- Door lock and hinge complete bh 0.15
- Plywood lbr 0.06
- Remuneration :

DATE :
Rev.1
NAME OF BIDDER :
Page 130 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00
- Woker man/day 2.00
- Carpenter man/day 2.00
- Brick Layer man/day 1.00
- Worker chief man/day 0.30
- Supervisor man/day 0.05

DATE :
Rev.1
NAME OF BIDDER :
Page 131 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

4 1 m2 Site storage
- Material :
- Wooden / Kayu m3 0.18
- Nail kg 0.30
- Portland cement kg 10.50
- Sand m3 0.03
- Split m3 0.05
- Atap Asbes lbr 0.80
- Renumeration :
- Woker man/day 1.00
- Carpenter man/day 2.00
- Worker chief man/day 0.20
- Supervisor man/day 0.05

5 1 m2 Site Clearing and Grubbing (pengupasan t=20cm)


- Remuneration :
- Worker man/day 0.10
- Supervisor man/day 0.05

6 1 m3 Excavation of Soil
- Equipment :
- Hoe unit 0.01
- Remuneration :
- Worker man/day 0.73
- Supervisor man/day 0.03

7 1 m3 Excavation of Rock
- Equipment :
- Hoe unit 0.02
- Remuneration :
- Worker man/day 1.00
- Supervisor man/day 0.03

DATE :
Rev.1
NAME OF BIDDER :
Page 132 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

8 1 m3 Back Filling (Compacted)


- Equipment :
- Hoe unit 0.01
- Stamper hour 0.20
- Remuneration :
- Worker man/day 0.33
- Supervisor man/day 0.03

9 1 m3 Soil Disposal
- Equipment :
- Hoe unit 0.01
- Pick Up hour 0.40
- Remuneration :
- Worker man/day 0.33
- Supervisor man/day 0.01

DATE :
Rev.1
NAME OF BIDDER :
Page 133 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

10 1 m3 Import Soil Fill (Compacted)


- Material :
- Soil m3 1.20
- Equipment :
- Buldozer hour 0.02
- Water tank truck hour 0.02
- Vibro Roller hour 0.04
- Remuneration :
- Worker man/day 0.30
- Supervisor man/day 0.01

11 1 m3 Compacted Sand layer


- Material :
- Sand m3 1.05
- Equipment :
- Stamper hour 0.10
- Remuneration :
- Worker man/day 0.50
- Supervisor man/day 0.05

12 1 m3 Compacted Gravel
- Material :
- Gravel m3 1.20
- Remuneration :
- Worker man/day 0.50
- Supervisor man/day 0.05

13 1 m2 Half Brick 1 pc : 3 ps
- Material :
- Red brick unit 70.00
- Portland cement (PC) kg 15.30
- Sand m 3
0.04
- Remuneration :

DATE :
Rev.1
NAME OF BIDDER :
Page 134 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00
- Brick layer man/day 0.20
- Worker man/day 0.40
- Supervisor man/day 0.02
- Worker Chief man/day 0.01

14 1 m2 plaster cement 1 pc : 3 ps thickness 15 mm


- Material :
- Portland cement (PC) kg 7.80
- Sand m3 0.03
- Remuneration :
- Brick layer man/day 0.19
- Worker man/day 0.38
- Supervisor man/day 0.03
- Worker Chief man/day 0.02

DATE :
Rev.1
NAME OF BIDDER :
Page 135 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

15 1 m2 Acian
- Material :
- Portland cement (PC) kg 3.25
- Remuneration :
- Brick layer man/day 0.10
- Worker man/day 0.20
- Supervisor man/day 0.01
- Worker Chief man/day 0.01

16 1 m3 Lean Concrete K 125


- Material :
- Portland cement (PC) kg 276.00
- Sand m 3
0.60
- Split 2/3 m 3
0.57
- Equipment :
- Molen Machine hour 2.00
- Concrete Vibrator hour 1.00
- Remuneration :
- Brick layer man/day 0.20
- Worker man/day 1.32
- Supervisor man/day 0.13
- Worker chief man/day 0.02

1 m2 Lean Concrete K 125 (t=10 cm)

17 1 m3 Concrete f'c = 19,3 MPa (K 225)


- Material :
- Portland cement (PC) kg 371.00
- Sand m 3
0.50
- Split 2/3 m 3
0.78
- Equipment :
- Molen Machine unit/day 2.00
- Concrete Vibrator hour 1.00
- Remuneration :
- Brick layer man/day 0.20

DATE :
Rev.1
NAME OF BIDDER :
Page 136 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00
- Worker man/day 1.32
- Supervisor man/day 0.13
- Worker chief man/day 0.02

DATE :
Rev.1
NAME OF BIDDER :
Page 137 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

18 1 m3 Concrete f'c = 26,4 MPa (K 300)


- Material :
- Portland cement (PC) kg 413.00
- Sand m 3
0.50
- Split 2/3 m 3
0.78
- Equipment :
- Molen Machine unit/day 2.00
- Concrete Vibrator hour 1.00
- Remuneration :
- Brick layer man/day 0.20
- Worker man/day 1.32
- Supervisor man/day 0.13
- Worker chief man/day 0.02

19 1 m3 Stone Masonry 1 PC : 3 Sand


- Material :
- Batu Belah 20-30 cm m3 1.20
- Portland cement (PC) kg 202.00
- Sand m 3
0.49
- Remuneration :
- Brick layer man/day 0.75
- Worker man/day 1.50
- Supervisor man/day 0.08
- Worker chief man/day 0.08
- Equipment :
- Molen Machine hour 0.17

20 100 kg steel work U 24 or BJTP 24:


- Material
- Steel Bar (Reinforcement) U 24 or BJTP 24 kg 105.00
- Concrete wire kg 1.50
- Remuneration
- Steel worker man/day 0.70
- Worker man/day 0.70

DATE :
Rev.1
NAME OF BIDDER :
Page 138 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00
- Supervisor man/day 0.70
- Worker chief man/day 0.07

Per kg

21 100 kg steel work U 32 or BJTD 35:


- Material :
- Steel Bar (Reinforcement) U 32 or BJTD 35 kg 105.00
- Concrete wire kg 1.50
- Remuneration :
- Steel worker man/day 0.70
- Worker man/day 0.70
- Supervisor man/day 0.70
- Worker chief man/day 0.07

Per kg

DATE :
Rev.1
NAME OF BIDDER :
Page 139 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

22 1.00 ton stell Structure


- Material :
- Galvanized Steel Structure (HTS) kg 682.50
- Galvanized Steel Structure (MS) kg 367.50
- Galvanis Bolt and Nuts NO 120.00
- Galvanized Steel Plate kg 35.00
- Remuneration :
- Steel worker man/day 12.00
- Worker man/day 20.00
- Supervisor man/day 2.00

Per kg

23 Post Steel Structure Gantry TW-1 (High 18m)


- Material :
- Steel Structure kg 3,015.00
- Delivery & Erection (pemasangan) : kg 3,015.00

24 Post Steel Structure Gantry TW-2 (High 10m)


- Material :
- Steel Structure kg 1,950.00
- Delivery & Erection (pemasangan) : kg 1,950.00

25 Post Steel Structure Gantry TW-3 (High 14 m) for GSW


- Material :
- Steel Structure kg 1,322.00
- Delivery & Erection (pemasangan) : kg 1,322.00

26 Beam steel structure lenght 14 m


- Material :
- Steel Structure kg 1,385.00
- Delivery & Erection (pemasangan) : kg 1,385.00

DATE :
Rev.1
NAME OF BIDDER :
Page 140 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

27 Beam steel structure lenght 12 m


- Material :
- Steel Structure kg 1,205.00
- Delivery & Erection (pemasangan) : kg 1,205.00

28 1 m2 Formwork ( Beam meranti 5/7 height 4 m)


- Material :
- Wooden m3 0.05
- Nail kg 0.35
- Remuneration :
- Carpenter man/day 0.20
- Worker man/day 0.20
- Supervisor man/day 0.06
- Worker chief man/day 0.06

DATE :
Rev.1
NAME OF BIDDER :
Page 141 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

29 1 m' Driven Pile 30x30 K 450


- Material :
- Tiang Pancang Driven Pile 30 x 30 K450 m' 1.03
- Equipment :
- Crawler Crane 10-15 Ton hour 0.07
- Hydrolic Pile Driver hour 0.07
- Alat Penyambung Pile bh 0.25
- Support Equipment Ls 1.00
- Mobilization Equipment Ls 1.00
- Remuneration :
- Worker man/day 0.05
- Surveyor man/day 0.01
- Supervisor man/day 0.01
- Operator man/day 0.01
- Mechanic man/day 0.01

30 1 m' Bored Pile Ø 40 cm K 225


- Material :
- Concrete K 225 m3 0.14
- Reinforced steel screw U32 kg 10.40
- Reinforced steel plain U24 kg 7.80
- Casing ls 1.00
- Equipment :
- Drilling Machine hour 0.15
- Tremie Pipa hour 0.15
- Mollen hour 0.15
- Total Station hour 0.15
- Support Equipment : hour 0.15
- Mobilisasi alat (per meter pile) ls 1.00
- Remuneration :
- Worker man/day 0.05
- Surveyor man/day 0.01

DATE :
Rev.1
NAME OF BIDDER :
Page 142 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00
- Supervisor man/day 0.01
- Operator man/day 0.01
- Mechanic man/day 0.01

31 1 m2 Steel painting
- Material :
- Naturally Meni kg 0.20
- Colour painting steel kg 0.08
- Kuas NO 0.01
- Thinner Liter 0.01
- Remuneration :
- Worker Paint man/day 0.25
- Worker man/day 0.25
- Supervisor man/day 0.00
- Worker chief man/day 0.03

DATE :
Rev.1
NAME OF BIDDER :
Page 143 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

32 1 m2 Wall painting (Interior) 1xplamur, 3xpaint


- Material :
- Plamur kg 0.10
- Colour painting wall emulsi kg 0.36
- Remuneration :
- Worker Paint man/day 0.06
- Worker man/day 0.02
- Supervisor man/day 0.00
- Worker chief man/day 0.01

33 1 m2 Wall painting weathershield (eksterior) 1xplamur, 3xpaint


- Material :
- Plamur kg 0.10
- Colour painting wall weathershield kg 0.36

- Remuneration :
- Worker Paint man/day 0.06
- Worker man/day 0.02
- Supervisor man/day 0.00
- Worker chief man/day 0.01

34 1 m2 Compacted Subgrade
- Equipment :
- Vibro Roller hour 0.05
- Remuneration :
- Operator man/day 0.10
- Supervisor man/day 0.01

35 1m2 Compacted Sandgravel (Sirtu) t = 20 cm


- Material :
- Sandgravel (sirtu) m3 0.20
- Equipment :
- Vibro Roller hour 0.05

DATE :
Rev.1
NAME OF BIDDER :
Page 144 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00
- Remuneration :
- Operator man/day 0.16
- Supervisor man/day 0.01

36 1 m2 Reinforced Concrete Road K 300


- Work :
- Concrete K 300 m3 0.25
- Steel work U 24 kg 18.00
- Formwork m2 0.35

DATE :
Rev.1
NAME OF BIDDER :
Page 145 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

CABLE TRENCH SWITCHYARD :

37 1 m' Cable Trench Type 1 (±1.2 m width)


- Excavation of soil m3 2.10
- Backfilling m3
1.05
- Compacted sand layer m3
0.12
- Lean concrete K 125 m3 0.06
- Reinforced Concrete K 225 m3 0.57
- Reinforced steel plain U24 kg 45.60
- Formwork m2
4.00
- Galvanis Steel L50x50x5 (Cable Rack) kg 15.70
- Dynabolt 10 mm pcs 4.00

38 1 m' Cable Trench Type 2 (±0.8 m width)


- Excavation of soil m3 1.20
- Backfilling m3
0.60
- Compacted sand layer m3
0.08
- Lean concrete K 125 m3
0.04
- Reinforced Concrete K 225 m3
0.36
- Reinforced steel plain U24 kg 28.80
- Formwork m2 3.00
- Galvanis Steel L50x50x5 (Cable Rack) kg 7.85
- Dynabolt 10 mm pcs 4.00

39 1 m' Cable Trench Type 3 (±0.6 m width)


- Excavation of soil m3 0.60
- Backfilling m3
0.30
- Compacted sand layer m3
0.06
- Lean concrete K 125 m3
0.03
- Reinforced Concrete K 225 m3
0.24
- Reinforced steel plain U24 kg 19.20
- Formwork m2
2.20
- Galvanis Steel L50x50x5 (Cable Rack) kg 3.93
- Dynabolt 10 mm pcs 2.00

DATE :
Rev.1
NAME OF BIDDER :
Page 146 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

40 1 m' Cable Trench Type 4 (Crossing Road ±1.2 m width)


- Excavation of soil m3 2.30
- Backfilling m3
1.15
- Compacted sand layer m3
0.13
- Lean concrete K 125 m3
0.07
- Reinforced Concrete K 225 m3 0.72
- Reinforced steel plain U24 kg 57.60
- Formwork m2 4.20
- Galvanis Steel L50x50x5 (Cable Rack) kg 15.70
- Dynabolt 10 mm pcs 4.00

DATE :
Rev.1
NAME OF BIDDER :
Page 147 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

CABLE TRENCH INDOOR :

41 1 m' Cable Trench Type 1 (±1.2 m width)


- Excavation of soil m3 2.10
- Backfilling m3
1.05
- Compacted sand layer m3
0.12
- Lean concrete K 125 m3 0.06
- Reinforced Concrete K 225 m3 0.44
- Reinforced steel plain U24 kg 35.20
- Formwork m2
4.00
- Galvanis Steel L50x50x5 (Cable Rack) kg 15.70
- Galvanis Steel Angle & Bordes (Cover Cable Trench) kg 46.20
- Dynabolt 10 mm pcs 4.00

42 1 m' Cable Trench Type 2 (±0.8 m width)


- Excavation of soil m3 1.20
- Backfilling m3
0.60
- Compacted sand layer m3
0.08
- Lean concrete K 125 m3
0.04
- Reinforced Concrete K 225 m3
0.24
- Reinforced steel plain U24 kg 19.20
- Formwork m2 3.00
- Galvanis Steel L50x50x5 (Cable Rack) kg 7.85
- Galvanis Steel Angle & Bordes (Cover Cable Trench) kg 29.80
- Dynabolt 10 mm pcs 2.00

43 1 m' Cable Trench Type 3 (±0.4 m width)


- Excavation of soil m3 0.32
- Backfilling m3
0.16
- Compacted sand layer m3
0.04
- Lean concrete K 125 m3
0.02
- Reinforced Concrete K 225 m3
0.12
- Reinforced steel plain U24 kg 9.60
- Formwork m2
1.60

DATE :
Rev.1
NAME OF BIDDER :
Page 148 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00
- Galvanis Steel L45x45x5 (Cable Rack) kg 6.40
- Galvanis Steel Angle & Bordes (Cover Cable Trench) kg 11.60
- Dynabolt 10 mm pcs 2.00

44 1 m' Open Drainage (stone masonry) 40/70 cm


- Excavation of soil m3 0.73
- Backfilling m3 0.22
- Compacted sand layer m3 0.08
- Plaster cement 1 pc : 3 ps m2 1.80
- Acian m2 1.80
- Stone Masonry 1 PC : 3 Sand m3
0.44

DATE :
Rev.1
NAME OF BIDDER :
Page 149 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

45 1 m' Open Drainage (brick) 30/40 cm


- Excavation of soil m3 0.35
- Backfilling m3
0.11
- Compacted sand layer m3
0.06
- Plaster cement 1 pc : 3 ps m2 1.10
- Acian m2 1.10
- Brick 1 pc : 3 ps m2 1.40

46 1 m' Sub Soil Drainage


- Excavation of soil m3 0.64
- Backfilling m3
0.51
- Compacted sand layer m3
0.08
- Pipe Concrete Ø 30 cm m' 1.00
- Palm Fibre kg 2.00
- Gravel m3
0.24

47 1 unit Control Box (Brick 60x60x70 cm)


- Excavation of soil m3 0.89
- Backfilling m3
0.27
- Compacted sand layer m3 0.08
- Plaster cement 1 pc : 3 ps m2 1.20
- Brick 1 pc : 3 ps m2 2.40

48 1m' Fence BRC height 1.90 m


- Excavation of Soil m3 0.24
- Back Filling m3 0.07
- BRC height 1.9 m m' 1.00
- Galvanized Steel pipe dia 2.5'' inc and clamp m' 1.88
- Foundation & sloof concrete K 225 m3
0.16
- Reinforced steel plain U24 kg 9.60
- Formwork m3
0.88
- Steel Worker man/day 1.00

DATE :
Rev.1
NAME OF BIDDER :
Page 150 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

49 1m' Fence BRC height 1.50 m


- Excavation of Soil m3 0.24
- Back Filling m3 0.07
- BRC height 1.5 m m' 1.00
- Galvanized Steel pipe dia 2.5'' inc and clamp m' 1.13
- Foundation & sloof concrete K 225 m3
0.16
- Reinforced steel plain U24 kg 9.60
- Formwork m3 0.88
- Steel Worker man/day 1.00

DATE :
Rev.1
NAME OF BIDDER :
Page 151 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

50 Sliding Gate 2.40 m height, 6.00 m width


- Excavation of Soil m3 2.40
- Back Filling m 3
0.72
- Compacted sand layer m 3
0.14
- Lean concrete m 3
0.07
- Galvanized Steel Pipe Dia 2,5 inch m 50.40
- Galvanized Steel Pipe Dia 3 inch m 28.60
- Galvanized Steel Plate kg 94.00
- Foundation, Pillar column concrete K 225 m3 0.78
- Reinforced steel plain U24 m 3
62.40
- Formwork m 2
7.20
- Plaster cement 1 pc : 3 ps m 2
3.20
- Acian m 2
3.20
- Engsel set 1.00
- Rel & steel roller kg 68.20
- Lock & key/gembok set 1.00
- Steel Worker/Welder man/day 3.00
- Worker man/day 3.00

51 1m' Fence from Brick Wall height 2.40 m


and barbed wire 0,60 m (upper)
- Excavation of Soil m3 0.72
- Back Filling m3 0.22
- Compacted sand layer m 3
0.08
- Lean concrete m 3
0.04
- Brick 1 pc : 3 ps m2 2.40
- Plaster cement 1 pc : 3 ps m2 4.80
- Acian m 2
4.80
- Foundation, column & sloof concrete K 225 m3 0.42
- Reinforced steel plain U24 kg 33.60
- Galvanized steel angle 45.45.5 kg 2.80
- Barbed wire kg 2.50
- Wall painting (weathershield) m2 4.80

DATE :
Rev.1
NAME OF BIDDER :
Page 152 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00
52 1 m' Kerbs (30x20 cm)
- Excavation of Soil m3 0.03
- Concrete K 225 m3 0.06
- Lean concrete m3 0.02
- Compacted sand layer m3 0.03

53 1 m' Kerbs (40x25 cm)


- Excavation of Soil m3 0.05
- Concrete K 225 m3 0.10
- Lean concrete m2 0.02
- Compacted sand layer m3 0.03

DATE :
Rev.1
NAME OF BIDDER :
Page 153 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

54 1 m2 Acoustic Ceiling with frame


- Material :
- Akustik panel 120 x 60 (plafon) sheet 1.45
- Alumunium Frame & hanger m' 4.00
- Accessories Ls 1.00
- Nail kg 0.11
- Remuneration :
- Carpenter man/day 0.05
- Steel worker man/day 0.25
- Worker man/day 0.10
- Supervisor man/day 0.01
- Worker chief man/day 0.01

55 1 m2 Ceilling Gypsum board (GRC), Hollow frame


- Material :
- Gypsum board 9 mm sheet 0.50
- Hollow steel 40.40 mm m' 3.50
- Accessories Ls 1.00
- Nail kg 0.11
- Remuneration :
- Carpenter man/day 0.05
- Steel worker man/day 0.25
- Worker man/day 0.10
- Supervisor man/day 0.01
- Worker chief man/day 0.01

56 1 m' list profil ceiling


- Material :
- List profil (wooden) m' 1.00
- Lem Kayu kg 0.04
- Paint of wooden kg 0.04
- Remuneration :
- Carpenter man/day 0.08
- Worker man/day 0.20

DATE :
Rev.1
NAME OF BIDDER :
Page 154 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00
- Supervisor man/day 0.01

57 1 m2 Ceramic floor tiles 200 x 200 mm


- Material :
- Floor tile ceramic 200 x 200 mm m2 1.06
- Portland Cement (PC) kg 9.60
- Sand m3 0.05
- Colour Cement (PC) kg 0.20
- Remuneration :
- Brick layer man/day 0.12
- Worker man/day 0.24
- Supervisor man/day 0.01
- Worker chief man/day 0.01

DATE :
Rev.1
NAME OF BIDDER :
Page 155 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

58 1 m2 Ceramic floor tiles 300 x 300 mm


- Material :
- Ceramic tile 300 x 300 mm m2 1.06
- Portland Cement (PC) kg 10.00
- Sand m3
0.05
- Colour Cement kg 1.00
- Remuneration :
- Brick layer man/day 0.13
- Worker man/day 0.26
- Supervisor man/day 0.01
- Worker chief man/day 0.01

59 1 m2 Ceramic wall tiles 200 x 250 mm


- Material :
- Ceramic wall tiles 200 x 250 mm m2 1.06
- Portland Cement (PC) kg 9.80
- Sand m3
0.05
- Colour Cement kg 1.00
- Remuneration :
- Brick layer man/day 0.13
- Worker man/day 0.25
- Supervisor man/day 0.01
- Worker chief man/day 0.01

60 1 m' Ceramic plint tile 150 x 300 mm


- Material :
- Plint tile 150 x 300 mm no 3.33
- Portland Cement (PC) kg 1.14
- Sand m3
0.00
- Colour Cement kg 0.10
- Remuneration :
- Brick layer man/day 0.09
- Worker man/day 0.09
- Supervisor man/day 0.01

DATE :
Rev.1
NAME OF BIDDER :
Page 156 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00
- Worker chief man/day 0.01

61 1 m' Stepnosing 100 x 300 mm


- Material :
- Stepnosing 100 x 300 mm no 2.65
- Portland Cement (PC) kg 1.24
- Sand m3 0.00
- Remuneration :
- Brick layer man/day 0.09
- Worker man/day 0.09
- Supervisor man/day 0.01
- Worker chief man/day 0.01

DATE :
Rev.1
NAME OF BIDDER :
Page 157 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

62 1 m2 Roofing klip lock HI-TEN


- Material :
- Roofing klip lock HI-TEN m2 1.05
- Nail drat no 8.00
- Remuneration :
- Carpenter man/day 0.75
- Worker man/day 0.15
- Supervisor man/day 0.01
- Worker chief man/day 0.08

63 1 m2 Roofing Spandek Metal Sheet


- Material :
- Roofing Spandek Colorbond m2 1.05
- Nail drat no 8.00
- Remuneration :
- Carpenter man/day 0.75
- Worker man/day 0.15
- Supervisor man/day 0.01
- Worker chief man/day 0.08

64 1 m' Nok Standard HI-TEN


- Material :
- Nok Standard HI-TEN m' 1.20
- Nail drat no 6.00
- Remuneration :
- Carpenter man/day 1.00
- Worker man/day 0.10
- Supervisor man/day 0.05
- Worker chief man/day 0.10

65 1 m' Nok Spandek Metal


- Material :
- Nok Spandek Colorbond m' 1.20

DATE :
Rev.1
NAME OF BIDDER :
Page 158 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00
- Nail drat no 6.00
- Remuneration :
- Carpenter man/day 1.00
- Worker man/day 0.10
- Supervisor man/day 0.05
- Worker chief man/day 0.10

66 1 m2 Thermal Insulation Glasswool t=10 cm


- Material :
- Glasswool t=10 cm, aluminium foil (single sided) with 2 (two) layer m2 1.05
- Roof mesh kg 3.00
- Remuneration :
- Carpenter man/day 0.05
- Worker man/day 0.15
- Supervisor man/day 0.01
- Worker chief man/day 0.01

DATE :
Rev.1
NAME OF BIDDER :
Page 159 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

67 1 m' Listplank Metal


- Material
- listplank Superplank (GRC board) m' 1.10
- Nail kg 0.10
- Remuneration
- Worker man/day 0.10
- Supervisor man/day 0.01
- Worker chief man/day 0.02

68 1 m2 Waterproofing
- Material
- Waterproofing kg 0.35
- Serat Fiber m2
1.00
- Remuneration
- Worker man/day 0.05
- Supervisor man/day 0.00

69 1 m2 Floorhardener
- Material
installation kg 5.00
- Remuneration
- Worker man/day 0.12
- Supervisor man/day 0.01
- Worker Chief man/day 0.01

70 1 Unit Pekerjaan Closet Duduk


- Material
- Closet Duduk with eco washer complete (equal toto) no 1.00
- Remuneration
- Worker man/day 3.30
- Supervisor man/day 0.16
- Worker chief man/day 0.01

DATE :
Rev.1
NAME OF BIDDER :
Page 160 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

71 1 Unit Pekerjaan Urinoir


- Material
- Urinoir complete (equal toto) no 1.00
- Remuneration
- Worker man/day 1.00
- Supervisor man/day 0.05
- Worker chief man/day 0.10

72 1 Unit Pekerjaan Wastafel


- Material
- Wastafel complete (equal toto) no 1.00
- Remuneration
- Worker man/day 1.20
- Supervisor man/day 0.06
- Woker chief man/day 0.15

DATE :
Rev.1
NAME OF BIDDER :
Page 161 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

73 1 Unit Pekerjaan Wash Sink


- Material
- Wash sink complete no 1.00
- Remuneration
- Worker man/day 1.20
- Supervisor man/day 0.06
- Woker chief man/day 0.15

74 1 Unit Foundation Surge Arrester


- Excavation of Soil m3 10.200
- Back Filling m3
7.140
- Compacted sand m3
0.225
- Lean Concrete m3
0.113
- Concrete K-300 m3
2.200
- Reinforced steel screw U32 kg 176.000
- Reinforced steel plain U24 kg 66.000
- Formwork m2
8.800
- PVC Ø 2" for earthing cable m' 0.700
- Anchor bolt Ø 22 mm pcs 4.000

75 1 Unit Foundation Current Voltage Transformer


- Excavation of Soil m3 12.500
- Back Filling m3
8.750
- Compacted sand m3
0.324
- Lean Concrete m3
0.162
- Concrete K-300 m3
2.400
- Reinforced steel screw U32 kg 192.000
- Reinforced steel plain U24 kg 72.000
- Formwork m2
9.600
- PVC Ø 2" for earthing cable m' 0.700
- PVC Ø 4" for cable trench m' 1.500
- Anchor bolt Ø 22 mm pcs 4.000

DATE :
Rev.1
NAME OF BIDDER :
Page 162 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

76 1 Set (3 unit) Foundation Disconnecting /& Earthing Switches (DS/E)

- Excavation of Soil m3 34.800


- Back Filling m3
24.360
- Compacted sand m3
1.640
- Lean Concrete m3
0.820
- Concrete K-300 m3
6.950
- Reinforced steel screw U32 kg 556.000
- Reinforced steel plain U24 kg 208.500
- Formwork m2
20.400
- PVC Ø 2" for earthing cable m' 3.000
- PVC Ø 4" for cable trench m' 6.000
- Anchor bolt Ø 22 mm pcs 12.000

DATE :
Rev.1
NAME OF BIDDER :
Page 163 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

77 1 Unit Foundation Current Transformer


- Excavation of Soil m3 12.500
- Back Filling m3
8.750
- Compacted sand m3
0.324
- Lean Concrete m3
0.162
- Concrete K-300 m3
2.400
- Reinforced steel screw U32 kg 192.000
- Reinforced steel plain U24 kg 72.000
- Formwork m2 9.600
- PVC Ø 2" for earthing cable m' 0.700
- PVC Ø 4" for cable trench m' 1.500
- Anchor bolt Ø 22 mm pcs 4.000

78 1 Set (3 unit) Foundation Circuit Breaker


- Excavation of Soil m3 34.800
- Back Filling m3
24.360
- Compacted sand m3
1.640
- Lean Concrete m3
0.820
- Concrete K-300 m3
6.950
- Reinforced steel screw U32 kg 556.000
- Reinforced steel plain U24 kg 208.500
- Formwork m2 20.400
- PVC Ø 2" for earthing cable m' 3.000
- PVC Ø 4" for cable trench m' 6.000
- Anchor bolt Ø 22 mm pcs 12.000

79 1 Set Foundation Power Transformer 60 MVA


- Excavation of Soil m3 35.52
- Back Filling m3
7.10
- Compacted sand m3
3.74
- Lean Concrete m3
1.87
- Concrete K-300 m3
30.40
- Reinforced steel screw U32 kg 3,040.00
- Formwork m2
43.60

DATE :
Rev.1
NAME OF BIDDER :
Page 164 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00
- Grille/greeting for Oil Pit, Steel Galvanis, anchor kg 730.20

80 1 Unit Fire Wall


- Excavation of Soil m3 40.50
- Back Filling m3
12.15
- Compacted sand m3
1.95
- Lean Concrete m3 0.98
- Concrete K-300 m3 22.40
- Reinforced steel screw U32 kg 2,240.00
- Formwork m2
112.00
- Plaster cement 1 pc : 3 ps m2
118.80
- Acian m2
118.80

DATE :
Rev.1
NAME OF BIDDER :
Page 165 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

81 1 Unit Foundation Marshalling Kiosk


- Excavation of Soil m3 1.20
- Back Filling m3
0.36
- Compacted sand m3
0.10
- Lean Concrete m3
0.05
- Concrete K-300 m3
0.60
- Reinforced steel screw U32 kg 36.00
- Reinforced steel plain U24 kg 24.00
- Formwork m2 4.20
- PVC Ø 2" for earthing cable m' 2.00
- PVC Ø 4" for cable trench m' 4.00
- Anchor bolt pcs 4.00

82 1 Unit Foundation NGR


- Excavation of Soil m3 18.40
- Back Filling m3
5.52
- Compacted sand m3
0.32
- Lean Concrete m3
0.16
- Concrete K-300 m3
2.40
- Reinforced steel screw U32 kg 144.00
- Reinforced steel plain U24 kg 96.00
- Formwork m2 6.75
- PVC Ø 2" for earthing cable m' 2.00
- PVC Ø 4" for cable trench m' 4.00
- Anchor bolt pcs 4.00

83 1 Unit Foundation Support 20 kV


- Excavation of Soil m3 3.52
- Back Filling m3
1.06
- Compacted sand m3
0.20
- Lean Concrete m3
0.10
- Concrete K-300 m3
1.44
- Reinforced steel screw U32 kg 86.40
- Reinforced steel plain U24 kg 57.60

DATE :
Rev.1
NAME OF BIDDER :
Page 166 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00
- Formwork m2
4.80
- Anchor bolt pcs 4.00

84 1 Unit Foundation Post Insulator


- Excavation of Soil m3 10.200
- Back Filling m3
7.140
- Compacted sand m3 0.225
- Lean Concrete m3 0.113
- Concrete K-300 m3 2.200
- Reinforced steel screw U32 kg 176.000
- Reinforced steel plain U24 kg 66.000
- Formwork m2
8.800
- PVC Ø 2" for earthing cable m' 0.700
- Anchor bolt Ø 22 mm pcs 4.000

DATE :
Rev.1
NAME OF BIDDER :
Page 167 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

85 1 Unit Foundation Service Transformers


- Excavation of Soil m3 3.24
- Back Filling m3
0.97
- Compacted sand m3
0.58
- Lean Concrete m3
0.29
- Concrete K-300 m3
3.40
- Reinforced steel screw U32 kg 204.00
- Reinforced steel plain U24 kg 136.00
- Formwork m2 5.80
- PVC Ø 2" for earthing cable m 2.00
- PVC Ø 4" for cable trench m 4.00
- Metal Roofing, Fencing BRC 1.5 m height & Gate Set 1.00

86 1 Unit Foundation Post for Gantry TW1 (18m)


- Excavation of Soil m3 50.50
- Back Filling m3
35.35
- Compacted sand m3
3.40
- Lean Concrete m3
1.70
- Concrete K-300 m3
17.70
- Reinforced steel screw U32 kg 1,416.00
- Reinforced steel plain U24 kg 708.00
- Formwork m2
28.00
- PVC Ø 2" for earthing cable m' 2.00
- Anchor bolt Ø 32 mm pcs 16.00

87 1 Unit Foundation Post for Gantry TW2 (10m)


- Excavation of Soil m3 30.60
- Back Filling m3
21.42
- Compacted sand m3
3.00
- Lean Concrete m3
1.50
- Concrete K-300 m3
13.75
- Reinforced steel screw U32 kg 1,100.00
- Reinforced steel plain U24 kg 550.00

DATE :
Rev.1
NAME OF BIDDER :
Page 168 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00
- Formwork m2
22.00
- PVC Ø 2" for earthing cable m' 2.00
- Anchor bolt Ø 32 mm pcs 16.00

88 1 Unit Foundation Post for Gantry TW3 Earthing (14m)


- Excavation of Soil m3 18.40
- Back Filling m3 12.88
- Compacted sand m3 2.40
- Lean Concrete m3 1.20
- Concrete K-300 m3
7.80
- Reinforced steel screw U32 kg 624.00
- Reinforced steel plain U24 kg 312.00
- Formwork m2
18.00
- PVC Ø 2" for earthing cable m' 2.00
- Anchor bolt Ø 32 mm pcs 16.00

86 1 Sets Tower Type DDR6+0


- Material Steel Structure for Towers kg 17,735.00
- Delivery & Erection (pemasangan) kg 17,735.00

DATE :
Rev.1
NAME OF BIDDER :
Page 169 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.3 : ANALISA HARGA SATUAN

NO DESCRIPTION UNIT QTY

1 2 3 4.00

87 1 Sets Foundation Towers Type DDR6+0 Class 6 (Pile foundation)


- Site clearing m2 800.00
- Installation of setting plan (bowplank) m2 800.00
- Material :
- Excavation of soil m3 173.00
- Compacted back fill m3 173.00
- Sand layer t = 0.1 m m3 3.80
- Lean Concrete K 100 t = 0,1 m m3 3.80
- Concrete K-250 m3 36.50
- Stub & Cleat kg 408.00
- Formwork m2 84.00
- Reinforced steel screw U32 kg 5,475.00
- Reinforced steel plain U24 kg 822.00
- Bored Pile Ø 40 cm m' 192.00
- Setting Stub ls 1.00
- Installation eathing device & counterpoise ls 1.00

DATE :
Rev.1
NAME OF BIDDER :
Page 170 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

5,169,262 1,137,238
34,462 103,385
24,123 24,123
1,503,309 601,324

204,319 204,319
136,212 272,425
408,637 40,864
2,383,677

5,169,262 51,693
24,123 482

204,319 10,216
136,212 6,811
272,425 2,724
408,637 4,086
76,012

5,169,262 930,467
24,123 12,062
2,047 2,047
441,328 110,332
482,533 72,380
1,764 52,919
74,236 59,389
2,043,187 85,133
197,508 15,801
700,813 105,122
335,083 20,105

DATE :
Rev.1
NAME OF BIDDER :
Page 171 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5
136,212 272,425
204,319 408,637
204,319 204,319
272,425 81,727
408,637 20,432
2,453,296

DATE :
Rev.1
NAME OF BIDDER :
Page 172 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

5,169,262 930,467
24,123 7,237
2,047 21,496
441,328 13,240
482,533 24,127
74,236 59,389

136,212 136,212
204,319 408,637
272,425 54,485
408,637 20,432
1,675,722

136,212 include
408,637 20,432
20,432

272,425 2,724

136,212 include
408,637 12,259
14,983

272,425 5,448

136,212 136,212
408,637 13,076
154,737

DATE :
Rev.1
NAME OF BIDDER :
Page 173 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

272,425 2,724
17,027 3,405

136,212 44,950
408,637 include
51,080

272,425 2,724
136,212 54,485

136,212 include
408,637 4,086
61,296

DATE :
Rev.1
NAME OF BIDDER :
Page 174 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

61,296 73,555

272,425 5,448
136,212 2,724
381,293 15,252

136,212 40,864
408,637 4,086
141,929

441,328 463,395

17,027 1,703

136,212 68,106
408,637 20,432
553,635

482,533 579,039

136,212 68,106
408,637 include
647,145

1,764 123,477
2,047 31,323
441,328 18,977

DATE :
Rev.1
NAME OF BIDDER :
Page 175 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5
204,319 40,864
136,212 include
408,637 include
272,425 include
214,641

2,047 15,969
441,328 13,240

204,319 38,821
136,212 51,761
408,637 include
272,425 include
119,790

DATE :
Rev.1
NAME OF BIDDER :
Page 176 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

2,047 6,654

204,319 20,432
136,212 27,242
408,637 include
272,425 include
54,328

2,047 565,047
441,328 264,797
482,533 275,044

34,053 68,106
51,080 51,080

204,319 40,864
136,212 179,800
408,637 53,123
272,425 5,448
1,503,309
150,331

2,047 759,538
441,328 220,034
482,533 374,231

34,053 include
51,080 51,080

204,319 40,864

DATE :
Rev.1
NAME OF BIDDER :
Page 177 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5
136,212 179,800
408,637 include
272,425 5,448
1,630,995

DATE :
Rev.1
NAME OF BIDDER :
Page 178 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

2,047 845,524
441,328 220,034
482,533 374,231

34,053 include
51,080 51,080

204,319 40,864
136,212 179,800
408,637 include
272,425 5,448
1,716,981

373,563 448,275
2,047 413,549
441,328 216,251

204,319 153,239
136,212 include
408,637 32,691
272,425 21,794

34,053 5,789
1,291,588

12,259 1,287,208
27,569 41,354

204,319 143,023
136,212 95,349

DATE :
Rev.1
NAME OF BIDDER :
Page 179 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5
408,637 286,046
272,425 19,070
1,872,049
18,720.49

12,259 1,287,208
27,569 41,354

204,319 143,023
136,212 95,349
408,637 286,046
272,425 19,070
1,872,049
18,720.49

DATE :
Rev.1
NAME OF BIDDER :
Page 180 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

22,034 15,038,017
22,034 8,097,394
40,395 4,847,420
22,034 771,180

204,319 2,451,824
136,212 2,724,249
408,637 817,275
34,747,359
34,747.36

34,747 104,763,286
4,086 12,320,416
117,083,702

34,747 67,757,349
4,086 7,968,428
75,725,777

34,747 45,936,008
4,086 5,402,186
51,338,194

34,747 48,125,092
4,086 5,659,627
53,784,719

DATE :
Rev.1
NAME OF BIDDER :
Page 181 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

34,747 41,870,567
4,086 4,924,080
46,794,647

5,169,262 258,463
24,123 8,443

204,319 40,864
136,212 27,242
408,637 24,518
272,425 16,345
375,876

DATE :
Rev.1
NAME OF BIDDER :
Page 182 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

333,448 343,452

449,399 32,716
469,933 34,211
681,062 170,266
170,266 include
34,053 include

136,212 7,083
408,637 4,250
408,637 2,125
340,531 3,542
204,319 2,125
599,769

3,128,635 432,645
18,720 194,693
18,720 146,020
102,159 102,159

469,933 70,490
17,027 2,554
34,053 5,108
46,367 6,955
46,367 6,955
34,053.11 34,053

136,212 7,083
408,637 4,250

DATE :
Rev.1
NAME OF BIDDER :
Page 183 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5
408,637 2,125
340,531 3,542
204,319 2,125
1,020,757

47,674 9,535
110,434 8,835
34,053 341
34,462 345

204,319 51,080
136,212 34,053
408,637 531
272,425 6,811
111,529

DATE :
Rev.1
NAME OF BIDDER :
Page 184 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

46,993 4,699
110,434 39,756

204,319 12,872
136,212 2,724
408,637 1,226
272,425 1,716
62,994

46,993 4,699
170,266 61,296

204,319 12,872
136,212 2,724
408,637 1,226
272,425 1,716
84,533

381,293 19,065

340,531 34,053
408,637 4,086
57,204

441,669 88,334

381,293 19,065

DATE :
Rev.1
NAME OF BIDDER :
Page 185 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

340,531 54,485
408,637 4,086
165,970

1,716,981 429,245
18,720 336,969
93,969.05 32,889
799,103

DATE :
Rev.1
NAME OF BIDDER :
Page 186 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

14,983 31,465
51,080 53,634
553,635 66,436
1,503,309 90,199
1,630,995 929,667
18,720 853,655
187,938 751,752
34,747 545,534
17,708 70,830
3,393,172

14,983 17,980
51,080 30,648
553,635 44,291
1,503,309 60,132
1,630,995 587,158
18,720 539,150
187,938 563,814
34,747 272,767
17,708 70,830
2,186,771

14,983 8,990
51,080 15,324
553,635 33,218
1,503,309 45,099
1,630,995 391,439
18,720 359,433
187,938 413,464
34,747 136,383
17,708 35,415

DATE :
Rev.1
NAME OF BIDDER :
Page 187 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5
1,438,766

14,983 34,462
51,080 58,742
553,635 71,973
1,503,309 97,715
1,630,995 1,174,317
18,720 1,078,300
187,938 789,340
34,747 545,534
17,708 70,830
3,921,212

DATE :
Rev.1
NAME OF BIDDER :
Page 188 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

14,983 31,465
51,080 53,634
553,635 66,436
1,503,309 90,199
1,630,995 717,638
18,720 658,961
187,938 751,752
34,747 545,534
34,747 1,605,328
17,708 70,830
4,591,777

14,983 17,980
51,080 30,648
553,635 44,291
1,503,309 60,132
1,630,995 391,439
18,720 359,433
187,938 563,814
34,747 272,767
34,747 1,035,471
17,708 35,415
2,811,391

14,983 4,795
51,080 8,173
553,635 22,145
1,503,309 30,066
1,630,995 195,719
18,720 179,717
187,938 300,701

DATE :
Rev.1
NAME OF BIDDER :
Page 189 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5
34,747 222,383
34,747 403,069
17,708 35,415
1,402,184

14,983 10,908
51,080 11,156
553,635 44,291
119,790 215,622
54,328 97,790
1,291,588 568,299
948,065

DATE :
Rev.1
NAME OF BIDDER :
Page 190 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

14,983 5,259
51,080 5,379
553,635 33,218
119,790 131,769
54,328 59,761
214,641 300,497
535,883

14,983 9,589
51,080 26,153
553,635 44,291
25,240 25,240
4,308 8,617
482,533 115,808
229,698

14,983 13,335
51,080 13,638
553,635 44,844
119,790 143,748
214,641 515,138
730,703

14,983 3,596
51,080 3,678
537,755 537,755
178,211 335,037
1,630,995.14 260,959
18,720 179,717
187,938.10 165,386
204,319 204,319
1,690,446

DATE :
Rev.1
NAME OF BIDDER :
Page 191 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

14,983 3,596
51,080 3,678
424,245 424,245
178,211 201,379
1,630,995 260,959
18,720 179,717
93,969.05 82,693
204,319 include
1,156,266

DATE :
Rev.1
NAME OF BIDDER :
Page 192 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

14,983 35,960
51,080 36,777
553,635 77,509
1,503,309 105,232
178,211 8,981,849
230,426 6,590,185
22,034 2,071,170
1,630,995 1,272,176
18,720 1,168,159
187,938.10 1,353,154
119,790 383,328
54,328 173,850
216,169 216,169
34,747 2,369,770
340,531 340,531
204,319 612,956
136,212 408,637
26,197,412

14,983 10,788
51,080 11,033
553,635 44,291
1,503,309 60,132
214,641 515,138
119,790 574,991
54,328 include
1,630,995 685,018
18,720 629,009
22,034 include
27,569 include
84,533 include
2,530,400

DATE :
Rev.1
NAME OF BIDDER :
Page 193 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

14,983 375
3,128,635 187,718
1,503,309 include
553,635 include
188,093

14,983 749
3,128,635 312,863
1,503,309 include
553,635 include
313,613

DATE :
Rev.1
NAME OF BIDDER :
Page 194 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

163,455 237,010
40,728 162,910
20,432 20,432
24,123 2,654

204,319 10,216
204,319 51,080
136,212 13,621
408,637 2,043
272,425 1,362
501,327

170,266 85,133
51,080 178,779
20,432 20,432
24,123 2,654

204,319 10,216
204,319 51,080
136,212 13,621
408,637 2,043
272,425 1,362
365,319

53,940 53,940
61,296 2,452
34,462 1,378

204,319 16,345
136,212 27,242

DATE :
Rev.1
NAME OF BIDDER :
Page 195 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5
408,637 4,086
105,445

183,751 194,776
2,047 19,654
441,328 19,860
3,822 764

204,319 24,518
136,212 32,691
408,637 4,904
272,425 3,269
300,436

DATE :
Rev.1
NAME OF BIDDER :
Page 196 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

168,767 178,893
2,047 20,473
441,328 19,860
3,822 3,822

204,319 26,561
136,212 35,415
408,637 5,312
272,425 3,542
293,878

157,189 166,621
2,047 20,063
441,328 19,860
3,822 3,822

204,319 25,540
136,212 34,053
408,637 5,312
272,425 3,542
278,812

88,538 295,097
2,047 2,334
441,328 1,324
3,822 382

204,319 18,389
136,212 12,259
408,637 2,043

DATE :
Rev.1
NAME OF BIDDER :
Page 197 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5
272,425 2,452
334,280

88,538 234,626
2,047 2,539
441,328 1,324

204,319 18,389
136,212 12,259
408,637 2,043
272,425 2,452
273,631

DATE :
Rev.1
NAME OF BIDDER :
Page 198 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

299,667 314,651
5,506 44,046

204,319 153,239
136,212 20,432
408,637 2,452
272,425 21,794
556,613

214,126 224,832
5,506 44,046

204,319 include
136,212 20,432
408,637 2,452
272,425 include
291,762

299,667 359,601
5,506 33,034

204,319 204,319
136,212 13,621
408,637 20,432
272,425 27,242
658,249

214,126 256,951

DATE :
Rev.1
NAME OF BIDDER :
Page 199 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5
5,506 33,034

204,319 204,319
136,212 13,621
408,637 20,432
272,425 27,242
555,600

115,781 121,570
27,569 82,708

204,319 10,216
136,212 20,432
408,637 3,269
272,425 1,362
239,557

DATE :
Rev.1
NAME OF BIDDER :
Page 200 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

59,593 65,552
24,123 2,412

136,212 13,621
408,637 2,043
272,425 5,448
89,077

98,690 34,542
117,483 117,483

136,212 6,811
408,637 1,022
159,857

20,432 102,159

136,212 16,345
408,637 2,452
272,425 3,269
124,226

10,900,971 10,900,971

136,212 449,501
408,637 65,382
272,425 2,724
11,418,579

DATE :
Rev.1
NAME OF BIDDER :
Page 201 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

3,657,304 3,657,304

136,212 136,212
408,637 20,432
272,425 27,242
3,841,191

1,589,599 1,589,599

136,212 163,455
408,637 24,518
272,425 40,864
1,818,436

DATE :
Rev.1
NAME OF BIDDER :
Page 202 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

716,477 716,477

136,212 163,455
408,637 24,518
272,425 40,864
945,314

14,983 152,830
51,080 364,709
553,635 124,568
1,503,309 169,122
1,716,981 3,777,357
18,720 3,294,807
18,720 1,235,553
187,938 1,653,855
32,861 23,003
68,106 272,425
11,068,229

14,983 187,292
51,080 446,947
553,635 179,378
1,503,309 243,536
1,716,981 4,120,753
18,720 3,594,335
18,720 1,347,876
187,938 1,804,206
32,861 23,003
93,510 140,265
68,106 272,425
12,360,015

DATE :
Rev.1
NAME OF BIDDER :
Page 203 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

14,983 521,421
51,080 1,244,301
553,635 907,962
1,503,309 1,232,714
1,716,981 11,933,015
18,720 10,408,594
18,720 3,903,223
187,938 3,833,937
32,861 98,584
93,510 561,059
68,106 817,275
35,462,085

DATE :
Rev.1
NAME OF BIDDER :
Page 204 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

14,983 187,292
51,080 446,947
553,635 179,378
1,503,309 243,536
1,716,981 4,120,753
18,720 3,594,335
18,720 1,347,876
187,938 1,804,206
32,861 23,003
93,510 140,265
68,106 272,425
12,360,015

14,983 521,421
51,080 1,244,301
553,635 907,962
1,503,309 1,232,714
1,716,981 11,933,015
18,720 10,408,594
18,720 3,903,223
187,938 3,833,937
32,861 98,584
93,510 561,059
68,106 817,275
35,462,085

14,983 532,209
51,080 362,870
553,635 2,072,811
1,503,309 2,814,195
1,716,981 52,196,210
18,720 56,910,300
187,938 8,194,101

DATE :
Rev.1
NAME OF BIDDER :
Page 205 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5
34,747 25,372,521
148,455,219

14,983 606,826
51,080 620,618
553,635 1,079,589
1,503,309 1,465,727
1,716,981 38,460,366
18,720 41,933,905
187,938 21,049,067
119,790 14,231,035
54,328 6,454,166
125,901,299

DATE :
Rev.1
NAME OF BIDDER :
Page 206 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

14,983 17,980
51,080 18,389
553,635 55,364
1,503,309 75,165
1,716,981 1,030,188
18,720 673,938
18,720 449,292
187,938 789,340
32,861 65,723
93,510 374,039
68,106 272,425
3,821,842

14,983 275,694
51,080 281,960
553,635 179,378
1,503,309 243,536
1,716,981 4,120,753
18,720 2,695,751
18,720 1,797,167
187,938 1,268,582
32,861 65,723
93,510 374,039
68,106 272,425
11,575,009

14,983 52,741
51,080 53,940
553,635 108,513
1,503,309 147,324
1,716,981 2,472,452
18,720 1,617,451
18,720 1,078,300

DATE :
Rev.1
NAME OF BIDDER :
Page 207 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5
187,938 902,103
68,106 272,425
6,705,249

14,983 152,830
51,080 364,709
553,635 124,568
1,503,309 169,122
1,716,981 3,777,357
18,720 3,294,807
18,720 1,235,553
187,938 1,653,855
32,861 23,003
68,106 272,425
11,068,229

DATE :
Rev.1
NAME OF BIDDER :
Page 208 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

14,983 48,546
51,080 49,649
553,635 318,894
1,503,309 432,953
1,716,981 5,837,734
18,720 3,818,981
18,720 2,545,987
187,938 1,090,041
32,861 65,723
93,510 374,039
29,966,737.78 29,966,738
44,549,285

14,983.37 756,660
51,080 1,805,666
553,635 1,882,361
1,503,309.32 2,555,626
1,716,980.61 30,390,557
18,720 26,508,219
18,720.49 13,254,109
187,938.10 5,262,267
32,861.25 65,723
68,106 1,089,700
83,570,887

14,983 458,491
51,080 1,094,126
553,635 1,660,906
1,503,309 2,254,964
1,716,981 23,608,483
18,720 20,592,543
18,720 10,296,271

DATE :
Rev.1
NAME OF BIDDER :
Page 209 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5
187,938 4,134,638
32,861 65,723
68,106 1,089,700
65,255,846

14,983 275,694
51,080 657,906
553,635 1,328,725
1,503,309 1,803,971
1,716,981 13,392,449
18,720 11,681,588
18,720 5,840,794
187,938 3,382,886
32,861 65,723
68,106 1,089,700
39,519,435

34,747 616,244,407
4,018 71,263,967
687,508,374

DATE :
Rev.1
NAME OF BIDDER :
Page 210 of 237
SIGNATURE OF BIDDER :
NGUNAN GI 150 KV TELUK NAGA II
: DAFTAR HARGA DAN KUANTITAS (BOQ)
SIAN 3.3 : ANALISA HARGA SATUAN

UNIT PRICE TOTAL PRICE

5 6=4x5

20,432 16,345,493
76,012 60,809,812

14,983 2,592,123
51,080 8,836,782
553,635 2,103,815
1,503,309 5,712,575
1,630,995 59,531,323
34,747 14,176,922
187,938 15,786,800
18,720 102,494,702
18,720 15,388,246
599,769 115,155,580
871,760 871,760
871,760 871,760
420,677,693

DATE :
Rev.1
NAME OF BIDDER :
Page 211 of 237
SIGNATURE OF BIDDER :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.4 : DAFTAR HARGA SATUAN

NO. UNIT PRICE MATERIAL, REMUNERATION AND RENT OF EQUIPMENT UNIT


I MATERIAL :
1 Portland Cemen (PC) kg
2 Colour Cement kg
3 Red brick unit
4 Batu Belah 20-30 cm m3
5 Split m3
6 Gravel m3
7 Sangravel (Sirtu) m3
8 Sand m3
9 Soil m3
10 BBM / solar litre
11 Plain reinforced steel U 24 - BJTP 24 kg
12 Sceew reinforced steel U 32 - BJTD 35 kg
13 Galvanized steel angle HTS kg
14 Galvanized steel angle MS kg
15 Galvanized Steel Plate kg
16 Galvanis Bolt and Nuts kg
17 Paint of steel kg
18 Paint of wooden kg
19 Paint of wall (Interior) kg
20 Paint of wall Weathershield (eksterior) kg
21 Thinner litre
22 Kuas / Rol no
23 Plamur of wall kg
24 Amplas Besi sheet
25 Amplas Kayu sheet
26 Door closer unit
27 Hinge/Engsel for door (1 set= 3 pcs) set
28 Hinge/Engsel for window (1 set= 2 pcs) set
29 Door lock set
30 Grendel for window (1 set= 2 pcs) no
31 Wind hook of window (1 set = 2 pcs) set
32 Palm fibre kg
33 Concrete wire kg
34 Wire mesh M4 lembar
35 Wire mesh M6 lembar
36 Wire mesh M8 lembar
37 Barbed wire kg
38 Wooden/kayu m3
39 Floor tile ceramic 200 x 200 mm m2
40 Ceramic floor tiles 300 x 300 mm m2
41 Wall tile ceramic 200 x 250 mm m2
42 Floor tile ceramic 300 x 300 mm m2

Date :
Rev.1
Name of Bidder :
PAGE 212 of 237
Signature of Bidder :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.4 : DAFTAR HARGA SATUAN

NO. UNIT PRICE MATERIAL, REMUNERATION AND RENT OF EQUIPMENT UNIT

43 Plint tiles 150 x 300 mm no


44 Stepnosing 100 x 300 mm no
45 Glass 5 mm m2
46 Naturally paint (Meni) kg
47 Minyak bekisting litre
48 Fence BRC height 1,50 m m'
49 Fence BRC height 1,90 m m'
50 Nail kg
51 Nail drat no
52 Single Gate BRC height 1,50 m width 1,10 m complete unit
53 Double Gate BRC height 1,50 m width 3 m complete unit

Date :
Rev.1
Name of Bidder :
PAGE 213 of 237
Signature of Bidder :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.4 : DAFTAR HARGA SATUAN

NO. UNIT PRICE MATERIAL, REMUNERATION AND RENT OF EQUIPMENT UNIT

54 Galvanized Steel Pipe Dia 2,5 inch m'


55 Galvanized Steel Pipe Dia 3 inch m'
56 Pipa Concrete dia 30 cm m'
57 PVC Pipe dia 2 AW" m'
58 PVC Pipe dia 4 AW" m'
59 PVC Pipe dia 6 AW" m'
60 Zinc 0.8 x 1.8 x 0.3mm sheet
61 Asbes Roof 150x105 cm sheet
62 Roofing Klip-lock Hi-Ten t=0.50 mm m2
63 Roofing Spandek Colorbond m2
64 Nok Standard Hi-Ten m'
65 Nok Spandek Colorbond m'
66 Downlight fitting Led 9 watt inculding installation, wiring and switch no
67 Emergency lighting lamp 30 W incl installation wiring no
68 Stop contact incl installation wiring no
69 Plywood/multiplex 120 x 240, t=12 mm sheet
70 Akustik panel 120 x 60 (plafon) sheet
71 Gypsum board 9 mm sheet
72 Listplank Superplank (metal) m'
73 Baja Hollow 40.40.08 m'
74 Baja Hollow 40.20.08 m'
75 Alumunium Frame & hanger m'
76 List profil (wooden) m'
77 Lem Kayu kg
78 Tepung gypsum kg
79 Glasswool t=10 cm, aluminium foil (single sided) with 2 (two) layer m2
80 Roof mesh kg
81 Closet Duduk with eco washer complete (equal toto) no
82 Closet Jongkok complete (equal toto) no
83 Urinoir complete (equal toto) no
84 Wastafel complete (equal toto) no
85 Wash sink complete no
86 Tempat tisu roll (equal toto) no
87 Tempat sabun (equal toto) no
88 Gantungan Pakaian / hook (equal toto) no
89 Landscaping (sodding grass) m2
90 Stop contact incl installation wiring no
91 Panel Box MCB Complete set
92 Exhaus fan wall 60 W/220 Volt (16") industrial, include installation and wiring no
93 Exhaus fan ceiling 40 W/220 Volt (10") low noice, include installation and wiring no
94 Anchor bolt Ф 32-36 mm pcs
95 Anchor bolt Ф 20-24 mm pcs
96 Waterproofing kg

Date :
Rev.1
Name of Bidder :
PAGE 214 of 237
Signature of Bidder :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.4 : DAFTAR HARGA SATUAN

NO. UNIT PRICE MATERIAL, REMUNERATION AND RENT OF EQUIPMENT UNIT

97 Serat fiber m2
98 Floorhardener ex sika kg
99 Raised Floor m2
100 Driven Pile 30 x 30 cm K 450 m'
101 Dynabolt 10mm bh
102 Hoe bh
103 AC split 2 PK include installation and wiring unit
104 AC split 1 PK include installation and wiring unit

Date :
Rev.1
Name of Bidder :
PAGE 215 of 237
Signature of Bidder :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.4 : DAFTAR HARGA SATUAN

NO. UNIT PRICE MATERIAL, REMUNERATION AND RENT OF EQUIPMENT UNIT

II REMUNERATION
1 Worker man/day
2 Surveyor man/day
3 Supervisor man/day
4 Operator man/day
5 Brick Layer man/day
6 Steel worker/welder man/day
7 Carpenter man/day
8 Paint worker man/day
9 Mechanic man/day
10 Asphalt worker man/day
11 Worker Chief man/day

III RENT OF EQUIPMENT


1 Mollen of machine hour
2 Pick Up hour
3 Buldozer hour
4 Drilling Machine hour
5 Stamper hour
6 Total Station hour
7 Crane (crawler 10-15 ton) hour
8 Tremie Pipa hour
9 Concrete Vibrator hour
10 Jack Hammer hour
11 Gergaji bh
12 Tripod unit/day
13 Vibro Roller hour
14 Water Tank Truck unit/day
15 Hidrolic Pile Driver unit/day

Date :
Rev.1
Name of Bidder :
PAGE 216 of 237
Signature of Bidder :
GUNAN GI 150 KV TELUK NAGA II
DAFTAR HARGA DAN KUANTITAS (BOQ)
AN 3.4 : DAFTAR HARGA SATUAN

PRICE
(Rp.)

2,047
3,822
1,764
373,563
482,533
482,533
441,669
441,328
61,296
12,940
12,259
12,259
22,034
22,034
22,034
40,395
110,434
34,462
110,434
170,266
34,462
34,053
46,993
6,422
6,422
783,222
216,169
144,113
340,531
156,644
78,322
4,308
27,569
202,957
424,983
755,979
27,569
5,169,262
183,751
168,767
157,189
183,751

Date :
Rev.1
Name of Bidder :
PAGE 217 of 237
Signature of Bidder :
GUNAN GI 150 KV TELUK NAGA II
DAFTAR HARGA DAN KUANTITAS (BOQ)
AN 3.4 : DAFTAR HARGA SATUAN

PRICE
(Rp.)
88,538
88,538
197,508
47,674
12,259
424,245
537,755
24,123
5,506
1,498,337
4,495,011

Date :
Rev.1
Name of Bidder :
PAGE 218 of 237
Signature of Bidder :
GUNAN GI 150 KV TELUK NAGA II
DAFTAR HARGA DAN KUANTITAS (BOQ)
AN 3.4 : DAFTAR HARGA SATUAN

PRICE
(Rp.)
178,211
230,426
25,240
32,861
93,510
207,520
214,126
74,236
299,667
214,126
299,667
214,126
704,899
1,089,700
442,690
335,083
163,455
170,266
238,372
51,080
29,286
40,728
53,940
61,296
16,345
115,781
27,569
10,900,971
885,381
3,657,304
1,589,599
716,477
340,531
340,531
340,531
74,917
340,531
6,129,560
12,940,182
4,767,436
68,106
68,106
98,690

Date :
Rev.1
Name of Bidder :
PAGE 219 of 237
Signature of Bidder :
GUNAN GI 150 KV TELUK NAGA II
DAFTAR HARGA DAN KUANTITAS (BOQ)
AN 3.4 : DAFTAR HARGA SATUAN

PRICE
(Rp.)
117,483
20,432
2,084,050
674,252
17,708
272,425
19,069,742
10,215,933

Date :
Rev.1
Name of Bidder :
PAGE 220 of 237
Signature of Bidder :
GUNAN GI 150 KV TELUK NAGA II
DAFTAR HARGA DAN KUANTITAS (BOQ)
AN 3.4 : DAFTAR HARGA SATUAN

PRICE
(Rp.)
-
-
136,212
408,637
408,637
340,531
204,319
204,319
204,319
204,319
204,319
204,319
272,425
-
-
34,053
136,212
272,425
469,933
17,027
46,367
449,399
17,027
51,080
936,461
204,319
204,319
381,293
136,212
3,759,463

Date :
Rev.1
Name of Bidder :
PAGE 221 of 237
Signature of Bidder :
PEMBANGUNAN GI 150 KV TELUK NAGA II
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.5 : REKAPITULASI HARGA

NO. DESCRIPTION
(1) (2)

1 TOTAL PRICE FOR ELEKTROMEKANIK WORK GI 150 KV

2 TOTAL PRICE FOR CIVIL WORK GI 150 KV

SUB TOTAL
PPN 10 %
TOTAL

Date :
Name of Bidder :
Signature of Bidder :
S (BOQ)

TOTAL PRICE
(Rp)
(3)

73,119,980,000

33,800,020,000

106,920,000,000
10,692,000,000
117,612,000,000

Date :
Name of Bidder :
Signature of Bidder :
DAFTAR ISIAN 1.2 : BILL OF QUANTITY FOR CIVIL WORKS
4. BILL NO 4 : ANALYSIS UNIT PRICE
UNIT PRICE MATERIAL, REMUNERATION AND RENT OF EQUIPMENT

UNIT PRICE MATERIAL, REMUNERATION AND RENT PRICE


NO. UNIT
OFEQUIPMENT (Rp.)

I MATERIAL :
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46

Name of Bidder :Signed of Bidder : UP. 224 of 237


DAFTAR ISIAN 1.2 : BILL OF QUANTITY FOR CIVIL WORKS
4. BILL NO 4 : ANALYSIS UNIT PRICE
UNIT PRICE MATERIAL, REMUNERATION AND RENT OF EQUIPMENT

UNIT PRICE MATERIAL, REMUNERATION AND RENT PRICE


NO. UNIT
OFEQUIPMENT (Rp.)

47
48
49
50
51
52

Name of Bidder :Signed of Bidder : UP. 225 of 237


DAFTAR ISIAN 1.2 : BILL OF QUANTITY FOR CIVIL WORKS
4. BILL NO 4 : ANALYSIS UNIT PRICE
UNIT PRICE MATERIAL, REMUNERATION AND RENT OF EQUIPMENT

UNIT PRICE MATERIAL, REMUNERATION AND RENT PRICE


NO. UNIT
OFEQUIPMENT (Rp.)

53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78

II REMUNERATION
1
2
3
4
5
6
7
8
9
10

Name of Bidder :Signed of Bidder : UP. 226 of 237


DAFTAR ISIAN 1.2 : BILL OF QUANTITY FOR CIVIL WORKS
4. BILL NO 4 : ANALYSIS UNIT PRICE
UNIT PRICE MATERIAL, REMUNERATION AND RENT OF EQUIPMENT

UNIT PRICE MATERIAL, REMUNERATION AND RENT PRICE


NO. UNIT
OFEQUIPMENT (Rp.)

III RENT OF EQUIPMENT


1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25

Name of Bidder :Signed of Bidder : UP. 227 of 237


: BILL OF QUANTITY FOR CIVIL WORKS
NO 4 : ANALYSIS UNIT PRICE
REMUNERATION AND RENT OF EQUIPMENT

REMARK

Name of Bidder :Signed of Bidder : UP. 228 of 237


: BILL OF QUANTITY FOR CIVIL WORKS
NO 4 : ANALYSIS UNIT PRICE
REMUNERATION AND RENT OF EQUIPMENT

REMARK

Name of Bidder :Signed of Bidder : UP. 229 of 237


: BILL OF QUANTITY FOR CIVIL WORKS
NO 4 : ANALYSIS UNIT PRICE
REMUNERATION AND RENT OF EQUIPMENT

REMARK

Name of Bidder :Signed of Bidder : UP. 230 of 237


: BILL OF QUANTITY FOR CIVIL WORKS
NO 4 : ANALYSIS UNIT PRICE
REMUNERATION AND RENT OF EQUIPMENT

REMARK

Name of Bidder :Signed of Bidder : UP. 231 of 237


DAFTAR ISIAN 1.2 : BILL OF QUANTITY FOR CIVIL WORKS
4. BILL NO 4 : ANALYSIS UNIT PRICE
BREAKDOWN PRICE FOR CIVIL WORKS
UNIT PRICE

UNIT PRICE
NO DESCRIPTION UNIT QTY LOCAL CURRENCY
PORTION
(RUPIAH)

Name of Bidder :Signed of Bidder : Bdprice 232 of 237; R-1


DAFTAR ISIAN 1.2 : BILL OF QUANTITY FOR CIVIL WORKS
4. BILL NO 4 : ANALYSIS UNIT PRICE
BREAKDOWN PRICE FOR CIVIL WORKS
UNIT PRICE

UNIT PRICE
NO DESCRIPTION UNIT QTY LOCAL CURRENCY
PORTION
(RUPIAH)

Name of Bidder :Signed of Bidder : Bdprice 233 of 237; R-1


2 : BILL OF QUANTITY FOR CIVIL WORKS
NO 4 : ANALYSIS UNIT PRICE
DOWN PRICE FOR CIVIL WORKS
UNIT PRICE

TOTAL PRICE
LOCAL

(RUPIAH)

Name of Bidder :Signed of Bidder : Bdprice 234 of 237; R-1


2 : BILL OF QUANTITY FOR CIVIL WORKS
NO 4 : ANALYSIS UNIT PRICE
DOWN PRICE FOR CIVIL WORKS
UNIT PRICE

TOTAL PRICE
LOCAL

(RUPIAH)

Name of Bidder :Signed of Bidder : Bdprice 235 of 237; R-1


4. BILL NO 4 : ANALYSIS UNIT PRICE
Breakdown Price for Foundation and Steel Structure for 150 kV Switchgear

Foundation : .....................................
UNIT PRICE
NO DESCRIPTION UNIT QTY LOCAL CURRENCY
PORTION
(RUPIAH)

TOTAL

Note:
1. Breakdown Price for Foundation (Fixed Price)
2. Shall be installed in BILL NO 2

Name of Bidder :Signed of Bidder : B.Price.Foundation : 236 of 237 ; R-1


BILL NO 4 : ANALYSIS UNIT PRICE
Foundation and Steel Structure for 150 kV Switchgear

TOTAL PRICE

(RUPIAH)

Name of Bidder :Signed of Bidder : B.Price.Foundation : 237 of 237 ; R-1