1.1.2. Scenario
You are required to navigate Prometheus, reschedule a task and created relationships.
1.1.3. Trigger
You need to schedule tasks and are not familiar with the Prometheus tool.
1.1.4. Pre-requisites
N/A
There is no menu path for this transaction. Use transaction code /PGPNL/IGS to access
Prometheus
Step Action
Step Action
The input fields in the Application Settings section control how the data is displayed in
Scheduler.
Display Setting - When a variant is entered in this field, the saved Display Setting
options will be loaded when the selection is executed. The Edit Display Setting
button can be used to view and edit the selected Display Setting directly from the
selection screen.
Layout - A layout that has been saved for viewing the List Edit report can be entered
here.
Capacity Layout - Allows the user to select a layout that has been saved for viewing the
Resource List in the Planning Board.
Shift Updater Layout - Allows the user to select the layout for the Shift Updater.
Scheduling Date Range - When a date range is entered here, Scheduler will load the
objects within that range (that satisfy any additional search criteria entered). If no dates
are entered, all objects fulfilling the additional search criteria will be loaded.
Capacity Date Range - If no dates are provided here, Scheduler will attempt to calculate
capacities for all dates that are loaded.
Days in the Future/Past - These inputs can be used to pad the Planning Board with
additional days. Days in the Future will display the specified amount of days past the
latest end date of the objects loaded. Days in the Past will display the specified amount
of days prior to the earliest start date of the objects loaded.
Enter Planning Board or Enter List Edit - The option chosen using the radio button will
determine which Scheduler view is displayed first when the selection is executed. Both
views have a button that allows the user to access to the other view without returning to
the selection screen.
Data Selection Tab Options - The checkboxes display the modules that are available to
be loaded into Scheduler. A checked box will make a selection tab visible in the bottom
section of the selection screen.
There are two modules that are loaded into the Scheduler:
Project Systems
Plant Maintenance
A variant can be set up and saved with your basic parameters. Saved variants can be
retrieved via the Goto menu.
Step Action
(1) Click on the Goto menu item to view the drop-down menu.
Step Action
Hover over Variants from the drop-down selection and click on the
(1) Get button from the drop-down menu.
Step Action
Step Action
Step Action
Step Action
Step Action
1. Item Details
2. Gantt Chart
3. Resource List
4. Capacity.
1. Item Details:
The top left quadrant displays the first 11 columns from the List Edit screen with
the same layout.
Users can drill into an order or operation by double-clicking the respective row.
Direct edits can also be made in the Item Details by clicking on an applicable field.
The first column allows the user to collapse and expand rows.
Double-clicking on a column header allows the user to change the layout.
2. Gantt Chart:
The top right quadrant displays a graphical representation of the Item Details section,
with the dates displayed at the top of the quadrant. Users can perform functions such as
drag and drop and create relationships.
3. Resource List:
The bottom left quadrant displays the resources assigned to the objects brought
into the Planning Board, which can include work centers, HR resources assigned
to the work centers, and equipment PRTs.
A user can drill into a work center in standard SAP by double-clicking the row.
Double clicking an HR resource will take the user to the Shift Updater table for the
work center.
Double-clicking a column header allows the user to change the layout, as well as
apply a sort.
4. Capacity:
The lower right quadrant shows the capacity utilisation and available capacity by
work center for each period.
Capacity utilisation is color-coded using a stoplight system – green indicates
under capacity, yellow is a configurable warning zone, and red indicates over
capacity.
A grey cell indicates the work center or HR resource is non-working and has no
available hours during that period.
A white cell indicates the work center or HR resource has not been assigned work
during that period.
Double-clicking a cell in this section will run the Inspect Resource Capacity report,
which filters the Gantt Chart to display only the objects that make up that selected
capacity period.
The List Edit button allows you to switch to the List Edit format.
The Edit Display Settings button allows you to edit the current display setting
options.
The Layouts button allows you to change, select, and save layouts for the List
Edit/Item Details, as well as for the Capacity quadrant.
The Refresh button refreshes all data and checks current values in the Item
Details.
The Undo button allows you to undo drag and drop movements.
The Redo button allows you to redo drag and drop movements.
The Zoom Out button decreases the viewing magnification of the Planning Board.
The Zoom In button increases the viewing magnification of the Planning Board.
The Select All button selects all items on the Planning Board, except relationship
lines.
The Scroll to Node button. If a row in the Item Details is selected, the Gantt Chart
will scroll to the date on which the object is scheduled.
The Mass Change button allows you to mass change any configured field from the
Planning Board/List Edit for the selected objects.
The HR Capacity Assignment button allows you to edit the personnel assigned
to the selected operation(s). Drop-down allows you to remove all personnel.
The Capacity Planner button allows you to display the daily capacities, as well as a
weekly summation, in a tabular format for all operations.
The XF Function button opens the S-Curve Analysis. Drop-down allows you to
open the Progress Tracking tool.
The Auto Level Orders button opens the Auto Level pop-up window.
The Split Operations button opens the Split Operations window for a selected
operation.
The blue line indicates the Work Order Header and the white lines are the
operations/tasks within the Work Order.
The area on the right is called the Planning Board and also displays the date and
calendar week.
The bottom section of the screen displays the resource work center weekly capacity
utilisation. The white indicates that no work has been assigned the work center yet.
We will now discuss the Menu Toolbar and relevant Menu items for Prometheus
Scheduler.
Step Action
(1) Click on the Selection Actions menu item to view the drop-down
menu.
Step Action
Step Action
The Simulation Mode allows you to simulate a scenario without effecting any change in
SAP. If the scenario is an efficient and desirable one, you may execute it.
Step Action
(1) Click on the System menu item to display the system drop-down menu.
Step Action
Step Action
Step Action
(1) Click on the Exit button to return to the SAP Easy Access screen.