Sunteți pe pagina 1din 4

CURRICULUM VITAE

1. Proposed Position : Mechanical Engineer


2. Name of Firm : PT. Prima Layanan Nasional Enjiniring
3. Name of Personnel : TOYO
4. Date of Birth : October 29th, 1958 Nationality : Indonesian
5. Education : Bachelor’s Degree in Mechanical Engineering, Class of 1985,
Brawijaya University, Malang ( East Java )

6. Membership of Professional Associations:


- N/A
7. Proficiency Training :
- N/A
8. Countries of Work Experience : Indonesia
9. Languages : Speaking Reading Writing
- Indonesian Native Native Native
- English Good Good Good

10. Work Experiences


From : 2013 to present
Employer : PT Prima Layanan Nasional Enjiniring (PLN Enjiniring)
Responsibility :
- Review Project Management which has been submitted by Contractor.
- Review erection procedure, ITP and WPS which has been submitted by
Contractor.
- Review Monthly progress report in connection with claim of Contractor.
- Review schedule and progress every week included material delivery,
manpower and equipment with Contractor.
- Review Site issue every week with Contractor.
- Site Weekly meeting with Contractor.
- HSE Weekly meeting with Contractor.
Client : PT PLN UIP IX
Position Held : Co PTL

From : Oct, 2011 to Oct, 2013


Project title : Spining Fiber Plant Unit # 5
Employer : PT.SDM-PRIME RESOURCES, Jakarta.
Client : PT.SOUTH PACIFIC VISCOSE, Purwakarta ( West Java )
Responsibility :
- Review Project Management which has been submitted by Contractor.
- Review erection procedure, ITP and WPS which has been submitted by
Contractor.
- Review Monthly progress report in connection with claim of Contractor.
- To support problem solving if piping system design can not be implemented on site.
- Joint inspection for piping system included punch list, Hydro test, Painting and
Insulation.
Position held : Mechanical Engineer

From : Mar,2008 to Oct, 2011


Project title : Coal Fire steam Power Plant 2 x ( 300 – 400 MW ) Rembang (Mid Java )
Employer : PT.ZELAND PRIAMANAYA TRONOH, Malaysia (Main Contractor)
Client : PT PLN
Responsibility :
- Reviewing Project Management which has been submitted by Sub-Contractor.
- Reviewing ITP, method statement erection equipment or Site plan, WPS for Steam
Turbine Area which Have been proposed by Sub-Contractor before submitted to
The Client.
- Controlling Sub-Contractor in connection with actual progress work and Planning.
- Joint inspection with Client for piping system included punch list, Hydro test, Painting
Insulation and Embedment of Steam Turbine Foundation.
Position held : Mechanical Engineer

From : Jan, 2006 to Nov, 2007


Project title : Rehabilitation project for Muara Karang Steam Power Plant Unit # 3 & 4
( 2 x 200 MW ), Suralaya Steam Power Plant Unit # 1 & 2, Paiton Steam
Power Plant Unit # 1 & 2.
Employer : PT.WIGUNA KARYA TATA, Jakarta
Client : PT.PLN Jasa Enjiniring
Responsibility :
- Reviewing price of equipment which has been proposed Contractor to PLN.
- Recalculate price of equipment with using last price power plant parts in Indonesia
to compare Contractor proposal price.
- Review Bid Document of Rehabilitation for Muara Karang Steam Power Plant
Unit # 3 & 4 ( 2 x 200 MW ), Suralaya Steam Power Plant Unit # 1 & 2, Paiton Steam
Power Plant Unit # 1 & 2.
Position held : Mechanical Engineer

From : March, 2002 to March, 2003


Project title : Major Maintenanace of Smelting Plant.
Employer : PT.UPI, Gresik ( East Java )
Client : PT.SMELTING, Gresik ( East Java )
Responsibility :
- Supervision shut down for major maintenance include HRSG and smelting plant.
Position held : Mechanical Engineer

From : Oct, 1997 to Jul, 1999


Project title : Paiton Coal Fire Steam Power Plant ( 2x615MW ).
Employer : PT PAITON ENERGY, Probolinggo ( East Java ).
Client : PT PAITON ENERGY, Jakarta
Responsibility :
- Supervision for Equipment, Aux.equipment and piping system at Main Building
or Steam Turbine area.
- Review erection procedure, ITP and WPS to controlling construction activity.
- Review Monthly progress work which is proposed by Contractor.
- Joint inspection for piping system included punch list, Hydro test , Insulation and
Painting.
Position held : Mechanical Engineer

From : March,1995 to Feb, 1997


Project title : Grati Pasuruan Combine Cycle Power Plant ( 600 MW ).
Employer : PT MITZA EWBANK PREEZE IN ASSOCIATED with PT ASIANENCO
CONSULT – MONENCOAGRA, Jakarta.
Client : PT PLN
Responsibility :
- Supervision for Equipment, Aux.equipment and piping system at Steam Turbine
Area.
- Reviewing ITP, method statement erection equipment or Site plan, WPS for Steam
Turbine Area which Have been submitted by Contractor.
- Joint inspection for piping system included punch list, Hydro test , Insulation and
Painting.
Position held : Mechanical Engineer

From : Jan, 1991 to March, 1993


Project title : Paiton Coal Fire Power Plant Unit 1 & 2 ( 2 x 300 MW ).
Employer : PT.INDRA KARYA CONSULTING ENGINEERING, Malang ( East Java ).
Client : PT.PLN
Responsibility :
- Supervision for Equipment and piping system construction at Boiler area and ESP.
- Joint inspection for piping system included punch list, Hydro test, insulation and
Painting.
Position held : Mechanical Engineer

From : Feb, 1989 to Jan, 1991


Project title : Pulp and Paper Plant
Employer : PT.PAKERIN, Mojosari Mojokerto ( East Java )
Client : PT.PAKERIN, Surabaya.
Responsibility :
- Staff of Mechanical Department to support pulp and paper plant Maintenance.
Position held : Mechanical Engineer

From : Jan, 1986 to Feb, 1989


Project title : Rehabilitation Project PG.KEDAWUNG, Pasuruan ( East Java ).
Employer : PT.TRISULA ABADI, Surabaya.
Client : PTP XXIV – XXV , Surabaya
Responsibility :
- Site coordinator constuction of Nira station and Vacum pan station.
Position held : Mechanical Engineer
Date :
[Signature of authorized representative] Day / Month / Year